2016 Adopted Transit Improvement Plan

t
Adopted
Transit Improvement Plan
2016
December 2015
To request accommodations for persons with disabilities or to receive information in alternative
formats, please call 1-888-889-6368, TTY Relay 711 or e-mail [email protected]
Contents
Transit Improvement Plan Overview ......................................................................................................................... 1
Financial Plan ........................................................................................................................................................... 1
Project Budgeting ..................................................................................................................................................... 1
Transit Modes .............................................................................................................................................................. 3
Projects 1 ...................................................................................................................................................................... 4
Lifetime Budget Changes from 2015 to 2016 ............................................................................................................ 5
Project Summary and Detail Pages ........................................................................................................................... 5
System Expansion – Link Light Rail .......................................................................................................................... 7
System Expansion – Sounder Commuter Rail ........................................................................................................ 26
System Expansion – Regional Express ................................................................................................................... 44
System Expansion – Other ...................................................................................................................................... 56
Enhancement Projects ............................................................................................................................................ 68
Rehabilitation & Replacement Projects ................................................................................................................. 101
Administrative Projects .......................................................................................................................................... 117
Reserves .................................................................................................................................................................. 125
Appendices .............................................................................................................................................................. 126
Appendix A – Sound Transit 2 Cost Estimates .................................................................................................... 126
Appendix B – Sound Move Lifetime Budgets ....................................................................................................... 128
Appendix C – Sound Transit Project Phases ....................................................................................................... 129
Appendix D – Subarea Allocations ....................................................................................................................... 130
Appendix E – Reconciliation of the Proposed 2016 TIP to Adopted 2016 TIP ..................................................... 135
Appendix F – Glossary ......................................................................................................................................... 137
1
Index of Project Details follows on next page.
Alphabetical Index of Project Details by Mode
LINK LIGHT RAIL
Beacon Avenue Paving ............................................................................................................................................................. 106
Central Link Card Readers .......................................................................................................................................................... 94
Central Link HVAC – Instrument House and UPS Room ............................................................................................................ 84
Central Link HVAC for Traction Power ........................................................................................................................................ 93
Central Link Overhead Catenary System Tie Switch ................................................................................................................... 95
Downtown Redmond Link Extension ........................................................................................................................................... 14
East Link Extension ..................................................................................................................................................................... 24
Enhancements to Tacoma Link Expansion ................................................................................................................................. 12
Federal Way Link Extension ........................................................................................................................................................ 13
First Hill Streetcar ........................................................................................................................................................................ 18
Initial Segment ............................................................................................................................................................................. 22
Link CCTV System Upgrade ........................................................................................................................................................ 87
Link Operations & Maintenance Satellite Facility ......................................................................................................................... 16
Link Remote Switch Heaters ........................................................................................................................................................ 79
Link Station Braided Tile Replacement ...................................................................................................................................... 108
LRV On Board Energy Storage .................................................................................................................................................... 81
LRV Overhaul ............................................................................................................................................................................ 109
Lynnwood Link Extension ............................................................................................................................................................ 17
Noise Abatement ......................................................................................................................................................................... 82
Non-revenue Support Vehicles .................................................................................................................................................... 98
Northgate Link Extension ............................................................................................................................................................. 20
Northgate Link Extension Project Reserve .................................................................................................................................. 25
South 200th Link Extension ......................................................................................................................................................... 23
Signage Improvements ................................................................................................................................................................ 78
ST2 Light Rail Vehicle Expansion ................................................................................................................................................ 19
Tacoma Link Announcement/Sign System ................................................................................................................................ 107
Tacoma Link Light Rail Vehicle Overhaul .................................................................................................................................. 104
Tacoma Link Expansion ............................................................................................................................................................... 15
Tacoma Link Fare Collection ....................................................................................................................................................... 83
University Link Extension ............................................................................................................................................................. 21
SOUNDER COMMUTER RAIL
D St – M St Track & Signal .......................................................................................................................................................... 39
Kent Station Parking Lot Paving .................................................................................................................................................. 91
Kent Station Platform Lighting ..................................................................................................................................................... 90
Lakewood Station Improvements ................................................................................................................................................. 33
M St – Lakewood Track & Signal ................................................................................................................................................. 38
Mukilteo Station, S Platform ......................................................................................................................................................... 40
Passenger Information System .................................................................................................................................................... 41
Point Defiance Bypass ................................................................................................................................................................. 34
Positive Train Control ................................................................................................................................................................... 80
Puyallup Station Improvements ................................................................................................................................................... 32
Puyallup Station LED Lighting ..................................................................................................................................................... 88
Sounder South Expanded Service ............................................................................................................................................... 35
Sounder ST2 Fleet Expansion ..................................................................................................................................................... 43
Sounder Vehicle Overhaul Program .......................................................................................................................................... 110
Sounder Yard & Shops Facility .................................................................................................................................................... 30
Sounder Yard Expansion ............................................................................................................................................................. 37
Station Midlife Refurbishment Program ..................................................................................................................................... 113
Sumner Station Improvements .................................................................................................................................................... 31
Sumner Station LED Lighting ....................................................................................................................................................... 89
Tacoma Trestle Track & Signal .................................................................................................................................................... 36
Tukwila Station ............................................................................................................................................................................. 42
REGIONAL EXPRESS
85th Corridor, Kirkland ................................................................................................................................................................. 51
Bothell Transit Related Improvements ......................................................................................................................................... 49
Bus Maintenance Facility ............................................................................................................................................................. 73
Federal Way Post Tension Cable Repair ................................................................................................................................... 112
Federal Way Transit Center ......................................................................................................................................................... 53
I-90 Two-Way Transit & HOV Operations, Stage 3 ..................................................................................................................... 54
Kirkland Transit Center/3rd ........................................................................................................................................................... 52
Pierce Transit Radio System Upgrade ......................................................................................................................................... 96
ST Express Bus Base .................................................................................................................................................................. 48
ST Express Fleet Expansion ........................................................................................................................................................ 55
ST Express Fleet Replacement ................................................................................................................................................. 114
ST Express Mid-Day Bus Storage ............................................................................................................................................... 50
ST Express Mobile Communications ........................................................................................................................................... 97
OTHER
Administrative Capital ................................................................................................................................................................ 122
Agency Administration Operating .............................................................................................................................................. 120
Bike Locker Program ................................................................................................................................................................... 86
Central & East HCT Study ........................................................................................................................................................... 61
Downtown Seattle Transit Tunnel Mitigation ............................................................................................................................... 74
Environmental Mitigation, Monitoring & Maintenance ................................................................................................................ 121
Fare Administration ...................................................................................................................................................................... 67
Fare Collection ............................................................................................................................................................................. 65
HCT Corridor Planning Studies .................................................................................................................................................... 62
Information Technology Program ............................................................................................................................................... 123
IT Link Light Rail ........................................................................................................................................................................ 105
IT Transit Systems ..................................................................................................................................................................... 116
Operations & Maintenance Facility LRV Vehicle Lift .................................................................................................................... 75
OMF LRV Wash Heater System .................................................................................................................................................. 92
Regional Parking Pilot Project ..................................................................................................................................................... 77
Research & Technology ............................................................................................................................................................... 66
Security Enhancements ................................................................................................................................................................ 85
Small Works Program ................................................................................................................................................................. 115
South Corridor Alternatives Planning ........................................................................................................................................... 59
ST3 Planning ............................................................................................................................................................................... 60
STart ............................................................................................................................................................................................ 63
STart Operations & Maintenance.................................................................................................................................................. 64
Surplus Property Disposition ...................................................................................................................................................... 124
Tacoma Dome Station ............................................................................................................................................................... 111
Transit Oriented Development Planning .................................................................................................................................... 100
Transit Oriented Development Property Disposition .................................................................................................................... 99
Union Station Garden Level Remodel ......................................................................................................................................... 76
Marilyn Strickland, Tacoma Mayor and Sound Transit Board Vice Chair, speaks to the need for transit improvements.
Ahmad Fazel, Executive Director of Sound Transit’s Design, Engineering and Construction
Management Department and Tracy Reed, Rail Activation Manager, at the Capitol Hill Station.
Sound Transit employees tour the Angle Lake Station site. The station is located 1.6 miles south of the Link SeaTac/Airport station.
Transit Improvement Plan Overview
The Adopted 2016 Transit Improvement Plan (TIP) provides
a long-term forecast of project and transit mode costs, plus
reserves set aside for potential future expenditures.The
Sound Transit Board adopts the TIP and the annual budget
to authorize spending for the budget year, as well as lifetime
project budgets.
agency programs against the financial plan ensures a
balance of revenues and expenditures, as well as
affordability of the overall program. Sensitivity analysis,
using the financial plan, gauges the impact of potential
changes in the economy as well as changes in project
schedule and scope on overall program affordability.
Transit Modes
Project Budgeting
The TIP includes annual forecasts for six years of operating
expenses for each of the agency’s transit modes. The
expense forecasts are developed in a detailed long-term
operating and maintenance plan and reflect service plans
contained in the 2016 Service Implementation Plan (SIP).
Project Prioritization Process
During the development of the budget, the agency follows
an objective process to vet all proposed new projects and
increases to existing projects that are not part of the Sound
Move or ST2 programs. Projects are scored using objective
criteria including: safety, sustainability, regulatory, financial,
impact on asset “State of Good Repair,” system
enhancements, security, and impact on ridership. The goal
is to identify high-value, high-priority projects and pair them
with available resources.
Projects
The TIP includes project scope, schedule, budget, and risk
information for all active projects. Budget information is
presented at the phase-level including life-to-date costs,
annual spending forecasts for the upcoming six years,
summarized costs for years beyond this six-year period, and
the total authorized lifetime budget. Only board-approved
budget amounts are included. Where a baseline budget has
not been approved, the total budget only includes the
authorized phases. The baseline budget reflects the
estimated costs for the entire project and is used to measure
actual project budget performance. For most projects,
Phase Gate status is also provided. For ST2 projects only,
cost estimate information is shown in the Projects section
and in Appendix A. Lifetime budgets for active Sound Move
projects are shown in Appendix B.
Budget Approval and Phase Gate Process
Prior to 2010, the Sound Transit Board approved project
lifetime budgets at the outset of a capital project. Since 2010,
our approach to project budgeting has been modified to
provide greater Board oversight and control. As projects
reach key milestones, requests for budget approval to
complete the next project phase are presented for Board
approval. Phase Gate, our project management oversight
process, confirms that the project is ready to move forward
to the next phase and triggers the request to the Board for
additional budget. There are exceptions to having projects
pass through each gate in sequence, such as procurements
and alternative contracting methods, as in design-bid-build.
Reserves
The TIP includes reserves that are set aside for both
planned and unplanned expenditures. Reserves are not
considered appropriations, and Board authorization is
required to use reserved funds.
Typical budget requests include funding for:
Financial Plan
In addition to the TIP that is published annually, Sound
Transit maintains a long-term agency financial plan – a
model of forecasted cash flows through 2040. A review of

Project
development
through
preliminary
engineering and environmental investigation.

Final design and right-of-way acquisition.

Baseline or total expected project budget.
TRANSIT IMPROVEMENT PLAN SUMMARY
(in millions)
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
$0
$263
$276
$283
$291
$299
$352
$0
$1,763
6,322
947
1,614
1,417
1,085
909
715
1,008
14,016
318
69
14
9
9
3
3
8
433
$6,641
$1,279
$1,904
$1,708
$1,385
$1,211
$1,069
$1,015
$16,213
Transit Modes
Projects
Reserves
Total
Adopted 2016 Transit Improvement Plan
1 of 140
The initial project development budget includes alternatives
analysis to shape the scope of the project and selection of a
preferred alternative, compliance with environmental
requirements which may include an Environmental Impact
Statement, development of operations and maintenance
plans, and preliminary engineering for the preferred
alternative.
A final design and right-of-way budget includes funding for
all design work – civil, structural, electrical and HVAC,
systems and architectural through to construction
procurement documentation, as well as purchase or lease of
all property needed to build the project.
A baseline budget is established during final design when
sufficient information is available to establish a project’s cost
through construction. Project spending is benchmarked
against the baseline through completion of the project.
Projects are fully funded when the Board approves the
baseline.
Cost Estimates
Each ST2 capital project has a cost estimate that originated
from the 2008 voter-approved plan. Original ST2 cost
estimates, 2015 cost estimates, and 2016 cost estimates for
ST2 projects appear in Appendix A.
Our cost estimates are maintained on a current year,
constant dollar basis. For instance, in the 2016 TIP, full
project cost estimates are presented in constant 2015
dollars. However, the Board approves budgets in year-ofexpenditure dollars to take into account the fact that project
spending occurs over several years and so must be adjusted
for inflation.
Sparks fly as crews work on the Angle Lake light rail station.
.
2 of 140
Adopted 2016 Transit Improvement Plan
Transit Modes
The Adopted 2016 TIP contains forecasted expenses to
operate and maintain the regional transit system from 2016
– 2021. Operating expenses include the costs of third-party
operators for light rail, commuter rail, and bus services, as
well as Sound Transit’s direct costs for providing those
services.
In 2016, service levels provided by three of Sound Transit’s
four modes will be increasing. In the fourth quarter of 2016,
an additional round trip for Sounder commuter rail service is
planned. An additional 19,750 service hours (annualized
32,000 hours in future years) will be phased in for ST
Express service to help mitigate East Link Extension
construction congestion and address capacity and schedule
issues on many routes.
As a part of the annual budget, the Sound Transit Board
approves spending for each of these modal services for the
following fiscal year. The agency also maintains a Service
Implementation Plan (SIP) that includes service level and
expenditure forecasts for a six-year period. The 2016 SIP
provides the service plan on which the Adopted 2016 Budget
is based. Reviewed and recommended by the Operations
and Administration Committee, the Board adopts the 2016
SIP at the same time as adopting the budget for 2016. The
TIP only includes summary spending information for the sixyear period described in the SIP. The SIP may be read at
www.soundtransit.org.
In March 2016, Link expansion north to the University of
Washington will open, followed later in the year by the
addition of light rail service south to Angle Lake Station at
South 200th Street in SeaTac. In 2021, light rail service north
to Northgate will begin. Additional extensions of light rail
service are planned for 2023 north to Lynnwood, south to
Kent/Des Moines in the vicinity of Highline Community
College, and east to Overlake in Redmond. There are no
changes planned for Tacoma Link light rail service through
2020; however, fare collection is proposed to begin in late
2016. The extension of Tacoma Link service approved by
voters in ST2 is moving through the planning process, and
is projected to open in late 2021.
TRANSIT MODES SUMMARY
(in millions)
Link Light Rail
Tacoma Link Light Rail
Sounder Commuter Rail
ST Express Bus
Total
Adopted 2016 Transit Improvement Plan
2016
2017
2018
2019
2020
2021
Total
$88
$92
$95
$98
$104
$144
$623
5
5
5
6
6
12
39
46
49
52
54
56
59
315
124
130
130
133
132
137
786
$263
$276
$283
$291
$299
$352
$1,763
3 of 140
Projects
The Adopted 2016 TIP contains all board-authorized budgets for active projects. The majority of Sound Transit’s projects support
the planning, design, and construction of light rail, commuter rail, and express bus transit infrastructure as described in the
Sound Move and ST2 plans. The TIP uses project categories, which align with common industry practice and provides
transparency into the agency’s investment in expanding service versus investment in existing assets. Projects are also reported
by program.
PROJECTS SUMMARY BY PROJECT TYPE
(in millions)
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
System Expansion
Link
$5,085
$600
$1,246
$1,260
$987
$827
$614
$839
$11,458
Sounder
570
140
129
13
0
0
0
0
852
Regional Express
132
85
75
21
9
0
0
0
322
49
19
34
14
9
4
4
31
164
5,836
844
1,483
1,308
1,005
832
618
869
12,795
74
26
34
1
1
1
1
0
139
Rehabilitation & Replacement
132
13
28
36
5
2
24
3
242
Administrative
280
64
70
72
73
75
72
134
840
$6,322
$947
$1,614
$1,417
$1,085
$909
$715
$1,008
$14,016
Other
Subtotal
Enhancement
Total
PROJECTS SUMMARY BY PROGRAM
(in millions)
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
$5,100
$609
$1,254
$1,260
$987
$827
$614
$839
$11,491
Sounder
616
155
145
16
0
0
0
0
932
Regional Express
266
88
105
52
11
0
21
0
545
Link
Other
Total
340
94
110
89
86
81
79
168
1,048
$6,322
$947
$1,614
$1,417
$1,085
$909
$715
$1,008
$14,016
The Projects section of the TIP document displays project lifetime budgets primarily in terms of cash flow – what year dollars will
be spent and on which phase of a project. The total budget to complete a project is not necessarily included in the TIP because
the agency’s Phase Gate process requires most project budgets be approved by the Board in phases, rather than all at once.
There are a number of terms that require definition in order to clearly understand the tables in this section.
Life to Date – Sum of all project expenditures prior to the budget year.
Annual Cash Flow – Annual projected expenditures are shown for six years beginning with the budget year.
Future – Refers to the sum of projected expenditures for years seven and beyond.
Total – The total Board-approved budget for a project. It may be just preliminary engineering, final design, and right-of way, or it
could be the budget for the entire project budget.
Each of the project detail pages include the type and amount of the Board-approved lifetime budget. Lifetime budget is stated in
year-of-expenditure dollars (YOE$). Appendix B contains a summary of lifetime budgets for active Sound Move projects.
Cost Estimates – Most comparable to a baseline budget—cost estimates are for the entire project scope. Cost estimates are
periodically updated as new information becomes available. Estimates are also adjusted each year for inflation and stated in
constant-year dollars.
For ST2 projects only, project detail pages in the following subsections show project cost estimates. Cost estimates for 2008 (the
year ST2 was adopted by voters), 2015, and 2016 are stated in constant-2015 dollars. A summary of ST2 cost estimates is
provided in Appendix A.
4 of 140
Adopted 2016 Transit Improvement Plan
Lifetime Budget Changes from 2015 to 2016
The table below is a reconciliation of changes in lifetime budget from the Adopted 2015 TIP to the Adopted 2016 TIP by project
type. A breakdown of the lifetime budget changes by project is included at the beginning of the relevant subsections ahead.
SUMMARY OF PROJECT LIFETIME BUDGET CHANGES FROM 2015 TO 2016
(in millions)
2015
Lifetime
Total
Closed
Projects
New
Projects
Budget
Transfers
Increase/
Decrease
Transfer
from Cost
Estimate
2016
Lifetime
Total
System Expansion
Link Light Rail
$7,762
($267)
$764
$0
($226)
$3,425
$11,458
Sounder Commuter Rail
767
(7)
0
0
86
5
852
Regional Express
402
(106)
26
0
0
0
322
Other
164
(5)
0
0
5
0
164
9,095
(385)
790
0
(134)
3,430
12,795
Enhancement
123
0
9
0
6
0
139
Rehabilitation & Replacement
240
0
1
0
1
0
242
Administrative
840
0
0
0
0
0
840
$10,297
($385)
$800
$0
($127)
$3,430
$14,016
Subtotal
Total
Project Summaries and Detail Pages
In the Projects section, details pertaining to each project are provided as well as summaries of each program.
Summary Tables
Summary tables for all budgets approved by the Board include three views:

Projects by budget approval phase. Two exceptions are programs, which are comprised of a number of projects, and
reserves.

Subarea by allocation to Sound Transit’s five geographic subareas.

Project phase, by the agency’s work breakdown structure phases that group costs relative to activities and deliverables
such as final design, construction, and startup and testing.
Project Detail
Each active project has a full page that covers scope, lifetime budget and cashflow detail, phase gate status, and schedule and
budget risk information. For ST2 projects, cost estimate updates are included. The following is an explanation of terms used in
the project pages.
Capital Budget (in YOE dollars)
Phase Gate Passed
The most recent gate passed indicates a project’s progress. Certain Sound Move projects pre-date implementation of our Phase
Gate process and are not required to pass through gates that they would have if the process had been in place at that time.
Pending – Projects that will pass through Gate 1 before the end of the coming year
Gate 1 – Enter Project Development
Gate 5 – Establish Baseline
Gate 2 – Identify Alternatives
Gate 6 – Proceed to Construction
Gate 3 – Identify Preferred Alternative
Gate 7 – Transition to Operations
Gate 4 – Enter Final Design
Gate 8 – Close Out Project
None – Projects that advanced through project development prior to implementation of Phase Gate (includes some Sound Move
projects).
N/A – Projects not subject to the Phase Gate process, e.g., procurements, installation of equipment, etc.
Adopted 2016 Transit Improvement Plan
5 of 140
Baseline
Baseline budget is the lifetime budget for the entire project in year of expenditure dollars. The baseline budget is established
once the project scope and schedule are defined.
2015 TIP
Project lifetime budget authorized by the Board in 2015 or prior.
2016 TIP
Project lifetime budget authorized by the Board in 2016 or prior.
ST2 Project Cost Estimate (in 2015 dollars)
This section of the project page is for ST2 projects only and provides a history of funded cost estimate updates in constant
dollars. Cost estimates provided include the original 2008 estimate, prior year estimate, and budget year estimate.
Budget Risk Assessment
Estimate Type
Basis of current budget estimate used for a project:

Initial Estimate – Sound Move or ST2 program plans

Planning – preliminary conceptual estimate developed for specific sites based on limited project information

Conceptual Engineering

Scoping – itemized right-of-way and construction costs on an estimated unit price basis

PE/ED – preliminary engineering/environmental design

Final Design

Construction – full design drawings, specifications, and known unit prices

Fixed Contribution – contractual amount of funds Sound Transit is to contribute to a project implemented by another
transit agency or governmental entity. This may not reflect a project’s total cost estimate.
Budget Risk Level
Overall risk level for each project is classified as low, medium, or high, depending on the presence of uncertainties that could
impact the scope or budget.
Schedule Risk Assessment
Schedule Risk Level
Overall risk level for each project is classified as low, medium, or high depending on the presence of risk factors that could
impact the completion schedule for budgeted phases. If the project has a baseline budget, then risk is assessed at the level of
the entire project through to putting the asset into service.
2015 Budget Schedule
The year anticipated for completion of the budgeted phases of the project at the time the 2015 TIP is published.
2016 Budget Schedule
The year anticipated for completion of the budgeted phases of the project at the time the 2016 TIP is published.
Project Risk Assessment
Explanation of the budget or schedule risk for the budgeted phases of the project.
6 of 140
Adopted 2016 Transit Improvement Plan
System Expansion – Link
As a relatively young transit system, the majority of Sound Transit’s project budget is focused on building light rail to connect the
region. Both Sound Move and ST2 programs funded light rail facilities and tracks – in tunnels, at grade, and elevated. By 2023,
these two programs will extend light rail north to Lynnwood, south to Federal Way, and east to the Overlake area of Redmond.
Highlights

Complete University Link and South 200th Street Link extensions and begin passenger service along these two new light
rail extension segments.

Begin construction on East Link Extension segments in south Bellevue, downtown Bellevue-Spring District, and Bel-Red
area, with tunneling in Bellevue.

Complete preliminary engineering for a 7.8-miles light rail extension from South 200th Street to Federal Way Transit
Center and begin final design for just the first 2.4-mile segment to Kent/Des Moines Road.

Continue with final design and construction for Northgate Link Extension.

Begin final design for Lynnwood Link Extension.

Complete preliminary engineering of the preferred alternative to expand Tacoma Link.
Lifetime Budget Changes
The table below explains the changes in individual project lifetime budgets since the publication of the Adopted 2015 TIP.
BUDGET CHANGES
(in thousands)
Project
Overlake Village Bridge
Reason
Closed Project
Tacoma Link Expansion
Transfer from Cost
Estimate
Transfer from Cost
Estimate
Decrease
Link Operations &
Maintenance Facility
Northgate Link Extension
Lynnwood Link Extension
Airport Link
Federal Way Transit
Extension
East Link
Transfer from Cost
Estimate
Closed Project
Increase
Transfer from Cost
Estimate
Adopted 2016 Transit Improvement Plan
Budget Type
Explanation
Preliminary Engineering Scope and budget incorporated into East Link
Extension. Project closed.
Final Design
Begin final design, right of way activities and
vehicle procurement. Resolution No. R2015-33.
Final Design
Commence final design and early right of way
activities. Resolution No. R2015-34.
Baseline
Transfer budget for vehicle purchases to new
project - Resolution No. R2015-23 and increase
baseline to accommodate transit-oriented
development at U District Station - Resolution
No. R2015-25.
Final Design
Commence final design and early right of way
activities. Resolution No. R2015-30.
Baseline
Project completed and to be closed in 2016.
Preliminary Engineering Budget added to include preliminary
engineering from Kent/Des Moines to Federal
Way Transit Center. Resolution No. R2016-04.
Baseline
Project baseline budget established. Resolution
No. R2015-04.
Change
($5,186)
$25,216
$96,800
($231,645)
$423,742
($261,650)
$5,913
$2,878,803
7 of 140
Project
ST2 LRV Fleet Expansion
Reason
New Project
Downtown Redmond Link
Extension
New Project
Enhancements to Tacoma New Project
Link Expansion
Total
Budget Type
Baseline
Explanation
Project created to purchase light right vehicles
for Northgate, Lynnwood and East Link
extensions. Resolution No. R2015-24.
Preliminary Engineering Preliminary engineering and environmental
reviews to extend light rail from Overlake Transit
Center to Redmond Terminal Station.
Resolution No. R2016-04.
Baseline
Process grant reciepts for City of Tacoma for
transit access and station area improvements
near the Tacoma Link Expansion project.
Resolution No. R2015-36.
Change
$733,006
$28,617
$2,000
$3,695,616
TACOMA LINK LIGHT RAIL CAPITAL PROJECTS
8 of 140
Adopted 2016 Transit Improvement Plan
LINK LIGHT RAIL CAPITAL PROJECTS
Adopted 2016 Transit Improvement Plan
9 of 140
10 of 140
Adopted 2016 Transit Improvement Plan
Downtown Redmond Link Extension
4X630
Northgate Link Extension
University Link Extension
Initial Segment
South 200th Link Extension
East Link Extension
4X100
4X200
4X300
4X420
4X600
4X199
7,452
137
0
0
$595,689
0
$5,085,189
Total
442,324
4,975,724
0
203,268
23,010
0
40,561
164,837
10,511
405,778
283,451
2,068,518
1,463,828
620,769
1,102
132,279
70,366
127,671
51,784
49,853
89,480
30,745
6,951
4,120
25,694
0
25,194
500
2016
19,985
19,985
0
Life to Date
Subtotal
Northgate Link Extension Project Reserve
Subtotal
ST2 Light Rail Vehicle Fleet Expansion
400032
Reserve
First Hill Streetcar
400007
Baseline
Subtotal
Link Operations & Maintenance Satellite
Facility
Lynnwood Link Extension
400009
4X115
Tacoma Link Expansion
400008
Final Design & ROW
Federal Way Link Extension
4X445
Subtotal
Enhancements to Tacoma Link Expansion
400034
Project Number and Name
Preliminary Engineering
System Expansion
LINK
$1,230,401
0
0
1,046,421
510,425
76,779
23,250
66,207
304,310
65,342
107
178,868
125,482
43,532
9,854
5,111
15,120
3,611
1,500
2017
90,786
9,498
2,393
0
9,377
0
0
2018
$1,250,151
0
0
1,147,474
638,433
0
0
184,822
295,451
28,728
40
102,677
(in thousands)
0
1,775
0
0
0
0
2019
$987,126
0
0
940,872
641,488
0
0
589
190,120
108,636
40
46,254
44,479
2016 TIP Cashflow by Budget Approval
$827,406
0
0
789,326
576,900
0
0
0
76,929
135,457
40
38,080
36,306
0
1,775
0
0
0
0
2020
$614,192
0
0
584,303
383,807
0
0
0
37,142
163,314
40
29,889
28,116
0
1,774
0
0
0
0
2021
$838,834
50,000
50,000
747,263
317,051
0
0
0
210,198
219,916
97
41,571
40,542
0
1,030
0
0
0
0
Future
$11,457,606
50,000
50,000
10,673,708
3,677,150
383,241
2,091,768
1,756,007
1,899,756
733,006
132,780
654,491
487,861
133,628
33,002
79,407
28,617
48,790
2,000
Total
Adopted 2016 Transit Improvement Plan
11 of 140
Total
619,600
40-Row Acquisition+Permits
Total
218,585
35-Third Party
90-Contingency
0
$599,809
$5,085,189
3,009
9,737
58,715
213,924
145,326
12,697
78,856
23,864
2016
53,682
0
21,677
230,990
70-Vehicles
80-System Testing+Startup
232,303
55-Construction Services
2,716,790
482,993
50-Construction
198,031
30-Final Design+Specifications
Life to Date
364,220
20-Prelim Engineering/Env Review
Phase # and Description
10-Agency Administration
$1,245,521
11,354
570,649
103,270
474,752
2017
85,496
(in thousands)
$1,259,528
2,393
661,001
5,558
535,565
2018
55,011
$1,245,521
0
3,239
66,458
75,690
744,970
178,393
17,142
77,975
17,985
2017
63,669
(in thousands)
$1,259,528
0
0
29,198
82,723
913,145
84,421
19,122
57,834
6,604
2018
66,481
2016 TIP Cashflow by Phase
$599,809
232,385
$5,085,189
417,090
4 - East King
59,142
250,179
7,952
845,642
3 - South King
2016
50,150
6,951
3,780,643
2 - North King
5 - Pierce
Life to Date
34,863
Subarea
1 - Snohomish
System Expansion
LINK
2016 TIP Cashflow by Subarea
$987,126
0
1,216
106,082
84,177
715,143
309
10,136
25,460
203
2019
44,400
$987,126
1,775
686,525
14,123
247,382
2019
37,322
$827,406
0
5,067
133,310
69,080
527,377
22,203
8,031
21,644
208
2020
40,487
$827,406
1,775
634,394
17,609
137,550
2020
36,078
$614,192
0
5,274
161,040
53,130
332,354
0
7,431
16,788
213
2021
37,962
$614,192
1,774
454,995
21,231
101,244
2021
34,949
$838,834
72,200
1,373
215,061
54,221
336,036
25,730
14,199
17,108
249
Future
102,659
$838,834
1,030
414,111
28,589
346,579
Future
48,526
$11,457,606
72,200
40,855
951,876
710,039
6,499,739
1,075,983
307,342
778,657
247,357
Total
773,559
$11,457,606
35,002
4,071,150
1,095,165
5,873,894
Total
382,395
System Expansion
LINK
400034
Enhancements to Tacoma Link Expansion
Managed by: FIT
Scope: Engineering and streetscape design for transit access improvements and station area enhancements around the Tacoma Link Expansion
project. This project is also focused on job access needs and identify barriers that currently limit the Tacoma Hilltop residents from participation in
existing workforce training and apprenticeship programs. The City of Tacoma and Sound Transit received a $2,000,000 grant from the Federal Transit
Administration for this project. Sound Transit is the designated recipient and needs to administer the grant while the City of Tacoma will execute the
scope and provide the $500,000 in local matching funds.
The scope of this project is independent of the Tacoma Link Expansion project
Changes in lifetime budget since 2015: Resolution R2015-36 established this project during the 2016 budget development process.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$0
2015 Cost Estimate:
N/A
2016 TIP:
$2,000
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Pierce
Total
Phase
20-Prelim Engineering/Env
Review
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
0
500
1,500
0
0
0
0
0
2,000
0
500
1,500
0
0
0
0
0
2,000
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
0
500
1,500
0
0
0
0
0
2,000
0
500
1,500
0
0
0
0
0
2,000
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Fixed Contribution
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2016 Budget Schedule:
Project Risk Assessment
Although the risk is low in both schedule and budget, this project will be managed by a third party and Sound Transit will submit costs for
reimbursement. In situations such as this, the risk of not recovering funds due to ineligibility or a delay in schedule always exists.
12 of 140
Adopted 2016 Transit Improvement Plan
2017
System Expansion
LINK
4X445
Federal Way Link Extension
Managed by: PEPD
Scope: Federal Way Link Extension project adds approximately 7.8 miles of light rail from S. 200th Street in the city of SeaTac to the Federal Way
Transit Center. Alternatives analysis and environmental scoping were completed in 2013 and a draft environmental impact statement was published in
April 2015. Completion of preliminary engineering and publication of a Final Environmental Impact Statement is anticipated in late 2016. The project
will transition to final design in 2017. Currently, the agency's Financial Plan includes construction for the initial 2.4-mile segment to Kent/Des Moines
only. The Board has approved additional budget (Resolution R2016-04) to complete preliminary engineering from Kent/Des Moines through to Federal
Way Transit Center.
Changes in lifetime budget since 2015: With Resolution R2016-04, the Board approved an additional $5.9 million to include preliminary engineering
from Kent/Des Moines Station to Federal Way Transit Center, plus additional third-party coordination and right-of-way activities to the project scope.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
3-Identify Preferred Alternative
Baseline:
$0
2008 Cost Estimate:
$492,281
2015 TIP:
$42,877
2015 Cost Estimate:
$437,636
2016 TIP:
$48,790
2016 Cost Estimate:
$437,636
TIP Cashflow (in thousands)
Subarea
South King
Total
Phase
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
19,985
25,194
3,611
0
0
0
0
0
48,790
19,985
25,194
3,611
0
0
0
0
0
48,790
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
3,288
4,369
1,728
0
0
0
0
0
9,385
20-Prelim Engineering/Env
Review
16,162
15,660
1,507
0
0
0
0
0
33,329
35-Third Party
195
2,254
0
0
0
0
0
0
2,449
40-Row Acquisition+Permits
340
2,911
376
0
0
0
0
0
3,627
19,985
25,194
3,611
0
0
0
0
0
48,790
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Planning
High
Schedule Risk Level:
High
2015 Budget Schedule:
2016
2016 Budget Schedule:
2017
Project Risk Assessment
Project is entering environmental review and beginning preliminary engineering work. Uncertainties exist in design, environmental, third party, and
jurisdictional requirements that could present budget and schedule risks.
Adopted 2016 Transit Improvement Plan
13 of 140
System Expansion
4X630
LINK
Managed by: PEPD
Downtown Redmond Link Extension
Scope: Downtown Redmond Link Extension includes environmental reviews and preliminary engineering only to establish route and station locations for a 3.7
mile extension of light rail from Overlake Transit Center to Redmond Terminal Station.
Changes in lifetime budget since 2015: This new project was establish by Resolution R2016-04.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
Pending
Baseline:
$0
2008 Cost Estimate:
2015 TIP:
$0
2015 Cost Estimate:
$21,997
$0
2016 TIP:
$28,617
2016 Cost Estimate:
$18,195
TIP Cashflow (in thousands)
Subarea
East King
Total
Phase
Life to Date
2016
2017
2018
0
4,120
15,120
9,377
2019
2020
28,617
0
4,120
15,120
9,377
28,617
2016
2017
2018
0
815
2,745
1,746
5,306
20-Prelim Engineering/Env Review
0
2,805
10,550
6,406
19,761
35-Third Party
0
450
1,125
925
2,500
40-Row Acquisition+Permits
0
50
700
300
1,050
4,120
15,120
9,377
28,617
Estimate Type:
Budget Risk Level:
2021
Future
Total
Life to Date
Budget Risk Assessment
2020
Future
10-Agency Administration
Total
2019
2021
Total
Schedule Risk Assessment
Planning
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2016 Budget Schedule:
2018
Project Risk Assessment
Project is beginning preliminary engineering work. Uncertainties exist in design, environmental, third party, and jurisdictional requirements that could present
budget and schedule risks.
14 of 140
Adopted 2016 Transit Improvement Plan
System Expansion
LINK
400008
Tacoma Link Expansion
Managed by: DECM
Scope: In cooperation with the city of Tacoma and Pierce Transit, design and construction of the selected expansion of Tacoma Link from north
downtown Tacoma to the Stadium District and Hilltop.
Lifetime budget increased per Resolution R2015-33 by $25,216,229 for the commencement of final design, right of way activities and vehicle
procurement.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
4-Enter Final Design
Baseline:
$0
2008 Cost Estimate:
$100,162
2015 TIP:
$33,002
2015 Cost Estimate:
$135,876
2016 TIP:
$33,002
2016 Cost Estimate:
$135,876
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
6,951
7,452
9,854
2,393
1,775
1,775
1,774
1,030
33,002
6,951
7,452
9,854
2,393
1,775
1,775
1,774
1,030
33,002
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
1,940
1,332
1,629
1,279
1,175
1,175
1,174
898
10,600
20-Prelim Engineering/Env
Review
4,987
260
599
0
0
0
0
26
5,872
0
2,450
6,125
550
550
550
550
55
10,830
Pierce
Total
Phase
30-Final Design+Specifications
35-Third Party
40-Row Acquisition+Permits
70-Vehicles
Total
0
125
125
50
50
50
50
50
500
24
2,285
377
514
0
0
0
0
3,200
0
1,000
1,000
0
0
0
0
0
2,000
6,951
7,452
9,854
2,393
1,775
1,775
1,774
1,030
33,002
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
PE/ED
High
Schedule Risk Level:
Low
2015 Budget Schedule:
2015
2016 Budget Schedule:
2018
Project Risk Assessment
The choice to extend the length of the preferred alternative chosen may exceed budget. Project requires continued coordination with community
stakeholders and contribution from public/private partners.
Adopted 2016 Transit Improvement Plan
15 of 140
System Expansion
LINK
400009
Link Operations & Maintenance Satellite Facility
Managed by: DECM
Scope: Development, design, and construction of a light rail operations and maintenance facility in support of link system expansion.
Resolution R2015-34 approved in Dec 2015 increased lifetime budget to $133,628,000 for the commencement of final design and early ROW
activities.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
4-Enter Final Design
Baseline:
$0
2008 Cost Estimate:
$298,615
2015 TIP:
$133,628
2015 Cost Estimate:
$251,589
2016 TIP:
$133,628
2016 Cost Estimate:
$251,589
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
Snohomish
6,456
10,469
9,142
1,995
0
0
0
0
28,062
North King
5,134
8,326
7,270
1,586
0
0
0
0
22,316
South King
5,903
9,572
8,358
1,824
0
0
0
0
25,657
13,251
21,487
18,762
4,094
0
0
0
0
57,594
30,745
49,853
43,532
9,498
0
0
0
0
133,628
East King
Total
Phase
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
1,274
1,963
0
0
0
0
0
0
3,237
20-Prelim Engineering/Env
Review
6,305
3,886
0
0
0
0
0
0
10,191
35-Third Party
40-Row Acquisition+Permits
55-Construction Services
Total
0
1,060
590
0
0
0
0
0
1,650
23,166
42,644
42,642
9,498
0
0
0
0
117,950
0
300
300
0
0
0
0
0
600
30,745
49,853
43,532
9,498
0
0
0
0
133,628
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Final Design
High
Schedule Risk Level:
High
2015 Budget Schedule:
2016
2016 Budget Schedule:
2016
Project Risk Assessment
Design challenges and coordination efforts with third parties, stakeholders, and jurisdictions have the potential to impact both the budget and the
schedule for completing design activities. This could result in potential schedule delays affecting the opening of the facility in 2020 and adding costs
to the project.
16 of 140
Adopted 2016 Transit Improvement Plan
System Expansion
LINK
4X115
Lynnwood Link Extension
Managed by: DECM
Scope: Lynnwood Link Extension will extend light rail approximately 8.5 miles from Northgate through Shoreline and Mountlake Terrace to Lynnwood.
In November 2015 Resolution R2015-30 increased the lifetime budget by $423,742,313 to commence final design and right of way activities.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
4-Enter Final Design
Baseline:
$0
2008 Cost Estimate:
$1,668,579
2015 TIP:
$487,861
2015 Cost Estimate:
$1,421,593
2016 TIP:
$487,861
2016 Cost Estimate:
$1,421,593
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
28,274
38,420
68,513
49,569
24,286
19,823
15,351
22,136
266,372
23,510
31,946
56,969
41,217
20,194
16,483
12,765
18,406
221,489
51,784
70,366
125,482
90,786
44,479
36,306
28,116
40,542
487,861
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
7,345
6,532
9,553
12,017
9,985
10,115
10,350
22,409
88,305
20-Prelim Engineering/Env
Review
37,997
412
3,590
0
0
0
0
0
42,000
0
20,900
37,050
29,722
4,228
5,284
5,284
8,984
111,453
Snohomish
North King
Total
Phase
30-Final Design+Specifications
35-Third Party
40-Row Acquisition+Permits
55-Construction Services
Total
352
2,318
3,000
3,000
2,000
2,000
2,000
2,729
17,400
6,090
32,953
61,889
22,847
0
0
0
0
123,779
0
7,250
10,400
23,201
28,267
18,906
10,481
6,419
104,925
51,784
70,366
125,482
90,786
44,479
36,306
28,116
40,542
487,861
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
PE/ED
Medium
Schedule Risk Level:
Medium
2015 Budget Schedule:
2016
2016 Budget Schedule:
2018
Project Risk Assessment
Budget Risk: Working with Final Designer, GC/CM contractor, and Construction Management Consultant in 2016 to develop updated construction
cost estimates.
Schedule Risk: Coordination efforts with multiple third parties, stakeholders, and jurisdictions, and complying with the requirements of the Federal
Transit Administration’s (FTA) New Starts process has the potential to impact the schedule for completion of Final Design.
Adopted 2016 Transit Improvement Plan
17 of 140
System Expansion
LINK
400007
First Hill Streetcar
Managed by: PEPD
Scope: Provide funding for planning, design and construction of a street car providing connections between Capitol Hill and International
District/Chinatown stations via the First Hill neighborhood. Substantial completion of the system was accomplished in 2014, with revenue operations
commencing in 2015. Balance of activity supports work items related to the completion of the project.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
5-Establish Baseline
Baseline:
$132,780
2008 Cost Estimate:
$138,141
2015 TIP:
$132,780
2015 Cost Estimate:
$136,590
2016 TIP:
$132,780
2016 Cost Estimate:
$136,590
TIP Cashflow (in thousands)
Subarea
North King
Total
Phase
10-Agency Administration
35-Third Party
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
132,279
137
107
40
40
40
40
97
132,780
132,279
137
107
40
40
40
40
97
132,780
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
218
137
107
40
40
40
40
97
719
132,061
0
0
0
0
0
0
0
132,061
132,279
137
107
40
40
40
40
97
132,780
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Fixed Contribution
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2015
2016 Budget Schedule:
2025
Project Risk Assessment
The project is in revenue service and overall budget and schedule risk is low.
18 of 140
Adopted 2016 Transit Improvement Plan
System Expansion
LINK
400032
ST2 Light Rail Vehicle Fleet Expansion
Managed by: DECM
Scope: To provide project management, design, manufacturing, delivery, assembly inspection and testing in the support of a procurement of 122 low
floor light rail vehicles (LRVs) to meet fleet requirements to support revenue service of all the ST2 light rail expansion projects; and centralize
procurement of the LRVs for Northgate Link Extension, Lynnwood Link Extension and East Link Extension into one project.
New project created by adoption of the Sound Transit Board in September 2015 (R2015-24, adopted 9/24/15) with a baseline project budget of $733
million.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
6-Proceed to Construction
Baseline:
$733,006
2008 Cost Estimate:
N/A
2015 TIP:
$733,006
2015 Cost Estimate:
N/A
2016 TIP:
$733,006
2016 Cost Estimate:
$733,006
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
Snohomish
132
1,261
7,841
3,447
13,036
16,255
19,598
26,390
87,961
North King
330
3,153
19,603
8,618
32,591
40,637
48,994
65,975
219,902
South King
143
1,366
8,495
3,735
14,123
17,609
21,231
28,589
95,291
East King
496
4,730
29,404
12,928
48,886
60,956
73,491
98,962
329,853
1,102
10,511
65,342
28,728
108,636
135,457
163,314
219,916
733,006
Total
Phase
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
16
936
536
380
479
435
446
1,521
4,748
55-Construction Services
1,086
989
1,217
1,850
2,075
1,712
1,828
3,334
14,090
0
8,587
63,590
26,498
106,082
133,310
161,040
215,061
714,168
1,102
10,511
65,342
28,728
108,636
135,457
163,314
219,916
733,006
70-Vehicles
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Medium
Schedule Risk Level:
Medium
2015 Budget Schedule:
2024
2016 Budget Schedule:
2024
Project Risk Assessment
The project is in the initial stages of development and identified risks include establishing a set of specifications that assure the new LRV(s) are
system compatible and are interchangeable with the existing fleet.
Adopted 2016 Transit Improvement Plan
19 of 140
System Expansion
LINK
4X100
Northgate Link Extension
Managed by: DECM
Scope: The Northgate Link Extension extends light rail 4.3-miles from the University of Washington Station north under the campus via twin bored
tunnels to an underground U-District Station along Brooklyn Avenue NE between NE 43rd and NE 45th Streets, and underground Roosevelt Station
along 12th Avenue NE between NE 65th Street and NE 67th Street, and continuing to an elevated station in Northgate along 1st Avenue NE spanning
NE 103rd Street. The Northgate Link Extension is scheduled to be completed in September 2021 and will provide an interim terminus for Link at
Northgate until the Lynnwood Link Extension is in service, currently anticipated in 2023.
The budget was amended by two resolutions of the Sound Transit Board for a net reduction of $231.6 million to the project baseline budget; in
September 2015 to transfer budget for Vehicles to the new ST2 LRV Fleet Expansion project (Resolution R2015-23), and in October 2015 to increase
the baseline budget for changes to the U District Station to accommodate transit-oriented development (Resolution R2015-25).
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
6-Proceed to Construction
Baseline:
$1,899,756
2008 Cost Estimate:
$1,734,306
2015 TIP:
$1,899,756
2015 Cost Estimate:
$1,904,550
2016 TIP:
$1,899,756
2016 Cost Estimate:
$1,904,550
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
620,769
164,837
304,310
295,451
190,120
76,929
37,142
210,198
1,899,756
620,769
164,837
304,310
295,451
190,120
76,929
37,142
210,198
1,899,756
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
35,406
13,057
16,168
15,518
13,605
10,259
8,291
35,576
147,879
20-Prelim Engineering/Env
Review
15,077
0
0
0
0
0
0
0
15,077
30-Final Design+Specifications
93,213
12,203
4,603
4,869
4,511
2,960
2,091
4,716
129,167
North King
Total
Phase
35-Third Party
40-Row Acquisition+Permits
50-Construction
55-Construction Services
5,057
1,710
1,752
1,273
737
350
224
696
11,800
91,852
2,173
4,996
2,240
309
0
0
25,730
127,300
350,623
117,565
258,374
257,898
159,237
50,553
12,528
108,314
1,315,093
29,542
18,128
18,417
13,653
10,504
7,739
8,734
11,593
118,310
70-Vehicles
0
0
0
0
0
0
0
0
0
80-System Testing+Startup
0
0
0
0
1,216
5,067
5,274
1,373
12,930
90-Contingency
0
0
0
0
0
0
0
22,200
22,200
620,769
164,837
304,310
295,451
190,120
76,929
37,142
210,198
1,899,756
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Medium
Schedule Risk Level:
Medium
2015 Budget Schedule:
2021
2016 Budget Schedule:
2021
Project Risk Assessment
Risks associated with underground conditions, limited site access, deep stations and groundborne noise and vibration have the potential to impact
costs and schedule. TBM progress continues to be slower than planned, which has the potential for delaying critical path work.
20 of 140
Adopted 2016 Transit Improvement Plan
System Expansion
LINK
4X200
University Link Extension
Managed by: DECM
Scope: University Link Extension is a 3.15-mile light rail extension located entirely underground extending east from the Downtown Seattle Transit
Tunnel, under I-5 to an underground Capitol Hill Station that will serve the First Hill/Capitol Hill urban center. The tunnel route crosses under the Lake
Washington Ship Canal to an interim terminus in an underground University of Washington Station near Husky Stadium. University Link Extension is
expected to generate high ridership by connecting the three major population and employment centers of Downtown Seattle, Capitol Hill, and the
University District when it opens in 2016.
Changes in lifetime budget since 2015: None
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
6-Proceed to Construction
Baseline:
$1,756,007
2008 Cost Estimate:
N/A
2015 TIP:
$1,756,007
2015 Cost Estimate:
N/A
2016 TIP:
$1,756,007
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
North King
Total
Phase
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
1,463,828
40,561
66,207
184,822
589
0
0
0
1,756,007
1,463,828
40,561
66,207
184,822
589
0
0
0
1,756,007
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
74,594
7,438
12,970
18,053
500
0
0
0
113,554
20-Prelim Engineering/Env
Review
24,261
0
0
0
0
0
0
0
24,261
30-Final Design+Specifications
84,741
1,659
3,082
826
0
0
0
0
90,308
35-Third Party
10,988
600
1,020
6,038
0
0
0
0
18,646
40-Row Acquisition+Permits
125,599
10
145
26,578
0
0
0
0
152,332
50-Construction
956,828
24,650
36,936
130,281
89
0
0
0
1,148,783
55-Construction Services
83,007
3,296
8,164
347
0
0
0
0
94,814
70-Vehicles
99,191
150
1,868
2,700
0
0
0
0
103,909
4,619
2,759
2,022
0
0
0
0
0
9,400
1,463,828
40,561
66,207
184,822
589
0
0
0
1,756,007
80-System Testing+Startup
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2016
2016 Budget Schedule:
2016
Project Risk Assessment
Budget and schedule risks significantly decreased after the completion of tunneling work in 2013. Some low-level risk associated with tighter
constraints and coordination between Civil station contractors and Systems contractor. Some additional risk had surfaced regarding the LRV retrofit
project; although those risks were captured in that project. Execution of an early revenue service start date could be affected by coordination of
contractors and work necessary for completion.
Adopted 2016 Transit Improvement Plan
21 of 140
System Expansion
LINK
4X300
Initial Segment
Managed by: DECM
Scope: The 13.9-mile Initial Segment of the Link light rail system connecting South 154th Street in Tukwila with downtown Seattle opened for service
in July 2009. All work completed in 2015 and the project is expected to close out in 2016; budget cash flow in 2017 reflects surplus budget.
Changes in lifetime budget since 2015: None
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
7-Transition to Operations
Baseline:
$2,070,000
2008 Cost Estimate:
N/A
2015 TIP:
$2,091,768
2015 Cost Estimate:
N/A
2016 TIP:
$2,091,768
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
North King
South King
Total
Phase
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
1,532,358
0
17,223
0
0
0
0
0
1,549,582
536,160
0
6,026
0
0
0
0
0
542,186
2,068,518
0
23,250
0
0
0
0
0
2,091,768
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
186,785
0
77
0
0
0
0
0
186,862
20-Prelim Engineering/Env
Review
33,268
0
0
0
0
0
0
0
33,268
143,997
0
0
0
0
0
0
0
143,997
61,101
0
0
0
0
0
0
0
61,101
30-Final Design+Specifications
35-Third Party
40-Row Acquisition+Permits
205,046
0
0
0
0
0
0
0
205,046
1,187,370
0
23,171
0
0
0
0
0
1,210,541
55-Construction Services
102,528
0
1
0
0
0
0
0
102,529
70-Vehicles
131,799
0
0
0
0
0
0
0
131,799
16,625
0
0
0
0
0
0
0
16,625
2,068,518
0
23,250
0
0
0
0
0
2,091,768
50-Construction
80-System Testing+Startup
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2009
2016 Budget Schedule:
2009
Project Risk Assessment
N/A
22 of 140
Adopted 2016 Transit Improvement Plan
System Expansion
LINK
4X420
South 200th Link Extension
Managed by: DECM
Scope: The South 200th Link Extension will extend light rail approximately 1.6 miles south from Sea-Tac/Airport Station to Angle Lake Station at
South 200th Street. The design features an elevated light rail guide way, an elevated station, and detached park-and-ride facility at South 200th. The
project is being delivered through a design-build (DB) delivery strategy and is expected to begin revenue service operation in 2016.
Changes in lifetime budget since 2015: None
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
6-Proceed to Construction
Baseline:
$383,241
2008 Cost Estimate:
$404,745
2015 TIP:
$383,241
2015 Cost Estimate:
$385,788
2016 TIP:
$383,241
2016 Cost Estimate:
$385,788
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
283,451
23,010
76,779
0
0
0
0
0
383,241
283,451
23,010
76,779
0
0
0
0
0
383,241
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
12,215
2,349
2,200
0
0
0
0
0
16,764
20-Prelim Engineering/Env
Review
5,698
0
0
0
0
0
0
0
5,698
30-Final Design+Specifications
8,727
0
1,174
0
0
0
0
0
9,902
South King
Total
Phase
35-Third Party
40-Row Acquisition+Permits
50-Construction
55-Construction Services
80-System Testing+Startup
Total
3,358
607
3,120
0
0
0
0
0
7,085
37,773
300
5,476
0
0
0
0
0
43,549
204,069
15,965
60,988
0
0
0
0
0
281,022
11,177
3,539
2,605
0
0
0
0
0
17,322
433
250
1,217
0
0
0
0
0
1,900
283,451
23,010
76,779
0
0
0
0
0
383,241
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2016
2016 Budget Schedule:
2016
Project Risk Assessment
Project being delivered through alternative design-build delivery strategy. The project approaches revenue service in 2016, the schedule and budget
risks are low. In 2016, construction work will conclude and close coordination of system testing between University Link and South 200th may be
required between both projects.
Adopted 2016 Transit Improvement Plan
23 of 140
System Expansion
LINK
4X600
East Link Extension
Managed by: DECM
Scope: East Link extends light rail 14 miles to East King County from downtown Seattle serving Mercer Island via I-90, Bellevue and the Overlake area
of Redmond, with ten new light rail stations. Revenue service to the Overlake Transit Center is forecasted for mid-2023.
Resolution R2015-04 established the baseline budget for the project.
Changes in lifetime budget since 2015: None
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
6-Proceed to Construction
Baseline:
$3,677,150
2008 Cost Estimate:
$3,311,457
2015 TIP:
$3,677,150
2015 Cost Estimate:
$3,134,891
2016 TIP:
$3,677,150
2016 Cost Estimate:
$3,134,891
TIP Cashflow (in thousands)
Subarea
North King
East King
Total
Phase
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
2,435
1,220
3,063
3,831
3,849
3,461
2,303
1,902
22,063
403,343
202,048
507,363
634,603
637,639
573,439
381,504
315,149
3,655,087
405,778
203,268
510,425
638,433
641,488
576,900
383,807
317,051
3,677,150
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
41,140
14,755
15,957
17,450
18,617
18,463
17,661
42,157
186,200
20-Prelim Engineering/Env
Review
54,276
340
240
198
203
208
213
222
55,900
152,314
41,643
25,941
21,867
16,172
12,849
8,862
3,352
283,000
5,473
3,572
6,410
7,836
7,349
5,631
5,157
10,724
52,150
129,710
62,000
61,792
22,445
0
22,203
0
0
298,150
17,901
55,744
365,501
524,966
555,816
476,824
319,827
227,721
2,544,300
30-Final Design+Specifications
35-Third Party
40-Row Acquisition+Permits
50-Construction
55-Construction Services
Total
4,964
25,214
34,586
43,672
43,331
40,722
32,087
32,875
257,450
405,778
203,268
510,425
638,433
641,488
576,900
383,807
317,051
3,677,150
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
High
Schedule Risk Level:
Medium
2015 Budget Schedule:
2023
2016 Budget Schedule:
2023
Project Risk Assessment
The project presents technical and third party approval challenges, and requires close coordination with stakeholders and other governmental
jurisdictions. Timely decision-making, maintaining the schedule for completing Final Design, and Construction contracts procurement will be
necessary in 2016. Project costs are heavily influenced by the competitiveness in the construction market.
24 of 140
Adopted 2016 Transit Improvement Plan
System Expansion
LINK
4X199
Northgate Link Extension Project Reserve
Managed by: DECM
Scope: Project reserve created for the Northgate Link Extension that, if required, can be directed to mitigate budget risks associated with project
construction. Funding for the reserve originated from unused funds in the project reserve that was set up for the Initial Segment. The project reserve
cannot be used for additional scope and approval for its use requires super-majority approval by the Board.
Changes in lifetime budget since 2015: None
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
None
Baseline:
$50,000
2008 Cost Estimate:
N/A
2015 TIP:
$50,000
2015 Cost Estimate:
N/A
2016 TIP:
$50,000
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
North King
Total
Phase
90-Contingency
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
0
0
0
0
0
0
0
50,000
50,000
0
0
0
0
0
0
0
50,000
50,000
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
0
0
0
0
0
0
0
50,000
50,000
0
0
0
0
0
0
0
50,000
50,000
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Medium
Schedule Risk Level:
Medium
2015 Budget Schedule:
2021
2016 Budget Schedule:
2021
Project Risk Assessment
Reflects overall Northgate Link Extension project risk.
Adopted 2016 Transit Improvement Plan
25 of 140
System Expansion – Sounder
Sounder commuter rail provides rail service between Everett and Seattle from the north and Lakewood to Seattle from the south.
Projects are now focused on rail station improvements among its 12 commuter rail stations, track and signal improvements in
Tacoma, and the improvement of track and signals between Lakewood and Nisqually.
Highlights

Continue construction on track and signal improvements from Tacoma to Nisqually along Sound Transit owned right-ofway for Point Defiance Bypass.

Increase capacity at the layover facility in Lakewood to accommodate up to seven train sets.

Conduct preliminary planning and due diligence for development of a commuter rail base to support operations and
maintainance of the Sounder fleet.
Lifetime Budget Changes
The table below explains the changes in individual project lifetime budgets since the publication of the Adopted 2015 TIP.
BUDGET CHANGES
(in thousands)
Project
Permitting & Mitigation
Puyallup Station
Improvements
Sounder Yard & Shops
Facility
Tacoma Trestle Track &
Signal
Total
26 of 140
Reason
Budget Type
Closed
Baseline
Transfer from Cost Preliminary Engineering
Estimate
Transfer from Cost Preliminary Engineering
Estimate
Increase
Baseline
Explanation
Project closed in 2015.
Project anticipates making a strategic property
acquisition.
Aquire property prior to project baseline.
Change
($6,516)
$4,867
Project was baselined. Resolution No. R201509.
$85,955
$560
$84,867
Adopted 2016 Transit Improvement Plan
SOUNDER COMMUTER RAIL CAPITAL PROJECTS
Adopted 2016 Transit Improvement Plan
27 of 140
28 of 140
Adopted 2016 Transit Improvement Plan
Puyallup Station Improvements
Sumner Station Improvements
Lakewood Station Improvements
300017
300018
300019
Sounder South Expanded Service
3X510
Tacoma Trestle Track & Signal
Sounder Yard Expansion
M St-Lakewood Track & Signal
D St-M St Track & Signal
Mukilteo Station, S Platform
Passenger Information System
Tukwila Station
Sounder ST2 Fleet Expansion
300021
300026
3X130
3X135
3X206
3X216
3X236
7X755
Baseline
Point Defiance Bypass
300027
Final Design & ROW
Sounder Yard & Shops Facility
300004
Preliminary Engineering
Project Number and Name
SOUNDER
System Expansion
353,461
$570,209
Total
40,548
36,908
6,441
14,395
152,934
80,431
2,004
19,799
208,344
194,146
14,198
8,403
Subtotal
Subtotal
Subtotal
262
4,463
1,681
1,997
Life to Date
$140,089
71,265
8,982
727
0
2,819
460
5
11,405
46,866
56,782
4,300
52,482
12,042
138
1,173
5,945
4,786
2016
$128,995
62,468
0
8,333
0
1,099
4,868
217
7,141
40,810
64,842
3,522
61,320
1,686
3
836
789
58
2017
13,034
0
0
0
0
0
0
0
13,034
0
0
0
0
0
0
0
0
2018
$13,034
(in thousands)
$0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
2019
2016 TIP Cashflow by Budget Approval
$0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
2020
$0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
2021
$14
14
0
0
14
0
0
0
0
0
0
0
0
0
0
0
0
0
Future
$852,340
500,241
49,530
45,969
6,455
18,313
158,262
80,654
20,550
120,509
329,968
201,968
128,000
22,131
404
6,472
8,414
6,841
Total
Adopted 2016 Transit Improvement Plan
29 of 140
Total
Total
35,064
30-Final Design+Specifications
80-System Testing+Startup
70-Vehicles
$570,209
1,046
58,452
9,561
169,688
50-Construction
55-Construction Services
259,809
40-Row Acquisition+Permits
865
14,434
20-Prelim Engineering/Env Review
35-Third Party
21,249
42
Life to Date
10-Agency Administration
02-Operation+Maintenance-Agency
Phase # and Description
$570,209
514,157
39,863
3 - South King
5 - Pierce
16,189
Life to Date
1 - Snohomish
Subarea
SOUNDER
System Expansion
2016
2017
$128,995
115,798
12,089
1,107
$13,034
13,034
0
0
2018
$140,089
0
8,832
11,550
94,700
9,754
759
4,699
5,227
4,568
0
2016
$128,995
64
0
4,607
107,178
6,103
943
2,516
2,858
4,726
0
2017
(in thousands)
$13,034
0
0
1,053
10,767
267
54
771
0
122
0
2018
2016 TIP Cashflow by Phase
$140,089
129,825
6,726
3,537
(in thousands)
2016 TIP Cashflow by Subarea
$0
0
0
0
0
0
0
0
0
0
0
2019
$0
0
0
0
2019
$0
0
0
0
0
0
0
0
0
0
0
2020
$0
0
0
0
2020
$0
0
0
0
0
0
0
0
0
0
0
2021
$0
0
0
0
2021
$14
0
0
0
11
0
0
0
0
3
0
Future
$14
6
4
3
Future
Total
$852,340
1,110
67,284
26,770
382,343
275,932
2,621
43,049
22,519
30,669
42
Total
$852,340
772,821
58,682
20,836
System Expansion
SOUNDER
300004
Sounder Yard & Shops Facility
Managed by: PEPD
Scope: Sound Transit is evaluating operations and maintenance cost efficiencies associated with the development of commuter rail operations and
maintenance facilities to support existing and future service levels. Funding has been approved for completing site selection, preliminary engineering
(30% design), and environmental determination. Detailed project oversight requires a step by step involvement of the Board before moving from one
project phase to another.
Changes in lifetime budget since 2015: Increased by $560 thousand for property acquisition.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
2-Identify Alternatives
Baseline:
$0
2008 Cost Estimate:
$171,727
2015 TIP:
$6,281
2015 Cost Estimate:
$149,559
2016 TIP:
$6,841
2016 Cost Estimate:
$149,559
TIP Cashflow (in thousands)
Subarea
Life to Date
Snohomish
Pierce
Total
Phase
10-Agency Administration
20-Prelim Engineering/Env
Review
40-Row Acquisition+Permits
Total
2016
2017
2018
2019
2020
2021
Future
Total
300
718
9
0
0
0
0
0
1,026
1,698
4,068
49
0
0
0
0
0
5,815
1,997
4,786
58
0
0
0
0
0
6,841
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
369
491
0
0
0
0
0
0
860
1,591
3,481
44
0
0
0
0
0
5,116
37
814
14
0
0
0
0
0
865
1,997
4,786
58
0
0
0
0
0
6,841
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
PE/ED
High
Schedule Risk Level:
High
2015 Budget Schedule:
2016
2016 Budget Schedule:
2016
Project Risk Assessment
Uncertainties exist in siting, design, environmental, third party and jurisdictional requirements that present budget and schedule risks.
30 of 140
Adopted 2016 Transit Improvement Plan
System Expansion
SOUNDER
300018
Sumner Station Improvements
Managed by: PEPD
Scope: The Sumner Station Access Improvement Project is evaluating potential capital improvements to facilitate access to Sumner Station for
pedestrians, bicyclists, and drivers. Improvements include additional parking facilities, pedestrian access improvements, bicycle route improvements,
and secure bicycle storage.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
3-Identify Preferred Alternative
Baseline:
$0
2008 Cost Estimate:
$48,603
2015 TIP:
$6,472
2015 Cost Estimate:
$44,113
2016 TIP:
$6,472
2016 Cost Estimate:
$44,113
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
4,463
1,173
836
0
0
0
0
0
6,472
4,463
1,173
836
0
0
0
0
0
6,472
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
353
266
143
0
0
0
0
0
762
20-Prelim Engineering/Env
Review
1,305
737
643
0
0
0
0
0
2,685
40-Row Acquisition+Permits
2,708
170
34
0
0
0
0
0
2,912
97
0
16
0
0
0
0
0
113
4,463
1,173
836
0
0
0
0
0
6,472
Pierce
Total
Phase
10-Agency Administration
50-Construction
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
PE/ED
Medium
Schedule Risk Level:
Medium
2015 Budget Schedule:
2016
2016 Budget Schedule:
2016
Project Risk Assessment
Uncertainties exist in siting, design, environmental, third party and jurisdictional requirements that present budget and schedule risks.
Adopted 2016 Transit Improvement Plan
31 of 140
System Expansion
SOUNDER
300017
Puyallup Station Improvements
Managed by: PEPD
Scope: The Puyallup Station Access Improvement Project is evaluating potential capital improvements to facilitate access to Puyallup Station for
pedestrians, bicyclists, and drivers. Improvements include additional parking facilities, pedestrian access improvements, bicycle route improvements,
and secure bicycle storage.
Changes in lifetime budget since 2015: Increase project budget $4.8 million for property acquisition.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
3-Identify Preferred Alternative
Baseline:
$0
2008 Cost Estimate:
$68,525
2015 TIP:
$3,547
2015 Cost Estimate:
$57,977
2016 TIP:
$8,414
2016 Cost Estimate:
$57,977
TIP Cashflow (in thousands)
Subarea
Pierce
Total
Phase
10-Agency Administration
20-Prelim Engineering/Env
Review
40-Row Acquisition+Permits
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
1,681
5,945
789
0
0
0
0
0
8,414
1,681
5,945
789
0
0
0
0
0
8,414
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
352
264
141
0
0
0
0
0
757
1,301
737
643
0
0
0
0
0
2,680
28
4,944
6
0
0
0
0
0
4,977
1,681
5,945
789
0
0
0
0
0
8,414
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
PE/ED
Medium
Schedule Risk Level:
Medium
2015 Budget Schedule:
2016
2016 Budget Schedule:
2016
Project Risk Assessment
Uncertainties exist in siting, design, environmental, third party and jurisdictional requirements that present budget and schedule risks.
32 of 140
Adopted 2016 Transit Improvement Plan
System Expansion
SOUNDER
300019
Lakewood Station Improvements
Managed by: PEPD
Scope: Construction of a pedestrian bridge in the city of Lakewood connecting the community to the northwest of Lakewood Station with the station.
This work is partly funded by a capped contribution from Sound Transit. Additional access improvements contemplated in ST2 and reflected in the ST2
cost estimate were evaluated through the Station Access and Demand Study project and may be proposed in the future.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
Pending
Baseline:
$0
2008 Cost Estimate:
$44,466
2015 TIP:
$404
2015 Cost Estimate:
$37,798
2016 TIP:
$404
2016 Cost Estimate:
$37,798
TIP Cashflow (in thousands)
Subarea
Pierce
Total
Phase
10-Agency Administration
35-Third Party
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
262
138
3
0
0
0
0
0
404
262
138
3
0
0
0
0
0
404
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
24
13
3
0
0
0
0
0
40
238
125
0
0
0
0
0
0
363
262
138
3
0
0
0
0
0
404
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Fixed Contribution
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2014
2016 Budget Schedule:
2016
Project Risk Assessment
N/A
Adopted 2016 Transit Improvement Plan
33 of 140
System Expansion
SOUNDER
300027
Point Defiance Bypass
Managed by: DECM
Scope: Sound Transit will administer the construction of the Point Defiance Bypass Project which will construct a new second track adjacent to Sound
Transit’s existing main line between South Tacoma (South 66th Street Bridge) and Lakewood (Bridgeport Way) and install new rails, ties, and ballast
on Sound Transit’s existing track between Lakewood and Nisqually. Improvements will be made at the connection to BNSF’s main line near Nisqually
and safety improvements will be made at some existing at-grade crossings within the project corridor.
The project started in 2014 with $6.4 million lifetime budget which is used for the procurement of a construction services contract, right-of-way
acquisition, and associated staff costs to administer the same in support of the construction of a second track between South Tacoma and Lakewood.
These costs are reimbursable through the Federal High Speed Rail grant administered by the Washington State Department of Transportation
(WSDOT).
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
5-Establish Baseline
Baseline:
$128,000
2008 Cost Estimate:
N/A
2015 TIP:
$128,000
2015 Cost Estimate:
N/A
2016 TIP:
$128,000
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Pierce
Total
Phase
02-Operation+MaintenanceAgency
10-Agency Administration
30-Final Design+Specifications
40-Row Acquisition+Permits
50-Construction
55-Construction Services
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
14,198
52,482
61,320
0
0
0
0
0
128,000
14,198
52,482
61,320
0
0
0
0
0
128,000
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
42
0
0
0
0
0
0
0
42
1,038
1,235
545
0
0
0
0
0
2,818
103
0
97
0
0
0
0
0
200
49
10
941
0
0
0
0
0
1,000
12,020
43,437
58,883
0
0
0
0
0
114,340
947
7,800
853
0
0
0
0
0
9,600
14,198
52,482
61,320
0
0
0
0
0
128,000
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
High
2015 Budget Schedule:
2017
2016 Budget Schedule:
2017
Project Risk Assessment
Due to grant requirements and expiration of grant fund eligibility, the project is on a very tight schedule to maximize reimbursement opportunities.
34 of 140
Adopted 2016 Transit Improvement Plan
System Expansion
SOUNDER
3X510
Sounder South Expanded Service
Managed by: DECM
Scope: Purchase of four additional commuter rail easements between Seattle and Lakewood from Burlington Northern Santa Fe (BNSF) Railroad.
BNSF is responsible for track and signal improvements; Sound Transit maintains responsibility for environmental permitting and mitigation. The fourth
easement payment was made in 2015.
Sound Transit is working with BNSF and federal and local environmental regulatory agencies on environmental impacts and mitigation. A fish passage
culvert will be designed by ST and construction will be performed by King County. Construction to be complete by April 2018.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
4-Enter Final Design
Baseline:
$0
2008 Cost Estimate:
$196,715
2015 TIP:
$201,968
2015 Cost Estimate:
$253,762
2016 TIP:
$201,968
2016 Cost Estimate:
$253,762
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
194,146
4,300
3,522
0
0
0
0
0
201,968
194,146
4,300
3,522
0
0
0
0
0
201,968
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
1,078
300
872
0
0
0
0
0
2,250
482
0
225
0
0
0
0
0
707
30-Final Design+Specifications
0
700
0
0
0
0
0
0
700
35-Third Party
0
140
160
0
0
0
0
0
300
185,182
160
1,143
0
0
0
0
0
186,485
7,405
2,800
1,022
0
0
0
0
0
11,226
0
200
100
0
0
0
0
0
300
194,146
4,300
3,522
0
0
0
0
0
201,968
Pierce
Total
Phase
10-Agency Administration
20-Prelim Engineering/Env
Review
40-Row Acquisition+Permits
50-Construction
55-Construction Services
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Final Design
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2016
2016 Budget Schedule:
2018
Project Risk Assessment
N/A
Adopted 2016 Transit Improvement Plan
35 of 140
System Expansion
SOUNDER
300021
Tacoma Trestle Track & Signal
Managed by: DECM
Scope: Design and construct additional track, bridge and platforms along an approximately 0.65 mile section of track between the existing Tacoma
Dome Station and the vicinity of M Street in Tacoma.
Project baseline was established in 2015 per Resolution No. R2015-09.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
5-Establish Baseline
Baseline:
$120,509
2008 Cost Estimate:
$75,114
2015 TIP:
$120,509
2015 Cost Estimate:
$63,529
2016 TIP:
$120,509
2016 Cost Estimate:
$63,529
TIP Cashflow (in thousands)
Subarea
Pierce
Total
Phase
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
19,799
46,866
40,810
13,034
0
0
0
0
120,509
19,799
46,866
40,810
13,034
0
0
0
0
120,509
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
1,898
1,195
871
122
0
0
0
0
4,086
20-Prelim Engineering/Env
Review
4,005
82
410
0
0
0
0
0
4,497
30-Final Design+Specifications
7,842
3,649
1,219
771
0
0
0
0
13,481
22
454
547
54
0
0
0
0
1,077
35-Third Party
40-Row Acquisition+Permits
50-Construction
55-Construction Services
Total
5,874
2,365
1,555
267
0
0
0
0
10,061
44
36,721
34,109
10,767
0
0
0
0
81,641
113
2,400
2,100
1,053
0
0
0
0
5,666
19,799
46,866
40,810
13,034
0
0
0
0
120,509
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
High
Schedule Risk Level:
High
2015 Budget Schedule:
2017
2016 Budget Schedule:
2018
Project Risk Assessment
The schedule has been accelerated in order to meet a Fall 2017 completion date which allows for maximum use of expiring grant revenues. Several
challenges to the construction of the project are recognized and may result in potential lost of grant revenues supporting the project.
36 of 140
Adopted 2016 Transit Improvement Plan
System Expansion
SOUNDER
300026
Sounder Yard Expansion
Managed by: DECM
Scope: Increase track capacity at the layover facility in Lakewood to store up to seven train sets. The project will also complete drainage improvements
and increase electrical power to accommodate additional wayside power and yard lighting. The increase in capacity is needed for the additional ST2
Sounder South service that begins in 2016 before the Sounder Yard & Shops Facility project is complete.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
5-Establish Baseline
Baseline:
$20,550
2008 Cost Estimate:
N/A
2015 TIP:
$20,550
2015 Cost Estimate:
$21,092
2016 TIP:
$20,550
2016 Cost Estimate:
$21,092
TIP Cashflow (in thousands)
Subarea
South King
Pierce
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
1,054
5,999
3,756
0
0
0
0
0
10,809
950
5,406
3,385
0
0
0
0
0
9,741
2,004
11,405
7,141
0
0
0
0
0
20,550
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
486
425
289
0
0
0
0
0
1,200
1,215
40
895
0
0
0
0
0
2,150
184
20
196
0
0
0
0
0
400
50-Construction
75
10,070
5,255
0
0
0
0
0
15,400
55-Construction Services
44
850
506
0
0
0
0
0
1,400
2,004
11,405
7,141
0
0
0
0
0
20,550
Total
Phase
10-Agency Administration
20-Prelim Engineering/Env
Review
40-Row Acquisition+Permits
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Medium
2015 Budget Schedule:
2017
2016 Budget Schedule:
2017
Project Risk Assessment
Availability of materials requiring long lead time could potentially create delays in construction.
Adopted 2016 Transit Improvement Plan
37 of 140
System Expansion
SOUNDER
3X130
M St-Lakewood Track & Signal
Managed by: DECM
Scope: Reconstruction of approximately seven miles of rail track between M Street in Tacoma and Lakewood was completed in 2010. Remaining
project elements include restoration of the South 66th Street Bridge and installation of the Centralized Train Control system. Commuter rail service
began in 2012 following the completion of the D Street to M Street Track and Signal project (Project 3x135). Project will be completed in 2016.
Changes in lifetime budget since 2015: None
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
7-Transition to Operations
Baseline:
$78,630
2008 Cost Estimate:
N/A
2015 TIP:
$80,654
2015 Cost Estimate:
N/A
2016 TIP:
$80,654
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Pierce
Total
Phase
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
80,431
5
217
0
0
0
0
0
80,654
80,431
5
217
0
0
0
0
0
80,654
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
3,652
0
113
0
0
0
0
0
3,765
20-Prelim Engineering/Env
Review
1,496
0
0
0
0
0
0
0
1,496
30-Final Design+Specifications
2,982
0
3
0
0
0
0
0
2,985
40-Row Acquisition+Permits
12,769
5
41
0
0
0
0
0
12,815
50-Construction
50,579
0
60
0
0
0
0
0
50,639
8,953
0
0
0
0
0
0
0
8,953
80,431
5
217
0
0
0
0
0
80,654
70-Vehicles
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2010
2016 Budget Schedule:
2016
Project Risk Assessment
N/A
38 of 140
Adopted 2016 Transit Improvement Plan
System Expansion
SOUNDER
3X135
D St-M St Track & Signal
Managed by: DECM
Scope: Design and construct a 1.4 mile rail conneciton between Tacoma Dome Station and Sound Transit owned right-of-way at the Lakewood
Subdivision Line. Construction included; rail work, an overpass at Pacific Avenue, roadway improvements, utility relocations and centralized traffic
control for the rail line. The project completed construction and began Sounder service between Lakewood and Tacoma in October 2012. Follow-on
work continues and is anticipated to be completed by the end of 2016.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
7-Transition to Operations
Baseline:
$161,581
2008 Cost Estimate:
N/A
2015 TIP:
$158,262
2015 Cost Estimate:
N/A
2016 TIP:
$158,262
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Pierce
Total
Phase
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
152,934
460
4,868
0
0
0
0
0
158,262
152,934
460
4,868
0
0
0
0
0
158,262
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
8,829
95
682
0
0
0
0
0
9,606
20-Prelim Engineering/Env
Review
1,733
0
0
0
0
0
0
0
1,733
17,308
200
604
0
0
0
0
0
18,112
605
5
236
0
0
0
0
0
846
30-Final Design+Specifications
35-Third Party
40-Row Acquisition+Permits
42,137
10
1,482
0
0
0
0
0
43,629
50-Construction
67,150
100
1,249
0
0
0
0
0
68,499
55-Construction Services
5,173
50
550
0
0
0
0
0
5,773
70-Vehicles
8,953
0
0
0
0
0
0
0
8,953
80-System Testing+Startup
1,046
0
64
0
0
0
0
0
1,110
152,934
460
4,868
0
0
0
0
0
158,262
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2014
2016 Budget Schedule:
2016
Project Risk Assessment
Continued coordination with local jurisdictions may result in additional requirements.
Adopted 2016 Transit Improvement Plan
39 of 140
System Expansion
SOUNDER
3X206
Mukilteo Station, S Platform
Managed by: DECM
Scope: The Mukilteo Station South Platform project includes the second platform, stair, and elevator towers for both platforms and the pedestrian
bridge connecting them.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
6-Proceed to Construction
Baseline:
$18,313
2008 Cost Estimate:
N/A
2015 TIP:
$18,313
2015 Cost Estimate:
N/A
2016 TIP:
$18,313
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
14,395
2,819
1,099
0
0
0
0
0
18,313
14,395
2,819
1,099
0
0
0
0
0
18,313
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
1,252
130
158
0
0
0
0
0
1,540
30-Final Design+Specifications
2,240
100
307
0
0
0
0
0
2,647
Snohomish
Total
Phase
35-Third Party
40-Row Acquisition+Permits
50-Construction
55-Construction Services
Total
0
35
0
0
0
0
0
0
35
478
1,250
50
0
0
0
0
0
1,778
8,751
1,054
559
0
0
0
0
0
10,363
1,674
250
26
0
0
0
0
0
1,950
14,395
2,819
1,099
0
0
0
0
0
18,313
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Medium
2015 Budget Schedule:
2015
2016 Budget Schedule:
2016
Project Risk Assessment
Schedule delays have pushed the project completion into 2016 as the certificate of occupancy issuance was delayed.
40 of 140
Adopted 2016 Transit Improvement Plan
System Expansion
SOUNDER
3X216
Passenger Information System
Managed by: FIT
Scope: Upgrade of station communications and all closed circuit television (CCTV) and passenger information systems for commuter rail stations. The
system includes communications between stations and the Union Station centralized security and operations control center for CCTV cameras; audible
rail announcement capabilities; variable message signs; customer emergency stations; and onboard, automated vehicle location. Project was
completed in 2015 and will be closed in 2016 any remaining funds are considered surplus.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
None
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$6,455
2015 Cost Estimate:
N/A
2016 TIP:
$6,455
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
Snohomish
1,494
0
0
0
0
0
0
3
1,497
South King
1,900
0
0
0
0
0
0
4
1,904
Pierce
3,047
0
0
0
0
0
0
6
3,053
6,441
0
0
0
0
0
0
14
6,455
Total
Phase
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
207
0
0
0
0
0
0
3
210
20-Prelim Engineering/Env
Review
204
0
0
0
0
0
0
0
204
6,030
0
0
0
0
0
0
11
6,040
6,441
0
0
0
0
0
0
14
6,455
50-Construction
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2015
2016 Budget Schedule:
2015
Project Risk Assessment
N/A
Adopted 2016 Transit Improvement Plan
41 of 140
System Expansion
SOUNDER
3X236
Tukwila Station
Managed by: DECM
Scope: Construction of a new permanent commuter rail station to replace the existing temporary Tukwila Sounder Station on Sound Transit owned
property at Longacres Way in Tukwila. The project includes two 600-foot-long platforms with shelters, ADA compliant ramps, stairs, ticket vending
machines, improvements to the underpass connecting the two platforms, a bus transit area with shelters, 390 car parking stalls, 68 bicycle parking
spaces, and underground water quality and stormwater detention facilities. Project is expected to continue well into 2016 to complete follow-on work
including potential platform crack repairs, removal of soil stockpile, and possible lighting enhancements.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
6-Proceed to Construction
Baseline:
$45,969
2008 Cost Estimate:
$40,943
2015 TIP:
$45,969
2015 Cost Estimate:
$48,360
2016 TIP:
$45,969
2016 Cost Estimate:
$48,360
TIP Cashflow (in thousands)
Subarea
South King
Total
Phase
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
36,908
727
8,333
0
0
0
0
0
45,969
36,908
727
8,333
0
0
0
0
0
45,969
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
1,710
155
908
0
0
0
0
0
2,773
20-Prelim Engineering/Env
Review
1,101
0
0
0
0
0
0
0
1,101
30-Final Design+Specifications
4,589
50
286
0
0
0
0
0
4,924
40-Row Acquisition+Permits
10,362
5
642
0
0
0
0
0
11,009
50-Construction
17,537
517
6,026
0
0
0
0
0
24,081
1,609
0
472
0
0
0
0
0
2,081
36,908
727
8,333
0
0
0
0
0
45,969
55-Construction Services
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Final Design
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2016
2016 Budget Schedule:
2016
Project Risk Assessment
N/A.
42 of 140
Adopted 2016 Transit Improvement Plan
System Expansion
SOUNDER
7X755
Sounder ST2 Fleet Expansion
Managed by: Operations
Scope: Fleet expansion to add train sets to support additional trips between Seattle and Lakewood. The number of coaches and cab cars that will be
procured will be refined based on ridership trends and forecasts. In 2012, three locomotives were ordered and received from Motive Power, Inc. Nine
cabs were ordered in 2013 from Bombardier and will be received in 2015 through 2016.
Changes in lifetime budget since 2015: None
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
$36,854
2015 TIP:
$49,530
2015 Cost Estimate:
$30,438
2016 TIP:
$49,530
2016 Cost Estimate:
$30,438
TIP Cashflow (in thousands)
Subarea
Pierce
Total
Phase
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
40,548
8,982
0
0
0
0
0
0
49,530
40,548
8,982
0
0
0
0
0
0
49,530
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
2
0
0
0
0
0
0
0
2
20-Prelim Engineering/Env
Review
0
150
0
0
0
0
0
0
150
40,546
8,832
0
0
0
0
0
0
49,378
40,548
8,982
0
0
0
0
0
0
49,530
70-Vehicles
Total
Budget Risk Assessment
Schedule Risk Assessment
Estimate Type:
Scoping
Schedule Risk Level:
Medium
Budget Risk Level:
Medium
2015 Budget Schedule:
2016
2016 Budget Schedule:
2016
Project Risk Assessment
Time between the contract for purchase and delivery can be affected by manufacturing delays or unforeseen challenges.
Adopted 2016 Transit Improvement Plan
43 of 140
System Expansion – Regional Express
Projects in support of ST Express bus services are mostly completed and the focus is now on the expansion of high occupancy
vehicle (HOV) lanes on I-90 to make way for the construction of light rail from downtown Seattle to Bellevue.
Highlights

Purchase 27 new buses to support increased bus service fulfilling the commitment made to the public in the ST2 plan.

Conduct preliminary planning and due diligence for development of a bus base to support operations and maintainance of
the ST Express bus fleet.
Lifetime Budget Changes
The table below explains the changes in individual project lifetime budgets since the publication of the Adopted 2015 TIP.
BUDGET CHANGES
(in thousands)
Project
Reason
ST Express Fleet Expansion New Project
Budget Type Explanation
Baseline
Expand fleet by 27 buses to accommodate
additional service hours.
Closed Project Baseline
Project completed.
Rainier Avenue Arterial
Improvements
Strander Boulevard
Closed Project Baseline
Extension
Moutlake Terrace Freeway Closed Project Baseline
Station
S Everett Freeway Station Closed Project Baseline
Issaquah Transit
Center/SR900
Total
44 of 140
Closed Project Baseline
Change
$26,185
($15,348)
Project completed.
($4,073)
Project completed.
($29,260)
Project completed.
($28,358)
Project completed.
($28,962)
($79,816)
Adopted 2016 Transit Improvement Plan
REGIONAL EXPRESS CAPITAL PROJECTS
Adopted 2016 Transit Improvement Plan
45 of 140
46 of 140
Adopted 2016 Transit Improvement Plan
ST Express Bus Base
Kirkland Transit Center/3rd
Federal Way Transit Center
I-90 Two-Way Transit & HOV Operations,
Stage 3
5X142
5X321
5X387
700720
ST Express Fleet Expansion
0
$131,781
Total
0
130,641
74,179
37,929
10,808
5,418
2,306
4
4
1,136
1,136
Life to Date
Subtotal
Subtotal
85th Corridor, Kirkland
5X141
Operating
ST Express Mid-Day Bus Storage
Subtotal
Bothell Transit Related Improvements
Subtotal
500020
Baseline
500030
Final Design & ROW
500005
Preliminary Engineering
Project Number and Name
REGIONAL EXPRESS
System Expansion
$85,060
9,061
9,061
75,413
75,368
0
45
0
0
0
0
587
587
2016
$74,684
17,124
17,124
48,439
45,813
1,525
106
172
822
5,036
5,036
4,085
4,085
2017
0
0
21,424
21,424
0
0
0
0
0
0
0
0
2018
$21,424
(in thousands)
$8,864
0
0
8,864
8,864
0
0
0
0
0
0
0
0
2019
2016 TIP Cashflow by Budget Approval
$0
0
0
0
0
0
0
0
0
0
0
0
0
2020
$0
0
0
0
0
0
0
0
0
0
0
0
0
2021
$0
0
0
0
0
0
0
0
0
0
0
0
0
Future
$321,813
26,185
26,185
284,781
225,648
39,455
10,959
5,590
3,128
5,040
5,040
5,808
5,808
Total
Adopted 2016 Transit Improvement Plan
47 of 140
Total
6,407
20-Prelim Engineering/Env Review
0
90-Contingency
$131,781
0
238
89,594
7,608
0
70-Vehicles
55-Construction Services
50-Construction
40-Row Acquisition+Permits
35-Third Party
22,106
5,827
30-Final Design+Specifications
Life to Date
10-Agency Administration
$131,781
Phase # and Description
Total
90,938
4 - East King
2,579
38,061
3 - South King
5 - Pierce
203
Life to Date
1 - Snohomish
Subarea
REGIONAL EXPRESS
System Expansion
2016
2017
$74,684
2,522
65,425
3,866
2,872
$21,424
0
21,424
0
0
2018
$85,060
0
9,061
0
75,190
10
0
80
505
215
2016
$74,684
100
17,124
32
44,463
197
5,000
3,297
3,460
1,012
2017
(in thousands)
$21,424
0
0
0
18,730
0
0
923
0
1,770
2018
2016 TIP Cashflow by Phase
$85,060
521
82,246
1,056
1,238
(in thousands)
2016 TIP Cashflow by Subarea
$8,864
0
0
0
8,864
0
0
0
0
0
2019
$8,864
0
8,864
0
0
2019
$0
0
0
0
0
0
0
0
0
0
2020
$0
0
0
0
0
2020
$0
0
0
0
0
0
0
0
0
0
2021
$0
0
0
0
0
2021
$0
0
0
0
0
0
0
0
0
0
Future
$0
0
0
0
0
Future
Total
$321,813
100
26,185
270
236,842
7,814
5,000
26,406
10,372
8,824
Total
$321,813
5,622
268,896
42,982
4,313
System Expansion
REGIONAL
EXPRESS
500005
ST Express Bus Base
Managed by: PEPD
Scope: Sound Transit is evaluating constructing an ST Express Bus Base for operating and maintaining the ST Express bus fleet. The Board has
approved initial project development activities including confirmation of fleet operating assumptions, development of facilities and site programming
evaluations and review of alternative project delivery methods.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
1-Enter Project Development
Baseline:
$0
2008 Cost Estimate:
$196,007
2015 TIP:
$5,808
2015 Cost Estimate:
$189,577
2016 TIP:
$5,808
2016 Cost Estimate:
$189,577
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
Snohomish
203
105
731
0
0
0
0
0
1,040
South King
132
68
474
0
0
0
0
0
674
East King
528
273
1,900
0
0
0
0
0
2,701
Pierce
273
141
980
0
0
0
0
0
1,394
1,136
587
4,085
0
0
0
0
0
5,808
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
Total
Phase
10-Agency Administration
335
72
437
0
0
0
0
0
844
20-Prelim Engineering/Env
Review
798
505
3,460
0
0
0
0
0
4,763
40-Row Acquisition+Permits
Total
3
10
188
0
0
0
0
0
201
1,136
587
4,085
0
0
0
0
0
5,808
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Planning
Medium
Schedule Risk Level:
Medium
2015 Budget Schedule:
2016
2016 Budget Schedule:
2016
Project Risk Assessment
Uncertainties exist in siting, design, environmental, third party and jurisdictional requirements that present budget and schedule risks.
48 of 140
Adopted 2016 Transit Improvement Plan
System Expansion
REGIONAL
EXPRESS
500030
Bothell Transit Related Improvements
Managed by: PEPD
Scope: Capital contribution to transit center/park-and-ride project near SR 527/Bothell Way NE and NE 185th Street in the downtown Bothell area.
Sound Transit and the city of Bothell would enter into an memorandum of understanding to confirm the responsibilities of each party, the project capital
component(s) to receive funding, and the financial participation schedule.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
$6,129
2015 TIP:
$5,040
2015 Cost Estimate:
N/A
2016 TIP:
$5,040
2016 Cost Estimate:
$6,112
TIP Cashflow (in thousands)
Subarea
East King
Total
Phase
10-Agency Administration
35-Third Party
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
4
0
5,036
0
0
0
0
0
5,040
4
0
5,036
0
0
0
0
0
5,040
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
4
0
36
0
0
0
0
0
40
0
0
5,000
0
0
0
0
0
5,000
4
0
5,036
0
0
0
0
0
5,040
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Fixed Contribution
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2015
2016 Budget Schedule:
2018
Project Risk Assessment
The execution of the grant matching contribution is reliant on the city of Bothell receiving the grant award. As such the actual payment may be
carried over year to year until such time the grant is received.
Adopted 2016 Transit Improvement Plan
49 of 140
System Expansion
REGIONAL
EXPRESS
500020
ST Express Mid-Day Bus Storage
Managed by: DECM
Scope: Replace temporary bus storage at the Link Operations Maintenance Facility employee parking area with permanent storage with capacity for
30, forty-five foot buses. The project is complete, any remaining funds are considered surplus.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
7-Transition to Operations
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$3,128
2015 Cost Estimate:
$3,336
2016 TIP:
$3,128
2016 Cost Estimate:
$3,336
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
2,306
0
822
0
0
0
0
0
3,128
2,306
0
822
0
0
0
0
0
3,128
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
226
0
127
0
0
0
0
0
353
20-Prelim Engineering/Env
Review
229
0
0
0
0
0
0
0
229
30-Final Design+Specifications
418
0
37
0
0
0
0
0
455
Pierce
Total
Phase
40-Row Acquisition+Permits
50-Construction
55-Construction Services
Total
1
0
9
0
0
0
0
0
10
1,193
0
618
0
0
0
0
0
1,811
238
0
32
0
0
0
0
0
270
2,306
0
822
0
0
0
0
0
3,128
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2015
2016 Budget Schedule:
2015
Project Risk Assessment
N/A
50 of 140
Adopted 2016 Transit Improvement Plan
System Expansion
REGIONAL
EXPRESS
5X141
85th Corridor, Kirkland
Managed by: DECM
Scope: Street widening, traffic signal and bus shelter installations, and sidewalk improvements at various intersections in the city of Kirkland to
enhance reliability and connections to transit. This project is being led by the city of Kirkland; transit elements are funded by capped contribution from
Sound Transit. Project is complete and will be closed in 2016. Any remaining funds are considered surplus.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
5-Establish Baseline
Baseline:
$6,015
2008 Cost Estimate:
N/A
2015 TIP:
$5,590
2015 Cost Estimate:
N/A
2016 TIP:
$5,590
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
East King
Total
Phase
10-Agency Administration
20-Prelim Engineering/Env
Review
30-Final Design+Specifications
40-Row Acquisition+Permits
50-Construction
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
5,418
0
172
0
0
0
0
0
5,590
5,418
0
172
0
0
0
0
0
5,590
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
447
0
14
0
0
0
0
0
460
1,124
0
0
0
0
0
0
0
1,124
554
0
0
0
0
0
0
0
554
876
0
0
0
0
0
0
0
876
2,417
0
158
0
0
0
0
0
2,575
5,418
0
172
0
0
0
0
0
5,590
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Fixed Contribution
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2015
2016 Budget Schedule:
2015
Project Risk Assessment
N/A
Adopted 2016 Transit Improvement Plan
51 of 140
System Expansion
REGIONAL
EXPRESS
5X142
Kirkland Transit Center/3rd
Managed by: DECM
Scope: Design and construct, and place into service, a new regional transit center in Kirkland on Third Street, south of Central Way to accommodate
existing and anticipated bus service by King County Metro and ST Express routes. The project also includes a capped contribution for intersection
improvements near the transit center to enhance bus service speed and reliability. This project was completed in 2015 and will be closed in 2016.
Any remaining funds are considered surplus.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
7-Transition to Operations
Baseline:
$13,300
2008 Cost Estimate:
N/A
2015 TIP:
$10,959
2015 Cost Estimate:
N/A
2016 TIP:
$10,959
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10,808
45
106
0
0
0
0
0
10,959
10,808
45
106
0
0
0
0
0
10,959
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
947
5
1
0
0
0
0
0
953
20-Prelim Engineering/Env
Review
1,154
0
0
0
0
0
0
0
1,154
30-Final Design+Specifications
1,574
0
0
0
0
0
0
0
1,574
East King
Total
Phase
10-Agency Administration
40-Row Acquisition+Permits
187
0
0
0
0
0
0
0
187
50-Construction
6,946
40
5
0
0
0
0
0
6,991
90-Contingency
0
0
100
0
0
0
0
0
100
10,808
45
106
0
0
0
0
0
10,959
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2015
2016 Budget Schedule:
2015
Project Risk Assessment
N/A
52 of 140
Adopted 2016 Transit Improvement Plan
System Expansion
REGIONAL
EXPRESS
5X321
Federal Way Transit Center
Managed by: DECM
Scope: Construct a new transit center and five level 1,200 stall parking structure in Federal Way. Connect I-5 high occupancy vehicle (HOV) lanes to
the transit center via South 317th Street. Project is complete and pending closeout. Any remaining funds are considered surplus.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
7-Transition to Operations
Baseline:
$39,455
2008 Cost Estimate:
N/A
2015 TIP:
$39,455
2015 Cost Estimate:
N/A
2016 TIP:
$39,455
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
37,929
0
1,525
0
0
0
0
0
39,455
37,929
0
1,525
0
0
0
0
0
39,455
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
2,396
0
130
0
0
0
0
0
2,526
20-Prelim Engineering/Env
Review
1,553
0
0
0
0
0
0
0
1,553
30-Final Design+Specifications
1,701
0
0
0
0
0
0
0
1,701
40-Row Acquisition+Permits
6,541
0
0
0
0
0
0
0
6,541
25,739
0
1,395
0
0
0
0
0
27,134
37,929
0
1,525
0
0
0
0
0
39,455
South King
Total
Phase
50-Construction
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2006
2016 Budget Schedule:
2006
Project Risk Assessment
N/A
Adopted 2016 Transit Improvement Plan
53 of 140
System Expansion
REGIONAL
EXPRESS
5X387
I-90 Two-Way Transit & HOV Operations, Stage 3
Managed by: DECM
Scope: Stage 3 of the I-90 Two-way Transit and HOV Operations project will provide reliable two-way transit and HOV operations eastbound and
westbound on I-90 between 80th Avenue SE on Mercer Island and Rainier Avenue/I-5 in Seattle. This stage will also include the installation of
screening on the shared pathway on the I-90 floating bridge. Upon completion of the Stage 3 project, the center roadway will be closed to allow the
construction of East Link to proceed.
Changes in lifetime budget since 2015: None
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
6-Proceed to Construction
Baseline:
$225,648
2008 Cost Estimate:
N/A
2015 TIP:
$225,648
2015 Cost Estimate:
N/A
2016 TIP:
$225,648
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
74,179
75,368
45,813
21,424
8,864
0
0
0
225,648
74,179
75,368
45,813
21,424
8,864
0
0
0
225,648
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
1,472
138
267
1,770
0
0
0
0
3,648
20-Prelim Engineering/Env
Review
1,549
0
0
0
0
0
0
0
1,549
East King
Total
Phase
30-Final Design+Specifications
17,858
80
3,260
923
0
0
0
0
22,121
50-Construction
53,300
75,150
42,286
18,730
8,864
0
0
0
198,330
74,179
75,368
45,813
21,424
8,864
0
0
0
225,648
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
High
Schedule Risk Level:
Medium
2015 Budget Schedule:
2017
2016 Budget Schedule:
2017
Project Risk Assessment
Fire Life Safety in a tunnel retrofit does create risk in cost and in schedule. Commissioning of the fire life safety equipment and system will require a
multi-phase detailed plan through commissioning. Other construction risks are known and suitable contingencies and project schedule float included
in the baseline budget.
54 of 140
Adopted 2016 Transit Improvement Plan
System Expansion
REGIONAL
EXPRESS
700720
ST Express Fleet Expansion
Managed by: Operations
Scope: Procure and accept 11 Compressed Natural Gas (CNG) buses and 16 double deck diesel buses to support the increase in peak hour bus
service with an additional 19,750 hours in 2016, equivalent to 32,000 hours of annualized peak hours. The added service hours will include 29,000
hours for the peak service period and the balance for non-peak hour support. The existing fleet is fully utilized during peak hour service, requiring the
additional buses.
Changes in lifetime budget since 2015: New Project with lifetime budget of $26,184,555
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
None
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$0
2015 Cost Estimate:
N/A
2016 TIP:
$26,185
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
Snohomish
0
1,133
2,140
0
0
0
0
0
3,273
South King
0
988
1,867
0
0
0
0
0
2,854
East King
0
6,560
12,398
0
0
0
0
0
18,958
Pierce
Total
Phase
70-Vehicles
Total
0
381
719
0
0
0
0
0
1,100
0
9,061
17,124
0
0
0
0
0
26,185
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
0
9,061
17,124
0
0
0
0
0
26,185
0
9,061
17,124
0
0
0
0
0
26,185
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Scoping
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2016 Budget Schedule:
2017
Project Risk Assessment
N/A
Adopted 2016 Transit Improvement Plan
55 of 140
System Expansion – Other
Sound Transit is working to finalize the next transit expansion plan —Sound Transit 3 (ST3). The scope of the plan, including
specific projects, will be selected by the Board in June 2016.
Highlights

Research and Technology project will continue to build and deploy passenger oriented technologies that enhance rider
experience.

ST3 Planning will produce a high-capacity transit system plan to expand regional transit beyond the Sound Move and
ST2 programs.
Lifetime Budget Changes
The table below explains the changes in individual project lifetime budgets since the publication of the Adopted 2015 TIP.
BUDGET CHANGES
(in thousands)
Project
Research & Technology
Reason
Budget Type
Cost Increase Program
ST3 Planning
Transfer
Preliminary Engineering
Central & East HCT Study Transfer
Preliminary Engineering
Transfer
Preliminary Engineering
HCT Corridor Planning
Studies
Ballard to Downtown HCT Closed Project Preliminary Engineering
Lynnwood to Everett HCT Closed Project Preliminary Engineering
Study
South King County HCT Closed Project Preliminary Engineering
Study
South Corridor Alternative Transfer
Plannning
Total
56 of 140
Preliminary Engineering
Explanation
Expand use of technology to provide customers
with rider alerts, interactive signage, and
personalized on-demand information and
Americans with Disabilities rider support. Share
data with more transit providers.
Surplus funds transferred from the HCT Corridor
Planning Studies, South King County HCT
Corridor Study and Lynnwood to Everett HCT
Surplus funds transferred to the ST3 Planning
project for long range planning needs.
Surplus funds transferred to the ST3 project for
long range planning needs.
Surplus funds transferred to the ST3 Planning
project for long range planning needs. Project
closed.
Surplus funds transferred to the ST3 project for
long range planning needs. Project closed.
Surplus funds transferred to the ST3 Planning
project for long range planning needs. Project
closed.
Surplus funds transferred to the ST3 project for
long range planning needs. Project closed.
Change
$5,344
$3,723
($2,373)
($500)
($1,167)
($1,670)
($2,374)
($850)
$133
Adopted 2016 Transit Improvement Plan
Adopted 2016 Transit Improvement Plan
57 of 140
Central & East HCT Study
809103
Subtotal
Fare Collection
Research & Technology
Fare Administration
5X410
600016
5,009
$18,546
16,647
$49,143
Subtotal
Total
2,727
1,494
7,717
788
250
748
8,020
250
748
1,254
1,254
15,325
15,325
65
12,033
2,087
0
11,968
0
2016
16,424
65
12,232
2,040
Life to Date
910
Subtotal
STart Operations & Maintenance
3X212
Program
600668
Operating
6X668
STart
HCT Corridor Planning Studies
809102
Baseline
ST3 Planning
809100
Subtotal
South Corridor Alternatives Planning
4X446
Preliminary Engineering
Project Number and Name
System Expansion
OTHER
$33,714
3,217
600
2,033
584
210
210
1,691
1,691
28,596
0
0
28,448
148
2017
0
0
0
0
0
2018
$13,873
7,484
5,673
1,414
398
145
145
6,244
6,244
(in thousands)
$9,485
2,651
371
1,821
460
144
144
6,690
6,690
0
0
0
0
0
2019
2016 TIP Cashflow by Budget Approval
$4,371
2,538
190
1,911
437
145
145
1,688
1,688
0
0
0
0
0
2020
$3,996
2,819
1,200
1,036
583
150
150
1,026
1,026
0
0
0
0
0
2021
$30,601
12,116
7,173
1,342
3,601
3,137
3,137
15,349
15,349
0
0
0
0
0
Future
$163,729
52,482
17,611
20,000
14,870
4,927
4,927
49,267
49,267
57,053
2,152
65
52,648
2,188
Total
58 of 140
Adopted 2016 Transit Improvement Plan
61-Art
50-Construction
40-Row Acquisition+Permits
26-Research+Technology
Total
20-Prelim Engineering/Env Review
10-Agency Administration
$49,143
14,799
7,498
1
2,633
16,241
4,121
850
0
01-Operation+Maintenance
02-Operation+Maintenance-Agency
Life to Date
Phase # and Description
$18,546
890
735
200
3,525
11,053
1,985
158
0
2016
$18,546
415
667
569
$49,143
6,317
5 - Pierce
Total
7,809
4 - East King
16,189
5,933
3 - South King
385
322
2016
20,924
4,804
2 - North King
6 - Systemwide
3,356
Life to Date
1 - Snohomish
Subarea
System Expansion
OTHER
$13,873
7,087
615
2,611
1,351
1,495
714
2018
$33,714
1,316
584
99
2,233
25,983
3,384
115
0
2017
$13,873
5,858
398
0
6,604
483
484
47
0
2018
(in thousands)
2016 TIP Cashflow by Phase
$33,714
31,081
512
790
570
445
316
2017
(in thousands)
2016 TIP Cashflow by Subarea
$9,485
6,290
460
0
1,970
222
501
43
0
2019
$9,485
2,192
671
2,794
1,457
1,599
772
2019
$4,371
1,278
437
0
1,911
190
514
41
0
2020
$4,371
2,101
302
758
504
429
277
2020
$3,996
604
583
0
1,836
400
529
43
0
2021
$3,996
2,236
312
495
433
275
245
2021
$30,601
13,702
2,841
0
8,036
479
3,124
2,419
0
Future
$30,601
8,515
2,732
7,624
4,794
4,326
2,611
Future
Total
$163,729
44,737
13,537
300
31,747
55,051
14,642
3,715
0
Total
$163,729
90,225
11,875
23,599
15,611
13,807
8,612
System Expansion
OTHER
4X446
South Corridor Alternatives Planning
Managed by: PEPD
Scope: Identification and evaluation of high-capacity transit (HCT) alternatives for the corridor between Federal Way and Tacoma. It also includes an
examination of potential projects for Pierce and South King subareas to enhance transit use and operational efficiencies. This is one of the HCT
Corridor Planning studies that will serve as a resource for the Board and public during the update of the Long-Range Plan.
Project is complete any remaining funds are considered surplus and will be transferred to ST3 Planning upon project closure.
Changes in lifetime budget since 2015: Project budget was reduced and transferred to ST3 Planning to recognize a project surplus.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
1-Enter Project Development
Baseline:
$0
2008 Cost Estimate:
$82,921
2015 TIP:
$3,038
2015 Cost Estimate:
$3,077
2016 TIP:
$2,188
2016 Cost Estimate:
$3,077
TIP Cashflow (in thousands)
Subarea
Pierce
Total
Phase
10-Agency Administration
20-Prelim Engineering/Env
Review
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
2,040
0
148
0
0
0
0
0
2,188
2,040
0
148
0
0
0
0
0
2,188
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
195
0
26
0
0
0
0
0
221
1,844
0
122
0
0
0
0
0
1,967
2,040
0
148
0
0
0
0
0
2,188
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Planning
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2015
2016 Budget Schedule:
2015
Project Risk Assessment
N/A
Adopted 2016 Transit Improvement Plan
59 of 140
System Expansion
OTHER
809100
ST3 Planning
Managed by: PEPD
Scope: Provide funding for the study of future regional transit system expansion beyond the Sound Move and ST2 programs. The ST3 plan includes
funding for studying public transit expansion options in nine corridors. These studies were split into their own projects reducing the scope to long-range
planning beyond the Sound Move and ST2 programs. The project is currently in the ST3 project identification phase.
Changes in lifetime budget since 2015: Project budget increased by $3.7 million to reflect transfer of surplus budget from multiple corridor planning
studies projects.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
1-Enter Project Development
Baseline:
$0
2008 Cost Estimate:
$67,204
2015 TIP:
$48,925
2015 Cost Estimate:
$47,399
2016 TIP:
$52,648
2016 Cost Estimate:
$50,325
TIP Cashflow (in thousands)
Subarea
Systemwide
Total
Phase
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
12,232
11,968
28,448
0
0
0
0
0
52,648
12,232
11,968
28,448
0
0
0
0
0
52,648
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
1,672
1,278
2,888
0
0
0
0
0
5,838
20-Prelim Engineering/Env
Review
10,559
10,490
25,461
0
0
0
0
0
46,510
40-Row Acquisition+Permits
Total
1
200
99
0
0
0
0
0
300
12,232
11,968
28,448
0
0
0
0
0
52,648
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Planning
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2018
2016 Budget Schedule:
2018
Project Risk Assessment
N/A
60 of 140
Adopted 2016 Transit Improvement Plan
System Expansion
OTHER
809102
HCT Corridor Planning Studies
Managed by: PEPD
Scope: ST2 includes funding for identifying and evaluating potential high-capacity transit improvements beyond those identified in ST2. These studies
have been budgeted separately under other projects. The remaining budget will fund additional ST3 corridor planning work as requested by the Sound
Transit Board of Directors during the ST3 planning process as related to the High-Capacity Transit corridor studies.
Changes in lifetime budget since 2015: Project budget decreased by $500 thousand reflecting the transfer of remaining funds to ST3 Planning project.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
1-Enter Project Development
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$565
2015 Cost Estimate:
$554
2016 TIP:
$65
2016 Cost Estimate:
$54
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
65
0
0
0
0
0
0
0
65
65
0
0
0
0
0
0
0
65
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
65
0
0
0
0
0
0
0
65
20-Prelim Engineering/Env
Review
0
0
0
0
0
0
0
0
0
65
0
0
0
0
0
0
0
65
Systemwide
Total
Phase
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Planning
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2015
2016 Budget Schedule:
2015
Project Risk Assessment
N/A
Adopted 2016 Transit Improvement Plan
61 of 140
System Expansion
OTHER
809103
Central & East HCT Study
Managed by: PEPD
Scope: Identify and evaluate alternative high-capacity transit (HCT) modes, routes, and potential station areas along high-capacity transit corridors.
Changes in lifetime budget since 2015: Project budget decreased by $2.4 million reflecting the transfer of funds to ST3 Planning.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
1-Enter Project Development
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$4,525
2015 Cost Estimate:
$4,736
2016 TIP:
$2,152
2016 Cost Estimate:
$2,112
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
North King
1,043
33
0
0
0
0
0
0
1,076
East King
1,043
33
0
0
0
0
0
0
1,076
2,087
65
0
0
0
0
0
0
2,152
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
142
22
0
0
0
0
0
0
164
1,944
43
0
0
0
0
0
0
1,988
2,087
65
0
0
0
0
0
0
2,152
Total
Phase
10-Agency Administration
20-Prelim Engineering/Env
Review
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Planning
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2015
2016 Budget Schedule:
2016
Project Risk Assessment
N/A
62 of 140
Adopted 2016 Transit Improvement Plan
System Expansion
OTHER
6X668
STart
Managed by: DECM
Scope: The Sound Transit Art Program (STart) incorporates art into Sound Transit facilities. The artwork is intended to reflect the communities served
and contribute to a positive experience for customers. The Board supports a public art budget of one percent of construction costs excluding tunneling
for all Sound Move and ST2 projects. In 2010, Resolution No. R2010-21 consolidated the Sound Move and ST2 Art programs and established an Art
Policy. Ten percent of the total Art program funding is earmarked for the maintenance of the art collection (see project 600668).
Changes in lifetime budget since 2015: None
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$49,267
2015 Cost Estimate:
$49,267
2016 TIP:
$49,267
2016 Cost Estimate:
$49,267
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
Snohomish
1,502
123
166
North King
3,586
293
396
South King
2,896
237
320
East King
6,237
510
Pierce
1,103
90
15,325
Total
Phase
10-Agency Administration
61-Art
Total
2018
2019
2020
2021
Future
Total
612
656
165
101
1,504
4,828
1,461
1,565
395
240
3,592
11,529
1,180
1,264
319
194
2,901
9,312
688
2,541
2,723
687
418
6,247
20,052
122
450
482
122
74
1,105
3,547
1,254
1,691
6,244
6,690
1,688
1,026
15,349
49,267
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
526
364
375
386
400
410
422
1,647
4,530
14,799
890
1,316
5,858
6,290
1,278
604
13,702
44,737
15,325
1,254
1,691
6,244
6,690
1,688
1,026
15,349
49,267
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Planning
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2023
2016 Budget Schedule:
2023
Project Risk Assessment
N/A
Adopted 2016 Transit Improvement Plan
63 of 140
System Expansion
OTHER
600668
STart Operations & Maintenance
Managed by: DECM
Scope: Maintain Sound Transit art installations, including documentation, monitoring, cleaning, repair and occasional replacement. As part of the
Sound Transit Art program (STart), the lifetime budget is set at ten percent of the total STart program.
Changes in lifetime budget since 2015: None
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$4,927
2015 Cost Estimate:
$4,927
2016 TIP:
$4,927
2016 Cost Estimate:
$4,927
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
Snohomish
73
25
21
14
14
14
15
307
483
North King
175
59
49
34
34
34
35
734
1,153
South King
141
47
40
27
27
27
28
593
931
East King
304
102
85
59
58
59
61
1,277
2,005
54
18
15
10
10
10
11
226
355
748
250
210
145
144
145
150
3,137
4,927
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
02-Operation+MaintenanceAgency
574
158
115
47
43
41
43
2,419
3,439
10-Agency Administration
174
92
95
98
101
104
107
717
1,488
748
250
210
145
144
145
150
3,137
4,927
Pierce
Total
Phase
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Planning
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2023
2016 Budget Schedule:
2023
Project Risk Assessment
N/A
64 of 140
Adopted 2016 Transit Improvement Plan
System Expansion
OTHER
3X212
Fare Collection
Managed by: FIT
Scope: Maintain and upgrade as required, Agency fare collection systems which includes: Ticket Vending Machines (TVMs), One Regional Card for All
(ORCA) system, secure payment requirements, and electronic citations for fare validation and enforcement.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$14,870
2015 Cost Estimate:
N/A
2016 TIP:
$14,870
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
Snohomish
1,781
175
South King
2,895
284
130
88
211
144
225
22
16
3,120
307
8,020
788
Life to Date
10-Agency Administration
20-Prelim Engineering/Env
Review
East King
Pierce
Total
Phase
50-Construction
Total
2020
2021
Future
Total
102
97
166
158
129
799
3,301
210
1,300
5,368
11
13
12
16
101
416
227
155
584
398
179
170
227
1,401
5,785
460
437
583
3,601
14,870
2016
2017
2018
2019
2020
2021
Future
Total
372
53
0
0
0
0
0
759
1,184
150
0
0
0
0
0
0
0
150
7,498
735
584
398
460
437
583
2,841
13,537
8,020
788
584
398
460
437
583
3,601
14,870
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
High
Schedule Risk Level:
Medium
2015 Budget Schedule:
2023
2016 Budget Schedule:
2023
Project Risk Assessment
The current budget and schedule is based on early planning estimates for rehabilitation and replacement for these assets. The costs are at high risk
until more detailed assessment of the condition of the fielded assets and associated repair and replacement costs are developed.
Adopted 2016 Transit Improvement Plan
65 of 140
System Expansion
OTHER
5X410
Research & Technology
Managed by: FIT
Scope: Assess and implement new transit technologies to improve the agency's operational effectiveness, efficiency and customer experience. This program
focuses on system wide security and safety technology, real-time service information and passenger communications, and deploying applications to manage
operations better.
Changes in lifetime budget since 2015: Increased lifetime budget by $5.3 million to expand new features and functions in application development to include
sharing transit data on to a wider audience of transit providers, interface of useful customer data to web platforms, rider alerts, interactive signage and fare
payment expansion.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$14,656
2015 Cost Estimate:
N/A
2016 TIP:
$20,000
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Systemwide
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
7,717
2,727
2,033
1,414
1,821
1,911
1,036
1,342
20,000
7,717
2,727
2,033
1,414
1,821
1,911
1,036
1,342
20,000
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
02-Operation+Maintenance-Agency
276
0
0
0
0
0
0
0
276
10-Agency Administration
975
176
0
0
0
0
0
0
1,151
20-Prelim Engineering/Env Review
946
71
0
0
0
0
0
0
1,017
5,520
2,479
2,033
1,414
1,821
1,911
1,036
1,342
17,556
7,717
2,727
2,033
1,414
1,821
1,911
1,036
1,342
20,000
Phase
26-Research+Technology
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Planning
Medium
Schedule Risk Level:
High
2015 Budget Schedule:
2023
2016 Budget Schedule:
2023
Project Risk Assessment
Elements of this program are in various stages of design and include new technologies that require custom software development which creates budget and
schedule risk while a project goes from an idea or concept to a fully scoped project. Extensive coordination with external agencies adds level of schedule risk.
66 of 140
Adopted 2016 Transit Improvement Plan
System Expansion
OTHER
600016
Fare Administration
Managed by: FIT
Scope: Create and install fare system enhancements to the existing regional smart card system (ORCA) and fare collection systems. Beginning in
2015 this project includes the planning, development and implementation of a new fare collection system. The program also manages fares and pricing
for Sound Transit.
Changes in lifetime budget since 2015: None
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$17,611
2015 Cost Estimate:
N/A
2016 TIP:
$17,611
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Systemwide
Total
Phase
10-Agency Administration
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
910
1,494
600
5,673
371
190
1,200
7,173
17,611
910
1,494
600
5,673
371
190
1,200
7,173
17,611
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
0
0
0
0
0
0
0
0
0
20-Prelim Engineering/Env
Review
797
448
400
483
222
190
400
479
3,420
26-Research+Technology
113
1,046
200
5,190
149
0
800
6,694
14,191
910
1,494
600
5,673
371
190
1,200
7,173
17,611
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Planning
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2023
2016 Budget Schedule:
2023
Project Risk Assessment
N/A
Adopted 2016 Transit Improvement Plan
67 of 140
Enhancement
Although the majority of Sound Transit’s projects are related to expanding the regional transit system, work is planned and
ongoing to improve operating efficiency and effectiveness, improve the rider experience, increase system functionality, or reduce
operating costs.
Highlights

Install more energy efficient LED lighting at Kent, Sumner, and Puyallup Sounder stations.

Begin operation of Positive Train Control (PTC) to increase operational safety of commuter rail.

Design and install a second light rail vehicle lift at the Link Operations & Maintenance Facility.

Upgrade the Link Closed Circuit Television System (CCTV) to be compatible with technology installed for the University
Link and South 200th Link extensions.

Install heating systems in washers for light rail vehicles, in order to allow for all-weather operation and reduce hazards to
operators in freezing weather conditions.
Lifetime Budget Changes
The table below explains the changes in individual project lifetime budgets since the publication of the Adopted 2015 TIP.
BUDGET CHANGES
(in thousands
Project
LINK
Central Link HVAC Instrument House and UPS
Room
SOUNDER
Kent Station Parking Lot
Paving
Kent Station Platform
Lighting
Puyallup Station LED
Lighting
Sumner Station LED
Lighting
OTHER
Downtown Seattle Transit
Tunnel Mitigation
Reason
Explanation
Change
Cost Increase Baseline
Acquire right-of-way for the project.
$661
New Project
Operating
Add 39 parking spaces including 2 ADA spaces.
$700
New Project
Operating
$236
New Project
Operating
New Project
Operating
Install energy efficient lighting to reduce costs
and energy use.
Install energy efficient lighting to reduce costs
and energy use.
Install energy efficient lighting to reduce costs
and energy use.
New Project
Preliminary Engineering Street improvements in downtown Seattle to
accommodate an increase in bus traffic due to
light rail's increasing use of the tunnel.
Preliminary Engineering Installation of a second lift to support light rail
vehicle maintenance.
Program
Project decreased by $494 thousand and
transferred to Transit Oriented Development
(TOD) disposition.
Operations & Maintenance New Project
Facility LRV Vehicle Lift
Transit Oriented
Transfer
Development Planning
68 of 140
Budget Type
$178
$134
$2,334
$4,898
($494)
Adopted 2016 Transit Improvement Plan
Project
Transit-Oriented
Development Property
Disposition
Reason
Budget Type
Cost Increase Program
Link CCTV System Upgrade New Project
Baseline
OMF LRV Wash Heater
System
Baseline
New Project
Total
Adopted 2016 Transit Improvement Plan
Explanation
The number of surplus properties are
increasing as ST2 projects are completed.
Increase includes $494 thousand transfer from
TOD Planning Project.
Upgrade existing systems to be compatible with
newer equipment for U Link and S 200th Link
extensions. Resolution No. R2015-19.
Enable the washbay facility to be used in
freezing temperatures. Resolution No. R201506.
Change
$6,014
$700
$300
$15,661
69 of 140
70 of 140
Adopted 2016 Transit Improvement Plan
Operations & Maintenance Facility LRV
Vehicle Lift
Union Station Garden Level Remodel
Regional Parking Pilot Project
Signage Improvements
Link Remote Switch Heaters
700730
700736
700784
700793
700798
Noise Abatement
Tacoma Link Fare Collection
Central Link HVAC - Instrument House and
UPS Room
Security Enhancements
Bike Locker Program
4X340
600029
700774
7X743
7X753
Link CCTV System Upgrade
Puyallup Station LED Lighting
Sumner Station LED Lighting
Kent Station Platform Lighting
Kent Station Parking Lot Paving
OMF LRV Wash Heater System
Central Link HVAC for Traction Power
Central Link Card Readers
Central Link Overhead Catenary System Tie
Switch
Pierce Transit Radio System Upgrade
600033
700724
700725
700726
700727
700733
700773
700775
700777
700790
Operating
LRV On Board Energy Storage
4X210
Subtotal
Positive Train Control
300011
Subtotal
Downtown Seattle Transit Tunnel Mitigation
700723
Baseline
Bus Maintenance Facility
5X261
Preliminary Engineering
Project Number and Name
ALL MODES
Enhancement
562
5
44
1,013
105
0
0
0
0
0
49,170
1,154
2,445
379
64
8,986
1,488
34,654
9,253
0
89
195
23
189
0
8,757
Life to Date
438
150
379
0
195
700
236
134
178
700
9,605
161
0
853
392
26
93
8,081
8,293
200
843
280
1,360
2,475
1,728
1,407
2016
0
2,845
0
266
0
0
0
0
0
0
14,466
39
0
0
58
3,987
63
10,319
14,709
0
0
0
0
2,234
606
11,869
2017
(in thousands)
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
2018
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
2019
2016 TIP Cashflow by Budget Approval
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
2020
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
2021
0
0
0
0
0
0
0
0
0
0
53
0
53
0
0
0
0
0
0
0
0
0
0
0
0
0
Future
1,000
3,000
423
1,278
300
700
236
134
178
700
73,295
1,355
2,498
1,232
514
13,000
1,643
53,054
32,255
200
931
475
1,383
4,898
2,334
22,033
Total
Adopted 2016 Transit Improvement Plan
71 of 140
$74,046
1,146
Total
Transit Oriented Development Planning
8X100
420
2,016
3,582
Transit-Oriented Development Property
Disposition
12,041
10,311
Life to Date
Subtotal
Non-revenue Support Vehicles
804100
Subtotal
ST Express Mobile Communications
700781
Program
7X745
Project Number and Name
ALL MODES
Enhancement
$26,494
5,267
0
4,261
1,006
3,329
220
2016
$33,765
1,479
0
1,315
163
3,111
0
2017
(in thousands)
$1,463
1,463
0
1,291
172
0
0
2018
$1,406
1,406
0
1,273
133
0
0
2019
2016 TIP Cashflow by Budget Approval
$644
644
0
644
0
0
0
2020
$717
717
0
673
44
0
0
2021
$388
335
0
143
192
0
0
Future
Total
$138,921
14,891
1,146
11,615
2,130
18,480
10,531
72 of 140
Adopted 2016 Transit Improvement Plan
1,503
20-Prelim Engineering/Env Review
1,774
90-Contingency
$74,046
0
86
5,167
70-Vehicles
80-System Testing+Startup
2,795
55-Construction Services
56,002
40-Row Acquisition+Permits
50-Construction
2,510
35-Third Party
704
3,503
30-Final Design+Specifications
Life to Date
10-Agency Administration
$74,046
195
Phase # and Description
6 - Systemwide
Total
8,911
4 - East King
Total
7,434
3 - South King
36,472
15,340
2 - North King
5 - Pierce
5,694
Life to Date
1 - Snohomish
Subarea
ALL MODES
Enhancement
2017
$33,765
0
12,248
5,627
4,460
8,822
2,609
$1,463
0
0
0
58
1,405
0
2018
2016
$26,494
77
500
1,098
504
15,285
3,109
3,118
994
381
1,427
$33,765
1,725
903
163
4,298
22,503
1,019
973
117
87
1,977
2017
(in thousands)
$1,463
0
0
172
0
100
891
0
0
100
200
2018
2016 TIP Cashflow by Phase
$26,494
280
8,747
771
3,409
12,445
842
2016
(in thousands)
2016 TIP Cashflow by Subarea
$1,406
0
0
133
0
80
893
0
0
100
200
2019
$1,406
0
0
0
45
1,361
0
2019
$644
0
0
0
0
29
314
0
0
100
200
2020
$644
0
0
0
0
644
0
2020
$717
0
0
44
0
0
366
0
0
107
200
2021
$717
0
0
0
15
702
0
2021
$388
0
0
192
0
53
69
0
0
0
74
Future
$388
0
0
0
64
324
0
Future
Total
$138,921
1,802
1,490
6,970
7,598
94,053
8,435
6,601
1,815
2,379
7,780
Total
$138,921
475
57,467
15,309
15,484
41,042
9,145
Enhancement
REGIONAL
EXPRESS
5X261
Bus Maintenance Facility
Managed by: Operations
Scope: Fund expansion of Sound Transit's fleet maintenance capacity through contributions to facilities managed by third party service providers.
Changes in lifetime since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
None
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$22,033
2015 Cost Estimate:
N/A
2016 TIP:
$22,033
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
Snohomish
1,384
222
1,875
0
0
0
0
0
3,481
South King
972
156
1,317
0
0
0
0
0
2,446
East King
4,151
667
5,626
0
0
0
0
0
10,444
Pierce
2,251
362
3,050
0
0
0
0
0
5,662
8,757
1,407
11,869
0
0
0
0
0
22,033
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
24
25
477
0
0
0
0
0
527
20-Prelim Engineering/Env
Review
8
0
0
0
0
0
0
0
8
Total
Phase
40-Row Acquisition+Permits
50-Construction
Total
59
0
0
0
0
0
0
0
59
8,665
1,382
11,392
0
0
0
0
0
21,439
8,757
1,407
11,869
0
0
0
0
0
22,033
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Planning
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2017
2016 Budget Schedule:
2017
Project Risk Assessment
The schedule is flexible as it is predicated on partners to submit projects for participation. The schedules dates can change if no projects are
planned.
Adopted 2016 Transit Improvement Plan
73 of 140
Enhancement
OTHER
700723
Downtown Seattle Transit Tunnel Mitigation
Managed by: Operations
Scope: This project reflects the Sound Transit contribution to a partnership for a series of mitigation improvements, including street improvements in
downtown Seattle to improve bus operations as buses transition from the Downtown Seattle Transit Tunnel (DSTT) to surface streets to accommodate
increased light rail activity in the tunnel.
Changes in lifetime budget since 2015: New Project.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$0
2015 Cost Estimate:
N/A
2016 TIP:
$2,334
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
North King
Total
Phase
35-Third Party
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
0
1,728
606
0
0
0
0
0
2,334
0
1,728
606
0
0
0
0
0
2,334
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
0
1,728
606
0
0
0
0
0
2,334
0
1,728
606
0
0
0
0
0
2,334
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Fixed Contribution
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2017
2016 Budget Schedule:
2017
Project Risk Assessment
N/A
74 of 140
Adopted 2016 Transit Improvement Plan
Enhancement
LINK
700730
Operations & Maintenance Facility LRV Vehicle Lift
Managed by: DECM
Scope: Design, procure and install a second lift in the Link Operations and Maintenance Facility (OMF). The installation of a second lift in support of
operations is required to accommodate scheduled and unscheduled light rail vehicle (LRV) maintenance needs and capacity.
Changes in lifetime budget since 2015: New Project
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
Pending
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$0
2015 Cost Estimate:
N/A
2016 TIP:
$4,898
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
North King
South King
Total
Phase
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
162
2,112
1,906
0
0
0
0
0
4,179
28
363
328
0
0
0
0
0
719
189
2,475
2,234
0
0
0
0
0
4,898
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
53
175
71
0
0
0
0
0
299
20-Prelim Engineering/Env
Review
136
64
0
0
0
0
0
0
200
30-Final Design+Specifications
0
900
0
0
0
0
0
0
900
50-Construction
0
1,204
2,032
0
0
0
0
0
3,236
55-Construction Services
Total
0
131
132
0
0
0
0
0
263
189
2,475
2,234
0
0
0
0
0
4,898
Budget Risk Assessment
Estimate Type:
Schedule Risk Assessment
Conceptual Engineering
Budget Risk Level:
Medium
Schedule Risk Level:
High
2015 Budget Schedule:
2016 Budget Schedule:
2017
Project Risk Assessment
Constructability of project given the constraints of having to install the lift in an on-going working environment, creates challenges in both schedule
and cost.
Adopted 2016 Transit Improvement Plan
75 of 140
Enhancement
OTHER
700736
Union Station Garden Level Remodel
Managed by: Operations
Scope: Renovate Union Station's Garden Level: convert cubicle space from 8X8 to 6X8 configuration, add 7 enclosed offices, relocate 3 offices,
create a new mailroom, install new carpet, purchase and install 132 cubicles, and install new data cabling to support additional staff and consultants.
Change in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$1,383
2015 Cost Estimate:
N/A
2016 TIP:
$1,383
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
North King
Total
Phase
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
23
1,360
0
0
0
0
0
0
1,383
23
1,360
0
0
0
0
0
0
1,383
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
3
0
0
0
0
0
0
0
3
20-Prelim Engineering/Env
Review
0
10
0
0
0
0
0
0
10
21
0
0
0
0
0
0
0
21
0
1,350
0
0
0
0
0
0
1,350
23
1,360
0
0
0
0
0
0
1,383
30-Final Design+Specifications
50-Construction
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Planning
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2015
2016 Budget Schedule:
2016
Project Risk Assessment
76 of 140
Adopted 2016 Transit Improvement Plan
Enhancement
OTHER
700784
Regional Parking Pilot Project
Managed by: Operations
Scope: Conduct test and evaluate parking management strategies under the system implementation of customer parking permits to include: vanpool
customer parking, community outreach activities and real time parking availability monitoring.
Changes in lifetime budget since 2015: None
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$475
2015 Cost Estimate:
N/A
2016 TIP:
$475
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Systemwide
Total
Phase
20-Prelim Engineering/Env
Review
50-Construction
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
195
280
0
0
0
0
0
0
475
195
280
0
0
0
0
0
0
475
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
95
107
0
0
0
0
0
0
202
100
173
0
0
0
0
0
0
273
195
280
0
0
0
0
0
0
475
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Planning
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2014
2016 Budget Schedule:
2016
Project Risk Assessment
N/A
Adopted 2016 Transit Improvement Plan
77 of 140
Enhancement
LINK
700793
Signage Improvements
Managed by: Operations
Scope: Sound Transit is modifying and updating signage at existing Link and Sounder stations and ticket vending machine (TVM) locations to improve
wayfinding and reflect system expansion. Work includes design, fabrication, and installation of new signage elements.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$931
2015 Cost Estimate:
N/A
2016 TIP:
$931
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
Snohomish
0
3
0
0
0
0
0
0
3
North King
42
403
0
0
0
0
0
0
445
South King
45
432
0
0
0
0
0
0
478
0
1
0
0
0
0
0
0
1
East King
Pierce
0
4
0
0
0
0
0
0
5
89
843
0
0
0
0
0
0
931
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
36
40
0
0
0
0
0
0
76
30-Final Design+Specifications
50
44
0
0
0
0
0
0
94
3
725
0
0
0
0
0
0
728
0
33
0
0
0
0
0
0
33
89
843
0
0
0
0
0
0
931
Total
Phase
50-Construction
55-Construction Services
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Scoping
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2015
2016 Budget Schedule:
2016
Project Risk Assessment
N/A
78 of 140
Adopted 2016 Transit Improvement Plan
Enhancement
LINK
700798
Link Remote Switch Heaters
Managed by: Operations
Scope: Install remote switch heaters at Rainier Beach Station and Stadium Station interlockings to enhance the capabilities of providing all-weather
service.
Changes in lifetime budget since 2015: None
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$200
2015 Cost Estimate:
N/A
2016 TIP:
$200
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
North King
Total
Phase
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
0
200
0
0
0
0
0
0
200
0
200
0
0
0
0
0
0
200
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
0
35
0
0
0
0
0
0
35
50-Construction
0
165
0
0
0
0
0
0
165
0
200
0
0
0
0
0
0
200
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Initial Estimate
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2015
2016 Budget Schedule:
2017
Project Risk Assessment
Remote switch heaters will be installed by Sound Transit maintenance staff. Risk of other work receiving the resource allocaitons resulting in delays
to the project schedule.
Adopted 2016 Transit Improvement Plan
79 of 140
Enhancement
SOUNDER
300011
Positive Train Control
Managed by: DECM
Scope: Integrate command, control, communications, and information systems for controlling passenger train movements with safety, security,
precision, and efficiency. These systems will improve railroad safety by significantly reducing the probability of collisions between trains, casualties to
railway workers and damage to their equipment, and over speed accidents. Federal regulations had previously mandated that PTC be operational on
all passenger rail systems by the end of December 2015, but this was recently extended by three years. The project was originally scheduled to be
completed in 2015, however due to third party delays, it will now likely complete in third quarter of 2016. Budget displayed in 2017 is considered
surplus at this time.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
6-Proceed to Construction
Baseline:
$53,054
2008 Cost Estimate:
N/A
2015 TIP:
$53,054
2015 Cost Estimate:
N/A
2016 TIP:
$53,054
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Snohomish
South King
Pierce
Total
Phase
10-Agency Administration
30-Final Design+Specifications
35-Third Party
50-Construction
55-Construction Services
80-System Testing+Startup
90-Contingency
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
2,460
574
733
0
0
0
0
0
3,767
1,525
356
454
0
0
0
0
0
2,334
30,669
7,152
9,133
0
0
0
0
0
46,953
34,654
8,081
10,319
0
0
0
0
0
53,054
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
1,212
151
876
0
0
0
0
0
2,238
226
0
52
0
0
0
0
0
279
2,510
1,390
367
0
0
0
0
0
4,267
29,912
5,750
3,333
0
0
0
0
0
38,995
707
290
3,064
0
0
0
0
0
4,062
86
500
903
0
0
0
0
0
1,490
0
0
1,725
0
0
0
0
0
1,725
34,654
8,081
10,319
0
0
0
0
0
53,054
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Medium
2015 Budget Schedule:
2015
2016 Budget Schedule:
2016
Project Risk Assessment
Limited availability of contractor technical staff and high demand for their services. Availability of Federal Railroad Administration staff for final
certification.
80 of 140
Adopted 2016 Transit Improvement Plan
Enhancement
LINK
4X210
LRV On Board Energy Storage
Managed by: DECM
Scope: Design, procure, and install energy storage units on up to five light rail vehicles to capture and store energy generated by vehicle braking for
reuse to improve vehicle operational efficiencies, lower energy consumption, and reduce operating costs. The project is partially funded by a Transit
Investment for Greenhouse Gas and Energy Reduction (TIGGER) grant awarded to Sound Transit in 2011. Work was completed in June 2014
however, the project will not close until contract warranty support is closed out in 2016. Budget cash flow in 2017 reflects projected surplus budget.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
6-Proceed to Construction
Baseline:
$1,643
2008 Cost Estimate:
N/A
2015 TIP:
$1,643
2015 Cost Estimate:
N/A
2016 TIP:
$1,643
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
North King
Total
Phase
10-Agency Administration
30-Final Design+Specifications
70-Vehicles
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
1,488
93
63
0
0
0
0
0
1,643
1,488
93
63
0
0
0
0
0
1,643
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
7
0
53
0
0
0
0
0
60
0
0
10
0
0
0
0
0
10
1,481
93
0
0
0
0
0
0
1,573
1,488
93
63
0
0
0
0
0
1,643
Budget Risk Assessment
Estimate Type:
Schedule Risk Assessment
Construction
Budget Risk Level:
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2014
2016 Budget Schedule:
2016
Project Risk Assessment
Project pending final payment of warranty coverage in 2016.
Adopted 2016 Transit Improvement Plan
81 of 140
Enhancement
LINK
4X340
Noise Abatement
Managed by: DECM
Scope: Design and construct a noise wall along the Link elevated guideway in Tukwila. Funding for the completion of the Residential Sound Insulation
Program (RSIP) for residences impacted by noise from operations of Central Link in the Rainier Valley is included in this project. Construction of the
noise wall was completed in 2013. The project is expected to close in 2016. Budget cash flow in 2017 reflects projected surplus budget.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
6-Proceed to Construction
Baseline:
$13,000
2008 Cost Estimate:
N/A
2015 TIP:
$13,000
2015 Cost Estimate:
N/A
2016 TIP:
$13,000
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
North King
6,136
18
2,723
0
0
0
0
0
8,876
South King
2,850
8
1,265
0
0
0
0
0
4,124
8,986
26
3,987
0
0
0
0
0
13,000
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
1,022
10
168
0
0
0
0
0
1,200
5
0
55
0
0
0
0
0
60
Total
Phase
10-Agency Administration
30-Final Design+Specifications
40-Row Acquisition+Permits
50-Construction
55-Construction Services
Total
16
1
83
0
0
0
0
0
100
5,856
15
2,579
0
0
0
0
0
8,450
2,088
0
1,102
0
0
0
0
0
3,190
8,986
26
3,987
0
0
0
0
0
13,000
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2015
2016 Budget Schedule:
2016
Project Risk Assessment
N/A
82 of 140
Adopted 2016 Transit Improvement Plan
Enhancement
LINK
600029
Tacoma Link Fare Collection
Managed by: FIT
Scope: Install and commission eight ticket vending machines at Tacoma Link stations, establish a spare parts inventory, set up fare collection and fare
enforcement support, and conduct public outreach.
Changes in lifetime budget since 2015: None
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$514
2015 Cost Estimate:
N/A
2016 TIP:
$514
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
64
392
58
0
0
0
0
0
514
64
392
58
0
0
0
0
0
514
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
50-Construction
64
325
58
0
0
0
0
0
447
90-Contingency
0
67
0
0
0
0
0
0
67
64
392
58
0
0
0
0
0
514
Pierce
Total
Phase
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Initial Estimate
Low
Schedule Risk Level:
Medium
2015 Budget Schedule:
2014
2016 Budget Schedule:
2016
Project Risk Assessment
Key project risks include a further deferment of implementation. Additionally, fare system contractor timelines for software development and ability
to reach intergovernmental agreements for fare enforcement may cause a delay once implementation is approved.
Adopted 2016 Transit Improvement Plan
83 of 140
Enhancement
LINK
700774
Central Link HVAC - Instrument House and UPS Room
Managed by: DECM
Scope: Install HVAC system in the uninterruptible power supply (UPS) rooms and signal houses. This project consists of installing AC units in ten
instrument houses along the Central Link corridor. AC units are needed to keep equipment inside the bungalows from overheating during periods of
hot weather. This project is necessary to ensure the continued integrity of the signal equipment throughout the system. This is the current design
standard for Link light rail.
Changes in lifetime budget since 2015: Increased lifetime budget $661 thousand due to complications and procurement of real property at various
sites.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$571
2015 Cost Estimate:
N/A
2016 TIP:
$1,232
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
North King
South King
Total
Phase
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
254
570
0
0
0
0
0
0
824
125
282
0
0
0
0
0
0
408
379
853
0
0
0
0
0
0
1,232
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
140
310
0
0
0
0
0
0
450
30-Final Design+Specifications
116
0
0
0
0
0
0
0
116
2
43
0
0
0
0
0
0
46
121
500
0
0
0
0
0
0
621
379
853
0
0
0
0
0
0
1,232
40-Row Acquisition+Permits
50-Construction
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2015
2016 Budget Schedule:
2016
Project Risk Assessment
Project delays associated with small right-of-way needs to allow for the proper installation of equipment.
84 of 140
Adopted 2016 Transit Improvement Plan
Enhancement
OTHER
7X743
Security Enhancements
Managed by: FIT
Scope: Install 95 analog cameras and 8 digital video recorders with a central monitoring application. Upgrade networked video recorders with six times
the amount of video storage and high quality digital video capabilities. Upgrade 62 cameras to either a megapixel IP camera or a higher quality
encoded video camera which allows such features as video analytics, high definition viewing, and a streamlined video administration and video
sharing capability. Project is complete.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$2,498
2015 Cost Estimate:
N/A
2016 TIP:
$2,498
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
North King
Total
Phase
20-Prelim Engineering/Env
Review
50-Construction
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
2,445
0
0
0
0
0
0
53
2,498
2,445
0
0
0
0
0
0
53
2,498
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
162
0
0
0
0
0
0
0
162
2,283
0
0
0
0
0
0
53
2,336
2,445
0
0
0
0
0
0
53
2,498
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2015
2016 Budget Schedule:
2015
Project Risk Assessment
N/A
Adopted 2016 Transit Improvement Plan
85 of 140
Enhancement
OTHER
7X753
Bike Locker Program
Managed by: DECM
Scope: Install new bicycle parking at various Sounder commuter rail, ST Express bus, and Link light rail stations. In addition, project-funded design
and construction of a bicycle plaza adjacent to the light rail Columbia City station. In King County, Sound Transit will add bicycle parking spaces at six
light rail and commuter rail stations (Tukwila Station, Kent Station, Auburn Station, Columbia City Station, Othello Station, and Rainier Beach Station).
In Pierce County, Sound Transit will expand secured bicycle parking at Puyallup and Sumner Stations. The project will also add benches, lighting,
signage, and other pedestrian and bicycle amenities at the commuter rail stations.
Anticipated completion of this project is 2016.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$1,355
2015 Cost Estimate:
N/A
2016 TIP:
$1,355
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
Snohomish
35
5
1
0
0
0
0
0
41
North King
569
80
19
0
0
0
0
0
668
South King
320
45
11
0
0
0
0
0
375
17
2
1
0
0
0
0
0
20
East King
Pierce
213
30
7
0
0
0
0
0
251
1,154
161
39
0
0
0
0
0
1,355
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
283
61
39
0
0
0
0
0
383
30-Final Design+Specifications
98
0
0
0
0
0
0
0
98
40-Row Acquisition+Permits
13
0
0
0
0
0
0
0
13
760
101
0
0
0
0
0
0
861
1,154
161
39
0
0
0
0
0
1,355
Total
Phase
10-Agency Administration
50-Construction
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2015
2016 Budget Schedule:
2016
Project Risk Assessment
N/A
86 of 140
Adopted 2016 Transit Improvement Plan
Enhancement
LINK
600033
Link CCTV System Upgrade
Managed by: FIT
Scope: Upgrade existing Link light rail Closed-Circuit Television (CCTV) NiceVision system at 16 stations and Link Operations and Maintenance
Facility (OMF). This upgrade will be compatible with the new equipment for University Link and South 200th Link extensions.
Changes in lifetime budget since 2015: New project established per Resolution No. R2015-19.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$700
2015 Cost Estimate:
N/A
2016 TIP:
$700
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
North King
South King
Total
Phase
50-Construction
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
0
468
0
0
0
0
0
0
468
0
232
0
0
0
0
0
0
232
0
700
0
0
0
0
0
0
700
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
0
700
0
0
0
0
0
0
700
0
700
0
0
0
0
0
0
700
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Scoping
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2016 Budget Schedule:
2016
Project Risk Assessment
Adopted 2016 Transit Improvement Plan
87 of 140
Enhancement
SOUNDER
700724
Puyallup Station LED Lighting
Managed by: Operations
Scope: Install energy efficient lighting at Puyallup Station. Work will result in receiving a utility incentive based upon the energy reduction achieved
and will reduce energy consumption on a ongoing basis.
Changes in lifetime budget since 2015: New project.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$0
2015 Cost Estimate:
N/A
2016 TIP:
$178
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
0
178
0
0
0
0
0
0
178
0
178
0
0
0
0
0
0
178
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
20-Prelim Engineering/Env
Review
0
19
0
0
0
0
0
0
19
50-Construction
0
159
0
0
0
0
0
0
159
0
178
0
0
0
0
0
0
178
Pierce
Total
Phase
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2016 Budget Schedule:
Project Risk Assessment
N/A
88 of 140
Adopted 2016 Transit Improvement Plan
2016
Enhancement
SOUNDER
700725
Sumner Station LED Lighting
Managed by: Operations
Scope: Install energy efficient lighting at Sumner Station. Work will result in receiving a utility incentive based upon the energy reduction achieved and
will reduce energy consumption on a ongoing basis.
Changes in lifetime budget since 2015: New project.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$0
2015 Cost Estimate:
N/A
2016 TIP:
$134
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
0
134
0
0
0
0
0
0
134
0
134
0
0
0
0
0
0
134
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
20-Prelim Engineering/Env
Review
0
15
0
0
0
0
0
0
15
50-Construction
0
120
0
0
0
0
0
0
120
0
134
0
0
0
0
0
0
134
Pierce
Total
Phase
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2016 Budget Schedule:
2016
Project Risk Assessment
N/A
Adopted 2016 Transit Improvement Plan
89 of 140
Enhancement
SOUNDER
700726
Kent Station Platform Lighting
Managed by: Operations
Scope: Install energy efficient lighting at Kent Station. In late 2012 lighting was upgraded in the Kent Garage, this project will extend the upgrades to
the platform, surface lots, pedestrian bridge, and bus loop areas. Work will result in receiving a utility incentive based upon the energy reduction
achieved and will reduce energy consumption on an ongoing basis.
Changes in lifetime budget since 2015: New project.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$0
2015 Cost Estimate:
N/A
2016 TIP:
$236
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
0
236
0
0
0
0
0
0
236
0
236
0
0
0
0
0
0
236
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
20-Prelim Engineering/Env
Review
0
26
0
0
0
0
0
0
26
50-Construction
0
210
0
0
0
0
0
0
210
0
236
0
0
0
0
0
0
236
South King
Total
Phase
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2016 Budget Schedule:
Project Risk Assessment
N/A
90 of 140
Adopted 2016 Transit Improvement Plan
2016
Enhancement
SOUNDER
700727
Kent Station Parking Lot Paving
Managed by: Operations
Scope: Design and install paved and landscaped commuter parking to an additional 36 standard spaces, 1 compact space and 2 Americans with
Disabilities Act (ADA) spaces.
Changes in lifetime budget since 2015: New project.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$0
2015 Cost Estimate:
N/A
2016 TIP:
$700
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
0
700
0
0
0
0
0
0
700
0
700
0
0
0
0
0
0
700
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
20-Prelim Engineering/Env
Review
0
140
0
0
0
0
0
0
140
50-Construction
0
560
0
0
0
0
0
0
560
0
700
0
0
0
0
0
0
700
South King
Total
Phase
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2016 Budget Schedule:
2016
Project Risk Assessment
N/A
Adopted 2016 Transit Improvement Plan
91 of 140
Enhancement
OTHER
700733
OMF LRV Wash Heater System
Managed by: Operations
Scope: Install a heating system within the OMF LRV washbay facility that includes overhead radiant heaters, water line heat tracing, and a small unit
heater. The installation of the system will allow for all-weather operation and reduce the risk to operators of working in icy conditions when weather is
below freezing.
Changes to lifetime budget since 2015: New project.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
1-Enter Project Development
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$300
2015 Cost Estimate:
N/A
2016 TIP:
$300
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
North King
70
130
0
0
0
0
0
0
201
South King
35
64
0
0
0
0
0
0
99
105
195
0
0
0
0
0
0
300
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
105
30
0
0
0
0
0
0
135
0
165
0
0
0
0
0
0
165
105
195
0
0
0
0
0
0
300
Total
Phase
10-Agency Administration
50-Construction
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Initial Estimate
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2016 Budget Schedule:
Project Risk Assessment
N/A
92 of 140
Adopted 2016 Transit Improvement Plan
2016
Enhancement
LINK
700773
Central Link HVAC for Traction Power
Managed by: DECM
Scope: Install air conditioning required in the Traction Power Substation to protect and enhance the useful life of temperature sensitive equipment.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$1,278
2015 Cost Estimate:
N/A
2016 TIP:
$1,278
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
North King
South King
Total
Phase
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
677
0
178
0
0
0
0
0
855
335
0
88
0
0
0
0
0
423
1,013
0
266
0
0
0
0
0
1,278
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
198
0
0
0
0
0
0
0
198
30-Final Design+Specifications
188
0
0
0
0
0
0
0
188
50-Construction
626
0
266
0
0
0
0
0
892
1,013
0
266
0
0
0
0
0
1,278
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2015
2016 Budget Schedule:
2015
Project Risk Assessment
N/A
Adopted 2016 Transit Improvement Plan
93 of 140
Enhancement
LINK
700775
Central Link Card Readers
Managed by: DECM
Scope: Install card readers on all doors at Central Link stations' public areas. Card readers are required to ensure secure premises, eliminate the
need to issue keys to a large number of staff and ensure consistency in key control.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$423
2015 Cost Estimate:
N/A
2016 TIP:
$423
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
North King
South King
Total
Phase
10-Agency Administration
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
30
253
0
0
0
0
0
0
283
15
125
0
0
0
0
0
0
140
44
379
0
0
0
0
0
0
423
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
44
20
0
0
0
0
0
0
64
30-Final Design+Specifications
0
50
0
0
0
0
0
0
50
50-Construction
0
249
0
0
0
0
0
0
249
55-Construction Services
0
50
0
0
0
0
0
0
50
0
10
0
0
0
0
0
0
10
44
379
0
0
0
0
0
0
423
90-Contingency
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2015
2016 Budget Schedule:
2017
Project Risk Assessment
N/A.
94 of 140
Adopted 2016 Transit Improvement Plan
Enhancement
LINK
700777
Central Link Overhead Catenary System Tie Switch
Managed by: Operations
Scope: Install the mechanical means to electrically bridge the Overhead Catenary System (OCS) section insulators at approximately 34 various
locations throughout the Link alignment to allow inspection and maintenance of traction power substations without interrupting Link service.
Changes in lifetime budget since 2015: None
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$3,000
2015 Cost Estimate:
N/A
2016 TIP:
$3,000
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
North King
South King
Total
Phase
10-Agency Administration
50-Construction
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
3
100
1,903
0
0
0
0
0
2,007
2
50
942
0
0
0
0
0
993
5
150
2,845
0
0
0
0
0
3,000
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
0
25
0
0
0
0
0
0
25
5
125
2,845
0
0
0
0
0
2,975
5
150
2,845
0
0
0
0
0
3,000
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Scoping
Low
Schedule Risk Level:
Medium
2015 Budget Schedule:
2015
2016 Budget Schedule:
2017
Project Risk Assessment
Project is intended to be completed by Link Maintenance staff. There is a risk to schedule when competing projects use limited resources initially
allocated to this project.
Adopted 2016 Transit Improvement Plan
95 of 140
Enhancement
REGIONAL
EXPRESS
700790
Pierce Transit Radio System Upgrade
Managed by: Operations
Scope: Replace all ST owned mobile radios currently installed in Pierce Transit-operated buses and necessary radio infrastructure components to be
compliant with F.C.C. 6.25 MHZ narrow band, digital technology effective December 31, 2016. The project will cover 118 radios for installation on ST
Express buses, plus 13 mobile/portable radios assigned to supervisors/mechanics.
The project is completed and will close in 2016. any remaining funds are considered surplus.
Change since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$1,000
2015 Cost Estimate:
N/A
2016 TIP:
$1,000
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Pierce
Total
Phase
50-Construction
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
562
438
0
0
0
0
0
0
1,000
562
438
0
0
0
0
0
0
1,000
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
562
438
0
0
0
0
0
0
1,000
562
438
0
0
0
0
0
0
1,000
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2014
2016 Budget Schedule:
2015
Project Risk Assessment
N/A
96 of 140
Adopted 2016 Transit Improvement Plan
Enhancement
REGIONAL
EXPRESS
7X745
ST Express Mobile Communications
Managed by: Operations
Scope: As part of the operation of the ST Express bus fleet, mobile communications are necessary to ensure driver and passenger safety, to enhance
the customer service information, and to improve the information available to the service planning function. The existing mobile communications
systems are aging and in need of upgrades. In addition, this investment allows the ST Express bus fleet to be compatible with partner communication
systems. A signed project participation agreement with Pierce Transit was executed in 2007. This project is in service. It was tested and accepted in
2010. Agreements for ST project participation with King County Metro and Community Transit projects were approved by the Board in 2008. These
projects were completed in 2014, any remaining funds in this project are considered surplus.
Changes in lifetime budget since 2015: None
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$10,531
2015 Cost Estimate:
N/A
2016 TIP:
$10,531
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
Snohomish
1,815
39
0
0
0
0
0
0
1,853
South King
1,041
22
0
0
0
0
0
0
1,064
East King
4,743
101
0
0
0
0
0
0
4,844
Pierce
2,712
58
0
0
0
0
0
0
2,770
10,311
220
0
0
0
0
0
0
10,531
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
50-Construction
7,044
220
0
0
0
0
0
0
7,264
70-Vehicles
3,267
0
0
0
0
0
0
0
3,267
10,311
220
0
0
0
0
0
0
10,531
Total
Phase
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Scoping
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2015
2016 Budget Schedule:
2015
Project Risk Assessment
N/A
Adopted 2016 Transit Improvement Plan
97 of 140
Enhancement
LINK
700781
Non-revenue Support Vehicles
Managed by: Operations
Scope: Purchase and replace maintenance vehicles to improve maintenance efficiencies for the Link light rail system.
Changes in lifetime budget since 2015: None
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$2,130
2015 Cost Estimate:
N/A
2016 TIP:
$2,130
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
North King
279
669
109
115
88
0
29
128
1,416
South King
141
337
55
58
45
0
15
64
713
420
1,006
163
172
133
0
44
192
2,130
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
420
1,006
163
172
133
0
44
192
2,130
420
1,006
163
172
133
0
44
192
2,130
Total
Phase
70-Vehicles
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Planning
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2019
2016 Budget Schedule:
2019
Project Risk Assessment
N/A
98 of 140
Adopted 2016 Transit Improvement Plan
Enhancement
OTHER
804100
Transit-Oriented Development Property Disposition
Managed by: PEPD
Scope: Dispose of properties that have been declared surplus and are suitable for transit oriented development based on size and proximity to ST
transit services; consistent with Sound Transit's Transit Oriented Development Policy.
Changes in lifetime budget since 2015: Project budget increased by $5.6 million: $5.1 million to add TOD eligible properties acquired through ST 2
phase and $494 thousand from the transfer of remaining funds from TOD Planning project.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$5,601
2015 Cost Estimate:
N/A
2016 TIP:
$11,615
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
North King
Total
Phase
10-Agency Administration
20-Prelim Engineering/Env
Review
40-Row Acquisition+Permits
50-Construction
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
2,016
4,261
1,315
1,291
1,273
644
673
143
11,615
2,016
4,261
1,315
1,291
1,273
644
673
143
11,615
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
331
546
293
200
200
200
200
74
2,044
0
0
87
100
100
100
107
0
494
1,684
3,065
936
891
893
314
366
69
8,217
1
650
0
100
80
29
0
0
860
2,016
4,261
1,315
1,291
1,273
644
673
143
11,615
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Planning
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2020
2016 Budget Schedule:
2023
Project Risk Assessment
N/A
Adopted 2016 Transit Improvement Plan
99 of 140
Enhancement
OTHER
8X100
Transit Oriented Development Planning
Managed by: PEPD
Scope: Provide planning and technical assistance to local jurisdictions and Sound Transit project teams to help identify and shape transit oriented
development and joint development opportunities.
Changes in lifetime budget since 2015: Project budget is decreased by $494 thousand. Project is completed and remaining funds are transferred to
TOD Property Disposition project.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$1,640
2015 Cost Estimate:
N/A
2016 TIP:
$1,146
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
North King
Total
Phase
10-Agency Administration
20-Prelim Engineering/Env
Review
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
1,146
0
0
0
0
0
0
0
1,146
1,146
0
0
0
0
0
0
0
1,146
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
43
0
0
0
0
0
0
0
43
1,103
0
0
0
0
0
0
0
1,103
1,146
0
0
0
0
0
0
0
1,146
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Planning
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2016
2016 Budget Schedule:
2017
Project Risk Assessment
N/A
100 of 140
Adopted 2016 Transit Improvement Plan
Rehabilitation & Replacement
Rehabilitation & Replacement projects extend the life of existing system assets and replace those at the end of their useful life.
As the transit system ages, investment in maintaining our assets in a state of good repair will rise.
Highlights

Replace deficient braided tile at Link stations to improve wayfinding and meet ADA standards.

Overhaul three Sounder locomotives to maintain them in good repair.

Upgrade CCTV and Public Announcement systems at Sounder stations and ST Express transit centers.
Lifetime Budget Changes
The table below explains the changes in individual project lifetime budgets since the publication of the Adopted 2015 TIP.
BUDGET CHANGES
(in thousands)
Project
LINK
Link Station Braided Tile
Replacement
Tacoma Link Light Rail
Vehicle Overhaul
OTHER
Small Works Program
Reason
Budget Type
New Project
Operating
New Project
Remove and replace braided wayfinding tile at
five link stations.
Preliminary Engineering Overhaul traction motors and trucks for all three
Tacoma Link light rail vehicles.
Cost Increase Program
Total
Adopted 2016 Transit Improvement Plan
Explanation
Extend the program another year and provide
an earmark for safety projects that need
immediate action.
Change
$435
$731
$1,179
$2,345
101 of 140
102 of 140
Adopted 2016 Transit Improvement Plan
Sounder Vehicle Overhaul Program
Tacoma Dome Station
Federal Way Post Tension Cable Repair
700770
7X356
7X768
0
2,838
$131,535
IT Transit Systems
870101
Total
Small Works Program
7X740
694
115,013
118,546
ST Express Fleet Replacement
7X701
11,281
4
0
10,064
1,213
0
1,550
342
1,208
157
157
0
Life to Date
Subtotal
Station Midlife Refurbishment Program
700771
Program
LRV Overhaul
700769
Subtotal
Link Station Braided Tile Replacement
700728
Operating
Tacoma Link Announcement/Sign System
7X758
Subtotal
Beacon Avenue Paving
4X360
Subtotal
IT Link Light Rail
870100
Baseline
Tacoma Link Light Rail Vehicle Overhaul
700718
Preliminary Engineering
Project Number and Name
ALL MODES
Rehabilitation & Replacement
$13,290
2,845
515
856
824
650
10,044
521
0
5,301
3,787
435
29
29
0
372
0
372
2016
$28,018
20,469
776
656
18,932
106
6,159
0
414
5,745
0
0
792
0
792
599
240
359
2017
31,710
480
614
30,615
0
3,191
0
0
3,191
0
0
0
0
0
673
673
0
2018
$35,574
(in thousands)
$4,963
4,057
550
979
2,528
0
0
0
0
0
0
0
0
0
0
906
906
0
2019
2016 TIP Cashflow by Budget Approval
$1,791
1,335
343
992
0
0
0
0
0
0
0
0
0
0
0
456
456
0
2020
$23,690
23,203
840
1,006
21,357
0
0
0
0
0
0
0
0
0
0
488
488
0
2021
$3,417
2,401
2,401
0
0
0
0
0
0
0
0
0
0
0
0
1,016
1,016
0
Future
$242,278
204,566
5,905
7,942
189,269
1,450
30,675
525
414
24,301
5,000
435
2,371
371
2,000
4,666
3,935
731
Total
Adopted 2016 Transit Improvement Plan
103 of 140
35,312
5 - Pierce
70-Vehicles
55-Construction Services
50-Construction
$131,535
120,350
166
10,233
0
97
35-Third Party
24
30-Final Design+Specifications
506
10-Agency Administration
20-Prelim Engineering/Env Review
157
Life to Date
$131,535
09-Admin Capital
Phase # and Description
Total
53,445
4 - East King
Total
18,225
3 - South King
0
2,562
2 - North King
6 - Systemwide
21,990
Life to Date
1 - Snohomish
Subarea
ALL MODES
Rehabilitation & Replacement
2017
$28,018
776
7,984
8,833
5,154
1,068
4,204
2018
$35,574
480
9,367
14,200
5,031
591
5,905
$13,290
10,120
0
2,719
150
91
42
168
0
2016
$28,018
23,020
64
4,669
0
159
34
72
0
2017
(in thousands)
$35,574
33,671
0
1,768
0
101
23
11
0
2018
2016 TIP Cashflow by Phase
$13,290
515
2,957
542
5,198
3,097
983
2016
(in thousands)
2016 TIP Cashflow by Subarea
$4,963
2,528
0
2,435
0
0
0
0
0
2019
$4,963
550
1,037
1,349
637
818
572
2019
$1,791
0
0
1,791
0
0
0
0
0
2020
$1,791
343
377
188
267
486
129
2020
2021
$23,690
21,357
0
2,334
0
0
0
0
0
2021
$23,690
840
5,999
10,015
2,434
512
3,890
$3,417
0
0
3,324
0
0
0
0
93
Future
$3,417
2,401
0
0
263
752
0
Future
Total
$242,278
211,046
230
29,272
150
449
123
758
250
Total
$242,278
5,905
63,032
88,573
37,209
9,886
37,673
Rehabilitation & Replacement
700718
LINK
Tacoma Link Light Rail Vehicle Overhaul
Managed by: Operations
Scope: Maintain, preserve, and extend the life of Tacoma Link light rail vehicles. This program overhauls the traction motors and trucks for the
Tacoma Link fleet comprised of three light rail vehicles.
Changes in lifetime budget since 2015: New project
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
Pending
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$0
2015 Cost Estimate:
N/A
2016 TIP:
$731
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
0
372
359
0
0
0
0
0
731
0
372
359
0
0
0
0
0
731
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
0
20
21
0
0
0
0
0
41
20-Prelim Engineering/Env
Review
0
19
6
0
0
0
0
0
25
0
333
332
0
0
0
0
0
665
0
372
359
0
0
0
0
0
731
Pierce
Total
Phase
70-Vehicles
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Scoping
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2016 Budget Schedule:
Project Risk Assessment
N/A
104 of 140
Adopted 2016 Transit Improvement Plan
2017
Rehabilitation & Replacement
OTHER
870100
IT Link Light Rail
Managed by: FIT
Scope: Maintain the lifecycle maintenance of the IT infrastructure behind the Link light rail (LLR) SCADA system to mitigate equipment failure of an
operationally-critical system. This project will provide for lifecycle maintenance of SCADA systems including, but not limited to, servers, SANs,
networking equipment, Video Messaging Systems/backend and other computer-based infrastructure. This will also entail enhancements and
maintenance for IT SCADA security.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
None
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$3,935
2015 Cost Estimate:
N/A
2016 TIP:
$3,935
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
North King
117
0
178
499
671
338
361
752
2,915
South King
41
0
62
174
235
118
126
263
1,020
157
0
240
673
906
456
488
1,016
3,935
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
157
0
0
0
0
0
0
93
250
0
0
240
673
906
456
488
923
3,685
157
0
240
673
906
456
488
1,016
3,935
Total
Phase
09-Admin Capital
50-Construction
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Medium
Schedule Risk Level:
Low
2015 Budget Schedule:
2023
2016 Budget Schedule:
2023
Project Risk Assessment
Potential for risk of increased cost as system expands and integration and support require more resources to meet system compliance standards.
Adopted 2016 Transit Improvement Plan
105 of 140
Rehabilitation & Replacement
LINK
4X360
Beacon Avenue Paving
Managed by: DECM
Scope: As agreed with the city of Seattle, perform roadway improvements on Beacon Avenue between South McClellen Street and South Landers
Street to mitigate construction impacts by construction of the Initial Segment. All work is complete and the project is expected to close out in 2016;
budget cash flow in 2017 reflects surplus budget.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
6-Proceed to Construction
Baseline:
$2,000
2008 Cost Estimate:
N/A
2015 TIP:
$2,000
2015 Cost Estimate:
N/A
2016 TIP:
$2,000
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
1,208
0
792
0
0
0
0
0
2,000
1,208
0
792
0
0
0
0
0
2,000
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
109
0
41
0
0
0
0
0
150
79
0
46
0
0
0
0
0
125
50-Construction
855
0
640
0
0
0
0
0
1,495
55-Construction Services
166
0
64
0
0
0
0
0
230
1,208
0
792
0
0
0
0
0
2,000
North King
Total
Phase
10-Agency Administration
30-Final Design+Specifications
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2014
2016 Budget Schedule:
2016
Project Risk Assessment
N/A
106 of 140
Adopted 2016 Transit Improvement Plan
Rehabilitation & Replacement
LINK
7X758
Tacoma Link Announcement/Sign System
Managed by: Operations
Scope: Procure and install a new communications system for Tacoma Link. System replacement is required due to the limited availability of
replacement parts and technical support for the existing technology.
Project is complete and will be closed in 2016. Any remaining funds are considered surplus.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$371
2015 Cost Estimate:
N/A
2016 TIP:
$371
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Pierce
Total
Phase
10-Agency Administration
50-Construction
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
342
29
0
0
0
0
0
0
371
342
29
0
0
0
0
0
0
371
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
2
19
0
0
0
0
0
0
21
340
10
0
0
0
0
0
0
350
342
29
0
0
0
0
0
0
371
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2015
2016 Budget Schedule:
2015
Project Risk Assessment
N/A
Adopted 2016 Transit Improvement Plan
107 of 140
Rehabilitation & Replacement
LINK
700728
Link Station Braided Tile Replacement
Managed by: Operations
Scope: Demolition and reinstallation of braided wayfinding tile at five Link light rail stations.
Changes in lifetime budget since 2015 - New project
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$0
2015 Cost Estimate:
N/A
2016 TIP:
$435
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
North King
Total
Phase
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
0
435
0
0
0
0
0
0
435
0
435
0
0
0
0
0
0
435
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
0
22
0
0
0
0
0
0
22
50-Construction
0
413
0
0
0
0
0
0
413
0
435
0
0
0
0
0
0
435
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Initial Estimate
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2016 Budget Schedule:
Project Risk Assessment
N/A
108 of 140
Adopted 2016 Transit Improvement Plan
2016
Rehabilitation & Replacement
LINK
700769
LRV Overhaul
Managed by: DECM
Scope: Complete repairs of the gear units and traction motors on light rail vehicles (LRVs), and purchase materials, equipment, services, and labor
necessary to complete repairs. Work is projected to complete in 2016.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$5,000
2015 Cost Estimate:
N/A
2016 TIP:
$5,000
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
North King
South King
Total
Phase
70-Vehicles
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
812
2,533
0
0
0
0
0
0
3,345
402
1,253
0
0
0
0
0
0
1,655
1,213
3,787
0
0
0
0
0
0
5,000
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
1,213
3,787
0
0
0
0
0
0
5,000
1,213
3,787
0
0
0
0
0
0
5,000
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Initial Estimate
High
Schedule Risk Level:
Low
2015 Budget Schedule:
2015
2016 Budget Schedule:
2016
Project Risk Assessment
Budget risk remains high given no agreement regarding the warranty coverage on repairs has been reached between manufacturer, supplier and
Sound Transit.
Adopted 2016 Transit Improvement Plan
109 of 140
Rehabilitation & Replacement
SOUNDER
700770
Sounder Vehicle Overhaul Program
Managed by: Operations
Scope: Maintain, preserve, and extend the life of Sounder locomotives and cab car fleet. This program overhauls 11 locomotives of the Sounder fleet
while upgrading technolgies and emisison efficiencies, truck overhauls of cab cars and HVAC upgrades to the same.
Change in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$24,301
2015 Cost Estimate:
N/A
2016 TIP:
$24,301
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
Snohomish
1,379
726
787
437
0
0
0
0
3,329
South King
5,274
2,778
3,010
1,672
0
0
0
0
12,734
Pierce
3,412
1,797
1,948
1,082
0
0
0
0
8,238
10,064
5,301
5,745
3,191
0
0
0
0
24,301
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
0
11
11
11
0
0
0
0
32
20-Prelim Engineering/Env
Review
0
23
28
23
0
0
0
0
74
Total
Phase
30-Final Design+Specifications
50-Construction
70-Vehicles
Total
0
91
113
101
0
0
0
0
305
6,130
0
1,838
0
0
0
0
0
7,968
3,935
5,176
3,756
3,056
0
0
0
0
15,923
10,064
5,301
5,745
3,191
0
0
0
0
24,301
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Initial Estimate
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2018
2016 Budget Schedule:
2018
Project Risk Assessment
N/A
110 of 140
Adopted 2016 Transit Improvement Plan
Rehabilitation & Replacement
OTHER
7X356
Tacoma Dome Station
Managed by: Operations
Scope: Provide financial support to address major maintenance requirement at Tacoma Dome Station per agreement with Pierce Transit.
Changes in lifetime budget since 2015: None
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$414
2015 Cost Estimate:
N/A
2016 TIP:
$414
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Pierce
Total
Phase
50-Construction
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
0
0
414
0
0
0
0
0
414
0
0
414
0
0
0
0
0
414
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
0
0
414
0
0
0
0
0
414
0
0
414
0
0
0
0
0
414
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Fixed Contribution
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2015
2016 Budget Schedule:
2018
Project Risk Assessment
N/A
Adopted 2016 Transit Improvement Plan
111 of 140
Rehabilitation & Replacement
REGIONAL
EXPRESS
7X768
Federal Way Post Tension Cable Repair
Managed by: DECM
Scope: Repair post tension cables that provide structural reinforcement of the Federal Way parking garage. Grease has been leaking out of the post
tension cable grout pockets indicating water penetration. The budget funds complete remediation. At a minimum, removal of failed grout pockets and
replacement of the grease-filled caps is required; however, more extensive remediation may be needed. The project was determined unnecessary and
will be closed in 2016. Any remaining funds are considered surplus.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$525
2015 Cost Estimate:
N/A
2016 TIP:
$525
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
South King
Total
Phase
10-Agency Administration
50-Construction
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
4
521
0
0
0
0
0
0
525
4
521
0
0
0
0
0
0
525
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
4
96
0
0
0
0
0
0
100
0
425
0
0
0
0
0
0
425
4
521
0
0
0
0
0
0
525
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2015
2016 Budget Schedule:
2015
Project Risk Assessment
N/A
112 of 140
Adopted 2016 Transit Improvement Plan
Rehabilitation & Replacement
SOUNDER
700771
Station Midlife Refurbishment Program
Managed by: Operations
Scope: Provide rehabilitation and mid-life maintenance for Sound Transit facilities that have been in service for fifteen years or longer.
Changes in lifetime budget since 2015: None
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$1,450
2015 Cost Estimate:
N/A
2016 TIP:
$1,450
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
South King
Pierce
Total
Phase
10-Agency Administration
50-Construction
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
463
434
70
0
0
0
0
0
967
231
216
35
0
0
0
0
0
483
694
650
106
0
0
0
0
0
1,450
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
8
0
0
0
0
0
0
0
8
687
650
106
0
0
0
0
0
1,442
694
650
106
0
0
0
0
0
1,450
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Planning
Low
Schedule Risk Level:
Medium
2015 Budget Schedule:
2016
2016 Budget Schedule:
2017
Project Risk Assessment
Undefined scope of work at the various station locations could affect both the budget and schedule.
Adopted 2016 Transit Improvement Plan
113 of 140
Rehabilitation & Replacement
REGIONAL
EXPRESS
7X701
ST Express Fleet Replacement
Managed by: Operations
Scope: Funds the bus fleet replacement program for ST Express.
Current Assumptions: FTA guidelines indicate that buses are to be replaced no earlier than either 12 years of service or 500,000 miles. Due to the
unique service characteristics of the ST Express fleet, Sound Transit buses typically reach 500,000 miles after only 10 years of operations.
Replacement decisions are informed by specific fleet performance in consultation with our operating partner agencies. During the period from 20132021 more than 185 buses will be replaced. The current fleet size is 280.
Changes in lifetime since 2015: None
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$189,269
2015 Cost Estimate:
N/A
2016 TIP:
$189,269
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
Snohomish
20,242
145
3,332
5,388
445
0
3,759
0
33,311
South King
11,616
83
1,912
3,092
255
0
2,157
0
19,116
East King
52,906
379
8,709
14,083
1,163
0
9,824
0
87,064
Pierce
Total
Phase
50-Construction
70-Vehicles
Total
30,248
217
4,979
8,052
665
0
5,617
0
49,778
115,013
824
18,932
30,615
2,528
0
21,357
0
189,269
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
47
0
0
0
0
0
0
0
47
114,966
824
18,932
30,615
2,528
0
21,357
0
189,222
115,013
824
18,932
30,615
2,528
0
21,357
0
189,269
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Planning
Medium
Schedule Risk Level:
Low
2015 Budget Schedule:
2020
2016 Budget Schedule:
2021
Project Risk Assessment
Budget risk is a concern as the cost estimates and vehicle types are annually reviewed as replacements are identified and the agency adopts onboard technologies to be included in future replacements.
114 of 140
Adopted 2016 Transit Improvement Plan
Rehabilitation & Replacement
OTHER
7X740
Small Works Program
Managed by: Operations
Scope: Projects completed under the small works program include modification/repairs of operating facilities and systems with an estimated total cost
of less than $200,000 per project. The budget for this program is based on number of sites maintained, age of facilities, and amount of use.
Changes in lifetime budget since 2015: Project budget increased by $1.2 million - $979 thousand to extend the program another year and $200
thousand earmarked for potential safety related projects.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$6,763
2015 Cost Estimate:
N/A
2016 TIP:
$7,942
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
Snohomish
369
111
85
80
127
129
131
0
1,032
North King
426
128
98
92
147
149
151
0
1,191
South King
426
128
98
92
147
149
151
0
1,191
East King
539
163
125
117
186
188
191
0
1,509
1,079
325
249
233
372
377
382
0
3,018
2,838
856
656
614
979
992
1,006
0
7,942
Pierce
Total
Phase
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
10-Agency Administration
385
0
0
0
0
0
0
0
385
20-Prelim Engineering/Env
Review
24
0
0
0
0
0
0
0
24
30-Final Design+Specifications
19
0
0
0
0
0
0
0
19
35-Third Party
50-Construction
70-Vehicles
Total
0
150
0
0
0
0
0
0
150
2,175
706
656
614
979
992
1,006
0
7,129
236
0
0
0
0
0
0
0
236
2,838
856
656
614
979
992
1,006
0
7,942
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Scoping
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2020
2016 Budget Schedule:
2021
Project Risk Assessment
N/A
Adopted 2016 Transit Improvement Plan
115 of 140
Rehabilitation & Replacement
OTHER
870101
IT Transit Systems
Managed by: FIT
Scope: Maintain, upgrade and replace multiple computer and technology-based systems at Sounder stations and ST Express transit centers to keep
them safe, secure, and functional for our customers.
Systems maintained include: Sounder Stations & Transit Centers - Closed circuit television (CCTV) access control and customer emergency stations.
Sounder - Passenger information systems, automated passenger counters and variable message signage.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$5,905
2015 Cost Estimate:
N/A
2016 TIP:
$5,905
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Systemwide
Total
Phase
50-Construction
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
0
515
776
480
550
343
840
2,401
5,905
0
515
776
480
550
343
840
2,401
5,905
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
0
515
776
480
550
343
840
2,401
5,905
0
515
776
480
550
343
840
2,401
5,905
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Medium
Schedule Risk Level:
Medium
2015 Budget Schedule:
2023
2016 Budget Schedule:
2023
Project Risk Assessment
Information technology is ever changing and could adversely affect both the cost of the equipment and the availability of the equipment and
technology.
116 of 140
Adopted 2016 Transit Improvement Plan
Administrative
Administrative projects are not specific to any transit mode or capital program. However, these projects fund disposition of
surplus real estate, procurement of administrative equipment, facilities, and technology, as well as administrative support critical
to the successful operation of the agency. Administrative costs that support projects are charged to construction in progress and
capitalized with the resulting assets.
Highlights

Replace eight non-revenue vehicles used by administrative staff.

Replace asphalt shingles on the Union Station administration building.

Continue landscape and wetland hydrology mitigation and maintenance activities at selected Sound Transit properties.

Procure and implement the eBid system to improve vendor solicitation process.

Investigate the potential of a business intelligence system to enhance usability of agency and industry data.
Lifetime Budget Changes
The table below explains the changes in individual project lifetime budgets since the publication of the Adopted 2015 TIP.
BUDGET CHANGES
(in thousands)
Project
Reason Budget Type Explanation
OTHER
Administrative Capital Increase Operating
Purchase furniture for additional work space
needed to accommodate consultants and
employees.
Total
Adopted 2016 Transit Improvement Plan
Change
$150
$150
117 of 140
118 of 140
Adopted 2016 Transit Improvement Plan
18,123
189
$280,346
Surplus Property Disposition
804500
5,677
11,982
Total
Information Technology Program
803800
274
262,223
262,223
Life to Date
Subtotal
Administrative Capital
802000
Subtotal
Environmental Mitigation, Monitoring &
Maintenance
Agency Administration Operating
600025
Program
0X002
Operating
Project Number and Name
ALL MODES
Administrative
$63,679
3,575
120
2,164
1,097
194
60,104
60,104
2016
$69,577
5,297
113
2,305
2,726
153
64,281
64,281
2017
3,370
285
2,068
856
160
68,629
68,629
2018
$71,999
(in thousands)
$73,257
2,836
0
2,172
551
113
70,421
70,421
2019
2016 TIP Cashflow by Budget Approval
$74,632
2,941
0
2,296
645
0
71,691
71,691
2020
$72,015
2,741
0
2,071
670
0
69,274
69,274
2021
$134,263
8,968
0
7,177
1,261
529
125,296
125,296
Future
$839,768
47,850
708
32,235
13,484
1,423
791,918
791,918
Total
Adopted 2016 Transit Improvement Plan
119 of 140
40
5 - Pierce
$280,346
0
189
40-Row Acquisition+Permits
90-Contingency
490
262,845
16,821
0
Life to Date
$280,346
20-Prelim Engineering/Env Review
10-Agency Administration
09-Admin Capital
02-Operation+Maintenance-Agency
Phase # and Description
Total
16
4 - East King
Total
170
3 - South King
279,882
189
2 - North King
6 - Systemwide
48
Life to Date
1 - Snohomish
Subarea
ALL MODES
Administrative
$69,577
69,311
22
9
95
113
27
2017
$71,999
71,554
24
9
99
285
28
2018
$63,679
50
120
194
60,464
2,702
149
2016
$69,577
50
113
263
64,402
4,749
0
2017
(in thousands)
$71,999
50
285
270
68,750
2,643
0
2018
2016 TIP Cashflow by Phase
$63,679
63,365
28
11
120
120
34
2016
(in thousands)
2016 TIP Cashflow by Subarea
$73,257
50
0
223
70,421
2,563
0
2019
$73,257
73,144
17
7
70
0
20
2019
$74,632
50
0
100
71,691
2,537
254
2020
$74,632
74,632
0
0
0
0
0
2020
$72,015
50
0
110
69,274
2,581
0
2021
$72,015
72,015
0
0
0
0
0
2021
$134,263
97
0
838
125,296
7,936
96
Future
$134,263
133,734
78
31
328
0
93
Future
$839,768
397
708
2,488
793,143
42,532
500
Total
$839,768
837,637
209
83
882
708
249
Total
Administrative
OTHER
0X002
Agency Administration Operating
Managed by: FIT
Scope: Funds administrative overhead expenses that are charged to capital projects and overhead expenses that are not allocated to either
projects or transit operations. Overhead expenses allocated to projects are included in the capitalized cost of the resulting assets. Unallocated
overhead expenses are included in general and administrative expenses for the agency.
The agency uses a cost allocation plan approved by the Federal Transit Administration. Use of this approved model makes the majority of indirect
project expenses eligible for federal grant funding. The project timeline coincides with that of the ST2 program: 2010 - 2023.
Changes in lifetime since 2015: None
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$791,918
2015 Cost Estimate:
N/A
2016 TIP:
$791,918
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Systemwide
Total
Phase
10-Agency Administration
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
262,223
60,104
64,281
68,629
70,421
71,691
69,274
125,296
791,918
262,223
60,104
64,281
68,629
70,421
71,691
69,274
125,296
791,918
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
262,223
60,104
64,281
68,629
70,421
71,691
69,274
125,296
791,918
262,223
60,104
64,281
68,629
70,421
71,691
69,274
125,296
791,918
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Planning
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2023
2016 Budget Schedule:
2023
Project Risk Assessment
N/A
120 of 140
Adopted 2016 Transit Improvement Plan
Administrative
OTHER
600025
Environmental Mitigation, Monitoring & Maintenance
Managed by: PEPD
Scope: Monitor and maintain post-construction environmental mitigation including wetland hydrology, plant establishment, and other site features.
Duration depends upon permit conditions and may be 10 years and/or may last for the life of the property.
Changes in lifetime budget since 2015: None
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$1,423
2015 Cost Estimate:
N/A
2016 TIP:
$1,423
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
Snohomish
48
34
27
28
20
0
0
93
249
South King
170
120
95
99
70
0
0
328
882
East King
16
11
9
9
7
0
0
31
83
Pierce
40
28
22
24
17
0
0
78
209
274
194
153
160
113
0
0
529
1,423
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
274
194
153
160
113
0
0
529
1,423
274
194
153
160
113
0
0
529
1,423
Total
Phase
20-Prelim Engineering/Env
Review
Total
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Construction
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2030
2016 Budget Schedule:
2030
Project Risk Assessment
N/A
Adopted 2016 Transit Improvement Plan
121 of 140
Administrative
OTHER
802000
Administrative Capital
Managed by: FIT
Scope: Funds capital expenditures for administrative assets that support agency staff, including administrative facilities, non-revenue administrative
fleet, office equipment, space planning, and furnishings.
Changes in lifetime budget since 2015: Increase of $150,000 in lifetime budget for furniture in support of Agency's need for additional work space.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$13,334
2015 Cost Estimate:
N/A
2016 TIP:
$13,484
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Systemwide
Total
Phase
09-Admin Capital
90-Contingency
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
5,677
1,097
2,726
856
551
645
670
1,261
13,484
5,677
1,097
2,726
856
551
645
670
1,261
13,484
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
5,677
1,047
2,676
806
501
595
620
1,164
13,087
0
50
50
50
50
50
50
97
397
5,677
1,097
2,726
856
551
645
670
1,261
13,484
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Planning
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2023
2016 Budget Schedule:
2023
Project Risk Assessment
N/A
122 of 140
Adopted 2016 Transit Improvement Plan
Administrative
OTHER
803800
Information Technology Program
Managed by: FIT
Scope: Support agencywide hardware and software infrastructure, develop and implement technology solutions to improve administrative efficiency
through 2023.
Changes in lifetime budget since 2015: None.
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$32,235
2015 Cost Estimate:
N/A
2016 TIP:
$32,235
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
11,982
2,164
2,305
2,068
2,172
2,296
2,071
7,177
32,235
11,982
2,164
2,305
2,068
2,172
2,296
2,071
7,177
32,235
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
0
149
0
0
0
254
0
96
500
11,144
1,654
2,074
1,837
2,062
1,942
1,961
6,772
29,445
10-Agency Administration
622
360
121
121
0
0
0
0
1,225
20-Prelim Engineering/Env
Review
216
0
110
110
110
100
110
309
1,065
11,982
2,164
2,305
2,068
2,172
2,296
2,071
7,177
32,235
Systemwide
Total
Phase
02-Operation+MaintenanceAgency
09-Admin Capital
Total
Budget Risk Assessment
Estimate Type:
Schedule Risk Assessment
Conceptual Engineering
Budget Risk Level:
High
Schedule Risk Level:
High
2015 Budget Schedule:
2023
2016 Budget Schedule:
2023
Project Risk Assessment
Future year forecasts reflect initial planning estimates so costs are subject to change. Schedules are dependent on staff capacity and the specific
application or approach selected.
Adopted 2016 Transit Improvement Plan
123 of 140
Administrative
OTHER
804500
Surplus Property Disposition
Managed by: DECM
Scope: Prepare surplus properties for sale that due to their size or location do not lend themselves to Transit-Oriented Development (TOD)
opportunities. Surplus properties represent remnant properties that may have been used during construction or were acquired and no longer needed
for transit use.
Changes in lifetime budget since 2015: None
Board Approved Capital Budget (in thousands of YOE dollars)
Phase Gate Passed:
ST2 Total Project Cost Estimate (in thousands of 2015 dollars)
N/A
Baseline:
$0
2008 Cost Estimate:
N/A
2015 TIP:
$708
2015 Cost Estimate:
N/A
2016 TIP:
$708
2016 Cost Estimate:
N/A
TIP Cashflow (in thousands)
Subarea
North King
Total
Phase
40-Row Acquisition+Permits
Total
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
189
120
113
285
0
0
0
0
708
189
120
113
285
0
0
0
0
708
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
189
120
113
285
0
0
0
0
708
189
120
113
285
0
0
0
0
708
Budget Risk Assessment
Estimate Type:
Budget Risk Level:
Schedule Risk Assessment
Planning
Low
Schedule Risk Level:
Low
2015 Budget Schedule:
2017
2016 Budget Schedule:
2017
Project Risk Assessment
N/A
124 of 140
Adopted 2016 Transit Improvement Plan
Reserves
The 2016 TIP includes life to date contributions to the
agency’s various reserves as well as expected future
contributions through 2023, which corresponds with the
expected completion of ST2.
Emergency/Loss
Systemwide Contingency
While the agency maintains a comprehensive insurance
program, the policies do contain retentions (deductibles),
which the agency would have to cover in the event of an
insurable loss. In such instances, the Board could authorize
the use of the emergency/loss fund on a case-by-case basis.
The systemwide contingency was established as part of the
Sound Move program and was supplemented in the ST2
plan. This fund is for use by the Board to deal with any
unforeseen events.
Capital Replacement
Insurance Systemwide
The agency maintains a minimum $300.0 million reserve for
unanticipated expenditures necessary to keep the system in
good working condition. In addition, the agency maintains a
forecast of the funds necessary to repair and replace
existing assets to keep the regional transit system in a state
of good repair, consistent with industry standards. These
forecasts are included in the agency’s long-term financial
plan as a financial commitment. When such investments are
required, they are added to the budget and TIP in the Repair
& Replacement project category.
The insurance systemwide reserve is forecasted to be
funded beginning in 2016 when major new construction gets
underway. It will be available to partially pay for builders’ risk
insurance in conjunction with funds provided by building
contractors.
Operations & Maintenance
Sound Transit’s financial policies require the agency to
maintain an operation and maintenance reserve equal to two
months of department operating expenses, including costs
allocated to transit modes and projects.
AGENCY RESERVE SUMMARY
(in millions)
Life to Date
2016
2017
2018
2019
2020
2021
Future
Total
$12
$3
$3
$3
$3
$3
$3
$8
$38
Insurance Systemwide
0
6
6
6
6
0
0
0
23
Operations & Maintenance
0
60
0
0
0
0
0
0
60
Systemwide Contingency
0
0
5
0
0
0
0
0
5
306
0
0
0
0
0
0
0
306
$318
$69
$14
$9
$9
$3
$3
$8
$433
Emergency Loss
Capital Replacement
Total
Adopted 2016 Transit Improvement Plan
125 of 140
Appendix A – Sound Transit 2 Cost Estimates
The agency maintains cost estimates for all of its projects
that are funded in the agency’s financial plan. These
estimates are updated as new engineering, right-of-way,
public outreach, and other project information are
developed. Project cost estimates are updated prior to
seeking Board authorization of budgets for preliminary
engineering, final design, and right-of-way acquisition, and
baseline budget, which includes total project costs and
construction.
ST2 cost estimates were initially developed and reported in
2007 constant-year dollars. To enable comparisons
between cost estimates, the figures in this appendix have
been updated to 2015 constant-year dollars based on the
agency’s August 2015 inflation forecasts. The table on the
next page includes the following information:

2008 cost estimates from the initial ST2 plan
approved by voters in November 2008.

2015 cost estimates match the adopted 2015 TIP.

2016 cost estimates include all ST2 projects
currently funded in the agency’s financial plan.
The changes to the cost estimates between 2015 and 2016
include:

The transfer of cost estimates from HCT Corridor
Planning Studies and Central and East HCT Study
to ST3 Planning to provide additional funding for
long-range planning.

The closure of projects Ballard to Downtown
Seattle HCT Planning Study, Lynnwood to Everett
HCT Study and the South King County HCT Study.
These projects were removed from the cost
estimates.

The Sound Transit Board authorized the creation of
the Downtown Redmond Link Extension project to
complete the preliminary engineering from
Overlake to Redmond Transit Center.
The Angle Lake light rail station opens in 2016.
126 of 140
Adopted 2016 Transit Improvement Plan
ST2 COST ESTIMATES
(in thousands/constant 2015 dollars)
2008 Estimate
Inc / (Dec)
2015 Estimate
Inc / (Dec)
2016 Estimate
Link Light Rail
East Link
Downtown Redmond Link Extension
$3,311,457
($176,566)
$3,134,891
21,997
(21,997)
0
$3,134,891
18,195
18,195
Northgate Link Extension
1,734,306
170,244
1,904,550
1,904,550
Lynnwood Link Extension
1,421,593
1,668,579
(246,986)
1,421,593
First Hill Link Connector
138,141
(1,552)
136,590
136,590
South 200th Street Link Extension
404,745
(18,957)
385,788
385,788
South Corridor HCT - S200th to KDM Rd
492,218
(54,582)
437,636
437,636
South Corridor HCT - KDM Rd to S 272nd St
535,365
(535,365)
0
0
HCC to Tacoma Dome - P/E & ROW
47,267
(47,267)
0
0
South Corridor Alternatives Analysis
82,921
(79,843)
3,077
3,077
Tacoma Link Expansion
100,162
35,714
135,876
135,876
Link Maintenance & Storage
298,615
(47,026)
251,589
251,589
Link Fleet Expansion
Subtotal Link Light Rail
583,579
(255,326)
328,253
9,419,351
(1,279,507)
8,139,844
328,253
18,195
8,158,039
Sounder Commuter Rail
Station Access & Demand Study
148,901
(87,676)
61,226
61,226
Sumner Station Improvements
48,630
(4,518)
44,113
44,113
Puyallup Station Improvements
68,525
(10,548)
57,977
57,977
Lakewood Station Improvements
44,466
(6,668)
37,798
37,798
171,727
(22,168)
149,559
149,559
Sounder Yard & Shop Facility
Sounder Yard Expansion
0
21,092
21,092
21,092
Tukwila Permanent Station
40,943
7,417
48,360
48,360
Edmonds Permanent Station
27,168
(27,168)
196,715
Sounder South Expanded Service
0
0
57,047
253,762
253,762
Sounder ST2 Fleet Expansion
36,854
(6,416)
30,438
30,438
Tacoma Trestle Track & Signal
75,114
(11,585)
63,529
63,529
Tacoma Track & Signal
30,574
(306)
30,268
30,268
Platform Extensions - South King / Pierce
61,318
(61,318)
0
0
Eastside Rail Partnership
57,584
(57,582)
1
1,008,520
(210,397)
798,123
196,007
(6,429)
189,577
Subtotal Sounder Commuter Rail
1
0
798,123
Regional Express
ST Express Bus Base
Mid-Day Bus Storage
189,577
0
3,336
3,336
3,336
ST Express Fleet Expansion
41,041
4,179
45,220
45,220
ST Express Capital Reserve Program
28,164
(28,164)
I-90 Contribution
55,033
Burien - Parking Garage / Transit Center
16,357
Bothell - Parking Garage / Transit Center
6,129
Subtotal Regional Express
0
0
55,033
55,033
(645)
15,712
15,712
(18)
6,112
342,732
(27,743)
314,989
0
314,989
64,099
(16,700)
47,399
2,926
50,325
0
6,112
Other
ST3 Planning
HCT Corridor Planning Studies
0
554
554
(500)
54
Central and East HCT Study
0
4,538
4,538
(2,426)
2,112
ST Art Program
Subtotal Other
TOTAL ST2 Capital Estimate
0
27,306
27,306
64,099
15,698
79,797
0
79,797
$9,332,753
$18,195
$9,350,948
$10,834,702
($1,501,949)
27,306
Note: The cost estimates included in the table above reflect the amount included in the agency's long-term Financial Plan. Projects
proposed to proceed with only limited engineering activity are funded only to the extend that activtiy requires. Projects proposed to
be suspended or deleted have no funding in the current Long-term Financial Plan.
Adopted 2016 Transit Improvement Plan
127 of 140
Appendix B – Sound Move Lifetime Budgets
The agency has two voter-approved system expansion
programs, Sound Transit 2 (ST2) approved in 2008 and the
earlier Sound Move program approved in 1996. Appendix A
reflects the cost estimates in constant-year dollars for all
projects funded under the ST2 program. This appendix
displays adopted lifetime budgets in year-of-expenditure
dollars for active Sound Move system expansion projects.
Regional Express
Lifetime budgets for Sound Move projects were adopted as
total project budgets/baseline budgets, since these projects
pre-date the agency’s Phase Gate process. As with the ST2
projects in Appendix A, Sound Move lifetime budgets are
shown for 2008, 2015, and 2016.

Rainier Avenue Arterial improvements project was
closed in 2015.

Strander Boulevard Extension project was closed
in 2015.

Mountlake Terrace Freeway Station project was
closed in 2015.

S. Everett Freeway Station project was closed in
2015.

Issaquah transit Center/SR900 project was closed
in 2015.

The I-90 Two-Way Transit and HOV Operations,
Stage 3 project was baselined in 2014. This
project is funded by Sound Move & ST2, Regional
Express Reserve, and agency financial capacity.
The changes between 2015 and 2016 include:
Link Light Rail

Airport Link project was closed in 2015.
Sounder Commuter Rail

Permitting and Environmental Mitigation was
closed in 2015.
ADOPTED LIFETIME BUDGETS FOR ACTIVE SOUND MOVE PROJECTS
Year of Expenditure (YOE) Dollars (in thousands)
2008
Link Light Rail
University Link
Initial Segment
Inc/(Dec)
2015
Inc/(Dec)
2016
Subtotal Link Light Rail
$1,614,007
2,070,000
3,684,007
$142,000
21,768
163,768
$1,756,007
2,091,768
3,847,775
-
$1,756,007
2,091,768
3,847,775
Sounder Commuter Rail
M Street to Lakewood Track and Signal
D Street to M Street Track and Signal
Mukilteo Station, South Platform
Tukwila Station (see Notes)
Subtotal Sounder Commuter Rail
73,601
76,025
9,371
158,997
7,053
82,237
8,942
98,232
80,654
158,262
18,313
257,229
-
80,654
158,262
18,313
257,229
Regional Express
I-90 2-Way Transit & HOV Op, Stage 3 (see note)
85th Corridor, Kirkland
Kirkland Transit Center
Federal Way Transit Center
Subtotal Regional Express
STart Program
Total Active Sound Move Projects
1,722
6,015
13,300
39,455
60,492
18,100
$3,921,596
223,926
225,648
(425)
5,590
(2,341)
10,959
39,455
221,160
281,652
16,100
34,200
$499,260 $4,420,856
225,648
5,590
10,959
39,455
281,652
34,200
- $ 4,420,856
Notes: Numbers may not add due to rounding.
Tukwila Station is a project recognized in ST2, but Sound Move did fund the project through Final Design.
I-90 2-Way Transit and HOV Op, Stage 3 is recognized in Sound Move, but ST2 contributed $45 million of planned
funding. Additionally, to fully fund the project agency financial capcity was used $89.3 million and the balance of the REX
program reserve $27.2 million.
128 of 140
Adopted 2016 Transit Improvement Plan
Appendix C – Sound Transit Project Phases
Projects are typically planned and executed in phases. Project teams track and report on project costs relative to the activities
and deliverables in each. Project phases include:
01 – Operations+Maintenance
Costs to operate and maintain capital assets where the
budget to do so is part of an established lifetime budget.
Currently used to maintain Sound Transit’s public art
assets.
02 – Operations+Maintenance-Agency
Costs that cannot be capitalized. Currently used for
Research and Technology project costs incurred prior to
the establishment of project scope.
09 – Administrative Capital
Design, development and implementation or procurement
of Agency assets such as non-revenue vehicle fleet, IT
systems, furniture, and equipment.
10 – Agency Administration
Administrative expenditures occur throughout the life of the
project and include costs for direct labor by Sound Transit
staff (staff dedicated to specific projects) and other direct
charges to the project necessary for project execution.
20 – Preliminary Engineering & Environmental Review
Professional services to complete the preliminary
engineering and environmental assessments and
evaluations. Preliminary engineering identifies project
requirements and defines the project work scope. This
includes preliminary design studies, permitting
requirements, data collection, public involvement, legal and
technical documentation, cost estimates, and assessment
of alternatives. The environmental review includes
achievement of all necessary environmental permits.
26 – Research & Technology
Implementation of new transit technologies focused on
systemwide safety, security and communications with
passengers.
30 – Final Design & Specification
Final design includes professional consultant activities to
complete design and full construction plans and
specifications, legal and technical documentation,
environmental clearance, constructability review, value
engineering, data collection, advertising, assessment of
alternatives related to project design, and bid reviews.
35 – Third Parties
rather than the lead agency, it includes Sound Transit’s
funding obligation to the lead agency.
40 – Right-of-Way (ROW) Acquisition & Permits
ROW includes the cost to purchase or lease real property
required for construction and construction staging,
easements, rights-of-way, and any residential or
commercial relocations. This phase includes budget for
negotiating the purchase price, relocation costs, surveys,
appraisals, environmental audits, permits, legal costs,
maps, charts, and all permits not included under the
general construction contracts.
50 – Construction
Construction covers project construction contracts,
professional and technical assistance, advertising, legal
and technical documentation, inspection, testing, and
permitting. In addition, the construction budget includes
service startup, commissioning of all systems, and training.
55 – Construction Services
Construction Services includes construction management
and other professional services in support of the Agency’s
management of construction activities.
61 – Art
Procurement and installation of public art at stations and
along guideways.
70 – Vehicles
Procurement, manufacture, delivery, testing, and
commissioning of revenue vehicles, spare parts, and
warranty support. Also includes procurement of nonrevenue vehicles.
80 – Startup and Testing
Includes tests of new systems, new schedules, and various
specific equipment. This phase includes the training of
personnel before the completion of the project to identify
issues and correct them to enable a smooth transition to
operations and the close out of the project.
90 – Contingency
Contingency provides a funding source to address general
project risks, such as market fluctuations and changes in
regulatory requirements. It also covers unforeseen
expenses and cost estimate variances.
Third party expenditures occur through the life of the
project and include agreements with other governmental
units to reimburse their costs for review of alternatives,
design review, and construction monitoring and inspection.
In certain cases, when Sound Transit is a funding partner
Adopted 2016 Transit Improvement Plan
129 of 140
Appendix D – Subarea Allocations
The Central Puget Sound Regional Transit Authority
(Sound Transit) has implemented an accounting and
reporting system consistent with the financial policies
approved in the ST2 voter-approved program. Annually,
Sound Transit (the agency) prepares a Schedule of
Sources and Uses of Funds by Subarea (the schedule) that
is based on the agency’s audited financial statements and
the agency’s long-term Financial Plan. The schedule
reports actual tax revenues received by subarea and an
allocation to each subarea of other sources and uses
earned.
This system is integrated into the agency’s system of
internal control over financial reporting, ensuring the
integrity of the information reported and providing
management, the Board, and the Citizen Oversight Panel
required information to monitor progress against Sound
Transit’s subarea commitments to its voters.
Annually, the agency’s financial statement auditors perform
agreed upon procedures which look at the allocation of
sources and uses of funds presented. These procedures
were developed by management, reviewed by the Citizen
Oversight Panel, and approved by the Audit and Reporting
Committee of the Board. All results from independent
examinations are presented to the Board.
This appendix provides the drivers that will be used to
allocate sources and uses to subareas in 2015 as well as
new projects for 2016. Any additional projects are added at
the end of the year when subarea allocations are
calculated.
Revenues and Financing Sources
SOURCES
Description
Driver
Bond Proceeds
Financial Plan
Capital Grants
Project Costs or Board Designation
Interest Earnings
Financial Plan
Motor Vehicle Excise Tax
Zip Code Location
Operating Grants
Operating Uses by Mode
Other Revenue
Location/Modal Operating Use Drivers (see Operating
Uses section below)
Passenger Fares
(see next section)
Rental Car Tax
Department of Revenue Location Code/County Level
Sales & Use Tax
Department of Revenue Location Code
PASSENGER FARES
Description
Driver
Central Link Light Rail Fares
Station Boardings
Sounder Fares
Station Boardings
ST Express Fares
Route Boardings/Platform Hours
Tacoma Link Light Rail Fares
Station Boardings
130 of 140
Adopted 2016 Transit Improvement Plan
Operating Uses
LINK LIGHT RAIL SERVICES OPERATING USES
Description
Driver
Central Link Operations
Track Miles/Boardings
Tacoma Link Operations
Location
SOUNDER COMMUTER RAIL SERVICES OPERATING USES
Description
Driver
BNSF North Line
Track Miles
BNSF South Line
Track Miles
All Other Sounder Operations
Vehicle Miles
ST EXPRESS SERVICES OPERATING USES
Description
Driver
Bus Operations
Platform Hours
DSTT Operations
Location
OTHER USES
Description
Driver
Art Maintenance
Location
Other Expenses
Location or Board Designation
Capital Project Uses (Outlays)
System Expansion – Link Light Rail Projects
Driver
East Link Extension
ST2 Adopted Financial Plan Location
Downtown Redmond Link Extension
Location
Federal Way Link Extension
Location
First Hill Link Streetcar
Location
Initial Segment
2009 Sound Move Reported Rules
Link Operations & Maintenance Satellite Facility
ST2 Adopted Financial Plan
Lynnwood Link Extension
ST2 Adopted Financial Plan
Northgate Link Extension
Location
S. 200th Link Extension
Location
Tacoma Link Expansion
Location
University Link Extension
Location
ST2 LRV Fleet Expansion
ST2 Adopted Financial Plan
Enhancements to Tacoma Link Expansion
Location
Adopted 2016 Transit Improvement Plan
131 of 140
System Expansion – Sounder Commuter Rail Projects
Driver
D St-M St Track & Signal
Location
Lakewood Station Improvements
Location
M St.-Lakewood Track & Signal
Location
Mukilteo Station, South Platform
Location
Passenger Information System/CCTV
Location
Point Defiance Bypass
Location
Puyallup Station Improvements
Location
Sounder South Expanded Service
ST2 Adopted Financial Plan
Sounder ST2 Fleet Expansion
ST2 Adopted Financial Plan
Sounder Yard & Shops Facility
ST2 Adopted Financial Plan
Sounder Yard Expansion
Track Miles
Sumner Station Improvements
Location
Tacoma Trestle Track & Signal
Location
Tukwila Station
Location
System Expansion – ST Express Projects
Driver
85th Corridor, Kirkland
Location
Bothell Transit Related Improvements
Location
Federal Way Transit Center
Location
I-90 Two-Way Transit & HOV Operations, Stage 3
Location
Kirkland Transit
Center/3rd
Location
ST Express Bus Base
ST2 Adopted Financial Plan
ST Express Mid-Day Bus Storage
Location
System Expansion – Other
Driver
Central & East HCT Study
Financial Policies
Fare Administration
Financial Policies
Fare Collection
Location
HCT Corridor Planning Studies
Financial Policies
Research and Technology
Financial Policies
South Corridor Alternatives Planning
Location
ST3 Planning
Financial Policies
STart
Location
Enhancement Projects
Driver
Bike Locker Program
Location
Bus Maintenance Facility
Platform Hours
132 of 140
Adopted 2016 Transit Improvement Plan
Enhancement Projects
Driver
Central Link Card Readers
Boardings/Track Miles
Central Link HVAC – Instrument House & UPS Room
Boardings/Track Miles
Central Link HVAC for Traction Power
Boardings/Track Miles
Central Link Overhead Catenary System Tie Switch
Boardings/Track Miles
Downtown Seattle Transit Tunnel Mitigation
Location
Kent Station Parking Lot Paving
Location
Kent Station Platform Lighting
Location
Link CCTV System Upgrade
Boardings/Track Miles
LRV On Board Energy Storage
Location
Noise Abatement
Location
Non Revenue Support Vehicles
Boarding/ Track Miles
OMF LRV Wash Heater System
Boardings/Track Miles
Operations & Maintenance LRV Vehicle Lift
Boardings/Track Miles
Pierce Transit Radio System Upgrade
Platform Hours
Positive Train Control
Location
Puyallup Station LED Lighting
Location
Regional Parking Pilot Project
Financial Policies
Remote Switch Heaters
Location
Security Enhancements
Location
Signage Improvements
Location
ST Express Mobile Communications
Platform Hours
Sumner Station LED Lighting
Location
Tacoma Link Fare Collection
Location
TOD Planning
Location
TOD Property Disposition
Location
Union Station Remodel – Renovation of Garden Level Remodel
Location
Rehabilitation & Replacement Projects
Driver
Beacon Avenue Paving
Location
Federal Way: Post Tension Cable Repair
Location
IT Link Light Rail
Financial Policies
IT Transit Systems
Financial Policies
Link Station Braided Tile Replacement
Location
LRV Overhaul
Track Miles/Boardings
Small Works Program
Location
Sounder Vehicle Overhaul Program
Vehicle Miles
ST Express Fleet Replacement
Platform Hours
Adopted 2016 Transit Improvement Plan
133 of 140
Station Midlife Refurbishment Program
Location
Tacoma Dome Station
Location
Tacoma Link LRV Overhaul
Location
Tacoma Link LRV Communications Upgrade
Location
Administrative Projects
Driver
Administrative Capital
Financial Policies
Environmental Mitigation, Monitoring and Maintenance
Modal Operating Expense Rules
Information Technology Program
Financial Policies
Surplus Property Disposition
Location
Systemwide Uses
Description
Driver
Agency Administration
Financial Policies
Debt Service
Description
Driver
Debt Service
Financial Plan
134 of 140
Adopted 2016 Transit Improvement Plan
Appendix E – Reconciliation of the Proposed
2016 TIP to Adopted 2016 TIP
There are three circumstances when the project lifetime
budget would change from the Proposed TIP to the
Adopted TIP:
The TIP contains Board-approved lifetime budget for active
projects by phase and year of expenditure forecast. The
Proposed TIP, and any amendments to it before the Board
adopts the Budget and TIP, is approved by the annual
budget resolution. Additional changes to the Proposed TIP
arise from budget amendments approved as separate
Board actions, in the time between publication of the
Proposed and Adopted TIP, or from non-material error
corrections. The 2016 TIP was adopted by Resolution No.
R2015-36 on December 17, 2015. The TIP also includes
summary level six year forecasts for Transit Mode
expenses contained in the 2016 Service Implementation
Plan (SIP).
1.
1.
Amendments adopted by the annual budget
resolution.
2.
Amendments adopted between publication of the
proposed and adopted TIP.
3.
Non-material error corrections.
Amendments adopted by the annual budget resolution
Board committees reviewed and recommended for approval to the Board, amendments to project lifetime budgets published
in the proposed TIP. These amendments were adopted by the annual budget resolution (Resolution No. R2015-36,
Attachment C) and are shown below.
Project
Lifetime Budget
as reported in
Proposed TIP
($000)
Revised
Lifetime
Budget
($000)
Change to Project
Budget ($000)
Comments
SYSTEM EXPANSION - LINK
0
2,000
2,000
New Project: Engineering and streetscape design for transit
access improvements and station area enhancements
around the Tacoma Link Expansion project. ST is grant
recipient and administrator.
0
26,185
26,185
Budget to fund expansion of ST Express bus fleet by 27
buses to support added peak service hours.
4X446 - S CORRIDOR ALTERNATIVES PLAN
3,038
2,188
(850)
Projected to close in 2015 with project savings.
809100 - ST3 PLANNING
51,851
52,648
797
Transfer project savings from corridor projects to ST3
Planning.
809103 - CENTRAL & EAST HCT STUDY
2,099
2,152
53
Increase lifetime budget to fund additional 2016 project
deliverables.
0
731
731
New Project: The project provides necessary maintenance to
the Tacoma Link LRV fleet to extend the useful life of the
vehicles and maintain them in a good state of repair.
1,334
2,334
1,000
13,334
13,484
150
400034 - ENHANCEMENTS TO TLE
SYSTEM EXPANSION - REGIONAL EXPRESS
700720 - ST EXPRESS FLEET EXPANSION
SYSTEM EXPANSION - OTHER
REHABILITATION & REPLACEMENT
700718 - TACOMA LINK LRV OVERHAUL
ENHANCEMENT
700723 - DSTT MITIGATION
Project Budget Amendment: Amendment would fund
additional planning work related to surface street
improvements.
ADMINISTRATIVE
802000 - ADMINISTRATIVE CAPITAL
Procurement of furniture for space to be used by final design
consultants for Lynnwood Link Extension, Link OMSF and
Tacoma Link Expansion projects.
Note: There may be insignificant variances due to rounding.
Adopted 2016 Transit Improvement Plan
135 of 140
2.
Amendments adopted between the publication of the proposed and adopted TIP
Other budget amendments adopted by the Board subsequent to publication of the Proposed 2016 TIP and prior to
publication of the Adopted 2016 TIP are shown below:
Project
Lifetime Budget
Revised
Change to Project
as reported in
Lifetime
Budget ($000)
Proposed TIP
Budget ($000)
($000)
Comments
SYSTEM EXPANSION - LINK
400008 - TACOMA LINK EXPANSION
7,786
33,002
25,216
Project commenced final design per Resolution R2015-33 in
December 2015.
400009 - LINK O&M SATELLITE FACILITY
36,828
133,628
96,800
Project commenced final design per Resolution R2015-34 in
December 2015.
400032 - ST2 LRV FLEET EXPANSION
0
733,006
733,006
New Project: This project was established in September
2015 by Resolution R2015-24 to purchase Light Rail
Vehicles (LRVs) for Northgate Link Extension, East Link
Extension and Lynnwood Link Extension.
461600 - DOWNTOWN REDMOND LINK
EXTENSION
0
28,617
28,617
Project was established per Resolution 2016-05 in February
2016.
4X100 - NORTHGATE LINK EXTENSION
2,131,400
1,899,756
(231,645)
The lifetime budget was amended in September 2015 and
October 2015 by Resolutions: R2015-23 to transfer budget
for Vehicles to the new ST2 LRV Fleet Expansion project;
and R2015-25 to increase the baseline budget for changes
to the U District Station to accommodate transit-oriented
development.
4X115 - LYNNWOOD LINK EXTENSION
64,119
487,861
423,742
Project commenced final design per Resolution R2015-30 in
December 2015.
4X445 - FEDERAL WAY LINK EXTENSION
42,877
48,790
5,913
Expands the scope of the project to include PE from the
Kent/Des Moines Station to the Federal Way Transit Center
per Resolution R2016-04 in February 2016.
Note: There may be insignificant variances due to rounding.
3.
Non-material error corrections.
Resolution No. R2015-36, section 5, authorizes the CEO to correct the budget for “non-material errors” to be consistent with
Board actions.
There were no corrections for 2016.
136 of 140
Adopted 2016 Transit Improvement Plan
Appendix F – Glossary
A-87 – A federal government Office of Management and
Budget circular that establishes principles and standards for
determining costs for Federal awards carried out through
grants, cost reimbursement contracts, and other
agreements with State and local governments. The A-87
Revised (effective June 9, 2004) rescinds and supersedes
Circular A-87 (issued May 4, 1995).
ADA (Americans with Disabilities Act) – Federal law
passed in 1990 that prohibits discrimination in services,
facilities, and employment against individuals with
disabilities.
Adopted Budget – The Board-approved budget and capital
plan for Sound Transit for the current fiscal year.
Average Weekday Boardings – Number of one-way
passenger movements (trips) between two points on a
single vehicle on all routes on an average weekday.
Baseline – A plan, design, specification, contract, or other
approved document or configurations against which actual
performance is measured. Baseline can also refer to a
schedule or budget used for management control and
reporting purposes.
BNSF – Burlington Northern Santa Fe Railway - The railroad
company that contractually operates Sounder, Sound
Transit’s commuter rail service.
Board – The Sound Transit Board of Directors, made up of
18 members: 17 elected officials from local jurisdictions
within the Sound Transit district and the Secretary of the
Washington State Department of Transportation.
CEO – Chief Executive Officer of Sound Transit who reports
directly to the Board of Directors.
COLA (Cost-of-Living Adjustment) – Refers to the annual
percentage increase applied to an employee’s salary for
inflationary factors.
Commuter Rail – Railway for urban passenger train service
consisting of local short distance travel operating between a
central city and adjacent suburbs.
Complaints per 100,000 Boardings – The performance
metric (calculated for each mode) that measures the number
of service complaints per 100,000 passenger boardings.
Calculation = ((Service Complaints Received/ Modal
Passenger Boardings) * 100,000)
Contingency – A budgetary reserve put aside for
emergencies or unforeseen expenses.
COP (Citizen Oversight Panel) – An independent panel of
15 volunteers appointed by the Board of Directors
representing each of Sound Transit’s five subareas. Its
mission is to monitor the agency’s commitment to the public,
reviewing projects, budgets, and performance, and reporting
its findings and recommendations for improvement to the
Board.
Cost per Boarding – Calculated for each mode, this metric
represents the fully allocated cost of providing service to a
passenger.
Calculation = (Modal Operating Expenses/Modal Passenger
Boardings)
Boarding – The number of one-way passenger trips
between two points on a single vehicle. Also synonymous
with unlinked passenger trip, rider, or passenger.
Cost per Platform Hour – Calculated for each mode, this
metric measures the fully allocated cost of providing one
hour of service, inclusive of revenue and non-revenue time.
Capital Asset – Individual assets costing $5,000 or more
and having useful lives greater than one year. Also,
significant alterations, renovations, or structural changes
that increase the usefulness of a Sound Transit owned
asset, enhance its efficiency, or prolong its useful life by
more than one year.
Calculation = (Modal Operating Expenses/Modal Platform
Hours)
Capital Outlay – An expense that results in the acquisition
of or addition to fixed assets.
Capital Projects – Projects that purchase or construct
capital assets.
Catenary – Suspended overhead wire that carries high
voltage for electrically-powered transit vehicles (such as
light rail) from a central power source.
CCTV (Closed Circuit Television) – Cameras installed
aboard transit vehicles and at passenger stations for
security purposes.
CEA – Communications & External Affairs department.
Adopted 2016 Transit Improvement Plan
Cost per Revenue Vehicle Hour – Calculated for each
mode, this metric represents the fully allocated cost of
providing one revenue vehicle hour of service.
Calculation = (Modal Operating Expense/Modal Revenue
Vehicle Hours)
CPI (Cost Performance Index) – A measure of the value of
the work completed compared to the actual cost or progress
made on the project.
Deadhead – The amount of non-revenue service time or
miles when a bus or train is not carrying revenue
passengers, usually a trip from, to, or between lines, yards,
or garages.
Debt Service – The payment of interest and the repayment
of principal on long-term borrowed funds according to a
predetermined schedule.
137 of 140
DECM – Design, Engineering & Construction Management
department
DB (Design-build) – A procurement method used to
minimize design and construction risks while reducing the
project delivery schedule by overlapping the design phase
and construction phase of a project. Using DB, the owner
contracts with a single entity for all engineering, design, and
construction services for a transit facility/system.
Department – Highest organizational unit of Sound Transit,
consisting of Communications & External Affairs; Design,
Engineering & Construction Management; Executive;
Finance & Information Technology; Legal; Operations; and
Planning, Environment & Project Development.
Depreciation – A method by which the costs of property and
equipment are systematically and rationally allocated over
their useful life.
Division – Organizational sub-unit within departments.
DSTT – Downtown Seattle Transit Tunnel
EIS (Environmental Impact Statement) – A study of the
impacts of a major project on the environment and
surrounding areas, required for any capital construction
project for which federal funds are used.
Expense – A decrease in net current assets. Expenses
include salaries and benefits, administrative expenses, debt
service, and those current operating costs that require the
use of current assets.
Farebox Recovery – Calculated for each mode collecting
fares, this metric represents the percentage of operating
cost of each mode that is paid by transit riders.
Calculation = (Modal Operating Expenses/Modal Passenger
Fare Revenue)
FCC – Federal Communications Commission
Fiscal Year – A 12-month period to which the annual
operating budget applies and at the end of which a
government determines its financial position and results of
its operations. Sound Transit’s fiscal year is concurrent with
the calendar year.
FIT – Finance & Information Technology department
FTA (Federal Transit Administration) – The federal
agency responsible for the administration of federal transit
programs, including the allocation of grant funds. FTA is a
part of the U.S. Department of Transportation.
FTE (Full Time Equivalent) – The fractional equivalent of
one full-time employee working a 40-hour work week for one
calendar year.
FY – Fiscal Year
138 of 140
GCCM (General Contractor/Construction Manager) – A
procurement method used to reduce construction risk. Using
GCCM, the owner has access to construction expertise and
experience prior to completion of design. Services offered
by a GCCM contractor include assistance with decisionmaking, constructability reviews, value engineering, budget
control, cost estimating, and schedule control.
GFOA (Government Finance Officers Association) – An
organization whose purpose is to enhance and promote the
professional management of governments for the public’s
benefit by identifying and developing financial policies and
practices and promoting them through education, training,
and leadership.
GIS – Geographic Information Services
HCT (High Capacity Transit) – Public transportation within
an urbanized region operating principally on exclusive rights
of way, including interim express services and high
occupancy vehicle lanes, which taken as a whole, provides
a substantially higher level of passenger capacity, speed,
and service frequency than traditional public transportation
systems operating principally in general purpose roadways.
HOV (High-Occupancy Vehicle) – A vehicle containing two
or more passengers. Occupancy designations are used on
designated auto traffic lanes to encourage car-pooling, ride
sharing, or the use of public transportation.
IT – Information Technology
KCM (King County Metro) – The public transit division of
King County Department of Transportation, responsible for
providing bus, trolley bus, light rail, water taxi, paratransit,
and vanpool services in a service area of about 2,000 square
miles. Sound Transit contracts a portion of its express bus
service as well as all of its light rail service with KCM.
Light Rail – Service using trains powered with overhead
catenary power, operating on tracks embedded in city
streets or along a separate right-of-way. Passengers are
picked up and discharged at fixed locations (stations)
located along the tracks.
LRV (Light Rail Vehicle) – A vehicle with overhead
catenary power operating on tracks. It may be connected to
other vehicles and operated as a train.
MMIS (Maintenance Management Information System) –
The Maintenance Management Information System is an
online system that helps gather and analyze data about an
organization’s maintenance operations with the intention of
helping management make informed decisions and staff do
their jobs more effectively.
Mode – A system for carrying transit passengers described
by specific right-of-way, technology, and operational
features. Sound Transit modes are light rail, commuter rail,
and regional express bus.
Adopted 2016 Transit Improvement Plan
MVET (Motor Vehicle Excise Tax) – Also called the “car
tab” tax; this is a tax on vehicles based on the depreciated
value of the vehicle using the Manufacturer's Suggested
Retail Price (MSRP) as the initial vehicle value. The tax on
commercial trucks and trailers is based on the depreciated
value using the latest purchase price and year as the initial
vehicle value. Sound Transit currently assesses a 0.3
percent MVET within its taxing district.
NRV (Non-Revenue Vehicles) – Agency fleet consisting of
cars, trucks, vans, SUVs, specialty vehicles, and equipment
used for administrative purposes.
O&M – Operations and Maintenance
OMF – Operations Maintenance Facility
On-Time Performance – A performance ratio that
measures how often a transit service is on time (i.e., at a
designated pick-up spot within a predetermined timeframe).
The timeframe differs based on mode and frequency of
service.
Calculation = ((# Scheduled Trips – # Trips Early or
Late)/Total # of Scheduled Trips)
ORCA (One Regional Card for All) – A stored-value smart
card used for payment of public transit fares in the Central
Puget Sound region.
Paratransit – The comparable transportation service
required by the ADA for individuals with disabilities who are
unable to use fixed-route (bus and rail) service. The vehicles
used do not operate over a fixed route or on a fixed
schedule.
PE/ED – Preliminary Engineering and Environmental
Documentation
PEPD – Planning, Environment & Project Development
department
Percentage of Scheduled Trips Operated – A
performance ratio that measures the number of times a
Sound Transit vehicle or mode of service completes its
scheduled route/trip
Phase Gate – Phase Gate is a project management process
designed around a series of eight defined gates. Gates
represent key transition and/or decision points in a project’s
progression through planning and environmental review,
design, construction, and transition to operations.
PLA (Project Labor Agreement) – PLAs are collective
bargaining agreements between building trade unions and
contractors. They govern terms and conditions of
employment for all craft workers – union and nonunion – on
a construction project.
Adopted 2016 Transit Improvement Plan
Platform Hours (also called Service Hours) – For any
mode, the total time the operator operates the vehicle,
including revenue service (scheduled route, special event,
and layover time) and non-revenue service (pullout and pullin times from first/last stop to garage).
Platform Miles (also called Service Miles) – For any
mode, the total miles traveled by a vehicle from pullout of
garage/yard to return to garage/yard at end of revenue
service, including any layover time and time when not
carrying passengers.
Preventable Accidents per 100,000 Revenue Miles – For
any mode, the number of preventable accidents reported per
100,000 miles of actual revenue vehicle mileage. A
preventable accident is one in which the driver failed to do
everything that reasonably could have been done to avoid
the crash.
Calculation = (Preventable Accidents / Actual Revenue
Mileage) * 100,000
Proposed Budget – The recommended and unapproved
Sound Transit budget submitted by the CEO to the Board.
Purchased Transportation – Transportation service
provided to a public transit agency from a public or private
transportation provider, based on a written contract.
Revenue Vehicle Hours – The number of hours that a
vehicle is in revenue service and there is a reasonable
expectation of carrying passengers (includes layover time,
but not deadhead).
Revenue Vehicle Miles – The number of miles that a
vehicle is in revenue service and there is a reasonable
expectation of carrying passengers (includes layover time,
but not deadhead).
Revenues – Increases in proprietary fund type net total
assets from other than expense refunds and capital
contributions.
ROW (Right-of-Way) – A right-of-way is a right to make a
way over a piece of land, usually to and from another piece
of land. A right of way is a type of easement granted or
reserved over the land for transportation purposes. Also
used to describe the land on which a railroad line, road, or
utility is built.
Sales Tax – A 0.9 percent tax levied on sales of eligible
items within the boundaries of the Sound Transit District and
collected by the State for the benefit of Sound Transit.
SCADA (Supervisory Control and Data Acquisition) – A
centralized system to control signals, systems, and
substations on Sound Transit’s light rail system. The system
also provides real-time location data to a control center.
139 of 140
Service Hours (also called Platform Hours) – For any
mode, the total time the operator operates the vehicle,
including revenue service (scheduled route, special event,
and layover time) and non-revenue service (pullout and pullin times from first/last stop to garage).
Service Miles (also called Platform Miles) – For any
mode, the total miles traveled by a vehicle from pullout of
garage/yard to return to garage/yard at end of revenue
service, including any layover time and time when not
carrying passengers.
SIP (Service Implementation Plan) – This document is
produced annually by the Service Planning division and
approved by the Board. It details the development of each
mode of service, describes any service changes planned for
the year, and contains preliminary service proposals and
financial projections for the following five years.
Smart Card – A small card, usually plastic, with an
imbedded computer chip good for one or more trips that is
usually altered by a fare collection machine removing some
or all of the stored value as each trip is taken.
SODO – The general area south of downtown Seattle; also,
the name of one of Sound Transit’s light rail stations located
in that neighborhood.
Sound Move – Voter-approved plan (1996) to build a highcapacity public transit system.
Sound Transit – The Central Puget Sound Regional Transit
Authority
SPI (Schedule Performance Index) – A measure of
schedule efficiency on a project. It is the ratio of earned
value (EV) to planned value (PV).
SR – State Route
ST2 (Sound Transit 2) – Voter-approved (2008) second
phase of Sound Transit’s plan for mass transit expansion.
ST3 (Sound Transit 3) – The third phase of Sound Transit’s
plan for mass transit expansion.
STart (Sound Transit Art Program) – Program whose
purpose is to incorporate public art into Sound Transit
systems and facilities that will reflect the communities
served and enhance the customer experience.
STU (Sound Transit University Program) – Refers to a
range of training courses, both on-site and off-site, offered
for Sound Transit employees to improve professional and
technical skills.
TCO (Total Cost of Ownership) – A financial estimate
intended to help buyers and owners determine the direct and
indirect costs of a product or system.
TGT (Technology Governance Team) – Team of Sound
Transit employees who provide leadership and direction for
the Information Technology (IT) division to ensure reliable,
consistent, cost-effective, and accountable services.
TIFIA (Transportation Infrastructure Financing and
Innovation Act) – A direct loan, loan guarantee, and
standby line of credit program allowing the USDOT to
provide credit assistance of up to 33 percent of the
construction costs of a regionally or nationally significant
surface transportation project. Loans are made at U.S.
Treasury rates and may be repaid over as long as 35 years
after substantial completion of the project.
TIP (Transit Improvement Plan) – This document provides
projected capital and operating expenditures for the
construction and operation of the Sound Transit regional
transit system in the central Puget Sound. The TIP contains
information on scope and budget as well as changes in
budget and schedule for all active phases of both capital and
operating programs.
TOD (Transit-Oriented Development) – The development
of residential, commercial, and retail uses within walking
distance of a transit station or stop.
TPSS (Traction Power Sub Station) – A wayside unit that
converts electric power from the form provided by the public
utility to an appropriate voltage, current type, and frequency
to supply traction power to the motor of the light rail vehicle
through the overhead catenary.
TVM (Ticket Vending Machine) – Automated equipment
located at customer facilities that enable the purchase of fare
media for access to the Sound Transit transportation
system.
UPS – Uninterrupted Power Supply
UW – University of Washington
Variance – The difference between planned costs and
actual costs.
WSDOT – Washington State Department of Transportation
YOE (Year of Expenditure) – refers to the representation of
a project’s cost inclusive of an annual inflationary factor
calculation.
Subarea – Five subareas of the Sound Transit District
defined for planning and budgeting purposes consisting of
Snohomish County, North King County, East King County,
South King County, and Pierce County.
System Plan – (see Sound Move).
140 of 140