The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report This report has been prepared by Arup Energy solely for use by the Carbon Trust by whom it was commissioned. It is not addressed to and may not be relied upon by any person or entity other than the Carbon Trust without the prior written permission of both the Carbon Trust and Arup Energy. In producing this report, Arup Energy has relied upon information provided by third parties. Neither the Carbon Trust nor Arup Energy nor their respective directors, employees or affiliated companies give any representation or warranty, express or implied, as to the accuracy, completeness or fairness of the contents of the report, nor accept any responsibility or liability for any loss, whether direct, indirect or consequential, arising from reliance on it. Any use of this report by any third party for whatever purpose is solely the responsibility of that party who should use such due diligence to verify the report's contents and consult its own advisers as may be appropriate. The Carbon Trust does not give investment advice and nothing in this report constitutes, or should be taken as, a recommendation to enter into, or the giving of any advice in relation to, any investment. This report may be copied and distributed only with the consent of the Carbon Trust. The Carbon Trust 2005 Contents Executive Summary ............................................................................................................................................. 1 1 2 Scope of Work & Report Structure......................................................................................................... 7 1.1 Background to the OWC Evaluation ..................................................................................... 7 1.2 First Stage Evaluation........................................................................................................... 7 1.2.1 State-of-the-art Review ......................................................................................................... 7 1.2.2 Market Assessment .............................................................................................................. 8 1.2.3 Report Structure ................................................................................................................... 8 1.3 Second Stage Evaluation...................................................................................................... 8 1.3.1 Scope for improvement......................................................................................................... 8 1.3.2 Future Visions....................................................................................................................... 9 1.3.3 Shoreline against near-shore device installation................................................................... 9 1.3.4 Sensitivities and prioritisation................................................................................................ 9 1.3.5 Report Structure ................................................................................................................... 9 1.4 Third Stage Evaluation.......................................................................................................... 9 1.4.1 Recommendations for development work............................................................................. 9 1.4.2 Report Structure ................................................................................................................... 9 1.5 Developer input and peer review ........................................................................................ 10 Glossary of Terms ............................................................................................................................... 11 2.1 Oscillating Water Column Terminology............................................................................... 11 2.2 Terminology ........................................................................................................................ 11 State-of-the-art Review & Market Assessment .................................................................................................. 13 3 Existing Shoreline OWCs .................................................................................................................... 14 3.1 LIMPET 500 [3,5,6,27,56] ................................................................................................... 14 3.1.1 Concept .............................................................................................................................. 14 3.1.2 Geometry ............................................................................................................................ 14 3.1.3 Design Parameters (Assumptions and working principles) ................................................ 15 3.1.4 Project Experience.............................................................................................................. 15 3.2 Pico [4,26,45,46,67,68] ....................................................................................................... 18 3.2.1 Concept .............................................................................................................................. 18 3.2.2 Geometry ............................................................................................................................ 18 3.2.3 Design Parameters (Assumptions and working principles) ................................................. 19 3.2.4 Project Experience.............................................................................................................. 19 3.3 OSPREY [10]...................................................................................................................... 22 3.3.1 Concept .............................................................................................................................. 22 4 3.3.2 Geometry (OSPREY 1)....................................................................................................... 22 3.3.3 Design Parameters (Assumptions and working principles) ................................................. 24 3.3.4 Project Experience & Reported Conclusions ...................................................................... 24 3.3.5 Performance ....................................................................................................................... 25 3.4 Port Kembla, NSW, Australia [47,70,71] ............................................................................. 26 3.4.1 Concept .............................................................................................................................. 26 3.4.2 Geometry ............................................................................................................................ 26 3.4.3 Design Parameters (Assumptions and working principles) ................................................. 26 3.4.4 Project Experience.............................................................................................................. 27 3.4.5 Performance ....................................................................................................................... 28 3.5 Vizhinjam OWC, Trivandrum, India [11,48]......................................................................... 29 3.5.1 Concept .............................................................................................................................. 29 3.5.2 Geometry ............................................................................................................................ 30 3.5.3 Design Parameters (Assumptions and working principles) ................................................. 31 3.5.4 Costs................................................................................................................................... 32 3.5.5 Performance ....................................................................................................................... 32 3.6 Sakata, Japan..................................................................................................................... 34 3.6.1 Concept .............................................................................................................................. 34 3.6.2 Geometry ............................................................................................................................ 34 3.6.3 Design Parameters (Assumptions and working principles) ................................................. 36 3.6.4 Performance ....................................................................................................................... 36 3.7 Other OWC installations ..................................................................................................... 36 3.8 Recent Developments......................................................................................................... 37 3.9 Risk Matrix .......................................................................................................................... 38 3.10 Key Performance Indicators................................................................................................ 41 3.10.1 Structural Quantities v Output............................................................................................. 41 3.10.2 Wave Energy at Collector v Output..................................................................................... 41 Summary of OWC technology (State-of-the-Art) ................................................................................. 42 4.1 Resource Assessment [2,51] .............................................................................................. 42 4.2 Modelling and Performance Prediction [9,13,29,30,32,33,34,40,41] .................................. 42 4.3 Structural Form ................................................................................................................... 43 4.4 Turbine Design and Optimisation [77,78,79,82,84,85,87 & as shown below] ..................... 44 4.4.1 Summary of the Current State-of-the-Art ............................................................................ 44 4.5 Controls [83, 86] ................................................................................................................. 45 4.5.1 Treating the water Column itself as a tuned oscillator ........................................................ 45 4.5.2 Modifying the Characteristics of the Turbine-Generator...................................................... 45 4.5.3 Machine Technology........................................................................................................... 45 5 6 4.5.4 Control Systems ................................................................................................................. 46 4.6 Power Conversion Efficiency .............................................................................................. 46 4.7 Maintenance and Reliability ................................................................................................ 46 Market Size.......................................................................................................................................... 47 5.1 Assessment Method ........................................................................................................... 47 5.2 UK Wave Energy Resource ................................................................................................ 47 5.2.1 Distribution.......................................................................................................................... 47 5.2.2 Variation / range ................................................................................................................. 48 5.2.3 Ranking method.................................................................................................................. 50 5.3 Sea Bed Profile................................................................................................................... 52 5.3.1 Method of review ................................................................................................................ 52 5.3.2 Ranking............................................................................................................................... 54 5.4 Tidal Range ........................................................................................................................ 56 5.4.1 Ranking............................................................................................................................... 57 5.5 Grid Accessibility ................................................................................................................ 59 5.5.1 Ranking............................................................................................................................... 59 5.5.2 Results................................................................................................................................ 59 5.6 Local Construction Factor ................................................................................................... 62 5.6.1 Shoreline Construction........................................................................................................ 62 5.6.2 Near-shore Construction..................................................................................................... 62 5.7 Relative Economics of Near-shore versus Shoreline Construction..................................... 62 5.8 Ranking Matrix, Combination and Weighting ...................................................................... 63 5.9 Potential Resource ............................................................................................................. 67 5.9.1 Shoreline............................................................................................................................. 67 5.9.2 Near-shore.......................................................................................................................... 68 5.10 Existing Structures .............................................................................................................. 68 5.11 Conclusions ........................................................................................................................ 69 Generic Base Case Elements.............................................................................................................. 71 6.1 Existing device similarities .................................................................................................. 71 6.2 Existing device differences ................................................................................................. 71 6.3 Focus Areas for Stage 2 Evaluation ................................................................................... 72 6.3.1 Generic design.................................................................................................................... 72 6.3.2 Plant optimisation ............................................................................................................... 72 Scope for Improvement & Future Vision ............................................................................................................ 73 7 Choice of device type and structure..................................................................................................... 74 7.1 Shoreline OWC Devices ..................................................................................................... 74 7.1.1 Resource Assessment ........................................................................................................ 74 8 7.1.2 Site specific design and preparation ................................................................................... 75 7.1.3 Construction techniques ..................................................................................................... 76 7.1.4 Weather and programme risk ............................................................................................. 78 7.1.5 Contractual risks ................................................................................................................. 78 7.2 Near-Shore OWC Devices.................................................................................................. 79 7.2.1 Advantages......................................................................................................................... 79 7.2.2 Disadvantages .................................................................................................................... 80 7.3 Breakwater OWC devices................................................................................................... 80 7.4 Conclusions ........................................................................................................................ 81 Scope for Improvement ....................................................................................................................... 82 8.1 Site–specific tailoring of designs......................................................................................... 82 8.1.1 Chamber geometry ............................................................................................................. 82 8.1.2 Chamber lip ........................................................................................................................ 83 8.1.3 Device Capture Width ......................................................................................................... 83 8.1.4 Anti-slosh Devices .............................................................................................................. 84 8.1.5 Air Plenum Configuration .................................................................................................... 84 8.1.6 Collector Width ................................................................................................................... 85 8.1.7 Tidal range.......................................................................................................................... 85 8.2 Turbine choice and specification......................................................................................... 85 8.2.1 Air flow rate matching ......................................................................................................... 85 8.2.2 Blade and vane configuration ............................................................................................. 86 8.2.3 Orientation of axis ............................................................................................................... 87 8.3 Device construction methods.............................................................................................. 87 8.3.1 Balance of Plant Materials .................................................................................................. 87 8.3.2 Mass production / manufacture........................................................................................... 88 8.4 Conversion efficiency.......................................................................................................... 89 8.4.1 Understanding Pneumatic Capture ..................................................................................... 89 8.4.2 Wave to pneumatic efficiency ............................................................................................. 89 8.4.3 Pneumatic to mechanical.................................................................................................... 92 8.4.4 Mechanical to electrical....................................................................................................... 93 8.4.5 Total device efficiency......................................................................................................... 93 8.5 Survivability......................................................................................................................... 95 8.5.1 Wave loading ...................................................................................................................... 95 8.5.2 Return Period...................................................................................................................... 95 8.5.3 Balance of Plant.................................................................................................................. 96 8.6 Reliability, operation and maintenance ............................................................................... 96 8.7 Prediction and modelling..................................................................................................... 97 8.8 9 10 Control of export power....................................................................................................... 97 Future Visions...................................................................................................................................... 99 9.1 Location .............................................................................................................................. 99 9.2 Optimum water depth.......................................................................................................... 99 9.2.1 Energy vs. Water Depth...................................................................................................... 99 9.2.2 Wave Loading versus Water Depth .................................................................................. 100 9.2.3 OWC cost versus water depth .......................................................................................... 101 9.2.4 Sea-bed Conditions .......................................................................................................... 102 9.2.5 Overall Economics of Power Capture against OWC CAPEX............................................ 103 9.3 Structure ........................................................................................................................... 103 9.3.1 Design description ............................................................................................................ 103 9.3.2 Foundation........................................................................................................................ 104 9.3.3 Device concept ................................................................................................................. 105 9.3.4 Scour Protection ............................................................................................................... 105 9.3.5 Construction...................................................................................................................... 105 9.3.6 Installation......................................................................................................................... 110 9.4 Turbine.............................................................................................................................. 110 9.4.1 Turbine sizing ................................................................................................................... 110 9.4.2 Blade profile...................................................................................................................... 111 9.5 Generator.......................................................................................................................... 111 9.5.1 Specification ..................................................................................................................... 111 9.6 Costing.............................................................................................................................. 111 9.6.1 Caisson............................................................................................................................. 111 9.6.2 Turbine.............................................................................................................................. 112 9.6.3 Generator.......................................................................................................................... 112 9.6.4 Grid connection................................................................................................................. 113 9.6.5 Operation and Maintenance.............................................................................................. 119 9.7 Costing Summary ............................................................................................................. 120 9.8 Risk................................................................................................................................... 121 9.8.1 Risk Schedule................................................................................................................... 121 Economics ......................................................................................................................................... 125 10.1 Economic models ............................................................................................................. 125 10.1.1 Common assumptions ...................................................................................................... 125 10.2 Sensitivity assessment...................................................................................................... 127 10.2.1 Upper bound / Lower bound sensitivity assessment ......................................................... 127 10.3 Improvement priorities / targets ........................................................................................ 130 10.3.1 Priorities............................................................................................................................ 130 10.3.2 Targets.............................................................................................................................. 130 10.4 Learning Rates ................................................................................................................. 131 10.4.1 Shoreline Targets ............................................................................................................. 132 10.4.2 Near-shore Targets........................................................................................................... 132 10.4.3 Port Kembla ...................................................................................................................... 133 Research & Development ................................................................................................................................ 134 11 12 Areas for Research and Development............................................................................................... 135 11.1 Wave Climate ................................................................................................................... 135 11.2 Wave Collector/Capture.................................................................................................... 135 11.3 Construction and Installation............................................................................................. 135 11.4 Turbine.............................................................................................................................. 136 11.5 Generator and Power Take Off......................................................................................... 137 11.6 Controls ............................................................................................................................ 137 11.7 Grid Connection................................................................................................................ 137 11.8 Power System Dynamics .................................................................................................. 137 11.9 Business Development and Partnerships ......................................................................... 138 Conclusions ....................................................................................................................................... 139 APPENDICES Appendix A References Appendix B OWC Construction Programmes Appendix C OWC Cost Estimates Appendix D Economic Model Appendix E Discount Rate Sensitivity Appendix F Improvement Variables Discount Rate Sensitivity Appendix G Peer Review Responses Submission Reference 115214-00 Description Final Issue with minor corrections Prepared by Name Ian Webb, Chris Seaman, Gordon Jackson Reviewed by Approved by Adrian Fox Gordon Jackson Initials Date 4 February 2005 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Executive Summary Oscillating Water Column (OWC) wave energy conversion devices comprise a chamber in which air is compressed and rarefied by wave action. The energy transmitted to the air is converted to useful power by passing it through a turbine. Several prototype scale OWCs have been constructed and operated with varying degrees of success over the last 30 years. There are examples of shoreline, near-shore and breakwater devices in a number of countries. The device with the greatest operational history and evaluation work in the public domain is the shoreline LIMPET device on the island of Islay, Western Scotland. This report considers the current state-of-the-art in OWC deployment as a basis for establishing the future potential and economics of this technology. State-of-the-art Review and Market Assessment An assessment of the state-of-the-art in the design, construction and operation of near-shore and shoreline OWC wave energy devices was first conducted. The state-of-the-art review, together with an assessment of the potential range of applicability of OWC technology around the UK coastline, was used to identify the most promising conditions in which to develop OWCs. All presently operational OWCs (December 2004) have been constructed in concrete and have relied on its weight (with ballast when deployed near-shore) to ensure foundation stability. The concrete devices have had fairly regular geometry and have not sought to focus the wave energy. One unsuccessful OWC and a new facility being constructed in Australia have chosen to construct in steel and have aimed to minimise the structure size to both reduce quantities and survival wave loading whilst aiming to capture the maximum possible wave energy through incorporating guides that are wider than the air collector chamber. All the structures have been bespoke designs for particular locations. The selected geometric form of the collector chamber is considered to depend on the wave climate in each location. The greater prevalence of larger breaking or near-breaking waves at the shallow North East Atlantic shoreline sites requires a sloping chamber for greatest efficiency. Deeper water devices in less severe metocean conditions can have near vertical chambers. The construction experience of the shoreline devices has been poor with extended construction schedules and difficulties in providing adequate temporary works to allow safe year-round working. This has not been the case with near-shore and breakwater devices that have largely been constructed off-site. A number of prototype OWCs have had too great an installed power capacity compared to the actual wave resource encountered. In some cases, significant modification has been undertaken, or is planned, to match the power train to the actual resource encountered. In one typical example operational average wave-to-wire efficiencies have been consistently below 10% despite initial estimates of greater than 30% efficiency. These difficulties highlight the need to match the power train and OWC so that these experiences are not replicated on future devices. The UK coastline has been evaluated with respect to wave resource, sea-bed slope, tidal range, water depth and proximity of suitable grid connection points. A matrix method was adopted to rank regions of the coastline. The most promising areas for OWCs are in Northern and Western Scotland, the Outer Hebrides, the Shetland and Orkney Islands and the north coast of SW England. A potential for 141km frontage of near-shore OWCs and 8km of shoreline OWCs was identified although the assessment of the shoreline potential was fairly cursory within the confines of this study. The near-shore OWCs have the potential to supply power to around 1.8m households (7.8TWh/annum). Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 1 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Scope for Improvement & Future Vision The existing operational experience has been critically appraised with a view to identifying the scope for improvement in OWCs. This included an examination of the potential and the constraints in developing a larger market for shoreline devices and a brief review of the alternative shoreline OWC technology of tunnelling. This led to the conclusion that, while significant improvements could be made to shoreline devices, there are substantial barriers to developing a resource that could be considered significant in terms of national power consumption. Shoreline devices are accordingly considered most appropriate for serving smaller isolated communities such as on Islay. Attention was then focused on the improvements that might be made on near-shore devices by incorporating the lessons learnt from previous projects and by assessing, through analysis and related experience, the effectiveness of a range of improvements in design, fabrication and installation of OWCs. Such improvements would reap greater reward in view of the larger near-shore resource that can be realised. The key elements of improved economics are reduced structural quantities and survival loading combined with the maximum possible wave energy capture. Generic Future Vision – a near-shore concrete caisson OWC A generic near-shore OWC was developed to take advantage of the following factors: • A greater available resource, with a more flexible choice of locations. • The ability to use a generic design rather than a site-specific design for each device. • The possibility for mass production • Little or no below-water working is required • The structure is built in a controlled environment and as such is less susceptible to adverse weather conditions and programme delay. • Ability to tune the structure for a particular wave climate by varying the device depth and / or orientation. Concrete was chosen as the material of construction as it appeared marginally more cost-effective than steel for UK application in a brief screening exercise. It should not be concluded from this that steel should be discounted when examining future OWC potential. The OWC would be fabricated offsite, towed and installed offshore. The device was configured for the more prevalent rocky or sandy areas of the western UK where it was sited in a fairly energetic location with an average energy flux of 34kW/m passing the 20m depth contour (a depth being promoted for consistency of reporting between nearshore devices). A water depth of 9m was selected, following an optimisation exercise that indicated that depths of 9 - 11m would yield the most economic fixed structure design in relation to the wave power that could be collected. The OWC was sited where the tidal amplitude was no greater than 2m, as greater tidal amplitudes had been shown to be detrimental to the economics. The generic near-shore OWC was assessed to perform as follows: • 42% of the average wave flux at 20m contour over the maximum width of the OWC was convertible to pneumatic power in the collector (or 59% at the collector) • 65% of the pneumatic power was convertible to mechanical power (average) • 91% of the mechanical power was convertible to electrical power. This gives an overall wave-to-wire efficiency of 24.8% (or 34.8% using energy fluxes at the collector). Developers have agreed that such an efficiency is achievable on prototype devices to be developed in the near term. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 2 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report The suggested geometric form is shown below: Power Production Cost Cost estimates were prepared for a shoreline device, one near-shore unit 82.5m wide, and 10 such units. The expected benefits of applying mass production techniques and the learning curve of repeatability were then applied to the 10 near-shore units to arrive at a capital cost for economic modelling. All modelling was based on UK costs and productivities. Lower construction costs can be obtained in some parts of the European Union (and elsewhere in the world) and should be considered in the future scope for improvement. Device Generic Shoreline 1 x Near-shore 10 x Nearshore 10 x Nearshore (with productivity benefits) Total frontal width (m) 20 82.5 825 825 Rated power (kW) 500 2,250 22,500 22,500 1,480 6,100 61,000 61,000 £1,762,605 £4,884,376 £40,088,497 £33,278,908 £310,000 £1,795,000 £17,250,000 £12,750,000 £2,072,605 £6,679,376 £57,338,497 £46,028,908 85 % 73 % 70 % 72 % £4,145,210 £2,968,612 £2,548,378 £2,045,729 £103,630 £80,962 £69,601 £55,793 Annual power capture (no outage) (MWhr/year) Structure cost (incl. temp. works / installation) Balance-of-plant and grid connection cost Total Cost Structure cost as % total cost Cost / MW rated capacity Cost / m collector Power Production Cost (10% discount rate) p/kWh 17.5 Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 9.6 4 February 2005 Page 3 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Economic models were established for shoreline and near-shore devices to investigate the likely p/kWh power output cost, and to test the sensitivity of this cost to the main design elements of an OWC development. Improvements with the biggest impact on the power production cost, requiring the least effort to implement, were then identified. Sensitivity analysis showed that increased capture efficiency had the biggest impact on the development’s economic viability. The wave resource at the development site was the next most critical factor. The effect of development size was also investigated in relation to power output cost. It was concluded that, for smaller developments up to 2 MW, shoreline OWCs are preferable. Near-shore devices are less viable for small-scale development due to the dry dock and installation vessel mobilization costs (but can be made more viable if construction facility costs can be minimised). The facility and vessel mobilisation costs, when shared on a multi-device development, have a reduced impact on the final cost and continue to reduce with development size. Grid connection costs are site-specific, however, significant capacity was found to be available at a cost of around £120,000/MW. As grid connection is a mature technology, improvements were not explored in this area. Viability of OWCs In order to illustrate the future viability of this technology in the medium term, a power production cost target was chosen for each device type, and the viability of the improvements required to reach the target assessed. Due to the more limited market resource and the lower CAPEX and power production cost for smaller developments (less than 2 MW); shoreline OWCs would be more appropriate for remote power supply to small communities. This could be as an alternative, or supplement to, small diesel generator power production. As such a target power production cost of 8 to 10 p/kWh is considered reasonable. Our current assessment of this technology suggests a power production cost of 17.5 p/kWh for a 500kW shoreline OWC (with a 10% discount rate). Reaching the 8 p/kWh target would require a combination of capture efficiency being increased by 10% to 52%, turbine efficiency being increased by 2.5% to 67.5%, generator efficiency being increased by 3% to 94%, and civil costs being reduced by 50%. Such a reduction in civil costs would have to be achieved through a change in concept – perhaps to the ‘roof only’ LIMPET proposed by Wavegen. Near-shore development is better suited for power supply above 2 MW, with greater economies as the project increases to the 20 MW scale. This type of development should be compared with the current offshore wind technology, as such targeting a 5 p/kWh power production cost. Our current assessment of this technology suggests a power production cost of 9.6 p/kWh (with a 10% discount rate) for a 22.5MW near-shore demonstration project. Reaching the 5 p/kWhr target would require a combination of capture efficiency being increased by 13% to 55%, turbine efficiency being increased by 2.5% to 67.5%, generator efficiency being increased by 3% to 94%, balance of plant costs decreasing by 40% to £300/kW, civil costs reducing by 20% and the cost contingency reducing from 10% to zero. The reduction in civil costs may be achieved by importing from a lowercost country of construction. Achieving the Targets An engineering assessment approach has been taken in this report whereby the potential for refinement and development of sub-systems and components has been evaluated. An alternative empirical approach, based on learning rates – i.e. the rate at which cost decreases with each doubling of cumulative production - has been considered to assess how achievable these improvements are. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 4 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Learning rates in renewable energy technologies have been assessed to be 10-30%. The rate of progress achieved on Arup dry-built offshore concrete platforms was examined, as this form of construction is directly comparable to the future vision for the civil construction of a near-shore OWC. A learning rate of 7.3% was found, which reflects the fact that marine concrete design and construction is a relatively mature field. Since the relatively low rate of learning foreseen in the large civil works cost element will dominate over the improvements in wave-to-wire efficiency and the balance of plant, a learning rate of 13% was suggested as being applicable to OWC technology (compared to 18% for onshore wind). For shoreline OWCs, if the learning rate of 13% is applied, the cost of power will decrease from th 17.5p/kWh to 8p/kWh by the time the 50 unit has been constructed. This would amount to 12.5% of the total market foreseen in the UK for shoreline OWCs, or a capital expenditure approaching £80m. It is considered unlikely that the necessary financial support to allow this quantity of units to be constructed will be readily secured by developers without assistance from government. The capital cost is approaching twice the level of funding currently being made available through the Dti for all wet renewable power demonstration projects. This suggests that efforts are best directed at researching designs that may achieve substantial cost savings through a ‘concept shift’ such as Wavegen’s roofonly LIMPET. For near-shore OWCs, 5p/kWh would be achieved when 250 number 82.5m long units had been installed at a rated capacity of 562MW and a capital cost of approximately £1bn. These would constitute 15% of the total market foreseen for near-shore OWCs around the UK. By comparison, this is the size of five of the UK round 1 offshore windfarms for which some capital grant funding was available. It is considered unlikely that this volume of construction would secure the level of financial support to make it attractive to investors, especially considering that developments on this scale would merely permit near-shore OWCs to reach the level of current power cost performance of offshore wind. Instead, some further stimulus to test whether economics can be improved should be the first step. The target improvements, whilst considered achievable, only take OWCs to the stage of a first medium-scale demonstration project. A greater range of improvements must be sought or a greater rate of learning achieved to be sure that the industry can grow to the level where better economics would be achieved. Increasing the learning rate to 18% would mean that 5p/kWh was achieved by the th production of the 100 near-shore unit and 2p/kWh if the full UK resource was developed. Deployment of OWCs in other countries would, of course, mean that 2p/kWh was reached before the whole UK resource had been exploited. Research & Development Priorities The research & development priorities identified to help deliver the improvements needed are: • To make wave climate data available for representative near-shore sites • To conduct parametric exercises using computational fluid dynamics (CFD) tools matched by wave tank testing to distil out the fundamental principles of good collector design in order to deliver the improved capture efficiency essential to improved economics • To conduct a further Marine Energy Challenge type exercise to brainstorm and prove construction and installation methods that can show savings in the dominant civil works costs • Conduct research coordinated with breakwater and coastal engineers into the nature of impact loading and structural response • Explore the potential for adopting reduced load and material factors in design recognizing the consequences of failure of an OWC • Developing a renewable energy development contract that would aim to place risk with those best able to carry it Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 5 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report • Comprehensive benchmarking of fixed-bladed turbine, guide vane, throttle valve and control systems using CFD tools validated against large-scale prototype devices followed by investigation into variable pitch blade control • Development of performance standards for defining the performance characteristics of OWC installations to allow like-for-like comparisons • Assessment of the scale of sub-synchronous resonance in power systems to establish the nature of this issue • Encouragement of the creation of strategic partnerships between technology developers and potential volume manufacturers • Investment in the use of LIMPET as a proper test-bed for OWC technology Conclusions If OWCs are to have a long-term future, rate of progress must be improved. The Marine Energy Challenge was devised as a way of pushing wet renewable technology forward and encouraging faster learning. Hopefully, this report for the Challenge demonstrates that near-shore OWCs can, within a reasonable timescale, reach a point where they can work within the current UK framework for renewable power generation without needing additional government support. The improvements reported here in performance and cost to reach this position do seem achievable. However, the OWC industry will not deliver these improvements without a more coherent development approach and appropriate financial assistance. The best use of any future funding would be to stimulate the rate of learning that will deliver a similar progress rate to that of successful renewable energy technologies such as onshore wind. It is believed that attention to the identified research and development priorities will show whether the potential can be realised. Shoreline OWC technology will never achieve as low a power price as near-shore OWCs. Nonetheless, it can still play a role in serving isolated communities where there is power price premium. Efforts commensurate with the scale of resource should continue, to help the shoreline OWCs reduce costs and improve performance, so that they can be a viable niche power provider. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 6 The Carbon Trust 1 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Scope of Work & Report Structure 1.1 Background to the OWC Evaluation The Marine Energy Challenge aimed to inform the Carbon Trust (CT) on the scope and potential for marine energy technology. One important area that the CT wished to understand was shoreline Oscillating Water Columns (OWCs). The CT wanted to form a view on the status and prospects for such devices. Shoreline OWCs are the most widely deployed wave energy technology, with several large-scale prototype devices installed in the Azores (Portugal), China, India, Japan, Sweden and the UK. These designs are broadly similar and comprise: • A shoreline superstructure, incorporating a wave ‘collector’ (with an opening to sea and containing a water column). • A turbine-generator power take-off system. • A flow control system The design and construction of OWCs depends significantly on their intended location, and many designs must be tailored to site-specific conditions. The market size for a particular device configuration is highly sensitive to the adaptability of that design to local site environments (and costs), including the depth of water at entry to the collector and method of superstructure construction. The term shoreline refers to OWCs that are constructed on land at the shore or in cliffs. The evaluation work was extended to incorporate bottom-founded OWCs denoted as near-shore devices in this evaluation. Floating OWCs were being separately evaluated by the Carbon Trust. 1.2 First Stage Evaluation 1.2.1 State-of-the-art Review Numerous studies have been made of OWC designs. In fact, the device category may be the most reported of all wave energy systems. A literature review was required containing a concise summary of: • The main characteristics of existing devices, in terms of their conceptual designs, geometric forms, main components and performance were to be identified. This was to illustrate the extent of development to date and demonstrate the state-of-the-art. Where key design decisions had been justified in the literature (e.g. with regard to selection of materials), these were to be noted, together with important design assumptions and working principles. • The prevailing technical uncertainties, risks, and associated opportunities for either cost-reduction or performance improvement, from the perspectives of various authors were to be summarised. The second part of the literature review was to enable CT to form a view on the potential markets for shoreline OWCs. The design, performance and cost of OWCs are sensitive to the situations in which they are sited; e.g. against a cliff, or as part of a breakwater; in shallow or deep water. The ability of an OWC design to be installed in different locations affects its scope for replication and consequently the size of its potential market. A number of applications was to be identified for shoreline OWCs in terms of the primary siting requirements e.g. water depth, wave climate, proximity to electrical demand centres or infrastructure, etc. These were to be in the applications for which the largest markets were thought to exist. The contractor was required to estimate the overall market size, through an assessment of resource and primary constraints to exploiting the resources. Detailed market analysis was not required. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 7 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report This market review served two purposes: • A first indication to the CT of the potential markets for OWCs. • A ‘base-case’ for use in the scope for improvement assessment discussed below. This was to define the applications for which most OWCs should be designed. 1.2.2 Market Assessment The market size for a particular OWC device configuration is highly sensitive to the adaptability of that design to local site environments, including the depth of water at entry to the collector and method of superstructure construction. The UK coastline has been evaluated with respect to wave resource, sea-bed slope, tidal range, water depth and proximity of population centres. A matrix method was adopted to rank regions of the coastline. The most promising areas for OWC developments were identified. This phase of the study assessed the potential scope for improvement measured against the existing device technology. It went on to consider the most promising near-shore areas to develop a base case OWC with this design evaluated on the basis of cost of energy and market size. This included an estimate of both the capital cost and the performance of the design. 1.2.3 Report Structure The results of this first stage evaluation are included as chapters 3 to 6 following the divider entitled ‘State-of-the-art Review and Market Assessment’. 1.3 Second Stage Evaluation 1.3.1 Scope for improvement With respect to the state-of-art of this technology identified in the first stage, this second stage of the evaluation identified the potential areas for improvement to shoreline OWC designs, in terms of both installed costs and expected performance. The study considered: • Site –specific tailoring of designs • Turbine choice and specification • Incorporation of devices into existing structures • Conversion efficiency • Mass production / manufacture • Materials selection • Survivability • Reliability, operation and maintenance • Economic design life • Prediction and modelling • Resource assessment • Control of export power • Device construction methods For each area identified, the potential to lower the cost of energy was to be estimated with reasoned assumptions. ‘Knock-on’ effects to other design attributes were also to be stated, so as to define the relationships between various design parameters. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 8 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report 1.3.2 Future Visions Based on the list of areas offering scope for improvement, a future vision of this type of device was to be developed and an economic model established. This was to be used to explore the potential improvements in terms of cost of energy and market size by the combination of several design changes. These were to be: • The current state-of-the-art • An optimistic case • A base case (being the most likely) • A pessimistic case The scenarios were to be defined by – • The types of improvements assumed for each • The overall effects on cost of energy • The assumed relative contribution of each area to the overall effect These scenarios were to be compared on the basis of cost of energy and market size. These were to include, where appropriate, estimates of both the capital cost and the performance of the designs. Where there was a trade-off between cost of energy and market size (estimated in stage 1) this was to be explained. 1.3.3 Shoreline against near-shore device installation The stage 1 evaluation concluded that a near-shore device offered a greater potential resource than a shoreline device. As such the focus of the stage 2 evaluation was to be directed towards this technology. However, this report continued to study the shoreline OWC concept as a base line comparison to near-shore OWCs. 1.3.4 Sensitivities and prioritisation Using the scenarios, the sensitivity of cost of energy to different design changes was to be explored. A well-reasoned, technically-rigorous summary was required of where the greatest improvements were most likely, and consequently efforts for cost reduction/performance improvement should be focussed (Stage 3). This was a key deliverable of the work. 1.3.5 Report Structure The results of this second stage evaluation are included as chapters 7 to 10 following the divider entitled ‘Scope for Improvement & Future Vision’. 1.4 Third Stage Evaluation 1.4.1 Recommendations for development work For each area identified as a priority for improvement and therefore further work, well-considered proposals for reducing cost/improving performance were to be made and justified. Estimates of costof-energy benefits and market size were to made with reference to the development scenarios previously outlined in stage 1. Amongst the recommendations, some elements of technology transfer from other industry sectors were expected, and suggestions were to be given on how to motivate this. 1.4.2 Report Structure The results of this third stage evaluation are included as chapters 11and 12 following the divider entitled ‘Research and Development’. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 9 The Carbon Trust 1.5 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Developer input and peer review The views of people and organisations involved in the design, construction and operation of OWCs were to be sought since they had not been directly involved in the Marine Energy Challenge. These views, where accepted, are incorporated throughout the report and in the final conclusions. The comments of the peer reviewers and the responses to their views are recorded in Appendix G. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 10 The Carbon Trust 2 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Glossary of Terms 2.1 Oscillating Water Column Terminology AIR CHAMBER OR PLENUM COLLECTOR OR /RAREFIED LIP Figure 2.1 2.2 An OWC (Source: The Green Trust) Terminology Capture width – The maximum linear dimension of the collector chamber, or collector chamber plus guide walls where present, perpendicular to the approaching wave front Capture efficiency – The proportion of wave energy captured in the compression and rarefaction of the air in the collector out of the total incident wave energy flux (commonly taken at the 20m contour) crossing a line equal to the capture width Pneumatic efficiency – Sometimes used as an alternative to capture efficiency Mechanical efficiency – the proportion of pneumatic power that is converted to mechanical power in the turbine Turbine efficiency – Sometimes used as an alternative to mechanical efficiency Electrical efficiency – the proportion of power that is converted from mechanical power to electrical power in the generator Wave-to-wire efficiency – the product of capture efficiency, mechanical efficiency and electrical efficiency Availability – the proportion of the year that the OWC is available to generate power ie 8760 hours/year less planned maintenance Capacity factor – Describes how well the generator capacity is utilised. It is the actual electrical energy yield as a percentage of the maximum theoretical or ideal yield. Shoreline – An OWC is classified shoreline if connected to the shore above mean high water. It also includes OWCs that use tunnelling technology Nearshore – A device is classified as nearshore if it is not connected to the shore. The OWC is fixed to the sea-bed for the purposes of this review. Access will normally be by boat. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 11 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Breakwater – a structure that aims to provide sheltered conditions in its lee Caisson – a monolithic structure usually in steel or concrete and usually divided into compartments, deployed in the marine environment Power train – the combination of a turbine, any gearbox or flywheel and the generator Balance of plant – the power conversion elements of an OWC that are not civil works, namely the turbine, generator and controls Market – the quantity of power that can credibly be produced using the OWC technology, recognizing limitations in grid capacity, acceptability of the technology and existence of suitable conditions for its deployment Cost of energy – the calculated cost at which the net present value for the project become zero ie the cost beyond which a profit can be returned from the investment Equity discount rate – the rate at which costs are depreciated in future years to reflect the time value of money Out-turn costs – the entire capital costs of developing an OWC Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 12 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report State-of-the-art Review & Market Assessment Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 13 The Carbon Trust 3 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Existing Shoreline OWCs This section provides a summary of the existing more recent OWC projects. The LIMPET and Pico projects are shoreline mounted systems, the OSPREY and Port Kembla are examples of near shore OWCs, with the Trivandrum and Sakata projects examples of breakwater devices. These projects have been key to contributing to the current understanding of OWC technology, and in many cases serve either as on going test beds or are used for data collection. While there are many other OWCs throughout the world including many powering navigational buoys, these are considered the most important in defining the current state-of-the-art. 3.1 LIMPET 500 [3,5,6,27,56] 3.1.1 Concept The LIMPET 500 (Land Installed Marine Pneumatic Energy Transformer – 500kW) is an OWC built into the shoreline near Portnahaven on the island of Islay. Construction began at the end of 1998, with the civil structural works substantially complete by the end of August 2000. The plant was commissioned at the end of 2000. It comprises an insitu concrete collector, with the generation unit installed immediately behind the rear collector wall. Self- rectifying Wells turbines mounted directly on the generator shaft have been used, enclosed by a small turbine hall. The process air exits the turbine hall via an acoustic attenuator, installed behind the turbine hall. Foam from a spent breaker cascades down the face of the LIMPET. (Wavegen) The LIMPET structure was built in-situ into a rock cliff. This was done by excavating from the cliff top and leaving a temporary rock bund on the seaward side of the construction site. The collector chamber was then constructed and plant installed prior to removal of the bund. This left the device slightly set back from the original shoreline. 3.1.2 Geometry The device consists of 3 chambers 6 x 6m built at an angle of 40 degrees to the horizontal. /RAREFIED 3D View of LIMPET Chamber (The Green Trust) Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 14 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report The inclined column has been shown to offer an easier path for water ingress and egress resulting in less turbulence and lower energy loss. This is particularly true at the shoreline where shallow water effects are increasing the surge motions relative to heave. (The improved performance of an inclined water column in comparison to a vertical column was established through tank testing). The width of the device was split into 3 chambers to reduce the risk of transverse wave excitation reducing the energy capture performance. 3.1.3 Design Parameters (Assumptions and working principles) The following table summarizes the principal design characteristics of this project. Geometry Wave / Sea Characteristics Total Width No. of Chambers + Width Chamber Angle Lip depth below MWL Total Height above MWL 21.0m 3 x 6.0m 40o to horiz. 2.3m 12.8m Depth at lip 6.0m Design Wave Height, Hs max 4.4m Design Wave Period 13.4s Return period (n/a waves depth limited) Max design wave pressure 600kN/m2 Turbine Generator Turbine Dia. 2.6m Nominal operating speed 1050rpm No. of Turbines 2 Arrangement In line, contra rotating Type F3GTS 400 G8G Power at Generator Terminals 2 x 250kW Duty Type continuous inverter driven Rotor Type Wound rotor (but used with rotors shorted) Rated Voltage 400V Rated Speed 1016rpm Max test speed 1500rpm Inertia Generator 11.5kgm2 2 Load 1300kgm Blade Form Number of blades Blade Chord Hub to tip ratio NACA 12 7 320mm 0.62 A wave climate of approximately 20kW/m was initially estimated during the concept stage to exist at the collector. Model tests during the design period reduced the estimated resource to 17.9kW/m at the OWC lip. Values measured in service are only 12kW/m at the lip. 3.1.4 3.1.4.1 Project Experience Turbines LIMPET uses two back-to-back, horizontal axis, contra-rotating Wells turbines. This configuration was believed, based on model test results, to give better performance than the equivalent single stage machine, due to the nozzle effect of the first stage on the second stage. However, in practice, the cyclical motion does not allow the system to stabilise and energy recovery is minimal. Two inlet valves are used in series for isolation (including emergency shut down) and control, although it is indicated that only one of these would probably be sufficient when technology is proven through operational experience. An actuated and counterweighted butterfly valve is used as the primary means of flow modulation and also serves as an emergency stop valve. Modulation of the valve gives flow throttling, thereby smoothing the velocity profile over time and improving performance of the turbine. Problems have been encountered with ensuring free movement of the valve spindle and with flow induced vibration, although both of these are claimed to have been overcome. An array of radial vanes is also provided for isolation purposes downstream from the butterfly valve. The arrangement of the vanes, and indeed of the air inlet structure, appears to be similar to the nose cone and inlet guide vanes (IGVs) on gas turbine compressors. Modulation of the radial vanes to achieve control is not currently possible due to lack of instrumentation, but steps are being taken to address this. Actuator power needed for radial vanes may be lower than for the butterfly valve due to lower mass and inertia. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 15 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report A general conclusion made by the project report [5] was that to achieve high turbine efficiency will require development of variable pitch machines with an appropriate control strategy. It may be possible to combine of the stop valve radial vanes with inlet vanes for control of incidence angle onto the moving blades. 3.1.4.2 Control and Electrical Aspects The project has produced a number of useful lessons; among these, are not only the obvious recognition of the need for protection of the turbine/generator from over-speed events, but a useful list of the measures taken to ensure this under a wide set of circumstances. The literature [5] refers to the ‘layered’ measures taken in the automatic control and protection software provided, which ensures that the plant comes to no harm. These layers consist of a series of progressively more positive actions taken by the protection systems (mechanical and electrical), ending up with full turbine/generator trip, and isolation of the plant from both the grid and from the power source (the OWC). Protection measures for the electronic control systems (PLCs) themselves are listed, and include the provision of an Uninterruptible Power Supply (UPS), and the designing-in at an early stage of fail-safe measures for the main electro-mechanical protection and isolating systems. Thus a butterfly valve used to control the air inlet to the turbine is operated by a solenoid valve. If power is lost, the solenoid is de-energised and the valve closes to isolate the turbine on the inlet side. Similarly, the variable vane control actuator is pneumatically operated. If the actuation signal is lost, then the piston cylinder inlet is opened to atmosphere and the reservoir dumps actuation air to the closing side of the piston. In both cases, loss of the main controller power system will result in the fail-safe shutdown of the installation The literature [5] also gives extensive information on the instrumentation systems installed to provide an internal health-check (condition monitoring) of the rotating and actuator parts, and to provide information for the protection and automatic control systems themselves. The original induction machine drive design used resistors to dissipate rotor energy and provide variable speed operation. This would, as with the 75kW prototype, give rise to poor efficiencies. Replacement with an industrial standard drive system should have given much better electrical efficiencies than those reported. If the figure of 32% electrical efficiency is correct than it is probably due to a combination of rotor resistance losses, over rating of the machine and operation in low sea states. The lessons gained from LIMPET are valuable, and provide insight into some of the problems encountered in an industrial size OWC generator, and the solutions adopted in overcoming them. There is an active programme at LIMPET designed to address the issues raised. 3.1.4.3 Problems The following problems have been reported has having a major detrimental effect on the overall project programme, cost and performance. • Feasibility study – a lack of detailed site data prior to the final device location being chosen led to a lower than predicted wave energy resource due to sea bed friction. In addition the benefits of ‘harbour wall focus’ do not occur in shallow water. In such shallow water a parallel gully was found to be detrimental to the overall performance of the collector. • Civil construction planning – a lack of flexibility in resource allocation and programme for activities to be tuned around weather windows. • Civil construction method – insufficient protection of the work area by the temporary bund. • Civil construction method – Removal of temporary bund led to a scatter of rock fragments and water chamber blockage. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 16 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report • Operational - Deluge of the turbine hall from overtopping, later improved through installation of a marine standard doorway, although one wooden door is still present on the turbine room. • Efficiency - The acoustic attenuation was found to reduce the efficiency of the turbine. This was due to an unbalanced airflow through the turbine during the inlet stroke, achieving only 75% of the outflow. • Efficiency – At low generator speed the percentage parasitic losses are very high. 3.1.4.4 Successes The following have been reported as particular successes on this project. • Low maintenance costs. • Remote control by modem • Grid connection • Pre-cast elements for turbine hall • Use as a test-bed has allowed operational experience to be matched to engineering models 3.1.4.5 Performance A summary of the device estimated and operational efficiencies is listed below. Type of energy conversion Structure / device Wave to pneumatic (measured at lip) Oscillating water column Pneumatic to mechanical Wells turbine Mechanical to electrical Generator Overall efficiency Estimated Efficiency% Measured Efficiency% 80 64 60 (average) 40 (average) 100 * 32 48 (average) 8 * Note that Wavegen now accept that this figure was unrealistically high and should have been 90%. While the original estimate of wave resource was 20kW/m the actual measured resource at the OWC lip has only been 12kW/m. This equates to an initial estimate of 202kW output against a measured output of only 21kW. A crew works on LIMPET's turbine (Wavegen) 3.1.4.6 Reported Conclusions The project participants have reported a number of findings that could have an impact on any future OWC design. These include: • The need to optimise the device design for a particular water depth. • Measurement of applied loads proved to be less than extreme used in design by a third, with wave slam and peak pressure not co-existent. • Internal wave slam has been less than predicted. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 17 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report 3.2 Pico [4,26,45,46,67,68] 3.2.1 Concept The Pico project is a 400kW OWC built into a small natural gully near Porto Cachorro on the island of Pico in the Azores. Construction of the civil structural works began in 1996 and was completed in the summer of 1998. The plant was first commissioned at the end of 1999, however flood damage to the electrical and control equipment led to a further year delay. The plant comprises an insitu concrete collector, with the back wall stepped and the generation unit installed immediately behind the upper constriction of the collector wall. The plant is equipped with a horizontal-axis Wells turbine-generator set enclosed by a small turbine hall. Front view of Pico OWC (Maretec) 3.2.2 Geometry Elevation of the chamber design for the PICO plant (IST 1996) Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 18 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Rear view of Pico OWC (Maretec) 3.2.3 Design Parameters (Assumptions and working principles) The following table summarizes the principal design characteristics of this project. Geometry Wave / Sea Characteristics Total Width No. of Chambers + Width Chamber Angle Lip depth below MWL Total Height above MWL 12.0m 1 x 12.0m 60o to horiz. 2.5m 15.0m Depth 8m at lip, 8 – 10m approach Design Wave Height 7.5m Design Wave Period 12.0s Return period Max design wave load 700kN/m2 Turbine Generator Turbine Dia. 2.3m Nominal operating speed 750 – 1500rpm No. of Turbines 1 Arrangement Horiz. axis Blade Form 3D symmetrical NACA15 at root and NACA12 at tip Number of blades 8 Blade Chord 375mm Hub to tip ratio 0.59 Type Induction, Wound Rotor, Kramer Power at Generator Terminals, 400kW Duty Type 50Hz, 8 Pole Rotor Type Wound, slip rings Rated Voltage 400V Rated Speed Max test speed Inertia 1400 RPM 1500 RPM 600kgm2 From offshore measurement with wave-rider buoys, and close shore measurement using ultrasonic probes a wave resource of 13.4 kW/m at the OWC lip was determined. 3.2.4 3.2.4.1 Project Experience Problems The following problems have been reported has having a major detrimental effect on the overall project programme, cost and performance • A new access road was required to the construction site. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 19 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report • The temporary cofferdam, erected to protect the construction works was badly damaged several times. • Underwater work was particularly diificult. • Flooding of the control room both during installation and commissioning caused a major programme extension (The control room has subsequently been moved). • Little infrastructure on the island • Limited choice of contractor 3.2.4.2 Performance The rated power of the Pico plant is 400 kW, which is estimated to deliver around 0.5 GWh per year. A summary of the device estimated and operational efficiencies is listed below. Type of energy conversion Structure / device Wave to pneumatic Oscillating water column (measured at lip) Pneumatic to mechanical Horizontal axis Wells turbine Mechanical to electrical Wound rotor, induction Generator Overall efficiency Estimated Efficiency Measured Efficiency % % NA NA 75 (peak) NA NA NA 35 (average) NA The plant is equipped with a single horizontal axis Wells turbine with fixed pitch blades and guide vanes. The plant is designed to have a controlled bypass relief valve located on the roof of the structure, although it is believed not to have been installed to date. (Reference report was dated December 2000 [26]). The bypass relief valve would be expected to enhance the performance under heavy sea conditions by limiting the air velocity through the turbine and thus preventing stall. However, it is important that the power consumed in operating the valve does not outweigh the benefits gained from increased power capture in the turbine. The assumed turbine peak efficiency of 75% is that obtained in a steady flow. The time-averaged efficiency in a bi-directional flow will clearly be less than this at around 50%. A second horizontal axis machine with variable blade pitch, designed under a JOULE project, is planned for installation alongside the fixed pitch machine. In general horizontal axis machines should be easier for maintenance than vertical axis machines. The thrust bearing loading will be reduced (not required to support the machine weight) but the thrust bearing will need to be designed for loading in both directions to allow for bi-directional air flow. A second JOULE project which started in 1999 sought to optimise OWC control and blade geometry. 3.2.4.3 Reported Conclusions The project participants have reported a number of findings that could have an impact on any future OWC design. These include: • The use contractors experienced in working in marine environments is crucial to the success of the civil element of the works • Underwater work should be minimised. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 20 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report • Two air valves were installed in series with the turbine to enhance safety. One adequately designed valve would allow a cost reduction. • A by-pass valve control of the turbine flow rates is a relatively inexpensive way of increasing efficiency of a conventional fixed pitch Wells turbine. • Variable speed generator enables the turbine to respond efficiently to a to a wide range of sea states, and also allows a temporary storage of excess available energy (by fly wheel effect) with a short term smoothing effect on the electrical power supplied to the grid. The wound rotor induction machine with Kramer variable speed drive allows variable speed operation. • A study of the performance of various construction materials is on going. The plant developer reported ‘Considerably more than half of the total cost of the Pico plant concerned the civil construction. Recent studies carried out in Portugal have shown that the cost of the concrete structure of a commercial OWC of similar size (and in a less remote site) can be reduced by a factor of more than three.’ Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 21 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report 3.3 OSPREY [10] 3.3.1 Concept The OSPREY (Ocean Swell Powered Renewable EnergY) is a near-shore device designed to operate in a water depth up to 15m and up to 1km offshore. OSPREY 1 was the first variation of this 2 MW concept. It was constructed in 1995 to be installed 100m off the coast at Dounreay in the North of Scotland, and comprised a rectangular steel collector chamber with trapezoidal steel ballast tanks fixed either side for gravity anchoring of the device. Mounted on top of the collector chamber was the power module containing the turbine- generators (mounted vertically) and the control equipment. However during the installation of the 750 tonne structure, a large wave smashed open the ballast tanks and the device had to be abandoned. The OSPREY (Universitat Leipzig including subsequent images) Wavegen has re-designed this device, known as the OSPREY 2000, as a composite steel and concrete unit. This led to the announcement in 1998 that Wavegen had gained backing from the Irish Government (through its Alternative Energy Requirement III). The tender would have resulted in a 15year power purchase agreement, however funding was not forthcoming and the project is not considered likely to proceed. The following sections comment on the design and technology associated with the OSPREY 1 project. 3.3.2 Geometry (OSPREY 1) The collector chamber is 20m wide and is fabricated using a double skinned, composite construction, comprising panels each containing a layer of concrete sandwiched between two sheets of steel. Each ballast tank is a maximum of 20m high and 44m long, manufactured with stiffened 10mm thick plate. The bottom of the tanks was covered with a layer of concrete to provide trim and additional stiffness during tow out. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 22 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 23 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report 3.3.3 Design Parameters (Assumptions and working principles) The following table summarizes the principal design characteristics of this project. Geometry Total Collector Width No. of Chambers + Width Chamber Angle Lip depth below MWL Total Height above MWL (to collector roof) Turbine Wave / Sea Characteristics 20.0m 1 x 20.0m Curved 3.8m 5.24m Turbine Dia. 3m Nominal operating speed 800-1400rpm No. of Turbines 4 Arrangement Back-to-back pairs Blade Form NACA12 Number of blades 9/11 (different to minimise effects of blade passing) Blade Chord 444/363mm Hub to tip ratio 0.62 Depth 14.5m Design Wave Height, Hs 8.6m Design Wave Period, tz 10.9sec Return period (n/a – depth limited waves) Max design wave load Generator Type Induction / Cage Power at Generator Terminals 4 x 500kW Duty Type continuous inverter driven Rotor Type Cage Rated Voltage 600V AC Rated Speed 1000 rpm Max test speed Inertia 1500rpm 1500kgm2 per rotor A design wave climate of approximately 30kW/m was estimated to exist at the OWC lip. The climate at the test site was 12kW/m but the extreme conditions were typical of more energetic sites. 3.3.4 Project Experience & Reported Conclusions No installed experience and performance monitoring exists for this project as, after it was towed to its station, it was destroyed by the tail end of hurricane Felix before it could be secured to the sea-bed. An extreme wave smashed open the structure's ballast tanks. Although OSPREY's builders had time to rescue valuable equipment, the sea eventually tore the device apart. The project participants have reported a number of findings that could have an impact on any future OWC design. These include: • Part of the problem was the inability to ballast the device quickly enough to beat the weather, before 7,000 tonnes of sand-ballast had been pumped in. Any future device would need to look at the weather exposure risk incurred between installing and ballasting the structure. • Towing the structure to the site with neutral ballasting. This would stabilise the structure during tow out and could assist during the placement process. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 24 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report • 3.3.5 Cellular construction such that localised damage would only lead to flooding a small volume of the structure. Performance A summary of the device’s estimated average efficiencies is listed below. Type of energy conversion Structure / device Wave to pneumatic Oscillating water column (measured at lip) Estimated Efficiency Measured Efficiency % % 115 * NA Pneumatic to mechanical Wells turbine 70 NA Mechanical to electrical Slip-ring induction generator 80 NA 65 (average) NA Overall efficiency * The wave-to-pneumatic efficiency exceeds one because the effective capture width of the device is greater than the collector width. The mechanical and electrical efficiencies are acknowledged to be high. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 25 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report 3.4 Port Kembla, NSW, Australia [47,70,71] 3.4.1 Concept This 300kW wave energy demonstration device is a near-shore OWC to be installed at Port Kembla, part of the Illawarra Region, approximately 100km south of Sydney, Australia. It will be installed 200m off Port Kembla Harbour breakwater with taut mooring lines and legs extending to the seabed. The structure is currently being fabricated to the design produced by Energetech and JPKenny Ltd. An alternative bi-directional turbine to the Wells turbine, the Denniss-Auld turbine will be installed in the plant, which is planned to be commissioned by the end of 2004. (Source: Energetech) The device is intended as a demonstrator project and has been designed for a three-year deployment period. Energetech has plans for future devices to follow this demonstrator. 3.4.2 Geometry The device is approximately 36m long and 35m wide, and uses a ‘parabolic wave focuser’ to focus all the energy of a plane surface gravity wave crest to a single area. As the wave converges, the crest height grows to a maximum in the focus area. At this focal point the collector chamber is positioned. It extends to a depth below the minimum possible wave trough such that the oscillatory wave motion causes a forward and backward airflow through the chamber. To obtain the greatest capture efficiency, the device should be aligned so that the wave crests propagate parallel to the axis of symmetry of the parabolic focuser. The greater the angle between the axis of symmetry and the propagation direction, the lower the level of wave energy entering the device (a cosӨ term). 3.4.3 Design Parameters (Assumptions and working principles) The following table summarizes the principal design characteristics of this project. Geometry Wave / Sea Characteristics Total Width 36.0m No. of Chambers + Width 1 x 10m Chamber Angle vertical rear, approx 45 o front Lip depth below MWL 3.0m Total Height above MWL 12m Depth Design Wave Height Design Wave Period Return period Max design wave load Turbine Turbine Dia. Nominal operating speed No. of Turbines Arrangement Blade Form Number of blades (variable pitch) Blade Chord Hub to tip ratio Generator Type Squirrel cage/induction Power at Generator Terminals 200/300kW Duty Type 50Hz, 12-pole Rotor Type Cage Rated Voltage 415 V Rated Speed 500RPM 1.6m 500rpm 1 horizontal axis 21 blade 0.75 Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC Max test speed Inertia 8-16m 7.0m 9 to 12s 100 year 750RPM 4 February 2005 Page 26 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report A 9 kW/m wave has been assumed at the chamber mouth. The sea bottom should be reasonably flat, so it does not disturb the wave direction, and deep enough so that when wave section enters the parabola, the crests do not steepen and break as they grow. Energetech believes that the relatively shallow slope of the sea-bed will ensure that the breaking waves are of the spilling type which would reduce loads considerably compared to plunging breakers. Nevertheless, the structure has been designed against a breaking wave. A choppy scattered incoming wave will scatter some energy away from the focus. The energy loss arising from the above-mentioned conditions can be minimized by choosing the appropriate focal length of the parabola, so that the waves do not have the time or space to vary greatly. 3.4.4 Project Experience This project is still in the development stage, and as such no installed project experience is available. Based on the main characteristics of this device, an assessment of the inherent project risks is included in section 3.9. Particular project specific challenges that must be overcome during the execution phase include: • Providing sufficient strength to the parabolic reflector during extreme wave loading. • The complexity of the steelwork detailing and its resultant behaviour in fatigue • Keeping the anchors taut • Providing access for maintenance past the taut-moored anchoring system • Any requirement to adjust the legs in service Problems may occur during the commissioning of both the turbine and control equipment due to the advanced and untested nature of this plant. The use of this technology is, however, one of the principal drivers of this project. Progress Photos in October/November 2004 (www.energetech.com.au) Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 27 The Carbon Trust 3.4.5 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Performance Energetech’s Port Kembla Wave Energy plant is expected to produce almost 1 GWh of electricity per year. A summary of the device’s estimated efficiencies is listed below. Type of energy conversion Structure / device Wave to pneumatic Oscillating water column Pneumatic to mechanical Denniss-Auld turbine Mechanical to electrical Not known Estimated Efficiency Measured Efficiency % % 67 NA 54 average NA 80 peak Overall efficiency 90 NA 32.4 (average) NA The turbine has been tested by Lloyd’s Register and showed lower than expected losses from windage and bearing friction, averaging around 3kW at a normal running speed of 500rpm. Noise testing has also been conducted, with decibel readings taken at a number of locations one metre from the turbine. The result was an average reading of 73dB. 3.4.5.1 The Denniss-Auld Turbine The Energetech turbine is a variable pitch machine that uses a slower rotational speed with higher torque. This they believe improves efficiency and reliability and reduces the need for maintenance. The turbine uses a sensor system with a pressure transducer. This measures the pressure exerted on the ocean floor by each wave as it approaches the capture chamber, or as it enters the chamber. The transducer then sends a voltage signal proportional to the pressure, thus identifying the height, duration and shape of each wave. The system is calibrated to ignore small-scale “noise” from activating it. The signal from the transducer is sent to a Programmable Logic Controller (PLC), which adjusts various parameters to optimise turbine efficiency that are selected based on particular conditions and energy content of each site. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 28 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report 3.5 Vizhinjam OWC, Trivandrum, India [11,48] 3.5.1 Concept A 150 kW pilot OWC was built onto the breakwater of the Vizhinjam Fisheries Harbour, near Trivandrum in India in 1991. Located directly in front of a rubble-mound breakwater at Vizhinjam harbour a cellular reinforced concrete caisson providing the geometric structure for the OWC was floated into place. The installation comprises a 3,000 tonne concrete caisson topped by a steel tower. The turbine is connected directly to the local grid The structure was not integrated into the breakwater as no actual reconstruction or new build breakwater projects were available at the time. The hydrodynamic efficiency was enhanced by continuing the chamber side-walls towards the sea. This (has been claimed) helps to smooth the different wave frequencies to an optimum range at the collector chamber. The following pictures show the OWC caisson situated in front of the harbour breakwater of Vizhinjam. Vizhinjam OWC caisson in front of rubble mound breakwater structure [Graw, 1999] Caisson construction took place locally despite the fact that no heavy plant, wharves or docks were available. A small construction dock was excavated on the beach inside the harbour and kept free of water by means of pumps. The 3 m high base plate was then cast in this pit. The excavation was then flooded, the sand between the pit and the harbour basin removed and the base plate towed out into Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 29 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report the harbour. The side-walls of the caisson were then cast using sliding formwork (slipform), with a steel gate placed across the seaward opening to prevented the ingress of water. The progress of the work was organised in such a way, that the caisson floated horizontally throughout the entire process. Upon completion of the casting, the caisson (now with a draft of 9.9 m) was towed to its final location, lowered onto the prepared stone bed by flooding and subsequently filled with 3,000 tonnes of sand ballast. Vizhinjam OWC under construction 3.5.2 Geometry The concrete caisson structure is 23.2m x 17.0m x 15.3m high. The chamber entrance is 10m wide by 6m high. The top of the CWC chamber is a double cubic curved shell in concrete 10 x 7.75 m at the bottom, reducing to 2.0 m circle at the top and 3.0 m high to support the power module. Other principal dimensions are shown on the following diagrams. (Source: niot, India) Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 30 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report (Source: niot, India) 3.5.3 Design Parameters (Assumptions and working principles) The following table summarizes the principal design characteristics of this project. Geometry Total Width No. of Chambers + Width Chamber Angle Lip depth below MWL Total Height above MWL Wave / Sea Characteristics 14.0m 1 x 10.0m vertical 1.1m 14.5m Depth Design Wave Height Design Wave Period Return period Max design wave load Turbine Generator Turbine Dia. Nominal operating speed No. of Turbines Arrangement Blade Form Number of blades Blade Chord Hub to tip ratio Type Power at Generator Terminals Duty Type Rotor Type Rated Voltage Rated Speed Max test speed Inertia 2 NACA 0021 8 380mm 0.6 10.2m 7m 8 to 12s 1000kN/m2 1:10 model of the OWC (TU Berlin) A sea-bed slope of 1:50 exists in front of the caisson, with a wave resource of 20kW/m average monsoon input wave. 5 to 10 kW/m is typically available outside monsoon periods. During caisson design the wave forces were estimated by treating the caisson as a vertical wall obstruction to the waves. The highest probably non-breaking lateral wave force was 12,000 kN. The Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 31 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report highest probable breaking wave was estimated to be 7 m. The peak design force intensity used was 2 1000kN/m . 3.5.4 Costs The costs for erection of the OWC were reported to be approximately £400,000 (1990 prices?), with the electricity cost claimed to be 3.5 p/kWh, if the additional costs for the harbour construction are taken into account. It has not been possible to verify these figures and they should not be relied upon for future power cost prediction. 3.5.5 Performance A summary of the device estimated and operational efficiencies is listed below. Type of energy conversion Structure / device Estimated Efficiency Measured Efficiency % % Wave to pneumatic Oscillating water column 50 Pneumatic to mechanical Wells turbine 25 Mechanical to electrical Slip-ring induction generator 50 Overall efficiency 6.3 The OWC has functioned successfully, providing data on the in-service performance of the Wells' turbine and the mechanical and electrical plant. After the initial tests, the plant has been used to test different types of generating equipment. This information has been used to produce new designs for a breakwater comprising 10 OWC units with a total capacity of 1.1 MW. Plant operational performance revealed several areas where improvements could be made. The power module, designed for a peak power of 150 kWe, had large no-load losses and windage losses amounting to almost 15 kW. When the instantaneous wave power was low even the no-load losses could not be met by the turbine. Hence, the system would motor, drawing power from the grid. This resulted in poor long-term efficiency of the wave power plant. Also, the squirrel cage induction generator had a limited variation in speed up to eight per cent of synchronous speed. The vertical axis assembly of the power module posed operational and maintenance problems. Based on the experience, several improvements were incorporated in a new module installed in April 1996: • A tapered chord design was chosen for the turbine blades • two horizontal axis thrust opposing turbine rotors were coupled to an electrical generator on a common shaft, each having peak installed capacity of 55 kW to allow one module to be run during non-monsoon times and both during the peak season • A slip-ring induction electrical generator replaced the earlier squirrel cage machine • Better instrumentation and data acquisition system installed • A current controller was installed on the stator of the electrical machine in order to reduce the ‘peak to average ratio’ of electrical power exported to the grid. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 32 The Carbon Trust 3.5.5.1 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Performance Analysis of the Second power module Efficiencies as function of wave power-Second module (niot, India) The efficiencies of the various element of the power take-off, as a function of incident wave power, measured during its operation from April 1996 to July 1996 are shown above. A drop in efficiency for increasing incident energy is evident. As the output was most limited by the turbine, efforts were directed towards increasing the absolute value of the efficiency and the dynamic range over which the efficiency remains high. Wells turbines are claimed to have efficiencies of around 40% under oscillating flow conditions. Such efficiencies were being obtained at an average pneumatic input of only about 20 kW or only 3 kW/m average wave power. The dynamic range of the turbine was increased by increasing the external resistance connected across the rotor in conjunction with a controller. The resistance value was chosen so that the plant behaves as a high slip machine, thus enabling the turbine to freely ride the wave. When the speed exceeded a preset upper limit, the external resistance was reduced. Some optimisation of resistance values along with the speed settings resulted in improved overall efficiency, particularly with higher incident wave power where stalling had previously occurred, as shown below. Effect of increase of rotor resistance on plant efficiency (niot, India) Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 33 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report 3.6 Sakata, Japan 3.6.1 Concept This project consists of a five chamber OWC, built as part of the harbour wall at Sakata Port in Japan. The device became operational in 1989 but, after a test programme, only three air chambers were used for energy production. A turbo-generator module of 60 kW has been installed and is being used as a power generator unit for demonstration and monitoring purposes. This will possibly be replaced by a larger turbine (130 kW) sometime in the future. The project was developed by the Port and Harbour Research Institute, a division of the Ministry of Transport. Wave power generation system used in Sakata Port, Yamagata The Japanese Sakata OWC was implemented as part of the port infrastructure, integrated into the ports second northern breakwater as one of the reinforced concrete breakwater modules. The construction method for this caisson was similar to the Vizhinjam OWC project with the bottom section of the caisson cast first in a dry-dock. The completed base was then floated, before being completed to its final height. The caisson was then towed to its required location, lowered onto the prepared sea-bed and protected against scouring around the foot of the structure by placing rock or tetrapods. Sakata port is an industrial harbour and was able to provide all the necessary technical equipment for the implementation of this project. 3.6.2 Geometry The principal dimensions of each caisson were 20.0 m X 24.5 m X 27.0 m high, with an operating water depth of approximately 18 m. Each caisson had 5 openings on its front surface facing the predominant wave direction. Corresponding with the frontal openings, partition walls divided the internal space into 5 chambers. The front wall of the OWC caisson was inclined to 45°, designed to reduce the horizontal force and causes a vertical force downwards, stabilising the caisson. The following picture shows the OWC integrated into the northern breakwater during the construction phase. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 34 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Construction phase of Sakata caisson breakwater OWC [Graw, 1999] Sakata breakwater caisson in heavy sea [Graw, 1999] Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 35 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report 3.6.3 Design Parameters (Assumptions and working principles) The following table summarizes the principal design characteristics of this project. Geometry Wave / Sea Characteristics Total Width 20.0m No. of Chambers + Width 5 x 3m Chamber Angle Wave chamber – vert, air 45 o Lip depth below MWL 3.0m Total Height above MWL 12.5m Depth Design Wave Height Design Wave Period Return period Max design wave load Turbine Generator Turbine Dia. Nominal operating speed No. of Turbines Arrangement Blade Form Number of blades Blade Chord Hub to tip ratio 1.337m 16 18.0m 15.3m 14.5s Type Power at Generator Terminals Duty Type Rotor Type Rated Voltage Rated Speed Max test speed Inertia 60kW 200V AC . 3.6.4 Performance Information regarding the performance of this plant has not been located. 3.7 Other OWC installations The following table is a summary of other shoreline OWC devices. Location Type Rated Output Width Water Depth Operation Period Shanwei, Guangdong, China Coastal OWC 100kW 20m ? Since 2001? Dawanshan, China Coastal OWC 3kW 4m 10m Since 1990 Isle of Islay, Scotland Coastal OWC, (Islay 1) 75kW 17m 3m 1988 – 1999 Kujukuri, Japan OWC with pressure storage 30kW 10 x 2m dia. 2m Since 1987 Niigata, Japan Breakwater OWC 40kW 13m 6.5m 1986 – 1988 Toftestallen, Norway Coastline OWC 500kW 10m 70m 1985 – 1988 Sanze, Japan Coastal OWC 40kW 17m 3m 1983 – 1984 Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 36 The Carbon Trust 3.8 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Recent Developments Another form of shoreline device is the bored tube/cavern. This report has considered this technology briefly in the stage 2 evaluation based on the plans (SeWave – Wavegen) for this technology to be deployed on the Færoe Isles. Wavegen is re-focussing its attention on the OWC market and has developed new designs for nearshore deployment that it hopes to implement as a demonstrator project in the coming years. A smaller OWC power take-off system is being developed by Wavegen for deployment on breakwater projects worldwide. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 37 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report 3.9 Risk Matrix The following table summarises an assessment of the project risks encountered, or possibly to be encountered, for each device. The degree to which the identified risks affected the project outcome, or may affect projects under development, was assessed to be high, medium or low based on our observations. A comment on the risk mitigation for future projects is included in the comment column. Shore line Feasibility Energy resource assessment H L M L L L Risk reduced if initial investigation thorough Permitting L L M M L L Risk increased if large development, particularly if considering shoreline device. Costing inaccuracy M M H M L L Future designs can get contractor buy-in before committing to project Schedule inaccuracy H H M M M L Promoter to employ contractors with adequate standing that will be capable of the necessary planning Sea bed conditions H L L L L L Risk reduced if initial investigation thorough Bathymetry H L L L L L Risk reduced if initial investigation thorough Correct channel geometry M L na na na na Risk reduced if initial investigation thorough Rock integrity M M na M na na Risk reduced if initial investigation thorough Concept freeze M M H H M L Do not commit to final investment until sufficient engineering completed Material selection M M H M L L Steel structures have a shorter maintenance-free life than concrete offshore Scour / undermining L L H H M M More prevalent the closer inshore the device is placed Turbine efficiency M M M H M M Port Kembla is adopting new technology Control systems L L M M M M Significant development has taken place in this field Site Investigation Design Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC Comment Sakata India Breakwater Port Kembla Nearshore OSPREY Pico Risk Description LIMPET Stage 4 February 2005 Page 38 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report M H M M M Onshore Access to site L L H L M L Construction Component / material delivery L M L L L L Contractor skills / equipment M M H M M L Productivity Gain H H H M M M All previous designs have been bespoke with no opportunity for productivity gain through repetition. Late delivery of components M M H H H M Port Kembla schedule considered tight Errors in fit up M M H H H M Temporary works H H L L M L Will remain difficult for all shoreline devices Workforce safety H H L L M L Will remain difficult for all shoreline devices Weather down time H H L L L L Will remain difficult for all shoreline devices Adverse sea state na na H M M M Devices should be made as sea-state tolerant as possible Ballast placement na na H na M M Devices should be stable without ballast in moderate sea-states Bed preparation na na H M M M Difficult in exposed sites Skirt penetration na na na na na na Commissioning na na H M M L Shore connection na na H M L L Setting taut mooring na na na H na na Tug / barge availability na na M M M L (solid/water) Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC Comment Sakata M India Breakwater Port Kembla Peak wave load est. Offshore Installation Nearshore OSPREY Shore line Pico Risk Description LIMPET Stage Understanding of impacting wave pressures has improved over the period of development of these devices Short taut moorings are difficult to install and maintain taut. 4 February 2005 Page 39 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Operation and Maintenance na H H M L Access L L H M M L Number of moving parts M M M M M M Any moving parts must be accessible and replaceable Davits / cranes / runway beams M L H H M L Maintenance provision must be built-in from the outset Marine fouling L L H L L L Port Kembla is a temporary structure so any fouling should be less significant Fatigue L L M L L L Complex connections and multiple members undesirable on long-life devices Chamber blockage M M L L L L Only an issue on shoreline devices where rock removal may be incomplete. Integrity inspection L L H M M M Deluge of plant rooms H H M M M M Devices should be detailed to prevent this in future Cathodic protection inspection na na M M na na Not required on concrete structures unless embedded steel present below water-line \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC Comment Sakata na India Prior experience Arup Breakwater Port Kembla Nearshore OSPREY Shore line Pico Risk Description LIMPET Stage Experienced installation teams not yet established for work of this nature. 4 February 2005 Page 40 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report 3.10 Key Performance Indicators 3.10.1 Structural Quantities v Output Device Schedule Conceptual Development / Design Construction and Commissioning Principal Structural Quantity Estimated Delivered Cost (UK 2004 Prices) CAPEX expressed in p/kWh amortised over 25 years (no discounting) LIMPET 1992 – 1998 Pico 1993 – 1995 OSPREY 1994 Nov 1998 – end 2000 1386m³ (concrete) 1995 £2.2m 5.0 estimated (£1.75m reported in 1999 money) 48 actual 1400m³ £2.1m 4.2 estimated 750te (steel) £5.9m 2.2 estimated 7000te (ballast) Port Kembla 2003 Jan – Dec 2004 485te (steel) £2.6m 2.6 estimated Vizhinjam 1987 – 1989 Dec 1990 – Oct 1991 1200m³ £2.0m 198 actual £4.7m Not known (concrete) 3000te (ballast) Sakata 3.10.2 OWC Device LIMPET Complete 1989 2900m³ Wave Energy at Collector v Output Wave Energy (kW/m) at Collector Device frontage 20 estimated 21 m 12 measured Wave energy x frontage Annual Average Output Overall Average Wave-to-Wire Efficiency 420 202kW estimated 48% Estimated 252 21kW measured 8% Measured Pico 13.4 measured 12 161 57kW estimated 35% Estimated OSPREY 29.9 estimated 20 chamber up to 44 with wing walls 598 to 1200kW estimated 91% Estimated based on wing walls 1316 Port Kembla 10 35 350 114kW estimated 33% Estimated Vizhinjam 5 to 10, 20 average monsoon 10 100 average 6kW measured 6% Measured Sakata 20 Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 41 The Carbon Trust 4 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Summary of OWC technology (State-of-the-Art) 4.1 Resource Assessment [2,51] Northwest Europe is situated in the mid-latitudes, which are affected by the west-to-east passage of Atlantic depressions. The winds associated with these depressions create large waves over long fetch lengths travelling across the Atlantic Ocean into the Western coast of Europe. The offshore wave climate around the Western coast of the UK is therefore very energetic. The most exposed regions of the Western coastline have the most vigorous climate, in particular, the islands off the Western and Northern coasts of Scotland. The more sheltered East coast of the UK has, in general, low wave energy resource. When considering the development of a shoreline or near-shore device, the energy losses from offshore locations into near-shore and shoreline locations have to be determined. The main energy loss mechanisms are related to refraction and shoaling, seabed friction and wave breaking. The prediction of wave energy at offshore locations can be carried out without too much difficulty by utilising metocean hindcast models available from the UK Met Office and other commercial services. The hindcast models cover a variety of areas at differing levels of resolution. The hindcast model for UK waters has approximately a 12km grid. With the increasing sophistication of computer technology, the Met Office hindcast models have been continually improving over several years and are benchmarked against data from wave rider buoys. A large database of satellite wave and wind data is held by various companies (e.g. ARGOSS, [57]) allowing access to retrieve joint probability distributions, histograms or plot short time-series. Parameters including wind speed and direction, significant wave height, mean period and zerocrossing period and mean direction are available as well as statistics for wind-sea and swell waves. Such data is available at much lower cost than commercial hindcasting services. The Department of Trade and Industry (DTI) has commissioned a consortium led by ABP Marine Environmental Research Ltd (ABPmer) to produce the UK Marine Renewable Energy Atlas [81]. The purpose of the Atlas is to spatially map wave, tidal and offshore wind resource potential within the limits of the UK Continental Shelf (UKCS). Its use for OWC evaluation is limited as the coarseness of modelling make predictions within 12km of the shoreline less reliable. The DTI plan to use the Atlas to assist decisions on future rounds of licensing for large-scale deployment of marine renewable technologies. This work was undertaken as part of the DTI-led Strategic Environmental Assessment (SEA) combined programme covering Oil & Gas and Marine Renewable agendas. The challenge in bringing predictive data inshore is to reliably account for the seabed profile, shielding, shoaling and wave breaking at every frequency for each wave energy spectrum around the coastline to provide design data at the prospective OWC locations. A possible solution to this problem, which reduces the required computational effort, is to calculate the inshore energy for target development sites that are broadly representative of larger areas of the coast. 4.2 Modelling and Performance Prediction [9,13,29,30,32,33,34,40,41] A number of technical papers have been written over the past twenty years on the modelling and performance prediction of Oscillating Water Column (OWC) structures. During the design process, a scale model test of OWC structures is carried out in a wave tank that accurately reproduces the wave climate at the site. During these tests, the maximum calculated design loadings are verified and the performance of the device is assessed. The cost of tank testing for these structures is relatively high and thus several methods of mathematical modelling are used to minimise model testing time. Some examples of the design methods used are summarised below: Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 42 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report The calculation of the device resonant frequency can be carried out initially by simplified mathematical formulae that include the geometrical size of the opening, excitation forces, damping and stiffness. Some of the available formulae are device specific such as those integrated into a breakwater. Other formulae are more general based on calculations of semi-submerged ducts representing the OWC. When the resonant frequency and wave amplitude of the device is known, further approximations of the available power take-off can be made based upon the change in damping. More sophisticated methods, such as boundary element methods, have been used that more accurately predict the diffraction around and inside the device. Transfer functions can be derived from the surface velocity within the diffraction model that can relate to the air pressure inside the chamber. A more accurate prediction of the power available can then be made based on the site spectra encountered throughout the year. A further sub model based upon the performance of the turbine and other electrical equipment can be made that will further refine the model to give a full wave-to-wire prediction. One of the shortcomings of the boundary element method is that it is based upon linear diffraction theory and therefore cannot account for higher order viscous effects. This is particularly important in the design of the lip of the inlet to the chamber. A method used for design of the lip into the chamber is Particle Image Velocimetry (PIV) [30]. This method illuminates the water particles by use of very thin laser light and a combination of lenses. The losses around the lip can be quantified using this method. It has been found through using this method that the size, shape and inclination of the lips are of importance. Computational Fluid Dynamics (CFD) software has been used in some applications of wave energy devices. There do not appear, however, to have been any models of the entire OWC device. CFD software has the capability to model the waves, viscous effects, air pressure movement and turbine rotation. A model of this size would involve considerable computational effort and the costs would possibly become similar to tank testing. This could, however, become a more favourable option in the future as the software and computer technology improves. The theoretical maximum conversion efficiency of the OWC (wave to pneumatic) at any given period (frequency) of the incoming wave is thus determined purely by its geometry, the direction of the wave, and an optimum value of the ‘damping’ in the chamber. The damping is determined by the turbine and generator characteristics. This optimum value of damping is frequency dependent. Thus, the conversion efficiency of the OWC under operating conditions is governed by the load characteristics. Device developers have claimed average capture efficiencies of 50 to 80%. These values are examined more closely in subsequent sections of this report to assess whether there is potential to reach such capture efficiencies. 4.3 Structural Form The main requirements of the structure of an OWC is to create a chamber of air suitable for compression and rarefaction by wave action, and provide a platform and protection to the turbine / generator equipment. This structure must maintain a fixed location while exposed to an extreme and varied loading regime. The geometric properties of the OWC chambers are fairly similar from device to device. This includes a lip, inclined chamber and main air void leading to the turbine collector duct. The lip is set to a depth below mean water level to limit the occurrence of inlet broaching. This is when the water level falls below the level of the entry lip and a direct air passage is opened between the working chamber and the atmosphere (ending the loss of pressure and hence capture efficiency). The wave height at which this broaching occurs is a function of the lip penetration at still water, the state of the tide and the dynamic characteristics of the water column. The LIMPET design incorporates a restriction at the lip that restricts the outflow from the column during the down stroke Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 43 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report hence allowing the turbine to operate with an extreme low water of two to three metres below the entry lip. A curved entry lip profile helps to reduce turbulent losses at the entry. An inclined water column has two main advantages. Firstly it offers an easier path for water ingress and egress resulting in less turbulence and lower energy loss. Secondly the plane area of water rising in the column is increased. This permits the primary water column resonance (a function of the water plane area to entry area ratio) to be tuned to the predominant period of the incoming waves. The water column should be sufficiently long that water does not rise high enough to flood the rear wall, which could either over pressurise the turbine collector ductwork or rear wall. The main air chamber should allow for control of the peak turbine flow pressures. In addition, the Port Kembla project includes wing walls to focus the incoming wave energy. The true benefits of wave guides have not been fully demonstrated and would benefit from future attention. 4.4 Turbine Design and Optimisation [77,78,79,82,84,85,87 & as shown below] 4.4.1 Summary of the Current State-of-the-Art Turbine technology for use with oscillating water columns (OWCs) relies primarily on the extraction of useful work from the induced, bi-directional flow of air above the water column as it rises and falls. The majority of OWC turbine studies, both theoretical and experimental, have been to investigate the performance characteristics of variants of the Wells turbine. Work on impulse turbines has also been investigated but to a much lesser extent. Wells turbines with various blade and guide vane geometries, with and without bypass valves have been investigated and performance curves have been generated over a range of representative flows. The work has generally sought to identify the optimum configuration to overcome the inherent weaknesses of the Wells turbine in a variable flow environment, particularly at low or high stall air velocity when the turbine may actually consume power to maintain rotation. Performance is considered in terms of turbine efficiency as a function of flow rate and / or aggregated net power. The performance is significantly influenced by the blade and vane configuration and whether or not a bypass valve is used. Machines with fixed blade pitch angle generally have a narrow efficiency curve (peak efficiency over a narrow flow range) whereas machines with variable blade pitch angle maintain efficiency over a wider flow range, albeit at a lower absolute level. Aggregate net power is generally improved by using a bypass valve to vent excess air at higher air flow rates. One of the studies [38] describes a theoretical study of a complex system for control of vane and blade pitch angle in a modified wells turbine, including a predictive model for wave patterns. The study applies the model to the Pico plant and concludes that the performance gains appear relatively small. It may be questionable whether such a complex control system is of real benefit on a commercial scale machine where it could result in poor reliability and high maintenance requirements. The concept of such a control system, including wave prediction, is expected to be incorporated in the Port Kembla machine currently under construction [47]. By comparison a relatively simple control option involves the use of an automatic blow off valve where the flow rate is capped. The valve may be actuated or a simple non-return valve, the latter having the advantage of no parasitic power requirement but at the expense of not being under positive control. Alternatively a throttling device may be used in series with the turbine, such as at Pico. The civil structure for an installation with blow off valves would most likely need to be custom designed for the specific location, but this potentially offers the option of a range of standard, geometrically similar turbines with narrow efficiency curves to operate at varying levels of output power. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 44 The Carbon Trust 4.5 4.5.1 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Controls [83, 86] Treating the water Column itself as a tuned oscillator Various attempts have been made to ‘tune’ the water column to the peak energy frequency of the incoming waves under varying sea conditions. These can involve actively controlling the physical profile of the column, in order to maintain the resonant frequency at the desired value. Alternatively, active control of baffles or walls using sensors and actuators, or opening up/closing off smaller side chambers to the main water column chamber, have been considered. Allied to this, active control of the resonance wave itself within the column is important, so that its amplitude neither decays nor increases uncontrollably. Too far in one direction would reduce the energy content of the water; too far the other way might physically destroy the OWC installation. Research efforts in this area have taken place to actively control the ‘resistance’, ‘damping’ or ‘inertia’ of the ‘terminations’ within the water column. In this case, ‘terminations’ usually refer to the physical properties of the escape route for the compressed air at the top of the water column. This can refer to the turbine characteristic itself, and how this can be modified and controlled, or to other devices placed in series or in parallel with the turbine to modify the dynamic characteristics of the air/water interface. In many cases, these ‘other devices’ consist of an actively controlled valve or damper which affects the amount of compressed air flow to, or around, the turbine. Physically, this active tuning of these parasitical routes can be seen as varying the physical and dynamic properties of the OWC, and if done in a sympathetic way, achieve the desired aim of the researcher. Much of the research carried out in this area has been to compare alternative strategies for control, with a view to optimising the energy abstracted from the incoming waves. The work has been carried out for simple wave spectra, and for time-varying wave profiles. Much of this work has been done by computer simulation, some by using small-scale physical models in the laboratory, and some on small-scale trials on functioning OWCs. These have been done under particular sets of wave conditions and considerably more research is required in this area. 4.5.2 Modifying the Characteristics of the Turbine-Generator In general, researchers have settled on the use of a Wells-type (rectifying) turbine for converting kinetic and potential energy in the OWC to rotational energy suitable for driving an attached electrical generator. The characteristics of the Wells turbine show that the torque/air pressure relationship peaks at a certain value of OWC air pressure. Above this value, the turbine output torque falls and the turbine can enter a ‘stall’ phase, where energy conversion efficiency falls off rapidly. It is therefore important that the incoming wave energy profile is controlled so that the unwelcome stall condition is not reached. A number of research projects consider the benefits and drawbacks of varying the geometry of the Wells turbine blade (variable pitch system), and of running the turbine as a fixed or variable speed device, but as yet no conclusions could be drawn as further research work needs to be done. Consideration has been given to the possible sources of power for driving any regulating surfaces (control valves, dampers, blade vanes etc) of the control philosophy adopted. This work includes consideration of the electrical power inputs required by the electrical rectifier/inverter (converter) system required to maintain the electrical power from the turbine generator train at a constant frequency, given that the turbine/generator may run at a different, and time varying frequency itself. 4.5.3 Machine Technology Current projects use both synchronous and induction generators, generally with electronic control of speed. The review of existing projects and associated studies makes little mention of doubly-fed induction generators (DFIGs), since they largely predate the more recent popularity of such machines used in the wind power industry, however these modern drive systems are very similar to the well Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 45 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report established Kramer drive systems which have been used in OWC applications. It should be noted that whether the design is considered as a single system optimisation problem or a series of smaller subsystems to be optimised, each sub-system’s design and performance is dependent on the others. 4.5.4 Control Systems The control of the machine itself is largely a feature of the machine design, rather than the prime mover. In many of the prototype OWCs a traditional slip energy recovery or Kramer drive, has been used. Modern DFIG drives are essentially the same concept, but with increasingly more complex control strategies. 4.6 Power Conversion Efficiency It is clear from the wealth of papers and project reports published on the subject of the OWC and its associated air turbines that overall efficiency is still somewhat of an unknown quantity. Developers have embarked upon prototype installations with high expectations, hoping to achieve wave-to-wire efficiencies of 70-80%, only to find after months or years of operation that the best that can be achieved is more like half this figure. As described in the research papers on the subject of the OWC, the matching of the wave frequencies to that of the resonant frequency of the water column is key to the efficiency of energy conversion. Interactions within the chamber can also have a considerable impact. Efficiency figures for the OWC independent of the turbine were not available from the papers reviewed. So far it doesn’t appear that much of the state of the art R&D from the universities laboratories has been successfully implemented in the prototype installations. Implementation of the best automatic control schemes could also have considerable impact on the efficiencies currently being achieved in prototypes. As described in the survey of the turbine design papers, there are currently a number of different designs of air turbine being used with the OWC. Peak efficiencies of 70-80% for the turbine are theoretically possible but only at specific air velocities. Practical prototype installations are giving much lower average efficiencies due to the variation in air velocity, due to the variation in wave conditions. Electrical induction machines normally operate at around full load with typical efficiencies of around 98%+, however some prototype OWC installations report efficiencies of as low as 50% and similar stories apply to inverter efficiencies. Such reports do not seem to be credible, average electrical efficiencies of 90%+ should be easily achievable even with a variable load. Correct sizing of the equipment and the use of modern commercial designs should resolve these issues. 4.7 Maintenance and Reliability The OWC and its associated air turbine either Wells, Impulse or variations of these types form the OWC based WEC. This WEC system has been under development for some thirty or so years in several countries. Despite many years of R&D the technology is still very much at the early stages of development. A number of prototype projects have been successfully operated around the world, however these have so far been largely run very much as R&D projects managed by academics with limited funding. The technologies and designs are many and varied, characteristics that are unlikely to be taken into the commercial exploitation stage. In contrast to this, many small-scale navigational buoy OWCs have operated successfully over many years and proven to be low-maintenance facilities. The current prototype projects have suffered from maintenance problems and plant failures however this should not be an indication that the commercial installations will be the same. Clearly the marine environment creates its own problems however these issues are all resolvable, given the time and money to design and develop the technology. Most of the issues have been faced before in the offshore and marine industries so it should be largely a case of transferring existing technologies. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 46 The Carbon Trust 5 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Market Size 5.1 Assessment Method The ‘market’ in this report is taken to be the amount of power generation that can realistically be generated using OWC technology. An assessment method has been developed to evaluate the market size. As part of this exercise areas around the UK were ranked in terms of their potential for construction and operation of a shoreline or near-shore OWC. The proposed method will not match that produced by other authors [73] and the market size should always be considered as an indicative figure given the judgements made by various authors in arriving at market size estimates. The factors considered in the ranking exercise were: • Wave Energy resource • The average sea-bed slope • Tidal range • Grid capacity • Cost of local construction or ease of transportation of units built off-site • Overall capital cost of shoreline and near-shore devices The rankings were used to prepare an evaluation matrix that would show both the best areas to develop and the potential resource from each location. A range of 0 to 4 being worst to best respectively was used for each ranked variable. Factors were derived for each ranked variable to allow different importance to be ascribed to each aspect of the overall cost and suitability of OWC deployment. These importance factors are necessarily somewhat subjective since they could only be otherwise established by extensive technical and economic modelling. Since the main aim was to rank areas and then assess resource, it was considered to be a reasonable method. 5.2 UK Wave Energy Resource 5.2.1 Distribution Figure 5.1 shows the available offshore wave energy resource for UK waters. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 47 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Figure 5.1 UK Offshore Wave Energy Resource (kW/m) (source: Dti Marine Atlas) It can be seen from Figure 5.1 that the wave energy along the Western coast of the UK is high. This is due to the long fetch of the Atlantic. The wave energy around the West coast of the UK is perhaps the highest in the world. It can also be seen, however, that the available power levels are significantly less for the East coast of the UK. 5.2.2 Variation / range Figure 5.2 shows an estimate of the available near-shore wave energy around the coastline compiled from [2] and other data. The energy levels reported are predominantly in the West coast of the UK where the resource is highest. Near-shore values appear to be somewhat higher than the Atlas of UK Marine Renewable Energy Resources [81] would suggest. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 48 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Figure 5.2 Near-shore Average Wave Energy Resource (at 20m contour in kW/m) 38 46 32 28 42 19 31 35 37 26 40 13 24 9 7 33 44 48 20 22 40 36 22 25 9 21 34 23 1 36 1 21 4 43 3 17 2 15 40 26 31 8 15 2 3 9 7 11 13 29 15 14 39 29 22 26 14 35 35 32 34 24 49 28 6 6 6.5 12 10 5 Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 49 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report 5.2.3 Ranking method It can be seen from Figure 5.2, that the near-shore wave energy available around the coast varies from 0-50 kW/m. The ranking of each area is as follows: Power <5kW/h 0 Power 5-10kW/h 1 Power 10-15kW/h 2 Power 15-25kW/h 3 Power >25kW/h 4 A colour plot of the wave energy ranking is shown in Figure 5.3. A weighting factor of 2 was applied to the wave energy ranking. The contour plot is to be used to rank large areas of coastline as part of the overall ranking process and not as a definitive assessment of the wave energy at any specific location. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 50 The Carbon Trust Figure 5.3 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Wave Energy Ranking at 20m Contour Colour Plot United Kingdom Wave Energy Ranking Energy <5 kW/m Energy 5-10 kW/m Energy 10-15 kW/m Energy 15-25 kW/m Energy >25 kW/m Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 51 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report 5.3 Sea Bed Profile 5.3.1 Method of review The seabed profile has a significant effect on the available energy at inshore locations. A shallow sloping seabed is more likely to create more energy loss mechanisms such as seabed friction and wave breaking than a steep sloped seabed. An approximation has been made into the seabed slope around the UK and is shown in Figure 5.4. The assessment of the seabed slope has been made using a combination of previously published literature and admiralty charts. Although the assessment is relatively simplistic, it serves as a reasonable indicator of seabed slope ranking for the purposes of this study. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 52 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Figure 5.4 Seabed Slope United Kingdom Seabed Slope Approximation Slope 1:96 Slope 1:107 Slope 1:36 Slope 1:120 Slope 1:267 Slope 1:150 Slope 1:0.025 Slope 1:0.05 Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC Slope 1:500-800 4 February 2005 Page 53 The Carbon Trust 5.3.2 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Ranking As discussed in section 5.2.1, a steeper seabed slope results less energy losses between the offshore and near-shore / shoreline locations. The ranking of the seabed slope is therefore: Slope 1:500+ 0 Slope 1:100-500 1 Slope 1:50-100 2 Slope 1:1-50 3 Slope 1:0-1 4 Figure 5.5 shows a contour plot of the seabed slope ranking. A weighting factor of 0.5 has been used to allow for the assessed importance of sea-bed slope. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 54 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Figure 5.5 Seabed Slope Ranking United Kingdom Seabed Slope Ranking Slope 1:500+ Slope 1:100-500 Slope 1:50-100 Slope 1:1-50 Slope 1:0-1 Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 55 The Carbon Trust 5.4 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Tidal Range The tidal range around the UK varies considerably from almost zero to over 14m, one of the highest tidal ranges anywhere in the world. Figure 5.6 shows the spring tidal contours around the UK. Figure 5.6 Note; Spring Tidal Amplitude around UK (Source: HSE) Spring tidal amplitude is half the spring tidal range Contours are in metres To obtain the approximate highest and lowest astronomical tides (HAT and LAT respectively) from Figure 5.6, the conversion factors shown in Table 5.1 should be used in conjunction with the following formulae. + T = Level of HAT relative to MSL Spring tidal amplitude T- = Level of LAT relative to MSL Spring tidal Amplitude Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 56 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Table 5.1 HAT / LAT Conversion Factors 5.4.1 Ranking Figure 5.6 can be used for approximate ranking of areas around the coastline. Further more specific data would be required for the actual chosen sites as tidal range can vary significantly over small localised areas. In general, the tuning of oscillating water columns is more complicated when the device is situated in an area with a large tidal range. This is due to the changing natural frequency of the chamber and the requirement to alter the damping of the system. The ranking of the area with respect to tide is therefore: Range >6m 0 Range 4-6m 1 Range 2-4m 2 Range 1-2m 3 Range 0-1m 4 Figure 5.7 shows a colour plot of the tide range ranking around the coastline. A weighting factor was devised for the effects of tidal range on overall cost. This was based on the assessment that capital cost would be proportional to the maximum design water depth squared. An average water depth of 12m was assumed. Thus the factor became: 2 2 Depth /(Depth + tidal amplitude) Smoothing the numbers resulted in the following: Tidal Factor Rank 0.3 0 0.5 1 0.7 2 0.85 3 1.0 4 The tidal factor is used as a multiplier on the overall weighting. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 57 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Figure 5.7 Figure 5.7 Tide Range Ranking Tide Range Ranking Tide Range Ranking Range >6m Range 4-6m Range 2-4m Range 1-2m Range 0-1m Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 58 The Carbon Trust 5.5 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Grid Accessibility Although the smallest wave power installations can expect to connect at 33 kV or even 11 kV, the vast majority of commercial-scale projects will require a connection at or close to a 132 kV substation. New 132 kV substations are possible, but add considerably to the price, so the distance to the nearest existing substation has been taken as an indicator of the accessibility of the grid from any location. 5.5.1 Ranking A rank was assigned to each location based on distance as follows: Distance Rank Up to 10 km: 4 11 – 30 km: 3 31 – 50 km: 2 51 km or more: 1 A point was deducted if the connection was insecure; that is, if it relied on a single 132 kV circuit, or if the 132 kV system was known to be already utilised to capacity with existing generators. Similarly a point was deducted if the connection required a substantial sea crossing, since this is considerably more expensive than a land connection. This applied to islands such as Arran or Mull, which currently have no 132 kV infrastructure. The Isle of Man has a 90 kV interconnector to the mainland. The terminal of this interconnector, near Douglas, was taken as the nearest 132 kV substation for the purpose of the study. 5.5.2 Results Figure 5.8 shows the approximate distances for various stretches of coastline. In the case of islands, no distinction has been made between exposed and sheltered coasts (i.e. facing the sea or the mainland), but a distance from the approximate centre of the island, or an average around the whole coast, has been used. Figure 5.9 shows the rankings on a map of the coast. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 59 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Figure 5.8 Connection distance and ranking Typical / Average Distance (km) Secure Connection Sea Crossing Required Ranking: 8 Yes No 4 10 Yes No 4 10 Yes No 4 10 Yes No 4 10 Yes No 4 12 Yes No 3 15 Yes No 3 15 Yes No 3 15 15 Yes No No No 3 2 18 Yes No 3 20 Yes No 3 20 Yes No 3 20 20 Yes No No No 3 2 25 25 25 Yes No No No No No 3 2 2 30 35 No No No Yes 2 0 Isle of Lewis and North Harris North Uist North of Scotland Islay, Jura Colonsay Benbecula South Uist Orkney Islands Mull Tiree Coll 40 45 50 50 50 50 50 60 60 100 100 No No No No No No No Yes No Yes Yes No Yes No Yes Yes Yes Yes Yes Yes Yes Yes 1 0 1 0 0 0 0 0 0 0 0 Shetland Islands 240 Yes Yes 0 Area Stranraer Lancaster Hastings Felixstowe Weymouth Portsmouth Portsmouth Hastings Inner Bristol Channel Lancaster Birkenhead North East of Scotland South Cornwall / Devon Outer Bristol Channel Kintyre North Cornwall / Devon Felixstowe Cromer St Davids Head Outer Bristol Channel North / West Wales Isle of Skye Bridlington Montrose Cromer-Bridlington Isle of Man Cardigan - St Davids Head The Small Isles Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 60 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Figure 5.9 Coastal Grid Accessibility Ranking Great Britain Grid Accessibility Ranking Rank 0: Insecure/Submarine Connection > 50 km Rank 1:Secure Connection > 50 km (or insecure/submarine 31–50 km) Rank 2: Secure Connection 31–50 km (or insecure/submarine 11–30 km) Rank 3: Secure Connection 11–30 km (or insecure/submarine < 10 km) Rank 4: Secure Connection < 10 km Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 61 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report 5.6 Local Construction Factor 5.6.1 Shoreline Construction A local construction factor has been ascribed to each location to reflect the ease of supplying labour, plant and materials to the site of the OWC construction. Relative construction cost factors were selected based on concrete gravity substructure cost estimates previously prepared for NE England, Nigg Bay in Ross-shire and Loch Kishorn in the Western Highlands. The factor reflects the fact that construction in remote regions is more costly due to transport premiums on materials and plant and the additional costs of acquiring labour. The cost factor is multiplied by the site weighting. Cost Factor Rank 0.7 0 0.8 1 0.9 2 0.95 3 1.0 4 5.6.2 Near-shore Construction A construction cost factor was selected based on the distance a unit might be transported from an offsite construction facility to the final installation site. The factor has been based on an assumption that locations that have previously been used for the construction of steel or concrete gravity platforms would be candidate locations for building OWCs. Once again, the cost factor is multiplied by the weighting. Cost Factor Rank 0.8 0 0.85 1 0.9 2 0.95 3 1.0 4 5.7 Relative Economics of Near-shore versus Shoreline Construction The cost of an offshore concrete gravity substructure constructed in a developed country is often considered to comprise 1/3 labour, 1/3 plant and 1/3 materials. At this stage of assessment, it has been assumed that shoreline and near-shore OWCs might require the same amount of materials per kW of power captured. Onshore OWCs have had extended construction schedules thus far so a relative labour productivity of 1.5:1 between shoreline and nearshore construction (off-site) is considered reasonable. Plant demands for temporary works and actual construction are assessed to be in the ratio 1.25:1 between shoreline and near-shore. This results in a relative weighting of: (1.5/3 + 1.25/3 + 1/3) : (1/3 + 1/3 + 1/3) or 1.25:1 in the overall efficiency of shoreline compared to near-shore construction. Near-shore weightings of 1.25 are thus applied. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 62 The Carbon Trust 5.8 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Ranking Matrix, Combination and Weighting The aim of the ranking assessment in Section 6 of this report has been to gain a broad outline of the areas around the UK coastline where the conditions for installing a wave energy device would be most favourable. The assessment has aimed at general large areas of coast where the focus of further refined study should be undertaken. The totals in the ranking table are derived as below: (Seabed Rank *0.5 + Wave Rank *2 + Grid Accessibility Rank *0.5) * Tide Factor * Construction Location Factor * Near-shore or Shoreline Factor A summary of the ranking matrix is shown in Figure 5.10 for near-shore, Figure 5.11 for shoreline and Figure 5.10 for the combined rankings. The latter figure shows that the highest ranked shoreline th location lies in 12 place. This shows a clear conclusion that near-shore OWC development should be considered ahead of shoreline when aiming to maximise the resource that can be developed. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 63 The Carbon Trust Figure 5.10 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Near-shore Ranking Matrix Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 64 The Carbon Trust Figure 5.11 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Shoreline Ranking Matrix Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 65 The Carbon Trust Figure 5.12 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Composite Ranking Matrix Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 66 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report 5.9 Potential Resource 5.9.1 Shoreline An assessment has been made of the suitability of the UK coastline for shoreline OWC deployment. The coastline of the UK was examined on Admiralty charts to assess areas where water depths of at least 10m were present close to shore. These areas were then examined in relation to topography to assess which areas of coastline could be considered for construction. Generally, coastline with cliffs or scarps was targeted and a height limit of around 20m considered the limit of practical construction. Actual access was not considered in the selection process and the actual water depths shoreline have not been verified. A percentage of the available coastline was assessed for all regions of the UK in this way. It was further considered that considerations such as measured water depths, environmental suitability, loss of amenity, ease of maintenance and so forth might reduce the prospective sites to 1/10 of the possible maximum. Furthermore, only the top twelve ranked locations were considered that had shoreline possibilities. This resulted in 8.8km of coastline as being the maximum that could be considered for development of shoreline devices. If the average shoreline wave energy resource were 15kW/m at the lip, and an overall wave-to-wire efficiency of 20% could be realised, this would yield 230GWh of power per annum, or enough power for 58,000 households. This is somewhat lower than has previously been forecast by ETSU who reported that 400GWh might be realisable [ 73 ]. 5.9.1.1 Shoreline Resource Example An example is given for Islay, adjacent to the LIMPET site: Cliffs < 20m high Fig 5.13 Ordnance Survey Map of Islay near LIMPET site (shown as crimson spot) This shows that, of the 100km available coastline on Islay and the adjacent Isle of Jura, only around 7km has access to the sea in cliff areas that are less than about 20m high. This area lies near the LIMPET site as shown in Figure 5.13 above. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 67 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Deepwater Near-shore Fig 5.14 Part of Admiralty Chart 2168 covering Islay © Crown Copyright The Admiralty Chart shows areas where acceptable, deep water appears to exist at the shoreline. The area around The Oa has cliffs too high and the area on the SE side of the Rhinns of Islay does not face the wave resource. Combining siting factors with the presence of deep water at the shore might leave around 700m of the Islay coastline, or 1/10 of that practicable, as being suitable for shoreline OWC deployment. 5.9.2 Near-shore A similar process has been followed for near-shore devices. Here the proportion of coastline with reasonable opportunity to deploy near-shore OWCs was assessed. Steeply shelving areas at the base of cliffs were avoided. Then an assessment of direct conflicts with OWC deployment was made including port access, conurbations or conflicting amenity use and the coastline proportion accordingly reduced. It was then further considered that 20% of the available coastline might be a practical upper limit for deployment before environmental effects such as coastline shielding or current blockage became too significant. This reflects the greater degree of flexibility afforded by a larger choice of development locations. The land use, construction access and coastal geometry constraints experienced on shoreline devices are not present. Furthermore, only the top twelve ranked locations that had near-shore potential were included in the total. This resulted in 141km of coastline as having potential for development of near-shore devices. If the average near-shore wave energy resource were 25kW/m (at the 20m contour), and an overall wave-to-wire efficiency of 25% could be realised, this would yield 7.8 TWh of power per annum, or enough power for 1.8m households. This is somewhat higher than has previously been forecast by ETSU who reported that 2.1TWh might be realisable [ 73 ]. 5.10 Existing Structures The integration of wave energy devices has been carried out successfully in a few locations around the world. A review of the major ports around the UK in areas of significant wave energy resource was carried out. It was found that there were very few breakwater locations that were in the normal OWC Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 68 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report operating depth and tidal range. It may be possible that a device could be fitted at a small number of locations although the supply of a significant proportion of grid energy through integration into existing structures is unlikely. 5.11 Conclusions A sizeable market has been identified for OWC deployment based on near-shore application. All the prospective sites, with the exception of North Cornwall and the North of Scotland, are remote from both population centres and grid infrastructure. However, the potential market is of sufficient size for commercial scale developments to be considered. Such development might help to overcome the current grid access difficulties faced by the more remote locations. The market for shoreline devices is much more limited and is more likely to be realised as a power supply to remote communities, as is the case at Islay. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 69 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report 5 4 4 3 4 3 3 3 3 4 1 3 1 1 1 3 3 33 3 3 4 4 2 4 3 3 4 3 1 0 3 0 0 1 0 0 2 2 1 1 4 0 2 3 2 1 2 0 Seabed Slope Ranking 0 2 2 2 2 2 1 0 2 2 0 0 2 1 2 0 1 1 3 3 4 1 2 4 4 1 3 3 33 3 3 3 2 2 4 1 1 0 4 1 1 1 Wave Energy Ranking Tidal Range Ranking 0 1 2 3 4 Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 70 2 The Carbon Trust 6 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Generic Base Case Elements 6.1 Existing device similarities Most of the existing OWCs have used a structural form bespoke to the specific location of the project. Concrete has been the material of choice for the completed projects. Generally, smaller designers and contractors have been involved in the project realisation and the overall skill required in the project execution has been relatively low. This may have been the best approach for these small projects as the overheads associated with major contractors could probably not have been borne by the developer. Previous OWC projects have demonstrated that the site preparation and civil construction cost is approximately 70% of the completed project, and can contribute approximately the same percentage to the on site programme. Clearly, there is a desire to develop a structural system that would be suitable for a wide range of locations, that could be mass-produced and that would demand less of the total project cost and programme resource. This can be more readily achieved near-shore than shoreline. All devices with collector chambers above a certain size have sub-divisions in the chamber to reduce the risk of transverse wave excitation reducing the energy capture performance. All devices, apart from the Port Kembla device, use the established Wells’ turbine technology. Most have found that the generator originally specified has been too large thus reducing the power-train efficiency under the lower than expected wave climate. Most have, or plan to, re-configure the power train to improve efficiency. This will have the largest effect on the power losses being experienced at low load. Most devices were not well configured to deal with the wide fluctuations of power output to be expected between calm and storm conditions. While much research effort has been expended upon the design and efficiencies of the mechanical and control equipment, there appears to have been less of a focus on the marine and civil aspects of OWC facilities. It has also been the wish of many developers to incorporate the structural part of the device into a breakwater or other structure (e.g. wind turbine foundation) in order to offset a portion of the project CAPEX. While valid for countries that are developing their infrastructure (e.g. India), the opportunity in the UK for incorporation into breakwater new build is very limited. The only real potential would be to add a device in front of an existing breakwater, as at Trivandrum. Such a device would have more in keeping with a near-shore device, however. The OWC technology can readily provide a foundation for an offshore wind turbine thereby improving the energy capture density and economics of any development. However, OWC technology is not mature enough for major incorporation in the current licence rounds of UK offshore wind development. 6.2 Existing device differences Of the operational devices, the major difference has been in the inclination of the OWC chamber. An inclined column offers an easier path for water ingress and egress resulting in less turbulence and lower energy loss. This is particularly true at the shallow water shoreline devices where the horizontal component of wave motion begins to dominate compared to the vertical motion. This is most pronounced at Islay. The OSPREY and Port Kembla devices have chosen steel and are relatively light-weight construction. Their lack of weight has been compensated for by ballast and tethering respectively. Both have kept the structural quantities to a minimum by utilising wave focusing devices. Steel solutions have most potential where stability can be readily assured, such as through piling. Concrete operates best as a gravity structure. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 71 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report The estimated, or achieved, wave-to-wire efficiencies vary widely. Measured efficiencies have been less than 10% whereas estimated efficiencies exceed 30%. 6.3 Focus Areas for Stage 2 Evaluation 6.3.1 Generic design The market assessment has identified that the greatest potential lies with near-shore devices. The highest ranked locations all have relatively low tidal range and substantial incident wave power so these factors should be targeted when seeking scope for improvement. The task in the second stage was to identify the most promising design configuration. There was a need to optimise the design for water depth, distance from shore, wave height and structure loading. This would lead to the selection of a generic design for which improvements could be sought. Inherent in this development would be a choice of location: shoreline or near-shore. The second stage work placed less emphasis on shoreline devices and integration opportunities because of their more limited applicability and repeatability. 6.3.2 Plant optimisation The following aspects arising from the state-of-the-art review of the mechanical plant were to be assessed during the second stage evaluation: • evaluation of asymmetric inward and outward air flow and associated optimisation of turbine geometry; • development of a range of standard, geometrically similar turbines of high efficiency for use in associated custom built civil structures incorporating one or more bypass valves; • wider investigation of alternative turbine types, for example the impulse turbine. Improvements were to be assessed against the operational performance of existing plant and other examples of plant in comparable service conditions. The issues examined were to include: • Reliability • Robustness of design • Materials issues - hostile environment • Performance under real conditions • Maintenance (including access, frequency) Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 72 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Scope for Improvement & Future Vision Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 73 The Carbon Trust 7 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Choice of device type and structure There are three classes of fixed OWC device; shoreline, near shore and breakwater. While many of the elements, and as such sources of improvement, are the same for each (particularly in relation to the balance of plant), there are significant differences in relation to the structural form and potential market size for these devices. The initial decision in relation to the scope for improvement of this technology is the choice of generic OWC device. 7.1 Shoreline OWC Devices The majority of UK and European operational experience of fixed OWC plant is with ‘shoreline’ devices, i.e. with the structure built into a coastal cliff or gully. An efficiently designed, well planned and constructed shoreline device should be capable of producing power at a competitive price for power from a renewable source. However, actual projects have reported considerable cost and programme overruns relating to the civil construction element of the projects. The main challenges faced by the developer include: • Resource assessment • Site specific design • Site preparation and rock removal • Site access and material supply • Specialised construction skills and equipment required • Temporary works and risk of water ingress • Weather dependant construction, prediction and planning Experience to date, and possible improvements to eliminate or reduce the risk of occurrence of such problems are discussed in more detail in this section. 7.1.1 7.1.1.1 Resource Assessment Challenges Accurate resource assessment has been difficult to achieve close to shore due to the greater departure from linear wave theory leading to less certain numerical modelling, and a number of factors such as bed friction losses and local shoaling effects. These can lead to an inefficient design with the device pneumatic and turbine performance not matching the chosen generator. In these circumstances the machine losses incur a higher percentage reduction to the actual output than originally estimated. 7.1.1.2 Improvements At present, inshore data in the public domain is available from an early study carried this out using forward and back tracking wave ray models that considered the refraction and shoaling and used the Bretschneider and Reid spectrum to model seabed friction [2]. The forward and back tracking ray method is the most commonly available method for calculating inshore conditions. More recently, though, a more sophisticated spectral transformation model known as SWAN has been developed that can be set up to predict inshore conditions to a 100m grid. The model can be set up to account for depth induced breaking, seabed friction, tidal range and wind induced wave rise inshore. The SWAN method involves substantial computational effort and accurate grid bathymetry. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 74 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Further advances in wave prediction have been made involving the use of satellites that can measure the instantaneous wave heights. The most recent advances in this field involve the use of microwave radar on the satellites that can predict wave energy spectra at specific points. It is unlikely, however, that all the latest technological advances in wave prediction will result in significantly different wave energy levels from earlier studies such that it would affect the wave energy device location focus. However, at a project level the accurate prediction of wave resource without extensive wave-rider buoy deployment remains difficult. The problems are exacerbated the closer the OWC is to the shoreline as the influence of local bathymetry and coastline is magnified. Large area bathymetric surveys of shallow seas are also now available using satellite imagery to map the depth. Radar images routinely acquired by satellites since 1991 have allowed production of charts using only a fraction of the sounding data normally needed. This saves money when a large area needs to be charted in shelf and coastal seas where depths are less than about 30 m. Whilst these improvements in data mapping can aid initial assessments, additional site specific studies would still be required. This could include tank testing of the near-shore bathymetry in conjunction with the OWC. However, this can be costly and as much of the initial scheme design as possible should be completed with the satellite imagery techniques. Developers should have an appreciation of importance of the survey data required at the project conception, and include sufficient budget and programme allowance from the outset. 7.1.2 7.1.2.1 Site specific design and preparation Challenges Due to the nature of the shore line, each cove, gully, and cliff face location will be slightly different from location to location. This will include: • Rock type and formation affecting strength, method of removal and OWC structural geometry. • Local bathymetry, affecting the modification of the incoming wave resource. • Access road / infrastructure requirements differ from site to site. • Proposed development site land use, cost, and planning requirements may vary. The energy output of an installation is proportional to the length of coastine used by the installation. As fewer large sites are available, and a greater number of small sites are available, the specific market for OWCs is restricted by the OWC site. A multiple location development does not gain the benefit of economies of scale due to site specific re-design and resource analysis required, multilocation construction costs, plus the additional grid connection costs. 7.1.2.2 Costs As such it becomes very difficult to produce a generic design suitable for many locations. Therefore each location will attract a site-specific design cost. This cost would include: • Survey costs, approx. £75k per device location • Re-calculation of wave resource losses, including tank testing costs, approx. £60k per device location • Re-design of civil structure for adaptation to site-specific geometry and rock interface, approx. £40k per device location • Design and establishment of site-specific access, approx. £100k per device location • Planning approval • Additional costs for multi-location working. (E.g. plant required at each location.) Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 75 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report 7.1.2.3 Improvements The possible improvements will depend upon the size of the proposed development. • Only develop large continuous coastal frontages • Limit the site-specific variables such that each location is prepared (excavated and dredged) to be near identical 7.1.3 Construction techniques Shoreline devices all require tailoring of the local water line / coast interface and the immediate seabed approach; however several different shoreline concepts exist with differing associated construction methods. 1. In-situ construction behind a rock bund or cofferdam (e.g. LIMPET). 2. A roof-only OWC using pre-cast elements fixed to a rail bolted into an excavated / profiled rock face. 3. An OWC tunnelled into a cliff face. 7.1.3.1 Challenges Each construction method has particular challenges plus the generic problems associated with exposed or remote coastal construction sites. In situ construction The decision to construct a device in an excavation behind a rock bund has several impacts on the device situation. Firstly it pushes the collector back from the original coastline. This arrangement has been shown to be detrimental in shallow water. Secondly, it requires a specific coastal bluff / cliff height to provide sufficient protection to the construction site. This limits the number of suitable site locations. Final bund rock removal has proven to be less straightforward than anticipated, with loose rock scattered in front of the collector and deposited by wave action into the chamber itself that had to be cleared in a separate work programme. Protection of the construction site with temporary works would also be problematic as by the very nature of the project the wave loading would be fairly extreme. As with the permanent works, the temporary structure design would be site-specific offering limited repeat construction savings. It would be costly to provide a wide frontage and difficult to install, particularly if a more traditional sheet pile coffer dam was used. Final removal and other access problems would also increase the cost of this type of construction. Roof-only OWC A roof-only OWC concept has been devised by Wavegen that utilizes the natural cliff face as the bottom element of the chamber with pre-cast elements for the chamber roof fixed to a rail bolted to the excavated rock face. A roof-only OWC concept requires extensive in-situ rock shaping with specific requirements in relation to access, geometry and geological properties. Given these requirements, the potential resource that can be realised from shoreline OWCs will most likely be unaffected by this development. The majority of construction would be required to be completed in favourable weather windows, and as such programme contingency and risk would need to be considered. In addition, construction and finishing below the water line would attract a cost premium. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 76 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Cliff face tunnel OWC Some of the difficulties associated with exposed working at the shoreline can be avoided by using tunnelling techniques to form the OWC collector and plant space within a cliff. The OWC collector exits below the water line as the tunnel is broken through to the sea. The tunnel OWC is less visually intrusive so may prove more acceptable to the public. This method is resource constrained in a similar manner to shoreline devices, needing deep competent rock and an exit to deep water direct from the cliff. Such conditions may be relatively common on parts of the Shetland and Orkney Isles, but are less common elsewhere. A project on the Færoe Isles is currently at the development stage. Wavegen has formed a joint venture with local utility company to undertake this project. It is beyond the scope of this study to evaluate the general economic applicability of the tunnelling approach. This could be done and would need to consider typical geologies and available specialist tunnelling equipment. Wavegen report that power costs in the range 9-15p/kWh are expected in the Færoe Isles. This would appear to be somewhat better than the economics of shoreline demonstration projects. Generic The majority of the preferable OWC development sites are in fairly remote and exposed sites. For in situ constructed projects this presents a number of problems: • Labour and equipment may need to be specially mobilised due to lack of indigenous resources • Guaranteed material supply may involve establishing a dedicated batching plant • Summer working period only 7.1.3.2 Costs The nature of the in situ work in exposed or remote locations either attracts a premium on to standard working methods, or requires specialist activities (such as below-water working) or requires extensive additional temporary works: • Temporary works cost and design • Specialist equipment and skilled contractors working at a premium compared with less remote sites • Labour and accommodation premium 7.1.3.3 Improvements The lessons learnt by the developer on LIMPET have identified several areas for improvement: • The use of pre-cast elements for the chamber roof reduced in-situ construction time, reducing the programme and temporary works and hence the associated weather risk. • The extension of the rock bund provided additional protection to the work site. A more robust and higher extension would have meant construction activities could have continued on a greater number of days and would have limited the amount of re-work and repair required to the formwork. • Flexible working methods, resource allocation and programme would have allowed construction to match weather windows but possibly with an associated higher labour cost. A near shore device prefabricated in a dry dock would again be a significant improvement mitigating many of the problems associated with an in-situ construction technique. • Limited or low cost site preparation required. • No requirement for local land take or access during construction Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 77 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report • Temporary works costs are shared over several devices • Limited underwater working that is non programme critical • Locally available skilled construction labour and equipment at lower cost. • Year round working 7.1.4 Weather and programme risk The nature of shoreline sites means that they are exposed to storm and extreme wave conditions particularly in the winter months. This means that the construction programme is best tailored to match the summer months. Appendix B shows the programme for the LIMPET project [56] plus a generic programme if all the improvements outlined in chapter 6 were implemented. It can be seen that it would be difficult to complete all activities within the summer working window even for the improved schedule, automatically extending the overall programme by four months. 7.1.4.1 Challenges • Constraining the on site construction to be completed within the summer construction window. • Planning construction activities to be flexible such that storms and unpredictable weather can be accommodated. 7.1.4.2 Costs • Storm damage rework and repair impacts the planned programme. Contingency and flexibility to mitigate such problems has an overall project cost. Additional cost of standby equipment, a flexible but inefficient programme and extended working hours could add approximately 10 to 15% onto standard construction rates • Programme extension, demobilisation and re-mobilisation in the spring also would have a cost impact. See the programme and cost model included in Appendix B. • Costs for meteorological and metocean forecasting need to be included in the project cost build up. 7.1.4.3 Improvements • Construction could be broken into short-duration tasks completed within weather windows, with the non-weather-dependant activities saved for storm periods. • It should be noted that while a near shore device would be sensitive to weather conditions during installation, all other activities could be completed within the shelter of the dry dock making the construction programme more flexible than shoreline in situ construction. 7.1.5 Contractual risks The development of OWC projects is still in its early stages. A pool of experienced developers, designers and contractors is not available. Considerable risks are thus present throughout the project development stage. Proper engineering and planning can mitigate some of these risks, but it is likely that new entrants will not understand all the risks to which they will be subjected. It is a common requirement of financial institutions that they require contracts to be placed on a lump sum design and build basis on the assumption, commonly misplaced, that this gives greater certainty in project financing. However, given the immature market, if risk is passed from the developer to the contractor this will typically result in the contractor either underestimating the scope of the works, or the contractor making extensive provision within his pricing to cover the unknown. The former can lead developers to believe that developments will be more economically attractive; the later can lead to overly costly OWCs. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 78 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report An example of the differences that might arise from the two approaches was given by Wavegen, who stated that a turnkey design and build estimate for an OWC was twice the sum of individual subcontract prices. Part of the difference relates to main contractor overheads and management, but the remainder probably can be apportioned to risk. Costings presented for future visions in later sections of this report have been based on risk levels that have been mitigated as far as is currently considered practicable given the current state of OWC development. 7.2 Near-Shore OWC Devices The UK experience of near shore structures to date has not been favourable. The OSPREY (Ocean Swell Powered Renewable Energy) was designed to operate in a water depth up to 15m and up to 1km offshore. It was constructed in 1995 to be installed 100m off the coast at Dounreay in the North of Scotland. During the installation of the 750 tonne structure, a large wave smashed open the ballast tanks and the device had to be abandoned. This experience however should not prejudice any future use of near shore structures. The Port Kembla project plans to demonstrate that viable near-shore devices can be deployed. The team hope that the successful deployment of this device will generate substantial learning that will allow future designs to be much more economic. The team has opted for offsite construction, utilising a low-cost fabrication location, Indonesia. This is an important factor in the economics of the device. The construction methods, technology and skills required to successfully install near-shore structures are readily available and have been successfully proven in developing countries, as witnessed by the Trivandrum OWC, India. Hence the ability to construct offsite and a critical appraisal of the best materials for a particular site should be carried forward into the future vision for OWCs. 7.2.1 Advantages Many of the inherent limitations of ‘shoreline’ OWC devices are eased by placing them in a ‘nearshore’ location. These include: 7.2.1.1 Generic design / Mass production The use of a dry dock or fabrication yard as a facility for the construction of the near-shore devices negates any requirement for in-situ temporary works. This provides a more secure safer working environment, offering increased levels of productivity. While the use of the dock or fabrication site itself could prove costly, once spread across a multiple device development the overall cost becomes more acceptable. This is demonstrated in the cost estimates to support the future vision included in Appendix C. A modular approach to the construction of the devices could allow mass manufacturing techniques to be employed. This would lead to cost reduction through increased productivity and programme reduction. Greater levels of quality would also be achieved. A modular approach could also lead to a flexible device size better matched to site-specific resource or balance of plant. 7.2.1.2 Controlled construction environment • Little or no underwater working is required • The structure is built in controlled environment and as such is less susceptible to adverse weather conditions which may delay the programme • Locally available plant, material, labour and skills • Little or no site preparation required Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 79 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report • 7.2.1.3 Sufficient number must be constructed to justify dry dock cost. Water depth optimisation / sea bed losses A near shore device chamber approach depth can be optimised to minimise cost simply by moving the structure further towards or away from the shore. Shoreline sites have little opportunity to adjust the inlet / lip depth other than through careful choice of development site or through excavation of the seabed approach. Wave sea-bed friction affects the performance of the device, with shoreline devices typically being most prone to wave breaking prior to the collector and greater bed friction losses. 7.2.2 7.2.2.1 Disadvantages Installation • Equipment availability / cost • Installation weather windows • Cable connection underwater. 7.2.2.2 • 7.2.2.3 Maintenance and operation Access is more difficult increasing maintenance costs, although the basic scope of maintenance for both at shore and near shore devices is expected to be similar. Offshore environment The lateral load resistance of the structure must rely on the self weight / ballast. A sloped front wall can be beneficial in this regard as this encourages a downward-acting wave loading component. 7.2.2.4 Visual impact All OWCs involve a change of land use and some change to the visual amenity of a particular location. It could be argued that near-shore OWCs, sited less than 5km offshore will be more visually intrusive that shoreline devices, particularly if developed on a large scale. A near-shore structure will have an impact on benthic processes and change the pelagic environment. It seems likely that any near-shore device development will have to expect the level of interest expressed in offshore wind turbine development and it is hoped that a greater public realisation that renewable energy developments are beneficial in the round will eventually ease the development process. 7.3 Breakwater OWC devices The integration of wave energy devices has been carried out successfully in a few locations around the world. A review of the major ports around the UK found that there were very few breakwater locations that were in the normal OWC operating depth and tidal range. It may be possible that a device could be fitted at a small number of locations although the supply of a significant proportion of grid energy through integration into existing structures is unlikely. While this would obviously reduce the relative CAPEX apportioned to the OWC development, this method of OWC improvement is not considered further in a UK context. However, there is undoubtedly potential to incorporate OWCs in breakwaters being considered in exposed locations for port development around the world. Baja California is one such area where substantial breakwater structures are planned for LNG import facilities. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 80 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report 7.4 Conclusions The inherent constraints on shoreline OWCs outlined above limit the scope for improvement and scale of the resource that potentially can be realised. Near-shore devices can avoid some of the shoreline constraints. This includes: • A greater available resource, with a more flexible choice of locations. • The ability to use a generic design rather than a site-specific design for each device. • The possibility for mass production • Little or no underwater working is required • The structure is built in a controlled environment and as such is less susceptible to adverse weather conditions and programme delay. • Greater ability to tune the structure for a particular wave climate by varying the device depth and / or orientation. Nearshore Cost Split Shoreline OWC Cost Split 3% 12% 19% 3% Temp Works / Site Prep 10% 6% Temp Works / Site Prep Structure Structure Turbine / Generator Turbine / Generator Grid Connection 24% Elec Connection 57% Installation Vessel Costs 66% Shoreline v Near-shore Power Production Cost 24.00 22.00 20.00 p/kWhr 18.00 16.00 14.00 12.00 10.00 8.00 6.00 4.00 0 5 10 15 20 25 Development Size MW Shoreline Trend Nearshore Trend This relationship is discussed in detail in section 10. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 81 The Carbon Trust 8 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Scope for Improvement The technical review of OWC demonstration devices has highlighted aspects of the technology and means of delivery of projects that show scope for improvement. The potential and technical proposals for improvement are discussed in this section. They are intended to be as generic as possible although LIMPET experience is frequently referenced. The scope for improvement is related to the energy flux at the 20m contour in this chapter. 8.1 Site–specific tailoring of designs 8.1.1 Chamber geometry An OWC formed from a circular tube submerged in water can be considered as the simplest embodiment of this type of device. The frequency (in rad/sec) of oscillations, neglecting end effects, is [40]: ω = √ gL L Fig 8.1 Submerged Tube Resonance The submergence depth, L, is related to the mass (and added mass) of the moving water column and determines the natural frequency of oscillation. For practical submergence depths of around 5m, the natural period of oscillation is approximately 5 seconds. Adding a horizontal section to the tube will increase the effective mass thus increasing the natural period. The use of a constraint at the lip and adopting an inclined tube such that the water-plane area in the tube increases and the area at the outlet decreases are both beneficial in increasing the natural period of oscillation. The best geometric form of the air chamber also appears to be dependant on the wave climate in each location. The greater prevalence of larger breaking or near-breaking waves at the shallow shore-line sites, where the energy is more concentrated into horizontal motion, suggests that a sloping chamber will result in greater capture efficiency since horizontal movement can be converted more readily into vertical movement. Selecting an inclined water column in shallow shoreline conditions also offers an easier path for water ingress and egress resulting in less turbulence and lower energy loss. A downside of having the sloping face is that water surface pitching (i.e. front to back slosh can be induced) rather than heave with consequent loss of captured power. Deeper water devices in less severe metocean conditions may exhibit acceptable performance with near-vertical chambers. In order for the maximum benefit of resonant response to be utilised both a crest and trough need to develop at the chamber. However, it has been observed that a trough has not been forming in the LIMPET device and this has been attributed to the water running down the inclined outer face inhibiting trough development in front of the wall. A possible design refinement would be profile the Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 82 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report front face of the chamber to shed the receding wave flow to one side or to explore whether a lip on the base of the sloping face would stop this backwash affecting the developing trough. The natural period of oscillation of practical OWC devices lies below the practical range of periods containing the most significant wave energy. The table below, for conditions in 8m water depth offshore Islay, shows that the most frequent energetic sea-state has a mean period of 10.5sec, well in excess of the resonant period of 5 seconds. Wave amplification away from this resonant period will thus be reduced. For example, the response of a system with a natural period of 5 seconds to a forcing function with 10.5 second period would only be 1.3 times ambient, in the absence of damping. Hence the OWC might be better described as an amplifier of forced oscillations. Hs vs te 2.8 3.9 5.0 220 0.5 1.5 6.2 1,352 5,680 2.5 7.3 3,877 30,303 2,551 8.4 8,163 76,448 33,094 3.5 4.5 5.5 9.5 8,367 90,992 110,398 17,083 10.6 6,628 87,854 138,590 88,577 9,762 11.8 4,454 52,340 117,548 169,764 50,112 12.9 2,145 29,531 78,876 123,677 92,001 15,270 14.0 15.1 16.2 1,281 14,991 41,642 62,783 83,027 15,504 519 5,835 16,208 31,767 42,010 15,689 131 3,534 6,545 6,414 10,603 17.4 6.5 7.5 Wave Energy Flux in W/m times percentage frequency of occurrence For UK applications with energetic shallow water conditions, a 45° chamber angle appears the most appropriate. Such a choice may incur a small constructability penalty but the need to capture the most power will over-ride such considerations. 8.1.2 Chamber lip The lip depth should be selected to limit the occurrence of inlet broaching. Broaching is undesirable as it causes loss of power take-off and sudden pressure changes in the collector. Broaching occurs when the water level falls below the level of the entry lip and a direct air passage is opened between the working chamber and the atmosphere. The wave height at which this broaching occurs is a function of the lip penetration at still water, the state of the tide and the dynamic characteristics of the water column. The LIMPET design incorporates a restriction at the lip that constrains the outflow from the column during the down stroke hence allowing the turbine to operate with an extreme low water of two to three meters below the entry lip. A curved entry lip profile helps to reduce turbulent losses at the entry. Given that the selection of a lower lip, whilst increasing the natural period of oscillation of the OWC, will also be cutting out some of the incoming wave energy and reflecting it back, the highest lip level should be sought. The depth of wave troughs below still water level in the steep waves expected near-shore is around 1⁄3 the wave height. Further, the maximum wave height encountered at the OWC will typically be depth-limited at around 0.78 times depth. It is thus suggested that the lip is set at a minimum of 25% water depth below Mean Low Water Springs to minimise the likelihood of chamber broaching. 8.1.3 Device Capture Width The capture width associated with an OWC has often been assumed to be the width of the collector. Incidences of capture efficiency (pneumatic power as a percentage of energy flux) being greater than 1 have been reported which is unhelpful in terms of understanding the capacity and efficiency of a particular device. The reason for apparently high capture efficiencies is usually some form of focusing device used in conjunction with the collector. Both the OSPREY and Port Kembla devices incorporate such features. Subsea guide walls or structures are more likely to be adopted on steel substructures where there is a desire to minimise the area exposed to the most severe wave loading yet still capture power over the entire width of the structure. An individual OWC will have an influence on the wave climate beyond its collector width. It will thus have a higher apparent capture factor than an infinite length of devices. The quantification of the Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 83 132 1,187 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report extent of influence is less tractable than on devices such as point absorbers as energy can be reflected, re-radiated and lost in viscous effects in a more complex pattern. It is hoped that arrays of OWCs will be deployed near-shore thus making the consideration of capture width less relevant. However, for the present, it is suggested that the maximum width of the device is used to define the potential energy capture, to minimise the potential for pneumatic power capture factors being reported that exceed one, as was the case with OSPREY. The effectiveness of guide vanes has not yet been proven in practice, although Port Kembla will help in this regard. It is recommended that research and development activities are directed to evaluating how effective the guide vanes are. 8.1.4 Anti-slosh Devices The chamber must be suitably sub-divided where the formation of standing waves within the chamber, that would store energy but produce no usable power, is expected. The wave sloshing period is well known and should generally be kept below 5 sec. This would imply that the chamber should be subdivided into chambers where the maximum plan dimension of the chamber exceeded about 10m. The actual choice of chamber width is thus a balance between avoiding sloshing and having element spans that are suitable for the loading to which they are subjected. 8.1.5 Air Plenum Configuration The geometry and volume of the plenum should be selected in combination with the turbine to optimise power capture. A smaller air plenum will be subject to higher pressure and greater flow both of which must be considered in relation to the turbine characteristics. The air plenum may be subjected to high pressures if the flow exceeds the turbine capacity and the control valve is closed. The maximum crest height (assuming 2⁄3 crest and 1⁄3 trough) has been assessed for the LIMPET geometry. Hs vs te 2.8 3.9 0.5 5.0 6.2 7.3 8.4 9.5 10.6 11.8 12.9 14.0 15.1 16.2 17.4 0.21 0.24 0.73 0.26 0.79 1.31 0.28 0.83 1.38 0.28 0.85 1.42 1.99 0.29 0.87 1.45 2.04 2.62 0.29 0.88 1.47 2.06 2.65 0.30 0.89 1.49 2.08 2.68 3.27 0.30 0.90 1.50 2.09 2.69 3.29 0.30 0.90 1.50 2.10 2.70 3.30 0.30 0.90 1.50 2.11 2.71 0.30 0.90 1.5 2.5 3.5 4.5 5.5 6.5 Estimated Crest Height in Collector (m) The maximum predicted crest is +3.3m, which would be a level of +5.9m with respect to local datum at the time of MHWS for the nearby Orsay Island. The lowest point on the turbine inlet is +8.54m with respect to local datum and a bench is provided at +4.94m. Thus there seems to be scope for lowering the overall height of the chamber. The plenum was originally designed for a considerable internal pressure. The corresponding locked in pressure associated with the above crest level has been assessed to be 0.34barg as shown in the table below. This value is relatively small compared to the external design hydrostatic head. Hs vs te 0.5 1.5 2.5 2.8 3.9 5.0 0.02 6.2 0.02 0.06 7.3 0.02 0.06 0.11 8.4 0.02 0.07 0.12 3.5 9.5 0.02 0.07 0.12 0.18 4.5 5.5 10.6 0.02 0.07 0.13 0.19 0.25 11.8 0.02 0.07 0.13 0.19 0.26 12.9 0.02 0.07 0.13 0.19 0.26 0.34 14.0 0.02 0.07 0.13 0.19 0.26 0.34 15.1 0.02 0.07 0.13 0.19 0.26 0.34 16.2 0.02 0.07 0.13 0.19 0.26 6.5 Estimated Plenum Peak Pressure in bar gauge It should thus be possible to effect savings in the collector chamber design compared to previous more conservative assumptions. Such savings will be carried forward to the future vision generic design. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 84 17.4 0.02 0.07 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report The air plenum could also be actively adjusted using baffles and valves to better match the required turbine damping requirements. This has to be viewed further in relation to the power required to control the valves and the additional instrumentation and control system that would be needed. 8.1.6 Collector Width The maximum frontal width that can be selected for one air chamber depends on the degree to which long wave fronts can be expected to reach the device at the same instant. A collector that was linked to a crest in one location and a trough in another would have a reduced capture efficiency. It would be possible to have a wide collector facing the waves with only one turbine set but a significant amount of valves and controls would be needed to ensure useful power was not lost. It seems preferable to limit the collector width to the continuous crest length that can be reasonably expected. A maximum collector width of 40m is suggested, which would automatically limit the size of turbine that needed to be developed for OWCs. For an incident wave power at the 20m contour of 34kW/m and a pneumatic capture of 40-50%, the maximum rated power for a turbine set would be around 1300kW based on the rated power being around three times the average power captured. More accurate determination would require the degree to which shoaling effects encouraged offshore spread seas to become more long-crested to be assessed. Further, angular offset that would be expected between the line of advancing wave fronts and the contour of constant water depth on which it was designed to site the OWCs would need to be determined. 8.1.7 Tidal range It has been shown in the stage 1 evaluation that the capital cost of an OWC could be considered proportional to the maximum design water depth squared since the device has to become proportionally wider or heavier to resist wave loading whilst also getting taller. Taking a typical water depth of 10m, the sensitivity of device CAPEX to tidal amplitude could be assessed to be proportional to: (Depth + tidal amplitude) 2 If an average UK tidal amplitude of 2m is assumed compared to a location without tidal influence, a cost increase of 44% might occur. Hence it is important to concentrate on sites with the smallest tides. It is for this reason that the vast majority of the development sites associated with the future vision all have a tidal amplitude less than 2m. 8.2 Turbine choice and specification 8.2.1 Air flow rate matching For the limited number of projects developed to date, mismatching of the collector and turbine appears to have been a critical factor in the poor performance that has been achieved. Although there has been much theoretical analysis, primarily in the area of turbine damping, there has seemingly been little effort directed towards the creation of accurate, generic predictive tools for matching collector and turbine characteristics. Much of the work appears to have been undertaken on an empirical basis and where theoretical models have been developed their validation has been rather limited, typically against a very limited range of experimental data. Consequently the design process and matching between collector and turbine is in many cases likely to be sub-optimal. Modern CFD techniques should be capable of analysing the problem. A comprehensive dynamic model incorporating the collector, variable speed turbine, exhaust system (including any noise abatement) and cyclic, reversing flow would undoubtedly require substantial computational capacity and although feasible may not be practicable in all cases. Nonetheless, if the limit is solely one of computational capacity then it should be possible to create a number of more manageable sub-models with matching boundary conditions. Development of these techniques would enable a better Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 85 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report understanding of the interaction between collector and turbine characteristics and should lead to improved designs with better performance and output. Overall performance will be improved if turbine efficiency can be maintained over a wide range of sea states. This implies either that the collector structure and intake duct must be designed to deliver steady flow to the turbine over a wide range of sea states (e.g. by turbine inlet flow modulation using bypass and/or inlet throttling valves) or that the turbine must be capable of efficient operation over a broad range of inlet flows. The latter option would seem preferable as there is less risk of flow mismatch due to incorrect design of the collector structure. At least one developer has observed that the performance of Wells turbines is better at low wave energy input levels with low air flow rates whereas an impulse design is potentially more suited to higher wave energy input applications. It may therefore be appropriate to select the basic type of machine based on local wave energy available. This approach would be similar to that for water turbines where the basic design (Pelton, Francis or Propeller) is determined by the available input head and flow. The goal should be to develop a range of standard turbines with known characteristics such that collector structures can be designed to deliver the required air pressure and flow conditions. In this respect a parallel can be drawn with thermal power generation where it is usual for a steam boiler to be custom built against a recognised code to deliver the required steam conditions to a steam turbine selected from a standard range. For near shore applications where the collector structure is not constrained by local topographical considerations, it should be possible to develop a range of matched collectors and turbines. Such an approach would be expected to deliver significant cost savings in terms of both reducing the amount of site-specific design activity and enabling savings due to standardisation of the manufacturing process. 8.2.2 Blade and vane configuration The performance of the turbine will be substantially determined by the blade and vane configuration and each design will have a specific characteristic for efficiency against inlet flow. The characteristic may be a single curve that includes speed variation or a family of curves at constant speeds. The shape of the performance characteristic will be determined by the generic blade type. For example, an impulse machine will in general have a broader characteristic curve than a Wells machine, primarily due to it being less susceptible to stall at higher air flow rates. Much of the development work to date has considered variations on the Wells turbine in order to broaden the performance characteristic. This may be due to the simpler blade design with fewer blades and hence lower cost in a research and development environment. However, in its simplest form the Wells turbine suffers from inherently poor performance and a narrow characteristic due to its low torque development and susceptibility to stall at off-optimum air flows. Variants investigated to improve performance include variable and fixed guide vanes, variable pitch blades, bypass valves and inlet flow throttling. Whilst such schemes can be shown to improve the theoretical performance, there is a danger that for those involving additional moving components the advantages conferred by simplicity of the blade design could be outweighed by an over-complex control system (with inherent reliability and maintenance risk), increased maintenance burden and increased parasitic losses. An impulse design appears equally valid and greater evaluation of its potential would be justified. Notwithstanding the above, the use of guide vanes is in general likely to improve performance and in the case of impulse design machines is essential. Fixed guide vanes offer the simplest solution with minimal maintenance and would be expected to give higher reliability due to the simpler control system. However, the reversing nature of the air flow and variable turbine speed makes optimisation of the design somewhat difficult; exit vanes that become inlet vanes on flow reversal generally reduce performance as the optimum aerofoil geometry for an exit vane differs substantially from that for an inlet vane under reverse flow conditions. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 86 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Valve arrangements to rectify the flow could be possible. This would obviate the need for exit vanes but a complex control system may still be required, reliability may reduce and parasitic losses would increase if the valves required powered actuation. Partial arc admission has also been proposed, for example the air flow path could be divided into quadrants with two diametrically opposed quadrants being optimised for forward flow and two for reverse flow. However, the practical implementation of this would need some development as simple blanking would not be possible in a reversing flow stream. For machines with variable pitch blades it is likely that a pitch change would be required during each forward and reverse flow cycle; this is the philosophy for the Dennis Auld turbine under construction for the Port Kembla project where real time wave measurement is incorporated in the control software to maintain optimum performance. The success of this approach has yet to be demonstrated and the increased complexity may not be cost effective and could introduce poor reliability. Both Wells and impulse turbines for OWC applications have traditionally used symmetric blade profiles on the basis that forward and reverse flow will be the same. Consequently much of the theoretical and experimental work to date has been based on uni-directional flow, often under steady state conditions. However, there is evidence (Pico, LIMPET) that forward and reverse flow rates are not the same and thus there is a case for the investigation of asymmetric blade profiles optimised for each direction of flow. For configurations in which guide vanes are used it follows that these can be of different profile on each side of the rotating blades. The use of asymmetric blade profiles also opens the possibility of introducing blade twist, lean and section changes with radius to better match the incidence angles to the radial distribution of flow within the annular duct. The contra-rotating design has not proved successful at LIMPET and simpler monoplane and bi-plane designs appear to be favoured for the future. The disappointing performance of contra-rotating designs is believed to be due to having too much damping for the OWC. However, it should be possible to design multiple stage turbines to provide similar damping to single stage turbines by changes such as increased turbine diameter and reduced blade area. In the final analysis multiple stage machines may only offer modest performance improvements that are not sufficient to justify the additional costs. 8.2.3 Orientation of axis The most common arrangement to date is for horizontal axis machines in a horizontal duct. This reduces the thrust bearing loading (no self weight to be carried) and allows horizontal split casings for maintenance access. For shoreline installations the risk of water ingress to the turbine under storm conditions is also reduced as the atmospheric vent can be directed away from the wave source (at LIMPET waves have been observed to break over the cliff top structure). An alternative configuration is for a vertical axis machine in a vertical duct. However, this arrangement has the potential disadvantage of turbine deluge during wave overtopping unless the atmospheric vent is positioned substantially above the sea level. 8.3 Device construction methods 8.3.1 Balance of Plant Materials Construction materials must be capable of withstanding operation in a hostile environment with respect to corrosion, dynamic stressing and possible impact loading in the event of water carry over from the wave collector. To date, blades generally have been manufactured from a metallic material, the most common being aluminium (LIMPET) or stainless steel (Port Kembla) or both (Pico). Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 87 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Aluminium offers some advantage in terms of being resistant to corrosion but may suffer long term limitations in terms of fatigue under cyclic loading. Fatigue cracking under cyclic loading due to blade vibration under stall conditions in a Wells turbine is potentially a significant operational and maintenance issue. At LIMPET, aluminium blades have been used in conjunction with steel rotor discs. The use of dissimilar metals can present a natural tendency for corrosion due to galvanic cells being created, particularly in a moist atmosphere. Blades removed from the LIMPET machine are reported to have suffered particular corrosion pitting and possible cracking in the region of the blade to disc interface. It was suggested that the blades would not be re-useable after just 6,000 hours running in 30,000 hours of service. Stainless steel is likely to be more fatigue resistant and due to its greater density will give a greater contribution to rotor inertia (see below). However, the blade weight would lead to greater parasitic losses for applications involving variable blade pitch due to greater inertia about the blade radial axis. Blades manufactured from composite materials (e.g. resin impregnated carbon fibre) would be expected to have excellent corrosion resistance and would have low pitch inertia for variable pitch applications. However, composite materials may be constrained by strength limitations perhaps making them more suitable for lower speed, lower diameter impulse type machines. In addition a composite blade aerofoil is likely to be less resistant to water droplet erosion in a high moisture environment and will therefore require a protective metallic coating. The application of the protective coating may present manufacturing difficulties in terms of ensuring adequate adhesion to the composite substrate. Nonetheless such blades are being proposed for a variable pitch machine intended for installation at the Pico site in 2005. The choice of material for rotating components is likely to have an impact on rotor inertia. This can be significant in terms of response to load rejection (potential over-speed) and power quality issues. A high inertia rotor is preferable and will reduce the need for a flywheel with a potential performance benefit due to reduced windage losses. Casings are generally fabricated structures manufactured from coated steel. Hot dip galvanising and aluminium flame sprayed coating have been used to enhance corrosion resistance. Cathodic protection may be appropriate in some circumstances. Casing technology has synergies with that for duct structures for thermal plant and if correctly maintained these structures should be capable of at least 25 years operational life and perhaps longer. Corrosion is likely to be the main life limiting issue and high integrity corrosion protection or use of non-corroding materials such as plastic or fibre glass will be required. From a production viewpoint, metallic materials are most likely to offer the potential for mass production, these being readily suited to existing fabrication and automated CNC machining methods. 8.3.2 Mass production / manufacture Mass production would be feasible for a range of standardised turbines and a potential volume manufacturer has indicated a maximum volume of around 200 units per week to be a realistic production target within five years, a rate that is likely to far outstrip demand. There is general consensus that the market is likely to be very large; one developer has suggested a total worldwide market potential (for their own products alone) of around 12,000 grid connected machines and 2,500 machines for stand alone remote generation. Current effort is concentrated on demonstration plants to prove the technology prior to development of mass production sources. Costs for mass manufacture would initially be high but would be expected to fall over a three to five year period. Cost for a one off development machine at LIMPET was around £900/kW. This would be expected to reduce substantially for a standardised design, perhaps to around £300/kW. Such figures should be possible by the time 1000 units have been produced if previous energy technology learning rates are experienced [76]. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 88 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report It should be noted that for large coastal installations the cost of the turbine and balance of plant could represent 5% or less of the total project cost. Unit costs for the turbine may not therefore be critical in determining the viability of such projects. However, for near shore devices where a steel collector structure is used the cost of the turbine and balance of plant is expected to represent a more significant proportion (perhaps 20% to 30%) of total costs due to the lower cost of construction and opportunities for standardisation of the collector structure. 8.4 Conversion efficiency 8.4.1 Understanding Pneumatic Capture Pneumatic efficiencies of OWCs have generally been assessed using model testing. Although the principles of wave capture are well-known, a ready means of developing and evaluating new collector performance does not seem to be available. A simple spreadsheet based system was thus developed to gain better confidence in the understanding whether developers were reporting capture efficiencies in a manner that would allow general capture efficiency conclusions to be drawn. It also allowed some basic testing to sea how capture efficiencies might be improved through the change of basic parameters such as collector size and turbine damping. 8.4.2 Wave to pneumatic efficiency An OWC sited in a wave flume could be configured for a particular monochromatic wave to have 100% power capture for the correct value of damping associated with the turbine. In reality, sea-states comprise waves of a range of frequencies and this makes continuous turbine matching more difficult. An energy model (developed for LIMPET) is typical of OWCs: Fig 8.2 Energy model developed for LIMPET [6] (source: Wavegen) The only part of the energy model that produces useful power is the heave of the water column caused by incoming waves. The geometry of the collector should thus be selected to maximise the energy in heave motion whilst minimising the losses and energy contained in outgoing waves. The theoretical maximum conversion efficiency of the OWC (wave to pneumatic) at any given period (frequency) of the incoming wave is thus determined by its geometry, the direction of the wave, and an optimum value of the ‘damping’ in the chamber. The damping is determined by the turbine and generator characteristics. 8.4.2.1 Resonant Frequency The resonant frequency of OWCs can be established by numerical modelling or through model testing. Resonant frequency determination has been examined using a linear diffraction analysis code, AQWA, using LIMPET as a reference case. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 89 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Response Amplitude Operator (RAO) in Heave (m/m) Dynamic Amplification on LIMPET model (7m water depth case) 14 12 10 LIMPET in Isolation 8 LIMPET with channel geometry modelled 6 4 2 0 0 5 10 15 20 25 30 Period (s) Fig 8.3 Resonant frequency determination using Linear Diffraction Modelling Two analyses were carried out using 1m amplitude waves: one with the local gully geometry modelled and one with the OWC in isolation. The resonant amplitude peak without the gully in the collector chamber is around 4 seconds, perhaps illustrating the importance of the added mass of water in the gully in increasing the resonant period. With the gully present, a resonant peak is observed around 5 seconds (the model would not calculate for lower periods than 5.5seconds) and secondary peaks are observed that possibly relate to the harbour resonance effect (reported to be around 10 seconds period). Hence, although diffraction analysis is relatively quick to perform and gives a reasonable indication of natural period, it is expected that a CFD model that included the air chamber and turbine characteristics as well would be the more appropriate analysis platform. It is recommended that research be directed to such CFD modelling techniques to assess their effectiveness. 8.4.2.2 Numerical Modelling The spreadsheet model was based on the geometry and performance characteristics of the LIMPET device. The model assumed a resonant period for LIMPET of 5 seconds [6]. Standard relationships for the response of a single degree of freedom (SDOF) system (i.e. heave in the collector) to a forcing frequency were used to determine the wave amplitude expected at different forcing frequencies. Spectral techniques were used to establish the resonant response of the collector for each sea-state the collector would experience in one year. A critical damping value for the collector was estimated by calculating the mass of water in the collector (plus some added mass) and its water-plane stiffness. A critical damping value of 3500kNs/m was estimated. The damping value due to viscous losses caused by friction on the walls and the 40° bend was evaluated but this was much lower than the expected turbine damping and was thus ignored. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 90 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report The work done by the turbine was calculated for the standard SDOF relationship for the working done during resonant sinusoidal motion: π P a = π c ω a2 where: P = external force c = turbine damping ω ω = natural frequency a = amplitude of motion P is determined from the potential energy of the oscillating water column. The percentage of critical damping of the water column was set to be that given by the turbine damping coefficient and the turbine damping coefficient was adjusted until the work done by the external force matched the work done in the turbine. Hs vs te 2.8 3.9 0.5 1.5 5.0 6.2 7.3 8.4 9.5 10.6 11.8 12.9 14.0 15.1 16.2 17.4 83.2% 74.3% 74.3% 66.6% 66.6% 66.6% 60.0% 60.0% 60.0% 54.4% 54.4% 54.4% 54.4% 49.6% 49.6% 49.6% 49.6% 49.6% 45.5% 45.5% 45.5% 45.5% 45.5% 42.0% 42.0% 42.0% 42.0% 42.0% 42.0% 38.9% 38.9% 38.9% 38.9% 38.9% 38.9% 36.2% 36.2% 36.2% 36.2% 36.2% 36.2% 33.9% 33.9% 33.9% 33.9% 33.9% 31.9% 31.9% 2.5 3.5 4.5 5.5 6.5 Capture factors for individual sea-states The capture factors (lip power to pneumatic) produced by the spreadsheet were comparable to the values reported by Wavegen for monochromatic waves. A typical value of 40% was reported by Wavegen for 10 second waves. This gave confidence that the spreadsheet was a useful tool for assessing the scope for improvement in capture efficiency. The total capture efficiency obtained was 33% with respect to the 20m contour value and 47% with respect to the chamber lip. QUB Wide Tank - LIMPET 3D Optimum Damping Trials - August 2003 7m Water Depth 400 Sea31 - Pi Sea29 - Pi Sea24 - Pi Sea21 - Pi 350 67.3kW/m 39.6kW/m 21.2kW/m 5.26kW/m - 0.5% - 1.5% - 7.1% - 9.5% Pneumatic power [kW] 300 250 200 150 100 2800kNs/m 50 0 [Ns/m5] 0 [kNs/m] 0 17340 Fig 8.4 100 2890 200 5780 300 8670 Damping coefficient 400 11560 500 14450 600 LIMPET turbine damping optimisation tests [60] Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 91 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report This compares with peak capture values reported for LIMPET [60] of 28.5 to 40% based on the 20m energy flux values. These are estimated to be 43 to 60% with respect to lip energy fluxes. An average turbine damping value for all sea-states of 2800kNs/m was assessed. This is close to the optimum values that Wavegen reports, again raising confidence in the spreadsheet method. 8.4.2.3 Scope for Improvement If the LIMPET chamber is increased in area (200m² rather than 159m²) until the capture factors become one at the lower sensible energy ranges of the sea-states, the capture factor can be increased to 59% at the lip and 42% with respect to the 20m contour. This increase will only be real if this amount of energy is actually transmitted across the lip. This aspect will still need to be assessed through CFD or model testing. Further refinement of the chamber and possible variable damping arrangements might increase the capture factor to 65 or 70% at the lip or conceivably 80% as some developers claim [5]. This compares with 64% reported, by Wavegen [5], to be currently achievable for an ideal LIMPET. The scope for improvement in both the understanding and assessment seems to be substantial and further research effort in this area will probably yield the greatest dividends in better OWC performance. 8.4.3 Pneumatic to mechanical Wavegen reported the following findings following investigation of the performance of the turbine installed at the LIMPET device: The efficiency of the Wells turbine depends on the turbine flow coefficient; with a clear stall point at high flow coefficients resulting in a rapid reduction in efficiency. To maximise turbine torque the amount of turbine flow needs to be limited to avoid an excess flow coefficient and thus low turbine efficiency. For a Wells turbine the flow rate is proportional to the pressure drop across the turbine and thus this condition is equivalent to limiting the pressure in the plenum chamber. Thus, a perfect blow-off valve would operate so that the chamber pressure was never higher than a critical value defined by the turbine characteristics. The matching of the wave frequencies to that of the resonant frequency of the water column can involve the active control of baffles or walls using sensors and actuators, or by opening up/closing off smaller side chambers to the main water column chamber etc. Research efforts in this area have taken place to actively control the ‘resistance’, ‘damping’ or ‘inertia’ of the ‘terminations’ within the water column. In this case, ‘terminations’ usually refer to the physical properties of the escape route for the compressed air at the top of the water column. This can refer to the turbine characteristic itself, and how this can be modified and controlled, or to other devices placed in series or in parallel with the turbine to modify the dynamic characteristics of the air/water interface. In many cases, these ‘other devices’ consist of an actively controlled valve or damping which affects the amount of compressed air flow to, or around, the turbine. Physically, this active tuning of these parasitical routes can be seen as varying the physical and dynamical properties of the OWC, and if done in a sympathetic way, achieve the desired aim of providing optimum damping for the OWC. The characteristics of the Wells turbine show that the torque/air pressure relationship peaks at a certain value of OWC air pressure. Above this value, the turbine output torque falls and the turbine can enter a ‘stall’ phase, where energy conversion efficiency falls off rapidly. It is therefore important that the incoming wave energy profile or collector geometry is controlled so that the unwelcome stall condition is not reached. For an optimised design an instantaneous peak turbine efficiency of between 60% and 70% is probably a realistic expectation for a Wells or an impulse turbine with flow in either direction. With appropriate design development it should be possible to extend the breadth of the performance characteristic such that greater than 50% efficiency is achieved over a defined range of flows. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 92 The Carbon Trust 8.4.4 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Mechanical to electrical Experience with wind turbines has shown that directly connected synchronous machines do not cope well with fluctuating power sources, especially in the range of frequencies observed in oscillating water columns, but rather reflect these with undesirable sub-synchronous oscillations on the system. For a directly connected machine, an induction machine is preferable, since the slip characteristic tends to damp such oscillations. Generators for wind turbines usually operate at a much higher level of slip than commercial induction motors, the increased losses being a small price to pay for the vital damping action. The review of existing projects and associated studies makes little mention of doubly-fed induction generators (DFIGs), since they largely predate the more recent popularity of such machines used in the wind power industry, however these modern drive systems are very similar to the well established Kramer drive systems which have been used in OWC applications. It is hoped that experience gained with wind power will prove useful in marine energy. The control systems employed are largely a feature of the machine design, rather than the prime mover. In many of the prototype OWCs a traditional slip energy recovery or Kramer drive, has been used. The modern DFIG drives which are the current state of the art in the wind industry are essentially the same concept, but with increasing more complex control strategies. In wind power these schemes are generally cheaper than the other popular method, decoupling the machine completely from the grid with an electronic converter. In wave power, however, if the machine is frequently cycled between full speed and stationary, the converter for the DFIG may be no cheaper than the in-line converter used with other kinds of machine. The intermittency of the power source is something that OWCs have in common with WTGs, however with current designs of OWC the low frequency pulsating nature presents a more onerous power system issue. However as has been found with large wind farms, large arrays of OWCs will help to smooth out this variation. Other existing power system techniques such as use of SVC and STATCOM may also be needed to improve the quality of the supply. The use of existing technology and what has been developed for the wind industry is likely to be used. The control of output is more involved because it depends on the nature of the power source and the nature of the electrical system. Historically, network operators have required a strong enough connection for a small generator that minimal control is required; where this has been impossible, they have tended to require extensive remote control of the machine from the network control room. There are a number of innovative control strategies currently being developed and considered as part of the OFGEM remit to connect more distributed generation. The developments fall largely into two categories, enhanced and novel generator control systems, and co-ordinated network based control. Again these are generic issues with the connection of generation into weak power systems that were designed only for passive loads. It is likely that any solutions developed for the connection of distributed generation will transfer into the wave power market. In contrast to the turbine the electrical plant will make use of existing state of the art industrial and wind industry technology. The range of mechanical to electrical efficiencies is expected to be 90-95%. This range will depend to a certain degree on the type of technology used such as cage machine direct drive or DFIG. However the most significant variations will result from the design choices made in the range of device operation in varying sea states. 8.4.5 Total device efficiency Measured performance data from LIMPET indicate that instantaneous peak turbine efficiencies of around 70% for forward flow and 30% for reverse flow have been achieved. However, this was over a relatively narrow energy input range and the challenge will be to extend this performance over a wider range of sea conditions. Average performance for the LIMPET machine over the full energy spectrum is substantially lower with overall wave to wire efficiency of less than 10%. This is understood to be Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 93 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report largely due to poor original wave climate data and the consequential mismatch between the collector and turbine. The reverse flow efficiency of the LIMPET turbine is significantly influenced by the retrofitted acoustic attenuator which causes poor circumferential distribution of the air flow. This is not expected to be an issue for a machine in which the acoustic attenuator is included in the original design. Nonetheless, differences between forward and reverse flow turbine efficiencies may persist due to differences in boundary conditions in each part of the cycle. It is therefore considered more appropriate that an overall efficiency should be stated that takes account of this variation. The Dennis Auld turbine for Port Kembla has a predicted efficiency based on numerical modelling and wave tank tests in excess of 80% peak. Overall turbine efficiency is expected to average around 54%. No operational performance data are available for the Pico project due to a series of operational problems not directly related to the turbine technology. Nonetheless from limited data the developer (IST) is confident that the turbine efficiency will achieve that predicted in the design process. The maximum attainable overall efficiency for the Wells turbine (forward and reverse flow) was thought to be around 60% compared to around 50% currently. When comparing overall efficiency values it is important to determine the basis on which efficiency is being quoted, in particular the reference point for wave energy. Each developer currently appears to be free to quote efficiency on any convenient basis, potentially making like-for-like comparison of designs difficult. It is therefore recommended that a common standard should be developed for the definition of the performance of wave energy devices (in line with current practice for fossil fired plant). Some progress is being made on his issue at the EMEC facility on Orkney [80]. In the case of the LIMPET site the generator and turbine were over rated for the wave resource available. This was due to mistakes made in assessing the resource. The question has been asked as to whether the turbine and generator should be rated for the average or peak wave energy. The best analogy here is with wind farm wind resource calculations. Once a set of annual wave resource data is available for a given site then yield calculations can be carried out of different turbine and generator sizes. The lowest p/kW will depend on the capital cost and wave distribution and cut in and out speeds of the turbine. It seems likely that the turbine and generator will be rated above the average available resource but well short of the peak storm conditions. Until resource calculation tools and devices have reached greater maturity, it is difficult to determine the best rating as many developers have found. Typically wind turbines have an electrical rating based on around twice the average wind speed, however this typically corresponds to around four times the power. Energetech the developer of the Port Kembla project have chosen to rate their turbine and generator at three times the average available power. A rating of three times the average power has been selected for the generic base case design. It is suggested that two turbines be adopted per collector with the second generator being activated when higher sea-states are expected. On this basis, only 2.6% of the available resource might be lost or not fully-utilised as shown below. Hs vs te 0.5 2.8 3.9 Not operating 1.5 2.5 5.0 733 6.2 902 8,114 One 375kW turbine 3.5 4.5 7.3 1,020 9,183 25,508 8.4 1,103 9,928 27,579 9.5 1,162 10,459 29,052 56,942 Two 375kW turbines 5.5 6.5 10.6 1,205 10,846 30,128 59,051 97,615 11.8 1,237 11,136 30,934 60,630 100,225 12.9 1,262 11,358 31,550 61,839 102,223 152,704 14.0 1,281 11,532 32,032 62,783 103,784 155,036 Flow to be throttled for Two 375kW turbines 15.1 1,297 11,669 32,415 63,534 105,025 156,889 16.2 1,309 11,781 32,724 64,140 106,027 17.4 1,319 11,872 % Resource 2.1% 52.0% 43.4% 2.6% 7.5 Turbine selection for range of energy fluxes at 8m depth site Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 94 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report 8.5 Survivability 8.5.1 Wave loading The design of near-shore caisson structures requires a detailed understanding of the wave loading to which they are subjected. Wave loading can be determined from diffraction theory for unusual geometries or from breakwater theory for reasonably uniform-fronted caisson or shoreline OWCs. The study of impacting loads on caisson structures has been the subject of recent research through the PROVERBS [61] programme. Caisson structures and their sub-elements have previously been designed for high impact pressures treated as quasi-static loading. However, the nature of the impacting load events is that they typically act over less than 100msec. An approach that considers the natural period of the element being designed in relation to the impact duration allows a much smaller quasi-static force to be designed for. This approach should be researched further as it will have an important bearing on future OWCs designs. It is preferable to site an OWC in an environment where impacting waves are less prevalent. PROVERBS indicates that if the proportion of impacting events is less than 2% then impacting conditions can be ignored. Figure 8.5 below shows that these conditions are present above about 11m water depth taking offshore Islay as a reference case. 45.00% 40.00% Waves Breaking or Impacting 35.00% 30.00% 25.00% Breaking Waves Impacting Waves 20.00% 15.00% 10.00% 5.00% 2% 0.00% 6 7 8 9 10 11 12 13 14 Depth (m) Fig 8.5 Percentage of Breaking and Impacting Waves in Sea-State The adoption of a sloping face to the OWC also limits the potential for a plunging breaker impacting the OWC. Tank testing by Wavegen seemed to confirm this for LIMPET [6]. If plunging breakers are not present this allows the front face of the chamber to be designed for normal reflecting wave pressures such as those given by Goda [62]. This should be taken forward in future designs as it reduces the capital cost of the structure. 8.5.2 Return Period In practical near-shore water depths, the design wave height is limited by the water depth. A maximum wave height of 0.78 x water depth is conventionally used [63]. The concept of a return period for Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 95 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report design thus has little meaning as the depth will govern for waves of the minimum return period appropriate for a design life of typically 25 years. 8.5.3 Balance of Plant Both LIMPET and Pico have experienced problems with flooding of the plant room during wave overtopping. At Pico this is being addressed by proposed relocation of all electrical and control equipment except the generator to a separate installation around 100m inland. Where electrical equipment is located within a plant room in the main structure it will need to be enclosed to at least IP56. Some of this protection may be provided by the structure of the module. Water tight construction techniques should be applied to the construction of the plant room including water tight doors and access penetrations. The turbine should ideally be designed to withstand 100% deluge, particularly if used in a vertical axis configuration. The Port Kembla machine (horizontal axis) is understood to have been designed on this basis. Where such capability is not part of the turbine design the layout of the installation should be such as to minimise the risk of major water ingress. Location of the turbine rotor body and the generator in a nacelle structure will give additional protection and limit the risk of water ingress. 8.6 Reliability, operation and maintenance Operational reliability of the LIMPET machine is reported to be high. However, the availability is rather low (65%) due to frequent loss of grid connection. The problem is thought to be more related to poor design than any inherent weakness in the local grid system. The Pico plant is located on a small, and potentially less stable, island grid system and no such similar problems are reported albeit operation has been somewhat limited for other reasons. The control system at LIMPET is such that remote manual intervention is required for a re-start following a plant trip under fault conditions. In general this is a sound philosophy, as it will protect the plant from further damage in the event of a genuine fault. However, the current arrangement includes re-starts following loss of grid connection, even if the loss is only of short duration. The noncommercial basis of operation has meant that depending on the time of the grid loss, the plant can be shut down for several hours or days. The provision of auto restart following loss of grid should enable an availability of greater than 90% to be achieved. For unmanned operation the reliability of the control system must be high. The plant must be capable of automatic start up and shut down according to wave climate. The capability for remote interrogation of the control system for condition monitoring and investigation and re-start after trip is essential. Standard remote monitoring systems similar in principle to that for the LIMPET installation are likely to be readily available in the market place. Maintenance requirements must be low for an unmanned site and the plant must be capable of sustained operation without manual intervention for long periods. Given the relatively simple nature of the OWC plant, maintenance should not prove too onerous in comparison to floating devices and devices that have hydraulic power conversion systems. Planned routine maintenance at 8,000 hour (1 year) intervals should be the minimum expectation as for conventional thermal plant. Annual maintenance would be expected to encompass inspection of the turbine and generator bearings, inspection of the turbine blades (fixed and moving) and blade actuator mechanisms (variable pitch machines) and checks on the control and electrical systems. Typical routine operational maintenance would include greasing of inlet valve bearings and actuator linkages, and draining of compressed air receivers. Both of these activities should be achievable by automatic means. In time, the requirements for maintenance and reliability can hopefully become as low as those for hydro-electric plant. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 96 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report For shoreline OWCs the main maintenance consideration is the likely remote location of the plant and the potential for associated transportation difficulties if major work is to be undertaken such as removal of plant to works for maintenance or repair. However, provided adequate facilities are incorporated in the design (e.g. local lifting and workshop facilities) on-site routine maintenance activities should be expected to proceed as with any other electro-mechanical installation of similar size. For near shore devices there is the additional consideration of access to the structure and maintenance in a potentially more hostile environment. One approach to alleviate this issue might be to develop modular turbines that could be removed for maintenance on shore in a controlled workshop environment. Use of a rotating spare would minimise the downtime for maintenance to that for exchange of the module. The same principle could also be applied to shoreline OWCs. 8.7 Prediction and modelling It has been illustrated earlier that the calculation of the device resonant frequency can be carried out initially by simplified mathematical formulae that include the geometrical size of the opening, excitation forces, damping and stiffness. More sophisticated methods such as boundary element methods have been used that more accurately predicts the diffraction around and inside the device. Transfer functions can be derived from the surface velocity within the diffraction model that can relate to the air pressure inside the chamber. A more accurate prediction of the power available can then be made based on the site spectra encountered throughout the year. A further sub model based upon the performance of the turbine and other electrical equipment can be made that will further refine the model to give a full wave-to-wire prediction. One of the shortcomings of the boundary element method is that it is based upon linear diffraction theory and therefore cannot account for higher order viscous effects. This is particularly important in the design of the lip of the inlet to the chamber. A method used for design of the lip into the chamber is Particle Image Velocimetry (PIV). This method illuminates the water particles by use of very thin laser light and a combination of lenses. The losses around the lip can be quantified using this method. It has been found through using this method that the size, shape and inclination of the lips are of importance. Computational Fluid Dynamics (CFD) software has been used in some applications of wave energy devices. CFD software has the capability to model the waves, viscous effects, air pressure movement and turbine rotation. A model of this size would involve enormous computational effort and the costs would possibly become similar to tank testing. This could, however, become a more favourable option in the future as the software and computer technology improves. It should be noted that such CFD models have been created for the Port Kembla project currently under construction in Australia and to a partial extent for the Pico project. 8.8 Control of export power The primary source of short-term variations in mechanical power will be the waves themselves – generating a high level of output as the water rises and falls, and much less output in between these states. The frequency of this variation will vary according to the wave conditions, and there will be a range of frequencies characteristic of any particular site. This is by contrast with wind power (from which the control system is likely to be adapted), which experiences random variations (gusts), and a sub-synchronous variation at the blade frequency, directly related to the mechanical speed. The OWC controller must cope with sub-synchronous power variation at a range of frequencies; it will probably be necessary to analyse the system for subsynchronous resonance and program the controller for maximum damping at the resonant frequencies. On the other hand random variation is likely to be much less, and the controller will Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 97 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report probably not need to accommodate power spikes of several times the continuous rating, as are observed from wind turbines. It is likely that initial commercialisation of OWC will utilise fully rated converter drives and cage induction generators rather than the DFIG generators that have become the standard on large WTG. Power quality issues may lead to the adoption of DFIG in the long term once a significant small generator market is established. Steady state control of export power will be carried out by operating vanes in the air path, but transient control, using the energy stored in the converter electronics, can be given the required characteristic in software. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 98 The Carbon Trust 9 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Future Visions A generic design incorporating the improvements highlighted in the previous sections has been developed as the future vision of OWC technology. The generic design is a near-shore OWC device. The exact nature of the generic device, its geometric form and materials of construction are merely one future vision. The aspects considered in this section could be applied to a number of OWC devices and the most successful will emerge once a number of these fundamental design exercises have been worked through. The designs that are ultimately successful will most likely be the ones that can deliver the highest learning rate. 9.1 Location An assessment method was used to rank areas around the UK in terms of their potential for construction and operation of the generic OWC [Section 5]. The top twelve UK near-shore areas identified were: 1. Shetland Islands 2. Islay, Jura 3. Orkney Islands 4. Tiree 5. The Small Isles 6. Colonsay 7. Isle of Lewis and North Harris 8. Benbecula 9. North Cornwall / Devon 10. North of Scotland 11. North Uist 12. South Uist In developing a test case future vision, Islay has been chosen as a development location. Although not the highest ranked it does allow some of the learning from the existing LIMPET device to be used. 9.2 Optimum water depth There is a need to optimise the design for water depth, distance from shore, wave height and structure loading. Such work will identify a preferred depth range in which to site a fixed near-shore device for the greatest overall capture efficiency and economy. 9.2.1 Energy vs. Water Depth When considering the development of a shoreline or near-shore device, the energy losses from offshore locations into near-shore and shoreline locations have to be determined. The main energy loss mechanisms are related to refraction and shoaling, seabed friction and wave breaking. The seabed profile has a significant effect on the available energy at inshore locations. A shallow sloping seabed is more likely to create more energy loss mechanisms such as seabed friction and wave breaking than a steep sloped seabed. It is recommended that reporting of wave capture efficiency is based on the energy flux at the 20m contour. Studies on the near-shore wave climate have typically been carried out by adjusting offshore data for near-shore conditions. Data on the reduction in wave energy with depth has been less widely Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 99 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report published so a typical calculation was performed using hindcast data corrected for shallow water effects provided for offshore Islay by Argoss [57]. This gives an energy versus depth relationship as shown in Figure 9.1. Energy Flux 28.0 24.0 kW/m 20.0 Pierson-Moskowitz JONSWAP 16.0 12.0 8.0 4 8 12 16 20 Depth m Fig 9.1 Energy Flux versus Water Depth Figure 9.1 shows that the penalty in reduced energy flux only becomes marked with water depths below 9m. The choice of a Pierson-Moskowitz spectrum [58] gives a 2% greater resource value than the peakier JONSWAP spectrum developed for fetch-limited conditions. It may be more appropriate for shallow water spectra, such as the TMA spectrum, to be used for energy flux determination as these include the energy that is shifted from the peak due to wave breaking [59]. This could have a bearing of capture efficiency. 9.2.2 Wave Loading versus Water Depth The wave loading on a caisson structure can be established by using Goda’s formula in reflecting conditions. In impacting conditions, the approach of Allsop and Vicinanza [64] can be used together with an assessment of the lateral and rocking natural periods of the caisson structure. Using a typical design, the variation in wave loading with water depth was assessed as shown in Fig 9.2. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 100 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report 1400 Horixontal Load (kN/m run) 1200 1000 800 Goda Impacting 600 Design Load 400 200 0 6 7 8 9 10 11 12 13 14 Water Depth (m) Fig 9.2 Gravity Structure Wave Loading versus Water Depth This shows that depths of 9 to 10m are promising in terms of minimising wave load whilst maximising available wave energy. 9.2.3 OWC cost versus water depth The results of the wave load determination can be used to perform outline sizing of structures capable of resisting the loading in sliding and overturning. Designs for four types of structure were considered: • Concrete gravity substructure on sand (or gravel/rock) foundation with sand ballast • Concrete gravity substructure on stiff clay foundation with sand ballast • Steel gravity substructure on sand foundation with sand ballast • Piled steel structure with steel cylindrical collector structure with subsea wave guides The capital costs were normalised against the minimum cost concrete substructure on the sand foundation. The results are shown in Fig 9.3. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 101 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report 2 1.8 Relative cost (min sand cost = 1.0) 1.6 1.4 Relative cost concrete caisson medium-dense sand Relative cost concrete caisson stiff clay Relative cost steel piles 1.2 1 0.8 Relative cost steel caisson 0.6 0.4 0.2 0 6 7 8 9 10 11 12 13 14 Depth (m) Fig 9.3 Assessment of CAPEX versus water depth The structure size and cost in Fig 9.3 follow a similar trend to the wave loading water depth relationship. Although structures in the minimum water depth considered appear cheapest, costs exhibit a second minimum between 8 and 10m. The most cost effective solution is the concrete caisson structure on stiff clay soil. However, a survey of surface sediments around the target areas for near-shore OWC development showed a greater prevalence of sand or rock at the surface. Sand/rock foundations have thus been considered as the future vision. Steel caisson structures of similar geometry to the concrete caisson (i.e. relatively continuous structure with a collector width similar to the device width) appear less favourable because of the cost of steel fabrication compared to concrete construction. However, a more favourable cost for the steel caisson might be obtained by reducing the collector width at the water line and using subsea guide walls, as with OSPREY and Port Kembla. This might reduce capture efficiency, however, thereby negating some of the cost saving arising from reduced wave loading. Based on this assessment, a concrete caisson OWC appears most favourable for near-shore installation. This evaluation also shows that the rate of increase of cost with water depth is just less than proportional to water depth squared for depths exceeding 9m, as has been used in the tidal amplitude impact assessment (Section 5). 9.2.4 Sea-bed Conditions The ideal choice for the gravity caisson would be a level sand or clay foundation. However, the most likely foundation material in the better resource areas is rock that could well have an uneven even if covered with a layer of sand or gravel. The caisson structures cannot tolerate excessive out-of-plane deformations so the sea-bed has to be prepared in some way to best suit the OWCs. An OWC founded on uneven sediments can adopt underbase grouting together with the means to break the structure free at the time of decommissioning. Rock anchors could be considered where the OWC is founded directly on rock, although this does increase the offshore work content. Siting on rock is beneficial in that solid ballast can be reduced. In economic terms, the reduced cost of ballasting is Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 102 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report considered to equate to the cost of either under-base grouting or rock anchoring in the costing exercises presented in later sections. 9.2.5 Overall Economics of Power Capture against OWC CAPEX If the curve of available power versus water depth is combined with the average OWC capital cost, a further trend curve can be prepared as shown in Fig 9.4. This clearly shows that it is advantageous to site the device in around 10m water depth. 1.4 Relative capital cost of power production 1.3 1.2 1.1 1 0.9 0.8 6 8 10 12 14 Depth (m) Fig 9.4 Relative capital cost of delivering power versus water depth 9.3 Structure 9.3.1 Design description Having established the ideal coastal area and optimum depth for the proposed near-shore device, the wave loading regime and other design drivers can be assessed. The device principal dimensions were established for the installed depth and wave climate to ensure that the wave trough does not cause chamber broaching, that the amplified wave within the chamber does not cause turbine deluge, and that the device is not significantly over topped. From these constraints a caisson was developed that would have an installation draft less than 8m. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 103 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report OWC Finite Element Analysis Stresses A reference design was developed for conditions offshore Islay in 9m water depth to chart datum and tidal amplitude of 2m. Tow out conditions were analyzed to establish internal cell pressures and assess device torsion. The ballasting requirements both for device stability at float out and to resist horizontal loading, sliding, and overturning once installed was calculated, as well as checking the peak base contact pressure. The chamber front wall wave loading was also analyzed to check the structural integrity of the caisson. OWC Analysis Deflections 9.3.2 Foundation The foundation design has been based on medium-dense sand conditions. Such foundations can be made stable in sliding and overturning through the addition of solid ballast material. The device has been configured to allow sand ballasting and the ballast chamber has been configured so that the ballast is best placed to resist overturning. Experience has shown that, where sandy sea-beds are found, they are normally acceptably flat for directly placing the OWC on the sea-bed so that under-base grouting is not required. The foundation design of caisson structures could follow the established Det norske Veritas (DnV) method used for oil and gas installations [65] or the International Navigation Association (PIANC) Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 104 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report approach used for caisson breakwaters [66]. The PIANC approach accepts a greater probability of foundation failure than is inherent in DnV and will thus lead to lower solid ballast requirements for gravity foundations. The PIANC design guidelines recognize that near-shore wave protection facilities are usually multiple structures and the failure of one unit can perhaps be tolerated. There is a lower threat to personnel safety on an unmanned caisson compared to a manned offshore oil and gas installation. Both these considerations would apply to near-shore caisson OWCs so it would seem appropriate to consider the PIANC approach for design. It would also be a useful exercise to consider overall safety and reliability levels that ought to be achieved for these unmanned devices. This work is currently being undertaken by DnV for the Carbon Trust. 9.3.3 Device concept This is illustrated below: 9.3.4 Scour Protection Scour protection is required, particularly to the front of the support piers and in front of the collector chamber, to prevent foundation undermining. This would be a two-layer graded rock blanket. A steel skirt is provided to allow the structure to be founded below any looser sand at the surface and to inhibit undermining between device emplacement and the placing of scour protection. Similar arguments to the risk-based approach to foundation design can be advanced for the design of scour protection. Complete loss of scour protection would lead to undermining of foundations on sand but a design that permits some loss of material in larger design events followed by inspection and maintenance is probably a more cost-effective approach than designing the scour protection to withstand the worst conceivable conditions without damage. 9.3.5 Construction Construction of near-shore OWCs can take place away from the offshore site making weatherdowntime considerations less relevant. There is no requirement for the design and construction of a temporary cofferdam and bund/cofferdam overtopping leading to possible formwork damage does not have to be considered. The adoption of a construction site dedicated to OWC production allows much greater potential for productivity gain leading to lower capital cost. The initial stage of construction would be the preparation of the dry dock. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 105 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report A suitable dry dock for multiple device construction would be Hunterston Marine Yard, located near Clydeport 30 miles south west of Glasgow on the west coast of Scotland. The dry dock facility covers an area of 90 acres and was a specialist in the construction and decommissioning of offshore structures. Hunterston’s main features are: Dock Floor Length 230 m Dock Floor Width 150 m Width (Earth Bund Entrance) 150 m Maximum Depth (In Dock) 14.5 m Maximum Depth (At Sill) 11 m The yard benefits from good road communications, easily accessible from Glasgow and has rail facilities available from Clydeport’s adjacent Hunterston Coal Terminal site. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 106 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Once the dock is prepared, and the base slabs constructed slipforming of the buoyancy tank piers can take place. The OWC chamber cell modules would be constructed horizontally, for ease of construction. The chamber modules are then rotated into position The balance of plant would be fabricated off site and installed as a complete containerised module into the buoyancy pier. It is envisaged that there would be three generators per device. This ensures that Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 107 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report wave fronts that are not totally parallel to the device do not cause an out of phase wave pneumatic contribution to a single turbine. Due to the requirement for installation in relatively shallow water, and to reduce the size of the buoyancy piers (thus reducing wave loading), the chamber volume is required to provide buoyancy during transportation. This would be achieved by placing buoyancy bags in the chamber modules. The Dunlin A Platform utilised this technology during float-out. Example : Concrete Pipe Positioning Floats With the device construction complete the dock is flooded…. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 108 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report …… and the bund removed. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 109 The Carbon Trust 9.3.6 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Installation OWC installation should follow normal working practice for the installation of offshore oil & gas platforms. A transportation sea-state can be selected based on the duration of the tow. Typically, a 10year seasonal storm should be considered for tow and installation durations that exceed 3 days. The marine transportation and installation will usually be insured and the insurer would normally appoint a Marine Warranty Surveyor (MWS) to evaluate the transportation and installation plans. The MWS would record approval to proceed with particular stages in the marine operations, once satisfied that the operations met normal industry standards and that metocean conditions were favourable. OWCs should be designed to satisfy normal intact and stability criteria for oil and gas installations [69]. The scheduling of OWC construction and installation should aim to complete all offshore installation work between typically mid-April to late September. A maximum installation sea-state of 1.5 to 2.0m Hs is the practical limit for personnel transfer to the OWC to operate the flooding system for set down. The design of caisson devices should recognize that swell conditions are likely to be present at the time of installation, even if the total sea-state is less than 1.5m Hs. Swell can cause substantial heave motions on caisson devices and the design should ideally be configured to suppress heave excitation to allow a straightforward set-down procedure. On sand sites, the installation should not proceed unless the scour protection vessel is on standby to place the initial protection material. Failure to place scour protection within around 24 hours after OWC emplacement could lead to the foundation being undermined. 9.4 Turbine 9.4.1 Turbine sizing Development machines to date have been typically of the order 500kW either as a single unit or as two 250 kW modules in series. Economies of scale are likely to be achieved for larger units. There is, in theory, no limit to the size of unit that could be manufactured. However, the practical limit for a device will be the wave energy available to the collector structure over a reasonable length of capture and the energy losses associated with wave interactions inside the collector structure. Such considerations are likely to limit the maximum energy that can be obtained such that the maximum unit size is never likely to exceed 2MW. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 110 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Optimum performance may best be achieved by designing unit capacity for commonly occurring sea states rather than extreme storm conditions. The performance would then be optimised for a greater time period and the parasitic losses (particularly on the generator) would represent a smaller proportion of average output. To permit continued operation during storm conditions wave collectors would need to be designed for partial close off to moderate the pneumatic power input to the turbine, or additional turbines brought on line. 9.4.2 Blade profile It is clear that a broad variety of blade and vane configurations is possible. Future effort should be directed to establishing the optimum configuration and, to support this, a structured development process is required. In the first instance the options should be evaluated by the use of CFD techniques, leading on to scale model tests in a wind tunnel or purpose designed test rig before final development of a prototype for field trials. All generic blade types should be considered. At all stages the aim should be to achieve acceptable turbine performance over as broad a range of air flows (sea states) as possible, thereby reducing the sensitivity to collector design. From a reliability point of view the design should aim to be as simple as possible with the minimum number of moving parts and without an overly complex control system. Limiting the number of moving parts will also deliver benefits in terms of a reduction in parasitic losses and reduced maintenance burden. The benefits of this approach are expected to be a reduction in cost of turbine manufacture (standardisation, fewer components, simpler control system), improved performance (estimated up to a factor of five compared to current prototypes) and improved reliability. 9.5 Generator 9.5.1 Specification The generator will be a doubly-fed induction generator (DFIG), i.e. a wound-rotor induction machine with an ac-dc-ac converter in the rotor circuit. The rating of the generator stator will be 750 kW electrical for the near-shore device; the rating of the rotor circuit will need to be determined following detailed modelling of the turbine and water column. To a first approximation, the rotor power is given by: Rotor Power = Stator Power × Mechanical Speed − Synchronous Speed Synchronous Speed The rating of the rotor circuit is therefore determined by the range of speeds over which the turbine is to operate. For simplicity of design, both the stator terminals and the grid-side converter terminals will be designed to connect at 400 V. 9.6 Costing 9.6.1 Caisson A generic shoreline cost was produced from a quantity take off of the LIMPET as-built structure. This was based on a modified design-then-build approach where the design development risk is taken by the operator and the constructor and installation risk is taken by suitably experienced contractors in their respective fields. A novation arrangement, whereby the OWC designer completes the detailed design for the civil contractor, would allow constructability input to be brought into the design, helping to reduce construction cost. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 111 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report From the scheme near-shore design a cost was produced for the production of a single device. This cost was then modified for the construction of a 10 device production run such that certain economies of scale could be applied, then again with productivity discounts applied to certain construction activities. Economies of scale cost reductions include• Preparation / modification of dry dock • Re-use of pre-fabricated formwork • Repeat design • Offshore SI • Tug / ballast vessel mobilisation • Flotation bag re-use. Increased productivity discount rates were applied to – • Pre-fabricated rebar panels • Slipform preparation / re-use • Installation procedure • Plant and equipment usage. 9.6.2 Turbine Manufacturing experience to date is limited to a small number of development machines and costs of production are consequently high. In addition the cost breakdown between the major constituent parts of the machine (turbine, generator, control system) is not readily available from the developers. While costs for mass production would be expected to fall substantially compared to those for small volumes of prototype machines, it is difficult, if not impossible, to give an accurate prediction of future manufacturing costs based on current experience. The commercial viability of OWC technology will be determined by the total costs for initial construction (and hence debt financing) and ongoing maintenance in comparison to the expected income stream over the life of the plant. For an end user, the breakdown of construction costs between the constituent parts is usually less important than the overall unit cost and in evaluating the commercial viability of a project it is standard practice to consider the capital cost of plant in terms of cost per kW installed. Costs to date for an OWC turbine, generator and balance of plant range from around £900/kW (excluding civil work) at LIMPET to around £2500/kW at Port Kembla (including design development). The Port Kembla team foresee this cost reducing to £625/kW by the time 1000 units have been constructed. The Port Kembla costs have been queried, as the device does not seem likely to become economic if correct. Instead, the LIMPET costs have been used as the starting point for future improvements. 9.6.3 Generator The generators proposed for the reference design are the doubly-fed induction machines now almost universal in the wind industry, and the costs are based on figures provided by wind turbine manufacturers. The figures cannot be used directly because the requirements for the generator are not the same as for a wind turbine: • In the wind industry it is now standard, due to the large distances between turbines, to include a step-up transformer and high voltage switch with each generator. For OWC devices, it may be more economical to cable between generators at low voltage, and share a transformer between two or three generators. The step-up transformer and HV switch are therefore not included here but in the grid connection costs. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 112 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report • Even off shore, wind turbine plant is elevated well above the salt spray, and protection against moisture ingress is often somewhat rudimentary. By contrast, wave power devices are potentially fully exposed to the waves, and a higher degree of protection is required. • The nature of the power fluctuations for wind power (deriving from gusts, and from the blades passing the tower)) differs from that of the fluctuations due to waves. Some custom tuning of the controller software may be required to suit the wave climate of individual sites. While the wind industry is now concentrating on large machines, typically above 600kW, the reference OWC design uses 2 x 375kW machines (the few wind turbine manufacturers still offering 375kW machines use conventional induction machines). A choice will have to be made between the use of cage induction generators with a fully rated converter drive and the DFIG currently favoured by the wind industry. It is likely that initial commercialisation will use conventional cage machines. The DFIG may become favoured in the long term once there is a significant sub 1MW market for DFIG. For the 750kW reference design considered, the choice of cage induction generator or DFIG will not significantly affect the BOP costs. The cost of a 250kW generator, together with associated plant and a suitable enclosure, has been estimated at £100,000. This gives a cost for the generator of £400,000 per megawatt. If the cost of the enclosure, and the cost of installing the generator in it, are accounted elsewhere in the model, a figure of £250,000 per megawatt may be achievable for the generator and auxiliaries alone. If larger generators are used, such as are now standard in the wind power industry, the costs may be reduced even further. 9.6.4 Grid connection The purpose of these studies is to establish the approximate cost of connecting OWC generating modules to the grid in the regions identified as most suitable in phase 1 of the project. The figures should be treated with some caution; in particular, the following caveats apply: • No actual sites have been selected at this stage, and the costs given are indicative for each region. The costs for actual sites will depend strongly on the site chosen. • Where a major reinforcement, such as a 132 kV cable, is indicated, the cost of the reinforcement is largely independent of the capacity installed. In such cases, the permegawatt figures quoted refer to installed capacities close to the limit stated. Lower capacities, unable to achieve the same economy of scale, will have higher costs per megawatt. • The costs quoted assume that development is in small clusters of no more than a few megawatts each, and that each cluster requires switchgear, step-up transformer(s), and overhead line to connect to the system. The costs are quoted in most cases for 11/33 kV and 132 kV. 11 and 32 kV are treated together because the cheaper plant at 11 kV is balanced by the smaller cluster size that can be accommodated. 9.6.4.1 Orkney and Shetland Orkney and Shetland are two groups of islands off the north coast of Scotland. The Orkney islands are separated from the mainland by a strait, the Pentland Firth, which at its narrowest is little more than 10 km wide. This is crossed by two 33 kV cables, with a capacity of 20 MW each, connecting the Orkneys to the mainland. Demand on the Orkney islands varies from a summer minimum of 6 MW to a winter maximum of 31 MW [52]. The supply is therefore adequate, but not secure; security is provided by a 16.5 MW diesel power station at Kirkwall, and there is a gas turbine of unknown capacity, apparently associated with the oil terminal on Flotta [53]. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 113 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report The capacity for generation on Orkney is 26 MW if a firm connection is required, or 46 MW if an interruptible connection is used (i.e. up to 20 MW would be tripped on the loss of a cable to the mainland). Above this level, load following would be required, or an additional cable to the mainland. The price of an additional 33 kV cable has been estimated at £15 million. In any case, additional voltage support would be required. The Shetland islands are approximately 213km, by a likely cable route offshore, and have at present no connection to the mainland. The maximum demand is believed to be around 50 MW, so minimum demand is unlikely to exceed 10 MW. At present all the electricity in the Shetlands is supplied by a 67 MW diesel power station at Lerwick; a replacement power station, or possibly a DC link to the mainland, are being considered [54]. 11/33 kV Connection The islands provide two variants of the connection problem: on the western part of Mainland Orkney and the northern two-thirds of Mainland Shetland, the power lines run 20 km or more from the coast. On most of the smaller islands, the southern peninsula of Mainland Shetland, and the east coast of Mainland Orkney, power lines run within 10 km of the coast. Substations are plentiful, and a reasonable density of wave power generators might be connected by perhaps 10 km of overhead line per 5 MW of generation. Each cluster of around 5 MW would also require switchgear and a step-up transformer. Smaller clusters might be able to connect at 11 kV. This would allow the use of cheaper switchgear and transformers; but, apart from the smallest clusters, an 11 kV connection would require a longer overhead line (in order to connect at a suitable substation), and the price per megawatt remains much the same. As noted above, the maximum (cumulative) size for such schemes is around 40 MW on Orkney plus 10 MW on Shetland. The price (based on Central Networks data) is around £100,000 per MW. 132 kV Connection A 132 kV connection on Orkney or Shetland would require a new cable. The most likely route is from the supergrid substation at Dounreay to a new substation at Stromness (for Orkney) or Scalloway (Shetland). The cost of this cable would dominate the cost of the project: it has been estimated at £40 million for Orkney, or perhaps £150 million for Shetland, dependent on capacity. Connecting generators to the cable substation would cost only slightly more than connecting to the existing 33 kV system, since the latter could transmit much of the power required. The capacity of such a cable would be between 100 MW and 200 MW, and would not be secure. A reasonable estimate of the cost of connecting generation would therefore be £1.5 million per megawatt on Shetland, or £400,000 per megawatt on Orkney, provided the full capacity of the cable is utilised. Orkney 11/33 kV, up to 40 MW £100,000 per MW 132 kV, 150 MW £400,000 per MW Shetland 11/33 kV, up to 10 MW £100,000 per MW 132 kV, 150 MW £1,500,000 per MW Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 114 The Carbon Trust 9.6.4.2 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Islay, Jura, Colonsay This group of islands, at what might loosely be described as the Southern end of the Inner Hebrides, connects to the mainland by a 33 kV cable across Jura Sound to the Mull of Kintyre. The 33 kV power line runs along the East coast of Jura and across the centre of Islay; in most parts of the island it is around 10 km from the presumed preferred wave energy sites on the West coast. The transmission system on Kintyre, from a generation point of view, is full. With all the connected hydro and wind power operating at full output, the 132 kV line from Inveraray to Loch Sloy is not secure: an outage of one circuit of this line could leave the other slightly overloaded. Any generation, therefore, connecting in these islands, would need a control system for load following, an intertrip, or a system reinforcement. Minimum demand on the islands is small – around 2 MW – so the limit on generation derives from the booster transformer at Tayvallich, which is rated at 15 MVA. 11/33 kV Connection Islay has two 33/11 kV substations rated at 8 MVA, but the 11 kV system on Jura is extremely weak, with 1 MVA being the highest transformer rating seen. On Islay, then, there is the possibility of connecting a small installation to the 11 kV system, while on Jura, all the installations will be connected at 33 kV. As with Orkney and Shetland, 11 kV connections are likely to be possible only for small installations, and 33 kV is likely to be required for larger projects. The economies of scale balance the increased costs of 33 kV plant, and the cost is about £120,000 per megawatt at either voltage. The link to the mainland limits the capacity to around 15 MW. Larger capacities could probably be achieved by reinforcing this link with a second cable. Best use of existing assets would be achieved by routing the cable from Port Ellen to West Park Fergus, on the Mull of Kintyre. This would be expensive – around £20 million – but cheaper options are possible if a lower capacity is acceptable. This gives a total cost of around £500,000 per MW. 132 kV Connection A 132 kV connection is required if large numbers of generators are to connect. This would involve a new cable to connect the islands; 132 kV infrastructure on the islands themselves; and a reinforcement of the existing 132 kV system between Kintyre and the rest of Scotland. The cost of this reinforcement is approximately the same whether the existing lines are re-strung between Loch Sloy and the tee point for the new cable, or a new line is constructed from Port Ann to Dunoon. It is largely independent of the amount of generation to be connected, so the 132 kV connection is only worth considering if development proceeds on a very large scale 9.6.4.3 Colonsay and the Small Isles The Small Isles are a group of islets off the East coast of Jura. The 33 kV system is relatively close, but water must be crossed. The total cost may be assumed to be the same as for Jura itself. Colonsay is a larger island about 15 km off the West coast of Jura, and a similar distance off the North coast of Islay. There is at present no 33 kV connection; since it would connect via the Jura 33 kV system, generation installed on Colonsay would use up the capacity on Jura. It is unlikely to be beneficial to locate generation here rather than on Jura itself. Islay / Jura / Small Isles 11/33 kV, up to 15 MW £120,000 per MW 33 kV, up to 40 MW £500,000 per MW 132 kV, 100 MW £550,000 per MW Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 115 The Carbon Trust 9.6.4.4 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report North Devon and Cornwall This coastline runs diagonally south-west to north-east, with a few small bays along most of its length and one large bay at Barnstaple. Some 30 km of coastline in the Bristol Channel also belong to Devon, but this has less wave energy and a greater tidal range than the rest of the coast, and accordingly has not been studied. Rather, the preliminary studies showed that part of the southern Cornish coast, from Land's End to Lizard Point, had similar conditions to the north coast and this is included. South-west England is much more densely populated than Scotland, and this coast is well-served with 33 kV and 132 kV infrastructure apart from a short stretch near Bodmin, where the moor reaches almost to the coast, and another stretch north of the Tamar [55]. Unlike most of the Scottish locations, this coast has several 132 / 33 kV substations, and the capacity of the system is quite high provided the generators are not all connected in one neighbourhood. It is therefore unlikely that a 132 kV connection would be required, and only the 33 kV option has been studied. 33 kV Connection There are few places on this coast where the 33 kV lines are more than 8 km away, and there are long stretches where the nearest 33 kV line is within 5 km. On the other hand, the high population density means that some of the connection to the 33 kV system may require underground cable. Assuming as elsewhere a 5 MW block to connect at 33 kV, with a 5 km connection which is 50% overhead and 50% underground, the price is comparable with a typical Scottish site, at around £600,000, or £120,000 per megawatt. If the entire connection is constructed as overhead line, this falls to around £400,000 or £80,000 per megawatt. A careful selection of sites could utilise seven or eight bulk supply points: Camborne, Fraddon, Hayle, Rame and Truro in west Cornwall; St Tudy and Pyworthy either side of Bodmin Moor; and East Yelland if development extends into Barnstaple Bay. Excluding East Yelland, the total load on these sites is about 460 MW at winter peak, so it may be expected to be around 90 MW at the summer minimum. One may therefore assume that perhaps 100 MW could be accommodated with minimal system reinforcement, and maybe 300–400 MW with suitable uprating of 33 kV circuits, and voltage control plant. For a development of up to 400 MW, it is likely that most of the individual installations would be larger than the 5 MW assumed elsewhere in this study. The consequent saving on switchgear means that the price is kept to around £50 million, or about £125,000 per megawatt. Cornwall and Devon North Coast 9.6.4.5 33 kV, up to 100 MW £80,000 per MW – £120,000 per MW depending on cable requirement 33 kV, up to 400 MW £125,000 per MW Tiree, Coll and Mull The islands of Mull, Tiree and Coll belong to the Inner Hebrides, between Jura to the South and Skye to the North. The isle of Mull derives its supply from two 33 kV cables connecting it to the mainland, of which only one is switched in at any time. There is a small generating station on the island, at Tobermory. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 116 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report The isles of Coll and Tiree derive their supply from a small diesel plant on Tiree. As a backup there is an 11 kV cable that can import power from Mull. These islands, like Islay and Jura, are connected to the Kintyre 132 kV system. As noted above, this system already contains as much generation as it can securely accommodate; intertrips are necessary even for small projects, and reinforcements for more extensive developments 11/33 kV Connection The 33 kV line runs around the Northern side of Mull. There are few places where it approaches the western (exposed) coast, and a long peninsula (the Ross of Mull) that appears to have little or no electrical infrastructure. As an average, installations may require around 20 km of overhead line to connect to the network. The capacity, limited by the cable to the mainland, is around 10 MW. It is not known where the 11 kV line runs on Coll and Tiree, but it is unlikely that any installation will be further than 10 km from it. The capacity on these islands is very small, though – around 2 MW. Connecting within the existing capacity costs in the region of £130,000 per megawatt. To increase the capacity would require an additional 33 kV submarine cable; a capacity of around 20 MW could be achieved at a cost of about £300,000 per megawatt. 132 kV Connection This involves reinforcing the line from Oban via Inveraray to Loch Sloy, and building a new line and cable to Mull. Once again the cost of this is largely independent of the capacity, and it only becomes competitive on a per megawatt basis above about 100 MW. Mull / Coll / Tiree 9.6.4.6 Coll/Tiree, 11 kV, up to 1 MW £130,000 per MW Mull, 11/33 kV, up to 10 MW £130,000 per MW Mull, 33 kV, up to 25 MW £400,000 per MW Mull, 132 kV, 100 MW £400,000 per MW Lewis and North Harris The Isle of Lewis (of which North Harris is a part) lies at the Northern end of the Outer Hebrides. It connects to the mainland via the Isle of Skye, with a 33 kV cable across the Little Minch, the strait that separates the islands. There is 132 kV infrastructure on the island, and an interconnector at this voltage appears to be planned, but is not shown on the system diagrams for 2010. The existing inter-connector has a capacity of around 20 MW, which is not secure. In addition there is around 9 MW of minimum demand. The total capacity is thus in the region of 30 MW. 11/33 kV connection Lewis is a large island, and the 33 kV system does not go very close to the coast. By the same token, there appears to be a reasonable 11 kV system reaching the scattered settlements, with a number of 33/11 kV transformers rated between 2 and 8 MVA. Assuming a cluster of about 5 MW capacity could connect to the 33 kV system with about 20 km of overhead line, and a cluster of about 2 MW could connect to the 11 kV system with 15 km of overhead line, the cost of connecting generation on the island works out around £130,000 per megawatt. 132 kV Connection The capacity of the system could be markedly increased by adding a 132 kV cable from Harris Grid Substation to Ardmore. This would connect with the 132 kV system on Skye, and while this is only a Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 117 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report single circuit, it could provide 100 MW of capacity if backed by suitable intertrips. This capacity would apply to all the generating plant on Skye and in the Outer Hebrides, and further reinforcement would be necessary to accommodate (say) 100 MW on Lewis, 20 MW on Uist and 20 MW on Skye. The cost of the 35 km cable has been estimated at £30 million, adding some £300,000 per MW to the cost of connecting the generation. Isle of Lewis 9.6.4.7 11/33 kV, up to 30 MW £130,000 per MW 132 kV, 110 MW £400,000 per MW Uist Uist, for the purposes of this study, comprises a string of islands in the Outer Hebrides, of which the major members are North Uist, Benbecula and South Uist. A 33 kV system covers the three islands, running (for once) close to the West coast, although much of North Uist is not served by 33 kV. Like the Isle of Lewis, Uist is connected to the mainland via a 33 kV cable to Ardmore; there is also a 12 MW diesel power station at Loch Carnan. The cable can carry about 20 MW, and the islands have a minimum load of about 2 MW, giving a total capacity of 22 MW. As with most of the other island systems, this capacity is not secure. 11/33 kV Connection The topography of the coast is quite different on the East and West coasts of the islands, and wave power development is likely to see a bias to one or the other. (Gently shelving beaches, as on the West coast, tend to reduce the energy, while cliffs and deep water, as on the East coast, tends to make installation expensive.) On the West coast, the 33 kV power lines are within 5 km of the coast, and readily accessible. This leads to the cheapest connection costs observed [for any of the Scottish sites], around £80,000 per megawatt On the East coast, and most of North Uist, the power lines are much further away, and the cost of connection is greater. A small amount of generation (perhaps 2 MW on the whole of North Uist) could be connected at 11 kV, for a similar cost to the West coast schemes; developments over most of the islands would require longer 33 kV connection, leading to a cost of around £120,000 per megawatt. 132 kV Connection Unlike Lewis, Uist possesses no 132 kV infrastructure; and the crossing to Skye is slightly further than that from Harris, leading to a more expensive scheme. The capacity would be around 100 MW, but this would have to be shared with Lewis and Skye. Allowing about £40 million for the cable, the cost of connection comes to around £600,000 per megawatt. Uist North Uist, 11 kV, up to 1 MW £90,000 per MW N Uist and East Coast, 33 kV, up to 20 MW £120,000 per MW West Coast of S Uist / Benbecula, up to 20 MW £80,000 per MW 132 kV, 100 MW £600,000 per MW Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 118 The Carbon Trust 9.6.5 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Operation and Maintenance To minimise operating costs, future commercial installations will need to be designed for fully remote, unmanned operation. It follows that the control system must be robust and have a high level of reliability. Remote monitoring and diagnostic capability will be an essential requirement. In much the same manner as wind turbines have a permissible range of wind speeds for which operation is possible, it is likely that OWC installations will have a permissible range of sea states. The control system must therefore be capable of implementing fully automatic start up and shut down determined by measured sea state. The optimum method for defining and measuring sea states will need to be developed. Maintenance requirements for the turbine and electrical equipment are expected to be generally low. A target of at least 8,000 operating hours between maintenance inspections should be possible. Remote monitoring should eliminate the need for frequent on-site visual inspection of the plant. An availability of 95% or more should be attainable for mature technology. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 119 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report 9.7 Costing Summary Device Generic Shoreline 1 x Near-shore 10 x Nearshore 10 x Nearshore (with productivity benefits) Total frontal width (m) 20 82.5 825 825 Rated power (kW) 500 2,250 22,500 22,500 1,480 6,100 61,000 61,000 £1,762,605 £4,884,376 £40,088,497 £33,278,908 £310,000 £1,795,000 £17,250,000 £12,750,000 £2,072,605 £6,679,376 £57,338,497 £46,028,908 85 % 73 % 70 % 72 % £4,145,210 £2,968,612 £2,548,378 £2,045,729 £103,630 £80,962 £69,601 £55,793 Annual power capture (no outage) (MWhr/year) Structure cost (incl. temp. works / installation) Balance-of-plant and grid connection cost Total Cost Structure cost as % total cost Cost / MW rated capacity Cost / m collector Power Production Cost (10% discount rate) 17.5 9.6 p/kWh Nearshore Cost Split Shoreline OWC Cost Split 12% 3% 19% 3% Temp Works / Site Prep 10% 6% Temp Works / Site Prep Structure Structure Turbine / Generator Elec Connection Turbine / Generator Grid Connection 24% 57% Installation Vessel Costs 66% A detailed cost build up for the construction of the OWC structure has been included in Appendix C. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 120 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report 9.8 Risk The potential risks in terms of safety, cost overrun, programme etc, that the future vision development may encounter have been considered, divided into the project stage when such problems may be encountered. The risks considered are the same as those in the stage 1 report, allowing direct comparison with existing devices. A method of risk reduction has then been applied and the residual risk classed as low medium or high. Low risks would thus require no further action and medium risks would require a contingency sum assigned. The remaining high risks help to highlight the focus of further R&D of this technology. 9.8.1 Risk Schedule Stage Aspect Comment Residual Risk H, M, or L Feasibility Site Investigation Design Energy resource assessment While this has been a problem for a number of the existing demonstration devices, an adequately funded project would be able to obtain sufficient data to accurately assess the available wave resource. L Costing inaccuracy Detailed cost plans and scheme design should be developed to a level suitable to obtain sub-contractor prices and buy-in prior to committing to project. A contract strategy should be set that considers risk management / risk ownership. However, a cost contingency must be included in the build up for inaccuracy due to the pioneering nature of the development. M Schedule inaccuracy Device construction in a dry dock facility mitigates the impact of adverse weather. Construction by slipforming and other known technology should increase the accuracy of the programme estimate providing the promoter employs contractors with adequate experience. L Sea bed conditions Risk reduced if initial investigation is thorough with sufficient cost allowance. The percentage cost contribution of the SI is reduced for a large-scale development. L Bathymetry As above L Rock integrity As above L Concept freeze Do not commit to final investment until sufficient engineering completed L Scour / undermining More prevalent the closer inshore the device is placed, which pushes the development into the deepest water that is practicable. Sea bed preparation must be included in the cost build up. L Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 121 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Stage Aspect Comment Residual Risk H, M, or L Onshore Construction Offshore Installation Chamber efficiency Biggest impact on the project economy, but the most difficult to mitigate / estimate through model test and calculation. H Turbine efficiency Considerable design development needed before full potential can be realised. CFD modelling of the turbine and OWC is a complex undertaking. H Control systems The greatest areas for development are around OWC tuning, and turbine blade pitch control. M Peak wave load est. Understanding of impacting wave pressures has improved over the period of development of these devices L Access to site Dry dock access is very good. L Component / material delivery As above L Contractor skills / equipment Locally available skills L Productivity Productivity gain through repetition. A covered construction yard could be contemplated. L Late delivery of components Programme flexibility and concrete modular construction allows activities to continue. L Errors in fit up As above L Temporary works Dry dock construction minimises the reliance on the competence of the temporary works. L Workforce safety Controlled environment of the dry dock is a safer working environment. L Weather down time Dry dock is less susceptible to weather down time. L Adverse sea state Devices should be made as sea-state tolerant as possible, however programme contingency should be allowed for. M Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 122 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Stage Aspect Comment Residual Risk H, M, or L Operation and Maintenance Ballast placement (solid/water) Devices should be stable on the sea-bed without ballast in moderate sea-states. This is well understood from the offshore industry. L Bed preparation Difficult in exposed sites. Sites should be avoided that would require bed preparation. M Skirt penetration Suitable device location sites should be chosen such that with adequate SI the correct skirt can be designed. L Commissioning Offshore activity attracts a degree of programme uncertainty. M Shore connection Offshore activity attracts a degree of programme uncertainty. M Tug / barge availability Large-scale development would help to secure sufficient tug operator commitment. L Prior experience Lack of exact experience, however similar skills to other offshore activities. Programme contingency should be considered. M Access Offshore activity attracts a degree of programme/ availability uncertainty. Maintenance / availability assessment should be included in income estimate. M Number of moving parts Any moving parts must be accessible and replaceable. Modular approach to balance of plant. L Davits / cranes / runway beams Maintenance provision must be built-in from the outset L Marine fouling M Fatigue Concrete structures are less fatigue sensitive. BOP cost and design should mitigate such risks. L Chamber blockage Only an issue on shoreline devices L Integrity inspection Offshore activity attracts a degree of programme uncertainty. Concrete structures have an excellent maintenance free record in seawater if well constructed from good quality materials. M Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 123 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Stage Aspect Comment Residual Risk H, M, or L Deluge of plant rooms Modular BOP container design to be watertight. L It can be seen that the highest residual risk with the greatest impact on any future development is an inaccurate estimate of the chamber wave to pneumatic efficiency. The residual risk in the future vision has been reflected by applying a 10% contingency to estimated costs in the economic modelling. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 124 The Carbon Trust 10 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Economics Section 7 assessed the relative merits of shoreline versus near-shore OWCs. Section 8 outlines the potential and technical proposals that could improve the performance of OWCs, with section 9 describing a future vision of a device that has incorporated these improvements. In order to evaluate the effectiveness of these improvements economic models of a shoreline and a near-shore device have been created. The method of evaluation, results and conclusions are summarised in the following sections. 10.1 Economic models The economic models produced uses the project Net Present Value to test the project commercial viability to varying CAPEX, power production cost, wave power, and capture efficiency. It is based on UK costing and power pricing regimes. Other countries have different construction cost, power cost and ways of encouraging renewable power generation. This would make direct use of these financial models outside the UK somewhat misleading. However, as an initial indicator, the total required power sales production cost to achieve economic viability can be examined. 10.1.1 Common assumptions The assumptions listed below represent our current best estimate of the OWC design parameters. The effects of upper bound and lower bound variables have been tested by the economic model and are reported in the sensitivities section. A wave power at 20m water depth of 34kW/m has been assumed to be present in any future development site. Other assumptions relating to size, location, input energy etc. are set out below. 10.1.1.1 Assumed yearly averaged efficiencies Type of energy conversion Structure / device Assumed Efficiency Wave to pneumatic (The energy coming in to the advice is taken to be the maximum width of the OWC facing the waves multiplied by the energy flux passing the 20m contour) Oscillating water column 42.0* Pneumatic to mechanical Wells turbine 65.0 Mechanical to electrical Generator 91.0 % Overall efficiency 24.8 * Shoreline efficiency would be reduced due to sea bed friction in shallow water, however with no specific site chosen actual sea bed loss has not been calculated and a capture efficiency equal to near-shore has been used for direct comparison purposes. Also, the cliff effect tends to increase efficiency compared to an isolated near-shore OWC. In addition to the above, a 2% transmission loss has been assumed. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 125 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report 10.1.1.2 Assumed Operating, Maintenance and Insurance costs • A decommissioning cost at 10% of CAPEX has been assumed (inflated). • A Crown Estate rent of 2% of energy revenue • Contractors all risk insurance is assumed at 2% of initial CAPEX. • Cost overrun insurance is set at 3% of the first year revenue. • An operational insurance of 0.8% of the CAPEX has been assumed. • Business interruption insurance of 2% of energy revenue • Maintenance cost of 1.5% of BOP The total operating cost equates to £16.60/MWh generated. This figure is in line with experience from offshore wind farm operations and similar to that suggested by other authors [72]. 10.1.1.3 General Financial assumptions • A 10% contingency on initial CAPEX has been included • 2.5% rate of inflation • Renewable Obligation Certificate value assumed to inflate over life of project. • Climate change levy remains constant • Capital grant financing has not been included in model • Tax liability has not been included • The equity discount rate has been plotted against varying CAPEX, power production cost, wave power, and capture efficiency to examine the project Net Present Value as a test of the project’s commercial viability. 10.1.1.4 • Shoreline assumptions Each device has a 500kW generator using a 20m collector frontage. 10.1.1.5 Near-shore assumptions • Each 750kW generator has a 27.5m collector frontage made up of 20m open plus 7.5m collector focusing structure. 3 such units / generators per device • A development field of 10 devices. This allows certain economies of scale to be applied, reducing the balance of plant cost to £500/kW, and increasing the OWC structure construction productivity. • A modular system for the incorporation of the BOP into the device structure assumes interchangeable units. This combined with the simple nature of the BOP means that only 3% of the total operating hours have been assumed to be lost to maintenance activities. It should be noted that wave availability is accounted for in pneumatic capture efficiency figure. • An initial Third Party insurance cost of £100,000, inflated over the project period. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 126 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report 10.2 Sensitivity assessment The main variables that influence the outturn power production cost are the development size, wave resource, device efficiency (capture, turbine and generator efficiency), and the initial capital expenditure including civil, Balance of Plant, and grid connection costs. Section 9.6 has highlighted the cost reduction possible as the scale of the development increases. Shoreline v Near-shore Power Production Cost 24.00 22.00 20.00 p/kWhr 18.00 16.00 14.00 12.00 10.00 8.00 6.00 4.00 0 5 10 15 20 25 Development Size MW Shoreline Trend Nearshore Trend The above figure shows that below 2 MW shoreline technology is more cost effective. The rate of the cost reduction with increased development size plateaus for shoreline devices at approximately 5 MW. This is because a single construction location would not be available for such a large wave capture frontage, the development site would become more disparate and economies of scale are lost. Near-shore devices are less viable for small-scale development due to the dry dock and installation vessel mobilization costs. These costs reduce quite quickly with development size as the mobilization costs are shared, leading to the fairly pronounced change in curvature above. However, cost savings would also plateau as a development size reaches 30 MW as a second dry dock facility would be required and multiple vessels needed to support multi-location activities. This would assume a reasonably compact construction programme of approximately 18 months. While the possible cost improvement by development scale should be recognized, the development size will largely be governed by the developer’s financial commitment and project ambition. 10.2.1 Upper bound / Lower bound sensitivity assessment Each of the other variables has a range of possible values, a worst-case scenario, a current best estimate, and an upper bound value that may be achieved with further development. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 127 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report To assess the sensitivity of the project to each variable, the improvement scale of these factors has been ranked, with the best estimate ranked zero with a +/- 5 limit. Each step change from zero has an increasing degree of difficulty of achievement. Wave resource A wave resource of 34 kW/m has been chosen as the zero rank. This is the highest wave resource that could be expected at the 20 m contour while still offering a degree of flexibility of project site development areas. 51 kW/m should be considered the absolute maximum that could be achieved for a single development, offering little site flexibility with the high probability of suffering other detrimental factors to the project in the limited locations available. A lower range of 17 kW/m was chosen to test the viability of a wider range of site locations. Capture efficiency A yearly capture efficiency of 42% of the 20m contour resource (59% at lip) over a capture width taken as the maximum width of the OWC represents the current best estimate. Developers have estimated that 80% capture of the energy at the OWC lip should be possible. Allowing for some loss in energy from the 20m contour, a highest expected capture efficiency of 67% is suggested. A low value of 17% would represent poorer performance than any existing OWCs have reported. Turbine efficiency For an optimised design an instantaneous peak turbine efficiency of between 60% and 70% is probably a realistic expectation for a Wells or an impulse turbine with flow in either direction. With appropriate design development it should be possible to extend the breadth of the performance characteristic such that greater than 50% efficiency is achieved over a defined range of flows. Generator efficiency The probable range of mechanical to electrical efficiencies is expected to be 90-95%, with 91% the current best estimate of likely efficiency. This range will depend to a certain degree on the type of technology used such as cage machine direct drive or DFIG. The maximum of 96% corresponds to the manufacturer's upper limit. The lower limit of 86% is based on the likely result of a greater range of rotor speed and increased rotor resistance to enhance damping. Out-turn Civil Costs +/- 20% would be the typical range that civil costs could vary compared to the level of cost estimate produced for this report. Increased accuracy could be obtained through engaging project participants across the range of subcontractors involved in such a project following the production of a more detailed tender design. Greater cost changes could only be expected if a step change in design could be achieved for shoreline construction (perhaps through development of the ‘roof only’ LIMPET) or by considering overseas construction for near-shore devices. Balance of Plant Costs The upper bound reduction to £300/kW corresponds to manufacturers’ expectations of mass production of near-shore devices. The lower bound of £700/kW corresponds to the use of state-of-theart available technology on a smaller scale limited production basis. Grid Connection The potential for improvement in grid connection cost is not related to OWC performance so has not been considered as a variable in the sensitivity exercise. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 128 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Lower Bound Best Est. Upper bound Rank -5 -4 -3 -2 -1 0 1 2 3 4 5 Wave resource kW/m 17 20.4 23.8 27.2 30.6 34 37.4 40.8 44.2 47.6 51 Capture efficiency % 17 22 27 32 37 42 47 52 57 62 67 Turbine efficiency % 50 53 56 59 62 65 66 67 68 69 70 Generator efficiency 86 87 88 89 90 91 92 93 94 95 96 Outturn civil costs % 20 16 12 8 4 0 -4 -8 -12 -16 -20 BOP cost £/kW 700 660 620 580 540 500 460 420 380 340 300 The possible range of each variable has then been tested in the economic model (with an Equity Discount Rate of 10%) to assess the effect on the outturn power production cost. The results have been plotted. (Appendix E and F shows the sensitivity of the economic model and the influencing factors to a range of discount rates). Shoreline Improvement Sensitivity 5 3 2 1 0 45.0 40.0 35.0 30.0 25.0 20.0 15.0 10.0 5.0 -1 -2 -3 Improvement rank 4 -4 -5 p/kWh Civil Cost Turbine Efficiency Wave Resource Generator Efficiency Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC Capture Efficiency BoP Cost 4 February 2005 Page 129 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Near-shore Improvement Sensitivity 5 3 2 1 0 25.0 20.0 15.0 10.0 5.0 -1 -2 -3 Improvement rank 4 -4 -5 p/kWh Civil Cost Turbine Efficiency Wave Resource Generator Efficiency Capture Efficiency BoP Cost The flatter the curve the greater the influence on the power production cost. Therefore, from the graph it can be seen that changes within the possible improvement range of capture efficiency and available resource have a greater effect than reductions in CAPEX or turbine / generator efficiencies. 10.3 Improvement priorities / targets 10.3.1 Priorities Improvements with the biggest impact on the power production cost, requiring the least effort to implement have been identified above, and could be considered as the priority actions to undertake. Capture efficiency has the biggest impact on the developments economic viability. A greater understanding of collector performance through CFD modelling and tank tests may lead to greater efficiency. While having less of an impact on the power production cost, many of the methods of reducing the civil cost require less development effort. Developing a generic contract strategy to better manage cost, risk and programme of these projects is a low effort improvement. 10.3.2 Targets In order to summarize the future viability of this technology, a power production cost target has been chosen for each device type, and the viability of the improvements required to achieve that target assessed. These should be considered as medium-term targets that could be achieved by 2008-2012. 10.3.2.1 Shoreline Due to the more limited market resource and the lower CAPEX and power production cost for smaller developments (less than 2MW) this device type should be considered for remote power supply to small communities. This would be as an alternative or supplement to small diesel generator power production. As such a target power production cost of 8 to 10 p/kWhr would be a comparable cost target. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 130 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Our current assessment of this technology predicts a power production cost of approximately 17.5 p/kWhr (with a 10% EDR). In order to reach the above target a number of simultaneous improvements would have to be made: • Yearly average capture efficiency up from 42% to 52% • Turbine efficiency up from 65% to 67.5% • Generator efficiency up from 91% to 94% • Civil cost reduction of 50% This would result in an 8 p/kWhr production cost. 10.3.2.2 Near-shore As shown by the previous project scale relationship, near-shore development is better suited for power supply above 1 MW with greater economies as the project increases to the 10 MW scale. This type of development should be compared with the current offshore wind technology, as such targeting a 5 p/kWhr power production cost. Our current assessment of this technology predicts a power production cost of approximately 9.6 p/kWhr (with a 10% EDR). In order to reach the above target a number of improvements would have to be made: • Yearly average capture efficiency up from 42% to 55% • Turbine efficiency up from 65% to 67.5% • Generator efficiency up from 91% to 94% • Balance of plant cost reduction from £500/kW to £300/kW • Civil cost reduction of 20% • No capital cost contingency (previously 10%) This would result in a 5 p/kWhr production cost. 10.4 Learning Rates The approach taken within this report is one of ‘engineering assessment’ [74]. The technological maturity of OWCs has been assessed by a ‘technology stretch’ process whereby the potential for refinement and development of sub-systems and components has been evaluated. The potential that can be realised through this method is dependent on the judgement of the people involved and, as such, is open to interpretation and manipulation. Hence, in order to view the potential for improvements, an alternative empirical approach has been considered. The main alternative to engineering assessment for assessing potential future cost reductions is so called learning, learning by doing, or experience, curves. Evidence from a wide range of technologies demonstrates a clear relationship between production and cost [75]. A learning rate can be defined which is the rate at which cost decreases with each doubling of cumulative production. Learning rates in renewable energy technologies have been assessed to be 10-30% [76]. Onshore wind in Europe was assessed to have an 18% learning rate. To assess the possible learning rate that might be applicable to near-shore OWCs, the rate of progress achieved on Arup dry-built offshore concrete platforms was examined. This form of construction is directly comparable to the future vision for the civil construction of a near-shore OWC. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 131 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report US$/cu. m concrete 10000 7.3% Learning Rate Ravenspurn Wandoo Malampaya 1000 1 Figure 10.1 10 100 Learning Rates for dry-built offshore concrete platforms The assessed learning rate is only 7.3%, which reflects the fact that marine concrete design and construction is a relatively mature field so learning rates can be expected to be lower. The learning rate present for the civil works in the future vision near-shore OWC is 11%. The productivity increases and cost reductions that led to this 11% learning rate were all felt to be achievable. The balance of plant learning rate already present in the future vision is 10%. This seems low compared to the wind energy example (18%) and can probably be increased. The other elements that make up the composite OWC learning rate are the performance improvements expected in the wave-to-wire efficiency. Overall, since the lower rate of improvement foreseen in the large civil works cost element will dominate the composite learning rate, a learning rate of 13% is suggested as being applicable to OWC technology. 10.4.1 Shoreline Targets To achieve the 8p/kWh cost of power target above, a 50% civil cost reduction was considered to be one of the improvements required. At a learning rate of 7.3% for civil works alone, this would not be achieved until 500 OWCs had been constructed, more than the forecast UK market. If the suggested overall learning rate of 13% is applied, the cost of power will decrease from th 17.5p/kWh to 8p/kWh by the time the 50 unit has been constructed. This would amount to 12.5% of the total market foreseen in the UK for shoreline OWCs, or a capital expenditure approaching £80m. It is considered unlikely that the government would provide the necessary financial support to allow this quantity of units to be constructed. The capital cost is approaching twice the level of funding currently being made available through the Dti for all wet renewable power demonstration projects. This analysis suggests that efforts are best directed at researching designs that may achieve substantial cost savings through ‘concept shift’ such as Wavegen’s roof-only LIMPET. 10.4.2 Near-shore Targets The target cost of power for near-shore was 5p/kWh compared to a future vision cost of 9.6p/kWh. This would require 250 number 82.5m long units to be installed at a rated capacity of 562MW and a capital cost of approximately £1bn. These would comprise 15% of the total market foreseen for nearshore OWCs around the UK. By comparison, this is the size of five of the UK round 1 offshore windfarms for which some capital grant funding was available. It is considered unlikely that this volume Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 132 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report of construction would secure the level of financial support to make it attractive to investors, especially considering that developments on this scale would merely permit near-shore OWCs to reach the level of current power cost performance of offshore wind. Hence, although the target improvements are considered achievable, the economics still appear unattractive. Consequently, a greater range of improvements must be sought or a greater rate of learning achieved. Increasing the learning rate to 18% would mean that 5p/kWh was achieved by the th production of the 100 unit. Such learning rates seem essential for OWCs to have a viable future. 10.4.3 Port Kembla The Port Kembla OWC team has been evaluating the improvements that might be possible through an engineering assessment and the degree of technology stretch they can foresee. The team expect wave-to-wire efficiency to improve from 33% to 55% and capital costs to decrease by 75% by the time th the 1000 unit is constructed. This compares with the medium-term target wave-to-wire efficiency of 49% forecast in this report, based on energy at the collector lip (35% based on 20m contour energy flux). Simultaneously, the team expect to move the device to locations with a much greater wave energy resource. th The Port Kembla team forecasts a cost of power of around 2.5p/kWh by the time the 50 unit is constructed. This has been assessed to be a learning rate of 16.5%. The suggested rate of learning for the Port Kembla device appears optimistic and the evidence available from the Port Kembla team to date does not demonstrate that the economics envisaged in this report can be bettered. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 133 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Research & Development Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 134 The Carbon Trust 11 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Areas for Research and Development 11.1 Wave Climate The wave climate can be confidently predicted for anywhere around the UK in deep water away from the coastline. The challenge for developers working near-shore and at the shoreline is to characterise the wave parameters expected there. The transformation of offshore data to inshore locations is a relatively manhour intensive activity that is reliant on skilled practitioners. Data gathering with a wave rider buoy is more reliable than analysis but the long deployment periods needed to gather comprehensive design data inhibit project development. To make development easier, inshore wave climates should be determined for a number of target locations for OWC deployment. This could be an extension to the Marine Renewable Energy Atlas recently produced for UK waters. 11.2 Wave Collector/Capture Improving the capture efficiency of the wave collector has been shown to have the greatest impact on the economics of OWCs. The geometrical factors affecting capture efficiency are well known but they have not been translated into a set of sizing rules that can be followed by designers on new projects. Likewise, the loss in efficiency due to internal slosh and wave wash down the front wall has been recognized but this has not been translated into a body of learning that can be drawn upon when designing the next generation of OWCs. The selection of collector size, geometrical form, inclination angle, lip depth and profile has hitherto been done on something of a trial-and-error basis supported by flume or wave tank testing. The knowledge that has been gained is becoming more valued by developers as they begin to exploit their intellectual property in order to secure funding for future projects. However, the rather closed approach of developers, striving to secure financial backing, can be somewhat self-defeating as it can decrease the learning rate and hence the rate at which the improved economic performance can be delivered. To overcome this, parametric analysis of collector chambers is recommended. This should be performed using CFD tools in conjunction with tank testing. The CFD model may have to treat the turbine as a simple damper initially, but ultimately, complete CFD models of the wave excitation, air chamber response and turbine interaction will be tractable. The CFD tools themselves warrant some fundamental development so that wave time histories can be readily generated by commercially available packages. The use of CFD would help overcome some of the disadvantages in relying on the linear wave theory that has been the foundation for much of the research on OWCs to date despite the knowledge that non-linear behaviour was having a significant bearing on results. The parametric exercise would distil the geometrical arrangements, both inside and outside the chamber, that lead to greatest capture efficiency for a range of environmental conditions. The exercise should also include an assessment of the effects of guide walls compared to continuous lines of capture chambers. The management of such exercises should be through engineering companies, rather than developers, as engineering companies have the requisite skills to devise and then draw out the lessons from parametric work and can bring experience in related technology fields to bear to best effect. 11.3 Construction and Installation Comprising typically 70% of OWC cost, it was evident that changes to the cost of construction and installation of devices would show the highest impact on economics after capture efficiency. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 135 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Bottom-mounted OWCs are faced with the challenges of resisting extreme wave loading without structural or foundation failure to be able to capitalise on the more energetic locations. The best sites for wave resource are the worst in terms of offering suitable weather windows in which to deploy devices. There is some potential to lower the factors of safety commonly specified for offshore structures and this would translate directly into lower cost. The new DnV guidelines should be tested for OWCs and the consequences and likelihood of damage or complete loss of devices should be understood. The response of caisson structures and breakwaters to wave impact loading is a developing field of research in marine coastal engineering. OWCs could benefit from, or extend, this research to help assess the true loading that OWCs must resist. The Port Kembla device has departed significantly from conventional offshore wisdom by adopting short taut moorings and a lightweight structure that offers many sites for impact pressures to be experienced. However, if successful, it could stimulate further research that might improve the concept so that better economic performance can be delivered. The approach of trial-and-error by individual developers is a painful one though, as witnessed by the OSPREY team. The OWC future vision in this report has chosen to follow the conventional design practice for offshore oil & gas gravity structures. From an examination of learning rates in this sector, the rate of improvement seems insufficient to attract investors. To help overcome this, a design competition is suggested. Teams of designers, fabricators and installers should be formed with a brief of delivering a prototype near-shore OWC for deployment at a designated site such as EMEC on Orkney. Their brief would be to brainstorm and then develop an outline design for a new OWC. The teams should include experts in conventional marine structure design and construction, power engineers, installation contractors, specialists in rock anchoring or piling as well as the developers. Specific use of new materials such as fibre-reinforced concrete or construction methods could be explored within this programme. The design shown to be the most economic and have the most future potential to an independent adjudicator could then proceed to deployment. The unsuccessful teams would have their costs covered to ensure a positive attitude was fostered towards the competition. Such an approach is in keeping with the aims of the Marine Energy Challenge and is supported by the Wavenet study [8]. A further mechanism that would help drive down costs would be to develop a renewable energy project development contract. Such a contract would aim to place the development risk with those best able to bear it, thereby encouraging contractors to reduce their risk provision in tenders. Some form of capped liability arrangement could be considered, when the government was providing financial support, whereby the government would take the role of ultimate project guarantor. Such arrangements would, of course, need careful consideration to ensure the fledgling industry was being supported to a point where it could grow independently rather than being just subsidised. 11.4 Turbine The design process for oscillating water column (OWC) installations would benefit from the development of comprehensive, generic CFD tools for analysis of complete systems to enable better and more effective matching of turbines to collector structures. It is desirable that the CFD tools should be validated and calibrated against as wide a variety of experimental data as possible, particularly from large-scale prototype machines. There has already been much theoretical and experimental work on a wide variety of possible blade and vane configurations, relief valves and control methods. The majority of this work has concentrated on the Wells turbine but there has apparently been little effort into direct comparison of different designs on a like-for-like basis and the alternative impulse design has been somewhat overlooked. A comprehensive and qualitative comparison of a variety of vane and blade configurations on a like-forlike basis is required and will assist in the determination of the optimum configuration and turbine type, which may be different for different wave climates. The comparison should initially be undertaken Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 136 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report using CFD and backed up by wind tunnel tests on a significant scale (at least ¼ full size). Both Wells and impulse type designs should be considered. Development of standards for defining performance characteristics of OWC installations would greatly enhance the ability to compare different designs on a like-for-like basis. A range of standard turbines with known characteristics should be developed for use in shoreline systems where the collector system can be custom built to provide the required input air flow. A corresponding range of matched turbine and collector structures for near-shore deployment over a range of sea states should also be developed. Efforts to better understand turbine and relief valve noise production and suppression would also have merit. 11.5 Generator and Power Take Off The generator, power electronic converter and inverter will be state-of-the-art technology adopted from current industrial and wind industry standard technology. There may be design considerations that are application specific to wave energy particularly as a result of the pulsating nature of the power. However, it is not envisaged that there will need to be any specific technology development required in this area. 11.6 Controls Probably the most productive control area for further research is that of throttle valve control. The throttle valve can be controlled to prevent stall and allow operation in high sea states. The valve position also affects damping. Its control should be considered following on from full CFD modelling. Some academic work has been done into the use of controls to tune the OWC to changing wave period; however this has been far from comprehensive. The turbine acts as a damping element to the OWC and hence the full CFD modelling of the OWC chamber and turbine will need to come before active tuning for changing wave climate can be comprehensively considered. The full potential of fixed parameter designs should be achieved first but there is scope to investigate the potential for active tuning at the later stages of development; this should be considered together with throttle valve control. Although we are recommending that the full potential of fixed blade turbine designs are investigated first, there is scope to investigate the area of variable pitch turbine blade control, in order to optimise efficiency and also maybe to adjust damping. 11.7 Grid Connection Grid connection is a site-specific issue and is not specific to OWCs or wave energy. In recent years a number of studies have been carried out in order to quantify the cost of grid connecting wind farms and embedded generators in order to meet government targets. The general order of grid connection costs for OWC sites has been set out in this report, and further useful work would be detailed connection design studies which would normally be carried out as part of a commercial project. 11.8 Power System Dynamics The main power system issue with the OWC technology is that of sub- synchronous resonance that can arise from the pulsating nature of the power when connected into some networks. There would be merit in carrying out detailed studies based on specific sites to establish the nature of the issue. Some work could be done using existing prototype data provided suitable turbine models were available. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 137 The Carbon Trust 11.9 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Business Development and Partnerships To ensure that commercially viable technologies are developed, the creation of strategic partnerships between technology developers and potential volume manufacturers should be encouraged. The majority of the OWC installations have been developed on a prototype basis, often by academic institutions or small research and development companies. These organisations have built up a significant level of knowledge and expertise but, in order to move the development forward, expertise from other key technology areas needs to be incorporated. These key areas are civil and structural engineering, turbine design and manufacture, CFD and mathematical modelling and electrical power engineering. If such technology development is to be publicly funded then engineering consultants with power industry experience should also be appointed. Although the LIMPET site has its limitations from a wave climate point of view, it does have significant advantages of access and is currently the only operational OWC site in the world. The facility would benefit from some investment; so that it could become a more commercial test bed facility particularly for developing turbine and power take off designs. A similar argument could be made for the Pico site, however despite its more favourable wave climate the difficulty of access and poor operational track record suggests that costs could be higher. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 138 The Carbon Trust 12 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Conclusions OWCs have the longest track-record of deployment of any of the wet renewable technologies under consideration in the Marine Energy Challenge. Grid-connected facilities have been operational now for several years. Small-scale OWCs in navigation buoys have proven economic and reliable. Yet despite this history, an OWC market has not been established and other wet renewable technologies are threatening to supplant the predominant position OWCs have had. Two companies, Wavegen and Energetech, have begun to make some progress towards commercialising the technology but multi-megawatt projects are probably still five years away from being realised. If OWCs are to have a long-term future, their rate of development must be increased. The Marine Energy Challenge was devised as a way of pushing wet renewable technology forward. This report for the Challenge demonstrates that near-shore OWCs can, within a reasonable timescale, reach a point where they can work within the current UK framework for renewable power generation without needing additional government support. The improvements reported here in performance and cost to reach this position do seem achievable. However, the OWC industry will not deliver these improvements without a more coherent approach and some financial assistance. The best use of future funding would be to stimulate a rate of learning that will deliver the progress rate of successful renewable energy technologies such as onshore wind. Shoreline OWC technology will never achieve as low a power price as near-shore OWCs. Nonetheless, it can still play a role in serving isolated communities where there is power price premium. Efforts commensurate with the scale of resource should continue, to help the shoreline OWCs reduce costs and improve performance, so that they can be a viable niche power provider. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 139 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Supporting Information Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page 140 Appendix A References The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report A1.1 1] 2] 3] 4] 5] 6] 7] 8] 9] 10] 11] 12] 13] 14] 15] 16] 17] 18] 19] 20] 21] 22] 23] 24] 25] 26] 27] 28] 29] References Binnie Black & Veatch with IT Power Ltd.; The commercial prospects for tidal stream power, ETSU T/06/0209/REP, Dti/Pub URN 01/1011, 2001 Queen’s University of Belfast with Kirk McClure Morton & Heriot Watt University; The UK nearshore and shoreline wave energy resource, ETSU WV 1683, 1992 Whittaker, T.J.T.; McIwaine, S.J. & Raghunathan, S.; A review of Islay shoreline wave power plant, European Wave Energy Symposium, 1993 Falcao, A.F. deO.; Sabino, M.; Whittaker, T.J.T. & Lewis, A.W.; Design of a shoreline wave power plant for the island of Pico, Azores, 1995 Heath, T.; Islay LIMPET project monitoring, ETSU V/06/00180/00/Rep, Dti Pup URN No 02/1435, 2002 Wavegen, Research into the further development of the LIMPET shoreline wave energy plant, Dti, V/06/00183/00/Rep, 2002 Scarr, D., Kollek, R. & Collier, D.; Wave energy: technology transfer and generic R&D recommendations, Arup Energy, ETSU V/06/00187/REP, Dti Pub/URN 01/799, 2001 WaveNet, results from the work of the European Thematic Network on wave Energy European,Community Project funded through the Energy Environment and Sustainable research program, http://www.wave-energy.net/Library/WaveNet%20Full%20Report(11.1).pdf Whitaker, T.J.T. & Stewart T.P., An experimental study of near-shore and shoreline oscillating water columns with harbours, European Wave Energy Symposium, July 1993 Thorpe, T.W.; An Assessment of The Art OSPREY Wave Energy Device, ETSU-R-90, Dti, October 1995 Jayakumar; Neelamani, S. & Raju, V.S., An experimental investigation of wave forces on an oscillating water column type wave energy caisson, European Wave Energy Symposium, July 1993. Wave Energy converters: Generic technical evaluation study, Annex report B2, Device Components and Materials, ETSU, August 1993 Scale 1:10 wave flume experiments on IIT oscillating water column wave energy device, August 1993, http://www.uni-leipzig.de/~grw/lit/texte_099/16_1993_scale.pdf Schaffarczyk, A.P.; On the aerodynamic design of a Wells-turbine’s blade, July 2003, http://stheno.maschinenwesen.fh-kiel.de/~nummech/pdf-files/wells.pdf Wave Energy Converters, Generic Technical Valuation Study, Electrical systems Control & Grid Interaction, Annex B4, Power take off System, Annex B3, ETSU, 1993 Wave Energy Converters, Generic Technical Evaluation Study, Annex B5, Methodology for Reliability and Economic Assessment, ETSU, March 1993 The Offshore Wave Energy Converter Report (Annex III), Mathematical Models & Tank Testing, Joule Contract No. JOU2-CT93-0394, January 1994-December 1995 The Offshore Wave Energy Converter Project (Annex II), Float Systems, Joule Contract No. JOU2-CT93-0394, January 1994-December 1995 The Offshore Wave Energy Converter Project (Annex I), Structural and Preliminary Design, Joule Contract No. JOU2-CT93-0394 January 1994 - December 1995 The Offshore Wave Energy Converter Project (Annex IV), Power Take Off, Joule Contract No. JOU2-CT93-0394, January 1994 - December 1995 The Offshore Wave Energy Converter Project (Annex V), OWEC-1 Presentations at Second European Wave Energy Conference, Joule Contract No. JOU2-CT93-0394, January 1994December 1995 The Offshore Wave Energy Converter Report (Main Report), Joule Contract No. JOU2-CT930394, January 1994-December 1995 Thorpe, T.W.; An overview of wave energy technologies: status, performance and costs, Wave Power: moving towards Commercial Viability, November 1999 Guide to UK renewable energy companies, Dti URN 04/1199, 2004 Foresight Report of the working group on offshore energies (Annex G wave energy), DTI/Pub 2984/1k/5/98/NP. URN 97/732, 1997 Falcao, A. F. deO.; The shoreline OWC wave power plant at the Azores, Wave Energy 2000, 2000 Heath, T., Whittaker, T.J.T & Boake, C.B.; The design, construction and operation of the LIMPET wave energy converter, Wave Energy 2000, 2000 Neumann, F. & Sarmento, A.J.N.A.; An assessment of technical and economical viability of OWC integration in breakwaters, Wave Energy 2000, 2000 Godoy-Diana, R. & Czitrom, S.P.R.; Tuning an oscillating water column Sea-water pump to polychromatic wave spectra, Wave Energy 2000, 2000 Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page A1 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report 30] Graw, K-U; Schimels, S. & Joachim Lengrucht, J.; Quantifying the losses around the lip of an OWC by use of particle image velocimetry, Wave Energy 2000, 2000 31] Weber, J & Thomas, G.P.; Optimising of the hydrodynamic-aerodynamic coupling for an Oscillating water column wave energy device, Wave Energy 2000, 2000 32] Yuangang Liu & Lars Bergdahl, Simulation and control for a cluster of OWCs, Wave Energy 2000, 2000 33] Delaure, Y.M.C & Lewis, A.; A comparison of OWC response predictions by a boundary element method with scaled modelled test results, Wave Energy 2000, 2000 34] Brito-Melo, A. & Sarmento, A.J.N.A.; Numerical study of the performance of a OWC wave power plant integrated in a semi-infinite breakwater, Wave Energy 2000, 2000 35] Olveral, A.; Prado, E. & Czitrom, S.P.R.; Wave Energy Proceeding - Performance improvement of OWC systems by parametric resonance, Wave Energy 2000, 2000 36] Justino, P.A.P. & Falcao, A.F. deO.; Active relief-valve control for an OWC wave energy device, Wave Energy 2000, 2000 37] Alcom, R.G.; Beattie,W.C. & Cully, N.; Control valve comparison for oscillating water column wave-power devices, Wave Energy 2000, 2000 38] Vakalis, I.S. & Sarmento, A.J.N.A.; Real-time control of an OWC with a variable pitch-angle turbine, Wave Energy 2000, 2000 39] Brito-Melo, A.; Gato, L.M.C. & Sarmento, A.J.N.A.; Analysis of wells turbine design parameters by numerical simulation of the OWC performance, Wave Energy 2000, 2000 40] Czitrom, S; Prado, E. & Merino, M.; OWC performance enhancement Resonant duct wave amplification, European Wave Energy Symposium, July 1993 41] Bremdo, A; Falnes, J.; Lillebekken, P.M. & Sarmento, A.J.N.A; Transient experiments and a time-domain model of a twin OWC, European Wave Energy Symposium, July 1993, 42] European Wave Energy Symposium, Power output of an offshore OWC wave power station at Dawanshan island, July 1993, Z Yu N Jiang, Y.You 43] Johnson, F.; Design, development and evaluation of the 'Sperboy' MOWC Wave energy device, Dti pub RPP039, DTI/Pub URN 02/623, http://www.dti.gov.uk/energy/renewables/publications/pdfs/rpp039.pdf, March 2000 44] Boud, R.; Status and research and development priorities, Wave and Marine current energy, DTI report number FES-R-132, AEAT report number AEAT/ENV/1054, http://www.dti.gov.uk/energy/renewables/pdfs/IEAWaveTidalreport.pdf, 2002 45] Falcao, A.F. de O. & Justino, P.A.P.; OWC wave energy devices with air flow control, Ocean Engineering, Volume 26, Issue 12, pages 1275-1295, December 1999 46] Falcao, A.F. deO.; Control of an oscillating-water-column wave power plant for maximum energy production, Applied Ocean Research, Volume 24, Issue 2, pages 73-82, April 2003, 47] Energetech web site, March 2004, http://www.energetech.com.au/ 48] http://www.niot.res.in/m1/mm1.html 49] Arsel, T.; Bjarte-Larsson, T. & Falnes, J.; Hydrodynamic parameters for a floating WEC force reacting against a submerged body, Wave Energy 2000, 50] RegenSW, Seapower South West- next steps in developing a commercial wave and tidal current industry in the UK, October 2003 51] METOC; Resources, Constraints and Development Scenarios for Wave and Tidal Stream Power in the South West of England, SW of England Regional Development Association, Report 1220, January 2004 52] Telford, D.; Renewable Generation Connections and Network Management, , Scottish and Southern Energy, Scottish Hydro Electric Power Distribution Ltd, Fifth Annual Conference on Distributed Generation and the Network, June 2004 53] Scottish and Southern Energy, "Long Term Development Statement for Scottish Hydro Electric Power Distribution Ltd's Electricity Distribution System", November 2002 54] Scottish and Southern Energy, "Seven Year Transmission Statement 2002", June 2002 55] Western Power Distribution, "Long Term Development Statement for Western Power Distribution (South West) plc's Electricity Distribution System", November 2003 56] The Queen’s University of Belfast, Islay LIMPET Wave Power Plant, Non-nuclear Energy Programme Joule III, CORDIS, JOR3-CT98-0312, 2002 57] www.argoss.nl 58] http://oceanworld.tamu.edu/resources/ ocng_textbook/chapter16/chapter16_04.htm 59] Hughes, S. A.; The TMA Shallow-water Spectrum Description and Applications, Department of the Army, Coastal Engineering Research Center, December 1984 60] Heath, T. V.; A Review of the Potential of the Wells Turbine/ OWC combination based on Practical Experience, ART2126, Wavegen Internal Report, 2004. 61] http://www-public.tu-bs.de:8080/~i5102401/proverbs.html 62] Goda Y : Random seas and design of maritime structures, University of Tokyo press, Tokyo, 1985 63] Sarpkaya , T. and Isaacson, M.; Mechanics of Wave Forces on Offshore Structures, van Nostrand Reinhold, 1981 Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page A2 The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report 64] Allsop, N.W.H.; Vicinanza, D.; McKenna, J.E.; Wave forces on vertical and composite breakwaters. Strategic Research Report. Hydraulic Research Wallingford, Wallingford, U.K., 94 pp., 1996 65] Det norske Veritas, Classification Notes 30.4, Foundations, 1992 66] Burcharth, H. F,; PIANC PTCII WG28 on Breakwaters with Vertical and Inclined Concrete Walls, Identification and Evaluation of Design Tools, Report of Sub-Group A, 2001. 67] Falcao, A. F. deO.; Stochastic Modelling in wave power-equipment optimisation: maximum energy production versus maximum profit, Ocean Engineering, 2004 68] Falcao, A. F. deO.; Control of an oscillating-water-column wave power plant for maximum energy production, Applied Ocean Research 24 (2002) 73-82, July 2002. 69] Det Norske Veritas, Marine Operations Guidelines VMO 1.1 Mooring and Towage of Gravity Base Structures, November 1989. th 70] Finnigan, T. & Alcorn, R.; Numerical simulation of a variable-pitch turbine with speed control, 5 European Wave Energy Conference, Cork, September 2003 71] Finnigan, T.; Development of a 300kW ocean wave energy demonstration plant, Pacific 2004 International Maritime Conference, Sydney, February 2004 72] Palmer, C.; Target Costs and Performance of Wave Energy Conversion Devices, Engineering Challenges at the Dawn of Wave and Tidal Energy, I Mech E, November 2004. 73] Thorpe, T.W.; A review of wave energy, ETRU R120, May 1999 74] Chapman, J. & Gross, R.; The technical and economic potential of renewable energy generating technologies: Potentials and cost reductions to 2020, Foresight energies from the sea – towards 2020, A Marine Foresight Report, Performance & Innovation Unit 75] International Energy Agency, Experience Curves for energy technology policy, OECD2000 76] McDonald, A & Schrattenholzer, L.; Learning Rates for Energy Technologies, Energy Policy 29, pp255-261, 2001 77] Setoguchi,T., Santhakumar, S., Takao, M. T. H., Kim, T.H. & Kaneko, K.; A modified Wells turbine for wave energy conversion, Renewable Energy, Volume 28, Issue 1, Pages 79-91, January 2003 78] Brito-Melo, A., Gato, L.M.C. & Sarmento, A.J.N.A.; Analysis of Wells turbine design parameters by numerical simulation of the OWC performance, Ocean Engineering, Volume 29, Issue 12, Pages 1463-1477, September 2002 79] Govardhan, M. & Dhanasekaran, T.S.; Effect of guide vanes on the performance of a selfrectifying air turbine with constant and variable chord rotors, Renewable Energy, Volume 26, Issue 2, Pages 201-219, June 2002 80] EMEC, Performance Assessment for Wave Energy Conversion Systems in Open Sea Test Facitilies. 81] Department of Trade and Industry, Atlas of Marine Renewable Energy Resources, Report R.1106, June 2004. 82] Kim, T.H., Takao, M., Setogucchi, T., Kaneko, K. and Inoue, M.; Performance comparison of turbines for wave power conversion, International Journal of Thermal Sciences, Volume 40 Issue 7, Pages 681-689, July-August 2001. 83] Falcao, A.F. de O., and Justino, P.A.P.; OWC wave energy devices with air flow control, Ocean Engineering, Volume 26, Issue 12, Pages 1275-1295, December 1999. 84] Korde, U.A.; Efficient primary energy conversion in irregular waves. Ocean Engineering, Volume 26, Issue 7, Pages 625-651, July 1999 85] Ghosh, K.; Cascade wind turbines for the oscillating water column wave energy device: Part1, Renewable Energy, Volume 9, Issues 1-4, Pages 1219-1222, September-December 1996. 86] Korde, U.A.; Development of a reactive control apparatus for a fixed tow-dimensional oscillating water column wave energy device, Ocean Engineering, Volume 18, Issue 5, Pages 465-483, 1991. 87] Sarmento, A.J.N.A., Gato, L.M.C and de O Falcao, A.F.; Turbine-controlled wave energy absorption by oscillating water column devices *1, Ocean Engineering, Volume 17, Issue 5, Pages 481-497, 1990. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page A3 Appendix B OWC Construction Programmes The Carbon Trust Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page B1 Appendix C OWC Cost Estimates Page 1 Shoreline cost GENERIC SHORELINE OWC CIVIL COSTS Item Short description Quantity Unit Unit rate Amount £ £ 1 GENERAL SITE WORKS 1.1 excavate (stripping) topsoil 50 cm including storage for re-use, haul maximum 1 km 13,000 m² 5.00 65,000 1.2 Access Road - layer of sand/gravel - 300mm 3,000 m² 20.00 60,000 1.3 install fence for protecting site including material supply, height 2 m, material wire mesh 400 m 50.00 Total General Site Works 2 EXCAVATION & PREP 2.1 excavate rock 2.2 20,000 145,000 5,400 m3 Rock bund prep and height extension 1 item 20,000 2.3 install dewatering system 1 item 10,000 2.4 provide and install pumping equipment, raiser and discharge pipes etc., 1 item 20,000 2.5 pump out water down to excavation base 1 item 1,000 2.6 50mm blinding concrete on dock floor 500 m² 5.00 2,500 2.7 dewatering during construction period including time for dewatering and foundation works 12 month 500.00 6,000 30.00 Total Excavation and Prep 162,000 221,500 3 PLANT AND FACILITIES 3.1 site offices, toilets, washrooms item 15,000 3.2 generators and power distribution system item 5,000 3.3 electrical/mechanical/welding/carpentry and formwork workshop item 2,000 3.4 store and laydown areas item 2,000 3.5 concrete batch plant 1 no 12,000.00 3.6 water storage tanks 1 no 1,000.00 Total Plant and Facilities 4 DEVICE CONSTRUCTION 4.1 base slab - formwork 100 4.2 base slab - reinforcement supply 60 4.3 base slab - reinforcement fix 4.4 base slab - concrete supply 400 base slab - concrete place 4.6 base slab - concrete top form / slope allowance 4.7 walls - formwork 4.8 walls - reinforcement supply 1,000 37,000 SITE WORK TOTAL 4.5 12,000 2 403,500 m Te 30.00 3,000 500.00 30,000 60 Te 250.00 15,000 400 m3 55.00 22,000 m 3 24.00 9,600 100 m 2 50.00 5,000 1,260 m2 50.00 63,000 70 Te 500.00 35,000 4.9 walls - reinforcement fix 70 Te 300.00 21,000 4.10 walls - concrete supply 441 m3 55.00 24,255 4.11 walls - concrete place 441 m3 24.00 10,584 4.12 walls - formwork - permanent steel (e.g. lip) 10 Te 2,000.00 20,000 4.13 roof - prepare precast beds (4 No) 55 m2 100.00 5,500 4.14 roof - pre-cast panel reinforcement supply 25 Te 500.00 12,500 4.15 roof - pre-cast panel reinforcement fix 25 Te 300.00 7,500 4.16 roof - pre-cast panel concrete supply 150 m3 55.00 8,250 4.17 roof - pre-cast panel concrete place 150 12.00 1,800 4.18 roof - curing per panel 90 m3 no 25.00 2,250 4.19 roof - erection of panels 90 no 100.00 9,000 4.20 roof - concrete supply topping 265 m3 55.00 14,575 3 4.21 roof - concrete place topping 265 m 24.00 6,360 4.22 roof - topping reinforcement supply 40 Te 500.00 20,000 4.23 roof - topping reinforcement fix 40 Te 300.00 12,000 4.24 turbine hall & attentuation - slab formwork 25 m2 30.00 750 4.25 turbine hall & attenuation - reinforcement 15 Te 500.00 7,500 4.26 turbine hall & attentuation - reinforcement fix 15 Te 250.00 3,750 4.27 turbine hall & attentuation - concrete supply 100 m3 55.00 5,500 4.28 turbine hall & attentuation - concrete place 100 m 3 24.00 2,400 4.29 turbine hall & attentuation - blockwork 300 m2 35.00 10,500 4.30 turbine hall & attentuation - roof steelwork 9 Te 2,000.00 18,000 4.31 turbine hall & attentuation - concrete roof 30 m3 350.00 10,500 4.32 Turbine Hall Architectural fit out (water tight door, etc.) 1 item 5,000.00 5,000 4.34 Turbine Hall - Lifting beam 1 te 2,000.00 2,000 DEVICE CONSTRUCTION SUB-TOTAL (excl indirects) 424,074 5 CONSTRUCTION INDIRECTS 5.1 detailed design item 15% 5.2 site data collection item 10% 79,057 5.3 management and supervision item 20% 158,115 5.4 plant &equipment item 15% 118,586 5.5 craneage item 15% 118,586 5.6 small tools item 1.8% 14,230 5.7 indirect labour item 10% 79,057 5.8 freight item 0.25% 5.9 profit & overheads item 15% Total Construction Indirects 118,586 1,976 118,586 806,781 DEVICE CONSTRUCTION TOTAL 1,230,855 6 FINAL FINISHING 6.1 clearing and demolition of bund including haulage and disposal of material 2,000 m² 30.00 60,000 6.2 Landscaping 10,500 m³ 6.50 68,250 6.3 dredging operation 0 m3 6.00 TOTAL FINISHING 7 BOP 7.1 Power Train Cost Estimate 7.2 Grid Connection 0 128,250 £/kW 500 kW 500.00 item 250,000 60,000 TOTAL BOP 310,000 CIVIL TOTAL BOP Estimate £1,762,605 £310,000 GRAND TOTAL £2,072,605 COST / m FRONT 1 £103,630 OWC Cost & Prog rev 09 Near Shore cost NEAR SHORE CONSTRUCTION Item SINGLE DEVICE MEASURE Short description Quantity Unit 1 SITE PREP AND TEMPORARY WORKS 1.1 Dry dock modification / refurbishment 1 item 1.2 Dry dock rent 8 month 1.3 Offshore SI item Page 2 SCALE COST COMPARISON Unit rate Cost per device Cost per generator Cost for 10 devices % Productivity £ £ £ £ Rate Reduction m Front 82.5 27.5 825 Factored 10 device £ 825 45,000 45,000 45,000 0% 45,000 50,000.00 400,000 400,000 4,000,000 40% 2,400,000 125,000 125,000 125,000 250,000 0% 250,000 570,000 570,000 4,295,000 Total Dry Dock Cost SITE WORK TOTAL 2 2,695,000 DEVICE CONSTRUCTION m2 Te 30.00 4,500 1,500 45,000 0% 45,000 500.00 30,000 9,998 300,000 0% 300,000 60 Te 200.00 12,000 3,999 120,000 40% 72,000 400 m3 55.00 22,000 7,332 220,000 10% 198,000 400 m3 12.00 4,800 1,600 48,000 0% 48,000 400 m3 10.00 4,000 1,333 40,000 0% 40,000 m2 Te 100.00 320,000 106,640 3,200,000 10% 2,880,000 500.00 180,000 59,985 1,800,000 0% 1,800,000 2.1 base slab - formwork 150 2.2 base slab - reinforcement supply 60 2.3 base slab - reinforcement fix 2.4 base slab - concrete supply 2.5 base slab - concrete place 2.6 base slab - concrete pumping allowance 3,200 2.7 ballast tank walls - prepare slipform 2.8 ballast tank walls - reinforcement supply 360 2.9 ballast tank walls - reinforcement fix 360 Te 250.00 90,000 29,993 900,000 20% 720,000 2.10 ballast tank walls - concrete supply 2,400 m3 55.00 132,000 43,989 1,320,000 10% 1,188,000 2.11 ballast tank walls - concrete place 2,400 m3 12.00 28,800 9,598 288,000 0% 288,000 2.12 ballast tank slab - formwork 760 30.00 22,800 7,598 228,000 0% 228,000 2.13 ballast tank slab - reinforcement supply 32 m2 Te 500.00 16,000 5,332 160,000 0% 160,000 2.14 ballast tank slab - reinforcement fix 32 Te 200.00 6,400 2,133 64,000 20% 51,200 2.15 ballast tank slab - concrete supply 220 m3 55.00 12,100 4,032 121,000 10% 108,900 2.16 ballast tank slab - concrete place 220 m3 12.00 2,640 880 26,400 0% 26,400 2.17 ballast tank slab - concrete pumping allowance 220 m3 10.00 2,200 733 22,000 0% 22,000 2.18 chamber rear slab (sloped) - formwork 400 m2 50.00 20,000 6,667 60,000 0% 60,000 2.19 chamber rear slab (sloped) - reinforcement supply 100 Te 500.00 50,000 16,667 500,000 0% 500,000 2.20 chamber rear slab (sloped) - reinforcement fix 100 Te 250.00 25,000 8,333 250,000 20% 200,000 2.21 chamber rear slab (sloped) - concrete supply 610 m3 55.00 33,550 11,183 335,500 10% 301,950 2.22 chamber rear slab (sloped) - concrete place 610 m3 12.00 7,320 2,440 73,200 0% 73,200 2.23 chamber rear slab (sloped) - e/o for top formwork 400 m2 50.00 20,000 6,667 60,000 0% 60,000 2.24 chamber walls - formwork 2,200 110,000 36,667 1,100,000 0% 1,100,000 chamber walls - reinforcement supply 80 m2 Te 50.00 2.25 500.00 40,000 13,333 400,000 0% 400,000 2.26 chamber walls - reinforcement fix 80 Te 250.00 20,000 6,667 200,000 20% 160,000 2.27 chamber walls - concrete supply 540 m3 55.00 29,700 9,900 297,000 10% 267,300 2.28 chamber walls - concrete place 540 12.00 6,480 2,160 64,800 0% 64,800 2.29 chamber walls - formwork - permanent steel (e.g. lip) 25 m3 Te 2,000.00 50,000 16,667 500,000 0% 500,000 2.30 roof - formwork 835 41,750 13,917 417,500 0% 417,500 roof - reinforcement supply 62 m2 Te 50.00 2.31 500.00 31,000 10,333 310,000 0% 310,000 2.32 roof - reinforcement fix 62 Te 200.00 12,400 4,133 124,000 40% 74,400 2.34 roof - concrete supply 425 m3 55.00 23,375 7,792 233,750 10% 210,375 2.35 roof - concrete place 425 m3 12.00 5,100 1,700 51,000 0% 51,000 2.36 roof - e/o for top formwork 835 m2 50.00 41,750 13,917 417,500 0% 417,500 2.37 Steel skirt 45 te 1,500.00 67,500 22,500 675,000 10% 607,500 2.38 Plant Penetrations 12 te 5,000.00 60,000 20,000 600,000 0% 600,000 2.39 Towing Fittings, rubbing strips 10 te 15,000.00 0% DEVICE CONSTRUCTION SUB-TOTAL (excl indirects) 150,000 50,000 1,500,000 1,735,165 578,314 17,071,650 1,500,000 16,051,025 3 DEVICE CONSTRUCTION INDIRECTS 3.1 detailed design item 20% 347,033 115,678 694,066 0% 694,066 3.2 management and supervision item 20% 347,033 115,678 3,470,330 20% 2,776,264 3.3 plant &equipment item 10% 173,517 57,839 1,735,165 20% 1,388,132 3.4 craneage item 10% 173,517 57,839 1,735,165 10% 1,561,649 3.5 small tools item 1.8% 31,233 10,411 312,330 0% 312,330 3.6 indirect labour item 10% 173,517 57,839 1,735,165 15% 1,474,890 3.7 freight item 0.25% 3.8 profit & overheads item 15% Total Construction Indirects DEVICE CONSTRUCTION TOTAL 4,338 1,446 43,379 0% 43,379 260,275 86,758 2,602,748 30% 1,821,923 1,510,461 503,487 12,328,347 10,072,633 3,245,626 1,081,801 29,399,997 26,123,658 4 MARINE OPERATIONS 4.1 tug mobilisation/demobilisation 4 days 14,000.00 56,000 56,000 56,000 0% 56,000 4.2 tow to field 5 days 14,000.00 70,000 70,000 700,000 0% 700,000 4.3 installation 2 days 14,000.00 28,000 28,000 280,000 20% 224,000 4.4 Flotation bags item 30,000 30,000 60,000 0% 60,000 4.5 winches, dead-anchors, rigging item 50,000 50,000 100,000 10% 90,000 4.6 mobilise/demobilise dredger / rock dumper 350,000 350,000 350,000 0% 350,000 4.7 Scour protection 2,000 m3 35.00 70,000 23,333 700,000 20% 560,000 4.8 ballast - pumped sand 13,400 m3 15.00 201,000 67,000 2,010,000 20% 1,608,000 855,000 674,333 4,256,000 3,648,000 855,000 674,333 4,256,000 3,648,000 item Total Marine Operations MARINE OPERATIONS SUB-TOTAL (excl indirects) 5 MARINE OPERATIONS INDIRECTS 5.1 management and supervision item 10% 85,500 85,500 855,000 80% 171,000 5.2 profit & overheads item 15% 128,250 128,250 1,282,500 50% 641,250 213,750 213,750 2,137,500 812,250 1,068,750 888,083 6,393,500 4,460,250 Total Marine Operation Indirects MARINE OPERATIONS TOTAL 6 BOP 6.1 Power Train Cost Estimate 6.2 Offshore cable (installed) 6.3 Grid Connection £/kW 2,250 kW 700.00 1,575,000 1,575,000 15,750,000 29% 250 m 400.00 100,000 100,000 500,000 0% 500,000 120,000 120,000 1,000,000 0% 1,000,000 1,795,000 1,795,000 17,250,000 12,750,000 CIVIL TOTAL BOP Estimate £4,884,376 £1,795,000 £2,539,885 £1,795,000 £40,088,497 £17,250,000 £33,278,908 £12,750,000 GRAND TOTAL £6,679,376 £4,334,885 £57,338,497 £46,028,908 COST / 250kW £742,153 £481,654 £637,094 £511,432 £2,968,612 £17,339,538 £2,548,378 £2,045,729 £80,962 £157,632 £69,501 £55,793 item TOTAL BOP COST / MW COST / m FRONT 2 11,250,000 OWC Cost & Prog rev 09 Appendix D Economic Model OWC Cost & Prog rev 01 Nearshore Economic Model Year Ending Power in the Sea Frontage per unit Units per device Number of devices Capture efficiency Turbine efficiency Generator efficiency Device Output Total Output transmission and transformer losses Capacity after losses (MW) 2007 0 kW/m 34.0 m 27.5 no. 3.0 no. 10.0 % 42% % 65.0% % MW 2% MW 6.8 £/MWhr Income £ / year £/yr 2013 6 2014 7 2015 8 2016 9 2017 10 2018 11 2019 12 2020 13 2021 14 2022 15 2023 16 2024 17 2025 18 2026 19 2027 20 2028 21 2029 22 2030 23 2031 24 2032 25 8760 8,760 8,784 8,760 8,760 8,760 8,784 8,760 8,760 8,760 8,784 8,760 8,760 8,760 8,784 8,760 8,760 8,760 8,784 8,760 8,760 8,760 8,784 8,760 8,760 3% 263 264 263 263 263 264 263 263 263 264 263 263 263 264 263 263 263 264 263 263 263 264 263 263 263 8,497 8,520 8,497 8,497 8,497 8,520 8,497 8,497 8,497 8,520 8,497 8,497 8,497 8,520 8,497 8,497 8,497 8,520 8,497 8,497 8,497 8,520 8,497 8,497 8,497 8,760 2.5% 35 37.7 38.6 39.6 40.6 41.6 42.6 43.7 44.8 45.9 47.1 48.2 49.5 50.7 52.0 53.3 54.6 56.0 57.4 58.8 60.3 61.8 63.3 64.9 66.5 68.2 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 10.8 11.6 11.9 12.2 12.5 12.8 13.2 13.5 13.8 14.2 14.5 14.9 15.3 15.6 16.0 16.4 16.8 17.3 17.7 18.1 18.6 19.1 19.5 20.0 20.5 21.0 21.6 69.9 53.62 54.85 56.12 57.41 58.74 60.10 61.50 62.93 64.39 65.90 67.44 69.01 70.63 72.29 73.99 75.73 77.52 79.35 81.22 83.15 85.12 87.14 89.21 91.33 93.51 95.74 3,248,075 3,332,015 3,399,619 3,478,244 3,558,835 3,651,417 3,726,111 3,812,898 3,901,856 4,003,976 4,086,497 4,182,294 4,280,486 4,393,136 4,484,296 4,590,038 4,698,424 4,822,696 4,923,392 5,040,111 5,159,749 5,296,849 5,408,071 5,536,908 5,668,965 5.01 50.10 £/kW kW 500.00 750.00 (£) (£) (£) 11,250,000 23.9% 33,278,908 70.7% 1,500,000 3.2% 2.0% 920,578 2.0% 3.0% 97,442 0.2% (£) 47,046,928 0% 10% (£) 51,499,819 - 51,499,819 2.50% 108,000 - 2.00% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% - - 2.50% 2.50% 2.50% 110,700 113,468 116,304 119,212 122,192 125,247 128,378 131,588 134,877 138,249 141,705 145,248 148,879 152,601 156,416 160,327 164,335 168,443 172,654 176,971 181,395 185,930 190,578 195,342 64,961 66,640 67,992 69,565 71,177 73,028 74,522 76,258 78,037 80,080 81,730 83,646 85,610 87,863 89,686 91,801 93,968 96,454 98,468 100,802 103,195 105,937 108,161 110,738 10% % (£) @£/yr 2.50% 200,226 113,379 8,722,237 1.5% £168,750 172,969 177,293 181,725 186,268 190,925 195,698 200,591 205,605 210,746 216,014 221,415 226,950 232,624 238,439 244,400 250,510 256,773 263,192 269,772 276,517 283,429 290,515 297,778 305,223 312,853 680,760 0.80% 376,375 385,785 395,429 405,315 415,448 425,834 436,480 447,392 458,577 470,041 481,792 493,837 506,183 518,838 531,809 545,104 558,731 572,700 587,017 601,693 616,735 632,153 647,957 664,156 2.0% 64,961 66,640 67,992 69,565 71,177 73,028 74,522 76,258 78,037 80,080 81,730 83,646 85,610 87,863 89,686 91,801 93,968 96,454 98,468 100,802 103,195 105,937 108,161 110,738 113,379 102,500 105,063 107,689 110,381 113,141 115,969 118,869 121,840 124,886 128,008 131,209 134,489 137,851 141,297 144,830 148,451 152,162 155,966 159,865 163,862 167,958 172,157 176,461 180,873 185,394 892,467 914,888 937,133 960,306 984,059 1,008,805 1,033,362 1,058,941 1,085,160 1,112,472 1,139,581 1,167,816 1,196,757 1,226,901 1,256,827 1,287,993 1,319,938 1,353,209 1,386,244 1,420,646 1,455,907 1,492,629 1,529,097 1,567,070 10,328,230 - 51,499,819 2,355,608 2,417,127 2,462,486 2,517,938 2,574,775 2,642,611 2,692,749 2,753,957 2,816,695 2,891,504 2,946,916 3,014,479 3,083,730 3,166,235 3,227,469 3,302,045 3,378,486 3,469,487 3,537,147 3,619,465 3,703,841 3,804,220 3,878,974 3,969,838 - 1 0.9000 0.8100 0.7290 0.6561 0.5905 0.5314 0.4783 0.4305 0.3874 0.3487 0.3138 0.2824 0.2542 0.2288 0.2059 0.1853 0.1668 0.1501 0.1351 0.1216 0.1094 0.0985 0.0886 0.0798 0.0718 - 51,499,819 2,120,047 1,957,873 1,795,152 1,652,019 1,520,379 1,404,392 1,287,934 1,185,488 1,091,245 1,008,205 924,774 851,378 783,843 724,333 664,507 611,876 563,436 520,751 477,816 440,042 405,271 374,629 343,791 316,660 - 334,488 -2,059,993 -2,059,993 -2,059,993 -2,059,993 -2,059,993 -2,059,993 -2,059,993 -2,059,993 -2,059,993 -2,059,993 -2,059,993 -2,059,993 -2,059,993 -2,059,993 -2,059,993 -2,059,993 -2,059,993 -2,059,993 -2,059,993 -2,059,993 -2,059,993 -2,059,993 £100,000 - cash EBITDA Equity Discount rate Asset Life - Straight Line (years) Salvage Value (£) Depreciation Rate Tax - Declining Balance 2012 5 (28,808.5) Power Price (£ per MWh) Present Value Project NPV (£'000) IRR 2011 4 7.0 % £/MWhr £/MWhr £/MWhr p/kWhr Insurance Cost Operational (£/yr) - % of CAPEX Business interruption (£/yr) - % of revenue 3rd Party (£/yr) 2010 3 696.8 RPI increase Renewable Obligations Certificate Climate Change Levy (2002 prices) Power price (standard market price comparison) Total Operating Cost Operating Costs - (£) @£/yr Crown Estate rent @%of energy revenue Decommission Maintenance Cost % of BOP cost 2009 2 91% kW Hours Available Production hours in year Maintenance hrs-during summer ie forced outage CAPEX BoP cost / kW Unit turbine BoP cost foundations electrical, grid connection Contractors all risk (£) - one off on CAPEX Cost overun (£) - % of 1st year revenue total capital expenditure capital grant contingency Capital Expenditures 2008 1 10.0% (£'000) 4,659,265 (28,808.5) 2.473% 25.0 -2,059,993 0% 18:03 on 24/09/2004 -2,059,993 OWC Cost & Prog rev 01 Shoreline Economic Model Year Ending Power in the Sea Frontage per unit Units per device Number of devices Capture efficiency Turbine efficiency Generator efficiency Device Output Total Output transmission and transformer losses Capacity after losses (MW) 2007 0 kW/m 34.0 m 20.0 no. 1.0 no. 42% % 65% % 2% MW 0.2 2013 6 2014 7 2015 8 2016 9 2017 10 2018 11 2019 12 2020 13 2021 14 2022 15 2023 16 2024 17 2025 18 2026 19 2027 20 2028 21 2029 22 2030 23 2031 24 2032 25 (1,178.1) 8760 8,760 3% £/MWhr Income £ / year £/yr 8,784 8,760 8,760 8,760 8,784 8,760 8,760 8,760 8,784 8,760 8,760 8,760 8,784 8,760 8,760 8,760 8,784 8,760 8,760 8,760 8,784 8,760 8,760 8,760 263 264 263 263 263 264 263 263 263 264 263 263 263 264 263 263 263 264 263 263 263 264 263 263 263 8,497 8,520 8,497 8,497 8,497 8,520 8,497 8,497 8,497 8,520 8,497 8,497 8,497 8,520 8,497 8,497 8,497 8,520 8,497 8,497 8,497 8,520 8,497 8,497 8,497 2.5% 35 37.7 38.6 39.6 40.6 41.6 42.6 43.7 44.8 45.9 47.1 48.2 49.5 50.7 52.0 53.3 54.6 56.0 57.4 58.8 60.3 61.8 63.3 64.9 66.5 68.2 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 60.7 65.4 67.0 68.7 70.4 72.2 74.0 75.8 77.7 79.6 81.6 83.7 85.8 87.9 90.1 92.4 94.7 97.0 99.5 102.0 104.5 107.1 109.8 112.5 115.3 118.2 121.2 69.9 107.36 109.93 112.58 115.28 118.06 120.90 123.82 126.80 129.87 133.01 136.22 139.52 142.90 146.37 149.92 153.56 157.29 161.12 165.04 169.05 173.17 177.40 181.72 186.16 190.70 195.36 157,806 162,040 165,483 169,466 173,548 178,219 182,021 186,417 190,924 196,078 200,277 205,129 210,103 215,791 220,427 225,783 231,274 237,550 242,670 248,582 254,642 261,569 267,221 273,747 280,437 - - - - - - - - - - - - - - - - - - - - - - - - - 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2,050 2,101 2,154 2,208 2,263 2,319 2,377 2,437 2,498 2,560 2,624 2,690 2,757 2,826 2,897 2,969 3,043 3,119 3,197 3,277 3,359 3,443 3,529 3,617 3,708 3,156 3,241 3,310 3,389 3,471 3,564 3,640 3,728 3,818 3,922 4,006 4,103 4,202 4,316 4,409 4,516 4,625 4,751 4,853 4,972 5,093 5,231 5,344 5,475 5,609 12,813 13,133 13,461 13,798 14,143 14,496 14,859 15,230 15,611 16,001 16,401 16,811 17,231 17,662 18,104 18,556 19,020 19,496 19,983 20,483 20,995 21,520 22,058 22,609 23,174 30,590 10 100.00 £/kW kW 500.00 500.00 total capital expenditure capital grant contingency Capital Expenditures (£) (£) (£) 250,000 11.8% 1,762,605 83.4% 60,000 2.8% 2.0% 41,452 2.0% (£) 2,114,057 0% 10% (£) 2,325,463 - 2,000 2,325,463 - 2.00% 10% % (£) @£/yr 391,934 5.0% £12,500 0.80% 16,912 17,335 17,769 18,213 18,668 19,135 19,613 20,104 20,606 21,121 21,649 22,191 22,745 23,314 23,897 24,494 25,107 25,734 26,378 27,037 27,713 28,406 29,116 29,844 2.0% 3,156 3,241 3,310 3,389 3,471 3,564 3,640 3,728 3,818 3,922 4,006 4,103 4,202 4,316 4,409 4,516 4,625 4,751 4,853 4,972 5,093 5,231 5,344 5,475 £2,000 - EBITDA Equity Discount rate 10.0% - (£'000) 5,609 2,050 2,101 2,154 2,208 2,263 2,319 2,377 2,437 2,498 2,560 2,624 2,690 2,757 2,826 2,897 2,969 3,043 3,119 3,197 3,277 3,359 3,443 3,529 3,617 3,708 40,137 41,152 42,157 43,204 44,278 45,399 46,507 47,664 48,849 50,086 51,310 52,586 53,895 55,260 56,611 58,020 59,464 60,971 62,462 64,018 65,612 67,275 68,921 70,638 464,332 2,325,463 117,669 120,888 123,326 126,261 129,270 132,821 135,514 138,754 142,074 145,992 148,967 152,543 156,208 160,531 163,816 167,764 171,809 176,580 180,207 184,564 189,030 194,294 198,300 203,109 - 183,895 1 0.9000 0.8100 0.7290 0.6561 0.5905 0.5314 0.4783 0.4305 0.3874 0.3487 0.3138 0.2824 0.2542 0.2288 0.2059 0.1853 0.1668 0.1501 0.1351 0.1216 0.1094 0.0985 0.0886 0.0798 0.0718 2,325,463 105,902 97,919 89,905 82,840 76,332 70,586 64,816 59,729 55,042 50,904 46,747 43,083 39,706 36,724 33,728 31,087 28,653 26,504 24,343 22,439 20,684 19,134 17,575 16,201 - 13,202 -93,019 -93,019 -93,019 -93,019 -93,019 -93,019 -93,019 -93,019 -93,019 -93,019 -93,019 -93,019 -93,019 -93,019 -93,019 -93,019 -93,019 -93,019 -93,019 -93,019 -93,019 -93,019 -93,019 -93,019 cash Asset Life - Straight Line (years) Salvage Value (£) Depreciation Rate Tax - Declining Balance 2012 5 0.2 % Power Price (£ per MWh) Present Value Project NPV (£'000) IRR 2011 4 168.9 MW £/MWhr £/MWhr £/MWhr p/kWhr Insurance Cost Operational (£/yr) - % of CAPEX Business interuption (£/yr) - % of revenue 3rd Party (£/yr) 2010 3 91% kW RPI increase Renewable Obligations Certificate Climate Change Levy (2002 prices) Power price (standard market price comparison) Total Operating Cost Operating Costs - (£) @£/yr Crown Estate rent @%of energy revenue Decommission Maintenance Cost % of BOP cost 2009 2 1.0 % Hours Available Production hours in year Maintenance hrs-during summer ie forced outage CAPEX BoP cost / kW Unit turbine BoP cost foundations electrical, grid connection Contractors all risk (£) - one off on CAPEX 2008 1 (1,178.1) 3.564% 25.0 0% 18:03 on 24/09/2004 Appendix E Discount Rate Sensitivity The Carbon Trust E1 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Introduction This appendix looks at the economic viability of shoreline and near shore OWCs by assessing the future development’s Net Present Value (NPV) compared with a range of equity discount rates (EDR). The range of particular project variable is set out across the top of the following tables, and shows the effect on the NPV. The base case variables are as defined in the economic model in Appendix D. In line with section 10.3, the shoreline project is assessed using a 10p/kWhr production cost, and the near-shore using a current possible production cost of 5p/kWhr. E2 Shoreline EDR Sensitivities E2.1 Project CapEx Our current best estimate of the total construction cost for a project of this scale is £2.3 million. In a remote location allowing for a power production cost, including ROCs and CCL of 10p/kWhr the project would still not be economically viable. However if the CapEx figure could be reduced by 50%, then a positive NPV could be achieved at approximately 10% EDR. E2.2 Power Production cost In a remote location allowing for a power production cost, including ROCs and CCL of 10p/kWhr the project, again the project would still not be economically viable. However, if the total power production value including ROCs and CCL were increased to £180/MWhr an equity discount rate of approximately 10% would achieve a positive NPV. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page E1 The Carbon Trust E2.3 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Wave Resource The table shows that the OWC would need to be sited in the best wave resource available around the UK of 51kW/m to achieve a positive NPV with a discount rate of 8%. E2.4 Capture efficiency A minimum of 60% pneumatic capture efficiency would be required to achieve a positive NPV. E2.5 Capital Grant The table below gives an illustration of the level of capital grant required to achieve a positive NPV. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page E2 The Carbon Trust E3 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Near-shore Sensitivities E3.1 Project CapEx Our current best estimate of the total construction cost for a project of this scale is £40.8 million (all in, including 10% contingency – see economic model). In the UK context with a power production cost, including ROCs and CCL of 6p/kWhr the project would require an equity discount rate of approximately 7.5% to achieve a positive NPV. The CapEx figure could realistically vary by plus or minus 20%. This at best would give a positive NPV at approximately 10% EDR, and at worst would leave the project far from viable. E3.2 Power Production cost The target power production cost of £60/MWhr assumes a power trading value of £21/MWhr, a ROC value of £35/MWhr and CCL of £4/MWhr. This should be considered the current best estimate and lower bound figure, and again would require an equity discount rate of approximately 7.5% to achieve a positive NPV. However, if the total power production value including ROCs and CCL were increased to an assumed upper bound of £95/MWhr (It is currently forecast that the value of ROCs may increase to £55/MWhr in the run up to 2010) an equity discount rate of approximately 10% would achieve a positive NPV. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page E3 The Carbon Trust E3.3 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Wave Resource The table shows that the OWC would need to be sited in the best wave resource available around the UK of 51kW/m to achieve a positive NPV with a discount rate of 7%. E3.4 Capture efficiency An optimistic future vision of 60% would require an equity discount rate of approximately 6.5% to achieve a positive NPV. E3.5 Capital Grant The table below gives an illustration of the level of capital grant required to achieve a positive NPV. Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page E4 Appendix F Improvement Variables Discount Rate Sensitivity The Carbon Trust F1.1 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Shoreline OWC Improvement Variables Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page F1 The Carbon Trust F1.2 Marine Energy Challenge Oscillating Water Column Wave Energy Converter Evaluation Report Near-shore Improvement Variables Arup \\EGYNTS01\JOBS\100000\115214-00\4 INTERNAL PROJECT DATA\4-05 REPORTS\WORKING DRAFTS\OWC FINAL REPORT REV1.DOC 4 February 2005 Page F2 Appendix G Peer Review Responses OWC Peer Review Form Arup Ref Number: 115214-00 Powertech Ref Number: Principal Reviewer: Date Graeme Mackie 11 October 2004 Company Discipline WAVEGEN PLEASE COMMENT OF THE FOLLOWING ASPECTS OF THE REPORT, USING YOUR OWN EXPERIENCE, DATA AND RESULTS WHERE APPROPRIATE TO ILLUSTRATE COMMENTS MADE STATE OF THE ART ACTIONS TAKEN / RESPONSES Note: E-On responses are in red Missing data Recent advances Economics of Near-Shore OWC Wavegen’s current projections are 5.7p/kWh based on UK pricing for a fully developed system in a large scale development. A further review of economics has been made. This report forecasts 5p/kWh as a target in near term. General comments Executive Summary (page 1) 6th para. Replace ‘actual wave resource’ with ‘average wave resource’. The distribution of wave heights is such that for any exposed site the will always be occasions when there is sufficient energy to drive an oversized turbine/generator but there may be insufficient of those occasions in relation to the annual average wave environment. Generic Future Vision – a near-shore concrete caisson OWC (page 2) Do sandy bottom sites exist where there is 34kW/m average wave power? From British Geological Survey maps we would expect rock bottom with 1 to 2 m sand or gravel which would be fugitive in nature. If deep sand sites are not available does this change the solution or economics? Power Production Costs (page 3) For the Near-shore device the annual energy produced per device is 6100MWh. To arrive at this figure assumes an input power of 34kW/m. However, this is the incident power at 20m water depth. The incident power at 9 – 11m water depth will be less. Agreed. Importance is firm, acceptably level sea-bed. Efficiency of pneumatic capture is taken from the 20m contour value. 3.1.1 Concept (page 11) LIMPET was commissioned at the end of 2000 (November 2000). Report changed. 3.1.4.1 (Page 12) – first para. The benefit of the contra-rotating unit on LIMPET was to allow the downstream blade to recover energy from the swirl introduced by the upstream blade. Under steady state conditions on a test rig this gave broader bandwidth than a monoplane turbine. However, in practice the Added to end of first para..“However, in practice the cyclical motion does not allow the system to stabilise and energy recovery is minimal.” \\Egynts01\jobs\100000\115214-00\4 Internal Project Data\4-05 Reports\External Peer Review\Peer Review Form Wavegen 1st pass with Arup & EON responses final.doc cyclical motion does not allow the system to stabilise and energy recovery is minimal. 3.1.4.1 (Page 12) – third para. There is no flow induced vibration problem with the butterfly valve. 3.1.4.1 (Page 12) – forth para. Modulation of the radial valve to achieve flow control is feasible. The problem on LIMPET relates to a lack of instrumentation which is currently being addressed. 3.1.4.2 (Page 13) – fifth para. The induction machine using resistors to dissipate rotor energy was the 75kW QUB machine, not LIMPET. Remove 5th, add below:The original induction machine drive design used resistors to dissipate rotor energy and provide variable speed operation this would as with the 75kW prototype give rise to poor efficiencies. Replacement with an industrial standard drive system should have given much better electrical efficiencies than those reported. If the figure of 32% electrical efficiency is correct than it is probably due to a combination of rotor resistance losses, over rating of the machine and operation in low sea states. 3.1.4.2 (Page 13) – sixth para. LIMPET is very much under active development. In 2004 Wavegen installed and tested a new small modular turbine with improved controls on LIMPET’s north outlet. The main unit has been reconfigured to a 250kW monoplane unit and additional instrumentation has been added to transmit measurements of flow and noise in real time. Modifications are planned to the acoustic attenuation solution. Detailed analysis of the flow regime has been carried out using state of the art CFD software in order to align predicted flow improvements with mathematical modelling and site measurements. LIMPET has a full programme of tests through to 2006 involving a range of turbine solutions. 3.1.4.3 (Page 13) – fifth bullet point Deluge of the turbine hall by overtopping is an expected event and the structure has been designed to survive it. There was one incident where a door was pushed in by the external head of water but the door has been replaced by a more substantial one. 3.1.4.4 (Page 14) – Successes Could also add:- Checked with E-ON No change - Reference is made to the claim that these problems have been over come. Removed “However, read across…” Added.. “This is reported to be due to the lack of instrumentation which is currently being addressed” Checked with E-ON. – Changed 5th paragraph to that indicated. Report changed to say LIMPET still under development. There is still one standard wooden fabricated door that is a turbine room access and is totally unsuitable for the environment. Report changed. OK • • • • • Reliability of basic system Performance matches mathematical model Performance matches tank model after correct bathymetry applied Successful integration to local grid Demonstrates the potential of future optimally designed units 3.1.4.5 (Page 14) – Performance Did we really quote that we expected 100% generator efficiency? Yes. [Ref.5] – P35, Fig 29 \\Egynts01\jobs\100000\115214-00\4 Internal Project Data\4-05 Reports\External Peer Review\Peer Review Form Wavegen 1st pass with Arup & EON responses final.doc Estimated Efficiency 80% 60% 90% 43% 3.2.3 Design (assumptions and working principles) Geometry: Total height above MWL is 15m Blade form: 3D symmetrical Rated voltage: 400V Inertia: 600kg.m^2 13.4kW/m wave resource was based on 4 years of site measurement. 3.2.4.1 Problems As a note on the flooding of the control room, the control room has now been re-positioned separate from the device. Reasons for doing this were to improve access and remove equipment from the splash zone 3.4.5.1 The Denniss-Auld Turbine Text does not mention that this is a variable pitch device. 3.7 Other OWC installations QUB’s 75kW device on Islay was dismantled in 1999. 3.9 Risk Matrix LIMPET Schedule inaccuracy – Medium (was commissioned Nov 2000, not end 2001) LIMPET Operation & Maintenance Deluge of equipment room – Should be Low. The equipment room is behind a bund and has never suffered deluge. The turbine room is regularly overtopped but is designed for such. - If marine standard doors were fitted throughout turbine building, but they are not. Maybe change this to Control and Equipment Room to avoid confusion. The fact that it was moved is an indication of the high risk. Pico’s problems also illustrates the point. 3.10.1 LIMPET was commissioned Nov 2000. 3.10.2 Presumably annual average output for Port Kembla is ‘estimated’ Items added to report. OK Noted. No change needed. Note added on moving control room. OK Note added that it is variable pitch. OK Report changed. OK Considered a high risk compared to other projects. Report re-worded saying equipment room not deluged Suggest leaving it at High. Done. Report amended. Report amended. OK Noted. Recognition of Wavegen given elsewhere. Yes – Added – “estimated” 7.1.4 2. edit text to read ‘Wavegen’s roof only OWC concept using pre-cast …..’ Report amended. OK 7.1.4.1 Roof only OWC Text to read “A roof only OWC is a concept developed by Wavegen that utilizes the ….” OK \\Egynts01\jobs\100000\115214-00\4 Internal Project Data\4-05 Reports\External Peer Review\Peer Review Form Wavegen 1st pass with Arup & EON responses final.doc OWC Peer Review Form Arup Ref Number: 115214-00 Powertech Ref Number: Principal Reviewer: Date Graeme Mackie 4 November 2004 Company Discipline Wavegen PLEASE COMMENT OF THE FOLLOWING ASPECTS OF THE REPORT, USING YOUR OWN EXPERIENCE, DATA AND RESULTS WHERE APPROPRIATE TO ILLUSTRATE COMMENTS MADE STATE OF THE ART ACTIONS TAKEN / RESPONSES Note: E-On responses in red. Discussed further with Wavegen who Executive Summary – Generic Future Vision – a nearshore OWC now accept the efficiencies quoted by The report indicates 42% wave to pneumatic conversion efficiency. Arup/E-on. There was a Wavegen achieves this level of conversion efficiency in its wave tank misunderstanding in that Arup/E-on with devices having low freeboard wing walls and would expect better are quoting efficiencies based on 20m than 42% for the geometry shown in the report. The NEL OWC contour values whereas Wavegen were breakwater device “NEL OWC Breakwater Device 2GW Power Station, using lip values. When the expected Report 103/80 dated 1980” quotes a measured wave-to-pneumatic efficiencies are normalised they are not conversion efficiency of 71% based on a PM Spectrum representative of too dissimilar. west of Lewis seas. Wavegen would expect about 60% to be achievable OK with the Arup-E.ON arrangement. 3.8 Wavegen is also targeting the new breakwater market with small (20kW – 35kW) Wells turbine-generator units, one of which is currently being tested in LIMPET. (see also paragraph 9.4.1) 3.10.1 – LIMPET LIMPET cost was £1,746,577 including Wavegen R&D and project management of £300,000 and grid connection of £129,000. Changing from £2.2M to £1.75M reduces the actual cost of power in column six to 39p/kWh. With the improved turbine efficiency now being achieved (48% instead of 22%) this brings the cost of power down to 18p/kWh. Were LIMPET to experience the designed 20kW/m input power then the cost would further fall to 11p/kWh (at zero interest rate as in your table). 6.1 - 1st para. With reference to the statement, “skill required in the project execution has been relatively low”, just because the projects executed to date have been small it does not follow that the skills required to execute them have been any less than for big projects. In some ways a tightly funded small project can offer more challenges than a large well funded project. 7.1.4.1 – in situ construction (2nd para) Secondary dredging operations on LIMPET have been relatively inexpensive, i.e. about 1.5% of project cost. Text added covering this development. OK Costs have been escalated to 2004 values. Arup/E-on also believe that Wavegen’s recorded costs are lower because contractual risks were passed down to a subcontractor who was unable to perform. The true costs of project execution are believed to have not been passed through to Wavegen because of this. OK Text amended to say that a ‘small scale’ low overhead methodology may be appropriate and cheapest for smaller projects but production projects will need a different approach. OK ‘Difficult’ has been removed. OK \\Egynts01\jobs\100000\115214-00\4 Internal Project Data\4-05 Reports\External Peer Review\Peer Review Form Wavegen 2nd pass withArup & EON responses final.doc 7.1.4.1 – Cliff face tunnel OWC – 3rd para. Wavegen is in a joint venture with the local Utility and performs assessments and design on behalf of the JV. Wavegen is reporting costs in the range 9 to 15p/kWh for this project. Text amended to reflect jv arrangement and economics. OK 7.1.4.3 – 4th bullet point Blasting and dredging proved to be a low cost means of bund removal. Water column blockage has not been a significant issue. Bullet point deleted. OK 8.2.2 – last para Neither LIMPET nor Pico had bi-planar turbines. The QUB 75kW device on Islay tested a bi-planar turbine and found it to be marginally superior to a monoplane unit. A bi-planar turbine is a simple solution for introducing increased solidity and damping and Wavegen is finding the performance of its small 20kW bi-planar unit currently being tested on LIMPET gives whole cycle blade efficiencies approaching 60%. Strictly speaking this is a twin rotor solution as the blade separation is greater than 1.5 chord lengths. Further tests are planned with a true bi-planar set up. Replace first 2 sentences with:….The contra-rotating design has not proved successful at Limpet and simpler monoplane and bi-plane designs appear to be favoured for the future. The disappointing performance of contra-rotating designs is believed to be due to having too much damping for the OWC. However ……etc 8.3.1 – 2nd para. Pico blades are also aluminium alloy. The stator blades however are stainless steel. Change 2nd paragraph: To date …etc….or stainless steel (Port Kembla) or both (Pico). 8.3.1 – 4th para. Wavegen requests that the reference to 6000 hours between blade changes be removed from the report. While cracks were detected on some of the blades the change out of blades was also linked to a reconfiguration of the turbine to run as a single monoplane unit and the wish to introduce stress monitoring on the new blades. The stress corrosion fatigue is as much exposure time related as stress cycle related. The blades were in-service for 30,000 hours. Mechanisms that might lead to stress corrosion fatigue are currently under investigation at Wavegen. Solutions to extend blade life are being evaluated including changes to blade manufacturing process, improved protective coatings, leading edge and root protection from abrasion and improved air flow to reduce turbulence inducing stress variations. Change last sentence to:It was suggested that the blades would not be re-useable after 6,000 hours running in 30,000 hours of service. 8.4.5 – 2nd para. Wavegen recently (August 2004) installed a new small twin rotor Wells turbine unit at LIMPET. This unit has an in-line silencer and with this configuration no difference in performance between the inhale and exhale cycles is evident from initial trial results. Early results with this unit have demonstrated overall pneumatic-to-wire (turbine + generator + inverter drive) efficiencies of just under 50% which, after deduction of electrical losses, gives a whole cycle turbine efficiency in excess of 60%. E-on commented: Changed first 2 sentences of paragraph as shown opposite. E-on commented: Pico blades were reported to us as stainless steel by IST. We were aware of the confusion at the time of writing and the report comments still stand. We were told a number of blades were unsuitable to be reused after the stated period this is the case and the comment is relevant to the point made. Changed end of paragraph as indicated. E-on commented: This prototype was witnessed during our site visit and only ran for a day, before a clutch throttle valve mechanism failed. The OWC is not matched to this 20kW turbine, and hence the forward and reverse flow efficiencies may well not be typical of matched OWC and turbine. This level of expect turbine efficiency has been \\Egynts01\jobs\100000\115214-00\4 Internal Project Data\4-05 Reports\External Peer Review\Peer Review Form Wavegen 2nd pass withArup & EON responses final.doc assumed in the Future Vision. Comments in this section reflect the view that Limpet’s reported performance can be improved. 8.6 – 1st para. Loss of grid does lead to a loss of availability as explained in your second paragraph and this is linked to the fact that LIMPET is not operated with 24 hour / 7 day coverage and therefore grid events can lead to, at worst case over a weekend, up to 2 days loss of production. Design is also an attributable factor in that there is no redundancy built in to any of LIMPET’s systems, but this is forced by financial constraints on an ambitious prototype project run by an SME. Therefore failure of a fairly minor component such as a sensor or PLC cards can lead to lengthy downtime while spares are procured and fitted. More recently we have introduced a planned maintenance scheme to maximise system availability. It also has to be considered that LIMPET is a demonstration device and as such is linked to a programme of research involving changes to systems, particularly data capture systems, and testing of alternative control strategies. All of these activities involve shut down while being implemented. As such, 65% plant availability is considered quite a good figure by Wavegen. The reliability data acquired on key components confirms that, for a commercial project properly manned on a 24/7 basis and with first line spares and on-call maintenance team, 90% availability is quite achievable with the current design. 9.2.3 & 9.3.2 The prime sites identified in the report (Shetland, Islay, Orkney) will more likely require a nearshore device to be placed on rock with a thin fugitive covering of sand or gravel. While charts might show sand, geological survey maps show this to be a thin covering over rock as would be expected in areas of high wave energy. 9.4.1 - 1st para. The 20kW turbine referred to has specific application to breakwater projects of relatively low incident wave energy. The economics for such schemes can be very attractive as most of the civil costs are incurred irrespective of the installation of wave energy device. Breakwaters can extend up to more than a kilometre in length at large ports and a scheme experiencing only 8kW/m could involve an installed capacity of around 4MW made up of 200 x 20kW turbines. The attraction of this scheme is the low manufacturing and installation cost for the mass produced turbine-generator modules and their easy of change-out for maintenance. In addition, the output from a number of small units provides a smoother integrated power supply than the output from a single large unit. 10.4 – last para. Someone stepping straight to the final conclusion paragraph of this report without understanding the nuances of the terms shoreline and nearshore might read this paragraph and conclude that it applies to OWC devices in total, particularly as the previous bullet points refer to nearshore devices. E-On commented: We are aware of all these points and we agree, and have made the point that an availability of great than 90% should be achievable if auto restart following loss of grid is provided as would be expected with a commercial design Report amended to clarify that rock sites can be developed too. OK This section of the report has been removed. The points made in the (original) section are valid. The maximum unit size should read 1MW, at the end of paragraph 2. The comments about economies of scale apply. Large scale commercialisation of this technology is not likely at 20kW even in breakwaters. Recommend keeping section and amend if required. Note section has been removed. This section has been replaced for the final draft. OK \\Egynts01\jobs\100000\115214-00\4 Internal Project Data\4-05 Reports\External Peer Review\Peer Review Form Wavegen 2nd pass withArup & EON responses final.doc OWC Peer Review Form Arup Ref Number: 115214-00 Powertech Ref Number: Principal Reviewer: Tom Thorpe Date 14 October 2004 Company Energetech Discipline PLEASE COMMENT OF THE FOLLOWING ASPECTS OF THE REPORT, USING YOUR OWN EXPERIENCE, DATA AND RESULTS WHERE APPROPRIATE TO ILLUSTRATE COMMENTS MADE Action taken / Response General Comment Note: E-On comments in red Before moving onto addressing your report using the structure you propose, some initial orientation is required. Hence I have moved the ‘General Comments’ section to here. The report tries to address a difficult question that I have worked on for some years, namely given what we know of the immature technology known as wave energy, what are the likely future generating costs. The methodology you have used is an intriguing one but, given the time allowed for the feedback, it is not one that I can assess in detail given the information presented in the report. Nevertheless, I am in agreement with what you have set down and I congratulate you on devising such a methodology. It is difficult to be clear about the Economic model used in Section 10.1 and the Appendices (this might be attributable to having lots of information with little time to review it – what is the discount rate used in the calculation? This approach is not the one normally used by the DTI and so I would encourage discussions with the Carbon Trust on agreeing an economic model to be used by all the consultancies in the Marine Energy Challenge. Equity discount rate is 10% in a ‘with inflation’ cost model. My main point is that you have, of necessity, used two generic types of wave power device and one type of turbine to calculate the likely mature technology costs. Your analysis here shows that, in general, shoreline devices do not appear to be economically viable, even with elevated power purchase price, and nearshore devices would only become viable with discount rates of 7.5% or less and then at a power purchase price of £60/MWh. I would generally agree with these values and they confirm the finding of R122 from ETSU that shoreline and nearshore devices have unfavourable economics, even when the nearshore device has a wind turbine on top – Wavegen might wish you to consider that option. However, the Energetech OWC design is very different from the LIMPET/OSPREY concept for the following reasons: • It is fabricated from steel • It is a floating device held in place by mooring lines (it does have ‘feet’ mounted on concrete pads but the main mooring method is taut lines) The assessed ‘learning rate’ from the future costings supplied for the Energetech device appears to be around 16.5% compared to 10% stated in the paper. \\Egynts01\jobs\100000\115214-00\4 Internal Project Data\4-05 Reports\External Peer Review\Peer Review Form Energetech with Arup & EON responses final.doc • • It has a ‘parabolic’ wall to focus the waves on the central OWC area (not a spot since the walls only approximate to a parabola) It does not use a Wells turbine but rather a variable pitch turbine You have noted all these difference within various parts of the report but they have not been included in the economic calculations and ‘Future Visions. However, it is far from clear whether it is possible to do for the Energetech system what you did for concrete devices – we ourselves are only now considering the design of our next device for deeper, more energetic sites. Nevertheless, it means that several of the assumptions made and predicted results from the report are not applicable to this technology. This will be a general R&D focus for any OWC. The turbine may prove better than Wells but improved efficiency is already factored into the economics so should also hold for Energetech. - YES The report will be widened a little in its scope to be more inclusive for the Energetech approach. Text added on learning curves and potential improvements that could be made. \\Egynts01\jobs\100000\115214-00\4 Internal Project Data\4-05 Reports\External Peer Review\Peer Review Form Energetech with Arup & EON responses final.doc \\Egynts01\jobs\100000\115214-00\4 Internal Project Data\4-05 Reports\External Peer Review\Peer Review Form Energetech with Arup & EON responses final.doc General comments - continued P23 – Section 3.4.2: • First para – crest to a single area not point • The end of last para should read ‘the lower the level of wave energy entering the device’ (a cosθ term) not the greater the energy capture loss. P24 – 3.4.3 • End of first para. This sentence should read ‘The relatively shallow slope of the sea bed would ensure that the breaking wave is of the ‘spilling’ type1, which would reduce loadings considerably. Nevertheless, the device has been designed against a breaking wave. P24 – 3.4.4 The meaning of the bullet points is unclear. The parabolic wall has been designed against breaking waves; all the steelwork has been fabricated; the device is moored using taut moorings and legs to ensure the correct chamber level; the anchoring system has no access problems and the feet rest on concrete pads. P 35 – 3.9, Table • The rock integrity is at least a M risk – it governs the piling for the mooring system, so we conduct extensive drilling for cores • Scour is probably a L or M risk – we use concrete pads • Turbine efficiency is probably an M risk – it has been studied extensively, so it should be similar to the others P 36 – 3.9, Table • Productivity gain should be better than the rest because it is a steel construction, which offers some benefit from replication: e.g. we would employ reusable bags to provide additional buoyancy rather than build in steel buoyancy tanks • Ballast placement should be an L – the device is floating and moored against its buoyancy P 44 – 4.5.6 • Most turbines have some inertia to smooth out speed variations, others have a flywheel attached for this purpose P45 – 4.7 • There are also hundreds of OWCs operating with minimal maintenance as power sources for navigational buoys P69 – 6.1 • Para 1 – it is true that small designers and contractors make for low skill levels in construction – that is why we use J P Kenny and experienced offshore fabricators and installers • Para 3 – we don’t have sub-divisions, because we have a different shape of ‘wave front’ approaching the OWC chamber - a converging ‘circular’ wave front. We believe that sub-divisions are not needed but the Port Kembla device will confirm or deny this. Report amended. Report amended. Reflector wording amended. Other points noted but no changes proposed. Report amended. Report unchanged as the concrete pads might be undermined. No change as the turbine type is still a prototype whereas Wells turbines had been used in each of the other OWCs Agreed - no available data yet. Noted – no change made. Concrete also has repeatability benefits and PK is already shown as being better than LIMPET and Pico. Report amended to ‘not applicable’. Comment added that flywheels are used. Yes, there are different approaches. This section is about control systems. Report amended. OK Comment added about small scale vs large scale. Report amended. P 79 – 7.2.1.3 \\Egynts01\jobs\100000\115214-00\4 Internal Project Data\4-05 Reports\External Peer Review\Peer Review Form Energetech with Arup & EON responses • It would make more sense to utilise an existing dry dock. final.doc The steel structure has allowed Energetech to use an existing fab yard. P82 – 8 • Queens University Belfast has lots of information on the topics covered here, which might be better to use. It seems ambitious to develop a Grand Unified Theory of OWCs as part of this exercise. For instance, J P Kenny looked at AQWA for our system but found out that its accuracy was low in shallow water systems. • Nearly all this Section is not applicable to the Port Kembla system. QUB were involved in an interactive workshop on OWC’s with Arup & Wavegen where the procedure for assessment shown here was presented without undue comment. Text widened a little to avoid comments that it is not relevant to the PK system. P99-9 • For reasons noted above, several parts of this Section are not relevant to the Energetech device. Ditto, above point. P 102 – 9.2.3 • We have assessed both a concrete and steel structure for the same duties at Port Kembla and the steel structure turned out cheaper due to the vast size of the caissons needed for the concrete structure. Importing steel structures from Indonesia is likely to be cheaper than Australian concrete construction. No change made. 1 Hedges, TS, (2001). “Wave Breaking and Reflection”, Technical Note, University of Liverpool, Dept. of Civil Engineering. Henderson, AR, (2001). “Breaking Wave Loads on Offshore Wind Turbines”, EWEA Special Topic Conf. On Offshore Wind Turbines, Brussels, December 2001. Holmes, P, (2001). “Coastal and Offshore Structures”, in a Course on Coastal Defence Systems, University of West Indies, July 18-21, 2001 \\Egynts01\jobs\100000\115214-00\4 Internal Project Data\4-05 Reports\External Peer Review\Peer Review Form Energetech with Arup & EON responses final.doc STATE OF THE ART Missing data P17- End of 3.2.4.1: There were additional problems that I think have significant implications for wave energy. • The fabrication and installation was at a remote site with little infrastructure • There was often a single source for construction work These observations confirm your recommendation to build at a central fabrication yard and then tow and install. P 27 - 3.4.3: • Total height above MWL – 12 m • Arrangement – horizontal axis • Duty type – 50 Hz, 12 pole • Rated speed – 500 rpm • Max test speed – 750 rpm • Hub tip ratio – 0.75 • Blade chord - mm P24 – 3.4.5 • Wave to pneumatic – 67% • Pneumatic to mechanical – peak 80%, average 54% • Mechanical to electrical – 90% • Overall – 32.4% Report amended. Data added to table. Data added to table. OK \\Egynts01\jobs\100000\115214-00\4 Internal Project Data\4-05 Reports\External Peer Review\Peer Review Form Energetech with Arup & EON responses final.doc Recent advances P94 – 8.4.5 • The latest predictions of turbine efficiency are shown below. Noted \\Egynts01\jobs\100000\115214-00\4 Internal Project Data\4-05 Reports\External Peer Review\Peer Review Form Energetech with Arup & EON responses final.doc RESOURCE ASSESSMENT Data Sources Method of Data Acquisition UK Resource / Development Site Ranking Definition of energy input Shoreline v Nearshore Energy Calculation • ETSU report R-120 gives a shoreline resource of 400 GWh/year (v Arup 230) and nearshore of 2.1 TWh per year (v Arup’s 7.8). A reasonably good agreement considering the very different methodologies used. Notes added to s5.1 & conclusions. DEVICE MODELLING Methods used Model limitations Specific modelling tools used Modelling of damping TANK TESTING Accuracy / limitations Facilities used Damping considerations \\Egynts01\jobs\100000\115214-00\4 Internal Project Data\4-05 Reports\External Peer Review\Peer Review Form Energetech with Arup & EON responses final.doc EFFICIENCIES Wave capture calculation Turbine efficiency P 41 – 4.3 The addition of parabolic walls makes the Port Kembla device very different. You are no longer dealing with a wave front impacting on a rectangular OWC chamber but with a nearly circular wave surge approaching the column from the front and sides. This behaviour will have different characteristics (e.g. effect of column inclination and lip) to a conventional system. I agree with you that this system needs optimisation. P41 – 4.4.1 In the penultimate para, a control system is cited to have poor reliability and high maintenance requirements but in the next para an actuated valve has none of these downsides. The control system on the turbine is an actuator – out of the air flow. Text expanded to cover Port Kembla case in greater detail. E-ON commented: We think these are very different systems. Consideration needs to be given to the duty of the device. A rotating mechanical control system that is continually operative is somewhat different to a static device that only operates occasionally. However a blow off value and throttle valve are still challenging systems to design. Generator efficiency COSTS BOP £/kW Grid connection Operation & Maintenance \\Egynts01\jobs\100000\115214-00\4 Internal Project Data\4-05 Reports\External Peer Review\Peer Review Form Energetech with Arup & EON responses final.doc ECONOMIC MODEL Power Price P78 – 7.2 If only it did generate at 5 p/kWh!!! The wave regime at Port Kembla is low, as befits an initial device and, therefore, it is unlikely to generate at 5 p/kWh. We have made no prediction of the cost as yet, because we have seen how all previous device predictions have been incorrect. We must have misunderstood previous discussions – the section has been deleted. Likewise Insurance costs IMPROVEMENTS Priorities Possibilities / Future vision CONCLUSIONS ANY OTHER COMMENTS \\Egynts01\jobs\100000\115214-00\4 Internal Project Data\4-05 Reports\External Peer Review\Peer Review Form Energetech with Arup & EON responses final.doc OWC Peer Review Form Arup Ref Number: 115214-00 Powertech Ref Number: Principal Reviewer: Date António F. de O. Falcão 16 October 2004 Company Discipline IST, Portugal PLEASE COMMENT OF THE FOLLOWING ASPECTS OF THE REPORT, USING YOUR OWN EXPERIENCE, DATA AND RESULTS WHERE APPROPRIATE TO ILLUSTRATE COMMENTS MADE STATE OF THE ART ACTIONS TAKEN / RESPONSES Note: E-On responses in red. 1. General comments The report is a very valuable contribution to the assessment and to the Arup/E-on deliberately chose to review the more recent papers starting development of OWC technology for wave energy conversion. around 1993. The reference list is, of Most of the assessment conclusions in the Report coincide with my points course, not exhaustive but we consider of view (and in many cases my intuition) and with my own experience that enough has been reviewed to gain with wave energy in general and OWC technology in particular (I was the a picture of OWC technology. co-ordinator of the several projects within whose framework the design and construction of the Pico OWC plant took place). EON reviewed over 100 papers As could be expected, a large part of the report is devoted to the special applicable to the areas of the turbine, case of how to exploit the UK wave energy resource with OWC OWC control, generator and controls converters. Since my own experience is rather with the Portuguese case, I and prototype project reports. Not all abstain from commenting such sections. of these are included in the references. On what concerns the technology, understandably the Report relies We are adding another 9 references heavily on the UK experience, with important roles played by that are relevant to the report. Although there has been a lot of WAVEGEN and the Queen´s University of Belfast. academic research carried out, the Although the number of references (about 70) is by no means outcomes are often far from insignificant, one should say that a very large portion of published conclusive. Similarly attempts have material relevant to OWC technology is not mentioned (was it overlooked been made with many prototype or simply not quoted?). devices but reliable published data is elusive. The authors of the report rightly regard the air turbine as a key piece of OWC plant equipment. The turbine is responsible for a large part of the losses that occur in the energy conversion chain. The Wells turbine (especially its fixed-pitch version) is known to exhibit a relatively modest time-averaged efficiency. Unfortunately, the competing types of selfrectifying turbines are also far from highly efficient. Nevertheless, I would have expected more attention devoted to alternative types of turbine; for example, a relatively large number of easily available papers on the impulse turbine, reporting R&D work in Japan and Ireland, seem to have been overlooked. (The situation is different for the Dennis-Auld turbine, on which (reliable) published information is scarce.) E-On commented & checked out Japanese or Irish research: See above comments. Papers on the research carried out on the impulse turbine have been covered, and comments are made about the improvements that can be made with fixed blade designs. Impulse turbine is referred to throughout the report and the technical issues are discussed in 8.2.1, 8.2.2 and 8.4.3. \\Egynts01\jobs\100000\115214-00\4 Internal Project Data\4-05 Reports\External Peer Review\Peer Review Form Falcao with Arup & EON responses final.doc 2. Detailed comments Pages 16, Table on Pico Plant: • Hub to tip ratio: 0.59 • Blade form: NACA 0012 at tip, NACA 0015 at root • Depth: 8m at lip, 8-10m approach • Rated speed: 1400 rpm (note that the torque is zero at synchronous speed 750 rpm) • Max test speed: 1500 rpm Details added to report. OK Page 17, on the Pico plant. Your statement is confusing: "The assumed E-On commented on time-averaged turbine peak efficiency of 75% seems optimistic for a fixed pitch machine efficiency: Change paragraph as in variable bi-directional flow". Indeed 75% seems to be attainable (from indicated. testing on 0.6m diameter Wells turbine models) as peak efficiency in steady flow, but obviously not as time-averaged efficiency under randomly-varying pressure head. Has there been a misunderstanding on information supplied by the Portuguese team? Yes, apparently. Replace paragraph with:The assumed turbine peak efficiency of 75% is that obtained in a steady flow. The time averaged efficiency in a bi-directional flow will clearly be less than this at around 50%. Page 44. The title 4.6 Mechanical Efficiency is clearly inadequate. Changed to Power Conversion OK Page 70, on the differences between measured and estimated efficiencies. Agreed The low figure of 10% (which I believe concerns to LIMPET) should not be taken as representative of present state-of-the-art OWC technology. We also agree. Indeed, I believe this to be largely due, in LIMPET: (i) to the (surprisingly?) small water depth in front of the structure; and (ii) to the large distortion in the velocity inward-flow distribution at turbine inlet, produced by the (inadequately designed) noise-suppressing device. Page 85. Section 8.2.1. Your conclusion (from the LIMPET experience) E-On commented: should not be made general. Indeed, there is no evidence (on the contrary) You could take that line. Unfortunately due to operational and funding issues that such mismatching occurs at the Pico plant. at Pico, there is insufficient data to make the case that Pico is different. As the turbines are from the same design team, our comments reflect our assessment of that process. Page 86 (last 7 lines). The problem of the guide vanes, that become E-On commented: alternately inlet and exit guide vanes, is very different in the Wells turbine We are aware of these issues and have as compared with the impulse turbine. From the aerodynamic point of stated as such in the text. view, this is known to be a serious problem in the case of the impulse turbine (a major limitation to its peak efficiency) but not for the Wells turbine (see a detailed analysis in L.M.C. Gato, A.F. de O. Falcão, "Performance of Wells turbine with double row of guide vanes". International Journal of Japan Society of Mechanical Engineers, series II, \\Egynts01\jobs\100000\115214-00\4 Internal Project Data\4-05 Reports\External Peer Review\Peer Review Form Falcao with Arup & EON responses final.doc vol. 33, p. 265-271 (1990)). Page 87 (mid-page). Note that the Pico turbine is neither bi-plane nor E-On commented: contra-rotating (it is a mono-plane rotor with double row of guide vanes): This has been corrected following Your conclusion may apply to LIMPET and OSPREY, but not to Pico. comments received from Wavegen. \\Egynts01\jobs\100000\115214-00\4 Internal Project Data\4-05 Reports\External Peer Review\Peer Review Form Falcao with Arup & EON responses final.doc OWC Peer Review Form Arup Ref Number: 115214-00 Powertech Ref Number: Principal Reviewer: RCT Rainey Date 18/11/04 Company Atkins Discipline Structural PLEASE COMMENT OF THE FOLLOWING ASPECTS OF THE REPORT, USING YOUR OWN EXPERIENCE, DATA AND RESULTS WHERE APPROPRIATE TO ILLUSTRATE COMMENTS MADE STATE OF THE ART Missing data Recent advances General comments 1. Survivability of the Generic OWC Devices The proposed offshore WECs appear to be about 10% of the weight of an equivalent breakwater – the author is effectively suggesting that breakwaters could be made much lighter. The Alderney breakwater (see http://www.alderney.gov.gg/pimages/gallery_lg/143.jpg), for example, has a similar wave climate, and is of similar dimensions, but is much heavier because it is solid rather than hollow. It has repeatedly been breached by storms, however, and is not considered to be over-designed, but rather under-designed (see http://www.alderney.gov.gg/index.php/pid/114 contact: [email protected]). There is an ongoing EPSRC-funded research project into the failure mechanism (contact: [email protected]). Model tests have revealed extremely high wave impact pressures (3MPa at model scale), which are absorbed by the inertia of the breakwater, as it shakes in response. Making the structure lighter will tend to increase this dynamic response (reduced inertia implies increased accelerations), and thus make the cracking of the structure more severe. The rubble mound on which the breakwater is built is also vulnerable at Alderney - typical UK sites for the proposed WECs (e.g. Benbecula) would likewise require such mounds, because the seabed is uneven. Thus there would appear to be significant uncertainties over the survivability of the concept. (Note: A representative rate for offshore concrete construction for the North Sea is about £2000/cubic metre. The unit cost of the generic OWC equates to £55,793/metre in total, with 72% dedicated to the structural costs i.e. £40,170/metre. In broad terms, this could equate to a two metre thick concrete section, ten metres high.) 2. Installation Could the author comment on the installation methodology for the generic OWC caisson units at the 9m water depth contour? In our experience, this zone is inaccessible to conventional handling vessels and land-based machinery. Special equipment e.g. jack-up barges could be used, but costs of this equipment would need to be accounted for in the economics. RESOURCE ASSESSMENT Data Sources Method of Data Acquisition Summary of Comments on Microsoft Word Peer Review Form_RCTR_Review.doc Page: 2 Author: gordon.jackson Subject: Note Date: 21/01/2005 14:57:20 The OWC has been designed to gravity substructure standards. It is not a masonry breakwater with earth filling as Alderney. Author: gordon.jackson Subject: Note Date: 21/01/2005 14:57:20 Concrete elements will be designed for impact pressures following current practice. The ability of the foundation to resist impact factors takes account of the relatively large natural period of the structure compared to individual impact events. Author: gordon.jackson Subject: Note Date: 21/01/2005 14:57:20 Scour protection is used on sand sites. Where rock is present at the surface, either underbase grouting or rock anchoring can be considered. Such foundation types would not be susceptible to undermining. Author: gordon.jackson Subject: Note Date: 21/01/2005 14:57:20 The cost estimate has been built up using labour, plant and equipment norms as used on offshore oil and gas concrete platforms. The lower unit cost of the OWCs reflects the lower reinforcement densities, greater productivities and reduced preliminaries requirement for the OWC. Author: gordon.jackson Subject: Note Date: 21/01/2005 14:57:20 The OWC units are floated into position and set down by water ballasting the compartments. The only vessels required are tugs and a dredger to discharge sand ballast into the structure. Both will have reasonable operability in the target summer installation windows. UK Resource / Development Site Ranking 1. Foundation Conditions Could the author comment on the proportion of UK sites that are thought to comply with the foundation requirements for the generic OWC caisson i.e. level uniform sand or clay combined with the power capture requirement for a steeply sloping seabed? At Benbecula, for example, which is typical of the Hebrides, the seabed is characterised as metamorphic bedrock, with randomly distributed depressions and gullies up to 10m deep, filled with loose sand and gravels. The slope trend is approximately 1:100, but there are significant local variations. See Figure 1 below: Figure 1 – Typical Hebridean bathymetric contours Definition of energy input Shoreline v Nearshore Page: 3 Author: gordon.jackson Subject: Note Date: 21/01/2005 14:58:33 The final report enlarges on the possibility of rock sites. Energy Calculation Page: 4 1. Plant availability It is noted that the effects of plant availability are excluded from the production cost assessment i.e. no outages are assumed in calculation. Author: gordon.jackson Subject: Note Date: 21/01/2005 14:57:20 3% planned outage is taken. No allowance is made for un-planned outages. DEVICE MODELLING Methods used Model limitations Specific modelling tools used OWC Peer Review Form Arup Ref Number: 115214-00 Powertech Ref Number: Principal Reviewer: Date Professor Peter White 15 December 2004 Company Discipline University of Coventry Wells Turbines & Thermofluids PLEASE COMMENT OF THE FOLLOWING ASPECTS OF THE REPORT, USING YOUR OWN EXPERIENCE, DATA AND RESULTS WHERE APPROPRIATE TO ILLUSTRATE COMMENTS MADE STATE OF THE ART ACTIONS TAKEN / RESPONSES 1. General Note: E-On comments in red The report gives a fair and accurate description of the world wide design, construction and operation of Oscillating Water Column (OWC) wave energy conversion devices. The Executive Summary highlights the major problems encountered especially for shoreline devices which are unique to the location, have been provided with inadequate temporary works and as a result suffered from extended construction phases. Low wave to wire conversion rates have been experienced largely due to inadequate knowledge of the local wave resource, and poor matching of the turbogenerator, of which more details are given in section3. It is interesting to note that construction costs are still the major factor affecting viability, and is the same as the outcome of the ETSU 1992 report which quoted construction costs and discount rates as having major impacts on the cost of power generation. Turbine Throughout the report, and starting in the viability of OWCs section of the Executive Summary, values of turbine efficiency are quoted, and it is not clear whether these are peak uni-directional steady state values, or overall values in the random flows resulting from the interaction of the OWC with the wave resource, as it is of course the latter value which is of interest. To reinforce this the table in section3.1.4.5 quotes estimated and measured efficiencies of the LIMPET without stating if they are peak values or taken over a one year operating period. In section 3.2.4.2 the meaning of efficiency is also unclear as the estimated efficiency of the turbine is quoted as 75%, and the overall efficiency as 35% whereas below the table is a comment that the assumed turbine peak efficiency of 75% seems optimistic. Clarity is required wherever efficiency is referred to within the document, and should certainly be specified in section 10.1.1.1. The general conclusion in 3.1.4.1 concerning turbine energy capture that a variable pitch turbine is required needs to be considered with the implication this will have on generator sizing, as the turbine will be delivering a wide range of power levels, and large power ranges are not conducive to high generator ffi i i h i t bl 3 1 4 5 Clarified as peak and average as appropriate. This point has also been made by Prof Falcao. The efficiencies in the table should refer to average values that could be obtained in the actual designed for sea state. Where this is not the case it should be clearly stated. The paragraph about a peak efficiency of 75% has been changed, to make this clear. Added 3rd paragraph to 10.1.1:The assumed efficiencies below are the average values that could be obtained in the designed sea state. The issues of low generator efficiency are largely to do with correct sizing of \\Egynts01\jobs\100000\115214-00\4 Internal Project Data\4-05 Reports\External Peer Review\Peer Review Form White with Arup & EON responses final.doc efficiencies as shown in table 3.1.4.5. In sections 4.2 and 8.2.1 Computational Fluid Dynamics (CFD) is suggested as a means of modelling wave to wire performance. It should be noted that CFD predictions of Wells turbine performance are comparable to measured data until the turbine stalls, after which they diverge. the turbine & generator and the “cut in speed” in low sea states. Noted. In section 4.4.1 a potential weakness of the Wells turbine is identified as the turbine consuming power after it has fully stalled, however, what is much more relevant to overall output is that the turbine does not produce any power until the airflow reaches a particular value. Thus at the point of flow reversal in every wave the turbine produces no power, and requires power input to maintain the speed of rotation. This is a major factor in turbine optimisation and sizing. Changed 2nd Paragraph last sentence thus:- “…., particularly at low or high stall air velocity when the turbine may actually consume power to maintain rotation.” The importance of matching the whole system should be emphasised in section 4.5.3. In section 4.6 the improvement of wave to wire efficiencies is discussed with reference to correct sizing, blade design, and best practice from other turbine types. An idea of these effects can be obtained using the work of Lockett, Webster and White which uses a frequency domain model incorporating wave data, OWC conversion rates, and steady state turbine efficiency curves. The programme output is an efficiency of the turbine from air to shaft power over the yearly sea states optimised to give maximum efficiency. For example a Wells turbine with NACA 0015 blades in an OWC subjected to South Uist sea data has an overall efficiency over the year of 47% from a measured peak efficiency of 58% in steady unidirectional air flow. This work can be used to test the comparison between Wells and impulse turbines discussed in section 8.2.1. – A useful tool for further research, work. Noted. Fixed guide vanes on a Wells turbine as mentioned in section 8.2.2 have been shown to improve measured efficiencies by 5-10%. Noted The figures quoted in sections 8.4.3 and 10.2.1 of peak turbine efficiencies of 60-70% hopefully giving overall efficiencies over a range of sea states of circa 50% are born out by the frequency domain predictions mentioned above. ok Added a new paragraph to the end of 4.5.3. Thus:It should be noted that whether the design is considered as a single system optimisation problem or a series of smaller sub-systems to be optimised, each sub-system’s design and performance is dependent on the others. Work has already been carried out on investigating some different blade profiles for use in Wells turbines, and in order to incorporate the effects of Noted. the blades operating on a rotor which is a cascade with a 90o stagger angle tests need to be carried out on A Wells turbine. The tests must be carried out at the same Reynolds number as the full scale Wells turbine, as the operating Reynolds number has a significant effect on the blade and hence turbine performance. Priorities From the aspects of the report discussed the priorities for improving the performance of OWCs are: • Obtain accurate sea wave data for the site being considered. This is especially crucial for shoreline devices \\Egynts01\jobs\100000\115214-00\4 Internal Project Data\4-05 Reports\External Peer Review\Peer Review Form White with Arup & EON responses final.doc • • • • is especially crucial for shoreline devices. Carry out matching of the wave data to the OWC, the pneumatic output of the OWC to the turbine and the shaft output of the turbine to the generator, optimising each component to maximise the electrical output over the year. Use CFD to ensure that the air flow reaching the turbine is uniformly distributed and equal in both directions. Utilise wave to wire predictive models which can assess the effects of turbine type, guide vanes, blade profiles, blow off valves, and any other idea to improve performance before a device is built. Collect data from working OWCs which can be used to verify predictive models. This may necessitate academic institutions working more closely with constructors and operators. We would agree and this is what we have suggested in the scope for improvement and future vision. These priorities are also set out in the R&D section, which is in the final draft. We would also add the use of CFD for optimising the design of turbines as there is still much work to do here. \\Egynts01\jobs\100000\115214-00\4 Internal Project Data\4-05 Reports\External Peer Review\Peer Review Form White with Arup & EON responses final.doc
© Copyright 2026 Paperzz