Decentralized Investment and Quality Decisions In Common-Pool Networks* Manuel A. Abdala Pablo T. Spiller 1. Introduction During the last two decades network industries throughout both the developed and developing world have witnessed a profound degree of unbundling, privatization and increased competition. Although overall successful, these experiments have encountered difficulties in establishing adequate rules of the game for decisions that require a high level of coordination among the multiple participants sharing common-pool resources. When organizing diverse network activities with multiple agents such as the operation and expansion of an electricity grid, management of passenger train timetables, waterways, irrigation systems, groundwater basins, fisheries, etc., countries have often resorted to centralized solutions. Centralized or administrative solutions have two principal attractions: first, they save on transaction costs that multiple agents would have to incur to get organized; and second, they allow a more direct regulatory control over activities that typically require government intervention because of externalities, free riding, and property rights problems. Yet in network systems where competition has flourished, these same elements of centralized, regulatory decision-making may create additional distortions and transaction costs that may actually end up hurting the development of these industries. This happens, for example, when a centralized agency imposes a particular allocation of investment costs among electricity grid users that is deemed unfair for a set of parties. Or when a standard is set for the level of reliability (quality) of the pool that is adequate for some users but may send wrong incentives for others. The distorting elements are normally associated with information asymmetries. Investment and quality decisions that should be taken by private agents are either delayed or not incurred because the centralized agency fails to internalize the true preferences of network users. Complex meshed networks require decisions that affect multiple users, whose relationships could be either complementary (such as a port and shipping companies in waterways), competitive (electricity generators) or both. When the structure of the network (either its quality or size) is affected, externalities may abound and both present and future users get affected. In network industries where open-access principle prevails, as in electricity, property rights and free riding issues emerge as a potential barrier to optimal investment decisions. In this paper we explore and analyze features and experiences of decentralized mechanisms that put in place governance structures for network industries with common-pool values. The idea behind decentralized mechanisms is that a certain coordination problems can be best dealt through self-enforcing contractual arrangements among network users, with minimum regulatory oversight. In the context of transaction cost theory, Menard (2000) defines selfenforcement as “… a set of clauses based on mutual consent among partners with no arbitrariness in their implementation and, therefore, no need for intervention of a third party…”1. In our context, the decentralized mechanism is not as pure as the definition above. Rather, given the specificity of assets and hold up problems that are so characteristic in network industries, self-enforcement will have to be backed up by a third party who could intervene to solve potential conflicts. In other words, procedures on how to govern the decentralized mechanism are agreed ex-ante by the parties, but such procedures foresee the resort to public enforcement in case of major disputes.2 Decentralized Investment and Quality Decisions in Common-Pool Networks The challenges of any decentralized mechanism would be not only to deal with the transaction costs of getting grid users organized, but also to provide effective solutions to problems such as externalities, economies of scale, property rights, free riding, as well as allocative, cost, and dynamic efficiency associated with investment decisions. We focus our main attention and examples on electricity networks, but the main ideas could be applied to other network environments as well. Several studies have addressed the issue of self-governance and self-regulated institutions,3 but very few have been applied to competitive network industries. Ostrom (1990) has analyzed empirical examples of successful and unsuccessful efforts to govern and manage natural resources through the use of self-organization and self-governance in common-pool resource situations.4 Ravnborg and del Pilar Guerrero (1999) examine watershed-level qualities as a common-pool resource problem that could be solved through coordinated collective action by land users5. Tang (1992) describes the typical collective-action situations faced by irrigators and examines the role of local, self-governing organizations in resolving collective-action problems in irrigation, based on case studies of forty-seven community, bureaucratic, or local-government sponsored irrigation systems in a number of countries. Barker, Tenenbaum and Woolf (1997) have compared self-governance mechanisms for electricity pool organization in four different cases,6 but their focus is different from ours. They examine the degree of autonomy, governance and regulatory arrangements within the organization of the pool company itself. In a more akin research path on network utilities, Abdala and Chambouleyron (1998) have proposed a decentralized system for regional transmission investment and following this idea IDIED (1999) has developed a similar scheme for decentralized investment decisions for waterways private investment7. The main thrust of this paper is that decentralized solutions work much better than centralized ones. Rent seeking and politicization is avoided at much lower costs. Problems of free riding and the potential raising of entry barriers may remain. The former can be handled by better self-governance procedures, while the second may require antitrust supervision. Both of these problems have been handled in the examples we present here, of the FREBA in the Buenos Aires Province in Argentina, and the MACQS in New Zealand. We believe these two examples show the way for further decentralized mechanisms to develop throughout network utilities. 2. Centralized vs. Decentralized Solutions Problems with centralized decisions in electricity networks Investment and quality decisions may cause positive or negative externalities to electricity agents. These agents can be competitors, providers or clients of those who would like to initiate a change in quality or undertake a new investment project. In electric networks, externalities arise when, for example, the existing capacity of a line diminishes/expands due to a new project. Also, externalities take the form of quality aspects of the network, through changes in system reliability. It is difficult for a centralized agent to assess the preferences of investors when considering the addition of a new transmission line, or of users when assessing the appropriate quality standards on common-pool resources. First, beneficiaries of new transmission investment belong to different classes of stakeholders (ISO, transmission firms, generators, distributors, dealers, etc.) who are unlikely to have similar risk profiles, sector-specific risk premia, and Abdala and Spiller hence discount rates. In addition, transmission stakeholders are likely to have different views on the transmission asset utilization and the stream of economic benefits associated with any particular investment or quality decision. Similarly, quality preferences differ among grid users. Common quality standards, for example, will be very different for a supplier or distributor that faces strong penalties for loss of load (LOL) – whether regulated or commercially determined, than for a one that does not carry penalties at all. If quality is determined centrally by government or by an ISO type institution governed by government control, who bears the costs of common quality being too low or too high? How does the centralized decision take into account what the market wants in terms of common quality? Who have the responsibilities for achieving common quality levels? How are these levels determined? Does the regulator frequently revise quality standards? Some countries have left transmission investment and quality decisions within the domain of a transmission monopoly.8 Here, the most relevant question is how investment (or additional costs due to increased quality) will be recovered through the tariff structure (i.e. Colombia, Chile). There are several problems with this approach: a) Tariffs may be too high and by-pass may not be feasible. If bypass is not possible, rents from other parts of the production chain will be transferred to the transmission monopoly (i.e. Colombia). b) Tariffs may be too high and by-pass is feasible. Bypass could be efficient or inefficient (i.e. Chile’s Colbún competing transmission line is an example of inefficient bypass). c) Tariffs may be too low, in which case investment will not take place or will be substantially delayed. d) Investment decisions are not cost-efficient, as the monopoly has no incentive to cut down on construction costs. Other countries have converted electricity transmission into a more contestable market. Argentina, New Zealand, El Salvador, and certain regions in the US designed more competitive environments for transmission operation and environment. The key feature is that new entrants are allowed to the transmission business. Yet free entry will not be a sufficient condition for success, since - for the reasons mentioned above: externalities, property rights, free riding - the way the allocation of investment and quality costs is made is equally important. Transmission congestion contracts (TCCs) have also been recommended as a remedy to the property right and free riding problems associated with transmission investment. A TCC from node A to node B would give a user the right to collect congestion rents due to flows between these two nodes. Users that congest a line would generate congestion rents that would accrue to TCCs holders, thus sending right economic signals to investors.9 TCCs can be seen as way to allocate financial property rights among grid users who could either use or trade them in a secondary market according to actual use of the network.10 Nevertheless, TCCs does not address the issue of coordinating network users’ preferences and are only a partial remedy to protect ownership rights and free riding, for at least three main reasons: a) Determining the nominal capacity in meshed networks is not an easy task. Capacity depends on loop flows, time of day, and other factors. The administration of TCCs becomes very cumbersome in meshed networks since it is Decentralized Investment and Quality Decisions in Common-Pool Networks not possible to define available physical transmission capacity in a way that can be translated to tradable property rights.11 b) Since congestion rents collected trough TCCs depend on spot prices of electricity, market shocks would put at risk the ability of TCCs to recover capital costs12. c) Congestion rents do not recoup all costs, in particular because congestion is alleviated or even eliminated right after investment takes place. Alternative ways of granting property rights have been thought of through the use of transmission capacity rights (TCRs), or capacity reservations. Granting rights over incremental line capacity could be achieved without hurting the open access principle13. Moreover, if capacity rights are auctioned under certain rules, grid users have a chance to reveal true preferences in the auction. A problem remains, though, with the implementation of TCRs, since, as with TCCs, the mechanism does not work well in meshed networks where measurement of incremental capacity becomes obscure.14 Other centralized solutions involve quality and investment decisions taken by the system or pool operator, with participation of transmission companies15. Decentralized mechanisms For decentralized mechanisms to be better placed to solve this problem they will have to promote self-revelation of preferences among grid users’ preferences. For this purpose, a self-governance structure, with self-made arrangements among grid users will have to have the following features: a) b) c) d) e) f) Minimal regulatory oversight to limit the politicization risk Institutionalization of collective choice Successful proposals should require substantial support among users Veto power should be granted to protect minorities Compensation to those receiving negative externalities (either directly or indirectly through voting rights) To avoid allocative inefficiencies, the mechanism should be subject to antitrust enforcement. But even if all these features are taken into account, this type of mechanism has also potential drawbacks. Among those are: a) High transaction costs: To set up new institutions and get agreements among parties with divergent interests. b) Difficulty to pass successful proposals: Tyranny of the status quo. When strong majority is required to get consensus, it may be difficult to alter the status quo. c) Inefficient outcomes: Although closer in conception to a market solution, the decentralized mechanisms provide no guarantee that an efficient outcome will be achieved. d) Free riding problems: Depending on the type of decentralized arrangements, free riding may not be fully eliminated. e) Antitrust exclusion practices: In particular, there is the risk that members of decentralized agencies that have self-regulatory powers perceive themselves as a “club” and act accordingly to exclude competitors and new entrants to their industries. Abdala and Spiller 3. Two relevant decentralization examples 3.1. Case 1: Grid Expansions in Argentina. The Buenos Aires province initiative 3.1.1.Motivation Electricity distributors and cooperatives of the Buenos Aires province16 decided to create a regional board named FREBA17 to coordinate transmission investment and allocate its costs on the basis of self-imposed rules. Two major regulatory flaws triggered the need for coordinated private action. First, nationlevel procedures for transmission investment rely on a centralized administrative rule for its most sensitive aspect: the allocation of costs among potential beneficiaries18. The rule is flawed as cost allocation is based on an elementary measure of power flows. Hence, it does not take into account externalities or users preferences, and produces unfair results that distributors are not willing to accept. Veto safeguards to protect those receiving negative externalities or those who had to bear a share of investment costs larger than their willingness to pay are insufficient, and there are no provisions for compensation mechanisms. Second, provincial-level regulation for pass-through of transmission investment costs to end-user prices was also incoherent, as some distributors are allowed to transfer these costs to tariffs, while others are not. Therefore, the main motivation for private coordinated action was to overcome drawbacks from centralized administrative rules for transmission investment. 3.1.2. The organization of a decentralized private forum The regional forum FREBA was formally founded in December 1999 as a non-profit organization with the main purpose of fostering coordination for transmission investment19. FREBA membership is open to distributors, cooperatives and large industrial users from the Buenos Aires province. It also allows transmission companies to play a counsel role, granting them an affiliation that has no voting power within FREBA’s decision20. To become a member, distributors have to make a mandatory contribution to a trust fund called FITBA21, and also bear the administrative costs of FREBA. The global level of mandatory contributions for each year is determined as the minimum amount of funds that are necessary to start up a list of transmission projects selected from a portfolio of initiatives presented by FREBA members (under the modality of a BOM contract, financed in 10 years). This global level is then prorated by the individual demand size (in MWh) for each distributor, therefore determining the share of the mandatory contribution of each distributor22. Members’ contributions to FITBA are deposited in individual accounts, and determine voting rights within FREBA’s Assembly. FREBA’s internal distribution of power, therefore, is related to the physical size of distributors, provided that they have deposited the corresponding contributions in FITBA. Voting rights within FREBA’s Assembly are crucial to elect the Board of Directors (BD) (renewable every two years) and its operative arm, the Technical Committee (TC). The BD is composed of five representatives elected by the Assembly and the TC has seven professionals named by the BD. FITBA sources of funds is not only composed of contributions from FREBA’s members, but also from a special tariff component charged to end customers. The funds collected in this form are called “pass-through funds” and are to be used under special conditions (see following sections). Decentralized Investment and Quality Decisions in Common-Pool Networks 3.1.3. Project selection procedure Initiatives FREBA’s members present initiatives to the TC where projects are subject to a preliminary evaluation. All initiatives must contain project characteristics information such as technical description, trace, rights of way, environmental analysis, flow simulations, and the expected physical impact on all grid users. They should also stipulate an estimate of the annual cannon to be paid to the transmission company which would be in charge of constructing, operating and maintaining the line under a BOM contract. The cannon is calculated as the annual component of the estimated BOM contract fee, over a period of 10 years, at a preestablished discount rate set by FREBA23. The cannon listed for each initiative at the CT preliminary examination becomes a reference for FREBA members as to initiators’ estimated annual costs of the new project. Consultation and compensation devices Once the CT has examined initiators’ proposals, it passes this information throughout FREBA members, accompanied by a technical opinion. This consultation period has the main purpose of letting grid users reveal their preferences to the extent that they may be negatively affected by the project. In this case, a FREBA member can file either an objection or a compensation request. Both petitions have to be based on sound grounds and are subject to first-instance review by the TC. The objection solicitation must prove that the project in question bears no positive social benefit to the community of grid users of the province. For an objection to be automatically approved, 6 out of 7 votes within the TC are required (very strong majority). On the other hand, if the objection has the support of only three or less votes of the TC, the project would continue with the selection procedure and the objection petition will be dismissed. In a middle course, when an objection is supported by four or five votes (simple and strong majority), the project is labeled as “conditional”, and the decision on whether it should be objected or not goes on to FREBA’s Assembly. For a conditional project to be objected the Assembly needs 30% or more of total votes. That is, for a controversial project to be finally objected, it requires first, a majority opposition from TC opinions, and second, opposition from at least a strong minority within the Assembly. The compensation solicitation, on the other hand, allows grid users that may be negatively affected by externalities to file a request for economic compensation. The request have to sustained on technical and economic grounds, and a solicitation fee equivalent to 15% of the amount of compensation is required to have the petition analyzed by the TC24. For a compensation to be approved, the TC needs simple majority only (at least 4 of 7 votes). However, a positive TC decision on allowing compensation, does not mean agreement on the amount solicited. If there is such disagreement, the TC informs the solicitor on the amount authorized and asks him for consensus. If the solicitor is not content with the decision, he could choose to submit a “referendum” to the Assembly. In this second stage, the Assembly votes over the amount of the compensation, and simple majority are needed to reach a decision. Therefore, for a compensation to be accepted, it requires simple majority both at the TC and Assembly level, but the amount of compensation can be adjusted within FREBA’s two-stage instances (TC and Assembly). Competing projects that are mutually exclusive can be examined at the same time by the TC, which has no power to make any selection among them. The TC can only make technical Abdala and Spiller recommendations and comments about the nature of each competing project and will inform so to FREBA members. Economic revelation of preferences Initiators will be the ultimate responsible for signing a BOM contract with a transmission company. They will pay for the investment partly through their own sources, and partly through the recovery of pass-through funds, once the works are finished. Therefore, in a new project involving several grid users, initiators have to voluntarily structure coalitions that would ex-ante settle their individual shares over total investment costs. An important caveat for helping revealing true preferences and avoid free riding is that passthrough funds collected in FITBA are allowed to be reimbursed only to initiators, keeping proportions to their individual share within the coalition. That is, there is a strong incentive for a distributor to identify itself as a beneficiary of a new project and accommodate a coalition, since otherwise pass-through funds collected from its clients will not be eligible for use in such project. Pass-through funds collected from customers of distributor A could only be used by such distributor. Thus, there are no direct cross-subsidies in the use of passthrough funds among distributors. Another important element of this governance structure is that pass-through funds could be used to finance only a partial amount (∼) of total investment costs. This feature is an additional mean to guarantee the regulator that investment costs will be minimized (the other important element in the same direction is the competition of transmission firms to get the BOM contract). FREBA has proposed the provincial regulator that ∼ be equal to 0.9. Once coalitions are structured and initiators have passed TC requirements, a special FREBA Assembly is gathered to decide the final allocation of investment costs for each project. At this stage, questions on conditional projects and referendums on compensations have all been cleared. The special Assembly procedure is divided in three rounds. In the first round, FREBA members can allocate their individual contributions to FITBA to any of the list of projects that had cleared the TC examination. This first round may seem too obvious, as initiators would allocate their funds to the projects they support, but one of the purposes is to allow FREBA members that are not initiators to have an opportunity to express economic preferences at this stage. For approval in this round, total funds already deposited in FITBA and allocated to a particular project, should be sufficient to pay the first installment of the estimated annual cannon. In addition, such allocation also commits the member to pay similar amounts on the remaining nine years. Projects that did not get enough financing support pass on to the second round. In the second round FREBA members that still have available funds in their FITBA accounts could voluntarily decide to lend money to initiators whose projects have fallen short of funds25. If FITBA is also able to capture funds from third parties (external investors), such funds will also be allocated to the “borrowing pool”. An auction is conducted to allocate funds from this pool if the demand exceeds supply. The borrowing interest rate is the variable over which coalitions will bid upon. There is a price floor on the interest rate, based on market prices, and FREBA has a strong internal system of guarantees, so as to alleviate differences on credit risk ratings among distributors26. If a project does not get sufficient funds in the second round, a third round is open for voluntary contributions to FITBA. Initiators could thus have a final chance to allocate additional funds to the projects they support27. Decentralized Investment and Quality Decisions in Common-Pool Networks A particular situation could be expected if, at any point of the three rounds, two or more competing projects get sufficient funds. Although quite unlikely, such economic dispute would be solved by FREBA’s assembly with a strong majority support requiring 75% of votes to decide on final approval. Approved projects are then eligible for BOM contract public tender, to select a competitive transmission company. These tenders have as base price the annual cannon set by initiators. Competitive bids would eventually result on a cannon amount that is lower to the reference price, provided that the FREBA reference discount rate is not substantially below market prices and that project cost estimation were not downward biased. 3.1.4. Forum interfaces with the regulator The whole FREBA mechanism requires an initial consensus with the regulator, because of the presence of pass-through funds and the delegation of certain activities that are traditionally conceived under the domain of the regulator, like evaluating the environmental impact of a new line. An important regulatory definition involves both the size of the total annual pass-through to be deposited on FITBA, as well as the size of ∼. The government trade off here is quite clear. It wants investment to take place, but at an optimal amount. It also wants to see projects undertaken with cost efficiency, to avoid hurting captive consumers through an excessive pass-through. In the FREBA mechanism, distributors have the incentive to minimize costs, as they bear a portion of the investment costs directly. One should therefore expect that the investment decision be taken optimally in dimensions such as price, location, timing, and scale. Minimum regulatory intervention takes place at least twice during the selection process. First, before projects enter the special Assembly stage, the regulator makes sure that the environmental impact analysis and other technical considerations have been comprehensively evaluated. Second, the regulator could double-check that pass-through funds are used correctly. For example, it could monitor that pass-through funds are not used to roll in investments that have extra-regional beneficiaries28. Finally, antitrust agencies could eventually act as watchdogs, to prevent exclusionary practices that may limit competition between existing and future FREBA members. 3.1.5. Current experience and challenges ahead It took about a year to get FREBA organized, and the forum is still in the process of polishing up its internal rules. So far, distributors representing more than 70% of total provincial demand have voluntarily joined FREBA, and it is expected that the rest will join afterwards. Credibility of the institution has not been achieved yet, as the mechanism has not been fully tested and is too young to be judged. The first project selection mechanism has not been triggered yet, as governmental definitions on the total amount of pass-through were still pending. One area that may need further discussion is lack of agreement among parties to set up a coalition of initiators, leading to free riding problems. It is suspected that in those projects where a party has a major stake and interest in getting the project done, whereas the other(s) only receives marginal benefits, the party with the small share may try to free ride by Abdala and Spiller not joining the coalition. Since insofar there are no mandatory rules of participation, there is a concern on how potential conflicts of this nature could be solved. Other regions with similar problems are looking into FREBA as a model for solving their regional transmission investment deficit. If FREBA agreement turns into a success, this type of decentralized mechanism could, in the medium turn, be converted into a broader institution that set policies for common quality and security issues, for example. The decentralization move could also challenge the existing incentives derived from centralized rules for transmission grid operation. For instance, level of penalties and bonuses faced by transmission firms for line availability, could be determined matching grid users’ preferences about line reliability and costs of LOL29. 3.2. Case 2: Grid Quality Determination in New Zealand’s wholesale market The widespread reforms in the electricity sector in New Zealand brought about a vertically and horizontally fragmented industry, with TPNZ, the transmission company, at the center of the system, with transmission and dispatch responsibilities.30 One of the key components of New Zealand’s regulatory approach has been the emphasis of competition regulation over industry regulation. Thus, as in the other utility sectors, the industry was essentially deregulated but with the Commerce Commission having supervision responsibilities over antitrust. Distribution companies were subjected to disclosure requirements, and TPNZ’s tariff structure was subjected to substantial industry and Commerce Commission review.31 The industry created its own wholesale market (NZEM),32 its own metering and reconciliation system (MARIA),33 and recently, its own way of determining wholesale quality (awkwardly named MACQS).34 As it relates to the MACQS agreement, there was an industry concern with TPNZ’s high cost structure, and in particular, that the fact that TPNZ determined the wholesale electricity quality provided incentives to increase costs unnecessarily. The industry, then, after several months of meetings reached a decentralized way of setting quality at the wholesale level. As of today, though, this agreement may be jeopardized by the new government’s decision to centralize the three governance structures into one under government supervision – potentially defeating, by increasing rent seeking and politicization, the effort undertaken by the industry over the last four years.35 Here we will summarily present the industry’s way of determining quality responsibilities. The industry first determined an Interim Grid Security Committee, composed of grid users and TPNZ. It held weekly meetings for 10 months, and made institutional recommendations to determine and implement quality aspects, including security. The results of these recommendations were presented for approval to the Commerce Commission, and after obtaining authorization, started operating, following the signing by the users, in November 1999. The main institutional innovations as they relate to the determination of quality is, first of all, that quality will be determined by the system users and not by a service providers. But that is not the only innovations. Procedural innovations are fundamental as well, in particular, the development of participative procedures, and the development of bilateral and multilateral contracts with minimum performance standards for each party. Figure 1 presents the main way by which the MACQS determines both quality and each individual participant’s responsibilities.36 Decentralized Investment and Quality Decisions in Common-Pool Networks Figure 1: Interactions between MACQS Members and CQC MACQS Members Multilateral Contract Performance Targets for the CQC Real Time Operation to Meet Targets •Accountable for Schedule & Dispatch •Outage Coordination •Grid Emergency Response Advice on Standards to GSC Complex Equivalence Judgments Information provision Administration CQC Security Contracts Common Standards (in performance terms) Minimum Scheduling and Dispatch Ancillary Services (Transition) and Settlement Ancillary Services Cost Allocation Dispute Resolution Equipment Capability Statements by Owners Generation Transmission Demand Asset Contracts Requirement to hold a Security Contract Asset Performance to meet contract performance objectives Liability for Performance as contracted Safety / Environmental Asset Cost Recovery The MACQS has two major institutions: the Common Quality Coordinator, CQC, and the MACQS members, who are the buyers of quality. The MACQS members are essentially the grid users, whether final users, generators, distributors, or transmission grid owners. The CQC’s main responsibilities are specified in the multilateral contracts it has with the MACQS via a deed between the Grid Security Committee (as representative of the MACQS members), and in turn, the CQC enters into security contracts with asset holders, i.e., generators, transmission companies, and demanders.37 As Figure 1 shows, the multilateral contracts requires the CQC to be accountable for real time operations, and in particular, minimum quality targets are specified and penalties for deviation imposed. The CQC also has responsibility for controlling the application of minimum operation standards by asset owners. The multilateral contracts among the CQC and the buyers of quality, and the “cascade contracts” among the CQC and asset owners, then, determine common standards, individual asset owner requirements, and in particular, specifies conflict resolution procedures. Abdala and Spiller The Grid Security Committee, in turn, is in charge of evaluating proposals for changing parts of the MACQS. It also supervises the CQC contract arrangements, admits new members, and appoints mediators for conflict resolution purposes. The GSC is composed of ten members, nine of which are elected representatives, representing generators (three), retailers, local networks, grid owners, domestic, commercial and industrial end users (one each). Each member of MACQS receives voting rights based on its demand or generation capacity at the node. These voting rights – based on MW injection or offtake, are transferable, and whoever holds the voting right is responsible for covering administrative costs.38 GSC decisions must follow particular procedures. Figure 2 presents the GSC’s decision making process. Figure 2: GSC’s Decision-Making Process GSC Issues Recommendation Public Comment Period 2 GSC members opposed Resolution withdrawn 1 or less of members of the GSC opposed 5% of votes call for vote No vote called for 25%+ reject resolution less than 25% against Resolution Rejected Resolution accepted Resolution accepted The main implication of the GSC procedures is that as it relates to common quality decisions, it avoids both inefficient decisions, or rent seeking. For either one to take place, nine out of the ten members must support the decision, the change must benefit at least 75% of the voting rights, the losses to the 25% must not be too high (if these were high, they would buy some of the rights from some of the members voting with the winning majority),39 and furthermore, the Commerce Commission must allow it. Thus, serious inefficiencies or rent seeking outcomes probably would not take place.40 To summarize, the MACQS is an institutional innovation that creates user participation in the decision-making process concerning transmission quality. It assigns responsibilities to the common quality coordinator; responsibilities arrived via a consensus building process. The CQC, in turn, enters into contract with asset holders to motivate these to maintain and operate those assets in ways that limit costs to the system. Important expansions that benefits all are then implemented via the CGS procedures. Decentralized Investment and Quality Decisions in Common-Pool Networks 4. Conclusions and challenges ahead Two examples of decentralized systems in electricity grids were presented in this paper (FREBA in Buenos Aires province, Argentina; and the MACQS in New Zealand). One interesting common feature is that both initiatives emerged as an alternative to centralized administrative rules, in search of fair outcomes, free of discretionary results that could be imposed by a regulator. A remarkable point is that these innovative institutions developed despite the presence of externalities, transaction costs, and other features that typically call for regulatory intervention over transmission network facilities. A natural consequence of self-governance in the use of a common-pool network is the internalization of externalities. Key features for the organization to be effective are the provision of incentives that lead to self-revelation of preferences, and the efficient resolution of conflicts and negotiations among grid users. The examples examined here provided for special compensation mechanisms to deal with externalities, either directly or through the use of voting rights. Special voting provisions were considered to reach strong consensus on decisions that are relevant for the management of the common network, such as investment, quality, security, and reliability. Actual performance of decentralized systems in electricity transmission remains to be evaluated. One area of concern seems to be how to assure that a self-governance structure will lead to efficient decisions. In this paper we do not evaluate whether decentralized decisions are Pareto optimal. But the initiatives indicate that both regulator and private users perceive that a decentralized arrangement is superior to the traditional form of organization. So, even if only second-best efficiency outcomes were achieved, the more relevant question is, are transaction costs lower than in the centralized alternative? We believe that in the two examples analyzed the main challenge to transaction costs in the decentralized arrangement may come through the presence of inter-temporal free riding behavior. As electricity networks in competitive environments operate usually under the open access principle, new grid users may benefit from investment for which they can not easily be forced to contribute, unless there is some minimum property rights enforcement, through a public authority. The free riding issue brings about the question on the degree of regulator’s supervision required in decentralized institutions. Often times a decentralized institution may be required to coexist with old-style active regulation of legal monopolies that require heavier regulatory control. What type of precautions should a regulator take vis-a-vis a self-governed institution such as FREBA or MACQS in this context? Should these be within the jurisdiction of industry regulators or antitrust authorities? How would the mechanisms work with minimum public oversight? What are the regulatory consequences of a self-governed institution in an environment where regulatory enforcement is poor, due to a weak institutional endowment? How much credibility is needed to reduce to public oversight? Could exclusion of newcomers to the decentralized institution become an antitrust problem? These concerns need to be explored and further investigated. It would be of help to the field of industrial organization if experiments could be conducted to test the ability of selfgoverned institutions to work out negotiations, internalize externalities and solve conflicts in complex environments such as electricity networks. Abdala and Spiller References Abdala, M.A. (1994) “Transmission Pricing in Private-Owned Electricity Grids: An Illustration from the Argentine Electricity Pool” XXIX Annual Meeting of Asociación Argentina de Economía Política. La Plata. Abdala, M.A., J.L. Arrufat, and C. Torres (1997) “Subasta de Derechos Negociables de Capacidad: Un Mecanismo de Mercado para Asignar Derechos Propietarios en Inversiones de Transmisión Eléctrica” Estudios 80. Abdala, M. A. and A. Chambouleyron (1998), “Opciones de regulación para mecanismos descentralizados de inversión en transmisión eléctrica” XXXIII Annual Meeting of Asociación Argentina de Economía Política. Mendoza. Abdala, M. A. and A. Chambouleyron (1999), “Transmission Investment in Competitive Power Systems. Decentralizing decisions in Argentina” Public Policy for the Private Sector, Note 192, The World Bank. Ayres, I., and J. Braithwaite (1992), “Responsive regulation: Transcending the deregulation debate” Oxford Socio-Legal Studies. Oxford; New York; Toronto and Melbourne: Oxford University Press. Bastos, C. M. and M. A. Abdala (1996), “Reform of the Electric Power Sector in Argentina” Buenos Aires: Edited by the authors. Barker, J., B. Tenenbaum and F. Woolf (1997), “Governance and regulation of power pools and system operators: An international comparison” Technical Paper, no. 382. Washington, D.C.: World Bank, page xvii, 80. Bergara, M. and P. T. Spiller (1997), “The Introduction of Direct Access in New Zealand’s Electricity Market”, Utility Policy, Vol. 6, No.2, pages 97-106. Chao, H. and S. Peck (1996), “A Market Mechanism for Electric Power Transmission” Journal of Regulatory Economics 10 (1), pages 25-59. Chao, H., S. Peck, S. Oren, and R. Wilson, (2000) " Flow-based Transmission Rights and Congestion Management," (forthcoming Electricity Journal). Dinar, A., and E. Loehman (1995) “Water Quantity/Quality Management and Conflict Resolution: Institutions, Processes, and Economic Analyses” Westport, Conn. and London: Greenwood, Praeger. Hogan, W. (1992) “Contract Networks for Electric Power Transmission” Journal of Regulatory Economics, 4, pages 211-242 Hogan, W. (1999) “Electric Transmission Adequacies and Market Institutions” Mimeo presented at the Meeting of the NARUC Committee on Electricity, San Francisco. IDIED - (1999) “Descentralización de Decisiones de Inversión en Infraestructura Fluvial” Serie Estudios nº 8. Facultad Ciencias Empresariales, Universidad Austral. Loehman, E. and D. Kilgour (1998), “Designing institutions for environmental and resource management” in Loehman, E., and D. Kilgour eds. “New Horizons in Environmental Economics” Cheltenham, U.K. and Northampton, Mass.: Elgar. Decentralized Investment and Quality Decisions in Common-Pool Networks Menard, C. (2000) “Enforcement Procedures and Governance Structures” in Menard, C. Ed. “Institutions, Contracts and Organizations. Perspectives from New Institutional Economics”. Cheltenham, Northampton: Edward Elgar Publishing Inc. Oren, S. (1997) “Economic Inefficiency of Passive Transmission Rights in Congested Electricity Systems with Competitive Generation” Energy Journal, 18 (1): 63-84. Ostrom, E. (1990), “Governing the Commons: The Evolution of Institutions for Collective Action” Political Economy of Institutions and Decisions series, Cambridge; New York and Melbourne: Cambridge University Press. Ravnborg, H., and del Pilar Guerrero, M. (1999) “Collective Action in Watershed Management – Experiences from the Andean Hillsides” Agriculture and Human Values 16(3), pages 257-266. Steins, N., and V. Edwards (1999), “Synthesis: Platforms for Collective Action in Multiple-Use Common-Pool Resources” Agriculture and Human Values 16(3), pages 309-315 Spiller, P. and C. Torres (1996), “Argentina’s Electricity Regulation: Its Performance, Credibility, and Options for the Future” Mimeo The World Bank. Stephenson, K. (1996), “Groundwater Management in Nebraska: Governing the Commons through Local Resource Districts” Natural Resources Journal; 36(4), pages 761-78. Tabors, R. (1996), “A Market-Based Proposal for Transmission Pricing” Electricity Journal, 9:9, pages 61-67. Tang, S. (1992), “Institutions and collective action: Self-governance in irrigation”, San Francisco: ICS Press. Williamson, O. (1985) “ “The Economic Institutions of Capitalism” New York: Free Press, Macmillan. Williamson, O. (1991) “Comparative Economic Organization: The Analysis of Discrete Structural Alternatives” Administrative Science Quarterly, 36(2), pages 269-96. 1 Menard. C. (2000), page 242. This specification corresponds to the so called “hybrid organizational forms”. See Menard (2000), Williamson (1985, 1991). 3 See, for example, Ayres and Braithwaite (1992), Stephenson (1996) Steins and Edwards (1999), Loehman and Kilgour (1998). 4 The author focuses on cases like the organization of mountain grazing and forest common-pool resources in Switzerland and Japan, and some irrigation systems in Spain and the Philippines. There are also analyses on a set of institutions to manage a series of groundwater basins located beneath the Los Angeles metropolitan area, fisheries in Turkey; groundwater in San Bernardino County, California; and fisheries and irrigation systems in Sri Lanka. 5 Experiences of a micro-watershed research in the Andean hillsides of southern Colombia are narrated. 6 England and Wales, Victoria (Australia), Alberta (Canada) and the NordPool. 2 Abdala and Spiller 7 See Dinar and Loehman (1995) for numerous examples of coordinated efforts in the water management field. 8 Hogan (1999) suggests that one way of dealing with the problem of the commons associated with network externalities in competitive markets is to give the transmission company a monopoly with the obligation to provide unlimited transmission services to everyone. 9 See the early works from Hogan (1992), and Chao and Peck (1996). Financial TCCs are also known as passive rights (See Oren 1997). For a more recent work, see also, Chao, Peck, Oren and Wilson (2000). 10 According to Hogan (1999), TCCs is the approach that dominates thinking in the United States and stands behind the policy at the Federal Energy Regulatory Commission. 11 See Hogan (1999), Abdala and Chambouleyron (1999), and Oren (1997). 12 For instance, a fall in the cost of generation would cause a drop in the spot price (in a competitive market) and thus entitle TCC holders to smaller-than-expected congestion rents. 13 See, for example, Tabors (1996) for a system of point-to-point capacity reservations. 14 For a proposal on TCRs sold through auctions, see Abdala, Arrufat and Torres (1997). The "Direct Link" project between Queensland and New South Wales in Australia is an example of granting property rights to incremental capacity (Hogan, 1999). Although, this is not a meshed case. 15 California is an example of a mechanism that attempts to be flexible and bring full participation to all stakeholders, but yet final decisions are centralized by the ISO (Independent System Operator). 16 Composed of 9.2 million inhabitants in 303.000 square km of pampas, who consume about 9,500 GWh/year. Three private distributors concentrate two thirds of total provincial demand whereas the rest is served by about 200 cooperatives. 17 FREBA: Foro Regional Eléctrico de la Provincia de Buenos Aires. 18 In Argentina, there are no major barriers to entry in transmission, other than the centralized administrative rules for determining who ends up paying the investment cost for a new facility. A new transmission firm can enter the market if it wins a competitive tender. The winner is the firm that bids lower construction and operation costs. For transmission operation and maintenance the firm receives revenue that is capped, and has to meet certain quality standards (including line availability) that are subject to penalties and bonuses. For a more comprehensive description and criticisms of Argentine transmission regulation see Abdala (1994), Bastos and Abdala (1996), Spiller and Torres (1996) and Abdala and Chambouleyron (1999) 19 Previous ideas on the organization of decentralized regional forums for electricity transmission appeared in Abdala and Chambouleyron (1998). 20 Generators were not invited to the Forum, as the province is an importer of energy from other regions (provincial transmission lines basically configure a meshed distribution network in high and medium tension levels). 21 FITBA is a trust fund specially created to finance transmission investment projects in the province. It stands for Fondo Fiduciario para Inversiones en Transmisión en la Provincia de Buenos Aires. 22 Industrial users are not required to make mandatory contributions to FITBA. 23 Establishing a discretionary discount rate bears no economic effect at this stage, since the BOM contract would be subject to competition among transmission companies in a public tender process once FREBA approves the list of eligible projects. 24 The solicitation fee is totally reimbursed if the compensation is authorized. Otherwise, the CT will deduct all administrative costs incurred to examine the petition, before reimbursement. 25 Initiators can borrow today to help finance the first installment of the estimated cannon, but they are still responsible for financing (with own or external sources) the remaining installments for the equivalent proportion of what they borrow today. 26 There is a triple-deck system of guarantees for a borrowing distributor. Own deposit to FITBA is the first level, followed by its own pass-through funds and, finally, the faculty to exert a judicial order over its electricity revenue collection. 27 Project approval in this round is made contingent to the deposit of the additional funds in FITBA within 48 hrs following the special Assembly. 28 A similar situation was faced in the Argentine gas transportation sector, since rolling in investment costs among domestic users for pipelines whose value was mainly associated to export projects, has raised regulatory complaints. 29 In the Argentine regulation for transmission, norms are quite strict on penalties for line unavailability. But distributors and marketers can not freely give incentives to transmission companies for different levels of quality. Thus, there is a gap between supply and demand that is not well addressed by the current means of centralized regulation. Decentralized Investment and Quality Decisions in Common-Pool Networks 30 See Bergara and Spiller (1997). For a chronology of the electricity reforms from 1994 to the present, see, Ministry of Economic Development, Energy Resources and Safety, http://www.med.govt.nz/ers/electric/chronology/chronology02.html. 32 New Zealand Electricity Market, NZEM, the multilateral agreement under which most wholesale electricity is bought by retailers and sold by generators on a half-hourly basis. 33 MARIA, the Metering and Reconciliation Information Agreement, which outlines the rules that, allow a buyer and seller to form a contract to supply electricity. 34 The MACQS, or the new Multilateral Agreement on Common Quality Standards, which aims to transfer responsibility for transmission supply quality to the industry (this responsibility currently lies with Transpower). 35 See, Ministerial Inquiry into the Electricity Industry, Inquiry into the Electricity Industry: June 2000 Report to the Minister of Energy, at http://www.electricityinquiry.govt.nz/reports/final/index.html. 36 For details on the workings of MACQS, see http://www.gsp.co.nz/welcome.html. 37 In the interim, TPNZ is the Common Quality Coordinator. 38 Thus, final consumers may transfer their voting rights to distributors, brokers or any other agent. 39 Members may split votes, i.e., transfer one vote to one agent and another vote to another. 40 At the same time, the demands for changing rules are so difficult to implement that a potential “tyranny of the status quo” may have been generated here. 31
© Copyright 2025 Paperzz