Requirements Specification

Requirements Specification
1st and 2nd Fix Plumbing Installation
Project
Site Location
Client
Client Address
Client Contact
Client Phone
Client Email
New build dwelling – 3 storeys, 5 beds, 4 baths
Land adjacent to 7 Lime Walk, Maidenhead, Berkshire, SL6 6QB
Kingsacre Homes Ltd
7 Lime Walk, Maidenhead, Berkshire, SL6 6QB
Malcolm Booker
0797 707 2262
[email protected]
Requirements
We are undertaking a new build and require a quotation for the following works on a supply
and fit basis unless otherwise stated.
Quote to exclude sanitaryware.
Kitchen layout and final requirements are TBD but an estimate of requirements has been
included in the figures below.
Split the quote out between first fix and second fix since this has to be budgeted for in our
cash flow.
All works shall comply with all NHBC, Building Control, Gas Safe, and Thames Water
requirements.
Boiler Room (Second Floor Eaves)
Description
First Fix
Second
Fix
Total
First Fix
Second
Fix
Total
Supply and fit 2 x 40 CDI conventional boilers & roof flues
Supply and fit 2 x CL250 HE mega flows
Pipe up heating valves, boilers and mega flows
Electric and wiring not included, to be completed by other contractors
Ground Floor
Description
All copper pipes in screed to be covered by Denso tape – and insulation?
Size up gas pipe & run gas stove 1st and 2nd fix
Size up gas pipe & run gas fire in lounge 1st and 2nd fix
Carcass hot and cold supplies on ground floor to kitchen and cloak room
WCs and basins
Supply and fit 2 x outside taps
Fit 2 x sinks (not required in this quote – just run pipes ready to fit sinks)
Fit 2 x dishwashers (not required in this quote – just run pipes ready to
fit dishwashers)
Connect cold feed to coffee machine, fridge, steamer, filtered drinking
81900739
1 of 3
31/07/2017
water & zip tap (not required in this quote – just run pipes ready to fit
these items)
Connect waste disposal tap (not required in this quote – just run pipes
ready to fit these items)
Fit water softener supplied by customer (moved from boiler cupboard to
kitchen as this is a better location?)
Supply and fit extractor fans to kitchen and WC (electrics by others)
1st and 2nd fix WC & basin taps, mastic where appropriate
Run 28mm flow and return from boiler to the Underfloor Heating
manifold in the kitchen then connect up to UFH when UFH is installed
and passes pressure tests
First Floor
Description
First Fix
Second
Fix
Total
First Fix
Second
Fix
Total
Second
Fix
Total
Carcass hot and cold pipes
1st and 2nd fix family bathroom – 2 basins, 1 toilet, 1 bath, 1 shower,
shower screens, towel radiator, mastic where appropriate
1st and 2nd fix master en-suite wet room – 2 basins, 1 toilet, 1 freestanding bath, 1 shower, shower screen, towel radiator, mastic where
appropriate
Supply and fit extractor fans to family bathroom and master ensuite
(electrics by others)
Supply and fit clothes dryer vent from family bathroom (electrics by
others)
1st and 2nd fix washing machine in master bathroom
Run 22mm flow and return from boiler to the Underfloor Heating
manifold in family bathroom then connect up to UFH when UFH is
installed and passes pressure tests
Second Floor
Description
Carcass hot and cold pipes
1st and 2nd fix 2 x ensuites wet rooms – 2 basins, 2 toilets, 2 showers, 2
shower screens, 2 towel radiators, mastic where appropriate
Supply and fit extractor fans to 2 x ensuites (electrics by others)
Run 22mm flow and return from boiler to the Underfloor Heating
manifold in the boiler cupboard then connect up to UFH when UFH is
installed and passes pressure tests
Under Floor Heating (assume 1st fix flow and returns are included above)
Description
First Fix
Supply and fit poly-pipe under floor heating
Supply controls and rooms stats to be wired up by other contractors
Under floor heating to be fitted on all 3 floors (some others may need to
change)
Labour and materials
Supply floor insulation and damp proof membrane
Fit floor insulation and damp proof membrane
81900739
2 of 3
31/07/2017
Wastes
Description
First Fix
Second
Fix
Total
First Fix
Second
Fix
Total
First Fix
Second
Fix
Total
First Fix
Second
Fix
Total
First Fix
Second
Fix
Total
Connect onto soil wastes above ground
Supply and fit four x soil pipes internally as per architect’s drawings with
tile vents
Connect into wastes from bathroom
Run wastes into bathrooms
Connect and run wastes to kitchen, WC, all bathrooms, boiler and
Megaflow overflows as applicable.
Generally
Description
Commission and test system (including pressure tests)
Issue Gas Safe certificate
Provide for future swimming pool area
Description
Carcass hot and cold pipes for WC, basin, shower, pool filler tap
Consider the waste drainage requirements of these items in waste
drainage design.
Price Option
Description
Price option to fit (not supply) hot water solar panel
Price option to supply and fit hot water solar panel
Separate Quote to fit kitchen appliances
Description
Fit 2 x sinks
Fit 2 x dishwashers
Connect cold feed to coffee machine, fridge, steamer, filtered drinking
water & zip tap
Connect waste disposal tap
Mastic where appropriate
Price option to fit (not supply) hot water solar panel
Price option to supply and fit hot water solar panel