Generator Cycling due to High Penetrations of Wind Power by Niamh Troy A thesis submitted to the School of Graduate Studies in fulfilment of the requirements for the degree of Doctor of Philosophy in the School of Electrical, Electronic and Communications Engineering University College Dublin, Ireland Supervisor of Research: Prof. Mark O’Malley Co-Supervisor of Research: Dr. Damian Flynn Nominating Professor: Prof. Mark O’Malley August 2011 Abstract Power systems have changed considerably in recent years. The introduction of deregulation has brought about competitive electricity markets, forcing generators to operate in a more flexible manner. Coupled with this, the rapid integration of wind power world-wide has introduced increased levels of variability and uncertainty into power system operation. This has led to generators being started up and shut down, ramped and operated at part-load levels more frequently, in order to meet an increasingly variable net load (load minus wind generation) and respond to unexpected net load changes. As base-load units are designed to achieve maximum fuel efficiency they tend to have limited operational flexibility and consequently this type of cycling operation results in serious degradation of plant equipment through various mechanisms such as thermal fatigue, erosion, corrosion, etc. leading to more frequent forced outages and reduced plant lifetime. Increased costs for base-load generators will also result from cycling operation, the most apparent being increased operations and maintenance (O&M) and capital costs resulting from deterioration of the components. However, fuel costs, environmental penalties and income losses will also arise. Quantifying these costs is challenging given the vast array of components affected and the time delay that is typical between cycling operation occurring and the damage manifesting itself. The uncertainty surrounding cycling costs can lead to these costs being under-estimated by generators, which in turn can lead to increased cycling. I This thesis examines how the operation of base-load units, coal and combined-cycle gas turbines (CCGTs) in particular, are impacted with increasing penetrations of wind generation on a system. The technical characteristics of these units, such as their startup times and contribution to system reserve requirements, are shown to influence the type and level of cycling that will be experienced. Despite collective agreement that more flexible generation is needed to support the variability and uncertainty of wind generation, it is shown here that paradoxically it is the most inflexible generation (i.e coal plants) that are the most rewarded as wind generation increases. Having identified that CCGT units are severely impacted by increasing wind penetrations and in many cases are forced into mid-merit operation, a novel operating strategy is investigated for these units. Many CCGTs include bypass stacks allowing them to vent exhaust gas directly into the atmosphere and bypass the steam section of the plant entirely. Running in this open-cycle manner, CCGTs will have reduced efficiency but can start-up quickly. This thesis examines if a system with increasing wind penetration can benefit from increased flexibility when CCGT units are allowed to operate in a multi-mode regime. It is shown that such operation can improve system reliability by increasing the sources of replacement reserve and that production from peaking capacity is displaced, reducing the need for such units to be built. Other options which are commonly cited as improving the flexibility of power systems include pumped storage, compressed air energy storage, interconnection and demand side management. Each of these can assist in balancing net load variability and so are considered beneficial to the integration of wind power, however typically their impact on the operation of base-load units has not been examined. This thesis investigates how various forms of flexibility can alleviate or aggravate cycling of base-load generation. It is found that many of these options will in fact be in competition with base-load generation to provide energy and/or reserve to the system and so can actually increase plant cycling. On the premise that penetrations of variable renewables will continue to increase for the foreseeable future, and that cycling operation will be a growing concern for generators, this thesis presents a novel formulation for cycling related costs to be represented in a unit commitment algorithm. Incremental cycling costs related to start-ups II or ramping can be represented using the new formulation and depending on the level of knowledge that is available, the resulting cost function can be linear, piece-wise linear or step shaped. This new approach to modelling cycling costs has applications for both long-term planning studies and real-world scheduling models. A case study on a 20 unit system was carried out and the inclusion of the new cycling cost formulation was shown to reduce cycling operation, distribute the burden of cycling more evenly across the units and reduce overall system costs relative to the case where cycling costs were not modelled. III Contents Abstract I Publications Arising from Thesis VII Acknowledgements VIII Acronyms and Symbols X Nomenclature XII 1 Introduction 1.1 Evolving Power Systems and the Rise of Wind Power . 1.2 Impact of Wind Power on System Operation . . . . . 1.3 Wind Power on the Irish Power System . . . . . . . . 1.4 Thesis Objectives . . . . . . . . . . . . . . . . . . . . . 1.5 Summary of Thesis Contributions . . . . . . . . . . . . 1.6 Thesis Overview . . . . . . . . . . . . . . . . . . . . . 2 Cycling of Thermal Plant 2.1 Introduction . . . . . . . . . . . . . . . . 2.2 Damage to Power Plants Due to Cycling 2.3 Cycling Costs . . . . . . . . . . . . . . . 2.4 Next Generation Thermal Plant . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 Unit Commitment with High Wind Power Penetrations 3.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.2 The Wilmar Planning Tool . . . . . . . . . . . . . . . . . . 3.2.1 The Scenario Tree Tool . . . . . . . . . . . . . . . . 3.2.2 The Scheduling Model . . . . . . . . . . . . . . . . . 3.3 Other Unit Commitment Models . . . . . . . . . . . . . . . 3.4 The Irish 2020 Test System . . . . . . . . . . . . . . . . . . IV . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 1 4 7 10 11 12 . . . . 14 14 15 18 21 . . . . . . 22 22 23 23 24 28 29 4 Cycling of Base-load Plant on the Irish Power System 4.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4.2 Scenarios Examined . . . . . . . . . . . . . . . . . . . . . . . . . . . 4.3 Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4.3.1 Increasing Wind Penetration and the Operation of Base-Load 4.3.2 Sensitivity Analysis . . . . . . . . . . . . . . . . . . . . . . . 4.3.3 Effect of Modelling Assumptions . . . . . . . . . . . . . . . . 4.4 Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 Multi-mode Operation of Combined-Cycle Gas Turbines 5.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . 5.2 Methodology . . . . . . . . . . . . . . . . . . . . . . . . . . 5.3 Test System . . . . . . . . . . . . . . . . . . . . . . . . . . . 5.4 Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5.4.1 Utilization of the Multi-mode Function . . . . . . . 5.4.2 Benefits Arising from Multi-mode Operation . . . . 5.4.3 Sensitivity Studies . . . . . . . . . . . . . . . . . . . 5.5 Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6 Power System Flexibility and the Impact on Plant Cycling 6.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.2 Methodology . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.3 Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.3.1 Impact on the Operation of Base-load Units . . . . . . . 6.3.2 Impact on Wind Curtailment and CO2 Emissions . . . . 6.4 Summary of Results . . . . . . . . . . . . . . . . . . . . . . . . 6.5 Other Flexibility Options . . . . . . . . . . . . . . . . . . . . . 6.5.1 Battery Electric Vehicles . . . . . . . . . . . . . . . . . . 6.5.2 Maintenance Scheduling . . . . . . . . . . . . . . . . . . 6.5.3 Control of Wind Power Output . . . . . . . . . . . . . . 6.5.4 Market Options . . . . . . . . . . . . . . . . . . . . . . . 7 Unit Commitment with Dynamic Cycling Costs 7.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . 7.2 Formulation of Dynamic Cycling Costs . . . . . . . . 7.2.1 Cycling Costs Related to Start-ups . . . . . . 7.2.2 Cycling Costs Related to Ramping . . . . . . 7.3 Model and Test System . . . . . . . . . . . . . . . . 7.4 Results . . . . . . . . . . . . . . . . . . . . . . . . . . 7.4.1 Start-up Related Cycling Costs Results . . . 7.4.2 Ramping Related Cycling Costs Results . . . 7.4.3 Start-up and Ramping Cycling Costs Results 7.5 Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33 . . 33 . . 34 . . 37 Units 37 . . 43 . . 49 . . 50 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53 53 56 60 61 62 66 71 77 . . . . . . . . . . . 79 79 81 84 84 91 92 93 93 94 96 96 . . . . . . . . . . 98 98 99 100 104 108 113 113 117 118 120 8 Conclusions 122 8.1 Future Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 124 V References 127 Appendix A. Probability distribution of net load ramps 136 Appendix B. Cycling data for CCGT and coal units 138 Appendix C. Base-load cycling with/without storage/interconnection 141 Appendix D. Fuel Cost Curves 143 Appendix E. Publications 145 VI Publications Arising from Thesis Journal Publications: 1. Troy, N., Flynn, D., Milligan M. and O’Malley, M. “Unit Commitment with Dynamic Cycling Costs”, IEEE Transactions on Power Systems, in review. 2. Troy, N., Flynn, D. and O’Malley, M. “Multi-mode Operation of Combined-Cycle Gas Turbines with Increasing Wind Penetration”, Accepted to IEEE Transactions on Power Systems 3. Troy, N., Denny, E. and O’Malley, M. “Base-load cycling on a system with significant wind penetration”, IEEE Transactions on Power Systems, vol. 25, issue 2, pp. 1088 - 1097, 2010. Conference Publications: 1. Troy, N. and O’Malley, M. “Multi-mode Operation of Combined-Cycle Gas Turbines with Increasing Wind Penetration”, in Proceedings of the IEEE Power & Energy Society General Meeting, Minnesota, USA, July 2010. 2. Troy, N. and Twohig, S. “Wind as a Price-Maker and Ancillary Services Provider in Competitive Electricity Markets”, in Proceedings of the IEEE Power & Energy Society General Meeting, Minnesota, USA, July 2010. 3. Troy, N., Denny, E. and O’Malley, M. “Evaluating which forms of flexibility most effectively reduce base-load cycling at large wind penetrations”, in Proceedings of the 8th International Workshop on Large-Scale Integration of Wind Power, Bremen, Germany, October 2009. 4. Tuohy, A., Troy, N., Gubina, A. and O’Malley, M. “Managing wind uncertainty and variability in the Irish power system”, in Proceedings of the IEEE Power & Energy Society General Meeting, Calgary, USA, July 2009. 5. Troy, N., Denny, E. and O’Malley, M. “The relationship between base-load generation, start-up costs and generator cycling”, in Proceedings of the 14th Annual North American Conference of the International Association of Energy Economics, Louisiana, USA, December 2008. VII Acknowledgements I would like to thank everybody whose help and support contributed to this thesis, but in particular the following: My supervisor Professor Mark O’Malley for his guidance and encouragement over the past four years. Through his hard work and efforts I have benefited from many wonderful opportunities for which I am extremely grateful and consider myself lucky to have found such a dynamic mentor. My co-supervisor Dr Damian Flynn for the enthusiasm and time he invested in my work. His attention to the finest detail is exemplary and I am very thankful for the effort he put into my thesis. Dr. Eleanor Denny for her support, insights and advice in the earlier stage of my PhD. Dr. Aidan Tuohy, to whom I am indebted for getting me up to speed with the Wilmar model and answering my many annoying questions even when busy writing up his own thesis. Dr. Michael Milligan for hosting me at NREL and indeed all the other members of the Grid Integration Group. My time at NREL was both insightful and enjoyable and I am very grateful for the opportunity. Dr. Jonathan O’Sullivan and Sonya Twohig for hosting me at EirGrid and for many interesting discussions during that time. Ms Magdalena Szczepanska for all her help over the past four years and for keeping things running smoothly. All the students at the ERC who have been good fun and great friends. I look forward to many more adventures together! VIII My parents, grandparents, extended family and friends, for their support and for providing relief from my academic pursuits. But most especially I’d like to thank Shane for always being kind, supportive and patient. I could not have done it without you. IX Acronyms and Symbols ADGT Aero-derivative gas turbine AIGS All Island Grid Study ARMA Auto-regressive moving average BNE Best new entrant CAISO California Independent System Operator CCGT Combined-cycle gas turbine CEMS Continuous Emissions Monitoring Scheme CHP Combined heat and power CO Carbon monoxide CO2 Carbon dioxide DOE Department of Energy (US) DSM Demand side management EDUD Expected duration of unmet demand ELCC Effective load carrying capability EPRI Electric Power Research Institute ERCOT Electric Reliability Council of Texas EU European Union EV Electric vehicle EWEA European Wind Energy Association X GADS Generating Availability Data System GAMS Generic Algebraic Modeling System GE General Electric HRSG Heat recovery steam generator IRRE Insufficient ramping resource expectation LOLE Loss of load expectation NEPOOL New England Power Pool NERC North American Electric Reliability Council OCGT Open-cycle gas turbine O&M Operations and maintenance PHEV Plug-in hybrid electric vehicle REFIT Renewable energy feed-in tariff ROC Renewable Obligation Certificate ROCOF Rate of change of frequency RPS Renewable Portfolio Standards SEM Single Electricity Market SONI System Operator Northern Ireland SPP Southwest Power Pool STT Scenario Tree Tool TR1 Tertiary operating reserve (Ireland) UK United Kingdom US United States V2G Vehicle-to-Grid XI Nomenclature Chapter 3 & 5 Indices ccgt CCGT units ccgtopen CCGT units in open-cycle mode g Units i Interval of the start-up process s Scenarios t Time Parameters Pgmin Minimum power output for unit ’g’ (MW) Pgmax Maximum power output for unit ’g’ (MW) PU (g, i) Power output for unit ’g’ at interval ’i’ of the start-up process (MW) Startf uelg Start-up fuel required by unit ’g’ (GJ) U Dg Duration of start-up process for unit ’g’ (h) Binary Variables Online 0/1 variable equal to 1 if unit ’g’ is online in scenario ’s’, at time ’t’ Vs,t,g Start 0/1 variable equal to 1 if unit ’g’ is started in scenario ’s’, at time ’t’ Vs,t,g Shut 0/1 variable equal to 1 if unit ’g’ is started in scenario ’s’, at time ’t’ Vs,t,g XII p(s,t,g) power output for unit ’g’, in scenario ’s’, at time ’t’ (MW) Positive Variables Start Start-up fuel used if unit ’g’ is started in scenario ’s’, at time ’t’ (GJ) F uels,t,g PgOf f Offline contribution to replacement reserve from unit ’g’ in scenario ’s’, at time ’t’ (MW) Chapter 7 Indices/Sets t, T Time step, set of time steps g, G Units, set of units i, I Interval of cycling cost function, set of intervals of cycling cost function j, J Level of ramp, set of all ramp levels l, L Segment of the piecewise linearisation of the variable cost function, set of all segments of the piecewise linearisation of the variable cost function Constants costSg Cycling cost increment for each additional start ThSg (i) ith threshold corresponding to cumulative start-ups costSg (i) Cycling cost increment for each additional start-up, while NS (t,i) < ThS (i+1) Rg production change (MW) over time period ‘t’ deemed damaging for unit ‘g’ Rg (j) jth production change (MW) over time period ‘t’ deemed damaging for unit ‘g’ costR g Cycling cost increment for each additional ramp > R ThR g (i) ith threshold corresponding to cumulative ramps costR g (i) Cycling cost increment for each additional ramp, while NR (t,i) < ThR (i+1) costX g Cycling cost increment for each additional bi-directional ramp ThX g (i) ith threshold corresponding to cumulative bi-directional ramps XIII costX g (i) Cycling cost increment for each additional bi-directional ramp, while NX (t,i) < ThX (i+1) Ig Total number of intervals in cycling cost function for unit ‘g’ j̄g Number of ramp levels defined for unit ‘g’ P̄g Maximum capacity for unit ‘g’ P g Minimum capacity for unit ‘g’ Ag Fixed cost for unit ‘g’($/h) ag , bg , cg Coefficients of the quadratic production cost function of unit ‘g’ NLg Number of segments in piecewise linearization of the variable cost function for unit ‘g’ Fl g Slope of segment l of the variable cost function for unit ‘g’ Tl g Upper limit of segment ‘l’of the variable cost function of unit ‘g’(MW) U Tg Minimum up time for unit ‘g’ DTg Minimum down time for unit ‘g’ T̄ Number of hours in the planning period Tgcold Number of hours unit must be offline for, beyond its minimum downtime, before it is considered to be in a cold state ccg Start up cost for cold start for unit ‘g’ hcg Start up cost for hot start for unit ‘g’ hup Number of hours unit ‘g’has been online for at start of planning period (h) hdown Number of hours unit ‘g’has been offline for at start of planning period (h) M Large number α, β, γ Scaling factors Binary Variables sg (t) equal to 1 when a unit starts up at time t, zg (t) equal to 1 when a unit shuts down at time t, vg (t) equal to 1 when a unit is online at time t, stepSg (t, i) equal to 1 when NS (t,1) ≥ ThS (i) at time t, rg (t) equal to 1 when a unit undergoes ramp > Rg between time t and t-1, XIV rg (t, j) equal to 1 when a unit undergoes ramp > Rg (j) between time t and t-1, stepR g (t, i) equal to 1 when NS (t,1) ≥ ThR (i) at time t, upg (t) equal to 1 when production at time t > production at t-1, downg (t) equal to 1 when production at time t < production at t-1, xg (t) equal to 1 when ramping switches direction between consecutive periods, stepX (t, i) equal to 1 when NX (t,1) ≥ ThX (i) at time t. Positive Variables NSg (t) Cumulative start-ups, NSg (t,i) Cumulative start-ups beyond threshold ThS (i), CSg (t) Total cycling cost attributed to start-ups, NR g (t) Cumulative ramps > Rg , NR g (t,i) Cumulative ramps > Rg beyond threshold ThR (i), CR g (t) Total cycling cost attributed to ramping, NX g (t) Cumulative incidents of bi-directional ramping, NX g (t,i) Cumulative incidents of bi-directional ramping beyond threshold ThX (i), CX g (t) Total cycling cost attributed to bi-directional ramping, cpg (t) Production cost for unit ‘g’ at time ‘t’, csg (t) Start-up fuel cost for unit ‘g’ at time ‘t’, pg (t) Output (MW) for unit ‘g’ at time ‘t’, D(t) System demand (MW) at time ‘t’, δl (g,t) Variable used in the linearization of the variable cost function of unit ‘g’ at time ‘t’, represents the lth segment (MW). XV CHAPTER 1 Introduction 1.1 R Evolving Power Systems and the Rise of Wind Power ECENT years have seen the power generation sector undergo significant changes. Traditionally electricity systems were operated by vertically integrated monopo- lies whose main aim was to meet the demand as opposed to minimising cost (Narula et al., 2002). However, by the 1980s deregulation and unbundling of utilities was seen as a means of improving economic performance. In 1982 Chile kick-started electricity deregulation by passing a law which allowed large consumers of electricity to choose their retailer and negotiate their prices freely. In 1990 the United Kingdom (UK) government privatised the electricity supply industry, which led to other Commonwealth countries, notably New Zealand and Australia, also pursuing deregulation. The European Union (EU) directive 96/92 introduced in 1996 required Member States to create competitive electricity markets, whilst by the late 1990s many states in the United States (US) were also moving towards deregulation (Al-Sunaidy and Green, 2006). 1 Chapter 1. Introduction 2 Figure 1.1: Increased cycling due to introduction of electricity market in Ontario (APPrO, 2006) In the resulting competitive and volatile marketplaces that were created, generators which had previously operated as base-load plant were often forced into flexible operation (Kitto Jr et al., 1996; Narula et al., 2002). Figure 1.1 which illustrates increased plant start-ups following the introduction of a competitive electricity market in Ontario provides an example of how greater flexibility is required in competitive markets. In a competitive marketplace, energy traders or suppliers, seeking to maximise profitability, will offer generation into power, exchange and ancillary service markets requiring units to have short start-up times and good cycling capabilities. The ability to operate flexibly can bring considerable economic advantage for generators, as they have increased opportunities to earn revenue from the market, such as through hourly and seasonal market arbitrage or peak shaving for example (Balling and Hofmann, 2007). However, the financial pressure to reduce capital costs in a competitive market can often lead to power generating companies purchasing plants with cheaper and consequently poorer performing components, which are more susceptible to cycling related wear and tear. As such, older coal plants have been found to be more rugged and cost effective to cycle compared to newer combined-cycle units (Lefton and Besuner, 2006). Meanwhile, the acceptance that anthropogenic greenhouse gas emissions are resulting in climate change has led to the introduction of energy policies seeking to reduce the Chapter 1. Introduction 3 environmental impact of electricity generation. Supporting renewable energy sources and energy efficiency measures has been identified as vital to achieving emission reductions. Coupled with this, rising fossil fuel prices and instability in countries where fossil fuels are sourced has led to widespread backing of renewables as a means of improving security of supply and reducing exposure to fossil fuel price volatility. In 2008 the EU imposed demanding climate and energy targets known as the ‘20-20-20’ targets which are to be met by 2020. These aim to reduce EU greenhouse gas emissions by 20% below 1990 levels, supply 20% of energy consumption from renewable energy sources and reduce primary energy consumption by 20% through energy efficiency measures (EU, 2008). Although the US has no comprehensive long-term energy policy, initiatives such as Renewable Portfolio Standards (RPSs) and Renewable Energy Certificates (RECs) have been taken at a state level to increase the use of renewable energy (Black & Veatch, 2011). Thus 28 out of 50 US states have set compulsory targets seeking renewable energy penetrations up to 40%, with a further 5 states having voluntary targets (DOE, 2009). Wind power, now a proven and mature technology which offers near-zero emissions and operating costs, represents a feasible means of meeting emissions and renewable energy targets and consequently has experienced rapid growth over the past decade. The cumulative installed wind power capacity in the U.S stood at 41.4 GW in the first quarter of 2011 (AWEA, 2011b), just behind China which is set to reach 58 GW by the end of 2011 (Castano, 2011). In Europe the total installed wind capacity exceeds 84 GW, with countries such as Germany, Spain and Denmark representing the largest shares. In terms of energy penetration however, Denmark, Portugal, Spain and Ireland lead the way, as seen for 2009 in Figure 1.2 (IEA, 2010). In spite of the unprecedented economic downturn, the annual growth rate for wind power has remained high with the installed wind power capacity in the EU increasing by 12.4% in 2010, compared with 15% in the US (AWEA, 2011a; EWEA, 2011c). This rapid pace of wind power installation is set to continue through the coming years, as with the majority of hydro resources already exploited, wind power (and solar power in some countries) represents the most scalable and competitive means of achieving 2020 Chapter 1. Introduction 4 Figure 1.2: Top 10 highest wind penetrations, as % of electricity consumption, in EU countries (IEA, 2010) targets. Up to now wind power has been supported by some form of subsidy such a feed-in tariff or renewable certification scheme. However, with growing sales and larger and more efficient turbines the cost of wind power is, in some countries (Brazil, Sweden, Mexico and US) similar to the cost per MWh of coal generation and consequently it may be possible to phase out subsidies over the coming years without hampering wind power development (Bloomberg, 2011). EWEA (European Wind Energy Association) predicts between 230 and 265 GW of installed wind power in Europe for the year 2020 (40 GW of which is assumed to be offshore wind) which would supply between between 14.4% and 16.7% of the total electricity demand (EWEA, 2011b). 1.2 Impact of Wind Power on System Operation As higher penetrations of wind power are achieved, power system operation becomes increasingly complex due to the variable and unpredictable nature of wind power. Traditionally system demand has been largely predictable as demand profiles follow daily, weekly and seasonal patterns, allowing generation to be efficiently committed. Wind power however introduces another element of uncertainty and thus systems with significant levels of wind need to utilise wind forecasts when committing and dispatching Chapter 1. Introduction 5 generation. Approaches to wind forecasting can be categorised as physical or statistical, with modern forecasting systems employing a combination of the two. Physical approaches, namely weather prediction models, which are typically used for horizons of 6 to 72 hours, utilise data such as land and sea surface temperatures to physically model atmospheric dynamics. Statistical approaches transform meteorological predictions into wind generation (often using artificial-intelligence based models) and are found to give better accuracy for horizons up to 6 hours (Monteiro et al., 2009). The desire of system operators for information regarding the reliability of forecast has led to ensemble or probabilistic forecasts becoming popular. Ensemble forecasting produces multiple forecasts, by varying the input parameters or by using multiple weather prediction models, to generate a probability density function of the most likely outcome (Möhrlen et al., 2007). Wind power forecast error however, increases with the forecast horizon and even when these state-of-the-art methods of forecasting are employed, the day-ahead wind forecast error (root mean square error) for a region can be 8-12% of the total wind capacity as reported in Siebert (2008), which can result in thermal units being over- and under-committed (Ummels et al., 2007). Thus power systems with large wind power capacities will need to re-evaluate commitment decisions on a continual basis as more up-to-date wind forecasts become available. The unpredictable nature of wind power also requires conventional plant to carry additional reserves in order to maintain system reliability, should an unexpected drop in wind power occur. Many approaches have been proposed to determine how much wind power increases the reserve requirement on a given system and it has often been found that the increased reserve requirements represents only a small percentage of the wind power output (Dany, 2001; Doherty and O’Malley, 2005; Holttinen et al., 2008; Holttinen, 2005) The variable nature of wind power will increase variability in net load (load minus wind generation), which must be met by conventional generation on the system, resulting in a greater demand for operational flexibility from these units (Ummels et al., 2007; Holttinen, 2005). Expected or unexpected reductions in net load, which can arise due to declining wind power output, will force conventional plant to ramp up their output, or if sufficient ramping capability is not available, fast-starting units will need to come Chapter 1. Introduction 6 online. Periods of low demand coinciding with high wind power output can lead to conventional plant being shut down, a problem which has been exacerbated of late due to a reduction in demand as a result of widespread economic recession (Axford, 2009). The culmination of adding more variability and unpredictability to a power system is that thermal units will undergo increased start-ups, ramping and periods of operation at low load levels, collectively termed “cycling” (Braun, 2004; Göransson and Johnsson, 2009; Holttinen and Pedersen, 2003; Meibom et al., 2009). Furthermore, in some systems wind is allowed to self-dispatch, so the forecast output from wind farms is not included in the day-ahead schedule. This can lead to increased transmission constraints which will further intensify plant cycling (GE, 2005). Many systems are currently experiencing increased plant cycling as a result of wind power and wind integration studies are predicting this problem to worsen. The Southwest Power Pool (SPP) wind integration study noted that in order to accommodate higher wind penetration levels more operational flexibility (i.e. more start-ups and cycling of units) would be required and this would increase as the forecast error increases (Charles River Associates, 2010). The Californian Independent System Operator’s (CAISOs) renewables integration study had similar findings, but with combinedcycle gas turbine (CCGT) units specifically identified as undergoing increased cycling. Relative to a 2012 reference case, CCGT plant start-ups increased by 35% with 20% renewables on the system. Both the ‘NYISO 2010 Wind Generation Study’ and the ‘New England Wind Integration Study’ also found that the operation of CCGTs was significantly impacted by an increased penetration of wind power (NYISO, 2010; GE, 2010). The Nova Scotia wind integration study predicted that start-ups for large thermal units would be significantly increased as wind penetrations increased and acknowledged that the cost impact of this was not fully understood (Hatch, 2008), while Xcel Energy are currently experiencing cycling of their coal fleet due to high wind penetrations in Colorado. In Göransson and Johnsson (2009), which studied the power system of Western Denmark, the capacity factor for units with low start-up and turn-down performance and high minimum load levels (i.e. base-load units) were found to be the most significantly impacted by wind power, while Oswald et al. (2008) found that more ramping Chapter 1. Introduction 7 will be required from fossil fuel plants on the British system to maintain the power balance. Wind power will also impact a system’s dynamic performance. As wind power will tend to displace conventional generation, it will also displace the inertial response provided by these units, which is vital to maintain system security when faults or outages occur. In addition, wind turbines supply asynchronous power to the system which can impact the system’s voltage stability. However, it is possible to implement control features to emulate inertial response and mitigate the impact on voltage stability and these will be necessary in order to increase the upper limit to the maximum penetration of wind power on a system. 1.3 Wind Power on the Irish Power System Situated on the western edge of Europe, Ireland is well positioned to benefit from strong Atlantic winds and consequently has one of the best wind resources in the world (SEAI, 2010), as seen in Figure 1.3. The current installed wind capacity in Ireland stands at over 1.8 GW, which provides in excess of 10% of the electrical energy demand and another 4 GW of proposed wind capacity is in various stages of planning. The growth of wind power in Ireland is also supported by ambitious Government targets (40% of all electricity consumption to come from renewables by 2020) and competitive feedin tariffs (REFIT in Republic of Ireland and ROCs in Northern Ireland). REFIT (Renewable Energy Feed-In Tariff) is guaranteed for up to 15 years (but not to extend beyond 2024) and is paid to suppliers to encourage them to enter into power purchase agreements with wind generators. The REFIT is linked to the Best New Entrant (BNE) generator and has averaged at e57/MWh for large scale wind and e59/MWh for small scale wind in previous years. The ROCs (Renewable Obligation Certificate) scheme in Northern Ireland is somewhat different in that an obligation to purchase renewable generation is mandated on suppliers. The Irish system is small and relatively electrically isolated: a 500 MW interconnec- Chapter 1. Introduction 8 Figure 1.3: Wind resource in Europe (Risø National Laboratory, 1989) tor is in place linking Northern Ireland and Scotland, however, trading arrangements limit exports from Ireland to Great Britain to a maximum of 70 MW and with power exchanges set one month ahead of time, Ireland infrequently exports power. Therefore, variations in power output and high penetrations of wind generation are managed domestically by conventional generation rather than by exchanges to Great Britain. As such, record high instantaneous wind penetrations, in excess of 50%, have been experienced on the Irish system, as seen in Table 1.1. This is resulting in increased cycling of conventional generation on the Irish system as seen in Table 1.2, which compares the annual number of plant start-ups for three CCGT units in 2008 and 2010. Consequently the Market Monitoring Unit (MMU) within the Energy Regulatory Authorities has identified power plant cycling as one of the foremost concerns of thermal power generators operating in SEM (Single Electricity Market), the electricity market of the Republic and Northern Ireland (MMU, 2010). However, MMU (2010) attributes the intense plant cycling that some plants are experiencing to the introduction of SEM Chapter 1. Introduction 9 and the subsequent increase in competition rather than the increasing wind power penetration. Table 1.1: Wind penetration on the Republic of Ireland and Northern Ireland systems Installed Wind (MW) Maximum Output (MW) Maximum Energy Penetration (%) Maximum Daily Energy Penetration (%) Republic of Ireland 1455 1323 52.3 37 Northern Ireland 355 320 50 29 Table 1.2: Annual plant start-ups Unit Huntstown 1 Tynagh Dublin Bay Power 2008 23 27 7 2010 63 45 37 In anticipation of the challenges facing power system operation with such high wind penetrations, the Irish Governments commissioned a study entitled the ‘All Island Grid Study’ (AIGS), published in 2008, to examine the ability of the 2020 Irish power system to handle various amounts of electricity from renewable sources. Various levels of installed wind capacity ranging from 2000 MW to 8000 MW were examined in this study, with an assumed peak demand of 9.6 GW assumed. The study was divided into several workstreams, the most relevant to this work being ‘Workstream 2B’, which utilized a stochastic unit commitment and economic dispatch model to examine system operation under the various renewable scenarios (AIGS, 2008). The key results of this workstream, which are particularly relevant to the work of this thesis are as follows: “With increasing wind power capacity installed, extreme values and the standard deviation of the variation of the net load (load minus wind power production in the actual hour) increases as well. Hence, the power plant portfolio has to show enough flexible units (for example with sufficient ramp up and down rates as well as low start-up times) to be able to follow the net load.” “Generally, the bigger part of the electricity production in the All Chapter 1. Introduction 10 Island power system from conventional power plants is borne by coal fired plants and newer CCGTs. With increasing wind power capacity installed, the production and capacity factors of these units tends to be decreased.... Coal fired units and newer CCGTs have a relative low number of start-ups and high number of online hours. The number of start-ups of these units tends to be increased with increasing wind power capacity installed.” Following on from the All Island Grid Study, the tranmsission system operators of Northern Ireland (SONI) and the Republic of Ireland (EirGrid) conducted a comprehensive study to better understand the technical and operational implications associated with high shares of renewable energy called the ‘All Island TSO Facilitation of Renewbles Studies’, which identified two key limitations to wind power penetration, namely (i) frequency stability after a loss of generation and (ii) frequency and transient stability after severe network faults. This study suggested that the maximum amount of ‘inertialess power’ (wind power and interconnector imports) that the system could cope with lies between 60% and 80%, but could be as low as 50% unless ROCOF relays on distribution connected wind farms were disabled. Nonetheless, the study found that the limitations for instantaneous wind penetration did not fundamentally conflict with the 2020 policy targets aiming at 40% electricity from renewables by 2020 (EirGrid and SONI, 2010a). 1.4 Thesis Objectives The main objective of this research has been to investigate how the operation of thermal plant will be impacted by high penetrations of wind generation on a power system. Base-load coal and CCGT units in particular are examined, as these units, having been designed for maximum fuel efficiency, tend to have limited operational flexibility. As such, when subjected to cycling operation these units can accrue large levels of damage to plant components, leading to increased maintenance requirements and forced outage rates. In examining the operational impacts of high wind power penetrations on CCGT Chapter 1. Introduction 11 units, a novel operating strategy for these units was identified, which involved allowing CCGTs to switch between combined- and open-cycle mode when economically optimal. The potential benefits and impacts of this new multi-mode strategy are investigated in this research. In an effort to improve power system flexibility and support integration of variable renewable generation, various flexibility options such as storage, interconnection and demand side management are commonly put forward in the literature. Analysis of these options is typically concerned with their profitability in a system or their impact on system production costs, wind curtailment or emissions, while the impact on base-load generation is typically over-looked. This research investigates how incorporating such flexibility options (and others) into a power system will impact cycling of base-load units in a high wind power scenario. Finally, having identified that the operation of base-load plant will be significantly impacted as wind power penetrations increase, this research develops a unit commitment formulation to allow cycling related costs to be modelled in a dynamic manner. The impact of accounting for cycling costs in a dynamic manner on plant dispatch is evaluated. 1.5 Summary of Thesis Contributions The novel contributions emanating from this thesis can be categorised as (i) the identification and investigation of a new operating strategy for CCGT units in a high wind power scenario, (ii) the investigation of how various power system sources of flexibility will impact the operation of base-load plant and (iii) the development of a new unit commitment formulation to allow cycling costs to be modelled dynamically, such that they accumulate over time based on plant operation, reflecting increased wear to plant components and reduced plant life-time. Examining the potential for running CCGT units in open-cycle mode, as well as combined-cycle mode, revealed that a system can benefit from the additional fast- Chapter 1. Introduction 12 starting capacity. The increased replacement (non-spinning) reserve availability from CCGT units in open-cycle mode also results in increased system security. Furthermore, open-cycle operation of CCGT units will displace production from conventional peaking units, reducing the need for such units to be built and thus indicating a societal benefit. Sensitivity studies revealed how the usage of this multi-mode function will be dependent on the underlying level of flexibility present in the system. Optimizing the system stochastically or allowing intra-day trading on interconnectors reduced the need for flexibility to be extracted from generators and consequently resulted in less frequent deployment of the multi-mode function. The impact of various sources of power system flexibility, such as storage, interconnection or demand side management, on the operation of base-load plant has been examined in this thesis. A side-by-side comparison reveals which are effective at reducing plant cycling, or alternatively which will aggravate plant cycling, in a high wind power context. The results are somewhat surprising as it was found that many of these options will in fact be in competition with base-load generation to provide energy and/or reserve to the system and so actually increase plant cycling. A novel unit commitment formulation was developed which utilises binary variables to incur a dynamic incremental cost when cycling operation occurs. The types of operation which elicit a cycling related cost can be plant start-ups or ramping. The cycling cost accumulates in tandem with plant operation such that it influences the dispatch decisions. This formulation has particular applications for long term studies, such as wind integration studies, as it can reflect the depreciation of a plant and potentially show how the merit order of generation can be altered over time. A case study in which this new formulation was implemented revealed that by modelling cycling costs dynamically, the burden of cycling operation will, over time, be distributed more evenly across the fleet of generators. 1.6 Thesis Overview The remainder of this thesis is organised as follows: Chapter 1. Introduction 13 • Chapter 2 describes the effects of cycling operation on plant equipment and the damage mechanisms involved. It describes the cost components which make up the total cost of cycling a unit and the difficulties in calculating these costs. Various approaches which have been used to approximate these costs are also described. • Chapter 3 describes the stochastic unit commitment and economic dispatch modelling tool that was used in this thesis. A detailed description of the test system is also provided. • Chapter 4 examines how the operation of base-load units, coal and CCGT units specifically, will be impacted with an increasing wind penetration. Sensitivities are also conducted to examine the level of cycling these units would undergo in the absence of pumped storage or interconnection on the system. • Chapter 5 examines the potential for multi-mode operation of CCGT units under various wind scenarios to determine if this new mode of operation can deliver benefits to the power system, via increased flexibility, or the generators themselves, via increased generation opportunities. • Chapter 6 examines how various flexibility options, namely pumped storage, interconnection, demand side management (DSM), multi-mode operation of CCGTs and reduced minimum generating levels impact the operation of base-load units. A side-by-side comparison of these options reveals which are the most effective at reducing cycling of base-load plant. • Chapter 7 presents a novel formulation for modelling the cycling costs in a dynamic manner within a Mixed Integer Programming (MIP) unit commitment model. The formulation can be used to implement incrementing cycling costs for starts or ramps for linear, piece-wise linear or step cycling cost functions. • The thesis is concluded in Chapter 8. CHAPTER 2 Cycling of Thermal Plant 2.1 Introduction A S discussed in Chapter 1, the increased variability and uncertainty that arises when wind power is integrated into a power system can lead to more flexible operation or ‘cycling’ being demanded from conventional plants. In addition to wind power, the competitive markets in which these units operate are also a significant driver of plant cycling as generators are forced into more market-orientated, flexible operation to increase profits, while at the same time maintenance intervals are often lengthened in order to minimize downtime and costs. An overcapacity of generation on a system can also exacerbate plant cycling as less efficient plant may be prematurely forced down the merit order. Thermal plant can be broadly categorised as base-load, mid-merit or peaking. Midmerit units follow the daily demand profile and shut down nightly whilst peaking units 14 Chapter 2. Cycling of Thermal Plant 15 are used to meet the extreme peaks in demand. Base-load thermal units, typically coal, Combined-Cycle Gas Turbine (CCGT) or nuclear, are those units which traditionally run on a continuous basis, at maximum efficiency, to supply the base electricity demand and therefore tend to have minimal operational flexibility. As such, the rapid changes in temperatures and pressures that occur during cycling operation will result in accelerated deterioration of these units’ components through various degeneration mechanisms such as fatigue, erosion, corrosion, etc. This in turn will lead to more frequent forced outages, reduced plant lifetime and significant costs for these units. As illustrated in Figure 2.1, the damage incurred from cycling operation is related to the temperature transients in the plant’s components, with online ramping being the least damaging and cold start-ups the most damaging. Figure 2.1: Cycling damage increases as plant temperature decreases (Lefton, 2004) This chapter discusses some of the common wear-and-tear effects that plants will experience when undertaking cycling operation. The various cost implications of cycling operation are identified and the approaches used to quantify these costs are examined. 2.2 Damage to Power Plants Due to Cycling Fatigue damage is the most common problem for cycling units (EPRI, 2001b). Fatigue is caused by repeated exposure to large temperature and pressure transients, typical of cycling operation (Lefton et al., 1997), and manifests as cracking or mechanical failure of structures (EPRI, 2001b). Traditionally, base-load units ran uninterrupted at full production and as such were designed to operate under creep conditions (constant Chapter 2. Cycling of Thermal Plant 16 stress), with older design codes neglecting to consider fatigue (fluctuating stress) as a damage mechanism (EPRI, 2001b). Creep and fatigue can interact in a synergistic manner in that creep will reduce fatigue life and likewise fatigue reduces creep life, as depicted in Figure 2.2 (EPRI, 2001b). Therefore when a base-load unit which has been operating under creep conditions, switches to cycling operation, the creep-fatigue interaction renders the unit highly susceptible to component failure (Lefton et al., 1995, 1997). Creep-fatigue interaction is a particular concern for components such as superheater, reheater and economizer headers (MMU, 2010). Figure 2.2: Creep-fatigue interaction (EPRI, 2001b) Thick-walled components such as boilers, which are necessary to withstand the extreme temperature and pressure associated with base-load operation, can develop through-wall temperature differences during cyclic operation. This results in differential thermal expansion and ultimately places the component under high stress, causing cracks to initiate and grow (EPRI, 2001b). An example of this is shown in Figure 2.3. Rapid temperature transients will also cause differential thermal expansion and fatigue issues in components such as header ligaments or boiler tube ties (EPRI, 2001b). Peak stresses typically occur in regions of discontinuity (Brown, 1994), and therefore welded joints are highly stressed locations (King, 1996). Expansion related issues can also arise due to cycling operation. Thin-walled com- Chapter 2. Cycling of Thermal Plant 17 Figure 2.3: Cracking seen from inside economizer header (King, 1996) ponents, heat recovery steam generator (HRSG) ducts for example, will heat up rapidly during plant start-up, whilst the supporting steelwork remains cold, resulting in differential thermal expansion and consequently high stress (Brown, 1994). Likewise, on start-up, a typical large boiler will expand downward from its roof support by 250 mm which must be supported by the boiler support framework. If start-ups are occurring on a regular basis it can lead to failure of the boiler support framweork (MMU, 2010). Mechanical fatigue is also common during turbine run-up, when the rotor passes through a series of critical speeds where vibration levels are increased significantly. Repeated start-ups can subject components such as turbine blades to high cycle fatigue levels (MMU, 2010). Thermal shocking of economizer headers occurs when cold feedwater is introduced to warm headers when a unit is re-starting following an overnight shut-down, for example (King, 1996), or alternatively when hot steam is admitted to cold superheater headers (EPRI, 2001b). If this is occurring on a regular basis it will lead to internal fatigue cracking (King, 1996). This is irreparable and must be monitored constantly for propagation. Start-ups and shut-downs can also cause oxide scales that have accumulated in steam-side equipment to spall due to the differences in the coefficients of thermal expansion between the oxide and the metal. The hard oxide particles become entrained in the steam and are carried through to the turbine causing erosion of the turbine blades (French, 1993). Increased frequency of shutdowns can contribute to infiltration of dissolved oxy- Chapter 2. Cycling of Thermal Plant 18 gen and other non-condensible gases, which will also lead to higher levels of erosion and corrosion. This can occur in cycling units when the condenser vacuum is not maintained sufficiently during offline periods. In addition as a plant goes through various modes of operation and cycles, contaminant can be disturbed and disseminated throughout the steam-condensate cycle. Thus cycling units will need to employ continuous water chemistry monitoring (Energy-Tech, 2004). Fatigue stresses during start-up and shutdown can also result in cracking of electrical equipment such as copper turns, as shown in Figure 2.4, and the resulting arcing and burning can cause short-circuits (Moore, 2006). Coils with shorted turns operate at lower temperatures than regular coils and the resulting temperature difference can give rise to rotor bowing. This will cause unbalanced magnetic forces giving rise to rotor vibration. If the problem becomes severe enough forced outages can occur (Albright et al., 1999). Figure 2.4: Cracked copper turn and rotor bowing (Moore, 2006) 2.3 Cycling Costs Any power generating company seeking to maintain profitable operation desires to know the cost impact of cycling operation for their fleet of generators. However, quantifying, or even estimating, the magnitude of these cycling costs is challenging given the extensive range of components affected by cycling, as discussed in Section 2.2. In addition, the damage caused by cycling may not be immediately apparent and often it can be several years before it manifests itself. Studies by Aptech Engineering Inc. (now Intertek Aptech) suggest that it can take from 1 to 7 years for an increase in the failure rate to become evident after switching from base-load to cycling operation Lefton et al. Chapter 2. Cycling of Thermal Plant 19 (1998). The challenge of attributing costs to cycling operation is complicated further by the fact that normal base-load operation also results in some degree of damage to a units components and identifying the damage due to cycling from that associated with normal operation is also problematic. Considering these difficulties Aptech have concluded that utilities typically underestimate cycling costs by a factor of 3 to 30 Lefton et al. (1998). Research related to the cost of generation cycling has been led by EPRI (Electric Power Research Institute) and Aptech and the approaches employed can be categorized as top-down (statistical analysis) or bottom-up (component modelling). EPRI carried out a top-down study as part of its ‘Cycling Impacts Program’ which utilized multivariate regression models to analyze the operating regimes of 158 units from NERC (North American Electric Reliability Corporation) GADS (Generating Availability Data System) and CEMS (Continuous Emission Monitoring) data, in an attempt to identify patterns relating operation to capital expenditure. However, the inconsistency in accounting practices between individual units complicated the modelling process and no correlation was found (EPRI, 2001a, 2002). Aptech employ a combination of top-down models based on historical operations, forced outage and cost data, as well as bottomup methods which calculate operational stresses and the life expenditure of critical components using physical models fine-tuned with real plant data, in order to determine cycling costs for individual generating units (Lefton, 2004). Aptech have analyzed cycling costs for over 300 generating units and found that the cost of cycling a conventional fossil-fired power plant can range from $2,500-500,000 per start/stop cycle depending on unit age, operating history and design features, and are often grossly underestimated by utilities (Lefton, 2004; Lefton et al., 1998). Babcock Energy Ltd. also developed a methodology for determining the long-term damage that arises from two-shift operation in order to optimize operating procedures and minimize damage. This involved identifying components most susceptible to creep-fatigue damage using data from thermocouples and modelling these components using finite elements so that operational events could be related to induced stresses (Brown, 1994). The factors which contribute to the total cost of cycling are: (i) increased fuel con- Chapter 2. Cycling of Thermal Plant 20 Figure 2.5: Impact of cycling on forced outage rate (Lefton, 2011) sumption due to increased plant start-ups and operation at part-load levels (and therefore reduced efficiency), (ii) increased fuel consumption due to loss of plant efficiency arising from increased wear to components, (iii) increased operations and maintenance (O&M) costs due to increased wear-and-tear to plant components, (iv) increased capital costs resulting from component failures, (v) increased environmental costs resulting from increased emissions, and (vi) loss of income due to longer and more frequent forced outages. Figure 2.5, provides an example of how the forced outage rate of a plant can increase as a result of cycling operation, however, capital expenditure on plant upgrades can help combat this. Of the studies undertaken to date, the magnitude of these cycling costs has been significant. For example, a recent study by Aptech on Excel Energy’s Harrington coal plant suggested that for each additional hot start the unit performed, the maintenance related cycling costs the unit would incur were $87k, more than 5 times greater than the cost of the start-up fuel consumed (Xcel Energy, 2010). This would indicate the importance of having a good understanding of cycling costs in order to maintain profitable operation in the long term. However, in reality generators will often under-value these costs in order to keep their short-run costs down in a competitive marketplace, the consequence of which is that the generator will subsequently be scheduled to cycle more often. Or in some situations generators will take advantage of the uncertainty surrounding these cycling Chapter 2. Cycling of Thermal Plant 21 costs in order to exercise market power. For example, a generator may increase its startup costs excessively in order to avoid shut-down, although this strategy may result in them being left offline following a trip or scheduled shut-down because of their excessive start-up cost. In any case in most markets at present it is unclear how these costs should be represented in a generator’s bid. Generators in SEM, the Irish electricity market, are directed to include cycling costs in their start-up costs, however cycling costs could also be included in shut-down, no-load or energy costs, or even defined as a new market product such as ramping costs (Flynn et al., 2000). 2.4 Next Generation Thermal Plant With increasing penetrations of variable renewables and competitive electricity markets becoming the norm worldwide, power plant manufacturers are recognising the need for greater operational flexibility (Probert, 2011). Siemens, for example, have outlined areas where CCGT plant can be upgraded with new features such as a stress and fatigue monitoring system for the HRSG, a piping warm-up system, attemperators in the steam lines to maintain required temperatures in order to make them more capable of frequent cycling (Siemens, 2008b). General Electric (GE) meanwhile have launched their ‘FlexEfficiency CCGT’ which offers faster ramp rates, shorter start-up times, lower turndown and fuel flexibility whilst achieving an efficiency of 61%. Next generation thermal plant can also avail of new materials which have been developed such as the high strength P91 steel which allows for high-pressure components to be made thinner (EPRI, 2001b). Thinner components will reach thermal equilibrium quicker and therefore are less susceptible to cracking. Improvements in instrumentation will also allow for easier start-up and shut-downs and part-load operation (Energy-Tech, 2004). Online monitoring systems can help to protect critical components from thermal stresses. However, although next generation thermal plant may be more suited to cycling operation, current generation will still be in operation for decades more. Thus cycling poses serious difficulties for generators seeking to remain in profitable operation and system operators who must maintain a stable system in spite of increasing forced outages. CHAPTER 3 Unit Commitment with High Wind Power Penetrations 3.1 Introduction P RIOR to the large-scale deployment of renewables, uncertainty in power systems was limited to load forecast error and the unplanned outages of generators or transmission lines. In order to maintain a secure system, adequate levels of spinning and non-spinning reserve were maintained to cover this error. Incorporating variable renewable generation adds an additional source of uncertainty given the unpredictable nature of renewable power sources. With low levels of renewables on power systems, additional reserve is needed to cover the additional uncertainty associated with renewables. However, as the penetration of renewables grows, it becomes increasingly inefficient to rely on reserves alone to cover the uncertainty related to renewables. Rather more robust schedules are required through stochastic scheduling, which considers multiple scenarios corresponding to multiple values of the stochastic variable, in this case the power output from the renewable generation (Monteiro et al., 2009). In addition, 22 Chapter 3. Unit Commitment with High Wind Penetration 23 to make the most efficient use of the renewable generation, forecasts need to be utilized. As the accuracy of these forecasts increases as the forecast horizon decreases, it is important that updated forecasts are used to update the commitment decisions through a rolling unit commitment mechanism (Kiviluoma and Meibom, 2011). This can in turn lead to a reduced reserve requirement (AIGS, 2008). 3.2 The Wilmar Planning Tool The Wilmar Planning Tool is an output of a collaborative research effort supported by the European Commission to develop a tool to analyse the integration of wind power in large liberalised electricity systems (Meibom, 2006). The original model was developed for two power pools: NordPool and the European Power Exchange, (i.e. Germany, Denmark, Norway, Sweden and Finland). It was later adapted to the Irish system as part of the All Island Grid Study (AIGS, 2008; Meibom et al., 2011; Tuohy et al., 2009). Wilmar is an advanced stochastic, mixed integer unit commitment and economic dispatch model, the main functionality of which is embedded in the Scenario Tree Tool and the Scheduling Model. 3.2.1 The Scenario Tree Tool The Scenario Tree Tool (STT) generates scenarios trees which feed into the Scheduling Model. Each branch of the scenario tree represents a realistic forecast scenario of load, wind power output and demand for replacement reserve (activation time > 5 minutes). The STT also produces a forced outage time series for each generating unit. The STT utilizes knowledge of historical wind speed forecast accuracy and knowledge of the correlation between wind speed forecast errors in neighbouring areas, as well as historical load data and load forecasts, to identify an Auto Regressive Moving Average (ARMA) series, based on the methods described in (Söder, 2004). The parameters of the ARMA series are determined by minimizing the difference between the standard Chapter 3. Unit Commitment with High Wind Penetration 24 deviation of the historical forecast error and the standard deviation of the forecast error produced by the ARMA series for each hour. The ARMA series is used to simulate load and wind speed forecast errors for various time horizons. These simulated load and wind speed forecast errors are paired in a random way before a scenario reduction technique, following the approach of (Dupacova et al., 2003), is applied. The resulting load and wind speed forecast error scenarios are combined with scaled-up load and wind speed time series to produce load and wind speed forecast scenarios. Finally, the wind speed forecast scenarios are transformed to wind power forecast scenarios using an aggregated wind power curve following the approach of (Norgaard and Holttinen, 2004). For each scenario the demand for replacement reserve (activation time >5 minutes) is calculated based on a comparison of the hourly power balance considering perfect forecasts and no forced outages with the power balance considering scenarios of wind and load forecast errors as well as forced outages. A percentile of the deviation between the compared power balances must be covered by replacement reserves; in this case the 90th percentile is chosen based on current practice (Meibom et al., 2011). A forced outage time series for each unit is also generated by the STT using a semi-Markov process based on historical plant data of forced outage rates, mean time to repair and scheduled outages. 3.2.2 The Scheduling Model The Scheduling Model minimizes the expected costs for all scenarios, subject to system constraints for reserve and minimum number of units online (in this case 6 units must be online in all time periods in the Republic of Ireland and 2 units in Northern Ireland). A minimum number of online units are maintained to ensure a sufficient level of system inertia. These costs include fuel, carbon and start-up fuel costs (always assumed to be hot starts). In addition to replacement reserve, one category of spinning reserve, namely tertiary operating reserve (TR1), is modelled, which has a response time of 90 seconds to 5 minutes and can only be supplied by online units. Wind generators, when curtailed, are assumed to be capable of contributing to spinning reserve requirements. Sufficient spinning reserve must be available to cover an outage of the largest online unit occurring concurrently with a fast decrease in wind power production over the Chapter 3. Unit Commitment with High Wind Penetration 25 TR1 time frame, as described in (Doherty and O’Malley, 2005). Generator constraints such as minimum down times (the minimum time a unit must remain offline following shut-down), synchronization times (time taken to come online), minimum operating times (minimum time a unit must spend online once synchronized) and ramp rates must also be obeyed. Rolling planning is employed to re-optimize the system as new wind generation and load information become available. Starting at noon each day, the system is scheduled over 36 hours until the end of the next day. The model steps forward with a three hour time step and in each planning period a three-stage, stochastic optimisation problem is solved. This involves a deterministic first-stage covering three hours, a stochastic second stage with three scenarios covering three hours and a stochastic third stage with six scenarios covering a variable number of hours, depending on the planning period in question, as seen in Figure 3.1 (AIGS, 2008). The structure of the scenario tree assumes perfect knowledge of load and wind power output in the first three hours and uncertainty in subsequent hours, and the opportunity to revise the planned commitment every three hours based on information from new forecasts. The model produces a yearlong dispatch at an hourly time resolution for each individual generating unit. The model can also be run in deterministic and perfect foresight modes whereby only one wind generation and load scenario are planned for. In deterministic mode, this scenario is the expected value of wind and load. The expected value of wind is found by summing, for all (post-reduction) scenarios, the product of the wind power forecasts and their probability of occurrence. The expected value of load and replacement reserve is found similarly (Tuohy et al., 2009). Consequently, the scenario planned for will differ from the realized scenario. This mode is typical of the scheduling process currently practiced by most system operators, i.e. only one scenario is planned for and it will contain some level of forecast error. Perfect foresight mode contains no forecast error for wind generation or load but forced outages still occur, as with all other modes. Further detail on the model and formulation of the unit commitment problem can be found in (Meibom et al., 2011). The Generic Algebraic Modeling System (GAMS) Chapter 3. Unit Commitment with High Wind Penetration 26 Figure 3.1: Illustration of rolling planning and decision structure in Wilmar is used to solve the unit commitment problem using the mixed integer feature of the CPLEX solver (version 12). For all simulations in this study the model was run with a duality gap of 0.5%. A year-long simulation takes > 3 hours when run in deterministic mode or > 24 hours in stochastic mode, on an Intel core quad 3 GHz processor with 4 GB of RAM. 3.2.2.1 Modelling DSM Later versions of the Wilmar planning tool included add-ons to model demand side management (DSM), which is utilised in Chapter 6. Chapter 3. Unit Commitment with High Wind Penetration 27 DSM units can be either peak clipping or peak shifting units. Peak clipping units allow demand to be reduced at a cost to the system without increasing demand at another time. They are modelled as flexible gas turbines with a variable operating cost and no fuel or start-up costs. Peak shifting units allow demand to be reduced and reallocated in time at a cost to the system, without reducing the overall energy demand. They are modelled as storage units with 100% efficiency. The constraints implemented in Wilmar to model DSM ensure that (i) the DSM units are scheduled day-ahead and their dispatch cannot be revised intra-day, (ii) the DSM units cannot provide non-spinning reserve, (iii) all demand shifted over a day must must be added to demand at another point in that day, and (iv) the amount of demand clipped by a peak clipping unit cannot exceed a defined energy limit. 3.2.2.2 Improved Modelling of Plant Start-ups More detailed modelling of plant start-ups was implemented to improve the validity of results. In the original version of the Wilmar Planning Tool, units remained at zero production over the course of their start-up period. Here, units are block loaded from zero to minimum output over the course of the start-up process, following the formulation given in (Arroyo and Conejo, 2004). The start-up and shut-down binary variables are set appropriately by Equation 3.1. Power output levels, PU (i), are defined for each interval, i, of the units’ start-up process. Equation 3.2 sets the minimum allowable power output for a unit equal to PU (g,i) when the unit is in the ith interval of the start-up process, or equal to its minimum stable operating level when the unit is online and not in its start-up process. Likewise, Equation 3.3 sets the maximum allowable power output for a unit equal to PU (g,i) when the unit is in the ith interval of the start-up process, or equal to its maximum operating level when the unit is online and not in its start-up process. Equation 3.4 is needed for the commitment logic (Arroyo and Conejo, 2004). Start Shut Online Online Vs,t,g − Vs,t,g = Vs,t,g − Vs,t−1,g (3.1) Chapter 3. Unit Commitment with High Wind Penetration U Dg Online p(s, t, g) ≥ Pgmin [Vs,t,g − X U Dg Start Vs,t−i+1,g ] + i=1 X Start PU (g, i)Vs,t−i+1,g X (3.2) i=1 U Dg p(s, t, g) ≤ 28 U Dg Start Online PU (g, i)Vs,t−i+1,g + Pgmax [Vs,t,g − i=1 X Start Vs,t−i+1,g ] (3.3) i=1 U Dg Online Vs,t,g ≥ X Start Vs,t−i+1,g (3.4) i=1 3.3 Other Unit Commitment Models Many approaches are available for solving the unit commitment problem, as discussed in (Padhy, 2004; Salam, 2007; Sen and Kothari, 1998), ranging from heuristic approaches such as priority list to mathematical programming approaches such as dynamic programming, Lagrangian relaxation or mixed integer programming. Dynamic programming was the first optimization based method to be applied to the unit commitment problem and is used worldwide (Padhy, 2004), however it suffers from the curse of dimensionality as it evaluates the complete decision tree, and thus for larger systems the solution time can become impractical (Sen and Kothari, 1998). Simplifications such as truncation or fixed priority ordering have been implemented to reduce the search space but this can lead to suboptimal schedules (Salam, 2007). Lagrangian relaxation, which involves decomposing the primal problem into sub-problems which are linked by Lagrangian multipliers, is one of the most commonly used unit commitment formulations in electricity markets worldwide. However, it is well understood that given the nature of how it works it will generally produce sub-optimal solutions and not produce a global optimal solution (EirGrid and SONI, 2010b). One of the key advantages to using MIP models (such as the Wilmar model), in addition to global optimality is the ease of adding constraints. As noted in Streiffert et al. (2005), MIP models do not require complex algorithmic development to implement sim- Chapter 3. Unit Commitment with High Wind Penetration 29 ple constraints unlike Lagrangian relaxation models for example which would require the addition of new Lagrangian multipliers. (Streiffert et al., 2005) also notes that more accurate modelling of combined-cycle plant is more challenging for a Lagrangian relaxation model compared to a MIP model; a topic that is dealt with in this thesis. MIP models have also benefited in recent years from improvements in the solution methods. Traditionally MIP models were solved using the branch and bound technique, however, more recently other techniques such as node pre-solve, heuristics and cutting planes have been implemented to improve the solution and the optimization time. The commercial solver CPLEX (which was used in this work to solve the Wilmar model) employs these techniques to reduce the upper (heuristics and node presolve) and lower (cutting planes and node presolve) bounds of the objective function (Bixby et al., 2000). Implementing a combination of solution techniques has been found to yield a dramatic reduction in optimization time. Branch and bound algorithms have an additional advantage of being suitable for parallel processing (Streiffert et al., 2005). Many systems such as CAISO, PJM and the Irish system are now using or testing MIP unit commitment models (EirGrid and SONI, 2010b). 3.4 The Irish 2020 Test System The test system used in the following chapters is the Irish 2020 system, based on portfolio 5 from the All Island Grid Study (AIGS, 2008; CER, 2010). Table 3.1 shows the number of units, installed capacity and average operating cost (fuel) by generation type for this test system. The peak demand from AIGS (2008) was 9.6 GW peak and the total demand was 54 TWh. More recent long term forecasts (EirGrid, 2009) however, have indicated a considerably lower peak demand for 2020, resulting from the current economic depression. Thus a revised test system has also been studied, in which the demand profile is scaled down to a 7.55 GW peak and a total demand of 42 TWh. In this revised system four 103.5 MW OCGT units were also removed from the original grid study portfolio (which contained 8 OCGT units as seen in Table 3.1), as recent generation adequacy reports would indicate they are unlikely to be built by Chapter 3. Unit Commitment with High Wind Penetration 30 2020 (EirGrid, 2009). Table 3.1: Generation Mix of Test System Generation Type Wind power CCGT Coal OCGT Gasoil Other renewables Peat Pumped storage Hydro Legacy CCGT CHP ADGT Tidal Capacity (MW) No. Units 2000/4000/6000 4012 1324 828 383 360 343 292 216 215 166 111 72 10 5 8 8 3 4 15 2 2 1 Avg. Operating Cost (e/MWh) 0 39.79 18.45 61.16 121.26 10 36.32 0 0 47.97 37.94 47.85 0 For both of the test systems, three different levels of installed wind power were examined: 2000, 4000 and 6000 MW, which supply 11%, 23% and 34% or 15%, 29% and 43% of the total energy demand, on the 9.6 GW peak and 7.55 GW peak systems respectively. The wind power data used to generate the scenario trees, used in AIGS (2008) and this thesis, was 2004 data from 11 onshore regions across Ireland and Northern Ireland and 10 offshore regions. The wind power time series collected from each region were smoothed to account for wind correlation effects. To simulate wind speed forecast errors, required for generating the scenario trees, wind speed forecasts for 6 locations were used. However, forecast results were only available for time horizons greater than 5 hours so in order to generate forecast errors for the first 5 hours persistence forecasts were assumed for the 6 locations. Figure 3.2 shows the day-ahead wind power forecast error probability function (mean absolute error is 9.6%). It is evident that wind power is more frequently over-forecast on the test system but the largest forecast errors were under-forecasts. The additional amount of spinning reserve that must be carried to cover wind power uncertainty was determined in Doherty and O’Malley (2005) for the Irish 2020 test system and is shown in Table 3.2. Chapter 3. Unit Commitment with High Wind Penetration 31 Figure 3.2: Day-ahead wind forecast error Table 3.2: Additional spinning reserve requirement due to wind generation Wind Generation (MW) 0-1000 1000-2000 2000-3000 3000-4000 4000-5000 5000-6000 TR1 (MW) 5 18 37 63 94 131 The pumped storage units, with a round-trip efficiency of 75% and a maximum pumping capacity of 70 MW each, are large providers of spinning reserve to the system, however at least 50% of the spinning reserve target has to be provided by conventional units (excluding pumped storage and wind generation). The 2 CHP units have ‘mustrun’ status as they provide heat for industrial purposes. The outputs for hydro and tidal units are inputted to the scheduling model as a time series and these units are also not dispatchable. Sewage gas, landfill gas, biogas and biomass generation make up the ‘other renewables’ category. Fuel prices are as given in Table 3.3. Base-load gas generators (i.e. CCGTs and CHP) are assumed to have long-term fuel contracts and therefore pay a cheaper fuel price compared to mid-merit gas generators (i.e. OCGTs, Chapter 3. Unit Commitment with High Wind Penetration 32 ADGTs and legacy CCGTs). Differences in the fuel price for coal and gasoil in the Republic of Ireland and Northern Ireland reflect varying delivery costs. Table 3.3: Fuel Prices by Fuel Type Fuel Renewables Coal - Republic of Ireland Coal - Northern Ireland Peat Base-load gas Mid-merit gas Gasoil - Northern Ireland Gasoil - Republic of Ireland Fuel Price (e/GJ) 0 1.75 2.11 3.71 5.91 6.12 8.33 9.64 The test system assumes that there is 1000 MW of HVDC interconnection in place between Ireland and Great Britain and it is scheduled on an intra-day basis, i.e. it can be rescheduled in every 3 hour rolling planning period. It is assumed that the total 1000 MW can be exported from Ireland to Britain, however, when Ireland is importing from Britain 100 MW of capacity is maintained to provide spinning reserve. In addition another 50 MW of spinning reserve is assumed to be available from interruptible load. A simplified model of the British power system is included, with aggregated units, no integer variables for generators and where wind generation and load are assumed to be perfectly forecast. The total demand in Britain is assumed to be 370 TWh with a peak of 63 GW and the installed wind capacity is assumed to be 14 GW. A carbon price of e30/ton was assumed. The 2020 Irish system serves as an interesting test system to study issues arising from large-scale wind power. Being a small island system, with limited interconnection to Great Britain integration issues arise and become more obvious at lower levels of wind power and can indicate future issues for other power systems pursuing large-scale wind power. The large proportion of base-load units on the Irish system, most of which are CCGTs, combined with the high wind penetration deem it useful for studying plant cycling and investigating means of limiting the extent of this cycling operation. Thus, the findings in this thesis bear relevance to other gas and wind-dominated systems, for example the ERCOT system. CHAPTER 4 Cycling of Base-load Plant on the Irish Power System 4.1 C Introduction ERTAIN developments in the electricity sector may result in suboptimal operation of base-load generating units in countries worldwide. Despite the fact that they were not designed to operate in a flexible manner, increasing penetration of variable power sources, such as wind generation, coupled with increased competition in the electricity sector can lead to these base-load units being shut down, ramped or operated at part-load levels more often. An overcapacity of generation on a system can also exacerbate plant cycling as less efficient plant may be prematurely forced down the merit order. Although all conventional units will be impacted to some degree by the integration of wind generation, it is cycling of base-load units that is particularly concerning for system operators and plant owners. As these units are designed for maximum efficiency, 33 Chapter 4. Cycling of Base-load Plant 34 they typically have limited operational flexibility, and as such cycling these units will result in accelerated deterioration of plant components through various degeneration mechanisms such as fatigue, erosion, corrosion, etc. This will lead to more frequent forced outages and loss of income, as discussed in Chapter 2. Start/stop operation and varying load levels result in thermal transients being set up in thick-walled components placing them under stress and causing them to crack. Cycling interrupts plant operation which can in turn disrupt the plant chemistry resulting in higher amounts of oxygen and other ionic species being present, and therefore leading to corrosion and fouling issues. Thus, excessive cycling of base-load units can potentially leave these units permanently out of operation prior to their expected lifetimes. The severity of plant cycling, will be dependent on the generation mix and the physical characteristics of the power system. It is widely reported that the availability of interconnection and storage can assist the integration of wind on a power system (IEA, 2008; EWEA, 2011a). Interconnection can allow imbalances from predicted wind power output or variations in net load to be compensated via imports/exports, whilst some form of energy storage can allow excess wind to be more easily absorbed by charging (and thereby increasing demand) during these periods. This should relieve cycling duty on thermal units as the onus on them to balance fluctuations is relieved. This chapter examines the effect that an increasing penetration of wind power will have on the operation of base-load units. The role that interconnection and storage play in alleviating or aggravating the cycling of base-load units is also investigated across different wind penetration scenarios. 4.2 Scenarios Examined The 2020 Irish system, as described in Chapter 3, was chosen as a test case for this study because its unique features make it suitable for investigating base-load cycling. It is a small island system, with limited interconnection to Great Britain, a large portion of base-load plant and significant wind penetration. Thus, potential issues with cycling of Chapter 4. Cycling of Base-load Plant 35 base-load units may arise on this system at a lower wind energy penetration, compared to a larger, more interconnected or more flexible system. Two versions of the 2020 Irish system are discussed in Chapter 3, one with a 7.55 GW peak demand and the other with a 9.6 GW peak demand. Both versions are examined in this chapter. For each of the demand scenarios, three levels of installed wind generation, namely 2000, 4000 and 6000 MW, were examined. As seen in Chapter 3, the remaining generation is primarily thermal generation, with a small portion of inflexible hydro capacity while the base-load is composed of coal and combined-cycle gas turbine (CCGT) generation. The characteristics of a typical base-load CCGT and coal unit on the test systems are shown in Table 4.1. Table 4.1: Characteristics of a Typical CCGT and Coal Unit on the Test System Characteristic CCGT Coal Maximum Power (MW) 400 260 Minimum Power (MW) 200 105 Maximum Efficiency (%) 57.6 36.9 Hot Start-up Cost (e) 13,280 5,320 Full Load Cost (e/hour) 15,900 4,880 (% of Max Power) 9 13 Minimum Down Time (Hour) 1 5 Start-up time (Hour) 2 5 Maximum Spinning Reserve Contribution The Wilmar model was run deterministically (i.e. the expected value of wind and load is planned for), for one year, for each of the three wind cases, and for both levels of peak demand in order to examine the effect that increasing wind power penetration will have on the operation of base-load units. These are the units with the most limited operational flexibility, and as such, will suffer the greatest deterioration from increased cycling. A sensitivity analysis was conducted to investigate the role that storage and interconnection play in altering the impact of increasing wind penetration on base-load operation. This involved running the model deterministically for one year, for each of the three wind cases, first, without any pumped storage on the system, and second Chapter 4. Cycling of Base-load Plant 36 without any interconnection on the system. In order to fairly compare systems without storage/interconnection to the systems with storage/interconnection, the systems must maintain the same level of reliability. Thus it was necessary to replace the pumped storage units and interconnection with conventional plant. The 292 MW of pumped storage was replaced with three 97.3 MW open cycle gas turbine (OCGT) units while the 1000 MW of interconnection was replaced with nine 100 MW OCGT units (as 100 MW is always used as spinning reserve, the maximum import capacity is 900 MW). The characteristics of these substitute units were set such that they could deliver the same amount of generation over the same time period as the interconnection/storage units that they replaced. The OCGT units which replaced the storage units were capable of delivering the same amount of spinning reserve (132 MW in total). The OCGT units that replaced the interconnection did not contribute to spinning reserve but instead 100 MW was subtracted from the demand for spinning reserve in each hour. This is the assumption used when the interconnector is in place. The cost per MWh from the OCGT units is generally greater than the cost of imports or production from the storage units, thus the production previously provided from storage/interconnection is not shifted directly to these OCGT units. This is advantageous in this type of study, as the operation of other units on the system without storage/interconnection can be observed, whilst the system adequacy is not undermined by the reduced capacity, thus facilitating the sensitivity analysis. For example, had CCGT capacity been used to replace the interconnector, it would likely provide the energy that had been previously delivered by the interconnector, but this would not allow examination of how the existing units on the system are affected in the absence of interconnection. The results from the systems without storage and interconnection were compared to the base case (i.e. with storage and interconnection). To examine the results, the base-load units were categorized as coal or CCGT. The results for the individual units in each group were normalized by their capacity to obtain the result per MW for each unit. The average result per MW was then obtained and this was multiplied by the capacity of a typical coal or CCGT unit (chosen to be 260 MW and 400 MW respectively) to give the result for a typical coal or CCGT unit Chapter 4. Cycling of Base-load Plant 37 as shown below: Pn i=1 (xi /ci ) n ∗ T ypical U nit Size (4.1) where xi is the result for the ith unit, ci is the capacity of the ith unit and n is the number of units 4.3 4.3.1 Results Increasing Wind Penetration and the Operation of Base-Load Units As the penetration of wind generation on a power system is increased, large fluctuations in the net load (load minus wind generation) will occur more frequently, as seen in Table 4.2 and Table 4.3, which shows the annual number of hourly net load ramps which exceed 1000 MW on the 7.55 and 9.6 GW peak demand test systems. (The probability distribution for net load ramps can also be found in Appendix A and shows larger net load ramps occur more frequently on the 9.6 GW peak demand system relative to the 7.55 GW peak demand system.) Table 4.2: No. hours when net load changes by >1000 MW from previous hour on the 7.55 GW peak demand system Wind energy penetration 7.55 GW peak system 15% 29% 43% 90 135 211 Table 4.3: No. hours when net load changes by >1000 MW from previous hour on the 9.6 GW peak demand system Wind energy penetration 11% 23% 34% 9.6 GW peak system 277 342 454 In addition, as wind generation is modelled as having zero operating costs, produc- Chapter 4. Cycling of Base-load Plant 38 Table 4.4: Number of thermal units online with increasing wind penetration (averaged at each hour shown over the year) Time (Hour) 00 03 06 09 12 15 18 21 15% wind energy penetration 12.9 11.1 12.3 16.1 16.5 16.1 17.2 15.5 29% wind energy penetration 12.3 10.8 11.6 14.6 15.2 14.9 15.7 14.6 43% wind energy penetration 11.6 10.5 11.1 13.9 14.3 13.8 14.6 13.6 tion from thermal units is increasingly displaced, thus the number of units online will decrease. This is shown for the 7.55 GW peak demand system, in Table 4.4. Therefore, with less units online to manage growing fluctuations in net load, the onus on thermal units becomes more demanding with increasing wind penetration. Figure 4.1 and Figure 4.2 show the annual number of start-ups and capacity factor for an average sized CCGT (400 MW) and coal unit (260 MW), as wind penetration increases on the 7.55 and 9.6 GW peak demand systems respectively. The capacity factor is defined as the ratio of actual generation to maximum possible generation in a given time period (in this case over the test year). As the wind energy penetration grows and the variability and unpredictability involved in system operation is increased, the operation of a base-load CCGT unit is severely impacted. Moving from 15% to 43% wind energy penetration the annual start-ups for a typical base-load CCGT unit rise from 67 to 107, an increase of 60%. On the 9.6 GW peak demand system, annual CCGT start-ups increase from 31 to 86, a 177% increase, as wind energy penetration increases from 11% to 34%. This increase in CCGT start-ups corresponds to a plummeting capacity factor for the units as seen in Figure 4.1 and Figure 4.2, as increasing levels of wind power will displace production from CCGT units and force them closer to midmerit type operation. The start-ups are higher and the capacity factor is lower for a typical CCGT unit on the 7.55 GW peak demand system relative to the 9.6 GW peak demand system, as CCGTs will more frequently be the marginal units on the system with less demand. (Not shown in Figures 4.1 and 4.2 are those CCGT units on the system, originally built for base-load operation, but having over time been displaced into mid-merit operation. With increasing penetration of wind power, such units also Chapter 4. Cycling of Base-load Plant 39 Figure 4.1: Annual number of start-ups and capacity factor for an average CCGT and coal unit with increasing wind penetration on the 7.55 GW peak demand system tend to have a decreasing capacity factor, however their annual number of start-ups, which are much larger than a typical base-load CCGT shown in Figure 4.1 and 4.2, actually reduce as they are forced from mid-merit into peaking operation.) As wind generation on the system increases, the timing and predictability of when CCGT units will be started is also impacted, as seen in Table 4.5, which shows the percentage of total CCGT starts that occur during each two hour interval over the year, on the 7.55 GW peak demand system. With just 2000 MW installed wind power (15% energy penetration) CCGT start-ups are seen to be concentrated around 6-7am. However moving to 6000 MW installed wind power CCGT start-ups are now more widely distributed throughout the day. This will have repercussions for plant personnel who are responsible for plant start-ups and would indicate that stringent start-up procedures will need to be put in place for these units, to minimize the risk of difficulties arising during the start-up process. In the UK market, for example, a generating unit must be synchronized within a +/- five-minute window when delivering power to the grid. If late, the grid operator may not accept the power at all, regardless of the fuel and production costs already incurred (OSIsoft, 2007). Unlike a CCGT unit, the annual number of start-ups for a typical coal unit on the Chapter 4. Cycling of Base-load Plant 40 Figure 4.2: Annual number of start-ups and capacity factor for an average CCGT and coal unit with increasing wind penetration on the 9.6 GW peak demand system Table 4.5: Percentage of total start-ups occurring during each two-hour interval over the year Time (Hour) 00-01 02-03 04-05 06-07 08-09 10-11 2000 MW wind power 1.09 0.82 1.63 46.74 22.01 11.68 6000 MW wind power 1.03 2.07 7.76 28.79 23.45 9.66 Time (Hour) 12-13 14-15 16-17 18-19 20-21 22-23 2000 MW wind power 2.17 2.45 8.15 2.44 0.27 0.54 6000 MW wind power 3.10 6.38 14.14 1.21 1.72 0.69 7.55 GW peak demand system decreases somewhat as the wind energy penetration increases, as seen in Figure 4.1. On the 9.6 GW peak demand system start-ups for a coal unit increase with wind energy penetration up to 23% (albeit not as drastically as a CCGT unit). However, at wind energy penetrations greater than 23%, this pattern diverges and the start-ups for a coal unit begin to decrease, as seen in Figure 4.2. As wind energy penetration grows, the demand for spinning reserve will increase. Due to high part-load efficiencies, coal units are the main thermal providers of spinning reserve on this system. As CCGT units are taken offline more frequently with increasing wind penetration, the requirement on coal units to provide reserve to the system is driven even higher. Coal units also have lengthy start-up times; once taken offline it Chapter 4. Cycling of Base-load Plant 41 is a minimum of ten hours (minimum down time plus synchronization time as seen in Table 4.1) before the unit can be online and generating again. Thus on a system with a high wind energy penetration, coal units are even less likely to be cycled offline to avoid shortfalls in spinning reserve. This would indicate that the units with the most limited operational flexibility may actually be rewarded at high levels of wind for their inflexibility and suggests that some form of incentive may be needed to secure investment in flexible plants (for example OCGTs), which are commonly reported as being beneficial to system operation with large amounts of wind (Kirby and Milligan, 2008; Strbac et al., 2007). Coal units do, however, have low minimum outputs so at times of high wind power penetration more coal units can remain online to meet the minimum units online constraint, thus minimizing wind curtailment. CCGT units, on the other hand, are typically restricted by high minimum outputs because of emissions restrictions as opposed to physical limitations. When running base-load, CCGTs achieve high firing temperatures which allows CO (carbon monoxide) to be oxidized into CO2 . However, at part load levels, when the firing temperature is lower, the CO to CO2 oxidation reaction is quenched by cool regions near the walls of the combustion liner resulting in increased levels of CO (Siemens, 2008a). It would appear from examination of capacity factors in Figure 4.1 and Figure 4.2 that a crossover point exists when coal units become the most base-loaded plant on the system. It is clear from Table 4.1, that coal generation is cheaper than generation from CCGT units and so these units are in fact the most base-loaded plant at all wind energy penetrations examined, however they are modelled as having more frequent outages compared to the CCGT plant, thus yielding relatively lower capacity factors (at some wind energy penetrations) compared with the CCGT units. Figures 4.3 and 4.4 show the utilization factor for an average base-load coal and CCGT unit, and the number of hours they perform severe ramping as wind penetration increases. The utilization factor is the ratio of actual generation to maximum possible generation during hours of operation in a given period. Severe ramping is defined here as a change in output greater than half the difference between a unit’s maximum and minimum output over one hour. Periods when the unit was starting up or shutting down Chapter 4. Cycling of Base-load Plant 42 Figure 4.3: Utilization factor and annual number of hours where severe ramping is performed for an average CCGT and coal unit with increasing wind penetration on the 7.55 GW peak demand system were not included. Although coal units, as the most base-loaded thermal generation, will avoid heavy start-stop cycling as wind levels grow they do experience increased part-load operation. This is indicated by a drop in utilization factor from 0.90 to 0.81, or 0.92 to 0.88, as wind energy penetration increase from 15% to 43%, or 11% to 34%, on the 7.55 and 9.6 GW peak systems respectively, as seen in Figures 4.3 and 4.4. The utilization factor for a CCGT unit is also seen to decrease with increasing levels of wind power, however, it remains high in comparison with a coal unit, indicating the relatively smaller contribution to spinning reserve it provides to the system and correspondingly the infrequent periods of part-load operation. As seen in both Figures 4.3 and 4.4, both types of unit experience a dramatic increase in periods where severe ramping is required as wind energy penetration increases. For both test systems CCGT units experience more ramping as they are more frequently the marginal units on the system, however the rate of increase in ramping is higher for the coal units as the number of operating hours exceeds that for a CCGT as the wind energy penetration increases. Such increases in part-load operation and ramping can lead to cycling damage such as fatigue damage, boiler corrosion or cracking of headers, as discussed in Chapter 2. A recent study of the impacts of ramping on three of Xcel Energy’s coal plants, for Chapter 4. Cycling of Base-load Plant 43 Figure 4.4: Utilization factor and annual number of hours where severe ramping is performed for an average CCGT and coal unit with increasing wind penetration on the 9.6 GW peak demand system example, predicted a 200%-500% increase in variable O&M costs and capital expenses (Danneman and Beuning, 2011). The results reported here are for “average sized” CCGT and coal units. In order to show how these results correspond to the actual results for the real units modelled, the maximum, minimum, average and standard deviation of the number of start-ups and capacity factor for the modelled CCGT and coal units are given in Appendix B. 4.3.2 Sensitivity Analysis The previous section showed the serious impact increasing levels of wind power will have on the operation of base-load units. The extent of this impact will be determined by the generation portfolio and the characteristics of the system. This section provides a sensitivity analysis of the effect of the portfolio on the results, by examining the operation of the base-load units with increasing levels of wind power when storage and interconnection are removed from the system. Chapter 4. Cycling of Base-load Plant 4.3.2.1 44 No Storage Case Figure 4.5 shows the number of hours online for an average CCGT and coal unit, for increasing wind energy penetrations on the 7.55 GW peak demand system, with and without pumped storage. Although storage will typically charge overnight when prices are low, thus raising the base-load, Figure 4.5 reveals that base-load units in fact spend more hours online on the system without pumped storage, compared to the system with storage. Pumped storage units can provide spinning reserve to the system when pumping and when generating, and as such they are large providers of spinning reserve to the system. Their typical mode of operation is to charge at night, although this is typically seen to be concentrated over a small number of hours, and generate at minimum load, providing the maximum amount of spinning reserve possible to the system (a maximum of 50% of the total spinning reserve demand can come from storage units), throughout the day. On the system without pumped storage, this spinning reserve must now be provided by conventional plant. The increased requirement on base-load units to provide spinning reserve in the absence of storage is evident in Table 4.6, which shows the total amount of spinning reserve provided by a CCGT or coal unit on the 7.55 GW peak demand system, with and without pumped storage. Thus on occasions when CCGT or coal units may have been cycled offline on the system with pumped storage, they will now be more likely to be kept online on the system without pumped storage. Table 4.6: Total contribution to spinning reserve (MWh) from typical CCGT and coal unit on the 7.55 GW peak demand system Installed wind capacity (MW) With storage Without storage 2000 4000 6000 CCGT 150,001 156,557 151,965 coal 166,069 167,295 173,303 CCGT 238,609 238,473 217,015 coal 223,884 228,462 225,772 As such, Figure 4.6, which shows the number of start-ups for a typical base-load CCGT and coal unit on a system with and without pumped storage as wind penetration Chapter 4. Cycling of Base-load Plant 45 Figure 4.5: Number of hours online for an average CCGT and coal unit with/without storage and an increasing wind penetration on the 7.55 GW peak demand system increases on the 7.55 GW peak demand test system reveals that without storage on the system, both CCGT and coal units have reduced start-ups (although the difference is small). However, although base-load units may benefit from less start-ups and more hours online on the system without storage, the increase in reserve provision from these units implies increased part-load operation, which has been shown to cause component degradation in base-load plant. The HRSGs in CCGTs in particular can be affected by flow instability, which is associated with part load operation (Wambeke, 2006). (Similar results were obtained for the 9.6 GW test system and have been included in Appendix C.) 4.3.2.2 No Interconnection Case Figure 4.7 compares the number of hours spent online by a typical CCGT and coal unit on the 7.55 GW peak demand system with and without interconnection, as wind energy penetration is increased. The base-load units are seen to spend significantly more hours online on the system without interconnection compared to the system with interconnection. (A similar result was found for the 9.6 GW test system and this has been included in Appendix C.) Due to a large portion of base-load nuclear plant and Chapter 4. Cycling of Base-load Plant 46 Figure 4.6: Number of start-ups for an average CCGT and coal unit with/without storage and an increasing wind penetration on the 7.55 GW peak demand system cheaper gas prices compared with Ireland, the market price for electricity tends to be cheaper in Great Britain. As a consequence Ireland tends to be a net importer of electricity from Great Britain and as such will often favour importing electricity before turning on domestic units. Thus interconnection to Great Britain displaces conventional generation on the Irish system, forcing units down the merit order and exacerbating plant cycling. Without the option to import electricity, as shown in Figure 4.7, all demand must be met by domestic units, requiring more units to be online generating more often. Thus, a typical CCGT and coal unit are seen in Figure 4.7 to spend more time online without interconnection, particularly the CCGT unit which is closer to being the marginal unit and therefore its production is displaced ahead of production from a coal unit. Likewise interconnection is seen to displace more base-load production on the 7.55 GW peak demand system compared to the 9.6 GW peak demand system, and at higher wind energy penetrations compared to lower wind energy penetrations, as with less demand less conventional generation will be online and therefore base-load units are closer to being the marginal units on the system. On the 9.6 GW peak demand system, removing interconnection is seen in Figure 4.9 to also reduce plant cycling as domestic units were required to stay online. However, Chapter 4. Cycling of Base-load Plant 47 Figure 4.7: Number of hours online for an average CCGT and coal unit with/without interconnection and an increasing wind penetration on the 7.55 GW peak demand system as the wind energy penetration is increased, the electricity price in Ireland undercuts British prices more often making exports economically viable and eventually a crossover point is reached when the system with interconnection can deal with large fluctuations in the wind power output via imports/exports more favourably and avoid plant shutdowns relative to the system without interconnection. Coal units, being the most base-loaded units on the system, are first to benefit from increased exports on the system and thus a crossover point can be observed for the coal units in Figure 4.9 at 34% wind energy penetration. Likewise, for the 7.55 GW peak demand test system electricity prices in Ireland tend to be lower than British prices so exports to Britain are up to four times greater than on the 9.6 GW peak demand system. Thus coal units are seen in Figure 4.8 to benefit from reduced start-ups relative to the case without interconnection. However, similar to the 9.6 GW peak demand system, at lower wind energy penetrations the CCGT units experience less cycling on the system without interconnection, until again a crossover point occurs, this time at 35% wind energy penetration, beyond which the system with interconnection benefits from reduced CCGT cycling. Chapter 4. Cycling of Base-load Plant 48 Figure 4.8: Number of start-ups for an average CCGT and coal unit with/without interconnection and an increasing wind penetration on the 7.55 GW peak demand system A further sensitivity was conducted to examine base-load cycling when CCGT generation were the most base-loaded plant on the system. This was conducted for the 7.55 GW peak demand system with 6000 MW installed wind capacity and with no interconnection, so that changes to plant operation could be directly attributable to the change in the merit order rather than a change in the operation of the interconnector. In this sensitivity analysis the cost of coal generation was increased such that it was more expensive than generation from base-load CCGT units (but still less expensive than mid-merit CCGTs). Such a scenario is not unrealistic given the current trend for low gas prices and the rising cost of coal generation due to environmental restrictions (Carrino and Jones, 2011). As seen in Table 4.7, the results showed drastic increases in cycling, not only for coal plant, but CCGT plant also. During periods of very low net load (i.e. high wind generation) it becomes difficult to meet the minimum number of units online constraint while also avoiding curtailment of wind generation. As CCGT units have high minimum loads relative to coal units, they cannot reduce their output sufficiently to accommodate the wind power, forcing them to be cycled off-line and requiring other units, in this case the coal units, to be started. The result is greatly increased cycling for both types of units. Chapter 4. Cycling of Base-load Plant 49 Figure 4.9: Number of start-ups for an average CCGT and coal unit with/without interconnection and an increasing wind penetration on the 9.6 GW peak demand system Table 4.7: Annual start-ups for a typical CCGT and coal unit on 7.55 GW peak demand system with 6000 MW installed wind power and no interconnection 4.3.3 Coal most CCGT most base-load generation base-load generation CCGT starts 130 204 Coal starts 47 214 Total 117 418 Effect of Modelling Assumptions The results in this chapter were produced by running the Wilmar model in deterministic mode, i.e. the model planned for the expected values of load, wind generation and demand for replacement reserve. It is considered that this mode is most representative of current practice. However, in the future as higher wind energy penetrations are reached, stochastic scheduling is likely to be implemented to provide schedules that are more robust, thus maintaining reliable system operation when large forecast errors may occur. To determine the impact that stochastic scheduling will have on the operation of base-load plant further simulations were run using the Wilmar model in stochastic mode, for the 7.55 GW and 9.6 GW peak demand systems, each with 2000, 4000 and Chapter 4. Cycling of Base-load Plant 50 6000 MW installed wind power. Figure 4.10 shows the difference in annual start-ups that was found for a typical CCGT and coal unit, at each of the wind penetrations, when optimized deterministically and stochastically on the 7.55 GW peak demand system. As can be seen there is relatively little difference between the two optimization methods at the lower wind energy penetrations, but at 43% wind energy penetration (6000 MW installed) the system optimized stochastically has slightly increased starts (+11 for CCGT, +2 for coal). When optimized stochastically, the model must find a solution that satisfies multiple scenarios, covering high and low net loads. Units with long start-up times, i.e. base-load units, are therefore more often committed when the system is optimized stochastically, because if they are required for any of the scenarios they will have to be committed in advance. No decision has to be made in advance for fast start units, on the other hand, as these can be started in a given hour, when the load and wind generation are known. At lower wind penetrations, as compared to high wind penetrations, it is more likely that the committed base-load generation will be required as the net demand will simply be higher. However, with a high wind energy penetration, base-load generation that has been committed to meet a high net demand scenario, may in fact not be needed, if the net demand that is realised is low. This may lead to these units being shut-down more frequently, as seen in Figure 4.10, although the difference is relatively small. 4.4 Summary Increasing penetration of wind generation on a power system will lead to changes in the operation of the thermal units on that system, but most worryingly to the base-load units. The base-load units are impacted differently by increasing levels of wind, depending on their characteristics. CCGT units see significant increases in start-stop cycling, plummeting capacity factors and are essentially displaced into mid-merit operation. On the test systems examined coal units are the main thermal providers of spinning reserve to the system and also are highly inflexible and as a result avoid start-stop cycling but Chapter 4. Cycling of Base-load Plant 51 Figure 4.10: Annual start-ups on the 7.55 GW peak demand system, optimized stochastically and deterministically see increased part-load operation and ramping. This increase in cycling operation can over time lead to increased forced outages and plant depreciation. Certain power system assets are widely reported to assist the integration of wind power. This chapter examined if pumped storage and interconnection reduced cycling of base-load units by comparing a system with storage and interconnection to a system without either, across a range of wind penetrations. It was found that in the absence of storage there was a greater requirement to keep base-load units online to meet the system’s spinning reserve requirement. Thus, base-load units were seen to be cycled less on a system without pumped storage, compared to a system with pumped storage. For a system with a high electricity price relative to its neighbours, interconnection was found to displace generation from domestic units. As such, base-load units were also seen to be cycled less on a system without interconnection compared to a system with interconnection. In the long term if power systems are to include large portions of variable wind power, a flexible plant portfolio will be needed. As shown in this chapter, a unit that is highly inflexible but provides a large portion of spinning reserve to the system will benefit from its inflexibility by being kept online more. It is also possible that generators that are repeatedly cycled would alter the technical characteristics of the plant which are bid into the market, such as minimum down time or ramp rates, Chapter 4. Cycling of Base-load Plant 52 in an attempt to avoid or minimise cycling. This would indicate that in order to incentivise new plant to be flexible the revenue streams available to a unit may need to be adjusted to reflect the value of flexibility. Some markets include a capacity payment in order to incentivise generators to be available as much as possible. As power systems evolve to include greater penetrations of wind, these payments could be restructured in order to incentivise generator performance, such that new plant is more adequately designed to deal with cycling. New ancillary services could also be defined and increasing the ancillary services fund could also incentivise operational flexibility. For example, ramping payments to generators for providing ramping service has been proposed for the Ontario power system (APPrO, 2006). CHAPTER 5 Multi-mode Operation of Combined-Cycle Gas Turbines 5.1 C Introduction OMBINED -cycle gas turbines (CCGTs) are a type of power generating unit that achieve high efficiencies (up to 61%) by capturing the waste heat from a gas turbine in a heat recovery steam generator (HRSG) and using it to produce superheated steam to drive a steam turbine (Kehlhofer et al., 2009). The high efficiencies achieved, combined with their ease of installation, short-build times and relatively low gas prices have made the CCGT a popular technology choice (Watson, 1996; Colpier and Cornland, 2002). In the Republic of Ireland, for example, 43% of the installed thermal capacity is CCGT technology, whilst in the markets of Texas (ERCOT) and New England (NEPOOL) CCGTs represent 37% of the total installed capacity. The operational flexibility of a CCGT unit is limited by the steam cycle, which contains many thick-walled components, necessary to withstand extreme temperatures 53 Chapter 5. Multi-mode Operation of Combined-Cycle Gas Turbines 54 Figure 5.1: Schematic of CCGT in open- and combined-cycle mode (Eskom, 2007) and pressures (Shibli and Starr, 2007; Starr, 2003). To avoid differential thermal expansion across these components and the subsequent risk of cracking, these components must be brought up to temperature slowly, resulting in slower start-up times and ramp rates for the unit overall (Anderson and van Ballegooyen, 2003). Although, as CCGT units were traditionally base-loaded, this was not a major concern for plant operators. However, by incorporating a bypass stack upstream of the HRSG at the design stage, as shown in Figure 5.1, a CCGT unit has the option to bypass the steam cycle and run in open-cycle mode, whereby exhaust heat from the gas turbine is ejected directly into the atmosphere via the bypass stack (Anderson and van Ballegooyen, 2003). This reduces the power output and efficiency of the plant but offers greater operational flexibility. Running in open-cycle mode, the gas turbine has a short start-up time of 15 to 30 minutes and is capable of changing load quickly. However, bypass stacks are not always incorporated because they can potentially lead to leakage losses, thus reducing plant efficiency, while also introducing additional capital costs (Kehlhofer et al., 2009). As discussed in Chapter 1, international energy policy is driving ever greater penetrations of renewable energy and thus wind power is set to represent a larger portion of the future generation mix (Bird et al., 2005). This is driving a greater demand for Chapter 5. Multi-mode Operation of Combined-Cycle Gas Turbines 55 flexibility within power systems in order to deal with high penetrations of variable and difficult to predict energy sources (IEA, 2008; Van Hulle and Gardner, 2008). Storage, interconnection and responsive demand are commonly cited as flexible options for dealing with variability issues (Brown et al., 2008; Göransson, 2008; Hamidi and Robinson, 2008) however these options have considerable costs associated with them. Facilitating open-cycle operation of CCGT units that have the technical capability to run in opencycle mode (i.e. those with a bypass stack) can also deliver much needed flexibility to a system with a high wind penetration. This resource is often technically available, but inaccessible due to market arrangements. For example, in SEM (Single Electricity Market), the electricity market of Northern Ireland and the Republic of Ireland, generators submit technical (operating characteristics) and commercial (cost characteristics) data day-ahead and the cheapest generators are dispatched on the trading day until the demand is met (EirGrid and SONI, 2010b). The current market rules do not facilitate multiple bids from CCGT units which are capable of open-cycle operation. Instead these units can bid into the market day-ahead either their combined-cycle or open-cycle characteristics, but not both at the same time. In order to derive the greatest benefits from a CCGT unit that can run in open-cycle mode, it is necessary for the scheduling algorithm to explicitly consider both modes of operation for the unit, i.e. open-cycle and combined-cycle (Lu and Shahidehpour, 2004). These will have greatly different technical and cost characteristics and so need to be declared individually. Currently most markets do not facilitate CCGT units to submit multiple bids representing different modes of operation, thus presently opencycle operation of a CCGT unit is typically limited to periods when the steam section is undergoing maintenance. However, some US systems have begun addressing this issue to varying degrees, with ERCOT and CAISO seeking to implement configuration based modelling of CCGTs (Blevins, 2007; CAISO, 2010b). The option to run in open-cycle mode could also provide benefits for the generators. Renewable integration studies have shown that CCGT units will experience signifi- Chapter 5. Multi-mode Operation of Combined-Cycle Gas Turbines 56 cant decreases in running hours and thus will receive less revenue from the market as they are displaced by greater levels of wind generation which has an almost zero marginal cost (CAISO, 2010a; Göransson and Johnsson, 2009; NREL, 2010; NYISO, 2010; Troy et al., 2010). Due to their high minimum loads CCGTs are shut down frequently with high wind penetrations as they cannot reduce output sufficiently to accommodate the wind power output (Troy et al., 2010). By facilitating CCGT units to operate in open-cycle mode, these units may have a new opportunity to capture revenue from increased operation during periods when they might otherwise be offline. For example, if a CCGT unit has been forced offline by high wind generation on the system, it may have the opportunity to run as a peaking unit. Multi-mode operation may also lead to a reduction in plant cycling. Online CCGT units which have bypass stacks can instantaneously switch to open-cycle operation, while remaining online, by opening the bypass damper to release exhaust gases through the bypass stack. This could allow the gas turbine to remain online during periods when the CCGT would otherwise be shut-down for minimum load reasons, thereby reducing start-ups for the gas turbine. Likewise, offline CCGT units with bypass stacks can start-up in open-cycle mode and the steam unit can be warmed slowly to be brought into operation at a later point. This chapter examines if a power system with a high wind penetration can benefit from the additional flexibility introduced, or if the CCGT units themselves benefit, when they are facilitated to operate in open-cycle mode when technically feasible and economically suitable. As discussed in Chapter 3, the all-island Irish 2020 system (AIGS, 2008) is expected to contain both a large share of wind power and CCGT units (50% of which include a bypass stack) and thus provides an appropriate test system. 5.2 Methodology In order to examine the potential for multi-mode operation of CCGT units some changes were made to the Wilmar model. A set, ‘ccgt’, of all CCGT units capable of prolonged Chapter 5. Multi-mode Operation of Combined-Cycle Gas Turbines 57 open-cycle operation, i.e. those with bypass stacks, was defined. The set ‘ccgtopen ’ cora responds to these CCGT units when run in open-cycle mode. CCGT units comprised of two or more gas turbines will have multiple ‘ccgtopen ’ units, as indicated by index a ‘a’. The relation ‘multi-mode’ is defined to pair each member of ‘ccgt’ with the corresponding member(s) of ‘ccgtopen ’. To ensure the mutually exclusive operation of these a ‘ccgt’ units and the corresponding ‘ccgtopen ’ units, the constraint shown in (5.1) was a added to the model, where VOnline is the state binary variable which describes the online status of the unit. This allows the model to dispatch, when economically optimal, either the ‘ccgt’ (combined-cycle mode) or any/all of the corresponding ‘ccgtopen ’ units a (open-cycle mode), for all scenarios ‘s’ and time steps ‘t’, but not both simultaneously as they are in reality the same unit. Online Online open ≤ 1, Vs,t,ccgt + Vs,t,ccgt a ∀ s, t, multi − mode(ccgt, ccgtopen ) a (5.1) Equation (5.2), taken from (Arroyo and Conejo, 2004), sets the state binary variShut ables VStart s,t,i or Vs,t,i equal to 1 for all units ‘i’, when a unit is started up or shut down respectively. Start Shut Online Online Vs,t,i − Vs,t,i = Vs,t,i − Vs,t−1,i (5.2) When modelling multi-mode operation of CCGT units two new circumstances arise when calculating the start-up fuel consumption, FuelStart s,t,i , which must be explicitly represented. Firstly, when a ‘ccgt’ unit transitions from conventional combined-cycle operation into open-cycle operation no start-up fuel is consumed by the ‘ccgtopen ’ unit as represented by inequality (5.3), where Startfueli is the start-up energy used by each unit (measured in MWh). When the ‘ccgtopen ’ unit starts from zero production (VStart s,t,ccgtopen a = 1 and VShut s,t,ccgt = 0), the first term on the right hand side of inequality (5.3) determines the fuel used by the unit whilst the second term equals zero. Alternatively, when the Chapter 5. Multi-mode Operation of Combined-Cycle Gas Turbines 58 unit switches from combined-cycle to open-cycle operation (VStart = 1 and VShut s,t,ccgt s,t,ccgtopen a = 1) the second term causes the right hand side of (5.3) to equal zero. Setting FuelStart s,t,i as a positive variable and using an inequality condition ensures that when a ‘ccgt’ unit is shutting down and the corresponding ‘ccgtopen ’ unit is not starting up FuelStart s,t,ccgtopen a will be 0. Start Start open ≥ (Startf uelccgtopen ∗ V ) F uels,t,ccgt s,t,ccgtopen a a a Shut − (Startf uelccgtopen ∗ Vs,t,ccgt ) a (5.3) The second circumstance relates to the unit transitioning from open-cycle to combinedcycle operation. In this case the start-up fuel consumed is less than the start-up fuel used in bringing the CCGT online from zero production, as some of this start-up fuel has already been used to bring the unit online in open-cycle mode and the gas section of the plant is in a hot state. As an approximation, the start-up fuel used to bring the unit into combined-cycle operation from open-cycle operation is the difference between the start-up fuel for the ‘ccgt’ and a fraction, α, of the start-up fuel for the ‘ccgtopen ’, as seen in (5.4). Based on the operating experience of generators, α was chosen to be 0.5 here. When the ‘ccgt’ unit is started from zero production (VStart s,t,ccgta = 1 and VShut = 0), the first term on the right hand side of (5.4) provides the start-up s,t,ccgtopen a fuel consumed whilst the second term equals zero. When the unit switches from opencycle to combined-cycle operation the second term is included, thus approximating the start-up fuel consumed in this situation. Start Start F uels,t,ccgt ≥ (Startf uelccgt ∗ Vs,t,ccgt ) Shut open ∗ α) − (Startf uelccgtopen ∗ Vs,t,ccgt a a (5.4) In the Wilmar model any unit can contribute to the target for replacement (nonspinning) reserve, provided that an offline unit can come online in time to provide Chapter 5. Multi-mode Operation of Combined-Cycle Gas Turbines 59 reserve for the hour in question and the reserve available from an online unit is not needed to meet spinning reserve targets. In Wilmar, the contribution from online and f offline units to the replacement reserve target, POf s,t,i (MW), are calculated individually. In this case the ‘ccgt’ units cannot provide offline replacement reserve as they have long start-up times, but the corresponding ‘ccgtopen ’ units can, given their fast start-up times. The constraints shown in (5.5) and (5.6), where Pmax is a unit’s maximum i capacity (MW), ensure that if either the ‘ccgt’ unit or the ‘ccgtopen ’ unit is online, then the ‘ccgtopen ’ unit cannot contribute to the portion of replacement reserve that is provided from offline units. This is necessary to avoid the situation where a ‘ccgt’ unit is online and the model allows the corresponding ‘ccgtopen ’ unit to contribute to offline replacement reserve. Of f Online max ∗ (1 − Vs,t,ccgt ) Ps,t,ccgt open ≤ P a ccgtopen a (5.5) Of f max Online open ) Ps,t,ccgt ∗ (1 − Vs,t,ccgt open ≤ P ccgtopen a a (5.6) a a When the bypass stack is utilized to switch from combined-cycle to open-cycle operation, the transition is automatic and occurs without shutting down the gas turbine or reducing its power output. However, the transition from open-cycle to combined-cycle operation is dependent on the temperature state of the boiler. Therefore, if the CCGT unit has been operating for a period of time in open-cycle mode and is then scheduled to switch to combined-cycle mode, its output must adjust in order to achieve the correct HRSG inlet temperature, as depicted in Figure 5.2. This was implemented by setting the allowable power output (PU (i) from (Arroyo and Conejo, 2004)) for each interval of the CCGT’s start-up process, which begins at hour 0 in Figure 5.2, such that the appropriate soak time is achieved. Scheduled outages for each unit, determined from historical experience (AIGS, 2008), Chapter 5. Multi-mode Operation of Combined-Cycle Gas Turbines 60 Figure 5.2: CCGT start-up from open-cycle mode are inputted in time-series format to the Wilmar model. In this case, CCGT units with the capability to operate in open-cycle mode are considered to be available to run in open-cycle mode for a portion of their scheduled outage. Given that gas turbine equipment is more accessible and compact in comparison with the steam turbine equipment, it was assumed that one third of the maintenance period was sufficient for the gas turbine. 5.3 Test System The test system used was the 7.55 GW peak demand test system as set out in Chapter 3. Five (of the ten) CCGT units on the Irish system include bypass stacks and therefore can run in open-cycle mode. Each of these units is currently installed and operational. The characteristics of these units in combined-cycle mode are given in Table 5.1. Limited data was available for these units in open-cycle mode so each was given characteristics similar to a typical open-cycle gas turbine (OCGT) unit, as shown in Table 5.1. As CCGT 2 and CCGT 5 are comprised of two gas turbines connected to one steam turbine (2+1 configuration), these units were modelled as having two iden- Chapter 5. Multi-mode Operation of Combined-Cycle Gas Turbines 61 tical open-cycle units available for dispatch when the CCGT is operated in open-cycle mode. CCGTs 2 and 3, located in Northern Ireland and CCGTs 1, 4 and 5, located in the Republic of Ireland contribute to the minimum units online constraint which is modelled in Wilmar (as discussed in Chapter 3), for their respective regions. Table 5.1: Characteristics of CCGT units (capable of multi-mode operation) in combined- and open-cycle modes CCGT Configuration Max output (MW) Min output (MW) Max efficiency (%) Min up time (Hours) Min down time (Hours) Start-up time (Hours) Hot start-up fuel (GJ) Max spinning reserve contribution (MW) Efficiency at max spinning reserve (%) Max output (MW) Max efficiency (%) Min up time (Hours) Min down time (Hours) Start-up time (Hours) Hot start-up fuel (GJ) Max spinning reserve contribution (MW) Efficiency at max spinning reserve (%) 5.4 1 2 3 4 5 1+1 2+1 1+1 1+1 2+1 Characteristics in combined-cycle mode 445 480 404 343 480 240 232 260 220 280 57.6 58.9 53.9 52.9 52.3 4 4 6 4 4 1 2 4 4 2 2 1 1 2 4 2600 2000 1080 1732 2000 42 37 40 57.4 58.1 52.8 Characteristics in 280 160 256 39.5 38 39.3 0 0 0 0 0 0 0 0 0 14 8 13 25 52.2 open-cycle 265 39.3 0 0 0 13 40 51.3 mode 160 38 0 0 0 8 20 20 20 20 20 39.3 37.5 39.1 39.2 37.5 Results A number of model runs were conducted to investigate the potential for multi-mode operation of CCGT units. The Wilmar model was run in deterministic mode as this is more representative of current scheduling practice. A year long dispatch was produced Chapter 5. Multi-mode Operation of Combined-Cycle Gas Turbines 62 for each of the three wind power penetrations outlined in Section III, when (i) multimode operation of CCGT units is not allowed and (ii) when multi-mode operation of CCGT units is allowed. 5.4.1 Utilization of the Multi-mode Function The average number of times a CCGT unit with multi-mode capability was run in open-cycle mode and the average production from a CCGT in open-cycle mode over the year, at each of the wind penetrations examined, is shown in Figure 5.3. Despite increasing wind penetration being correlated with an increased demand for flexibility, be it fast starting or ramping, Figure 5.3 shows the multi-mode function is used less frequently as wind penetration on the system increases. As more wind power, with an almost zero marginal cost, is added to a system, the production from thermal plant is increasingly displaced and as such there is an increased likelihood of generators operating at part-load. To illustrate this, Table 5.2 gives the annual utilization factor (ratio of actual generation to maximum possible generation during hours of operation) averaged for the coal, CCGT and peat units on the system with 2000, 4000 and 6000 MW wind power. Therefore, as wind penetration increases, online part-loaded units are more often available to ramp up their output to meet unexpected shortfalls in production, avoiding the need to switch on fast-starting units, such as the CCGTs in open-cycle mode. Table 5.2: Average utilization factors with increasing wind penetration Installed Wind Coal CCGT Peat 2000 MW 0.90 0.83 0.75 4000 MW 0.87 0.79 0.55 6000 MW 0.82 0.80 0.51 The trend seen in Figure 5.3 is consistent with the production from peaking plants as wind penetration increases. Table 5.3 shows the drop in production from the most utilized OCGT unit, with increasing wind penetration when multi-mode operation is, and is not, allowed. Reduced production from peaking plants due to increased Chapter 5. Multi-mode Operation of Combined-Cycle Gas Turbines 63 Figure 5.3: Average production from a CCGT in open-cycle mode (line) and average number of instances generators utilized open-cycle operation (grey column), shown for various levels of installed wind capacity wind penetration has also been observed in other wind integration studies, such as NYISO(2010), however, it is also likely that systems with base-load units that have slower ramp rates than those examined in this study will rely on fast-starting units (such as CCGTs in open-cycle mode) more often as wind penetration increases. (All units on the test system are assumed to be capable of ramping from minimum to maximum output in one hour or less.) The average production from the CCGT units in open-cycle mode, as seen in Figure 5.3, is comparable with average production levels from dedicated OCGT peaking plants on the system when multi-mode operation of CCGTs is not enabled. Table 5.3: OCGT production (GWh) with increasing wind penetration Installed Wind Multi-mode not allowed Multi-mode allowed 2000 MW 8.5 2 4000 MW 3.9 0.2 6000 MW 3.4 0.3 As wind penetration increases so too will the demand for replacement reserve, due to the increased forecast error. The replacement reserve target can be met by fast-starting offline units or from excess spinning reserve, if available. If sufficient excess spinning reserve is not available to meet the replacement reserve target, the model must ensure Chapter 5. Multi-mode Operation of Combined-Cycle Gas Turbines 64 a number of fast-starting units are offline and available for operation to maintain a secure system. Consequently, as a result of maintaining the replacement reserve target, production from fast-start units (such as the multi-mode units in open-cycle mode) is reduced. Additional simulations were conducted for the various wind penetrations with no replacement reserve target, to investigate the extent that maintaining replacement reserve suppressed the multi-mode units from running in open-cycle mode. For many systems, such as the Irish system, this is more representative of current practice, where no replacement reserve target formally exists. Table 5.4 shows the difference in the average open-cycle production from multi-mode units that results when no replacement reserve targets are enforced. Table 5.4: Difference in Open-cycle production (GWh) from multi-mode units with no replacement reserve target enforced Installed Wind 4 Production 2000 MW 16.9% 4000 MW 7.2% 6000 MW -0.5% As seen, in the absence of a target for replacement reserve, open-cycle production from the multi-mode units is utilized substantially more for the 2000 MW and 4000 MW wind power scenarios. However, with 6000 MW wind power, due to more frequent part-loading of units, there is more frequently an excess of spinning reserve on the system, as well as off-line fast-starting units (as per Table 5.3) which can contribute to the replacement reserve target. Thus with 6000 MW wind power, the replacement reserve target has little effect on the open-cycle operation of multi-mode units. Table 5.5 shows the average surplus spinning reserve available and the average replacement reserve target per hour for each of the wind cases examined. Table 5.5: Average hourly surplus spinning reserve (MW) available and replacement reserve target (MW) Installed Wind Surplus spinning reserve Replacement reserve target 2000 MW 65 500 4000 MW 120 580 6000 MW 240 700 Similarly, if additional peaking capacity, lower in merit relative to the CCGT units Chapter 5. Multi-mode Operation of Combined-Cycle Gas Turbines 65 Figure 5.4: Combined-cycle capacity factor (dashed line) and open-cycle production (solid line) for each CCGT with multi-mode capability for the 2000 MW wind power system in open-cycle mode, is added to the system, open-cycle operation from the multimode CCGTs increases as the new peaking plants are now kept offline to meet the replacement reserve target instead of the CCGTs in open-cycle mode. To demonstrate this, 4 new OCGT units were added to the test system and the model was run for the 2000 MW installed wind power scenario. The results showed a 32% increase in open-cycle production from multi-mode CCGTs. Figure 5.4 shows the capacity factor for each CCGT in combined-cycle mode and its production over the year in open-cycle mode for the 2000 MW wind power scenario. An inverse relationship is evident between the open-cycle production from a CCGT and the capacity factor of the CCGT, which indicates that usage of the multi-mode function is related to the amount of time the CCGT is offline. The more often a CCGT is not in operation but available for dispatch, the more opportunities it has to run in open-cycle mode, and this relationship would be expected regardless of the plant portfolio. The percentage change in total production (combined-cycle plus open-cycle) that results when multi-mode operation of CCGTs is enabled is shown in Table 5.6, for each of the wind penetrations examined. Multi-mode operation increased production for CCGT5, the lowest merit CCGT, which was seen to utilize the function most Chapter 5. Multi-mode Operation of Combined-Cycle Gas Turbines 66 Table 5.6: Percentage change in total production when multi-mode is enabled, shown for each wind penetration Installed Wind CCGT1 CCGT2 CCGT3 CCGT4 CCGT5 2000 MW 5.5 0 -3.3 -1.4 13.3 4000 MW 5.4 0.1 5 -7.3 38.5 6000 MW -7.5 -0.1 -2.5 -37.1 11.1 frequently across all the wind penetrations examined. Total production from CCGT3 and CCGT4, which are mid-merit CCGTs, is reduced in all cases but one. There is a risk (particularly for CCGTs that are frequently the marginal unit on the system, such as CCGT3 and CCGT4) when offering open-cycle operation, of being dispatched from combined-cycle to open-cycle operation at times of low net demand (demand minus wind generation) to alleviate minimum load issues and then losing out to another generator that can come online faster/cheaper, when the net demand increases again. However, it is also likely that in a market environment, generators would strategise when they would offer this multi-mode capability to avoid losing out on production. CCGT1, the highest merit CCGT, benefits from increased production when multi-mode operation is enabled on the system with 2000 MW and 4000 MW installed wind power. This is due to increased exports and reduced production from the other CCGTs, as opposed to increased production in open-cycle mode. 5.4.2 Benefits Arising from Multi-mode Operation The efficiencies of the OCGT peaking units on the system are comparable with the CCGT units in open-cycle mode. However, the CCGT units running in open-cycle operation are assumed to have a lower gas price, to reflect the advantage of long-term contracts. Their open-cycle capacity (as seen in Table 5.1) is also larger than the capacity of the OCGTs (103.5 MW each) and they benefit from avoided start-up costs when transitioning from combined-cycle mode. Thus, when multi-mode operation of CCGTs was enabled, production from OCGT peaking plant tended to be substituted by pro- Chapter 5. Multi-mode Operation of Combined-Cycle Gas Turbines 67 Figure 5.5: Average production from OCGT peaking units in each wind power scenario, with multi-mode operation of CCGTs not allowed (light grey) and allowed (dark grey) duction from the CCGTs in open-cycle mode. Figure 5.5, which shows the average production from OCGTs for each wind penetration level when multi-mode operation of CCGTs is allowed and not allowed, illustrates this point. Assuming open-cycle production from CCGTs is more economic than production from OCGTs, as is the case here, it is possible that by enabling multi-mode operation of CCGTs sufficient flexibility could be extracted from a system’s portfolio of plant to avoid building additional peaking units, or equally that OCGT units would no longer be able to cover their costs and so would be forced to retire from service. Both situations may then lead to increased production from CCGTs in open-cycle mode. Table 5.7 shows the total shortfall in replacement reserve over the year and the number of hours in which this occurred, for each of the wind penetrations examined, when multi-mode operation of CCGTs is, and is not, allowed. The additional faststarting generation available to the system when multi-mode operation of CCGT units is allowed significantly reduces the shortfall in replacement reserve. This contributes to a more secure system by preventing capacity shortfalls when wind forecasts prove to be overly optimistic and also indicates that, depending on the market structure, the generators may benefit from an additional revenue stream, via ancillary service payments for the replacement reserve provided. Chapter 5. Multi-mode Operation of Combined-Cycle Gas Turbines 68 Table 5.7: Magnitude and frequency of replacement reserve shortfall, shown for various levels of installed wind Installed Wind MW 2000 4000 6000 Multi-mode CCGT not allowed MWh No. hours 1688.7 13 2972.9 17 609.9 13 Multi-mode CCGT allowed MWh No. hours 861.4 3 880.2 5 7.6 1 In addition to enhanced system security, the additional flexibility available to the system when multi-mode operation of CCGT units is allowed will also yield operating cost savings. Table 5.8 shows the total system production cost savings achieved by enabling multi-mode operation of CCGTs. The total system cost is made up of fuel, carbon and start-up costs for the Irish and British system combined, as they are cooptimized. In this case, these savings were achieved at no additional cost as each of the CCGTs is currently capable of multi-mode operation. Table 5.8: Total system cost saving (Me) resulting from multi-mode operation of CCGTs Installed Wind Reduction in costs 2000 MW 1.55 4000 MW 0.51 6000 MW 2.65 The availability of less expensive peaking capacity when multi-mode operation of CCGTs is enabled will tend to reduce price spikes. In addition, the model includes cost penalties (these are not included in the system production costs) if demand, spinning reserve or replacement reserve targets are not met. There were no hours when demand was not met. However, the reduction in hours when the replacement reserve target is not met, achieved by enabling multi-mode operation, as seen in Table 5.7, consequently reduces the number of hours when this cost penalty (e10,000 for the given hour) is incurred. This is seen in Table 5.9 which shows the average electricity price (excluding hours with a cost penalty imposed) and the number of hours when the electricity price exceeded e500/MWh (including hours with a cost penalty imposed) when multi-mode operation of CCGTs is allowed, and not allowed, for each of the wind penetration levels. Chapter 5. Multi-mode Operation of Combined-Cycle Gas Turbines 69 Table 5.9: Average price and frequency of price spikes (>e500/MWh) Installed Wind MW 2000 4000 6000 Multi-mode CCGT not allowed Average No. Price Price (e/MWh) Spikes 49.76 27 48.10 27 45.21 21 Multi-mode CCGT allowed Average No. Price Price (e) Spikes 49.70 8 47.96 9 45.11 8 Figure 5.6: Change in exports across the interconnector when multi-mode operation of CCGTs is enabled A direct consequence of the reduced prices is seen in Figure 5.6 which shows the change in exports over the interconnector from the Irish to British systems that result when multi-mode operation of CCGTs is allowed, for each of the wind scenarios examined. A substantial increase in exports is seen as a result of enabling multi-mode operation of CCGTs, as the number of time periods when the electricity price on the Irish system is less than the British system increases. Imports are largely unaffected. The operation of the interconnector in the scenarios when multi-mode operation of CCGTs was not allowed is shown in Table 5.10. The increase in exports, resulting from multi-mode operation of CCGTs being en- Chapter 5. Multi-mode Operation of Combined-Cycle Gas Turbines 70 Table 5.10: Operation of interconnector when multi-mode is not allowed Installed Wind Import (MWh) Export (MWh) 2000 MW 658,561 3,859,473 4000 MW 1,776,893 2,418,475 6000 MW 3,339,921 1,598,117 abled, supports a reduction in the level of wind curtailment, as more power is exported to the British system during periods of high wind generation, thus avoiding generator minimum load issues. The reduction in curtailment was significant, approximately 57% and 82% on the 2000 MW wind system with the interconnector traded intra-day and day-ahead respectively, but the actual percentage of the annual wind energy this represented was small (<0.01%). However, given that network congestion issues are not modelled here it is likely that real levels of wind curtailment would be more significant and consequently a reduction in curtailment levels arising from multi-mode operation of CCGT units would be more advantageous. The increase in exports also supports a reduction in CO2 emissions as generation on the British system, which is more carbon intensive relative to the Irish case, is displaced. The observed CO2 reduction resulting from multi-mode operation of CCGTs is small (≈100,000 tonnes or <0.05% of total Irish and British system emissions). However, it was achieved at no additional cost to the consumer or the generators as, in this case, the infrastructure (i.e. the bypass stacks) is already in place. In addition to enabling a new mode of operation, allowing multi-mode operation of CCGTs may reduce cycling operation of these units. Table 5.11 shows the number of start-ups (in combined-cycle mode), the utilization factor and the average duration of time spent offline for CCGTs 3, 4 and 5 for the 2000 MW installed wind power scenario. These units are seen to benefit from a reduced number of start-ups which not only implies a start-up fuel saving, but also a reduction in plant wear-and-tear. As discussed in Chapter 2, it is difficult to quantify the value of a reduction in cycling but some studies have indicated that an avoided start-up could save generators substantial amounts (up to $500,000 for a single start/stop cycle) (Lefton et al., 1998). An increase in the utilization factor for the CCGT units (in CCGT mode) is also observed when Chapter 5. Multi-mode Operation of Combined-Cycle Gas Turbines 71 multi-mode operation is allowed. This implies a reduction in part-load operation, which is particularly beneficial for CCGT plant, given HRSG components are susceptible to differential thermal expansion resulting from flow instability, as well as water chemistry issues, when operated at part-load (Wambeke, 2006). As the time spent online increases when multi-mode operation is allowed, the average duration of the offline period will be reduced. If the duration of time spent offline decreases the plant is more likely to be in a warmer state when it starts up, thus alleviating the level of creep-fatigue damage associated with start-ups (Lefton et al., 1997). Table 5.11: Impact of Multi-mode on CCGT 3, 4 & 5 with 2000 MW installed wind power Start-ups Utilization Factor CCGT 3 CCGT 4 CCGT 5 No multi-mode 257 157 29 multi-mode 247 141 21 No multi-mode 0.94 0.86 0.67 Multi-mode 0.94 0.87 0.72 Average Duration of No multi-mode 19 46 284 Offline Period (Hours) Multi-mode 20 41 46 5.4.3 Sensitivity Studies Usage of the multi-mode function is dependent on many factors, particularly the amount of flexibility already present in the system. A sensitivity study was conducted to examine usage of the multi-mode function when the system was less flexible to meeting demand. This involved running the model with 2000 MW wind power (as this level of wind generation led to the greatest usage of CCGTs in open-cycle mode) and power exchange across the interconnector fixed day-ahead as opposed to intra-day. Examining the usage of the multi-mode function when the interconnector is scheduled day-ahead versus intra-day illustrates how a less flexible system will more frequently utilize the flexibility present in multi-mode CCGT operation. Figure 5.7 shows the average production from the multi-mode CCGTs in open-cycle mode and the average number of instances the CCGTs utilized open-cycle operation, with the interconnector scheduled Chapter 5. Multi-mode Operation of Combined-Cycle Gas Turbines 72 Figure 5.7: Average production from a CCGT in open-cycle mode (line) and average number of instances generators utilized open-cycle operation (grey column), with interconnector scheduled day-ahead and intra-day on the 2000 MW wind system day-ahead and intra-day on the 2000 MW wind power system. The average production from CCGTs in open-cycle mode with day-ahead scheduling of the interconnector is seen to be more than three times greater than the system with intra-day scheduling of the interconnector. By fixing the power exchange between the Irish and British systems day-ahead, when there is greater uncertainty in the expected wind generation and demand, the system is forced to dispatch generators such as the multi-mode CCGT units, as opposed to rescheduling imports/exports, to compensate for wind and load forecast errors. Likewise, systems with seasonal hydro restrictions may see greater usage of multi-mode CCGT operation during those periods when the operating flexibility of the system is reduced. In addition, the quality of wind and load forecasts employed by a system will also determine the usage of the multi-mode function. Additional simulations were completed running the model in stochastic and perfect foresight modes. These represent different means of including load and wind forecasts in the scheduling process; whereby stochastic optimization can be considered to represent a system employing ensemble forecasts, deterministic optimization is representative of a system utilizing a single forecast and the perfect forecast scenario is a hypothetical case where no forecast error exists. The Chapter 5. Multi-mode Operation of Combined-Cycle Gas Turbines 73 Figure 5.8: Average production from CCGT in open-cycle mode (GWh), shown for different methods of optimization with 2000 MW wind power robust solutions obtained by stochastic optimization showed less deployment of the multi-mode function compared with the deterministic results. The stochastic solution, optimized over several wind and load scenarios, typically has more units online to cover all scenarios and therefore is more prepared to deal with unforseen shortfalls in wind generation or increases in demand, without the need for starting peaking plant. The capacity factors of the CCGT units are also higher for the stochastic case compared to the deterministic case indicating that there was also less opportunity for these units to run in open-cycle mode when the system is optimized stochastically. Running the Wilmar model with perfect foresight of the system demand and wind profile also reveals even less open-cycle operation from CCGTs, as in this case, with no forecast errors on the system (except forced outages of generators), fast starting units are in less demand relative to the deterministically optimized solution. Figure 5.8 compares the average open-cycle operation from the multi-mode CCGTs, on the system with 2000 MW wind power, when optimized with perfect foresight, stochastically and deterministically. The average open-cycle production from a CCGT unit is seen to be 11% less on the stochastically optimized system and 35% less on the system with perfect forecast compared to the deterministic case. A sensitivity analysis was also conducted using a higher level of demand on the Chapter 5. Multi-mode Operation of Combined-Cycle Gas Turbines 74 system. In this case the original demand profile from AIGS (2008) with a 9.6 GW peak, discussed in Chapter 3, was run for each wind scenario. The average production from the multi-mode CCGTs in open-cycle mode over the year is shown in Figure 5.9 to be six to eight times greater on the 9.6 GW peak demand system, where peaking capacity is in greater demand, compared to the 7.55 GW peak demand system, at each of the wind power penetrations examined. In addition to the increased demand resulting in increased open-cycle production from the multi-mode CCGTs (as well as combined-cycle production), the other main difference between the scenarios is the predominant direction of power transfer on the interconnector. With 2000 MW installed wind capacity the Irish system is a net importer of power from Britain, at both levels of demand examined. However, as more wind power is installed on the 7.55 GW peak demand system the marginal electricity price is reduced sufficiently with respect to the British system such that Ireland becomes a net exporter of power. Although increasing wind power penetration on the 9.6 GW peak demand system also reduces the marginal price it is still a net importer with 6000 MW installed wind power. Thus, on occasions when forecast wind is overestimated and the system is in need of fast-starting plant, the 7.55 GW peak demand system, being a net exporter, can more frequently choose to curtail exports or start up a unit to compensate. In contrast, the 9.6 GW peak demand system, being a net importer, more often only has the option to turn on faststarting plant. Hence, this implies that a system which tends to be a net exporter is inherently more flexible, and has more options for dealing with variable wind power than a system that is a net importer of power. In this scenario with higher demand, each of the multi-mode CCGT units experienced increased total production (combinedcycle plus open-cycle) when multi-mode operation was allowed, suggesting that offering multi-mode capability may prove more profitable on a system with a smaller capacity margin. Given the low deployment of the multi-mode functionality on the 7.55 GW peak demand system and the high capacity factor in combined-cycle mode for CCGT 1 and 2, as seen in Figure 5.4, it would appear that there is insufficient incentive for all CCGTs capable of multi-mode operation to offer this flexible capability. Thus, given Chapter 5. Multi-mode Operation of Combined-Cycle Gas Turbines 75 Figure 5.9: Average production from a CCGT in open-cycle mode on the 7.55 GW peak demand system (light grey) and the 9.6 GW peak demand system (dark grey), shown for various levels of installed wind power that CCGTs 3, 4 and 5 have low capacity factors in combined-cycle mode, additional simulations were conducted to investigate the resulting benefits if these units alone, and if CCGT 5 alone, offered multi-mode capability. Table 5.12 shows the total system cost (for Ireland and Britain) and the magnitude of the replacement reserve shortfall over the year for these configurations (in addition to other configurations examined in the paper). Examining the shortfall in the replacement reserve target for the different configurations reveals that the majority (≈ 80%) of the reduction in replacement reserve shortfall due to multi-mode capability is attributable to CCGT 5, while CCGTs 1 and 2 are seen to have no impact on the replacement reserve shortfall. Thus, CCGTs capable of open-cycle operation, which have very low output in combined-cycle mode, have value in providing replacement reserve. All cases with 2000 MW wind power 7.55 GW Peak, No Multi-mode 7.55 GW Peak, 5 Multi-mode CCGTs 7.55 GW Peak, 3 Multi-mode CCGTs (3, 4 & 5) 7.55 GW Peak, 1 Multi-mode CCGT (5) 7.55 GW Peak, No Multi-mode, day-ahead interconnector trading 7.55 GW Peak, 5 Multi-mode CCGTs, day-ahead interconnector trading 7.55 GW Peak, No Multi-mode, stochastic 7.55 GW Peak, 5 Multi-mode CCGTs, stochastic 7.55 GW Peak, No Multi-mode, perfect foresight 7.55 GW Peak, 5 Multi-mode CCGTs, perfect foresight 9.6 GW Peak, Multi-mode not allowed 9.6 GW Peak, 5 Multi-mode CCGTs Configuration Total System Cost / Saving Me 13372.03 / 13370.48 / 1.55 13368.99 / 3.04 13371.73 / 0.3 13384.64 / 13382.98 / 1.66 13371.23 / 13371.27 /-0.04 13370.87 / 13369.38 / 1.49 13997.24 / 13996.16 / 1.08 Replacement Reserve Shortfall MWh 1688.7 861.4 861.4 1032.4 2197.9 798 966.5 394 0 0 68345.9 63265.3 Avg. Top-up Payment (no. units) Me 1.36 (2) 0.49 (3) 0 1.66 (2) 0.91 (2) 0.45 (1) 0 Table 5.12: Total system cost, replacement reserve shortfall and top-up payment, shown for various multi-mode configurations Chapter 5. Multi-mode Operation of Combined-Cycle Gas Turbines 76 Chapter 5. Multi-mode Operation of Combined-Cycle Gas Turbines 77 As seen in Table 5.6, the multi-mode CCGTs may experience a reduction in total production as a result of offering multi-mode capability to the market. This was also observed to be the case for CCGTs 3 and 4, when only three units offered multi-mode operation. This indicates that a system seeking to increase its flexibility via multimode operation of CCGTs, possibly to facilitate integration of variable renewables, may need to reward these units either through ancillary service payments or another market mechanism to restore their revenue to original levels (i.e. when multi-mode operation was not allowed). The subsidy or “top-up payment” required to restore the revenue of these units to their original level is estimated here as the loss in total production multiplied by the average electricity price. The average “top-up payment” required is shown in Table 5.12 with the number of units requiring this payment shown in parenthesis. However, it should be noted that this represents the worst-case figure given that the multi-mode CCGT unit offered this capability in all time periods, rather than when it was profitable for them to do so, as would likely be the case in reality. 5.5 Summary Amending the scheduling model used by TSOs to include the bids and technical characteristics of a CCGT unit in open-cycle mode, in addition to the conventional CCGT unit, is a simple task. The CCGT unit in open-cycle mode can be defined as a new unit, with a constraint added to ensure that the CCGT unit and the CCGT unit in open-cycle mode cannot be scheduled to run at the same time. This chapter examined if allowing CCGT units to operate in open-cycle mode, when this is technically feasible and cost optimal, could deliver benefits to a system with a high wind penetration or to the generators themselves. It was shown that the additional fast-starting capacity available from multi-mode operation of CCGTs reduced the replacement reserve shortfall, indicating an opportunity for increasing system reliability. Low-merit CCGTs were seen to utilize the multi-mode function more than high-merit CCGTs, as they are frequently offline and available for dispatch, whilst the increased competition among generators, typical at higher levels of wind generation, resulted in multi-mode operation of CCGTs being Chapter 5. Multi-mode Operation of Combined-Cycle Gas Turbines 78 utilized less frequently. Peaking production from CCGTs in open-cycle mode displaced peaking production from OCGTs, potentially reducing the need for such units to be built. Sensitivity studies revealed that usage of the multi-mode function is dependent on the level of flexibility inherent in the system. Optimizing the system stochastically or allowing intra-day trading on interconnectors reduced the need for flexibility to be extracted from generators and consequently resulted in less frequent deployment of the multi-mode function. The analysis in this chapter assumed that the CCGT units capable of multi-mode operation offered this flexibility in all time periods, whereas in reality generators would strategise when to offer open-cycle operation such that plant production levels are not negatively impacted, as was seen for some units under certain scenarios in this chapter. Nonetheless, it was shown that the payment required to restore generator revenue to levels when they did not offer multi-mode operation, in those cases where generator production was reduced, was typically less than the system cost saving, indicating a net benefit to society. A cost saving is also associated with the reduction in replacement reserve shortfall which has not been considered here. CHAPTER 6 Power System Flexibility and the Impact on Plant Cycling 6.1 Introduction P OWER system flexibility is defined in IEA (2008) as the ability to respond rapidly to large fluctuations in supply or demand. A flexible power system, therefore, is inherently capable of supporting a larger penetration of variable renewables. As wind generation continues to grow, the operating flexibility of conventional plant may prove insufficient to meet an increasingly variable net demand. In addition, increased cycling of these plants can lead to extensive damage to the plant’s components, particularly for base-load plant, as described in Chapter 2. Thus, considerable interest surrounds the idea of incorporating sources of flexibility into power systems to support a higher penetration of wind power. Energy storage facilities, interconnection to neighbouring power systems and demand side management schemes (DSM) are well cited sources of flexibility within a 79 Chapter 6. Options for Increasing Power System Flexibility 80 power system (IEA, 2008; Van Hulle and Gardner, 2008). Each of these flexibility options can assist in balancing variations in the net load. The flexibility of interconnection is present in the ability to import electricity from, or export electricity to, a neighbouring power system, thus reducing the burden of managing net load variability domestically. Energy storage will charge when the electricity price is low and generate when prices are high, which will tend to flatten the net load curve (somewhat). Low prices are associated with high wind penetration, and if storage units charge during these periods it will raise the system demand, requiring increased production from conventional plant and possibly keeping them online when they may otherwise have been forced off-line. Demand side management schemes, depending on their nature, can allow demand to be shed completely or shifted in time to better suit the net load profile. In the context of a system with a large wind penetration the ability to shed or reschedule demand is useful if forecast wind fails to materialise or wind generation begins to reduce rapidly and production from conventional plant cannot be ramped up quickly enough to compensate or alternatively when high wind generation coincides with low demand, potentially forcing generators to be shut-down. It was found in Brown et al. (2008) that pumped storage on isolated systems can allow a greater penetration of renewables and improve the dynamic security of the system, however Tuohy and O’Malley (2009) also shows that, although pumped storage can reduce wind curtailment, the increased use of base-load units can actually lead to increased emissions. Hamidi and Robinson (2008) found that responsive demand on a system with a high wind penetration makes greater use of the wind resource and reduces emissions, whilst Keane et al. (2011) finds DSM substitutes production from peaking units and can provide a valuable source of reserve. It was also noted in Malik (2001) that the avoided cycling cost of thermal units is a major benefit of DSM. The net benefits of wind generation can be increased significantly by increasing the level of interconnection on the power system, as shown in Denny and O’Malley (2007), whilst Göransson (2008) also shows that investment in transmission to a region sufficiently far away to make wind speeds uncorrelated (supergrid), or to a region with excess flexible capacity, can decrease the total system costs of a system with a high wind penetration. Chapter 6. Options for Increasing Power System Flexibility 81 In addition, the next generation of fossil-fired generation is set to be more flexible as plant manufacturers, in response to the changing needs of power companies, are now launching high efficiency power plants which are suited to cycling operation (GE, 2011; Siemens, 2008a,b). As discussed in Chapter 4, the high minimum loads of CCGT units resulting from emissions limitations often lead to them being forced off-line during high penetrations of wind generation. However, plant manufacturers have now developed solutions (such as bypassing compressed air around the combustor into the turbine to increase the fuel-to-air ratio inside the combustor) to achieve higher firing temperatures at lower loads, thus reducing the part-load emissions. This could facilitate new CCGT units to remain online during periods of high wind generation (Siemens, 2008a). The new Siemens H class CCGT, for example, can operate stably at 100 MW, less than 20% of its rated output (Probert, 2011). As shown in Chapter 5, it is also plausible that existing CCGT units may in the future be operated in open-cycle mode as well as combined-cycle mode (assuming simple market changes are made), releasing an additional source of flexibility to the system. This chapter examines how these various forms of flexibility will alter the operation of base-load plant and investigates which is most beneficial to scheduling a system with a large supply of variable wind power to reduce cycling of these inflexible plants. The effect on wind curtailment and CO2 emissions are also examined. In addition, other forms of flexibility are discussed, namely battery electric vehicles, maintenance scheduling (with consideration of system flexibility), the ability to control wind generation and faster markets. 6.2 Methodology The approach employed here was to incorporate equal capacities of the various sources of flexibility in turn into the test system. By comparing each scenario against the base case, the impacts of each flexibility option on system operation, and in particular the operation of base-load plant, could be determined. The test system used is the Irish 2020 test system with a 7.55 GW peak and 6000 MW installed wind capacity, as Chapter 6. Options for Increasing Power System Flexibility 82 described in Chapter 3. As per Chapter 4, the results have been normalized to give the result for a typically sized CCGT or coal unit. Five scenarios were developed altogether, each incorporating 500 MW of a flexible resource into the base case test system. These scenarios included 500 MW interconnection, pumped storage, DSM, additional turndown capability for CCGTs (i.e. reduced minimum operating levels) and open-cycle capacity from multi-mode operation of CCGTs, as summarised in Table 6.1. Table 6.1: Scenarios Examined Scenario Scenario Scenario Scenario Scenario 1 2 3 4 5 500 500 500 500 500 MW MW MW MW MW Interconnection Pumped Storage DSM Turndown Multi-mode In scenario 1 which included 500 MW interconnection, the transfer of electrical energy between the interconnected systems can be rescheduled in every planning period. In scenario 2, the 500 MW pumped storage was split into 4 identical 125 MW storage units, with characteristics as shown in Table 6.2. The storage units in scenario 2 all pumped to, and generated from, the same reservoir. (Thus if one unit has not pumped any water it can still generate, provided the other units have pumped water into the reservoir.) Pumping at maximum output required 8.5 hours to fill the reservoir. Running at minimum output, the storage units, as they can run independently, could generate for 408 hours. Table 6.2: Characteristics of new pumped storage units Max generation (MW) Min generation (MW) Max storage content (total) (MWh) Min storage content (total) (MWh) Max charging (MW) Min charging (MW) Max contribution to TR1 (MW) Round trip efficiency (%) 125 10 5000 920 120 120 50 78 Chapter 6. Options for Increasing Power System Flexibility 83 In scenario 3 which contained 500 MW DSM, the DSM was modelled as two 250 MW units, one a peak shifting unit and the other a peak clipping unit (the 50:50 ratio between shifting and clipping capacity was also used in KEMA (2005)). The peak shifting unit corresponded to load which could be shifted in time during the day without reducing the overall energy demand, for example refrigeration load. As such any reduction in demand must be replaced within the day (i.e. the total energy exchange is equal to zero). It was modelled as a storage unit with 100% efficiency, as described in Chapter 3. When the storage unit generates it corresponds to a demand reduction by DSM, and when the storage unit charges it corresponds to the demand being replaced. The DSM peak shifting unit could contribute up to 42 MW of spinning reserve when it was actively reducing demand (i.e. when the representative storage unit was generating) and had a variable operating cost of e40/MWh. The peak clipping unit corresponded to peak load which could be reduced at times of high electricity prices and does not increase demand at another time, for example lighting demand. The peak clipping unit had a variable operating cost of e80/MWh and could also deliver up to 42 MW of spinning reserve when it was actively reducing demand. The values for the variable operating costs and spinning reserve capabilities of the peak shifting and peak clipping units were taken from Keane et al. (2011). In scenario 4, the minimum operating level for five CCGT units on the test system was reduced by 100 MW each (from an average minimum operating level of 220 MW). For scenario 5, two CCGT units on the system (CCGT 4 & 5 from Chapter 5) were assumed to be capable of multi-mode operation, thus releasing 500 MW additional open-cycle capacity to the system when the units were not running in combined-cycle mode. (The open-cycle capacity of these CCGTs is altered here compared with Chapter 5 in order to provide 500 MW flexible capacity in total.) Chapter 6. Options for Increasing Power System Flexibility 6.3 6.3.1 84 Results Impact on the Operation of Base-load Units The cycling activity of the CCGT and coal units on the base case test system was described in Chapter 4. CCGTs were seen to undergo a large number of annual startups relative to the coal units. Given their high minimum operating levels they are forced off-line during periods of high wind penetration. The coal units on the other hand avoid start-stop cycling as they provide the cheapest fossil-fired generation to the system and also their low minimum operating levels allow them to stay online during periods of high wind generation. However, the high part-load efficiency of the coal units means they are the main providers of spinning reserve on the system and so operate at part-load levels frequently. Coal units are also subject to severe ramping during periods of very high wind generation as they are some of the few thermal units online to provide power balancing. Severe ramping is defined here as a change in output greater than half the difference between a unit’s maximum and minimum output over one hour (excluding hours when the unit is starting up or shutting down). Figure 6.1: Change in start-ups and production for a typical CCGT unit in each scenario relative to the base case Chapter 6. Options for Increasing Power System Flexibility 85 Scenario 1 - Interconnection Figure 6.1 shows the change in the average number of annual startups and production for a typical CCGT unit, for each of the scenarios investigated. Of all the flexibility options examined the addition of 500 MW interconnection on the test system resulted in the greatest reduction in start-stop cycling (17 less starts per year) for a typical base-load CCGT unit. The reduction in cycling for CCGTs was also seen in Figure 6.1 to be correlated with increased production (an additional 80 GWh, an increase of approximately 3.4%). With 6000 MW installed wind power capacity on the system, prices on the Irish system frequently undercut those in Britain to the extent that the Irish system is a net exporter of electricity, as discussed in Chapter 4. The increase in exports allows for increased production from base-load plant and also with the opportunity to export during periods of high wind power penetration CCGT units can avoid being shut-down. Although not shown here, production from lower merit CCGTs however, which are effectively in mid-merit operation, is displaced by the increased interconnection capacity, as import levels also tend to increase at times when these units are the marginal units on the system. Figure 6.2 shows the change in the average number of annual startups and production for a typical coal unit, for each of the scenarios investigated. The coal units in the base case were at their minimum number of annual start-ups so no reduction in coal plant start-ups was possible. However, the coal units did benefit from a large reduction in ramping operation, as seen in Figure 6.3, which shows the average number of hours severe ramping was required from CCGT and coal units over the year. The reduction of 118 hours (38%) of severe coal ramping relative to the base scenario was the largest reduction in ramping of all scenarios examined. Likewise the reduction in CCGT ramping of 47 hours (42%) relative to the base case was the largest observed over all the scenarios investigated given that the increased export capacity will allow more opportunities to balance net load variability through exchanges with the British system. Thus, the additional flexibility that interconnection provides is particularly beneficial to a system that is a net exporter, however, as seen in Chapter 4, it can Chapter 6. Options for Increasing Power System Flexibility 86 exacerbate cycling on a system that is a net importer. Figure 6.2: Change in start-ups and production for a typical coal unit in each scenario relative to the base case Scenario 2 - Pumped Storage The addition of 500 MW of pumped storage increased the annual start-ups for a typical CCGT unit by 9 relative to the base case, as seen in Figure 6.1. This increase in cycling for a typical CCGT is correlated with slightly increased CCGT production (+1%) and online hours (not shown), implying that although the CCGT units are being cycled more they are gaining new opportunities for generation due to the introduction of the new storage units. The increase in start-ups for a typical CCGT, with the additional pumped storage on the system, was seen to arise as the addition of storage led to increased levels of exports, requiring CCGT units to be started up to meet the additional demand. Table 6.3: Operation of new storage units Utilization factor for generation (%) Utilization factor for spinning reserve (%) Unit 1 40.9 38.5 Unit 2 44.5 40.4 Unit 3 43.4 42.9 Unit 4 43.1 45.3 However, the production for a typical coal unit on the system, shown in Figure 6.2, was seen to decrease by 3.6%, while annual start-ups were seen to increase (+5), due to the additional pumped storage capacity. Examining the operation of these new storage Chapter 6. Options for Increasing Power System Flexibility 87 units revealed that they were used as much to provide spinning reserve to the system as generation to the system. Table 6.3, which provides the utilization factor for each of these new storage units on the system (total generation divided by maximum generation possible during online hours) as well as the spinning reserve utilization factor (defined here as total spinning reserve provided divided by maximum spinning reserve possible during online hours), illustrates this trend. Consequently, the demand for spinning reserve from coal units, which are the main thermal providers of primary reserve on the system, is reduced and as such, as was seen in Chapter 4 also, these units can now be cycled off-line on occasion as the requirement for them to be online providing spinning reserve is reduced. Therefore, the amount of spinning reserve provided from coal units drops 12% with the introduction of 500 MW pumped storage. Increased instances of severe coal ramping were also observed in Figure 6.3. Figure 6.3: Change in the number of hours severe ramping was required by a typical CCGT or coal unit in each scenario relative to base case Scenario 3 - Demand Side Management The schedule for the DSM peak shifting and peak clipping units are set day-ahead and cannot be revised intra-day. This limits the flexibility they can provide to the system and can lead to sub-optimal decisions due to forecast uncertainty. As shown in Chapter 6. Options for Increasing Power System Flexibility 88 Chapter 3, day-ahead wind generation is more often over-forecast than under-forecast, thus reducing the net load predicted for the following day. This will thereby tend to reduce the amount by which DSM will be utilised, particularly the expensive peak clipping DSM unit. As such, the peak clipping unit has a capacity factor of 1.3% over the year, while the peak shifting unit has a capacity factor of 5.7%. The clipping unit is never dispatched at its maximum output, but provides its maximum contribution to spinning reserve (42 MW) in every hour that it is utilised. Similarly the peak shifting unit provides its maximum contribution to spinning reserve (42 MW also) in 89% of the time that it is online. Thus the main functionality of the DSM units is in providing reserve rather than reducing the demand. This was seen to have a detrimental effect on the cycling of the base-load generation, despite its limited utilization. The addition of 500 MW of DSM increased start-ups for a typical CCGT by 18, relative to the base case, as seen in Figure 6.1, while starts for a typical coal unit increased by 7, as seen in Figure 6.2. These were the largest increases observed across all scenarios. Figure 6.3 also showed a large increase in the instances of severe ramping for a typical coal unit (+294). As was seen previously with pumped storage, when DSM units contribute to the spinning reserve target there is less requirement for thermal units to be online providing spinning reserve. Thus, the system with DSM will tend to commit less generation day-ahead. When forecast wind generation then fails to materialize the following day, conventional generation needs to be started at short notice, giving rise to the large increase in start-ups. (Production from peaking units also increased by almost 400%). Ramping is also increased, particularly for coal units as seen in Figure 6.3. To examine if DSM could bring about a reduction in base-load cycling, assuming that it did not contribute to spinning reserve, sensitivities were run in which (i) the peak clipping and peak shifting units did not provide spinning reserve, (ii) the peak clipping and peak shifting units did not provide spinning reserve and their dispatches could be rescheduled intra-day, and (iii) same as (ii), but with the variable operating cost for the clipping unit reduced from e80/MWh to e60/MWh and the variable operating cost for the shifting unit reduced from e40/MWh to e20/MWh. Table 6.4 shows the Chapter 6. Options for Increasing Power System Flexibility 89 Figure 6.4: Change in start-ups for a typical CCGT and coal unit for each DSM scenario capacity factor of the DSM peak clipping and shifting units for each of these scenarios. Removing the ability to provide spinning reserve reduced the utilization of these units, while allowing their dispatch to be changed intra-day increased utilization of the peak clipping unit, but reduced utilization of the peak shifting unit. Reducing the variable cost of DSM increased its utilization relative to the original scenario. These relatively small reductions in the utilization of the DSM units had large impacts on cycling of base-load plant as seen in Figure 6.4 and Figure 6.5 which show the change in starts and production from the base case for each of the DSM scenarios examined. Table 6.4: Capacity factor of DSM units for various scenarios DSM DSM, no reserve DSM, no reserve, with rescheduling DSM no reserve, with rescheduling, reduced cost Peak clipping 1.3% 0.16% 0.35% 3.68% Peak shifting 5.7% 4.9% 4.8% 7.5% For the new sensitivities the level of plant cycling is comparable with the base case. Only a minor reduction in CCGT start-ups was achieved (-2) and this was seen to correspond to reduced production from those units. Given the need for DSM shifting units to have zero impact on net energy over the day, its utilization is limited and as such, as shown in these results, it does not hold benefits for cycling of base-load plant. Chapter 6. Options for Increasing Power System Flexibility 90 Figure 6.5: Change in production for a typical CCGT and coal unit for each DSM scenario Scenario 4 - Turndown In this scenario the CCGTs whose minimum operating level was reduced were seen to utilise the increased turndown over an average of 330 hours throughout the year. By reducing the minimum operating level of five CCGTs on the system, those CCGTs were seen to benefit from reduced annual start-ups (annual start-ups for a typical CCGT were down by 15) and subsequently increased levels of production (+95 GWh), as seen in Figure 6.1. However, these units did experience increased instances of severe ramping, as they are now kept online during periods of high wind generation when previously they were shut-down. As such, Figure 6.3 shows an increase of 103 hours when severe ramping was required from a typical CCGT unit. As might be expected with CCGTs gaining increased production, production for a coal unit was consequently reduced (-30 GWh), as seen in Figure 6.2. Increased production from the five CCGTs also reduced production from peaking capacity (-27%), thus resulting in reduced CO2 emissions as seen in Table 6.6. Scenario 5 - Multi-mode operation of CCGTs The total production over the year from the multi-mode CCGTs in open-cycle mode was 27.5 GWh, almost 4 times as much as the highest merit OCGT peaking unit in the base case. Overall, the impact of including 500 MW of additional open-cycle capacity, Chapter 6. Options for Increasing Power System Flexibility 91 via multi-mode operation of 2 CCGT units, had a small impact on the system dispatch. The multi-mode CCGTs, when dispatched, were typically online around evening peak hours and tended to impact production from low-merit CCGT units and peaking units. As seen in Figure 6.1, the number of annual start-ups for a typical CCGT unit and the number of instances that a typical CCGT or coal unit was required to perform severe ramping, as seen in Figure 6.3, decreased indicating avoided cycling damage. 6.3.2 Impact on Wind Curtailment and CO2 Emissions The available wind power on the test system in the test year was 18.4 TWh. Table 6.5 shows the amount of available wind that was curtailed in each of the scenarios. It is clear that pumped energy storage, having the most flexible energy storage potential of the options examined, was most effective at minimising wind curtailment events on the system. Table 6.5: Curtailment of wind in each scenario Scenario Base Case Interconnection Pumped storage DSM Turndown Multi-mode Wind Curtailed (GWh) % Change from Base Case 148.4 61.5 56.0 117.3 108.9 153.6 -58.5 -62.3 -20.9 -26.6 3.49 The total Irish and British CO2 emissions for each scenario can be seen in Table 6.6. Each scenario is seen to reduce CO2 relative to the base case, however, the overall changes are small. The largest CO2 reduction occurred in scenario 1 with increased interconnector capacity. Emissions increased on the Irish system due to the increased production to meet increased export levels, however the production that was displaced on the British system was more CO2 intensive, thus yielding a net reduction. Chapter 6. Options for Increasing Power System Flexibility 92 Table 6.6: CO2 emissions in each scenario Scenario Base Case Interconnection Pumped storage DSM Turndown Multi-mode 6.4 CO2 emissions (Mtonnes) Change from base case (Mtonnes) 199.4 198.9 199.1 199.1 199.2 199.4 -0.5 -0.3 -0.3 -0.2 0 Summary of Results This chapter so far has investigated how commonly cited sources of power system flexibility will interact with base-load generation on a power system with a high wind energy penetration and alleviate or aggravate plant cycling. The results have been somewhat counter-intuitive as several of the flexibility options examined, including storage, were shown to contribute to plant cycling. The limited utilization of DSM, had little impact on cycling (although a large increase in cycling if it is assumed to provide reserve). Interconnection resulted in avoided cycling for both CCGT and coal plant while, increased turndown for CCGTs was also seen to benefit CCGT operation. The decision to invest in any of these options will be based on capital costs and expected revenues. Benefits to the power system such as a reduction in production costs, emissions or wind energy curtailment are often considered also. This chapter has shown that plant cycling is another important factor to be weighed up, regardless of whether the effects are positive or negative, particularly considering the high cycling costs that have been found, as discussed in Chapter 2. Chapter 6. Options for Increasing Power System Flexibility 6.5 6.5.1 93 Other Flexibility Options Battery Electric Vehicles Plug-in hybrid electric vehicles (PHEVs) and fully electric vehicles (EVs) provide an opportunity to reduce emissions and decrease the dependence of the transport sector on petroleum products. Consequently, many countries have announced national targets for electric vehicles, for example, the Department of Energy (D.O.E) in the US is seeking 1,000,000 vehicles on the road by 2015, while in Ireland the target is for 10% of the vehicle fleet (≈250,000 vehicles) to be electrified by 2020. Plug-in hybrid electric vehicles (PHEVs) and fully electric vehicles (EVs) can also deliver flexibility to power systems via the energy storage capacity present in the batteries. By employing a ‘smart charging’ strategy, whereby the system operator manages the charging of electric vehicles, the net load profile can be flattened somewhat by charging vehicles during the valleys, as depicted in Figure 6.6. This is particularly beneficial on a windy night when base-load units may be forced off-line to accommodate high wind power penetration. Thus, EVs should facilitate more base-load and less part-load operation from generators alleviating cycling issues and reducing emissions, as was found to be the case in Göransson et al. (2010). Figure 6.6: Illustration of load valley filling by EV charging Chapter 6. Options for Increasing Power System Flexibility 94 However, as shown in Hadley and Tsvetkova (2009) and Göransson et al. (2010), if a significant number of these vehicles are introduced without any control over the time of charging, i.e. a typical owner charges the vehicle on arriving home from work and the battery is charged until full, the evening peak demand will be exaggerated, requiring more production from peaking units and thus resulting in higher CO2 emissions. Assuming a smart charging scheme is in place, the system operator also has the ability to stop vehicle charging temporarily if, for example, wind generation on the system unexpectedly dropped off. Likewise, if wind generation unexpectedly picked up the system operator (or a demand aggregator) can begin charging vehicles with depleted or partially charged batteries. Thus, EVs can effectively deliver both positive and negative spinning reserve (not actually ‘spinning’ but with an equivalent activation time) to a power system (Kiviluoma and Meibom, 2011). However, it has been shown that the marginal benefits of EVs will saturate at a point as there is a limit to the amount of reserve that is required and the amount by which the net load profile can be flattened (Kiviluoma and Meibom, 2009). Vehicle-to-Grid (V2G) schemes have also been investigated, whereby it is possible for electrical energy present in the battery to be delivered to the grid. In this case EVs can deliver positive spinning reserve by not only reducing charging, but by actually providing electrical energy to the power system. However, repeatedly reversing the flow of electricity between the battery and the grid will result in some level of degradation to the battery which must be taken into consideration. When this, and the cost of the bidirectional power electronics required, were taken into consideration in Dallinger et al. (2011), it was found that it was not economical to provide positive spinning reserve from EVs by discharging the battery. 6.5.2 Maintenance Scheduling Another area where improvements in plant cycling could be gained (without the need for costly additions to the power system) is maintenance scheduling. One of the duties of a system operator is to agree an outage schedule with the power producing companies Chapter 6. Options for Increasing Power System Flexibility 95 which allows each generating unit to fulfill its maintenance requirements without compromising the reliability of the power system. This process typically involves generators submitting their outage requests for the year ahead to the system operator, who then determines the impact of the aggregate outage requests on system reliability, based on some reliability index (Feng and Wang, 2010; Shahidehpour and Marwali, 2000). The loss of load expectation (LOLE), expected duration of unmet demand (EDUD), expected unsupplied energy or expected lack of available reserve are typical indices used to determine the impact on system reliability (Mukerji et al., 1991). If the requested maintenance schedules do not cause the system reliability to fall below some defined standard (for example, the Irish system operator uses an LOLE of 8 hours per year), they will be approved. Otherwise, if maintenance requests are causing periods of reliability concern, the generator(s) involved must revise their outage request(s) in order to preserve system reliability. Typically generators seek to schedule their outages such that their overall revenue is maximized, or in other words they request outages for periods with the lowest electricity prices and hence the lowest electricity demand. Traditionally, system operators have focussed on ensuring that there is sufficient capacity to meet demand at all times during the year. However, a system with a large wind penetration will also need to maintain a certain level of operational flexibility, in addition to plant capacity, in order to maintain a reliable system. For example, if a large quantity of fast-starting or fast-ramping plant is unavailable due to maintenance, a system may still have sufficient capacity available to serve the load, however, should a sudden drop in wind power output occur, there may not be sufficient fast response generation available to compensate, or inflexible generators may be forced to operate outside their normal operational limits. This type of operation, particularly when required frequently of base-load generators, is associated with equipment deterioration, increased maintenance costs and a reduction in reliability, as discussed in Chapter 2. By ensuring that there is sufficient operating flexibility available within the generation fleet to meet net load variations at all times during the year, excessive cycling of conventional plant may be reduced/avoided. One approach to evaluating the level of flexibility present in power systems was Chapter 6. Options for Increasing Power System Flexibility 96 discussed in Lannoye et al. (2010), in a which a new metric, the insufficient ramping resource expectation (IRRE), based on the loss of load expectation (LOLE) metric for generation adequacy was presented. Utilizing such a metric in conjunction with multiple net load projections (perhaps based on historical demand and wind power data from several years) would go some way to ensuring that a power system maintained sufficient flexibility throughout the year. 6.5.3 Control of Wind Power Output By controlling the pitch angle of wind turbine blades it is possible to curtail wind power output or limit its upward ramp rate. Curtailment of wind power is often viewed as a negative outcome of a system having too little flexibility. However, there are occasions when wind curtailment is the most economic solution to meeting demand. For example, consider a system which has forecast a surge in wind power output, followed a short time later by a drop-off in wind power output. If accommodating this ‘short-lived’ high penetration of wind means switching off thermal plant, that will need to be restarted shortly afterwards when the wind penetration begins to decline, the resulting startup fuel costs, cycling costs and carbon costs may instead make it more favourable to curtail the wind power output for the short period. Ideally this is achieved by the system operator sending a dispatch instruction to the wind generators. Presently Bonneville Power Administration and Alberta Electric Service Operator are utilising ramp controls on wind generation under certain reliability criteria. However, some systems do not have the ability to control wind farm output (for example in Ireland a large proportion of the wind generation is connected to the distribution system, which cannot be controlled by the TSO), which can result in uneconomic system operation and plant cycling. 6.5.4 Market Options The power output from a wind farm is variable as the energy source itself, i.e. the wind, is variable. However, the correlation in wind speeds between any two given Chapter 6. Options for Increasing Power System Flexibility 97 sites decreases as the distance between those sites increases. Thus, when the power output from various wind farms dispersed over a large area is aggregated, the overall variability is less than the variability of the individual wind farms. This indicates that a system which is interconnected to a neighbouring system can benefit from the principle of statistical independence and thus reduce the burden on its thermal plant to manage net load variability. The US is divided into 130 balancing areas, each responsible for matching generation to demand in that area. Many studies have shown that consolidating some of these balancing areas can benefit the integration of variable renewables (NREL, 2011). With a high wind penetration ‘faster’ markets are also advantageous. Currently many markets are settled on an hourly basis, which can restrict access to flexible resources on the system. For example, in an hourly market a fast starting generator cannot be started up within the hour to meet an increase in net load. Instead it would have to wait until the beginning of the next hour to be dispatched, while online units would have to ramp their output to meet the increased net load instead. Milligan et al. (2010) finds the benefits of faster markets include greater access to flexibility and reduced a ramping requirement from conventional units. CHAPTER 7 Unit Commitment with Dynamic Cycling Costs 7.1 T Introduction HE increased levels of cycling that base-load plant will be forced to undergo due to increasing penetrations of wind generation have been shown in Chapter 4 and have also been seen in Göransson and Johnsson (2009). As discussed in Chapter 2, this can lead to high levels of damage accumulating within the plant’s components ultimately resulting in increased maintenance requirements and forced outage rates. Cycling related costs will arise via increased maintenance costs for generators, loss of revenue resulting from longer and more frequent outages, increased fuel costs due to reduced plant efficiency, as well as capital costs due to component replacement. Studies indicate that the magnitude of these cycling related costs are high but, as discussed in Chapter 2, accurately quantifying them is a challenging task given the range of components affected, the unit specific nature of the analysis and the lengthy time lag that is typically seen before cycling damage becomes apparent through component 98 Chapter 7. Unit Commitment with Dynamic Cycling Costs 99 failure (Lefton, 2004). Not considering these costs however will result in the uneconomic dispatch of plants, yet still markets currently do not include specific cycling cost components in their bidding mechanisms, or at best cycling costs are bundled into a generator’s start-up or ramping costs. Depending on the operating regime of a plant, these cycling related costs can accumulate rapidly and are therefore dissimilar to plant characteristics such as heat rate, which typically vary over a much longer time-scale. Therefore, to examine the impact of these costs accurately, they should be modelled in a dynamic manner such that they accumulate within the optimization process based on how the unit is being operated and can thereby influence dispatch decisions. This chapter presents a novel formulation that allows these cycling costs to be modelled dynamically, which can be integrated into a MIP (mixed integer programming) unit commitment and economic dispatch model. This facilitates more accurate modelling of these costs and examination of how they accumulate in line with the operating regime of a plant. The formulation sets up a cycling cost which increments with each additional plant start-up or ramp, with the resulting cost function being linear, piecewise linear or step-shaped. This new approach to modeling cycling costs is particularly suitable for long-term planning studies where it can be used to reflect the ageing effect on a plant over time. It may also have applications for real-world dispatch models where it can discourage the same unit from being repeatedly dispatched to cycle, as this will incur an incremental cost to reflect the wear-and-tear to that unit and can consequently alter its position in the merit order. A case study is included to determine how implementing dynamic cycling costs over a period of one year will affect the resulting dispatch relative to a scenario where cycling costs are not considered. 7.2 Formulation of Dynamic Cycling Costs A detailed formulation for implementing dynamic cycling costs which increase in line with unit operation is presented here. Cycling costs are subdivided into costs for Chapter 7. Unit Commitment with Dynamic Cycling Costs 100 (A) start-ups and (B) ramps. The formulation utilizes three main steps: (i) a binary variable is set to indicate that damaging operation has occurred at time step t, (ii) a counter tracks how much of that type of operation has occurred up to that point, and (iii) an incrementing cycling cost is incurred at that time step. Linear, piece-wise linear and step-shaped cost functions for both starts and ramps are detailed here. 7.2.1 Cycling Costs Related to Start-ups Linear Constraints 7.1 - 7.3 allow a dynamic, linearly incrementing cost for wear-and-tear related to start-ups to be modelled. Based on the online binary variable, vg (t), constraint 7.1 sets the start-up, sg (t), and shut-down, zg (t), binary variables equal to 1 appropriately, when a unit ‘g’ is started or shut down at time t. Constraint 7.2 increments a counter, NgS (t), to track how many start-ups have been performed by that unit. Constraint 7.3 determines the start-up related cycling cost, CgS (t), with the final term ensuring that a cost is only incurred when the decision is made to start the unit at time ‘t’ (i.e. sg (t) = 1). Figure 7.1 provides an example of this linearly increasing cost function, where the incremental cost, costSg , is set equal to 100. sg (t) − zg (t) = vg (t) − vg (t − 1), ∀ t ∈ T, ∀ g ∈ G (7.1) NgS (t) ≥ NgS (t − 1) + sg (t), ∀ t ∈ T, ∀ g ∈ G (7.2) ¡ ¢ CgS (t) ≥ NgS (t).costSg − M. 1 − sg (t) , ∀ t ∈ T, ∀ g ∈ G (7.3) Chapter 7. Unit Commitment with Dynamic Cycling Costs 101 Figure 7.1: Linearly increasing start-up related cycling cost Piecewise Linear By defining i thresholds, T hSg (i), each corresponding to a cumulative number of plant start-ups, at which point the start-up related cycling cost, CgS (t), will increase by incremental cost costSg (i) for each additional start, a piecewise linear incremental cost function can be modelled. Constraint 7.4 is a modified form of constraint 7.2 which counts the cumulative number of start-ups. For i > 1, the start-up counter, NgS (t, i), will not have a positive value until NgS (t, 1) has reached T hSg (i). T hSg (1) must equal 1. Constraint 7.5 determines the total cycling cost. Figure 7.2 provides an example of a piecewise linearly increasing cost function, where costSg (1) is set equal to 100, costSg (2) is set equal to 150 and T hSg (2) equals 4. NgS (t, i) µ ¶ S ≥ Ng (t − 1, 1) + sg (t) + 1 − T hSg (i), (7.4) ∀ t ∈ T, ∀ g ∈ G, ∀ i ≤ Ig CgS (t) ¶ Ig µ X ¡ ¢ S S S ≥ Ng (t, i). costg (i) − costg (i − 1) i ¡ ¢ − 1 − sg (t) .M, ∀ t ∈ T, ∀ g ∈ G (7.5) Chapter 7. Unit Commitment with Dynamic Cycling Costs 102 Figure 7.2: piecewise linearly increasing start-up related cycling cost Step Function Alternatively, if less information is known regarding the shape of the cost function an appropriate simplification may be to define a step function, where CgS (t) does not increment until T hSg (i) is reached. Again, it is required that T hSg (1) is equal to 1. NgS (t, i) is determined by constraint 7.6 and in this case can be greater than or less than 0 (it was previously defined as a positive variable only). Constraint 7.7 sets the binary variable stepg (t, i) equal to 1 when NgS (t, i) has exceeded T hSg (i), and constraint 7.8 determines the cycling cost. Figure 7.3 provides an example of this incrementing, step-shaped cost function, where costSg (t, 1) is set equal to 100, costSg (t, 2) is set equal to 150 and T hSg (2) equals 4. NgS (t, i) µ ¶ S = Ng (t − 1, 1) + sg (t) + 1 − T hSg (i), (7.6) ∀ t ∈ T, ∀ g ∈ G, ∀ i ≤ Ig NgS (t, i) − stepg (t, i).M ≤ 0, ∀ t ∈ T, ∀ g ∈ G, ∀ i ≤ Ig (7.7) Chapter 7. Unit Commitment with Dynamic Cycling Costs CS (t) ≥ costSg (i).stepg (t, i) − ¡ ¢ 1 − sg (t) .M, 103 (7.8) ∀ t ∈ T, ∀ g ∈ G, ∀ i ≤ Ig Figure 7.3: Step increasing start-up related cycling cost Hot and Cold Starts Either the linear, piecewise linear or step formulations can be extended to differentiate between hot and cold start-ups for units. Constraint 7.9 will set the binary variable cold plus its scold g (t) equal to 1 only if a unit is started at time t, having been offline for t minimum downtime, DTg . In constraints 7.2, 7.4 and 7.6 ‘+ sg (t)’ is replaced with ‘+ sg (t) + α.scold g (t)’. A scaling factor, α, is chosen based on the ratio of cycling damage caused by a hot start relative to a cold start, and thus normalizes NgS (t, i) to count in terms of hot starts. Tgcold +DTg scold g (t) ≥ vg (t) − X n=1 vg (t − n), ∀ t ∈ T, ∀ g ∈ G (7.9) Chapter 7. Unit Commitment with Dynamic Cycling Costs 7.2.2 7.2.2.1 104 Cycling Costs Related to Ramping Define one ramp level The simplest form of incurring cycling costs related to ramping duty is to define a change in output, Rg , between consecutive time periods, greater than which, damaging transients will occur within the unit. Constraints 7.10 and 7.11 ensure that the binary variable r(t) is set to 1 when a change in output exceeding Rg occurs. To avoid double counting cycling costs when large ramps are experienced in the start-up or shut-down process, the final term ensures that the constraints are non-binding when the unit is in the start-up or shut-down process. If the ramp-related cycling costs are likely to exceed the start-up or shut-down cost, constraint 7.12 is needed to prevent the model setting s(t) and z(t) both equal to 1 in constraint 7.1, in order to make constraints 7.10 and 7.11 non-binding. ¡ ¢ pg (t) − pg (t − 1) − M.rg (t) ≤ Rg + sg (t).M , ∀ t ∈ T, ∀ g ∈ G (7.10) ¡ ¢ pg (t − 1) − pg (t) − M.rg (t) ≤ Rg + zg (t).M , ∀ t ∈ T, ∀ g ∈ G (7.11) sg (t) + zg (t) ≤ 1, ∀ t ∈ T, ∀ g ∈ G (7.12) Utilizing the binary variable, rg (t), a counter is defined, as before, to incur an incrementing, ramp-related cycling cost, CgR (t). Using the formulation from Section 7.2.1, the ramp-related cycling cost function may be linear, piecewise linear or stepshaped. Constraints 7.2 and 7.3 are replaced with the analogous ramp terms shown in Table 7.1 to implement a linearly incrementing cost. Constraints 7.4 and 7.5, or 7.6 to 7.8, are replaced with the analogous ramp terms as shown in Table 7.1 to define a piecewise linear, or a step shaped, incrementing ramp related cycling cost respectively. Chapter 7. Unit Commitment with Dynamic Cycling Costs 105 Table 7.1: Analogous Terms Linear Piecewise Linear & Step 7.2.2.2 Starts Ramps Bi-directional Ramps sg (t) rg (t) xg (t) costSg NSg (t) CSg (t) costR g R Ng (t) CR g (t) costX g NX g (t) sg (t) rg (t) xg (t) costSg (i) NSg (t,i) ThSg (i) CSg (t) stepSg (t) costR g (i) NR g (t,i) ThR g (i) R Cg (t) stepR g (t) costX g (i) CX g (t) NgX (t,i) ThX g (i) CX g (t) stepX g (t) Define multiple ramp levels The previous formulation, where one level Rg is set to define a ramp, can be expanded to incur a dynamic ramp-related cycling cost, for j ramps of different magnitudes, Rg (j). Constraint 7.13 ensures that for a ramp less than Rg (1), rg (t, j) will equal zero for all j. A ramp greater than Rg (1), but less than Rg (2), will set rg (t, 1) equal to one, and so forth. The final term ensures that the constraint is non-binding when the unit ¡ is starting up. A corresponding constraint is needed for down ramps, where pg (t)¢ ¡ ¢ pg (t − 1) in constraint 7.13 is replaced with pg (t − 1)-pg (t) and M.s(t) is replaced with M.z(t). Constraint 7.14 ensures that the binary variable, rg (t, j), which indicates that a ramp ≥ Rg (j) has occurred, can only have a value of 1 for one ramp level j, at any given time. As before, constraint 7.12 is required to prevent sg (t) and zg (t) both being set to 1 to make constraint 7.13 and its corresponding constraint non-binding. Chapter 7. Unit Commitment with Dynamic Cycling Costs 106 j X ¡ ¢ ¡ ¢ pg (t) − pg (t − 1) < Rg (1). 1 − rg (t, j) + Rg (2).rg (t, 1) j=1 +... + Rg (j).rg (t, j − 1) + P¯g .rg (t, j) + M.sg (t), (7.13) where Rg (1) < Rg (2) < Rg (j)... < P¯g , ∀ t ∈ T, ∀ g ∈ G, ∀ j ≤ j̄g j X rg (t, j) ≤ 1, ∀ t ∈ T, ∀ g ∈ G, ∀ j ≤ j̄g (7.14) j=1 As with hot and cold starts, scaling factors are used to normalize NgR (t) to count in terms of one ramp level, as shown in constraint 7.15, where r(t, j) is expressed in terms of r(t, 1). Constraint 7.16 determines the total ramp-related cycling cost, shown here with a constant cost increment, costR g , with the final term ensuring that a cost is only incurred in a time period when a ramp (> Rg (1)) occurs. NgR (t) = NgR (t − 1) + rg (t, 1) + β.rg (t, 2) + .... + γ.rg (t, j), (7.15) ∀ t ∈ T, ∀ g ∈ G, ∀ j ≤ j̄g CgR (t) ≥ NgR (t).costR g − j X ¡ ¢ 1− rg (t, j) .M j=1 (7.16) ∀ t ∈ T, ∀ g ∈ G, ∀ j ≤ j̄g To combine this formulation of j ramp levels with i cost thresholds (i.e piecewise linear) constraints 7.15 and 7.16 are replaced by constraints 7.17 and 7.18, such that R R once NgR (t, i) reaches T hR g (i), Cg (t, i) will begin incrementing by costg (i). Chapter 7. Unit Commitment with Dynamic Cycling Costs ¡ NgR (t, i) = NgR (t − 1, 1) + rg (t, 1) + β.rg (t, 2) ¢ +.... + γ.rg (t, j) + 1 − T hR g (i) 107 (7.17) ∀ t ∈ T, ∀ g ∈ G, ∀ j ≤ j̄g , ∀ i ≤ Ig CgR (t) ¶ Ig µ X ¡ ¢ R R R ≥ Ng (t, i). costg (i) − costg (i − 1) − i j X (7.18) rg (t, j).M, ∀ t ∈ T, ∀ g ∈ G, ∀ j ≤ j̄g j=1 To include a step-shaped ramp related cycling cost function, constraints 7.6-7.8 are replaced with the analogous terms for ramping from Table 1. 7.2.2.3 Bi-directional ramps Bi-directional ramping, typically experienced by a load-following unit, is thought to be significantly more severe than ramps in one direction. A more detailed analysis of cycling costs can include costs for bi-directional ramping as follows. Constraints 7.19 and 7.20 set the binary variables upg (t) and downg (t) to indicate the direction of ramping. Only ramps of magnitude greater than Rg are considered as there will be some level of ramping capability a generator can undertake relatively free of wear-andtear. Constraints 7.21 and 7.22 determine when a unit experiences large load changes in opposite directions between two consecutive time periods. pg (t) − pg (t − 1) ≤ Rg + M.upg (t) + M.sg (t), ∀ t ∈ T, ∀ g ∈ G (7.19) Chapter 7. Unit Commitment with Dynamic Cycling Costs pg (t − 1) − pg (t) ≤ Rg + M.downg (t) + M.zg (t), ∀ t ∈ T, ∀ g ∈ G 108 (7.20) upg (t) + downg (t − 1) − M.xg (t) ≤ 1, ∀ t ∈ T, ∀ g ∈ G (7.21) upg (t − 1) + downg (t) − M.xg (t) ≤ 1, ∀ t ∈ T, ∀ g ∈ G (7.22) The binary variable xg (t) can now be used to increment a counter which in turn can incur a dynamic bi-directional ramp-related cycling cost. To implement a linearly incrementing cost function constraints 7.2 and 7.3 are replaced with the analogous ramp terms shown in Table 1. Again, constraints 7.4 and 7.5, or constraints 7.6 to 7.8, are replaced with the analogous ramp terms, as shown in Table 1, to implement a piecewise linearly incrementing cost or a step-shaped incrementing cost respectively. If dynamic cycling costs for ramping and bi-directional ramping are implemented together it is necessary to avoid double counting ramping costs. This is achieved by subtracting [r(t, j).costR (j) + r(t − 1, j).costR (j)] from the total cycling cost for bi-directional ramping, CgX (t), when the reverse directional ramp is detected (when xg (t)=1). 7.3 Model and Test System To examine how cycling costs, modelled dynamically, will impact plant dispatch the new formulation was implemented in a conventional MIP unit commitment model based on Carrión and Arroyo (2006) and Arroyo and Conejo (2000). The unit commitment problem was formulated as Chapter 7. Unit Commitment with Dynamic Cycling Costs M inimize XX cpg (t) + csg (t) + CgS (t) + CgR (t) 109 (7.23) t∈T g∈G subject to X pg (t) = D(t), ∀ t ∈ T (7.24) pg (t) ≤ P̄g .vg (t), ∀ t ∈ T (7.25) pg (t) ≥ P g .vg (t), ∀ t ∈ T (7.26) g∈G As per Carrión and Arroyo (2006) and illustrated by Figure 7.4, a piecewise linear approximation of a quadratic production cost function for each unit was adopted as represented by: N Lg cpg (t) = Ag vg (t) + X Flg δl g(t), ∀ t ∈ T, ∀ g ∈ G (7.27) l=1 N Lg pg (t) = X δl g(t) + P g vg (t), ∀ t ∈ T, ∀ g ∈ G (7.28) l=1 δ1 (g, t) ≤ T1g − P g , ∀ t ∈ T, ∀ g ∈ G (7.29) δl (g, t) ≤ Tlg − Tl−1g , ∀ t ∈ T, ∀ g ∈ G ∀ l = 2...N Lg − 1 (7.30) δN Lg (g, t) ≤ P̄g − TN Lg −1 − Tl−1g , ∀ t ∈ T, ∀ g ∈ G (7.31) Chapter 7. Unit Commitment with Dynamic Cycling Costs δl (g, t) ≥ 0, ∀ t ∈ T, ∀ g ∈ G ∀ l = 1...N Lg 110 (7.32) where Ag = ag + bg P g + cg P 2g . Figure 7.4: Piecewise linear production cost (Carrión and Arroyo, 2006) Start-up costs which were dependent on the period of time the unit had been offline were modelled as follows: ¡ ¢ csg (t) ≥ vg (t) − vg (t − 1) .hcg ∀ t ∈ T, ∀ g ∈ G csg (t) Tgcold +DTg X ¡ ≥ vg (t) − ¢ vg (t − n) .ccg , ∀ t ∈ T, ∀ g ∈ G (7.33) (7.34) n=1 Minimum up time constraints were formulated by constraints 7.35, 7.36 and 7.37. Equation 7.35 is only included if the number of hours a unit must remain online to satisfy its minimum uptime, Bg , is greater than or equal to 1. t≤Bg X¡ ¢ 1 − vg (t) = 0, ∀ g ∈ G t (7.35) Chapter 7. Unit Commitment with Dynamic Cycling Costs 111 t+U Tg −1 X vg (n) ≥ U Tg .sg (t), ∀ g ∈ G, ∀ t = Bg + 1...T̄ − U Tg + 1 (7.36) n=t T̄ X ¡ ¢ vg (n) − sg (t) ≥ 0, ∀ g ∈ G, ∀ t = T̄ − U T + 2...T̄ (7.37) n=t ¡ ¢ where Bg = max 0, vg (T)U Tg -hup g +vg (T) . Minimum down time constraints were formulated using constraints 7.38, 7.39 and 7.40. Equation 7.35 is only included if Lg ≥ 1. t≤Lg X¡ ¢ vg (t) = 0, ∀ g ∈ G. (7.38) t t+DTg −1 X vg (n) ≥ DTg .zg (t), ∀ g ∈ G, ∀ t = Lg + 1...T̄ − DTg + 1 (7.39) n=t T̄ X ¡ ¢ 1 − vg (n) − zg (t) ≥ 0, ∀ g ∈ G, ∀ t = T̄ − DT + 2...T̄ (7.40) n=t ¢ ¡ +(1 − vg (T)) . where Lg = max 0, (1 − vg (T)).DTg -hdown g The formulation was applied to the 10 unit test system used in Carrión and Arroyo (2006); Kazarlis et al. (1996); Damousis et al. (2004), which was duplicated to give a 20 unit system, thus facilitating a larger case study. The technical and economic characteristics of these units are given in Table 7.2 and Table 7.3. (The initial state Chapter 7. Unit Commitment with Dynamic Cycling Costs 112 is the number of hours a unit is assumed to have been online for at the start of the optimization.) The fuel cost curves for the test units are given in Appendix D. The peak demand (1500 MW) was doubled (3000 MW) and a historical year-long hourly demand profile for the Irish system was scaled to produce a demand profile with a 3000 MW peak. The model was run for the test year, optimizing each day at an hourly resolution. Table 7.2: Generator Data Units P̄g (MW) Pg (MW) U Tg (h) DTg (h) Initial State (h) 1-4 5-8 9-10 11-12 13-14 15-20 455 130 162 80 85 55 150 20 25 20 25 10 8 5 6 3 3 1 8 5 6 3 3 1 8 -5 -6 -3 -3 -1 Table 7.3: Generator production cost data Units ag ($/h) bg ($/MWh) cg ($/M W 2 h) hcg ($/h) ccg ($/h) tcold g (h) 1-2 3-4 5-6 7-8 9-10 11-12 13-14 15-16 17-18 19-20 1000 970 700 680 450 370 480 660 665 670 16.19 17.26 16.60 16.50 19.70 22.26 27.74 25.92 27.27 27.79 0.00048 0.00031 0.00200 0.00211 0.00398 0.00712 0.00079 0.00413 0.00222 0.00173 4500 5000 550 560 900 170 260 30 30 30 9000 10000 1100 1120 1800 340 520 60 60 60 5 5 4 4 4 2 2 0 0 0 Generator cycling costs are difficult to determine and largely uncertain as discussed in Section I. The figures used here, shown in Table 7.4, to implement dynamic cycling costs for the test system, are a conservative assumption based on those shown in Lefton et al. (2006) and are intended to illustrate how dynamic cycling costs could Chapter 7. Unit Commitment with Dynamic Cycling Costs 113 impact system operation, rather than provide an accurate estimate of such costs. Piecewise linear costs for starts and ramps were implemented with the incremental S cost (costSg (i) or costR g (i)) increasing by 10% and 20% when the start counter (Ng (t, 1)), S or ramp counter (NgR (t, 1)), exceeded 100 (T hSg (2) or T hR g (2)) and 200 (T hg (3) or T hR g (3)) respectively. The scaling factor, α, was chosen to be 2, i.e. each cold start incremented NgS (t, 1) by 2 (while a hot start incremented NgS (t, 1) by 1). Two ramp levels, Rg (1) and Rg (2) corresponding to 20% and 40% of the difference between maximum and minimum output for a unit, were modelled. Scaling factors were chosen such that ramps greater than Rg (1) or Rg (2) incremented NgR (t, 1) by 1 or 2 respectively. Table 7.4: Incremental cycling costs $, (i=1) Units Base-load (Units 1-4) Mid-merit (Units 5-10) Peaking (Units 11-20) 7.4 costSg (i) costR g (i) 300 60 30 15 3 1.5 Results This section examines how plant dispatches are affected when (i) a cycling cost related to start-ups is implemented, (ii) a cycling cost related to ramping is implemented and (iii) cycling costs related to start-ups and ramping are implemented simultaneously. 7.4.1 Start-up Related Cycling Costs Results Implementing a dynamic cycling cost for plant start-ups, as shown in Table 7.4, was seen to result in an overall reduction in plant start-ups. This is seen in Table 7.5, which reveals reducing starts for base-load and mid-merit units. For base-load units, the reduction in starts was correlated with increased production as, having the largest incremental cycling costs, these units avoided shut-downs and gained more online hours. This is seen via the average capacity factor shown in Table 7.6. Mid-merit units how- Chapter 7. Unit Commitment with Dynamic Cycling Costs 114 ever, who also had reduced starts, saw reduced production indicating that they were utilised less often. As these units were started up and shut down, and subsequently incurred cycling costs, it became more economical after some point to dispatch peaking units. Thus, starts and production increased for peaking units when a dynamic cycling cost for start-ups was modelled. Figure 7.5 illustrates the cumulative start-ups for the mid-merit and peaking units over the year when (i) cycling costs were modelled and (ii) when cycling costs were not modelled. Starts are seen to accumulate rapidly between 0 and 2000 hours and from hours greater than 7000, as these are the winter months and thus have higher demand, requiring more plant start-ups. Up to 1000 hours, the level of cycling costs incurred by the mid-merit and peaking units is seen to have no impact on the number of start-ups. However, beyond 1000 hours the cycling costs which are accumulated by mid-merit begins to have an effect on their position in the merit order and consequently peaking plant are seen to be dispatched more frequently. Modelling dynamic cycling costs related to plant start-ups was also found to have the knock on effect of increasing generator ramping. Over the year a 22% increase in ramping (NgR (t, 1)) was observed relative to the case when no cycling costs were modelled as generators were more frequently ramped down to minimum output, rather than shut-down, in an effort to avoid the increasing cycling costs. Table 7.5: Impact of dynamic cycling costs for start-ups on total annual starts No cycling costs modeled Cycling cost for starts modeled Base-load (Units 1-4) Mid-merit (Units 5-10) Peaking (Units 11-20) 34 1372 577 12 1005 838 Total 1983 1855 Units Units within the same class, i.e. base-load, mid-merit or peaking, were also seen to converge to a similar number of annual start-ups, as indicated by the reduced standard deviation of annual start-ups seen in Table 7.7. This indicates that once a unit has been cycled and its cycling cost is incremented, the next time a unit needs to be cycled the costs will have now changed such that a different unit (most likely the next in the Chapter 7. Unit Commitment with Dynamic Cycling Costs 115 Table 7.6: Impact of dynamic cycling costs for start-ups on average plant capacity factors (%) No cycling Cycling cost for costs modeled starts modeled Base-load (Units 1-4) 92.59 92.73 Mid-merit (Units 5-10) 27.82 25.42 Peaking (Units 11-20) 0.85 2.23 Units Figure 7.5: Cumulative plant start-ups over the year, shown when dynamic cycling costs for starts were (i) modelled and (ii) not modelled merit order) may be scheduled. This leads to the burden of cycling operation being more evenly distributed across the units. Over a long horizon, i.e. several years, this effect can lead to a shift in the merit order, a trend which is somewhat emerging in Figure 7.5. To facilitate a sensitivity analysis, multiples of the initial incremental cycling costs, costSg (1), that were shown in Table 7.4, were also examined. As the incremental cost was increased the reduction in start stop cycling that is achieved by modelling dynamic cycling costs quickly saturated as seen in Figure 7.6, thus indicating that the majority of plant cycling is unavoidable. Table 7.8 shows a breakdown of the total number of Chapter 7. Unit Commitment with Dynamic Cycling Costs 116 Table 7.7: Impact of dynamic cycling costs on plant start-ups by unit type No cycling Cycling cost for cost modelled starts modelled Units Avg Std. Dev Avg Std. Dev Base-load (Units 1-4) 8.5 9.9 3 3.6 Mid-merit (Units 5-10) 228.7 75.7 167.5 26.1 Peaking (Units 11-20) 57.7 73.1 83.8 27.5 starts by unit group, which again reveals that increasing starts for peaking units are correlated with increasing incremental cycling cost, as it becomes more favourable to dispatch these units due to the relatively larger cycling costs associated with the midmerit units. (The ripples in the curve shown in Figure 7.6 result from the increasing starts for peaking units, as seen in Table 7.8.) Figure 7.6: Impact of dynamic cycling cost on total start-ups, shown for various multiples of costSg (i) A scenario where cycling costs were only modelled for a subset of the total fleet was also examined. The 6 largest units on the system (units 1, 2, 3, 4, 9, 10) were chosen based on the assumption that these units would be most impacted by cycling operation and thus most likely to bid a wear-and-tear cost into the market to reflect this. The results showed that although the number of annual start-ups was reduced for these units, the start-ups for other units increased by an amount much greater than Chapter 7. Unit Commitment with Dynamic Cycling Costs 117 Table 7.8: Impact of dynamic cycling costs for starts on total plant start-ups, shown for various multiples of costSg (i) Base-load Mid-merit Peaking Units 1-4 Units 5-10 Units 11-20 No cycling cost 34 1372 577 costSg (i)*0.5 13 1104 781 costSg (i)*1 costSg (i)*2 costSg (i)*3 costSg (i)*10 12 1005 838 13 941 896 13 907 948 13 869 992 the reduction achieved for the units which bid a cycling cost, as seen in Table 7.9. This would indicate the need for a uniform policy relating to the bidding of cycling costs to be implemented in markets, such that all units reflect their cycling costs, or do not, to avoid the situation where only some generators are bidding cycling costs which leads to inefficient operation and excessive costs. Table 7.9: Change in starts when a subset of units bid cycling costs for start-ups ∆ Starts Units 1, 2, 3, 4, 9, 10 All other units 7.4.2 -86 +256 Ramping Related Cycling Costs Results Implementing a dynamic cycling cost for plant ramping (shown in Table 7.4) resulted in a 90% reduction in ramping overall as seen in Table 7.10. As described previously, assuming a ramp greater than 20% or 40% of the difference between a unit’s maximum and minimum output increments the ramp counter, NgR (t), by a value of 1 or 2 respectively. The total value of NgR (t) at the end of the test year, summed for all units, is shown in Table 7.10. Base-load units which carried out the greatest amount of ramping when cycling costs were not modelled, saw the greatest reduction in ramping Chapter 7. Unit Commitment with Dynamic Cycling Costs 118 operation when cycling costs for ramps were implemented. The drastic reduction in ramping that was achieved by implementing dynamic ramping costs, however, led to increased start-stop cycling as might be expected, although only by 3.3% over the year. The most notable change to the overall dispatch that resulted from the introduction of dynamic ramping costs was a slight reduction in production from base-load plant allowing for increased production from mid-merit and peaking units as seen in Table 7.11, thereby spreading the ramping requirement over more units. Thus, including the ramping cost was also seen to result in a slightly greater number of units online (5.94 per hour on average when dynamic ramping costs were modelled, versus 5.92 when no cycling costs were modelled). Table 7.10: Impact of dynamic cycling costs for ramping on total annual ramping (NgR (t, 1)) No cycling Cycling cost for costs modeled ramps modeled Base-load (Units 1-4) 3717 120 Mid-merit (Units 5-10) 2214 1224 Peaking (Units 11-20) 795 623 Total ramping 6726 1967 Units Table 7.11: Impact of dynamic cycling costs for ramping on average plant capacity factors (%) No cycling Cycling cost for costs modeled ramps modeled Base-load (Units 1-4) 92.59 92.21 Mid merit (Units 5-10) 27.82 28.61 Peaking (Units 11-20) 0.85 1.02 Units 7.4.3 Start-up and Ramping Cycling Costs Results Implementing dynamic cycling costs (as shown in Table 7.4) for starts and ramping simultaneously, reduced both types of cycling operation relative to the case when no Chapter 7. Unit Commitment with Dynamic Cycling Costs 119 cycling costs were modelled, as shown in Table 7.12. Base-load units, having the largest cycling costs, see the greatest reductions in cycling operation. Nonetheless, neither total starts nor total ramps were reduced in this scenario as much as starts alone or ramps alone were reduced when cycling costs for starts or ramps were modelled individually. However, when cycling costs for start-ups only were modelled, ramping operation increased and likewise when cycling costs for ramping only were modelled, starts increased, thus when the cycling costs that would have been incurred, assuming the costs given in Table 7.4 increment as described in Section 7.3, the case in which cycling costs for start-ups and ramping were modelled simultaneously had the lowest overall cycling costs, as shown in Figure 7.7. This would indicate that modelling cycling costs for starts and ramping simultaneously most cost effectively reduces cycling and as such one should not be considered without the other. Table 7.12: Impact on total annual starts and ramps when dynamic cycling costs for both start-ups and ramping were modelled Units No cycling costs Cycling cost for starts modeled and ramps modeled Starts Ramps Starts Ramps 34 3717 12 144 Mid merit (Units 5-10) 1372 2214 1003 2069 Peaking (Units 11-20) 577 795 855 1456 Total 1983 6726 1870 3669 Base-load (Units 1-4) Finally, when total system costs are examined for the scenario including cycling costs and compared to the total system cost for the scenario in which cycling costs were not modeled, but were calculated and added afterwards, it can be seen that modeling cycling costs leads to lower system costs overall. This is shown in Figure 7.8. In this example, the cost saving seen is considerable i.e. 14%. Chapter 7. Unit Commitment with Dynamic Cycling Costs 120 Figure 7.7: Cycling costs (that would have been incurred) shown for various scenarios Figure 7.8: Total system costs shown for various scenarios 7.5 Summary Interest concerning cycling costs is growing and this paper sets out a formulation that can utilize knowledge of incremental wear-and-tear costs related to plant start-ups or ramping, to implement a dynamic incrementing cycling cost. The formulation covers linear, piecewise linear and step-shaped cycling cost functions, the appropriate choice for a user being determined by the level of knowledge of the generator’s cycling costs. The formulation for piecewise linear incremental cycling costs related to plant start- Chapter 7. Unit Commitment with Dynamic Cycling Costs 121 ups and ramps was implemented for a test system. Although the incremental costs chosen are approximations, the results reveal certain trends that are likely for power systems where generators undergo regular cycling and reflect the resulting wear-andtear costs in their bids. For example, dynamically modeling cycling costs for generator starts was seen to reduce the number of starts, but caused ramping operation to be increased (and vice-versa), whilst modeling cycling costs for only a subset of the generation fleet was seen to induce much higher levels of cycling in the remaining generation. It was also seen that as cycling costs accumulated over time changes in the merit order occurred, and that modeling cycling costs led to an overall saving for the system as cycling operation was subsequently reduced. CHAPTER 8 Conclusions T HIS thesis presented research related to the cycling of base-load generation with increasing penetrations of wind energy on a power system. In Chapter 1 the evolution of power systems to incorporate higher levels of wind generation against a background of deregulation and increased competition is discussed. The likelihood of increased generator cycling resulting has been found in many studies, such as GE (2010); NREL (2010); NYISO (2010), and is beginning to become apparent in real world systems (MMU, 2010). The physical consequences for increased cycling are explored in Chapter 2 and thus provides the motivation for this research. Chapter 4 outlined how the operation of CCGT and coal units will be impacted by increasing levels of wind generation on a power system. Base-load CCGT units were seen to undergo a large increase in start-stop cycling as wind penetration increased, while coal units, being the most base-load generation, tended to remain online but were subject to increased ramping and part-load operation. Thus, both CCGT and coal units would be expected to experience increasing costs and forced outage rates 122 Chapter 8. Conclusions 123 over time due to wear and degradation of components from cycling operation. Sensitivity analyses were conducted to examine the level of cycling occurring when storage and interconnection were removed (individually) from the system. The results showed reduced cycling for base-load plant in both cases. Without storage on the system, there is an increased requirement on base-load units to be online providing reserve to the system, resulting in reduced start-stop cycling, while without interconnection the entire system demand must be met domestically yielding increased production from and reduced cycling of base-load units. Having observed the decreasing production and online hours for CCGT units, Chapter 5 examined a new mode of operation for these units. Many CCGT units are fitted with a bypass stack which allows the steam cycle to be bypassed and the gas turbine to be run in open-cycle mode; a highly flexible, although less efficient, mode of operation. The benefits of allowing CCGTs to operate in this manner, when technically possible and economically optimal, included increased availability of replacement reserve. Production from peaking plant was also seen to be displaced when multi-mode operation of CCGTs was introduced, indicating a reduced need for these units to be built and consequently a saving to society. The results also showed that low-merit CCGTs utilized the multi-mode function more than high-merit CCGTs, as they are frequently offline and available for dispatch, whilst the increased competition among generators, typical at higher levels of wind generation, resulted in multi-mode operation of CCGTs being utilized less frequently. Chapter 6 examined how incorporating various sources of flexibility onto a power system would impact cycling of base-load units and interestingly some were found to have negative impacts on plant cycling. Pumped storage and DSM (assuming it provided reserve) increased coal cycling as the requirement on these units to remain online for reserve provision was reduced. Interconnection and lower minimum operating levels for CCGT units were found to reduce CCGT cycling and yield increased production for these units. Chapter 7 presented a novel formulation to allow cycling costs to be represented in Chapter 8. Conclusions 124 a dynamic manner. Implementation of this formulation in a unit commitment model allowed a case study to be conducted. The results showed that modelling dynamic cycling costs will result in a reduction in cycling operation, however, if cycling costs are modelled for a subset of generation only (the 6 largest units on the test system in this case), the resulting level of cycling is significantly higher than the case when no cycling costs were modelled. This indicates the importance of a uniform approach to bidding cycling costs in electricity markets. It was also found that as cycling costs accumulated over time, changes in the merit order became apparent. Specifically, as mid-merit units were started up and shut down, and subsequently accumulated cycling costs, it was found that after some point it became more economical to dispatch peaking units, which had lower incremental cycling costs. This highlights the importance of investing in flexible generation and retrofitting existing plant to be more capable of frequent cycling. 8.1 Future Work The analysis completed in Chapter 4, which examined the impact of increasing wind penetrations on the operation of base-load plant, was conducted with an hourly time resolution model, ie. the Wilmar Planning Tool. Each of the generators modelled on the test system was capable of ramping from its minimum to maximum output (or vice versa) in under one hour, so ramp rate constraints were non-binding. However, at a time resolution under one hour modelling generator ramp rates would almost certainly have an impact on the resulting dispatch, particularly as wind energy penetration increases and the magnitude of net load ramps also increase. Consequently, a new version of the Wilmar model, which operates with a 15 minute time step, has been in development at the Electricity Research Centre in conjunction with this work. A change to the structure of the model requires a change to the structure of the scenario trees which are inputted into the model. Thus, an updated Scenario Tree Tool is also being developed which will allow greater flexibility in making alterations to the model structure, such as the time step, frequency of rolling planning, length of optimization Chapter 8. Conclusions 125 Figure 8.1: CO2 emissions increase linearly with production horizon or the number of branches in the scenario tree. Future work should utilise this new version of the model to analyse if generator cycling is currently underestimated using an hourly time step. The analysis completed in Chapters 4 to 6 included estimates of the CO2 emissions from generators based on the fuel consumption of the generators. Each fuel type was assigned a carbon content (tonnes/GJ) and this was used to determine the CO2 emissions of the fuel consumed (GJ) by each generator in each hour. Thus, CO2 emissions increased linearly (or piece-wise linearly if multiple heat rate slopes were modelled) as production from a generator (and therefore fuel consumption) increased, as shown in Figure 8.1 for a CCGT unit from the test system described in Chapter 3. However, in reality generator fuel consumption, and thus emissions, are nonlinear and Figure 8.1 represents a common modelling simplification for linear models. Motivated by the need to understand the link between emissions and generator cycling, recent work conducted at NREL (as part of the Western Wind and Solar Phase 2 Study) has utilised CEMs data to analyse the emissions from generators at various levels of production. The results of this work determines the increase in emissions or ‘emissions penalty’ that is incurred, relative to one hour of full-load operation, when a unit is (i) operated at part-load (defined as 50% of max generation), (ii) ramped (defined as Chapter 8. Conclusions 126 5% capacity change in one hour) and (iii) started-up (Brinkman, 2011). The findings are detailed in Table 8.1. Future work could perform a similar analysis on emissions penalties using data for generators on the Irish system. Reproducing Table 8.1 for the Irish system would allow for more accurate analysis of the impact of generation cycling on system emissions. Also as CO2 costs can represent almost a quarter of total system costs, more detailed analysis of CO2 costs is warranted. Table 8.1: CO2 emissions penalties for cycling operation (Brinkman, 2011) Unit type Coal CCGT OCGT Part-load penalty 5.1% 15.6% 12.4% Ramping penalty 0.4% 0.3% 0.3% Start-up penalty 110% 32% 32% A technical approach has been taken in this thesis to examine the issue of baseload cycling with increasing wind penetration. However, many interesting policy and market design issues have been indirectly raised, for example the fact that variable wind generation may perversely support inflexible generation or that generators may seek to bid cycling costs into the market and by doing so can avoid cycling operation. If the goal for power systems is to achieve a high penetration of renewable generation, in order to improve security of supply and reduce emissions without compromising system reliability, the portfolio of conventional generation will need to become more flexible, which may require incentives. The evolution of existing portfolios into more flexible portfolios, in light of these concerns, is an interesting research area that warrants investigation. References AIGS, 2008. All Island Renewable Grid Study, Workstream 2B, [Online] Available: http://www.dcenr.gov.ie. Al-Sunaidy, A., Green, R., 2006. Electricity deregulation in OECD (Organization for Economic Cooperation and Development) countries. Energy 31 (6-7), 769–787. Albright, D., Albright, D., Albright, J., 1999. Generator field winding shorted turn detection technology. Generatortech, Inc. Anderson, R., van Ballegooyen, H., 2003. Steam turbine bypass systems. Combined Cycle Journal, Fourth Quarter, [Online] Available: http://www.psimedia.info/CCJ.htm. APPrO, 2006. The Association of Power Producers of Ontario, Adopting a Ramp Charge to Improve Performance of the Ontario Market, [Online] Available: http://www.ieso.ca/imoweb/pubs/consult/mep/MP WG-20060707-ramp-cost.pdf. Arroyo, J., Conejo, A., 2000. Optimal response of a thermal unit to an electricity spot market. IEEE Transactions on Power Systems 15 (3), 1098–1104. Arroyo, J., Conejo, A., 2004. Modeling of start-up and shut-down power trajectories of thermal units. IEEE Transactions on Power Systems 19 (3), 1562–1568. AWEA, 2011a. American Wind Energy Association, U.S. wind industry continues growth, Press Release, [Online] Available: http://www.awea.org/newsroom/pressreleases/release 07APR11 .cfm. AWEA, 2011b. American Wind Energy Association, U.S. Wind Industry First Quarter 2011 Market Report, [Online] Available: http://www.awea.org. Axford, M., 2009. Recession reduces demand for electricity. Power, [Online] Available: http://www.powermag.com. 127 References 128 Balling, L., Hofmann, D., 2007. Fast cycling towards bigger profits. Modern power systems, [Online] Available: http://www.modernpowersystems.com. Bird, L., Bolinger, M., Gagliano, T., Wiser, R., Brown, M., Parsons, B., 2005. Policies and market factors driving wind power development in the United States. Energy Policy 33 (11), 1397–1407. Bixby, R., Fenelon, M., Gu, Z., Rothberg, E., Wunderling, R., 2000. MIP: Theory and Practice Closing the Gap. In: Proc. of 19th IFIP TC7 Conference on system modelling and optimization. Vol. 174. pp. 19–49. Black & Veatch, 2011. 2011 Strategic Directions Survey Results, [Online] Available: http://www.bv.com/Downloads/Resources/Brochures/. Blevins, B., 2007. Combined-cycle unit modeling in the nodal design, [Online] Available: http://www.ercot.com. Bloomberg, 2011. Bloomberg New Energy Finance, Wind turbine prices fall to their lowest in recent years, Press Release, [Online] Available: http://www.bnef.com/PressReleases/view/139. Braun, M., 2004. Environmental external costs from power generation by renewable energies. Thesis, Stuttgart University, Stuttgart, Germany. Brinkman, G., 2011. NREL, Wind impact on emissions?, [Online] Available: http://www.uwig.org/kcworkshop/Brinkman-KCWork.pdf. Brown, P., Lopes, J., Matos, M., May 2008. Optimization of pumped storage capacity in an isolated power system with large renewable penetration. IEEE Transactions on Power Systems 23 (2), 523–531. Brown, T. B., 1994. Assessing the effect of thermal transients on the life of boiler plant. In: Proc. of International Conference on Life Management of Power Plants. pp. 137–143. CAISO, 2010a. California ISO, Integration of renewable resources - operational requirements and generation fleet capability at 20 percent RPS, [Online] Available: http://www.caiso.com/2804/2804d036401f0ex.html. CAISO, 2010b. California ISO, Multi-stage generating (MSG) unit modeling, [Online] Available: http://www.caiso.com/2078/2078908392d0.html. Carrino, A., Jones, R., 2011. Coal plants challenged as gas plants surge. Power, [Online] Available: http://www.powermag.com/. Carrión, M., Arroyo, J., 2006. A computationally efficient mixed-integer linear formulation for the thermal unit commitment problem. IEEE Transactions on Power Systems 21 (3), 1371–1378. Castano, I., 2011. China installing wind-power capacity as fast as it can [Online] Available: http://www.renewableenergyworld.com. References 129 CER, 2010. Commission for Energy Regulation, cast Model and PLEXOS Validation Report http://www.allislandproject.org. Redpoint Validated Fore2010, [Online] Available: Charles River Associates, 2010. Spp witf wind integration study. prepared for Southwest Power Pool, [Online] Available: http://www.uwig.org. Colpier, U., Cornland, D., 2002. The economics of the combined cycle gas turbine- an experience curve analysis. Energy Policy 30 (4), 309–316. Dallinger, D., Krampe, D., Wietschel, M., 2011. Vehicle-to-grid regulation reserves based on a dynamic simulation of mobility behavior. IEEE Transactions on Smart Grid (available online). Damousis, I., Bakirtzis, A., Dokopoulos, P., 2004. A solution to the unit-commitment problem using integer-coded genetic algorithm. IEEE Transactions on Power Systems 19 (2), 1165–1172. Danneman, E., Beuning, S., 2011. Wind integration System and generation issues, [Online] Available: http://www.energy-tech.com. Dany, G., 2001. Power reserve in interconnected systems with high wind power production. In: Proc. of IEEE PowerTech Conference. Vol. 4. Denny, E., O’Malley, M., 2007. Quantifying the total net benefits of grid integrated wind. IEEE Transactions on Power Systems 22 (2), 605–615. DOE, 2009. United States Department of Energy, States with Renewable Portfolio Standards, [Online] Available: http://apps1.eere.energy.gov/states/maps/renewable portfolio states.cfm. Doherty, R., O’Malley, M., 2005. A new approach to quantify reserve demand in systems with significant installed wind capacity. IEEE Transactions on Power Systems 20 (2), 587–595. Dupacova, J., Growe-Kuska, N., Romisch, W., 2003. Scenario reduction in stochastic programming: An approach using probability metrics. Mathematical Programming 95 (3), 493–511. EirGrid, 2009. Generation Adequacy Report 2010 - 2016, [Online] Available: http://www.eirgrid.com. EirGrid, SONI, 2010a. All Island TSO Facilitation of Renewbles Studies, [Online] Available: http://www.eirgrid.com/renewables/facilitationofrenewables/. EirGrid, SONI, 2010b. Solver Choice in the SEM: A Comparative Study of Lagrangian Relaxation vs. Mixed Integer Programming, [Online] Available: http://www.sem-o.com. Energy-Tech, 2004. Cycling of http://www.energy-tech.com. Combined-Cycle Plants, [Online] Available: References 130 EPRI, 2001a. Correlating cycle duty with cost at fossil fuel power plants. EPRI, Palo Alto, CA. 1004010. EPRI, 2001b. Damage to power plants due to cycling. EPRI, Palo Alto, CA. 1001507. EPRI, 2002. Determining the cost of cycling and varied load operations: Methodology. EPRI, Palo Alto, CA. 1004412. Eskom, 2007. Eskom Holdings Ltd., Ankerlig power station conversion and transmission integration project, [Online] Available: http://www.eskom.co.za/. EU, 2008. European Union, Climate change: Commission welcomes final adoption of Europe’s climate and energy package, Press Release, [Online] Available: http://europa.eu/rapid/pressReleasesAction.do?reference=IP/08/1998. EWEA, 2011a. European Wind Energy Association, Large Scale Integration of Wind Energy in the European Power Supply: Analysis, Issues and Recommendations, [Online] Available: Availablehttp://www.ewea.org/index.php?id=178. EWEA, 2011b. European Wind Energy Association, Wind Energy and the Grid, [Online] Available: http://www.ewea.org/index.php?id=196. EWEA, 2011c. European Wind Energy Association, Wind in power, 2010 European statistics, [Online] Available: http://ewea.org/index.php?id=1665. Feng, C., Wang, X., 2010. A competitive mechanism of unit maintenance scheduling in a deregulated environment. IEEE Transactions on Power Systems 25 (1), 351–359. Flynn, M., Walsh, M., O’Malley, M., 2000. Efficient use of generator resources in emerging electricity markets. IEEE Transactions on Power Systems 15 (1), 241–249. French, D. N., 1993. Metallurgical failures in fossil fired boilers. John Wiley & Sons Inc. GE, 2005. GE Energy and Consulting, The effects of integrating wind power on transmission system planning, reliability, and operations, prepared for New York State Energy Research and Development Authority, [Online] Available: http://www.nyserda.org/publications. GE, 2010. GE Energy Applications & Systems Engineering and EnerNex Corporation and AWS Truepower, New England Wind Integration Study, prepared for ISO New England, [Online] Available: http://www.uwig.org/CRA SPP WITF Wind Integration Study Final Report.pdf. GE, 2011. General Electric, FlexEfficiency Power Plant Technology, [Online] Available: http://www.ge-flexibility.com/index.jsp. Göransson, L., 2008. Wind power in thermal power systems - large-scale integration. Licentiate thesis, Dept. of Energy and Environment, Chalmers University of Technology, Goteburg, Sweeden. References 131 Göransson, L., Johnsson, F., 2009. Dispatch modeling of a regional power generation system-integrating wind power. Renewable Energy 34 (4), 1040–1049. Göransson, L., Karlsson, S., Johnsson, F., 2010. Integration of plug-in hybrid electric vehicles in a regional wind-thermal power system. Energy Policy 38 (10), 5482–5492. Hadley, S., Tsvetkova, A., 2009. Potential impacts of plug-in hybrid electric vehicles on regional power generation. The Electricity Journal 22 (10), 56–68. Hamidi, V., Robinson, F., 2008. Responsive demand in networks with high penetration of wind power. In: Proc. of IEEE/PES Transmission and Distribution Conference and Exposition. Hatch, 2008. Nova Scotia Wind Integration Study prepared for Nova Scotia Department of Energy, [Online] Available: http://www.gov.ns.ca. Holttinen, H., 2005. Impact of hourly wind power variations on the system operation in the Nordic countries. Wind Energy 8 (2), 197–218. Holttinen, H., Milligan, M., Kirby, B., Acker, T., Neimane, V., Molinski, T., 2008. Using standard deviation as a measure of increased operational reserve requirement for wind power. Wind Engineering 32 (4), 355–377. Holttinen, H., Pedersen, J., 2003. The effect of large-scale wind power on a thermal system operation. In: Proc. of 4th International Workshop on Large-scale Integration of Wind Power for Offshore Wind Farms. IEA, 2008. International Energy Agency, Empowering variable renewables, options for flexible electricity systems, [Online] Available: http://www.iea.org. IEA, 2010. International Energy Agency, IEA Wind Energy, Annual Report 2009, [Online] Available: http://www.ieawind.org/AnnualReports PDF/2009/2009AR 92210.pdf. Kazarlis, S., Bakirtzis, A., Petridis, V., 1996. A genetic algorithm solution to the unit commitment problem. IEEE Transactions on Power Systems 11 (1), 83–92. Keane, A., Tuohy, A., Meibom, P., Denny, E., Flynn, D., Mullane, A., O’Malley, M., 2011. Demand side resource operation on the Irish power system with high wind power penetration. Energy Policy 39 (5), 2925 – 2934. Kehlhofer, R., Rukes, B., Hannemann, F., Stirnimann, F., 2009. Combined-cycle gas & steam turbine power plants. Pennwell Books. KEMA, 2005. A Scoping Study: Demand Side Measures for Small Business and Residential Customers on Ireland’s Electrical System prepared for Sustainable Energy Ireland, [Online] Available: http://www.seai.ie. King, J., 1996. Recent experience in condition assessments of boiler header components and supports. In: Proc. of ASME Pressure Vessels and Piping Conference. References 132 Kirby, B., Milligan, M., 2008. Facilitating wind development: The importance of electric industry structure. The Electricity Journal 21 (3), 40–54. Kitto Jr, J., Bryk, S., Piepho, J., 1996. Upgrades and enhancements for competitive coal-fired boiler systems. In: Proc. of the 1996 International Joint Power Generation Conference. Kiviluoma, J., Meibom, P., 2009. Coping with wind power variability: How plug-in electric vehicles could help. In: Proc. of the 8th International Workshop on LargeScale Integration of Wind Power into Power Systems as well as on Transmission Networks for Offshore Wind Farms. pp. 336–340. Kiviluoma, J., Meibom, P., 2011. Methodology for modelling plug-in electric vehicles in the power system and cost estimates for a system with either smart or dumb electric vehicles. Energy 36 (3), 1758–1767. Lannoye, E., Milligan, M., Adams, J., Tuohy, A., Chandler, H., Flynn, D., O’Malley, M., 2010. Integration of variable generation: Capacity value and evaluation of flexibility. In: Proc. of IEEE Power and Energy Society General Meeting. Lefton, S., 2004. Profitable operation requires knowing how much it costs to cycle your unit. Combined Cycle Journal, [Online] Available: http://www.combinedcyclejournal.com/. Lefton, S., 2011. Power plant asset management Presented at UWIG Spring Workshop, Kansas City, [Online] Available: http://www.uwig.org/kcworkshop/Lefton-KCWork.pdf. Lefton, S., Besuner, P., 2006. The cost of cycling coal fired power plants. Coal Power Magazine, pp. 16–20. Lefton, S., Besuner, P., Agan, D., 2006. The real cost of on/off cycling. Modern power systems, [Online] Available: http://www.modernpowersystems.com. Lefton, S., Besuner, P., Grimsrud, G., 1995. Managing utility power plant assets to economically optimize power plant cycling costs, life, and reliability. In: Proc. of 4th IEEE Conference on Control Applications. pp. 195–208. Lefton, S., Besuner, P., Grimsrud, G., 1997. Cycling fossil fired units proves costly business. Electric Light and Power 75 (7). Lefton, S., Besuner, P., Grimsrud, P., Bissel, A., Norman, G., 1998. Optimizing power plant cycling operations while reducing generating plant damage and costs at the Irish Electricity Supply Board, Aptech Engineering Service Technical Report (TP123), [Online] Available: http://forgoodpower.com/technical papers.html. Lu, B., Shahidehpour, M., 2004. Short-term scheduling of combined cycle units. IEEE Transactions on Power Systems 19 (3), 1616–1625. Malik, A., 2001. Modelling and economic analysis of DSM programs in generation planning. International Journal of Electrical Power & Energy Systems 23 (5), 413– 419. References 133 Meibom, P., 2006. WILMAR - Wind Power Integration in Liberalised Electricity Markets, [Online] Available: http://www.wilmar.risoe.dk/Results.htm. Meibom, P., Barth, R., Brand, H., O’Malley, M., 2011. Stochastic optimization model to study the operational impacts of high wind penetrations in ireland. IEEE Transactions on Power Systems (available online). Meibom, P., Weber, C., Barth, R., Brand, H., 2009. Operational costs induced by fluctuating wind power production in germany and scandinavia. IET Renewable Power Generation 3 (1), 75–83. Milligan, M., Kirby, B., Beuning, S., 2010. Combining Balancing Areas’ Variability: Impacts on Wind Integration in the Western Interconnection. National Renewable Energy Laboratory. MMU, 2010. Market Monitoring Unit, Power Plant Cyling in SEM, [Online] Available: http://www.allislandproject.org/en/mmu decision documents.aspx. Möhrlen, C., Jørgensen, J., Pinson, P., Madsen, H., Runge Kristoffersen, J., 2007. High Resolution Ensemble for Horns Rev: A project overview. In: Proc. European offshore wind energy conference. Monteiro, C., Bessa, R., Miranda, V., Botterud, A., Wang, J., Conzelmann, G., 2009. Wind power forecasting: State-of-the-art 2009 Argonne National Laboratory (ANL), [Online] Available: http://www.dis.anl.gov/pubs/65613.pdf. Moore, W., 2006. Include generators and exciters in your outage inspections. Power, [Online] Available: http://www.powermag.com. Mukerji, R., Merrill, H., Erickson, B., Parker, J., Friedman, R., 1991. Power plant maintenance scheduling: optimizing economics and reliability. IEEE Transactions on Power Systems 6 (2), 476–483. Narula, R., Massy, M., Singh, J., 2002. Design Consideration for Combined Cycle Plants for the Deregulated Market - An EPC Contractors Perspective. Proceedings of International Gas Turbine Institute ASME TURBO EXPO. Norgaard, P., Holttinen, H., 2004. A multi-turbine power curve approach. In: Nordic Wind Power Conference. NREL, 2010. National Renewable Energy Laboratory, Western wind and solar integration study, [Online] Available: http://www.nrel.gov/wind/systemsintegration/wwsis.html. NREL, 2011. National Renewable Energy Laboratory, The Role of Large Balancing Areas in Integrating Solar Generation, [Online] Available: http://www.nrel.gov/docs/fy11osti/50059.pdf. NYISO, 2010. Growing Wind - Final Report of the NYISO Wind Integration Study, [Online] Available: http://www.nyiso.com. References 134 OSIsoft, 2007. Cutting the Cost of Flexible Operation in a Competitive Power Market, [Online] Available: http://www.osisoft.com/. Oswald, J., Raine, M., Ashraf-Ball, H., 2008. Will British weather provide reliable electricity? Energy Policy 36 (8), 3212–3225. Padhy, N., 2004. Unit commitment - a bibliographical survey. IEEE Transactions on Power Systems 19 (2), 1196–1204. Probert, T., 2011. Fast starts and flexibility: Let the gas turbine battle commence. Power Engineering International, [Online] Available: http: // www. powerengineeringint. com/ 19 (6). Risø National Laboratory, 1989. European wind resources at 50 metres a.g.l., [Online] Available: http://www.windatlas.dk/Europe/landmap.html. Salam, S., 2007. Unit commitment solution methods. In: Proc. of World Academy of Science, Engineering and Technology. Vol. 26. pp. 320–325. SEAI, 2010. Sustainable Energy Authority Ireland, History of Wind Energy, [Online] Available: http://www.seai.ie/Renewables/Wind Energy/History of Wind Energy/. Sen, S., Kothari, D., 1998. Optimal thermal generating unit commitment: a review. International Journal of Electrical Power & Energy Systems 20 (7), 443–451. Shahidehpour, M., Marwali, M., 2000. Maintenance scheduling in restructured power systems. Springer. Shibli, A., Starr, F., 2007. Some aspects of plant and research experience in the use of new high strength martensitic steel p91. International Journal of Pressure Vessels and Piping 84 (1-2), 114–122. Siebert, N., 2008. Development of methods for regional wind power forecasting. Ph.D. thesis, Mines ParisTech, Paris, France. Siemens, 2008a. Low Load Operational Flexibility for Siemens G-class Gas Turbines. In: Proc. of Power-Gen International. Siemens, 2008b. Operational flexibility enhancements of combined-cycle power plants. In: Proc. of Power-Gen Asia. Söder, L., 2004. Simulation of wind speed forecast errors for operation planning of multiarea power systems. In: IEEE International Conference on Probabilistic Methods Applied to Power Systems. pp. 723–728. Starr, F., 2003. Background to the design of HRSG systems and implications for CCGT plant cycling. Operation Maintenance and Materials Issues 2 (1). Strbac, G., Shakoor, A., Black, M., Pudjianto, D., Bopp, T., 2007. Impact of wind generation on the operation and development of the UK electricity systems. Electric Power Systems Research 77 (9), 1214–1227. References 135 Streiffert, D., Philbrick, R., Ott, A., 2005. A mixed integer programming solution for market clearing and reliability analysis. In: Proc. of IEEE Power Engineering Society General Meeting. pp. 2724–2731. Troy, N., Denny, E., O’Malley, M., 2010. Base-load cycling on a system with significant wind penetration. IEEE Transactions on Power Systems 25 (2), 1088–1097. Tuohy, A., Meibom, P., Denny, E., O’Malley, M., 2009. Unit commitment for systems with significant wind penetration. IEEE Transactions on Power Systems 24 (2), 592–601. Tuohy, A., O’Malley, M., 2009. Impact of pumped storage on power systems with increasing wind penetration. In: Proceedings of 2009 IEEE PES General Meeting. Calgary, Alberta, Canada. Ummels, B., Gibescu, M., Pelgrum, E., Kling, W., Brand, A., 2007. Impacts of wind power on thermal generation unit commitment and dispatch. IEEE Transactions on Energy Conversion 22 (1), 44–51. Van Hulle, F., Gardner, P., 2008. Wind Energy - The Facts, Part 2 Grid Integration, [Online]. Available: http://www.wind-energy-the-facts.org/. Wambeke, S., 2006. Risks to HRSGs in low-load operation. Combined Cycle Journal Second Quarter, [Online] Available: http://www.combinedcyclejournal.com/. Watson, W., 1996. The success of the combined cycle gas turbine. In: Proc. of the IEEE Conference on Opportunities and Advances in International Electric Power Generation. pp. 87–92. Xcel Energy, 2010. Integrating Wind Cost of Cycling Analysis for Harrington Station Unit 3 [Online] Available: http://www.blankslatecommunications.com/Images/Aptech-HarringtonStation.pdf. Appendix A. Probability distribution of net load ramps Figure 8.2: Probability distribution of hourly net load ramps on the 7.55 GW peak system 136 Appendix A. Probability distribution of net load ramps 137 Figure 8.3: Probability distribution of hourly net load ramps on the 9.6 GW peak system Appendix B. Cycling data for CCGT and coal units Figure 8.4: Start-ups and capacity factor for a typical low-merit CCGT unit on the 7.55 and 9.6 GW peak demand systems, with increasing wind penetration 138 Appendix B. Cycling data for CCGT and coal units 139 Table 8.2: Start-up data for CCGT and coal units on the 7.55 GW peak demand system Statistic CCGT Coal Wind energy penetration 15% 29% 43% 15% 29% 43% Max. value 161 186 197 65 54 43 Min. value 18 41 70 8 9 6 Average value 72.4 90.6 115.4 28.4 26.4 20.6 Std. Deviation 63.8 63.6 52.3 26.4 22.6 15.4 Table 8.3: Capacity factor data for CCGT and coal units on the 7.55 GW peak demand system Statistic CCGT Coal Wind energy penetration 15% 29% 43% 15% 29% 43% Max. value 0.81 0.75 0.64 0.77 0.71 0.69 Min. value 0.73 0.59 0.44 0.72 0.67 0.61 Average value 0.79 0.71 0.59 0.75 0.70 0.66 Std. Deviation 0.034 0.066 0.086 0.024 0.175 0.029 Table 8.4: Start-up data for CCGT and coal units on the 9.6 GW peak demand system Statistic CCGT Coal Wind energy penetration 11% 23% 34% 11% 23% 34% Max. value 116 170 198 56 81 67 Min. value 7 23 44 8 9 5 Average value 32.4 63.6 93 27.2 36.4 32.4 Std. Deviation 47.1 63.4 65.3 25.4 36.3 30.9 Appendix B. Cycling data for CCGT and coal units 140 Table 8.5: Capacity factor data for CCGT and coal units on the 9.6 GW peak demand system Statistic CCGT Coal Wind energy penetration 11% 23% 34% 11% 23% 34% Max. value 0.90 0.85 0.77 0.83 0.79 0.76 Min. value 0.85 0.76 0.65 0.77 0.75 0.72 Average value 0.87 0.82 0.74 0.80 0.76 0.74 Std. Deviation 0.02 0.03 0.05 0.02 0.02 0.02 Appendix C. Base-load cycling with/without storage/interconnection Figure 8.5: Number of hours online for an average CCGT and coal unit with/without storage and an increasing wind penetration on the 9.6 GW peak demand system 141 Appendix C. Base-load cycling with/without interconnection 142 Figure 8.6: Number of start-ups for an average CCGT and coal unit with/without storage and an increasing wind penetration on the 9.6 GW peak demand system Figure 8.7: Number of hours online for an average CCGT and coal unit with/without interconnection and an increasing wind penetration on the 9.6 GW peak demand system Appendix D. Fuel Cost Curves Figure 8.8: Fuel cost curves for test units 143 Appendix D. Fuel Cost Curves Figure 8.9: Fuel cost curves for test units 144 Appendix E. Publications 1. Troy, N., Denny, E. and O’Malley, M. “Base-load cycling on a system with significant wind penetration”, IEEE Transactions on Power Systems, vol. 25, issue 2, pp. 1088 - 1097, 2010. 2. Troy, N., Flynn, D. and O’Malley, M. “Multi-mode Operation of Combined-Cycle Gas Turbines with Increasing Wind Penetration”, IEEE Transactions on Power Systems, In Press 3. Troy, N., Flynn, D., Milligan M. and O’Malley, M. “Unit Commitment with Dynamic Cycling Costs”, IEEE Transactions on Power Systems, in review. 145 1088 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 25, NO. 2, MAY 2010 Base-Load Cycling on a System With Significant Wind Penetration Niamh Troy, Graduate Student Member, IEEE, Eleanor Denny, Member, IEEE, and Mark O’Malley, Fellow, IEEE Abstract—Certain developments in the electricity sector may result in suboptimal operation of base-load generating units in countries worldwide. Despite the fact they were not designed to operate in a flexible manner, increasing penetration of variable power sources coupled with the deregulation of the electricity sector could lead to these base-load units being shut down or operated at partload levels more often. This cycling operation would have onerous effects on the components of these units and potentially lead to increased outages and significant costs. This paper shows the serious impact increasing levels of wind power will have on the operation of base-load units. Those base-load units which are not large contributors of primary reserve to the system and have relatively shorter start-up times were found to be the most impacted as wind penetration increases. A sensitivity analysis shows the presence of storage or interconnection on a power system actually exacerbates base-load cycling until very high levels of wind power are reached. Finally, it is shown that if the total cycling costs of the individual base-load units are taken into consideration in the scheduling model, subsequent cycling operation can be reduced. Index Terms—Costs, interconnected power systems, power system modeling, pumped storage power generation, thermal power generation, wind power generation. I. INTRODUCTION S higher penetrations of wind power are achieved, system operation becomes increasingly complex, as variations in the net load (load minus wind) curve increase [1]. Wind is a variable energy source and fluctuations in output must be offset to maintain the supply/demand balance, thus resulting in a greater demand for operational flexibility from the thermal units on the system [2]. These units must also carry additional reserves to maintain system reliability should an unexpected drop in wind occur, as the power output from wind farms is also relatively difficult to predict [3]. However, even when state-of-the-art methods of forecasting are employed, the next day hourly predicted wind output can vary by 10%–15% of A Manuscript received May 25, 2009; revised September 24, 2009. First published January 08, 2010; current version published April 21, 2010. This work was conducted in the Electricity Research Centre, University College Dublin, Ireland, which is supported by Airtricity, Bord Gais, Bord na Mona, Cylon Controls, the Commission for Energy Regulation, Eirgrid, Electricity Supply Board (ESB) International, ESB Networks, ESB Power Generation, Siemens, SWS Group, and Viridian. This work was supported by a Charles Parsons Energy Research Award from the Department of Communications, Energy and Natural Resources administered by Science Foundation Ireland. Paper no. TPWRS-003772009. N. Troy and M. O’Malley are with the School of Electrical, Electronic, and Mechanical Engineering, University College Dublin, Dublin, Ireland (e-mail: [email protected]; [email protected]). E. Denny is with the Department of Economics, Trinity College Dublin, Dublin, Ireland (e-mail: [email protected]). Digital Object Identifier 10.1109/TPWRS.2009.2037326 the total wind capacity as reported in [4], which can result in thermal units being over- and under-committed [2]. Furthermore, in certain systems wind is allowed to self-dispatch, so forecast output is not included in the day-ahead schedule. This can lead to increased transmission constraints which will further intensify plant cycling and has been shown to displace energy from combined cycle gas turbines (CCGTs) in particular [5]. The culmination of adding more variability and unpredictability to a power system is that thermal units will undergo increased start-ups, ramping and periods of operation at low load levels collectively termed “cycling”[6]–[9]. In addition to wind, the competitive markets in which these units operate are also a significant driver of plant cycling; increased levels of competition brought about by widespread deregulation results in all types of generators being forced into more market-orientated, flexible operation to increase profits [10]. The severity of plant cycling, will be dependent on the generation mix and the physical characteristics of the power system. It is widely reported that the availability of interconnection and storage can assist the integration of wind on a power system [11], [12]. Interconnection can allow imbalances from predicted wind power output to be compensated via imports/exports whereas some form of energy storage can enable excess wind to be moderated in time to correlate with demand. This should relieve cycling duty on thermal units as the onus on them to balance fluctuations is relieved. Although all conventional units will be impacted to some degree by wind integration, it is cycling of base-load units that is particularly concerning for system operators and plant owners alike. As these units are designed with minimal operational flexibility, cycling these units will result in accelerated deterioration of the units’ components through various degeneration mechanisms such as fatigue, erosion, corrosion, etc, leading to more frequent forced outages and loss of income. The start/stop operation and varying load levels result in thermal transients being set up in thick-walled components placing them under stress and causing them to crack. The interruptions to operation caused by cycling disrupts the plant chemistry and results in higher amounts of oxygen and other ionic species being present, leading to corrosion and fouling issues. A multitude of other cycling related issues have been documented in the literature [13]–[19]. Excessive cycling of base-load units could potentially leave them permanently out of operation prior to their expected lifetimes. Hence cycling of base-load units will impose additional costs on the unit, the most apparent being increased operations and maintenance (O&M) and capital costs resulting from deterioration of the components. However, fuel costs will also increase with cycling operation as the unit will be starting up more frequently, and also because the overall efficiency of the unit will 0885-8950/$26.00 © 2010 IEEE TROY et al.: BASE-LOAD CYCLING ON A SYSTEM WITH SIGNIFICANT WIND PENETRATION deteriorate. Environmental penalties will arise as a result of increased fuel usage, while income losses arise as the unit will undergo longer and more frequent outages [17], [19], [20]. Quantifying these costs is particularly difficult given the vast array of components affected. Also, cycling related damage may not be immediately apparent. Studies have suggested it can take up to seven years for an increase in the failure rate to become apparent after switching from base-load to cycling [21]. The uncertainty surrounding cycling costs can lead to these costs being under-valued by generators, which in turn can lead to increased cycling. This paper examines the effect that increasing penetration of wind power will have on the operation of base-load units. The role that interconnection and storage play in alleviating or aggravating the cycling of base-load units is investigated across different wind penetration scenarios. Finally, the effect of increasing start-up costs (to represent increasing depreciation) on the operation of base-load units is examined. Section II details the methodology used in the study. Section III reports the results and discusses the impact of modeling assumptions on these results. Section IV provides some discussion surrounding how wind and plant cycling is treated in electricity markets. Section V concludes the paper. II. METHODOLOGY A. Modeling Tool Simulations were carried out using a scheduling model called the Wilmar Planning Tool, which is described extensively in [22] and [23]. The Wilmar Planning Tool was originally developed to model the Nordic electricity system and was later adapted to the Irish system as part of the All Island Grid Study [23]. It is currently employed in the European Wind Integration Study [24]. The Wilmar Planning Tool was the tool of choice for this study as it combined the benefits of mixed integer optimization with stochastic modeling. The main functionality of the Wilmar Planning Tool is embedded in the Scenario Tree Tool and the Scheduling Model. The Scenario Tree Tool generates scenario trees containing three inputs to the scheduling model: wind, load and demand for replacement reserve. Realistic possible wind forecast errors are generated using an auto regressive moving average (ARMA) approach which considers the historical statistical behavior of wind at individual sites. Historical wind speed series taken from the various sites are then added to the wind speed forecast error scenarios to generate wind speed forecast scenarios. These are then transformed to wind power forecast scenarios. Load forecast scenarios are generated in a similar manner. A multi dimensional ARMA model, as in [25], is used to simulate the wind correlation between sites. A scenario reduction technique similar to that in [26] is employed to reduce the large number of possible scenarios generated. In the modeling tool reserve is categorized as primary or replacement. Primary reserve, which is needed in short time scales (less than five minutes), is supplied only by synchronized units. The system should have enough primary reserve to cover an outage of the largest online unit occurring at the same time as a fast decrease in wind power production. Positive primary reserve is provided by increased production from online units or pumped storage, whilst negative primary reserve is provided by 1089 decreased production from online units or by pumped storage when in pumping mode. The demand for replacement reserve, which is reserve with an activation time greater than 5 min, is determined by the total forecast error which is defined according to the hourly distribution of wind power and load forecast errors and the possibilities of forced outages. A forced outage time series for each unit is also generated by the scenario tree tool using a semi-Markov process based on given data of forced outage rates, mean time to repair and scheduled outages is produced. Any unit that is offline and can come online in under one hour can provide replacement reserve. The Scheduling Model minimizes the expected cost of the system over the optimization period covering all scenarios generated by the scenario tree tool and subject to the generating units’ operational constraints, such as minimum down times (the minimum time a unit must remain offline following shut-down), synchronization times (time taken to come online), minimum operating times (minimum time a unit must spend online once synchronized) and ramp rates. In order to maintain adequate system inertia and dynamic reactive support at times of high wind, a minimum number of large base-load units must be online at all times. Details of the objective function which contains fuel, carbon and start-up costs are given in Appendix A and further details are included in [22]. The Generic Algebraic Modeling System (GAMS) was used to solve the unit commitment problem using the mixed integer feature of the Cplex solver. For all the simulations in this study the model was run with a duality gap of 0.01%. Rolling planning is used to re-optimize the system as new wind and load information becomes available. Starting at noon the system is scheduled over 36 hours until the end of the next day. The model steps forward with a three hour time step with new forecasts used in each step. In each planning period a three stage stochastic optimization model is solved having a deterministic first stage, a stochastic second stage with three scenarios covering three hours and a stochastic third stage with six scenarios covering a variable number of hours according to the planning period in question. The state of the units at the start of any time step must be the same as the state of the units at the end of the previous time step. B. Test System The 2020 Irish system was chosen as a test case for this study because its unique features make it suitable for investigating base-load cycling. It is a small island system, with limited interconnection to Great Britain, a large portion of base-load plant and significant wind penetration. Thus, potential issues with cycling of base-load units may arise on this system at a lower wind penetration. Various portfolios were developed in the Wilmar Planning Tool for the All Island Grid Study [27] to investigate the effects of different penetrations of renewables on the Irish system for the year 2020. Portfolios 1, 2, and 5 from [27] were used in this study and are outlined in Table I as the “moderate wind”, “high wind”, and “very high wind” cases. A “no wind” case has also been added. As seen in Table I, the test system is a thermal system, with a small portion of inflexible hydro capacity and the base-load is composed of coal and combined cycle gas turbine (CCGT) generation. The three wind cases examined have 2000 MW, 4000 MW, and 6000 MW wind installed on the system, 1090 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 25, NO. 2, MAY 2010 TABLE I INSTALLED CAPACITY (MW) BY FUEL TYPE TABLE III CHARACTERISTICS OF A TYPICAL CCGT AND COAL UNIT ON THE TEST SYSTEM TABLE II FUEL PRICES (C/GJ) BY FUEL TYPE power to be examined. The model was run stochastically, for one year, for the “no wind” case and each of the three wind cases to examine the effect that increasing wind power penetration will have on the operation of base-load units, as these are the units with the most limited operational flexibility and as such, will suffer the greatest deterioration from increased cycling. To conduct a sensitivity analysis investigating the role that storage and interconnection play in altering the impact of increasing wind penetration on base-load operation, the model was run stochastically, for one year, for the “no wind” case and each of the three wind cases, first, without any pumped storage on the system and second, without any interconnection on the system. In order to fairly compare systems without storage/interconnection to the systems with storage/interconnection, the systems must maintain the same reliability. Thus it was necessary to replace the pumped storage units and interconnector with conventional plant. The 292 MW of pumped storage was replaced with three 97.5-MW open cycle gas turbine (OCGT) units and the 1000 MW of interconnection was replaced with nine 100-MW OCGT units (as 100 MW is always used as primary reserve, the maximum import capacity is 900 MW). The characteristics of these units were set such that they could deliver the same capacity over the same time period as the interconnection/storage units they replaced. Thus, in terms of flexibility the systems with storage/interconnection were no more or less flexible than the systems without storage/interconnection. The OCGT units which replaced the storage units were capable of delivering the same amount to primary reserve (132 MW in total). The OCGT units that replaced the interconnection did not contribute to primary reserve but instead 100 MW was subtracted from the demand for primary reserve in each hour. This is the assumption used when the interconnector is in place. The cost of running these units is generally greater than the cost of imports or production from a storage unit thus production from storage/interconnection is not shifted directly to these units. This is advantageous in this type of study, as the operation of other units on the system without storage/interconnection can be observed whilst the system adequacy is not undermined by reduced capacity, thus facilitating sensitivity analysis. For example, had a CCGT unit been used to replace the interconnector, it would likely provide the energy that had been previously delivered by the interconnector but this would not allow examination of how the existing units on the system would be affected which supply 11%, 23%, and 34% of the total energy demand and represent 19%, 32%, and 42% of the total installed capacity on the system, respectively. The 2020 winter peak forecast is 9.6 GW and the summer night valley is 3.5 GW. Losses on the transmission system are included in the load. The test system includes four 73 MW pumped storage units with a round-trip efficiency of 75% and a maximum pumping capacity of 70 MW each and two 83 MW CHP units with “must-run” status as they provide heat for industrial purposes. The 2020 fuel prices used are shown in Table II and a carbon price of 30/ton was assumed. The gas prices shown in Table II are the averages over the year and the other fuel prices remain constant throughout. As this study is primarily concerned with the operation of base-load units, the characteristics of those units are shown in Table III. A simplified model of the British power system is included in which units are aggregated by fuel type. Wind and load is assumed to be perfectly forecast on the British system. The model includes 1000 MW of HVDC interconnection between Ireland and Great Britain and it is scheduled on an intra-day basis, i.e., it is rescheduled in every rolling planning period. Flows on the interconnector to Britain are optimized such that the total costs of both systems are minimized. A maximum of 873 MW can be imported as 100 MW is used as primary reserve at all times and there are 3% losses on the remainder. C. Scenarios Examined Different wind cases, as described in the previous section, were used in this study to allow various penetrations of wind TROY et al.: BASE-LOAD CYCLING ON A SYSTEM WITH SIGNIFICANT WIND PENETRATION 1091 TABLE IV FLUCTUATIONS IN WIND POWER OUTPUT WITH INCREASING WIND TABLE V NUMBER OF THERMAL UNITS ONLINE WITH INCREASING WIND PENETRATION (AVERAGED AT EACH HOUR SHOWN OVER A TWO-WEEK PERIOD IN APRIL) Fig. 1. Annual number of start-ups and capacity factor for an average CCGT and coal unit with increasing wind penetration. in the absence of interconnection. The results from the systems without storage and interconnection were compared to the base case (i.e., with storage and interconnection). The final part of the study examined the effect that increasing the start-up costs of the base-load units will have on their operation. It was assumed the cost of starting these units would increase, as they experienced more wear and tear, from increased cycling. Given the uncertainty surrounding what this increase in costs might be [17], [19], the operation of the base-load units was examined over a range of start-up costs. The start-up cost of each of the base-load units on the system was increased by a multiple of its original value and the model was run for one year. The process was repeated with the start-up costs incremented by a greater multiple of the original amount each time. This was carried out for the “moderate” (19% installed wind capacity) and “very high” (42% installed wind capacity) wind cases. To examine the results, the base-load units were categorized as coal or CCGT. As the total capacity of the coal and CCGT units varied across the portfolios, the results for the individual units in each group were normalized by their capacity to obtain the result per MW for each unit. The average result per MW was then obtained and this was multiplied by the capacity of a typical coal or CCGT unit (chosen to be 260 MW and 400 MW, respectively) to give the result for a typical coal or CCGT unit as shown as follows: (1) where is the result for the th unit, unit and is the number of units is the capacity of the th III. RESULTS A. Effect of Increasing Wind Penetration on the Operation of Base-Load Units As the wind penetration on a power system is increased, large fluctuations in the wind power output will become more frequent, as seen in Table IV. In addition, generation from thermal units is increasingly displaced, thus the number of units online will decrease. This is shown in Table V. Therefore the onus on thermal units to compensate fluctuations in the wind power output becomes more demanding with increasing wind penetration. Fig. 1 shows the annual number of start-ups and capacity factor for an average sized CCGT and coal unit of 400 MW and 260 MW, respectively, as wind penetration increases. The capacity factor is the ratio of actual generation to maximum possible generation in a given time period. As the wind penetration grows and the variability and unpredictability involved in system operation is increased, the operation of a base-load CCGT unit is severely impacted. Moving from 0% to 42% installed wind capacity the annual start-ups for a typical CCGT unit rise from 22 to 98, an increase of 340%. This increase in CCGT start-ups corresponds to a plummeting capacity factor as seen in Fig. 1. Thus increasing levels of wind effectively displaces CCGT units into mid-merit operation. Similar to a CCGT unit, start-ups for a coal unit increase with wind penetration up to 32% installed wind capacity, albeit not as drastically as a CCGT unit. However, at penetrations greater than 32% installed wind capacity, this correlation diverges and the start-ups for a coal unit begin to decrease, as seen in Fig. 1. As wind penetration grows, demand for primary reserve will grow. Due to high part-load efficiencies, as indicated by the minimum load heat rates seen in Table III, coal units are the main thermal providers of primary reserve on this system. In addition to this they have low minimum outputs so at times of high wind more coal units can remain online to meet the minimum units online constraint thus minimizing wind curtailment. Coal units are also highly inflexible; once taken offline it is a minimum of ten hours (minimum down time plus synchronization time as seen in Table III) before the unit can be online and generating again. The combination of these characteristics, increases the need for these units to be kept online to provide primary reserve to the system as high levels of wind are reached. Thus, despite the fact that the cost of starting a CCGT unit on this system is greater than the cost of starting a coal unit as seen in Table III, the CCGT unit has the greatest increase in start-stop cycling with increasing wind as it does not supply a large amount of reserve to the system, has a large minimum output and can come online in a shorter time compared to a coal unit. As CCGT units are taken offline more frequently with increasing wind penetration, the requirement on coal units to provide reserve to the system is driven even higher. Thus, although the capacity factor of a coal unit decreases as wind increases, 1092 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 25, NO. 2, MAY 2010 Fig. 2. Utilization factor and annual number of hours where severe ramping is performed for an average CCGT and coal unit with increasing wind penetration. Fig. 3. Number of hours online for an average CCGT and coal unit with/ without storage and an increasing wind penetration. the rate of decrease is much less than for a CCGT as seen in Fig. 1. Therefore, as wind penetration exceeds approximately 32% installed capacity a crossover point occurs and the inflexible coal units now become the most base-loaded units on the system whilst the relatively more flexible CCGT are forced into two-shifting, as seen by the capacity factors in Fig. 1. Thus, if capacity factor is indicative of the revenue earned by these units, the units with the most limited operational flexibility are the most rewarded at high levels of wind. This would suggest that some form of incentive may be needed to secure investment in flexible plants (for example OCGTs), which are commonly reported as beneficial to system operation with large amounts of wind [28], [29]. Fig. 2 shows the utilization factor for an average base-load coal and CCGT unit and the number of hours they perform severe ramping as wind penetration increases. The utilization factor is the ratio of actual generation to maximum possible generation during hours of operation in a given period. Severe ramping is defined in this paper as a change in output greater than half the difference between a unit’s maximum and minimum output over one hour. Hours when the unit was staring up or shutting down were not included. Although coal units will avoid heavy start-stop cycling as wind levels grow by being the main thermal providers of primary reserve and highly inflexible, they do experience increased part-load operation. This is indicated by a drop in utilization factor from 0.94 to 0.88 as wind levels increase from 0% to 42% installed wind capacity, as seen in Fig. 2. The utilization factor for a CCGT unit also decreases with increasing levels of wind as seen in Fig. 2, however, it remains high in comparison with a coal unit, indicating the small contribution of reserve it provides to the system and correspondingly the infrequent periods of part-load operation. As seen in Fig. 2, both types of unit experience a dramatic increase in hours where severe ramping is required, as wind penetration exceeds 32% installed capacity. As wind penetration moves from 32% to 42% installed wind capacity a coal unit experiences the greatest increase in severe ramping operation going from 4 to 78 h, compared to an increase from 4 to 32 h for a CCGT unit, as these units are now offline more often. The sharp increase in ramping corresponds to the substantial increase in wind fluctuations seen in Table IV between 32% and 42% installed wind capacity, which must be compensated by a smaller number of online units. Such an increase in part-load operation and ramping can lead to fatigue damage, boiler corrosion, cracking of headers and component depreciation through a variety of damage mechanisms. This is of major concern to plant managers. The results reported are for “average” CCGT and coal units. In order to show how these results correspond to the actual results for the real units modeled, the maximum value, minimum value, average value and standard deviation of the number of start-ups and capacity factor for the modeled CCGT and coal units are given in Appendix B. B. Sensitivity Analysis Section III-A showed the serious impact increasing levels of wind will have on the operation of base-load units. The extent of this impact will be determined by the generation portfolio and the characteristics of the system. This section provides a sensitivity analysis of the effect of the portfolio on the results, by examining the operation of the base-load units with increasing levels of wind power when storage and interconnection are removed from the system. 1) No Storage Case: Fig. 3 shows the number of hours online for an average CCGT and coal unit on systems with and without pumped storage and an increasing wind penetration. On the system without pumped storage the base-load units spend more hours online compared to the system with storage, until a very high wind penetration (greater than 32% installed capacity for a CCGT and greater than 42% installed capacity for a coal unit) is reached. The presence of pumped storage on a system will displace the primary reserve contribution required from conventional units and thus reduce the need for them to be online. Correspondingly, an average base-load unit spends more hours online on the system without pumped storage as there is more requirement on the unit to be online providing primary reserve to the system. As coal units, in this case, are the main thermal provider of primary reserve to the system they are the most affected by the addition of a storage unit, as seen for a typical coal unit in Fig. 3. The difference in hours online for a typical CCGT unit on the system with storage compared to the system without storage is small as they are not large contributors to primary reserve. However, at very high wind penetrations a crossover point occurs when large fluctuations in wind power output occur more frequently, as seen in Table IV, and now the system with pumped TROY et al.: BASE-LOAD CYCLING ON A SYSTEM WITH SIGNIFICANT WIND PENETRATION Fig. 4. Number of start-ups for an average CCGT and coal unit with/without storage and an increasing wind penetration. storage is more equipped to balance these fluctuations. As the demand for reserve is sufficiently large at very high wind penetrations, such that reserve from many thermal units is needed in addition to the reserve from the storage units, storage will no longer be a factor in base-load units going offline. Thus, at very high levels of wind, base-load units now spend more hours online on the system with storage compared to the system without storage. Fig. 4 shows the number of start-ups for an average base-load CCGT and coal unit on a system with and without pumped storage as wind penetration increases. Almost no difference in the number of start-ups for a typical CCGT unit is seen on the systems with and without storage until installed wind reaches greater than 32%. However, the number of start-ups for a typical coal unit is seen to be much greater on the system with storage compared to the system without storage, again indicating that storage will most adversely affect the units that provide the largest portion of primary reserve to the system. Again a crossover point is reached at some very high wind penetration after which start-ups rise rapidly on the system without storage due to large and frequent fluctuations in wind power output. This occurs at 32% installed wind for a CCGT and greater than 42% installed wind capacity for a coal unit. Thus, until very high wind penetrations are reached the existence of a pumped storage unit is shown to actually exacerbate cycling of base-load units. 2) No Interconnection Case: Fig. 5 compares the number of hours spent online by a typical CCGT and coal unit on systems with and without interconnection, as wind is increased. The base-load units are seen to spend significantly more hours online on the system without interconnection compared to the system with interconnection until a very high wind penetration is reached. Due to a large portion of base-load nuclear plant and cheaper gas prices compared with Ireland, the market price for electricity tends to be cheaper in Great Britain. As a consequence Ireland tends to be a net importer of electricity from Great Britain and as such will import electricity before turning on domestic units. Thus interconnection to Great Britain displaces conventional generation on the Irish system, forcing units down the merit order and exacerbating plant cycling. Without the option to import electricity, as in the “no interconnection case”, all demand must be met by domestic units requiring more units to be online generating more often. Thus a typical CCGT and coal unit are 1093 Fig. 5. Number of hours online for an average CCGT and coal unit with/ without interconnection and an increasing wind penetration. Fig. 6. Number of start-ups for an average CCGT and coal unit with/without interconnection and an increasing wind penetration. seen in Figs. 5 and 6 to spend more hours online and have less start-ups on the system without interconnection. However, as seen in Fig. 5 at some wind penetration between 32% and 42% installed wind capacity for a CCGT unit and greater than 42% installed capacity for a coal unit, a crossover point will occur when the units spend more hours online on the system with interconnection. As very high wind penetrations are reached, the electricity price in Ireland undercuts British prices more often making exports economically viable. Thus at very high penetrations of wind, the system with interconnection can deal with large fluctuations in the wind power output via imports/exports more favorably and avoid plant shut-downs. Thus interconnection is shown not to benefit the operation of base-load units on a system that is a net importer until wind penetration increases to such point that exports are economically viable. C. Effect of Increasing Start-Up Costs Having shown in Sections III-A and B the severe impact increasing wind penetration will have on the operation of the baseload units, this section now examines how the increasing costs imposed on these units by cycling operation, will subsequently affect their operation. A component of a unit’s start-up cost should be the cost of wear and tear inflicted on the unit during the start-up process [16]. However, given the uncertainty in determining such a cost, this aspect is often neglected, leading to the units being scheduled to start more frequently, yielding more 1094 Fig. 7. Number of base-load start-ups for increasing start-up costs. cycling related damage. This section examines how the operation of the base-load units changes as the start-up costs are incrementally increased to represent the increasing depreciation of the unit. 1) Start-Ups: The number of start-ups for an average CCGT and coal unit is shown in Fig. 7, as start-up costs are increased, with 19% and 42% installed wind capacity, respectively. Increasing the start-up costs of a CCGT unit results in a substantial reduction in start-stop cycling, particularly at the higher wind penetration. This indicates a feedback effect, whereby increased cycling will lead to increased costs, but when these costs are included in the cost function, cycling will subsequently be reduced. With 42% installed wind capacity, increasing the start-up costs by a factor of 6 sees the start-ups for a CCGT drop from 98 to 27, a decrease of 72%. Doubling the start-up costs of a coal unit in the low wind case reduced start-ups by 19, a 68% reduction. No further reduction in coal start-ups was possible as these units were then at their minimum number of annual start-ups (governed by scheduled and forced outages). A greater reduction in cycling is achieved by increasing start-up costs on the system with 42% installed wind capacity compared to the system with 19% installed wind capacity, as this system can export more due to lower electricity prices. Increasing the start-up costs of the base-load units in Ireland by a factor of 6, results in a 29% increase in exports on the system with 42% installed wind capacity as it becomes more economical to allow the base-load units in Ireland to stay online and avoid shut-downs by increasing exports to Britain. 2) Ramping and Part-Load Operation: Fig. 8 shows the number of hours that severe ramping is required by an average CCGT and coal unit, as start-up costs are increased with 19% and 42% installed wind capacity. Fig. 9 shows the utilization factor for an average CCGT and coal unit, with 19% and 42% installed wind capacity as their start-up costs are increased. The trade-off for the reduction in start-stop cycling of base-load units, achieved by increasing the start-up costs, is an increase in ramping activity as seen in Fig. 8 and part-load operation as seen in Fig. 9, which will also leads to plant deterioration although it is reported to be less costly compared with start-ups [30]. By increasing the start-up costs of the base-load units, start-ups are reduced and these units are kept online more, but at the expense of more flexible units which are taken offline. As a result the number of hours when the base-load units are IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 25, NO. 2, MAY 2010 Fig. 8. Number of hours of severe ramping duty for increasing start-up costs. Fig. 9. Utilization factor for increasing start-up costs. the only thermal units online increases with increasing start-up costs. During such hours there will be a considerable ramping requirement on these units to balance fluctuations in the wind power output. As there will be even less thermal units online in the 42% installed wind capacity case compared to the 19% installed capacity case the greatest increase in ramping is observed for the 42% installed wind capacity case as start-up costs are increased, as seen in Fig. 8. Some inconsistencies in the trend can occur because “severe ramping” is defined discretely, as seen for a CCGT with 42% installed wind. As the base-load units are being kept online more often, as their start-up costs are increased, they will experience increased part-load operation as indicated by the reduction in utilization factor in Fig. 9. As start-up costs are increased sufficiently it becomes more economical to run these units at part-load, than to take them offline and forgo expensive start-up costs at a later time. The greater increase in part-load operation occurs on the system with 42% installed wind capacity compared to the system with 19% installed wind capacity, corresponding to the large reduction in start-ups seen at 42% installed wind capacity. The difference in start-ups and ramping for a CCGT and coal unit between 19% installed wind and 42% installed wind is also seen in Figs. 1 and 2 for the original start-up costs and for brevity is not discussed again here. D. Effect of Modeling Assumptions The model used was limited to hourly time resolution. The lack of intra-hourly data may have lead to the severity of the TROY et al.: BASE-LOAD CYCLING ON A SYSTEM WITH SIGNIFICANT WIND PENETRATION cycling being seriously underestimated, for example the severe ramping events. The frequency of severe ramping events found in the study may be underestimated as severe ramps may have occurred over shorter time frames than one hour. Also, such a sizeable ramp occurring over a period shorter than one hour would have a much more damaging effect on the unit. For all simulations, rolling planning with a three hour time step was used. Had the system been re-optimized more regularly, the wind and load forecasts would have been updated more often. However, [22] shows this would have minimal impact on the operation of the base-load units examined here so a three hour time step was deemed adequate. IV. DISCUSSION How electricity markets evolve to manage plant cycling is beyond the scope of this paper, however, this section offers some discussion as to how cycling costs could be represented and areas for future market development with a large wind penetration. In many electricity markets generators submit complex bids for energy in addition to the technical characteristics of the plant. If the current trend for wind development continues, plant cycling, as shown in this paper, will inevitably becoming an increasing concern and generators may subsequently alter their bids or plant characteristics in order to minimize cycling damage. Section III-C examines how by taking the cost of cycling into consideration in a unit’s start-up cost, subsequent cycling can be reduced. Generators in SEM, the Irish electricity market, are directed to include cycling costs in their start-up costs so this approach was taken in this paper. Cycling costs could also be included in no-load or energy costs, or even defined as a new market product such as ramping costs [31]. However, increasing the energy cost will also increase the marginal cost of the unit, which risks changing the position of the unit in the merit order and inducing further cycling. Alternatively cycling costs could be incorporated in a unit’s shut-down costs. The Wilmar Planning Tool used in this study does not model shut-down costs at present. Future work could investigate the effect of incorporating shut-down costs in the scheduling algorithm on a generators dispatch. As cycling costs are difficult to quantify, generators may use the opportunity to exercise market power. For example a generator may increase the start-up costs excessively in order to avoid shut-down, although this strategy may result in them being left offline following a trip or scheduled shut-down because of their excessive start-up cost. Thus some may instead favor setting a maximum number of start-ups a unit can carry out over a period of time, however, this approach would unfairly reward inflexible units and provide no incentive to improve operational flexibility. In some electricity markets generators submit simple bids. This can result in increased start-ups for generators as no explicit consideration of the cost of starting the unit is taken. Incorporating wind in such a market would induce further cycling, indicating that a move to complex bidding could be beneficial. Longer scheduling horizons that take future wind forecasts into consideration may also reduce plant start-ups, however the forecast error increases with the time horizon. Thus enabling a later gate closure in a market with a significant wind penetration, 1095 which would allow the most up-to-date wind forecasts to be employed, could be more effective at reducing unnecessary plant start-ups [32]. V. CONCLUSIONS Increasing wind penetration on a power system will lead to changes in the operation of the thermal units on that system, but most worryingly to the base-load units. The base-load units are impacted differently by increasing levels of wind, depending on their characteristics. CCGT units see rapid increases in startstop cycling and plummeting capacity factor and are essentially displaced into mid-merit operation. On the test system examined coal units are the main thermal providers of primary reserve to the system and as a result see increased part-load operation and ramping. This increase in cycling operation will lead to increased outages and plant depreciation. Certain power system assets are widely reported to assist the integration of wind power. This paper examined if storage and interconnection reduced cycling of base-load units by comparing a system with storage and interconnection to a system without storage and without interconnection, across a range of wind penetrations. It was found that until very high penetrations of wind are reached storage will actually displace the need for base-load units to be online providing reserve to the system. This results in increased cycling of base-load units compared to the system without storage. Similarly, for a system that is a net importer, interconnection will actually displace generation from domestic units, also resulting in increased cycling of base-load units compared to a system without interconnection. At very large penetrations of wind a crossover point exists, where larger and more frequent fluctuations in the wind power output, can be dealt with more effectively on a system with interconnection and storage and thus the system with storage and interconnection becomes the most favorable to the operation of base-load units. Having shown how the operation of the base-load units is dramatically affected by increasing levels of wind power and assuming this would lead to added costs in various guises, the effect that increasing start-up costs for base-load units had on their subsequent operation was examined. This showed that as the cost of starting a base-loaded CCGT unit increased, startstop cycling of the unit was subsequently reduced. However, a reduction in start-ups is seen to be correlated with an increase in part-load operation and ramping. APPENDIX A WILMAR OBJECTIVE FUNCTION The objective function shown in (A1) consists of operating fuel cost, start up fuel cost (if a unit starts in that hour), emissions costs and penalties incurred for not meeting load or reserve targets. If a unit is online at the end of the day, its start-up costs are subtracted from the objective function to ensure that there are still units online at the end of the optimization period. The decision variable is given in the first three lines, showing whether a unit is online or offline. Further detail on the formulation of the unit commitment problem is given in [22]. 1096 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 25, NO. 2, MAY 2010 Indices: TABLE VI VARIATION IN CCGT START-UPS WITH INCREASING WIND F i,I r,R s,S START t,T USEFUEL Fuel. Unit group. Region. Scenario. Units with start-up fuel consumption. Time. Unit using fuel. TABLE VII VARIATION IN COAL START-UPS WITH INCREASING WIND Parameters: EMISSION END k L LOAD PRICE REP SPIN TAX Rate of emission. Endtime of optimization period. Probability of scenario. Infeasibility penalty. Penalty for loss of load. Fuel price. Penalty for not meeting replacement reserve. Penalty for not meeting primary reserve. Emission tax. TABLE VIII VARIATION IN CCGT CAPACITY FACTOR WITH INCREASING WIND Variables: CONS OBJ U V ONLINE QDAY QINTRA QREP QSPIN +, - Fuel consumed. Objective function. Relaxation variable. Decision variable—on or off. Integer on/off for unit. Day ahead demand not met. Intra day demand not met. Replacement reserve not met. Primary reserve not met. Up, down regulation. TABLE IX VARIATION IN COAL CAPACITY FACTOR WITH INCREASING WIND APPENDIX B SUMMARY OF NON-NORMALIZED BASE CASE RESULTS Tables VI–IX indicate the variation in start-ups and capacity factor of the CCGT and coal units in the base case (i.e., Tables VI–IX relate to Fig. 1), for each of the wind penetrations. The maximum value, minimum value, average and standard deviation are shown. It can be seen that the CCGT units have a greater spread in start-ups compared to the coal units and the standard deviation of start-ups is least at the highest wind case for both types of units. For capacity factor the spread in results across the units increased as the wind increased, with the CCGT units again having a greater variation compared to the coal units, however, there are more CCGT units than coal units in each of the wind cases. REFERENCES (A1) [1] H. Holttinen, “Impact of hourly wind power variations on the system operation in the Nordic countries,” Wind Energy, vol. 8, no. 2, pp. 197–218, Apr./Jun. 2005. [2] B. C. Ummels, M. Gibescu, E. Pelgrum, W. Kling, and A. Brand, “Impacts of wind power on thermal generation unit commitment and dispatch,” IEEE Trans. Energy Convers., vol. 22, no. 1, pp. 44–51, Mar. 2007. TROY et al.: BASE-LOAD CYCLING ON A SYSTEM WITH SIGNIFICANT WIND PENETRATION [3] G. Dany, “Power reserve in interconnected systems with high wind power production,” in Proc. IEEE Power Tech Conf., vol. 4, 6 pp, 2001. [4] Ahlstrom, L. Jones, R. Zavadil, and W. Grant, “The future of wind forecasting and utility operations,” IEEE Power and Energy Mag., vol. 3, no. 6, pp. 57–64, Nov.–Dec. 2005. [5] The Effect of Integrating Wind Power on Transmission System Planning, Reliability and Operations, Report prepared for New York State Energy Research and Development Agency, 2005. [Online]. Available: http://www.nyserda.org/publications/wind_integration_report.pdf. [6] P. Meibom, C. Weber, R. Barth, and H. Brand, “Operational costs induced by fluctuating wind power production in Germany and Scandinavia,” Proc. IET Renew. Power Gen., vol. 3, no. 1, pp. 75–83, Jan. 2009. [7] M. Braun, “Environmental external costs from power generation by renewable energies,” Master’s thesis, Stuttgart Univ., Stuttgart, Germany, 2004. [8] H. Holttinen, V. T. T. Finland, J. Pedersen, and E. Denmark, “The effect of large scale wind power on thermal system operation,” in Proc. 4th Int. Workshop Large-Scale Integration of Wind Power and Transmission Networks for Offshore Wind Farms, Billund, Denmark, Oct. 2003. [9] L. Goransson and F. Johnsson, “Dispatch modeling of a regional power generating system—Integrating wind power,” Renew. Energy, vol. 34, no. 4, pp. 1040–1049, Apr. 2009. [10] L. Balling and D. Hoffman, Fast Cycling Towards Bigger Profits, Modern Power Systems, 2007. [Online]. Available: http://www.modernpowersystems.com. [11] Variability of Wind Power and Other Renewables—Management Options and Strategies, International Energy Agency. [Online]. Available: http://www.iea.org/textbase/papers/2005/variability.pdf. [12] Large Scale Integration of Wind Energy in the European Power Supply: Analysis, Issues and Recommendations, European Wind Energy Association. [Online]. Available: http://www.ewea.org/index.php?id=178. [13] R. Viswanathan and J. Stringer, “Failure mechanisms of high temperature components in power plants,” Trans. ASME, vol. 122, pp. 246–255, Jul. 2000. [14] V. Viswanathan and D. Gray, Damage to Power Plants Due to Cycling, EPRI, Palo Alto, CA, 2001, Tech. Rep. 1001507. [15] J. Gostling, “Two shifting of power plant: Damage to power plants due to cycling—A brief overview,” OMMI, vol. 1, no. 1, Apr. 2002. [Online]. Available: http://www.ommi.co.uk/. [16] K. D. Le, R. R. Jackups, J. Feinstein, H. Thompson, H. M. Wolf, E. C. Stein, A. D. Gorski, and J. S. Griffith, “Operational aspects of generation cycling,” IEEE Trans. Power Syst., vol. 5, no. 4, pp. 1194–1203, Nov. 1990. [17] F. J. Berte and D. S. Moelling, “Assessing the true cost of cycling is a challenging assignment,” Combined Cycle J., pp. 23–25, 2003. [18] C. Johnston, “An approach to power station boiler and turbine life management,” in Proc. World Conf. NDT, Montreal, QC, Canada, Sep. 2004. [19] S. A. Lefton, P. M. Besuner, and G. P. Grimsrud, “Managing utility power plant assets to economically optimize power plant cycling costs, life, and reliability,” in Proc. 4th IEEE Conf. Control Applications, Albany, NY, Sep. 1995. [20] E. Denny and M. O’Malley, “The impact of carbon prices on generation cycling costs,” Energy Pol., vol. 37, no. 4, pp. 1204–1212, Apr. 2009. [21] S. A. Lefton, P. M. Besuner, G. P. Grimsrud, A. Bissel, and G. L. Norman, Optimizing Power Plant Cycling Operations While Reducing Generating Plant Damage and Costs at the Irish Electricity Supply Board. Sunnyvale, CA: Aptech Eng. Service, 1998. [22] A. Tuohy, P. Meibom, E. Denny, and M. O’Malley, “Unit commitment for systems with significant wind penetration,” IEEE Trans. Power Syst., vol. 24, no. 2, pp. 592–601, May 2009. [23] Wind Variability Management Studies, All Island Renewable Grid Study—Workstream 2B, 2008. [Online]. Available: http://www. dcmnr.gov.ie. [24] European Wind Integration Study. [Online]. Available: http://www. wind-integration.eu/. 1097 [25] L. Soder, “Simulation of wind speed forecast errors for operations planning of multi-area power systems,” in Proc. 2004 IEEE Int. Conf. Probabilistic Methods Applied to Power Systems, Ames, IA, Sep. 2004, pp. 723–728. [26] J. Dupacova, N. Growe-Kuska, and W. Romisch, “Scenario reduction in stochastic programming: An approach using probability metrics,” Math. Program., vol. 95, no. 3, pp. 493–511, 2003. [27] High Level Assessment of Suitable Generation Portfolios for the AllIsland System in 2020, All Island Renewable Grid Study—Workstream 2A, 2008. [Online]. Available: http://www.dcmnr.gov.ie. [28] B. Kirby and M. Milligan, “Facilitating wind development: The importance of electric industry structure,” Elect. J., vol. 21, no. 3, pp. 40–54, Apr. 2008. [29] G. Strbac, A. Shakoor, M. Black, D. Pudjianto, and T. Bopp, “Impact of wind generation on the operation and development of the UK electricity systems,” Elect. Power Syst. Res., vol. 77, no. 9, pp. 1214–1227, Jul. 2007. [30] Editorial, “Profitable operation requires knowing how much it costs to cycle your unit,” Combined Cycle J., pp. 49–52, 2004. [31] M. Flynn, M. Walsh, and M. O’Malley, “Efficient use of generator resources in emerging electricity markets,” IEEE Trans. Power Syst., vol. 15, no. 1, pp. 241–249, Feb. 2000. [32] C. Hiroux and M. Saguan, “Large-scale wind power in European electricity markets: Time for revisiting support schemes and market designs,” Energy Policy, to be published. Niamh Troy (GS’09) received the B.Sc. degree in applied physics from the University of Limerick, Limerick, Ireland. She is currently pursuing the Ph.D. degree at the Electricity Research Centre in the University College Dublin, Dublin, Ireland. Eleanor Denny (M’07) received the B.A. degree in economics and mathematics, the M.B.S. degree in quantitative finance, and the Ph.D. degree in wind generation integration from University College Dublin, Dublin, Ireland, in 2000, 2001, and 2007, respectively. She is currently a Lecturer in the Department of Economics at Trinity College Dublin and has research interests in renewable generation and integration, distributed energy resources, and system operation. Mark O’Malley (F’07) received the B.E. and Ph.D. degrees from University College Dublin, Dublin, Ireland, in 1983 and 1987, respectively. He is a Professor of electrical engineering at University College Dublin and is director of the Electricity Research Centre with research interests in power systems, control theory, and biomedical engineering. This article has been accepted for inclusion in a future issue of this journal. Content is final as presented, with the exception of pagination. IEEE TRANSACTIONS ON POWER SYSTEMS 1 Multi-Mode Operation of Combined-Cycle Gas Turbines With Increasing Wind Penetration Niamh Troy, Member, IEEE, Damian Flynn, Senior Member, IEEE, and Mark OMalley, Fellow, IEEE Abstract—As power systems evolve to incorporate greater penetrations of variable renewables, the demand for flexibility within the system is increased. Combined-cycle gas turbines are traditionally considered as relatively inflexible units, but those which incorporate a steam bypass stack are capable of open-cycle operation. Facilitating these units to also operate in open-cycle mode can benefit the power system via improved system reliability, while reducing the production needed from dedicated peaking units. The utilization of the multi-mode functionality is shown to be dependent on the flexibility inherent in the system and the manner in which the system is operated. Index Terms—Power system modeling, thermal power generation, wind power generation. I. INTRODUCTION C OMBINED-CYCLE gas turbines (CCGTs) are a type of power generating unit that achieve high efficiencies (up to 60%) by capturing the waste heat from a gas turbine in a heat recovery steam generator (HRSG) and using it to produce superheated steam to drive a steam turbine [1]. The high efficiencies achieved, combined with their ease of installation, short-build times, and relatively low gas prices, have made the CCGT a popular technology choice [2], [3]. In the Republic of Ireland, for example, 43% of the installed thermal capacity is CCGT technology, while in the markets of Texas (ERCOT) and New England (NEPOOL), CCGTs represent 37% of the total installed capacity. The operational flexibility of a CCGT unit is limited by the steam cycle, which contains many thick-walled components, necessary to withstand extreme temperatures and pressures [4], [5]. To avoid differential thermal expansion across these components and the subsequent risk of cracking, these components must be brought up to temperature slowly, resulting in slower start-up times and ramp rates for the unit overall [6]. However, by incorporating a bypass stack upstream of the HRSG at the design stage, a CCGT unit has the option to bypass the steam cycle and run in open-cycle mode, whereby exhaust heat from Manuscript received March 02, 2011; revised June 24, 2011; accepted July 22, 2011. This work was conducted in the Electricity Research Centre, University College Dublin, Ireland, which is supported by the Commission for Energy Regulation, Bord Gais Energy, Bord na Mona Energy, Cylon Controls, EirGrid, the Electric Power Research Institute (EPRI), ESB Energy International, ESB Energy Solutions, ESB Networks, Gaelectric, Siemens, SSE Renewables, and Viridian Power & Energy. This work was supported by Science Foundation Ireland under Grant Number 06/CP/E005. Paper no. TPWRS-00128-2011. The authors are with the School of Electrical, Electronic, and Mechanical Engineering, University College Dublin, Dublin, Ireland (e-mail: [email protected]; [email protected]; [email protected]). Digital Object Identifier 10.1109/TPWRS.2011.2163649 the gas turbine is ejected directly into the atmosphere via the bypass stack [6]. This reduces the power output and efficiency of the plant but offers greater operational flexibility. Running in open-cycle mode, the gas turbine has a short start-up time of 15 to 30 min and is capable of changing load quickly. However, bypass stacks are not always incorporated because they can potentially lead to leakage losses, thus reducing plant efficiency, while also introducing additional capital costs [1]. As international energy policy drives ever greater penetrations of renewable energy, wind power is set to represent a larger portion of the generation mix [7]. This is driving a greater demand for flexibility within power systems in order to deal with high penetrations of variable and difficult to predict energy sources [8], [9]. Storage, interconnection, and responsive demand are commonly cited as flexible options for dealing with variability issues [10]–[12]; however, these options have considerable costs associated with them. Facilitating open-cycle operation of CCGT units that have the technical capability to run in open-cycle mode (i.e., those with a bypass stack) can also deliver much needed flexibility to a system with a high wind penetration. This resource is often technically available, but inaccessible due to market arrangements. In order to derive the greatest benefits from a CCGT unit that can run in open-cycle mode, it is necessary for the scheduling algorithm to explicitly consider both modes of operation for the unit, i.e., open-cycle and combined-cycle [13]. These will have greatly different technical and cost characteristics and so need to be declared individually. Currently most markets do not facilitate CCGT units to submit multiple bids representing different modes of operation; thus, presently open-cycle operation of a CCGT unit is typically limited to periods when the steam section is undergoing maintenance. However, some U.S. systems have begun addressing this issue to varying degrees, with ERCOT and CAISO seeking to implement configuration-based modeling of CCGTs [14], [15]. The option to run in open-cycle mode could also provide benefits for the generators. Renewable integration studies have shown that CCGT units will experience significant decreases in running hours and thus will receive less revenue from the market as they are displaced by greater levels of wind generation which has an almost zero marginal cost [16]–[20]. Due to their high minimum loads, CCGTs are shut down frequently with high wind penetrations as they cannot reduce output sufficiently to accommodate the wind power output [16]. By facilitating CCGT units to operate in open-cycle mode, these units may have a new opportunity to capture revenue from increased operation during periods when they might otherwise be offline. For example, if a CCGT unit has been forced offline by high 0885-8950/$26.00 © 2011 IEEE This article has been accepted for inclusion in a future issue of this journal. Content is final as presented, with the exception of pagination. 2 IEEE TRANSACTIONS ON POWER SYSTEMS wind generation on the system, it may have the opportunity to run as a peaking unit. This paper builds on preliminary work in [21] and includes improved modeling of CCGTs from that in [21] to examine if a power system with a high wind penetration can benefit from the additional flexibility introduced when these units are facilitated to operate in open-cycle mode, when technically feasible and economically suitable. The all-island Irish 2020 system [22] is considered here as it is expected to contain both a large share of wind power and CCGT units. In addition, as it is a small, island system that is weakly interconnected, the challenges of maintaining the supply/demand balance with a high wind penetration are exacerbated, and so the solutions found can hold insights for other systems pursuing large-scale wind power. Section II describes the modeling tool used in this study and also the changes that were made to model multi-mode operation of CCGTs. Section III outlines the test system used. Section IV describes the results of the study and Section V concludes the paper. II. MODELING TOOL The Wilmar Planning Tool is a stochastic, mixed integer unit commitment and economic dispatch model, originally developed to model the Nordic electricity system and later adapted to the Irish system as part of the All Island Grid Study [22]–[25]. The main functionality of the Wilmar Planning Tool is embedded in the Scenario Tree Tool and Scheduling Model. The Scenario Tree Tool utilizes historical wind power or wind speed data, load data, and wind and load forecasts for different time horizons to identify an auto regressive moving average (ARMA) series which can then simulate wind and load forecast errors for various time horizons [26]. These simulated wind and load forecasts errors are paired in a random way before a scenario reduction technique, following the approach of [27], is applied. The wind and load forecast errors are combined with scaled up wind and load time series to produce wind power production and load forecast scenarios. For each scenario, the demin) is calcumand for replacement reserve (activation time lated based on a comparison of the hourly power balance considering perfect forecasts and no forced outages with the power balance considering scenarios of wind and load forecast errors as well as forced outages. A percentile of the deviation between the compared power balances must be covered by replacement reserves; in this case, the 90th percentile is chosen based on current practice [23]. A forced outage time series for each unit is also generated by the Scenario Tree Tool using a semi-Markov process based on historical plant data of forced outage rates, mean time to repair, and scheduled outages. The model can also be run in deterministic and perfect foresight modes whereby only one wind generation and load scenario is planned for. In deterministic mode, this scenario is the expected value of wind and load. The expected value of wind is found by summing, for all (post-reduction) scenarios, the product of the wind power forecasts and their probability of occurring. The expected value of load and replacement reserve is found similarly [24]. Consequently, the scenario planned for will differ from the realized scenario. This mode is typical of the scheduling process currently practiced by most system operators, i.e., only one scenario is planned for and it will contain some level of forecast error. Perfect foresight mode contains no forecast error for wind generation or load but forced outages still occur, as with all other modes. The Scheduling Model minimizes the expected costs for all scenarios, subject to system constraints for reserve and the minimum number of units online (6 units in the Republic of Ireland and 2 units in Northern Ireland). These costs include fuel, carbon, and start-up fuel costs (always assumed to be hot starts). In addition to replacement reserve, one category of spinning reserve, namely tertiary operating reserve (TR1), is modeled, which has a response time of 90 s to 5 min and is only supplied by online units. Enough spinning reserve must be available to cover an outage of the largest online unit occurring concurrently with a fast decrease in wind power production over the TR1 time frame, as described in [28]. Generator constraints such as minimum down times, synchronization times, minimum operating times, and ramp rates must also be obeyed. Rolling planning is employed to re-optimize the system as new wind generation and load information become available. Starting at noon each day, the system is scheduled over 36 h until the end of the next day. The model steps forward with a 3-h time step and reschedules the units based on information from new forecasts. The model produces a year-long dispatch at an hourly time resolution for each individual generating unit. Further detail on the model and formulation of the unit commitment problem can be found in [23]. The Generic Algebraic Modeling System (GAMS) is used to solve the unit commitment problem using the mixed integer feature of the Cplex solver (version 12). For all simulations in this study, the model was run with a duality gap of 0.5%. A year-long simulation takes h when run in deterministic mode or h in stochastic mode, on an Intel core quad 3-GHz processor with 4 GB of RAM. A. Modeling Multi-Mode Operation of CCGTs In order to examine the potential for multi-mode operation ”, of all CCGT units capable of proof CCGT units a set, “ longed open-cycle operation, i.e., those with bypass stacks, was ” corresponds to these CCGT units defined. The set “ when run in open-cycle mode. CCGT units comprised of two ” units, as inor more gas turbines will have multiple “ dicated by index “a”. The relation “multi-mode” is defined to ” with the corresponding member(s) pair each member of “ ”. To ensure the mutually exclusive operation of of “ these “ ” units and the corresponding “ ” units, the constraint shown in (1) was added to the model, where is the state binary variable which describes the online status of the unit. This allows the model to dispatch, when economically ” (combined-cycle mode) or any/all of optimal, either the “ ” units (open cycle mode), for all the corresponding “ scenarios “s” and time steps “t”, but not both simultaneously as they are in reality the same unit: (1) This article has been accepted for inclusion in a future issue of this journal. Content is final as presented, with the exception of pagination. TROY et al.: MULTI-MODE OPERATION OF COMBINED-CYCLE GAS TURBINES WITH INCREASING WIND PENETRATION 3 Equation (2), taken from [29], sets the state binary variables or equal to 1 for all units “i”, when a unit is started up or shut down, respectively: (2) When modeling multi-mode operation of CCGT units, two new circumstances arise when calculating the start-up fuel , which must be explicitly represented. consumption, Firstly, when a “ ” unit transitions from conventional combined-cycle operation into open-cycle operation no start-up fuel ” unit as represented by inequality is consumed by the “ (3), where is the start-up energy used by each unit ” unit starts from zero (measured in MWh). When the “ and ), the first term production ( on the right-hand side of inequality (3) determines the fuel used by the unit while the second term equals zero. Alternatively, when the unit switches from combined-cycle to open-cycle and ), the second term operation ( causes the right-hand side of (3) to equal zero. Setting as a positive variable and using an inequality condition ensures ” unit is shutting down and the corresponding that when a “ ” unit is not starting up, will be 0: “ Fig. 1. CCGT start-up from open-cycle mode. and (6), where is a unit’s minimum stable operating is a unit’s maximum capacity (MW), level (MW) and ” unit or the “ ” unit is onensure that if either the “ line, then the “ ” unit cannot contribute to the portion of replacement reserve that is provided from offline units. This ” unit is online is necessary to avoid the situation where a “ ” unit to conand the model allows the corresponding “ tribute to offline replacement reserve: (3) (5) The second circumstance relates to the unit transitioning from open-cycle to combined-cycle operation. In this case, the start-up fuel consumed is less than the start-up fuel used in bringing the CCGT online from zero production, as some of this start-up fuel has already been used to bring the unit online in open-cycle mode and the gas section of the plant is in a hot state. As an approximation, the start-up fuel used to bring the unit into combined-cycle operation from open-cycle operation ” and a is the difference between the start-up fuel for the “ ”, as seen in fraction, , of the start-up fuel for the “ (4). Based on the operating experience of generators, was ” unit is started from chosen to be 0.5 here. When the “ zero production ( and ), the first term on the right-hand side of (4) provides the start-up fuel consumed, while the second term equals zero. When the unit switches from open-cycle to combined-cycle operation, the second term is included, thus approximating the start-up fuel consumed in this situation: (6) (4) In the Wilmar model, any unit can contribute to the target for replacement (non-spinning) reserve, provided that an offline unit can come online in time to provide reserve for the hour in question and the reserve available from an online unit is not needed to meet spinning reserve targets. In Wilmar, the contribution from online and offline units to the replacement reserve (MW), are calculated individually. In this case the target, ” units cannot provide offline replacement reserve as they “ ” units have long start-up times, but the corresponding “ can, given their fast start-up times. The constraints shown in (5) Improved modeling of plant start-ups was also implemented following the formulation given in [29]. This allows for those units with start-up times greater than 1 h to be block-loaded over the course of their start-up time. In earlier versions of the Wilmar model, units remained at zero production for the duration of start-up process. The addition of this feature significantly increased the computation time, so only the start-up process of the CCGT units was modeled in detail. Other units with a start-up time greater than 1 h, namely the coal-fired units, typically have fewer starts over the year and lower minimum operating levels relative to the CCGTs and so modeling their start-up process in detail would have little impact on the results. When the bypass stack is utilized to switch from combined-cycle to open-cycle operation, the transition is automatic and occurs without shutting down the gas turbine or reducing its power output. However, the transition from open-cycle to combined-cycle operation is dependent on the temperature state of the boiler. Therefore, if the CCGT unit has been operating for a period of time in open-cycle mode and is then scheduled to switch to combined-cycle mode, its output must adjust in order to achieve the correct HRSG inlet temperature, as depicted in Fig. 1. This was implemented by setting the allowable power from [29]) for each interval of the CCGT’s output ( start-up process, which begins at hour 0 in Fig. 1, such that the appropriate soak time is achieved. Scheduled outages for each unit, determined from historical experience [22], are inputted in time-series format to the Wilmar model. In this case, CCGT units with the capability to operate in open-cycle mode are considered to be available to run in open-cycle mode for a portion of their scheduled outage. Given This article has been accepted for inclusion in a future issue of this journal. Content is final as presented, with the exception of pagination. 4 IEEE TRANSACTIONS ON POWER SYSTEMS TABLE I GENERATION MIX OF TEST SYSTEM TABLE III CHARACTERISTICS OF CCGT UNITS (CAPABLE OF MULTI-MODE OPERATION) IN COMBINED- AND OPEN-CYCLE MODES TABLE II FUEL PRICES BY FUEL TYPE that gas turbine equipment is more accessible and compact in comparison with the steam turbine equipment, it was assumed that one third of the maintenance period was sufficient for the gas turbine. III. TEST SYSTEM The test system used is the Irish 2020 system, based on portfolio 5 from the All Island Grid Study [22], [30]. Four 103.5-MW OCGT units were removed from the original grid study portfolio as recent generation adequacy reports would indicate they are unlikely to be built by 2020 [31]. Table I shows the number of units, installed capacity, and average operating cost (fuel) by generation type. (The multi-mode capable CCGT units in open-cycle mode are shown on the last row.) Three different levels of installed wind power were examined: 2000, 4000, and 6000 MW, which supply 15%, 29%, and 44% of the total energy demand, respectively. Fuel prices are as given in Table II. Base-load gas generators (i.e., CCGTs and CHP) are assumed to have long-term fuel contracts and therefore pay a cheaper fuel price compared to mid-merit gas generators (i.e., OCGTs, ADGTs, and legacy CCGTs). Differences in the fuel price for coal and gas oil in the Republic of Ireland and Northern Ireland reflect varying delivery costs. The original demand profile from [22] with a 9.6-GW peak and 54-TWh total demand was scaled down to a profile with a 7.55-GW peak and 42-TWh total demand to reflect a reduction in predicted demand, seen in recent long-term forecasts [31]. The test system assumes that there is 1000 MW of HVDC interconnection in place between Ireland and Great Britain and it is scheduled on an intra-day basis, i.e., it can be rescheduled in every 3-h rolling planning period. A simplified model of the British power system is included, with aggregated units, no integer variables for generators and where wind generation and load are assumed to be perfectly forecast. The total demand in Britain is assumed to be 370 TWh with a peak of 63 GW and the installed wind capacity is assumed to be 14 GW. A carbon was assumed. price of Five (of the ten) CCGT units on the Irish system include bypass stacks and therefore can run in open-cycle mode. Each of these units is currently installed and operational. The characteristics of these units in combined-cycle mode are given in Table III. Limited data was available for these units in opencycle mode so each was given characteristics similar to a typical open-cycle gas turbine (OCGT) unit, as shown in Table III. As CCGT 2 and CCGT 5 are comprised of two gas turbines configuration), these units connected to one steam turbine ( were modeled as having two identical open-cycle units available for dispatch when the CCGT is operated in open-cycle mode. CCGTs 2 and 3, located in Northern Ireland and CCGTs 1, 4, and 5, located in the Republic of Ireland, contribute to the minimum units online constraint in their respective regions. IV. RESULTS A number of model runs were conducted to investigate the potential for multi-mode operation of CCGT units. The Wilmar model was run in deterministic mode as this is more representative of current scheduling practice. A year-long dispatch was produced for each of the three wind power penetrations outlined in Section III, when 1) multi-mode operation of CCGT units is not allowed and 2) when multi-mode operation of CCGT units is allowed. This article has been accepted for inclusion in a future issue of this journal. Content is final as presented, with the exception of pagination. TROY et al.: MULTI-MODE OPERATION OF COMBINED-CYCLE GAS TURBINES WITH INCREASING WIND PENETRATION 5 TABLE V OCGT PRODUCTION (GWh) WITH INCREASING WIND PENETRATION TABLE VI DIFFERENCE IN OPEN-CYCLE PRODUCTION (GWh) FROM MULTI-MODE UNITS WITH NO REPLACEMENT RESERVE TARGET ENFORCED Fig. 2. Average production from a CCGT in open-cycle mode (line) and average number of instances generators utilized open-cycle operation (grey column), shown for various levels of installed wind capacity. TABLE VII AVERAGE HOURLY SURPLUS SPINNING RESERVE (MW) AVAILABLE AND REPLACEMENT RESERVE TARGET (MW) TABLE IV AVERAGE UTILIZATION FACTORS WITH INCREASING WIND PENETRATION A. Usage of the Multi-Mode Function The average number of times a CCGT unit with multi-mode capability was run in open-cycle mode and the average production from a CCGT in open-cycle mode over the year, at each of the wind penetrations examined, is shown in Fig. 2. Despite increasing wind penetration being correlated with an increased demand for flexibility, be it fast starting or ramping, Fig. 2 shows the multi-mode function is used less frequently as wind penetration on the system increases. As more wind power, with an almost zero marginal cost, is added to a system, the production from thermal plant is increasingly displaced and as such there is an increased likelihood of generators operating at part-load. To illustrate, Table IV gives the annual utilization factor (ratio of actual generation to maximum possible generation during hours of operation) averaged for the coal, CCGT, and peat units on the system with 2000-, 4000-, and 6000-MW wind power. Therefore, as wind penetration increases, online part-loaded units are more often available to ramp up their output to meet unexpected shortfalls in production, avoiding the need to switch on fast-starting units, such as the CCGTs in open-cycle mode. The trend seen in Fig. 2 is consistent with the production from peaking plants as wind penetration increases. Table V shows the drop in production from the most utilized OCGT unit, with increasing wind penetration when multi-mode operation is and is not allowed. Reduced production from peaking plants due to increased wind penetration has also been observed in other wind integration studies such as [17]; however, it is also likely that systems with base-load units that have slower ramp rates than those examined in this study will rely on fast-starting units (such as CCGTs in open-cycle mode) more often as wind penetration increases. (All units on the test system are assumed to be capable of ramping from minimum to maximum output in one hour or less.) The average production from the CCGT units in open-cycle mode, as seen in Fig. 2, is comparable with average production levels from dedicated OCGT peaking plants on the system when multi-mode operation of CCGTs is not enabled. As wind penetration increases, so too will the demand for replacement reserve, due to the increased forecast error. The replacement reserve target can be met by fast-starting offline units or from excess spinning reserve if available. If sufficient excess spinning reserve is not available to meet the replacement reserve target, the model must ensure a number of fast-starting units are offline and available for operation to maintain a secure system. Consequently, as a result of maintaining the replacement reserve target, production from fast-start units (such as the multi-mode units in open-cycle mode) is reduced. Additional simulations were conducted for the various wind penetrations with no replacement reserve target, to investigate the extent that maintaining replacement reserve suppressed the multi-mode units from running in open-cycle mode. For many systems, such as the Irish system, this is more representative of current practice, where no replacement reserve target formally exists. Table VI shows the difference in the average open-cycle production from multi-mode units that results when no replacement reserve targets are enforced. As seen, in the absence of a target for replacement reserve, open-cycle production from the multi-mode units is utilized substantially more for the 2000-MW and 4000-MW wind power scenarios. However, with 6000-MW wind power, due to more frequent part-loading of units, there is more frequently an excess of spinning reserve on the system, as well as offline fast-starting units (as per Table V) which can contribute to the replacement reserve target. Thus, with 6000-MW wind power, the replacement reserve target has little effect on the open-cycle operation of multi-mode units. Table VII shows the average surplus spinning reserve available and the average replacement reserve target per hour for each of the wind cases examined. Fig. 3 shows the capacity factor for each CCGT in combined-cycle mode and its production over the year in open-cycle mode for the 2000-MW wind power scenario. An inverse relationship is evident between the open-cycle production from a CCGT and the capacity factor of the CCGT, which indicates that usage of the multi-mode function is related to the amount This article has been accepted for inclusion in a future issue of this journal. Content is final as presented, with the exception of pagination. 6 IEEE TRANSACTIONS ON POWER SYSTEMS Fig. 3. Combined-cycle capacity factor (dashed line) and open-cycle production (solid line) for each CCGT with multi-mode capability for the 2000-MW wind power system. Fig. 4. Average production from OCGT peaking units in each wind power scenario, with multi-mode operation of CCGTs not allowed (light grey) and allowed (dark grey). TABLE VIII PERCENTAGE CHANGE IN TOTAL PRODUCTION WHEN MULTI-MODE IS ENABLED, SHOWN FOR EACH WIND PENETRATION TABLE IX MAGNITUDE AND FREQUENCY OF REPLACEMENT RESERVE SHORTFALL, SHOWN FOR VARIOUS LEVELS OF INSTALLED WIND of time the CCGT is offline. The more often a CCGT is not in operation but available for dispatch, the more opportunities it has to run in open-cycle mode and this relationship would be expected regardless of the plant portfolio. The percentage change in total production (combined-cycle plus open-cycle) that results when multi-mode operation of CCGTs is enabled is shown in Table VIII, for each of the wind penetrations examined. Multi-mode operation increased production for CCGT5, the lowest merit CCGT which was seen to utilize the function most frequently, across all the wind penetrations examined. Total production from CCGT3 and CCGT4, which are mid-merit CCGTs, is reduced in all cases but one. There is a risk (particularly for CCGTs that are frequently the marginal unit on the system such as CCGT3 and CCGT4), when offering open-cycle operation, of being dispatched from combined-cycle to open-cycle operation at times of low net demand (demand minus wind generation) to alleviate minimum load issues and then losing out to another generator that can come online faster/cheaper, when the net demand increases again. However, it is also likely that in a market environment, generators would strategize when they would offer this multi-mode capability to avoid losing out on production. CCGT1, the highest merit CCGT, benefits from increased production when multi-mode operation is enabled on the system with 2000-MW and 4000-MW installed wind power. This is due to increased exports and reduced production from the other CCGTs, as opposed to increased production in open-cycle mode. contracts. Their open-cycle capacity (as seen in Table III) is also larger than the capacity of the OCGTs (103.5 MW each) and they benefit from avoided start-up costs when transitioning from combined-cycle mode. Thus, when multi-mode operation of CCGTs was enabled, production from OCGT peaking plant tended to be substituted by production from the CCGTs in opencycle mode. Fig. 4, which shows the average production from OCGTs for each wind penetration level when multi-mode operation of CCGTs is allowed and not allowed, illustrates this point. Assuming open-cycle production from CCGTs is more economic than production from OCGTs, as is the case here, it is possible that by enabling multi-mode operation of CCGTs sufficient flexibility could be extracted from a systems portfolio of plant to avoid building additional peaking units, or equally that OCGT units would no longer be able to cover their costs and so would be forced to retire from service. Both situations may then lead to increased production from CCGTs in open-cycle mode. Table IX shows the total shortfall in replacement reserve over the year and the number of hours in which this occurred, for each of the wind penetrations examined, when multi-mode operation of CCGTs is and is not allowed. The additional fast-starting generation available to the system when multi-mode operation of CCGT units is allowed significantly reduces the shortfall in replacement reserve. This contributes to a more secure system by preventing capacity shortfalls when wind forecasts prove to be overly optimistic and also indicates that, depending on the market structure, the generators may benefit from an additional revenue stream, via ancillary services payments for the replacement reserve provided. In addition to enhanced system security, the additional flexibility available to the system when multi-mode operation of CCGT units is allowed will also yield production costs savings. Table X shows the total system operating cost savings achieved by enabling multi-mode operation of CCGTs. The total system B. Benefits Arising From Multi-Mode Operation The efficiencies of the OCGT peaking units on the system are comparable with the CCGT units in open-cycle mode. However, the CCGT units running in open-cycle operation are assumed to have a lower gas price, to reflect the advantage of long-term This article has been accepted for inclusion in a future issue of this journal. Content is final as presented, with the exception of pagination. TROY et al.: MULTI-MODE OPERATION OF COMBINED-CYCLE GAS TURBINES WITH INCREASING WIND PENETRATION 7 TABLE X TOTAL SYSTEM COST SAVING (MC) RESULTING FROM MULTI-MODE OPERATION OF CCGTS cost is made up of fuel, carbon, and start-up costs for the Irish and British system combined, as they are co-optimized. In this case, these savings were achieved at no additional cost as each of the CCGTs is currently capable of multi-mode operation. A modest reduction in plant start-ups for multi-mode units averaged (in combined-cycle mode) was also observed ( over the three wind power scenarios), relative to the case when multi-mode operation is not allowed, which would indicate benefits for the steam equipment via avoided wear-and-tear. Fig. 5. Average production from a CCGT in open-cycle mode (line) and average number of instances generators utilized open-cycle operation (grey column), with interconnector scheduled day-ahead and intra-day on 2000-MW wind system. C. Sensitivity Studies Usage of the multi-mode function is dependent on many factors, particularly the amount of flexibility already present in the system. A sensitivity study was conducted to examine the usage of the multi-mode function when the system was less flexible to meeting demand. This involved running the model with 2000-MW wind power (as this level of wind generation greatest usage of CCGTs in open-cycle mode) and power exchange across the interconnector fixed day-ahead as opposed to intra-day. Examining the usage of the multi-mode function when the interconnector is scheduled day-ahead versus intra-day illustrates how a less flexible system will utilize this flexible resource more frequently. Fig. 5 shows the average production from a CCGT in open-cycle mode and the average number of instances CCGTs utilized open-cycle operation, with the interconnector scheduled day-ahead and intra-day on the 2000-MW wind power system. The average production from CCGTs in open-cycle mode on the system with day-ahead scheduling of the interconnector is seen to be more than three times greater than the system with intra-day scheduling of the interconnector. By fixing the power exchange between the Irish and British systems day-ahead, when there is greater uncertainty in the expected wind generation and demand, the system is forced to dispatch generators such as the multi-mode CCGT units, as opposed to reschedule imports/exports, to compensate for wind and load forecast errors. Likewise, systems with seasonal hydro restrictions may see greater usage of multi-mode CCGT operation during these periods when the operating flexibility of the system is reduced. In addition, the type of wind and load forecasts employed by a system will also determine the usage of the multi-mode function. Additional simulations were completed running the model in stochastic and perfect foresight mode. These represent different means of including load and wind forecasts in the scheduling process; whereby stochastic optimization can be considered to represent a system employing ensemble forecasts, deterministic optimization is representative of a system utilizing a single forecast, and the perfect forecast scenario is a hypothetical case where no forecast error exists. The robust solutions obtained by stochastic optimization showed less deployment of the multi-mode function compared with the deterministic results. The stochastic solution, optimized for several wind and Fig. 6. Average production from CCGT in open-cycle mode (GWh), shown for different methods of optimization with 2000-MW wind power. load scenarios, typically has more units online to cover all scenarios and therefore is more prepared to deal with unforseen shortfalls in wind generation or increases in demand without the need for starting peaking plant. The capacity factors of the CCGT units are also higher for the stochastic case compared to the deterministic case, indicating that there was also less opportunity for these units to run in open-cycle mode when the system is optimized stochastically. Running the Wilmar model with perfect foresight of the system demand and wind profile also reveals even less open-cycle operation from CCGTs as in this case, with no forecast errors on the system (except forced outages of generators), fast starting units are in less demand relative to the deterministically optimized solution. Fig. 6 compares the average open-cycle operation from the multi-mode CCGTs, on the system with 2000-MW wind power, when optimized with perfect foresight, stochastically and deterministically. The average open-cycle production from a CCGT unit is seen to be 11% less on the stochastically optimized system and 35% less on the system with perfect forecast compared to the deterministic case. A sensitivity analysis was also conducted using a higher level of demand on the system. In this case, the original demand profile from [22] with a 9.6-GW peak, discussed in Section III, was run for each wind scenario. The average production from a CCGT in open-cycle mode over the year is shown in Fig. 7 to be six to eight times greater on the 9.6-GW peak demand system, where peaking capacity is in greater demand, compared to the 7.55-GW peak demand system, at each of the wind power penetrations examined. In addition to the increased demand resulting in increased open-cycle production from the multi-mode This article has been accepted for inclusion in a future issue of this journal. Content is final as presented, with the exception of pagination. 8 IEEE TRANSACTIONS ON POWER SYSTEMS TABLE XI TOTAL SYSTEM COST, REPLACEMENT RESERVE SHORTFALL AND TOP-UP PAYMENT, SHOWN FOR VARIOUS MULTI-MODE CONFIGURATIONS Fig. 7. Average production from a CCGT in open-cycle mode on the 7.55-GW peak demand system (light grey) and the 9.6-GW peak demand system (dark grey), shown for various levels of installed wind power. CCGTs (as well as combined-cycle production), the other main difference between the scenarios is the predominant direction of power transfer on the interconnector. With 2000-MW installed wind capacity, the Irish system is a net importer of power from Britain, at both levels of demand examined. However, as more wind power is installed on the 7.55-GW peak demand system, the marginal electricity price is reduced sufficiently with respect to the British system such that Ireland becomes a net exporter of power. Although increasing wind power penetration on the 9.6-GW peak demand system also reduces the marginal price, it is still a net importer with 6000-MW installed wind power. Thus, on occasions when forecast wind is overestimated and the system is in need of fast-starting plant, the 7.55-GW peak demand system, being a net exporter, can more frequently choose to curtail exports or start up a unit to compensate. In contrast, the 9.6-GW peak demand system, being a net importer, more often only has the option to turn on fast-starting plant. Hence, this implies that a system which tends to be a net exporter is inherently more flexible, and has more options for dealing with variable wind power than a system that is a net importer of power. In this scenario with higher demand, each of the multi-mode CCGT units experienced increased total production (combined-cycle plus open-cycle) when multi-mode operation was allowed, suggesting that offering multi-mode capability may prove more profitable on a system with a smaller capacity margin. Given the low deployment of the multi-mode functionality and the high capacity factor in combined-cycle mode for CCGT 1 and 2, as seen in Fig. 3, it would appear that there is insufficient incentive for all CCGTs capable of multi-mode operation to offer this flexible capability. Thus, given that CCGTs 3, 4, and 5 have low capacity factors in combined-cycle mode, additional simulations were conducted to investigate the benefits yielded if these units alone, and if CCGT 5 alone, offered multi-mode capability. Table XI shows the total system cost (for Ireland and Britain) and the magnitude of the replacement reserve shortfall over the year for these configurations (in addition to other configurations examined in the paper). Examining the shortfall in the replacement reserve target for the different configurations of the reduction in replacereveals that the majority ment reserve shortfall due to multi-mode capability is attributable to CCGT 5, while CCGTs 1 and 2 are seen to have no impact on the replacement reserve shortfall. Thus, CCGTs capable of open-cycle operation, which have very low output in combined-cycle mode, have value in providing replacement reserve. As seen in Table VIII, the multi-mode CCGTs may experience a reduction in total production as a result of offering multi-mode capability to the market. This was also observed to be the case for CCGTs 3 and 4, when only three units offered multi-mode operation. This indicates that a system seeking to increase its flexibility via multi-mode operation of CCGTs, possibly to facilitate integration of variable renewables, may need to reward these units either through ancillary service payments or another market mechanism to restore their revenue to original levels (i.e., when multi-mode operation was not allowed). The subsidy or “top-up payment” required to restore the revenue of these units to their original level is estimated here as the loss in total production multiplied by the average electricity price. The average “top-up payment” required is shown in Table XI with the number of units requiring this payment shown in parenthesis. However, it should be noted that this represents the worst-case figure given that the multi-mode CCGT unit offered this capability in all time periods, rather than when it was profitable for them to do so, as would likely be the case in reality. V. CONCLUSIONS This paper examines if allowing CCGT units to operate in open-cycle mode, when this is technically feasible and cost optimal, could deliver benefits to a system with a high wind penetration or to the generators themselves. It is shown that the This article has been accepted for inclusion in a future issue of this journal. Content is final as presented, with the exception of pagination. TROY et al.: MULTI-MODE OPERATION OF COMBINED-CYCLE GAS TURBINES WITH INCREASING WIND PENETRATION extra fast-starting capacity available from multi-mode operation of CCGTs can reduce the replacement reserve shortfall, indicating an opportunity for increasing system reliability. Low-merit CCGTs will utilize the multi-mode function more as they are frequently offline and available for dispatch, while the increased competition among generators, typical at higher levels of wind generation, results in multi-mode operation of CCGTs being utilized less frequently. Peaking production from CCGTs in open-cycle mode can displace peaking production from OCGTs, potentially reducing the need for such units to be built. Sensitivity studies reveal that usage of the multi-mode function is dependent on the level of flexibility inherent in a system. Optimizing the system stochastically or allowing intra-day trading on interconnectors reduces the need for flexibility to be extracted from generators and consequently results in less frequent deployment of the multi-mode function. ACKNOWLEDGMENT The authors would like to thank A. Mahon and A. Barnes of ESB for their helpful contributions. REFERENCES [1] R. Kehlhoffer, Combined-Cycle Gas & Steam Turbine Power Plants, 2nd ed. Tulsa, OK: PennWell, 1999. [2] W. J. Watson, “The success of the combined cycle gas turbine,” in Proc. IEEE Conf. Opportunities and Advances in International Electric Power Generation, 1996, pp. 87–92. [3] U. C. Colpier and D. Cornland, “The economics of the combined cycle gas turbine—An experience curve analysis,” Energy Policy, vol. 30, no. 4, pp. 309–316, 2002. [4] A. Shibli and F. Starr, “Some aspects of plant and research experience in the use of new high strength martensitic steel P91,” Int. J. Pressure Vessels and Piping, vol. 84, pp. 114–122, 2007. [5] F. Starr, “Background to the design of HRSG systems and implications for CCGT plant cycling,” Oper. Mainten. Mater. Issues, vol. 2, no. 1, Apr. 2003. [6] R. Anderson and H. van Ballegooyen, “Steam turbine bypass systems,” Combined Cycle J., 2003. [7] Winning With European Wind, European Wind Energy Association, 2009. [Online]. Available: http://www.ewea.org. [8] H. Chandler, Empowering Variable Renewables, Options for Flexible Electricity Systems. Paris, France: International Energy Agency, 2008. [9] F. Van Hulle and P. Gardner, Wind Energy—The Facts, Part 2 Grid Integration, 2008. [Online]. Available: http://www.wind-energy-the-facts.org/. [10] P. Brown, J. Lopes, and M. Matos, “Optimization of pumped storage capacity in an isolated power system with large renewable penetration,” IEEE Trans. Power Syst., vol. 23, no. 2, pp. 523–531, May 2008. [11] V. Hamidi and F. Robinson, “Responsive demand in networks with high penetration of wind power,” in Proc. IEEE/PES Transmission and Distribution Conf. Expo., 2008. [12] L. Göransson, “Wind power in thermal power systems—Large-scale integration,” Licentiate thesis, Dept. of Energy and Environment, Chalmers Univ. Technology, Goteburg, Sweeden, 2008. [13] B. Lu and M. Shahidehpour, “Short-term scheduling of combined-cycle units,” IEEE Trans. Power Syst., vol. 19, no. 3, pp. 1616–1625, Aug. 2004. [14] B. Blevins, Combined-Cycle Unit Modeling in the Nodal Design. Taylor, TX: ERCOT, 2007. [15] Multi-Stage Generating (MSG) Unit Modeling, CAISO, 2010. [Online]. Available: http://www.caiso.com/2078/2078908392d0.html. 9 [16] N. Troy, E. Denny, and M. O’Malley, “Base-load cycling on a system with significant wind penetration,” IEEE Trans. Power Syst., vol. 25, no. 2, pp. 1088–1097, May 2010. [17] Growing Wind—Final Report of the NYISO Wind Integration Study, NYISO, 2010. [Online]. Available: http://www.nyiso.com. [18] Integration of Renewable Resources—Operational Requirements and Generation Fleet Capability at 20% RPS, California ISO, 2010. [Online]. Available: http://www.caiso.com/2804/2804d036401f0ex.html. [19] Western Wind and Solar Integration Study, National Renewable Energy Laboratory, 2010. [Online]. Available: http://www.nrel.gov/wind/systemsintegration/wwsis.html. [20] L. Göransson and F. Johnsson, “Dispatch modeling of a regional power generation system—Integrating wind power,” Renew. Energy, vol. 34, no. 4, pp. 1040–1049, 2009. [21] N. Troy and M. O’Malley, “Multi-mode operation of combined cycle gas turbines with increasing wind penetration,” in Proc. IEEE Power and Energy Soc. General Meeting, 2010. [22] Wind Variability Management Studies, All Island Renewable Grid Study—Workstream 2B, 2008. [Online]. Available: http://www.dcenr. gov.ie. [23] P. Meibom, R. Barth, B. Hasche, H. Brand, and M. O’Malley, “Stochastic optimization model to study the operational impacts of high wind penetrations in Ireland,” IEEE Trans. Power Syst., vol. 26, no. 3, pp. 1367–1379, Aug. 2011. [24] A. Tuohy, P. Meibom, E. Denny, and M. O’Malley, “Unit commitment for systems with significant wind penetration,” IEEE Trans. Power Syst., vol. 24, no. 2, pp. 592–601, May 2009. [25] P. Meibom, WILMAR—Wind Power Integration in Liberalised Electricity Markets, 2006. [Online]. Available: http://www.wilmar. risoe.dk/Results.htm. [26] L. Söder, “Simulation of wind speed forecast errors for operation planning of multiarea power systems,” in Proc. Int. Conf. Probabilistic Methods Applied to Power Systems, 2004. [27] J. Dupacova, N. Growe-Kuska, and W. Romisch, “Scenario reduction in stochastic programming: An approach using probability metrics,” Math. Program., vol. 95, no. 3, pp. 493–511, 2003. [28] R. Doherty and M. O’Malley, “A new approach to quantify reserve demand in systems with significant installed wind capacity,” IEEE Trans. Power Syst., vol. 20, no. 2, pp. 587–595, May 2005. [29] J. M. Arroyo and A. J. Conejo, “Modeling of start-up and shut-down power trajectories of thermal units,” IEEE Trans. Power Syst., vol. 19, no. 3, pp. 1562–1568, Aug. 2004. [30] Redpoint Validated Forecast Model and PLEXOS Validation Report 2010, Commission for Energy Regulation, 2010. [Online]. Available: http://www.allislandproject.org. [31] Generation Adequacy Report 2010–2016, EirGrid, 2009. [Online]. Available: http://www.eirgrid.com. Niamh Troy (M’11) received the B.Sc. degree in applied physics from the University of Limerick, Limerick, Ireland. She is currently pursuing the Ph.D. degree at the Electricity Research Centre in University College Dublin, Dublin, Ireland. Damian Flynn (SM’11) is a senior lecturer in power engineering at University College Dublin, Dublin, Ireland. His research interests involve an investigation of the effects of embedded generation sources, especially renewables, on the operation of power systems. Mark O’Malley (F’07) received the B.E. and Ph.D. degrees from University College Dublin, Dublin, Ireland, in 1983 and 1987, respectively. He is a Professor of electrical engineering in University College Dublin and is director of the Electricity Research Centre with research interests in grid integration of renewables. Prof. O’Malley is a member of the Royal Irish Academy. 1 Unit Commitment with Dynamic Cycling Costs Niamh Troy, Student Member, IEEE, Damian Flynn, Senior Member, IEEE, Michael Milligan, Senior Member, IEEE, and Mark O’Malley, Fellow, IEEE Abstract—Increased competition in the electricity sector and the integration of variable renewable energy sources is resulting in more frequent cycling of thermal plant. Thus, the wearand-tear to generator components and the related costs are a growing concern for plant owners and system operators alike. This paper presents a formulation that can be implemented in a MIP dispatch model to dynamically model cycling costs based on unit operation. When implemented for a test system the results show that dynamically modeling cycling costs reduces cycling operation and tends to change the merit order over time. This leads to the burden of cycling operation being more evenly distributed over the plant portfolio and a reduces the total system costs relative to the case when cycling costs are not modeled. Index Terms—Thermal Power Generation, power system modeling N OMENCLATURE Indices/Sets t, T g, G i, I j, J l, L Time step, set of time steps Units, set of units Interval of cycling cost function, set of intervals of cycling cost function Level of ramp, set of all ramp levels Segment of the piecewise linearization of the variable cost function, set of all segments of the piecewise, linearization of the variable cost function Constants ag , bg , cg costSg ThSg (i) costSg (i) Rg Rg (j) Coefficients of the quadratic production cost function for unit g Cycling cost increment for each additional start-up for unit g ith threshold corresponding to cumulative start-ups for unit g Cycling cost increment for each additional start-up, while NSg (t,i) < ThSg (i+1) for unit g production change (MW) over time period t deemed damaging for unit g j th production change (MW) over time period t deemed damaging for unit g N. Troy ([email protected]), D. Flynn ([email protected]) and M. O’Malley ([email protected]) are with the School of Electrical, Electronic and Communications Engineering, University College Dublin, Ireland. Michael Milligan is with the National Renewable Energy Laboratory, Golden, CO 8041 USA (email: [email protected]). This work was conducted in the Electricity Research Centre, University College Dublin, Ireland, which is supported by the Commission for Energy Regulation, Bord Gais Energy, Bord na Mona Energy, Cylon Controls, EirGrid, the Electric Power Research Institute (EPRI), ESB Energy International, ESB Energy Solutions, ESB Networks, Gaelectric, SSE Renewables, and Viridian Power & Energy. This publication has emanated from research conducted with the financial support of Science Foundation Ireland under Grant Number 06/CP/E005. costR g ThR g (i) costR g (i) Ig j̄g P̄g Pg Ag NLg Flg Tlg U Tg DTg T̄ Tgcold ccg hcg hup hdown M α, β, γ Cycling cost increment for unit g for each additional ramp > Rg ith threshold corresponding to cumulative ramps for unit g Cycling cost increment for unit g for each R additional ramp, while NR g (t,i) < Thg (i+1) Total number of intervals in cycling cost function for unit g Number of ramp levels defined for unit g Maximum capacity for unit g Minimum capacity for unit g Fixed cost for unit g ($/h) Number of segments in piecewise linearization of the variable cost function for unit g Slope of segment l of the variable cost function for unit g Upper limit of block l of the piecewise linear production cost function of unit j (MW) Minimum up time for unit g Minimum down time for unit g Number of hours in the planning period Number of hours unit g must be offline, beyond its minimum downtime, before it is considered to be in a cold state Cold start-up cost for unit g Hot start-up cost for unit g Number of hours unit g has been online for at start of planning period (h) Number of hours unit g has been offline for at start of planning period (h) Large number Scaling factors Binary Variables sg (t) zg (t) vg (t) stepSg (t, i) rg (t) rg (t, j) stepR g (t, i) equal to 1 when a unit starts up at time t equal to 1 when a unit shuts down at time t equal to 1 when a unit is online at time t equal to 1 when NS (t,1) ≥ ThS (i) at time t equal to 1 when a unit undergoes ramp > Rg between time t − 1 and t equal to 1 when a unit undergoes ramp > Rg (j) between time t − 1 and t equal to 1 when NS (t,1) ≥ ThR (i) at time t Positive Variables NSg (t) NSg (t,i) Cumulative start-ups for unit g Cumulative start-ups for unit g beyond threshold ThSg (i) 2 CSg (t) NR g (t) NR g (t,i) CR g (t) cpg (t) csg (t) pg (t) D(t) δl (g,t) Total cycling cost attributed to start-ups for unit g Cumulative ramps > Rg for unit g Cumulative ramps > Rg beyond threshold ThR (i) for unit g Total cycling cost attributed to ramping for unit g Production cost for unit g at time t Start-up fuel cost for unit g at time t Output (MW) for unit g at time t System demand (MW) at time t Power produced in block l of the piecewise linear production cost function of unit g at time t (MW) I. I NTRODUCTION I NCREASED competition in the electricity generation sector coupled with the large-scale deployment of variable renewable energy sources, particularly wind power, has led to increased plant cycling in power systems worldwide [1], [2]. Cycling may be defined as frequent start-ups or ramping of units. Some generation types (such as hydro or even opencycle gas turbines) are more suited to frequent cycling, but for others, particularly units designed for base-load operation, cycling can accrue large levels of damage within the plant’s components leading to increased maintenance requirements and forced outage rates. Thermal shock, metal fatigue, corrosion, erosion and heat decay are common damage mechanisms that result from cycling operation [3]. The wear-and-tear which arises incurs increased maintenance costs for generators, but in addition to this, loss of revenue due to more frequent and longer outages, increased fuel costs due to more frequent startups and reduced plant efficiency, as well as additional capital costs due to component replacement can also be expected. Studies indicate that the magnitude of these cycling related costs are high, but accurately quantifying them is challenging [4], [5]. The level of wear-and-tear for a unit that undergoes cycling operation will be dependent on many factors including the operating history of the plant (i.e. how much creep damage it has accumulated), and the engineering design of the plant. It is also typical to see a time lag of several years from when cycling occurs to when the damage manifests itself [6]. Research related to the cost of generation cycling has been undertaken by EPRI and Intertek Aptech and the approaches employed can be categorized as top-down (statistical analysis) or bottom-up (component modeling). EPRI carried out a top-down study utilizing multivariate regression models to analyze the operating regimes of 158 units from NERC (North American Electric Reliability Corporation) GADS (Generating Availability Data System) and CEMS (Continuous Emission Monitoring) data in an attempt to identify patterns relating plant operation to capital expenditure. However, the inconsistency in accounting practices between the units complicated the modeling and no correlation was found [7], [8]. Intertek Aptech employ a combination of top-down models based on historical operations, forced outage and cost data as well as bottom-up methods which calculate operational stresses and the life expenditure of critical components to determine cycling costs for individual generating units [4]. Intertek Aptech have analyzed cycling costs for over 300 generating units and found that the cost of cycling a conventional fossil-fired power plant can be as much as $2,500-500,000 per start/stop cycle depending on unit age, operating history and design features, and are often grossly underestimated by utilities [4], [6]. Not considering these costs, however, will result in an uneconomic plant dispatch, yet markets currently do not include specific cycling cost components in their bidding mechanisms, or at best cycling costs are bundled into a generator’s startup or operating costs. Depending on the operating regime of a plant, these cycling related costs can accumulate rapidly and are therefore dissimilar to plant characteristics such as heat rate, which typically vary over a much longer time-scale. Therefore, to examine the impact of these costs accurately, they should be modeled in a dynamic manner such that they accumulate within the optimization process based on how the unit is being operated and thereby can influence dispatch decisions. This paper presents a novel formulation to dynamically model these cycling costs, which can be integrated into a MIP (mixed integer programming) unit commitment and economic dispatch model. This facilitates more accurate modeling of these costs and examination of how they accumulate in line with the operating regime of the plant. The formulation defines a cycling cost which increments with each additional plant start-up or ramp with the resulting cost function being linear, piecewise linear or step-shaped. A case study is included to determine how implementing dynamic cycling costs for a test system over a period of one year will affect the resulting dispatch, relative to a scenario where cycling costs are not considered. This new approach to modeling cycling costs is particularly suitable for long-term planning studies where it can be used to reflect the ageing effect on a plant over time. It may also have applications for real-world market models where it can discourage the same unit from being repeatedly dispatched to cycle by incurring an incremental cost to reflect the wear-and-tear to that unit, which can consequently alter its position in the merit order. The paper is organized as follows: Section II details the formulation of dynamic cycling costs, Section III describes a unit commitment model and economic dispatch model used to implement the dynamic cycling cost formulation and also describes the test system, Section IV details the results of the case study and Section V summarizes the findings. II. F ORMULATION OF DYNAMIC C YCLING C OSTS A detailed formulation for implementing dynamic cycling costs which increase in line with unit operation is presented. Cycling costs are subdivided into costs for (A) start-ups and (B) ramps. The formulation utilizes three main steps: (i) a binary variable is set to indicate that damaging operation has occurred at time step t, (ii) a counter tracks how much of that type of operation has occurred up to that point, and (iii) an incrementing cycling cost is incurred at that time step. Linear, piecewise linear and step-shaped cost functions for both starts and ramps are detailed here. 3 A. Cycling costs related to start-ups Linear: Constraints 1-3 allow a dynamic, linearly incrementing cost for wear-and-tear related to start-ups to be modeled. Based on the online binary variable, vg (t), constraint 1 sets the start-up, sg (t), and shut-down, zg (t), binary variables equal to 1 appropriately, when unit g is started up or shut down at time t. Constraint 2 increments a counter, NgS (t), to track how many start-ups have been performed by that unit. Constraint 3 determines the start-up related cycling cost, CgS (t), with the final term ensuring that a cost is only incurred when the decision is made to start the unit at time t (i.e. sg (t) = 1). Figure 1 provides an example of this linearly increasing cost function, where the cycling cost increment costSg is set equal to 100. (It is also possible to initialize the counter NgS (t) with the number of starts that have been carried out previously if this is known). sg (t) − zg (t) = vg (t) − vg (t − 1), ∀ t ∈ T, ∀ g ∈ G (1) NgS (t) ≥ NgS (t − 1) + sg (t), ∀ t ∈ T, ∀ g ∈ G (2) ¡ ¢ CgS (t) ≥ NgS (t).costSg − M. 1 − sg (t) , ∀ t ∈ T, ∀ g ∈ G (3) CgS (t) ≥ ¶ Ig µ X ¡ ¢ NgS (t, i). costSg (i) − costSg (i − 1) i Fig. 2. ¡ ¢ − 1 − sg (t) .M, ∀ t ∈ T, ∀ g ∈ G (5) Piecewise linearly increasing start-up related cycling cost Step Function: Alternatively, if less information is known regarding the shape of the cost function an appropriate simplification may be to define a step function, where CgS (t) does not increment until T hSg (i) is reached. Again, it is required that T hSg (1) is equal to 1. NgS (t, i) is determined by constraint 6 and in this case can be greater than or less than 0 (it was previously defined as a positive variable only). Constraint 7 sets the binary variable stepSg (t, i) equal to 1 when NgS (t, i) has exceeded T hSg (i), and constraint 8 determines the cycling cost. Figure 3 provides an example of this incrementing, stepshaped cost function, where costSg (t, 1) is set equal to 100, costSg (t, 2) is set equal to 150 and T hSg (2) equals 4. NgS (t, i) = µ ¶ NgS (t − 1, 1) + sg (t) + 1 − T hSg (i), (6) ∀ t ∈ T, ∀ g ∈ G, ∀ i ≤ Ig Fig. 1. NgS (t, i) − stepSg (t, i).M ≤ 0, Linearly increasing start-up related cycling cost ∀ t ∈ T, ∀ g ∈ G, ∀ i ≤ Ig Piecewise Linear: By defining i thresholds, T hSg (i), each corresponding to a cumulative number of plant start-ups, at which point the start-up related cycling cost, CgS (t), will increase by incremental cost costSg (i) for each additional start, a piecewise linear incremental cost function can be modeled. Constraint 4 is a modified form of constraint 2 which counts the cumulative number of start-ups. For i > 1, the start-up counter, NgS (t, i), will not have a positive value until NgS (t, 1) has reached T hSg (i). T hSg (1) must equal 1. Constraint 5 determines the total cycling cost. Figure 2 provides an example of a piecewise linearly increasing cost function, where costSg (1) is set equal to 100, costSg (2) is set equal to 150 and T hSg (2) equals 4. NgS (t, i) ≥ µ ¶ NgS (t − 1, 1) + sg (t) + 1 − T hSg (i), ∀ t ∈ T, ∀ g ∈ G, ∀ i ≤ Ig (4) CS (t) ≥ costSg (i).stepSg (t, i) − ¡ ¢ 1 − sg (t) .M, ∀ t ∈ T, ∀ g ∈ G, ∀ i ≤ Ig Fig. 3. Step increasing start-up related cycling cost (7) (8) 4 TABLE I A NALOGOUS T ERMS Hot and Cold Starts: Either the linear, piecewise linear or step formulations can be extended to differentiate between hot and cold start-ups for units. Constraint 9 will set the binary variable scold (t) equal to 1 only if unit g is started at time g t, having been offline for Tgcold plus its minimum downtime, DTg . In constraints 2, 4 and 6 ‘+ sg (t)’ is replaced with ‘+ sg (t) + α.scold (t)’. A scaling factor, α, is chosen based on g the ratio of cycling damage caused by a hot start relative to a cold start, and thus normalizes NgS (t, i) to count in terms of hot starts. X Piecewise Linear & Step vg (t − n), ∀ t ∈ T, ∀ g ∈ G n=1 (9) B. Cycling costs related to ramping 1) Define one ramp level: The simplest form of incurring cycling costs related to ramping duty is to define a change in output, Rg , between consecutive time periods, greater than which, damaging transients will occur within unit g. Constraints 10 and 11 ensure that the binary variable r(t) is set to 1 when a change in output exceeding Rg occurs. To avoid double counting cycling costs when large ramps are experienced in the start-up or shut-down process, the final term ensures that the constraints are non-binding when the unit is in the start-up or shut-down process. If the ramp-related cycling costs are likely to exceed the start-up or shut-down cost, constraint 12 is needed to prevent the model setting s(t) and z(t) both equal to 1 in constraint 1, in order to make constraints 10 and 11 non-binding. ¡ ¢ pg (t) − pg (t − 1) − M.rg (t) ≤ Rg + M.sg (t), ∀ t ∈ T, ∀ g ∈ G ¡ ¢ pg (t − 1) − pg (t) − M.rg (t) ≤ Rg + M.zg (t), ∀ t ∈ T, ∀ g ∈ G sg (t) + zg (t) ≤ 1, ∀ t ∈ T, ∀ g ∈ G (10) (12) Utilizing the binary variable, rg (t), a counter NgR (t) is defined, as before, to incur an incrementing, ramp-related cycling cost, CgR (t). Using the formulation from Section II.A, the ramp-related cycling cost function may be linear, piecewise linear or step-shaped. Constraints 2 and 3 are replaced with the analogous ramp terms shown in Table I to implement a linearly incrementing cost. Constraints 4 and 5, or 6 to 8, are replaced with the analogous ramp terms as shown in Table I to define a piecewise linear, or step shaped, incrementing ramp related cycling cost respectively. 2) Define multiple ramp levels: The previous formulation, where one level Rg is set to define a ramp, can be expanded to incur a dynamic ramp-related cycling cost, for j ramps of different magnitudes, Rg (j). Constraint 13 ensures that for a ramp less than Rg (1), the binary variable rg (t, j) will equal zero for all j. A ramp greater than Rg (1), but less than Rg (2), will set rg (t, 1) equal to one, and so forth. The final term rg (t) costR g (t) NR g (t) CR g (t) sg (t) costS g (t,i) NS g (t,i) ThS g (t,i) CS g (t) stepS g (t) rg (t) costR g (t,i) NR g (t,i) ThR g (t,i) CR g (t) stepR g (t) ensures that the constraint is non-binding when the unit is starting up. A¡ corresponding constraint is needed for down ¢ ramps, where p (t) − p (t − 1) in constraint 13 is replaced g g ¡ ¢ with pg (t−1)−pg (t) and M.sg (t) is replaced with M.zg (t). Constraint 14 ensures that the binary variable, rg (t, j), which indicates that a ramp ≥ Rg (j) has occurred, can only have a value of 1 for one ramp level j, at any given time. As before, constraint 12 is required to prevent sg (t) and zg (t) both being set to 1, to make constraint 13 and its corresponding down ramping constraint non-binding. j X ¢ ¡ ¢ ¡ rg (t, j) pg (t) − pg (t − 1) < Rg (1). 1 − j=1 + Rg (2).rg (t, 1) + ... + Rg (j).rg (t, j − 1) + P¯g .rg (t, j) + M.sg (t), where Rg (1) < Rg (2) < Rg (j)... < P¯g , ∀ t ∈ T, ∀ g ∈ G, ∀ j ≤ j̄g j X (11) Ramps sg (t) costS g (t) NS g (t) CS g (t) Linear Tgcold +DTg (t) ≥ vg (t) − scold g Starts rg (t, j) ≤ 1, ∀ t ∈ T, ∀ g ∈ G, ∀ j ≤ j̄g (13) (14) j=1 As with hot and cold starts, scaling factors are used to normalize NgR (t) to count in terms of one ramp level, as shown in constraint 15, where r(t, j) is expressed in terms of r(t, 1). Constraint 16 determines the total ramp-related cycling cost, shown here with a constant cost increment, costR g , with the final term ensuring that the cost is only incurred in a time period when a ramp (> Rg (1)) occurs. NgR (t) = NgR (t − 1) + rg (t, 1) + β.rg (t, 2) +.... + γ.rg (t, j), ∀ t ∈ T, ∀ g ∈ G, ∀ j ≤ j̄g CgR (t) ≥ NgR (t).costR g j X ¡ ¢ − 1− rg (t, j) .M j=1 (15) (16) ∀ t ∈ T, ∀ g ∈ G, ∀ j ≤ j̄g To combine this formulation of j ramp levels with i cost thresholds (i.e piecewise linear) constraints 15 and 16 are replaced by constraints 17 and 18, such that once NgR (t, i) R R reaches T hR g (i), Cg (t, i) will begin incrementing by costg (i). 5 NgR (t, i) = ¡ NgR (t − 1, 1) + rg (t, 1) + β.rg (t, 2) ¢ +.... + γ.rg (t, j) + 1 − T hR g (i) (17) ∀ t ∈ T, ∀ g ∈ G, ∀ j ≤ j̄g , ∀ i ≤ Ig CgR (t) ≥ − ¶ Ig µ X ¡ ¢ R NgR (t, i). costR (i) − cost (i − 1) g g i j X Start-up costs which were dependent on the period of time the unit had been offline were modeled as follows: ¡ ¢ csg (t) ≥ vg (t) − vg (t − 1) .hcg ∀ t ∈ T, ∀ g ∈ G (29) csg (t) ≥ vg (t) − X ¢ vg (t − n) .ccg , n=1 (18) To include a step-shaped ramp related cycling cost function, constraints 6-8 are replaced with the analogous terms for ramping from Table 1. Minimum up time constraints were formulated by constraints 31, 32 and 33. Equation 31 is only included if the number of hours a unit must remain online to satisfy its minimum up time, Bg , is greater than or equal to 1. t≤Bg X ¡ III. D ISPATCH M ODEL AND T EST S YSTEM ¢ 1 − vg (t) = 0, ∀ g ∈ G cpg (t) + csg (t) + CgS (t) + CgR (t) (19) t∈T g∈G t+U Tg −1 X vg (n) ≥ U Tg .sg (t), ∀ g ∈ G n=t pg (t) = D(t), ∀ t ∈ T (20) pg (t) ≤ P̄g .vg (t), ∀ t ∈ T (21) pg (t) ≥ P g .vg (t), ∀ t ∈ T (22) (32) ∀ t = Bg + 1...T̄ − U Tg + 1 T̄ X ¡ ¢ vg (n) − sg (t) ≥ 0, ∀ g ∈ G n=t subject to X (31) t To examine how cycling costs, modeled dynamically, will impact plant dispatch the new formulation was implemented in a conventional MIP unit commitment model based on [9], [10]. The unit commitment problem was formulated as XX (30) ∀ t ∈ T, ∀ g ∈ G rg (t, j).M, ∀ t ∈ T, ∀ g ∈ G, ∀ j ≤ j̄g j=1 M inimize Tgcold +DTg ¡ (33) ∀ t = T̄ − U T + 2...T̄ ¢ where Bg = max 0, vg (T)U Tg -hup g +vg (T) ¡ g∈G As per [9], a piecewise linear approximation of a quadratic production cost function for each unit was adopted, as represented by: Minimum down time constraints were formulated using constraints 34, 35 and 36. Equation 31 is only included if Lg ≥ 1. t≤Lg X¡ cpg (t) = Ag vg (t) + t+DTg −1 X Flg δl g(t), ∀ t ∈ T, ∀ g ∈ G (23) δl g(t) + P g vg (t), ∀ t ∈ T, ∀ g ∈ G (24) l=1 T̄ X ¡ 1 − vg (n) − zg (t) ¢ ≥ 0, ∀ g ∈ G n=t δ1 (g, t) ≤ T1g − P g , ∀ t ∈ T, ∀ g ∈ G (25) δl (g, t) ≤ Tlg − Tl−1g , ∀ t ∈ T, ∀ g ∈ G, ∀ l = 2..N Lg − 1 (26) δN L (g, t) ≤ P̄g − TN Lg −1 − Tl−1g , ∀ t ∈ T, ∀ g ∈ G (27) δl (g, t) ≥ 0, ∀ t ∈ T, ∀ g ∈ G, ∀ l = 1..N Lg where Ag = ag + bg P g + (35) ∀ t = Lg + 1...T̄ − DTg + 1 N Lg X vg (n) ≥ DTg .zg (t), ∀ g ∈ G n=t l=1 pg (t) = (34) t N Lg X ¢ vg (t) = 0, ∀ g ∈ G cg P 2g . (28) ¡ (36) ∀ t = T̄ − DT + 2...T̄ ¢ where Lg = max 0, (1 − vg (T)).DTg − hdown +(1 − vg (T)) g The formulation was applied to the 10 unit test system used in [9], [11], which was duplicated to give a 20 unit system, thus facilitating a larger case study. The peak demand (1500 MW) was doubled (3000 MW) and a historical year-long hourly demand profile for the Irish system was scaled to produce a demand profile with a 3000 MW peak. The model was run for the test year, optimizing each day at an hourly resolution. Generator cycling costs are difficult to determine and largely uncertain, as discussed in Section I. The figures used here, 6 shown in Table II, to implement dynamic cycling costs for the test system, are conservatively based on those in [12] and are intended to illustrate how dynamic cycling costs could impact system operation, rather than provide an accurate estimate of such costs. Piecewise linear costs for starts and ramps were implemented with the incremental cost (costSg (i) or costR g (i)) increasing by 10% and 20% when the start counter (NgS (t, 1)), or ramp counter (NgR (t, 1)), exceeded 100 (T hSg (2) or T hR g (2)) and 200 (T hSg (3) or T hR g (3)) respectively. The scaling factor, α, was chosen to be 2, i.e. each cold start incremented NgS (t, 1) by 2 (while a hot start incremented NgS (t, 1) by 1). Two ramp levels, Rg (1) and Rg (2) corresponding to 20% and 40% of the difference between maximum and minimum output for a unit, were modeled. Scaling factors were chosen such that ramps greater than Rg (1) or Rg (2) incremented NgR (t, 1) by 1 or 2 respectively. related to plant start-ups was also found to have the knock on effect of increasing generator ramping. Over the year a 22% increase in ramping (NgR (t, 1)) was observed relative to the case when no cycling costs were modeled as generators were more frequently ramped down to minimum output, rather than shut-down, in an effort to avoid incurring cycling costs for starting up. TABLE III I MPACT OF DYNAMIC CYCLING COSTS FOR START- UPS ON TOTAL ANNUAL STARTS Units Base-load (Units 1-4) Mid-merit (Units 5-10) Peaking (Units 11-20) Total No cycling costs modeled Cycling cost for starts modeled 34 1372 577 1983 12 1005 838 1855 TABLE II I NCREMENTAL CYCLING COSTS $, ( I =1) Units costS g (i) costR g (i) 1-4 5-10 11-20 300 60 30 15 3 1.5 IV. R ESULTS This section examines how plant dispatches for the test system are affected over one year when (i) a cycling cost related to start-ups is implemented, (ii) a cycling cost related to ramping is implemented, and (iii) cycling costs related to start-ups and ramping are implemented simultaneously. TABLE IV I MPACT OF DYNAMIC CYCLING COSTS FOR START- UPS ON AVERAGE PLANT CAPACITY FACTORS (%) Units Base-load (Units 1-4) Mid-merit (Units 5-10) Peaking (Units 11-20) No cycling costs modeled Cycling cost for starts modeled 92.59 27.82 0.85 92.73 25.42 2.23 A. Start-up Related Cycling Costs Results Implementing a dynamic cycling cost for plant start-ups, as shown in Table II, was seen to result in an overall reduction in plant start-ups. This is seen in Table III, which reveals reducing starts for base-load and mid-merit units. For base-load units, the reduction in starts was correlated with increased production as, having the largest incremental cycling costs, these units avoided shut-downs and their online hours increased. This is evident through the average capacity factor shown in Table IV. Mid-merit units, however, which also had reduced starts, saw reduced production indicating that they were utilized less often. As these units were started up and shut down, and subsequently incurred cycling costs, it became more economical after some point to dispatch peaking units. Thus, starts and production increased for peaking units when a dynamic cycling cost for start-ups was modeled. Figure 4 illustrates the cumulative start-ups for the mid-merit and peaking units over the year when (i) cycling costs were modeled and (ii) when cycling costs were not modeled. Starts are seen to accumulate rapidly between 0 and 2000 hours and for hours greater than 7000, as these are the winter months and thus have higher demand, requiring more plant start-ups. Beyond 1000 hours the cycling costs which are accumulated by midmerit plant begin to have an effect on their position in the merit order and consequently peaking plant are seen to be dispatched more frequently. Modeling dynamic cycling costs Fig. 4. Cumulative plant start-ups over the year, shown when dynamic cycling costs for starts were (i) modeled and (ii) not modeled Units within the same class, i.e. base-load, mid-merit or peaking, were also seen to converge to a similar number of annual start-ups, as indicated by the reduced standard deviation of annual start-ups seen in Table V. This indicates that once a unit has been cycled and its cycling cost is incremented, the next time a unit needs to be cycled the costs will have now changed such that a different unit (most likely the next in the merit order) may be scheduled. This leads to the burden of cycling operation being more evenly distributed across the units. Over a long horizon, i.e. several years, this effect can lead to a shift in the merit order, a trend which can be seen in Figure 4. To facilitate a sensitivity analysis, multiples of the initial incremental cycling costs, costSg (1), shown in Table II, were also examined. As the incremental cost was increased the reduction in start-stop cycling that is achieved by modeling 7 TABLE V I MPACT OF DYNAMIC CYCLING COSTS FOR START- UPS ON TOTAL ANNUAL STARTS Units Base-load (Units 1-4) Mid-merit (Units 5-10) Peaking (Units 11-20) No cycling cost modeled Avg. Std. Dev. 8.5 9.9 228.7 75.7 57.7 73.1 Cycling cost for starts modeled Avg. Std. Dev. 3 3.6 167.5 26.1 83.8 27.5 that all units reflect their cycling costs, or do not, to avoid the situation where only some generators are bidding cycling costs as this leads to inefficient operation and excessive costs. TABLE VII C HANGE IN STARTS WHEN A SUBSET OF UNITS BID CYCLING COSTS FOR START- UPS ∆ Starts Units 1, 2, 3, 4, 9, 10 All other units dynamic cycling costs quickly saturated as seen in Figure 5, thus indicating that the majority of plant cycling is unavoidable. Table VI shows a breakdown of the total number of starts by unit group, which again reveals that increasing starts for peaking units are correlated with increasing incremental cycling cost, as it becomes more favorable to dispatch these units due to the relatively larger cycling costs associated with the mid-merit units. (The ripples in the curve shown in Figure 5 result from the increasing starts for peaking units, as seen in Table VI.) -86 +256 B. Ramping Related Cycling Costs Results Fig. 5. Impact of dynamic cycling cost on total start-ups, shown for various multiples of costS g (i) Implementing a dynamic cycling cost for plant ramping (shown in Table II) resulted in a 90% reduction in ramping overall, as seen in Table VIII. As described previously, assuming a ramp greater than 20% or 40% of the difference between a unit’s maximum and minimum output increments the ramp counter, NgR (t), by a value of 1 or 2 respectively. The total value of NgR (t) at the end of the test year, summed for all units, is shown in Table VIII. Base-load units which carried out the greatest amount of ramping when cycling costs were not modeled, saw the greatest reduction in ramping operation when cycling costs for ramps were implemented. The dramatic reduction in ramping that was achieved by implementing dynamic ramping costs, however, led to increased start-stop cycling as might be expected, although only by 3.3% over the year. The most notable change to the overall dispatch that resulted from the introduction of dynamic ramping costs was a slight reduction in production from base-load plant allowing for increased production from mid-merit and peaking units as seen in Table IX, thereby spreading the ramping requirement over more units. Thus, including the ramping cost was also seen to result in a slightly greater number of units online (5.94 per hour on average when dynamic ramping costs were modeled, versus 5.92 when no cycling costs were modeled). TABLE VI I MPACT OF DYNAMIC CYCLING COSTS FOR STARTS ON TOTAL PLANT START- UPS , SHOWN FOR VARIOUS MULTIPLES OF costS g (i) TABLE VIII I MPACT OF DYNAMIC CYCLING COSTS FOR RAMPING ON TOTAL ANNUAL RAMPING (NgR (t, 1)) No cycling cost costS g (i)*0.5 costS g (i)*1 costS g (i)*2 costS g (i)*3 costS g (i)*10 Base-load (Units 1-4) Mid-merit (Units 5-10) Peaking (Units 11-20) 34 13 12 13 13 13 1372 1104 1005 941 907 869 577 781 838 896 948 992 A scenario where cycling costs were only modeled for a subset of the total fleet was also examined. The 6 largest units on the system (units 1, 2, 3, 4, 9, 10) were chosen based on the assumption that these units would be most impacted by cycling operation and thus most likely to bid a wear-andtear cost into the market if such an option was available. The results showed that although the number of annual start-ups was reduced for these units, the start-ups for the other units increased by a much greater amount as seen in Table VII. This would indicate the need for a uniform policy relating to the bidding of cycling costs to be implemented in markets, such Units Base-load (Units 1-4) Mid-merit (Units 5-10) Peaking (Units 11-20) Total ramping No cycling costs modeled Cycling cost for ramps modeled 3717 2214 795 6726 120 1224 623 1967 TABLE IX I MPACT OF DYNAMIC CYCLING COSTS FOR RAMPING ON AVERAGE PLANT CAPACITY FACTORS (%) Units Base-load (Units 1-4) Mid merit (Units 5-10) Peaking (Units 11-20) No cycling costs modeled Cycling cost for ramps modeled 92.59 27.82 0.85 92.21 28.61 1.02 C. Start-up and Ramping Cycling Costs Results Implementing dynamic cycling costs (as shown in Table II) for starts and ramping simultaneously, reduced both types 8 of cycling operation relative to the case when no cycling costs were modeled, as shown in Table X. Base-load units, having the largest cycling costs, see the greatest reductions in cycling operation. Nonetheless, neither total starts nor total ramps were reduced in this scenario as much as starts alone or ramps alone were reduced when cycling costs for starts or ramps were modeled individually. However, when cycling costs for start-ups only were modeled, ramping operation increased and likewise when cycling costs for ramping only were modeled, starts increased. Thus when the cycling costs that would have been incurred due to both start-ups and ramping are examined (assuming the costs given in Table II), the case in which cycling costs for start-ups and ramping were modeled simultaneously had the lowest overall cycling costs, as shown in Figure 6. This would indicate that modeling cycling costs for starts and ramping simultaneously is the most cost effective way to reduce cycling and as such one should not be considered without the other. TABLE X I MPACT ON TOTAL ANNUAL STARTS AND RAMPS WHEN DYNAMIC CYCLING COSTS FOR BOTH START- UPS AND RAMPING WERE MODELED Units Base-load (Units 1-4) Mid merit (Units 5-10) Peaking (Units 11-20) Total No cycling costs modeled Starts Ramps 34 3717 1372 2214 577 795 1983 6726 Cycling cost for starts and ramps modeled Starts Ramps 12 144 1003 2069 855 1456 1870 3669 Fig. 7. Total system costs shown for various scenarios being determined by the level of knowledge of the generator’s cycling costs. The formulation for piecewise linear incremental cycling costs related to plant start-ups and ramps was implemented for a test system. Although the incremental costs chosen are approximations, the results reveal certain trends that are likely for power systems where generators undergo regular cycling and reflect the resulting wear-and-tear costs in their bids. For example, dynamically modeling cycling costs for generator starts was seen to reduce the number of starts, but caused ramping operation to be increased (and vice-versa), whilst modeling cycling costs for only a subset of the generation fleet was seen to induce much higher levels of cycling in the remaining generation. It was also seen that as cycling costs accumulated over time changes in the merit order occurred, and that modeling cycling costs led to an overall saving for the system as cycling operation was subsequently reduced. R EFERENCES Fig. 6. Cycling costs (that would have been incurred) shown for various scenarios Finally, when total system costs are examined for the scenario including cycling costs and compared to the total system cost for the scenario in which cycling costs were not modeled, but were calculated and added afterwards, it can be seen that modeling cycling costs leads to lower system costs overall. This is shown in Figure 7. In this example, the cost saving seen is considerable i.e. 14%. V. C ONCLUSIONS Interest concerning cycling costs is growing and this paper sets out a formulation that can utilize knowledge of incremental wear-and-tear costs related to plant start-ups or ramping, to implement a dynamic incrementing cycling cost. The formulation covers linear, piecewise linear and stepshaped cycling cost functions, the appropriate choice for a user [1] L. Göransson, and F. Johnsson, “Large scale integration of wind power: moderating thermal power plant cycling”, Wind Energy, vol. 14, no. 1, pp. 91-105, 2011. [2] N. Troy, E. Denny and M. O’Malley, “Base-load cycling on a system with significant wind penetration”, IEEE Transactions on Power Systems, vol. 25, issue 2, pp. 1088 - 1097, 2010. [3] “Damage to Power Plants Due to Cycling”, EPRI, Palo Alto, CA, 2001. [4] Editorial, “Profitable Operation Requires Knowing How Much it Costs to Cycle your Unit,” Combined Cycle Journal [online], Spring 2004, available: http://www.combinedcyclejournal.com/ [5] S. Lefton, “Profitable Operation Requires Knowing How Much it Costs to Cycle your Unit”, Combined Cycle Journal, pp. 49-52, Second Quarter, 2004. [6] S. Lefton, P. Besuner, P. Grimsrud, A. Bissel and G. Norman, “Optimizing power plant cycling operations while reducing generating plant damage and costs at the Irish Electricity Supply Board”, Aptech Engineering Service, Tech. Rep. 123, Sunnyvale, CA, 1998. [7] “Determining the Cost of Cycling and Varied Load Operations: Methodology”, EPRI, Palo Alto, CA: 2002. 1004412. [8] “Correlating cycle duty with cost at fossil fuel power plants”, EPRI, Palo Alto, CA: 2001. 1004010. [9] M. Carrion and J.M. Arroyo, “A computationally efficient mixed-integer linear formulation for the unit commitment problem”, IEEE Transactions on Power Systems, vol. 21, no. 3, pp. 1371 - 1378, 2006. [10] J.M. Arroyo and A.J. Conejo, “Optimal response of a thermal unit to an electricity spot market”, IEEE Transactions on Power Systems, vol. 15, no. 3, pp. 1098 - 1104, 2000. [11] S.A. Kazarlis, A.G. Bakirtzis and V. Petridis, “A genetic algorithm solution to the unit commitment problem”, IEEE Transactions on Power Systems, vol. 11, no. 1, pp. 83-92, 1996. [12] S. Lefton, P. Besuner, D.D. Agan, “The real cost of on/off cycling”, Modern power systems, vol. 26, no. 10, 2006.
© Copyright 2025 Paperzz