Diapositiva 1 - MUSEUM communicator

MU.COM. PROJECT
Marco Merlini
“Next months steps: activities and expected
outcomes”
Second Transnational Workshop
Sibiu, 9 March 2012
EXPECTED MAIN PRODUCTS/ACTIVITIES
1 March – 30 June 2012
1. Final tuning of the course modules (according to
the national evaluation reports).
2. Completing the evaluation reports (reports will
be delivered to Irene not over March 12th)
OUTPUT: Validation and evaluation report
EXPECTED MAIN PRODUCTS/ACTIVITIES
March – June 2012
3. General monitoring of the project (31 March)
4. Course (start up 2 April – end 30 June)
5. Course intermediate evaluation from any
partner involved in the course (10 to 15 May).
OUTPUT: Evaluation synthesis report
EXPECTED MAIN PRODUCTS/ACTIVITIES
July - September 2012
6. Project works in Partner Museums (end of May
– end of July)
OUTPUT: Valorisation events at Museums
7. Final evaluation of the course made through
questionnaire (1-15 July)
OUTPUT: Final project report
EXPECTED MAIN PRODUCTS/ACTIVITIES
July-September 2012
8. Book on “Training Curriculum for Museum
Communicator” (EN/IT/BG/RO).
2000 printed copies
9. Final event in Rome in September 2012, capitalization of
the result and evaluation.
10. Preparation and delivery, from each partner, of the
administrative and financial documents (October
2012).
EXPECTED MAIN PRODUCTS/ACTIVITIES
Other outputs (1 MARCH TO 30 SEPTEMBER 2012)
- Updating of project mailing lists
- Newsletters nn. 5 to 8
- Monitoring report n. 2