OFFICIAL SENSITIVE LHCb Upgrade OsC PAR 1(14) Update Report Title Date Large Hadron Collider Beauty (LHCb) Upgrade Project 08/01/2016 Project Manager Principle Investigator Sponsor Chris Parkes Chris Parkes Mr Tony Medland Project Description LHCb is a particle physics experiment operating at the Large Hadron Collider (LHC) at CERN. It is the world’s leading flavour physics experiment and has a unique capability to explore physics beyond the Standard Model (SM). Flavour observables are sensitive to virtual quantum loops, which can be mediated by particles with masses significantly heavier than those that can be produced directly. LHCb’s main aim is to search for new physics beyond the SM through precision tests of matter anti-matter asymmetries (CP violation) and rare decays in heavy-quark flavour physics. The experiment also has world-class programmes related to lepton-flavour violation, forward electroweak, and QCD measurements. The LHCb Upgrade project will increase the reach of LHCb’s programme and widen the physics profile to that of a general purpose detector in the forward region, covering a kinematic regime inaccessible to ATLAS and CMS. The UK groups will provide major components of the upgrade of the VELO (Vertex Locator), the most precise vertex detector at the LHC, and LHCb’s unique RICH (Ring Imaging Cherenkov) particle identification (PID) system. These systems are crucial to the widely recognised success of the current LHCb experiment. A programme of work on development of the LHCb high level trigger algorithm development complements this work. These contributions are the key deliverables. The purpose of this project is the construction and installation of these elements. The upgraded experiment will be installed during the LS2 shutdown of the LHC, planned for 2019-21. LHC operations are expected to start in April 2021. The readiness of the detectors for the LHC start is the principal aim of the project. Progress Narrative summary of progress to date (i.e. since last report) - Overall opinion on whether project is on track and within budget - Key successes (e.g. milestones and/or deliverables met). - Problems (e.g. milestones missed, changes to specification, cost to completion issues/ contingency requests) - Future developments / next steps (and any constraints) - Include items from the last oversight committee as well as the office’s standpoint on issues Page 1 of 13 OFFICIAL SENSITIVE LHCb Upgrade OsC PAR 1(14) Third Progress Report covering period 13th June 2014 – 15th December 2015. Executive Summary The revised LHC schedule has been confirmed, delaying the start of operations by one year. Expenditure forecasts and milestones have been updated appropriately. The Consolidated Grant for Particle Physics has been announced, this has reduced the available staff funding for the project by £101k. Good progress has been made on the VELO, notably the EDR for micro-channel plates has taken place. Similarly the RICH project is proceeding well, the contract for the MaPMTs (single largest order in the full project) has been signed. The main concerns in the project are discussed below or commented in the risk register. UK Funding Situation -Desirable Additions. This text is largely unchanged from the previous report A statement of interest for the LHCb upgrade was submitted in May 2013 and a full proposal in August 2013. Limited bridging funds were awarded for the period January – September 2014. A descoped proposal was approved in August 2014 by science board (SB) with two scenarios recommended depending on the available funding in STFC. In this SB recommended a baseline programme with desirable additions, however due to capital limitations STFC was not able to award the capital elements of the additions at that time. Therefore a work plan document was submitted in November 2014 to meet the lower award value without the additions, with most details of the baseline grant being clarified by the start of 2015. The JeS grant starting certificate was received on 21st April 2015. Project posts and equipment grants were awarded for the period October 2014 – April 2020. Ring-fenced consolidated grant effort was awarded for the period April 2014-April 2020. LHCb UK believes the desirable additions would be of great benefit to the project. These elements approved by Science Board but for which funding is not yet available are: additional capital funding for WP1 of £199k and for WP2 of £356k. The funding decision on these is anticipated after the Comprehensive Spending Review, hence we assume we will hear before the next OSC meeting, and we urge the OSC to strongly support these. We were informed at the last OSC that contingency funds are not expected to be available for this project. -Consolidated Grant 2015-2019 Outcome. The ring-fenced effort in the project was subject to a cap on FTE / year on core staff, determined by the grants panel. Risks to the project exist for a small number elements for which the UK has responsibility in the TDRs and no international partner has been found. The collaboration was requested to submit bids for additional consolidated grant effort necessary for the project completion as part of the consolidated grant review. Fractions of ring-fenced consolidated grant positions (including the FTE equivalent of the agreed commissioning costs) at five UK institutions were not awarded. As instructed in the guidelines no cases for the ring-fenced fractions of posts was submitted. We are grateful to the office for reinstating the most problematic of these posts, a 50% per year ring-fenced position. Other posts removed were ring-fenced at the 20% level/year or below and we believe we can adjust for this without major degradation to the project. We detail the effect on individual posts below. The final outcome corresponds to a reduction in the funding of this project by a further £101k. The non-award of support for Tizick, removes Warwick's hardware contribution to the project. Page 2 of 13 OFFICIAL SENSITIVE LHCb Upgrade OsC PAR 1(14) The core post of E. Rodrigues (Manchester) was not awarded. This post was the only effort for WP2.1.2, VELO Silicon readout and reconstruction software. Consequently milestones and deliverables for this project element have been removed. The UK will attempt to still continue to contribute in this area on a best effort basis through students and synergies with PDRA work on the current detector where a UK responsive RA (J. Harrison, Manchester) is currently the software co-ordinator. The core post of A. Richards (Imperial) was not awarded. The post had effort on WP3.2 (Trigger) for the further development of multivariate analysis methods in the trigger. An attempt will be made to find this effort through flexibility of core staff awarded to other projects at Imperial but there is a significant risk that this is not possible. If that turns out, the involvement in the LHCb trigger will be scaled back. The core post of Ilya Tsurin (Liverpool) was not awarded. For the LHCb upgrade: Tsurin provided the mask design and was pixel engineer (WP 2.3.1) for the sensor tiles and would perform the testing of the bump-bonded pixels to produce a qualified pixel-tile assembly for delivery to Manchester. Although the development and design of LHCb pixels has been retained and will be delivered (as it was almost complete) there is now no Liverpool effort allocated for the QA necessary test the tiles prior to assembly. This represents a risk in the production chain. Additional fractional post funding was awarded for work on the VELO HV system (M.Perry, Manchester), where hardware costs will be born from central (CERN) project funds and a collaboration with Moscow state university has started. We are grateful for this award that will allow the UK to fulfil its TDR commitment in this area. The high priority areas for additional awards of the VELO vacuum feedthroughs and core computing contributions were not awarded. The international project management has been fully informed of the outcome. Negotiations are underway between CERN and a non-UK institution to cover the critical path development work on the VELO vacuum feedthroughs. The CG round was particularly hard in respect of computing posts. Some key existing LHCb computing posts were not awarded notably at Manchester, Imperial and Liverpool. All of these were material to the upgrade in one way or another (Ganga support, distributed computing support and the National Computing Board Rep). In additions, several small fractions of new posts were bid for to augment the computing manpower, but all of these were also not funded. This means that at present the computing manpower situation for LHCb is a high-risk element of the upgrade project. The LHCb management and computing management are fully aware. -Internal Finance/management arrangements Equipment funds were awarded through Manchester, Oxford, RAL. A collaboration agreement between all institutes to cover reimbursement of equipment expenses has been produced. A memorandum on VAT issues has also been produced, with input from advisors in all institutes. The VAT-free position of the primary project equipment costs is dependent on the ownership of the detector being gifted to CERN. CERN have agreed to this position and STFC replied that it did not have any objection. Alison Fletcher has replaced Deborah Lea as the project officer (20% post). LHC Schedule The revised LHC schedule discussed at the last OSC was approved by CERN in September 2015. The long shutdown 2 (LS2), in which the LHCb upgrade will be installed, will start at the end of 2018. The shutdown will last two years. Operations of the upgraded detector will start in early 2021. This is a delay of 12mths with respect to the awarded project. We are proceeding as discussed at the last OSC. Page 3 of 13 OFFICIAL SENSITIVE LHCb Upgrade OsC PAR 1(14) We assume that a zero-cost extension on project supported posts is permitted until April 2021. Institutes have thus been instructed that they can reprofile future costs to take account of the schedule delay. However, as most posts have already been hired in practice there is often limited freedom to do this. We assume that extensions to those project supported posts deemed critical will be financed through two mechanisms. CERN have indicated that savings in M&O B contributions to LHCb during LS2 could indeed be utilised for this purpose and this (item 1.1(0) of the feedback from the previous OSC) is now our baseline plan. The project has working allowance but does not have an allocated contingency. A component of the working allowance has been profiled to partially cover the costs of the delay, indeed a CERN schedule delay was always our highest rated project risk. A first working allowance profile has been circulated with this documentation in the finance spreadsheet. The consolidated grant ring-fence on this project runs until April 2020. We will discuss with STFC how best to handle the ring-fence request for the additional year of the programme. A revised set of milestones for the project has been produced and circulated with this documentation. These are agreed with the international experiment and match with those circulated recently to the CERN LHCC, though our UK milestones are more detailed. A revised equipment spend profile for the project has been produced and circulated with this documentation. Spend in this current financial year is notably low as many design reviews have been pushed back. WP1 RICH The design of the LHCb RICH systems has been documented in the LHCb Upgrade Particle Identification TDR CERN/LHCC 2013-022 LHCb TDR 14. Subsequently work has continued on producing prototypes and preparing designs for Engineering Design Reviews (EDRs). WP1.1 RICH Simulation, optimisation and reconstruction There are no issues associated with the simulation and reconstruction code for the RICH Upgrade. The optics and photon detector layouts for RICH1, including all modifications required by the engineering constraints, have been determined. Milestones M1.1.1A and M1.1.1B have thus been met. Further small modifications to the simulation will be made when PRR engineering details are finalized. As previously reported, the code is fully integrated into the LHCb Upgrade simulation, and milestones M1.1.2A and M1.1.3A have been completed. Work on providing a more complete simulation of the Boole digitisation code which simulates the detector electronics readout is progressing well. A fully functional implementation of the reconstruction code for the Upgrade is available and will evolve in the years up to data taking. WP1.2 RICH Photon Detectors As previously reported, the flat-panel Hamamatsu R11265 and H12700 MaPMTs have been fully qualified for use in the LHCb RICHes, completing milestones M1.2.1.A.and M1.2.1.B and deliverable D1.2.1. The photon detectors have been successfully operated in a second test beam campaign using a readout employing the penultimate submission of the CLARO readout chip. Four elementary cells (ECs) have been employed, each with 2x2 MaPMTs, including cooling and two prototype readout boards per EC. This represents a first system test with prototype electronics and the resolutions and photon yields are largely as expected. The Edinburgh Group shares the task at the 50% level of MaPMT testing and EC assembly and verification with Italian partners Padua and Ferrara (WP1.2.2, WP1.2.3). A work-plan has been agreed on the task sharing and testing sequence. The Hamamatsu delivery schedule has also been agreed (see below), which has introduced a minor 4 months delay on the photodetector milestones. The Edinburgh (and also Padua) MaPMT test centres will be ready for operation before the first tube deliveries. A major LHCC milestone was achieved in November 2015, namely the successful tendering and Page 4 of 13 OFFICIAL SENSITIVE LHCb Upgrade OsC PAR 1(14) acceptance of contract with Hamamatsu for the supply of 3100-off R13742 (formerly R11265) customized MaPMTs and 450-off R13743 (formerly H12700) customized MaPMTs. The tender did not exceed that estimated from the TDR (which was 4.9 MChF including mu-metal shielding) - the UK remains committed to its MoU share of £1.285M. Currency fluctuations of the Yen over the coming years remain a risk to the project; alternatively any potential savings from the same can facilitate purchase of unfunded RICH items. WP1.3 RICH Detector Mechanics and Optics The RICH1 geometry and optical arrangements have been optimised following rigorous simulations of performance. The RICH1 mechanical design is now well underway and the phase of preparing detailed engineering CAD drawings is proceeding rapidly. To this end an integrated CAD design model defines the constraints for the sub-component boundaries. The elementary cells have been designed in columns, and housed inside the existing RICH1 magneticshielding iron structures. The column arrangement, installation and extraction mechanisms for the photon detectors (WP1.3.1) remains a crucial design issue. This design has been guided by the synergy with RICH2 for the cooling strategy, cable routing and mountings for the electronics cards, and here the UK design team is working in close collaboration with Italian and CERN colleagues. There has been considerable progress in the mounting scheme for MaPMT columns into RICH1. The baseline is the “open” geometry where columns of MaPMTs can be removed/inserted individually (reducing significantly the access time required for replacement in case of a fault). The routing of cables and cooling pipes is now proceeding according to this scheme. The design of the gas enclosure (WP1.3.4), which is the structural frame to which all mirrors and windows are attached, is well advanced, and is now awaiting details of the interfaces for bolt-hole locations. The RICH1 exit window (carbon fibre skin/ foam core) and all seals will be manufactured in house and the designs are almost complete (WP1.3.3). The current RICH1 entrance seal to the beampipe and VELO will be reused if it doesn’t degrade after removal. The EDRs for the individual RICH1 mechanical components was scheduled for the end of this year, but due to the complex design of the MaPMT housings and extraction mechanism, plus this design is crucial to performance, the EDR milestone has been delayed by 6 months until July 2015. The likely scenario is that the EDR for RICH1 and RICH2 MaPMT housings will be reviewed together, with the EDRs for the gas enclosure and windows coming earlier. The designs of the installation equipment (WP1.3.6) for the photon detector boxes, mirrors and gas enclosure are proceeding in parallel with the design of the individual components. There continues to be steady progress on the mirror procurement (WP1.3.5). There are ongoing discussions with the CMA company (Tucson, Arizona) on the procurement and mounting of the 3.65 m radius of curvature spherical carbon fibre mirrors, fitting within the constraints of the gas enclosure. We are confident of achieving good spherical-mirror performance, and anticipate that the mirrors cost will come within TDR expectations, albeit with £150k as yet unfunded (as part of the desirable additions request to STFC). We have ordered a carbon-fibre flat mirror prototype from CMA and this has been tested for reflectivity and divergence of spot size (D0). A test facility was prepared in CERN by Bristol physicists, and this has operated well. Unfortunately this showed that the reflectivity of the prototype flat mirror fell short of the 90% specification, the D0 was just within specification but marginal, as well as there being a likely cost issue. Hence we have switched our focus to glass mirrors, for which several companies have been approached and a prototype will soon be ordered. We are now confident that the total flat-mirror cost will be held approximately within budget. The mounting mechanism for the flat mirrors is currently being designed. The EDRs for the mirrors and mounts will also be prepared for review by the revised July 2016 milestone. Konstantinos Petridis (Bristol) has taken over from Jonas Rademacker as WP1.3.5 project manager. WP1.4 RICH Electronics Readout, Data Acquisition and Controls The design of the front-end digital board, which serves 4 ECs, is progressing well (WP1.4.2). The digital Page 5 of 13 OFFICIAL SENSITIVE LHCb Upgrade OsC PAR 1(14) board design consists of a motherboard containing 3 Kintex-7 FPGAs. The layout of the prototype board, which has the required geometrical footprint for the RICHes, is in progress. The fully populated boards will be available for testing in around 6 months. There are two plug-in boards which sit on the motherboard: the dbVTTX prototype PCB plug-in boards have been delivered, and the layout of the dbVTRX plug-in board is in progress. The testing under irradiation of the FPGA that forms the core of the module is in progress; it is not yet clear whether fuse-link FPGAs will be necessary. The digital board EDR has been delayed by 3 months to June 2016 to accommodate the prototyping and radiation studies. Development of the digital board firmware (WP1.4.3) with design mitigation for single event upset (SEU) is underway and proceeding in parallel with the irradiation programme. The specification for basic functional readout for system integration is being developed and will continue into 2016. For the offdetector (PCIe40) firmware (WP1.4.4), the basic firmware for short term testing is being developed, including the data compression algorithms with the potential to reduce the number of required PCIe40s. The definition of the specification of the control software (WP1.4.5) is in progress (e.g. the configuration of the CLARO frontend chip, the readout control etc). Prototyping of the basic functionality will start early next year. In planning for the system test with pre-production electronics (WP1.4.6), the infrastructure at CERN will be commissioned during the third quarter of 2016. A PCIe40 is required for readout and although this has been ordered, it is unlikely to be available before the end of Q2 2016. Components will be replaced with prototype and pre-production prototypes of the final modules as they become available. We will also use the prototype firmware from WP 1.4.3 and 1.4.4. WP2 VELO WP2.1 VELO Software and Firmware Work on WP2.1.1, 2.1.3, 2.1.4 and 2.1.6 is progressing according to schedule with milestone M2.1.3A, having been met. WP2.1.2 has been removed as a result of the CG outcome (see above). The adoption of the GWT serialiser by the VELOPix chip, rather than GBT as used by other detectors, has meant that significant components of the common firmware of the experiment are not applicable in the VELO. Additional institutional effort (no cost to this project) was added to ensure this work remains on schedule. An FPGA workshop was held in Manchester in November 2015 and milestone M2.1.5.A met. The project is preceding well and it has been demonstrated in simulation that the prototype algorithms fit inside the available resources of the final FPGA, and the current prototype board has been extensively tested. 2.2 VELO Electronics, Data Links, Off Detector Electronics A detailed external review of the front-end electronics was conducted 17-18th November 2015. The review covered all parts of the electronics chain the UK is involved with. This includes: the hybrids that hold the pixel/sensor tile and allow the VELOPIX ASIC to be read out; the tapes that contain the data links and the LV and HV cabling through the vacuum; the electrical properties of the feedthroughs that allow the data to pass through the vacuum; the opto and power boards (OPB) that sit directly outside the VELO tank and performs opto-electrical conversion, LV distribution and control. Recent results have shown that there are some radiation hardness issues with the GBT chipset leading to an increase in current consumption at intermediate doses. This is believed to still fit within the cooling and power budget of the current design. The same issue may apply to a lesser extent to the VeloPix ASIC where a significant increase in current consumption would cause a problem. Studies have started to evaluate the detailed implications, hopefully it can still be accommodated by the present system but we have raised this issue as an additional item in the risk register. Hybrids Over the past year (2015) hybrids have been produced employing multilayer Kapton PCB technology to enable readout of ASICs. The hybrid EDR occurred in November 2015 completing an LHCC Milestone. Page 6 of 13 OFFICIAL SENSITIVE LHCb Upgrade OsC PAR 1(14) Half-sized electrical and full sized mechanical prototypes are now at an advanced stage of design. The hybrid design satisfies the required low mass and high frequency, radiation tolerance and wide temperature service requirements. Delivery of these hybrids is expected in Jan 2016. The electrical prototype are compatible with the prototype OPBs and will be evaluated together with those. High Speed Links & Feedthroughs Each VELO module will be readout out via 20 data links designed to operate at 5.12 Gbit/s and two control links (ECS/TFC) at 4.8Gb/s. Three variants (different pitch/spacing) were produced as “tapes” approximately 56cm long offering approx. 100 ohm differential impedance. Effort was invested in designing PCB’s that could act as electrical prototypes of the vacuum feed throughs. Even though the feedthroughs are no longer UK deliverables it was necessary to make electrical prototypes to evaluate the concept and to test the hybrids and OPBs. Simulation and measurement of the high-speed data tapes have been made. Currently effort is being invested in bringing the modelling and measurements into closer agreement before making the first prototypes in industry. Optical and Power Boards (OPB) The boards are located immediately outside the vacuum tank and provide electrical to optical conversion of data and control signals and provide the supply voltages. The board is based around the CERN developed radiation tolerant components from the versatile link and GBT family. A prototype design has been made supporting readout of a half-sized hybrid and will be produced in January 2015. These boards will together with the prototype hybrid and data tapes allow for the evaluation of the electrical design of the system once the VeloPix ASICs become available in April 2015. 2.3 Pixel Module Sensors have been designed, and sourced from Micron in the UK and HPK Japan and tested in testbeam. The sensor EDR occurred in June 2015 meeting milestone M2.3.1A and the corresponding LHCC milestone. The Micron sensors n-in-n design had a feature that gives slightly high current at edges. The use of n-in-n avoids the need for parylene coating which HPK cannot provide. Design is almost complete for a next generation of sensors which correct this feature and have minor geometrical improvements. Reception of detectors from Micron is expected late April 2016. UBM has been provided at ADVACAM, IZM and “bumping” was performed at IZM. IZM is the only company that claims to be able to handle the “thin-on-thin” bump bonding of thinned ASICS to thinned sensors and thus we expect IZM to be awarded the final production contract. Assembly Liverpool completed the manufacture of the module testing vacuum chamber, completing milestone M2.4.5A, and this has been commissioned in Manchester (assembly site) to the required pressure. The CO2 “blow” system has also been commissioned with a silicon-pyrex micro-channel plate. A new wire-bonder has been commissioned and test samples produced. A glue robot and pull tester were purchased. The silicon clean room space has been divided to allow R&D for other projects (notably ATLAS) to continue without impacting on the module assembly. A baseline module design was fixed meeting milestone M2.3.4A and will be reviewed in 2016. Risks remain on the thermal distortions of the module support structure. This stabilizing of design parameters has allowed the critical high precision double sided assembly jigs to be designed for the attachment of the sensors on micro-channel plate. These have been manufactured and preliminary tests show a placement precision of 5 microns can be achieved. Cooling The provision of the micro-channel substrate remains one of the largest UK contributions to the project. The EDR was held Nov 25th 2015 meeting an LHCC milestone. The dimensions and routing of the micro-channels has been finalised and substantial prototype work done on, metallization, connectors and pressure testing. Remaining issues that must be addressed before production readiness is achieved include: decision on substrate thickness, handling, wafer dicing techniques, the final technique used for soldering of the connectors. Although this technology is maturing rapidly substantial QA and pre-production testing will be required to ensure that the risks associated with the substrates are Page 7 of 13 OFFICIAL SENSITIVE LHCb Upgrade OsC PAR 1(14) minimized. Costs are on the edge and additional institutional staff resources are being supplied, a modest overspend is projected in this area in the finance tables and will be evaluated at the time of the PRR. Should additional redesign, and prototypes be required to address risks it is likely this will exceed the existing cost envelope. Good progress is being made on thermal modeling. 2.4 VELO Mechanics and Integration Detector-Half Bases Oxford is undertaking the design and manufacture of the detector-half bases. Manufacture will begin once the module and cable routing are finalised. Substantial work remains to be performed to finalize the Hood and Tertiary vacuum design. These influence a number of key decisions such as the detectorhalf, cable clamps and routing. UK effort for the upgrade mechanics is allocated at a 0.2FTE/year. This is proving to be insufficient to provide the required level of design oversight. We aim to increase the Liverpool and Oxford based effort to around 1.0 FTE (from institutional effort) for 2016 which will provide centralised system engineering and deliver a detailed programme for the final assembly and testing. An important issue that influences the whole project is the question of whether connectors will be permitted in the secondary (module) volume for the CO2 cooling. Connectors were not permitted for the first VELO and all connections were orbitally welded prior to module mounting. Due to the design of the modules this is no longer an option and either modules will require welding after being mounted OR the use of connectors. A programme of testing the suitability of connectors has been launched in the UK as no other partner has been found to take on this critical sub-programme. Non-approval of a connectorized design by the LHC vacuum group represents a risk to the project and has been added to the risk register. WP3 (Computing) The funding for WP3.2 only starts in 2017. Therefore there is no progress or change to report under this heading. LHCb held a software workshop in November 2015 specifically aimed at addressing upgrade computing. This will lead to a roadmap document early in 2016. 4. Outreach The LHCb discovery of pentaquarks was the largest CERN physics news story of the year, and named by the IOP as one of the physics breakthroughs of the year. We have applied for and been awarded a place at the 2016 Royal Society Summer Exhibition on the theme of "Antimatter matters", which will showcase the LHCb upgrade and the physics we hope to discover. This was the primary objective of our pathways to impact outreach section for this grant. 5. Industrial Liaison outwith UK workpackages While much of the general infrastructure for the upgrade proceeds via framework contracts, there will be opportunities in the upgrade of the PC farm and its infrastructure, as well as the general infrastructure as noted in the letter from the LHCb Upgrade Detector Coordinator of 30/4/2015. The timescale for the associated market surveys and invitations to tender will become clearer towards the end of 2016. The initial prototyping during the R&D phase of common hardware for the online system (PCIe optical readout boards) was carried out in the UK by Exception PCB. A market survey for the procurement of 325 such boards (MS-4080/PH/LHCB) with a value of more than CHF750k, was launched in June 2015 and will close in the coming weeks. UK companies have participated in the market survey, but details are not available until this closes. 6. Actions from previous meeting Action 1.2: technical questions. Replies submitted September 2015 Action 1.3: mitigation if no further funding available. Page 8 of 13 OFFICIAL SENSITIVE LHCb Upgrade OsC PAR 1(14) The current funding situation is discussed above. No detailed mitigation planning has been made though the international experiment has been kept fully informed of the funding situation. We stress that these elements were approved by science board and note the comparatively positive outcome of the CSR. We will discuss with STFC the timescale on which we expect to hear. Action 1.5: management organogram, internal and external STFC Oversight commi ee LHCb-UK Steering Board Project Management Team RAL Budget Holder Outreach WP1 RICH WP2 VELO WP3 Compu ng Industry Liaison Risk Manager Figure 1: LHCb-UK upgrade project structure with reporting lines. Figure 1 shows the bodies in the UK upgrade structure and their reporting lines. The role of the bodies, their make-up and the names of the post-holders are given in section 2 of the Project Management Plan. LHCC LHCb Collabora on Board LHC-RRB LHCb Management Safety Upgrade Planning Group RICH VELO Coordinators Compu ng Technical Board Upgrade Resources Board Figure 2: Upgrade structure in international LHCb Experiment with reporting lines Figure 2 shows the primary bodies in the international experiment upgrade structure relevant to the UK project. Oversight is provided by the CERN LHCC, comprised of leading international particle physicists, and the LHC Resources Review Board (RRB) for financial matters. The RRB is attended by representatives from STFC and the LHCb-UK PI. The upgrade planning group is chaired by the LHCb spokesperson. The LHCb management report to the LHCb Collaboration Board (CB), this is comprised of one member per institute. The collaboration has project leaders for each sub-detector element (current and upgrade), who appoint a deputy with particular responsibility for the upgrade and work closely with their UK project leader counterparts. The experiment has a number of co-ordinators including those for Technical, Resources and Outreach. The Technical co-ordinator chairs the Technical Board, which is attended by the Project Leaders. The Page 9 of 13 OFFICIAL SENSITIVE LHCb Upgrade OsC PAR 1(14) Upgrade resource co-ordinator chairs the Upgrade resources board, which is attended by the UK Upgrade PI. Major post holders are appointed by the CB for a fixed duration. The UK currently provides the LHCb spokesperson, the RICH and VELO project leaders and the deputy computing co-ordinator. Action 1.6: updates to risk register including non-technical risks. Updated version circulated in this documentation. Action 1.7: LHC schedule delay, revise milestones and deliverables Updated version circulated in this documentation. Action 1.8: Finance Template Completed and updated for LHC delay Action 1.10: support for staff during commissioning phase after LHC delay Discussed above. Key Milestones Key Milestones (including Deliverables) No. Description Baseline Date1 Target Completion Date Date Change2 A full milestone spreadsheet is provided updating all milestones where appropriate to accommodate the revised LHC schedule. 1 2 Determined by the dates presented in the PMP Any change in the target date from the previous meeting Page 10 of 13 OFFICIAL SENSITIVE LHCb Upgrade OsC PAR 1(14) Finances Financial Summary (£k) Project Projected Variance Approved Spend of Project (2)-(1) (1) (2) (3) 2,020 2,035 15 14 12 -2 Capital4 3,597 3,597 0 0 0 0 Resource5 280 280 0 0 0 0 Common Fund 1,810 1,810 0 143 143 0 Total 7,707 7,722 15 157 155 -2 Existing support 5,787 5,789 2 782 782 0 Approved (not awarded 2015 CG) 101 0 -101 0 0 0 Working Allowance 670 670 0 0 0 0 14,181 -84 939 937 -2 New Staff Costs3 Non-Staff Costs Budget to Date (FY) Spend to Date (4) (5) Variance to Date (5)-(4) (6) (CG/Core STFC) 14,265 Total Covers period to 1st October 2015. Risk Register Project Issues/Active Risks No. Issues/Risks identified 2.3.4 Microchannel plate layer does not achieve desired cooling, or is not vacuum qualified, or requires additional design effort. 3.2.5 UK share of Core computing not covered by UK Proposed/planned mitigation Engage with CERN experts and LHC vacuum group. Secondary solutions based on diamond (for example). Core computing must be covered by other countries delay to other areas, reduced performance at Run-II start Risk Status EDR successfully met. Safety system being designed. Need to continue close monitoring. Cuts made in 2015 CG outcome increase risk of loss of physics output The full risk register has been provided with updates. High risk items (prior to mitigation) are given here. 3 New Money and Effort Equipment 5 Consumables/Travel 4 Page 11 of 13 OFFICIAL SENSITIVE LHCb Upgrade OsC PAR 1(14) Upcoming Milestones Upcoming Milestones & Deliverables No. Description Original Date Optimised location and granularity of the photon detectors, photon optics. Photon Detector Optimisation Location – Final optimisations for EDRs. Nov-15 Nov-15 LHCC-M Place Photon Detector order and start production Completion Target Date ↔ Nov-15 Completed Nov-15 ↔ Nov-15 Completed Sep-15 Nov-15 Nov-15 Completed Apr-16 Apr-16 ↔ M1.2.2.A Photon detector test facilities fully commissioned ready to start production run M1.2.2.B Photon detector production testing starts Jun-16 Jun-16 ↔ LHCC-M RICH 1 Mechanics - EDR Jul-16 Jul-16 ↔ LHCC-M Digital Board - EDR Jun-16 Jun-16 ↔ M2.1.3.A Initial version tracking software Sep-15 M2.1.5.A First generation simulation & laboratory code Sep-15 Nov-15 Completed LHCC-M ASIC, Hybrid EDR Sep-15 Nov-15 Completed LHCC-M ASIC, Hybrid PRR Jul-16 Jul-16 ↔ Dependent on ASIC M2.2.1.A Flex Circuit Prototype Apr-16 Apr-16 ↔ M2.2.3.A Opto-electrical Board Prototype Apr-16 Apr-16 ↔ LHCC-M Sensor EDR Jun-15 Jun-15 ↔ LHCC-M Sensor PRR Jun-16 Jun-16 ↔ LHCC-M Cooling Substrate EDR Sep-15 Nov-15 Completed LHCC-M Cooling Substrate PRR Jul-16 Jul-16 ↔ Subject to Tender LHCC-M Module EDR Mar-16 Mar-16 ↔ Mechanical Protoype M2.3.1.A Sensor Prototypes qualified EDR Jun-15 Jun-15 ↔ D1.1.1 M1.1.1.B Nov-15 Change Notes Date Preparations proceeding well Apr-15 Page 12 of 13 Jun-15 Jun-15 Completed Completed Completed OFFICIAL SENSITIVE LHCb Upgrade OsC PAR 1(14) M2.3.1.A Prototype module design Dec-15 Dec-15 ↔ M2.4.5.A Delivery of vacuum system for module testing Jun-15 Aug-15 Dec-15 Completed Completed NB: To include all items within the next reporting period and any additional outstanding milestones from previous periods. All milestones since June 2015 (previous period) till July 2016 (next period) are included. Page 13 of 13
© Copyright 2026 Paperzz