Network Analysis Prepared by hanadi NetWork(start/end node) A. Draw network? B. Determine the critical path Activity (I,j) Prepared by hanadi Activity Duration (1,2) A 5 (1,4) B 4 (1,5) C 3 (2,3) D 1 (2,5) E 2 (2,6) F 3 (3,4) G 7 (3,6) I 9 (4,6) J 1 (4,7) K 10 (5,6) L 4 (5,7) M 5 (6,7) N 2 Prepared by hanadi Prepared by hanadi NetWork(Precedence list) A. B. Draw network? Determine the critical path Prepared by hanadi Activities Predecessor A - B - C A D B E C,D F E Output Prepared by hanadi Program Evaluation and review Technique PERT Example: Consider the following project that has activities, where the a,m and b time are given in the following table: Find Dij, V(Dij) ? Find the critical path and its expected and variance Of total duration time of project? activity Solution by QM and Tora A (I,j) (a,m,b) (1,2) (3,5,7) B (1,3) (4,6,8) C (2,4) (1,3,5) D (3,4) (5,8,11) E (4,5) (1,2,3) F (5,6) (9,11,13) Prepared by hanadi Prepared by hanadi Prepared by hanadi Prepared by hanadi Prepared by hanadi Prepared by hanadi Critical path method (CPM) Critical path: It is a sequence of critical activities. The critical path calculation involve • Forward pass: determine the earliest occurrence times of the events . • Backward pass : determine the latest occurrence time of the events( latest completion time) . Prepared by hanadi Where j Max i Dij j i The project starts at time 0 and i Min j Dij Prepared by hanadi j i Construction of the time schedule • Construction of preliminary schedule for the project. Activities Noncritical activities Critical activities Prepared by hanadi Critical Activities • An activity (i,j) will be critical if • i= j • i= j • ji= ji=Dij Prepared by hanadi Solution by Tora Open tora select from menu project planning CPM critical method and click enter. Enter activities and durations as the following table: Activity (I,j) Prepared by hanadi Activity Duration (1,2) A 5 (1,4) B 2 (1,5) C 2 (2,3) D 7 (2,5) E 5 (2,6) F 4 (3,4) G 3 (3,6) I 10 (4,6) J 5 (4,7) K 9 (5,6) L 4 (5,7) M 3 (6,7) N 3 Click on solve problem and select from options CPM bar chart and CPM calculations then we get : • Figure 1: Prepared by hanadi Determination of the floats Floats : are the slack times available within • the allotted span of the uncritical activity. TFij jiD 1- Total floats ij 2- Free floats FFij j- Where i Dij FFij TFij Prepared by hanadi Figure 2: Prepared by hanadi Red –Flagging Rule: The implication of the rule is that a noncritical activity will be red flagged if its. FFij TFij From previous example Red-Flagging are B and C. Prepared by hanadi
© Copyright 2026 Paperzz