BRIEF STATUS NOTE ON NLCP WORKS ENDING Dec. 2013

ANASAGAR
Water Purification System
 The Lake water purification system by Aeration &
floating fountains (4 Nos) were installed and is
functioning since 23.01.2009. 10 more floating
fountains have been installed in 2013 for
beautification and aeration of Anasagar Lake.
Water Purification System
Bio-Remediation
Bio-remediation of drains terminating into Anasagar
lake has been taken up since Feb-2013 for treatment
of waste water flowing through drains before
entering in to the lake. At present work is under
Progress In 7 drains are as under :
Nagphani(near Mahaveer colony)
Ramnagar(near R.K marble)
Ramnagar
Kazi ka nallah
Shantipura
Apsara Mension
Choursiawas Drain
Bio-Remediation
CHAURASIAWAS DRAIN
KAZI KA NALLAH
RAM NAGAR II
(NEAR R.K. MARBLE)
SHANTIPURA DRAIN
Jetty Platform & Walkway
The work of Jetty Platform near Chaupati and
walkway along the hillock below the circuit house
with lighting has been completed.
Jetty Platform near Chaupati &
Walkway
Fixing of Steel Grill-Jali to check entry of
Floating impurities into the Lake is being done
.
Grill at Shantipura Drain
Jali at Anasagar Lake
Fixing of Steel Grill-Jali
Grill at Ram Nagar II Drain
Grill at Chauarsiawas Drain
Different IEC has been taken up to create public
awareness & participation which includes showcase of
Jhanki of Anasagar lake on republic day function.
Distribution of pamphlets and cards for awareness of
lake conservation
WATER PURIFICATION
JALI FIXED AT ANASAGAR
Bio-Remediation
JETTY PLATFORM & WALKWAY
WORKS PERFORMED UNDER NLCP- ANASAGAR LAKE
• The sanctioned desilting work of the lake in
2,15,000 cum has been completed, The work of
Desilting in 20000 cum on Anted Nallah,
Chaurasiyawas Nallah, Kazi ka Nallah & Bandi
Nadi has been completed.
• Pucca works for construction work of a pilot
channel with cement concrete bed in about 308
m length in Anted Nallah has been completed
behind the Press club on the Gaurav Path.
• The fencing and Afforestation in 206 Ha &
construction of check dam 31 nos have been
completed by the forest Dept.
• Water Quality Monitoring by testing of sample
monthly is being done regularly in lake and drains.