PepsiCo’s ice tea production and filling plant in the south of Moscow is
regarded as one of the most modern plants in Russia. One reason for this:
The plant’s operator decided to implement a centralized power distribution
concept that boasts an extremely high level of uniformity.
M
sion the power distribution system,
including all of its components, during
the three-week conception phase.
Planning tools for complete solutions
In addition to automatic dimensioning,
during which the software suggests suitable components for the power distribution system, Simaris design also makes it
possible to respond to parameter changes
that occur during the planning process.
In this way, the tool checks the effect that
these changes have on other parts of the
plant and dimensions the resulting
changes. Both this high level of flexibility
and uniformity and
the convenient and
fast selection, dimensioning, and determination of set
values won over
those in charge at
PepsiCo. Even the short-circuit calculation, including all set values for the trip
units in the circuit breakers, was completed within a week.
The space available was limited, which
meant that the solutions could not be
selected based solely on the energy values. Three GEAFOL cast resin transformers of 5 MVA each now provide the
400 V low voltage required by the plant
from the 20 kV medium-voltage supply.
Thanks to their two-tier design, these
transformers require relatively little
installation space. They are also very
reliable in operation and have a long
service life. An NXplus C gas-insulated
medium-voltage switchgear system was
used as in infeed for the 20 kV mediumvoltage supply. This type-tested system
is smaller, very reliable in operation,
and maintenance-free – all essential
advantages compared to air-insulated
versions.
Fotolia
All Photos: Siemens AG
oscow is Europe’s largest urban
agglomeration. In 2007, PepsiCo
planned a new, approximately
300 m long filling plant in the south of
the city, in order to supply beverages to
the city’s population of around 10.6 million and to the roughly 14.6 million
inhabitants of the surrounding area.
When expanded to full capacity, up to
seven different production lines can be
used to fill bottles and cans with different drinks. In the first stage of expansion, production capacities and three
production lines were put in place for
filling cans and PET bottles with ice tea.
PepsiCo decided during the planning
phase that the power distribution should have a “one-piece”
infrastructure. The Simaris
design Totally Integrated
Power (TIP) software
made it possible to
plan and dimen-
The power distribution system in PepsiCo’s new production plant in the
south of Moscow was planned in a “one-piece” design using the Simaris
design software
16 E-Installation | 02-2011
Switchgear system for
high security requirements
can be changed around in no time at all ticularly energy-efficient in operation.
thanks to a special interlocking system, Empirical values show that the low voltallowing the doors to be individually age drop, starting at approximately
The Simaris design planning software adapted on site if space is restricted. 1600 A, has a positive effect on the
made it very easy to simulate the central The low-voltage power distribution sys- energy balance.
power supply. The single infeed reduces tem was designed, completely assemThe consumption values required for
the number of devices required and the bled, and tested according to the appli- energy management are measured by the
amount of installation work required – cable standards at the Siemens factory 3WL circuit breakers, but also by the
which, however, makes reliability in in Leipzig. This earned it the GOST cer- PAC3200 multimeters. These are capable
operation, availability and redundance tificate that is required in Russia.
of measuring over 50 measured values.
especially important. for this reason,
Their communication capability via
the planners chose type-tested Sivacon Flexible and energy-efficient:
Profibus/Profinet means that they can
S8 low-voltage switchgear systems: Busbar trunking
also be easily integrated into a higherThese deliver extremely high levels of
level control system.
+
plant safety through type-tested stan- The decision-makers at PepsiCo decided
dard modules (TSK) and personal safety to use the Sivacon 8PS busbar trunking
thanks to an arc fault-proof interlocking system for the power distribution to the
system.
consumers. The LDA system impleThe type-tested TSK standard modules mented in the PepsiCo plant is suitable
TIP highlights
include 3WL circuit breakers for cur- for currents ranging from 1100 A to
rents of up to 6300 A. In the PepsiCo 5000 A. The benefits of TIP’s system uni++ Uniform software tools for
plant, circuit breaker sizes for up to formity were also visible here: Connecplanning and configuration
4000 A were used. The set values for the tion pieces are available for direct conoverload and short-circuit protection nection of the LDA busbars to the
++ Products and systems
could be transferred directly from the Sivacon S8 low-voltage switchgear syscoordinated with each other –
Simaris design software. In this way, the tem.
from the medium-voltage
selectivity that is required for the plant
The flexibility in laying the LDA busswitchgear system through to
to be operated safely is achieved. An bars with a length of approximately 300
the socket outlet
additional motorized operating mecha- meters is especially beneficial in proj++ Connection to the building
nism also allows the 3WL circuit break- ects of this size. The setup of the busautomation/industrial
ers to be switched remotely, and they bars can be adapted to the structure of
automation system via
can be integrated into the plant’s control the building using connection pieces,
communication-capable
system, and thus into the central energy and feeders to supply power to the
switches and modules
management, via an additional commu- machines can be connected at intervals
of one meter if changes in production
nication module.
The high level of flexibility provided occur. Wall penetrations can be made
by Sivacon S8 is especially important in more precisely and safely than with
large projects and in projects where an sheathed copper wires. The fire load is
overview is hard to maintain. The indi- also significantly lower with busbar
Link to this topic:
vidual panels can be arranged as desired, trunking systems, which are communi+www.siemens.com/tip
even at a later date, as the main busbars cation-capable using either instabus
Contact:
are connected together in a segmented KNX, AS-Interface, or Profibus. This
[email protected]
fashion. The door hinges of the panels type of solution has proven to be par-
The type-tested Sivacon S8 low-voltage switchgear system
fulfills the requirements of the GOST certification
When expanded to full capacity, up to seven different production lines
can be used to fill bottles and cans with drinks