Energy storage: how an abandoned goldmine will be converted into

Energy storage: how an abandoned goldmine
will be converted into a world first
Australia has no plan for managing disused mines but a company has a novel
solution for producing renewable energy
A hydroelectric pumped storage power plant. Pumped hydro is the most affordable
and widely used form of industrial-scale energy storage globally. Photograph: Roman
Rybaleov/Getty Images/iStockphoto
Myles Gough
Monday 12 September 2016 – THE GUARDIAN
Gold was discovered on the Copperfield river in north-western Queensland
in 1907. As men flocked to find their fortune, a small township was
established and named for the state’s then premier, William Kidston. For
close to 100 years, Kidston was a mining town.
But, in 2001, the largest operation – a Canadian-owned goldmine – shut
down. The site became another of the roughly 50,000 “orphaned” mines
littered across Australia.
Photographs of the disused site show the prominent scars of human
activity: two adjacent craters, 300m deep. But in those voids lies an
opportunity.
Today, the site is coincidentally in the custody of the great-great-grandson
of the former Queensland premier. Simon Kidston is the executive director
of Genex, an ASX-listed company with plans to reuse the massive craters on
site for a world-first pumped hydroelectric energy storage (PHES) system,
combined with an integrated solar farm.
“We’re not aware of any examples anywhere else in the world where there
is a large pumped storage system, or any efficient storage mechanism, with
a renewable generation component attached to it – not on the scale we’re
talking about,” Kidston says.
Pumped hydro is the most affordable and widely used form of industrialscale energy storage globally, accounting for nearly 99% of the market. It
provides an option to store intermittent renewable energy from wind and
solar, and instantly dispatch it to the grid during periods of peak demand,
or in the event of an unplanned network outage.
A 50 megawatt (MW) solar farm is already under construction and is
scheduled for completion by the end of 2017. It will cost roughly $100m
and will generate 145,000 megawatt hours (MWh) per year, or enough
energy to power some 27,500 homes, Kidston says.
Stage two of the project is a 300MW PHES. This will operate for sevenhour generation cycles once each day, delivering a maximum of 2250 MWh
to the grid.
All that’s needed for a PHES are two reservoirs at different heights,
typically between 100m and 1,000m, and a way to pump water between
them. This difference in elevation is known as the “water head” and, along
with the volume of water stored in the upper reservoir, determines the
system’s potential energy.
When demand is low, electricity is sourced from the grid to pump water to
the higher reservoir. When the energy needs to be recovered, the water is
released. As it flows back down to the lower reservoir through a tunnel or
pipe, it drives a turbine in an underground powerhouse, which converts it
to electricity.
It’s estimated that the Genex system will have an average water head of
190m and will shift 5 million cubic metres of water, or the equivalent of
2,000 Olympic swimming pools, for each generation cycle.
There are hundreds of PHES systems worldwide and three in Australia. But
these three systems are linked with on-river hydroelectric facilities. The
Genex project will be the first large-scale, “off-river” solution. This means
the same water cycles continuously through the two reservoirs in a closed
loop, without being discharged. This minimises environmental impacts.
A satellite image of the Kidston site. the two large mine pits are in close
proximity, with water already inside, and a dam nearby with a pipeline to
the site. Photograph: Genex
“We realised environmental issues would prevent damming of rivers in
mountains, where most hydro is located,” Kidston says. “And we also
wanted to pursue a low-cost development strategy.”
The company took notice of some international projects using closed mine
sites and Kidston recalled the story of his great-great grandfather. “That
was just a seed in the back of my head and, when we first started thinking
about this concept, it emerged and we investigated it.”
The site and infrastructure left behind at Kidston were a perfect fit: the two
large mine pits are in close proximity, with water already inside, and a dam
nearby with a pipeline to the site. This will enable access to additional water
in case of drought, as the company already has a licence in place to draw up
to 4,600 megalitres per year.
There is a transmission line and substation on site, as well as good road
access, an airstrip and a camp for accommodating construction workers.
There’s also plenty of sunshine for solar generation and durable rocks
inside the pits, which won’t degrade with changing water levels, Kidston
says.
By leveraging the existing infrastructure and permits, Genex could save
hundreds of millions of dollars. Most conventional PHES systems cost
between $4m and $5m per installed megawatt to build, he says. By
comparison, Genex is projecting that its 300MW facility will cost just $1m
per installed megawatt.
He says the project will also provide a benefit for the local community and
an “enduring productive economic use” for land that was “extensively
disturbed” by open-cut mining.
Genex has received $4m from the Australian Renewable Energy Agency
(Arena) to support their feasibility work and is exploring options for
additional funding from the federal government’s Northern Australia
Infrastructure Facility program. Earlier this month the company
received an additional $8.9m from Arena under its large-scale solar
funding round.
“Pumped hydro is by far the cheapest and most mature storage
technology,” says Prof Andrew Blakers, director of the Centre for
Sustainable Energy Systems at the Australian National University.
He says the Kidston project is exciting because it’s the first large, off-river
PHES project in Australia.
“It’s a good model, particularly when combined with co-located PV and
wind,” he says. “However, there are hundreds of sites with much larger
height differences between top and bottom reservoirs throughout settled
Australia, so it’s not the only model.”
He says more PHES systems will be needed as renewable energy reaches
and exceeds 50% of Australia’s electricity grid.
Abandoned mines can pose pollution and safety risks, and often carry hefty
price-tags for clean-up efforts. In the US, the Environmental Protection
Agency runs a program that provides resources to communities,
developers, industry and local governments to enable renewable energy
projects at disused mine sites.
But “renewable energy projects at abandoned mines are novel in Australia”,
says Corinne Unger, a senior researcher at the University of Queensland’s
Centre for Mined Land Rehabilitation.
Unger says Australia should invest in research to explore the case studies
overseas and evaluate opportunities for a range of innovative uses for old
mines.
Australia has a strategic framework for managing disused mines but she
says there is still no implementation plan: “It would be valuable if the
Australian government followed through on the strategy to support state
and territory jurisdictions by providing useful guidance and resources ... to
demonstrate how the reality of ‘valuing abandoned mines’ could be
realised.”