17872-DipPM-ScopeUnitGuide

Manage Project Scope
Unit Guide
Diploma of Project Management 17872
Qualification Code BSB51507
Unit Code BSBPMG502A
BSBPMG501A Manage Application of Project Integrative Processes
Units of Study – Diploma
Units in the Diploma of Project Management
BSBPMG501A
Manage Application of Project Integrative Processes
BSBPMG502A
Manage Project Scope
BSBPMG503A
Manage Project Time
BSBPMG504A
Manage Project Costs
BSBPMG505A
Manage Project Quality
BSBPMG506A
Manage Project Human Resources
BSBPMG507A
Manage Project Communication
BSBPMG508A
Manage Project Risk
BSBPMG509A
Manage Project Procurement
BSBPMG501A Manage Application of Project Integrative Processes
Manage Project Scope
On completion of this unit you will –
• be able to determine and control the end products of the
project, and the processes to develop them
• be able to consult with stakeholders and apply tools and
techniques to manage development of the project scope
activities, including project objectives, deliverables,
constraints and assumptions
• This unit is Ungraded which means that you will be found
Competent or Not Yet Competent based on the
completion of the assessment activities and the evidence
of competency provided.
BSBPMG501A Manage Application of Project Integrative Processes
Elements of Competency
•
Each unit of study is composed of elements of
competency
•
Manage Project Scope comprises 3 elements of
competency –
1. Conduct project authorisation activities
2. Conduct project scope definition activities
3. Manage application of scope controls
•
Elements of competency are further broken down into
performance criteria, these can be found on the next
slides
BSBPMG501A Manage Application of Project Integrative Processes
1. Conduct Project Authorisation Activities
1. Project authorisation is confirmed with a higher authority
as the basis for future project management activity and
commitment of resources and effort
• This includes assigning responsibilities for Change
Control and decision making with respect to material
changes to Time, Cost and Scope.
• This is commonly performed in conjunction with Project
Integration Management
• The Project Charter is the initial document which
authorises the start of a project, this is performed as
part of Project Integration Management
BSBPMG501A Manage Application of Project Integrative Processes
2. Conduct Project Scope Definition Activities
1. Project objectives, deliverables, constraints and
assumptions and principal work activities are identified
with guidance of a higher project authority and agreed
between the project team and the client
2. Designated measurable project benefits and outcomes
are established to enable quantified evaluation of
project performance
3. Scope management plan is developed and
implemented
BSBPMG501A Manage Application of Project Integrative Processes
3. Manage Application of Scope Controls
1. Agreed scope management procedures and processes
are implemented
2. The impact of scope changes is managed within
established time, cost and quality constraints according
to change control procedures and to meet project
objectives
3. Progress is reviewed and results recorded to assess the
effectiveness of scope management procedures
BSBPMG501A Manage Application of Project Integrative Processes
Associated Readings
• Mandatory –
• PMBOK Chapter 5
• Recommended –
• Diploma of Project Management Skills Kit –
Manage Project Scope
BSBPMG501A Manage Application of Project Integrative Processes
Team Assignment Criteria
Team Assignment
Components
Marks
Basic Competency
Higher Competency
Project Scope Definition
5

Briefly states what is included of the
scope of the project

States what is IN scope and what is OUT of
scope
Project Objectives and Requirements
5


Objectives stated
High level requirements documented

Objectives stated in measurable terms
using SMART
Project Success Criteria
5

Success criteria stated in terms of scope,
time, cost and quality


Constraints, Assumptions and
Dependencies
5


Project Approach and High Level
Deliverables
5



Project constraints are listed in terms of
timeframe and budget
Assumptions are listed
Dependencies are identified if they exist
Work Breakdown Structure documented
Additional success criteria stated
Success criteria stated in measurable terms
using SMART
Outstanding issues are listed for resolution
by the Project Sponsor
Impacts of invalid assumptions is analysed
Scope Management Process
(Change Control)
5

Basic scope management process
documented
Basic Change Control form provided

Total

30
19.5 to 25
BSBPMG501A Manage Application of Project Integrative Processes



Work Breakdown Structure documented in
terms specific deliverables and the activities
required to develop these
Sophisticated scope management process
documented
Sophisticated Change Control form
provided
25.5 to 30
Individual Assignment Criteria
Individual Assignment
Components
Marks
Basic Competency
Higher Competency
Project Scope Definition
5

Scope definition document as basis of initial
project approval - may be a Statement of
Work, Project Brief, Project Charter or similar

States what is IN scope and what is OUT of
scope
Project Objectives and Requirements
5


Objectives stated
High level requirements documented

Objectives stated in measurable terms using
SMART
Project Success Criteria
5

Success criteria stated in terms of scope, time,
cost and quality


Constraints, Assumptions and Dependencies
5




Project constraints are listed in terms of
timeframe and budget
Assumptions are listed
Dependencies are identified if they exist
Additional success criteria stated
Success criteria stated in measurable terms using
SMART
Outstanding issues are listed for resolution by the
Project Sponsor
Impacts of invalid assumptions is analysed

Project Approach and High Level
Deliverables
5

Work Breakdown Structure documented

Work Breakdown Structure documented in terms
specific deliverables and the activities required to
develop these
Scope Management Process
(Change Control)
8

Basic scope management process
documented
Basic Change Control form provided

Sophisticated scope management process
documented
Sophisticated Change Control form provided
Requirements Traceability Matrix documented
Change Requests
10
Multiple change request forms including
analysis of the impacts on the overall project
objectives
Evidence of approval or rejection of the
change requests
Multiple project status reports tracking of
project objectives of time, cost and scope




Project Performance Reports
Total
7
50

32.5 to 42
BSBPMG501A Manage Application of Project Integrative Processes




Evidence of implementation of approved change
requests
Change Request Log
Multiple project status reports showing changes
to time and cost due to approved changes
42.5 to 50
Best wishes for your studies
Northern Beaches TAFE and the
Business and Commerce Business Line of the
Northern Sydney Institute
wish you success in your studies!