Conceptual Design of Supercritical O2-Based PC Boiler Final Report Andrew Seltzer Zhen Fan Archie Robertson November 2006 DE-FC26-04NT42207 Foster Wheeler Power Group, Inc. 12 Peach Tree Hill Road Livingston, New Jersey 07039 1 DISCLAIMER This report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof. The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof. 2 ABSTRACT The objective of the system design and analysis task of the Conceptual Design of Oxygen-Based Supercritical PC Boiler study is to evaluate the effects of oxygen firing on supercritical PC boiler design, operation and system performance. Simulations of the oxygen-fired plant with CO2 sequestration were conducted using Aspen Plus and were compared to a reference air-fired 460 MWe plant. Flue gas recycle is used to control the flame temperature and resultant wall temperature in the O2-fired PC. Parametric trade-off studies were made to determine the effect of flame temperature on system efficiency. The degree of improvement in system performance of various modifications was investigated. The objective of the advanced oxygen separation system integration task of the study is to evaluate the benefits, effects, and limitations of the integration of advanced oxygen separation technologies into a supercritical O2-fired PC. Simulations of the power generation unit, oxygen separation unit, and CO2 sequestration system were conducted using the Aspen Plus software. The improvement of the O2-fired PC system performance incorporating the Oxygen Ion Transport Membrane (OITM) and Ceramic Auto-thermal Recovery (CAR) were investigated. A parametric study was conducted to determine the sensitivity of the design and performance to various variables. Compared to the other CO2 removal and sequestration technologies, the oxygen-fired PC integrated with OITM shows substantially less CO2 removal penalty. The CO2 removal penalty of the oxygen-fired PC integrated with CAR is between cryogenic air separation and OITM. The objective of the furnace and heat recovery area design and analysis task of the study is to optimize the location and design of the furnace, burners, over-fire gas ports, and internal radiant surfaces. The furnace and heat recovery area were designed and analyzed using the FW-FIRE, Siemens, and HEATEX computer programs. The furnace is designed with opposed wall-firing burners and over-fire air ports. Water is circulated in the furnace by forced circulation to the waterwalls at the periphery and divisional wall panels within the furnace. Compared to the air-fired furnace, the oxygen-fired furnace requires only 65% of the surface area and 45% of the volume. Two oxygen-fired designs were simulated: 1) with a cryogenic air separation unit (ASU) and 2) with an oxygen ion transport membrane (OITM). The maximum wall heat flux in the oxygen-fired furnace is more than double that of the air-fired furnace due to the higher flame temperature and higher H2O and CO2 concentrations. The coal burnout for the oxygen-fired case is 100% due to a 500°F higher furnace temperature and higher concentration of O2. Because of the higher furnace wall temperature of the oxygen-fired case compared to the airfired case, furnace water wall material was upgraded from T2 to T92. Compared to the air-fired heat recovery area (HRA), the oxygen-fired HRA total heat transfer surface is 35% less for the cryogenic design and 13% less for the 3 OITM design due to more heat being absorbed in the oxygen-fired furnace and the greater molecular weight of the oxygen-fired flue gas. The HRA tube materials and wall thicknesses are nearly the same for the air-fired and oxygenfired designs since the flue gas and water/steam temperature profiles encountered by the heat transfer banks are similar. The capital and operating costs of the pulverized coal-fired boilers required by the three different plants (air-fired, O2-fired with cryogenic ASU and O2-fired with OITM) were estimated by Foster Wheeler and the balance of plant costs were budget priced using published data together with vendor supplied quotations. The cost of electricity produced by each of the plants was determined and oxygen-based plant CO2 mitigation costs were calculated and compared to each other as well as to values published for some alternative CO2 capture technologies. Compared to other CO2 sequestration technologies, the O2-fired PC is substantially more cost effective than both natural gas combined cycles and post CO2 removal PCs and it is superior, especially when a supercritical steam cycle is applied, to integrated gasification combined cycles. 4 Table of Contents ABSTRACT....................................................................................................................... 3 1.0 INTRODUCTION................................................................................................. 9 2.0 EXECUTIVE SUMMARY ................................................................................ 11 3.0 EXPERIMENTAL.............................................................................................. 17 4.0 RESULTS AND DISCUSSION ......................................................................... 18 4.1 SYSTEM DESIGN AND ANALYSIS ........................................................................ 18 4.1.1 Reference Site and Conditions .................................................................. 18 4.1.2 Air-Fired Reference Case (case-1) ........................................................... 19 4.1.3 Oxygen-Based PC Plant – Base Case....................................................... 22 4.1.4 Parametric Cases...................................................................................... 28 4.1.5 Part Load .................................................................................................. 40 4.1.6 Comparison With Post Combustion CO2 Capture.................................... 42 4.1.7 Furnace Waterwall Temperature.............................................................. 42 4.2 ADVANCED O2 SEPARATION SYSTEM INTEGRATION .......................................... 43 4.2.1 O2-Fired PC Integrated with Cryogenic ASU (case-6)............................ 43 4.2.2 O2-Fired PC Integrated with OITM.......................................................... 45 4.2.3 O2-Fired PC Integrated with CAR............................................................ 61 4.2.4 Comparisons ............................................................................................. 67 4.3 FURNACE AND HEAT RECOVERY AREA DESIGN AND ANALYSIS ........................ 69 4.3.1 Furnace Design and Analysis ................................................................... 69 4.3.2 Boundary Conditions ................................................................................ 71 4.3.3 Furnace Waterwall and Division Wall Design....................................... 115 4.3.4 Furnace Waterwall Corrosion................................................................ 123 4.3.5 Heat Recovery Area Design and Analysis .............................................. 125 4.4 ECONOMIC ANALYSIS ...................................................................................... 131 4.4.1 Main Assumptions................................................................................... 131 4.4.2 Plant Cost Basis...................................................................................... 134 4.4.3 Total Plant Investment (TPI) .................................................................. 142 4.4.4 Total Capital Requirement (TCR)........................................................... 142 4.4.5 Operating Costs And Expenses............................................................... 143 4.4.6 Cost Of Electricity (COE)....................................................................... 144 4.4.7 Tube Weld Overlay ................................................................................. 145 4.4.8 Reduced Pipeline Pressure ..................................................................... 146 4.4.9 Comparison with Other Technologies .................................................... 155 5.0 CONCLUSION ................................................................................................. 157 6.0 REFERENCES.................................................................................................. 161 7.0 BIBLIOGRAPHY ............................................................................................. 163 8.0 LIST OF ACRONYMS AND ABBREVIATIONS ........................................ 164 5 List of Figures Figure 4.1.1 - Reference Case of Air-fired Supercritical PC................................21 Figure 4.1.2 – Oxygen purity effect on ASU specific power ................................23 Figure 4.1.3 - Carbon burnout vs. O2 concentration to boiler ..............................25 Figure 4.1.4 - Base case of O2-fired supercritical PC..........................................27 Figure 4.1.5 - O2-fired supercritical PC with liquid CO2 pump (Case-3) .............31 Figure 4.1.6 - Temperature-Quality diagram for wet-end heat exchangers.........32 Figure 4.1.7 – Equilibrium and adiabatic temperatures vs. O2 concentration......33 Figure 4.1.8 - Boiler design with HRA series pass ..............................................38 Figure 4.1.9 - Boiler design with HRA series pass (56% Flue Gas Recycle) ......39 Figure 4.1.10 - Flue gas recycle flow vs. part load operation..............................41 Figure 4.1.11 Efficiency at part load operation....................................................41 Figure 4.2.1 - Base case of O2-fired supercritical PC with Cryogenic ASU .........44 Figure 4.2.2 - A Typical Oxygen Ion Transport Membrane Schematic [4]...........47 Figure 4.2.3 – Integration of Oxygen Ion Transport Membrane into O2-PC........48 Figure 4.2.4 - O2-PC with OITM .........................................................................51 Figure 4.2.5 – Effect of OITM O2 Recovery Efficiency on Efficiency ...................54 Figure 4.2.6 – Effect of Sweep Gas Pressure on LMPD .....................................55 Figure 4.2.7 – Effect of OITM Pressure on System Efficiency and LMPD: Variable O2 Recovery................................................................................................57 Figure 4.2.8 – Effect of O2 Recovery on System Efficiency ................................57 Figure 4.2.9 – Effect of OITM Pressure on System Efficiency and LMPD: Constant and Variable O2 Recovery ...........................................................58 Figure 4.2.10 - O2-PC with OITM with 58% Recycle Flow..................................60 Figure 4.2.11 - CAR Process Schematic ............................................................61 Figure 4.2.12 – Integration of CAR Process into O2-PC....................................65 Figure 4.2.13 - O2-PC with CAR.........................................................................66 Figure 4.3.1 – Computational Model of Air-Fired Furnace (with right side wall removed) .....................................................................................................76 Figure 4.3.2 – Computational Model of Oxygen-Fired Furnace With OFA..........77 Figure 4.3.3 – Air-Fired Boundary Conditions .....................................................78 Figure 4.3.4 – Oxygen-Fired Boundary Conditions (Cryogenic ASU) .................79 Figure 4.3.5 – Oxygen-Fired Boundary Conditions (OITM).................................80 Figure 4.3.6 – Air-Fired Boiler Design.................................................................81 Figure 4.3.7 – Summary of FW-FIRE Furnace Modeling Results .......................82 Figure 4.3.8 – Gas Velocity for Air-Fired Case ...................................................83 Figure 4.3.9 – Gas Temperature for Air-Fired Case............................................84 Figure 4.3.10 – O2 Mole Fraction for Air-Fired Case...........................................85 Figure 4.3.11 – Wall Heat Flux for Air-Fired Case ..............................................86 Figure 4.3.12 – Wall Temperature for Air-Fired Case .........................................87 Figure 4.3.13 – Wall CO for Air-Fired Case ........................................................88 Figure 4.3.14 – Char Mass Fraction (72 microns) for Air-Fired Case..................89 Figure 4.3.15 – Char Mass Fraction (176 microns) for Air-Fired Case................90 Figure 4.3.16 – Air-Fired and Oxygen-Fired Boiler Outlines ...............................91 Figure 4.3.17 – Oxygen-Fired Boiler Design (Cryogenic ASU) ...........................92 Figure 4.3.18 – Oxygen-Fired Boiler Design (OITM)...........................................93 Figure 4.3.19 – Gas Velocity for O2-Fired Case..................................................94 6 Figure 4.3.20 – Gas Temperature for O2-Fired Case..........................................95 Figure 4.3.21 – O2 Mole Fraction for O2-Fired Case ...........................................96 Figure 4.3.22 – Wall Heat Flux for O2-Fired Case...............................................97 Figure 4.3.23 – Wall Temperature for O2-Fired Case .........................................98 Figure 4.3.24 – Wall CO for O2-Fired Case.........................................................99 Figure 4.3.25 – Char Mass Fraction (69 micron) for O2-Fired Case..................100 Figure 4.3.26 – Char Mass Fraction (169 micron) for O2-Fired Case................101 Figure 4.3.27 - Flue gas recycle flow vs. part load operation...........................102 Figure 4.3.28 – Summary of O2-Fired Part Load Results, Cryogenic ASU .......103 Figure 4.3.29 – Gas Temperature for O2-Fired Part Load, Cryogenic ASU ......104 Figure 4.3.30 – Wall Heat Flux for O2-Fired Part Load, Cryogenic ASU ...........105 Figure 4.3.31 – Average and Peak Heat Flux in Waterwalls.............................106 Figure 4.3.32 – Gas Velocity for O2-Fired with OITM........................................107 Figure 4.3.33 – Gas Temperature for O2-Fired Case With OITM......................108 Figure 4.3.34 – O2 Mole Fraction for O2-Fired Case With OITM .......................109 Figure 4.3.35 – Wall Heat Flux for O2-Fired Case With OITM...........................110 Figure 4.3.36 – Wall Temperature for O2-Fired Case With OITM .....................111 Figure 4.3.37 – Wall CO for O2-Fired Case With OITM ....................................112 Figure 4.3.38 – Char Mass Fraction (69 micron) for O2-Fired Case, OITM.......113 Figure 4.3.39 – Char Mass Fraction (169 micron) for O2-Fired Case, OITM.....114 Figure 4.3.40 – Advantage of Low Mass Flux Design.......................................117 Figure 4.3.41 – Tube Wall Temperature with Smooth, Standard Rifled, and Optimized Rifled Tubes .............................................................................118 Figure 4.3.42 – Rifled Tube Design ..................................................................119 Figure 4.3.43 – Outside Tube Wall Temperature with Peak Heat Flux .............120 Figure 4.3.44 – Tube Inlet Mass Flow With a 10% Heat Flux Step Increase (No Pressure Equalization Header) ..................................................................121 Figure 4.3.45 – Tube Inlet Mass Flow With a 10% Heat Flux Step Increase (With Pressure Equalization Header at 80’) ...............................................122 Figure 4.3.46 – Predicted Wall Corrosion (mil/yr) in Air-Fired and O2-Fired Furnaces....................................................................................................124 Figure 4.3.47 – HRA Tube Bank Design...........................................................128 Figure 4.3.48 – HRA Tube Bank Performance .................................................130 Figure 4.4.1 – Increase in COE of O2 Plant Above Air-Fired Reference Plant ..152 Figure 4.4.2 – COE Breakdown ........................................................................153 Figure 4.4.3 - Comparison of Levelized Cost of Electricity Among Alternative Technologies .............................................................................................156 Figure 4.4.4 - Comparison of Mitigation Costs Among Alternative Technologies ...................................................................................................................156 7 List of Tables Table 4.1.1 - Summary of Plant Performance and Economics ...........................15 Table 4.1.1 - Site Conditions...............................................................................18 Table 4.1.2 - Setup and Assumptions .................................................................19 Table 4.1.3 - Case Summary .............................................................................29 Table 4.1.4 - Flame adiabatic temperature effect on performance .....................34 Table 4.1.5 – Flame adiabatic temperature effect on boiler flue gas flow ...........34 Table 4.2.1 – Comparison of O2PC with Cryogenic and OITM ASU ..................50 Table 4.2.2 – Parametric Case Summary ...........................................................52 Table 4.2.3 - Effect of OITM O2 Recovery Efficiency on LMPD ..........................54 Table 4.2.4 – Effect of Flame Temperature on Performance ..............................59 Table 4.2.5 - Comparison for CAR with Cryogenic ASU .....................................62 Table 4.2.6 – Comparison for CAR Using Different Sweep Gases .....................63 Table 4.2.7 – O2 PC Efficiency with Different O2 Separation Techniques ...........64 Table 4.2.8 - Gains from OITM and CAR Compared to Cryogenic ASU.............67 Table 4.2.9 – Comparison of CO2 Removal Technologies .................................68 Table 4.4.1 - Coal Properties ............................................................................132 Table 4.4.2 - CO2 Effluent Purity Design Conditions.........................................132 Table 4.4.3 – Economic Study Assumptions.....................................................133 Table 4.4.4 - Cost of 430.2 MWe Air-Fired Supercritical PC Plant ($1000 Yr 2006) .........................................................................................................138 Table 4.4.5 - Cost of 347.0 MWe ASU Based Supercritical PC Plant ($1000 Yr 2006) .........................................................................................................139 Table 4.4.6 - Cost of 463.3 MWe OITM Based Supercritical PC Plant ($1000 Yr 2006) .........................................................................................................140 Table 4.4.7 - Comparison of Total Plant Costs ($1000 Yr 2006) ......................141 Table 4.4.8 - Air Fired PC Plant Capital Investment & Revenue Requirement .147 Table 4.4.9 - ASU Based PC Plant Capital Investment & Revenue Requirement ...................................................................................................................148 Table 4.4.10 - OITM Based PC Plant Capital Investment & Revenue Requirement ..............................................................................................149 Table 4.4.11 - Summary of Plant Economics and CO2 Mitigation Costs...........150 Table 4.4.12 - Plant Daily Consumable Requirements .....................................151 Table 4.4.13 – COE and CO2 MC with Weld Overlay and 2200 psi Pressure ..154 8 1.0 Introduction The objective of the Conceptual Design of Oxygen-Based supercritical PC Boiler study is to develop a conceptual pulverized coal (PC)-fired power plant, which facilitates the practical capture of carbon dioxide capture for subsequent sequestration. The system design and analysis task, which was performed using the Aspen Plus computer program, is aimed at optimizing the PC boiler plant operating parameters to minimize the overall power plant heat rate. The flow rates and other properties of individual streams of the power plant were calculated as the results of the Aspen Plus simulations. The required performance characteristics of such operating components as pulverized coalfired furnace, heat recovery area, flue gas recuperator, and economizer were determined. Two plant configurations were simulated: 1) a conventional air-fired PC power plant and 2) the proposed oxygen-based supercritical PC plant. In order to compare the performance of the oxygen-based plant with that of the conventional plant, the main steam generation rate in the both plants was kept constant. The objective of the advanced oxygen separation system integration task is to identify promising, low cost advanced options of oxygen separation, which can be integrated into the O2-fired PC power plant. Currently, a number of new oxygen separation technologies are in development. They are categorized as high temperature ion membranes, such as oxygen ion transport membrane (OITM), and high temperature sorption, such as ceramic auto-thermal recovery (CAR). The former relies on oxygen transport through a ceramic membrane, and the latter on oxygen storage in perovskite type materials. Integration of these advanced oxygen separations into the O2-fired PC has the potential to substantially reduce the cost of CO2 removal. This task deals with the systemlevel evaluation of the O2-fired PC integrated with these advanced oxygen separation methods. The advanced oxygen separation system integration task, which was performed using the Aspen Plus computer program, is aimed at a system level optimization to minimize the overall heat rate and maximize system performance. Two types of advanced oxygen separation systems and related configurations were simulated: 1) high temperature membrane technology (OITM) and 2) high temperature oxygen sorbent technology (CAR). Determined are the required performance characteristics of the operating components such as the boiler (with air heater for OITM), GT expander, wet-end economizer for low-grade heat recovery, and air separation equipment. The furnace and heat recovery area design and analysis task, which was performed using the FW-FIRE, Siemens and HEATEX computer programs, is aimed at optimizing the location and design of the furnace, burners, over-fire gas ports, and internal radiant surfaces. Three furnace and HRA designs were developed: 1) a conventional air-fired PC power plant and 2) an oxygen-based 9 PC plant with cryogenic ASU and 3) an oxygen-based PC plant with oxygen ion transport membrane. The objective of the economic analysis is to prepare a budgetary estimate of the capital and operating costs of the O2-fired PC power plants to permit comparison to an equivalent, conventional, air-fired power plant (e.g. the reference plant) as well as other CO2 capture technologies. 10 2.0 Executive Summary The objective of the Conceptual Design of Oxygen-Based supercritical PC Boiler study is to develop and design a conceptual pulverized coal-fired power plant, which facilitates the practical capture of carbon dioxide capture for subsequent sequestration. The reference plant employs a supercritical steam turbine with conditions, 4035psia/1076ºF/1112ºF/2.0”Hg, fires high-volatile bituminous Illinois 6 coal, and produces 460 MWe at the generator. A conventional air-fired case was simulated as the comparison basis. The air-fired plant has a boiler efficiency of 88.2% and a net plant efficiency of 39.5%. The system design and analysis task (Task 1), which was performed using the Aspen Plus computer program, is aimed at optimizing the PC boiler plant operating parameters to minimize the overall power plant heat rate. The oxygenbased plant model contains all the components in the conventional plant model (with the exception of the FGD and SCR) plus the addition of an air separation unit and a flue gas cooler. Flue gas is recycled to control the flame temperature inside the PC boiler to minimize NOx formation, to minimize ash slagging in the furnace combustion zone, and to avoid the application of exotic materials. Equipment to compress and liquefy the CO2 effluent to 3000 psia and to reduce the moisture to 50 ppm (to avoid transport pipe corrosion) was included in the O2PC system model. Compression to 3000 psia is conservative compared to the pressure of 2200 psia specified in Reference 14. The supercritical O2-PC power plant simulated with the same flame temperature as the air-fired PC, shows a plant net efficiency drop from 39.5 to 30.8%, and a power reduction from 430 to 332 MWe. The flue gas flowing through the boiler changes from 3555 to 3363 klb/hr (179 to 125 Mcf/hr, a 30% reduction in volumetric flow). As the result of the air separation unit (ASU) power and CO2 compressions, the specific power penalty for CO2 removal is 129 kWh/klbCO2. Parametric trade-off runs were made by varying the amount of recycled flue gas (which directly affects the flame temperature) while maintaining the same boiler outlet O2 concentration (3%, vol.) as the air-fired case, and by varying the temperature of the recycled flue gas. The results show that by reducing the recycled flue gas flow rate by 38% (by volume), and by raising the temperature of the recycled flue gas from 95ºF to 260ºF, the equilibrium temperature increases from 3480ºF to 4160ºF, the system efficiency increases from 30.8% to 32.9%, and the specific penalty for CO2 removal reduces from 129 to 99 kWh/klbCO2. The objective of Task 2 is to develop a system design of a conceptual pulverized coal-fired oxygen combustion power plant, integrated with advanced oxygen separation technology. The baseline oxygen-based PC boiler incorporates cryogenic O2 separation, which can produce oxygen with high purity; but it requires substantial capital and operating costs. Membrane separation of O2 has 11 been demonstrated at small scale employing very thin membrane fibers, which preferentially allow O2 to permeate, but not N2. Membrane separation has the potential to use less power at a lower capital cost. The advanced oxygen separation system integration task (Task 2), which was performed using the Aspen Plus computer program, is aimed at a system level optimization to minimize the overall heat rate and maximize system performance. Two types of advanced oxygen separation systems and related configurations were simulated: 1) high temperature membrane technology (OITM) and 2) high temperature oxygen sorbent technology (CAR). Oxygen separation by oxygen ion transport membrane is driven by the difference in oxygen partial pressure across a membrane. To produce this pressure difference, the air is pressurized by a compressor and heated to a high temperature. The hot pressurized air is fed to an oxygen ion transport membrane (OITM), where about 85% of its O2 is separated through membrane, and the remaining O2 is carried by hot vitiated air to a gas expander. Power generated from the expander is used to drive the air compressor. The OITM does not consume electrical power; instead, it absorbs heat, generates power, as it separates O2 from air. The O2-fired reference plant with cryogenic ASU has a net plant efficiency of 31.9%, a net power generation of 338 MWe, and a CO2 removal penalty of 114 kWh/klbCO2. The O2-fired reference plant with OITM has a net plant efficiency of 36.1%, a net power generation of 463 MWe, and a CO2 removal penalty of 42 kWh/klbCO2. Parametric trade-off runs were conducted by varying the O2 recovery efficiency, the pressure difference across the membrane, the OITM operating pressure, the compressor discharge temperature, and the furnace flame temperature. OITM faces significant challenges with respect to the manufacture and stability of membranes, and scale up and design of large plants. The ceramic auto-thermal recovery (CAR) process is based on sorption and storage of oxygen in a fixed bed containing ionic and electronic conductor materials. For the CAR process utilizing extracted steam as the sweep gas, net system efficiency is increased by only by 0.7% point compared to the cryogenic ASU process. But if the CAR process uses recycled flue gas as the sweep gas, system efficiency can be increased by 2.6% points, compared to the gain of 3.2% points of the OITM process. At the same equilibrium temperature (4160ºF), the efficiency reduction of the O2-PC compared to the air-fired PC is 6.5% points with cryogenic air separation, 3.3% points with OITM, and 4.3% points with CAR. The furnace and heat recovery area design and analysis task (Task 3), which was performed using the FW-FIRE, Siemens, and HEATEX computer programs, is aimed at optimizing the location and design of the furnace, burners, over-fire gas ports, and internal radiant surfaces. 12 A simulation was made for both the reference air-fired case and for the oxygenfired case. Two oxygen-fired models were constructed: one for the cryogenic ASU design (with radiant superheater partial division walls) and the second for the OITM design with a furnace wall radiant superheater and a high temperature air heater. Boundary conditions are based on ASPEN simulations of the power plant. The furnace is designed with opposed wall-firing burners and over-fire air ports located at one burner pitch above the top burner row. The O2-PC supercritical boiler incorporates the BENSON vertical technology, which uses low fluid mass flow rates in combination with optimized rifled tubing. Water is circulated in the furnace by forced circulation to the waterwalls at the periphery and divisional wall panels within the furnace. For the air-fired furnace simulation, the maximum flue gas temperature is approximately 3350oF. The maximum heat flux is approximately 70,000 Btu/hr-ft2 and is located on the side wall at the top of the burner zone. The total heat absorbed by the furnace walls before the furnace exit is 1770 MM Btu/hr. The maximum temperature of the waterwalls is approximately 870oF and of the division walls is approximately 1000oF. Total burnout of all particle sizes is 99.6%. Average NOx concentration at the furnace outlet is 276 ppmvw (0.38 lb/MMBtu). Compared to the air-fired furnace, the oxygen furnace requires only 65% of the surface area and 45% of the volume. Two oxygen-fired designs were simulated: 1) with cryogenic ASU and 2) with OITM. The mixed primary/secondary gas O2 content (before combustion) is approximately 40%. In the oxygen-fired furnace, the maximum flue gas temperature is approximately 3900oF for cryogenic ASU and 3850oF for OITM. The maximum heat flux is 171,000 Btu/hr-ft2 for cryogenic ASU and 180,000 Btu/hr-ft2 for OITM. The maximum wall heat flux in the oxygen-fired furnace is more than double that of the air-fired furnace due to the higher flame temperature and higher H2O and CO2 concentrations. The total heat absorbed by the furnace walls before the furnace exit is approximately 2287 (cryogenic) and 2029 (OITM) MM Btu/hr. The coal burnout for the oxygen-fired case is 100% due to the high furnace temperature and high concentration of O2. NOx is 261 ppmvw (0.18 lb/MMBtu). The maximum temperature of the oxygen-fired furnace is approximately 1060oF for the waterwalls, 1065oF for the division walls, and 1100oF for OITM radiant superheater walls. Because of the higher temperature of the oxygen-fired case compared to the air-fired case, furnace tube material was upgraded from T2 to T92. Since the boiler is a supercritical once-through sliding pressure unit, part load cases (72%, 50%, and 25%) were run and evaluated with thermal/hydraulic and structural criteria. A pressure equalization header is included at an elevation of 80’ to ensure stable operation at low loads. 13 To reduce the corrosion in the O2-PC, tube weld overlays with high Nickel and Chromium contents (e.g. alloy 622) are applied to the waterwalls. This reduces the predicted maximum corrosion from 45 mil/yr to 10 mil/yr. HEATEX was used to determine the heat recovery area (HRA) design of the convective tube banks between the furnace exit and the SCR/air heater. These tube banks include the finishing superheater, finishing reheater, primary superheater, primary reheater, upper economizer, and lower economizer. For the air-fired design, total surface area of all convective banks is 335,025 ft2. The total heat transferred to the water/steam is 1431 MM Btu/hr as 3.59 MM lb/hr of flue gas is cooled from 2185ºF to 720ºF. For the cryogenic ASU oxygen-fired design, convective bank total surface area is 218,693 ft2 and the total heat transferred to the water/steam is 1151 MM Btu/hr as 2.12 MM lb/hr of flue gas is cooled from 2450ºF to 695ºF. For the OITM oxygen-fired design, convective bank total surface area is 274,466 ft2 and the total heat transferred to the water/steam is 1185 MM Btu/hr and to the air is 990 MM Btu/hr as 2.68 MM lb/hr of flue gas is cooled from 2950ºF to 695ºF.The total heat transfer surface required in the oxygen-fired HRA is less than the air-fired HRA due to more heat being absorbed in the oxygen-fired furnace and the greater molecular weight of the oxygen-fired flue gas. The HRA tube materials and wall thicknesses are nearly the same for the airfired and oxygen-fired designs since the flue gas and water/steam temperature profiles encountered by the heat transfer banks are similar. A tubular convective air heater is included in the OITM O2-PC to provide the necessary air heating for the membrane separation process. The furnace air heater is an Incoloy MA956 three-pass tubular design situated above the furnace nose. The objective of the economic analysis task (Task 4) is to prepare a budgetary estimate of the capital and operating costs of the O2-fired PC power plants to permit comparison to an equivalent, conventional, air-fired power plant (e.g. the reference plant) as well as other CO2 capture technologies. The economic analyses of the plants were carried out based on the EPRI Technical Assessment Guide (TAG) methodology. Plant capital costs were compiled under the Code of Accounts developed by EPRI. The estimate basis is year 2006 dollars, a 20-year life, and an 85 per cent capacity factor. Table 4.1.1 summarizes the performance and economics of the plants. 14 Table 4.1.1 - Summary of Plant Performance and Economics Reference Air-Fired Plant ASU Based Plant OITM Based Plant Net Power Output, MWe 430.2 347.0 463.3 Efficiency, % (HHV) 39.5 33.0 36.1 Coal Flow, Klb/hr 319.0 308.0 375.4 633.0 1,471 723.3 2,084 953.0 2,057 50.41 66.17 63.48 20.23 16.77 Total Plant Cost Millions of Dollars $/kW Levelized COE, $/MWhr CO2 Mitigation Cost, $/tonne Total plant costs are $633 million (1471 $/kW) for the air-fired reference plant, $723 (2084 $/kW) million for the cryogenic ASU O2-PC, and $953 (2057 $/kW) million for the OITM O2-PC. Even though the OITM O2-PC has a total plant cost that was 32 per cent higher than the ASU O2-PC, its higher power output results in a slightly lower $/kW cost of $2,057/kW versus $2,084/kW. The levelized cost of electricity (COE) was calculated for each of the plants assuming an 85 per cent capacity factor. The COE value is made up of contributions from capital cost, operating and maintenance costs, consumables, and fuel costs. The levelized COE was calculated to be $50.41/MWhr for the reference plant, $66.17/MWhr for the cryogenic ASU O2-PC, and $63.48/MWhr for the OITM O2-PC. Again, because of its higher output, the OITM O2-PC has a lower levelized cost of electricity ($63.48/MWhr versus $66.17/MWhr) and a lower CO2 mitigation cost (MC) ($16.77/tonne versus $20.23/tonne) than the ASU O2-PC. The addition of weld overlay increases the COE approximately 0.75%, but reducing the pipeline pressure from 3000 psia to 2200 psia (specified in Ref. 14) reduces the COE by 0.3%. Thus, the combined effect of these two adjustments on the COE is relatively small (+0.4% for cryogenic O2-PC and +0.1% for the OITM O2-PC). Compared to the COE of the supercritical cryogenic O2 PC, the COE for the other technologies is 52% higher for Air PC, 35% higher for NGCC, 15% higher for IGCC, and 5% higher for the subcritical O2PC, and 4% lower for the supercritical O2PC with OITM. Compared to the MC of the supercritical cryogenic O2 PC, the 15 MC for the other technologies is 238% higher for NGCC, 192% higher for Air PC, 25% higher for IGCC, 5% higher for the subcritical O2PC, and 17% lower for the supercritical O2PC with OITM. 16 3.0 Experimental This work performed for this report was performed utilizing computer program simulations. No experimental equipment was used. 17 4.0 Results and Discussion 4.1 System Design and Analysis 4.1.1 Reference Site and Conditions In December 2000, Parsons published a study of the cost of electricity of several case studies of CO2 sequestration from a PC boiler by post-combustion capture (Ref. 1). In September 2005, Foster Wheeler released a report of conceptual design of O2-fired PC boiler (Ref. 3). To provide a consistent comparison with the cases analyzed in the previous reports, the same site conditions (59ºF, 14.7 psia, 60% RH) and the same fuel (Illinois #6) were used. Site Conditions and fuel properties are presented in Table 4.1.1. Fuel HHV and LHV were estimated by a DuLong’s method and the stoichiometric air ratio of 867 lbair/lbcoal was calculated based on the fuel ultimate analysis. Table 4.1.1 - Site Conditions Standard site: elevation, ft amb p, psia amb T, F amb T, wet, F RH, % P-H2O, psia Y-H2O, %v condenser P, "Hg 0 14.70 59 51.5 60 0.247 1.010 2.00 air, %v N2 O2 Ar CO2 H2O sum dry 78.085 20.947 0.935 0.033 0.000 100.000 wet 77.297 20.735 0.926 0.033 1.010 100.000 coal, Ill#6 C H O N S A M V F sum fuel HHV given aspen %w 63.75 4.5 6.88 1.25 2.51 9.99 11.12 34.99 44.19 100.0 sorb CaCO3 %w 100 btu/lb 11666 11631 The CO2 fluid produced from the oxygen-based PC power plant is not chemically pure, but can be readily sequestered in geologic formations (depleted oil and gas reservoirs, unmineable coal seams, saline formations, and shale formations) or in oceans. The liquid CO2 exits the plant at over 2000 psia. The CO2 fluid inside pipeline under this pressure is in a liquid or a supercritical state. The other gases in the delivered CO2 are limited to H2O < 50 ppm (to avoid acid corrosion), and Ar+N2 < 3% (to avoid phase separation). The excess gases in CO2 stream either have to be purged or recycled. However, since SO2, as an acid gas, similar to CO2, it can be sent to pipeline directly under moisture free condition, and as mentioned in literature, it does not need to be separated out from CO2 product. Furthermore it is also not necessary to remove the small concentration of NOx in the CO2 effluent since it can be sequestered along with the CO2. 18 4.1.2 Air-Fired Reference Case (case-1) To study the effects of CO2 removal on the performance of the power plant, an air-fired supercritical PC boiler was been simulated in detail as a reference case. This model was used as the base, which was then extended to include the air separation unit (ASU) and CO2 compression unit for O2-fired PC cases. The reference plant employs a supercritical steam turbine with conditions, 4035psia/1076ºF/1112ºF/2.0”Hg, fires high-volatile bituminous coal, and produces 460 MWe at the generator. It employs eight feed water heaters to raise the final feed water temperature to 569ºF. It uses an auxiliary steam turbine to directly drive the high-pressure feed water pump. Case 1 is the reference air-fired supercritical PC boiler case, and the model and results shown in Figure 4.1.1 and Table 4.1.2. Table 4.1.2 - Setup and Assumptions Setup and Result ST Result main P, psia main T, F RH P, psia RH T, F FWHs end wet, % end P, "Hg 4035 1076 823 1112 8 9.5 2.0 F 5 10 569 FWH TD DC FW T DeSuperheat SH, % water T, F 5 569 Boiler PA, % UBC, % radiation/margin, % EXA, % flame T, F stack T, F blowdown, % miller exit T, F 20 1.0 0.59 17.9 3685 289 0 219 net power, MWe net eff, % gross @ST, MW aux power, MW as % HHV in, mmbtu Q to st, mmbtu Q, cond, mmbtu boiler eff, % ST cycle eff, % Generator eff, % Flow air, klb coal, klb sorb, klb flue gas, klb O2, % H2O, % CO, ppmv NOx, ppmv SOx, ppmv after FGD Ash, klb C, % main st, klb RH st, klb end st, klb Aux power 430 39.5 477 46.0 9.7 3721 3281 1696 88.2 47.7 98.3 condensed water pump HP feed water pump FGD pump CT pump PA Fan SA Fan ID Fan FGD Fan cooling tower Fan coal handling sorb handling ash handling + ESP others (=1%) 3270 319 26 3556 3.0 8.6 14 22 1979 37 33 6.0 2950 2406 1573 total MWe 0.6 17.5 0.8 3.4 1.1 2.0 5.4 4.1 1.9 2.0 0.8 1.8 4.6 46.0 FGD & SCR L/G Ca/S Excess air, % NH3/NOx DeSOx, % DeNOx, % 10 1.05 85 1.0 98 90 sum "H2O 4.0 6.0 10.0 20.0 FSH FRH RH PSH UECO ECO AAHX Damper BHG FGD sum "H2O 0.5 0.5 1.0 0.7 0.3 2.0 1.6 4.3 5.5 12.0 28.4 dP-air AAHX duct nozzle dp-gas dP-Fan PAFan IDFan SAFan eff FDFan IDFan CWPump BFPump Motor/mech The Aspen Plus model includes coal mills, flue gas heater, pulverized coal-fired furnace, steam generator, superheater, reheater, economizer, ash-removal unit, nitrogen oxides (NOx) selective catalytic reactor (SCR), flue gas de-sulfurization reactor (FGD), air blower, induced draft (ID) fan, feed water pump, cooling water 19 "H2O 60 28 20 % 75 70 80 80 95 pump, feed water heaters, and a single reheat steam turbine. A coal drying function has been modeled and added into mill module to produce the correct mill exit gas temperature. The furnace was simulated by a zero dimensional model for heat and mass balances. However, all key tube banks of the heat recovery area (HRA) were individually modeled. The furnace roof heat absorption was also simulated. The high-pressure steam temperature is controlled by water spray for de-superheat. The simulation also included heat losses from the boiler and HRA enclosure, as well as from the steam pipes. Some user-defined models were included to perform emission calculations. User built-in calculations have been added to determine boiler efficiency, system net efficiency, and net power. The heat carried by exhaust streams was automatically calculated by the program. For a given steam turbine output and a fuel, Aspen Plus iterates to determine the feed rates of air, coal, etc., based on specified temperature approaches and excess air requirement. The system configuration, detailed setup parameters and summary of results for the case 1 reference case are shown in Figure 4.1.1 and Table 4.1.2. The system has a steam turbine cycle efficiency (generator power divided by heat transferred to the steam cycle) of 47.6%, a boiler efficiency (heat to steam cycle divided by heat input from fuel to boiler) of 88.2%, an unburned carbon loss (UBC) of 1.0%, and a net plant efficiency of 39.46% (net plant heat rate of 8647 Btu/kWh). It has a gross power of 460 MWe at the generator, 18 MWe from auxiliary steam expander, an auxiliary power of 46 MWe, and a net power of 430 MWe. Total heat input from the fuel is 3720 MM Btu/hr. The temperature of the flue gas exhausted to the stack is 289ºF. The flue gas exiting the boiler contains 3.0%, vol., wet O2 (18% excess air) and contains 739 klb/hr (1.72 lb/kWh) of CO2. This 3.0% O2 level is kept constant for all of the O2fired cases. A SCR is applied to control NOx with NH3/NOx=1.0, and an FGD is used to control SOx by lime solution with Ca/S=1.05, L/G=10, and 85% excess air for aeration. The breakdown of auxiliary power for case 1 is listed in Table 4.1.2. Most of these power consumptions were simulated directly by the Aspen module. Some required user Fortran for those processes lacking Aspen modules, such as solids handling. The power consumption was based on stream flows and design data. Fan power consumption was simulated based on the pressure drops from both air side and gas side. The total auxiliary power consumption, including FGD, for case 1 is approximately 9.7% of the gross power, while it was about 9.2% for a subcritical case. Because of high temperature and high CO2 concentration, the CO concentration is high, producing a flame temperature, which is lower than the adiabatic combustion temperature. To represent this effect on boiler design, an estimation of the equilibrium flame temperature was modeled. 20 Figure 4.1.1 - Reference Case of Air-fired Supercritical PC Case: O2-PC-SC-01, 06/03/2005 1083 1076 4269.0 4035.0 2950 48 PC Boiler 1113 1112 1112 849.0 823.2 823.0 2406 2406 2406 2950 LS1 1076 823.0 4035.0 2389 67 43 835 PRPB Q=36 Q=137 2950 1585 1567 14.7 14.7 3588 3588 3588 G5 G6 1869 FRH 14.7 44 4595.0 890.0 2803 2406 72 1904 653 871 1305.3 890.0 353.2 3 2878 5 2679 SL6 G8 SL2 21 45 1076 2803 V7 11 890.0 435 323 863.3 6 522 89 80 V6 713 88 194.8 56 114 63 199 569 Q=335 60 V5 522 65 4929.0 2950 FWH8 148 382 218 38.9 36.9 127 127 99 226 92 25 10.0 3.9 5 79 SSR 9 FSPLIT 10.0 15.2 15.8 59 644 155 234 20 348 122 1 V4 VD 425 522 4954.0 15 610 114 4979.0 2950 FWH7 Q=0 181.2 386 66 V3 94 191.6 2950 FWH6 317 2226 429 V1 V2 712 430 342.6 863.3 3.7 77 78 262 545 36.9 93.8 257 127 191.6 FWH4 69 2226 214 208 226 15.2 206.6 70 2226 FWH3 145 71 150 COND 3.7 14 429 221.6 348 Q=-1696 2226 FWH2 FWH1 87 3588 G11 838 868 1651 81 G13 85 74 Q=311 396 1758 851 33 LECO 100 109 STK1 569 34 60 14.7 N2 46 60 15.0 14.7 SORB AIR 0 60 20.0 14.7 G15 3588 2803 99 Duty (MMBtu/hr) 109 L2 90 67.0 FGD PREC 3555 Mass Flow Rate (Mlb/hr) 0 W=0 POND 15.1 0 Temperature (F) Pressure (psi) 67.0 60 DIST Power(MW) 0 AC 14.7 DENOX LIQ NH3 EQ 35383 G20 99 L1 308 289 724 G16 3556 14.1 3589 3589 ESP AAHX 0 G18 15.1 G21 3588 W=5 580 0 GBY 80 14.9 14.8 58.4 231.6 0 0 0 0 49 AV 15.3 Q=-407 2720 NOZ 60 14.7 A4 A2 550 89 289 16.9 14.1 ASH 550 C3 308 C1 33 COL1 60 14.7 16.6 60 A5 16.7 869 MILL 319 580 A3 Q=0 14.7 3270 2720 W=1 0 A1 AIRB 70 308 15.4 15.1 BYP 2720 380 SEP1 C5 915.2 COMP3 367 W=0 0 C2 0 1200.0 PIPE 926.2 C10 0 0 CCT 14.8 0 0 Q=-0 14.9 D1 0 46 15.0 0 GRH RY1 O2 21 COL3 COL2 Q=-0 90 D2 80 58.4 231.6 D3 0 231.6 D4 50 925.2 80 80 0 0 368 W=0 233.6 C7 COL-4 14.8 RY2 50 DEM Q=-0 Q=0 W=2 59.4 W=0 0 90 257 SA COMP2 COMP1 90 Q=-0 SAFAN SPA 16.7 550 COAL 60 80 231.6 0 14.9 PA CO2 W=-0 C6 C4 15.1 VANT PAFAN A6 Q=0 0 EXPD RECY 3589 Power(MW) 67.0 80 90 W -146 308 90 Duty (MMBtu/hr) -183 IDFAN G17 14.7 ASU Q=-0 W=1 SPF 3556 G19 3685 Q Q=-0 35578 15.1 289 14.3 14.3 E1 A0 14.7 SLV RGIBBS SP1 53 W=1 401 COMP SLV 35578 308 0 219 CP 0 26 29.7 720 14.4 50 14.7 35552 3750 Q=128 41 G2 2226 64 BYFW FGD 14.7 478 WETECO 68 4822.0 2803 1.0 0 0 2950 W=18 2226 102 236.6 206.6 181.2 7 Q=95 102 Q=0 2950 SPQ 35 4770.0 14.7 Q=141 4839.0 606 4787.0 638 Q=-0 86 2803 Q=-1751 BFP1 52 569 14.5 374 610 FWV 3588 16 Q=110 269 DEA 342.6 179 G14 61 Q=135 Q=118 2950 DAMP HEATER 73 102 236.6 Q=162 32 22 BOILER 93 4904.0 14.6 14.7 QB 83 569 864 14.6 RSTOIC 267 93.8 152 57 Q=117 Q FLAME 545 93.8 95 527 1266.2 14.7 G1 AUX 76 353.2 18 746 SPRAY 4822.0 E2 644 93.8 871 199 1758 UECO 24 3552 40 17 654 112 RHB 2185 EL4 14.6 G12 2406 2803 532 1266.2 1.0 1573 219 EL3 EL2 SL3 658 199 4510.0 1651 857.0 46 750 1305.3 PW Q=315 2406 102 1652 108 W=-18 879 Q=-36 883 30 1775 EI3 657 1567 4665.0 G3 219 877.0 Q=210 3.9 1.2 96 G9 854 2950 29 152 1874 LS4 23 14.7 810 EI2 EI1 28 234 15.8 93.8 EH2 PSH 4500.0 545 2187 DPCRH G4 Q=389 8 1758 SPG Q=-39 Q=310 38.9 93.8 2301 SC1 3588 DIVW 6 2389 LP4 LP3 382 540 194.8 22 14.7 G10 LP2 LP1 IP3 713 750 1487 Q=-42 G7 Q=-19 14.7 IP2 IP1 HP2 658 EH1 SC23 FSH Q=1304 WEG MULT 88 SC4 47 EVAP W WE 84 HP1 42 17 2803 ROOF 964 4445.0 459 823.0 SL5 2878 27 19 26 1112 1112 MAIN DPHRH 830 4630.0 ST=4035/1076/1112/2.0"Hg=460 MW 0 915.2 Q=0 0 Q=-0 0 C11 D5 PCO2 0 4.1.3 Oxygen-Based PC Plant – Base Case 4.1.3.1 Boiler Plant Modifications The oxygen-based (or oxygen-fired) plant model contains essentially all the components in the conventional plant model. In addition, it also includes an air separation unit (ASU) and a flue gas cooler. In the O2-fired plant, the FGD is not needed because the SO2 is acid gas similar to CO2 and can thus be sent to pipeline together with the CO2. A substantial portion of the SOx will be removed as the flue gas is cooled down in the CO2 cooling and compression equipment. The steam side components remain very similar to the air-fired case with only some changes in heat bundle duties in the heat recover area (HRA). In O2-fired cases, flue gas is recycled to control the flame temperature inside the PC-fired boiler to minimize NOx formation, minimize ash slagging in the furnace combustion zone, and avoid the application of exotic materials. Before the flue gas is separated into a recycled and effluent stream (to the pipeline), it is cooled to 90ºF. Since this is below the acid/moisture dew point, a heat exchanger containing acid-resistant materials must be used. The recycled gas is then reheated, before the forced draft (FD) fan, by mixing it with a bypassed hot gas to avoid reaching the dew point. After the O2 from ASU plant is mixed with recycled flue gas, it is heated by the flue gas exiting the boiler in a gas-gas heat exchanger, which acts as a recuperator to improve cycle efficiency and reduce fan power requirements. It is assumed in this study that there is no tramp air ingress through the sealed boiler. 4.1.3.2 Air Separation Unit For an O2-fired PC, O2 purity is a key parameter for system performance and economics. A high purity O2 will produce a high purity of product CO2 gas, which will reduce CO2 purification and compression power. However, producing high purity O2 requires high ASU plant operational and equipment costs. Furthermore, too high O2 purity is not necessary because the fuel combustion itself will generate some gases, such as N2 and some excess O2 is required for complete combustion, in additional to CO2 as flue gas. Therefore there is a balance point to give an optimum. The method of air separation chosen for this study is the commercially available large-scale cryogenic air separation technique. A traditional cryogenic ASU plant was simplified in the simulation to include the power consumption, but without details of distillation columns and cold heat exchangers. The Aspen model does not include the air purifier, which removes moisture, hydrocarbons, CO2, and NOx in an adsorber and is located between the cold box and air compressor. 22 Although the separated N2/Ar gases could potentially be sold as byproducts, no economic credit for this is taken in this study. No heat recovery from the ASU air compressor inter-stage coolers is included, because recovery of this low grade heat is inefficient. Power consumption for different O2 purity is plotted in Figure 4.1.2. For the O2 purity of 99.5% used in this study, a power consumption of 24.5 kWh/klbair is applied. For a 460 MWe steam turbine generation, the ASU plant consumes about 70 MWe, or 15% of generated power, which is a large penalty for CO2 removal. Figure 4.1.2 – Oxygen purity effect on ASU specific power Power Demand vs Oxygen Purity 0.30 0.29 0.28 0.27 Pow e r, kWh/k gO2 0.26 0.25 0.24 0.23 0.22 0.21 0.20 0.19 0.18 0.17 0.16 0.15 70 75 80 85 90 95 100 Oxyge n Purit y, %v Advanced air separation methods such as high temperature membrane method will be incorporated into the cycle in task 2 (Section 4.2) to reduce both operation and capital costs. 23 4.1.3.3 CO2 Compression Unit The flue gas effluent stream (mainly CO2) has to be compressed to the high pipeline pressure of 1200 to 3000 psia depending upon end user specification. The CO2 sequestration equipment is added to the system and the effluent is conservatively compressed to 3000 psia. The dominant moisture in flue gas is condensed out first during flue gas cooling before the first stage compression. The condensed water contains acid gases and has to be treated before recycle or discharge. The flue gas composition after cooling but before the first stage CO2 compressor from this base case (case-2) is: CO2 90.4 O2 3.3 N2+Ar SOx 1.3 1.1 H2O 3.6 In literature, residual O2 as low as 1.3% was used. Reducing O2 content, such as from 3.0% to 2.0% by reducing excess air, is helpful in reducing CO2 compression power, but it is judged that and oxygen content of approximately 3.0% is required for good combustion efficiency. Both CO2 and SOX are acid gases. They combine with moisture to form acid, which causes a corrosion problem along CO2 pipeline. Therefore, after the 2nd stage, a chemical method of active dehydration with TEG (Triethyleneglycol) is applied to remove the rest of moisture to a very low level of less than 50 ppm, where the TEG can be regenerated by heating. In the model, the TEG dehydration was simulated, but the TEG itself was not simulated. A four-stage compression with inter-stage cooling was applied. To reduce power, an equal compression pressure ratio of approximately 4.0 was applied. 4.1.3.4 O2-fired PC: Base Case (case-2) Figure 4.1.4 presents the base case system model. The key parameter for the base case is that the adiabatic temperature in the boiler was kept the same as the reference air case (at about 3690ºF) by adjusting the recycle gas flow. Both fuel and air feed rates were iterated to match the heat duty and 3.0%v exit O2 level. Compared to reference air-fired case, the case 2 air flow rate is reduced by 13.4% (from 3270 klb/hr to 2832 klb/hr), O2 concentration to the boiler is 28.3% (compared to 20.7% for the air-fired case) yielding an increased combustion efficiency and a lower UBC (unburned carbon). The relation of UBC and O2% has been included in modeling as shown by Figure 4.1.3 (based on FW-FIRE modeling results). 24 Figure 4.1.3 - Carbon burnout vs. O2 concentration to boiler Carbon Burnout Function 100.0 99.8 Carbon burnout, % 99.6 99.4 99.2 99.0 98.8 0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 O 2 fraction The oxidant from the ASU was 99.5% O2 purity. ASU and CO2 plant power consumptions were 68.7 and 38.4 MWe respectively. This resulted in a total auxiliary power of 144.5 MWe, or about 30.4% of gross power. All CO2 generated from fuel combustion was 100% removed with a final CO2 purity of 93.8%v. The efficiency penalty for CO2 removal was 8.7% in points with efficiency drop from 39.46 to 30.81%, and the related electric power penalty was 129 kWh/klbCO2. The extra cooling duties for the CO2 stream were added into cooling tower calculation for auxiliary power. The volumetric flow in the O2-fired PC case was reduced from 179 to 125 MMft3/hr, or to 70%, due to a high gas molecular weight of CO2 instead of N2. The gas mass flow was reduced from 3555 to 3363 klb/hr, or 95% in comparison to the air-fired case. The recycled gas flow was 2425 klb/hr, at a temperature of 95ºF, which has been heated 5ºF by a bypass flue gas stream as shown in Figure 4.1.4. It is noted that compared to the air-fired case, the coal feed rate was reduced from 319 to 315 klb/hr as the result of low UBC, and low excess air. 25 Because of high CO2 content in flue gas at high flame temperature, part of CO2 dissociated and more CO slipped, the equilibrium flame temperature differed from adiabatic temperature. 26 Figure 4.1.4 - Base case of O2-fired supercritical PC ST=4035/1076/1112/2.0"Hg=460 MW Case: O2-PC-SC-02, 06/03/2005 Temperature (F) Pressure (psi) Mass Flow Rate (Mlb/hr) 1083 1076 4269.0 4035.0 2950 2950 48 PC Boiler 1113 1112 1112 849.0 823.2 823.0 2406 2406 2406 Duty (MMBtu/hr) 1112 MAIN LS1 DPHRH 830 1076 823.0 4035.0 2389 67 43 PRPB Q=36 Q=137 1867 FRH 14.7 47 1580 1562 14.7 14.7 3394 3394 G5 G6 750 4595.0 890.0 1305.3 2803 2406 3394 3 2878 5 2679 2389 382 93.8 38.9 8 545 2187 EI1 G8 219 Q=315 2803 6 890.0 435 323 863.3 522 89 80 152 10.0 3.9 5 57 79 SSR 76 9 FSPLIT 353.2 713 88 194.8 18 56 114 92 545 267 382 93.8 93.8 38.9 36.9 127 127 99 226 25 218 V5 746 199 522 234 15.8 59 155 644 15.2 10.0 20 348 122 1 569 4822.0 Q=333 60 65 4929.0 2950 FWH8 148 425 522 4954.0 66 386 610 15 114 4979.0 2950 FWH7 V3 712 Q=0 181.2 342.6 863.3 191.6 2950 FWH6 2226 150 36.9 93.8 257 127 191.6 94 429 V1 V2 262 545 317 3.7 77 78 V4 VD 430 527 1266.2 63 14.7 95 V6 V7 SPRAY 24 69 226 2226 FWH4 214 208 15.2 206.6 70 2226 FWH3 3.7 145 71 COND 14 429 221.6 348 FWH2 Q=-1696 2226 FWH1 87 Q=109 3394 83 848 849 1561 QB 85 32 2950 1663 Q=135 Q=118 396 610 14.5 G14 33 LECO 2803 60 SORB G15 700 60 14.4 20.0 3394 0 60 14.7 AIR 2177 400 67.0 COMP 2832 W=69 0 317 60 120 L2 90 67.0 POND FGD PREC 0 LIQ NH3 2832 DIST AC 14.3 14.3 E1 G16 3394 3394 302 14.1 3363 3363 ESP AAHX 15.1 IDFAN G19 3690 G18 15.1 G21 580 3363 2530 Q=-348 NOZ 95 14.7 A4 A2 550 119 302 16.9 14.1 ASH 550 90 90 90 14.9 14.8 58.4 788 779 RECY A5 60 95 32 16.6 14.7 14.7 865 16.7 580 0 COL1 SEP1 550 SPA AIRB A1 317 15.1 C5 BYP 2530 SA C2 95 90 14.8 2375 D1 150 46 15.0 Q=0 RY2 RY1 O2 27 D2 323 3000.0 W=7 926.2 C10 90 90 90 58.4 231.6 9 D3 776 776 PIPE Q=-43 Q=-49 90 14.9 GRH W=1 W=10 779 COL3 COL2 Q=0 655 A3 C7 Q=-1 50 COMP4 281 233.6 W=11 788 Q=-341 14.8 2425 COAL COMP3 313 59.4 W=11 3312 90 CO2 DEM 777 310 90 1875 SAFAN 16.7 MILL 315 W=1 12 COMP2 COMP1 15.4 776 90 231.6 3312 14.9 60 916.2 C6 C4 C3 317 PA 217 90 0 ASU 15.1 C1 RSTOIC Q=0 -183 AV 90 231.6 776 GBY PAFAN A6 Q=-250 Q=-3 3163 15.3 473 14.7 3395 W=4 A0 0 317 G17 14.7 L1 W=0 SPF 3394 98 14.7 SLV 317 302 700 0 G20 EQ RGIBBS SP1 53 2832 14.7 DENOX CP W=1 29.7 15.1 0 N2 46 15.0 0 SLV 97 FGD Q=135 41 G2 14.7 50 14.7 0 0 4822.0 34 2226 64 Q=0 14.7 14.7 STK1 569 35 2803 0 1.0 WETECO 68 100 2 COL4 231.6 D4 2226 236.6 102 BYFW SPQ 637 0 2950 W=18 120 4770.0 Q=95 102 206.6 181.2 Q=-0 2950 2803 Q=-1755 Q=141 4839.0 4787.0 3394 374 86 52 569 608 BFP1 Q=110 269 DEA 342.6 843 HEATER 102 16 236.6 Q=311 FWV DAMP 61 7 Q=162 170 23 BOILER 73 93 4904.0 14.6 G13 14.7 81 74 569 838 14.6 G11 Q FLAME AUX 112 UECO 2185 93.8 871 199 1663 RHB 2803 11 1266.2 40 644 14.6 G12 2406 46 532 199 4510.0 45 1065 Q=-36 857.0 4665.0 EL4 17 654 SL3 658 1305.3 21 1.0 1573 219 EL3 EL2 2406 879 Q=210 102 1652 W=-18 750 PW 30 108 1.2 LS4 SL2 657 1561 882 1775 1874 96 1562 854 29 3.9 877.0 23 2950 28 152 EI3 EH2 PSH 4500.0 G1 W EG MULT LP4 LP3 234 15.8 93.8 DPCRH 1663 SPG 14.7 E2 W LP2 LP1 540 2301 14.7 G10 Q=311 3481 6 194.8 EI2 22 1482 Q=-42 G7 G9 810 353.2 890.0 SL6 Q=-39 Q=1306 Power(MW) 713 871 EH1 G4 Q=389 72 IP3 IP2 IP1 653 SC1 3394 DIVW 658 SC4 Q=-19 14.7 G3 Duty (MMBtu/hr) WE HP2 835 44 SC23 1902 FSH EVAP 459 Q W 88 84 HP1 42 17 2803 ROOF 964 4445.0 2950 Power(MW) 823.0 SL5 2878 27 19 26 4630.0 1112 1 Q=-55 D5 916.2 0 4.1.4 Parametric Cases Various cases were simulated to evaluate the effects on O2-PC performance of different designs and operating conditions, as shown by Table 4.1.3, in which the red highlight shows the key parameter changed in comparing with previous cases. All these cases, including part load cases (100% to 25%), will be explained and discussed in details in the following sections. In Table 4.1.3, the efficiency drop was directly calculated from the difference between cases with and without CO2 removal. But in general, the specific power penalty for the CO2 removal cannot be calculated by difference directly, because extra power may be produced by firing more when integrated with different O2 separation techniques. In some cases, the extra power by added firing may be greater than the power required for CO2 removal. Therefore a new definition, here, is introduced as kWh/lbCO2 = (eff drop)*(power/efficiency)air /lbCO2 (1) Equation (1) is the way to compare penalty for CO2 removal for different systems without cost estimation, especially for a complex system such as O2-PC integrated with a high temperature oxygen separation membrane method, where even more net power is produced from with CO2 removal than without. 28 Table 4.1.3 - Case Summary case Waste heat economizer HRA Arrangement CO2 Condensation Vent Gas Recycle Coal flow Oxidant flow Air flow O2 purity 01 no parallel klb/hr 319.0 klb/hr 3270 klb/hr 3270 % klb/hr 0 Recycle gas flow % 0.0 Recycle gas temperature F Boiler Inlet O2 %, v 20.7 Boiler Outlet O2 %, v 3.0 MM cf/hr 179 Boiler outlet flue gas flow klb/hr 3555 Adiabatic Temperature F 3685 Equilibrium Temperature F 3552 Gas Temp. to FSH F 2185 Water temp. to evap. F 638 UBC % 1.00 Boiler Efficiency % 88.16 Pipeline pressure psia 0 Generated CO2 flow klb/hr 739 CO2 purity %,v wet 14.0 Removed CO2 flow klb/hr 0 CO2 removal efficiency % 0 CO2 purity % Gross Power MW 476.2 Auxiliary Power MW 46.0 ASU power MW 0.0 CO2 compression power MW 0.0 Net Power MW 430.2 Net Efficiency % 39.46 Efficiency Drop % pts. CO2 removal energy kWh/klbCO2 - 02 no parallel no 315.0 655 2832 99.5 2425 72.1 95 28.3 3.0 125 3363 3690 3481 2185 638 0.49 89.28 3000 732 81.3 732 100 93.8 476.2 37.4 68.7 38.4 331.7 30.81 8.7 129 03 no parallel yes 315.0 655 2832 99.5 2425 72.1 95 28.3 3.0 125 3363 3690 3481 2185 638 0.49 89.28 3000 732 81.3 732 100 93.8 476.2 37.6 68.7 34.7 335.2 31.14 8.3 124 04 no parallel yes no 312.0 649 2806 99.5 2429 72.4 138 27.8 3.0 126 3357 3678 3474 2185 638 0.51 90.14 3000 725 80.0 725 100 93.8 476.2 37.6 68.1 34.4 336.1 31.53 7.9 119 05 no parallel yes no 310.7 647 2798 99.5 2046 68.8 142 30.8 3.0 109 2972 4010 3669 2185 615 0.39 90.52 3000 723 78.7 723 100 93.7 476.2 37.1 67.9 34.3 336.9 31.73 7.7 117 06 no parallel yes no 309.4 645 2790 99.5 1751 65.5 146 33.8 3.0 96 2675 4321 3830 2185 597 0.30 90.90 3000 720 77.5 720 100 93.7 476.2 36.6 67.7 34.2 337.7 31.94 7.5 114 07 no parallel yes no 308.0 644 2784 99.5 1162 55.8 163 42.2 3.0 75 2083 5178 4182 2185 592 0.15 91.31 3000 718 74.2 718 100 93.6 476.2 36.9 67.6 34.2 337.5 32.07 7.4 112 29 08 yes parallel yes no 308.0 644 2784 99.5 1162 55.8 163 42.2 3.0 75 2083 5178 4182 2185 592 0.15 91.31 3000 718 74.2 718 100 93.6 483.1 37.5 67.6 34.2 343.9 32.67 6.8 103 09 yes parallel yes no 308.0 644 2784 99.5 1166 55.9 260 41.1 3.0 77 2087 5104 4161 2185 596 0.16 91.31 3000 718 71.3 718 100 93.6 486.4 38.1 67.6 34.2 346.6 32.93 6.5 99 10 yes parallel yes no 308.0 644 2784 99.5 1166 55.9 260 41.1 3.0 77 2087 5104 4161 2185 596 0.16 91.31 2000 718 74.2 718 100 93.6 486.4 38.1 67.6 32.9 347.9 33.05 6.4 97 p100 yes series yes no 308.0 644 2784 99.5 1166 55.9 259 41.1 3.0 75 2087 5104 4161 2450 593 0.16 91.31 3000 718 71.3 718 100 93.6 486.5 37.7 67.6 34.2 347.0 32.97 6.5 99 p72 yes series yes no 229.4 480 2074 99.5 1151 62.7 225 35.5 3.0 61 1837 4509 3919 2146 574 0.27 3000 535 73.9 535 100 93.5 349.0 26.1 50.3 25.5 247.1 31.52 7.9 0 p50 yes series yes no 168.0 350 1513 99.5 1072 68.2 205 30.9 3.0 49 1572 4001 3672 1918 553 0.37 3000 391 76.2 391 100 93.7 239.2 16.5 36.7 18.6 167.4 29.16 10.3 0 p25 yes series yes no 98.4 206 889 99.5 697 70.3 206 29.1 3.0 26 991 3723 3514 1458 495 0.43 3000 230 77 230 100 93.6 119.3 7.2 21.6 10.9 79.6 23.67 15.8 0 6A no series yes no 309.4 645 2790 99.5 1751 65.5 146 33.8 3.0 96 2675 4321 3830 2450 666 0.30 90.90 3000 720 77.5 720 100 93.7 476.2 36.6 67.7 34.2 337.7 31.94 7.5 114 6B no series yes no 309.4 645 2790 99.5 1751 65.5 146 33.8 3.0 96 2675 4321 3830 2185 603 0.30 90.90 3000 720 77.5 720 100 93.7 476.2 36.6 67.7 34.2 337.7 31.94 7.5 114 9A yes series yes no 308.0 644 2784 99.5 1166 55.9 260 41.1 3.0 77 2087 5104 4161 2450 591 0.16 91.31 3000 718 71.3 718 100 93.6 486.4 38.1 67.6 34.2 346.6 32.93 6.5 99 9B yes series yes no 308.0 644 2784 99.5 1166 55.9 259 41.1 3.0 75 2087 5104 4161 2450 594 0.16 91.31 3000 718 71.3 718 100 93.6 486.5 37.7 67.6 34.2 347.0 32.97 6.5 99 4.1.4.1 O2-fired PC with Liquid CO2 Pump (case-3) Case-3, as shown in Figure 4.1.5, was formed from case-2 by adding the CO2 condensing process into CO2 plant. The CO2 gas is compressed first by a threestage compressor to over 900 psia, and then is cooled down by cooling water to its dew point. Most of the CO2 is condensed out as liquid, some of the CO2 stays in gas by equilibrium partial pressure, where the gas dew point reduces from 76 to 55ºF during condensation. Both the gas stream and the liquid stream from the condenser are boosted to the pipeline pressure by a small gas compressor and a liquid pump, respectively. Thus a potentially large gas compressor is replaced by a small compressor and a liquid pump. The gas stream is cooled down to nearly same temperature as the liquid, and then mixed with the liquid CO2 stream. The final CO2 stream therefore consists of the same liquid compositions as that of the case-2. In this way, the last stage of compression is accomplished by liquid pumping. The power saving is about 3.7 MWe, or 1.1% to the net power, while the efficiency increases from 30.81 to 31.14%. The electric power penalty is reduced from 129 in case-2 to 124 kWh/klbCO2 in case-3. Because of this power saving, this option will be applied to most of CO2 compression processes for the other cases. 30 Figure 4.1.5 - O2-fired supercritical PC with liquid CO2 pump (Case-3) Case: O2-PC-SC-03, ST=4035/1076/1112/2.0"Hg=460 MW 06/03/2005 Temperature (F) Pressure (psi) Mass Flow Rate (Mlb/hr) 1083 1076 4269.0 4035.0 2950 1112 1112 849.0 48 PC Boiler Duty (MMBtu/hr) 2950 1113 2406 823.2 823.0 2406 2406 26 SL5 2878 27 19 Power(MW) 17 2389 4035.0 67 LS1 459 823.0 823.0 1076 MAIN DPHRH 830 1112 1112 88 84 Q Duty (MMBtu/hr) W Power(MW) W WE EG W MULT 4630.0 2803 ROOF HP2 HP1 43 964 4445.0 835 PRPB Q=36 Q=137 4595.0 2950 44 1867 1580 1562 14.7 14.7 3394 3394 3394 G5 G6 FRH 14.7 47 1902 3 2878 5 2679 SC4 LP1 6 93.8 2301 8 38.9 2187 EI2 23 219 G8 42 21 1266.2 863.3 199 522 89 80 713 88 194.8 92 93.8 127 218 38.9 25 127 36.9 99 59 226 234 155 15.8 15.2 122 348 9 10.0 20 1 863.3 4822.0 Q=333 60 65 425 610 2950 FWH7 15 386 Q=0 114 429 V1 V2 2226 2950 FWH6 36.9 93.8 94 150 262 545 317 191.6 4979.0 4954.0 2950 FWH8 148 66 V3 712 181.2 342.6 522 3.7 77 78 V4 VD 430 527 199 4929.0 257 127 69 208 226 FWH4 2226 70 14 429 221.6 348 2226 FWH3 71 145 15.2 206.6 191.6 COND 3.7 214 Q=-1696 2226 FWH2 FWH1 87 Q=109 G13 14.7 81 236.6 7 4904.0 14.6 849 1561 32 Q=118 Q=311 Q=162 2950 1663 170 QB 23 102 206.6 236.6 0 608 4787.0 WETECO LECO STK1 569 120 100 14.7 14.7 0 0 60 N2 46 60 15.0 14.7 2803 34 AIR 2177 2832 14.7 SORB 0 400 FGD 2803 Q=135 700 SLV 67.0 2832 W=69 0 317 20.0 3394 COMP 97 29.7 60 14.4 G15 60 POND 15.1 0 PREC FGD 0 0 L2 90 67.0 120 2832 DIST AC 14.7 DENOX 53 CP W=1 4822.0 41 50 64 BYFW 2950 SPQ 35 637 G2 2226 68 4839.0 33 4770.0 14.7 1.0 0 2950 LIQ NH3 0 98 G20 EQ A0 14.7 SLV RGIBBS L1 0 317 700 SP1 E1 G16 302 14.3 14.3 3394 3394 302 Q=-3 W=0 SPF IDFAN G19 317 G17 14.7 G18 G21 W=4 3363 90 90 90 14.9 14.8 58.4 231.6 916.2 236 3163 788 779 776 20 3000.0 C4 C6 C9 C11 AV 55 0 20 RECY C3 317 2530 14.7 90 ASU GBY 15.3 473 3395 -183 15.1 3394 580 FLAME 3363 3363 ESP AAHX 3690 G1 Q=-250 15.1 14.1 302 119 NOZ 95 14.1 16.9 14.7 A4 A2 550 A6 ASH 550 C1 3312 COL1 A5 217 60 95 16.6 14.7 14.7 865 60 580 16.7 16.7 MILL 315 550 W=1 A1 317 W=11 15.4 15.1 2530 BYP SA COL2 Q=0 926.2 C10 W=0 776 2375 D1 COL3 Q=-49 90 14.9 46 150 15.0 90 Q=-43 90 655 A3 323 W=10 779 97 COL4 14.8 14.8 2425 COAL C7 C2 50 90 95 C8 233.6 W=11 788 Q=-1 SAFAN SPA 313 59.4 C5 Q=-341 1875 0 AIRB 310 SEP1 COMP3 COMP4 90 14.9 3312 90 58.4 D2 9 231.6 90 231.6 D3 D4 Q=-115 55 3000.0 916.2 755 755 1 CPUMP PIPEL 2 D5 GRH W=1 RY2 CO2 DEM 777 COMP2 COMP1 PA PIPEG 231.6 32 PAFAN RSTOIC Q=0 90 15.1 RY1 O2 Q=0 31 2226 102 Q=0 14.5 3394 2803 Q=-1755 269 W=18 569 843 G14 181.2 86 52 DAMP Q=-0 610 FWV HEATER 374 BFP1 Q=95 Q=141 Q=110 Q=135 DEA 396 342.6 BOILER 102 16 61 73 569 838 14.6 G11 Q 93 85 74 83 848 3481 SSR 644 382 267 95 V5 1266.2 522 14.7 E2 545 93.8 114 746 63 UECO 3394 Q=1306 5 79 FSPLIT 56 V6 V7 2185 57 76 353.2 18 10.0 3.9 AUX 112 569 G3 435 323 2803 SPRAY 24 EVAP 11 4510.0 1663 RHB 2803 890.0 532 199 2406 46 4665.0 152 6 14.6 G12 857.0 Q=315 810 45 1065 PW 40 644 93.8 871 658 1305.3 Q=-36 882 EL4 17 W=-18 879 1561 854 219 EL3 SL3 SL2 1562 4500.0 2950 EL2 2406 750 Q=210 1.0 1573 1.2 654 G9 14.7 102 1652 108 877.0 G4 Q=311 30 1775 96 657 PSH 3.9 1874 LS4 SPG Q=-39 152 EI3 EH2 SC1 3394 DIVW Q=389 29 234 15.8 93.8 DPCRH 1663 28 545 LP4 LP3 382 14.7 G10 LP2 540 EI1 22 1482 Q=-42 IP3 713 194.8 2389 SL6 G7 Q=-19 14.7 72 2406 IP2 871 353.2 EH1 SC23 FSH 1305.3 890.0 2803 IP1 653 890.0 750 658 W=3 4.1.4.2 O2-fired PC with Hot Gas Recycle (case-4) A case with hot gas recycle (case 4) was run to evaluate its effect on the system performance. A hot gas recycle brings more energy back into boiler, reduces fuel and O2 feed rates, and reduces ASU duty, but it requires more power to the fan because of the increased recycle gas volumetric flow. As result, increasing the recycle gas temperature from 95ºF to 138ºF increases the boiler efficiency from 89.3% to 90.1% and net efficiency from 31.14% to 31.53%. The resultant fuel saving is approximately 3.0 klb/hr or 1.0%. The size of the gas-gas heat exchanger increases due to the reduction in LMTD (fluid temperature difference is reduced from 212ºF to 166ºF for the hot end, and from 120ºF to 78ºF for the cold end). There is a limit to increasing the recycle gas temperature without increasing the stack gas temperature, which will reduce efficiency and increase cooling duty. One option mentioned in literature is to raise both stack gas and recycle gas temperatures, and then recover heat from stack gas to replace part of the feedwater heaters. Figure 4.1.6 - Temperature-Quality diagram for wet-end heat exchangers T-Q Diagram 400 Col-1, HT 350 Temperature, F 300 250 Col-1, LT 200 150 100 50 0 -300 Col-4 -250 -200 -150 Col-2&3 -100 Duty, MMBtu/hr 32 -50 0 50 Figure 4.1.6 shows the cooling curves for flue gas cooling before each stage of CO2 compressor. Part of the heat can be recovered to preheat the condensate. If 90 MMBtu/hr of heat is recovered (exit temperature = 142ºF), the steam saved from extraction generates an additional 2.2 MWe, or an efficiency increase of 0.2% point. If a total 150 MMBtu/hr of heat is recovered, the steam saved from extraction generates an additional 3.4 MWe, or an efficiency increase of 0.3% points. 4.1.4.3 O2-fired PC with High Flame Temperature (case 4 to 7) In cases of 4 to 7 the amount of flue gas recycle was reduced, to increase the O2% level to the boiler. This increase in boiler O2% creates a higher adiabatic temperature and less flue gas flow, which reduces the size of the furnace and increases the boiler and overall cycle efficiency. The adiabatic temperature is the maximum theoretical temperature that can be reached by the combustion with no loss of heat and no dissociation. Actual flame temperature is lower than the adiabatic temperature especially at adiabatic temperatures greater than 3600ºF due to flue gas dissociation of CO2 to CO and O2 (Figure 4.1.7). Figure 4.1.7 – Equilibrium and adiabatic temperatures vs. O2 concentration Adiabatic and Equilibrium Temp. Vs. Inlet O2 5500 5000 Temperature, F Adiabatic 4500 4000 Equilibrium 3500 3000 2500 15 20 25 30 O2 Percentage 33 35 40 45 The effect of adiabatic temperature on cycle efficiency is shown by Table 4.1.4, where case-4 has nearly the same adiabatic temperature as air-fired reference case, while cases 5 to 7 have higher adiabatic temperatures. Although there is little change in gas exhaust flow to CO2 compressor among cases 4 to 7, the decreasing recycle gas flow results in reduced auxiliary power consumption for both the FD and ID fans. It is noted that both the total power and the auxiliary power are relatively insensitive to the adiabatic temperature when it is greater than 4320ºF. However the efficiency related indices such as net efficiency, coal flow rate, and CO2 removal penalty improve with increased flame temperature even when it is beyond 4320ºF. Table 4.1.4 - Flame adiabatic temperature effect on performance case Adiabatic Temperature F Boiler Inlet O2 %, v Coal flow klb/hr Boiler Efficiency % Total Aux Power, MW MW Net Power MW Net Efficiency % Generated CO2 flow klb/hr Efficiency Drop % pts. CO2 removal energy kWh/klbCO2 01 3685 20.7 319.0 88.16 46.0 430.2 39.46 739 - 04 3678 27.8 312.0 90.14 140.1 336.1 31.53 725 7.9 119 05 4010 30.8 310.7 90.52 139.3 336.9 31.73 722.7 7.7 117 06 4321 33.8 309.4 90.9 138.5 337.7 31.94 720 7.5 114 07 5178 42.2 308.0 91.31 138.7 337.5 32.07 718 7.4 112 Table 4.1.5 shows the relationship of flue gas flow both in mass and in volume to boiler adiabatic temperature. The air-fired data is shown for comparison. It can be observed that the O2-fired PC has a lower volumetric flow rate than does the air-fired PC due to the higher molecular weight of the flue gas (i.e. CO2 versus N2). Table 4.1.5 – Flame adiabatic temperature effect on boiler flue gas flow case Boiler outlet flue gas flow Adiabatic Temperature Equilibrium Temperature 01 179 3555 3685 3552 MM cf/hr klb/hr F F 04 126 3357 3678 3474 05 109 2972 4010 3669 06 96 2675 4321 3830 07 75 2083 5178 4182 From case 4 to case 7 the ratio of the O2-fired PC volumetric flow rate to the airfired PC volumetric flow rate drops from 70% to 42%, which means for a constant flue gas velocity, boiler size is reduced. 34 Another advantage of decreasing the quantity of recycle gas is the increase in O2 content in the boiler (from 27% to 42% by vol. from case 4 to case 7), which improves the fuel combustion and reduces the required height of the furnace. This credit from the reduction of UBC has been approximated in this system study, while a more thorough treatment will be modeled in the 3-D CFD boiler simulation study (Section 4.3). 4.1.4.4 O2-fired PC with Wet-End Economizer (case-8, 9) One option to increase system efficiency is to use an economizer to recover lowgrade heat from compressor inter-stage coolers, and from the flue gas cooler before the CO2 plant. Case-8 is such a case for integration of low grade heat recovery (based on case-7), where the heat recovered was used for low pressure feed water heating. A method of condensate split stream was applied. The steam extractions from ST at different LP ports were adjusted to match the duties. This option incurs no cost increase because all these heat exchangers were already installed to cool the flue gas for the CO2 plant. The only difference is in that the cold side cooling water was replaced by condensate from the ST. In this way, the cooling water duty was reduced too. The temperature-quality diagrams for these low-grade heat coolers are plotted in Figure 4.1.6, where 150ºF, just above the flue gas dew point, was used as hot exhaust temperature for heat recovery. This leads to a temperature approach at the hot side of about 50ºF, which is sufficient for economizer design and sizing. Because the tube wall temperature is below the flue gas temperature, part of the moisture is condensed out on the wall. A wet-end heat exchanger design therefore has to be considered for this application. Additional cooling is required to reduce gas temperature from 150 to 90ºF by cooling water before gas compression, and the condensate from gas moisture needs to be drained out before the compressor. The dominant change of this option is to produce more power from the generator as the result of less steam extraction. The total power generated increased substantially from 476 to 483 MWe, or 2% increase in net power. This leads to better system performance as the electrical power penalty is reduced from 112 to 103 kWh/klbCO2, an 8% drop. The efficiency drop changed from 7.4% to 6.8% in points. The net efficiency increased from 32.07% to as 32.67%, a net 0.6% point increase. The application of the wet-end heat exchanger to recover low-grade heat brings the benefit that the temperature of the hot recycle gas can be further boosted. This will cause a high gas exit temperature from gas-gas heat exchanger to ID fan. The heat from this high temperature exit stream can be recovered by an economizer, which means more steam condensate will be extracted and sent to economizer to pick up more low-grade heat. Because of temperature approach limitation at cold side of gas-gas heat exchanger, this option will not bring any 35 more energy back to the boiler. Instead, it will discharge more heat to the economizer and to the feed water. Therefore both the system efficiency and total power will be increased. Since this option does not bring more energy to boiler, the fuel feed rate, and the boiler efficiency were not changed. The main change is power generation, from 483 to 486 MWe in total as compared with case-8. As a result, the power penalty reduced to 99 kWh/klbCO2, and the efficiency drop to 6.5% in points. The net system efficiency changed to 32.93%. This hot gas recycle brings back more moisture to the boiler, as 15%v, and flue gas moisture went up to 23.8%v. This moisture slightly changes the boiler performance, such as recycle gas mass and volumetric flows, adiabatic temperature, and O2%v to boiler. The high moisture content in gas tends to reduce the difference between equilibrium and adiabatic flame temperatures, which is similar to water-gas shift equilibrium, where CO is shifted by water vapor to as H2, and the generated H2 is much easier to be burned than the CO. 4.1.4.5 O2-fired PC with Reduced Pipeline pressure (case-10) This pressure change only affects the CO2 plant power. When this pressure changed from 3000 to 2000 psia, the CO2 compression power changed from 34.2 to 32.9 MWe with liquid CO2 pumping as the last stage. While the power for the last stage compression, if only gas compressor is used without CO2 liquid pumping, would change from 6.5 to 3.9 MWe. Therefore even without the requirement of CO2 purification, the CO2 condensation before last stage is important in power saving, especially for the high pipeline pressure. At the Ref. 14 specified pressure of 2200 psia, overall cycle efficiency is increased by 0.1% points versus a pressure of 3000 psia. 4.1.4.6 O2-fired PC with HRA Series Pass (case-6A/6B, 9A/9B) Because of the reduced flue gas flow and lower HRA duty for high O2 concentration operating cases, designing the HRA in series instead of parallel will produce a more compact design The modified HRA arrangement will not affect the heat balance, but will affect the mechanical design and the heat duty arrangement. Due to less heat picked up by the pre-superheater, the water spraying for steam superheat temperature control was setup before the finishing superheater. Case-6B (Figure 4.1.8) applies nearly the same HRA inlet temperature (1451 vs. 1460ºF), as the case-6, while the case-6A applies a higher HRA inlet temperature, 1732ºF, to increase the energy discharge to HRA to maintain a better temperature profile. In case-6a, part of heat duty was shifted from boiler to HRA, which was absorbed by a larger economizer resulting in a higher feed water temperature (666 vs. 603ºF), while the furnace water wall heat duty was reduced from 1441 to 1198 MMBtu/hr. 36 Because of less flue gas recycle required for the higher adiabatic temperature of case-9, there was not enough heat to maintain the same HRA temperature profile. Consequently, either the economizer water temperature can be reduced or the HRA inlet temperature can be increased. A high HRA inlet temperature was applied for case-9A to keep the water temperature from economizer at about 590ºF. The higher HRA inlet temperature also helped to shift heat duty from division wall to the finish superheater. The exit steam temperature from the division wall was about 1021ºF in case-9A, which could require expensive high-grade materials to be used. In order to reduce this temperature, a different approach was used in case-9B, where the PSH (primary superheater) was removed and its heat duty was shifted to the finishing superheater. Kept constant were the flue gas temperature to the economizer, the water temperature to the evaporator, and the LMTD of lower reheater. Consequently, the finishing superheater size increased since its duty changed from 289 to 416 MMBtu/hr. Case-9B (Figure 4.1.9) has a modification, where the heat picked up by roof was reduced from 134 to 50 MMBtu/hr, and the difference was shifted to water wall, which leads to an increased steam exit temperature from water wall. This does not affect the heat and material balances, but only the design. 37 Figure 4.1.8 - Boiler design with HRA series pass ST=4035/1076/1112/2.0"Hg=460 MW Case: O2-PC-SC-06B, 09/28/2005 Temperature (F) Pressure (psi) Mass Flow Rate (Mlb/hr) 1076 PC Boiler Duty (MMBtu/hr) 4035.0 569 4822.0 148 1083 4286.0 2803 48 1112 1112 823.2 823.0 2406 2406 2406 LS1 67 823.0 2389 Q=134 1451 1409 14.7 14.7 2705 2705 2705 G5 G6 1829 FRH 14.7 47 837 4612.0 44 1864 1021 14.7 4472.0 2705 871 890.0 353.2 72 8 38.9 545 2193 EI1 28 29 SL2 219 199 877.0 55 1283 361 6 AUX G11 2705 863.3 199 522 89 80 18 5 47 SSR 9 FSPLIT 713 194.8 88 56 108 545 267 382 218 234 93.8 93.8 38.9 36.9 15.8 78 78 59 137 92 25 59 644 155 10.0 15.2 20 210 73 23 B1 V7 2406 V6 V5 522 2950 FWH8 522 4954.0 65 4929.0 2950 425 2950 FWH7 66 V3 386 610 15 108 Q=0 191.6 4979.0 257 150 262 545 36.9 93.8 257 78 191.6 94 1332 2950 FWH6 318 V1 V2 712 181.2 342.6 863.3 3.7 77 78 V4 VD 430 527 199 4904.0 Q=138 95 746 1266.2 63 569 45 1 112 877.0 PSH 2803 435 323 10.0 3.9 57 76 353.2 890.0 152 657 14.6 4527.0 11 1266.2 40 644 93.8 871 658 532 863 EL4 17 654 SL3 1305.3 21 1.0 1751 W=-18 657 102 1797 108 EI3 750 B2 30 1870 EL3 EL2 LS4 Q=106 3.9 1.2 219 DPCRH 49 152 1929 24 2406 234 15.8 93.8 96 RHB 869 Q=289 93.8 2301 EI2 EH2 DIVW Q=479 6 2389 LP4 LP3 382 22 910 857.0 Q=329 5 2679 EH1 2045 SC1 G4 3 2878 540 194.8 857.0 G8 Q=-36 Q=-31 2803 653 890.0 2406 LP2 713 750 1305.3 2803 SC23 81 WEG MULT WE Power(MW) LP1 IP3 IP2 IP1 658 SL6 SPRAY FSH W W 88 HP2 HP1 PRPB Q=36 2950 Duty (MMBtu/hr) 2950 43 4462.0 Q 17 84 60 974 469 823.0 SL5 2878 27 19 26 1076 4035.0 Power(MW) 1112 1112 MAIN DPHRH 832 4647.0 ROOF 2950 1113 849.0 69 137 1332 FWH4 145 15.2 206.6 70 1332 FWH3 3.7 214 208 71 COND 14 257 221.6 210 Q=-1860 1332 FWH2 FWH1 87 812 2185 4682.0 42 32 G3 Q 41 G12 2045 Q=162 657 2705 Q=311 RHA QB 396 2045 374 BFP1 Q=-0 610 52 4839.0 BOILER G13 4822.0 100 122 SPQ STK1 50 CP 695 60 14.5 20.0 2705 0 SORB N2 14.7 AIR 2145 400 COMP SLV 67.0 2790 W=68 60 POND FGD PREC 90 67.0 122 L2 0 2790 0 0 309 15.1 0 2790 DIST AC 14.7 DENOX LIQ NH3 EQ 0 G20 98 L1 309 SP1 296 695 14.4 14.4 E1 G16 2705 2705 ESP AAHX 296 15.1 14.2 2674 309 G18 15.1 2705 G21 W=3 625 Q=-246 Q=-3 IDFAN G17 14.7 0 W=0 SPF 2674 G19 4321 A0 14.7 SLV RGIBBS 2674 -183 90 90 90 90 14.9 14.8 58.4 231.6 2126 776 767 764 C4 C6 GBY AV 55 0 236 916.2 3000.0 29 29 RECY 15.3 1846 A2 550 ASH 550 C1 249 Q=0 PA 16.6 A5 60 625 16.7 MILL 550 60 145 14.7 14.7 0 1201 A1 Q=0 323 926.2 767 C10 W=0 764 98 COL4 1350 COL3 90 14.9 D1 147 46 15.0 90 90 231.6 58.4 D2 9 D3 3000.0 55 90 Q=-42 Q=-48 Q=0 645 A3 233.6 C7 COL2 14.8 14.8 1751 COAL 776 W=10 Q=-1 C2 401 90 145 SA C5 W=11 15.1 BYP 1846 SAFAN SPA AIRB 15.4 W=1 313 59.4 W=11 2273 309 Q=-281 119 859 16.7 309 SEP1 14.9 COMP3 COMP4 311 90 DEM 765 COMP2 COMP1 COL1 PIPEG 231.6 2273 31 PAFAN A6 C11 90 15.1 14.2 16.9 14.7 A4 296 171 145 2706 C3 309 Q=-282 NOZ RSTOIC 53 W=1 14.7 0 0 60 29.7 G15 489 2232 64 15.0 60 14.7 14.7 2803 G2 14.7 1.0 WETECO BYFW 2705 231.6 D4 Q=-113 735 916.2 735 CPUMP 1 PIPEL 2 D5 GRH W=1 RY2 RY1 O2 38 1332 102 900 900 2950 W=18 97 FLAME 236.6 Q=200 33 34 G1 206.6 46 569 LECO 14.7 7 Q=57 102 850 14.6 Q=118 3826 Q=84 322 68 35 E2 102 16 2950 Q=210 603 4787.0 2803 181.2 86 FWV 569 12 Q=-2042 61 Q=65 DEA 342.6 20 Q=1440 HEATER 73 Q=83 Q=118 877.0 EVAP 93 85 236.6 14.6 867.0 2705 74 1115 820 14.7 2803 83 W=3 Figure 4.1.9 - Boiler design with HRA series pass (56% Flue Gas Recycle) Case: O2-PC-SC-09B, ST=4035/1076/1112/2.0"Hg=460 MW 09/28/2005 Temperature (F) Pressure (psi) Mass Flow Rate (Mlb/hr) 1076 PC Boiler Duty (MMBtu/hr) 4035.0 569 4822.0 148 832 1083 4647.0 4286.0 48 2803 ROOF 2950 1113 1112 1112 849.0 823.2 823.0 2406 2406 2406 MAIN 19 1076 823.0 4035.0 2389 67 LS1 DPHRH 26 Q=50 1850 1379 1326 14.7 14.7 2117 2117 2117 G5 G6 FRH 14.7 47 658 837 81 974 14.7 4542.0 2117 72 2406 871 1305.3 353.2 8 EI2 EI1 2406 21 B2 55 219 EL2 EL3 G11 23 B1 93.8 6 AUX 152 10.0 3.9 5 47 SSR 435 323 863.3 522 89 80 871 713 353.2 194.8 18 56 88 108 545 267 382 93.8 93.8 38.9 36.9 78 78 59 137 92 25 218 95 527 199 863.3 234 15.8 59 155 644 15.2 10.0 20 210 73 425 522 4954.0 522 65 2950 FWH8 712 181.2 66 15 386 610 108 318 93.8 257 78 191.6 FWH4 1332 94 257 V1 V2 150 262 545 1332 2950 FWH6 V3 Q=0 191.6 4979.0 2950 FWH7 430 342.6 36.9 69 208 137 70 1332 FWH3 145 15.2 206.6 820 71 93 85 74 83 210 FWH2 Q=-1860 1332 FWH1 102 16 61 73 236.6 7 Q=118 Q=311 Q=162 657 2117 396 2045 342.6 DEA BFP1 Q=-0 610 86 52 4839.0 BOILER 322 102 374 206.6 236.6 181.2 900 1.0 2232 WETECO 68 W=18 50 64 833 BYFW 14.6 G13 33 SPQ 2803 100 126 4822.0 LECO 60 46 569 2117 2803 34 SORB AIR 2140 2784 0 400 SLV 97 Q=84 N2 14.7 0 0 67.0 COMP 2784 29.7 G2 G15 695 60 14.5 20.0 2117 0 W=68 0 383 60 15.1 0 L2 90 67.0 POND PREC FGD 0 126 2784 DIST AC 14.7 DENOX LIQ NH3 98 0 G20 EQ W=1 14.7 15.0 60 14.7 14.7 STK1 35 14.7 A0 14.7 SLV 383 RGIBBS 368 695 SP1 E1 G16 14.4 14.4 2117 2117 14.2 2087 2087 ESP AAHX 368 15.1 G19 15.1 G21 2118 Q=-246 Q=-3 383 G18 2117 625 FLAME 0 IDFAN G17 14.7 L1 W=0 SPF 5104 1260 W=2 2087 -183 90 90 90 90 14.9 14.8 58.4 231.6 1314 774 766 763 C4 C6 AV 55 0 916.2 236 37 3000.0 GBY 37 RECY Q=-188 NOZ 259 ASH 550 C1 30 257 RSTOIC A5 PA 60 625 16.7 MILL 550 60 259 14.7 14.7 A1 SAFAN BYP A3 SPA SA Q=0 COMP4 59.4 C5 323 233.6 W=11 774 C7 Q=-269 W=10 766 926.2 C10 W=0 763 Q=-1 COL2 259 90 14.8 14.8 1166 540 98 COL4 C2 626 Q=0 14.9 D1 146 COL3 Q=-48 90 46 90 58.4 D2 90 Q=-42 90 15.0 644 COAL COMP3 313 15.1 1260 616 0 AIRB 383 15.4 W=1 W=11 1461 163 858 16.7 308 SEP1 14.9 16.6 Q=0 DEM 763 311 90 COL1 PIPEG COMP2 COMP1 PAFAN C11 231.6 1461 550 A6 90 15.1 14.2 16.9 A2 C3 383 368 288 14.7 A4 53 CP Q=200 2950 Q=210 594 4787.0 9 231.6 D3 231.6 D4 Q=-112 55 3000.0 916.2 725 725 CPUMP 1 PIPEL 2 D5 GRH W=1 RY2 RY1 O2 39 1332 102 900 2950 FWV 569 12 Q=57 Q=84 Q=65 Q=83 877.0 19 14.7 14 257 221.6 14.6 G12 2045 Q=1558 15.3 COND 3.7 214 87 867.0 457 1 3.7 77 78 V4 VD V5 746 32 1161 RHA G1 9 FSPLIT 890.0 199 4929.0 2950 EVAP 11 1266.2 63 Q=4 2450 41 57 76 V6 V7 2406 4904.0 14.7 40 644 112 PSH 2117 EL4 657 877.0 2117 1.0 1751 17 654 658 199 657 14.6 569 E2 219 102 1797 108 W=-18 1266.2 361 30 1870 1.2 LS4 Q=106 3.9 1929 SL3 SL2 45 4161 29 152 EI3 1305.3 837 Q=-2089 28 234 15.8 93.8 750 2803 HEATER 38.9 545 2193 LP4 LP3 24 4597.0 QB 93.8 2301 DPCRH RHB Q LP2 382 96 877.0 G3 LP1 540 EH2 1167 2803 6 2389 22 910 532 825 5 2679 IP3 2045 49 42 3 2878 DIVW 4682.0 WEG MULT Power(MW) 713 194.8 857.0 G8 869 Q=416 IP2 653 890.0 2803 857.0 Q=329 IP1 750 SL6 SC1 G4 Q=487 W 88 EH1 Q=-36 Q=-25 2803 890.0 4612.0 44 SC23 1885 FSH W WE HP2 HP1 SPRAY 469 Duty (MMBtu/hr) 2950 PRPB Q=36 2950 Q 17 84 43 4532.0 Power(MW) 823.0 SL5 2878 27 60 934 1112 1112 W=2 4.1.5 Part Load For a sliding pressure supercritical system design, part load performance has to be considered and evaluated. For this purpose, the Aspen model can be used by converting its design model to a simulation model, where all of the equipment sizes are fixed from the design case. Based on the 100% load condition, the heat transfer coefficients are functions of operating conditions, such as temperatures and Reynolds number. At full load, the heat transfer coefficients vary from 14.4 for the finishing superheater to 9.7 Btu/ft2-hr-F for economizer. In order to simulate the air-air heat exchanger, the original lumped module was replaced by two modules for both the primary air and the secondary air. The steam turbine was also converted in the simulation model such that the turbine exit parameters are floated as loading changes. The model for feedwater heaters was adjusted so that the extraction pressures were automatically calculated. The water wall absorption of boiler is difficult to be simulated by the zero dimensional Aspen model. Therefore its performance such as the gas exit temperature was calculated separately using the 3-D FW-FIRE model and iterated with Aspen. Note that in conventional air fired PC boiler, the excess air has to be increased during part load to maintain steam exit temperatures. Increasing excess air is not necessary for the oxygen-fired boiler since the quantity of flue recycle can be increased at part load to maintain steam temperatures. Increasing flue gas recycle flow rather than excess air has less adverse effect on plant performance and emissions. The 72% part load (72% generator power) is shown as Case p72 in Table 4.1.3. The amount of flue gas recycled is adjusted to produce sufficient SH and RH steam temperatures. The water spray to SH was adjusted from 5% to 4% to boost SH steam temperature. In this way, the efficiency loss is kept at a minimum when boiler is operated in part load. The loading is further reduced to 50% as shown by p50 in Table 4.1.3. At this load, the main steam pressure is 2125 psia. At this pressure, the steam turbine can be operated at a reasonably high temperature to keep the system efficiency high. Therefore the boiler was adjusted to maintain both the SH and RH steam conditions as near as possible to those at 100% load. Note that the flue gas recycle flow changes only slightly as the loading changes from 100% to 50%. The lowest part load case for this study was 25% as shown by p25. In corresponding to a sliding pressure, both SH and RH steam temperatures were adjusted through the combination of firing rate and gas circulation rate to make sure the end steam exhausted from the steam turbine at right conditions. Because of lower steam conditions, the system efficiency reduced substantially. 40 Figure 4.1.10 and Figure 4.1.11 are plots, which show the effect of part load on performance. At some loadings, the flue gas absolute recycling flow does not change much, but its ratio to boiler flow changes because of less total boiler gas flow as shown by Figure 4.1.10. Figure 4.1.11 shows the relation between part load and system efficiency. Figure 4.1.10 - Flue gas recycle flow vs. part load operation Part Load Performance 100 1400 90 1200 70 60 800 50 600 40 30 400 gas recycling, % Gas recycling, klb/hr 80 1000 20 200 10 0 120 0 0 20 40 60 80 100 Load, % Figure 4.1.11 Efficiency at part load operation Part Load Performance 40 35 Efficiency, % 30 25 20 15 10 0 20 40 60 Loading, % 41 80 100 120 4.1.6 Comparison With Post Combustion CO2 Capture CO2 cannot be captured and sequestrated without reducing both the plant power and efficiency because of the potential energy stored in the pressurized liquid CO2. A minimum of 40 kw/klbCO2 additional auxiliary power is required for CO2 compression. The difference between technologies lies in the difference in power requirements of the different CO2 or O2 separation techniques. Parsons (Ref. 1) performed studies on CO2 removal by a post capture method for a conventional PC boiler. In their study for post combustion CO2 removal, the plant efficiency drops from 40.5% to 28.9% for a supercritical (3500 psia/1050ºF/1050ºF/1050ºF/2.0”Hg) boiler, and from 42.7% to 31.0% for an ultra supercritical (5000 psia/1200ºF/1200ºF/1200ºF /2.0”Hg) boiler. In the study presented herein, the CO2 removal using an O2-fired PC is used, which relies on an ASU. At a pipeline pressure of 2000 psia (as applied in the Parsons study) the efficiency drops from 36.7% to 30.4% for the subcritical (2415psia/1000ºF/1000ºF/2.5”Hg) boiler [3], and from 39.5% to 33.1% for the supercritical (4035psia/1076ºF/1112ºF/2.0”Hg) boiler. The net efficiency drops for these cases are 11.7% points for supercritical, post combustion CO2 removal 11.7% points for ultra supercritical, post combustion CO2 removal 6.3% points for subcritical, O2 fired 6.4% points for supercritical, O2 fired Another comparison basis is the kWh per klb CO2 removal, where the kW is power generation difference between cases with and without CO2 removal. Comparing the post CO2 capture to the O2-fired case yields: 187 kWh/lbCO2 for supercritical, 90% post combustion removal 188 kWh/lbCO2 for ultra supercritical, 90% post combustion removal 99 kWh/lbCO2 for subcritical, O2 fired 100% removal 97 kWh/lbCO2 for supercritical, O2 fired 100% removal Thus the efficiency drop and change in power penalty for CO2 removal appears independent of steam cycle. From the above data, it is clear that the O2-PC has significant advantages over the post combustion CO2 capture. 4.1.7 Furnace Waterwall Temperature The level of radiation in the O2-fired boiler is significantly higher than an air-fired boiler due to greater concentrations of radiating gas species (CO2 and H2O) and higher flame temperature. Consequently, it is important to select the proper amount of recycled flue gas to limit the water wall temperature such that a reasonable waterwall material can be used. The maximum waterwall temperature and furnace heat flux is determined in Section 4.3. 42 4.2 Advanced O2 Separation System Integration 4.2.1 O2-Fired PC Integrated with Cryogenic ASU (case-6) The model of the oxygen-fired plant with cryogenic ASU was described in Section 4.1.3. Figure 4.2.1 presents the cryogenic ASU base case system model (case-6). Flue gas recycle flow rate is 65.5% resulting in a boiler equilibrium temperature of 3830ºF and an overall cycle efficiency of 31.94%. The oxidant from the ASU is 99.5% O2 pure. ASU and CO2 plant power consumptions is 67.7 and 34.2 MWe, respectively, resulting in a total auxiliary power of 138.5 MWe, or about 29.1% of gross power. The efficiency drop compared to the air-fired case is 7.5% in points (39.46% to 31.94%), and the associated power penalty is 114 kWh/klbCO2. 43 Figure 4.2.1 - Base case of O2-fired supercritical PC with Cryogenic ASU Case: O2-PC-SC-06, ST=4035/1076/1112/2.0"Hg=460 MW 06/03/2005 1083 Mass Flow Rate (Mlb/hr) 4035.0 2950 48 1113 1112 1112 849.0 823.2 823.0 2406 2406 2406 830 2950 1112 MAIN 67 LS1 19 ROOF HP2 HP1 Q=137 47 1818 1460 1442 14.7 14.7 14.7 FRH 2705 2705 G5 G6 PRPB Q=36 2705 44 890.0 2803 2406 G10 G8 W WE EG W MULT PW G12 EI2 EI1 532 199 1266.2 219 EL2 435 323 863.3 Q=333 194.8 56 114 545 267 382 218 93.8 93.8 38.9 36.9 127 127 99 226 92 25 60 863.3 425 522 4954.0 65 527 81 386 610 4979.0 G13 15 114 2950 69 36.9 208 226 206.6 DEA BFP1 2226 86 695 60 14.4 20.0 0 DENOX 122 100 14.7 14.7 0 0 STK1 N2 AIR 2145 PREC FGD 400 67.0 2790 60 POND 122 L2 LIQ 14.3 14.1 2674 98 0 A0 14.7 0 Q=-246 15.1 Q=-3 W=0 SPF 311 G18 G21 90 90 15.1 2705 90 14.9 2674 90 58.4 14.8 2126 625 W=3 NOZ A4 550 C1 ASH 31 COL1 PA Q=0 120 16.7 309 60 14.7 14.7 0 1201 859 625 16.7 MILL COAL 550 SAFAN AIRB SPA SA A1 C5 776 W=11 COMP3 C7 146 767 C10 W=0 764 98 COL4 COL2 90 14.8 14.8 1350 GRH 926.2 Q=-1 C2 401 1751 RY2 CO2 COMP4 323 W=10 Q=-282 BYP A3 W=1 W=11 DEM 765 233.6 15.1 1846 29 C11 PIPEG 313 59.4 SEP1 311 15.4 W=1 311 2273 146 249 16.6 236 3000.0 29 231.6 COMP2 COMP1 14.9 RSTOIC 916.2 90 2273 90 PAFAN 55 0 ASU C6 C3 15.1 14.1 16.9 A2 550 -183 764 RECY 311 296 171 A6 GBY AV 231.6 767 776 146 Q=-282 14.7 90 AC 2674 IDFAN 14.7 W=68 2790 DIST SLV 311 ESP AAHX 4321 W=1 2790 0 COMP G20 2705 53 CP 14.7 15.0 60 14.7 67.0 0 14.3 2226 50 60 0 311 2705 1.0 0 Q=0 SORB RY1 Q=0 44 Q=0 90 14.9 D1 147 46 Q=-48 O2 90 Q=-42 58.4 15.0 645 COL3 D2 9 90 90 231.6 D3 2 231.6 D4 Q=-113 55 3000.0 916.2 735 735 CPUMP 1 2226 102 64 15.1 296 Q=95 WETECO 97 2803 NH3 G16 Q=-1696 102 BYFW FGD 296 COND 14 429 FWH1 102 0 46 EQ SP1 71 236.6 2950 14.7 E1 2226 Q=141 W=18 569 2705 695 145 221.6 348 FWH2 68 0 RGIBBS 3.7 214 15.2 16 Q=110 29.7 G15 150 206.6 181.2 Q=-0 4822.0 Q=79 429 V1 61 269 374 52 SPQ 34 G2 70 FWH3 73 2950 35 A5 1 112 77 4839.0 2803 60 20 348 122 236.6 592 2803 4770.0 1846 644 10.0 V2 2226 FWH4 4787.0 LECO 597 257 191.6 127 Q=135 396 569 799 2705 9 155 15.2 7 Q=118 Q=311 Q=162 342.6 14.5 G14 14.7 5 79 SSR 4904.0 32 811 135 DAMP 545 93 85 610 HEATER 2706 3.9 57 262 93.8 94 2226 2950 74 FWV 15.3 10.0 15.8 59 V3 Q=0 317 191.6 FWH6 FWH7 83 19 489 152 87 14.6 14.7 181.2 342.6 66 2950 2950 FWH8 569 818 14.6 41 234 78 V4 712 430 527 522 199 4929.0 148 95 VD V5 Q=17 14.7 40 644 93.8 FSPLIT 713 88 80 1266.2 63 2185 1758 1.0 1573 EL4 17 6 353.2 18 V6 569 BOILER 219 EL3 654 76 522 746 4822.0 G11 890.0 11 89 UECO 811 102 1652 3.7 811 V7 2705 30 108 1775 1.2 871 199 2803 RHB Q=-2042 29 1874 93.8 SL3 658 1305.3 21 SPRAY 24 QB 545 2187 3.9 AUX 750 2406 46 Q 8 152 14.6 Q=-36 14.7 2301 LP4 LP3 234 15.8 W=-18 2406 4510.0 45 893 2803 LP2 382 38.9 EI3 SL2 855 Q=114 1758 882 857.0 4665.0 LP1 540 93.8 96 1442 4500.0 FLAME Power(MW) LS4 14.7 Q=299 2389 SL6 657 23 Q=311 G1 W 877.0 PSH G9 810 2679 6 DPCRH 811 SPG 2950 IP3 194.8 EH2 SC1 Q=-31 835 3 2878 14.7 G4 3826 Duty (MMBtu/hr) 713 353.2 22 1362 DIVW Q=501 72 IP2 871 890.0 1305.3 SC4 Q=-20 G7 Q=-15 2705 4595.0 IP1 653 750 EH1 SC23 14.7 658 835 1853 FSH Q=1453 88 84 43 G3 Q SL5 2878 27 970 EVAP Power(MW) 17 2803 4445.0 42 459 823.0 2389 4035.0 Duty (MMBtu/hr) 1112 823.0 1076 DPHRH 26 4630.0 2950 Pressure (psi) 1076 4269.0 PC Boiler Temperature (F) PIPEL D5 W=3 4.2.2 O2-Fired PC Integrated with OITM Advanced oxygen separation through high temperature membranes such as OITM is currently under development [2, 4, 5, 7]. Oxygen ion transport membranes have the potential to provide a major reduction in oxygen separation capital and energy consumption. Oxygen ion transport is driven by the difference in oxygen partial pressure across a membrane. Oxygen atoms adsorb on the cathode (high oxygen partial pressure side of the membrane) and dissociate into ions as they pick electrons. These ions travel from cathode to anode (the low oxygen partial pressure) by jumping through lattice sites and vacancies until they reach the anode side of the membrane. On the anode side, the oxygen ions yield their electrons to become atoms/molecules, which are then desorbed into the gas phase. Electrons from the anode side are carried through the membrane to the cathode side to complete the circuit. The rate of oxygen transport through such membranes is temperature sensitive, and can be very fast at high temperatures. These membranes have infinite selectivity for oxygen over other gases, because only oxygen ions can occupy the lattice positions. A typical schematic of the oxygen ion transport membrane process is presented in Figure 4.2.2. The OITM process and design data are based on Reference 7. A schematic of the OITM process incorporated within the O2-PC plant is shown in Figure 4.2.3. To integrate the OITM into the O2-fired PC, air is pressurized by a compressor, and then heated to a high temperature. High pressure air provides a high oxygen partial pressure on the airside of the OITM to reduce the size and cost of the OITM. Air enters the compressor at 60ºF and 14.7 psia and is compressed at 85% efficiency to 215 psia and 743ºF. The compressed air is heated to 1652ºF by a tubular air heater inside the PC furnace. This hot pressurized air is fed to the OITM, where about 85% of its O2 is separated through the membrane to an exit pressure of 16 psia, and the rest of the vitiated air or O2-depleted air is sent to a gas expander to generate power at 86% turbine efficiency. Power generated from the expander is used to drive the air compressor. Since the power generated in the gas expander is greater than the air compressor power the OITM system produces a net power output. The separated O2 from the membrane is carried by a heated sweep gas. The use of a sweep gas reduces the oxygen partial pressure on the low-pressure side of the membrane and consequently reduces the size and cost of the OITM. A recuperator is applied between inlet and outlet sweep gas flows to reduce the heat requirement. Heat transfer from the sweep gas to the membrane to the air is neglected as it is expected to be relatively small (it was also neglected in Reference 7). The mixture of sweep gas and O2 is then injected into the furnace. In this design, the OITM does not consume electrical power; instead, it absorbs heat, generates power, and separates O2 from air. Therefore it is expected to reduce ASU operating and capital costs. 45 From a heat and mass balance point of view, if there is no heat transfer between the air and sweep gas, the model can be simplified by directly mixing the separated O2 with the sweep gas. Thus, to simplify the model, the recuperator and OITM are combined into a single module in the Aspen model. The operational details of the OITM, such as the O2 flux through the membrane as a function of OITM temperature and pressure, were not included in the Aspen model. These details are necessary only for OITM size and cost estimations. Moreover, the Aspen model does not directly model the recuperator, but the recuperator design and configuration is required for the economic analysis. Without performing a detailed economic study, it is difficult to determine the optimum OITM operating pressure. However, Reference 8 specifies that for an economic design, the ratio of oxygen partial pressures of the feed gas (air) to the permeate stream (sweep gas) should be approximately 7. The base case OITM design has an oxygen partial pressure ratio of 4.9 at the air inlet and 10.2 at the air outlet, yielding an approximate average ratio of 7.5. Reference 8 specifies that an 85% O2 recovery and an operating temperature of 1652ºF is within the operating range of the OITM. The effect of O2 recovery and OITM operating pressure on system performance and OITM design is examined in Section 4.2.2.3.1 and Section 4.2.2.3.2, respectively. Several cases incorporating an OITM ASU into the O2-PC have been simulated to evaluate the effect of different conceptual designs and operating conditions on power plant performance. 46 Figure 4.2.2 - A Typical Oxygen Ion Transport Membrane Schematic [4] 47 Figure 4.2.3 – Integration of Oxygen Ion Transport Membrane into O2-PC 48 4.2.2.1 Process Gains The inclusion of a gas turbine expander in the O2-PC power plant utilizing the OITM increases the overall system efficiency by allowing work to be done in the gas turbine at a higher temperature than can be achieved by the steam from the boiler. This principle has been applied by FW in its 1st generation Pressurized Fluidized Bed Combustor (PFBC) design. A further enhancement is the 2nd generation PFBC design (similar to IGCC) in which the turbine entrance temperature is increased by syngas combustion. This concept was also applied in the FW High Performance Power System (HIPPS) design, which includes an infurnace high temperature air heater similar to the one required for the O2-PC OITM concept. 4.2.2.2 Base Case (case-11) Figure 4.2.3 shows a schematic of the OITM ASU integrated with the O2-fired PC power plant. The OITM system includes a sweep gas system, and an air supply system. The pressurized vent gas from the CO2 plant is recycled back to the air separation unit, where it is mixed with the compressed air. In this way the rich O2 in the vent gas can be recovered, and the air to compressor can be reduced. Therefore this vent gas recycling increases system efficiency and reduces the operating cost. Figure 4.2.4 (case-11) is a process flow diagram generated by Aspen Plus for the OITM ASU integration. Air is compressed to about 200 psia by a compressor, and then heated within the boiler to about 1650ºF. This hot pressurized air is fed to OITM, where about 85% of its O2 is separated through a membrane, and the rest of vitiated air is sent to an expander. The separated O2 from the membrane is carried by a heated recycled flue gas after gas-to-gas heat exchange. A recuperator is applied between inlet and exit sweep gas flows (not shown in Figure 4.2.4 since it lumped inside the OITM module). The mixture of sweep gas and O2 is fed directly to the boiler. The exhaust gas from the expander passes through an economizer to release its heat for feedwater heating. Power generated from the expander is used to drive the air compressor. The O2 obtained from the OITM is swept with recycled flue gas. Since the compressed air is heated to 1650ºF inside the boiler, a special heat exchanger and boiler design has to be used for the OITM application (Sections 4.3.2.2.3 and 4.3.5.4). The boiler air heater duty is 974 MMBtu/hr. The coal feed rate is 377 klb/hr as compared with 319 klb/hr for the air-fired case-1, and 309 klb/hr for the O2-fired (cryogenic ASU) case-6. The corresponding flue gas flow increased to 3497 klb/hr, nearly approaching the air-fired flow of 3552 klb/hr. The boiler O2 concentration is 31%v, which is nearly the same as case-6. Because of increased flue gas flow created by greater coal-firing, more heat is carried to the boiler HRA in case-11 than in case-6. As result, distribution of heat 49 duty shifts: the heat duty of the division wall reduces from 501 MMBtu/hr in case6 to 396 MMBtu/hr in case-11, while the sum of the primary superheater and upper economizer duties increases from 131 MMBtu/hr in case-6 to 411 MMBtu/hr in case-11. Consequently, the inlet furnace feedwater temperature increases from 597ºF in case-6 to 666ºF in case-11. The total furnace duty for case-11 increases because of the 974 MMBtu/hr air heater duty, although the heat to waterwalls is reduced from 2042 to 1583 MMBtu/hr. Because more low-grade heat is released from the gas turbine (GT) exhaust and from boiler, all low-pressure feedwater heaters are shut off. The low-pressure feedwater heating is provided in parallel by the GT economizer and a HRA flue gas exhaust economizer (in parallel to flue gas heat recuperator), as well as by part of the compressor inter-stage coolers. The OITM O2-PC incorporates the recycling of vent gas from the CO2 compression system back to the OITM. The high-pressure vent gas from the CO2 plant is heated with GT exhaust gas before it is expanded for power recovery. After the expansion to the OITM operation pressure, the O2-rich vent gas is mixed with compressed air and sent to the OITM. Consequently, the compressor air flow and power is reduced. The emission control equipment treats the vent gas prior to the OITM requiring smaller equipment sizes due to the high pressure of the vent gas. The replacement of the cryogenic ASU with the OITM greatly reduces the efficiency loss penalty. This is caused by lower equivalent ASU power, better system integration, increased power from the OITM GT, and more low-grade heat recovery from cooling. As shown in Table 4.2.1 the OITM reduces the efficiency drop by 52% and the CO2 removal power penalty by 61%. Table 4.2.1 – Comparison of O2PC with Cryogenic and OITM ASU Air-fired ASU Main steam flow, klb/hr 2950 Coal flow, klb/hr 319 Net power, MW 430 Net efficiency, % 39.5 ASU Power, MW 0 CO2 Compression Power, MW 0 CO2 removal flow, klb/hr 0 Efficiency penalty, % points 0 CO2 removal penalty, kWh/klbCO2 0 50 O2-fired O2-fired cryogenic OITM 2950 2950 309.4 377 338 462 31.9 35.8 67.7 -26.7 34.2 41.3 720 874 7.5 3.6 114 45 Figure 4.2.4 - O2-PC with OITM Case: O2-PC-SC-11, ST=4035/1076/1112/2.0"Hg=460 MW 06/15/2005 Temperature (F) Pressure (psi) Mass Flow Rate (Mlb/hr) 1083 1076 4294.0 4035.0 2873 48 PC Boiler 1113 1112 1112 849.0 823.2 823.0 2483 2483 2406 Duty (MMBtu/hr) 2950 19 26 823.0 4035.0 2389 67 LS1 DPHRH 830 1076 MAIN HP2 HP1 PRPB Q=36 1907 1632 FRH 14.7 47 14.7 14.7 3534 3534 3534 G5 G6 1942 658 750 890.0 1305.3 2730 2483 72 3 2878 1534 Q=-50 LP1 540 382 2355 93.8 38.9 8 2355 G8 46 199 G12 545 93.8 93.8 0 0 92 382 545 398 38.9 25 36.9 0 746 60 65 2873 871 445 15 848 798 81 32 639 0 485.0 69 33 4812.0 3534 HR-B 1436 W=1 127 60 14.7 AIR 14.7 0 SLV SORB 3945 782 0 15.3 29.7 68 695 GC H3 GT 3179 W=195 W=-222 -974 POND 14.4 G15 PREC FGD 3534 0 470.0 DENOX 958 12 20.0 695 AAHX 14.3 4199 304 14.1 14.3 3497 3534 3534 G16 G17 LIQ 3497 216 C1 600 ASH 90 90 90 14.8 58.4 231.6 940 923 915 A3 37 14.7 14.7 MILL 220.0 220.0 18 18 C15 C14 319 W=1 233.6 59.4 C5 W=13 940 C7 A1 SA C13 93 C11 56 926.2 C8 W=13 C10 915 Q=-6 923 916.2 75 Q=-308 Q=-1 C2 1774 90 216 14.8 14.8 2374 1150 COL4 Q=0 Q=-61 90 90 D2 17 D4 Q=-115 1 D6 GRH RY1 RY2 Q=0 51 CO2 63 56 3000.0 916.2 897 822 231.6 58.4 183 231.6 Q=-48 90 14.9 D1 90 COL3 D3 PIPEL 7 D5 COAL W=1 W=-0 Q=3 TSA COMP3 308 W=13 COMP4 18 RH C12 DEM 308 309 SEP1 14.9 2273 700 896.2 56 COMP2 COL2 SPA AIRB 1224 56 916.2 18 916.2 15.4 SAFAN 16.7 377 393 231.6 1774 0 60 393 C9 90 2273 90 15.1 BYP 225 216 60 C6 C4 916 PA 600 C3 COMP1 COL1 16.7 A5 Q=0 H4 Q=-0 90 14.1 PAFAN 3179 Q=974 14.9 304 600 625 14.7 3179 HX 784 15.1 16.9 A2 14.7 A4 200 191.6 GBY 319 977 Q=-468 H1 319 243 Q=-367 1774 16.6 3963 1652 O2 15.1 G21 625 A6 3945 OTM RECY 15.3 231 199.6 H2 FGD W=0 G19 214.6 16.0 2090 705 A0 1652 0 SPF G18 W=4 L1 743 1652 3497 IDFAN ESP 14.7 3534 SLV 0 0 15.1 304 0 G20 319 14.7 14.7 319 15.1 60 100 127 EQ RGIBBS HR-A L2 QOTM 400 RSTOIC ASU/OTM 60 0 14.7 STK1 Q=161 100 2730 53 CP Q=152 41 G2 14.7 NOZ 2394 50 BYFW 0 3535 1.0 14.7 470.0 0 102 Q=465 WETECO 958 7 Q=0 102 W=17 4847.0 34 102 Q=0 Q=0 Q=0 1436 100 567 2730 FWH1 500.0 2873 SPQ 35 4795.0 Q=-2251 0 16 52 270 LECO 666 0 FWH2 450.0 86 BFP1 64 2730 Q=-2557 1 485.0 61 4864.0 612 COND 14 500.0 419 DEA 2873 Q=-0 958 G14 70 0 FWH3 71 430 567 846 1 3.7 639 15.2 485.0 73 342.6 80 500.0 14.5 1 3.7 641 66 FLAME 20 V1 376 639 0 0 FWH4 93 102 FWV 14.7 0 V2 36.9 639 87 Q=232 Q=162 2873 1943 141 DAMP NH3 15.2 0 863.3 74 445 16 SP1 15.8 398 545 93.8 94 485.0 0 455 4929.0 14.6 G13 34 2873 FWH7 568 848 14.7 9 644 10.0 77 V3 Q=0 342.6 4979.0 83 14.6 1449 V4 VD 445 144 Q=205 E1 376 78 527 863.3 519 199 FWH8 4847.0 Q=344 HEATER 234 59 0 95 4954.0 14.7 3534 BOILER SSR FSPLIT 18 1266.2 63 567 G11 5 0 0 34 V6 V7 SPRAY Q 57 579 UECO 2185 56 10.0 3.9 AUX W=-18 89 1943 RHB 24 2730 644 152 76 247 199 2483 4690.0 11 1266.2 2730 40 17 654 14.6 Q=-36 857.0 Q=292 21 4535.0 45 1199 PW EL4 93.8 194.8 353.2 890.0 529 219 EL3 6 658 1305.3 1.0 2169 713 871 750 1449 4525.0 882 EL2 SL3 SL2 657 879 102 2169 EI3 2483 Q=206 30 2169 108 96 1614 854 29 3.9 1.2 219 877.0 23 LP4 152 2169 LS4 14.7 G1 WEG MULT LP3 234 15.8 93.8 EI2 EI1 EH2 PSH 2873 28 545 DPCRH 1943 SPG Q=321 E2 WE LP2 194.8 14.7 G10 G9 QB IP3 2389 SL6 Q=-42 810 5 2679 EH1 G4 3776 Power(MW) 713 6 SC1 3534 Q=396 IP2 871 353.2 22 G7 DIVW Q=1149 W W IP1 653 890.0 SC4 Q=-21 14.7 835 4620.0 44 1614 SC23 FSH G3 Duty (MMBtu/hr) 88 84 43 Q=135 EVAP Q 17 2730 ROOF 970 4470.0 42 502 823.0 SL5 2878 27 4655.0 2873 Power(MW) 1112 1112 CPUMP W=3 4.2.2.3 OITM Parametric Studies Several OITM parametric cases were run as described in the following sections. The results are summarized in Table 4.2.2. Table 4.2.2 – Parametric Case Summary case Air separation method Waste heat economizer HRA Arrangement CO2 Condensation Vent Gas Recycle Coal flow Natural Gas Flow Oxidant flow Air flow O2 purity 01 06 09 10 11 12 13 14 15 16 17 18 19 None Cryo Cryo Cryo OITM OITM OITM OITM OITM OITM OITM OITM CAR no no yes yes yes yes yes yes yes yes yes yes yes parallel parallel parallel parallel parallel parallel parallel parallel parallel parallel parallel parallel series yes yes yes yes yes yes yes yes yes yes yes yes no no no yes yes yes yes yes yes yes yes no klb/hr 319.0 309.4 308.0 308.0 377.7 376.0 403.8 377.7 377.7 377.7 389.4 375.4 307.7 klb/hr 4.0 klb/hr 3270 645 644 644 784 780 838 784 784 784 808 781 1849 klb/hr 3270 2790 2784 2784 3945 3685 4945 4284 3810 3875 4067 3930 3165 % 99.5 99.5 99.5 100 100 100 100 100 100 100 100 43.2 klb/hr 0 1751 1166 1166 2374 2356 2523 2374 2374 2374 2392 1525 1190 Recycle gas flow % 0.0 65.5 55.9 55.9 67.9 67.8 67.8 67.9 67.9 67.9 67.4 57.7 56.0 Recycle gas temperature F 146 260 260 216 217 223 214 217 216 220 249 150 Boiler Inlet O2 %, v 20.7 33.8 41.1 41.1 31 31.1 31.1 31 31 31 31.4 39.3 41.8 Boiler Outlet O2 %, v 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 MM cf/hr 179 96 77 77 139 138 150 139 139 139 142 100 81 Boiler outlet flue gas flow klb/hr 3555 2675 2087 2087 3497 3474 3723 3497 3497 3497 3550 2644 2126 Adiabatic Temperature F 3685 4321 5104 5104 4196 4202 4208 4196 4196 4196 4243 5120 5120 Equilibrium Temperature F 3552 3830 4161 4161 3770 3773 3775 3770 3771 3771 3792 4169 4155 Gas Temp. to FSH F 2185 2185 2185 2185 2185 2185 2185 2185 2185 2185 2185 2185 2450 Water temp. to evap. F 638 597 596 596 666 664 690 666 666 666 672 599 591 UBC % 1.00 0.30 0.16 0.16 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.16 0.15 Boiler Efficiency % 88.16 90.90 91.31 91.31 Pipeline pressure psia 0 3000 3000 2000 3000 3000 3000 3000 3000 3000 3000 3000 3000 Generated CO2 flow klb/hr 739 720 718 718 874 869 934 874 874 874 900 866 729 CO2 purity %,v wet 14.0 77.5 71.3 74.2 75 74.9 74.9 75 75 75 74.8 70.8 76.5 Removed CO2 flow klb/hr 0 720 718 718 874 869 934 874 874 874 900 866 729 CO2 removal efficiency % 0 100 100 100 100 100 100 100 100 100 100 100 100 CO2 purity % 93.7 93.6 93.6 96.9 96.9 96.9 96.9 96.9 96.9 96.9 96.9 94.2 Gross Power MW 476.2 476.2 486.4 486.4 519.7 515.8 520.3 519.3 520.0 519.8 521.8 519.5 488.7 Auxiliary Power MW 46.0 36.6 38.1 38.1 43.0 42.8 44.0 43.1 43.0 43.0 43.4 41.6 42.5 ASU power MW 0.0 67.7 67.6 67.6 -26.7 -22.0 -42.2 -24.3 -27.3 -27.1 -35.9 -26.6 32.0 CO2 compression power MW 0.0 34.2 34.2 32.9 41.3 41.1 44.1 41.3 41.4 41.4 42.6 41.2 34.3 Net Power MW 430.2 337.7 346.6 347.9 462.1 453.9 474.4 459.2 462.9 462.5 471.7 463.3 379.9 Net Efficiency % 39.46 31.94 32.93 33.05 35.80 35.33 34.38 35.58 35.87 35.83 35.45 36.11 35.19 Efficiency Drop % pts. 7.5 6.5 6.4 3.7 4.1 5.1 3.9 3.6 3.6 4.0 3.3 4.3 CO2 removal energy kWh/klbCO2 114 99 97 46 52 59 48 45 45 49 42 64 52 4.2.2.3.1 Effect of O2 Recovery Efficiency (case 11 to 13) As described in Section 4.2.2.1, shifting more duty to the GT will increase system efficiency. Increasing OITM O2 recovery efficiency reduces the required air flow rate and decreases the GT mass flow and power generated. In Case-12 the O2 recovery is increased from 85% to 90.5%. As a result of high O2 recovery, less air is required to be fed to the system, and so less power is generated in the GT. This leads to a reduction of system efficiency from 35.8% to 35.3%. In Case-11 and Case-12 the low-grade heat released from GT exhaust, flue gas cooling before CO2 compression, and CO2 compressor inter-stage cooling is recovered to heat the low-pressure feedwater. In Case-13, when the O2 recovery is reduced from 85% to 73%, more air has to be fed to OITM (4945 vs. 3945 klb/hr) and so more heat is required by the OITM. The system fires more coal (404 vs. 378 klb/hr) and as result, the system generates more low-grade heat than can be recovered, which results in an increase of GT exhaust temperature from 200ºF to 330ºF. This reduces the system efficiency even with increased extra power from the GT. It is clear that the two opposing effects, more GT power and more low grade heat from increased air flow, form a system with an optimum performance for a given air side pressure as shown by Figure 4.2.5, where the system efficiency is maximum when the O2 recovery is approximately 85%. Note that recovering additional low-grade heat as through the use of a high-pressure economizer will shift the optimum O2 recovery efficiency. As more of the low grade heat is recovered by the use of more complex heat integration schemes or by cogeneration heat export, then the optimum O2 recovery efficiency is reduced and the maximum system efficiency is increased. Such a reduction in O2 recovery efficiency reduces the size of the OITM because of increased logarithm mean pressure difference (LMPD). Table 4.2.3 shows a comparison of different cases under the same airside pressure, including a case published by Alstom [7]. It is obvious that the higher is the O2 recovery efficiency, the lower is the LMPD, and the larger is the OITM size. 53 Figure 4.2.5 – Effect of OITM O2 Recovery Efficiency on Efficiency Efficiency, % 36.0 35.5 35.0 34.5 34.0 70 75 80 85 90 95 O2 recovery, % Table 4.2.3 - Effect of OITM O2 Recovery Efficiency on LMPD Ca s e O2 r e c o v e r y , % O2 t o b o i l e r , % L MPD Al s t o m 85 70 14. 7 Ca s e - 1 1 85 31 16. 5 54 Ca s e - 1 2 90 31 13. 9 Ca s e - 1 3 73 31 20. 9 4.2.2.3.2 Effect of LMPD Across the Membrane (cases 14-16) The performance of the OITM relies on the O2 partial pressure difference across the OITM membrane. Similar to the LMTD used in a heat transfer process, a LMPD is a key design parameter for a mass transfer process. The LMPD can be used to compare the design size of different options. An increase in the O2 level to the boiler increases the sweep gas outlet O2 partial pressure resulting in a reduced LMPD as shown in Table 4.2.3 (compare Alstom to case-11). Similarly an increase in sweep gas total pressure reduces the LMPD as shown in Figure 4.2.6. The effect is fairly small because of the limited operating pressure variation of the sweep gas. LMPD, psia Figure 4.2.6 – Effect of Sweep Gas Pressure on LMPD 20 18 16 14 12 10 8 6 4 2 0 0 5 10 15 20 25 Sweep gas pressure, psia 30 The air side pressure directly affects the OITM performance. Increasing the air side pressure (OITM operating pressure) will: (1) Increase LMPD, and so reduce OITM size (2) Increase compressor discharge temperature (CDT), and require less heat from the boiler (3) Reduce turbine exhaust temperature (TET), and so release less low grade heat and reduce the optimum O2 recovery efficiency (4) Increase equipment thickness 55 In Case-14 the OITM operating pressure is raised from 200 psia to 250 psia with constant coal feed rate and furnace air heater duty. This 250 psia OITM pressure requires the compressor discharge pressure to be increased from 214 to 265 psia, which raises the compressor discharge temperature. Thus, for the same operating temperature the OITM needs less heat per unit mass of air, and so the air to the OITM is increased to balance the heat released from the boiler. Because the amount of the O2 required is fixed, the O2 recovery is adjusted for the increased air flow through the OITM. Figure 4.2.7 shows that raising the air side pressure from 200 psia to 250 psia results in a small reduction in system efficiency (from 35.8 to 35.6%) and an attendant small increase in the CO2 removal specific power penalty (from 46 to 48 kWh/klbCO2). The system efficiency decreases with increased OITM pressure because of less heat being carried to the OITM per unit air. However, due to the increased air flow to the OITM, the LMPD is increased from 16.5 to 24.9 psia, which results in a decrease in OITM size of 34%. Opposite to the case-14, cases 15 and 16 were run with reduced OITM pressures of 180 psia and 190 psia, respectively. As shown in Figure 4.2.7, lower OITM operating pressure (for a given operation temperature) increases system efficiency because more heat is transferred from the boiler to the OITM cycle per unit mass of air. However, as the OTM pressure is reduced the LMPD decreases requiring a larger OITM size. In this scenario, the oxygen recovery is adjusted to changes on the airside pressure, which results in an indirect relationship between system efficiency and the O2 recovery as shown in Figure 4.2.8. Figure 4.2.8 presents a linear correlation for which each percent change in O2 recovery causes a 0.03 percent point change in efficiency. Figure 4.2.9 shows the effect of OITM pressure on LMPD when the O2 recovery efficiency is constant and O2 flow rate is variable (as in Figure 4.2.7). This is compared in Figure 4.2.9 with the effect of OITM on LMPD when the O2 flow rate is constant and the O2 recovery efficiency is variable (as in Figure 4.2.7). The selection of the OITM operating pressure is a trade-off between the cost of OITM and the system efficiency. If the OITM cost is not too high in future commercial application, the optimum OITM operating pressure will be relatively low. Furthermore, a higher OITM operation temperature will be better for the system efficiency. However, the magnitude of this temperature is constrained by material limitations. 56 Figure 4.2.7 – Effect of OITM Pressure on System Efficiency and LMPD: Variable O2 Recovery 38 30 eff, % 20 36 Eff 15 35 10 34 LMPD, psia 25 LMPD 37 5 33 100 150 200 0 300 250 OTM pressure, psia Figure 4.2.8 – Effect of O2 Recovery on System Efficiency efficiency, % 35.9 35.8 35.7 35.6 35.5 76 78 80 82 84 O2 recovery, % 57 86 88 90 LMPD, psia Figure 4.2.9 – Effect of OITM Pressure on System Efficiency and LMPD: Constant and Variable O2 Recovery 35 30 25 20 15 10 5 0 100 150 200 250 300 air pressure, psia 350 400 O2 recovery constant, O2 flow variable O2 recovery variable, O2 flow constant 4.2.2.3.3 Effect Of Compressor Discharge Temperature (case 17) Another way to boost the system efficiency is to transfer more heat to the gas turbine by increasing the temperature difference between the compressor discharge temperature (CDT) and the turbine inlet temperature (TIT). Increasing the TIT results in an increase in OITM operating temperature, which may be restricted due to material limitations. Without increasing the pressure, the increase of TIT will increase turbine exhaust temperature, which results in more low-grade heat that can be recovered in the HRSG. Another approach is to reduce CDT by the use of a compressor with inter-stage cooling. This will reduce compressor power, and let more heat be transferred from the boiler to the turbine, but it releases more low-grade heat from inter-stage cooling. If this heat cannot be recovered, system efficiency would be reduced. As discussed before, for the present configuration and integration, there was no margin to recover more low-grade heat. Therefore the inter-stage cooler will be applicable only for co-generation of heat and power, where low-grade heat could be recovered by low-pressure steam export. Case-17 employs an alternative method to reduce compressor power by interstage water quench to avoid the need for low-grade heat recovery. This quench (20 klb/hr of water) reduced the CDT from 743 to 698ºF, and therefore more heat flowed from the boiler to the gas turbine. As a result, the coal to boiler increased from 377.7 to 389.4 klb/hr, and the corresponding air to the OITM increased from 3945 to 4067 klb/hr (for the same OITM O2 recovery efficiency). The power from 58 the GT increased from 26.7 to 35.9 MWe, and the net power increased from 462 to 472 MWe. However, the system net efficiency was reduced from 35.80 to 35.45%, and the corresponding net penalty for CO2 removal increased from 46 to 49 kWh/klbCO2 because of efficiency loss. The great benefit from this option was the 10 MWe net power gain. Note also that the furnace air heat duty increased from 974 to 1060 MMBtu/hr. 4.2.2.3.4 Effect of Furnace Flame Temperature (case 18) Increased furnace flame temperature increases heat transfer, especially for radiant transfer, and so it will reduce the furnace size for both for the waterwalls and air heater. Similar to the effect of excess air in the boiler, higher flame temperature slightly increases system efficiency because of less flue gas flow out of the system. Higher flame temperature cases have been evaluated for the cryogenic ASU O2PC, as reported in Section 4.1.4.3. For the cryogenic ASU O2-PC raising the equilibrium temperature from 3830ºF (case 6) to 4182ºF (case 7) increased system efficiency about 0.15% in point, and reduced specific power penalty for CO2 removal from 114 to 112 kWh/klbCO2 as shown in Table 4.2.4. Case 18 (Figure 4.2.10) was generated from case 11 by raising the equilibrium temperature to nearly the same equilibrium temperature as case 7. Table 4.2.4 shows that for the OITM ASU O2-PC raising the equilibrium temperature to 4169ºF increases system efficiency by about 0.3% in point, and reduces the CO2 removal specific power penalty from 46 to 42 kWh/klbCO2. It is clear that increased flame temperature can reduce equipment size and slightly improve system efficiency, but could be limited by material cost in the furnace. Table 4.2.4 – Effect of Flame Temperature on Performance Case 6 4321 3830 146 31.94 114 Adiabatic Flame T, F Equilibrium flame T, F Recycle flue gas T, F system eff, % kWh/klbCO2 59 7 5178 4182 163 32.07 112 11 4196 3770 216 35.80 46 18 5120 4169 249 36.11 42 Figure 4.2.10 - O2-PC with OITM with 58% Recycle Flow Case: O2-PC-SC-18, ST=4035/1076/1112/2.0"Hg=460 MW 06/19/2006 P ressur e ( p si) 1083 Mass Flo w Rate (Mlb/h r ) 1076 4344.0 4035.0 2873 1113 1112 1112 849.0 823.2 823.0 2483 48 PC Boiler 2483 2950 2406 MAIN DPHRH 19 2878 27 HP2 HP1 Q=135 925 47 1831 2873 1472 PRPB Q=36 14.7 2873 43 14.7 FRH 2681 2681 G5 G6 14.7 835 658 750 4655.0 890.0 1305.3 2730 2483 72 14.7 751 23 836 G8 SL2 Q=296 830 G12 199 Q=344 519 199 4954.0 56 35 219 EL3 654 EL4 40 644 17 93.8 152 10.0 3.9 5 57 0 SSR 60 445 445 4979.0 2873 92 545 545 382 398 93.8 93.8 38.9 36.9 0 0 0 0 25 234 376 644 15.2 10.0 15.8 59 20 0 0 4929.0 14.6 G13 32 Q=162 0 20 639 641 0 485.0 69 0 70 0 376 639 15.2 485.0 0 FWH3 3.7 71 1 0 Q=-2250 FWH2 73 COND 14 FWH1 61 102 16 418 2873 450.0 DEA Q=0 Q=0 Q=0 7 Q=0 102 1436 Q=-0 1.0 1436 HR-B 2393 66 FWV BOILER DAMP HEA TER G14 592 14.5 4864.0 4812.0 2681 2873 2730 34 Q=82 G2 0 68 G15 AAHX 14.3 5120 321 321 14.1 14.3 2644 2681 2681 G16 G17 726 14.7 2682 FLAME IDFAN NOZ Q=-272 RSTOIC 249 337 A2 A5 A3 60 C1 ASH 249 14.7 0 925 920 W=1 A1 BYP 936 FGD RECY COL1 925 393 220.0 220.0 912 18 19 C15 C14 59.4 W=13 1718 C5 Q=-287 W=13 936 233.6 C7 C12 C13 Q=3 COMP3 309 W=13 C10 912 920 56 916.2 Q=-6 78 63 Q=-1 925 C2 249 90 14.8 Q=0 14.8 1525 600 90 Q=-60 90 14.9 D1 182 Q=-48 17 231.6 90 D4 1 COL4 56 D6 916.2 Q=-114 894 D3 PIPEL 6 D5 COAL W=1 Q=0 GRH RY2 RY1 60 3000.0 816 231.6 58.4 D2 90 COL3 W=-0 TSA 308 C11 926.2 C8 COMP4 RH DEM COMP2 310 SEP1 19 56 96 913 14.9 700 896.2 916.2 231.6 1718 56 916.2 19 90 C6 C3 COL2 SA H4 393 231.6 15.4 SPA AIRB 58.4 90 15.1 258 60 14.7 SAFAN MILL 337 37 3167 H1 90 90 14.8 COMP1 PA 600 16.7 375 GBY 14.1 16.7 Q=0 1536 321 600 PAFAN 14.7 3167 Q=970 90 14.9 2644 15.1 600 200 Q=-466 191.6 HX 781 90 15.1 16.9 14.7 625 A4 H2 O2 337 975 1652 Q=0 278 925 16.6 A6 3948 16.0 SPF W=3 15.3 236 OTM 3930 W=0 G21 625 199.6 1652 0 LIQ G18 2681 A0 14.7 0 15.1 HR-A 1652 SLV 0 3167 W=-221 ASU/OTM 214.6 100 2644 ESP 14.7 G1 G20 337 12 695 0 782 15.3 H3 GT W=194 L2 14.7 337 20.0 NH3 3930 743 957 60 SP1 AIR 0 GC 15.1 E1 14.7 14.7 SORB 130 EQ RGI BBS W=1 POND PREC FGD QOTM 470.0 DENOX 60 0 100 -970 400 2681 0 53 BYFW 60 0 14.4 14.7 CP 29.7 2730 695 41 4169 STK1 Q=161 4847.0 2730 50 52 14.7 130 14.7 957 567 35 WETECO 470.0 SPQ 604 4795.0 Q=463 100 270 LECO Q=-2931 W=17 64 567 801 0 102 500.0 86 BFP1 36.9 500.0 500.0 957 485.0 FWH4 342.6 80 102 0 93 430 Q=232 2873 751 639 94 1 V1 V2 398 93.8 87 863.3 74 445 161 485.0 455 83 727 14.7 35 15 568 81 639 77 V3 545 Q=0 342.6 2873 144 748 14.6 1 579 78 V4 871 FWH7 Q=41 1769 9 FSPLI T 0 VD 527 863.3 65 FWH8 829 QB EL2 95 V6 746 567 G11 1.0 2168 1.2 AUX 18 1266.2 63 4847.0 Q 102 2168 W=-18 89 751 2185 Q=1508 93.8 30 108 3.7 V7 14.7 2168 76 247 199 SPRAY 2681 3.9 6 890.0 11 1266.2 2730 29 EG M ULT LP4 152 2168 SL3 658 529 1305.3 UECO 24 G3 28 219 713 RHB EVAP EI1 38.9 545 2354 EI2 194.8 2483 46 2730 8 871 21 W LP3 234 15.8 14.6 Q=-36 4690.0 42 93.8 2354 353.2 4620.0 45 934 PW 6 2483 750 1769 882 857.0 2389 877.0 855 Q=103 WE LP2 382 96 1454 4610.0 P ow er ( MW ) W EI3 657 PSH 2873 2679 SL6 G9 Q=366 W LS4 SPG 14.7 Du ty ( MMBtu/h r) LP1 540 DPCRH SC1 Q=-32 IP3 713 194.8 EH2 14.7 G10 G4 Q=321 3 2878 IP2 871 353.2 22 1374 Q=-19 G7 IP1 653 890.0 EH1 SC4 2681 Q=-16 2681 DIVW 44 SC23 1866 FSH 1454 88 84 970 Q SL5 ROOF 4520.0 502 P ow er ( MW ) 17 2389 4035.0 67 823.0 823.0 1076 Du ty ( MMBtu/h r) 1112 1112 LS1 26 4555.0 Tem per atu r e ( F ) CPUMP W=3 4.2.3 O2-Fired PC Integrated with CAR 4.2.3.1 Overview The ceramic auto-thermal recovery (CAR) process [5, 6] is based on sorption and storage of oxygen in a fixed bed containing ionic and electronic conductor materials operated at high temperature and increased pressure. The stored oxygen is then released by pressure reduction using sweeping gas, such as recycled flue gas, or steam extracted from low-pressure section of steam turbine as shown in Figure 4.2.11. The continuous operation is obtained by employing multiple beds in a cyclic way, which is similar to the Pressure Swing Absorption (PSA) process. A large vessel is provided to provide a five second buffer time to smooth out any fluctuations in either flow and/or composition caused by a batch adsorption-desorption operation cycle. An important feature of the CAR process is in that it can be tailored to produce low-pressure oxygen at the concentration required for O2-fired combustion by using recycled cleaned flue gas as a sweep gas. The CAR process is based on conventional sorbent bed adsorption that is easy to fabricate and readily available. The scaling up for such a process is similar to the PSA process, and has fewer challenges than the OITM technology. Figure 4.2.11 - CAR Process Schematic steam/CO 2 N2 regenerator layer perows kite pellets lay er regenerator layer air s team /C O 2 and O 2 In general during adsorption, heat is released and system temperature is raised. The CAR adsorption process has to be operated at high temperature, therefore the air is preheated to a certain temperature before being fed to the adsorption bed. The heat generated during adsorption can be recuperated to heat up the 61 fresh air to reduce heat loading. For this purpose, a recuperator is employed to transfer heat between exhaust oxygen depleted air and the fresh air, where the heat generation during adsorption raises the exhaust air temperature. As result, the fresh air needs less preheating (i.e. 1020ºF) for the CAR process, compared to 1650ºF for the OITM process. On the other hand, the desorption process is associated with heat absorption, where heat has to be transferred to the bed during oxygen release. This is done by direct injection of natural gas into bed to combust with oxygen and by pre-stored heat in the sorbent bed during adsorption. The CAR process is so designed that it also stores the energy in the bed during the heat release in the adsorption cycle and releases this heat during the stripping cycle, by means of installation of inert layers on both ends of sorbent bed for heat storage. In this so called “auto-thermal recovery”, more heat is stored in bed, less heat is carried out by oxygen-depleted air, and less heat is required from fuel combustion to strip oxygen. High oxygen concentration can be obtained by steam striping providing that the steam is condensed out downstream. Oxygen concentration is limited to about 30-40% if the flue gas is applied as a sweep gas. As reported in the BOC study [5] with steam as sweeping gas, the air-to-steam molar ratio is about 2.66 with O2 recovery over 90%, which leads to an oxygen concentration in the sweeping gas of about 33-36%v before steam condensing. Simulated integration of the CAR process to the O2-PC has been reported by BOC to determine the technical and economical feasibility [5]. The air-fired reference plant is an existing ultra-supercritical lignite-fired 865 MWe Lippendorf power plant near Leipzig, Germany. A simulation of an oxyfuel power plant with cryogenic air separation was employed for comparison. The same plant was then applied for integration study with CAR process, where low-pressure steam extracted from steam turbine was applied as a sweep gas. Table 4.2.5 summarizes the key results. Table 4.2.5 - Comparison for CAR with Cryogenic ASU Case Net Power, MWe Net efficiency, %(LHV) Efficiency drop, % point Air 865 42.6 - ASU 687 33.3 9.3 CAR 726 34.0 8.6 Comparing the CAR to the cryogenic process, the efficiency drop reduced from 9.3 to 8.6% points, and the net power increased from 687 to 726 MWe. As reported, it is clear from the results of study that the steam consumption is a critical variable for this option. The steam extraction required for oxygen stripping is about 200 kg/s in comparison with the main steam flow as 692 kg/s. The reason recycled flue gas was not used as sweep gas was that the flue gas has to be cleaned up to avoid any contaminates to the sorbent bed, and the 62 effects of contaminates have not yet been studied in detail. In general, to be economic, recycle gas clean up should be avoided because the clean gas will be sent back to boiler, where it mixes with combustion gases to become dirty gas again. Optimally, the gas clean up process should be applied to the flue gas exiting from system and flowing to the CO2 plant. Moreover, this stream has much less flow to be treated than does the recycled flue gas. Since the CAR process is based on swings in the partial pressure of oxygen, it will be affected by pressure, and LMPD (logarithmic mean pressure difference). Increased adsorption pressure will enhance oxygen adsorption from air, and a low desorption pressure will favor adsorbed oxygen release. However too high a pressure will require more power for air compression. If steam is used as a sweep gas, heat carried by the sweep gas can be recovered through feedwater heating during steam cooling and condensing. If flue gas is used as a sweep gas, hot sweep gas can be directly fed to boiler. In order to explore the advantage of integration with CAR process for O2-fired combustion, an Aspen simulation has been made for the CAR process operated with recycled flue gas sweep gas. The difference in principle between steam and flue gas sweep gases is their pressure ratios, where steam extracted at 1.6 bar could continuously expand to a pressure as low as 0.038 bar to generate more power with a pressure ratio of 1.6/0.038, while the flue gas has to be compressed from about 1.0 bar to 1.6 bar to consume power with pressure ratio as 1.6/1.0. Thus, the substitution of flue gas by extracted steam reduces power because the low pressure ratio of the flue gas is replaced by the high pressure ratio of steam for the same amount of gas volumetric flow. The reduced power can be calculated by difference between power from steam expansion and power for recycle gas compression, without including the changes in auxiliary power and low grade heat integration. The net result is shown by Table 4.2.6. Table 4.2.6 – Comparison for CAR Using Different Sweep Gases Oxidant Air Separation Method Sweep Gas Net Power, MWe Net Efficiency, % (LHV) Efficiency Drop, % point Air 865 42.6 - Cryo 687 33.3 9.3 O2 CAR steam 726 34.0 8.6 CAR flue gas 767 35.9 6.7 As can be seen in Table 4.2.6, the system efficiency increases about 1.9% points when steam is replaced by recycled flue gas as the sweep gas. As compared with the cryogenic ASU, the CAR process with gas recycle sweep gas has an increased system efficiency of 2.6% in points, which is close to 3.2% points achieved by the OITM. It is obvious from the standpoint of system efficiency that the future of the CAR process is to use recycle flue gas as a sweep gas. 63 Note that in the CAR process, natural gas is fired to provide a portion of the heat for stripping out the adsorbed oxygen from sorbent bed, which is similar to the gas absorption-regeneration cycle. Because of auto-thermal recovery process, the ratio of energy input from the natural gas to coal is only about 3.2%, which is much less than the heat requirement by the OITM process. 4.2.3.2 Optimized Integration of CAR in O2-PC Advanced oxygen separation CAR process has been integrated into the oxygen fired PC as shown in the Figure 4.2.12 schematic. A multi-bed adsorptiondesorption batch operation cycle is simulated by a quasi-continuous operation of moving bed system, where the oxygen sorbent is circulated between two beds. The Aspen model of the O2-PC CAR power plant is presented in Figure 4.2.13. Flue gas, instead of steam extracted from steam turbine, is used as a sweep gas to strip out oxygen from desorption bed. Note that flue gas contains many contaminants such as fly ash, SOx, NOx, etc. that may be harmful to the perovskite sorbents used in the CAR process and future experimental studies will be required to quantify this effect. The flue gas from the boiler transfers heat to the oxygenated flue gas in an air-toair heat exchanger and then is further cooled down to 150ºF by feedwater economizers. After cooling, the flue gas is boosted to a pressure to overcome the pressure drop across the CAR oxygen desorption equipment. Exit gas from desorption bed, containing about 25-45% of oxygen, is then cooled down to 280ºF through the sweep gas recuperator. This oxygen containing flue gas is then sent to air-to-air heat exchanger to be heated up to 625ºF, and then fed to boiler. Air is compressed to a pressure of 30 psia and then fed to the adsorption bed after pre-heating in the air recuperator. About 90% of O2 in the air is adsorbed by solids in the bed. The heat released from adsorption increases the system temperature. Adsorption bed exit gas or vitiated air is cooled down to 280ºF in the air recuperator before being discharged to the stack. The solids circulated between two the moving beds adsorb and release oxygen nearly reversibly. The system net efficiency for the CAR integrated with the O2-PC power plant is 35.2%. Heat input from natural gas is about 2.7% of the total heat input. Table 4.2.7 lists a comparison among different air separation technologies in efficiency drop and CO2 energy removal penalty. OITM has less energy penalty than CAR due to the process gain associated with the gas turbine expander (see 4.2.2.1). Table 4.2.7 – O2 PC Efficiency with Different O2 Separation Techniques Air separation method Efficiency Drop % pts. CO2 removal energy kWh/klbCO2 64 Cryo 6.5 99 OITM 3.3 42 CAR 4.3 64 Figure 4.2.12 – Integration of CAR Process into O2-PC 65 Figure 4.2.13 - O2-PC with CAR Case: O2-PC-SC-19, 07/19/2006 1083 48 4822.0 832 147 4647.0 Mass Flow Rate (Mlb/hr) 4035.0 2950 569 1113 1112 1112 849.0 823.2 823.0 2406 2406 2406 19 27 Duty (MMBtu/hr) 2950 1112 LS1 67 SL5 2878 HP2 HP1 974 43 4462.0 Q=134 2022 1559 1508 14.7 14.7 2156 2156 2156 G5 G6 14.7 FRH 837 PRPB Q=36 4612.0 44 658 750 890.0 1305.3 2406 2156 IP3 2389 SL6 22 LP1 382 2301 38.9 8 545 2190 B2 G11 532 21 657 EI2 EI1 219 1893 EL2 199 QB 871 713 353.2 194.8 18 56 88 2156 92 545 268 382 93.8 38.9 36.9 62 62 49 111 199 65 4929.0 522 4954.0 181.2 342.6 386 610 4979.0 66 15 FWH6 94 569 569 4822.0 68 695 60 14.5 20.0 86 17.5 1115 29.7 AIR 14.7 SORB 97 2156 0 G36 A8 1022 30.0 29.0 3165 3165 HX A1 123 98 14.7 14.7 SLV 290 15.1 15.1 2126 1284 COOL G19 G23 90 90 1190 14.9 110 W=7 C6 290 ESP 14.4 2156 Q=0 918.5 918.5 0 0 90 303 90 15.1 14.9 842 842 C11 232.1 94 Q=75 SEP1 W=11 PIPEG DEM COMP2 COMP1 C5 COMP3 310 312 59.5 234.1 W=11 781 4 ASU/CAR 90 770 SPA 2510 232.1 NOZ A4 300.0 PAFAN 772 C3 Q=-1 NG 150 Q=-142 W=2 RSTOIC G24 769 1849 A6 Q=-1 21.5 VA 58.5 G22 781 2157 986 1190 59 280 Q=883 14.9 14.9 G21 G18 DES 22.0 1190 SPF IDFAN AAHX PV3 A2 PV1 150 W=0 2126 14.7 PV4 PV5 0 LIQ 303 SPO SPVA ADS POND L2 G20 14.2 2156 FLAME BYFW 203 W=32 PREC FGD 53 CP Q=170 22.5 23.0 2156 1.0 2229 50 64 W=1 3165 0 303 5120 102 2510 0 COMP 15.1 1115 Q=49 102 1124 1849 60 242 G29 Q=72 14.7 60 0 0 0 1294 102 16 1115 695 14.7 Q=-1897 FWH1 FWH2 61 2950 303 14.4 16.5 1115 14 215 WETECO 14.7 14.7 STK1 254 EQ 16.5 173 70 1115 71 236.6 100 123 206.6 NH3 457 221.6 236.6 W=18 FGD 1115 SPQ DENOX 625 15.2 Q=53 320 156.6 0 625 206.6 FWH3 COND 3.7 111 374 DEA 0 G16 150 146 995 34 SP1 215 V1 214 BFP1 108 33 2802 RGIBBS 77 V2 211 73 Q=66 FWV 2950 14.6 2156 LECO G15 1 112 181.2 35 G2 20 173 62 7 Q=118 Q=311 52 816 14.7 644 10.0 610 BOILER Q=74 9 156 15.2 36.9 1115 FWH4 93 Q=-0 Q=-2088 69 87 342.6 4839.0 G13 15.8 59 78 191.6 62 1115 396 85 74 Q=162 877.0 12 Q=210 5 40 262 258 93.8 110 191.6 16 591 3.9 657 L1 C9 PV2 5 E2 Q=1485 2802 10.0 SSR 234 V3 545 Q=0 316 2950 2950 FWH7 83 2045 4787.0 152 57 W=-18 221 95 425 2950 32 RHA HEATER 25 V4 712 430 863.3 14.6 G12 110 VD V5 527 522 FWH8 1145 2045 40 644 93.8 93.8 80 V6 746 63 Q=138 867.0 EL4 17 FSPLIT 435 863.3 522 1266.2 2950 EVAP 219 EL3 6 323 89 V7 2406 4904.0 41 1.0 1791 3.7 877.0 23 45 Q 102 1831 657 B1 2156 30 108 654 76 890.0 199 361 2156 11 1266.2 877.0 55 PSH 820 3.9 1.2 658 750 14.6 4527.0 152 AUX 569 G1 29 SL3 SL2 Q=106 2802 14.7 MULT LP4 234 15.8 1942 LS4 2406 Q=289 2450 EG EI3 DPCRH 1353 812 W LP3 24 49 E1 28 96 1305.3 4682.0 WE LP2 540 93.8 EH2 RHB 869 863 4155 Power(MW) 857.0 Q=329 G3 W W 93.8 DIVW 2802 Duty (MMBtu/hr) 194.8 2045 SC1 Q=-25 G4 42 Q 713 6 Q=-36 4472.0 2802 IP2 871 353.2 2679 2878 857.0 G8 14.7 1021 3 72 2802 910 SC23 2057 FSH IP1 653 890.0 EH1 47 SPRAY Q=479 88 84 60 81 471 17 2389 4035.0 Power(MW) 823.0 823.0 1076 MAIN DPHRH 26 1112 2802 ROOF 2950 Pressure (psi) 1076 4286.0 PC Boiler Temperature (F) ST=4035/1076/1112/2.0"Hg=460 MW C7 C8 323 COMP4 928.5 W=10 772 C10 769 247 16.4 A5 COL1 G17 290 625 308 14.2 16.5 A3 555 ASH 30 90 Q=-111 280 280 16.5 16.5 1849 1849 MILL ECOW G28 G27 COAL Q=0 90 COL2 60 16.7 Q=0 66 98 Q=-1 C2 C1 862 Q=0 D1 90 Q=-48 14.9 61 COL3 Q=-42 9 90 D4 1 Q=-116 55 3000.0 918.5 769 769 232.1 58.5 D2 COL4 232.1 D3 CPUMP PIPEL 2 D5 CO2 W=3 4.2.4 Comparisons CO2 cannot be captured and sequestrated without incurring an energy penalty because of the potential energy stored in the pressurized liquid CO2. A minimum of 40 kWh/klbCO2 additional auxiliary power is required for CO2 compression. The difference between technologies lies in the difference in power requirements of the different CO2 or O2 separation techniques, and the process gain when advanced power generation is integrated, such as power generation from OITM through hot gas expansion. Table 4.2.8 shows that compared to CAR, the OITM results in higher system efficiency and significantly more in power because of the process gain of the hot compressed air expanding through the gas turbine (gains are in reference to the cryogenic ASU O2-PC). When the OITM technology is integrated with O2-fired combustion, a conventional Rankine cycle power plant is upgraded to a combined cycle power plant. This improvement makes the OITM technology attractive for economic CO2 removal. Table 4.2.8 - Gains from OITM and CAR Compared to Cryogenic ASU Efficiency gain Power gain (% points) (MW) 3.2 117 0.7 20 2.6 50 OITM CAR/steam sweep gas CAR/flue gas sweep gas The OITM faces more technical challenges than does the CAR process because it operates under higher pressure and temperature. In addition to the OITM development itself, the integration and design of the boiler air heater presents a challenge (see Section 4.3.2.2.3). An alternative to the furnace air heater is to provide the air heating by a natural gas duct burner, although the high heat required (the ratio of heat absorbed by OITM to heat input by the coal is 22%) may preclude duct firing. For the CAR process, the heat input from natural gas is only 2.7% to the total energy input. In general, CO2 can be removed by means of: Post-combustion capture - Amine process or other Pre-combustion capture - IGCC Oxygen-combustion – cryogenic ASU, OITM, CAR Table 4.2.9 compares the efficiency drop and specific power requirement of the various CO2 removal technologies. Similar to the O2-PC designs employing 67 cryogenic ASU and OITM, the O2-PC CAR power plant is designed to include liquid CO2 pumping, wet-end heat recovery, increased flame temperature, and hot gas recycle. Table 4.2.9 – Comparison of CO2 Removal Technologies PC Boiler Type Removal Technique Efficiency drop CO2 removal penalty post comb. % ponts kWh/klbCO2 11.6 188 O2 fired cryo. ASU OITM 6.5 3.3 99 42 IGCC pre comb. CAR 4.3 64 From Table 4.2.9, it is clear that the O2-fired PC integrated with advanced oxygen separation technology has significant advantages over both the post combustion and pre-combustion CO2 techniques since the separation of oxygen from air is a physical process and involves less energy than the chemical separation of CO2 from flue gas or syngas. 68 7.2 116 4.3 Furnace and Heat Recovery Area Design and Analysis 4.3.1 Furnace Design and Analysis 4.3.1.1 FW-FIRE Computer Program Description FW-FIRE (Fossil fuel, Water-walled Furnace Integrated Reaction and Emission Simulation) simulates furnace combustion, heat transfer and pollutant formation based on fundamental principles of mass, momentum, and energy conservation [9]. FW-FIRE is an extended and enhanced version of PCGC-3, which was developed over a period of ten years by the Advanced Combustion Engineering Research Center (ACERC), operated jointly by Brigham Young University and the University of Utah. The FW-FIRE computer program incorporates the latest state-of-art coal combustion/gasification, pollutant formation, and physical analysis techniques based on extensive empirical research. The FW-FIRE code performs general three dimensional multiphase gas combustion steady state analysis of reactive fluid flows. The program is fully capable of analyzing gas-fired and coal-fired boilers although FW-FIRE was initially tailored for pulverized coal combustion and gasification. The FW-FIRE program models the gas flow field as a three dimensional (Cartesian or cylindrical) turbulent reacting continuum that is described locally by the Newtonian form of the Navier-Stokes equations coupled with the energy equation and other appropriate constitutive equations. These equations are solved in Eulerian framework to predict gas properties such as pressure, temperature, velocity, and pollutants and other species concentrations. The Reynolds stress terms, which result from Favre-averaging of the conservation equations, are approximated using the Boussinesq assumption and effective eddy viscosity. The value of the eddy viscosity and subsequent closure of the turbulence equations is made using either a linear or non-linear k-ε twoequation model. The effects of turbulence of the flow field on the combustion reactions are included. The turbulent flow field is also coupled with the combustion chemistry. Since gaseous reactions are limited by mixing rates and not reaction kinetics, the process chemistry is calculated using locally instantaneous equilibrium based on the degree of mixing of the species. Rate constants for processes such as devolatilization (two step process) and char oxidation are built-in to the program based on empirical testing. A Lagrangian model of the particle conservation equations is used to predict particle transport by characterizing the particle field as a series of discrete particle trajectories through the gas continuum. Particles interact with the gas 69 field via mass, momentum, and energy exchange. Particle properties such as burnout, velocities, temperatures, and particle component compositions are obtained by integrating the governing equations along the trajectory paths. The program possesses the capability to input a particle size distribution and chemical composition. In a pulverized coal flame, the radiation field is a multi-component, non-uniform, emitting, absorbing, gas-particle system. The coal particles cause anisotropic and multiple scattering, and the flame is surrounded by non-uniform, emitting, reflecting, absorbing surfaces. The radiation field calculations are based on an energy balance on a beam of radiation passing through a volume element containing the absorbing-reflecting-emitting medium. An Eulerian framework using a discrete-ordinates approach is used to model this process. Heat transfer via radiation and convection to waterwall and tube banks is determined by specifying a local wall temperature and emissivity. The set of non-linear differential equations is discretized and combined by a upwind and weighted central-differencing scheme. The resulting gas flow field finite difference equations are solved using variations of the SIMPLE/SIMPER algorithm. FW-FIRE contains a sub-model for the prediction of nitrogen pollutant emissions. This sub-model has the capability of predicting both fuel and thermal NOx formation. Fuel NO formation can proceed directly to N2 and NO (such as in the case of char) or through HCN and NH3 which are oxidized to form NO and reduced to N2 (such as in the case of volatiles). Global reaction rates are based on work by de Soete and Bose. Thermal NO formation is governed by the extended Zel=dovich mechanism. 4.3.1.2 Model Geometry A simulation was made for both the reference air-fired case and for the oxygenfired case. The FW-FIRE model simulates the furnace, in height from the bottom of the hopper to the roof, in depth from the front wall to the rear wall, and in width from the left side wall to the right side wall. Furnace partial division walls are also included in the model. Finer meshes are used to model the burners and over-fire air (OFA) ports. The air-fired model contains 528,840 (117x113x40) nodes and is shown in Figure 4.3.1. The oxygen-fired model contains 484,160 (136x89x40) nodes and is shown in Figure 4.3.2. 70 4.3.2 Boundary Conditions Boundary conditions are based on ASPEN simulations of the power plant [Sect. 4.1 and Sect. 4.2]. The air-fired, oxygen-fired with ASU and oxygen-fired with OITM ASPEN reference cycle diagrams are presented in Figure 4.1.1, Figure 4.1.9, and Figure 4.2.10, respectively The input data required by FW-FIRE include fuel analysis, coal particle size distribution (mass percentage for each size bin), waterwall fluid temperatures, and the velocities, flow rates and temperatures of primary and secondary gas streams. Boundary conditions are detailed in Figure 4.3.3, Figure 4.3.4, and Figure 4.3.5 The waterwalls of the furnace are assumed to be gray and diffusive. The wall temperature at each location is calculated based on the fluid temperature and the heat flux at the wall cell. For coal devolatilization kinetic properties, Ubhayakar rate parameters were employed for bituminous coal. For bituminous char oxidation, Sandia kinetic and burning mode parameters were applied for Illinois #6 coal. The selected quantity of flue gas recycle produces a 600ºF higher equilibrium temperature in O2-firing than air-firing. This may increase the potential for slagging in the furnace depending on the ash fusion characteristics. Consequently, for a dry bottom furnace design a minimum flue gas recycling flow may be required to avoid slagging depending on fuel type. Alternatively a wetbottom or slag type furnace could be used to resolve ash deposition and removal problems. 4.3.2.1 Air-Fired Reference Case The general layout drawing of the air-fired reference case is shown in Figure 4.3.6. The furnace has a total 24 opposed wall-fired burners (3 vertical x 4 horizontal x 2 walls) and 10 overfire air ports. 30% of the total combustion air is injected through the over-fire air ports located at one burner pitch above the top burner row. The radiant heat transfer surface consists of 2.75” OD tube waterwalls and five 2.0” OD tube partial divisional wall panels. Water is circulated in the furnace by forced circulation. The boundary conditions were applied to the computational model and FW-FIRE was run until steady state conditions were achieved. The modeling results are summarized in Figure 4.3.7. The coal burnout shown in the table is the percentage of dry ash-free based coal burned. The furnace exit gas temperature (FEGT) shown in the table is the average temperature of flue gas before the platen superheater. The energy absorption listed is the total energy absorbed by water walls and partial division walls prior to the platen superheater. Total furnace absorption and FEGT predicted by FW-FIRE and ASPEN match closely. 71 Figure 4.3.8 is a plot of the flue gas velocity magnitude in a vertical plane through the second burner column. It can be seen that the gas velocity near the burners accelerates to greater than 130 ft/s due to the reduced gas density after particle ignition. Figure 4.3.9 presents a plot of gas temperature in a vertical plane through the second burner column. The maximum flue gas temperature is approximately 3350oF. The mole fraction of O2 through the second burner column is presented in Figure 4.3.10. The heat flux at the furnace water wall is shown in Figure 4.3.11. The maximum heat flux is approximately 70,000 Btu/hr-ft2 and is located on the side wall at the top of the burner zone. The total heat absorbed by the furnace walls before the furnace exit is 1770 MM Btu/hr. Figure 4.3.12 displays temperatures of the furnace walls and roof. The maximum temperature of the waterwalls is approximately 870oF and of the division walls is approximately 1000oF. Figure 4.3.13 presents the CO concentration at the wall, peaks at approximately 10% due to the sub-stoichiometric conditions of the lower furnace (without overfire air the wall CO would be below 2%). The trajectories of the 72-micron particles are plotted in Figure 4.3.14 with colors in each trajectory representing the mass fraction of char in the particle. Char is formed from devolatilization and consumed by oxidation. The maximum char mass fraction is usually less than the mass fraction of fixed carbon in a proximate analysis. Figure 4.3.14 shows that all of the 72-micron particles are completely burned before the furnace exit. The trajectories of 176-micron particles are plotted in Figure 4.3.15. It can be observed from Figure 4.3.15 that some particles are not completely burned at the exit of the furnace, causing unburned carbon in the fly ash. Total burnout of all particle sizes is 99.66% (2.61% LOI). Average NOx concentration at the furnace outlet is 276 ppmvw (0.38 lb/MMBtu). 4.3.2.2 Oxygen-Fired Design Case The preliminary size of the furnace heat transfer area was based on a calculation of average wall heat flux using the Foster Wheeler computer program, EMISS [11]. The EMISS computer program calculates radiative heat flux of CO2 and H2O gases. A three dimensional CFD run was then made using FW-FIRE to more accurately determine the total heat absorption. Based on the CFD results, the height of the furnace model was adjusted until the total heat absorption approximately matched that required in the ASPEN oxygen-fired design case. Figure 4.3.16 shows a comparison between the sizes of the resultant oxygenfired furnace and the air-fired reference furnace. Compared to the air-fired furnace, the oxygen furnace has only approximately 65% of the surface area and approximately 45% of the volume. Figure 4.3.17 presents the oxygen-fired design general layout drawing for the cryogenic ASU design and Figure 4.3.18 for the OITM design. 72 The oxygen-fired furnace has a total 24 opposed wall-fired burners (4 vertical x 3 horizontal x 2 walls) and 8 overfire gas ports. The burner designs (including 0.5 primary air swirl) are based on the subcritical O2-PC burner design [3]. The radiant heat transfer surface consists of 2.75” OD tube waterwalls and ten 2.0” OD tube partial divisional wall panels. Water is circulated in the furnace by forced circulation. Two designs were simulated: 1) with cryogenic ASU and 2) with OITM. The designs differ as follows: Radiant Superheater: In the cryogenic ASU design, radiant superheat (downstream of the primary superheater) is provided by the partial division walls, whereas in the OITM design radiant superheat is provided by the waterwalls above 100’ and the furnace roof. No division wall surface is required in the OITM design due to the increased coal-firing such that less evaporator surface (below 100’) is required (in addition, in the OITM design the overall furnace height is reduced by 5’). Air Heater: A tubular convective air heater is included in the OITM to provide the necessary air heating for the membrane separation process. The modeling results are summarized in Figure 4.3.7. The coal burnout for the oxygen-fired cases is 100% due to the high furnace temperature and high concentration of O2. Total furnace absorption and FEGT predicted by FW-FIRE and ASPEN match well. NOx is reduced by oxygen firing (compared to air-firing) by about a factor of two from 0.38 lb/MMBtu to 0.18 lb/MMBtu. 4.3.2.2.1 Cryogenic ASU – Full Load Figure 4.3.19 is a plot of the flue gas velocity magnitude in a vertical plane through the middle burner column. It can be seen that the gas velocity near the burners accelerates to nearly 150 ft/s due to the reduced gas density after particle ignition. Figure 4.3.20 presents a plot of gas temperature in a vertical plane through the middle burner column. The maximum flue gas temperature is approximately 3900oF. The mole fraction of O2 through the middle burner column is presented in Figure 4.3.21. The mixed primary/secondary gas O2 content (before combustion) is 41%. The heat flux at the furnace water wall is shown in Figure 4.3.22. The maximum heat flux is approximately 171,000 Btu/hr-ft2 and is located on the side wall at the top of the burner zone. This maximum heat flux is approximately 2.5 times the air-fired case due to the higher flame temperature and higher H2O and CO2 concentrations. The total heat absorbed by the furnace walls before the furnace exit is 2287 MM Btu/hr. Figure 4.3.23 displays temperatures of the furnace walls and roof. The maximum temperature of the waterwalls is approximately 1035oF 73 and of the division walls is approximately 1050oF. Because of the higher temperature of the oxygen-fired case compared to the air-fired case, furnace water wall material was upgraded from 0.22” thick SA-213-T2 to 0.20” thick SA213-T92. Figure 4.3.24 presents the CO concentration at the wall, which is significantly greater than for the air-fired case (Figure 4.3.13) and its effects on corrosion are modeled analytically in Section 4.3.4, but will also need to be measured empirically in future work. The trajectories of the 69-micron particles are plotted in Figure 4.3.25 with colors in each trajectory representing the mass fraction of char in the particle. Figure 4.3.25 shows that all of the 69-micron particles are completely burned before the furnace exit. The trajectories of 169-micron particles are plotted in Figure 4.3.26. Note that due to the higher temperature and O2 concentration all the 169-micron particles are completely burned as compared to the air-fired case (Figure 4.3.15) where there is some residual unburned char at the outlet. 4.3.2.2.2 Cryogenic ASU – Part Load Since the boiler is a supercritical once-through sliding pressure unit, part load operation must be evaluated with thermal/hydraulic and structural criteria. Three part loads were selected for evaluation: 72%, 50%, and 25% (minimum BENSON load). Boundary conditions were based on the ASPEN System Analysis. Figure 4.3.27 presents the corresponding recycle flow versus load. The modeling results are summarized in Figure 4.3.28. Figure 4.3.29 presents the gas temperature in a vertical plane through the middle burner column for the part load cases. The heat flux at the furnace water wall is shown for the part load cases in Figure 4.3.30. The average and peak heat flux versus height is presented in Figure 4.3.31. 4.3.2.2.3 Integration of Oxygen Ion Transport Membrane Figure 4.3.32 is a plot of the flue gas velocity magnitude in a vertical plane through the middle burner column. It can be seen that the gas velocity near the burners accelerates to nearly 150 ft/s due to the reduced gas density after particle ignition. Figure 4.3.33 presents a plot of gas temperature in a vertical plane through the middle burner column. The maximum flue gas temperature is approximately 3850oF. The mole fraction of O2 through the middle burner column is presented in Figure 4.3.34. The mixed primary/secondary gas O2 content (before combustion) is 39%. The heat flux at the furnace water wall is shown in Figure 4.3.35. The maximum heat flux is approximately 180,000 Btu/hr-ft2 and is located on the side wall at the top of the burner zone. This maximum heat flux is approximately 2.5 times the air-fired case due to the higher flame temperature and higher H2O and CO2 concentrations. The total heat absorbed by the furnace walls before the furnace 74 exit is 2029 MM Btu/hr. Figure 4.3.36 displays temperatures of the furnace walls and roof. The maximum temperature of the evaporator waterwalls is approximately 1060oF, of the radiant superheater is approximately 1100oF, and of the air heater is approximately 1800 oF. Because of the higher temperature of the oxygen-fired case compared to the air-fired case, furnace water wall material was upgraded from 0.22” thick SA-213-T2 to 0.23” thick SA-213-T92. The air heater, which constructed from Incoloy MA956 material, is described in detail in Section 4.3.5.4. Figure 4.3.37 presents the CO concentration at the wall, which is significantly greater than for the air-fired case (Figure 4.3.13) and its effects on corrosion will need to be studied in future work. The trajectories of the 69-micron particles are plotted in Figure 4.3.38 with colors in each trajectory representing the mass fraction of char in the particle. Figure 4.3.38 shows that all of the 69-micron particles are completely burned before the furnace exit. The trajectories of 169-micron particles are plotted in Figure 4.3.39. Note that due to the higher temperature and O2 concentration all the 169-micron particles are completely burned as compared to the air-fired case (Figure 4.3.15) where there is some residual unburned char at the outlet. 75 Figure 4.3.1 – Computational Model of Air-Fired Furnace (with right side wall removed) Partial division walls OFA ports Burners 76 Figure 4.3.2 – Computational Model of Oxygen-Fired Furnace With OFA Superheater Partial division walls Air Heater OFA ports Evaporator Burners OITM Cryogenic ASU 77 Figure 4.3.3 – Air-Fired Boundary Conditions Coal Ultimate Analysis Ash S H C H2O N O Total Volatile Matter (daf) Density HHV, as received TCA Excess O2 OFA % % % % % % % % % lb/ft3 Btu/lb lb/hr % % Primary Inner Sec. Air Outer Sec. Air Tertiary Air Overfire Air - Inner Overfire Air - Outer Size (micron) Distribution 9.99% 9.3 2.51% 33.7 4.50% 71.7 63.75% 121.8 11.12% 175.5 1.25% Total 6.88% 100.00% < 75 micron < 150 micron 44.35% 80.0 11,666 3,299,687 11.0 % % % % % % Mass Percent 28.9 27.3 Coal Flow 23.9 Moisture in Coal 10.7 9.2 100.0 % % 319,000 35,473 70 99 Heat Input 3721.45 MM Btu/hr Divwall Inlet Outlet Temp (F) Temp (K) 854 730 964 791 WW Inlet Outlet Temp (F) Temp (K) 638 610 810 705 Density Inner Diam. Outer Diam. Area per Port No. of Ports Axial Velocity Tan./Axial Rad./Axial Coal Flow in in ft2 ft/sec lb/hr Velocity Velocity 20.0% Flow Rate lb/hr % 550,000 16.5 425,044 12.7 1,700,178 51.0 0 0.0 335,664 10.1 324,274 9.7 3,335,159 100.0 Temperature F 219 580 580 580 580 580 lb/ft3 0.059 0.039 0.039 0.039 0.039 0.039 13.100 23.750 33.875 0.000 0.000 19.500 78 22.750 33.375 49.000 12.100 19.000 27.000 1.887 2.999 6.837 0.799 1.969 1.902 24 24 24 24 10 10 57.1 42.5 74.6 0.0 122.7 122.7 0.00 0.00 0.41 0.00 0.00 0.00 0.00 283,527 0.21 0.41 0.00 0.00 0.21 Figure 4.3.4 – Oxygen-Fired Boundary Conditions (Cryogenic ASU) Coal Ultimate Analysis Ash S H C H2O N O Total Volatile Matter (daf) Density HHV, as received TCA Excess O2 OFA % % % % % % % % % lb/ft3 Btu/lb lb/hr % % Primary Inner Sec. Air Outer Sec. Air Tertiary Air Overfire Air - Inner Overfire Air - Outer Size (micron) Distribution 9.99% 10.7 2.51% 33.7 4.50% 69.3 63.75% 118.2 11.12% 169.2 1.25% Total 6.88% 100.00% < 75 micron < 150 micron 44.35% 80.0 11,666 1,809,811 11.0 % % % % % % Mass Percent 29.5 38.2 Coal Flow 25.9 Moisture in Coal 5.5 1.0 100.0 % % 308,000 34,250 85 99 Heat Input 3593.13 MM Btu/hr Divwall Inlet Outlet Temp (F) Temp (K) 837 720 974 796 WW Inlet Outlet Temp (F) 593 825 Density Inner Diam. Outer Diam. Area per Port No. of Ports Axial Velocity Temp (K) 585 714 20.0% Flow Rate lb/hr % 495,000 26.8 197,420 10.7 789,679 42.8 0 0.0 170,790 9.3 191,172 10.4 1,844,061 100.0 Temperature F 257 625 625 625 625 625 lb/ft3 0.073 0.046 0.046 0.046 0.046 0.046 in 9.500 16.000 21.750 0.000 0.000 14.000 79 in 15.000 20.750 29.000 8.500 13.500 20.000 ft2 0.735 0.952 2.007 0.394 0.994 1.113 24 24 24 24 8 8 ft/sec 106.3 52.6 99.8 0.0 130.8 130.8 Tan./Axial Rad./Axial Coal Flow Velocity Velocity lb/hr 0.50 0.00 0.41 0.00 0.00 0.00 0.00 273,750 0.21 0.41 0.00 0.00 0.21 Figure 4.3.5 – Oxygen-Fired Boundary Conditions (OITM) Coal Ultimate Analysis Ash S H C H2O N O Total Volatile Matter (daf) Density HHV, as received TCA Excess O2 Drum Pressure OFA Primary Inner Sec. Air Outer Sec. Air Tertiary Air Overfire Air - Inner Overfire Air - Outer % % % % % % % % % lb/ft3 Btu/lb lb/hr % psia % Size (micron) Distribution 9.99% 10.7 2.51% 33.7 4.50% 69.3 63.75% 118.2 11.12% 169.2 1.25% Total 6.88% 100.00% < 75 micron < 150 micron 44.35% 80.0 11,666 2,306,255 11.0 % % % % % % Mass Percent 29.5 38.2 Coal Flow 25.9 Moisture in Coal 5.5 1.0 100.0 % % 375,400 41,744 85 99 Heat Input 4379.42 MM Btu/hr Divwall Inlet Outlet Temp (F) Temp (K) 837 721 970 794 WW Inlet Outlet Temp (F) 599 830 Density Inner Diam. Outer Diam. Area per Port No. of Ports Axial Velocity Temp (K) 588 716 20.0% Flow Rate lb/hr % 600,000 25.6 257,350 11.0 1,029,399 43.8 0 0.0 217,639 9.3 243,612 10.4 2,347,999 100.0 Temperature F 236 625 625 625 625 625 lb/ft3 0.076 0.046 0.046 0.046 0.046 0.046 in 9.500 16.000 21.750 0.000 0.000 14.000 80 in 15.000 20.750 29.000 8.500 13.500 20.000 ft2 0.735 0.952 2.007 0.394 0.994 1.113 24 24 24 24 8 8 ft/sec 125.1 68.6 130.1 0.0 166.6 166.6 Tan./Axial Rad./Axial Coal Flow Velocity Velocity lb/hr 0.50 0.00 0.41 0.00 0.00 0.00 0.00 333,656 0.21 0.41 0.00 0.00 0.21 Figure 4.3.6 – Air-Fired Boiler Design 81 Figure 4.3.7 – Summary of FW-FIRE Furnace Modeling Results Air-Fired Burnout LOI Total Furnace Absorption Division Wall Absorption FEGT NOx % % M Btu/hr M Btu/hr F ppmvw lb/MMBtu FW-FIRE 99.6 2.76 1770 445 2107 276 0.38 ASPEN 99.0 7.32 1751 451 2185 % % M Btu/hr M Btu/hr F ppmvw lb/MMBtu FW-FIRE 100.0 0.00 2096 548 2266 261 0.18 ASPEN 99.9 0.78 2089 485 2450 % % M Btu/hr M Btu/hr M Btu/hr F ppmvw lb/MMBtu FW-FIRE 100.0 0.00 2029 458 935 1822 273 0.20 ASPEN 99.9 0.78 1961 502 970 2185 Oxygen-Fired (Cryogenic ASU) Burnout LOI Total Furnace Absorption Division Wall Absorption FEGT NOx Oxygen-Fired (OITM) Burnout LOI Total Furnace Absorption Radiant SH Absorption Air Heater Absorption FEGT NOx 82 Figure 4.3.8 – Gas Velocity for Air-Fired Case 83 Figure 4.3.9 – Gas Temperature for Air-Fired Case 84 Figure 4.3.10 – O2 Mole Fraction for Air-Fired Case 85 Figure 4.3.11 – Wall Heat Flux for Air-Fired Case 86 Figure 4.3.12 – Wall Temperature for Air-Fired Case 87 Figure 4.3.13 – Wall CO for Air-Fired Case 88 Figure 4.3.14 – Char Mass Fraction (72 microns) for Air-Fired Case 89 Figure 4.3.15 – Char Mass Fraction (176 microns) for Air-Fired Case 90 Figure 4.3.16 – Air-Fired and Oxygen-Fired Boiler Outlines (Black = Air-Fired, Red = Oxygen Fired) 91 Figure 4.3.17 – Oxygen-Fired Boiler Design (Cryogenic ASU) 92 Figure 4.3.18 – Oxygen-Fired Boiler Design (OITM) 93 Figure 4.3.19 – Gas Velocity for O2-Fired Case 94 Figure 4.3.20 – Gas Temperature for O2-Fired Case 95 Figure 4.3.21 – O2 Mole Fraction for O2-Fired Case 96 Figure 4.3.22 – Wall Heat Flux for O2-Fired Case 97 Figure 4.3.23 – Wall Temperature for O2-Fired Case 98 Figure 4.3.24 – Wall CO for O2-Fired Case 99 Figure 4.3.25 – Char Mass Fraction (69 micron) for O2-Fired Case 100 Figure 4.3.26 – Char Mass Fraction (169 micron) for O2-Fired Case 101 Figure 4.3.27 - Flue gas recycle flow vs. part load operation Part Load Performance 1400 100 90 1200 1000 70 60 800 50 600 40 30 400 20 200 10 0 0 20 40 60 80 Load, % 102 100 0 120 gas recycling, % Gas recycling, klb/hr 80 Figure 4.3.28 – Summary of O2-Fired Part Load Results, Cryogenic ASU 100% Load 72% Load 50% Load 25% Load Burnout % 100.00 100.00 100.00 99.81 LOI % 0.00 0.00 0.00 1.48 Total Furnace Absorption MM Btu/hr 2096 1572 1073 747 Division Wall Absorption MM Btu/hr 548 380 248 193 FEGT F 2266 2069 1912 1658 103 Figure 4.3.29 – Gas Temperature for O2-Fired Part Load, Cryogenic ASU 72 % 50 % 25 % 104 Figure 4.3.30 – Wall Heat Flux for O2-Fired Part Load, Cryogenic ASU 72 % 50 % 25 % 105 Figure 4.3.31 – Average and Peak Heat Flux in Waterwalls Average Flux Vs. Height 160000 Heat Flux (Btu/hr-ft2) 140000 120000 100000 80000 60000 40000 20000 0 0 20 40 60 80 100 120 140 160 Height (ft) no ofa, 100% ofa, 100% ofa, 25% ofa, 72% ofa, 50% OTM, 100% air-fired Peak Flux Vs. Height 200000 Heat Flux (Btu/hr-ft2) 180000 160000 140000 120000 100000 80000 60000 40000 20000 0 0 20 40 60 80 100 120 140 160 Height (ft) no ofa, 100% ofa, 100% ofa, 25% ofa, 72% 106 ofa, 50% OTM, 100% air-fired Figure 4.3.32 – Gas Velocity for O2-Fired with OITM 107 Figure 4.3.33 – Gas Temperature for O2-Fired Case With OITM 108 Figure 4.3.34 – O2 Mole Fraction for O2-Fired Case With OITM 109 Figure 4.3.35 – Wall Heat Flux for O2-Fired Case With OITM 110 Figure 4.3.36 – Wall Temperature for O2-Fired Case With OITM Air heater Furnace walls 111 Figure 4.3.37 – Wall CO for O2-Fired Case With OITM 112 Figure 4.3.38 – Char Mass Fraction (69 micron) for O2-Fired Case, OITM 113 Figure 4.3.39 – Char Mass Fraction (169 micron) for O2-Fired Case, OITM 114 4.3.3 Furnace Waterwall and Division Wall Design The O2-PC supercritical boiler incorporates the state-of-the-art once-through utility (OTU) BENSON Vertical technology, which uses low fluid mass flow rates in combination with optimized rifled tubing and offers the following advantages: “Natural Circulation” Flow Characteristic: By designing for low mass flow rates that minimize frictional pressure losses, high heat flux tubes receive more flow to minimize temperature unbalances (see Figure 4.3.40). Improved Heat Transfer Coefficient: By using optimized rifled tubing, departure from nucleate boiling (DNB) when operating near the critical pressure can be suppressed, even with relatively low fluid mass flow rates, and dryout can be prevented from occurring until steam qualities of greater than 90% are achieved. This lowers the wall temperature permitting the use of thinner wall less expensive materials (see Figure 4.3.41). Simple Configuration: A standard, simple support system can be used to support the vertical tube panels so that interconnecting piping and headers between multiple passes are not required. Low Pressure Losses: The low mass flow rates significantly reduce pressure loss, which reduces auxiliary power and therefore increases cycle efficiency. The boiler design pressure can also be lowered. The furnace heat transfer tube design utilizing optimized rifled tubes is summarized in Figure 4.3.42. 4.3.3.1 Tube Wall Temperature and Pressure Loss Thermal/hydraulic modeling of the waterwalls and division walls was performed using the Siemens computer program, Stade2 [12]. Stade2 creates a one-dimensional model of the tube panels to determine inside heat transfer, wall temperatures, and pressure loss and to perform linear dynamic and static stability analyses. Stade2 models of the waterwalls and division walls were created and the average heat flux (Figure 4.3.31) and average mass flow were applied to establish the net pressure difference between the inlet and outlet headers. Models of the peak heat flux tubes were then created and Stade2 was used to determine the increased mass flow rate corresponding to the average pressure drop (due to the natural circulation characteristic of the optimized rifled tube geometry). For example, for the cryogenic O2-PC design, the average heat flux and average mass flux (832 kg/m2-sec) produced a pressure loss of 33.7 psi. To match this pressure loss for the peak heat flux tube requires a mass flux of 966 kg/m2-sec (0.71 MM lb/ft2-hr). Due to the increased mass flow rate the maximum tube wall temperature of the peak heat flux tube is reduced. Figure 4.3.43 presents the 115 outside wall temperature of the peak heat flux waterwalls and division walls for the airfired and O2-fired designs. Based on the maximum outside wall temperatures of Figure 4.3.43 the minimum tube wall thickness is computed using stress allowables from the ASME Boiler and Pressure Vessel Code as follows (design pressure = 5000 psi): Air-Fired: O2-Fired Cryo.: O2-Fired OITM: 4.3.3.2 Material = SA-213-T2, min. wall thickness = 0.22” Material = SA-213-T92, min. wall thickness = 0.20” Material = SA-213-T92, min. wall thickness = 0.23” Tube Panel Stability The waterwall and division wall designs were determined by Stade2 to be statically and linearly dynamically stable at full and part loads (although the 25% load case appears to be near the dynamically unstable region). A more thorough treatment of dynamic stability was performed using the Siemens program, Dynastab [13]. Dynastab performs calculations for a single tube within a greater number of parallel tubes. The calculation starts from steady state and compares the flow behavior of a single tube, with slightly changed conditions (e.g. heat input, tube geometry), with the mean tubes of the heating surface. The mass flow of the single tube is stimulated by a distinct disturbance (e. g. global or local heating factor, inlet enthalpy), while pressure drop is kept constant. If this disturbance causes continuous oscillations, the tube is dynamically unstable; whereas if the disturbance results in a (new) steady state condition, the tube is dynamically stable. A 10% step increase in heat flux was applied to the single tube model. Figure 4.3.44 presents the transient results of inlet mass flow versus time (although a single tube was modeled the flow per entire furnace is presented). The 100% and 72% loads are stable, the 50% load is marginally stable, and the 25% load is unstable. To ensure stable operation at low loads, a pressure equalization header is added to the design at an elevation of 80’ and the resultant dynamic stability response is shown in Figure 4.3.45. With the pressure equalization header all loads are dynamically stable. 116 Figure 4.3.40 – Advantage of Low Mass Flux Design 117 Figure 4.3.41 – Tube Wall Temperature with Smooth, Standard Rifled, and Optimized Rifled Tubes 118 Figure 4.3.42 – Rifled Tube Design Material OD twall ID Pitch Ligament Ligament Width Number of waterwall tubes Number of radiant superheater tubes Number of ribs Rib Height in in in in in in in Air-Fired O2 PC SC Cryogenic O2 PC SC OITM SA-213-T2 1.40 0.22 0.96 2.00 0.60 0.25 1218 618 6 0.048 SA-213-T92 1.40 0.20 1.00 2.00 0.60 0.25 888 720 6 0.050 SA-213-T92 1.40 0.23 0.94 2.00 0.60 0.25 888 666 6 0.048 119 Figure 4.3.43 – Outside Tube Wall Temperature with Peak Heat Flux Outside Tube Wall Temperature Vs. Height 1150 1100 1050 Temperature (F) 1000 950 900 850 800 750 700 650 600 0 20 40 60 80 100 120 140 160 Height (ft) 100% no OFA Div. Wall 100% 100% load Div. Wall 72% 72% load Div. Wall air 120 50% load 100% oitm 100% air Figure 4.3.44 – Tube Inlet Mass Flow With a 10% Heat Flux Step Increase (No Pressure Equalization Header) Flow Vs. Time: No Pressure Equilization Header 6 5 Flow Rate (MM lb/hr) 4 3 2 1 0 0 20 40 60 80 100 120 140 -1 -2 Time (sec) 100% 72% 50% 121 25% 160 180 200 Figure 4.3.45 – Tube Inlet Mass Flow With a 10% Heat Flux Step Increase (With Pressure Equalization Header at 80’) Flow Vs. Time: With Pressure Equilization Header at 80' 3.5 3 Flow Rate (MM lb/hr) 2.5 2 1.5 1 0.5 0 0 20 40 60 80 100 120 140 Time (sec) 100% 72% 122 50% 25% 160 180 200 4.3.4 Furnace Waterwall Corrosion Waterwall corrosion is caused by sulfidation from a sub-stoichiometric gas containing H2S and from deposits containing carbon and iron sulfide. Corrosion is especially significant at the high waterwall surface temperatures of a supercritical and ultrasupercritical boiler. In the O2-PC without FGD, recycling of the flue gas will increase the H2S concentration of the furnace by a factor of 1/(1 – recycle fraction). For example for a recycle flow rate of 55%, the H2S concentration is increased by a factor of 2.2. An empirical EPRI formula was developed to predict the magnitude of waterwall corrosion due to the presence of H2S as follows: 1 ⎛ 15818 ⎞ 0.574 CR = 3.2 x10 5 exp⎜ − ⎟[H s S ] (Cr % + 10.5)1.234 ⎝ 1.987T ⎠ (Cr wt% < 10) 1 ⎛ 19230 ⎞ 0.29 CR = 1.04 x10 7 exp⎜ − ⎟[H s S ] (Cr % − 1.40)1.37 ⎝ 1.987T ⎠ (Cr wt% > 16) where, CR = corrosion rate (mil/year) T = metal temperature, K H2S = H2S flue gas concentration, ppm Cr% = Cr concentration of the metal Figure 4.3.46 shows the predicted corrosion rate for the air-fired and O2-fired cases. For the air-fired case the maximum corrosion on the waterwalls is 12 mil/yr and on the division walls is 18 mil/yr (maximum H2S concentration is 1600 ppm). For the oxygenfired case maximum corrosion on the waterwalls is 35 mil/yr and on the division walls is 45 mil/yr (maximum H2S concentration is 5600 ppm). Note that for the O2-fired case the corrosion is increased by the higher water wall temperature, higher concentration of H2S, but is reduced by the higher chromium content of T92 vs. T2. To reduce the corrosion in the O2-PC, weld overlays with high Nickel and Chromium contents are proposed. This will be much more cost-effective than adding an FGD system, which will be substantially more costly and reduce the corrosion by only a factor of 1.6 (by reducing the H2S by a factor of 2.2). Applying alloy 622 (20% Cr) as a weld overlay significantly reduces the corrosion rate as shown in Figure 4.3.46 to less than 10 mil/yr. Note that other alternatives to weld overlays include upgrading the base tube metal and thermal spray coatings. 123 Figure 4.3.46 – Predicted Wall Corrosion (mil/yr) in Air-Fired and O2-Fired Furnaces Air-Fired O2-Fired O2-Fired (Without Tube Overlay) (With Tube Overlay) 124 4.3.5 Heat Recovery Area Design and Analysis 4.3.5.1 HEATEX Program Description HEATEX [10] is a Foster Wheeler general-purpose program for thermal/hydraulic analysis of tube banks. The program performs heat transfer calculations on a local basis by dividing the tube bundle into a number of small heat transfer elements. 4.3.5.2 Air-Fired Reference Case HEATEX was used to determine the heat recovery area (HRA) design of the convective tube banks between the furnace exit and the SCR/air heater. These tube banks include the finishing superheater, finishing reheater, primary superheater, primary reheater, upper economizer, and lower economizer. Flue gas exits the furnace at 2185ºF and flows over the finishing superheater and finishing reheater tube bundles where it heats the main steam and reheat steam to 1083ºF and 1113ºF, respectively. The gas flow is then split into two parallel flows: one passing over the primary reheater and the other passing over the primary superheater and upper economizer. The gas split is controlled by dampers to achieve the proper reheater outlet temperature. Attemperating spray is used to control superheat temperature. The flue gas is combined downstream of the dampers and flows over the lower economizer, which receives water from the last feedwater heater stage. Flue gas exits the lower economizer at 720ºF and is sent to the SCR and then to the air heater. Figure 4.1.1 presents the heat transfer requirements of the HRA banks. Figure 4.3.47 presents the corresponding design of the HRA banks. Total surface area of all convective banks is 335,025 ft2. The performance of HRA tube banks is shown in Figure 4.3.48. The total heat transferred to the water/steam is 1431 MM Btu/hr as 3.59 MM lb/hr of flue gas is cooled from 2185ºF to 720ºF. 4.3.5.3 Oxygen-Fired Case, Cryogenic ASU Due to the 40% lower flue gas flow rate of the cryogenic ASU oxygen-fired case versus the air-fired case, the cross sectional area of the HRA is reduced to maintain the same gas side velocity (and pressure drop). HEATEX was used to determine the heat recovery area design of the convective tube banks between the furnace exit and the gas recuperator. These tube banks include the finishing superheater, finishing reheater, primary reheater, and lower economizer. Flue gas exits the furnace at 2450ºF and flows over the finishing superheater and finishing reheater tube bundles where it heats the main steam and reheat steam to 1083ºF and 1113ºF, respectively. Because of the reduced flue gas flow and lower HRA duty, the HRA is designed in series instead of parallel to produce a more compact design After exiting the finishing reheater the flue gas flows over the primary reheater and then the lower economizer, which receives water from the last feedwater heater stage. Flue gas exits the lower economizer at 695ºF and is sent to the gas recuperator. 125 Figure 4.1.9 presents the heat transfer requirements of the HRA banks. Figure 4.3.47 presents the corresponding design of the HRA banks. Total surface area of all convective banks is 218,693 ft2. The performance of HRA tube banks is shown in Figure 4.3.48. The total heat transferred to the water/steam is 1151 MM Btu/hr as 2.12 MM lb/hr of flue gas is cooled from 2450ºF to 695ºF. The total heat transfer surface required in the oxygen-fired HRA is 35% less than the air-fired HRA due to the following main reasons: 1. More heat is absorbed in the oxygen-fired furnace (2089 MM Btu/hr) than the air-fired furnace (1751 MM Btu/hr) due to the higher adiabatic temperature and the greater specific heat of the oxygen-fired furnace flue gas. This requires less heat transfer duty in the HRA (as a consequence the upper economizer is not needed) 2. A higher heat transfer coefficient can be achieved in the oxygen-fired HRA than the air-fired HRA for the same flue gas pressure loss due to greater molecular weight (38 mol/lb-mol vs. 29 mol/lb-mol) of the oxygen-fired flue gas. The HRA tube materials and wall thicknesses are nearly the same for the air-fired and oxygen-fired design (except for the finishing superheater where the 0.42” wall thickness of the air-fired case is increased to 0.46” for the oxygen-fired case) since the flue gas and water/steam temperature profiles encountered by the heat transfer banks are very similar. 4.3.5.4 Oxygen-Fired Case, OITM Due to the 25% lower flue gas flow rate of the OITM oxygen-fired case versus the airfired case, the cross sectional area of the HRA is reduced to maintain the same gas side velocity (and pressure drop). HEATEX was used to determine the heat recovery area design of the convective tube banks between the furnace exit and the gas recuperator. These tube banks include the finishing superheater, finishing reheater, primary superheater, primary reheater, upper economizer, and lower economizer. Flue gas exits the furnace at 2185ºF and flows over the finishing superheater and finishing reheater tube bundles where it heats the main steam and reheat steam to 1083ºF and 1113ºF, respectively. The flue gas is then used to heat the air used for the OITM process. The gas flow is then split into two parallel flows: one passing over the primary reheater and the other passing over the primary superheater and upper economizer. The gas split is controlled by dampers to achieve the proper reheater outlet temperature. Attemperating spray is used to control superheat temperature. The flue gas is combined downstream of the dampers and flows over the lower economizer, which receives water from the last feedwater heater stage. Flue gas exits the lower economizer at 695ºF and is sent to the gas recuperator. Figure 4.2.10 presents the heat transfer requirements of the HRA banks. Figure 4.3.47 presents the corresponding design of the HRA banks. Total surface area of all 126 convective banks is 291,150 ft2 (242,510 ft2 without the air heater). The total heat transfer surface required in the oxygen-fired OITM HRA is 13% less than the air-fired HRA (28% less not including the air heater). The performance of HRA tube banks is shown in Figure 4.3.48. The total heat transferred to the water/steam is 1181 MM Btu/hr and to the air is 990 MMBtu/hr as 2.68 MM lb/hr of flue gas is cooled to 695ºF. The total furnace + HRA heat transfer surface area for the OITM O2-PC is 309,799 ft2 as compared to 382,574 ft2 for the air-fired PC and 252,002 ft2 for the cryogenic ASU O2PC. The HRA tube materials and wall thicknesses are nearly the same for the air-fired and OITM oxygen-fired design (except for the finishing superheater where the 0.42” wall thickness of the air-fired case is increased to 0.46” for the oxygen-fired case) since the flue gas and water/steam temperature profiles encountered by the heat transfer banks are very similar. The air heater is constructed Incoloy MA956 which is an iron-chromium-aluminum alloy. Incoloy MA956 has been used in advanced gas turbine engines and is resistant to creep, oxidation, and corrosion at temperatures up to 2200ºF. The furnace air heater is a three pass tubular design situated above the furnace nose to reduce radiation and maximum metal temperature. Air is heated from 745 to 1650ºF as the flue gas is cooled from 2950 to 2185ºF. Maximum metal temperature is approximately 1900ºF. 127 Figure 4.3.47 – HRA Tube Bank Design Air-Fired O2 PC SC Cryogenic O2 PC SC OITM Air Heater Length No. of Tubes Deep No. of Tubes Wide Total Number of Tubes Tube Outside Diameter Tube Thickness Tube Material Design Pressure Design Temperature Stress Allowable Min. Wall Total Surface Area Finishing Superheater Length No. of Tubes Deep No. of Tubes Wide Total Number of Tubes Tube Outside Diameter Tube Thickness Tube Material Design Pressure Design Temperature Stress Allowable Min. Wall Total Surface Area ft 28.0 42 79 3,318 2.000 0.06 MA956 250 2000 8200 0.040 48,640 in in psi F psi in ft2 ft in in psi F psi in ft2 36.0 44 30 1,320 2.000 0.42 SA-213-T92 5000 1150 10200 0.414 26,539 24.0 56 32 1,792 2.000 0.47 SA-213-T92 5000 1180 8379 0.470 24,021 24.0 40 32 1,280 2.000 0.47 SA-213-T92 5000 1180 8379 0.470 17,152 30.5 40 63 2,520 2.250 0.165 SA-213-T92 1000 1200 7990 0.173 45,270 20.0 72 51 3,672 2.250 0.165 SA-213-T92 1000 1200 7330 0.173 43,260 20.0 60 51 3,060 2.250 0.165 SA-213-T92 1000 1200 6730 0.173 36,050 Vertical Reheater Length No. of Tubes Deep No. of Tubes Wide Total Number of Tubes Tube Outside Diameter Tube Thickness Tube Material Design Pressure Design Temperature Stress Allowable Min. Wall Total Surface Area ft in in psi F psi in ft2 Primary Superheater Length No. of Tubes Deep No. of Tubes Wide Total Number of Tubes Tube Outside Diameter Tube Thickness Tube Material Design Pressure Design Temperature Stress Allowable Min. Wall Total Surface Area ft 0 0 0 in in 17.0 96 63 6,048 2.250 0.42 SA-213-T2 5000 925 11550 0.412 63,252 psi F psi in ft2 128 9.5 64 90 5,760 2.250 0.42 SA-213-T2 5000 925 11550 0.412 33,662 Figure 4.49 – HRA Tube Bank Design (Continued) Air-Fired O2 PC SC Cryogenic O2 PC SC OITM 17.0 70 125 8,750 2.250 0.165 SA-213-T2 1000 950 9200 0.127 93,461 24.0 75 90 6,750 2.250 0.165 SA-213-T2 1000 950 9200 0.127 101,792 21.0 75 90 6,750 2.250 0.165 SA-213-T2 1000 950 9200 0.127 89,067 17.0 30 126 3,780 2.250 0.34 SA-210-A1 5000 700 15600 0.322 40,373 0.0 0 0 0 0.000 0 0 0 0 0 0 0 9.5 36 90 3,240 2.250 0.32 SA-210-A1 5000 650 17100 0.298 19,339 24.0 39 90 3,510 2.250 0.32 SA-210-A1 5000 650 17100 0.298 49,620 27.0 33 90 2,970 2.250 0.32 SA-210-A1 5000 650 17100 0.298 47,240 218,693 252,002 291,150 309,799 Horizontal Reheater Length No. of Tubes Deep No. of Tubes Wide Total Number of Tubes Tube Outside Diameter Tube Thickness Tube Material Design Pressure Design Temperature Stress Allowable Min. Wall Total Surface Area ft in in psi F psi in ft2 Upper Economizer Length No. of Tubes Deep No. of Tubes Wide Total Number of Tubes Tube Outside Diameter Tube Thickness Tube Material Design Pressure Design Temperature Stress Allowable Min. Wall Total Surface Area ft in in psi F psi in ft2 Lower Economizer Length No. of Tubes Deep No. of Tubes Wide Total Number of Tubes Tube Outside Diameter Tube Thickness Tube Material Design Pressure Design Temperature Stress Allowable Min. Wall Total Surface Area ft psi F psi in ft2 27.0 33 126 4,158 2.250 0.32 SA-210-A1 5000 650 17100 0.298 66,130 Total HRA Surface Area Total Furnace + HRA Surface Area ft2 ft2 335,025 382,574 in in 129 Figure 4.3.48 – HRA Tube Bank Performance Bank O2 PC OITM Air Heater Surface Heat Trans. Mean Temp. Heat Gas Area Coeff. Diff. Transfer Press. Drop (ft2) (Btu/hr-ft2-F) (F) (MM Btu/hr) (in H2O) 48,640 17.1 1189 990 0.38 Air PC Finishing Superheater O2 PC Finishing Superheater O2 PC OITM Finishing Superheater 26,539 24,021 17,157 11.4 14.7 16.0 1038 1173 1026 315 414 281 0.12 0.19 0.20 Air PC Primary Superheater O2 PC Primary Superheater O2 PC OITM Primary Superheater 63,252 0 33,662 8.6 356 194 11.2 268 101 0.29 0.00 0.44 Air PC Finishing Reheater O2 PC Finishing Reheater O2 PC OITM Finishing Reheater 45,270 43,260 36,050 10.2 12.2 14.1 722 629 658 333 331 334 0.18 0.35 0.47 Air PC Primary Reheater O2 PC Primary Reheater O2 PC OITM Primary Reheater 93,461 101,792 89,067 9.1 10.8 10.9 402 290 353 341 320 342 0.47 0.58 0.55 Air PC Upper Economizer O2 PC Upper Economizer O2 PC OITM Upper Economizer 40,373 0 19,339 7.5 367 111 15.6 367 111 0.20 0.00 0.19 Air PC Lower Economizer O2 PC Lower Economizer O2 PC OITM Lower Economizer 66,130 49,620 47,240 9.9 9.8 10.4 196 177 165 128 86 81 0.35 0.27 0.28 1431 1151 2171 1.61 1.39 2.51 Air PC Total O2 PC Total O2 PC OITM Total 335,025 218,693 291,155 130 4.4 Economic Analysis Economic analysis was performed for three cases: air-fired (reference), O2-fired with cryogenic ASU, and O2-fired with OITM. Economic analysis was not performed for the O2-fired PC with CAR since detailed cost information on the CAR process was not available in the literature nor was it provided by the vendor (BOC). 4.4.1 Main Assumptions The economic analysis was performed based on the DOE/NETL guidelines [14] using the EPRI Technical Assessment Guide (TAG) methodology. Plant capital costs were compiled under the Code of Accounts developed by EPRI. The estimate basis and major assumptions are listed below: • Total plant costs were estimated in January 2006 dollars. • Plant book life was assumed to be 20 years. • The net power output of the reference air-fired plant is 430.2 MWe versus 347.0 MWe for the ASU oxygen-based plant and 463.3 MWe for the OITM oxygenbased plant. • The plants operate with a capacity factor of 85 per cent (Plant operates at 100 per cent load 85 per cent of the time). • Cost of electricity (COE) was determined on a levelized constant dollar basis. • Average annual ambient air conditions for material balances, thermal efficiencies and other performance related parameters are at a dry bulb temperature of 60ºF and an air pressure of 14.7 psia. • The coal is 2.5 per cent sulfur Illinois #6 coal (see Table 4.4.1 for analysis). • Design CO2 effluent purity is presented in Table 4.4.2 • Terms used are consistent with the EPRI TAG. Economic study assumptions are detailed in Table 4.4.3. 131 Table 4.4.1 - Coal Properties Illinois No. 6 Coal C H O N Cl S Ash H2O Total % % % % % % % % % LHV Btu/lb HHV Btu/lb 63.75% 4.50% 6.88% 1.25% 0.29% 2.51% 9.70% 11.12% 100.00% 11,283 11,631 Table 4.4.2 - CO2 Effluent Purity Design Conditions Constituent N2 H2O O2 Units vppm vppm vppm 132 Value < 300 < 20 < 50 Table 4.4.3 – Economic Study Assumptions GENERAL DATA/CHARACTERISTICS Levelized Capacity Factor / Preproduction (equivalent months): 85% Capital Cost Year Dollars (Reference Year Dollars): 2006 (January) Design/ Construction Period: 4 years Plant Start-up Date (1st year Dollars): 2010 (January) Land Area/Unit Cost: 100 acres $1,600 / Acre FINANCIAL CRITERIA Project Book Life: Book Salvage Value: Project Tax Life: Tax Depreciation Method: Inflation Rate Property Tax Rate: Insurance Tax Rate: Federal Income Tax Rate: State Income Tax Rate: Investment Tax Credit/% Eligible 20 years 0% 20 years Accel. Based on ACRS Class 3.0 % 1.0 % 1.0 % 35.0 % 4.0 % 0% Economic Basis: Over Book Constant Dollars Capital Structure Common Equity Preferred Stock Debt Weighted Cost of Capital: (after tax) % of Total 20 0 80 Cost (%) 12 6.5 5.57% Coal Price Escalation Rate 3.0% Total Capital Requirement Initial Chemical Inventory (same as general escalation) 30 days Startup Costs 2% TPI 30 days of fuel and chemicals labor and miscellaneous items Spare Parts 0.5% TPC Working Capital 30 days fuel and consumables 30 days direct expenses Consumable Costs Coal, $/MMBtu Limestone, $/ton Water, $/kgal Water Treatment Chemicals, $/kgal Ash/Slag Disposal, $/ton $1.34 $15.00 $1.00 $0.50 $10.00 Plant Labor Operating labor Labor Rate 42.25 $/hr (includes labor burden) personnel 14 per shift Supervisory/clerical 30% of operating + maintenance labor cost Maintenance Costs Labor 0.88% TPC Materials 1.32% TPC 133 4.4.2 Plant Cost Basis For each of the plants, heat and material balances (Aspen simulations) were prepared that identified the flow rates and operating conditions of all major flow streams (Sect. 4.1 and Sect. 4.2). These balances also identified each boiler’s operating requirements and enabled design calculations to be performed that established the overall boiler dimensions, tube surface areas, materials of construction, weights, and auxiliary equipment requirements. With this information defined, the cost of each boiler, which together with its auxiliary equipment constitutes the plant “boiler island”, was determined from Foster Wheeler’s cost estimating database. 4.4.2.1 Air-Fired Reference Plant Cost In [15] Parsons presents a conceptual design of a supercritical pressure PC plant with a net power output of 550.2 MWe. Similar to the air-fired reference plant of this study, the Parsons plant burned 2.5 per cent sulfur Illinois No. 6 coal with air and, to control emissions, the boiler was provided with low NOx burners, SCR, wet flue gas desulfurization, and a baghouse filter. A detailed EPRI TAG cost estimate of the plant totaled $745.7 million or $1355/kW in year 2006 dollars and was broken down into 14 accounts, one of which (Account 4 entitled, “PC Boiler and Accessories”) included the cost of the PC boiler and its auxiliaries. Since the primary difference between the Parsons and the FW air-fired reference plant is size, the Parsons balance of plant costs (excluding the boiler island) were scaled down on an account-by-account basis to obtain the reference plant balance of plant costs. As recommended in [16] a scaling exponent of 0.65 applied to flow rate/output was used and a small adjustment to the PC plant’s feedwater and steam turbine accounts was made for the slightly higher operating pressure. Boiler island costs were estimated directly by FW based on designs generated in Task 3 (Sect. 4.3). To validate the scaling process, Parsons Account 4 boiler costs were scaled down and determined to be within 6 per cent of Foster Wheeler’s directly estimated costs. The results of the scaling, together with Foster Wheeler’s determined Account 4 (boiler island) costs, yielded a total plant cost of $633.0 million or $1471/kW for the 430.2 MWe reference plant. The account-by-account costs of the air-fired reference plant (case-1, Figure 4.1.1) are presented in Table 4.4.4. The total plant cost (TPC), also referred to as the plant capital cost is comprised of the following elements: 1. Bare erected plant cost (includes equipment supply and erection) 2. Architect engineering, construction management, and fee 3. Project and process contingencies The reference plant estimate uses the same erection factors, fees, and contingencies as the Parsons plant estimate (i.e. boiler erection at 80 per cent of equipment supply costs, architect engineering/construction management/home office/fees at 10 per cent 134 of bare erected costs, and contingency, totaling 10 per cent, applied to the sum of items 1 and 2). 4.4.2.2 Oxygen Based PC Plant Costs In [7] Parsons presents conceptual designs of two plants that burned 2.5 per cent sulfur Illinois No. 6 coal with oxygen to facilitate CO2 capture/removal for pipeline transport to a sequestering site. Both plants used flue gas recirculation to control their boiler combustion temperatures and their CO2 rich exhaust gases were dried and compressed for pipeline transport. The first plant had a net power output of 132.2 MWe; its oxygen was supplied by a conventional, cryogenic ASU, and the gas flow to the CO2 processing unit totaled 422.3 Klb/hr. The oxygen was 99 per cent pure and it was delivered to an “air heater” at the boiler where 660ºF flue gas heated the oxygen to 610ºF for delivery to the boiler at a rate of 327.1 Klb/hr. In the FW study’s ASU based plant, the oxygen from the ASU is also heated by an “air heater” at the boiler but to 625ºF with 695ºF flue gas; aside from some slight temperature differences, the plant arrangements are similar and their ASUs differ primarily in size/through put. The second Parsons plant had a net output of 197.4 MWe; its oxygen was supplied at a rate of 398.8 Klb/hr by an ion transport membrane, and the gas flow to CO2 processing was 515.8 Klb/hr. The OITM operated with 200 psia air that was heated to 1652ºF via heat transfer surface placed in the boiler; the hot air was then delivered to the OITM for separation of the oxygen and nitrogen. The oxygen, with a purity of 100 per cent, was then delivered to the boiler, whereas, the nitrogen was passed through a hot gas expander followed by a heat recovery steam generator for power recovery. Excepting for differences in flow rates, the operating conditions of the Parsons OITM plant are essentially identical to the OITM based plant of the FW study. Praxair Inc, a developer of oxygen transport membranes, participated in the detailed Alstom/Parsons study [7] and, per the Acknowledgement section of their study report, provided detailed design, performance, and cost information on the OITM system. Aside from a difference in flow rate, the FW OITM operates at essentially the same pressure and temperature as that used in the Alstom/Parsons study and, hence, the FW system cost estimate was obtained by scaling their system capital costs. Consequently, individual OITM component designs were not developed in the FW study. It is assumed that Parsons/Praxair selected the operating conditions of the OITM to minimize the overall system cost. Such a sensitivity/optimization cost evaluation of the OITM plant design is beyond the scope of the FW study. Note that there are several variables, which have direct influence on the OITM plant cost and performance (see Sect. 4.2.2.3 for more details). These variables include O2 Recovery Percentage: CO2 removal power penalty is minimum at an O2 recovery of 85% (The Alstom/Parsons study uses a O2 recovery of 85%). 135 Air Pressure: Increasing air pressure reduces OITM size, but also reduces system efficiency. Optimum pressure depends on the relative cost of the OITM. OITM Temperature: Increasing OITM operating temperature will increase system efficiency, but will increase boiler air heater cost and presumably OITM cost. A detailed 14 account EPRI TAG cost estimate in year 2003 dollars was prepared by Parsons for each of the two plants; in these estimates the oxygen (ASU or OITM) and CO2 processing system costs appear, respectively, as separate sub-accounts under the Boiler and Accessories and Flue Gas Clean Up Accounts. Since the arrangement and scope of supply of these systems is essentially identical to that of the FW study’s O2fired plants, the Parsons costs were used to estimate the costs of Foster Wheeler’s two plants. The Parsons ASU system costs were scaled up based on oxygen flow rate raised to the 0.65 exponent and escalated to year 2006 dollars; comparison of the scaled up costs with a vendor supplied budget price yielded good agreement further validating the scale up exponent. Comparison of the gas processing system costs given for Parsons’ two plants, however, revealed a greater sensitivity to flow rate and resulted in a scaling exponent of 0.87; this exponent was then used to calculate the CO2 gas processing system costs of Foster Wheeler’s plants. The Table 4.4.4 air-fired reference plant cost estimate served as a starting point for the determination of O2 based plant costs. The cost of the air-fired PC boiler package was removed from the Parsons cost estimate and the new value, determined by Foster Wheeler for the particular plant configuration under study, was inserted. Then each balance of plant account and or component was individually scaled based on flow rate/output and adjusted, where necessary, to reflect design differences. Some examples of the changes that were made are removal of SCR systems, limestone systems, flue gas desulfurization systems, etc. and elimination of the stack from the ASU based plant. Table 4.4.5 and Table 4.4.6 present a detailed cost breakdown of the ASU based O2 plant (case-9B, Figure 4.1.9) and the OITM based O2-PC plant (case-18, Figure 4.2.10) and Table 4.4.7 compares the total costs of all three plants. Although the oxygenbased plants use flue gas recirculation to control the boiler combustion temperature, they operate with higher oxygen concentrations than the air-fired reference plant boiler. As a result they produce a higher combustion temperature and a lower flue gas flow rate, which reduce the size of the boiler and its downstream flue gas components. With the SCR eliminated and the flue gas flow rate reduced, the PC boiler cost of the ASU based plant is about $32 million less than that of the air-fired case. Despite additional savings associated with elimination of some systems/components (e.g. SCR, limestone, FGD, and stack plus a reduction in size of other components, i.e. baghouse filter, ducting, foundations, etc.), the total cost of the cryogenic ASU based plant is approximately $91 million higher than the air-fired plant because of the high cost of the ASU ($115.0 million) and CO2 processing systems ($111.5 million). 136 In the OITM based plant, the PC boiler not only meets the steam generation and heating needs of the steam cycle, but it also contains tubing that heats air to 1600ºF for delivery to the OITM. Although the boiler flue gas flow rate of the OITM based plant is about 25 per cent less than the air-fired plant, the cost savings it provides is more than negated by the high cost of the air heater tubing; as a result, the OITM based PC boiler costs $18 million more than that of the air-fired plant. The compressor required to pressurize OITM air to 200 psia, the OITM, the OITM associated heat exchangers and piping, the OITM power recovery system (hot gas expander and HRSG), and a larger CO2 gas processing system add additional costs to the plant; as a result, the OITM plant costs approximately 50 per cent more than the air-fired reference plant ($953.0 million versus $633.0 million) and approximately 32 per cent more than the cryogenic ASU based plant ($953.0 million versus $723.3 million). Since the OITM based plant operates with a higher electrical output than the cryogenic ASU based plant (463.3 MWe versus 347.0 MWe), its total plant costs on a dollar per kilowatt basis are slightly lower ($2.057/kW versus $2,084/kW) but much higher than the air-fired plant ($2,057/kW versus $1,471/kW). 137 Table 4.4.4 - Cost of 430.2 MWe Air-Fired Supercritical PC Plant ($1000 Yr 2006) Account # 1 2 Bare Erected Costs Account Title Contingency at 10% Total Plant Costs Coal & Sorbent Handling Coal Limestone 12,985 3,114 1,299 311 1,428 343 15,712 3,768 Coal Limestone 2,599 6,934 260 693 286 763 3,145 8,390 47,879 4,788 5,267 57,933 155,621 15,562 17,118 188,301 0 17,111 58,705 0 1,711 5,871 0 1,882 6,458 0 20,705 71,033 0 Coal and Sorbent Prep & Feed 3 Feedwater & Misc BOP Systems 4 Boiler and Accessories Boiler with SCR, Air Heater, Fans, Ducts, etc Oxygen Supply; None 5 Engr, C.M. H.O. & Feee at 10% Flue Gas Clean Up Baghouse & Accessories FGD CO2 Processing 6 Combustion Turbine & Accessories 7 HRSG, Ducting, & Stack 0 Duct Work Stack Foundations 9,094 9,774 1,456 909 977 146 1,000 1,075 160 11,004 11,827 1,762 8 Steam Turbine Generator 88,706 8,871 9,758 107,334 9 Cooling Water System 24,540 2,454 2,699 29,693 10 Slag/Ash Handling Systems 7,746 775 852 9,373 11 Accessory Electric Plant 27,500 2,750 3,025 33,275 12 Instrumentation & Control 12,237 1,224 1,346 14,807 13 Improvements to Site 7,773 777 855 9,405 14 Buildings & Structures 29,353 2,935 3,229 35,517 523,126 52,313 57,544 632,984 Totals $/kW 138 1,471 Table 4.4.5 - Cost of 347.0 MWe ASU Based Supercritical PC Plant ($1000 Yr 2006) Account # Bare Erected Costs Account Title 1 Coal Handling 2 Coal Prep & Feed 3 Feedwater & Misc BOP Systems 4 Boiler and Accessories Boiler with Air Heater, Fans, Ducts, etc Oxygen Supply: ASU 5 Engr, C.M. H.O. & Feee at 10% Contingency at 10% Total Plant Costs 12,692 1,269 1,396 15,357 2,540 254 279 3,074 47,879 4,788 5,267 57,933 129,052 12,905 14,196 156,153 115,005 * 12,102 1,210 1,331 14,643 0 111,493 * Flue Gas Clean Up Baghouse & Accessories FGD CO2 Processing 6 Combustion Turbine & Accessories 0 7 HRSG, Ducting, & Stack Duct Work and Foundations Stack HRSG 6,432 643 707 7,782 0 0 8 Steam Turbine Generator 88,706 8,871 9,758 107,334 9 Cooling Water System 25,966 2,597 2,856 31,419 10 Slag/Ash Handling Systems 7,281 728 801 8,810 11 Accessory Electric Plant 27,885 2,789 3,067 33,741 12 Instrumentation & Control 12,408 1,241 1,365 15,014 13 Improvements to Site 7,882 788 867 9,537 14 Buildings & Structures 29,764 2,976 3,274 36,014 41,059 45,165 723,310 Totals $/kW 2,084 *Values Scaled from Parsons /Alstom Year 2003 Study and Escalated to 2006 at 5% per Year 139 Table 4.4.6 - Cost of 463.3 MWe OITM Based Supercritical PC Plant ($1000 Yr 2006) Account # Bare Erected Costs Account Title 1 Coal Handling 2 Coal Prep & Feed 3 Feedwater & Misc BOP Systems 4 Boiler and Accessories Boiler, Air Heater, Fans, Ducts, etc Oxygen Supply: OTM 5 Engr, C.M. H.O. & Feee at 10% Contingency at 10% Total Plant Costs 14,434 1,443 1,588 17,465 2,889 289 318 3,496 47,879 4,788 5,267 57,933 170,902 17,090 18,799 206,791 188,031 * 14,113 1,411 1,552 17,077 0 131,662 * Flue Gas Clean Up Baghouse & Accessories FGD CO2 Processing 6 Combustion Turbine & Accessories 7 HRSG, Ducting, & Stack 48,627 * Duct Work Stack Foundations HRSG 7,501 750 825 9,076 2,680 * 205 * 18,420 * 8 Steam Turbine Generator 88,706 8,871 9,758 107,334 9 Cooling Water System 29,489 2,949 3,244 35,682 10 Slag/Ash Handling Systems 8,344 834 918 10,097 11 Accessory Electric Plant 29,101 2,910 3,201 35,212 12 Instrumentation & Control 12,949 1,295 1,424 15,668 13 Improvements to Site 8,225 823 905 9,953 14 Buildings & Structures 31,061 3,106 3,417 37,584 46,559 51,215 952,993 Totals $/kW *Values Scaled from Parsons /Alstom Year 2003 Study and Escalated to 2006 at 5% per Year 140 2,057 Table 4.4.7 - Comparison of Total Plant Costs ($1000 Yr 2006) Reference Air-Fired Plant Net Power Output, MWe ASU Based Plant OITM Based Plant 430.2 347.0 463.3 319.0 26.0 33.0 3556.0 0.0 308.0 0.0 30.0 2087.0 774.0 375.4 0.0 37.0 2644.0 936.0 1696.0 1850.0 2250.0 Flow Rates, Klb/hr Coal Limestone Ash Boiler Flue Gas Gas to CO2 Processing Condenser Duty, MMBtu/hr Account # 1 2 Account Title Plant Costs by Account Coal and Limestone Handling Coal Limestone 15,712 3,768 15,357 0 17,465 0 Coal Limestone 3,145 8,390 3,074 0 3,496 0 57,933 57,933 57,933 188,301 156,153 115,005 206,791 188,031 20,705 71,033 0 14,643 0 111,493 17,077 0 131,662 0 0 48,627 11,004 11,827 1,762 0 7,782 0 in duct work 0 9,076 2,680 205 18,420 107,334 107,334 107,334 29,693 31,419 35,682 9,373 8,810 10,097 Coal and Limestone Prep & Feed 3 Feedwater & Misc BOP Systems 4 Boiler and Accessories Boiler, SCR*, Air Heater, Fans, Ducts, etc Oxygen Supply 5 Flue Gas Clean Up Baghouse & Accessories FGD CO2 Processing 6 Combustion Turbine & Accessories 7 HRSG, Ducting, & Stack Duct Work Stack Foundations HRSG 8 Steam Turbine Generator 9 Cooling Water System 10 Slag/Ash Handling Systems 11 Accessory Electric Plant 33,275 33,741 35,212 12 Instrumentation & Control 14,807 15,014 15,668 13 Improvements to Site 9,405 9,537 9,953 14 Buildings & Structures 35,517 36,014 37,584 632,984 723,310 952,993 Totals $/kW 141 1,471 2,084 2,057 4.4.3 Total Plant Investment (TPI) The TPI at date of start-up includes escalation of construction costs and allowance for funds used during construction (AFUDC). AFUDC includes interest during construction as well as a similar concept for timing of equity funds over the construction period. TPI is computed from the TPC based on a linear draw down schedule and the compounded interest (or implied equity rate) in the percentages of debt and equity. Draw down was over the assumed 48-month construction schedule for all three plants. As the analysis is done in constant 2006 dollars, no escalation was applied. The full AFUDC is used in calculating returns on debt and equity, but only the interest during construction is included in the depreciation base. 4.4.4 Total Capital Requirement (TCR) The TCR includes all capital necessary to complete the entire project. TCR consists of TPI, prepaid royalties, pre-production (or start-up) costs, inventory capital, initial chemical and catalyst charge, and land cost: • • • • Royalty Costs have been assumed to be zero, as none apply. Start-Up/Pre-Production Costs are intended to cover operator training, equipment checkout, extra maintenance, and use of fuel and other materials during plant start-up. They are estimated as follows: - Hiring and phasing-in prior to and during start up of operating and maintenance labor, administrative and support labor, variable operating costs ramped up to full capacity (including fuel, chemicals, water, and other consumables and waste disposal charges. These variable costs are assumed to be compensated by electric energy payments during the start up period. - Costs of spare parts usage, and expected changes and modifications to equipment that may be needed to bring the plant up to full capacity. Inventory capital is the value of inventories of fuel, other consumables, and by-products, which are capitalized and included in the inventory capital account. The inventory capital is estimated as follows: - Fuel inventory is based on full-capacity operation for 30 days. - Inventory of other consumables (excluding water) is normally based on full-capacity operation for the same number of days as specified for the fuel. - ½ percent of the TPC equipment cost is included for spare parts. Initial catalyst and chemical charge covers the initial cost of any catalyst or chemicals that are contained in the process equipment (but not in storage, which is covered in inventory capital). No value is shown because costs are assumed to have been included in the component equipment capital cost. 1. Land cost is based on 100 acres of land at $1,600 per acre. 142 4.4.5 Operating Costs And Expenses Operating costs were expressed in terms of the following categories: • • • • • Operating Labor Maintenance Cost - Maintenance labor - Maintenance materials Administrative and Support Labor Consumables Fuel Cost These values were calculated consistent with EPRI TAG methodology. All costs were based on a first year basis in January 2006 dollars. The first year costs do not include start-up expenses, which are included in the TCR. The cost categories listed above are calculated, on a dollars per year basis, as follows: • Operating labor is calculated by multiplying the number of operating personnel with the average annual (burdened) compensation per person. • Maintenance costs are estimated to be 2.2% of the TPC and are divided into maintenance labor and maintenance materials - Maintenance labor is estimated to be 40% of the total maintenance cost Maintenance materials are estimated to be 60% of the total maintenance cost • Administrative and support labor is estimated to be equal to 30% of the sum of operating and maintenance labor. • Consumables are feedstock and disposal costs calculated from the annual usage at 100 per cent load and 85 per cent capacity factor. The costs is expressed in year 2006 dollars and levelized over 20 years on a constant dollar basis. Fuel cost is calculated based on a coal delivered cost of $1.34/MMBtu. Fuel cost is determined on a first year basis and levelized over 20 years on a constant dollar basis. The calculation of first year fuel costs is done as follows: Fuel (tons/day) = Full Load Coal Feed Rate (lb/hr) x 24 hr/day / 2000 lbs/ton Fuel Unit Cost ($/ton) = HHV (Btu/lb) x 2000 lb/ton 143 Fuel Cost (1st year) = Fuel (tons/day) x Fuel Unit Cost ($/ton) x 365 day/yr x 0.85 (CF) The operating and maintenance costs, excluding fuel and consumables, are combined and divided into two components: 1) 90 per cent for Fixed O&M, which is independent of power generation, and 2) 10 per cent for Variable O&M, which is proportional to power generation. 4.4.6 Cost Of Electricity (COE) The COE value is made up of contributions from the capital cost (called the carrying charge), operating and maintenance costs, consumables, and fuel costs. The following relationship is used to calculate COE from these cost components: COE = LCC + LFOM x 100/(8760 x CF) + LVOM + LCM +LFC LCC = Levelized carrying charge, ¢/kWh LFOM = Levelized fixed O&M, $/kW-yr LVOM = Levelized variable O&M, ¢/kWh LCM = Levelized consumables, ¢/kWh LFC = Levelized fuel costs, ¢/kWh CF = plant capacity factor (0.85) The CO2 mitigation cost (MC) shows the cost impact, in dollars per tonne of CO2 that would otherwise be emitted, of a configuration that allows CO2 capture relative to the air-fired reference plant. The MC is calculated as follows: MC = COEwith removal - COEreference x 0.01 $/¢ Ereference – Ewith removal COE = Cost of electricity in ¢/kWh E = CO2 emission in tonnes/kWh The capital investment and revenue requirements of the three plants are presented in detail in Table 4.4.8 through Table 4.4.10 and summarized in Table 4.4.11. With the oxygen based plants having higher total plant costs than the air-fired reference plant, their interest during construction is higher and they have higher total plant investment costs; start-up and working capital costs, which are somewhat related to total plant costs are also higher and yield total capital requirement costs that are 14 and 51 per cent higher than the air-fired plant. 144 The air-fired reference plant incorporates an ammonia based SCR and a limestone based scrubber to control its NOx and SOx emissions. Although these systems are not required with the oxygen based plants, the latter incorporates oxygen supply and CO2 processing systems. Since the number of systems added equaled the number deleted, it was assumed, in the absence of a detailed staffing study, that all three plants required the same number of operating personnel. Although operator costs are identical, maintenance and administration costs, which key off of total plant costs, are higher for the oxygen-based plants. The consumable requirements of the three plants are given in Table 4.4.12. With the SCR and scrubber systems deleted, the consumable costs of the oxygenbased plants are lower (ammonia and limestone costs are eliminated), but because of their lower efficiency, their fuel costs are higher (per net MWe). The higher fuel and higher operating and maintenance costs exceed the lower consumable cost savings and, as a result, the ASU and OITM plants have higher 20 year levelized production costs of $24.42/MWhr and $22.27/MWhr, respectively, versus $20.93/MWhr for the air-fired plant. When added to their respective higher capital carrying costs of $41.75/MWhr and $41.21/MWhr versus $29.48/MWhr, their costs of electricity of $66.17/MWhr and $63.48/MWhr are 31 and 26 per cent higher than the air-fired reference plant at $50.41/MWhr (see Figure 4.4.1). The breakdown of the COE for the three plants is summarized in Figure 4.4.2, where plant capital cost is divided into CO2 Processing, ASU, Turbines, Boiler, and Balance of Plant (BOP). The CO2 mitigation costs of the ASU and OITM based plants were calculated to be $20.23 and $16.77 per tonne of CO2 sent to the pipeline for sequestering (not including transportation cost). With the OITM based plant offering the promise of a lower CO2 mitigation cost, this analysis has shown that reducing the costs of both the oxygen supply and the CO2 processing systems are a key to reducing both the cost of electricity and CO2 mitigation costs of these sequestration ready power plants. 4.4.7 Tube Weld Overlay As discussed in Section 4.3.4 tube wall weld overlays may be required to mitigate furnace waterwall corrosion. Conservatively assuming weld overlay is applied to the entire furnace adds approximately $7.5 million to the total plant cost. This increases the COE of the cryogenic O2-PC to 66.7 $/MWhr (increase of 0.75%) and the MC to $20.8 per tonne (increase of 3.0%). The weld overlay increases the COE of the OITM O2-PC to 63.7 $/MWhr (increase of 0.3%) and the MC to $17.0 per tonne (increase of 1.5%). Utilizing weld overlays would be more cost effective in mitigating corrosion than FGD since adding an FGD system (upstream of the recycle split) would increase the COE by approximately 9%. Note that adding an FGD system downstream of the recycle split (to remove SOx from the pipeline) would increase the COE by approximately 6%. 145 4.4.8 Reduced Pipeline Pressure The analysis performed herein was conservatively performed for a pipeline pressure of 3000 psia. The Reference 14 guidelines specify a pipeline pressure of 2200 psia. At 2200 psia system efficiency is increased by 0.1% and COE is reduced by 0.3%. The economic effects of adding tube overlay and reducing the pipeline pressure are shown in Table 4.4.13. 146 Table 4.4.8 - Air Fired PC Plant Capital Investment & Revenue Requirement TITLE/DEFINITION Case: Plant Size: Fuel (type): Design/Construction: TPC (Plant Cost) Year: Capacity Factor: Air Fired 430.2 MWe (net) Illinois No 6 Coal 48 Months Jan-06 85.0% CAPITAL INVESTMENT: TOTAL PLANT COST AFUDC TOTAL PLANT INVESTMENT Royalty Allowance Start Up Costs Working Capital Debt Service Reserve TOTAL CAPITAL REQUIREMENT OPERATING & MAINTENANCE COSTS (2006) Operating Labor Maintenance Labor Maintenance Material Administrative & Support Labor TOTAL OPERATION & MAINTENANCE (2006) FIXED O&M (2006) VARIABLE O&M (2006) CONSUMABLE OPERATING COSTS, LESS FUEL (2006) Water and Treatment Limestone Ash Disposal Ammonia Other Consumables TOTAL CONSUMABLES (2006) Steam Turbine: Net Efficiency: Fuel Cost: Book Life: 4005psig/1076F/1112F 39.5 % HHV $1.34/MMBtu 20 Years $x1000 632,982 105,458 732,440 $/kW 1,471 1,717 0 16,458 4,795 0 759,693 1,815 4,921 5,570 8,355 3,147 21,994 19,795 2,199 1,297 1,452 2,423 1,768 1,005 7,945 0 BY-PRODUCT CREDITS (2006) FUEL COST (2006) Coal FUEL COST (2006) 37,131 st PRODUCTION COST SUMMARY Fixed O&M Variable O&M Consumables By-Product Credit Fuel TOTAL PRODUCTION COST (2006) LEVELIZED 20 YEAR CARRYING CHARGES (Capital)* LEVELIZED 20 YEAR BUSBAR COST OF POWER *Levelized Fixed Charge Rate = 12.5% 147 1 Year (2010)) $/MWhr 6.18 0.69 2.48 0.00 11.59 20.94 20 Year Levelized $/MWhr 6.18 0.69 2.48 0.00 11.59 20.93 29.48 50.41 Table 4.4.9 - ASU Based PC Plant Capital Investment & Revenue Requirement TITLE/DEFINITION Case: Plant Size: Fuel (type): Design/Construction: TPC (Plant Cost) Year: Capacity Factor: Oxygen by ASU 347.0 MWe (net) Illinois No 6 Coal 48 Months Jan-06 85.0% CAPITAL INVESTMENT: TOTAL PLANT COST AFUDC TOTAL PLANT INVESTMENT Royalty Allowance Start Up Costs Working Capital Debt Service Reserve TOTAL CAPITAL REQUIREMENT OPERATING & MAINTENANCE COSTS (2006) Operating Labor Maintenance Labor Maintenance Material Administrative & Support Labor TOTAL OPERATION & MAINTENANCE (2006) FIXED O&M (2006) VARIABLE O&M (2006) CONSUMABLE OPERATING COSTS, LESS FUEL (2006) Water and Treatment Limestone Ash Disposal Ammonia Other Consumables TOTAL CONSUMABLES (2006) Steam Turbine: Net Efficiency: Fuel Cost: Book Life: 4005psig/1076F/1112F 33.0 % HHV $1.34/MMBtu 20 Years $x1000 723,310 120,507 843,818 $/kW 2,084 2,432 0 18,806 5,480 0 868,103 2,502 4,921 6,365 9,548 3,386 24,220 21,798 2,422 898 0 1,111 0 1,005 3,014 0 BY-PRODUCT CREDITS (2006) FUEL COST (2006) Coal FUEL COST (2006) 35,851 st PRODUCTION COST SUMMARY Fixed O&M Variable O&M Consumables By-Product Credit Fuel TOTAL PRODUCTION COST (2006) LEVELIZED 20 YEAR CARRYING CHARGES (Capital)* LEVELIZED 20 YEAR BUSBAR COST OF POWER *Levelized Fixed Charge Rate = 12.5% 148 1 Year (2010)) $/MWhr 8.43 0.94 1.17 0.00 13.88 24.42 20 Year Levelized $/MWhr 8.43 0.94 1.17 0.00 13.88 24.42 41.75 66.17 Table 4.4.10 - OITM Based PC Plant Capital Investment & Revenue Requirement TITLE/DEFINITION Case: Plant Size: Fuel (type): Design/Construction: TPC (Plant Cost) Year: Capacity Factor: Oxygen by Ion Transport Membrane 463.3 MWe (net) Illinois No 6 Coal 48 Months Jan-06 85.0% Steam Turbine: Net Efficiency: Fuel Cost: Book Life: CAPITAL INVESTMENT: TOTAL PLANT COST AFUDC TOTAL PLANT INVESTMENT Royalty Allowance Start Up Costs Working Capital Debt Service Reserve TOTAL CAPITAL REQUIREMENT OPERATING & MAINTENANCE COSTS (2006) Operating Labor Maintenance Labor Maintenance Material Administrative & Support Labor 36.1 % HHV $1.34/MMBtu 20 Years $x1000 952,993 158,774 1,111,767 2,400 0 24,778 7,220 0 1,143,764 2,469 $/kW 2,057 4,921 8,386 12,579 3,992 TOTAL OPERATION & MAINTENANCE (2006) FIXED O&M (2006) VARIABLE O&M (2006) 29,879 26,891 2,988 CONSUMABLE OPERATING COSTS, LESS FUEL (2006) Water and Treatment Limestone Ash Disposal Ammonia Other Consumables TOTAL CONSUMABLES (2006) 899 0 1,356 0 1,005 3,259 0 BY-PRODUCT CREDITS (2006) FUEL COST (2006) Coal 4005psig/1076F/1112F FUEL COST (2006) 43,696 st PRODUCTION COST SUMMARY Fixed O&M Variable O&M Consumables By-Product Credit Fuel TOTAL PRODUCTION COST (2006) LEVELIZED 20 YEAR CARRYING CHARGES (Capital)* LEVELIZED 20 YEAR BUSBAR COST OF POWER *Levelized Fixed Charge Rate = 12.5% 149 1 Year (2010)) $/MWhr 7.79 0.86 0.94 0.00 12.67 22.27 20 Year Levelized $/MWhr 7.79 0.86 0.94 0.00 12.67 22.27 41.21 63.48 Table 4.4.11 - Summary of Plant Economics and CO2 Mitigation Costs Reference Air-Fired Plant ASU Based Plant OITM Based Plant Net Power Output, MWe 430.2 347.0 463.3 Efficiency, % (HHV) 39.5 33.0 36.1 Coal Flow, Klb/hr 319.0 308.0 375.4 718.0 0.939 866.0 0.848 633.0 1,471 723.3 2,084 953.0 2,057 Total Capital Requirement in Millions of Dollars 760.0 868.1 1143.8 Levelized Production Costs, $/MWhr Operating & Maintenance Consummables Fuel Total 6.86 2.48 11.59 20.93 9.37 1.17 13.88 24.42 8.66 0.94 12.67 22.27 Levelized Capital Carrying Charges, $/MWhr 29.48 41.75 41.21 Levelized COE, $/MWhr 50.41 66.17 63.48 20.23 16.77 CO2 to Stack Klb/hr Tonnes/MWhr 739.0 0.779 CO2 to Pipe Line Klb/hr Tonnes/MWhr Total Plant Cost Millions of Dollars $/kW CO2 Mitigation Cost, $/tonne 150 Table 4.4.12 - Plant Daily Consumable Requirements Air-Fired 3,483 17,041 312 25 371 Cryogenic ASU 2,414 17,041 0 0 358 Fuel, tons/day 3,828 3,696 4,505 Fuel, lbs/hr/MWe Fuel, Btu/hr/kWe 741.5 8625 887.6 10324 810.3 9424 Water, 1000s gal/day Water Treatment Chemicals, lbs/day Limestone, tons/day Ammonia (28% NH3), tons/day Ash Disposal, tons/day 151 OITM 2,414 17,041 0 0 437 Figure 4.4.1 – Increase in COE of O2 Plant Above Air-Fired Reference Plant 35.0% Increase in COE 30.0% 25.0% 20.0% 15.0% 10.0% 5.0% 0.0% Cryogenic ASU OITM 152 Figure 4.4.2 – COE Breakdown 7.00 6.00 COE (cents/kwh) 5.00 CO2 Processing ASU BOP Turbines Boiler Consumables O&M Fuel 4.00 3.00 2.00 1.00 0.00 Air Cryogenic 153 OITM Table 4.4.13 – COE and CO2 MC with Weld Overlay and 2200 psi Pressure Reference Air-Fired Plant ASU Based Plant OITM Based Plant 50.4 66.2 66.7 66.5 63.5 63.7 63.6 20.2 20.8 20.6 16.8 17.1 16.8 Levelized COE, $/MWhr Base With tube overlay & 3000 psi pipeline pressure With tube overlay & 2200 psi pipeline pressure CO2 Mitigation Cost, $/tonne Base With tube overlay & 3000 psi pipeline pressure With tube overlay & 2200 psi pipeline pressure 154 4.4.9 Comparison with Other Technologies An economic comparison was performed between the O2-PC and other competing CO2 removal technologies. For comparison the following alternate technologies were chosen: Air PC: Supercritical PC plant with post-combustion CO2 mitigation (Ref. [15] case 12). NGCC: Natural Gas Combined Cycle with post combustion (Ref. [15] case 14). IGCC: Integrated Gasification Combined Cycle with pre-combustion CO2 mitigation (Ref. [15] case 4). SUB O2PC: Oxygen-fired subcritical PC (Ref. [3]). The economics of these technologies were compared with the supercritical O2PC using both the levelized cost of electricity and the CO2 mitigation cost as indexes. The CO2 mitigation cost (MC) shows the cost impact, in dollars per tonne of CO2 that would otherwise be emitted, of a configuration that allows CO2 capture relative to the reference plant. The COE and MC for the Air PC, NGCC, and IGCC were obtained from Ref. 15. Since the economic analysis of Ref. 15 were made for a larger power plant (480550 MWe net power) they were scaled to a 30% smaller power plant to be consistent with the supercritical O2-PC analyzed herein. The COE and MC for the subcritical O2-PC were obtained from Ref. 3 and adjusted from 2004 to 2006 dollars and from a coal cost of $1.14/MMBtu to $1.34/MMBtu. Figure 4.4.3 and Figure 4.4.4 present a comparison of the COE and MC using an 85% capacity factor. Compared to the COE of the supercritical cryogenic O2-PC, the COE for the other technologies is 52% higher for Air PC, 35% higher for NGCC, 15% higher for IGCC, and 5% higher for the subcritical O2-PC, and 4% lower for the supercritical O2-PC with OITM. Compared to the MC of the supercritical cryogenic O2-PC, the MC for the other technologies is 238% higher for NGCC, 192% higher for Air PC, 25% higher for IGCC, 5% higher for the subcritical O2-PC, and 17% lower for the supercritical O2-PC with OITM. Since based on operating experience an 85% capacity factor for IGCC technology appears too optimistic, the COE and MC with a 70% capacity factor is also shown in Figure 4.4.3 and Figure 4.4.4 (COE is increased by 16% and MC by 18%). 155 Figure 4.4.3 - Comparison of Levelized Cost of Electricity Among Alternative Technologies 12.0 Levelized COE, c/kWh 10.0 70% CF 8.0 6.0 4.0 2.0 0.0 Air PC NGCC Post Comb. Post Comb. IGCC Pre Comb. O2 PC Sub O2-Fired O2 PC ASU O2 PC OITM O2-Fired O2-Fired Figure 4.4.4 - Comparison of Mitigation Costs Among Alternative Technologies Mitigation Cost, $/tonne of CO2 80.00 70.00 60.00 50.00 40.00 30.00 70%CF 20.00 10.00 0.00 NGCC Air PC Post Comb. Post Comb. IGCC O2 PC Sub Pre Comb. O2-Fired 156 O2 PC ASU O2 PC OITM O2-Fired O2-Fired 5.0 Conclusion To assure continued U.S. power generation from its abundant domestic coal resources, new coal combustion technologies must be developed to meet future emissions standards, especially CO2 sequestration. Current conventional coalfired boiler plants burn coal using 15-20% excess air producing a flue gas, which is only approximately 15% CO2. Consequently, CO2 sequestration requires noncondensable gases stripping, which is both expensive and highly powerconsumptive. Several different technologies for concentrating the CO2 by removing the non-condensable gases have been proposed including aminebased absorption and membrane gas absorption. However, these techniques require substantial energy, typically from low-pressure steam. A new boiler is presented where the combustion air is separated into O2 and N2 and the boiler uses the O2, mixed with recycled flue gas, to combust the coal. The products of combustion are thus only CO2 and water vapor. The water vapor is readily condensed, yielding a pure CO2 stream ready for sequestration. The CO2 effluent is in a liquid form and is piped from the plant to the sequestration site. The combustion facility is thus truly a zero emission stackless plant. A conceptual design of a CO2 sequestration-ready oxygen-based 460 MWe supercritical PC boiler plant was developed. The selected O2-fired design case has a system efficiency of 32.9% compared to the air-fired system efficiency of 39.5%. The efficiency and cost-effectiveness of carbon sequestration in oxygen-firing boilers can be optimized by specifically tailoring boiler design by appropriate surface location, combustion system design, material selection, furnace layout, and water/steam circuitry. Boiler efficiencies of near 100% can be achieved by recovery of virtually all of the flue gas exhaust sensible heat. Boiler size can be drastically reduced due to higher radiative properties of O2-combustion versus air-combustion. Furthermore, a wider range of fuels can be burned due to the high oxygen content of the combustion gas and potential for high coal preheat. A conceptual design of a CO2 sequestration-ready oxygen-based 460 MWe supercritical PC boiler plant was developed with integration of advanced oxygen separation techniques, such as OITM and CAR. The optimized OITM O2-fired design case has a CO2 removal specific power penalty of 42 kWh/klbCO2 and a system efficiency of 36.1% compared to the air-fired system efficiency of 39.5%. Considering that CO2 compression itself consumes 40 kWh/klbCO2, the OITM integration into the O2-PC is a breakthrough in CO2 removal. The CAR process efficiency loss and specific power penalty lies approximately midway between the cryogenic ASU and OITM. The O2-fired PC CO2 removal penalty with integration of OITM is nearly a quarter of that from post combustion CO2 removal technologies, and only a half of IGCC. 157 OITM faces significant challenges with respect to the manufacture and stability of membranes, and scale up and design of large plants. A design and analysis of a reference air-fired boiler, an oxygen-fired boiler with cryogenic ASU, and an oxygen-fired boiler with oxygen ion transport membrane were performed. The O2-PC supercritical boiler incorporates the OTU BENSON vertical technology, which uses low fluid mass flow rates in combination with optimized rifled tubing. The following conclusions are made comparing the airfired furnace with the oxygen-fired furnace design and performance: 1. The oxygen furnace has only approximately 65% of the surface area and approximately 45% of the volume of the air-fired furnace due to the higher heat flux of the oxygen-fired furnace. 2. Due to the higher O2 concentration of the oxygen-fired furnace versus the air-fired furnace (40% vs. 21%), the maximum flame temperature of the oxygen-fired furnace is approximately 500°F higher. 3. Maximum wall heat flux in the oxygen-fired furnace is about 2.5 times that of the air-fired furnace (175,000 Btu/hr-ft2 vs. 70,000 Btu/hr-ft2) due to the higher flame temperature and higher H2O and CO2 concentrations. 4. 100% coal burnout is achieved in the oxygen-fired furnace (compared to 99.6% burnout in the air-fired furnace) due to higher furnace temperature and higher concentration of oxygen. The burnout differential between the oxygen-fired boiler and the air-fired boiler is expected to be significantly greater when harder to burn fuels are fired. 5. The higher heat flux of the oxygen-fired furnace significantly increases the maximum waterwall temperature (from 870°F for the air-fired furnace to 1060°F for the oxygen-fired furnace) requiring the material to be upgraded from T2 to T92. 6. NOx is reduced by oxygen firing (compared to air-firing) by about a factor of two from 0.38 lb/MMBtu to 0.18 lb/MMBtu. 7. A pressure equalization header is included at an elevation of 80’ to ensure stable operation at low loads. 8. The total heat transfer surface required in the HRA is 35% less than the air-fired HRA due to more heat being absorbed in the oxygen-fired furnace and the greater molecular weight of the oxygen-fired flue gas. To minimize the required surface area, the HRA design is in series for the cryogenic ASU O2-PC and parallel for the OITM O2-PC. 158 9. To reduce the corrosion in the O2-PC, weld overlays with high Nickel and Chromium contents (e.g. alloy 622) are applied to the waterwalls. This reduces the predicted maximum corrosion from 45 mil/yr to 10 mil/yr. 10. The required HRA tube materials and wall thicknesses are nearly the same for the air-fired and oxygen-fired design since the flue gas and water/steam temperature profiles encountered by the heat transfer banks are similar. 11. A tubular convective air heater is included in the OITM O2-PC to provide the necessary air heating for the membrane separation process. The furnace air heater is an Incoloy MA956 three-pass tubular design situated above the furnace nose. The levelized cost of electricity of the supercritical pressure, air-fired reference plant was calculated to be $50.41/MWhr and it operated with an efficiency of 39.5 per cent. The oxygen supply and CO2 gas processing systems required by the oxygen-based plants significantly increase their plant costs and parasitic power requirements. The cryogenic ASU based plant had a cost of electricity of $66.17/MWhr and an efficiency of 33.0 per cent. The oxygen transport membrane of the OITM based plant operates at 200 psia with air heated to 1600ºF via tubes placed in the boiler. The high cost of this boiler tubing, together with piping, heat exchangers, and the oxygen transport membrane itself, add considerable costs to the plant. Since the nitrogen exhausting from the membrane is hot and at pressure, it can be used for power recovery via a hot gas expander and HRSG. Although addition of these components further increases plant costs, the added power they provide increases the plant efficiency to 36.1 per cent and enables the OITM based plant to operate with a cost of electricity that is less than that of the ASU based plant e.g. $63.48/MWhr versus $66.17/MWhr. As a result the CO2 mitigation cost of the OITM based plant was calculated to be less than that of the ASU based plant e.g. $15.66/tonne versus $17.06/tonne, respectively. The addition of weld overlay increases the COE approximately 0.75%, but reducing the pipeline pressure from 3000 psia to 2200 psia (specified in Ref. 14) reduces the COE by 0.3%. Thus, the combined effect of these two adjustments on the COE is relatively small (+0.4% for cryogenic O2-PC and +0.1% for the OITM O2-PC). The oxygen supply and the CO2 gas processing systems have a major impact on the economics and efficiency of oxygen-based plants. Additional R&D aimed at improving these systems, especially OITMs, is necessary to improve both electricity costs and CO2 mitigation costs. The O2-fired PC CO2 removal penalty is nearly half that of post combustion CO2 removal technologies and 15% to 30% than that of IGCC pre-combustion 159 capture. Furthermore, of the CO2 sequestration-ready technologies, the O2-fired PC is the simplest, requires the least modification of existing proven designs, and requires no special chemicals for CO2 separation. Thus CO2 sequestration with an oxygen-fired combustion plant can be performed in a proven reliable technology while maintaining a low-cost high-efficiency power plant. As new lower power-consuming air separation techniques, such as membrane separation, become commercially available for large-scale operation in O2-fired plants, the CO2 removal power consumption and efficiency reduction will continue to decline. 160 6.0 References 1. White, J.S., Buchanan, T.L., Schoff, R.L. (Parsons); Stiegel, G. (DOE); Holt, N.A., Booras G. (EPRI); Wolk, R. (WITS), “Evaluation of Innovative Fossil Fuel Power Plants with CO2 Removal”, EPRI Report No. 1000316, December 2000. 2. Wilkinson, M., Boden, John (BP), Panesar, R. (Mitsui Babcock), Allam, R. (Air Products), “CO2 Capture Via Oxygen Firing: Optimisation of a Retrofit Design Concept for a Refinery Power Station Boiler”, First National Conference on Carbon Sequestration, May 15-17, 2001, Washington DC. 3. Seltzer, Andrew and Fan, Zhen, Conceptual Design of Oxygen-Based PC Boiler, DOE # DE-FC26-03NT41736, September 2005. 4. Philip A. Armstrong, E.P. Foster, Dennis A Horazak, Harry T Morehead, VanEric E. Stein, “Ceramic and Coal: ITM Oxygen for IGCC”, The 22nd Pittsburgh Coal Conference, Sept.11-15, 2005, Pittsburgh, USA 5. Divyanshu Acharya, Krish R. Krishnamurthy, Michael Leison, Scott MacAdam, Vijay K. Sethi, Marie Anheden, Kristin Jordal, Jinying Yan, “Development of a High Temperature Oxygen Generation Process and Its Application to Oxycombustion Power Plants with Carbon Dioxide Capture”, ibid 6. A.A. Leontiou, A.K. Ladavos, T.V. Bakas, T.C. Vaimakis, & P.J. Pomonis, “Reverse uptake of oxygen from La1-xSrx(Fe3+/Fe4+)O3 perovskite-type mixed oxides”, Applied Catalyst A: General 241 (2003) p143-154. 7. “Greenhouse Gas Emissions Control By Oxygen Firing In Circulating Fluidized Bed Boilers: Phase 1 – A Preliminary Systems Evaluation”, Alstom Power Inc. Power Plant Laboratories, PPL Report No. PPL-03CT-09, DOE/NETL Cooperative Agreement No. DE-FC26-01NT41146, May 15, 2003. 8. Philip A. Armstrong, “Method for Predicting Performance of an Ion Transport Membrane Unit-Operation”, Air Products and Chemicals, Inc. 9. FW-FIRE, Fossil-fuel Water-walled Furnace Integrated Reaction Emission, Theory and User’s Manual, Foster Wheeler Development Corp., 11/30/99. 10. HEATEX Computer Program, “A Program to Determine the Thermal/Hydraulic Performance of Gas-Cooled Heat Exchangers”, Revision 24, Foster Wheeler Corporation. 161 11. EMISS Computer Program, “A Program Emissivity”, Foster Wheeler Corporation. to Determine Gaseous 12. STADE2 Computer Program, ”Calculation Program for Pressure Drop and Heat Transfer in Tubes”, Siemens, Version 4.40. 13. DYNASTAB Computer Program, “Dynamic Stability of the Flow through Evaporator Heating Tubes in Fossil Fired Steam Generators”, Siemens, Version 1.1. 14. “Carbon Capture and Sequestration System Analysis Guidelines”, DOE/NETL, April 2005. 15. “2006 Cost and Performance Comparison of Fossil Energy Power Plants”, DOE/NETL-401/053106, Draft Final May 2006. 16. “Task 1 Topical Report - IGCC Plant Cost Optimization”, Gasification Plant Cost and Performance Optimization, DOE/NETL Contract No. DE-AC2699FT40342, May 2002. 162 7.0 Bibliography N/A 163 8.0 List of Acronyms and Abbreviations ASU BOP CAR CDT CF CFD COE DNB E EPRI FD FEGT FGD FW FW-FIRE GT HHV HIPPS HRA HRSG ID IGCC LCC LCM LFC LFOM LHV LMPD LMTD LOI LP LVOM MC NGCC NOx O&M OD OFA OITM OTU PC PFBC PSA RH Air Separation Unit Balance of Plant Ceramic auto-thermal recovery Compressor discharge temperature Capacity Factor Computational fluid dynamics Cost of Electricity Departure from nucleate boiling Emission of CO2 Electric Power Research Institute Forced draft Furnace exit gas temperature Flue Gas Desulfurization Foster Wheeler Fossil fuel, Water-walled Furnace Integrated Reaction and Emission Simulation Gas turbine Higher Heating Value High performance power system Heat recovery area Heat Recovery Steam Generator Induced draft Integrated gasification combined cycle Levelized Carrying Charge Levelized Consumables Levelized Fuel Costs Levelized Fixed O&M Lower Heating Value Log mean pressure difference Log mean temperature difference Loss on ignition Low pressure Levelized Variable O&M Mitigation Cost (CO2) Natural gas combined cycle Nitrogen Oxides Operation and Maintenance Outside diameter Over-fired air Oxygen Ion Transport Membrane Once-through utility Pulverized Coal Pressurized fluidized bed combustion Pressure swing absorption Reheater 164 SCR SH SOx ST T TCR TEG TET TPC TPI UBC Selective Catalytic Reactor Superheater Sulfur Oxides Steam Turbine Temperature Total Capital Requirement Triethyleneglycol Turbine Exit temperature Total Plant Cost Total Plant Investment Unburned carbon loss 165
© Copyright 2026 Paperzz