PAI PARIS GARE DE LYON PRESENTATION OF THE PROJECT 20/06/2017 TECHNICAL ORGANISATION OF THE COMMISSIONING Dominique BERGÉ DIRECTION DES PROJETS FRANCILIENS SUMMARY 01. TECHNICAL ORGANISATION OF THE COMMISSIONING – 01.1. BEFORE COMMISSIONING 01.2 DURING COMMISSIONING 01.3. AFTER COMMISSIONING 01. TECHNICAL ORGANISATION OF THE COMMISSIONING – COMMISSIONING ORGANISATION STANDARD IN 3225 "Commissioning on safety installations“ Standard Its goal: to prepare and carry out commissioning under optimum conditions of efficiency and safety   Preparing the commissioning operation: Cutting plan in elementary operations Safely: Implementation Plan for Regulatory Procedures  Shared by all: Traffic operation and overhead lines operation, Train Operating Companies, maintainers, PROJECT team, … – COMMISSIONING ORGANISATION Commissioning working group: EIC, INFRAPOLE, ITIF, TSEE, DCF, EF, PRI, EALE, ESTI…  Monthly meetings from september 2015  Definition of the test area  Definition of the Detailed Timeline  Follow-up of the Check List of the commission activities  Specific Risk Analysis for Commissioning (Organisational, external, technical, post commissioning, fallback solutions, dysfunctions,…) Preparation from Y-1 – Preparation from M-6 to D-14 D-14 COM. ASS 01.1 COMMISSIONING ORGANISATION : BEFORE COMMISSIONING – COMMISSIONING ORGANISATION BEFORE COMMISSIONING TEST AREA  Determine a perimeter to be protected by S6 / S9 / S11 measures to ensure the safety of switching installation works and commissioning tests  Ensure that the boundary of the ZEPs and their associated devices remain compatible with the tests to be carried out during the commissioning  Define, in accordance with the operators and the TOCs, the track occupancy in the area, as well as the authorised movements requiring PS9E measures  These documents must be known and shared by all the activities of the site 6105 zep 6171 1C Pas de ZEP en protection 3+080 2C ZEP6178 Z6102b 0+490 1270 1285 1083b 1057 1282 9+453 5 16a Secteur ParisPompadour 9+453 1048b 1021b z1023 1033b z1029 1043a 1083a 1281 limite domaine 1049 pas de protection 1048a 1081a 9+517 1 bis circul 16b 10+680 36 35 PosteA ZEP 517 z7A 9+301 X1056 32a It 39 Poste B 1 bis circul 24 Imp 34 10 V24 V25 Départ Nord V26 9+555 31b It 31 10+836 5 à 12 Formation V15 à 23 ZEP 765 PB 35 1256 1045 Cv13 Zep 773 1258 9+384 1046 1023a VSG PA Au 1016 10+353 2 1081b 1055 1253 TIV 3,4 z1710- z110 u S5 vers poste O 36b 1 circul 34 ZEP 387 PB C57 1047a 31a Secteur ParisPompadour Cv1265 32 2 circul M Cv 1263 9+241 32b 1268 fictif C55 1064a 1047b 1063 1252 1266 Au ES 2C Cv54 VSG P1 1264 fictif Cv53 PosteB ZEP 756 z53 10+409 Cv49 1062b 1064b ZEP 86+87 M Cv Cv41 Tiroir A 42 Cv48 z6 ZEP 82+83 Faisc reception 9+625 Au ES M1 Cv42 1262 fictif Preparation from Y-1 – Preparation from M-6 to D-14 D-14 COM. ASS COMMISSIONING ORGANISATION BEFORE COMMISSIONING COMMISSIONING TIMELINE  Sequencing all procedure, switching installation and commissioning testing activities  Dimension the number of agents (disciplines and accreditations) and the additional needs (radios, vehicles, ...)    By geographical location for switching installation and testing activities List and quantify specialised mobile teams Organize team turnover taking into account HR constraints Preparation from Y-1 – Preparation from M-6 to D-14 D-14 COM. ASS COMMISSIONING ORGANISATION BEFORE COMMISSIONING CHECK-LIST OF ACTIVITIES OF THE COMMISSIONING: built on the experience of previous projects, enriched and shared within the projects:  Editing the signalling notice  Technical documentation: Signalling scheme plan, Control tables, as-built drawings, Regulations, Works contract,…  Training  Removal of installations: supply contracts, ...  Preparation of work and switching installation sheets  Preparation of commissioning tests sheets  Resources: call for volunteers, team sizing, reinforcements (EIC, EALE, Contractors) ...  Cleaning and maintenance: cleaning of pathways, deoxidation of rails,…  Logistics for commissioning: reception, directory, catering, accommodation, transport,…  Preparation of means of communication: radios, portables,…  Security for the area access  Communication : before, during and after the commissioning Preparation from Y-1 – Preparation from M-6 to D-14 D-14 COM. ASS COMMISSIONING ORGANISATION BEFORE COMMISSIONING Trial run for the protection operations of the test area:  Simulation of the protection procedures for the area (10 km of track, 2 hours of procedure, 15 operational signal boxes  Repetition concerning the EIC / EF / MOET management for verifying the test area protection regulation Trial run for the test area closure operations:  Reconnaissance of the closure locations by the staff (Pk, voie, …)  Testing the means of communication  Checks of material means (SAM, detonators, DSh, ...)  Simulation of the closure implementation  Checks of organization, duration and sequencing of operations Repetition of the commissioning for all agents:  Presentation of the project, organisation of the commissioning, planning of assignment by agent, visit of the site of reception and intervention for each agent, provision of the worksheets for verification in order to detect any anomalies or Preparation from Y-1 – Preparation from M-6 to D-14 D-14 COM. ASS 01.2 COMMISSIONING ORGANISATION : DURING COMMISSIONING – COMMISSIONING ORGANISATION COMMISSIONING SEQUENCE 18/03/17 19/03/17 20/03/17 Reception Closure EIC Technical closure Removal IS Switching works PLX, Ag, CdV Switching works and complementary markings (KVB, SAAT, …) Preliminary tests records Concordance tests and Functional tests End of closure S11 End of closure S9 Commissiong records S6/S9 Measures from 3h30 to 0h00 S11 Measures from 3h30 to 22h00 0h00 08h00 16h00 0h00 08h00 Internal / external communication: VIP, Media, Rooftop, ... – 16h00 0h00 COMMISSIONING ORGANISATION DURING COMMISSIONING: ORGANISATION OF THE GENERAL COORDINATION Preparation from Y-1 – Preparation from M-6 to D-14 D-14 COM. ASS 01.3 COMMISSIONING ORGANISATION : AFTER COMMISSIONING – COMMISSIONING ORGANISATION AFTER COMMISSIONING  Transfer of the safety installations and removal of reservations identified before and during the commissioning  Thermography: infrared camera detection of hot spots on all power supplies  Airproof sealing of technical rooms (REX Denguin, efficiency of automatic fire suppression)  Assistance after commissioning: Accompanying instructions for the Commissioning and the ASS (After Sale Services):  Reinforcement EIC  MISTRAL testers: diagnostic aid to distinguish malfunctions from faults or nominal situations (operation in dynamics of automatisms)  Reinforcement Infrapôle : assistance to the fault clearance, mainly located in the SER 1  Contractors Reinforcements (ANSALDO, ATOS, SIEMA, TECHNILOG, …)  Reinforcement IP-SYS and IP-SF, ISI Preparation from Y-1 – Preparation from M-6 to D-14 D-14 COM. ASS CHIFFRES CLÉS –
© Copyright 2025 Paperzz