TE_MSC_MNC_Activities_YETS_15_16

TE-MSC-MNC Activities – YETS 2015/16
PSB – A. Newborough
TE-MSC Activities – YETS 2015/16 PSB
• Hardware Tests:
• Inspection with all magnets powered beginning of W48 ~ 1-2 hrs
(Requires Water, operations, controls, power converters, RF and tunnel
ventilation stopped if possible)
• High Voltage tests, 2nd half W48 ~ 2 days requires
• Visual inspection when water returns in January
• Foreseen magnet activities:
• None
• Unforeseen magnet activities:
• ????
• Reminder! If people need magnet covers removed it will be performed on
request with the relevant VAT, MALT etc… by TE-MSC-MNC.
• Activities lead by others:
• Vacuum: Change of quadrupole magnet BR.QFO72 due to vacuum leak
• Vacuum: Removal of corrector magnets for 4L1 for the vacuum hot spot
• Survey: Try of the SPS style jacks to move the BHZ magnet
(BR.BHZ72 TBC)
22/10/2015
A. Newborough
2