Method Statements

M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Index
Method Statement:
MJSM01.
Arrival on site
MJSM02.
Working in the area of stairwells
MJSM03.
Plaster boarding ceilings
MJSM04.
Loading of Plaster board
MJSM05.
Installation of TJI Floor joists
MJSM06.
1st & 2nd fix Carpentry
MJSM07.
Installation of Roof trusses
MJSM08.
Floorscreeding (Pumped)
MJSM09.
Floorscreeding (Wheel barrowed)
MJSM10.
External render Applied Traditionally
MJSM11.
External render applied via spray
MJSM12.
Installation of traditional wooden Joists
MJSM13.
Internal plastering
MJSM14.
Painting
MJSM15.
Installation of decorative coving products
MJSM16.
Application of Textured ceiling products
MJSM17
Installation of attic trusses
MJSM18
Timber frame erection
© M J Stevens Group
1 of 1
MJSM00
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Index
Method Statement:
MJSM01.
Arrival on site
MJSM02.
Working in the area of stairwells
MJSM03.
Plaster boarding ceilings
MJSM04.
Loading of Plaster board
MJSM05.
Installation of TJI Floor joists
MJSM06.
1st & 2nd fix Carpentry
MJSM07.
Installation of Roof trusses
MJSM08.
Floorscreeding (Pumped)
MJSM09.
Floorscreeding (Wheel barrowed)
MJSM10.
External render Applied Traditionally
MJSM11.
External render applied via spray
MJSM12.
Installation of traditional wooden Joists
MJSM13.
Internal plastering
MJSM14.
Painting
MJSM15.
Installation of decorative coving products
MJSM16.
Application of Textured ceiling products
MJSM17
Installation of attic trusses
MJSM18
Timber frame erection
© M J Stevens Group
1 of 1
MJSM00
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference
Number:
MJSM01
Area Assessed: Current site
Site location: Operatives Handbook
Description:
Operatives Identified:
Site based operatives
WORK ACTIVITY:
Arrival on site
Arrival on Site
Ensure your vehicle is parked in the designated parking area for that particular site where you
are going to conduct your work activity and not parked in an area which may cause a hazard
to others.
Vehicular and Pedestrian Routes
Ensure you adhere to any advisory and mandatory signs indicating speed limits for vehicles
and designated routes on site also ensure as a pedestrian you keep to any designated routes
as indicated by the Principle Contractor to reduce the risk of pedestrians impacting with
vehicles and items of plant machinery.
Personal Protective Equipment
Ensure that you are wearing the correct PPE and as you have to walk around the site you
have the basic requirements for this;
Hi-vis waistcoats
Protective footwear
Adequate Head Protection
Further requirements for PPE
required;
for the application of task on site, to be worn as and when
Gloves
Dust Masks
Safety Goggles
© M J Stevens Group
1 of 2
MJSM01
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference
Number:
MJSM01
Area Assessed: Current site
Site location: Operatives Handbook
Description:
Operatives Identified:
Site based operatives
WORK ACTIVITY:
Arrival on site
Arrival on Site
Ensure your vehicle is parked in the designated parking area for that particular site where you
are going to conduct your work activity and not parked in an area which may cause a hazard
to others.
Vehicular and Pedestrian Routes
Ensure you adhere to any advisory and mandatory signs indicating speed limits for vehicles
and designated routes on site also ensure as a pedestrian you keep to any designated routes
as indicated by the Principle Contractor to reduce the risk of pedestrians impacting with
vehicles and items of plant machinery.
Personal Protective Equipment
Ensure that you are wearing the correct PPE and as you have to walk around the site you
have the basic requirements for this;
Hi-vis waistcoats
Protective footwear
Adequate Head Protection
Further requirements for PPE
required;
for the application of task on site, to be worn as and when
Gloves
Dust Masks
Safety Goggles
© M J Stevens Group
1 of 2
MJSM01
In
Induction
duction Tr
Training
aining / Signing
Signing In On
On Site
Site
Al
p e ra t i v e s a
re tto
o rreport
eport tto
o site
site office
th e p
urpose o
offfice fo
or the
identifying themselves
themselves tto
o tthe
he
Alll o
operatives
are
for
purpose
off identifying
Pr
inciple C
ontractors Si
te M
a n a g em e n t a
nd ffor
or ssigning
igning iin.
n.
Principle
Contractors
Site
Management
and
En
sure yyou
ou a
re g
iven a ssite
ite iinduction
n d u ct i o n b
y tthe
he a
p p o in te d p
e r so n d
e s ig n a te d b
y tthe
he Pr
i n c ip l e
Ensure
are
given
by
appointed
person
designated
by
Principle
Co
n tr ac to r a
nd tthat
hat yyou
ou ffully
u lly u
nderstand tthe
he ccontent
ontent and al
he rrequirements
equirements as sset
et out by
Contractor
and
understand
alll tthe
th
eP
rinciple C
ontractor.
the
Principle
Contractor.
Ma
te r ia l S
re a s
to ra g e A
Material
Storage
Areas
Ma
terial sstorage
to ra g e a
nd mo
vement o
o u n d a rie s o
he ssite
ite mu
st b
te ria ls w
ithin tthe
he d
e fin e d b
e
Material
and
movement
off ma
materials
within
defined
boundaries
off tthe
must
be
conducted as
as instructed
instructed by
by tthe
he P
rinciple Contractor,
azardous m
anual h
a n d li n g
Contractor, tto
o a
v o id h
conducted
Principle
avoid
hazardous
manual
handling
oper
ations ens
ure tthat
hat al
tems w
e m
echanically handl
hich ar
e heav
y or aw
kward ar
ed
operations
ensure
alll iitems
which
are
heavy
awkward
are
mechanically
handled
wh
e re p
o s s ib le . L
oads a
re tto
ob
ed
e p o s ite d a
s cclose
lose tto
o tthe
he wo
rk i n g a
re a a
sp
r a c tic a l.
where
possible.
Loads
are
be
deposited
as
working
area
as
practical.
Welfare Facilities
F a c ilitie s
Welfare
Operatives
will
use
welfare
facilities
ill u
se tthe
he w
elfa
are fa
acilities provided
Op
e r a t iv e s w
provided by
by the
the Principle
Principle Contractor
Contractor to
to include
include ttoilet
o ile t
facilities
and
Mess
Canteen,
the
facilities
will
be
used
forr a
allll m
meal
breaks
and
no
nd M
ess C
anteen, th
e ccanteen
fa
cilities a
anteen fa
cilities w
ill b
e u
sed fo
eal b
re a k s a
nd n
o
ea, on any ot
her par
breaks
will
held
work
area,
other
partt of tthe
ill be hel
d iin
n tthe
he w
ork ar
br
eaks w
he ssite
ite nor iin
n vvehicles
ehicles ((Private
Private or
company
owned)
company owned)
NA
NAME
ME
DA
DATE
TE
Andy
Andy White
White
01/
01/11/2009
11/2009
RE
REVIEW
VIEW DA
DATE
TE
01/04/2015
SI
SIGNATURE
GNATURE
MBA
MBA Safety
Safety & Training
T ra in in g
Ltd
Lt
d
JO
JOBTITLE
B T IT L E
He
Health
alth and
an d s
safety
afety Co
Consultant
n s u lta n t
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
0AW
We
llington, TA21
TA21 0A
W
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
© M J Stevens
Stevens Group
Group
2 of 2
MJSM01
MJSM01
In
Induction
duction Tr
Training
aining / Signing
Signing In On
On Site
Site
Al
p e ra t i v e s a
re tto
o rreport
eport tto
o site
site office
th e p
urpose o
offfice fo
or the
identifying themselves
themselves tto
o tthe
he
Alll o
operatives
are
for
purpose
off identifying
Pr
inciple C
ontractors Si
te M
a n a g em e n t a
nd ffor
or ssigning
igning iin.
n.
Principle
Contractors
Site
Management
and
En
sure yyou
ou a
re g
iven a ssite
ite iinduction
n d u ct i o n b
y tthe
he a
p p o in te d p
e r so n d
e s ig n a te d b
y tthe
he Pr
i n c ip l e
Ensure
are
given
by
appointed
person
designated
by
Principle
Co
n tr ac to r a
nd tthat
hat yyou
ou ffully
u lly u
nderstand tthe
he ccontent
ontent and al
he rrequirements
equirements as sset
et out by
Contractor
and
understand
alll tthe
th
eP
rinciple C
ontractor.
the
Principle
Contractor.
Ma
te r ia l S
re a s
to ra g e A
Material
Storage
Areas
Ma
terial sstorage
to ra g e a
nd mo
vement o
o u n d a rie s o
he ssite
ite mu
st b
te ria ls w
ithin tthe
he d
e fin e d b
e
Material
and
movement
off ma
materials
within
defined
boundaries
off tthe
must
be
conducted as
as instructed
instructed by
by tthe
he P
rinciple Contractor,
azardous m
anual h
a n d li n g
Contractor, tto
o a
v o id h
conducted
Principle
avoid
hazardous
manual
handling
oper
ations ens
ure tthat
hat al
tems w
e m
echanically handl
hich ar
e heav
y or aw
kward ar
ed
operations
ensure
alll iitems
which
are
heavy
awkward
are
mechanically
handled
wh
e re p
o s s ib le . L
oads a
re tto
ob
ed
e p o s ite d a
s cclose
lose tto
o tthe
he wo
rk i n g a
re a a
sp
r a c tic a l.
where
possible.
Loads
are
be
deposited
as
working
area
as
practical.
Welfare Facilities
F a c ilitie s
Welfare
Operatives
will
use
welfare
facilities
ill u
se tthe
he w
elfa
are fa
acilities provided
Op
e r a t iv e s w
provided by
by the
the Principle
Principle Contractor
Contractor to
to include
include ttoilet
o ile t
facilities
and
Mess
Canteen,
the
facilities
will
be
used
forr a
allll m
meal
breaks
and
no
nd M
ess C
anteen, th
e ccanteen
fa
cilities a
anteen fa
cilities w
ill b
e u
sed fo
eal b
re a k s a
nd n
o
ea, on any ot
her par
breaks
will
held
work
area,
other
partt of tthe
ill be hel
d iin
n tthe
he w
ork ar
br
eaks w
he ssite
ite nor iin
n vvehicles
ehicles ((Private
Private or
company
owned)
company owned)
NA
NAME
ME
DA
DATE
TE
Andy
Andy White
White
01/
01/11/2009
11/2009
RE
REVIEW
VIEW DA
DATE
TE
01/11/2011
01/11
/2011
SI
SIGNATURE
GNATURE
MBA
MBA Safety
Safety & Training
T ra in in g
Ltd
Lt
d
JOBTITLE
JOBTITLE
He
Health
alth and
an d s
safety
afety Co
Consultant
n s u lta n t
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
0AW
We
llington, TA21
TA21 0A
W
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
© M J Stevens
Stevens Group
Group
2 of 2
MJSM01
MJSM01
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference Number:
MJSM02
Area Assessed:
Site location: Operatives Handbook
Description:
Working in Stairwells
Operatives Involved:
Site based operatives
WORK ACTIVITY:
Working in the area of stairwells
To be read in conjunction with the company’s Generic Risk
Assessments
MJSRa01
MJSRa02
MJSRa03
MJSRa10
MJSRa11
MJSRa12
MJSRa13
Working at Height
Manual Handling
Noise
Breathing in Dust Particles
Materials Delivery
Materials/Objects falling from height
Mobile scaffold towers and platforms
Work Area (General Precautions)
•
•
•
•
•
•
The work area, namely the stairwell is to be free of other trades working in the
immediate area.
All debris, rubbish & trip hazards are to be removed from the work area prior to the
work commencing.
If other trades are working within the property they must be advised as to the work
activities you are about to commence.
The existing temporary stairwell edge protection will be removed by MJS and one
purpose built “Stairwell Working Platform” will installed and be provided by the
Principle Contractor or installed by MJS qualified operative if directed by principle
contractor.
Due to the limitations of stairwell platforms, the principle contractor may be required to
erect a scaffold platform where this has been identified. (ie: Communal staircases)
Adequate lighting is to be provided by the Principle Contactor for the various activities
which will be conducted in the stairwell.
© M J Stevens Group
1 of 3
MJSM02
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference Number:
MJSM02
Area Assessed:
Site location: Operatives Handbook
Description:
Working in Stairwells
Operatives Involved:
Site based operatives
WORK ACTIVITY:
Working in the area of stairwells
To be read in conjunction with the company’s Generic Risk
Assessments
MJSRa01
MJSRa02
MJSRa03
MJSRa10
MJSRa11
MJSRa12
MJSRa13
Working at Height
Manual Handling
Noise
Breathing in Dust Particles
Materials Delivery
Materials/Objects falling from height
Mobile scaffold towers and platforms
Work Area (General Precautions)
•
•
•
•
•
•
The work area, namely the stairwell is to be free of other trades working in the
immediate area.
All debris, rubbish & trip hazards are to be removed from the work area prior to the
work commencing.
If other trades are working within the property they must be advised as to the work
activities you are about to commence.
The existing temporary stairwell edge protection will be removed by MJS and one
purpose built “Stairwell Working Platform” will installed and be provided by the
Principle Contractor or installed by MJS qualified operative if directed by principle
contractor.
Due to the limitations of stairwell platforms, the principle contractor may be required to
erect a scaffold platform where this has been identified. (ie: Communal staircases)
Adequate lighting is to be provided by the Principle Contactor for the various activities
which will be conducted in the stairwell.
© M J Stevens Group
1 of 3
MJSM02
Maintenance and replacement of personal Protective equipment
Every self-employed person shall ensure that any personal protective equipment provided to
him is maintained (including replaced or cleaned as appropriate) in an efficient state, in
efficient working order and in good repair - (Extract from the Personal Protective Equipment at
Work Regulations).
•
•
•
Every operative is to ensure that they have received adequate training with regards to the
use of any particular item of Personal Protective Equipment.
Self employed persons are to ensure they purchase and maintain PPE in line with the
relevant risk assessments
Employed persons are to ensure they look after and use any PPE provided for them and
report any defects etc to their supervisor immediately.
Work in the stairwells
Task to which this method statement applies (in order of fixing) are;
•
•
•
•
•
•
•
Board Ceiling.
Erect metal stud adjacent to stairwell.
Board and insulate the metal stud wall.
Tape and joint the boarded Ceiling and walls.
Sand the joints on the Ceiling and walls.
Coving if specified.
Any carpentry work above or next to the stair well
Sequence of work
Before work is started the principle contractor is to provide full height access into the building
through scaffold and the stairs installed. Temporary handrails around stair opening at each
floor level are to by installed by principle contractor.
M.J.S. may need to remove these barriers [and replace them] to load out boards and
studding.
1. Ensure the stairwell opening is covered with the proprietary stair system and fix ceiling
boards to truss or joist.
2. Dryliners will use an approved hop up to apply fixings to ceiling board. Props may be
used to support ceiling boards.
3. Where metal studding is fixed to the edge of the stairwell, the stud will be fixed from the
floor side, with fall into the stairwell protected by proprietary stair system, soft fall bags etc
[supplied by P.C.]
4. MJS will then reinstate the handrail protection until boarding commences.
5. On completion of works by first fix trades, boarding of all walls at stairwells will
commence, screw fixed boards first. Access for this work will be off the stairs for the lower
lift and a temporary proprietary landing for the upper lift.
6. Installation of dabbed boards to follow using the same access arrangement.
7. Board joints will be the taped and filled using the same access platform.
8. Ceiling coving if specified, to stairwells can then be fixed, using hop ups or short ladders
footed on the temporary landing platform.
Welfare Facilities
Operatives will use the welfare facilities provided by the Principle Contractor to include toilet
facilities and Mess Canteen, the canteen facilities will be used for all meal breaks and no
breaks will be held in the work area, on any other part of the site nor in vehicles (Private or
company owned)
On Completion of Works
© M J Stevens Group
2 of 3
MJSM02
Maintenance and replacement of personal Protective equipment
Every self-employed person shall ensure that any personal protective equipment provided to
him is maintained (including replaced or cleaned as appropriate) in an efficient state, in
efficient working order and in good repair - (Extract from the Personal Protective Equipment at
Work Regulations).
•
•
•
Every operative is to ensure that they have received adequate training with regards to the
use of any particular item of Personal Protective Equipment.
Self employed persons are to ensure they purchase and maintain PPE in line with the
relevant risk assessments
Employed persons are to ensure they look after and use any PPE provided for them and
report any defects etc to their supervisor immediately.
Work in the stairwells
Task to which this method statement applies (in order of fixing) are;
•
•
•
•
•
•
•
Board Ceiling.
Erect metal stud adjacent to stairwell.
Board and insulate the metal stud wall.
Tape and joint the boarded Ceiling and walls.
Sand the joints on the Ceiling and walls.
Coving if specified.
Any carpentry work above or next to the stair well
Sequence of work
Before work is started the principle contractor is to provide full height access into the building
through scaffold and the stairs installed. Temporary handrails around stair opening at each
floor level are to by installed by principle contractor.
M.J.S. may need to remove these barriers [and replace them] to load out boards and
studding.
1. Ensure the stairwell opening is covered with the proprietary stair system and fix ceiling
boards to truss or joist.
2. Dryliners will use an approved hop up to apply fixings to ceiling board. Props may be
used to support ceiling boards.
3. Where metal studding is fixed to the edge of the stairwell, the stud will be fixed from the
floor side, with fall into the stairwell protected by proprietary stair system, soft fall bags etc
[supplied by P.C.]
4. MJS will then reinstate the handrail protection until boarding commences.
5. On completion of works by first fix trades, boarding of all walls at stairwells will
commence, screw fixed boards first. Access for this work will be off the stairs for the lower
lift and a temporary proprietary landing for the upper lift.
6. Installation of dabbed boards to follow using the same access arrangement.
7. Board joints will be the taped and filled using the same access platform.
8. Ceiling coving if specified, to stairwells can then be fixed, using hop ups or short ladders
footed on the temporary landing platform.
Welfare Facilities
Operatives will use the welfare facilities provided by the Principle Contractor to include toilet
facilities and Mess Canteen, the canteen facilities will be used for all meal breaks and no
breaks will be held in the work area, on any other part of the site nor in vehicles (Private or
company owned)
On Completion of Works
© M J Stevens Group
2 of 3
MJSM02
Al
Alll w
work
o rk a
areas
re a s a
are
re tto
ob
be
e lleft
eftt iin
n a cclean
lean ccondition
o n d itio n a
and
nd a
allll a
aspects
s p e c ts o
off ssafety
afe
ety w
with
ith rregards
egards tto
o tthe
he
im
immediate
mediate w
work
o rk a
area
re a a
and
nd w
working
orking p
platform
latform tto
o sstairwells
tairwells m
must
ust h
have
ave a vvisual
isual in
inspection
spection b
by
y tthe
he
oper
ative to e
nsure th
at th
e ed
ge p
rotection iis
s iin
n place
place and
and tthat
hat there
there is
is no
no risk
risk to
to injury
injury tto
o
operative
ensure
that
the
edge
protection
others a
th
themselves
e m s e lv e s o
orr others
as
sad
direct
irect result
r e s u lt o
off a fa
fallll fr
from
om th
that
at a
area.
re a .
nd p
ro p e r m
anner
Ensure
allll o
other
material
which
used
sed fo
for
or yyour
work
n a ssafe
afe
ea
and
proper
manner
th e r m
a te r ia l w
hich iis
su
En
s u re a
our w
ork iis
s sstored
tored iin
before
departing
ou a
are
re w
working
orking iin.
n.
rting from
from tthe
he property
property yyou
bef
ore depa
ite
eam o
n ccompletion
o m p le tio n o
he wo
rk s a
nd iiff rrequired
e q u ir e d b
y tthe
he ssite
Re
port tto
o tthe
he S
ite M
anagem ent T
Report
Site
Management
Team
on
off tthe
works
and
by
ut b
efo
ore lleaving
ru
les ssign
ig n o
e a v in g
rules
out
before
NA
NAME
ME
DA
DATE
TE
Andy
Andy White
White
01/11/2009
01/11
/2009
RE
REVIEW
VIEW DATE
DATE
01/04/2015
SIGNATURE
SIGNATURE
MBA
MBA Safety
Safety & Training
T ra in in g
Ltd
Lt
d
JO
JOBTITLE
B T IT L E
He
Health
alth and
an d s
safety
afety Co
Consultant
n s u lta n t
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
We
Wellington,
llin g to n , T
TA21
A21 0
0AW
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
© M J Stevens
Stevens Group
Group
3 of 3
MJSM02
MJSM02
Al
Alll w
work
o rk a
areas
re a s a
are
re tto
ob
be
e lleft
eftt iin
n a cclean
lean ccondition
o n d itio n a
and
nd a
allll a
aspects
s p e c ts o
off ssafety
afe
ety w
with
ith rregards
egards tto
o tthe
he
im
immediate
mediate w
work
o rk a
area
re a a
and
nd w
working
orking p
platform
latform tto
o sstairwells
tairwells m
must
ust h
have
ave a vvisual
isual in
inspection
spection b
by
y tthe
he
oper
ative to e
nsure th
at th
e ed
ge p
rotection iis
s iin
n place
place and
and tthat
hat there
there is
is no
no risk
risk to
to injury
injury tto
o
operative
ensure
that
the
edge
protection
others a
th
themselves
e m s e lv e s o
orr others
as
sad
direct
irect result
r e s u lt o
off a fa
fallll fr
from
om th
that
at a
area.
re a .
nd p
ro p e r m
anner
Ensure
allll o
other
material
which
used
sed fo
for
or yyour
work
n a ssafe
afe
ea
and
proper
manner
th e r m
a te r ia l w
hich iis
su
En
s u re a
our w
ork iis
s sstored
tored iin
before
departing
property
ou a
are
re w
working
orking iin.
n.
rting from
from tthe
he p
roperty yyou
bef
ore depa
ite
eam o
n ccompletion
o m p le tio n o
he wo
rk s a
nd iiff rrequired
e q u ir e d b
y tthe
he ssite
Re
port tto
o tthe
he S
ite M
anagem ent T
Report
Site
Management
Team
on
off tthe
works
and
by
ut b
efo
ore lleaving
ru
les ssign
ig n o
e a v in g
rules
out
before
NA
NAME
ME
DA
DATE
TE
Andy
Andy White
White
01/11/2009
01/11
/2009
RE
REVIEW
VIEW DATE
DATE
01/
01/11/2011
11/2011
SIGNATURE
SIGNATURE
MBA
MBA Safety
Safety & Training
T ra in in g
Ltd
Lt
d
JO
JOBTITLE
B T IT L E
He
Health
alth and
an d s
safety
afety Co
Consultant
n s u lta n t
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
We
Wellington,
llin g to n , T
TA21
A21 0
0AW
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
© M J Stevens
Stevens Group
Group
3 of 3
MJSM02
MJSM02
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference
Number:
MJSM03
Area Assessed:
Site location: Operatives Handbook
Description:
Plaster boarding Ceilings
Operatives Involved:
Site based operatives
WORK ACTIVITY:
Application of plasterboard to underside of ceiling joists & roof trusses
To be read in conjunction with the company’s Generic Risk
Assessments & Method statements
MJSRa01
MJSRa02
MJSRa03
MJSRa04
MJSRa08
MJSRa09
MJSRa10
MJSRa11
MJSRa12
MJSRa13
MJSRa14
MJSRa15
MJSM01
Working at Height
Manual Handling
Noise
Vibration
Power tools
Electrocution
Breathing in dust particles
Materials Delivery
Materials / Objects falling from height
Mobile scaffold towers and platforms
Ladders and step ladders
Working off stilts
Arrival on site
Method of work (General precautions)
• The work area, namely the room where the plasterboard is to be applied must be free of
other trades working in the immediate area.
• All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing.
• If other trades are working within the property they must be advised as to the work
activities you are about to commence.
• To enable operatives to gain access to the working surface of the underside of existing
ceiling joist or and the underside of existing roof trusses a purposely constructed Heavy
Duty Plastic Step are to be used no other improvised or make shift equipment shall be
used, such as milk crates, beer crates, kitchen stools, chairs or home made hop-ups.
• Some operatives may carry out the task from stilts; these operatives will be fully
competent and aware of the risks associated with working off stilts.
• Adequate lighting is to be provided by the Principle Contactor for the various activities
that will be conducted in the work area.
• Operatives engaged in cutting, sawing, drilling or breaking the plasterboard sheets must
use the correct (PPE) and (RPE) required Personal Protective Equipment and
Respiratory Protective Equipment.
Positioning Plasterboard
Operatives are required to prepare the plasterboard in readiness to apply to the underside of
© M J Stevens Group
1 of 2
MJSM03
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference
Number:
MJSM03
Area Assessed:
Site location: Operatives Handbook
Description:
Plaster boarding Ceilings
Operatives Involved:
Site based operatives
WORK ACTIVITY:
Application of plasterboard to underside of ceiling joists & roof trusses
To be read in conjunction with the company’s Generic Risk
Assessments & Method statements
MJSRa01
MJSRa02
MJSRa03
MJSRa04
MJSRa08
MJSRa09
MJSRa10
MJSRa11
MJSRa12
MJSRa13
MJSRa14
MJSRa15
MJSM01
Working at Height
Manual Handling
Noise
Vibration
Power tools
Electrocution
Breathing in dust particles
Materials Delivery
Materials / Objects falling from height
Mobile scaffold towers and platforms
Ladders and step ladders
Working off stilts
Arrival on site
Method of work (General precautions)
• The work area, namely the room where the plasterboard is to be applied must be free of
other trades working in the immediate area.
• All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing.
• If other trades are working within the property they must be advised as to the work
activities you are about to commence.
• To enable operatives to gain access to the working surface of the underside of existing
ceiling joist or and the underside of existing roof trusses a purposely constructed Heavy
Duty Plastic Step are to be used no other improvised or make shift equipment shall be
used, such as milk crates, beer crates, kitchen stools, chairs or home made hop-ups.
• Some operatives may carry out the task from stilts; these operatives will be fully
competent and aware of the risks associated with working off stilts.
• Adequate lighting is to be provided by the Principle Contactor for the various activities
that will be conducted in the work area.
• Operatives engaged in cutting, sawing, drilling or breaking the plasterboard sheets must
use the correct (PPE) and (RPE) required Personal Protective Equipment and
Respiratory Protective Equipment.
Positioning Plasterboard
Operatives are required to prepare the plasterboard in readiness to apply to the underside of
© M J Stevens Group
1 of 2
MJSM03
ceiling
ceiling joist
joist or
or rroof
oof ttrusses,
russes, tthe
he si
size
ze of
of the
the plasterboard
plasterboard sh
should
ould be
be such
such tthat
hat iitt iis
s e
easily
asily
handl
handled
ed by tthe
he ffixing
ixing oper
operative
ative a
and
nd p
position
osition tthe
he p
plasterboard
la s te rb o a rd w
with
ith tthe
he a
assistance
ssistance ffrom
ro m a p
prop
ro p
ens
ensuring
uring tthe
he boar
board
d rremains
emains iin
n tthe
he cchosen
hosen pos
position
ition w
whilst
hilst tthe
he sscrew
crew ffixings
ixings ar
are
e appl
applied.
ied.
•
•
•
he ssafe
afe
e u
Ensure tthe
se o
ny h
and ttools
ools ii.e.
.e. St
anley Kn
ive s a
nd e
n s u re d
iscarded kknife
n ife
Ensure
use
off a
any
hand
Stanley
Knives
and
ensure
discarded
blades ar
e di
sposed o
in the
the correct
co rre c t m
a n n e r.
blades
are
disposed
off in
manner.
After a
u r fa c e s a
nd tthe
he a
p p lic a tio n o
p p lic a tio n o
asterboard tto
o vvertical
e r tic a l a
nd h
orizontal ssurfaces
After
application
off Pl
Plasterboard
and
horizontal
and
application
off
ea iis
s tto
o be ccleared
leared of unus
ed
any w
et pl
aster or textured
textured ccoatings
oatings tthe
he ccomplete
omplete ar
wet
plaster
area
unused
materials and
and waste
waste products.
p ro d u c ts .
materials
skips / area
area p
rovided b
y tthe
he
ob
ed
eposited iin
n tthe
he w
aste skips
The rremoved
emoved rrubbish
u b b is h / d
ebris is
is tto
The
debris
be
deposited
waste
provided
by
MJS.
S
MJS.
Personal
Protective
otective Equipment
Equipment
Pe
rsonal Pr
otective equi
pment pr
ovided tto
o
elf-employed per
son sshall
hall ens
ure tthat
hat any per
sonal pr
Every
person
ensure
personal
protective
equipment
provided
Every sself-employed
opriate) iin
tate, iin
n
aintained ((including
including rreplaced
eplaced or ccleaned
leaned as appr
him
maintained
appropriate)
an
n a
n efficient
effficient sstate,
hi
m iiss m
orking or
der and iin
n good rrepair
eff
ficient w
epair - ((Extract
Extract ffrom
rom tthe
he P
ers o n a l P
efficient
working
order
Personal
Protective
Equipment
att
r o te c tiv e E
q u ip m e n t a
Work Regulations).
R e g u la t io n s ) .
Work
•
•
•
Every o
perative iis
s tto
oe
nsure tthat
hat tthey
hey h
ave rreceived
e c e iv e d a
dequate ttraining
r a in in g w
ith rregards
egards tto
o tthe
he
Every
operative
ensure
have
adequate
with
use of any par
ticular item
item of
of Personal
P e rso n a l P
rotective E
quipment.
use
particular
Protective
Equipment.
he
Self e
m p lo y e d p
e rs o n s a
re tto
o e
nsure tthey
hey p
u rc h a s e a
nd m
aintain PPE iin
n lline
in e w
ith tthe
Self
employed
persons
are
ensure
purchase
and
maintain
with
relevant ri
sk a
s s e s s m e n ts
relevant
risk
assessments
nd
hey llook
ook a
fte r a
ny PPE p
rovided fo
or tthem
nd u
se a
hem a
Employed p
e rs o n s a
re tto
oe
nsure tthey
Employed
persons
are
ensure
after
and
use
any
provided
for
and
ny d
efe
e c ts e
to their
their su
pervisor immediately.
im m e d ia te ly .
report a
tc to
report
any
defects
etc
supervisor
F a c ilitie s
Welfare Facilities
Welfare
o ile t
Operatives
will
use
welfare
provided
by
Principle
Contractor
Op
e r a t iv e s w
ill u
se tthe
he w
elfare ffacilities
a c ilitie s p
r o v id e d b
y tthe
he P
r in c ip le C
ontractor tto
o iinclude
nclude ttoilet
facilities
and
Mess
Canteen,
the
facilities
will
be
used
forr a
allll m
meal
breaks
and
no
fa
cilities a
nd M
ess C
anteen, th
e ccanteen
anteen fa
cilities w
ill b
e u
sed fo
eal b
re a k s a
nd n
o
na
ny o
th e r p
a rt o
breaks
will
be
held
work
area,
on
any
other
part
off tthe
nor
orr
br
eaks w
ill b
eh
eld iin
n tthe
he w
o rk a
re a , o
he ssite
ite n
or iin
n vvehicles
ehicles ((Private
P riv a te o
company
company owned)
ow ned)
C o m p le tio n o
W o rk s
On Completion
off Works
re a s a
re tto
ob
e lleft
eftt iin
afe
ety w
o n d itio n a
nd a
s p e c ts o
All
work
areas
are
be
n a cclean
lean ccondition
and
allll a
aspects
off ssafety
with
All w
o rk a
ith rregards
egards tto
o tthe
he
o rk a
re a a
nd cconduct
onduct a visual
o ensure
ensure tthat
hat tthe
he e
dge
visual inspection
in s p e c tio n b
y tthe
he o
perative tto
immediate
work
area
and
by
operative
edge
immediate w
here iis
s no rrisk
isk tto
o iinjury
njurryy tto
s iin
n pl
ace and tthat
hat tthere
hemselves or ot
hers as a di
o tthemselves
protection
place
others
direct
pr
otection iis
rect
fa
all from
from that
that area.
area.
result
off a fall
re
s u lt o
our w
ork iis
s sstored
tored iin
sed fo
or yyour
safe
e and
n a safe
and proper
p ro p e r m
anner
th e r m
a te r ia l w
hich iis
su
Ensure
allll o
other
material
which
used
for
work
manner
En
s u re a
ou ar
ew
orking iin.
n.
ting ffrom
rom tthe
he pr
operty yyou
before
departing
property
are
working
bef
ore depar
Re
port tto
rk s a
nd iiff rrequired
e q u ir e d b
y tthe
he ssite
ite
o tthe
he S
ite M
anagem ent T
eam o
n ccompletion
o m p le tio n o
he wo
Report
Site
Management
Team
on
off tthe
works
and
by
ut b
efo
ore lleaving
ru
les ssign
ig n o
e a v in g
rules
out
before
NAME
NA
ME
Andy
White
An
dy W
h ite
DATE
DA
TE 01/11/2009
REVIEW
RE
VIEW DATE
DATE
01/04/2015
SI
SIGNATURE
GNATURE
MB
MBA
AS
Safety
a fe ty & T
Training
r a in in g L
Ltd
td
JO
B T IT L E
JOBTITLE
He
a lt h a
nd safety
safety Co
Health
and
Consultant
n s u lta n t
Un
it 6 ““The
The Co
unting Ho
use”
Unit
Counting
House”
Tonedale
eB
Business
usiness P
Park
ark
Tonedal
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823 668527
668527
tevens G
roup
©MJS
Stevens
Group
2 of 2
MJSM03
MJSM03
ceiling
ceiling jjoist
oist or
or rroof
oof ttrusses,
russes, tthe
he si
size
ze of
of the
the plasterboard
plasterboard sh
should
o u ld b
be
e such
such tthat
hat iitt iis
s e
easily
asily
handl
handled
ed by tthe
he ffixing
ixing oper
operative
ative a
and
nd p
position
osition tthe
he p
plasterboard
la s te rb o a rd w
with
ith tthe
he a
assistance
ssistance ffrom
ro m a p
prop
ro p
ens
ensuring
uring tthe
he boar
board
d rremains
emains iin
n tthe
he cchosen
hosen pos
position
ition w
whilst
hilst tthe
he sscrew
crew ffixings
ixings ar
are
e appl
applied.
ied.
•
•
•
he ssafe
afe
e u
Ensure tthe
se o
ny h
and ttools
ools ii.e.
.e. St
anley Kn
ive s a
nd e
n s u re d
iscarded kknife
n ife
Ensure
use
off a
any
hand
Stanley
Knives
and
ensure
discarded
blades ar
e di
sposed o
in the
the correct
co rre c t m
a n n e r.
blades
are
disposed
off in
manner.
After a
u r fa c e s a
nd tthe
he a
p p lic a tio n o
p p lic a tio n o
asterboard tto
o vvertical
e r tic a l a
nd h
orizontal ssurfaces
After
application
off Pl
Plasterboard
and
horizontal
and
application
off
ea iis
s tto
o be ccleared
leared of unus
ed
any w
et pl
aster or textured
textured ccoatings
oatings tthe
he ccomplete
omplete ar
wet
plaster
area
unused
materials and
and waste
waste products.
p ro d u c ts .
materials
skips / area
area p
rovided b
y tthe
he
ob
ed
eposited iin
n tthe
he w
aste skips
The rremoved
emoved rrubbish
u b b is h / d
ebris is
is tto
The
debris
be
deposited
waste
provided
by
MJS.
S
MJS.
Personal
Protective
otective Equipment
Equipment
Pe
rsonal Pr
otective equi
pment pr
ovided tto
o
elf-employed per
son sshall
hall ens
ure tthat
hat any per
sonal pr
Every
person
ensure
personal
protective
equipment
provided
Every sself-employed
opriate) iin
tate, iin
n
aintained ((including
including rreplaced
eplaced or ccleaned
leaned as appr
him
maintained
appropriate)
an
n a
n efficient
effficient sstate,
hi
m iiss m
orking or
der and iin
n good rrepair
epair - ((Extract
Extract ffrom
rom tthe
he P
ers o n a l P
eff
ficient w
efficient
working
order
Personal
Protective
Equipment
att
r o te c tiv e E
q u ip m e n t a
Work Regulations).
R e g u la t io n s ) .
Work
•
•
•
Every o
perative iis
s tto
oe
nsure tthat
hat tthey
hey h
ave rreceived
e c e iv e d a
dequate ttraining
r a in in g w
ith rregards
egards tto
o tthe
he
Every
operative
ensure
have
adequate
with
use of any par
ticular item
item of
of Personal
P e rso n a l P
rotective E
quipment.
use
particular
Protective
Equipment.
he
Self e
m p lo y e d p
e rs o n s a
re tto
o e
nsure tthey
hey p
u rc h a s e a
nd m
aintain PPE iin
n lline
in e w
ith tthe
Self
employed
persons
are
ensure
purchase
and
maintain
with
relevant ri
sk a
s s e s s m e n ts
relevant
risk
assessments
nd
hey llook
ook a
fte r a
ny PPE p
rovided fo
or tthem
nd u
se a
hem a
Employed p
e rs o n s a
re tto
oe
nsure tthey
Employed
persons
are
ensure
after
and
use
any
provided
for
and
ny d
efe
e c ts e
to their
their su
pervisor immediately.
im m e d ia te ly .
report a
tc to
report
any
defects
etc
supervisor
F a c ilitie s
Welfare Facilities
Welfare
o ile t
Operatives
will
use
welfare
provided
by
Principle
Contractor
Op
e r a t iv e s w
ill u
se tthe
he w
elfare ffacilities
a c ilitie s p
r o v id e d b
y tthe
he P
r in c ip le C
ontractor tto
o iinclude
nclude ttoilet
facilities
and
Mess
Canteen,
the
facilities
will
be
used
forr a
allll m
meal
breaks
and
no
fa
cilities a
nd M
ess C
anteen, th
e ccanteen
anteen fa
cilities w
ill b
e u
sed fo
eal b
re a k s a
nd n
o
na
ny o
th e r p
a rt o
breaks
will
be
held
work
area,
on
any
other
part
off tthe
nor
orr
br
eaks w
ill b
eh
eld iin
n tthe
he w
o rk a
re a , o
he ssite
ite n
or iin
n vvehicles
ehicles ((Private
P riv a te o
company
company owned)
ow ned)
C o m p le tio n o
W o rk s
On Completion
off Works
re a s a
re tto
ob
e lleft
eftt iin
afe
ety w
o n d itio n a
nd a
s p e c ts o
All
work
areas
are
be
n a cclean
lean ccondition
and
allll a
aspects
off ssafety
with
All w
o rk a
ith rregards
egards tto
o tthe
he
o rk a
re a a
nd cconduct
onduct a visual
o ensure
ensure tthat
hat tthe
he e
dge
visual inspection
in s p e c tio n b
y tthe
he o
perative tto
immediate
work
area
and
by
operative
edge
immediate w
here iis
s no rrisk
isk tto
o iinjury
njurryy tto
s iin
n pl
ace and tthat
hat tthere
hemselves or ot
hers as a di
o tthemselves
protection
place
others
direct
pr
otection iis
rect
fa
all from
from that
that area.
area.
result
off a fall
re
s u lt o
our w
ork iis
s sstored
tored iin
sed fo
or yyour
safe
e and
n a safe
and proper
p ro p e r m
anner
th e r m
a te r ia l w
hich iis
su
Ensure
allll o
other
material
which
used
for
work
manner
En
s u re a
ou ar
ew
orking iin.
n.
ting ffrom
rom tthe
he pr
operty yyou
before
departing
property
are
working
bef
ore depar
Re
port tto
rk s a
nd iiff rrequired
e q u ir e d b
y tthe
he ssite
ite
o tthe
he S
ite M
anagem ent T
eam o
n ccompletion
o m p le tio n o
he wo
Report
Site
Management
Team
on
off tthe
works
and
by
ut b
efo
ore lleaving
ru
les ssign
ig n o
e a v in g
rules
out
before
NAME
NA
ME
Andy
White
An
dy W
h ite
DATE
DA
TE 01/11/2009
REVIEW
RE
VIEW DATE
DATE
01/
01/11/2011
11/2011
SI
SIGNATURE
GNATURE
MB
MBA
AS
Safety
a fe ty & T
Training
r a in in g L
Ltd
td
JO
B T IT L E
JOBTITLE
He
a lt h a
nd s
afety Co
Health
and
safety
Consultant
n s u lta n t
Un
it 6 ““The
The Co
unting Ho
use”
Unit
Counting
House”
Tonedale
eB
Business
usiness P
Park
ark
Tonedal
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823 668527
668527
©MJS
Stevens
Group
tevens G
roup
2 of 2
MJSM03
MJSM03
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference Number:
MJSM04
Area Assessed:
Site location: Operatives Handbook
Description:
Loading Plasterboard
Operatives involved:
Site based operatives
WORK ACTIVITY:
Loading of Plasterboard
To be read in conjunction with the company’s Generic Risk
Assessments
MJSRa01
MJSRa02
MJSRa03
MJSRa11
MJSRa12
Working at Height
Manual Handling
Noise
Materials Delivery
Materials / Objects falling from height
Work Area (General Precautions)
•
•
•
•
•
The work area, namely the room where the plasterboard is to be loaded must be free of
other trades working in the immediate area.
All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing.
If other trades are working within the property they must be advised of the work activities
you are about to commence.
To enable operatives to have good access and egress to the work areas the entry door
for loading must be at ground level with no scaffold obstructions to reduce height.
Listed below are board weights and sizes
Product description
Standard wallboard 12.5mm
Standard wallboard 12.5mm
Standard wallboard 15mm
Soundshield 12.5mm
Soundshield 15mm
Fireshield 12.5mm
19mm Plank
Moisture shield 12.5mm
Bonding compound
•
Weight in kilos
13.5
24
29
33
39
26
19
33
25
Size
1800X900
2400X1200
2400X1200
2400X1200
2400X1200
2400X1200
2400X 600
2400X1200
Bag
Adequate lighting is to be provided by the Principle Contactor for the various activities
which will be conducted in the working area.
© M J Stevens Group
1 of 2
MJSM04
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference Number:
MJSM04
Area Assessed:
Site location: Operatives Handbook
Description:
Loading Plasterboard
Operatives involved:
Site based operatives
WORK ACTIVITY:
Loading of Plasterboard
To be read in conjunction with the company’s Generic Risk
Assessments
MJSRa01
MJSRa02
MJSRa03
MJSRa11
MJSRa12
Working at Height
Manual Handling
Noise
Materials Delivery
Materials / Objects falling from height
Work Area (General Precautions)
•
•
•
•
•
The work area, namely the room where the plasterboard is to be loaded must be free of
other trades working in the immediate area.
All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing.
If other trades are working within the property they must be advised of the work activities
you are about to commence.
To enable operatives to have good access and egress to the work areas the entry door
for loading must be at ground level with no scaffold obstructions to reduce height.
Listed below are board weights and sizes
Product description
Standard wallboard 12.5mm
Standard wallboard 12.5mm
Standard wallboard 15mm
Soundshield 12.5mm
Soundshield 15mm
Fireshield 12.5mm
19mm Plank
Moisture shield 12.5mm
Bonding compound
•
Weight in kilos
13.5
24
29
33
39
26
19
33
25
Size
1800X900
2400X1200
2400X1200
2400X1200
2400X1200
2400X1200
2400X 600
2400X1200
Bag
Adequate lighting is to be provided by the Principle Contactor for the various activities
which will be conducted in the working area.
© M J Stevens Group
1 of 2
MJSM04
Loading
Loading Plasterboard
Plasterboard
Operatives
are
re rrequired
equired tto
o ccarry
arry tthe
he p
plasterboard
la s te r b o a r d o
on
n iits
ts llongest
ongest e
edge
dge iin
n a
an
n a
almost
lmost vvertical
e r tic a l
Op
e r a t iv e s a
position
his sshould
hould be eas
easiest
iest handl
handling
ing pos
position.
ition.
pos
ition tthis
•
•
•
•
•
Ensure
use
gloves
he u
se g
loves or
or a ssuitable
uitable board-carrying
board-carrying device.
device.
Ensure tthe
Trolleys sshould
is ta n c e s a
re rrequired
equired ii.e.
.e. fflats
lats w
ith llong
ong ccorridors.
o r r id o r s .
Trolleys
be
used
distances
are
with
h o u ld b
eu
sed iiff llong
ong d
hrough tthe
he ffloor
loor iin
n a vvertical
errttical
Loadi
ng ffirst
irst & second
second ffloor
loor uni
ts w
ith w
inder sstairs
tairs m
ust be tthrough
Loading
units
with
winder
must
by the
the principle
principle co
ntractor,
ma
nor, this
this will
will require
require the
the temporary
temporary access
access to
to be
be created
created by
manor,
contractor,
orks. A suitable
suitable ssafety
a fe ty
and tthis
his will
will need
need to
to be
be replaced
replaced immediately
immediately on
on ccompletion
o m p le tio n o
off w
works.
ocess, tthis
his tto
o be er
ected by
bar
rier w
ill be rrequired
equired tto
o pr
otect tthe
he openi
ng dur
ing tthis
his pr
barrier
will
protect
opening
during
process,
erected
the p
rinciple ccontractor
ontractor
the
principle
aste skips
skips / area
area provided
provided by
by
The rremoved
emoved rubbish
rubbish / debris
debris iis
s tto
o be depos
ited iin
n tthe
he w
The
deposited
waste
MJ
S
S.
MJS.
platforms of
of a ssize
iz e a
nd
Contractor will
will erect
erect lloading
oading platforms
Wh
en loading
loading flats
flats the
the Principle
Principle Contractor
When
and
floor llevel.
e v e l.
these will
will be
be set
set at
at each
each floor
strength to
to suit
suit the
the board
board required,
required, these
strength
Personal
Pe
rsonal Protective
Protective Equipment
Equipment
Ev
Every
ery sself-employed
elf-employed per
person
son sshall
hall ens
ensure
ure tthat
hat any per
personal
sonal pr
protective
otective equi
equipment
pment pr
provided
ovided tto
o
opriate) iin
n an eff
ficient sstate,
hi
him
m iis
s m
maintained
aintained ((including
including rreplaced
eplaced or ccleaned
leaned as appr
appropriate)
efficient
tate, iin
n
eff
ficient w
rotective E
q u ip m e n t a
efficient
working
orking or
order
der and iin
n good rrepair
epair - ((Extract
Extract fr
from
om th
the
eP
Personal
ers o n a l P
Protective
Equipment
att
Work Regulations).
R e g u la t io n s ) .
Work
•
•
•
Every o
Every
operative
ensure
have
adequate
with
r a in in g w
ith rregards
egards tto
o tthe
perative iis
s tto
oe
nsure tthat
hat tthey
hey h
ave rreceived
e c e iv e d a
dequate ttraining
he
use of any par
use
particular
Personal
Protective
Equipment.
ticular iitem
tem of P
ersonal P
rotective E
quipment.
e
Self e
Self
employed
persons
are
ensure
they
purchase
and
maintain
PPE
with
the
aintain P
PE iin
n lline
in e w
ith th
m p lo y e d p
e rs o n s a
re tto
o e
nsure th
ey p
u rc h a s e a
nd m
relevant ri
relevant
risk
assessments
sk a
s s e s s m e n ts
nd
hey llook
ook a
fte r a
ny PPE p
rovided fo
or tthem
hem a
nd u
se a
Employed p
Employed
persons
are
ensure
after
and
use
any
provided
for
and
e rs o n s a
re tto
oe
nsure tthey
m m e d ia te ly .
report a
ny d
efe
e c ts e
tc tto
o ttheir
heir supervisor
supervisor iimmediately.
report
any
defects
etc
Welfare Facilities
F a c ilitie s
Welfare
Op
eratives will
will use
use tthe
ro v id e d b
y tthe
he P
rin c ip le C
Operatives
he welfare
welfare facilities
fa cil it i e s p
provided
by
Principle
Contractor
ontractor tto
o iinclude
nclude ttoilet
o ile t
fa
cilities a
anteen fa
cilities w
ill b
e u
sed fo
facilities
and
nd M
Mess
ess C
Canteen,
anteen, th
the
e ccanteen
facilities
will
be
used
forr a
allll m
meal
eal b
breaks
re a k s a
and
nd n
no
o
br
eaks w
ea, on any ot
her par
he ssite
breaks
will
ill be hel
held
d iin
n tthe
he w
work
ork ar
area,
other
partt of tthe
ite nor iin
n vvehicles
ehicles ((Private
Private o
orr
company owned)
company
ow ned)
On Completion
off Works
C o m p le tio n o
W o rk s
n a cclean
lean ccondition
All
work
areas
re a s a
are
re tto
ob
be
e lleft
eftt iin
and
allll a
aspects
off ssafety
afe
ety w
with
All w
o rk a
o n d itio n a
nd a
s p e c ts o
ith rregards
egards tto
o tthe
he
im
mediate w
o rk a
re a a
nd cconduct
onduct a vvisual
dge
immediate
work
area
and
inspection
by
operative
perative tto
oe
ensure
nsure tthat
hat tthe
he e
edge
isual in
spection b
y tthe
he o
pr
otection iis
s in p
lace a
nd tthat
hat tthere
here is n
o rrisk
isk tto
o in
jury tto
o tthemselves
hemselves o
th e rs a
s a d
irect
protection
place
and
no
injury
orr o
others
as
direct
fa
all from
re
s u lt o
from that
that area.
area.
result
off a fall
our w
ork iis
s sstored
tored iin
n a ssafe
a fe a
nd p
ro p e r m
anner
Ensure
allll o
other
material
used
sed fo
for
or yyour
work
and
proper
manner
th e r m
aterial tthat
hat iis
s u
En
s u re a
before
departing
property
ou ar
are
ew
working
orking in.
in .
ting ffrom
rom tthe
he pr
operty yyou
bef
ore depar
Re
Report
port tto
Site
Management
Team
on
off tthe
works
and
by
rk s a
nd iiff rrequired
e q u ir e d b
y tthe
he ssite
ite
eam o
n ccompletion
o m p le tio n o
he wo
o tthe
he S
ite M
anagem ent T
ut b
efo
ore lleaving
ru
rules
les ssign
ig n o
out
before
e a v in g
NAME
NA
ME
Andy
White
An
dy W
h ite
DATE
01/11/2009
DA
TE 01/
11/2009
RE
REVIEW
VIEW DA
DATE
TE
01/04/2015
SI
SIGNATURE
GNATURE
MB
MBA
A Sa
Safety
fety & Training
Training Ltd
L td
JO
B T IT L E
JOBTITLE
He
a lt h a
nd safety
safety Co
Health
and
Consultant
n s u lta n t
Unit
Counting
House”
Un
it 6 ““The
The Co
unting Ho
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
©MJS
Stevens
tevens Group
Group
2 of 2
MJSM04
M
JSM04
Loading
Loading P
Plasterboard
lasterboard
Operatives
are
re rrequired
equired tto
o ccarry
arry tthe
he p
plasterboard
la s te r b o a r d o
on
n iits
ts llongest
ongest e
edge
dge iin
n a
an
n a
almost
lmost vvertical
e r tic a l
Op
e r a t iv e s a
position
his sshould
hould be eas
easiest
iest handl
handling
ing pos
position.
ition.
pos
ition tthis
•
•
•
•
•
Ensure
use
gloves
he u
se g
loves or
or a ssuitable
uitable board-carrying
board-carrying device.
device.
Ensure tthe
Trolleys sshould
is ta n c e s a
re rrequired
equired ii.e.
.e. fflats
lats w
ith llong
ong ccorridors.
o r r id o r s .
Trolleys
be
used
distances
are
with
h o u ld b
eu
sed iiff llong
ong d
hrough tthe
he ffloor
loor iin
n a vvertical
errttical
Loadi
ng ffirst
irst & second
second ffloor
loor uni
ts w
ith w
inder sstairs
tairs m
ust be tthrough
Loading
units
with
winder
must
by the
the principle
principle co
ntractor,
ma
nor, this
this will
will require
require the
the temporary
temporary a
ccess to
to be
be created
created by
manor,
access
contractor,
orks. A suitable
suitable ssafety
a fe ty
and tthis
his will
will need
need to
to be
be replaced
replaced immediately
immediately on
on ccompletion
o m p le tio n o
off w
works.
ocess, tthis
his tto
o be er
ected by
bar
rier w
ill be rrequired
equired tto
o pr
otect tthe
he openi
ng dur
ing tthis
his pr
barrier
will
protect
opening
during
process,
erected
the p
rinciple ccontractor
ontractor
the
principle
aste skips
skips / area
area provided
provided by
by
The rremoved
emoved rubbish
rubbish / debris
debris iis
s tto
o be depos
ited iin
n tthe
he w
The
deposited
waste
MJ
S
S.
MJS.
platforms of
of a ssize
iz e a
nd
Contractor will
will erect
erect lloading
oading platforms
Wh
en loading
loading flats
flats the
the Principle
Principle Contractor
When
and
floor llevel.
e v e l.
these will
will be
be set
set at
at each
each floor
strength to
to suit
suit the
the board
board required,
required, these
strength
Personal
Pe
rsonal Protective
Protective Equipment
Equipment
Ev
Every
ery sself-employed
elf-employed per
person
son sshall
hall ens
ensure
ure tthat
hat any per
personal
sonal pr
protective
otective equi
equipment
pment pr
provided
ovided tto
o
opriate) iin
n an eff
ficient sstate,
hi
him
m iis
s m
maintained
aintained ((including
including rreplaced
eplaced or ccleaned
leaned as appr
appropriate)
efficient
tate, iin
n
eff
ficient w
rotective E
q u ip m e n t a
efficient
working
orking or
order
der and iin
n good rrepair
epair - ((Extract
Extract fr
from
om th
the
eP
Personal
ers o n a l P
Protective
Equipment
att
Work Regulations).
R e g u la t io n s ) .
Work
•
•
•
Every o
Every
operative
ensure
have
adequate
with
r a in in g w
ith rregards
egards tto
o tthe
perative iis
s tto
oe
nsure tthat
hat tthey
hey h
ave rreceived
e c e iv e d a
dequate ttraining
he
use of any par
use
particular
Personal
Protective
Equipment.
ticular iitem
tem of P
ersonal P
rotective E
quipment.
e
Self e
Self
employed
persons
are
ensure
they
purchase
and
maintain
PPE
with
the
aintain P
PE iin
n lline
in e w
ith th
m p lo y e d p
e rs o n s a
re tto
o e
nsure th
ey p
u rc h a s e a
nd m
relevant ri
relevant
risk
assessments
sk a
s s e s s m e n ts
nd
hey llook
ook a
fte r a
ny PPE p
rovided fo
or tthem
hem a
nd u
se a
Employed p
Employed
persons
are
ensure
after
and
use
any
provided
for
and
e rs o n s a
re tto
oe
nsure tthey
m m e d ia te ly .
report a
ny d
efe
e c ts e
tc to
to their
their supervisor
supervisor iimmediately.
report
any
defects
etc
Welfare Facilities
F a c ilitie s
Welfare
Op
e r a tiv e s w
ill u
se tthe
ro v id e d b
y tthe
he P
rin c ip le C
Operatives
will
use
he w
welfare
elfare ffacilities
a cil it i e s p
provided
by
Principle
Contractor
ontractor tto
o iinclude
nclude ttoilet
o ile t
fa
cilities a
anteen fa
cilities w
ill b
e u
sed fo
facilities
and
nd M
Mess
ess C
Canteen,
anteen, th
the
e ccanteen
facilities
will
be
used
forr a
allll m
meal
eal b
breaks
re a k s a
and
nd n
no
o
br
eaks w
ea, on any ot
her par
he ssite
breaks
will
ill be hel
held
d iin
n tthe
he w
work
ork ar
area,
other
partt of tthe
ite nor iin
n vvehicles
ehicles ((Private
Private o
orr
company owned)
company
ow ned)
On Completion
off Works
C o m p le tio n o
W o rk s
n a cclean
lean ccondition
All
work
areas
re a s a
are
re tto
ob
be
e lleft
eftt iin
and
allll a
aspects
off ssafety
afe
ety w
with
All w
o rk a
o n d itio n a
nd a
s p e c ts o
ith rregards
egards tto
o tthe
he
im
mediate w
o rk a
re a a
nd cconduct
onduct a vvisual
dge
immediate
work
area
and
inspection
by
operative
perative tto
oe
ensure
nsure tthat
hat tthe
he e
edge
isual in
spection b
y tthe
he o
pr
otection iis
s in p
lace a
nd tthat
hat tthere
here is n
o rrisk
isk tto
o in
jury tto
o tthemselves
hemselves o
th e rs a
s a d
irect
protection
place
and
no
injury
orr o
others
as
direct
all from
re
s u lt o
from tthat
hat area.
area.
result
off a fa
fall
our w
ork iis
s sstored
tored iin
n a ssafe
a fe a
nd p
ro p e r m
anner
Ensure
allll o
other
material
used
for
or yyour
work
and
proper
manner
th e r m
aterial tthat
hat iis
s u
sed fo
En
s u re a
before
departing
property
ou ar
are
ew
working
orking in.
in .
ting ffrom
rom tthe
he pr
operty yyou
bef
ore depar
Re
Report
port tto
Site
Management
Team
on
off tthe
works
and
by
rk s a
nd iiff rrequired
e q u ir e d b
y tthe
he ssite
ite
eam o
n ccompletion
o m p le tio n o
he wo
o tthe
he S
ite M
anagem ent T
ut b
efo
ore lleaving
ru
rules
les ssign
ig n o
out
before
e a v in g
NAME
NA
ME
Andy
White
An
dy W
h ite
DATE
01/11/2009
DA
TE 01/
11/2009
RE
REVIEW
VIEW DA
DATE
TE
01/
01/11/2011
11/2011
SI
SIGNATURE
GNATURE
MB
MBA
A Sa
Safety
fety & Training
Training Ltd
L td
JO
B T IT L E
JOBTITLE
He
a lt h a
nd s
afety Co
Health
and
safety
Consultant
n s u lta n t
Unit
Counting
House”
Un
it 6 ““The
The Co
unting Ho
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
© M J Stevens
Stevens Group
Group
2 of 2
MJSM04
M
JSM04
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference Number:
MJSM05
Area Assessed:
Site location: Operatives Handbook
Description:
Installation of T.J.I floor joists
Operatives Identified:
Site based operatives
WORK ACTIVITY:
Fixing of T.J.I. Joists 1st Floor Joist & 2nd Floor Joist
To be read in conjunction with the company’s Generic Risk
Assessments
MJSRa01
MJSRa02
MJSRa03
MJSRa04
MJSRa08
MJSRa09
MJSRa11
MJSRa12
MJSRa14
MJSRa16
Working at Height
Manual Handling
Noise
Vibration
Power tools
Electrocution
Materials Delivery
Materials / Objects falling from height
Ladders and step ladders
Joist installation
Method of work
•
•
•
•
•
•
•
•
The work area, namely the scaffolding to be provided by the principle contractor. This is
to be free of other trades working in the immediate area. The erected scaffold structure
will be inspected by the Principle Contractors representative as set out in the Work at
Height Regulations 2005
All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing.
Soft landing system is to be placed inside the unit by the principle contractor and
approved by site management.
No other trades are allowed to work within the property they must be advised as to
vacate the work area prior to you commencing work.
Operatives will mark out the position of joists on the appropriate walls in accordance with
the relevant plan.
All cutting to be carried out on the ground. Whilst cutting operations are conducted
consideration is to be given to the following legislations; The Control of Noise at Work
Regulations 2005 & The Vibration at Work Regulations 2005
All joist hangers are to be fitted prior to joists being fitted.
All joist to be lifted by mechanical means to the loading bay, two operatives to unload
together and layout as per plan, ensure once loading operations are completed that the
loading bay gate to the working platform is returned to is correct position allowing
adequate edge protection against falls, if during the loading operations it is felt that
further protection against falls is required, personal fall arrest systems must be
implemented.
© M J Stevens Group
1 of 2
MJSM05
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference Number:
MJSM05
Area Assessed:
Site location: Operatives Handbook
Description:
Installation of T.J.I floor joists
Operatives Identified:
Site based operatives
WORK ACTIVITY:
Fixing of T.J.I. Joists 1st Floor Joist & 2nd Floor Joist
To be read in conjunction with the company’s Generic Risk
Assessments
MJSRa01
MJSRa02
MJSRa03
MJSRa04
MJSRa08
MJSRa09
MJSRa11
MJSRa12
MJSRa14
MJSRa16
Working at Height
Manual Handling
Noise
Vibration
Power tools
Electrocution
Materials Delivery
Materials / Objects falling from height
Ladders and step ladders
Joist installation
Method of work
•
•
•
•
•
•
•
•
The work area, namely the scaffolding to be provided by the principle contractor. This is
to be free of other trades working in the immediate area. The erected scaffold structure
will be inspected by the Principle Contractors representative as set out in the Work at
Height Regulations 2005
All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing.
Soft landing system is to be placed inside the unit by the principle contractor and
approved by site management.
No other trades are allowed to work within the property they must be advised as to
vacate the work area prior to you commencing work.
Operatives will mark out the position of joists on the appropriate walls in accordance with
the relevant plan.
All cutting to be carried out on the ground. Whilst cutting operations are conducted
consideration is to be given to the following legislations; The Control of Noise at Work
Regulations 2005 & The Vibration at Work Regulations 2005
All joist hangers are to be fitted prior to joists being fitted.
All joist to be lifted by mechanical means to the loading bay, two operatives to unload
together and layout as per plan, ensure once loading operations are completed that the
loading bay gate to the working platform is returned to is correct position allowing
adequate edge protection against falls, if during the loading operations it is felt that
further protection against falls is required, personal fall arrest systems must be
implemented.
© M J Stevens Group
1 of 2
MJSM05
•
•
•
•
•
•
•
Stairwell
Stairwell ttrimmers
r im m e r s w
will
ill n
need
eed tto
ob
be
ep
positioned
ositioned ffrom
ro m b
below
elow [[off
offf a ssuitable
u ita b le w
working
o r k in g p
platform
la tfo r m
contractor] a
nd llifted
iftted iinto
supplied
supplied & erected
erected by
by the
th e p
principle
rinciple contractor]
and
n to p
position.
osition.
joists are
are to
to be
be fitted
fitted into
RSJs they
they will
will be
be fitted
f it t e d a
Where
Where joists
into RSJs
ass a
above.
bove .
oaded by fo
orklifftt ont
the loading
loading b
22m
m cchipboard
hipboard fflooring
looring w
ill be lloaded
o the
22mm
will
forklift
onto
bay.
ay.
st
ow o
off fflooring
lo o rin g o
off
fff tthe
he sscaffold,
cafffold, g
giving
platform
work
o rk
ill p
osition 1 rrow
Operatives
Operatives w
will
position
iving a ssafe
a fe p
latform tto
ow
offf for
for tthe
fo
he rrest
est of tthe
he floor.
floor.
All
be
and
designated
All off
offf ccuts
uts tto
ob
e ccleared
le a r e d a
nd placed
placed iin
n tthe
he d
esignated skip
skip as
as provided
provided by
by the
the principle
principle
contractor.
contractor.
y tthe
he Pr
in c ip le C
ontactor ffor
or tthe
he w
o rk .
Adequate
be
provided
by
Principle
Contactor
work.
Adequate llighting
ighting iis
s tto
ob
ep
rovided b
ith tthe
he rrelevant
e le v a n t C
OSHH a
ssessment fo
ob
e fa
a m ilia r w
or
Operatives
using
are
be
familiar
with
COSHH
assessment
for
Operatives u
sing adhesives
a d h e s iv e s a
re tto
he manufactures
manufa
actures
nd to m
ix th
e p
roduct as per tthe
the
product
they
will
be
and
mix
the
product
the p
roduct th
ey w
ill b
e using
u s in g a
instructions,
instructions,
Personal
Protective
otective Equipment
Equipment
Personal Pr
Every
elf-employed per
person
son sshall
hall ens
ensure
personal
protective
equipment
provided
otective equi
pment pr
ovided tto
o
ure tthat
hat any per
sonal pr
Every sself-employed
hi
m iis
sm
aintained ((including
including rreplaced
eplaced or ccleaned
opriate) iin
n a eff
ffficient sstate,
tate, iin
n eff
fffi
ficient
him
maintained
appropriate)
efficient
efficient
leaned as appr
wo
r k in g o
rd e r a
nd iin
ng
ood rrepair
epair - ((Extract
Extract ffrom
rom tthe
he P
e rs o n a l P
ro te c tiv e E
q u ip m e n t a
o rk
working
order
and
good
Personal
Protective
Equipment
att W
Work
Re
g u la tio n s ) .
Regulations).
hey h
ave rreceived
e c e iv e d a
dequate ttraining
r a in in g w
ith rregards
egards tto
o tthe
he
Every o
perative iis
s tto
oe
nsure tthat
hat tthey
• Every
operative
ensure
have
adequate
with
Protective E
quipment.
use of any par
ticular iitem
tem of P
ersonal Protective
use
particular
Personal
Equipment.
he
nsure tthey
hey p
u rc h a s e a
nd m
aintain PPE iin
n lline
in e w
ith tthe
Self e
m p lo y e d p
e rs o n s a
re tto
o e
• Self
employed
persons
are
ensure
purchase
and
maintain
with
relevant ri
sk a
s s e s s m e n ts
relevant
risk
assessments
nd
nd u
se a
hem a
hey llook
ook a
ftter a
ny PPE p
rovided fo
or tthem
Employed p
e rs o n s a
re tto
oe
nsure tthey
• Employed
persons
are
ensure
after
and
use
any
provided
for
and
ny d
efe
e c ts e
upervisor iimmediately.
mmediately.
report a
tc tto
o ttheir
heir ssupervisor
report
any
defects
etc
Welfare
F a c ilitie s
Welfare Facilities
Op
Operatives
e r a t iv e s w
will
ill u
use
se tthe
he w
welfare
elfa
are ffacilities
a c ilitie s p
provided
r o v id e d b
by
y tthe
he P
Principle
r in c ip le C
Contractor
ontractor tto
o iinclude
nclude ttoilet
o ile t
fa
facilities
cilities a
and
nd M
Mess
ess C
Canteen,
anteen, th
the
e ccanteen
anteen fa
facilities
cilities w
will
ill b
be
e u
used
sed fo
forr a
allll m
meal
eal b
breaks
re a k s a
and
nd n
no
o
br
breaks
eaks w
will
ill be hel
held
d iin
n tthe
he w
work
ork ar
area,
ea, o
on
na
any
ny o
other
ther p
part
art of
of the
the ssite
ite n
nor
or iin
n vvehicles
ehicles ((Private
Private o
orr
company
company owned).
o w n e d ).
On Completion
Completion of
of Works
W o rk s
Alll w
work
areas
re a s a
are
re tto
ob
be
e lleft
efftt iin
and
allll a
aspects
off ssafety
afe
e ty w
with
n a cclean
lean ccondition
o n d itio n a
nd a
s p e c ts o
ith rregards
egards tto
o tthe
he
Al
o rk a
immediate
work
o rk a
area
re a a
and
nd cconduct
onduct a vvisual
inspection
by
to ensure
ensure tthat
hat tthe
he edge
edge
isual in
spection b
y tthe
he operative
operative to
im
mediate w
protection
s iin
n pl
place
ace and tthat
hat tthere
here iis
hemselves or ot
others
hers as a di
direct
s no rrisk
isk tto
o iinjury
njury tto
o tthemselves
rect
pr
otection iis
all from
from tthat
hat area.
area.
result
off a fa
fall
re
s u lt o
Ensure
allll o
other
material
which
used
sed fo
for
or yyour
our w
work
ork iis
s sstored
tored iin
n a ssafe
a fe a
and
nd p
proper
ro p e r m
manner
anner
En
s u re a
th e r m
a te r ia l w
hich iis
su
before
departing
property
ou ar
are
ew
working
orking iin.
n.
bef
ore depar
ting ffrom
rom tthe
he pr
operty yyou
rk s a
nd iiff rrequired
e q u ir e d b
y tthe
he ssite
ite
Re
Report
porrtt tto
Site
Management
Team
on
off tthe
works
and
by
eam o
n ccompletion
o m p le tio n o
he wo
o tthe
he S
ite M
anagem ent T
ut b
efo
ore lleaving
ru
rules
les ssign
ig n o
out
before
e a v in g
DA
TE 1/
11/2009
An
dy W
h ite
NAME
Andy
White
DATE
1/11/2009
NA
ME
RE
VIEW DA
TE
REVIEW
DATE
01/04/2015
SI
SIGNATURE
GNATURE
MB
MBA
A Safety
S a f et y & T
Training
r a in in g L
Ltd
td
JOBTITLE
JO
BTITLE
Health
and
safety
Consultant
n s u lta n t
He
a lt h a
nd s
afety Co
Un
it 6 ““The
The Co
unting Ho
use”
Unit
Counting
House”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
© M J Stevens
Stevens Group
Group
•
•
•
•
•
•
•
2 of 2
MJSM05
MJSM05
Stairwell
Stairwell ttrimmers
r im m e r s w
will
ill n
need
eed tto
ob
be
ep
positioned
ositioned ffrom
ro m b
below
elow [[off
offf a ssuitable
u ita b le w
working
o r k in g p
platform
la tfo r m
contractor] a
nd llifted
iftted iinto
supplied
supplied & erected
erected by
by the
th e p
principle
rinciple contractor]
and
n to p
position.
osition.
joists are
are to
to be
be fitted
fitted into
RSJs they
they will
will be
be fitted
f it t e d a
Where
Where joists
into RSJs
ass a
above.
bove .
oaded by fo
orklifftt ont
the loading
loading b
22m
m cchipboard
hipboard fflooring
looring w
ill be lloaded
o the
22mm
will
forklift
onto
bay.
ay.
st
ow o
off fflooring
lo o rin g o
off
fff tthe
he sscaffold,
cafffold, g
giving
platform
work
o rk
ill p
osition 1 rrow
Operatives
Operatives w
will
position
iving a ssafe
a fe p
latform tto
ow
offf for
for tthe
fo
he rrest
est of tthe
he floor.
floor.
All
be
and
designated
All off
offf ccuts
uts tto
ob
e ccleared
le a r e d a
nd placed
placed iin
n tthe
he d
esignated skip
skip as
as provided
provided by
by the
the principle
principle
contractor.
contractor.
y tthe
he Pr
in c ip le C
ontactor ffor
or tthe
he w
o rk .
Adequate
be
provided
by
Principle
Contactor
work.
Adequate llighting
ighting iis
s tto
ob
ep
rovided b
ith tthe
he rrelevant
e le v a n t C
OSHH a
ssessment fo
ob
e fa
a m ilia r w
or
Operatives
using
are
be
familiar
with
COSHH
assessment
for
Operatives u
sing adhesives
a d h e s iv e s a
re tto
he manufactures
manufa
actures
nd to m
ix th
e p
roduct as per tthe
the
product
they
will
be
and
mix
the
product
the p
roduct th
ey w
ill b
e using
u s in g a
instructions,
instructions,
Personal
Protective
otective Equipment
Equipment
Personal Pr
Every
elf-employed per
person
son sshall
hall ens
ensure
personal
protective
equipment
provided
otective equi
pment pr
ovided tto
o
ure tthat
hat any per
sonal pr
Every sself-employed
hi
m iis
sm
aintained ((including
including rreplaced
eplaced or ccleaned
opriate) iin
n a eff
ffficient sstate,
tate, iin
n eff
fffi
ficient
him
maintained
appropriate)
efficient
efficient
leaned as appr
wo
r k in g o
rd e r a
nd iin
ng
ood rrepair
epair - ((Extract
Extract ffrom
rom tthe
he P
e rs o n a l P
ro te c tiv e E
q u ip m e n t a
o rk
working
order
and
good
Personal
Protective
Equipment
att W
Work
Re
g u la tio n s ) .
Regulations).
hey h
ave rreceived
e c e iv e d a
dequate ttraining
r a in in g w
ith rregards
egards tto
o tthe
he
Every o
perative iis
s tto
oe
nsure tthat
hat tthey
• Every
operative
ensure
have
adequate
with
Protective E
quipment.
use of any par
ticular iitem
tem of P
ersonal Protective
use
particular
Personal
Equipment.
he
nsure tthey
hey p
u rc h a s e a
nd m
aintain PPE iin
n lline
in e w
ith tthe
Self e
m p lo y e d p
e rs o n s a
re tto
o e
• Self
employed
persons
are
ensure
purchase
and
maintain
with
relevant ri
sk a
s s e s s m e n ts
relevant
risk
assessments
nd
nd u
se a
hem a
hey llook
ook a
ftter a
ny PPE p
rovided fo
or tthem
Employed p
e rs o n s a
re tto
oe
nsure tthey
• Employed
persons
are
ensure
after
and
use
any
provided
for
and
ny d
efe
e c ts e
upervisor iimmediately.
mmediately.
report a
tc tto
o ttheir
heir ssupervisor
report
any
defects
etc
Welfare
F a c ilitie s
Welfare Facilities
Op
Operatives
e r a t iv e s w
will
ill u
use
se tthe
he w
welfare
elfa
are ffacilities
a c ilitie s p
provided
r o v id e d b
by
y tthe
he P
Principle
r in c ip le C
Contractor
ontractor tto
o iinclude
nclude ttoilet
o ile t
fa
facilities
cilities a
and
nd M
Mess
ess C
Canteen,
anteen, th
the
e ccanteen
anteen fa
facilities
cilities w
will
ill b
be
e u
used
sed fo
forr a
allll m
meal
eal b
breaks
re a k s a
and
nd n
no
o
br
breaks
eaks w
will
ill be hel
held
d iin
n tthe
he w
work
ork ar
area,
ea, o
on
na
any
ny o
other
ther p
part
art of
of the
the ssite
ite n
nor
or iin
n vvehicles
ehicles ((Private
Private o
orr
company
company owned).
o w n e d ).
On Completion
Completion of
of Works
W o rk s
Alll w
work
areas
re a s a
are
re tto
ob
be
e lleft
efftt iin
and
allll a
aspects
off ssafety
afe
e ty w
with
n a cclean
lean ccondition
o n d itio n a
nd a
s p e c ts o
ith rregards
egards tto
o tthe
he
Al
o rk a
immediate
work
o rk a
area
re a a
and
nd cconduct
onduct a vvisual
inspection
by
to ensure
ensure tthat
hat tthe
he edge
edge
isual in
spection b
y tthe
he operative
operative to
im
mediate w
protection
s iin
n pl
place
ace and tthat
hat tthere
here iis
hemselves or ot
others
hers as a di
direct
s no rrisk
isk tto
o iinjury
njury tto
o tthemselves
rect
pr
otection iis
all from
from tthat
hat area.
area.
result
off a fa
fall
re
s u lt o
Ensure
allll o
other
material
which
used
sed fo
for
or yyour
our w
work
ork iis
s sstored
tored iin
n a ssafe
a fe a
and
nd p
proper
ro p e r m
manner
anner
En
s u re a
th e r m
a te r ia l w
hich iis
su
before
departing
property
ou ar
are
ew
working
orking iin.
n.
bef
ore depar
ting ffrom
rom tthe
he pr
operty yyou
rk s a
nd iiff rrequired
e q u ir e d b
y tthe
he ssite
ite
Re
Report
porrtt tto
Site
Management
Team
on
off tthe
works
and
by
eam o
n ccompletion
o m p le tio n o
he wo
o tthe
he S
ite M
anagem ent T
ut b
efo
ore lleaving
ru
rules
les ssign
ig n o
out
before
e a v in g
DA
TE 1/
11/2009
Andy W
h ite
NAME
Andy
White
DATE
1/11/2009
NA
ME
RE
VIEW DA
TE
REVIEW
DATE
01/
01/11/2011
11/2011
SI
SIGNATURE
GNATURE
MB
MBA
A Safety
S a f et y & T
Training
r a in in g L
Ltd
td
JOBTITLE
JO
BTITLE
Health
and
safety
Consultant
n s u lta n t
He
a lt h a
nd s
afety Co
Un
it 6 ““The
The Co
unting Ho
use”
Unit
Counting
House”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
© M J Stevens
Stevens Group
Group
2 of 2
MJSM05
MJSM05
M J StevensLtd
M J Stevens Contracting Division
Method Statement
Method Statement Reference Number:
MJSM06
Area Assessed:
Site location: Operatives Handbook
Description:
First & Second Fix Carpentry
Operatives Identified:
Site based operatives
WORK ACTIVITY:
First & Second Fix Carpentry
Final fix
Attaching Porches
To be read in conjunction with the company’s Generic Risk
Assessments
MJSRa01
MJSRa02
MJSRa03
MJSRa04
MJSRa08
MJSRa09
MJSRa10
MJSRa11
MJSRa12
MJSRa13
MJSRa14
Working at Height
Manual Handling
Noise
Vibration
Power tools
Electrocution
Breathing in dust particles
Materials Delivery
Materials / Objects falling from height
Mobile scaffold towers and platforms
Ladders and step ladders
This method statement covers all aspects of first and second fix carpentry which is: fixing
noggins to floor joists & ceiling trusses, fitting stairs to each floor level, timber studwork for
partitions [if specified], fitting all internal door linings to the studwork including to block work
openings, erect all soil pipe boxing, fit all sill boards, creating bulkheads to suit design and
airing cupboards if required.
The Work Area & Work at Height
•
The work areas, the area beneath any joist installations and the inside of the plot is to be
free of other trades, visitors and site staff.
•
All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing.
•
Site operatives are to ensure that the Principle Contractor has inspected any scaffold
structures in line with the requirements set out in the Work at Height Regulations 2005.
© M J Stevens Group
1 of 4
MJSM06
M J StevensLtd
M J Stevens Contracting Division
Method Statement
Method Statement Reference Number:
MJSM06
Area Assessed:
Site location: Operatives Handbook
Description:
First & Second Fix Carpentry
Operatives Identified:
Site based operatives
WORK ACTIVITY:
First & Second Fix Carpentry
Final fix
Attaching Porches
To be read in conjunction with the company’s Generic Risk
Assessments
MJSRa01
MJSRa02
MJSRa03
MJSRa04
MJSRa08
MJSRa09
MJSRa10
MJSRa11
MJSRa12
MJSRa13
MJSRa14
Working at Height
Manual Handling
Noise
Vibration
Power tools
Electrocution
Breathing in dust particles
Materials Delivery
Materials / Objects falling from height
Mobile scaffold towers and platforms
Ladders and step ladders
This method statement covers all aspects of first and second fix carpentry which is: fixing
noggins to floor joists & ceiling trusses, fitting stairs to each floor level, timber studwork for
partitions [if specified], fitting all internal door linings to the studwork including to block work
openings, erect all soil pipe boxing, fit all sill boards, creating bulkheads to suit design and
airing cupboards if required.
The Work Area & Work at Height
•
The work areas, the area beneath any joist installations and the inside of the plot is to be
free of other trades, visitors and site staff.
•
All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing.
•
Site operatives are to ensure that the Principle Contractor has inspected any scaffold
structures in line with the requirements set out in the Work at Height Regulations 2005.
© M J Stevens Group
1 of 4
MJSM06
The basics are to be checked by the operative prior to starting work i.e. that proper
access is available, handrails are in place, no missing boards etc.
•
If other trades are working within the property they must be advised of the work activities
that are about to commence.
•
To reduce the risk to injury from the direct results of a fall from height ensure that
adequate protection is given against a fall whilst installing flooring etc, the Principle
Contractor must provided a suitable fall prevention/arrest/mitigation system, this can be
provided in one of three ways, these being: soft landing bean bag or air bag systems
installed by competent persons in line with the manufacturers instructions and training.
The physical precautions for work at height are the responsibility of the principal
contractor but operatives must ensure these things are in place prior to starting work.
•
Adequate lighting is to be provided by the Principle Contactor for the various activities
which will be conducted in the unit.
•
Operatives using solvent based adhesives are to be familiar with the relevant COSHH
data sheet for the product they will be using as per the manufactures instructions, using
the correct (PPE) and (RPE) required Personal Protective Equipment and Respiratory
Protective Equipment. All PPE & RPE is maintained as set out in the Personal
Protective Equipment at Work Regulations 1992
First Fix Carpentry
Operatives are required to load all materials e.g. Stairs, floorboards, studwork, linings,
window boards & sundries. These materials will be deposited outside the relevant plot by
mechanical means, supplied by the principle contractor with an operator in a safe and
systematic manner, on level ground.
Method of work
•
•
•
•
•
•
•
•
•
•
•
•
•
•
Edge Protection to stairwells is to be maintained at all times
Staircases will be lifted into position in the relevant stairwell and fixed by two or more
operatives to allow for the weighty nature of these items
Herringbone strutting will be fixed between the joists securely as the plan indicates and
also secure perimeter noggins.
Floorboards will be carried up the secure flight of stairs and fixed to the joists in a safe
and systematic manner only after a temporary handrail has been constructed around the
stairwell.
On completion of the full laying of the floorboards, ceiling noggins will be fixed to the
ceiling joists of the roof trusses properly spaced to receive the plasterboard ceiling.
Stud framework will be made in accordance with the relevant plans on the floor and two
operatives will then raise the framework into position and fix.
Alternatively the studwork framework will be constructed by one operative.
The groundwork studwork will be constructed as above.
Linings will be made up by one operative and fixed securely by into the door openings
External doors will then be hung
Window boards will be fixed securely into the window openings
All these works will proceed throughout with off-cuts of timber and shavings being cleared
and deposited in waste skips at regular intervals to avoid hazards to prevent accidents
occurring.
All portable tools to be either battery operated or have power from 110v generator and
maintained in accordance with the Provision and Use of Work Equipment Regulations.
The removed rubbish / debris is to be deposited in the waste skips / area provided by the
Principle Contractor.
© M J Stevens Group
2 of 4
MJSM06
The basics are to be checked by the operative prior to starting work i.e. that proper
access is available, handrails are in place, no missing boards etc.
•
If other trades are working within the property they must be advised of the work activities
that are about to commence.
•
To reduce the risk to injury from the direct results of a fall from height ensure that
adequate protection is given against a fall whilst installing flooring etc, the Principle
Contractor must provided a suitable fall prevention/arrest/mitigation system, this can be
provided in one of three ways, these being: soft landing bean bag or air bag systems
installed by competent persons in line with the manufacturers instructions and training.
The physical precautions for work at height are the responsibility of the principal
contractor but operatives must ensure these things are in place prior to starting work.
•
Adequate lighting is to be provided by the Principle Contactor for the various activities
which will be conducted in the unit.
•
Operatives using solvent based adhesives are to be familiar with the relevant COSHH
data sheet for the product they will be using as per the manufactures instructions, using
the correct (PPE) and (RPE) required Personal Protective Equipment and Respiratory
Protective Equipment. All PPE & RPE is maintained as set out in the Personal
Protective Equipment at Work Regulations 1992
First Fix Carpentry
Operatives are required to load all materials e.g. Stairs, floorboards, studwork, linings,
window boards & sundries. These materials will be deposited outside the relevant plot by
mechanical means, supplied by the principle contractor with an operator in a safe and
systematic manner, on level ground.
Method of work
•
•
•
•
•
•
•
•
•
•
•
•
•
•
Edge Protection to stairwells is to be maintained at all times
Staircases will be lifted into position in the relevant stairwell and fixed by two or more
operatives to allow for the weighty nature of these items
Herringbone strutting will be fixed between the joists securely as the plan indicates and
also secure perimeter noggins.
Floorboards will be carried up the secure flight of stairs and fixed to the joists in a safe
and systematic manner only after a temporary handrail has been constructed around the
stairwell.
On completion of the full laying of the floorboards, ceiling noggins will be fixed to the
ceiling joists of the roof trusses properly spaced to receive the plasterboard ceiling.
Stud framework will be made in accordance with the relevant plans on the floor and two
operatives will then raise the framework into position and fix.
Alternatively the studwork framework will be constructed by one operative.
The groundwork studwork will be constructed as above.
Linings will be made up by one operative and fixed securely by into the door openings
External doors will then be hung
Window boards will be fixed securely into the window openings
All these works will proceed throughout with off-cuts of timber and shavings being cleared
and deposited in waste skips at regular intervals to avoid hazards to prevent accidents
occurring.
All portable tools to be either battery operated or have power from 110v generator and
maintained in accordance with the Provision and Use of Work Equipment Regulations.
The removed rubbish / debris is to be deposited in the waste skips / area provided by the
Principle Contractor.
© M J Stevens Group
2 of 4
MJSM06
Second Fix Carpentry
•
•
•
The second fix method of work is largely similar to first fix with all materials being brought
to the plot by the principle contractor.
Exceptions to this are kitchen units exceeding 25kg in weight. These will be lifted into the
position by two operatives. This also applies to worktops and vanity units. Units will be
loaded and brought to each plot by mechanical handling machine.
All portable tools will confirm to the provision of work and use of work-equipment
regulations.
Final fix
•
•
Will commence once the house is completed fixing door furniture latches etc.
All portable tools & equipment will conform to the Provision and Use of Work-Equipment
Regulations 1998.
Attaching Porches
•
•
•
•
The materials needed for construction of a porch will be loaded and brought to the
relevant plot by mechanical handling means and deposited outside the plot on level
ground.
A scaffold is to be erected and inspected in line with the Work at Height Regulations
2005 this will be provided at the correct height by the principle contractor for each porch.
Edge protection will be also provided.
All waste materials will be gathered up at regular intervals to avoid hazards of accidents
occurring.
All portable tools & equipment will conform to the Provision and Use of Work-Equipment
Regulations 1998.
Maintenance and replacement of personal Protective equipment
Every self-employed person shall ensure that any personal protective equipment provided to
him is maintained (including replaced or cleaned as appropriate) in a efficient state, in efficient
working order and in good repair - (Extract from the Personal Protective Equipment at Work
Regulations).
•
•
•
Every operative is to ensure that they have received adequate training with regards to the
use of any particular item of Personal Protective Equipment.
Self employed persons are to ensure they purchase and maintain PPE in line with the
relevant risk assessments
Employed persons are to ensure they look after and use any PPE provided for them and
report any defects etc to their supervisor immediately.
Welfare Facilities
Operatives will use the welfare facilities provided by the Principle Contractor to include toilet
facilities and Mess Canteen, the canteen facilities will be used for all meal breaks and no
breaks will be held in the work area, on any other part of the site nor in vehicles (Private or
company owned)
On Completion of Works
© M J Stevens Group
3 of 4
MJSM06
Second Fix Carpentry
•
•
•
The second fix method of work is largely similar to first fix with all materials being brought
to the plot by the principle contractor.
Exceptions to this are kitchen units exceeding 25kg in weight. These will be lifted into the
position by two operatives. This also applies to worktops and vanity units. Units will be
loaded and brought to each plot by mechanical handling machine.
All portable tools will confirm to the provision of work and use of work-equipment
regulations.
Final fix
•
•
Will commence once the house is completed fixing door furniture latches etc.
All portable tools & equipment will conform to the Provision and Use of Work-Equipment
Regulations 1998.
Attaching Porches
•
•
•
•
The materials needed for construction of a porch will be loaded and brought to the
relevant plot by mechanical handling means and deposited outside the plot on level
ground.
A scaffold is to be erected and inspected in line with the Work at Height Regulations
2005 this will be provided at the correct height by the principle contractor for each porch.
Edge protection will be also provided.
All waste materials will be gathered up at regular intervals to avoid hazards of accidents
occurring.
All portable tools & equipment will conform to the Provision and Use of Work-Equipment
Regulations 1998.
Maintenance and replacement of personal Protective equipment
Every self-employed person shall ensure that any personal protective equipment provided to
him is maintained (including replaced or cleaned as appropriate) in a efficient state, in efficient
working order and in good repair - (Extract from the Personal Protective Equipment at Work
Regulations).
•
•
•
Every operative is to ensure that they have received adequate training with regards to the
use of any particular item of Personal Protective Equipment.
Self employed persons are to ensure they purchase and maintain PPE in line with the
relevant risk assessments
Employed persons are to ensure they look after and use any PPE provided for them and
report any defects etc to their supervisor immediately.
Welfare Facilities
Operatives will use the welfare facilities provided by the Principle Contractor to include toilet
facilities and Mess Canteen, the canteen facilities will be used for all meal breaks and no
breaks will be held in the work area, on any other part of the site nor in vehicles (Private or
company owned)
On Completion of Works
© M J Stevens Group
3 of 4
MJSM06
Al
Alll w
work
o rk a
areas
re a s a
are
re tto
ob
be
e lleft
efftt iin
n a cclean,
lean, ti
tidy
dy and
and ssafe
afe ccondition.
ondition.
En
s u re a
th e r m
aterials stored
stored in
in a safe
safe and
and proper
proper manner
m anner b
Ensure
allll o
other
materials
before
efo
ore departing
departing ffrom
rom tthe
he
pr
operty yyou
ou ar
ew
orking iin/on.
n/on.
property
are
working
Re
Report
port tto
Site
Management
Team
on
off tthe
works
and
by
o tthe
he S
ite M
anagem ent T
eam o
n ccompletion
o m p le tio n o
he wo
rk s a
nd iiff rrequired
e q u ir e d b
y tthe
he ssite
ite
rules
out
before
ru
les sign
s ig n o
ut b
efo
ore lleaving
e a v in g
NA
ME
NAME
An
dy W
h ite
Andy
White
DA
DATE
TE 01/11
01/11/2009
/2009
RE
VIEW DATE
DATE
REVIEW
01/04/2015
SI
SIGNATURE
GNATURE
MB
MBA
AS
Safety
a f et y & T
Training
r a in in g L
Ltd
td
JO
B T IT L E
JOBTITLE
He
alth a
nd safety
s a fe t y C
Health
and
Consultant
onsultant
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
©MJS
Stevens
tevens Group
Group
4 of 4
MJSM06
MJ
SM06
Al
Alll w
work
o rk a
areas
re a s a
are
re tto
ob
be
e lleft
efftt iin
n a cclean,
lean, ti
tidy
dy and
and ssafe
afe ccondition.
ondition.
En
s u re a
th e r m
aterials stored
stored in
in a safe
safe and
and proper
proper manner
m anner b
Ensure
allll o
other
materials
before
efo
ore departing
departing ffrom
rom tthe
he
pr
operty yyou
ou ar
ew
orking iin/on.
n/on.
property
are
working
Re
Report
port tto
Site
Management
Team
on
off tthe
works
and
by
o tthe
he S
ite M
anagem ent T
eam o
n ccompletion
o m p le tio n o
he wo
rk s a
nd iiff rrequired
e q u ir e d b
y tthe
he ssite
ite
rules
out
before
ru
les ssign
ig n o
ut b
efo
ore lleaving
e a v in g
NA
ME
NAME
An
dy W
h ite
Andy
White
DA
DATE
TE 01/11
01/11/2009
/2009
RE
VIEW DATE
DATE
REVIEW
01/11/2011
01/11
/2011
SI
SIGNATURE
GNATURE
MB
MBA
AS
Safety
a f et y & T
Training
r a in in g L
Ltd
td
JO
B T IT L E
JOBTITLE
He
alth a
nd safety
s a fe t y C
Health
and
Consultant
onsultant
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
© M J Stevens
Stevens Group
Group
4 of 4
MJSM06
MJ
SM06
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference Number:
MJSM07
Area Assessed:
Site locations: Operatives Handbook
Description:
Installation of Roofing Trusses
Operatives Identified:
Site based operatives
WORK ACTIVITY:
Installation of standard Roof Trusses
To be read in conjunction with the company’s Generic Risk
Assessments
MJSRa01
MJSRa02
MJSRa03
MJSRa04
MJSRa08
MJSRa09
MJSRa11
MJSRa12
MJSRa17
Working at Height
Manual Handling
Noise
Vibration
Power tools
Electrocution
Materials Delivery
Materials / Objects falling from height
Roof truss installation
The Work Area & Work at Height
•
The work area (the wall plate level scaffold), the area beneath and the inside of the plot
are to be free of other trades, visitors and site staff.
•
All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing in particular the scaffold working platform.
•
Site operatives are to ensure that the Principle Contractor has inspected the scaffold
structure in line with the requirements set out in the Work at Height Regulations 2005.
The basics are to be checked by the operative prior to starting work i.e. that proper
access is available, handrails are in place, no missing boards etc.
•
If other trades are working within the property they must be advised of the work activities
that are about to commence.
•
To reduce the risk to injury from the direct results of a fall from height (i.e. when placing
the roof trusses) ensure that adequate protection is given against a fall from within the
building,
the
Principle
Contractor
must
provided
a
suitable
fall
prevention/arrest/mitigation system, this can be provided in one of three ways, these
being: soft landing bean bag or air bag systems installed by competent persons in line
© M J Stevens Group
1 of 3
MJSM07
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference Number:
MJSM07
Area Assessed:
Site locations: Operatives Handbook
Description:
Installation of Roofing Trusses
Operatives Identified:
Site based operatives
WORK ACTIVITY:
Installation of standard Roof Trusses
To be read in conjunction with the company’s Generic Risk
Assessments
MJSRa01
MJSRa02
MJSRa03
MJSRa04
MJSRa08
MJSRa09
MJSRa11
MJSRa12
MJSRa17
Working at Height
Manual Handling
Noise
Vibration
Power tools
Electrocution
Materials Delivery
Materials / Objects falling from height
Roof truss installation
The Work Area & Work at Height
•
The work area (the wall plate level scaffold), the area beneath and the inside of the plot
are to be free of other trades, visitors and site staff.
•
All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing in particular the scaffold working platform.
•
Site operatives are to ensure that the Principle Contractor has inspected the scaffold
structure in line with the requirements set out in the Work at Height Regulations 2005.
The basics are to be checked by the operative prior to starting work i.e. that proper
access is available, handrails are in place, no missing boards etc.
•
If other trades are working within the property they must be advised of the work activities
that are about to commence.
•
To reduce the risk to injury from the direct results of a fall from height (i.e. when placing
the roof trusses) ensure that adequate protection is given against a fall from within the
building,
the
Principle
Contractor
must
provided
a
suitable
fall
prevention/arrest/mitigation system, this can be provided in one of three ways, these
being: soft landing bean bag or air bag systems installed by competent persons in line
© M J Stevens Group
1 of 3
MJSM07
with the manufacturers instructions and training or a birdcage scaffold erected by a
specialist contractor. The safety physical precautions for work at height are the
responsibility of the principal contractor but operatives must ensure these things are in
place prior to starting work.
Placement of trusses
•
The Roof Trusses will be the responsibility of the principal contractor until they are placed
on the wall plate by mechanical means. The lifting operations used to achieve this are
not under the control of MJ Stevens. The principal contractor will arrange lifting
appliances, lifting plan, slingers, signallers etc. Using mechanical means in this way will
drastically reducing the manual handling operations required to complete the task.
•
When installing the Roof Trusses it is possible that the operatives are required to stand
on the truss edge or at the wall plate position, this may cause the operative to be above
the level of the edge protection on the scaffold. It may therefore be necessary for
additional guard rails to be constructed to protect the operative against the risks to falls.
If this is the case a competent scaffolder is to make the alterations (arranged by the
principal contractor).
•
All operatives will be trained in the installation of Roof Trusses and hold CSCS cards
•
The removed rubbish / debris is to be deposited in the waste skips / area provided by the
Principle Contractor no throwing or dropping of materials or waste from height is
permitted.
•
The Principal contractor is to make arrangements for materials and tools to be delivered
to the scaffold via a loading bay, hoist or similar Do Not carry any tools or materials up or
down ladders.
•
If there is any doubt over safety precautions at the location or if weather conditions are
safe to continue the supervisor is to be contacted immediately.
The truss roof will be installed in the following sequence:
1. Before you start work ensure: fall protection is in place, scaffold is erected to the correct
height, access to and from the work area is safe, all PPE and equipment required is on
site and in good condition, the method of work is understood, you have been inducted
and you are aware of the site procedures for fire etc and the right personnel are on site to
complete the work safely
2. When on the scaffold stand well clear while the trusses are guided into position and do
not attempt to lift them into place manually.
3. The first truss will be lifted into place, aligned and then fixed using battens to the scaffold
structure
4. With two operatives one on each side of the roof, working together and starting at one
side, walk the trusses into the correct position for fixing one at a time and secured to the
previous one ensuring the structure remains solid at all times. Fix using a nail gun (if you
have been trained to use one) or a hammer & nails.
5. Wind bracing is to be installed as the roof progresses.
6. When it is time to access the inside of the truss structure, ensure a good platform is
placed on the trusses to provide a good footing DO NOT walk on the trusses themselves.
7. When all the trusses are in place the battens holding the end trusses are then to be
removed.
8. Trim off the trusses if required and make any other final adjustments needed.
9. Ensure the work area is left in a clean and tidy condition for the next trade.
Personal Protective Equipment
© M J Stevens Group
2 of 3
MJSM07
with the manufacturers instructions and training or a birdcage scaffold erected by a
specialist contractor. The safety physical precautions for work at height are the
responsibility of the principal contractor but operatives must ensure these things are in
place prior to starting work.
Placement of trusses
•
The Roof Trusses will be the responsibility of the principal contractor until they are placed
on the wall plate by mechanical means. The lifting operations used to achieve this are
not under the control of MJ Stevens. The principal contractor will arrange lifting
appliances, lifting plan, slingers, signallers etc. Using mechanical means in this way will
drastically reducing the manual handling operations required to complete the task.
•
When installing the Roof Trusses it is possible that the operatives are required to stand
on the truss edge or at the wall plate position, this may cause the operative to be above
the level of the edge protection on the scaffold. It may therefore be necessary for
additional guard rails to be constructed to protect the operative against the risks to falls.
If this is the case a competent scaffolder is to make the alterations (arranged by the
principal contractor).
•
All operatives will be trained in the installation of Roof Trusses and hold CSCS cards
•
The removed rubbish / debris is to be deposited in the waste skips / area provided by the
Principle Contractor no throwing or dropping of materials or waste from height is
permitted.
•
The Principal contractor is to make arrangements for materials and tools to be delivered
to the scaffold via a loading bay, hoist or similar Do Not carry any tools or materials up or
down ladders.
•
If there is any doubt over safety precautions at the location or if weather conditions are
safe to continue the supervisor is to be contacted immediately.
The truss roof will be installed in the following sequence:
1. Before you start work ensure: fall protection is in place, scaffold is erected to the correct
height, access to and from the work area is safe, all PPE and equipment required is on
site and in good condition, the method of work is understood, you have been inducted
and you are aware of the site procedures for fire etc and the right personnel are on site to
complete the work safely
2. When on the scaffold stand well clear while the trusses are guided into position and do
not attempt to lift them into place manually.
3. The first truss will be lifted into place, aligned and then fixed using battens to the scaffold
structure
4. With two operatives one on each side of the roof, working together and starting at one
side, walk the trusses into the correct position for fixing one at a time and secured to the
previous one ensuring the structure remains solid at all times. Fix using a nail gun (if you
have been trained to use one) or a hammer & nails.
5. Wind bracing is to be installed as the roof progresses.
6. When it is time to access the inside of the truss structure, ensure a good platform is
placed on the trusses to provide a good footing DO NOT walk on the trusses themselves.
7. When all the trusses are in place the battens holding the end trusses are then to be
removed.
8. Trim off the trusses if required and make any other final adjustments needed.
9. Ensure the work area is left in a clean and tidy condition for the next trade.
Personal Protective Equipment
© M J Stevens Group
2 of 3
MJSM07
Every
Every sself-employed
elf-employed per
person
son sshall
hall ens
ensure
ure tthat
hat any per
personal
sonal pr
protective
otective equi
equipment
pment pr
provided
ovided tto
o
ffficient sstate,
tate, in e
ffficient
hi
him
m iiss m
maintained
aintained ((including
including rreplaced
eplaced or ccleaned
leaned as appr
appropriate)
opriate) in a e
efficient
efficient
rotective Eq
u ip m e n t a
wo
working
r k in g o
order
rd e r a
and
nd iin
ng
good
ood rrepair
epair - ((Extract
Extract ffrom
rom tthe
he P
Personal
e rs o n a l P
Protective
Equipment
att W
Work
o rk
Re
Regulations).
gulations).
•
•
•
Every operative
operative is
is to
to ensure
ensure that
that tthey
hey h
ave rreceived
eceived adequate
adequate ttraining
r a i n in g w
ith rregards
egards tto
o tthe
he
Every
have
with
use of any par
ticular iitem
tem of P
ersonal P
rotective E
quipment.
use
particular
Personal
Protective
Equipment.
he
Self e
m p lo y e d p
e rs o n s a
re tto
o e
nsure tthey
hey p
u rc h a s e a
nd m
aintain PPE iin
n lline
in e w
ith tthe
Self
employed
persons
are
ensure
purchase
and
maintain
with
relevant ri
sk a
s s e s s m e n ts
relevant
risk
assessments
they look
look af
ftter a
nd use
use any PPE
PPE provided
provided for
fo
or them
them and
Employed per
sons ar
e tto
o ens
ure they
Employed
persons
are
ensure
after
and
any defects
defe
e c ts e
m m e d ia te ly .
report any
tc tto
o ttheir
heir supervisor
supervisor iimmediately.
report
etc
F a c ilitie s
Welfare Facilities
Welfare
oilet
ill u
se tthe
he w
elfa
are fa
a c ilitie s p
r o v id e d b
y tthe
he P
r in c ip le C
ontractor tto
o iinclude
nclude ttoilet
Op
e r a t iv e s w
Operatives
will
use
welfare
facilities
provided
by
Principle
Contractor
o
nd M
ess C
anteen, th
e ccanteen
anteen fa
cilities w
ill b
e u
sed fo
eal b
re a k s a
nd n
fa
cilities a
facilities
and
Mess
Canteen,
the
facilities
will
be
used
forr a
allll m
meal
breaks
and
no
br
eaks w
ea, on any ot
her par
rtt of tthe
he ssite
ite nor iin
n vvehicles
ehicles ((Private
Private or
ill be hel
d iin
n tthe
he w
ork ar
breaks
will
held
work
area,
other
part
company owned)
ow ned)
company
C o m p le tio n o
W o rk s
On Completion
off Works
Al
o rk a
re a s a
re tto
n a cclean
lean ccondition
ondition and al
pects of ssafety
ith rregards
egards tto
o tthe
he
o be lleft
eftt iin
afe
ety w
Alll w
work
areas
are
alll as
aspects
with
immediate w
visual inspection
inspection b
y tthe
he o
perative to
o rk a
re a a
nd conduct
conduct a visual
to ensure
ensure tthat
hat tthe
he e
dge
immediate
work
area
and
by
operative
edge
pr
otection iis
here iis
s no rrisk
isk tto
o iinjury
njury tto
o tthemselves
hemselves or ot
s iin
n pl
ace and tthat
hat tthere
hers a
direct
protection
place
others
ass a direct
re
s u lt o
fa
all from
from that
that area.
area.
result
off a fall
En
sure all
al l o
th e r m
a te r ia l w
hich is u
sed ffor
or yyour
our w
ork is sstored
tored iin
n a ssafe
a fe a
nd p
ro p e r m
anner
Ensure
other
material
which
used
work
and
proper
manner
bef
ore depar
ting ffrom
rom tthe
he pr
operty yyou
ou ar
ew
orking iin.
n.
before
departing
property
are
working
Re
porrtt tto
o tthe
he S
ite M
anagem ent T
ea m o
n ccompletion
o m p le tio n o
he wo
rk s a
nd iiff rrequired
e q u ir e d b
y tthe
he ssite
ite
Report
Site
Management
Team
on
off tthe
works
and
by
ut b
efo
ore lleaving
ru
les ssign
ig n o
e a v in g
rules
out
before
NAME
NA
ME
DATE
DA
TE
Andy
Andy White
White
01/11/2009
01/11
/2009
RE
REVIEW
VIEW DA
DATE
TE
01/04/2015
SI
SIGNATURE
GNATURE
MBA
MBA Safety
Safety & Training
Training
Ltd
Lt
d
JO
JOBTITLE
B T IT L E
He
Health
a lt h a
and
nd s
safety
afety Co
Consultant
n s u lta n t
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
© M J Stevens
Stevens Group
Group
3 of 3
MJSM07
MJSM07
M0
Every
Every sself-employed
elf-employed per
person
son sshall
hall ens
ensure
ure tthat
hat any per
personal
sonal pr
protective
otective equi
equipment
pment pr
provided
ovided tto
o
ffficient sstate,
tate, in e
ffficient
hi
him
m iiss m
maintained
aintained ((including
including rreplaced
eplaced or ccleaned
leaned as appr
appropriate)
opriate) in a e
efficient
efficient
rotective Eq
u ip m e n t a
wo
working
r k in g o
order
rd e r a
and
nd iin
ng
good
ood rrepair
epair - ((Extract
Extract ffrom
rom tthe
he P
Personal
e rs o n a l P
Protective
Equipment
att W
Work
o rk
Re
Regulations).
gulations).
•
•
•
Every operative
operative is
is to
to ensure
ensure that
that tthey
hey h
ave rreceived
eceived adequate
adequate ttraining
r a i n in g w
ith rregards
egards tto
o tthe
he
Every
have
with
use of any par
ticular iitem
tem of P
ersonal P
rotective E
quipment.
use
particular
Personal
Protective
Equipment.
he
Self e
m p lo y e d p
e rs o n s a
re tto
o e
nsure tthey
hey p
u rc h a s e a
nd m
aintain PPE iin
n lline
in e w
ith tthe
Self
employed
persons
are
ensure
purchase
and
maintain
with
relevant ri
sk a
s s e s s m e n ts
relevant
risk
assessments
hey llook
ook af
ftter a
nd us
e any P
PE pr
ovided fo
or tthem
hem and
Employed per
sons ar
e tto
o ens
ure tthey
Employed
persons
are
ensure
after
and
use
PPE
provided
for
ny d
efe
e c ts e
upervisor iimmediately.
m m e d ia te ly .
report a
tc tto
o ttheir
heir ssupervisor
report
any
defects
etc
F a c ilitie s
Welfare Facilities
Welfare
oilet
ill u
se tthe
he w
elfa
are fa
a c ilitie s p
r o v id e d b
y tthe
he P
r in c ip le C
ontractor tto
o iinclude
nclude ttoilet
Op
e r a t iv e s w
Operatives
will
use
welfare
facilities
provided
by
Principle
Contractor
o
nd M
ess C
anteen, th
e ccanteen
anteen fa
cilities w
ill b
e u
sed fo
eal b
re a k s a
nd n
fa
cilities a
facilities
and
Mess
Canteen,
the
facilities
will
be
used
forr a
allll m
meal
breaks
and
no
br
eaks w
ea, on any ot
her par
rtt of tthe
he ssite
ite nor iin
n vvehicles
ehicles ((Private
Private or
ill be hel
d iin
n tthe
he w
ork ar
breaks
will
held
work
area,
other
part
company owned)
ow ned)
company
C o m p le tio n o
W o rk s
On Completion
off Works
Al
o rk a
re a s a
re tto
n a cclean
lean ccondition
ondition and al
pects of ssafety
ith rregards
egards tto
o tthe
he
o be lleft
eftt iin
afe
ety w
Alll w
work
areas
are
alll as
aspects
with
immediate w
visual inspection
inspection b
y tthe
he o
perative to
o rk a
re a a
nd conduct
conduct a visual
to ensure
ensure tthat
hat tthe
he e
dge
immediate
work
area
and
by
operative
edge
pr
otection iis
here iis
s no rrisk
isk tto
o iinjury
njury tto
o tthemselves
hemselves or ot
s iin
n pl
ace and tthat
hat tthere
hers a
direct
protection
place
others
ass a direct
re
s u lt o
fa
all from
from that
that area.
area.
result
off a fall
En
sure all
al l o
th e r m
a te r ia l w
hich is u
sed ffor
or yyour
our w
ork is sstored
tored iin
n a ssafe
a fe a
nd p
ro p e r m
anner
Ensure
other
material
which
used
work
and
proper
manner
bef
ore depar
ting ffrom
rom tthe
he pr
operty yyou
ou ar
ew
orking iin.
n.
before
departing
property
are
working
Re
porrtt tto
o tthe
he S
ite M
anagem ent T
ea m o
n ccompletion
o m p le tio n o
he wo
rk s a
nd iiff rrequired
e q u ir e d b
y tthe
he ssite
ite
Report
Site
Management
Team
on
off tthe
works
and
by
ut b
efo
ore lleaving
ru
les ssign
ig n o
e a v in g
rules
out
before
NAME
NA
ME
DATE
DA
TE
Andy
Andy White
White
01/11/2009
01/11
/2009
RE
REVIEW
VIEW DA
DATE
TE
01/
01/11/2011
11/2011
SI
SIGNATURE
GNATURE
MB
MBA
AS
Safety
afety & Training
Training
Ltd
Lt
d
JO
JOBTITLE
B T IT L E
He
Health
a lt h a
and
nd s
safety
afety Co
Consultant
n s u lta n t
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
© M J Stevens
Stevens Group
Group
3 of 3
MJSM07
MJSM07
M0
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference
Number:
Area Assessed:
Site locations: Operatives Handbook
MJSM08
Description:
Floor screeding using a pump
Operatives Involved:
Site based operatives
WORK ACTIVITY:
Floor screeding operations carried out using a pump
To be read in conjunction with the company’s Generic Risk
Assessments
MJSRa01
MJSRa02
MJSRa03
MJSRa04
MJSRa09
MJSRa11
MJSRa12
Working at Height
Manual Handling
Noise
Vibration
Electrocution
Materials Delivery
Materials / Objects falling from height
The Work Area (General Precautions)
•
The work area is to be free of other trades, visitors and site staff.
•
All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing.
•
Good access is to be provided by the principal contractor with full height access through
scaffold etc.
•
If other trades are working within the property they must be advised of the work activities
that are about to commence.
© M J Stevens Group
1 of 3
MJSM08
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference
Number:
Area Assessed:
Site locations: Operatives Handbook
MJSM08
Description:
Floor screeding using a pump
Operatives Involved:
Site based operatives
WORK ACTIVITY:
Floor screeding operations carried out using a pump
To be read in conjunction with the company’s Generic Risk
Assessments
MJSRa01
MJSRa02
MJSRa03
MJSRa04
MJSRa09
MJSRa11
MJSRa12
Working at Height
Manual Handling
Noise
Vibration
Electrocution
Materials Delivery
Materials / Objects falling from height
The Work Area (General Precautions)
•
The work area is to be free of other trades, visitors and site staff.
•
All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing.
•
Good access is to be provided by the principal contractor with full height access through
scaffold etc.
•
If other trades are working within the property they must be advised of the work activities
that are about to commence.
© M J Stevens Group
1 of 3
MJSM08
Method of work & use of screed pump
•
Operatives using this equipment are to be trained in its use and competent (training will
be carried out in house) operatives who are new to the equipment are to be supervised at
all times.
•
The equipment including: hoses, outlet nozzle, mixer, generator, guards and all other
associated paraphernalia is to be inspected by the foremen prior to each shift.
•
Hoses are not to be separated until the pressure has been removed from the system by
reversing the pump.
•
All moving parts are to be guarded with movable guards fitted with interlock switches this
will include guards to the engine compartment, mixing chamber and the pump chamber.
•
The laying/application and machine loading operations are to be shared by the gang to
reduce the risk of manual handling and repetitive strain injury.
•
The operatives must also have read and understood the COSHH assessment for the
product being pumped.
•
Materials are to be loaded into a sensible location near to the mixer by the principal
contractor. This will avoid excessive manual handling.
•
Safety glasses are to be worn by the operatives carrying out the application operation
and any other operatives in the immediate area.
•
Electrical safety to be tested by a competent person annually.
•
All controls to be kept clean and clearly labelled to prevent unintended start-up
•
All screed pumps are to be fitted with a proprietary emergency stop.
•
All hoses are to be laid in positions where tripping is unlikely e.g. not across the top of
staircases etc.
•
Protective clothing and kneeling pads are to be worn by operatives during the application
process to avoid cement burns and knee problems.
•
Warning signs are to be placed on the screed pump to ensure no unsafe practices are
adopted.
Personal Protective Equipment
Every self-employed person shall ensure that any personal protective equipment provided to
him is maintained (including replaced or cleaned as appropriate) in a efficient state, in
efficient working order and in good repair - (Extract from the Personal Protective Equipment
at Work Regulations).
•
•
•
Every operative is to ensure that they have received adequate training with regards to the
use of any particular item of Personal Protective Equipment.
Self employed persons are to ensure they purchase and maintain PPE in line with the
relevant risk assessments
Employed persons are to ensure they look after and use any PPE provided for them and
report any defects etc to their supervisor immediately.
Welfare Facilities
Operatives will use the welfare facilities provided by the Principle Contractor to include toilet
facilities and Mess Canteen, the canteen facilities will be used for all meal breaks and no
breaks will be held in the work area, on any other part of the site nor in vehicles (Private or
company owned)
On Completion of Works
© M J Stevens Group
2 of 3
MJSM08
Method of work & use of screed pump
•
Operatives using this equipment are to be trained in its use and competent (training will
be carried out in house) operatives who are new to the equipment are to be supervised at
all times.
•
The equipment including: hoses, outlet nozzle, mixer, generator, guards and all other
associated paraphernalia is to be inspected by the foremen prior to each shift.
•
Hoses are not to be separated until the pressure has been removed from the system by
reversing the pump.
•
All moving parts are to be guarded with movable guards fitted with interlock switches this
will include guards to the engine compartment, mixing chamber and the pump chamber.
•
The laying/application and machine loading operations are to be shared by the gang to
reduce the risk of manual handling and repetitive strain injury.
•
The operatives must also have read and understood the COSHH assessment for the
product being pumped.
•
Materials are to be loaded into a sensible location near to the mixer by the principal
contractor. This will avoid excessive manual handling.
•
Safety glasses are to be worn by the operatives carrying out the application operation
and any other operatives in the immediate area.
•
Electrical safety to be tested by a competent person annually.
•
All controls to be kept clean and clearly labelled to prevent unintended start-up
•
All screed pumps are to be fitted with a proprietary emergency stop.
•
All hoses are to be laid in positions where tripping is unlikely e.g. not across the top of
staircases etc.
•
Protective clothing and kneeling pads are to be worn by operatives during the application
process to avoid cement burns and knee problems.
•
Warning signs are to be placed on the screed pump to ensure no unsafe practices are
adopted.
Personal Protective Equipment
Every self-employed person shall ensure that any personal protective equipment provided to
him is maintained (including replaced or cleaned as appropriate) in a efficient state, in
efficient working order and in good repair - (Extract from the Personal Protective Equipment
at Work Regulations).
•
•
•
Every operative is to ensure that they have received adequate training with regards to the
use of any particular item of Personal Protective Equipment.
Self employed persons are to ensure they purchase and maintain PPE in line with the
relevant risk assessments
Employed persons are to ensure they look after and use any PPE provided for them and
report any defects etc to their supervisor immediately.
Welfare Facilities
Operatives will use the welfare facilities provided by the Principle Contractor to include toilet
facilities and Mess Canteen, the canteen facilities will be used for all meal breaks and no
breaks will be held in the work area, on any other part of the site nor in vehicles (Private or
company owned)
On Completion of Works
© M J Stevens Group
2 of 3
MJSM08
Al
o rk a
re a s a
re tto
ob
e left
left in
in a clean
clean ccondition
ondition a
nd a
spects o
afety w
ith rregards
egards to th
e
Alll w
work
areas
are
be
and
allll a
aspects
off ssafety
with
the
im
mediate w
o rk a
re a a
nd conduct
conduct a visual
visual inspection
inspection b
y tthe
he o
perative to
to ensure
ensure tthat
hat tthe
he
immediate
work
area
and
by
operative
edge pr
otection iis
s iin
n pl
ace and tthat
hat tthere
here iis
s no rrisk
isk tto
o iinjury
njury tto
o tthemselves
hemselves or ot
hers as a
protection
place
others
di
rect rresult
esult of a ffall
all ffrom
rom that
that area.
area.
direct
En
s u re a
th e r m
a te r ia l w
hich is u
sed fo
our w
ork is sstored
tored iin
n a ssafe
afe a
nd p
ro p e r m
anner
Ensure
allll o
other
material
which
used
forr yyour
work
and
proper
manner
bef
ore depar
ting ffrom
rom tthe
he pr
operty yyou
ou ar
ew
orking iin.
n.
before
departing
property
are
working
o tthe
he S
ite M
anagem ent T
ea m o
n ccompletion
o m p le tio n o
he wo
rks and
and if
if required
required by
by tthe
he si
te
Re
port tto
Report
Site
Management
Team
on
off tthe
works
site
e a v in g .
ru
les ssign
ig n o
ut b
efo
ore lleaving.
rules
out
before
NA
ME
NAME
DATE
DATE
Andy
White
An
dy W
h ite
01/11/2009
01/11
/2009
RE
REVIEW
VIEW DA
DATE
TE
01/04/2015
SI
SIGNATURE
GNATURE
MBA Safety
Safety & Training
T ra in in g
MBA
Lt
d
Ltd
JO
JOBTITLE
B T IT L E
He
Health
a lt h a
and
nd s
safety
afety Co
Consultant
n s u lta n t
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
668527
© M J Stevens
Stevens Group
Group
3 of 3
MJSM08
MJSM08
Al
o rk a
re a s a
re tto
ob
e left
left in
in a clean
clean ccondition
ondition a
nd a
spects o
afety w
ith rregards
egards to th
e
Alll w
work
areas
are
be
and
allll a
aspects
off ssafety
with
the
im
mediate w
o rk a
re a a
nd conduct
conduct a visual
visual inspection
inspection b
y tthe
he o
perative to
to ensure
ensure tthat
hat tthe
he
immediate
work
area
and
by
operative
edge pr
otection iis
s iin
n pl
ace and tthat
hat tthere
here iis
s no rrisk
isk tto
o iinjury
njury tto
o tthemselves
hemselves or ot
hers as a
protection
place
others
di
rect rresult
esult of a ffall
all ffrom
rom that
that area.
area.
direct
En
s u re a
th e r m
a te r ia l w
hich is u
sed fo
our w
ork is sstored
tored iin
n a ssafe
afe a
nd p
ro p e r m
anner
Ensure
allll o
other
material
which
used
forr yyour
work
and
proper
manner
bef
ore depar
ting ffrom
rom tthe
he pr
operty yyou
ou ar
ew
orking iin.
n.
before
departing
property
are
working
o tthe
he S
ite M
anagem ent T
ea m o
n ccompletion
o m p le tio n o
he wo
rks and
and if
if required
required by
by tthe
he si
te
Re
port tto
Report
Site
Management
Team
on
off tthe
works
site
e a v in g .
ru
les ssign
ig n o
ut b
efo
ore lleaving.
rules
out
before
NA
ME
NAME
DATE
DATE
Andy
White
An
dy W
h ite
01/11/2009
01/11
/2009
RE
REVIEW
VIEW DA
DATE
TE
01/11/2011
01/11
/2011
SI
SIGNATURE
GNATURE
MBA
MBA Safety
Safety & Training
T ra in in g
Ltd
Lt
d
JO
JOBTITLE
B T IT L E
He
Health
a lt h a
and
nd s
safety
afety Co
Consultant
n s u lta n t
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
668527
© M J Stevens
Stevens Group
Group
3 of 3
MJSM08
MJSM08
M J Stevens Ltd
M J Stevens Contracting Division
Risk Assessment
Hazard Reference
Number:
Area Assessed:
Site locations: Operatives Handbook
MJSRa09
Hazard:
Electrocution
Reason for Assessment:
Initial assessment
Risk:
Faulty Electricity Equipment / Cables
Operatives Involved:
All staff, visitors and other contractors
Hazard Description:
Electrocution
Likelihood
Severity
Frequency
7
10
5
Risk = Likelihood x Severity x Frequency
Risk score:
350
Mitigated Risk score:
100
Electric Shock
This hazard and has been the cause of many fatalities. A number of factors affect the severity
of electric shock. The actual harm depends on the current flowing through the body and
particularly the heart. This is affected, however, by voltage, the resistance of the internal
organs (dry skin – high: organs - low) the type of current (A.C or D.C) the current pathway
through the body, the duration of the current flow and the surface area of contact. The
concept of ‘let-go’ currents’ is important here. Let-go currents is defined as ‘the maximum
D.C. current a person can tolerate when holding an electrode and still let go using muscles
stimulated by the shock’. Average let-go currents are 16.0mA for men and 10.5mA for
women. A current of only 10mA passing through the heart can cause a serious effect on it
depending on the duration of the flow. At higher currents, ventricular fibrillation (heart ‘flutter’)
can set in, until at 100mA cessation of the heart beat altogether is the likely result.
Electrical safety
•
•
•
•
•
•
•
•
•
Ensure 110volt Equipment is used on site locations.
Operatives to inspect equipment on a daily basis.
DO NOT run electrical cables outside if raining or in wet conditions.
DO NOT run electrical cables amongst a scaffold structure, if cables are damaged by the
metal structure, then the whole of the scaffold could become LIVE!!
DO NOT run electrical cables in areas where there is the likelihood of the cable being
damaged.
All operatives must be trained in the safe use of all electrical equipment.
Never allow unauthorised persons & children to interfere with electrical cables.
Ensure adequate emergency procedures are in place in event of an emergency.
Trained First Aid person to be at site locations.
© M J Stevens Group
1 of 2
MJSRa09
M J Stevens Ltd
M J Stevens Contracting Division
Risk Assessment
Hazard Reference
Number:
Area Assessed:
Site locations: Operatives Handbook
Hazard:
Electrocution
Reason for Assessment:
Initial assessment
Risk:
Faulty Electricity Equipment / Cables
Operatives Involved:
All staff, visitors and other contractors
Hazard Description:
MJSRa09
Electrocution
Likelihood
Severity
Frequency
7
10
5
Risk = Likelihood x Severity x Frequency
Risk score:
350
Mitigated Risk score:
100
Electric Shock
This hazard and has been the cause of many fatalities. A number of factors affect the severity
of electric shock. The actual harm depends on the current flowing through the body and
particularly the heart. This is affected, however, by voltage, the resistance of the internal
organs (dry skin – high: organs - low) the type of current (A.C or D.C) the current pathway
through the body, the duration of the current flow and the surface area of contact. The
concept of ‘let-go’ currents’ is important here. Let-go currents is defined as ‘the maximum
D.C. current a person can tolerate when holding an electrode and still let go using muscles
stimulated by the shock’. Average let-go currents are 16.0mA for men and 10.5mA for
women. A current of only 10mA passing through the heart can cause a serious effect on it
depending on the duration of the flow. At higher currents, ventricular fibrillation (heart ‘flutter’)
can set in, until at 100mA cessation of the heart beat altogether is the likely result.
Electrical safety
•
•
•
•
•
•
•
•
•
Ensure 110volt Equipment is used on site locations.
Operatives to inspect equipment on a daily basis.
DO NOT run electrical cables outside if raining or in wet conditions.
DO NOT run electrical cables amongst a scaffold structure, if cables are damaged by the
metal structure, then the whole of the scaffold could become LIVE!!
DO NOT run electrical cables in areas where there is the likelihood of the cable being
damaged.
All operatives must be trained in the safe use of all electrical equipment.
Never allow unauthorised persons & children to interfere with electrical cables.
Ensure adequate emergency procedures are in place in event of an emergency.
Trained First Aid person to be at site locations.
© M J Stevens Group
1 of 2
MJSRa09
•
•
•
•
•
Office
Offfice e
equipment
quipment tto
oh
have
ave P
Portable
o r ta b le A
Appliance
p p lia n c e T
Testing
esting ccarried
a r r ie d o
out
ut o
on
na
an
na
annual
nnual b
basis.
a s is .
Site b
Site
based
ased equipment
equipment to
to have
have Portable
Portable Appliance
Appliance Testing
Testing carried
carried out
out on
on a three
three monthly
m o n th ly
basis.
basis.
q u ip m e n t.
PAT ttags
ags tto
ob
be
e present
present on
on all
all electrical
el e c t r i c a l e
equipment.
ob
e rremoved
emoved ffrom
rom sservice
ervice sstraight
tr a ig h t a
w ay.
All d
All
damaged
am aged e
equipment
q u ip m e n t a
and
nd lleads
eads tto
be
away.
Only qualified
q u a lifie d p
e rs o n n e l a
re tto
o ccarry
a rry o
ut m
aintenance on el
ectrical equipment
equipment and leads.
leads.
Only
personnel
are
out
maintenance
electrical
Controls
Further Controls
Further
r a in in g w
ill b
eg
iven tthrough
h r o u gh o
ur ccontinued
o n tin u e d p
ro g ra m m e o
r a in in g .
Furrtther ttraining
n ssafety
afe
ety ttraining.
Further
will
be
given
our
programme
on
NAME
NA
ME
Andy
White
An
dy W
h ite
DATE
01/11/2009
DA
TE 01/11
/2009
RE
REVIEW
VIEW DA
DATE
TE
01/04/2015
SI
SIGNATURE
GNATURE
MB
MBA
AS
Safety
a f et y & T
Training
r a in in g L
Ltd
td
JO
JOBTITLE
B T IT L E
He
Health
a lt h a
and
nd s
safety
afety Co
Consultant
n s u lta n t
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
© M J Stevens
Stevens Group
Group
•
•
•
•
•
2 of 2
MJSRa09
MJSRa09
Office
Offfice e
equipment
quipment tto
oh
have
ave P
Portable
o r ta b le A
Appliance
p p lia n c e T
Testing
esting ccarried
a r r ie d o
out
ut o
on
na
an
na
annual
nnual b
basis.
a s is .
Site b
Site
based
ased equipment
equipment to
to have
have Portable
Portable Appliance
Appliance Testing
Testing carried
carried out
out on
on a three
three monthly
m o n th ly
basis.
basis.
q u ip m e n t.
PAT ttags
ags tto
ob
be
ep
present
resent on
on all
all electrical
el e c t r i c a l e
equipment.
ob
e rremoved
emoved ffrom
rom sservice
ervice sstraight
tr a ig h t a
w ay.
All d
All
damaged
am aged e
equipment
q u ip m e n t a
and
nd lleads
eads tto
be
away.
On
ly q
u a lifie d p
e rs o n n e l a
re tto
o ccarry
a rry o
ut m
aintenance on el
ectrical equi
pment and lleads.
eads.
Only
qualified
personnel
are
out
maintenance
electrical
equipment
Controls
Fur
ther Controls
Further
r a in in g w
ill b
eg
iven tthrough
h r o u gh o
ur ccontinued
o n tin u e d p
ro g ra m m e o
r a in in g .
Fu
rrtther ttraining
n ssafety
afe
ety ttraining.
Further
will
be
given
our
programme
on
NAME
NA
ME
Andy
White
An
dy W
h ite
DATE
01/11/2009
DA
TE 01/11
/2009
RE
REVIEW
VIEW DA
DATE
TE
01/11/2011
01/11/2011
SI
SIGNATURE
GNATURE
MB
MBA
A Safety
S a f et y & T
Training
r a in in g L
Ltd
td
JO
JOBTITLE
B T IT L E
He
Health
a lt h a
and
nd s
safety
afety Co
Consultant
n s u lta n t
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
© M J Stevens
Stevens Group
Group
2 of 2
MJSRa09
MJSRa09
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference
Number:
Area Assessed:
Site locations: Operatives Handbook
MJSM10
Description:
Traditionally applied external render
Operatives Identified:
Site based operatives
WORK ACTIVITY:
Traditionally applied external renders
To be read in conjunction with the company’s Generic Risk
Assessments
MJSRa01
MJSRa02
MJSRa03
MJSRa10
MJSRa11
MJSRa12
MJSRa14
Working at Height
Manual Handling
Noise
Breathing in dust particles
Materials Delivery
Falling Objects
Ladders and step ladders
The Work Area & Work at Height
•
The work area (the render adapted scaffolding), the area beneath and around the plot are
to be free of other trades, visitors and site staff.
•
All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing in particular the scaffold structure.
•
Site operatives are to ensure that the Principle Contractor has inspected the scaffold
structure in line with the requirements set out in the Work at Height Regulations 2005.
The basics are to be checked by the operative prior to starting work i.e. that proper
access is available, handrails are in place, no missing boards etc.
•
All scaffolds are to be render adapted to allow for application of render from a stable
working platform, no standing on trestle platforms or stepladders etc placed on the
scaffold to gain extra height is permitted.
•
Scaffolds are to be adapted by specialist contractor prior to work commencing in order to
allow for access to the wall. This means a gap will be present on the inside of the
scaffold. Operatives are to check that this gap is not excessive prior to starting work.
© M J Stevens Group
1 of 2
MJSM10
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference
Number:
Area Assessed:
Site locations: Operatives Handbook
MJSM10
Description:
Traditionally applied external render
Operatives Identified:
Site based operatives
WORK ACTIVITY:
Traditionally applied external renders
To be read in conjunction with the company’s Generic Risk
Assessments
MJSRa01
MJSRa02
MJSRa03
MJSRa10
MJSRa11
MJSRa12
MJSRa14
Working at Height
Manual Handling
Noise
Breathing in dust particles
Materials Delivery
Falling Objects
Ladders and step ladders
The Work Area & Work at Height
•
The work area (the render adapted scaffolding), the area beneath and around the plot are
to be free of other trades, visitors and site staff.
•
All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing in particular the scaffold structure.
•
Site operatives are to ensure that the Principle Contractor has inspected the scaffold
structure in line with the requirements set out in the Work at Height Regulations 2005.
The basics are to be checked by the operative prior to starting work i.e. that proper
access is available, handrails are in place, no missing boards etc.
•
All scaffolds are to be render adapted to allow for application of render from a stable
working platform, no standing on trestle platforms or stepladders etc placed on the
scaffold to gain extra height is permitted.
•
Scaffolds are to be adapted by specialist contractor prior to work commencing in order to
allow for access to the wall. This means a gap will be present on the inside of the
scaffold. Operatives are to check that this gap is not excessive prior to starting work.
© M J Stevens Group
1 of 2
MJSM10
•
All
All m
materials
a te r ia ls a
are
re tto
o b
be
e llifted
ifftted tto
o tthe
he w
work
o rk a
area
re a b
by
y fforklift
orkliftt vvia
ia a lloading
o a d in g b
bay
ay u
under
nder n
no
o
circumstances
circumstances are
are MJ
MJ Stevens
Stevens oper
operatives
atives tto
o rremove
emove handr
handrails
ails et
etc
c ffor
or tthe
he lloading
oading of bi
bins
ns
et
etc.
c.
•
If other
other tr
ades a
re w
o r k in g w
ithin th
ep
roperty th
ey m
ust b
ea
dvised of the
th e w
o rk a
c tiv itie s
trades
are
working
within
the
property
they
must
be
advised
work
activities
th
at a
re a
bout to ccommence.
om m ence.
that
are
about
otective Eq
u ip m e n t
Pe
rsonal Pr
Personal
Protective
Equipment
Every sself-employed
ure tthat
hat any per
sonal pr
o
elf-employed per
son sshall
hall ens
otective equi
pment pr
ovided tto
Every
person
ensure
personal
protective
equipment
provided
hi
m is
is m
leaned as appr
fficient sstate,
aintained ((including
including rreplaced
eplaced or ccleaned
opriate) in a e
tate, in
him
maintained
appropriate)
efficient
eff
ficient w
repair - (Extract
(Extract from
from the
the Personal
Personal Protective
Protective Eq
u ip m e n t
orking or
der and in
in good
good repair
efficient
working
order
Equipment
at W
ork Regulations).
Regulations).
Work
•
•
•
Every operative
operative is
is to e
nsure that
that th
ey h
ave rreceived
e c e iv e d a
dequate tr
a in in g w
ith rregards
egards to th
e
Every
ensure
they
have
adequate
training
with
the
use of any par
ticular iitem
tem of P
ersonal P
rotective E
quipment.
use
particular
Personal
Protective
Equipment.
Self e
mployed per
sons ar
e tto
o ens
ure tthey
hey pur
chase and m
aintain P
PE iin
n lline
ine w
ith tthe
he
Self
employed
persons
are
ensure
purchase
maintain
PPE
with
relevant ri
sk a
s s e s s m e n ts
relevant
risk
assessments
hey llook
ook a
fftter a
nd use
use any P
Employed p
e rs o n s a
re tto
oe
nsure tthey
PE pr
ovided ffor
or tthem
hem and
Employed
persons
are
ensure
after
and
PPE
provided
ny d
efe
e c ts e
upervisor iimmediately.
m m e d ia te ly .
report a
tc tto
o ttheir
heir ssupervisor
report
any
defects
etc
Facilities
Welfare Facilities
Welfare
Operatives w
ill u
se tthe
he w
elfa
are fa
a c ilitie s p
r o v id e d b
y tthe
he P
r in c ip le C
Operatives
will
use
welfare
facilities
provided
by
Principle
Contractor
ontractor tto
o iinclude
nclude ttoilet
o ile t
fa
cilities a
nd M
ess C
anteen, th
e ccanteen
anteen fa
cilities w
ill b
e u
sed fo
eal b
re a k s a
nd n
o
facilities
and
Mess
Canteen,
the
facilities
will
be
used
forr a
allll m
meal
breaks
and
no
ea, on any ot
her par
the ssite
br
eaks w
ill be hel
d iin
n tthe
he w
ork ar
ite n
or iin
n vvehicles
ehicles ((Private
Private o
breaks
will
held
work
area,
other
partt o
off the
nor
orr
company owned)
ow ned)
company
On Completion
Completion of
of Works
W o rk s
o n d it i o n a
nd a
s p e ct s o
Alll w
work
areas
are
be
n a cclean
lean ccondition
and
allll a
aspects
off ssafety
with
re a s a
re tto
ob
e lleft
efftt iin
Al
o rk a
a fe ty w
ith rregards
egards tto
o tthe
he
visual inspection
inspection b
y tthe
he operative
immediate
work
area
and
by
ensure
o rk a
re a a
nd conduct
conduct a visual
im
mediate w
operative tto
o e
nsure tthat
hat tthe
he
hat tthere
here iis
s no rrisk
isk tto
o iinjury
njury tto
protection
place
others
otection iis
s iin
n pl
ace and tthat
edge pr
o tthemselves
hemselves or ot
hers as a
direct
all ffrom
rom that
that area.
area.
di
rect result
result of a ffall
En
sure all
al l o
th e r m
a te r ia l w
hich is u
sed ffor
or yyour
our w
ork is sstored
tored iin
n a ssafe
afe
ea
nd p
ro p e r m
anner
Ensure
other
material
which
used
work
and
proper
manner
bef
ore departing
departing ffrom
rom the
the property
property yyou
ou ar
ew
orking iin.
n.
before
are
working
o tthe
he S
ite M
anagem ent T
eam o
n ccompletion
o m p le tio n o
he wo
rk s a
nd iiff rrequired
e q u ir e d b
y tthe
he ssite
ite
Re
port tto
Report
Site
Management
Team
on
off tthe
works
and
by
ut before
befo
ore lleaving
e a v in g
ru
les ssign
ig n o
rules
out
NA
ME
NAME
An
dy W
h ite
Andy
White
DA
TE 01/11
/2009
DATE
01/11/2009
RE
VIEW DA
TE
REVIEW
DATE
01/04/2015
SI
SIGNATURE
GNATURE
MB
MBA
A Safety
Safety & Training
Training Ltd
Ltd
JO
B T IT L E
JOBTITLE
He
a lt h a
nd s
afety Co
Health
and
safety
Consultant
n s u lta n t
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
© M J Stevens
Stevens Group
Group
2 of 2
MJSM10
MJSM10
M
•
All
All m
materials
a te r ia ls a
are
re tto
o b
be
e llifted
ifftted tto
o tthe
he w
work
o rk a
area
re a b
by
y fforklift
orkliftt vvia
ia a lloading
o a d in g b
bay
ay u
under
nder n
no
o
circumstances
circumstances are
are MJ
MJ Stevens
Stevens oper
operatives
atives tto
o rremove
emove handr
handrails
ails et
etc
c ffor
or tthe
he lloading
oading of bi
bins
ns
et
etc.
c.
•
If other
other tr
ades a
re w
o r k in g w
ithin th
ep
roperty th
ey m
ust b
ea
dvised of the
th e w
o rk a
c tiv itie s
trades
are
working
within
the
property
they
must
be
advised
work
activities
th
at a
re a
bout to ccommence.
om m ence.
that
are
about
otective Eq
u ip m e n t
Pe
rsonal Pr
Personal
Protective
Equipment
Every sself-employed
ure tthat
hat any per
sonal pr
o
elf-employed per
son sshall
hall ens
otective equi
pment pr
ovided tto
Every
person
ensure
personal
protective
equipment
provided
fficient sstate,
hi
m is
is m
leaned as appr
aintained ((including
including rreplaced
eplaced or ccleaned
opriate) in a e
tate, in
him
maintained
appropriate)
efficient
eff
ficient w
Protective Eq
u ip m e n t
repair - (Extract
(Extract from
from tthe
he Personal
Personal Protective
orking or
der and in
in good
good repair
efficient
working
order
Equipment
at W
ork Regulations).
Regulations).
Work
•
•
•
Every operative
operative is
is to e
nsure that
that th
ey h
ave rreceived
e c e iv e d a
dequate tr
a in in g w
ith rregards
egards to th
e
Every
ensure
they
have
adequate
training
with
the
use of any par
ticular iitem
tem of P
ersonal P
rotective E
quipment.
use
particular
Personal
Protective
Equipment.
Self e
mployed per
sons ar
e tto
o ens
ure tthey
hey pur
chase and m
aintain P
PE iin
n lline
ine w
ith tthe
he
Self
employed
persons
are
ensure
purchase
maintain
PPE
with
relevant ri
sk a
s s e s s m e n ts
relevant
risk
assessments
hey llook
ook a
fftter a
nd use
use any P
Employed p
e rs o n s a
re tto
oe
nsure tthey
PE pr
ovided ffor
or tthem
hem and
Employed
persons
are
ensure
after
and
PPE
provided
ny d
efe
e c ts e
upervisor iimmediately.
m m e d ia te ly .
report a
tc tto
o ttheir
heir ssupervisor
report
any
defects
etc
Facilities
Welfare Facilities
Welfare
Operatives w
ill u
se tthe
he w
elfa
are fa
a c ilitie s p
r o v id e d b
y tthe
he P
r in c ip le C
Operatives
will
use
welfare
facilities
provided
by
Principle
Contractor
ontractor tto
o iinclude
nclude ttoilet
o ile t
fa
cilities a
nd M
ess C
anteen, th
e ccanteen
anteen fa
cilities w
ill b
e u
sed fo
eal b
re a k s a
nd n
o
facilities
and
Mess
Canteen,
the
facilities
will
be
used
forr a
allll m
meal
breaks
and
no
ea, on any ot
her par
the ssite
br
eaks w
ill be hel
d iin
n tthe
he w
ork ar
ite n
or iin
n vvehicles
ehicles ((Private
Private o
breaks
will
held
work
area,
other
partt o
off the
nor
orr
company owned)
ow ned)
company
On Completion
Completion of
of Works
W o rk s
o n d it i o n a
nd a
s p e ct s o
Alll w
work
areas
are
be
n a cclean
lean ccondition
and
allll a
aspects
off ssafety
with
re a s a
re tto
ob
e lleft
efftt iin
Al
o rk a
a fe ty w
ith rregards
egards tto
o tthe
he
visual inspection
inspection b
y tthe
he operative
immediate
work
area
and
by
ensure
o rk a
re a a
nd conduct
conduct a visual
im
mediate w
operative tto
o e
nsure tthat
hat tthe
he
hat tthere
here iis
s no rrisk
isk tto
o iinjury
njury tto
protection
place
others
otection iis
s iin
n pl
ace and tthat
edge pr
o tthemselves
hemselves or ot
hers as a
direct
esult of a ffall
all ffrom
rom that
that area.
area.
di
rect rresult
En
sure all
al l o
th e r m
a te r ia l w
hich is u
sed ffor
or yyour
our w
ork is sstored
tored iin
n a ssafe
afe
ea
nd p
ro p e r m
anner
Ensure
other
material
which
used
work
and
proper
manner
bef
ore dep
arting from
from the
the property
property yyou
ou ar
ew
orking iin.
n.
before
departing
are
working
n ccompletion
o m p le tio n o
he wo
rk s a
nd iiff rrequired
e q u ir e d b
y tthe
he ssite
ite
Re
port tto
o tthe
he S
ite M
anagement Team
Te a m o
Report
Site
Management
on
off tthe
works
and
by
ut b
efo
ore lleaving
ru
les ssign
ig n o
e a v in g
rules
out
before
NA
ME
NAME
An
dy W
h ite
Andy
White
DA
TE 01/11
/2009
DATE
01/11/2009
RE
VIEW DA
TE
REVIEW
DATE
01/11/2011
01/11
/2011
SI
SIGNATURE
GNATURE
MB
MBA
A Safety
Safety & Training
Training Ltd
Ltd
JO
B T IT L E
JOBTITLE
He
a lt h a
nd s
afety Co
Health
and
safety
Consultant
n s u lta n t
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
© M J Stevens
Stevens Group
Group
2 of 2
MJSM10
MJSM10
M
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference
Number:
Area Assessed:
Site locations: Operatives Handbook
MJSM11
Description:
External render applied via spray
Operatives Identified:
Site based operatives
WORK ACTIVITY:
External renders applied via spray
To be read in conjunction with the company’s Generic Risk
Assessments
MJSRa01
MJSRa02
MJSRa03
MJSRa04
MJSRa09
MJSRa10
MJSRa11
MJSRa12
Working at Height
Manual Handling
Noise
Vibration
Electrocution
Breathing in dust particles
Materials Delivery
Materials / Objects falling from height
The Work Area & Work at Height
•
The work area (the render adapted scaffolding), the area beneath and around the plot are
to be free of other trades, visitors and site staff.
•
All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing in particular the scaffold structure.
•
Site operatives are to ensure that the Principle Contractor has inspected the scaffold
structure in line with the requirements set out in the Work at Height Regulations 2005.
The basics are to be checked by the operative prior to starting work i.e. that proper
access is available, handrails are in place, no missing boards etc.
•
All scaffolds are to be render adapted to allow for application of render from a stable
working platform, no standing on trestle platforms or stepladders etc placed on the
scaffold to gain extra height is permitted.
•
Scaffolds are to be adapted by specialist contractor prior to work commencing in order to
allow for access to the wall. This means a gap will be present on the inside of the
© M J Stevens Group
1 of 3
MJSM11
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference
Number:
Area Assessed:
Site locations: Operatives Handbook
MJSM11
Description:
External render applied via spray
Operatives Identified:
Site based operatives
WORK ACTIVITY:
External renders applied via spray
To be read in conjunction with the company’s Generic Risk
Assessments
MJSRa01
MJSRa02
MJSRa03
MJSRa04
MJSRa09
MJSRa10
MJSRa11
MJSRa12
Working at Height
Manual Handling
Noise
Vibration
Electrocution
Breathing in dust particles
Materials Delivery
Materials / Objects falling from height
The Work Area & Work at Height
•
The work area (the render adapted scaffolding), the area beneath and around the plot are
to be free of other trades, visitors and site staff.
•
All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing in particular the scaffold structure.
•
Site operatives are to ensure that the Principle Contractor has inspected the scaffold
structure in line with the requirements set out in the Work at Height Regulations 2005.
The basics are to be checked by the operative prior to starting work i.e. that proper
access is available, handrails are in place, no missing boards etc.
•
All scaffolds are to be render adapted to allow for application of render from a stable
working platform, no standing on trestle platforms or stepladders etc placed on the
scaffold to gain extra height is permitted.
•
Scaffolds are to be adapted by specialist contractor prior to work commencing in order to
allow for access to the wall. This means a gap will be present on the inside of the
© M J Stevens Group
1 of 3
MJSM11
•
•
scaffold. Operatives are to check that this gap is not excessive prior to starting work.
All materials are to be lifted to a suitable area near to the spraying machine by forklift
If other trades are working within/on the property they must be advised of the work
activities that are about to commence.
Method of work/use of the spraying machine
•
Operatives using this equipment are to be trained in its use and competent (training will
be carried out in house) operatives who are new to the equipment are to be supervised at
all times.
•
The equipment including: hoses, spry nozzle, mixer, generator, guards and all other
associated paraphernalia is to be inspected by the foremen prior to each shift.
•
Hoses are not to be separated until the pressure has been removed from the system by
reversing the pump.
•
All moving parts are to be guarded with movable guards fitted with interlock switches this
will include guards to the engine compartment, mixing chamber and the pump chamber.
•
The spraying and mixing operations are to be shared by the gang to reduce the risk of
manual handling and repetitive strain injury.
•
Bags of material are to weigh no more than 25kg
•
Dust masks are to be worn by the operative working at the machine and by any
operatives in the vicinity. The operatives must also have read and understood the
COSHH assessment for the product being sprayed.
•
Materials are to be loaded into a sensible location near to the mixer by the principal
contractor. This will avoid excessive manual handling.
•
Safety glasses are to be worn by the operative using the spray gun and any other
operatives in the immediate area.
•
Electrical safety to be tested by a competent person annually.
•
All controls to be kept clean and clearly labelled to prevent unintended start-up
•
All spraying machines are to be fitted with a proprietary emergency stop.
Personal Protective Equipment
Every self-employed person shall ensure that any personal protective equipment provided to
him is maintained (including replaced or cleaned as appropriate) in an efficient state, in
efficient working order and in good repair - (Extract from the Personal Protective Equipment
at Work Regulations).
•
•
•
Every operative is to ensure that they have received adequate training with regards to the
use of any particular item of Personal Protective Equipment.
Self employed persons are to ensure they purchase and maintain PPE in line with the
relevant risk assessments
Employed persons are to ensure they look after and use any PPE provided for them and
report any defects etc to their supervisor immediately.
Welfare Facilities
Operatives will use the welfare facilities provided by the Principle Contractor to include toilet
facilities and Mess Canteen, the canteen facilities will be used for all meal breaks and no
breaks will be held in the work area, on any other part of the site nor in vehicles (Private or
company owned)
© M J Stevens Group
•
•
2 of 3
MJSM11
scaffold. Operatives are to check that this gap is not excessive prior to starting work.
All materials are to be lifted to a suitable area near to the spraying machine by forklift
If other trades are working within/on the property they must be advised of the work
activities that are about to commence.
Method of work/use of the spraying machine
•
Operatives using this equipment are to be trained in its use and competent (training will
be carried out in house) operatives who are new to the equipment are to be supervised at
all times.
•
The equipment including: hoses, spry nozzle, mixer, generator, guards and all other
associated paraphernalia is to be inspected by the foremen prior to each shift.
•
Hoses are not to be separated until the pressure has been removed from the system by
reversing the pump.
•
All moving parts are to be guarded with movable guards fitted with interlock switches this
will include guards to the engine compartment, mixing chamber and the pump chamber.
•
The spraying and mixing operations are to be shared by the gang to reduce the risk of
manual handling and repetitive strain injury.
•
Bags of material are to weigh no more than 25kg
•
Dust masks are to be worn by the operative working at the machine and by any
operatives in the vicinity. The operatives must also have read and understood the
COSHH assessment for the product being sprayed.
•
Materials are to be loaded into a sensible location near to the mixer by the principal
contractor. This will avoid excessive manual handling.
•
Safety glasses are to be worn by the operative using the spray gun and any other
operatives in the immediate area.
•
Electrical safety to be tested by a competent person annually.
•
All controls to be kept clean and clearly labelled to prevent unintended start-up
•
All spraying machines are to be fitted with a proprietary emergency stop.
Personal Protective Equipment
Every self-employed person shall ensure that any personal protective equipment provided to
him is maintained (including replaced or cleaned as appropriate) in an efficient state, in
efficient working order and in good repair - (Extract from the Personal Protective Equipment
at Work Regulations).
•
•
•
Every operative is to ensure that they have received adequate training with regards to the
use of any particular item of Personal Protective Equipment.
Self employed persons are to ensure they purchase and maintain PPE in line with the
relevant risk assessments
Employed persons are to ensure they look after and use any PPE provided for them and
report any defects etc to their supervisor immediately.
Welfare Facilities
Operatives will use the welfare facilities provided by the Principle Contractor to include toilet
facilities and Mess Canteen, the canteen facilities will be used for all meal breaks and no
breaks will be held in the work area, on any other part of the site nor in vehicles (Private or
company owned)
© M J Stevens Group
2 of 3
MJSM11
On Completion
Completion of
of Works
W o rk s
Al
o rk a
n a cclean
lean ccondition
re a s a
re tto
ob
e lleft
efftt iin
o n d itio n a
nd a
s p e c ts o
a fe ty w
ith rregards
egards tto
o tthe
he
Alll w
work
areas
are
be
and
allll a
aspects
off ssafety
with
immediate w
o rk a
re a a
nd conduct
conduct a visual
visual inspection
inspection b
y tthe
he o
perative to
to ensure
ensure tthat
hat tthe
he
immediate
work
area
and
by
operative
edge pr
otection iis
s iin
n pl
ace and tthat
hat tthere
here iis
s no rrisk
isk tto
o iinjury
njury tto
o tthemselves
hemselves or ot
hers as a
protection
place
others
di
rect rresult
esult of a ffall
all ffrom
rom that
that area.
area.
direct
tored iin
En
sure all
a ll o
ther m
aterial w
hich is used
used fo
our w
ork is sstored
n a ssafe
afe a
nd p
ro p e r m
anner
Ensure
other
material
which
forr yyour
work
and
proper
manner
ou ar
ew
orking iin.
n.
before depar
ting ffrom
rom tthe
he pr
operty yyou
before
departing
property
are
working
n ccompletion
o m p le tio n o
he wo
Re
port tto
o tthe
he S
ite M
anagem ent T
ea m o
rk s a
nd iiff rrequired
e q u ir e d b
y tthe
he ssite
ite
Report
Site
Management
Team
on
off tthe
works
and
by
ut before
befo
ore leaving
ru
les ssign
ig n o
leaving
rules
out
NA
NAME
ME
DA
DATE
TE
An
Andy
dy W
White
h ite
01/11/2009
01/11
/2009
RE
REVIEW
VIEW DA
DATE
TE
01/04/2015
SIGNATURE
SIGNATURE
MBA
MBA Safety
Safety & Training
T ra in in g
Lt
Ltd
d
JO
JOBTITLE
B T IT L E
He
Health
a lt h a
and
nd safety
safety Co
Consultant
n s u lta n t
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Fax:
Tel: 01823
01823 668526 / F
ax: 01823
668527
© M J Stevens
Stevens Group
Group
3 of 3
MJSM11
MJSM11
On Completion
Completion of
of Works
W o rk s
Al
o rk a
n a cclean
lean ccondition
re a s a
re tto
ob
e lleft
efftt iin
o n d itio n a
nd a
s p e c ts o
a fe ty w
ith rregards
egards tto
o tthe
he
Alll w
work
areas
are
be
and
allll a
aspects
off ssafety
with
immediate w
o rk a
re a a
nd conduct
conduct a visual
visual inspection
inspection b
y tthe
he o
perative to
to ensure
ensure tthat
hat tthe
he
immediate
work
area
and
by
operative
edge pr
otection iis
s iin
n pl
ace and tthat
hat tthere
here iis
s no rrisk
isk tto
o iinjury
njury tto
o tthemselves
hemselves or ot
hers as a
protection
place
others
di
rect rresult
esult of a ffall
all ffrom
rom that
that area.
area.
direct
yo u r w
tored iin
En
sure all
all other
other m
aterial which
which is used
used fo
ork is sstored
n a ssafe
afe a
nd p
ro p e r m
anner
Ensure
material
forr your
work
and
proper
manner
ou ar
ew
orking iin.
n.
before depar
ting ffrom
rom tthe
he pr
operty yyou
before
departing
property
are
working
n ccompletion
o m p le tio n o
he wo
Re
port tto
o tthe
he S
ite M
anagem ent T
ea m o
rk s a
nd iiff rrequired
e q u ir e d b
y tthe
he ssite
ite
Report
Site
Management
Team
on
off tthe
works
and
by
ut b
efo
ore lleaving
ru
les ssign
ig n o
eaving
rules
out
before
NA
NAME
ME
DA
DATE
TE
An
Andy
dy W
White
h ite
01/11/2009
01/11
/2009
RE
REVIEW
VIEW DA
DATE
TE
01/11/2011
01/11
/2011
SIGNATURE
SIGNATURE
MBA
MBA Safety
Safety & Training
T ra in in g
Ltd
Lt
d
JO
JOBTITLE
B T IT L E
He
Health
a lt h a
and
nd s
safety
afety Co
Consultant
n s u lta n t
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Fax:
Tel: 01823
01823 668526 / F
ax: 01823
668527
© M J Stevens
Stevens Group
Group
3 of 3
MJSM11
MJSM11
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference
Number:
MJSM12
Area Assessed:
Site location:
Operatives Handbook
Description:
Installation of Traditional wooden floor joists
Operatives Identified:
Site based operatives
WORK ACTIVITY:
Installation of traditional wooden floor Joists (1st & 2nd Floors)
To be read in conjunction with the company’s Generic Risk
Assessments
MJSRa01
MJSRa02
MJSRa03
MJSRa04
MJSRa08
MJSRa09
MJSRa11
MJSRa12
MJSRa14
MJSRa16
Working at Height
Manual Handling
Noise
Vibration
Power tools
Electrocution
Materials Delivery
Materials / Objects falling from height
Ladders and step ladders
Joist installation
Method of work
•
•
•
•
•
•
•
•
The work area, namely the scaffolding to be provided by the principle contractor. This is
to be free of other trades working in the immediate area. The erected scaffold structure
will be inspected by the Principle Contractors representative as set out in the Work at
Height Regulations 2005
All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing.
Soft landing system is to be placed inside the unit by the principle contractor and
approved by site management.
No other trades are allowed to work within the property they must be advised as to
vacate the work area prior to you commencing work.
Operatives will mark out the position of the joists on the appropriate walls in accordance
with the relevant plan.
All cutting to be carried out on the ground. Whilst cutting operations are conducted
consideration is to be given to the following legislations; The Control of Noise at Work
Regulations 2005 & The Vibration at Work Regulations 2005
All joist hangers are to be fitted prior to joists being fitted.
All joist to be lifted by mechanical means to the loading bay, two operatives to unload
together and layout as per plan, ensure once loading operations are completed that the
loading bay gate to the working platform is returned to is correct position allowing
adequate edge protection against falls, if during the loading operations it is felt that
further protection against falls is required, personal fall arrest systems must be
implemented.
© M J Stevens Group
1 of 2
MJSM12
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference
Number:
MJSM12
Area Assessed:
Site location:
Operatives Handbook
Description:
Installation of Traditional wooden floor joists
Operatives Identified:
Site based operatives
WORK ACTIVITY:
Installation of traditional wooden floor Joists (1st & 2nd Floors)
To be read in conjunction with the company’s Generic Risk
Assessments
MJSRa01
MJSRa02
MJSRa03
MJSRa04
MJSRa08
MJSRa09
MJSRa11
MJSRa12
MJSRa14
MJSRa16
Working at Height
Manual Handling
Noise
Vibration
Power tools
Electrocution
Materials Delivery
Materials / Objects falling from height
Ladders and step ladders
Joist installation
Method of work
•
•
•
•
•
•
•
•
The work area, namely the scaffolding to be provided by the principle contractor. This is
to be free of other trades working in the immediate area. The erected scaffold structure
will be inspected by the Principle Contractors representative as set out in the Work at
Height Regulations 2005
All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing.
Soft landing system is to be placed inside the unit by the principle contractor and
approved by site management.
No other trades are allowed to work within the property they must be advised as to
vacate the work area prior to you commencing work.
Operatives will mark out the position of the joists on the appropriate walls in accordance
with the relevant plan.
All cutting to be carried out on the ground. Whilst cutting operations are conducted
consideration is to be given to the following legislations; The Control of Noise at Work
Regulations 2005 & The Vibration at Work Regulations 2005
All joist hangers are to be fitted prior to joists being fitted.
All joist to be lifted by mechanical means to the loading bay, two operatives to unload
together and layout as per plan, ensure once loading operations are completed that the
loading bay gate to the working platform is returned to is correct position allowing
adequate edge protection against falls, if during the loading operations it is felt that
further protection against falls is required, personal fall arrest systems must be
implemented.
© M J Stevens Group
1 of 2
MJSM12
•
•
•
•
•
•
Stairwell
Stairwell ttrimmers
r im m e r s w
will
ill n
need
eed tto
o be pos
positioned
itioned ffrom
rom bel
below
ow ((off
of
offf a ssuitable
uitable w
working
orking pl
platform
atfo
or
om
osition.
supplied
supplied & e
erected
rected b
by
y th
the
ep
principle
rinciple ccontractor)
ontractor) a
and
nd llifted
ifted iinto
nto p
position.
joists are
are to
to be
be fitted
fitted into
bove.
Where
Where joists
into RSJs
RSJs they
they will
w ill b
be
e fi
fitted
tted a
as
sa
above.
or thicker
thicker te
mporary flooring
flooring w
22mm or
nto th
e lloading
o a d in g b
ay.
22mm
temporary
will
ill b
be
e lloaded
oaded b
by
y fo
forklift
rklift o
onto
the
bay.
st
ow o
off fflooring
lo o rin g o
off
fff tthe
he sscaffold,
c a f fo l d , g
giving
platform
work
ill p
osition 1 rrow
iving a ssafe
a fe p
latform tto
ow
o rk
Operatives
Operatives w
will
position
offf for
for the
fo
the rrest
est of tthe
he ffloor.
loor.
Alll o
off
be
and
placed
designated
provided
principle
Al
fff ccuts
uts tto
ob
e ccleared
le a r e d a
nd pl
aced iin
n tthe
he des
ignated sskip
kip as pr
ovided by tthe
he pr
inciple
contractor.
contractor.
y tthe
he Pr
in c ip le C
ontactor ffor
or tthe
he w
o rk .
Adequate
be
provided
by
Principle
Contactor
work.
Adequate llighting
ighting iis
s tto
ob
ep
rovided b
Personal
Protective
otective Equipment
Equipment
Personal Pr
ure tthat
hat any per
sonal pr
otective equipment
e q u ip m e n t p
rovided tto
o
Every
elf-employed per
person
son sshall
hall ens
ensure
personal
protective
provided
Every sself-employed
leaned as appr
opriate) iin
n an efficient
tate, in
in
effficient sstate,
him
maintained
aintained ((including
including rreplaced
eplaced or ccleaned
appropriate)
him is
is m
eff
ficient w
epair - (Extract
(Extract from
from the
the Personal
Personal Protective
at
Protective Equipment
Equipment at
efficient
working
orking or
order
der and iin
n good rrepair
Work Regulations).
R eg u la t io n s ) .
Work
•
•
•
Every
Every o
operative
ensure
hey h
have
ave re
received
c e iv e d a
adequate
dequate ttraining
raining w
with
ith re
regards
gards tto
o tthe
he
perative iis
s tto
oe
nsure that
that tthey
use
use of any par
particular
Personal
ersonal P
Protective
rotective E
Equipment.
quipment.
ticular iitem
tem of P
he
Self
Self e
employed
persons
are
ensure
nsure tthey
hey p
purchase
u rc h a s e a
and
nd m
maintain
aintain PPE iin
n lline
in e w
with
ith tthe
m p lo y e d p
e rs o n s a
re tto
o e
relevant
relevant ri
risk
assessments
sk a
s s e s s m e n ts
hey llook
ook af
ftter and us
PE pr
ovided fo
or tthem
Employed
Employed p
persons
are
after
use
e any P
PPE
provided
for
hem and
e rs o n s a
re tto
o ensure
ensure tthey
ny d
efe
e c ts e
upervisor iimmediately.
m m e d ia te ly .
report
report a
any
defects
etc
tc tto
o ttheir
heir ssupervisor
Welfare
F a c ilitie s
Welfare Facilities
o ile t
ontractor tto
o iinclude
nclude ttoilet
Operatives
will
ill u
use
se tthe
he w
welfare
elfa
are ffacilities
provided
by
Principle
Contractor
a c ilitie s p
r o v id e d b
y tthe
he P
r in c ip le C
Op
e r a t iv e s w
fa
cilities a
nd Me
ss C
anteen, tthe
he ccanteen
anteen ffacilities
a c ilitie s w
ill b
e u
sed ffor
or a
al b
re a k s a
nd n
o
facilities
and
Mess
Canteen,
will
be
used
allll me
meal
breaks
and
no
br
eaks w
ill be hel
d iin
n tthe
he w
ork ar
ea, on any ot
her par
he ssite
ite nor iin
n vvehicles
ehicles ((Private
Private or
breaks
will
held
work
area,
other
partt of tthe
company owned)
ow ned)
company
On Completion
off Works
C o m p le tio n o
W o rk s
Alll w
work
areas
re a s a
are
re tto
ob
be
e lleft
efftt iin
alll as
aspects
afe
ety w
with
ondition and al
pects of ssafety
ith rregards
egards tto
o tthe
he
n a cclean
lean ccondition
Al
o rk a
immediate
work
o rk a
area
re a a
and
nd cconduct
onduct a vvisual
inspection
by
operative
perative tto
oe
ensure
nsure tthat
hat tthe
he e
edge
isual in
spection b
y tthe
he o
dge
im
mediate w
protection
s iin
n pl
place
ace and tthat
hat tthere
hemselves or ot
others
hers as a di
direct
here iis
s no rrisk
isk tto
o iinjury
njury tto
o tthemselves
rect
pr
otection iis
a l ffrom
al
rom tthat
hat ar
ea.
result
off a ffall
area.
re
s u lt o
Ensure
allll o
other
th e r m
material
a te r ia l w
which
hich iis
su
used
sed fo
for
or yyour
work
n a ssafe
a fe a
and
nd p
proper
ro p e r m
manner
anner
our w
ork iis
s sstored
tored iin
En
s u re a
bef
before
ore depar
departing
ting ffrom
rom tthe
he pr
property
operty yyou
ou ar
are
ew
working
orking iin.
n.
rk s a
nd iiff rrequired
e q u ir e d b
y tthe
he ssite
ite
Re
Report
porrtt tto
Site
Management
Team
on
off tthe
works
and
by
o tthe
he S
ite M
anagem ent T
eam o
n ccompletion
o m p le tio n o
he wo
ut b
efo
ore lleaving
ru
rules
les ssign
ig n o
out
before
e a v in g
NAME
NA
ME
Andy
White
An
dy W
h ite
DATE
01/11/2009
DA
TE 01/
11/2009
RE
VIEW DA
TE
REVIEW
DATE
01/04/2015
SI
SIGNATURE
GNATURE
MB
MBA
AS
Safety
a f et y & T
Training
r a in in g L
Ltd
td
JOBTITLE
JO
B T IT L E
Health
and
safety
Consultant
n s u lta n t
He
a lt h a
nd s
afety Co
Un
it 6 ““The
The Co
unting Ho
use”
Unit
Counting
House”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
tevens G
roup
©MJS
Stevens
Group
•
•
•
•
•
•
2 of 2
MJSM12
MJSM12
Stairwell
Stairwell ttrimmers
r im m e r s w
will
ill n
need
eed tto
o be pos
positioned
itioned ffrom
rom bel
below
ow ((off
of
offf a ssuitable
uitable w
working
orking pl
platform
atfo
or
om
osition.
supplied
supplied & e
erected
rected b
by
y th
the
ep
principle
rinciple ccontractor)
ontractor) a
and
nd llifted
ifted iinto
nto p
position.
joists are
are to
to be
be fitted
fitted into
bove.
Where
Where joists
into RSJs
RSJs they
they will
w ill b
be
e fi
fitted
tted a
as
sa
above.
or thicker
thicker te
mporary flooring
flooring w
22mm or
nto th
e lloading
o a d in g b
ay.
22mm
temporary
will
ill b
be
e lloaded
oaded b
by
y fo
forklift
rklift o
onto
the
bay.
st
ow o
off fflooring
lo o rin g o
off
fff tthe
he sscaffold,
c a f fo l d , g
giving
platform
work
ill p
osition 1 rrow
iving a ssafe
a fe p
latform tto
ow
o rk
Operatives
Operatives w
will
position
offf for
for the
fo
the rrest
est of tthe
he floor.
floor.
All
be
and
placed
designated
provided
principle
All off
offf ccuts
uts tto
ob
e ccleared
le a r e d a
nd pl
aced iin
n tthe
he des
ignated sskip
kip as pr
ovided by tthe
he pr
inciple
contractor.
contractor.
y tthe
he Pr
in c ip le C
ontactor ffor
or tthe
he w
o rk .
Adequate
be
provided
by
Principle
Contactor
work.
Adequate llighting
ighting iis
s tto
ob
ep
rovided b
Personal
Protective
otective Equipment
Equipment
Personal Pr
ure tthat
hat any per
sonal pr
otective equipment
equipment provided
provided tto
o
Every
elf-employed per
person
son sshall
hall ens
ensure
personal
protective
Every sself-employed
leaned as appr
opriate) iin
n an efficient
tate, in
in
effficient sstate,
him
maintained
aintained ((including
including rreplaced
eplaced or ccleaned
appropriate)
him is
is m
eff
ficient w
epair - (Extract
(Extract from
from the
the Personal
Personal Protective
Protective Equipment
E q u ip m e n t a
efficient
working
orking or
order
der and iin
n good rrepair
att
Work Regulations).
R eg u la t io n s ) .
Work
•
•
•
Every
Every o
operative
ensure
hey h
have
ave re
received
c e iv e d a
adequate
dequate ttraining
raining w
with
ith re
regards
gards tto
o tthe
he
perative iis
s tto
oe
nsure that
that tthey
use
use of any par
particular
Personal
ersonal P
Protective
rotective E
Equipment.
quipment.
ticular iitem
tem of P
he
Self
Self e
employed
persons
are
ensure
nsure tthey
hey p
purchase
u rc h a s e a
and
nd m
maintain
aintain PPE iin
n lline
in e w
with
ith tthe
m p lo y e d p
e rs o n s a
re tto
o e
relevant
relevant ri
risk
assessments
sk a
s s e s s m e n ts
hey llook
ook af
ftter and us
PE pr
ovided fo
or tthem
Employed
Employed p
persons
are
after
use
e any P
PPE
provided
for
hem and
e rs o n s a
re tto
o ensure
ensure tthey
ny d
efe
e c ts e
upervisor iimmediately.
m m e d ia te ly .
report
report a
any
defects
etc
tc tto
o ttheir
heir ssupervisor
Welfare
F a c ilitie s
Welfare Facilities
o ile t
ontractor tto
o iinclude
nclude ttoilet
Operatives
will
ill u
use
se tthe
he w
welfare
elfa
are ffacilities
provided
by
Principle
Contractor
a c ilitie s p
r o v id e d b
y tthe
he P
r in c ip le C
Op
e r a t iv e s w
fa
cilities a
nd Me
ss C
anteen, tthe
he ccanteen
anteen ffacilities
a c ilitie s w
ill b
e u
sed ffor
or a
al b
re a k s a
nd n
o
facilities
and
Mess
Canteen,
will
be
used
allll me
meal
breaks
and
no
br
eaks w
ill be hel
d iin
n tthe
he w
ork ar
ea, on any ot
her par
he ssite
ite nor iin
n vvehicles
ehicles ((Private
Private or
breaks
will
held
work
area,
other
partt of tthe
company owned)
ow ned)
company
On Completion
off Works
C o m p le tio n o
W o rk s
Alll w
work
areas
re a s a
are
re tto
ob
be
e lleft
efftt iin
alll as
aspects
afe
ety w
with
ondition and al
pects of ssafety
ith rregards
egards tto
o tthe
he
n a cclean
lean ccondition
Al
o rk a
immediate
work
o rk a
area
re a a
and
nd cconduct
onduct a vvisual
inspection
by
operative
perative tto
oe
ensure
nsure tthat
hat tthe
he e
edge
isual in
spection b
y tthe
he o
dge
im
mediate w
protection
s iin
n pl
place
ace and tthat
hat tthere
hemselves or ot
others
hers as a di
direct
here iis
s no rrisk
isk tto
o iinjury
njury tto
o tthemselves
rect
pr
otection iis
a l ffrom
al
rom tthat
hat ar
ea.
result
off a ffall
area.
re
s u lt o
Ensure
allll o
other
th e r m
material
a te r ia l w
which
hich iis
su
used
sed fo
for
or yyour
work
n a ssafe
a fe a
and
nd p
proper
ro p e r m
manner
anner
our w
ork iis
s sstored
tored iin
En
s u re a
bef
before
ore depar
departing
ting ffrom
rom tthe
he pr
property
operty yyou
ou ar
are
ew
working
orking iin.
n.
rk s a
nd iiff rrequired
e q u ir e d b
y tthe
he ssite
ite
Re
Report
porrtt tto
Site
Management
Team
on
off tthe
works
and
by
o tthe
he S
ite M
anagem ent T
eam o
n ccompletion
o m p le tio n o
he wo
ut b
efo
ore lleaving
ru
rules
les ssign
ig n o
out
before
e a v in g
NAME
NA
ME
Andy
White
Andy W
h ite
DATE
01/11/2009
DA
TE 01/
11/2009
RE
VIEW DA
TE
REVIEW
DATE
01/
01/11/2011
11/2011
SI
SIGNATURE
GNATURE
MB
MBA
A Safety
S a f et y & T
Training
r a in in g L
Ltd
td
JOBTITLE
JO
B T IT L E
Health
and
safety
Consultant
n s u lta n t
He
a lt h a
nd s
afety Co
Un
it 6 ““The
The Co
unting Ho
use”
Unit
Counting
House”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
©MJS
Stevens
Group
tevens G
roup
2 of 2
MJSM12
MJSM12
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference
Number:
Area Assessed:
Site locations: Operatives Handbook
MJSM13
Description:
Internal plastering
Operatives Involved:
Site based operatives
WORK ACTIVITY:
Internal plastering
To be read in conjunction with the company’s Generic Risk
Assessments
MJSRa01
MJSRa02
MJSRa03
MJSRa04
MJSRa08
MJSRa09
MJSRa10
MJSRa11
MJSRa12
MJSRa13
MJSRa14
MJSRa15
Working at Height
Manual Handling
Noise
Vibration
Power tools
Electrocution
Breathing in dust particles
Materials Delivery
Materials / Objects falling from height
Mobile scaffold towers and platforms
Ladders and step ladders
Working off stilts
The Work Area (General Precautions)
•
The work area is to be free of other trades, visitors and site staff.
•
All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing.
•
Good access is to be provided by the principal contractor with full height access through
1 of 3
MJSM13
© M J Stevens Group
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference
Number:
Area Assessed:
Site locations: Operatives Handbook
MJSM13
Description:
Internal plastering
Operatives Involved:
Site based operatives
WORK ACTIVITY:
Internal plastering
To be read in conjunction with the company’s Generic Risk
Assessments
MJSRa01
MJSRa02
MJSRa03
MJSRa04
MJSRa08
MJSRa09
MJSRa10
MJSRa11
MJSRa12
MJSRa13
MJSRa14
MJSRa15
Working at Height
Manual Handling
Noise
Vibration
Power tools
Electrocution
Breathing in dust particles
Materials Delivery
Materials / Objects falling from height
Mobile scaffold towers and platforms
Ladders and step ladders
Working off stilts
The Work Area (General Precautions)
•
The work area is to be free of other trades, visitors and site staff.
•
All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing.
•
Good access is to be provided by the principal contractor with full height access through
1 of 3
MJSM13
© M J Stevens Group
scaffold etc.
•
If other trades are working within the property they must be advised of the work activities
that are about to commence.
Method of work
•
Operatives using the mixer are to be trained in its use and competent (training will be
carried out in house) operatives who are new to the equipment are to be supervised at all
times.
•
The equipment, guards and all other associated paraphernalia is to be inspected by the
foremen prior to each shift.
•
All moving parts are to be guarded with movable guards fitted with interlock switches this
will include guards to the engine compartment, mixing chamber.
•
The mixing operation is to be shared by the gang to reduce the risk of manual handling
and repetitive strain injury.
•
The operatives must also have read and understood the COSHH assessment for the
product being used.
•
Materials are to be loaded into a sensible location near to the mixer by the principal
contractor. This will avoid excessive manual handling.
•
Safety glasses are to be worn by the operatives carrying out the mixing operation and
any other operatives in the immediate area.
•
All controls to be kept clean and clearly labelled to prevent unintended start-up
•
All mixers are to be fitted with a proprietary emergency stop.
•
Protective clothing is to be worn by operatives during the application process to avoid
cement/lime burns.
•
Warning signs are to be placed on the mixer to ensure no unsafe practices are adopted.
•
Large amounts of plaster material will be carried to the work area from the batching area
by the principle contractor’s forklift and operator.
•
Small amounts of plaster material will be mixed up via a hand drill mixer at the place of
work.
•
Electrical safety to be tested by a competent person at 3 month intervals.
•
PAT labels will be on view and in date on all electrical equipment.
•
Plaster will be applied to the wall via hand trowel.
Personal Protective Equipment
Every self-employed person shall ensure that any personal protective equipment provided to
him is maintained (including replaced or cleaned as appropriate) in an efficient state, in
efficient working order and in good repair - (Extract from the Personal Protective Equipment
at Work Regulations).
•
•
•
Every operative is to ensure that they have received adequate training with regards to the
use of any particular item of Personal Protective Equipment.
Self employed persons are to ensure they purchase and maintain PPE in line with the
relevant risk assessments
Employed persons are to ensure they look after and use any PPE provided for them and
report any defects etc to their supervisor immediately.
Welfare Facilities
© M J Stevens Group
2 of 3
MJSM13
scaffold etc.
•
If other trades are working within the property they must be advised of the work activities
that are about to commence.
Method of work
•
Operatives using the mixer are to be trained in its use and competent (training will be
carried out in house) operatives who are new to the equipment are to be supervised at all
times.
•
The equipment, guards and all other associated paraphernalia is to be inspected by the
foremen prior to each shift.
•
All moving parts are to be guarded with movable guards fitted with interlock switches this
will include guards to the engine compartment, mixing chamber.
•
The mixing operation is to be shared by the gang to reduce the risk of manual handling
and repetitive strain injury.
•
The operatives must also have read and understood the COSHH assessment for the
product being used.
•
Materials are to be loaded into a sensible location near to the mixer by the principal
contractor. This will avoid excessive manual handling.
•
Safety glasses are to be worn by the operatives carrying out the mixing operation and
any other operatives in the immediate area.
•
All controls to be kept clean and clearly labelled to prevent unintended start-up
•
All mixers are to be fitted with a proprietary emergency stop.
•
Protective clothing is to be worn by operatives during the application process to avoid
cement/lime burns.
•
Warning signs are to be placed on the mixer to ensure no unsafe practices are adopted.
•
Large amounts of plaster material will be carried to the work area from the batching area
by the principle contractor’s forklift and operator.
•
Small amounts of plaster material will be mixed up via a hand drill mixer at the place of
work.
•
Electrical safety to be tested by a competent person at 3 month intervals.
•
PAT labels will be on view and in date on all electrical equipment.
•
Plaster will be applied to the wall via hand trowel.
Personal Protective Equipment
Every self-employed person shall ensure that any personal protective equipment provided to
him is maintained (including replaced or cleaned as appropriate) in an efficient state, in
efficient working order and in good repair - (Extract from the Personal Protective Equipment
at Work Regulations).
•
•
•
Every operative is to ensure that they have received adequate training with regards to the
use of any particular item of Personal Protective Equipment.
Self employed persons are to ensure they purchase and maintain PPE in line with the
relevant risk assessments
Employed persons are to ensure they look after and use any PPE provided for them and
report any defects etc to their supervisor immediately.
Welfare Facilities
© M J Stevens Group
2 of 3
MJSM13
Op
e r a t iv e s w
ill u
se tthe
he w
elfa
are fa
a c ilitie s p
r o v id e d b
y tthe
he P
r in c ip le C
ontractor tto
o iinclude
nclude ttoilet
o ile t
Operatives
will
use
welfare
facilities
provided
by
Principle
Contractor
fa
cilities a
nd M
ess C
anteen, th
e ccanteen
anteen fa
cilities w
ill b
e u
sed fo
eal b
re a k s a
nd n
o
facilities
and
Mess
Canteen,
the
facilities
will
be
used
forr a
allll m
meal
breaks
and
no
ea, on any ot
her par
br
eaks w
ill be hel
d iin
n tthe
he w
ork ar
he ssite
ite nor iin
n vvehicles
ehicles ((Private
Private or
breaks
will
held
work
area,
other
partt of tthe
company owned)
ow ned)
company
On Completion
Completion of
of Works
W o rk s
Al
o rk a
n a cclean
lean ccondition
re a s a
re tto
ob
e lleft
efftt iin
o n d it i o n a
nd a
s p e ct s o
a fe ty w
ith rregards
egards tto
o the
t
Alll w
work
areas
are
be
and
allll a
aspects
off ssafety
with
im
mediate w
o rk a
re a a
nd conduct
conduct a visual
visual inspection
inspection b
y tthe
he operative
operative to
to ensure
ensure tthat
hat tthe
he
immediate
work
area
and
by
edge pr
otection iis
s iin
n pl
ace and tthat
hat tthere
here iis
s no rrisk
isk tto
o iinjury
njury tto
o tthemselves
hemselves or ot
hers as a
protection
place
others
di
rect rresult
esult of a ffall
all ffrom
rom that
that area.
area.
direct
En
sure all
all o
th e r m
a te r ia l w
hich is u
our w
ork is sstored
nd p
ro p e r m
anner
sed ffor
or yyour
tored iin
n a ssafe
afe
ea
Ensure
other
material
which
used
work
and
proper
manner
bef
ore depar
ting ffrom
rom the
the pr
operty yyou
ou ar
ew
orking iin.
n.
before
departing
property
are
working
o tthe
he S
ite M
anagem ent T
eam o
n ccompletion
o m p le tio n o
he wo
Re
port tto
rk s a
nd iiff rrequired
e q u ir e d b
y tthe
he ssite
ite
Report
Site
Management
Team
on
off tthe
works
and
by
e a v in g
ut b
efo
ore lleaving
ru
les ssign
ig n o
rules
out
before
NA
ME
NAME
DA
TE
DATE
An
dy W
h ite
Andy
White
01/11/2009
01/11
/2009
RE
REVIEW
VIEW DA
DATE
TE
01/04/2015
SI
SIGNATURE
GNATURE
MBA
MBA Safety
Safety & Training
T ra in in g
Ltd
Lt
d
JO
B T IT L E
JOBTITLE
He
a lt h a
nd safety
safety Co
Health
and
Consultant
n s u lta n t
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
© M J Stevens
Stevens Group
Group
3 of 3
MJSM13
MJSM13
M
Op
e r a t iv e s w
ill u
se tthe
he w
elfa
are fa
a c ilitie s p
r o v id e d b
y tthe
he P
r in c ip le C
ontractor tto
o iinclude
nclude ttoilet
o ile t
Operatives
will
use
welfare
facilities
provided
by
Principle
Contractor
fa
cilities a
nd M
ess C
anteen, th
e ccanteen
anteen fa
cilities w
ill b
e u
sed fo
eal b
re a k s a
nd n
o
facilities
and
Mess
Canteen,
the
facilities
will
be
used
forr a
allll m
meal
breaks
and
no
ea, on any ot
her par
br
eaks w
ill be hel
d iin
n tthe
he w
ork ar
he ssite
ite nor iin
n vvehicles
ehicles ((Private
Private or
breaks
will
held
work
area,
other
partt of tthe
company owned)
ow ned)
company
On Completion
Completion of
of Works
W o rk s
Al
o rk a
n a cclean
lean ccondition
re a s a
re tto
ob
e lleft
efftt iin
o n d it i o n a
nd a
s p e ct s o
a fe ty w
ith rregards
egards tto
o the
t
Alll w
work
areas
are
be
and
allll a
aspects
off ssafety
with
im
mediate w
o rk a
re a a
nd conduct
conduct a visual
visual inspection
inspection b
y tthe
he operative
operative to
to ensure
ensure tthat
hat tthe
he
immediate
work
area
and
by
edge pr
otection iis
s iin
n pl
ace and tthat
hat tthere
here iis
s no rrisk
isk tto
o iinjury
njury tto
o tthemselves
hemselves or ot
hers as a
protection
place
others
di
rect rresult
esult of a ffall
all ffrom
rom that
that area.
area.
direct
En
sure all
all o
th e r m
a te r ia l w
hich is u
our w
ork is sstored
nd p
ro p e r m
anner
sed ffor
or yyour
tored iin
n a ssafe
afe
ea
Ensure
other
material
which
used
work
and
proper
manner
bef
ore depar
ting ffrom
rom the
the pr
operty yyou
ou ar
ew
orking iin.
n.
before
departing
property
are
working
o tthe
he S
ite M
anagem ent T
eam o
n ccompletion
o m p le tio n o
he wo
Re
port tto
rk s a
nd iiff rrequired
e q u ir e d b
y tthe
he ssite
ite
Report
Site
Management
Team
on
off tthe
works
and
by
e a v in g
ut b
efo
ore lleaving
ru
les ssign
ig n o
rules
out
before
NA
ME
NAME
DA
TE
DATE
An
dy W
h ite
Andy
White
01/11/2009
01/11
/2009
RE
REVIEW
VIEW DA
DATE
TE
01/11/2011
01/11
/2011
SI
SIGNATURE
GNATURE
MBA
MBA Safety
Safety & Training
T ra in in g
Ltd
Lt
d
JO
B T IT L E
JOBTITLE
He
a lt h a
nd s
afety Co
Health
and
safety
Consultant
n s u lta n t
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
© M J Stevens
Stevens Group
Group
3 of 3
MJSM13
MJSM13
M
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference
Number:
Area Assessed:
Site locations: Operatives Handbook
MJSM14
Description:
Painting
Operatives Involved:
Site based operatives
WORK ACTIVITY:
Painting
To be read in conjunction with the company’s Generic Risk
Assessments
MJSRa01
MJSRa02
MJSRa03
MJSRa09
MJSRa10
MJSRa11
MJSRa12
MJSRa13
MJSRa14
Working at Height
Manual Handling
Noise
Electrocution
Breathing in dust particles
Materials Delivery
Materials / Objects falling from height
Mobile scaffold towers and platforms
Ladders and step ladders
Also To be read in conjunction with the following method statement
MJSM02
Working in the area of Stairwells
The Work Area (General Precautions)
•
The work area is to be free of other trades, visitors and site staff.
•
All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing.
•
Good access is to be provided by the principal contractor with full height access through
scaffold etc.
© M J Stevens Group
1 of 3
MJSM14
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference
Number:
Area Assessed:
Site locations: Operatives Handbook
MJSM14
Description:
Painting
Operatives Involved:
Site based operatives
WORK ACTIVITY:
Painting
To be read in conjunction with the company’s Generic Risk
Assessments
MJSRa01
MJSRa02
MJSRa03
MJSRa09
MJSRa10
MJSRa11
MJSRa12
MJSRa13
MJSRa14
Working at Height
Manual Handling
Noise
Electrocution
Breathing in dust particles
Materials Delivery
Materials / Objects falling from height
Mobile scaffold towers and platforms
Ladders and step ladders
Also To be read in conjunction with the following method statement
MJSM02
Working in the area of Stairwells
The Work Area (General Precautions)
•
The work area is to be free of other trades, visitors and site staff.
•
All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing.
•
Good access is to be provided by the principal contractor with full height access through
scaffold etc.
© M J Stevens Group
1 of 3
MJSM14
•
If other trades are working within the property they must be advised of the work activities
that are about to commence.
Method of work
•
The works will take place according to the programme set out by the Principal Contractor.
Our operatives will undertake painting tasks as requested on the site order.
•
The operatives must read and understand the COSHH assessment for the products
being used.
•
Materials will be delivered to site via the supplier or in the Sub-contractors van; deliveries
will be delivered as close to the work area as physically possible to avoid excessive
manual handling activities.
•
Materials are to be loaded into the property via hand; no material used is in excess of
25kg.
•
Protective clothing is to be worn by operatives during the application process.
•
External painting applications will be carried out off of the principle contractors
scaffolding, at no time will work be carried out off of ladders, unless prior permission has
been gained from the principle contractor and there is no other safer practicable means
available, only short duration (under 15 minutes) work will be carried out in this way at
any time. Only 1 handed work will be carried out in this way.
•
Site operatives are to ensure that the Principle Contractor has inspected the scaffold
structure in line with the requirements set out in the Work at Height Regulations 2005.
The basics are to be checked by the operative prior to starting work i.e. that proper
access is available, handrails are in place, no missing boards etc.
•
All scaffolds are to be adapted to allow for the application of paint from a stable working
platform, no standing on trestle platforms or stepladders etc placed on the scaffold to
gain extra height is permitted.
•
All materials are to be lifted to the work area by forklift via a loading bay under no
circumstances are MJ Stevens operatives to carry materials up a ladder.
•
When working internally our operatives will ensure adequate local ventilation when
applying Decorative Paints. Avoiding excessive inhalation of a solvent vapours.
•
When rubbing down, our operatives will avoid the inhalation of dust by wearing a FFP2
Face mask: wet flatting when ever possible.
•
Paint will be applied via brushes and rollers via hand.
•
Short duration works at height will be carried out via a step ladder only when no other
safer means of work at height equipment is available, which will be maintained and
inspected by our competent sub-contractors on a daily basis, our supervisors will inspect
the work at height equipment supplied by M J Stevens on a weekly basis.
•
All flammable substances will be stored as specified by the manufacturer and the
COSHH assessment sheet produced by M J Stevens.
Personal Protective Equipment
Every self-employed person shall ensure that any personal protective equipment provided to
him is maintained (including replaced or cleaned as appropriate) in an efficient state, in
efficient working order and in good repair - (Extract from the Personal Protective Equipment
at Work Regulations).
•
•
•
Every operative is to ensure that they have received adequate training with regards to the
use of any particular item of Personal Protective Equipment.
Self employed persons are to ensure they purchase and maintain PPE in line with the
relevant risk assessments
Employed persons are to ensure they look after and use any PPE provided for them and
report any defects etc to their supervisor immediately.
© M J Stevens Group
•
2 of 3
MJSM14
If other trades are working within the property they must be advised of the work activities
that are about to commence.
Method of work
•
The works will take place according to the programme set out by the Principal Contractor.
Our operatives will undertake painting tasks as requested on the site order.
•
The operatives must read and understand the COSHH assessment for the products
being used.
•
Materials will be delivered to site via the supplier or in the Sub-contractors van; deliveries
will be delivered as close to the work area as physically possible to avoid excessive
manual handling activities.
•
Materials are to be loaded into the property via hand; no material used is in excess of
25kg.
•
Protective clothing is to be worn by operatives during the application process.
•
External painting applications will be carried out off of the principle contractors
scaffolding, at no time will work be carried out off of ladders, unless prior permission has
been gained from the principle contractor and there is no other safer practicable means
available, only short duration (under 15 minutes) work will be carried out in this way at
any time. Only 1 handed work will be carried out in this way.
•
Site operatives are to ensure that the Principle Contractor has inspected the scaffold
structure in line with the requirements set out in the Work at Height Regulations 2005.
The basics are to be checked by the operative prior to starting work i.e. that proper
access is available, handrails are in place, no missing boards etc.
•
All scaffolds are to be adapted to allow for the application of paint from a stable working
platform, no standing on trestle platforms or stepladders etc placed on the scaffold to
gain extra height is permitted.
•
All materials are to be lifted to the work area by forklift via a loading bay under no
circumstances are MJ Stevens operatives to carry materials up a ladder.
•
When working internally our operatives will ensure adequate local ventilation when
applying Decorative Paints. Avoiding excessive inhalation of a solvent vapours.
•
When rubbing down, our operatives will avoid the inhalation of dust by wearing a FFP2
Face mask: wet flatting when ever possible.
•
Paint will be applied via brushes and rollers via hand.
•
Short duration works at height will be carried out via a step ladder only when no other
safer means of work at height equipment is available, which will be maintained and
inspected by our competent sub-contractors on a daily basis, our supervisors will inspect
the work at height equipment supplied by M J Stevens on a weekly basis.
•
All flammable substances will be stored as specified by the manufacturer and the
COSHH assessment sheet produced by M J Stevens.
Personal Protective Equipment
Every self-employed person shall ensure that any personal protective equipment provided to
him is maintained (including replaced or cleaned as appropriate) in an efficient state, in
efficient working order and in good repair - (Extract from the Personal Protective Equipment
at Work Regulations).
•
•
•
Every operative is to ensure that they have received adequate training with regards to the
use of any particular item of Personal Protective Equipment.
Self employed persons are to ensure they purchase and maintain PPE in line with the
relevant risk assessments
Employed persons are to ensure they look after and use any PPE provided for them and
report any defects etc to their supervisor immediately.
© M J Stevens Group
2 of 3
MJSM14
Welfare
Welfare Facilities
F a c ilitie s
Op
eratives will
w ill u
se tthe
he w
elfa
are fa
a c ilitie s p
rovided by tthe
he P
rinciple C
ontractor tto
o iinclude
nclude ttoilet
oilet
Operatives
use
welfare
facilities
provided
Principle
Contractor
fa
cilities a
nd M
ess C
anteen, th
e ccanteen
anteen fa
cilities w
ill b
e u
sed fo
eal b
re a k s a
nd n
o
facilities
and
Mess
Canteen,
the
facilities
will
be
used
forr a
allll m
meal
breaks
and
no
ea, on any ot
her par
br
eaks w
ill be hel
d iin
n tthe
he w
ork ar
he ssite
ite nor iin
n vvehicles
ehicles ((Private
Private or
breaks
will
held
work
area,
other
partt of tthe
company owned)
ow ned)
company
On Completion
Completion of
of Works
W o rk s
Al
o rk a
n a cclean
lean ccondition
re a s a
re tto
ob
e lleft
efftt iin
o n d it i o n a
nd a
s p e ct s o
a fe ty w
ith rregards
egards tto
o tthe
he
Alll w
work
areas
are
be
and
allll a
aspects
off ssafety
with
im
mediate w
o rk a
re a a
nd conduct
conduct a visual
visual inspection
inspection b
y tthe
he operative
operative to
to ensure
ensure tthat
hat tthe
he
immediate
work
area
and
by
edge pr
otection iis
s iin
n pl
ace and tthat
hat tthere
here iis
s no rrisk
isk tto
o iinjury
njury tto
o tthemselves
hemselves or ot
hers as a
protection
place
others
di
rect rresult
esult of a ffall
all ffrom
rom that
that area.
area.
direct
En
sure all
al l o
th e r m
a te r ia l w
hich is u
our w
ork is sstored
nd p
ro p e r m
anner
sed ffor
or yyour
tored iin
n a ssafe
afe
ea
Ensure
other
material
which
used
work
and
proper
manner
bef
ore depar
ting ffrom
rom the
the pr
operty yyou
ou ar
ew
orking iin.
n.
before
departing
property
are
working
o the
th e S
ite M
anagement T
eam on ccompletion
ompletion of tthe
he w
orks and iiff rrequired
Re
port tto
equired by tthe
he ssite
ite
Report
Site
Management
Team
works
e a v in g
ut b
efo
ore lleaving
ru
les ssign
ig n o
rules
out
before
NA
ME
NAME
DA
TE
DATE
An
dy W
h ite
Andy
White
01/11/2009
RE
REVIEW
VIEW DA
DATE
TE
01/04/2015
SI
SIGNATURE
GNATURE
MBA
MBA Safety
Safety & Training
T ra in in g
Ltd
Lt
d
JO
B T IT L E
JOBTITLE
He
a lt h a
nd safety
safety Co
Health
and
Consultant
n s u lta n t
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Park
Tonedal
e Business
Business P
a rk
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
© M J Stevens
Stevens Group
Group
3 of 3
MJSM14
MJSM14
M
Welfare
Welfare Facilities
F a c ilitie s
Op
e r a t iv e s w
ill u
se tthe
he w
elfa
are fa
a c ilitie s p
rovided by tthe
he P
rinciple C
ontractor tto
o iinclude
nclude ttoilet
oilet
Operatives
will
use
welfare
facilities
provided
Principle
Contractor
fa
cilities a
nd M
ess C
anteen, th
e ccanteen
anteen fa
cilities w
ill b
e u
sed fo
eal b
re a k s a
nd n
o
facilities
and
Mess
Canteen,
the
facilities
will
be
used
forr a
allll m
meal
breaks
and
no
ea, on any ot
her par
br
eaks w
ill be hel
d iin
n tthe
he w
ork ar
he ssite
ite nor iin
n vvehicles
ehicles ((Private
Private or
breaks
will
held
work
area,
other
partt of tthe
company owned)
ow ned)
company
On Completion
Completion of
of Works
W o rk s
Al
o rk a
n a cclean
lean ccondition
re a s a
re tto
ob
e lleft
efftt iin
o n d it i o n a
nd a
s p e ct s o
a fe ty w
ith rregards
egards tto
o tthe
he
Alll w
work
areas
are
be
and
allll a
aspects
off ssafety
with
im
mediate w
o rk a
re a a
nd conduct
conduct a visual
visual inspection
inspection b
y tthe
he operative
operative to
to ensure
ensure tthat
hat tthe
he
immediate
work
area
and
by
edge pr
otection iis
s iin
n pl
ace and tthat
hat tthere
here iis
s no rrisk
isk tto
o iinjury
njury tto
o tthemselves
hemselves or ot
hers as a
protection
place
others
di
rect rresult
esult of a ffall
all ffrom
rom that
that area.
area.
direct
En
sure all
al l o
th e r m
a te r ia l w
hich is u
our w
ork is sstored
nd p
ro p e r m
anner
sed ffor
or yyour
tored iin
n a ssafe
afe
ea
Ensure
other
material
which
used
work
and
proper
manner
bef
ore depar
ting ffrom
rom the
the pr
operty yyou
ou ar
ew
orking iin.
n.
before
departing
property
are
working
o the
th e S
ite M
anagement T
eam on ccompletion
ompletion of tthe
he w
orks and iiff rrequired
Re
port tto
equired by tthe
he ssite
ite
Report
Site
Management
Team
works
e a v in g
ut b
efo
ore lleaving
ru
les ssign
ig n o
rules
out
before
NA
ME
NAME
DA
TE
DATE
An
dy W
h ite
Andy
White
01/11/2009
RE
REVIEW
VIEW DA
DATE
TE
01/11/2011
01/11
/2011
SI
SIGNATURE
GNATURE
MBA
MBA Safety
Safety & Training
T ra in in g
Ltd
Lt
d
JO
B T IT L E
JOBTITLE
He
a lt h a
nd s
afety Co
Health
and
safety
Consultant
n s u lta n t
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Park
Tonedal
e Business
Business P
a rk
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
© M J Stevens
Stevens Group
Group
3 of 3
MJSM14
MJSM14
M
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference
Number:
MJSM15
Area Assessed:
Site location: Operatives Handbook
Description:
Coving
Operatives Involved:
Site based operatives
WORK ACTIVITY:
Installation of decorative coving products
To be read in conjunction with the company’s Generic Risk
Assessments & Method statements
MJSRa01
MJSRa02
MJSRa10
MJSRa11
MJSRa12
MJSRa13
MJSRa14
MJSRa15
Working at Height
Manual Handling
Breathing in dust particles
Materials Delivery
Materials / Objects falling from height
Mobile scaffold towers and platforms
Ladders and step ladders
Working off stilts
Also To be read in conjunction with the following method statement
MJSM01
MJSM02
Arrival on site
Working in the area of Stairwells
Method of work (General precautions)
• The operatives must read and understand the COSHH assessment for the products
being used prior to commencing the installation.
• The work area, namely the room where the Coving is to be applied must be free of other
trades working in the immediate area.
• All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing.
• If other trades are working within the property they must be advised as to the work
activities you are about to commence.
• To enable operatives to gain access to the working surface of the underside of existing
ceilings a purposely constructed Heavy Duty Plastic Step is to be used no other
improvised or make shift equipment shall be used, such as milk crates, beer crates,
kitchen stools, chairs or home made hop-ups.
• Adequate lighting is to be provided by the Principle Contactor for the various activities
that will be conducted in the work area.
• Operatives engaged in cutting, sawing, or breaking the coving must use the correct (PPE)
and (RPE) required Personal Protective Equipment and Respiratory Protective
Equipment.
Positioning Coving
© M J Stevens Group
1 of 2
MJSM15
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference
Number:
MJSM15
Area Assessed:
Site location: Operatives Handbook
Description:
Coving
Operatives Involved:
Site based operatives
WORK ACTIVITY:
Installation of decorative coving products
To be read in conjunction with the company’s Generic Risk
Assessments & Method statements
MJSRa01
MJSRa02
MJSRa10
MJSRa11
MJSRa12
MJSRa13
MJSRa14
MJSRa15
Working at Height
Manual Handling
Breathing in dust particles
Materials Delivery
Materials / Objects falling from height
Mobile scaffold towers and platforms
Ladders and step ladders
Working off stilts
Also To be read in conjunction with the following method statement
MJSM01
MJSM02
Arrival on site
Working in the area of Stairwells
Method of work (General precautions)
• The operatives must read and understand the COSHH assessment for the products
being used prior to commencing the installation.
• The work area, namely the room where the Coving is to be applied must be free of other
trades working in the immediate area.
• All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing.
• If other trades are working within the property they must be advised as to the work
activities you are about to commence.
• To enable operatives to gain access to the working surface of the underside of existing
ceilings a purposely constructed Heavy Duty Plastic Step is to be used no other
improvised or make shift equipment shall be used, such as milk crates, beer crates,
kitchen stools, chairs or home made hop-ups.
• Adequate lighting is to be provided by the Principle Contactor for the various activities
that will be conducted in the work area.
• Operatives engaged in cutting, sawing, or breaking the coving must use the correct (PPE)
and (RPE) required Personal Protective Equipment and Respiratory Protective
Equipment.
Positioning Coving
© M J Stevens Group
1 of 2
MJSM15
Op
Operatives
e r a t iv e s a
are
re rrequired
equired tto
op
prepare
repare tthe
he Co
Coving
ving iin
n rreadiness
eadiness tto
oa
apply
pply tto
o tthe
he u
underside
n d e r s id e o
off the
the
he ssize
ize of
of tthe
ve sshould
hould b
a n d le d b
y tthe
he ffixing
ix in g o
ceiling;
ceiling; tthe
he Co
Cove
be
e ssuch
uch tthat
hat iitt iis
s e
easily
a s ily h
handled
by
operative
p e r a tiv e
he coving
coving w
ith tthe
he assistance
assistance ffrom
e c e s s a ry ) e
nsuring tthe
and p
position
osition tthe
with
ro m a p
prop
rop ((Wherever
W h ere v e r n
necessary)
ensuring
he
n th
e cchosen
hosen p
osition w
ip .
cove
cove remains
remains iin
the
position
whilst
hilst th
the
e adhes
adhesive
ive ttakes
akes gr
grip.
Ensure
Ensure tthe
he ssafe
afe
e use
use of any hand ttools
ools ii.e.
.e. S
Stanley
Knives
ensure
ure di
discarded
scarded kknife
tanley K
nives and ens
nife
blades
blades ar
are
e di
disposed
sposed of iin
n tthe
he ccorrect
orrect m
manner.
anner.
a te r ia ls a
nd
After th
un u s e d m
• After
the
e ccoving
oving iis
s ccompleted,
ompleted, the
the complete
complete area
area is
is to
to be
be cleared
c le a r e d o
off unused
materials
and
waste p
waste
products.
r o d u c ts .
he
re a p
r o v id e d b
emoved rrubbish
ubbish / debris
debris is
is tto
k ip s / a
The rremoved
• The
ob
be
ed
deposited
eposited iin
n tthe
he w
waste
aste sskips
area
provided
byy tthe
o n tra c to r.
Principle C
Principle
Contractor.
otective Equipment
Equipment
Personal Pr
Personal
Protective
o
otective equi
pment pr
ovided tto
elf-employed per
son sshall
hall ens
Every
person
ensure
ure tthat
hat any per
personal
sonal pr
protective
equipment
provided
Every sself-employed
n
opriate) iin
n an eff
ficient sstate,
tate, iin
aintained ((including
including rreplaced
eplaced or ccleaned
him
maintained
leaned as appr
appropriate)
efficient
hi
m iiss m
eff
ficient w
r o te c tiv e E
q u ip m e n t a
orking or
der and iin
n good rrepair
epair - ((Extract
Extract ffrom
rom tthe
he P
er s o n a l P
efficient
working
order
Personal
Protective
Equipment
att
Work Regulations).
R e g u la t io n s ) .
Work
• Every
perative iis
s tto
oe
nsure tthat
hat tthey
hey h
ave rreceived
e c e iv e d a
dequate ttraining
r a in in g w
ith rregards
egards tto
o tthe
he
Every o
operative
ensure
have
adequate
with
use o
ny p
articular iitem
tem of
of Personal
P er s o n a l P
rotective E
quipment.
use
off a
any
particular
Protective
Equipment.
he
• Self
Self e
m p lo y e d p
e rs o n s a
re tto
o e
nsure tthey
hey p
u rc h a s e a
nd m
aintain PPE iin
n lline
in e w
ith tthe
employed
persons
are
ensure
purchase
and
maintain
with
relevant ri
sk a
s s e s s m e n ts
relevant
risk
assessments
nd
hey llook
ook after
a fte r a
ny PPE p
rovided fo
or tthem
Employed p
ersons are
are tto
o ensure
ensure tthey
nd u
se a
hem a
• Employed
persons
and
use
any
provided
for
and
mmediately.
repor
port any defects
defects etc
etc to
to their
their supervisor
supervisor iimmediately.
report
Welfare Facilities
F a c ilitie s
Welfare
•
o ile t
r o v id e d b
y tthe
he P
r in c ip le C
ontractor tto
o iinclude
nclude ttoilet
Operatives
will
use
welfare
provided
by
Principle
Contractor
Operatives w
ill u
se tthe
he w
elfare ffacilities
a c ilitie s p
o
anteen fa
cilities w
ill b
e u
sed fo
eal b
reaks and
and n
facilities
and
Mess
Canteen,
the
facilities
will
be
used
forr a
allll m
meal
breaks
no
fa
cilities a
nd M
ess C
anteen, th
e ccanteen
ea, on any ot
her par
he ssite
ite nor iin
n vvehicles
ehicles ((Private
Private or
breaks
will
held
work
area,
other
partt of tthe
breaks w
ill be hel
d iin
n tthe
he w
ork ar
company owned)
ow ned)
company
Completion of
of Works
W o rk s
On Completion
re a s a
re tto
ob
e lleft
eftt iin
o n d itio n a
nd a
s p e c ts o
afe
ety w
ith rregards
egards tto
o tthe
he
Alll w
work
areas
are
be
n a cclean
lean ccondition
and
allll a
aspects
off ssafety
with
Al
o rk a
o rk a
rea a
nd cconduct
onduct a vvisual
isual iinspection
n s p e c tio n b
y tthe
he o
perative tto
oe
nsure tthat
hat tthe
he e
dge
immediate
work
area
and
by
operative
ensure
edge
im
mediate w
here iis
s no rrisk
isk tto
o iinjury
njurryy tto
s iin
n pl
ace and tthat
hat tthere
o tthemselves
hemselves or ot
hers as a di
rect
protection
place
others
direct
pr
otection iis
fa
all ffrom
rom tthat
hat area.
area.
result
off a fall
re
s u lt o
our w
Ensure
allll o
other
material
which
used
sed fo
for
or yyour
work
ork iis
s sstored
tored iin
n a ssafe
afe
e and pr
proper
manner
oper m
anner
th e r m
a te r ia l w
hich iis
su
En
s u re a
before
departing
property
ou ar
are
ew
working
orking iin.
n.
ting ffrom
rom tthe
he pr
operty yyou
bef
ore depar
Re
Report
port tto
Site
Management
Team
on
off tthe
works
and
by
eam o
n ccompletion
o m p le tio n o
he wo
rk s a
nd iiff rrequired
e q u ir e d b
y tthe
he ssite
ite
o tthe
he S
ite M
anagem ent T
ut b
efo
ore lleaving.
ru
rules
les ssign
ig n o
out
before
e a v in g .
NA
ME
NAME
An
dy W
h ite
Andy
White
DA
DATE
TE 01/11/2009
01/11/2009
RE
VIEW DATE
DATE
REVIEW
01/04/2015
SI
GNATURE
SIGNATURE
MB
MBA
A Safety
S a fe ty & T
Training
r a in in g L
Ltd
td
JO
JOBTITLE
B T IT L E
He
Health
a lt h a
and
nd safety
safety Co
Consultant
n s u lta n t
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
©MJS
Stevens
tevens Group
Group
2 of 2
MJSM15
MJSM15
Op
Operatives
e r a t iv e s a
are
re rrequired
equired tto
op
prepare
repare tthe
he Co
Coving
ving iin
n rreadiness
eadiness tto
oa
apply
pply tto
o tthe
he u
underside
n d e r s id e o
off th
the
e
he ssize
ize of
of tthe
ve sshould
hould b
a n d le d b
y tthe
he ffixing
ix in g o
ceiling;
ceiling; tthe
he Co
Cove
be
e ssuch
uch tthat
hat iitt iis
s e
easily
a s ily h
handled
by
operative
p e r a t iv e
he coving
coving w
ith tthe
he assistance
assistance ffrom
e c e s s a ry ) e
nsuring tthe
and p
position
osition tthe
with
ro m a p
prop
rop ((Wherever
W h ere v e r n
necessary)
ensuring
he
n th
e cchosen
hosen p
osition w
ip .
cove
cove remains
remains iin
the
position
whilst
hilst th
the
e adhes
adhesive
ive ttakes
akes gr
grip.
Ensure
Ensure tthe
he ssafe
afe
e use
use of any hand ttools
ools ii.e.
.e. S
Stanley
Knives
ensure
ure di
discarded
scarded kknife
tanley K
nives and ens
nife
blades
blades ar
are
e di
disposed
sposed of iin
n tthe
he ccorrect
orrect m
manner.
anner.
nused m
a te r ia ls a
nd
After th
• After
the
e ccoving
oving iis
s ccompleted,
ompleted, the
the complete
complete area
area is
is to
to be
be cleared
c le a r e d o
off u
unused
materials
and
wa
waste
s te p
products.
r o d u c ts .
he
re a p
r o v id e d b
y tthe
emoved rrubbish
ubbish / debris
debris iis
k ip s / a
The rremoved
s tto
ob
ed
eposited iin
n tthe
he w
aste sskips
• The
be
deposited
waste
area
provided
by
o n tra c to r.
Principle C
Principle
Contractor.
otective Equipment
Equipment
Pe
rsonal Pr
Personal
Protective
o
otective equi
pment pr
ovided tto
elf-employed per
son sshall
hall ens
Every
person
ensure
ure tthat
hat any per
personal
sonal pr
protective
equipment
provided
Every sself-employed
n
opriate) iin
n an eff
ficient sstate,
tate, iin
aintained ((including
including rreplaced
eplaced or ccleaned
him
maintained
leaned as appr
appropriate)
efficient
hi
m iiss m
eff
ficient w
r o te c tiv e E
q u ip m e n t a
orking or
der and iin
n good rrepair
epair - ((Extract
Extract ffrom
rom tthe
he P
er s o n a l P
efficient
working
order
Personal
Protective
Equipment
att
Work Regulations).
R e g u la t io n s ) .
Work
• Every
perative iis
s tto
oe
nsure tthat
hat tthey
hey h
ave rreceived
e c e iv e d a
dequate ttraining
r a in in g w
ith rregards
egards tto
o tthe
he
Every o
operative
ensure
have
adequate
with
use o
ny p
articular iitem
tem of
of Personal
P er s o n a l P
rotective E
quipment.
use
off a
any
particular
Protective
Equipment.
he
• Self
Self e
m p lo y e d p
e rs o n s a
re tto
o e
nsure tthey
hey p
u rc h a s e a
nd m
aintain PPE iin
n lline
in e w
ith tthe
employed
persons
are
ensure
purchase
and
maintain
with
relevant ri
sk a
s s e s s m e n ts
relevant
risk
assessments
nd
hey llook
ook a
fte r a
ny PPE p
rovided fo
or tthem
Employed p
e rs o n s a
re tto
oe
nsure tthey
nd u
se a
hem a
• Employed
persons
are
ensure
after
and
use
any
provided
for
and
mmediately.
repor
port any defects
defects etc
etc to
to their
their supervisor
supervisor iimmediately.
report
Welfare Facilities
F a c ilitie s
Welfare
•
o ile t
r o v id e d b
y tthe
he P
r in c ip le C
ontractor tto
o iinclude
nclude ttoilet
Operatives
will
use
welfare
provided
by
Principle
Contractor
Operatives w
ill u
se tthe
he w
elfare ffacilities
a c ilitie s p
o
anteen fa
cilities w
ill b
e u
sed fo
eal b
reaks and
and n
facilities
and
Mess
Canteen,
the
facilities
will
be
used
forr a
allll m
meal
breaks
no
fa
cilities a
nd M
ess C
anteen, th
e ccanteen
ea, on any ot
her par
he ssite
ite nor iin
n vvehicles
ehicles ((Private
Private or
breaks
will
held
work
area,
other
partt of tthe
breaks w
ill be hel
d iin
n tthe
he w
ork ar
company owned)
ow ned)
company
Completion of
of Works
W o rk s
On Completion
re a s a
re tto
ob
e lleft
eftt iin
o n d itio n a
nd a
s p e c ts o
afe
ety w
ith rregards
egards tto
o tthe
he
Alll w
work
areas
are
be
n a cclean
lean ccondition
and
allll a
aspects
off ssafety
with
Al
o rk a
o rk a
rea a
nd cconduct
onduct a vvisual
isual iinspection
n s p e c tio n b
y tthe
he o
perative tto
oe
nsure tthat
hat tthe
he e
dge
immediate
work
area
and
by
operative
ensure
edge
im
mediate w
here iis
s no rrisk
isk tto
o iinjury
njurryy tto
s iin
n pl
ace and tthat
hat tthere
o tthemselves
hemselves or ot
hers as a di
rect
protection
place
others
direct
pr
otection iis
fa
all ffrom
rom tthat
hat area.
area.
result
off a fall
re
s u lt o
our w
Ensure
allll o
other
material
which
used
sed fo
for
or yyour
work
ork iis
s sstored
tored iin
n a ssafe
afe
e and pr
proper
manner
oper m
anner
th e r m
a te r ia l w
hich iis
su
En
s u re a
before
departing
property
ou ar
are
ew
working
orking iin.
n.
ting ffrom
rom tthe
he pr
operty yyou
bef
ore depar
Re
Report
port tto
Site
Management
Team
on
off tthe
works
and
by
eam o
n ccompletion
o m p le tio n o
he wo
rk s a
nd iiff rrequired
e q u ir e d b
y tthe
he ssite
ite
o tthe
he S
ite M
anagem ent T
ut b
efo
ore lleaving.
ru
rules
les ssign
ig n o
out
before
e a v in g .
NA
ME
NAME
An
dy W
h ite
Andy
White
DA
DATE
TE 01/11/2009
01/11/2009
RE
VIEW DATE
DATE
REVIEW
01/
01/11/2011
11/2011
SI
GNATURE
SIGNATURE
MB
MBA
A Safety
S a fe ty & T
Training
r a in in g L
Ltd
td
JO
JOBTITLE
B T IT L E
He
Health
a lt h a
and
nd s
safety
afety Co
Consultant
n s u lta n t
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
© M J Stevens
Stevens Group
Group
2 of 2
MJSM15
MJSM15
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference
Number:
Area Assessed:
Site locations: Operatives Handbook
MJSM16
Description:
Textured Ceilings
Operatives Involved:
Site based operatives
WORK ACTIVITY:
Application of Textured ceiling products
To be read in conjunction with the company’s Generic Risk
Assessments
MJSRa01
MJSRa02
MJSRa03
MJSRa10
MJSRa11
MJSRa12
MJSRa13
MJSRa14
Working at Height
Manual Handling
Noise
Breathing in dust particles
Materials Delivery
Materials / Objects falling from height
Mobile scaffold towers and platforms
Ladders and step ladders
Also To be read in conjunction with the following method statement
MJSM02
Working in the area of Stairwells
The Work Area (General Precautions)
•
The work area is to be free of other trades, visitors and site staff.
•
All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing.
•
Good access is to be provided by the principal contractor with full height access through
scaffold etc.
•
If other trades are working within the property they must be advised of the work activities
that are about to commence.
© M J Stevens Group
1 of 3
MJSM16
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference
Number:
Area Assessed:
Site locations: Operatives Handbook
MJSM16
Description:
Textured Ceilings
Operatives Involved:
Site based operatives
WORK ACTIVITY:
Application of Textured ceiling products
To be read in conjunction with the company’s Generic Risk
Assessments
MJSRa01
MJSRa02
MJSRa03
MJSRa10
MJSRa11
MJSRa12
MJSRa13
MJSRa14
Working at Height
Manual Handling
Noise
Breathing in dust particles
Materials Delivery
Materials / Objects falling from height
Mobile scaffold towers and platforms
Ladders and step ladders
Also To be read in conjunction with the following method statement
MJSM02
Working in the area of Stairwells
The Work Area (General Precautions)
•
The work area is to be free of other trades, visitors and site staff.
•
All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing.
•
Good access is to be provided by the principal contractor with full height access through
scaffold etc.
•
If other trades are working within the property they must be advised of the work activities
that are about to commence.
© M J Stevens Group
1 of 3
MJSM16
Method of work
•
To enable operatives to gain access to the working surface of the underside of existing
ceilings a purposely constructed Heavy Duty Plastic Step is to be used no other
improvised or make shift equipment shall be used, such as milk crates, beer crates,
kitchen stools, chairs or home made hop-ups.
•
Adequate lighting is to be provided by the Principle Contactor for the various activities
that will be conducted in the work area.
•
Operatives using the handheld mixer are to be trained in its use and competent (training
will be carried out in house) operatives who are new to the equipment are to be
supervised at all times.
•
The equipment, and all other associated paraphernalia is to be inspected by the foremen
prior to each shift.
•
The operatives must have read and understood the COSHH assessment for the product
being used.
•
Materials are to be delivered to site via the supplier or sub-contractor carrying out the
application, deliveries to be off loaded as close to the work area as possible to minimise
manual handling activities.
•
Materials are to be carried into the plot via hand, one bag at a time using good manual
handling techniques (training will be carried out in house).
•
Safety glasses are to be worn by the operatives carrying out the mixing operation and
any other operatives in the immediate area.
•
All controls to be kept clean and clearly labelled to prevent unintended start-up
•
All handheld mixers are to be fitted with a proprietary emergency stop.
•
Protective clothing is to be worn by operatives during the application process to avoid
contact with the skin.
•
Electrical safety to be tested by a competent person at 3 month intervals.
•
PAT labels will be on view and in date on all electrical equipment.
•
The textured product will be applied to the ceiling via hand trowel.
Personal Protective Equipment
Every self-employed person shall ensure that any personal protective equipment provided to
him is maintained (including replaced or cleaned as appropriate) in an efficient state, in
efficient working order and in good repair - (Extract from the Personal Protective Equipment
at Work Regulations).
•
•
•
Every operative is to ensure that they have received adequate training with regards to the
use of any particular item of Personal Protective Equipment.
Self employed persons are to ensure they purchase and maintain PPE in line with the
relevant risk assessments
Employed persons are to ensure they look after and use any PPE provided for them and
report any defects etc to their supervisor immediately.
Welfare Facilities
Operatives will use the welfare facilities provided by the Principle Contractor to include toilet
facilities and Mess Canteen, the canteen facilities will be used for all meal breaks and no
breaks will be held in the work area, on any other part of the site nor in vehicles (Private or
company owned)
© M J Stevens Group
2 of 3
MJSM16
Method of work
•
To enable operatives to gain access to the working surface of the underside of existing
ceilings a purposely constructed Heavy Duty Plastic Step is to be used no other
improvised or make shift equipment shall be used, such as milk crates, beer crates,
kitchen stools, chairs or home made hop-ups.
•
Adequate lighting is to be provided by the Principle Contactor for the various activities
that will be conducted in the work area.
•
Operatives using the handheld mixer are to be trained in its use and competent (training
will be carried out in house) operatives who are new to the equipment are to be
supervised at all times.
•
The equipment, and all other associated paraphernalia is to be inspected by the foremen
prior to each shift.
•
The operatives must have read and understood the COSHH assessment for the product
being used.
•
Materials are to be delivered to site via the supplier or sub-contractor carrying out the
application, deliveries to be off loaded as close to the work area as possible to minimise
manual handling activities.
•
Materials are to be carried into the plot via hand, one bag at a time using good manual
handling techniques (training will be carried out in house).
•
Safety glasses are to be worn by the operatives carrying out the mixing operation and
any other operatives in the immediate area.
•
All controls to be kept clean and clearly labelled to prevent unintended start-up
•
All handheld mixers are to be fitted with a proprietary emergency stop.
•
Protective clothing is to be worn by operatives during the application process to avoid
contact with the skin.
•
Electrical safety to be tested by a competent person at 3 month intervals.
•
PAT labels will be on view and in date on all electrical equipment.
•
The textured product will be applied to the ceiling via hand trowel.
Personal Protective Equipment
Every self-employed person shall ensure that any personal protective equipment provided to
him is maintained (including replaced or cleaned as appropriate) in an efficient state, in
efficient working order and in good repair - (Extract from the Personal Protective Equipment
at Work Regulations).
•
•
•
Every operative is to ensure that they have received adequate training with regards to the
use of any particular item of Personal Protective Equipment.
Self employed persons are to ensure they purchase and maintain PPE in line with the
relevant risk assessments
Employed persons are to ensure they look after and use any PPE provided for them and
report any defects etc to their supervisor immediately.
Welfare Facilities
Operatives will use the welfare facilities provided by the Principle Contractor to include toilet
facilities and Mess Canteen, the canteen facilities will be used for all meal breaks and no
breaks will be held in the work area, on any other part of the site nor in vehicles (Private or
company owned)
© M J Stevens Group
2 of 3
MJSM16
On Completion
Completion of
of Works
W o rk s
Al
o rk a
re a s a
re tto
o be
be lleft
n a clean
clean ccondition
eftt iin
ondition and al
pects of ssafety
afety w
ith rregards
egards tto
o tthe
he
Alll w
work
areas
are
alll as
aspects
with
im
mediate w
o rk a
re a a
nd conduct
conduct a visual
visual inspection
inspection b
y tthe
he operative
operative to
to ensure
ensure tthat
hat tthe
he
immediate
work
area
and
by
edge pr
otection iis
s iin
n pl
ace and tthat
hat tthere
here iis
s no rrisk
isk tto
o iinjury
njury tto
o tthemselves
hemselves or ot
hers as a
protection
place
others
direct result
result of
of a fall
fall from
from that
that area.
area.
direct
En
sure all
al l o
th e r m
a te r ia l w
hich is u
our w
ork is sstored
nd p
ro p e r m
anner
sed ffor
or yyour
tored iin
n a ssafe
afe
ea
Ensure
other
material
which
used
work
and
proper
manner
before depar
ting ffrom
rom tthe
he pr
operty yyou
ou ar
ew
orking iin.
n.
before
departing
property
are
working
Re
port tto
o tthe
he S
ite M
anagem ent T
ite
eam o
n ccompletion
o m p le tio n o
he wo
rks and iiff required
required by the
the ssite
Report
Site
Management
Team
on
off tthe
works
ut b
efo
ore lleaving
ru
les ssign
ig n o
e a v in g
rules
out
before
NAME
NA
ME
DATE
DATE
An
Andy
dy W
White
h ite
01/11/2009
01/11
/2009
RE
REVIEW
VIEW DA
DATE
TE
01/04/2015
SIGNATURE
SIGNATURE
MBA
MBA Safety
Safety & Training
T ra in in g
Lt
Ltd
d
JO
JOBTITLE
B T IT L E
He
Health
a lt h a
and
nd s
safety
afety Co
Consultant
n s u lta n t
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
668527
© M J Stevens
Stevens Group
Group
3 of 3
MJSM16
MJSM16
M
On Completion
Completion of
of Works
W o rk s
Al
o rk a
re a s a
re tto
o be
be lleft
n a clean
clean ccondition
eftt iin
ondition and al
pects of ssafety
afety w
ith rregards
egards tto
o tthe
he
Alll w
work
areas
are
alll as
aspects
with
im
mediate w
o rk a
re a a
nd conduct
conduct a visual
visual inspection
inspection b
y tthe
he operative
operative to
to ensure
ensure tthat
hat tthe
he
immediate
work
area
and
by
edge pr
otection iis
s iin
n pl
ace and tthat
hat tthere
here iis
s no rrisk
isk tto
o iinjury
njury tto
o tthemselves
hemselves or ot
hers as a
protection
place
others
direct result
result of
of a fall
fall from
from that
that area.
area.
direct
En
sure all
al l o
th e r m
a te r ia l w
hich is u
our w
ork is sstored
nd p
ro p e r m
anner
sed ffor
or yyour
tored iin
n a ssafe
afe
ea
Ensure
other
material
which
used
work
and
proper
manner
before depar
ting ffrom
rom tthe
he pr
operty yyou
ou ar
ew
orking iin.
n.
before
departing
property
are
working
Re
port tto
o tthe
he S
ite M
anagem ent T
ite
eam o
n ccompletion
o m p le tio n o
he wo
rks and iiff required
required by the
the ssite
Report
Site
Management
Team
on
off tthe
works
ut b
efo
ore lleaving
ru
les ssign
ig n o
e a v in g
rules
out
before
NAME
NA
ME
DATE
DATE
An
Andy
dy W
White
h ite
01/11/2009
01/11
/2009
RE
REVIEW
VIEW DA
DATE
TE
01/11/2011
01/11
/2011
SIGNATURE
SIGNATURE
MBA
MBA Safety
Safety & Training
T ra in in g
Ltd
Lt
d
JO
JOBTITLE
B T IT L E
He
Health
a lt h a
and
nd s
safety
afety Co
Consultant
n s u lta n t
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
668527
© M J Stevens
Stevens Group
Group
3 of 3
MJSM16
MJSM16
M
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference
Number:
MJSM17
Area Assessed:
Site locations: Operatives Handbook
Description:
Installation of attic Trusses
Operatives Identified:
Site based operatives
WORK ACTIVITY:
Installation of Attic Roof Trusses
To be read in conjunction with the company’s Generic Risk
Assessments
MJSRa01
MJSRa02
MJSRa03
MJSRa04
MJSRa08
MJSRa09
MJSRa11
MJSRa12
MJSRa14
MJSRa17
Working at Height
Manual Handling
Noise
Vibration
Power tools
Electrocution
Materials Delivery
Materials / Objects falling from height
Ladders and step ladders
Roof truss installation
The Work Area & Work at Height
•
The work area (the wall plate level scaffold), the area beneath and the inside of the
plot are to be free of other trades, visitors and site staff.
•
All debris, rubbish & trip hazards are to be removed from the work area prior to the
work commencing in particular the scaffold working platform.
•
Site operatives are to ensure that the Principle Contractor has inspected the scaffold
structure in line with the requirements set out in the Work at Height Regulations
2005. The basics are to be checked by the operative prior to starting work i.e. that
proper access is available, handrails are in place, no missing boards etc.
•
If other trades are working within the property they must be advised of the work
activities that are about to commence.
•
To reduce the risk to injury from the direct results of a fall from height (i.e. when
placing the roof trusses) ensure that adequate protection is given against a fall from
within the building,
the Principle Contractor must provided a suitable fall
prevention/arrest/mitigation system, this can be provided in one of three ways, these
being: soft landing bean bag or air bag systems installed by competent persons in line
with the manufacturers instructions and training or a birdcage scaffold erected by a
© M J Stevens Group
1 of 3
MJSM17
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference
Number:
MJSM17
Area Assessed:
Site locations: Operatives Handbook
Description:
Installation of attic Trusses
Operatives Identified:
Site based operatives
WORK ACTIVITY:
Installation of Attic Roof Trusses
To be read in conjunction with the company’s Generic Risk
Assessments
MJSRa01
MJSRa02
MJSRa03
MJSRa04
MJSRa08
MJSRa09
MJSRa11
MJSRa12
MJSRa14
MJSRa17
Working at Height
Manual Handling
Noise
Vibration
Power tools
Electrocution
Materials Delivery
Materials / Objects falling from height
Ladders and step ladders
Roof truss installation
The Work Area & Work at Height
•
The work area (the wall plate level scaffold), the area beneath and the inside of the
plot are to be free of other trades, visitors and site staff.
•
All debris, rubbish & trip hazards are to be removed from the work area prior to the
work commencing in particular the scaffold working platform.
•
Site operatives are to ensure that the Principle Contractor has inspected the scaffold
structure in line with the requirements set out in the Work at Height Regulations
2005. The basics are to be checked by the operative prior to starting work i.e. that
proper access is available, handrails are in place, no missing boards etc.
•
If other trades are working within the property they must be advised of the work
activities that are about to commence.
•
To reduce the risk to injury from the direct results of a fall from height (i.e. when
placing the roof trusses) ensure that adequate protection is given against a fall from
within the building,
the Principle Contractor must provided a suitable fall
prevention/arrest/mitigation system, this can be provided in one of three ways, these
being: soft landing bean bag or air bag systems installed by competent persons in line
with the manufacturers instructions and training or a birdcage scaffold erected by a
© M J Stevens Group
1 of 3
MJSM17
specialist contractor. The physical safety precautions for work at height are the
responsibility of the principal contractor but operatives must ensure these things are in
place prior to starting work.
Placement of trusses
•
The Roof Trusses will be the responsibility of the principal contractor until they are placed
on the wall plate by mechanical means. The lifting operations used to achieve this are
not under the control of MJ Stevens. The principal contractor will arrange lifting
appliances, lifting plan, slingers, signallers etc. Using mechanical means in this way will
drastically reduce the manual handling operations required to complete the task.
•
When installing the Roof Trusses it is possible that the operatives may be required to
stand on the truss edge or at the wall plate position, this could cause the operative to be
above the level of the edge protection on the scaffold. It may therefore be necessary for
additional guard rails to be constructed to protect the operative against the risks to falls.
If this is the case a competent scaffolder is to make the alterations (arranged by the
principal contractor).
•
All operatives will be trained in the installation of Roof Trusses and hold CSCS cards
•
The removed rubbish / debris is to be deposited in the waste skips / area provided by the
Principle Contractor no throwing or dropping of materials or waste from height is
permitted.
•
The Principal contractor is to make arrangements for materials and tools to be delivered
to the scaffold via a loading bay, hoist or similar Do Not carry any tools or materials up or
down ladders.
•
If there is any doubt over safety precautions at the location or if weather conditions are
safe to continue the supervisor is to be contacted immediately.
•
The truss roof will be installed in the following sequence:
1. Before you start work ensure: fall protection is in place, scaffold is erected to the correct
height, access to and from the work area is safe, all PPE and equipment required is on
site and in good condition, the method of work is understood, you have been inducted
and you are aware of the site procedures for fire etc and the right personnel are on site to
complete the work safely
2. When on the scaffold stand well clear while the trusses are guided into position and do
not attempt to lift them into place manually.
3. The first truss will be lifted into place, aligned and then fixed using battens to the scaffold
structure
4. With two operatives one on each side of the roof, working together and starting at one
side, walk the trusses into the correct position for fixing one at a time and secured to the
previous one ensuring the structure remains solid at all times. Fix using a nail gun (if you
have been trained to use one) or a hammer & nails.
5. Wind bracing is to be installed as the roof progresses.
6. When it is time to access the inside of the truss structure, ensure a good platform is
placed on the trusses to provide a good footing DO NOT walk on the trusses themselves.
7. When all the trusses are in place the battens holding the end trusses are then to be
removed.
8. Trim off the trusses if required and make any other final adjustments needed.
9. The flooring is then to be fixed into position, beginning at a convenient corner of the plot
the first board will be fixed into place. This will then serve as a solid working platform for
the next. Each board will then be placed, glued and nailed into place following the same
precautions until the floor is complete. Ensure that the fall protection is still in place until
the floor is complete and the stair opening protected.
10. If a “top hat” is top be fitted to the structure this must be lifted into place by mechanical
means following the same procedure as for the main trusses.
11. When accessing the top of the roof structure to secure top hats a solid working platform
is required to gain access (Step ladders are not acceptable).
12. Stud work sections and finishing of the roof structure can then take place from a safe
working platform
© M J Stevens Group
2 of 3
MJSM17
specialist contractor. The physical safety precautions for work at height are the
responsibility of the principal contractor but operatives must ensure these things are in
place prior to starting work.
Placement of trusses
•
The Roof Trusses will be the responsibility of the principal contractor until they are placed
on the wall plate by mechanical means. The lifting operations used to achieve this are
not under the control of MJ Stevens. The principal contractor will arrange lifting
appliances, lifting plan, slingers, signallers etc. Using mechanical means in this way will
drastically reduce the manual handling operations required to complete the task.
•
When installing the Roof Trusses it is possible that the operatives may be required to
stand on the truss edge or at the wall plate position, this could cause the operative to be
above the level of the edge protection on the scaffold. It may therefore be necessary for
additional guard rails to be constructed to protect the operative against the risks to falls.
If this is the case a competent scaffolder is to make the alterations (arranged by the
principal contractor).
•
All operatives will be trained in the installation of Roof Trusses and hold CSCS cards
•
The removed rubbish / debris is to be deposited in the waste skips / area provided by the
Principle Contractor no throwing or dropping of materials or waste from height is
permitted.
•
The Principal contractor is to make arrangements for materials and tools to be delivered
to the scaffold via a loading bay, hoist or similar Do Not carry any tools or materials up or
down ladders.
•
If there is any doubt over safety precautions at the location or if weather conditions are
safe to continue the supervisor is to be contacted immediately.
•
The truss roof will be installed in the following sequence:
1. Before you start work ensure: fall protection is in place, scaffold is erected to the correct
height, access to and from the work area is safe, all PPE and equipment required is on
site and in good condition, the method of work is understood, you have been inducted
and you are aware of the site procedures for fire etc and the right personnel are on site to
complete the work safely
2. When on the scaffold stand well clear while the trusses are guided into position and do
not attempt to lift them into place manually.
3. The first truss will be lifted into place, aligned and then fixed using battens to the scaffold
structure
4. With two operatives one on each side of the roof, working together and starting at one
side, walk the trusses into the correct position for fixing one at a time and secured to the
previous one ensuring the structure remains solid at all times. Fix using a nail gun (if you
have been trained to use one) or a hammer & nails.
5. Wind bracing is to be installed as the roof progresses.
6. When it is time to access the inside of the truss structure, ensure a good platform is
placed on the trusses to provide a good footing DO NOT walk on the trusses themselves.
7. When all the trusses are in place the battens holding the end trusses are then to be
removed.
8. Trim off the trusses if required and make any other final adjustments needed.
9. The flooring is then to be fixed into position, beginning at a convenient corner of the plot
the first board will be fixed into place. This will then serve as a solid working platform for
the next. Each board will then be placed, glued and nailed into place following the same
precautions until the floor is complete. Ensure that the fall protection is still in place until
the floor is complete and the stair opening protected.
10. If a “top hat” is top be fitted to the structure this must be lifted into place by mechanical
means following the same procedure as for the main trusses.
11. When accessing the top of the roof structure to secure top hats a solid working platform
is required to gain access (Step ladders are not acceptable).
12. Stud work sections and finishing of the roof structure can then take place from a safe
working platform
© M J Stevens Group
2 of 3
MJSM17
13. Operatives
Oper
peratives m
must
ust ensure
ensure that
that a handr
handrail
ail iis
s iin
n pl
place
ace at tthe
he edge of tthe
he fflooring
looring ttop
op pr
prevent
event
eft bet
ffalls
alls tthrough
hrough tthe
he gap nor
normally
mally lleft
between
ween tthe
he edge of tthe
he ffloor
loor and tthe
he w
wall.
all.
he w
o rk a
rea iis
s left
leftt in
le a n a
nd ttidy
idy ccondition
ondition fo
or tthe
14. Ensure
Ensure tthe
work
area
in a cclean
and
for
he n
next
ext ttrade.
ra d e .
o t e c t iv e E
quipment
Pe
rsonal Pr
Personal
Protective
Equipment
Ev
ery sself-employed
elf-employed per
son sshall
hall ens
ure tthat
hat any per
sonal pr
otective equi
pment pr
ovided tto
o
Every
person
ensure
personal
protective
equipment
provided
effficient sstate,
hi
m iis
s m
aintained ((including
including rreplaced
eplaced or ccleaned
leaned a
appropriate) in an efficient
tate, in
in
him
maintained
ass appropriate)
eff
ficient w
Protective Eq
u ip m e n t
orking order
order and iin
n good rrepair
epair - (Extract
(Extract from
from tthe
he Personal
Personal Protective
efficient
working
Equipment
at W
ork Regulations).
Regulations).
Work
•
•
•
Every operative
operative is
is to
to ensure
ensure that
that they
t r a in in g w
ith rregards
egards tto
o tthe
they have
have received
r e c e iv e d a
dequate training
he
Every
adequate
with
use of any par
ticular iitem
tem of P
ersonal P
rotective E
quipment.
use
particular
Personal
Protective
Equipment.
Self e
m p lo y e d p
e rs o n s a
re tto
o e
he
aintain PPE in line
line with
with tthe
nsure tthey
hey p
u rc h a s e a
nd m
Self
employed
persons
are
ensure
purchase
and
maintain
relevant ri
sk a
s s e s s m e n ts
relevant
risk
assessments
hey llook
ook a
f te r a
nd use
use any P
PE pr
ovided fo
or tthem
Employed p
e rs o n s a
re tto
oe
nsure tthey
hem and
Employed
persons
are
ensure
after
and
PPE
provided
for
report a
ny d
efe
e c ts e
tc to
to their
their ssupervisor
upervisor iimmediately.
m m e d ia te ly .
report
any
defects
etc
Welfare Facilities
F a c ilitie s
Welfare
Op
e r a t iv e s w
Operatives
will
use
welfare
facilities
provided
by
Principle
Contractor
include
ill u
se tthe
he w
elfa
are fa
a c il i t i e s p
ontractor tto
o in
clude ttoilet
oilet
rovided b
y the
th e P
rinciple C
fa
cilities a
facilities
and
Mess
Canteen,
the
facilities
will
be
used
forr a
allll m
meal
breaks
and
no
nd M
ess C
anteen, th
e ccanteen
eal b
re a k s a
nd n
o
anteen fa
cilities w
ill b
e u
sed fo
ea, on any ot
her par
br
eaks w
breaks
will
held
work
area,
other
partt of tthe
ill be hel
d iin
n tthe
he w
ork ar
ite nor iin
n vvehicles
ehicles ((Private
Private or
he ssite
company owned)
company
ow ned)
Completion of
of Works
Works
On Completion
Al
o rk a
re a s a
re tto
ob
e lleft
efftt iin
n a cclean
lean ccondition
o n d it i o n a
nd a
s p e ct s o
a fe ty w
ith rregards
egards tto
o tthe
he
Alll w
work
areas
are
be
and
allll a
aspects
off ssafety
with
im
mediate w
o rk a
re a a
nd conduct
conduct a vvisual
isual inspection
inspection by
by the
th e o
perative tto
o e
nsure tthat
hat tthe
he
immediate
work
area
and
operative
ensure
edge pr
otection iis
s iin
n pl
ace and tthat
hat tthere
here iiss no rrisk
isk tto
o injury
injury tto
o tthemselves
hemselves or ot
hers as a
protection
place
others
di
rect rresult
esult of a ffall
all ffrom
rom that
that area.
area.
direct
sed ffor
or yyour
ork is sstored
tored iin
n a ssafe
afe
ea
En
sure all
al l o
th e r m
a te r ia l w
hich is u
o ur w
nd p
ro p e r m
anner
Ensure
other
material
which
used
work
and
proper
manner
ou ar
ew
orking iin.
n.
bef
ore depar
ting ffrom
rom the
the property
property yyou
before
departing
are
working
n ccompletion
ompletion o
ew
o rk s a
nd iiff rrequired
e q u ir e d b
y th
e ssite
Re
port to
to th
eS
ite M
anagement Team
Te a m o
ite
Report
the
Site
Management
on
off th
the
works
and
by
the
ut b
efo
ore lleaving.
ru
les ssign
ig n o
e a v in g .
rules
out
before
NA
NAME
ME
An
Andy
dy W
White
h ite
DA
DATE
TE 01/11
01/11/2009
/2009
REVIEW
RE
VIEW DATE
DATE
01/04/2015
SIGNATURE
SIGNATURE
MB
MBA
AS
Safety
a f et y & T
Training
r a in in g L
Ltd
td
JO
JOBTITLE
B T IT L E
He
Health
a lt h a
and
nd safety
safety Co
Consultant
n s u lta n t
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
© M J Stevens
Stevens Group
Group
3 of 3
MJSM17
MJSM17
13. Operatives
Oper
peratives m
must
ust ens
ensure
ure tthat
hat a handr
handrail
ail iis
s iin
n pl
place
ace at tthe
he edge of tthe
he fflooring
looring ttop
op pr
prevent
event
eft bet
ffalls
alls tthrough
hrough tthe
he gap nor
normally
mally lleft
between
ween tthe
he edge of tthe
he ffloor
loor and tthe
he w
wall.
all.
sure tthe
he w
o rk a
rea iis
s lleft
eftt in
le a n a
nd ttidy
idy ccondition
ondition fo
or tthe
14. En
Ensure
work
area
in a cclean
and
for
he n
next
ext ttrade.
ra d e .
o t e c t iv e E
quipment
Pe
rsonal Pr
Personal
Protective
Equipment
Ev
ery sself-employed
elf-employed per
son sshall
hall ens
ure tthat
hat any per
sonal pr
otective equi
pment pr
ovided tto
o
Every
person
ensure
personal
protective
equipment
provided
effficient sstate,
hi
m iis
s m
aintained ((including
including rreplaced
eplaced or ccleaned
leaned a
appropriate) in an efficient
tate, in
in
him
maintained
ass appropriate)
eff
ficient w
Protective Eq
u ip m e n t
orking order
order and iin
n good rrepair
epair - (Extract
(Extract from
from tthe
he Personal
Personal Protective
efficient
working
Equipment
at W
ork Regulations).
Regulations).
Work
•
•
•
Every operative
operative is
is to
to ensure
ensure that
that they
t r a in in g w
ith rregards
egards tto
o tthe
they have
have received
r e c e iv e d a
dequate training
he
Every
adequate
with
use of any par
ticular iitem
tem of P
ersonal P
rotective E
quipment.
use
particular
Personal
Protective
Equipment.
Self e
m p lo y e d p
e rs o n s a
re tto
o e
he
aintain PPE in line
line with
with tthe
nsure tthey
hey p
u rc h a s e a
nd m
Self
employed
persons
are
ensure
purchase
and
maintain
relevant ri
sk a
s s e s s m e n ts
relevant
risk
assessments
hey llook
ook a
f te r a
nd use
use any P
PE pr
ovided fo
or tthem
hem and
Employed p
e rs o n s a
re tto
oe
nsure tthey
Employed
persons
are
ensure
after
and
PPE
provided
for
report a
ny d
efe
e c ts e
tc to
to their
their ssupervisor
upervisor iimmediately.
m m e d ia te ly .
report
any
defects
etc
Welfare Facilities
F a c ilitie s
Welfare
Op
e r a t iv e s w
Operatives
will
use
welfare
facilities
provided
by
Principle
Contractor
include
ill u
se tthe
he w
elfa
are fa
a c il i t i e s p
ontractor tto
o in
clude ttoilet
oilet
rovided b
y the
th e P
rinciple C
fa
cilities a
facilities
and
Mess
Canteen,
the
facilities
will
be
used
forr a
allll m
meal
breaks
and
no
nd M
ess C
anteen, th
e ccanteen
eal b
re a k s a
nd n
o
anteen fa
cilities w
ill b
e u
sed fo
ea, on any ot
her par
br
eaks w
breaks
will
held
work
area,
other
partt of tthe
ill be hel
d iin
n tthe
he w
ork ar
ite nor iin
n vvehicles
ehicles ((Private
Private or
he ssite
company owned)
company
ow ned)
Completion of
of Works
Works
On Completion
Al
o rk a
re a s a
re tto
ob
e lleft
efftt iin
n a cclean
lean ccondition
o n d it i o n a
nd a
s p e ct s o
a fe ty w
ith rregards
egards tto
o tthe
he
Alll w
work
areas
are
be
and
allll a
aspects
off ssafety
with
im
mediate w
o rk a
re a a
nd conduct
conduct a vvisual
isual inspection
inspection by
by the
th e o
perative tto
o e
nsure tthat
hat tthe
he
immediate
work
area
and
operative
ensure
edge pr
otection iis
s iin
n pl
ace and tthat
hat tthere
here iiss no rrisk
isk tto
o injury
injury tto
o tthemselves
hemselves or ot
hers as a
protection
place
others
di
rect rresult
esult of a ffall
all ffrom
rom that
that area.
area.
direct
sed ffor
or yyour
ork is sstored
tored iin
n a ssafe
afe
ea
En
sure all
al l o
th e r m
a te r ia l w
hich is u
o ur w
nd p
ro p e r m
anner
Ensure
other
material
which
used
work
and
proper
manner
ou ar
ew
orking iin.
n.
bef
ore depar
ting ffrom
rom the
the property
property yyou
before
departing
are
working
n ccompletion
ompletion o
ew
o rk s a
nd iiff rrequired
e q u ir e d b
y th
e ssite
Re
port to
to th
eS
ite M
anagement Team
Te a m o
ite
Report
the
Site
Management
on
off th
the
works
and
by
the
ut b
efo
ore lleaving.
ru
les ssign
ig n o
e a v in g .
rules
out
before
NA
NAME
ME
An
Andy
dy W
White
h ite
DA
DATE
TE 01/11
01/11/2009
/2009
REVIEW
RE
VIEW DATE
DATE
01/11/2011
01/11
/2011
SIGNATURE
SIGNATURE
MB
MBA
A Safety
S a f et y & T
Training
r a in in g L
Ltd
td
JO
JOBTITLE
B T IT L E
He
Health
a lt h a
and
nd s
safety
afety Co
Consultant
n s u lta n t
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
© M J Stevens
Stevens Group
Group
3 of 3
MJSM17
MJSM17
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference
Number:
Area Assessed:
Site locations: Operatives Handbook
MJSM18
Description:
Timber frame erection
Operatives Involved:
Site based operatives
WORK ACTIVITY:
TIMBER FRAME ERECTION
To be read in conjunction with the company’s Generic Risk
Assessments & Method statements
MJSRa01
MJSRa02
MJSRa03
MJSRa04
MJSRa08
MJSRa09
MJSRa11
MJSRa12
MJSRa13
MJSRa14
MJSM01
Working at Height
Manual Handling
Noise
Vibration
Power tools
Electrocution
Materials Delivery
Materials / Objects falling from height
Mobile scaffold towers and platforms
Ladders and step ladders
Arrival on site
The Work Area (General Precautions)
•
The work area is to be free of other trades, visitors and site staff.
•
All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing.
•
Good access is to be provided by the principal contractor with full height access through
scaffold etc.
Timber Frame Erection
1. Lifting Operations
The appointed person (provided by the principle contractor) will have carried out a site survey
prior to our operatives commencing any works to confirm the site conditions and future crane
requirements. This survey will be viewed by our site erection team prior to any works
commencing. Document to include the following:
•
•
The types of loads planned to be lifted, their size & weight.
The position of the loads to be lifted in relation to the location of each work areas.
M J Stevens Ltd
M J Stevens Contracting Division
Method Statement
Method Statement Reference
Number:
Area Assessed:
Site locations: Operatives Handbook
MJSM18
Description:
Timber frame erection
Operatives Involved:
Site based operatives
WORK ACTIVITY:
TIMBER FRAME ERECTION
To be read in conjunction with the company’s Generic Risk
Assessments & Method statements
MJSRa01
MJSRa02
MJSRa03
MJSRa04
MJSRa08
MJSRa09
MJSRa11
MJSRa12
MJSRa13
MJSRa14
MJSM01
Working at Height
Manual Handling
Noise
Vibration
Power tools
Electrocution
Materials Delivery
Materials / Objects falling from height
Mobile scaffold towers and platforms
Ladders and step ladders
Arrival on site
The Work Area (General Precautions)
•
The work area is to be free of other trades, visitors and site staff.
•
All debris, rubbish & trip hazards are to be removed from the work area prior to the work
commencing.
•
Good access is to be provided by the principal contractor with full height access through
scaffold etc.
Timber Frame Erection
1. Lifting Operations
The appointed person (provided by the principle contractor) will have carried out a site survey
prior to our operatives commencing any works to confirm the site conditions and future crane
requirements. This survey will be viewed by our site erection team prior to any works
commencing. Document to include the following:
•
•
The types of loads planned to be lifted, their size & weight.
The position of the loads to be lifted in relation to the location of each work areas.
•
•
•
•
The Slingers/Signallers requirements in order to plan the safest system of work.
The on-site crane’s position in relation to the safe working length of the cranes boom and
each load to be lifted.
The site’s ground conditions, locations of services, external factors.
Access to and around the site and the individual plots.
The initial survey will be reviewed throughout the project and revised as necessary if
conditions change following consultation and approval of the appointed person.
The lift supervisor (provided by the principle contractor) will inspect documentation relating to
the maintenance and operation of the crane, including all test and thorough examination
certificates, before any lifting operations commence.
All involved in lifting operations will wear high visibility clothing. An orange high visibility jacket
will identify the Slingers/Signallers.
Items to Be Lifted
Wall Panels = manufactured internal and external wall panels up to a maximum size of 7
metres long by 2.5 metres high weighing a maximum of 1000 kgs (1 tonne) each.
Timber Beams & Structural Steelwork = Supplied floor or roof supporting sections not
exceeding a maximum weight of 1000kgs (1 tonne) each.
Floor Cassettes = manufactured floor cassettes up to a maximum size of 13.6 metres long
by 2.5 metres wide and 400mm deep, weighing a maximum of 1500 kgs (1.5 tonne) each.
Bay Window Panels = manufactured wall units incorporating glazed bay windows up to a
maximum size of 3 metres wide by 2.5 metres high weighing a maximum of 1000 kgs (1
tonne) each.
Under NO circumstances can any other item of equipment be lifted without prior
authorisation from the Lifting Supervisor or Appointed Person.
2. Crane Set Up
The crane will be driven onto the site and manoeuvred into the operating position detailed on
the crane layout drawing. The crane will then be set up in accordance with the crane
manufacturer’s manual, during which time the Principal Contractor will ensure that all noninvolved personnel are kept out of the assembly work area.
Access to the blind side of the crane will not be permitted at any time. Temporary barriers will
be positioned by the principle contractor to the whole lift area to prevent unauthorised access.
If the situation arises where an entrapment area of less than 600mm cannot be avoided, then
the potential entrapment area shall be fenced off to totally prevent access to that area.
3. Adverse Weather Conditions
The Lifting Supervisor and Crane Operator (both provided by the principle contractor) will
monitor the weather conditions continuously to ensure that it is safe to continue lifting
operations. The wind speed at which the crane must cease operation is clearly stated in the
manufacturer’s manual and must not be exceeded. It is the combined decision of the Crane
Operator and the Lifting Supervisor if the work should be stopped below this limit due to local
circumstances.
Any storm in the distance must be monitored to decide if it may pose a threat within the
timeframe of the lifting operations. No lifting operations can continue when there is a
lightning storm in the vicinity.
If there is any risk of lightning in the vicinity, the crane operator must leave the crane after
applying the conditions detailed above.
•
•
•
•
The Slingers/Signallers requirements in order to plan the safest system of work.
The on-site crane’s position in relation to the safe working length of the cranes boom and
each load to be lifted.
The site’s ground conditions, locations of services, external factors.
Access to and around the site and the individual plots.
The initial survey will be reviewed throughout the project and revised as necessary if
conditions change following consultation and approval of the appointed person.
The lift supervisor (provided by the principle contractor) will inspect documentation relating to
the maintenance and operation of the crane, including all test and thorough examination
certificates, before any lifting operations commence.
All involved in lifting operations will wear high visibility clothing. An orange high visibility jacket
will identify the Slingers/Signallers.
Items to Be Lifted
Wall Panels = manufactured internal and external wall panels up to a maximum size of 7
metres long by 2.5 metres high weighing a maximum of 1000 kgs (1 tonne) each.
Timber Beams & Structural Steelwork = Supplied floor or roof supporting sections not
exceeding a maximum weight of 1000kgs (1 tonne) each.
Floor Cassettes = manufactured floor cassettes up to a maximum size of 13.6 metres long
by 2.5 metres wide and 400mm deep, weighing a maximum of 1500 kgs (1.5 tonne) each.
Bay Window Panels = manufactured wall units incorporating glazed bay windows up to a
maximum size of 3 metres wide by 2.5 metres high weighing a maximum of 1000 kgs (1
tonne) each.
Under NO circumstances can any other item of equipment be lifted without prior
authorisation from the Lifting Supervisor or Appointed Person.
2. Crane Set Up
The crane will be driven onto the site and manoeuvred into the operating position detailed on
the crane layout drawing. The crane will then be set up in accordance with the crane
manufacturer’s manual, during which time the Principal Contractor will ensure that all noninvolved personnel are kept out of the assembly work area.
Access to the blind side of the crane will not be permitted at any time. Temporary barriers will
be positioned by the principle contractor to the whole lift area to prevent unauthorised access.
If the situation arises where an entrapment area of less than 600mm cannot be avoided, then
the potential entrapment area shall be fenced off to totally prevent access to that area.
3. Adverse Weather Conditions
The Lifting Supervisor and Crane Operator (both provided by the principle contractor) will
monitor the weather conditions continuously to ensure that it is safe to continue lifting
operations. The wind speed at which the crane must cease operation is clearly stated in the
manufacturer’s manual and must not be exceeded. It is the combined decision of the Crane
Operator and the Lifting Supervisor if the work should be stopped below this limit due to local
circumstances.
Any storm in the distance must be monitored to decide if it may pose a threat within the
timeframe of the lifting operations. No lifting operations can continue when there is a
lightning storm in the vicinity.
If there is any risk of lightning in the vicinity, the crane operator must leave the crane after
applying the conditions detailed above.
A full, detailed lifting plan is to be prepared by the Appointed Person (provided by the
principle contractor) prior to any lift activity taking place, M J Stevens operatives will expect to
be briefed on the lifting plan by the principle contractor prior to commencing the construction
of the timber frame unit.
4. Foundation & Provision of Scaffolding
The Principal Contractor will be responsible for:
•
•
•
•
All ground works and foundations prepared and inspected by “others”.
Sectional roof constructed on ground floor foundation by “others”.
External freestanding scaffold structure erected to an approved design by others.
Provision and control of the lift via mechanical means.
ERECTING AND PLACING OF GROUND FLOOR WALL PANELS
5. Assembling & fixing ground floor wall panels
When scaffolding is to be used, the assembly of the wall panels will not commence until the
perimeter scaffold structure has been completed inspected and an entry made into the site
Scaffold Register by the Principal Contractor.
The principle contractor will have completed a “Pre-Assembly Safety Checklist” for the
specific plot/s and ensure full compliance, arranging necessary works to rectify any shortfalls
or concerns prior to our erection team commencing any work in those areas.
When a sectional roof has been constructed on the foundation, the roof sections must first be
lifted off the slab to a designated temporary storage area prior to our erection team
commencing any task. The foundation must be cleared and then visually inspected including
the condition of the perimeter DPC before any sealant is applied.
•
The thermally insulated external wall panels (approximate size 6.8 metres x 2.6 metres)
will first be selected and then lifted individually from the storage stillages and placed into
position on the foundation within the work area.
•
Suitable slings will be attached to the wall panels using a pair of NXR panel clamps (SWL
500kgs each).
•
Some external wall panels in the stillage are described as “multi-walls” and may consist
of two or more individual wall elements that must be cut before handling and fixing.
External “multiwall”panels are not to be lifted into the work area as a whole unit.
•
The Assembly Team will provide and use suitable ladders to enable them to reach the
top of panels in the stillage. Access is required to separate the multi-wall panels into
smaller units using handsaws and attach lifting equipment to each section. Panel
sections must be supported on blocks before
•
Cutting any timber plates to avoid panels becoming unstable and tipping on the
stillage bearers.
•
Panel lifting operations must not commence whilst operatives are standing between
panels in the storage stillage.
•
Guide ropes to be attached as per standard operation to assist in controlling the load
during lifting and handling over the scaffolding.
•
Whenever possible, the wall panels will be “walked” towards the work area at low level to
maintain maximum control and then raised to the appropriate floor level by lifting up and
over the scaffolding.
A full, detailed lifting plan is to be prepared by the Appointed Person (provided by the
principle contractor) prior to any lift activity taking place, M J Stevens operatives will expect to
be briefed on the lifting plan by the principle contractor prior to commencing the construction
of the timber frame unit.
4. Foundation & Provision of Scaffolding
The Principal Contractor will be responsible for:
•
•
•
•
All ground works and foundations prepared and inspected by “others”.
Sectional roof constructed on ground floor foundation by “others”.
External freestanding scaffold structure erected to an approved design by others.
Provision and control of the lift via mechanical means.
ERECTING AND PLACING OF GROUND FLOOR WALL PANELS
5. Assembling & fixing ground floor wall panels
When scaffolding is to be used, the assembly of the wall panels will not commence until the
perimeter scaffold structure has been completed inspected and an entry made into the site
Scaffold Register by the Principal Contractor.
The principle contractor will have completed a “Pre-Assembly Safety Checklist” for the
specific plot/s and ensure full compliance, arranging necessary works to rectify any shortfalls
or concerns prior to our erection team commencing any work in those areas.
When a sectional roof has been constructed on the foundation, the roof sections must first be
lifted off the slab to a designated temporary storage area prior to our erection team
commencing any task. The foundation must be cleared and then visually inspected including
the condition of the perimeter DPC before any sealant is applied.
•
The thermally insulated external wall panels (approximate size 6.8 metres x 2.6 metres)
will first be selected and then lifted individually from the storage stillages and placed into
position on the foundation within the work area.
•
Suitable slings will be attached to the wall panels using a pair of NXR panel clamps (SWL
500kgs each).
•
Some external wall panels in the stillage are described as “multi-walls” and may consist
of two or more individual wall elements that must be cut before handling and fixing.
External “multiwall”panels are not to be lifted into the work area as a whole unit.
•
The Assembly Team will provide and use suitable ladders to enable them to reach the
top of panels in the stillage. Access is required to separate the multi-wall panels into
smaller units using handsaws and attach lifting equipment to each section. Panel
sections must be supported on blocks before
•
Cutting any timber plates to avoid panels becoming unstable and tipping on the
stillage bearers.
•
Panel lifting operations must not commence whilst operatives are standing between
panels in the storage stillage.
•
Guide ropes to be attached as per standard operation to assist in controlling the load
during lifting and handling over the scaffolding.
•
Whenever possible, the wall panels will be “walked” towards the work area at low level to
maintain maximum control and then raised to the appropriate floor level by lifting up and
over the scaffolding.
•
The panels will be lifted sequentially into the work area and positioned using the crane
and lifting equipment provide. The assembly will commence at one corner of the
foundation and work away progressively from that point.
•
Using a cartridge applicator, sealant mastic will be applied by hand to the external DPC
and each vertical joint between external wall panels to create an effective seal.
•
Individual panels will be temporarily supported – until securely fixed – using adjustable
support braces placed between the ground floor slab and the top of the panel. When
more than one support is required they will be set at centres no more than 2.6 metres
around the perimeter.
•
External panels are secured and joined at vertical joints along the inside edge with screw
or nail fixings using power tools in accordance with Standard Operating Procedures.
•
The work will progress by systematically assembling and fixing adjacent external panels
and corners working across the foundation toward the access gap and incorporating
internal load bearing panels as scheduled.
•
The assembly will continue until all ground floors external walls are permanently
positioned and all internal load bearing walls have been installed and fixed to support the
floor cassettes.
•
From time to time the construction will be quality checked using tapes, line and squares
including:
o
o
o
Dimensional checks.
Walls – plumb & square.
Straightness of external walls.
•
If non-load bearing internal wall panels are supplied they may be loaded into the unit,
sorted and stored, to be fixed at a later stage. Wall panels adjoining stairwell areas can
be temporarily fixed to allow later adjustment to align through into upper floors through
the stair opening when the floor cassettes have been fitted.
•
When required by the house design, “pockets” are to be cut out on site (usually along the
top edge of the panels) at designated positions to receive timber or steel beams. The
beams will then be lifted into position using slings or chains and fixed in accordance with
the standard process operation.
•
Bay window units will normally be delivered on the same load as the floor cassettes and
comprise a prefabricated panel unit with the glazed window unit fitted.
The unit complete is to be lifted into position using the threaded lifting rods supplied. If
the rods are damaged, the units can be lifted alternatively by slinging through open
casements but care must be taken to avoid damage to the window frames and units.
•
On completion of the external ground floor structure, the shell will be secured by screw
fixings to pairs of steel restraining straps built into each corner of the foundation and
positioned as specified on the client’s foundation drawing.
•
All internal load bearing ground floor panels will be fixed to the foundation slab through
the bottom place using hammer fixings put into holes drilled with a percussion drill.
•
All external joints in the cement particleboard (wider than 3.0mm) around the outside of
the walls are to be sealed with mastic sealant using the cartridge gun.
6. Fitting Floor Cassettes
When all necessary panel work has been completed on the level below, work installing the
floor cassettes will commence. Each cassette can be lifted directly off the delivery lorry by
crane under the guidance of the Slingers/Signallers and onto the assembled ground floor or
second floor structure.
•
The panels will be lifted sequentially into the work area and positioned using the crane
and lifting equipment provide. The assembly will commence at one corner of the
foundation and work away progressively from that point.
•
Using a cartridge applicator, sealant mastic will be applied by hand to the external DPC
and each vertical joint between external wall panels to create an effective seal.
•
Individual panels will be temporarily supported – until securely fixed – using adjustable
support braces placed between the ground floor slab and the top of the panel. When
more than one support is required they will be set at centres no more than 2.6 metres
around the perimeter.
•
External panels are secured and joined at vertical joints along the inside edge with screw
or nail fixings using power tools in accordance with Standard Operating Procedures.
•
The work will progress by systematically assembling and fixing adjacent external panels
and corners working across the foundation toward the access gap and incorporating
internal load bearing panels as scheduled.
•
The assembly will continue until all ground floors external walls are permanently
positioned and all internal load bearing walls have been installed and fixed to support the
floor cassettes.
•
From time to time the construction will be quality checked using tapes, line and squares
including:
o
o
o
Dimensional checks.
Walls – plumb & square.
Straightness of external walls.
•
If non-load bearing internal wall panels are supplied they may be loaded into the unit,
sorted and stored, to be fixed at a later stage. Wall panels adjoining stairwell areas can
be temporarily fixed to allow later adjustment to align through into upper floors through
the stair opening when the floor cassettes have been fitted.
•
When required by the house design, “pockets” are to be cut out on site (usually along the
top edge of the panels) at designated positions to receive timber or steel beams. The
beams will then be lifted into position using slings or chains and fixed in accordance with
the standard process operation.
•
Bay window units will normally be delivered on the same load as the floor cassettes and
comprise a prefabricated panel unit with the glazed window unit fitted.
The unit complete is to be lifted into position using the threaded lifting rods supplied. If
the rods are damaged, the units can be lifted alternatively by slinging through open
casements but care must be taken to avoid damage to the window frames and units.
•
On completion of the external ground floor structure, the shell will be secured by screw
fixings to pairs of steel restraining straps built into each corner of the foundation and
positioned as specified on the client’s foundation drawing.
•
All internal load bearing ground floor panels will be fixed to the foundation slab through
the bottom place using hammer fixings put into holes drilled with a percussion drill.
•
All external joints in the cement particleboard (wider than 3.0mm) around the outside of
the walls are to be sealed with mastic sealant using the cartridge gun.
6. Fitting Floor Cassettes
When all necessary panel work has been completed on the level below, work installing the
floor cassettes will commence. Each cassette can be lifted directly off the delivery lorry by
crane under the guidance of the Slingers/Signallers and onto the assembled ground floor or
second floor structure.
During the unloading process it is necessary for a team member to climb onto the trailer to
attach the lifting device tongs to each of the cassettes. The lorry driver is to advise the correct
method of access using the appropriate step-up points on the trailer unit. If step-up points are
not available, then stepladders set alongside the trailer must be used.
Extreme care is required when moving around and working on the trailer deck.
To make the most stable load for road transportation, cassettes may not be stacked on the
trailer in the correct assembly sequence. It may be necessary to first unload a number of
cassettes from the lorry and temporarily “set them aside” on suitable ground to get access to
the required cassette. When necessary the Team Leader will advise the Site Manager/Agent
if the only available space falls outside the designated work area. Barriers or fencing will be
repositioned as necessary to restrict access during the lifting operations.
To reduce the risk of falling from unprotected edges during the installation and positioning of
the cassettes, team members are not normally required to step onto the floor deck before
completion of the full floor deck. The following section details the method that must be
followed to avoid having to step onto the floor until it is fully in position.
Assembling Floor Cassettes to Make Complete Floors
•
The assembly and fixing of all necessary supporting timber beams and/or steelwork must
be completed before installing the floor cassettes at each level. All hangers must be fully
fixed prior to being covered by the cassette floor deck.
•
Each floor cassette must be unloaded using the mobile crane and lifted to the work area,
keeping the load as low to ground level as possible. A minimum of two guide ropes must
be attached to each cassette to control the load at all times.
•
Suitable chains will be attached to each standard floor cassette usually at four points
using the purpose made equipment designed to be released from below.
•
The Team Leader must monitor the weather conditions throughout the operation.
•
The orientation of the floor cassette should be checked against its intended position of
the plot and, if necessary, turned at low level to “be the right way round” for fixing.
•
The Team Leader must ensure that a minimum of two team members retain contact with
the cassette at all times. The lift must be planned to allow the guide ropes to be
transferred from one operative on the ground to another on the scaffolding. The load
must never be tied to the scaffolding.
•
Operatives are not allowed to stand under the suspended load unless the cassette
is aligned with the wall panels close to its final position and within 300mm from the
top edge of the walls. Entry at this stage must be under the close supervision of the
Team Leader.
•
The wall plate or rim beam of the cassette is designed to be positioned on the top edge of
the top plate or head binder plate of the wall panel and to fit flush with the outside edges
of the cement particleboard on the external walls.
•
To avoid the risk of falling from unprotected edges as the assembly progresses,
whenever possible team members will position the cassettes using the attached guide
ropes whilst working from behind the scaffolding safety handrails around each lift. It is
not permitted to step onto the cassettes without firstly, edge protection barriers or
a “soft landing system” in place.
•
Team operatives can only enter the working area (to make any final adjustments and
make temporary screw fixings) by stepping onto the inner scaffolding boards inside the
handrail when all the cassettes are in such a position that they prevent a potential fall
onto the floor below. Entry at this stage must be under the supervision of the Team
Leader.
During the unloading process it is necessary for a team member to climb onto the trailer to
attach the lifting device tongs to each of the cassettes. The lorry driver is to advise the correct
method of access using the appropriate step-up points on the trailer unit. If step-up points are
not available, then stepladders set alongside the trailer must be used.
Extreme care is required when moving around and working on the trailer deck.
To make the most stable load for road transportation, cassettes may not be stacked on the
trailer in the correct assembly sequence. It may be necessary to first unload a number of
cassettes from the lorry and temporarily “set them aside” on suitable ground to get access to
the required cassette. When necessary the Team Leader will advise the Site Manager/Agent
if the only available space falls outside the designated work area. Barriers or fencing will be
repositioned as necessary to restrict access during the lifting operations.
To reduce the risk of falling from unprotected edges during the installation and positioning of
the cassettes, team members are not normally required to step onto the floor deck before
completion of the full floor deck. The following section details the method that must be
followed to avoid having to step onto the floor until it is fully in position.
Assembling Floor Cassettes to Make Complete Floors
•
The assembly and fixing of all necessary supporting timber beams and/or steelwork must
be completed before installing the floor cassettes at each level. All hangers must be fully
fixed prior to being covered by the cassette floor deck.
•
Each floor cassette must be unloaded using the mobile crane and lifted to the work area,
keeping the load as low to ground level as possible. A minimum of two guide ropes must
be attached to each cassette to control the load at all times.
•
Suitable chains will be attached to each standard floor cassette usually at four points
using the purpose made equipment designed to be released from below.
•
The Team Leader must monitor the weather conditions throughout the operation.
•
The orientation of the floor cassette should be checked against its intended position of
the plot and, if necessary, turned at low level to “be the right way round” for fixing.
•
The Team Leader must ensure that a minimum of two team members retain contact with
the cassette at all times. The lift must be planned to allow the guide ropes to be
transferred from one operative on the ground to another on the scaffolding. The load
must never be tied to the scaffolding.
•
Operatives are not allowed to stand under the suspended load unless the cassette
is aligned with the wall panels close to its final position and within 300mm from the
top edge of the walls. Entry at this stage must be under the close supervision of the
Team Leader.
•
The wall plate or rim beam of the cassette is designed to be positioned on the top edge of
the top plate or head binder plate of the wall panel and to fit flush with the outside edges
of the cement particleboard on the external walls.
•
To avoid the risk of falling from unprotected edges as the assembly progresses,
whenever possible team members will position the cassettes using the attached guide
ropes whilst working from behind the scaffolding safety handrails around each lift. It is
not permitted to step onto the cassettes without firstly, edge protection barriers or
a “soft landing system” in place.
•
Team operatives can only enter the working area (to make any final adjustments and
make temporary screw fixings) by stepping onto the inner scaffolding boards inside the
handrail when all the cassettes are in such a position that they prevent a potential fall
onto the floor below. Entry at this stage must be under the supervision of the Team
Leader.
•
Working on incomplete floors some floor designs now require that sections of flooring
are to be made and completed on site “traditionally” using loose joists and sheet decking
materials to infill areas of floor in between factory made floor cassettes.
•
In the event that a cassette collides “heavily” with the scaffolding structure whilst
suspended, the scaffolding must be checked by a competent person before
continuing.
•
One member of the assembly team will detach the lifting equipment from the underside of
each cassette using stepladders when necessary to avoid overreaching. Operatives
must not climb onto the cassettes.
•
If any lifting equipment becomes jammed, or the slings “snagged” and it is necessary to
stop onto a floor cassette to remove the lifting equipment from above, then fixed edge
protection or alternatively a “Soft Landing System” (bean bags or other approved system)
must be positioned under the leading edge(s) and installed according to the supplier’s
instructions.
•
Each step of the process is repeated for the remaining floor cassette sections working to
the fitting sequence.
•
Edge protection barriers and safety rails must be fitted around the stairwell and along all
unprotected edges using the posts and timber (provided by the Principal Contractor)
before the assembly progresses to the next level.
•
Fix and secure floor cassettes at each joint and around the perimeter by the method
detailed in the fixing schedule using screws or nails.
•
When specified on houses higher than two storeys, sockets for scaffolding restraints
must be prepared at designated points details on the site drawing. These must be made
in accordance with the Standard Operating procedures.
•
Preformed flashing or breather fabric must be cut to size, folded and fixed around all
external edges of the floor or rim beams to protect exposed timber & finish external
surfaces.
•
Temporary weather protection, using 500 gauge plastic (provided by the Principal
Contractor) or similar can be fixed along the edge of the floor cassettes above each
opening and trapped under the flashings at bays, chimneys, low level roofs to reduce
water ingress.
•
If the decision is made to suspend assembly work due to/or expected adverse weather
then whenever possible work should stop on completion of a floor, then a tarpaulin can
be fitted to protect the structure from the weather.
Working on Incomplete Floors, the Fixing of “Loose” Joists & Decking Between
Cassettes to Complete Sections of Flooring
•
A “Soft Landing System” (bean bags or other approved system) must be installed in
accordance with the manufacturers/suppliers installation instructions below the area
where the floor section is to be made and before any work at the higher level can start.
•
“Loose” materials will be delivered with the main floor cassette delivery and unloaded by
the Assembly Team using the crane.
•
Beams & joists will usually be supplied in “kits” cut to length and pre-fitted with hangers.
The materials shall be loaded onto completed floor cassettes only and stored temporarily
in small stacks until used. They must not be stacked on open joist work.
•
An installation drawing will be supplied detailing the work to be completed. If temporary
bracing of the joists or temporary “propping” of the floor is required the details will also be
included on the drawing and must be installed as shown.
•
Working on incomplete floors some floor designs now require that sections of flooring
are to be made and completed on site “traditionally” using loose joists and sheet decking
materials to infill areas of floor in between factory made floor cassettes.
•
In the event that a cassette collides “heavily” with the scaffolding structure whilst
suspended, the scaffolding must be checked by a competent person before
continuing.
•
One member of the assembly team will detach the lifting equipment from the underside of
each cassette using stepladders when necessary to avoid overreaching. Operatives
must not climb onto the cassettes.
•
If any lifting equipment becomes jammed, or the slings “snagged” and it is necessary to
stop onto a floor cassette to remove the lifting equipment from above, then fixed edge
protection or alternatively a “Soft Landing System” (bean bags or other approved system)
must be positioned under the leading edge(s) and installed according to the supplier’s
instructions.
•
Each step of the process is repeated for the remaining floor cassette sections working to
the fitting sequence.
•
Edge protection barriers and safety rails must be fitted around the stairwell and along all
unprotected edges using the posts and timber (provided by the Principal Contractor)
before the assembly progresses to the next level.
•
Fix and secure floor cassettes at each joint and around the perimeter by the method
detailed in the fixing schedule using screws or nails.
•
When specified on houses higher than two storeys, sockets for scaffolding restraints
must be prepared at designated points details on the site drawing. These must be made
in accordance with the Standard Operating procedures.
•
Preformed flashing or breather fabric must be cut to size, folded and fixed around all
external edges of the floor or rim beams to protect exposed timber & finish external
surfaces.
•
Temporary weather protection, using 500 gauge plastic (provided by the Principal
Contractor) or similar can be fixed along the edge of the floor cassettes above each
opening and trapped under the flashings at bays, chimneys, low level roofs to reduce
water ingress.
•
If the decision is made to suspend assembly work due to/or expected adverse weather
then whenever possible work should stop on completion of a floor, then a tarpaulin can
be fitted to protect the structure from the weather.
Working on Incomplete Floors, the Fixing of “Loose” Joists & Decking Between
Cassettes to Complete Sections of Flooring
•
A “Soft Landing System” (bean bags or other approved system) must be installed in
accordance with the manufacturers/suppliers installation instructions below the area
where the floor section is to be made and before any work at the higher level can start.
•
“Loose” materials will be delivered with the main floor cassette delivery and unloaded by
the Assembly Team using the crane.
•
Beams & joists will usually be supplied in “kits” cut to length and pre-fitted with hangers.
The materials shall be loaded onto completed floor cassettes only and stored temporarily
in small stacks until used. They must not be stacked on open joist work.
•
An installation drawing will be supplied detailing the work to be completed. If temporary
bracing of the joists or temporary “propping” of the floor is required the details will also be
included on the drawing and must be installed as shown.
•
Joists will firstly be set out and fixed to span across between cassettes and wall plate as
specified in the drawing.
•
By design, some floor joists will be supported at one end on the load bearing walls below.
It is most important that the maximum joist bearing on the wall below is achieved and that
specified blocking pieces must also be fitted to prevent the joists overturning.
•
All joist hangers, timber blocks, stiffeners and top noggins must be fully fixed prior to
fixing the sheet decking material - no-one is allowed to walk on or across the open
joist work.
•
Installation of the sheet decking will start from one edge only; each sheet will be fully
fixed to the joist beneath before anyone is allowed to stand or kneel on that sheet. Once
fixed, additional sheets can be carried over one by one to extend the floor area in front of
the “fixer” as per the installation drawing. As the floor extends, the fixer will move forward
onto each of the fixed sheets to reach the next.
•
When specified, safety decks supported on timber bearers must also be fitted inside the
stairwell opening and set at a height to obtain a flush finish with the surface of the main
floor area as shown on the floor assembly drawing.
•
Edge protection barriers and safety rails must be fixed around the stairwell and along all
unprotected edges using the posts and timber (provided by the Principal Contractor)
before the assembly progresses to the next level.
Handling & Slinging “Large Floor Cassettes”
Some individual floor cassettes exceeding 12 metres in length or weighing more than
500kgs (0.5 tonnes) are to be lifted and positioned by adopting an alternative lifting
method. Each cassette will be identified and is designed and manufactured with blocking
between the joists to enable the cassettes to be under slung at designated points using
“endless slings” secured with “D shackles”.
Under –Slinging & Unloading
•
The floor cassettes will be stacked on the lorry and despatched from the factory each
separated by timber bearers to allow the fitting of the slings at a later stage during the
unloading operation.
•
Four endless slings are to be used for each lift, arranged in two pairs and connected by
“D shackles” to make two large loops under each cassette (minimum rating 3000kgs
SWL). The equipment will be provided by the crane operator, must be tested, in good
condition and visually inspected (by the lift supervisor) before use.
•
A sling will be threaded through the gap under the cassette to be lifted from one side of
the lorry and connected to the second sling at the other side using a “D shackle” (If
necessary, a piece of timber can be used to assist pushing the loose sling through). The
pin of the shackle must be checked and secure before pulling the end of the sling back to
centralise the slings under the cassette.
•
The second pair of slings is to be set up in the same way as the first and each loop
positioned under the lifting points shown on the drawing and located by the joist blocking.
•
Guide ropes to be attached as per standard operation to assist in controlling the load
during lifting and handling over the scaffolding.
Temporary Positioning
•
Each cassette will be lifted into the work area using the crane under the instruction of the
Slingers/Signallers and set down onto the lower wall panels close to their required
position.
•
Joists will firstly be set out and fixed to span across between cassettes and wall plate as
specified in the drawing.
•
By design, some floor joists will be supported at one end on the load bearing walls below.
It is most important that the maximum joist bearing on the wall below is achieved and that
specified blocking pieces must also be fitted to prevent the joists overturning.
•
All joist hangers, timber blocks, stiffeners and top noggins must be fully fixed prior to
fixing the sheet decking material - no-one is allowed to walk on or across the open
joist work.
•
Installation of the sheet decking will start from one edge only; each sheet will be fully
fixed to the joist beneath before anyone is allowed to stand or kneel on that sheet. Once
fixed, additional sheets can be carried over one by one to extend the floor area in front of
the “fixer” as per the installation drawing. As the floor extends, the fixer will move forward
onto each of the fixed sheets to reach the next.
•
When specified, safety decks supported on timber bearers must also be fitted inside the
stairwell opening and set at a height to obtain a flush finish with the surface of the main
floor area as shown on the floor assembly drawing.
•
Edge protection barriers and safety rails must be fixed around the stairwell and along all
unprotected edges using the posts and timber (provided by the Principal Contractor)
before the assembly progresses to the next level.
Handling & Slinging “Large Floor Cassettes”
Some individual floor cassettes exceeding 12 metres in length or weighing more than
500kgs (0.5 tonnes) are to be lifted and positioned by adopting an alternative lifting
method. Each cassette will be identified and is designed and manufactured with blocking
between the joists to enable the cassettes to be under slung at designated points using
“endless slings” secured with “D shackles”.
Under –Slinging & Unloading
•
The floor cassettes will be stacked on the lorry and despatched from the factory each
separated by timber bearers to allow the fitting of the slings at a later stage during the
unloading operation.
•
Four endless slings are to be used for each lift, arranged in two pairs and connected by
“D shackles” to make two large loops under each cassette (minimum rating 3000kgs
SWL). The equipment will be provided by the crane operator, must be tested, in good
condition and visually inspected (by the lift supervisor) before use.
•
A sling will be threaded through the gap under the cassette to be lifted from one side of
the lorry and connected to the second sling at the other side using a “D shackle” (If
necessary, a piece of timber can be used to assist pushing the loose sling through). The
pin of the shackle must be checked and secure before pulling the end of the sling back to
centralise the slings under the cassette.
•
The second pair of slings is to be set up in the same way as the first and each loop
positioned under the lifting points shown on the drawing and located by the joist blocking.
•
Guide ropes to be attached as per standard operation to assist in controlling the load
during lifting and handling over the scaffolding.
Temporary Positioning
•
Each cassette will be lifted into the work area using the crane under the instruction of the
Slingers/Signallers and set down onto the lower wall panels close to their required
position.
•
When the Team Leader is satisfied with the position of the cassette, then the slings can
be detached from under the load by detaching the shackles and lifting the slings away.
•
The next cassette in the sequence will be positioned with a stand off from the first
cassette leaving a gap no greater than 150mm to allow the slings to be removed.
•
This sequence is repeated until the last floor cassette is in position. The last cassette
must be set down temporarily onto timber blocks placed along the edge of the lower wall
panels to support the floor and allow the slings to be removed (the blocks will be removed
later).
Final Fixing
•
When all the cassettes are in their approximate positions, there will be no edges to allow
someone to fall from height.
•
Under the supervision of the Team Leader, Team Members can work from inside the
scaffolding handrail to make the necessary fixings.
•
The support blocks will be taken out from under the cassette that was lifted last, so that
all cassettes are level on the top wall plate of the panel.
•
Each cassette can then be levered into its final position according to the floor deck layout
also closing all minor gaps between cassettes.
•
Screw and nail fixings are completed to the specification before progressing to the next
level of wall panels.
7. Erecting and Placing of Wall Panels above Ground Floor Level
Panels on upper levels will be assembled and fixed in the same way as detailed in the
ground floor method (item 5) with the following additional measures:
•
Appropriate fall arrest protection must be used and any necessary barriers fixed to guard
all open edges. When open panel frames have been fitted in upper internal rooms
adjacent to stairwells then timber rails must be fixed horizontally, the main guard rail must
be at a height of at least 950 mm to prevent anybody falling into the stairwell.
•
Fixing blocks can be fixed around the outside edge of the external walls to assist in panel
location and alignment and prevent panels sliding off the edge of the unit.
•
Guide ropes not exceeding 10 metres in length will be attached to all first floor panels and
above to maintain control of the load when lifting over the scaffolding and working at the
higher levels.
•
Whenever possible, the wall panels will be “walked” towards the work area at low level to
maintain maximum control and then raised to the appropriate floor level by lifting up and
over the scaffolding.
•
Adjustable panel support brackets will be fixed as required to support unfixed panels. The
foot of each bracket is screwed directly into the timber of the floor cassette deck using
screws.
The process is then repeated; panels will be placed and secured as the ground floor panels,
commencing at one corner and progressively working away from this point.
•
When specified by design, on completion of the external panel works, timber head binder
plates will be fitted across the top of the wall panels before progressing to the next stage.
•
When the Team Leader is satisfied with the position of the cassette, then the slings can
be detached from under the load by detaching the shackles and lifting the slings away.
•
The next cassette in the sequence will be positioned with a stand off from the first
cassette leaving a gap no greater than 150mm to allow the slings to be removed.
•
This sequence is repeated until the last floor cassette is in position. The last cassette
must be set down temporarily onto timber blocks placed along the edge of the lower wall
panels to support the floor and allow the slings to be removed (the blocks will be removed
later).
Final Fixing
•
When all the cassettes are in their approximate positions, there will be no edges to allow
someone to fall from height.
•
Under the supervision of the Team Leader, Team Members can work from inside the
scaffolding handrail to make the necessary fixings.
•
The support blocks will be taken out from under the cassette that was lifted last, so that
all cassettes are level on the top wall plate of the panel.
•
Each cassette can then be levered into its final position according to the floor deck layout
also closing all minor gaps between cassettes.
•
Screw and nail fixings are completed to the specification before progressing to the next
level of wall panels.
7. Erecting and Placing of Wall Panels above Ground Floor Level
Panels on upper levels will be assembled and fixed in the same way as detailed in the
ground floor method (item 5) with the following additional measures:
•
Appropriate fall arrest protection must be used and any necessary barriers fixed to guard
all open edges. When open panel frames have been fitted in upper internal rooms
adjacent to stairwells then timber rails must be fixed horizontally, the main guard rail must
be at a height of at least 950 mm to prevent anybody falling into the stairwell.
•
Fixing blocks can be fixed around the outside edge of the external walls to assist in panel
location and alignment and prevent panels sliding off the edge of the unit.
•
Guide ropes not exceeding 10 metres in length will be attached to all first floor panels and
above to maintain control of the load when lifting over the scaffolding and working at the
higher levels.
•
Whenever possible, the wall panels will be “walked” towards the work area at low level to
maintain maximum control and then raised to the appropriate floor level by lifting up and
over the scaffolding.
•
Adjustable panel support brackets will be fixed as required to support unfixed panels. The
foot of each bracket is screwed directly into the timber of the floor cassette deck using
screws.
The process is then repeated; panels will be placed and secured as the ground floor panels,
commencing at one corner and progressively working away from this point.
•
When specified by design, on completion of the external panel works, timber head binder
plates will be fitted across the top of the wall panels before progressing to the next stage.
Lifting the Roof onto the Assembled House
On completion of the upper storey the roof sections can then be lifted onto the upper wall
panels (by others) to complete the shell.
PROTECTION AGAINST FALLS
Assembly with Freestanding Scaffold Structure
The Principal Contractor will supply a freestanding scaffolding structure. The scaffolding must
be fitted with handrails inside each lift and be designed to provide fixed edge protection
around the perimeter edge of the building under construction. It must be erected in
accordance with the client’s approved design drawing to meet current standards &
regulations.
To prevent falls, all platform lifts are fully boarded between the handrails and a pair of
additional scaffolding boards are set to “close” the gap between the handrails and wall panels
as the assembly progresses. All boards must be in position before work on the upper
floors can commence.
Loading bays and ladder towers must also be fully protected with handrails and gates. Safety
gates must be closed at all times when loading operations are not being carried out.
Access ladders provided to each lift must be in good condition, designed for the purpose to
be used and fully secured at the top. They must extend above each platform level by about
1.0m (by a minimum 5 rungs) to provide a handhold.
Stairwell Protection
A suitable stairwell and edge protection system will be provided by the Principal Contractor
and fitted by the Assembly team as the assembly and fixing of the floor progresses to protect
the stairwell, any lift openings and unprotected edges.
The protection around the stairwell opening will normally take the form of prefabricated steel
supports and double timber handrails provided by site. Though this is the preferred first
choice protection system, alternative systems can be used and will be agreed with the
Principal Contractor.
When specified, the Assembly team will fit a temporary safety deck inside the stairwell
opening to improve access for panel assembly and fixing. Fitted in accordance with the
drawing, it also temporarily reduces the “working size” of the opening. The deck can be left in
place following completion of the assembly and removed later by “others”. The deck is not
designed to be loaded or used to support internal scaffold structures.
In circumstances when scaffolding is not to be used, the use of an approved fall arrest
system must be used and will be covered by a separate Method Statement (provided by the
principle contractor).
As the erection of the inner walls on upper floors progresses, it may be necessary to remove
the posts and rails around the stairwell opening to achieve the correct position of the wall
frames. In this situation, the protection must be quickly restored by the team using timber
battens fixed horizontally across the wall frames at a height of 950 mm to prevent anyone
“walking through the frames”.
Personal Protective Equipment
Every self-employed person shall ensure that any personal protective equipment provided to
him is maintained (including replaced or cleaned as appropriate) in an efficient state, in
efficient working order and in good repair - (Extract from the Personal Protective Equipment
at Work Regulations).
•
Every operative is to ensure that they have received adequate training with regards to the
use of any particular item of Personal Protective Equipment.
Lifting the Roof onto the Assembled House
On completion of the upper storey the roof sections can then be lifted onto the upper wall
panels (by others) to complete the shell.
PROTECTION AGAINST FALLS
Assembly with Freestanding Scaffold Structure
The Principal Contractor will supply a freestanding scaffolding structure. The scaffolding must
be fitted with handrails inside each lift and be designed to provide fixed edge protection
around the perimeter edge of the building under construction. It must be erected in
accordance with the client’s approved design drawing to meet current standards &
regulations.
To prevent falls, all platform lifts are fully boarded between the handrails and a pair of
additional scaffolding boards are set to “close” the gap between the handrails and wall panels
as the assembly progresses. All boards must be in position before work on the upper
floors can commence.
Loading bays and ladder towers must also be fully protected with handrails and gates. Safety
gates must be closed at all times when loading operations are not being carried out.
Access ladders provided to each lift must be in good condition, designed for the purpose to
be used and fully secured at the top. They must extend above each platform level by about
1.0m (by a minimum 5 rungs) to provide a handhold.
Stairwell Protection
A suitable stairwell and edge protection system will be provided by the Principal Contractor
and fitted by the Assembly team as the assembly and fixing of the floor progresses to protect
the stairwell, any lift openings and unprotected edges.
The protection around the stairwell opening will normally take the form of prefabricated steel
supports and double timber handrails provided by site. Though this is the preferred first
choice protection system, alternative systems can be used and will be agreed with the
Principal Contractor.
When specified, the Assembly team will fit a temporary safety deck inside the stairwell
opening to improve access for panel assembly and fixing. Fitted in accordance with the
drawing, it also temporarily reduces the “working size” of the opening. The deck can be left in
place following completion of the assembly and removed later by “others”. The deck is not
designed to be loaded or used to support internal scaffold structures.
In circumstances when scaffolding is not to be used, the use of an approved fall arrest
system must be used and will be covered by a separate Method Statement (provided by the
principle contractor).
As the erection of the inner walls on upper floors progresses, it may be necessary to remove
the posts and rails around the stairwell opening to achieve the correct position of the wall
frames. In this situation, the protection must be quickly restored by the team using timber
battens fixed horizontally across the wall frames at a height of 950 mm to prevent anyone
“walking through the frames”.
Personal Protective Equipment
Every self-employed person shall ensure that any personal protective equipment provided to
him is maintained (including replaced or cleaned as appropriate) in an efficient state, in
efficient working order and in good repair - (Extract from the Personal Protective Equipment
at Work Regulations).
•
Every operative is to ensure that they have received adequate training with regards to the
use of any particular item of Personal Protective Equipment.
•
•
Self
Self e
employed
m p lo y e d p
persons
e rs o n s a
are
re tto
o e
ensure
nsure tthey
hey p
purchase
u rc h a s e a
and
nd m
maintain
aintain PPE iin
n lline
in e w
with
ith tthe
he
relevant
relevant ri
risk
sk a
assessments
s s e s s m e n ts
nd u
se a
ny PPE p
rovided ffor
or tthem
hem a
nd
hey llook
ook a
f te r a
Employed
Employed p
persons
e rs o n s a
are
re tto
oe
ensure
nsure tthey
after
and
use
any
provided
and
ny d
efe
e c ts e
upervisor iimmediately.
m m e d ia te ly .
report
report a
any
defects
etc
tc to
to their
their ssupervisor
Welfare Facilities
F a c ilitie s
Welfare
Op
e r a t iv e s w
ill u
se tthe
he w
elfa
are fa
a c ilitie s p
r o v id e d b
y tthe
he P
rinciple C
ontractor tto
o iinclude
nclude ttoilet
oilet
Operatives
will
use
welfare
facilities
provided
by
Principle
Contractor
fa
cilities a
nd M
ess C
anteen, th
e ccanteen
anteen fa
cilities w
ill b
e u
sed fo
eal b
re a k s a
nd n
o
facilities
and
Mess
Canteen,
the
facilities
will
be
used
forr a
allll m
meal
breaks
and
no
ea, on any ot
her par
br
eaks w
ill be hel
d iin
n tthe
he w
ork ar
he ssite
ite nor iin
n vvehicles
ehicles ((Private
Private or
breaks
will
held
work
area,
other
partt of tthe
company owned)
ow ned)
company
Completion of
of Works
W o rk s
On Completion
All w
o rk a
n a cclean
lean ccondition
o n d itio n a
nd a
s p e ct s o
re a s a
re tto
ob
e lleft
efftt iin
a fe ty w
ith rregards
egards tto
o tthe
he
All
work
areas
are
be
and
allll a
aspects
off ssafety
with
immediate w
visual inspection
inspection b
he operative
y tthe
o rk a
re a a
nd conduct
conduct a visual
operative tto
o e
nsure that
that tthe
he
immediate
work
area
and
by
ensure
edge pr
otection iis
s iin
n pl
ace and tthat
hat tthere
here iis
s no rrisk
isk tto
o injury
injury tto
o themselves
themselves or ot
hers as a
protection
place
others
di
rect rresult
esult of a ffall
all ffrom
rom that
that area.
area.
direct
En
sure all
al l o
th e r m
a te r ia l w
hich is u
sed ffor
or yyour
tored iin
n a ssafe
afe
ea
our w
ork is sstored
nd p
ro p e r m
anner
Ensure
other
material
which
used
work
and
proper
manner
bef
ore depa
rting from
from the
the property
property yyou
ou a
re w
orking iin.
n.
before
departing
are
working
o tthe
he S
ite M
anagem ent T
ite
Re
port tto
eam o
n ccompletion
o m p le tio n o
he wo
rk s a
nd iiff rrequired
e q u ir e d b
y tthe
he ssite
Report
Site
Management
Team
on
off tthe
works
and
by
ut b
efo
ore lleaving
e a v in g
ru
les ssign
ig n o
rules
out
before
Co
m m u n ic a t io n
Communication
Stevens will
will communicate
communicate tthe
he ccontents
o n te n ts o
his me
thod sstatement
tatement tto
o a
peratives
M J Stevens
off tthis
method
allll o
operatives
involved prior
prior tto
o ssite
ite sstart.
ta rt. C
onsultation w
ith e
mployees w
ill ttake
ake p
lace tthrough
h ro u g h M J S
te v e n s
involved
Consultation
with
employees
will
place
Stevens
area managers.
managers.
area
NAME
NAME
Andy
White
An
dy W
h ite
DATE
01/11/2009
DA
TE 01/11
/2009
REVIEW
RE
VIEW DATE
DATE
01/04/2015
SI
SIGNATURE
GNATURE
MB
MBA
AS
Safety
afe
et y & T
Training
r a in in g L
Ltd
td
JOBTITLE
JO
B T IT L E
Health
and
Consultant
onsultant
He
alth a
nd safety
s a fe t y C
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
•
•
Self
Self e
employed
m p lo y e d p
persons
e rs o n s a
are
re tto
o e
ensure
nsure tthey
hey p
purchase
u rc h a s e a
and
nd m
maintain
aintain PPE iin
n lline
in e w
with
ith tthe
he
relevant
relevant ri
risk
sk a
assessments
s s e s s m e n ts
nd u
se a
ny PPE p
rovided ffor
or tthem
hem a
nd
hey llook
ook a
f te r a
Employed
Employed p
persons
e rs o n s a
are
re tto
oe
ensure
nsure tthey
after
and
use
any
provided
and
ny d
efe
e c ts e
upervisor iimmediately.
m m e d ia te ly .
report
report a
any
defects
etc
tc to
to their
their ssupervisor
Welfare Facilities
F a c ilitie s
Welfare
Op
e r a t iv e s w
ill u
se tthe
he w
elfa
are fa
a c ilitie s p
r o v id e d b
y tthe
he P
rinciple C
ontractor tto
o iinclude
nclude ttoilet
oilet
Operatives
will
use
welfare
facilities
provided
by
Principle
Contractor
fa
cilities a
nd M
ess C
anteen, th
e ccanteen
anteen fa
cilities w
ill b
e u
sed fo
eal b
re a k s a
nd n
o
facilities
and
Mess
Canteen,
the
facilities
will
be
used
forr a
allll m
meal
breaks
and
no
ea, on any ot
her par
br
eaks w
ill be hel
d iin
n tthe
he w
ork ar
he ssite
ite nor iin
n vvehicles
ehicles ((Private
Private or
breaks
will
held
work
area,
other
partt of tthe
company owned)
ow ned)
company
Completion of
of Works
W o rk s
On Completion
All w
o rk a
n a cclean
lean ccondition
o n d itio n a
nd a
s p e ct s o
re a s a
re tto
ob
e lleft
efftt iin
a fe ty w
ith rregards
egards tto
o tthe
he
All
work
areas
are
be
and
allll a
aspects
off ssafety
with
immediate w
visual inspection
inspection b
he operative
y tthe
o rk a
re a a
nd conduct
conduct a visual
operative tto
o e
nsure that
that tthe
he
immediate
work
area
and
by
ensure
edge pr
otection iis
s iin
n pl
ace and tthat
hat tthere
here iis
s no rrisk
isk tto
o injury
injury tto
o themselves
themselves or ot
hers as a
protection
place
others
di
rect rresult
esult of a ffall
all ffrom
rom that
that area.
area.
direct
En
sure all
al l o
th e r m
a te r ia l w
hich is u
sed ffor
or yyour
tored iin
n a ssafe
afe
ea
our w
ork is sstored
nd p
ro p e r m
anner
Ensure
other
material
which
used
work
and
proper
manner
bef
ore depa
rting from
from the
the property
property yyou
ou a
re w
orking iin.
n.
before
departing
are
working
o tthe
he S
ite M
anagem ent T
ite
Re
port tto
eam o
n ccompletion
o m p le tio n o
he wo
rk s a
nd iiff rrequired
e q u ir e d b
y tthe
he ssite
Report
Site
Management
Team
on
off tthe
works
and
by
ut b
efo
ore lleaving
e a v in g
ru
les ssign
ig n o
rules
out
before
Co
m m u n ic a t io n
Communication
Stevens will
will communicate
communicate tthe
he ccontents
o n te n ts o
his me
thod sstatement
tatement tto
o a
peratives
M J Stevens
off tthis
method
allll o
operatives
involved prior
prior tto
o ssite
ite sstart.
ta rt. C
onsultation w
ith e
mployees w
ill ttake
ake p
lace tthrough
h ro u g h M J S
te v e n s
involved
Consultation
with
employees
will
place
Stevens
area managers.
managers.
area
NAME
NAME
Andy
White
An
dy W
h ite
DATE
01/11/2009
DA
TE 01/11
/2009
REVIEW
RE
VIEW DATE
DATE
01/11/2011
01/11/2011
SI
SIGNATURE
GNATURE
MB
MBA
A Safety
Safe
et y & T
Training
r a in in g L
Ltd
td
JOBTITLE
JO
B T IT L E
Health
and
Consultant
onsultant
He
alth a
nd safety
s a fe t y C
Un
Unit
it 6 ““The
The Co
Counting
unting Ho
House”
use”
Tonedale
Business
Park
Tonedale B
usiness P
ark
Wellington,
TA21
0AW
We
llin g to n , T
A21 0
AW
Tel:
Tel: 01823
01823 668526
668526 / Fax:
Fax: 01823
01823
668527
This is to certify that the Health & Safety documentation supplied by
MJ Stevens Ltd
has been checked by Safety Management Advisory Services Limited
and the Company named above has been awarded a
Worksafe Contractor Membership Certificate
as a
Contractor
The process was undertaken in line with,
The Health and Safety at Work Act etc 1974,
The Construction Design & Management Regulations 2007
The Management of Health & Safety at Work Regulations 1999
The process followed the CDM Regs: Core Criteria Stage 1 process,
evaluating the designated elements of Health and Safety Management documentation
SMAS Verification
Certificate expiry date
09/04/2013
Certificate Number
24219
Directors Signature
28/03/2014
Joe Laverick
Safety Management Advisory Services Limited is a full Member of the SSIP Forum
To check the validity of this certificate please contact SMAS Ltd direct by phone 01752 697370 or email [email protected]
SMAS Ltd, Office 42A Estover Close, Forrester’s Business Park, Estover, Plymouth, PL6 7PL Website: www.smasltd.com
SMAS operates two NATIONAL H&S ASSESSMENT SCHEMES: WORKSAFE CONTRACTOR and WORKSAFE CONSULTANT www.smasltd.com
The Safety Schemes in Procurement Competence Forum (SSIP) is an umbrella organization to facilitate mutual
recognition between health and safety pre-qualification schemes wherever it is practicable to do so
!
"
"
This will then be kept as a record by the Health & Safety Director at our
Head Office.
This Health & Safety Booklet on Method Statements and Risk Assessments
has been thoroughly read and understood by:
Name
Address
Postcode
Tel Home
Tel Mobile
Email
Date of Birth __ __ / __ __ / __ __ __ __
National Insurance Number _ _ / _ _ / _ _ / _ _ / _ _
Construction Skills Certification Card No.
CSCS Card type _______________________________________
CSCS Expiry date __ __ / __ __ / __ __ __ __
UTR number __________________________________________
This Method Statement book has been issued to and has been thoroughly
read and understood by
Signature _________________________________
Dated : ___________________________
This book is issued under copyright and remains the property of:
!
"
"
This will then be kept as a record by the Health & Safety Director at our
Head Office.
This Health & Safety Booklet on Method Statements and Risk Assessments
has been thoroughly read and understood by:
Name
Address
Postcode
Tel Home
Tel Mobile
Email
Date of Birth __ __ / __ __ / __ __ __ __
National Insurance Number _ _ / _ _ / _ _ / _ _ / _ _
Construction Skills Certification Card No.
CSCS Card type _______________________________________
CSCS Expiry date __ __ / __ __ / __ __ __ __
UTR number __________________________________________
This Method Statement book has been issued to and has been thoroughly
read and understood by
Signature _________________________________
Dated : ___________________________
This book is issued under copyright and remains the property of: