CASE STUDY Making the right connections for renewable energy Veolia Water’s Infrastructure Services team provided the electrical connections enabling an anaerobic digestion (AD) facility to export renewable energy to the Grid. When Cumbria’s Dryholme Farm was setting up an AD facility and needed an electrical connections expert, Farmgen appointed the Infrastructure Services team as Principal Contractor under CDM (construction, design and management) for all the offsite and onsite associated works. Project Manager Dave Harrison said: “Our contract was to provide a ‘one-stop’ service to the client for both the offsite and onsite high-voltage (HV) installation works. “For the offsite works, we had to install 2.5km of 11kV HV cable from the point of connection (POC) in Silloth to a HV metered substation at the site boundary that would be adopted by Electricity North West, the Distribution Network Operator (DNO). We carried out this installation work as an Independent Connection Provider (ICP). “For the onsite works we installed a private HV network and substation with an export capability for 2.4MVA. This included all the protection and control equipment for the private HV installation to comply with the requirements of the DNO and to ensure that the client’s AD plant generator met with all G59 import and export generation requirements. “The substation works to be adopted included the procurement and installation of a new type of DNO- WHAT WE DO Infrastructure Services is our multi-utility project management, design and construction business. Our expert team can provide a full end-to-end solution for electricity, water and gas infrastructure and connections, including private networks after the meter. specified G59 protection panel and emergency tripping facility, which was fully tested by our site team and witnessed by the DNO. We also supplied and installed the DNO substation glass reinforced plastic housing and a separate metering kiosk as well as the HV substation earth mat.” CASE STUDY Pulling out all the stops to meet superstore deadline “The client’s private installation works included a private HV cable and multicore protection cable (0.5km), 11kV switchgear, 3MVA transformer complete with LV air circuit breakers (ACBs) and LV singles from one of the LV ACBs to the clients’ AD generator housing.” The team also installed the private substation GRP housing (complete with fans for ventilation, internal small power and lighting), and a marshalling panel for all the necessary generation indication and tripping capabilities – and earthing – for the client’s private substation and transformer. Dave coordinated ‘pre-start’ meetings with the local highways and bridge structures departments at Cumbria County Council to discuss the works programme. It was agreed to delay work PROJECT DETAILS The Infrastructure Services team worked to install a HV metered supply, with G59 export capability. The works include the installation of DNO offsite HV cables and an onsite substation, plus the client’s private HV cable, onsite HV substation and transformer (complete with LV ACBs) and private LV singles to the generator for the AD plant. Veolia Water Infrastructure Services Registered Office: Fifth Floor, Kings Place, 90 York Way, London N1 9AG www.veoliawater.co.uk on a section of the cable route located close to a large caravan park, to avoid a negative impact during the summer holiday trading period. There were a number of special engineering difficulties for the team to overcome during the project. One required directional drilling under a river culvert, in order to avoid damaging it and to minimise disruption for holidaymakers. Another involved a quaint little humpback bridge - fixings were not permitted, so the team constructed a free-supporting highdensity duct crossing instead. The team also used a similar method to span a small stream on the farmer’s private land. Following an extensive programme of testing and pre-commissioning, the site was energised in October 2011 (only four months after commencing works). Veolia provided an Operational Engineer on the day to ease the handover of the client’s private HV installation, and completed all MPAN registration (import and export) with the DNO on the client’s behalf. Impressed with the quality of its service delivery, Farmgen has since awarded the Infrastructure Services team a further contract – another anaerobic digestion plant on a farm in Cumbria. Processes Installations: • 11kV HV cable (2.5km) from POC location to boundary DNO substation • G59 export capability for 2.4MVA • DNO offsite HV cables, onsite substation, GRP housing, metering kiosk and substation earth mat installation • Client’s private HV cable, onsite substation, 3MVA transformer and LV singles • GRP housing (with fans for ventilation) for client’s private sub Additional processes: All pre-commissioning and testing for both DNO and client’s private HV installation requirements for energisation Coordinating MPAN process for client’s metering installation Coordinating client’s G59 testing and witnessing with DNO for generator plant protection and synchronisation Providing all Health and Safety documentation to the client
© Copyright 2026 Paperzz