Handling the Walsh Space

C30-20081201-007R1
TSG-C WG3
Title:
Chair’s View of Working Schedule for Working Group 3
File:
C30-20090330-007 WG3Ch_proposed schedule_60
Abstract:
This contribution contains the chair’s view of the working
schedule for Working Group 3.
Source:
Sang Kim
Chair, TSG-C WG3
Date:
March 30, 2009
Notice
©2009 3GPP2. All rights reserved.
C30-20081201-007R1
–
–
–
–
–
–

1x-enhancements:
Baseline (closing plenary)
)
–
–



March 2009 (Regular meeting, March 30-April 3)
–
C.S0024-B (DO bugs):
V&V comments returned;
anticipated publishing or extended V&V begins
–
C.P1002-A (EM for Phase 2):
V&V comments back; V&V resolution;
anticipated publishing or extended V&V begins
–
DO-enhancements:
–
1x-enhancements:
–
1x-enhancements:
V&V
published or extended V&V
–
ITU:
Work on WP5A inputs
–
ITU:
Develop draft of M.2039 update input to the ITU
–
ITU:
Develop draft of M.2039 input to the ITU
–
ITU:
Finalize WP5A inputs
V&V comments back; resolution begins
comment
resolution
ITU:
Finalize M.2039 update input to the ITU
–
Finalize all WP5D inputs in conjunction with ITU Ad Hoc
June 2009 (Regular meeting, June 15-19)
framework decision

July 2009 (Regular meeting, July 20-24)

August 2009 (Regular meeting, August 17-21)
–


DO-enhancements:
components due
September 2009 (Regular meeting, September 21-25)
–

completed;
–
DO-enhancements:
DO-enhancements:
resolution,
proposals due
May 2009 (Regular meeting, May 11-15)
–
V&V
component decisions completed
October 2009 (Regular meeting, October 26-30)
–
DO-enhancements:
baseline (opening)
–
DO-enhancements:
R&F
–
DO-enhancements:
begin V&V
December 2009 (Regular meeting, December 7-11)
document
C30-20081201-007R1
–

DO-enhancements: V&V comments returned; V&V resolution, anticipated
publishing or extended V&V begins
January 2010 (Regular meeting, January 25-29)
Notes:

A schedule for femto cell work has not yet been developed.

A schedule for C.S0057-D has not yet been developed.

The DO-enhancements is expected to result in C.S0024-C.