Barrier to entry for legacy DR Eddie Webster Demand Response Lead Great River Energy GRE’s DR dispatch Barrier in MISO tariff • Energy and Operating Reserve Markets BPM – 2.2.5 – Commercial pricing nodes Barrier in MISO tariff cont. • Demand Response BPM – 4.1 Demand response resource characteristics • To comply with MISO settlements process the individual EP nodes comprising a DRR must be located in the same Local Balancing Authority (“LBA”). • LMR and EDR registrations are tied to a CP node. – No verbiage in any BPMs. Details CURRENT • ~20,000MWh of unregistered MW dispatched every year • Load drop is known and predictable by CP node • Load reduction is currently occurring outside of the market • When GRE’s DR clears for a single node the impact to other nodes is known. Proposed • GRE registers as either LMR or DRR type I • Best case is resource looks like a hub. – HUB’s can cross LBA’s. • Alternative – 6 LMR or DRR registrations. – Offers are contingent • If one clears the other offers will change to must run.