C1 C2 C3 C4 C4 C4 C5 C5 C1 C2 C3 as existing C3 C4 as existing

C1
10mm European Oak by ScandaFloor
on 18mm ply by GC
on separating layer
55mm min of RMC Supaflo Alpha Hemi Hydrate
floor screed totally encapsulating
Wirsbo 20 UFP pipe matrix system
on 50mm Wirsbo Rolltec EHD/A
expanded polystyrene insulation board
and woven membrane all installed
by an approved contractor.
C3 as existing
C2
Provide screw fixings to the ne decking
All in accordance with the Structural
Engineers details.
Overlay the floor boarding with insulation
C3
Existing carpet floor finish is to be lifted
and replaced upon completion of the work.
The existing floor boards are to be lifted
and removed form site
Provide and fix 32mm x 25mm tanalised roofing battens
to the sides of the existing joists.
Cut 10mm shuttering ply panels and drop into the
joist spacings.
The general contractor is to provide and lay 2 layers
of Gyplas 3611at 80mm thickness each.
The heating contractor compresses the insulation with the
heat reflecting plates and installs the heat tubing.
The general contractor provides and fixes
18mm flooring grade ply
screw fixed to the joists.
The general contractor refixes the carpet.
75mm of insulation
150mm of insulation
123.3
NEW SANCTUARY PLATFORM STRUCTURE.
NEW FONT PLATFORM.
Carefully set out the platform for inspection by the Architect
and the specialist marble contractor.
The top surface is to finish 60mm lower than the
proposed marble finished level.
A142 mesh
Form shuttering. This may be permanent by using concrete
brickwork to the perimeter shape.
The heating contractor will then pump
55mm min of RMC Supaflo Alpha Hemi Hydrate
floor screed totally encapsulating
Wirsbo 20 UFP pipe matrix system
on varying thicknesses of
expanded polystyrene insulation board
and woven membrane as approved by Wirsbo.
For insulation set outs see Drawing 01/341/9
forming part of previous faculty application.
New heat source to be high efficiency
model 2 Archie Kidd Thermal boiler
balanced flue through the stonework
at 2m above ffl.
Below the boiler cut hit and miss pockets
into the brickwork. Form downstand shuttering and
cast 200mm thick concrete floor slab reinforced
with 12mm dia stainless steel reinforcing bars
caged and bent to edge beam
All in accordance with Structural Engineers details.
Trim timbers around the slab leaving
30mm air space to full perimeter.
No Change to these areas.
Provide and fix new Oak panelled cupboard
with access door the front
Drugasar
C4
The existing Drugasar heaters
in the meeting room are to be
operational after the other
Drugasar heaters are removed.
Lounge
Drugasar
Drugasar
Drugasar
Drugasar
Vestry
The general contractor (Corgi registered) is to isolate the existing
Drugasar Heaters from power and gas and
remove the units from the walls.
The inner leaf is to be built up in clay brickwork
and plaster finished to match the existing.
The existing balamnce fkues are to be removed and the
grit stone is to be infilled with matching material
pointed with hydrated lime mortar.
C3
Existing gas meter is located
in the basement in this corner
NEW MARBLE ON SCREED STRUCTURE
300
C5
C2
Plan
C1
Ex 100mm sq oak corners
Altar
C5
C5
4
3
Meeting room/
Functions
Ex 125mm x 50mm oak door
framing.
Ex 75mm x 25mm oak v jointed
boarding
Front door to be side hung with
75mm brass hinges.
Pair of brass knobs and sash lock.
Side panels fixed to
ex 50mm sq sw framing with
brass cups and screws for removal
Top box front panels hinged.
Ex 75mm x 50mm sw framing
finished with 18mm ply
to form shelf.
Cupboard to be satin
seal finished.
2
Lady Chapel
Heating pipes encapsulated
in RMC screed on insulation
721
900
C2
C1
CDM regulations apply.
Method statements required for floor board removal.
Boiler installation.
Removal of Drugasar heaters.
Sealant application.
Cutting of boards.
Kitchen
1220
Boiler elevation
Risk of fall through floor. Provide working boards and protect open flooring.
Hard hats to be worn at basement level.
Heating pipes with
heat reflector
plates within insulated
timber flooring with ply
applied from basement
side.
300
1220
C5
Designers Risk assessment.
Care should be taken when handling wood products
Gloves should be worn.
Projecting nails from existing removed board are to be
withdrawn as the board are removed. Risk of foot and
hand injury.
Knee pads should be considered when work for long periods
bend down.
Qualified gas fitters to be in charge of gas piping and boiler installations.
Ventilation required when floor sanding and sealing.
Masks to be worn at all times. Restricted access for 12hrs after sealant applied.
560
2100
1600
Line of gallery over
C4
Male
1
C4
0
Font
Drugasar
Female
Heating pipes with
heat reflector plates
within insulated
timber flooring with
no access from below
therefore ply dropped in from above
Drugasar
Drugasar
Drugasar
Existing incoming water
and electric entry point in the
Basement
The general contractor is to provide and screw fix 10mm
shuttering ply to the underside of the floor joist (Basement side)
Scandafloor specialist joiners are to remove
the existing pews and store on site
and upon completion of the woodstrip re fix the pews.
HEATING PROPOSALS
In areas where it is not possible to access the
joists from below ie each side of the centre
aisle the general contractor is to
remove the floor board from above and
provide and fix British gypsum galvanised steel metal
component ref GA3 32mm x 19mm x 0.9mm
angle securely fixed into the face of the joist.
Provide and cut to joist spacings 10mm shuttering ply
and drop into place.
remaining construction as C4
The general contractor is to remove the existing carpet
floor finish and remove the
existing softwood floor boards from site.
The general contractor is to provide
temporary working boards to lay across the joists.
The general contractor is to infill the joists with
2 layers of 80mm Gyplas 3611 insulation.
JUNE 2002
ALAN
The heating contractor will compress the insulation with
aluminium heat reflecting trays and lay the heating pipes.
C4 as existing
The general contractor with provide and lay
18mm flooring grade plywood
screw fixed to the joists.
Scandafloor will finish the ply with 10mm European oak
wood strip. Stain finished
JAMES
HURST.
CHARTERED ARCHITECT
TEL:
C4
C5
0161
456 1203
SCALE 1:100 1:20 at A2
01/341/12