A & D High Tech Case PROJECT COMPLETION TIMELINE TEAM 3 A & D High Tech Project Plan • Project Go-Live Date • 11/15/2002 [Assuming Project start date of 06/03/2002] • Project Completion Date • 11/29/2002 • Total Cost • Labor Cost = $834,030.00 • Capital Cost = $98,500.00 • Total Cost = $932,530.00 A & D High Tech Project Plan • Critical Path A & D High Tech Case Plan • Potential of the project to be completed on time - Feasible – The online store project is feasible and could go live before the holiday season – Extensive testing phase should highlight potential problems – Strong Project Management & history of timely delivery project – Simple and clearly defined project scope – Detailed Project Plan – Strong Support from Upper Management A & D High Tech Case Plan • Risks & Mitigations – Scope Creep - Incorporate Checkpoints & Milestone, Functionality Vs Aesthetics, No changes after Functional Requirements – Human Resources - Hire only experienced resources with both prior Domain and Technical experience – Resource Back Up - Take services of another Consulting Firm – Mythical Man Month - Resource Leveling and Loading • Room for Accommodating Scope Changes – Minor alterations to existing requirements are feasible but no big changes can be accommodated e.g. adding/changing few fields vs adding a new page. QUESTIONS??????
© Copyright 2026 Paperzz