Post Opening Project Evaluation A2 / A282 Dartford Improvement and M25 J1b – 3 Widening One Year After September 2010 Notice This report was produced by Atkins Transport Planning for the Highways Agency for the specific purpose of the POPE Major Schemes Commission. This report may not be used by any person other than the Highways Agency without The Highway’s Agency’s express permission. In any event, Atkins accepts no liability for any costs, liabilities or losses arising as a result of the use of or reliance upon the contents of this report by any person other than the Highways Agency. Document History JOB NUMBER: 5084038 DOCUMENT REF: A2_A282_M25_J1b3_POPE_OYA_v2.docx 1 Draft PW SB PR PR 05/2010 2 Revised in response to HA comments PW SR NDM PR 09/2010 3 Minor revisions to Executive summary PW 4 Minor revision to Executive summary PW Revision Purpose Description Originated 11/2010 Checked Reviewed Authorised Date Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Contents Section Page Glossary iii Executive Summary vii 1. 2. 3. 4. Introduction 1 Background to Schemes Other Major Schemes nearby Scheme Locations History of the Schemes A2/A282 Dartford Improvement M25 J1b – 3 widening Post Opening Studies 1 2 2 3 4 7 9 Traffic 11 Introduction Sources of Data Background Traffic Growth and the Recession effect Traffic Volumes Volumes at the junction Volumes of Traffic on Strategic network Volumes of Traffic on Local Roads Traffic flows through the day Classified Data Journey Times Journey Times on A2 main carriageway Journey Times on M25 main carriageway Journey times for turning movements at Junction Traffic Forecasts vs. Outturn Journey Time Forecasts 11 11 11 14 14 18 22 23 26 27 27 30 32 35 40 Safety 42 Introduction Data Sources Accidents Scope of Accidents Analysis Forecasts Security 42 42 43 43 50 53 Economy 55 Introduction Economic Appraisals Overall Appraisals Summary with various scenarios Transport Economic Efficiency Evaluation of TEE benefits – Summary of Approach PAR Evaluation of TEE Monetised Safety benefits Scheme costs 55 55 56 58 58 59 61 63 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx i Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study 5. 6. 7. Benefit Cost Ratio Route stress/ Journey Time Reliability Wider Economic Impacts 65 66 68 Environment 71 Introduction Noise Local Air Quality Greenhouse gases Landscape and Townscape Cultural Heritage and Archaeology Biodiversity Water Quality and Drainage Physical Fitness Journey Ambience 71 75 79 81 83 91 95 101 103 105 Accessibility and Integration 108 Introduction Data Sources Option Values Severance Access to the Transport System Integration 108 108 108 108 109 110 Conclusions 113 Measurement against NATA Objectives: AST & EST Measurement against Scheme-specific Objectives 113 113 Appendices Appendix A Summary of Sources 116 Appendix B Scheme Objectives 118 B.1 B.2 119 120 A2/A282 Dartford Objectives M25 J1b - 3 Appendix C Environmental Sources 122 C.1 123 Standard list of information required to evaluate the environmental sub-objective Appendix D 125 D.1 D.2 126 126 Appraisal Summary Table Evaluation Summary Table The maps in this document are reproduced from Ordnance Survey material with the permission of Ordnance Survey on behalf of the Controller of Her Majesty's Stationery Office © Crown copyright. Unauthorised reproduction infringes Crown copyright and may lead to prosecution or civil proceedings. Highways Agency Licence No. 100018928. Published 2010. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx ii Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Glossary Accessibility Accessibility can be defined as ‘ease of reaching’. The accessibility objective is concerned with increasing the ability with which people in different locations, and with differing availability of transport, can reach different types of facility. ADT, AADT Average Daily Traffic, Annual Average Daily Traffic. Average of 24 hour flows, seven days a week. AIMSUN A micro-simulation modelling package which simulates movements of individual vehicles and weaving movements ALLI Area of Local Landscape Importance AM Denoting the morning peak period. In this study 7:00 – 10:00. AONB Area of Outstanding Natural Beauty AQMA Air Quality Management Area AST Appraisal Summary Table. This records the impacts of the scheme according to the Government’s five key objects for transport, as defined in DfT guidance contained on its Transport Analysis Guidance web pages, WebTAG. ATC Automatic Traffic Count, a machine which measures traffic flow at a point in the road. AWT, AAWT Average Weekday Traffic, Annual Average Weekday Traffic. As AADT but for five days, (Monday to Friday) only. BCR Benefit Cost Ratio - this is the ratio of the PVB divided by the PVC. CO2 Carbon Dioxide Colourless, tasteless, odourless, non-combustible gas which is present in vehicle emissions. For transport, this is the main greenhouse gas. COBA COst Benefit Analysis A computer program which compares the costs of providing road schemes with the benefits derived by road users (in terms of time, vehicle operating costs and accidents), and expresses the results in terms of a monetary valuation. The COBA model uses the fixed trip matrix unless it is being used in Accident-only mode. CM Controlled Motorway Motorway with an automatic speed-control environment, based on MIDAS, which uses of mandatory variable speed limit signals rather than advisory speed limits displayed on traditional motorway signals. Note this is not the same as a Managed Motorway which includes hard shoulder running in addition to the features of a controlled motorway. CTRL Channel Tunnel Rail Link 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx iii Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study DIADEM Dynamic Integrated Assignment and DEmand Modelling Variable demand transport modelling software developed for the DfT. Demand responses are based on: Trip frequency, Time period choice Mode choice, and Destination choice/distribution. EAR Economic Assessment Report EST Evaluation Summary Table. In POPE studies, this is a summary of the evaluations of the TAG objectives using a similar format to the forecasts in the AST. GETRAM Generic Environment for Traffic Analysis and Modelling: A micro-simulation model computer system used for looking at road traffic behaviour and patterns in detail. HA, Highways Agency An Executive Agency of the Department for Transport, responsible for operating, maintaining and improving the strategic road network in England. HATRIS Highways Agency Traffic Information System The Highways Agency (HA) currently maintains, operates and develops three traffic databases and associated applications. The Traffic Flow Data System (TRADS) holds information on traffic flows at sites on the network. The Journey Time Database (JTDB) system holds information on journey times and traffic flows for links of the network. These two databases are known collectively as the HA Traffic Information System (HATRIS). HEMP Handover Environmental Management Plan IP Inter Peak, the time between the AM and PM peaks Kent Thameside Kent Thameside is a regeneration area which covers the urban area north of the A2 in Dartford and Gravesham KTS Kent Thameside Model Owned by Kent CC, the Kent Thameside Model (KTS) is the primary tool for assessing the transport impacts of expected development around the Kent Thameside regeneration area. It is a multi-modal transport model, representing vehicular travel demand. SATURN software is used for the highways (cars and commercial vehicles) and the TRIPS software is used to assess public transport (rail, bus and coach). Link E In the original plans for the A2/A282 scheme, at the junction there were a number of different links which were labelled link A to link G. Link E was a proposed free-flow link northwest of the roundabout between the A2 westbound and the A282 main carriageway northbound. MAC Managing Agent Contractor Micro-Simulation Computer software for modelling the effect of different road layouts by modelling the movements of individual vehicles (cars, buses and lorries) along the road and through junctions. It is of particular use in assessing which road layouts will enable traffic to move freely and which would cause traffic jams. NAOMI New Assessment of Motorway Improvements NAOMI5 was a strategic traffic model developed for the ORBIT multimodal study covering the M25 corridor. Based on Saturn software. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx iv Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study NATA New Approach To Appraisal Used for transport scheme appraisal since 1998. NMU Non-Motorised User. A generic term covering pedestrians, cyclists and equestrians NRTF National Road Traffic Forecast. This document defines the forecasts produced by the Department of the Environment, Transport and the Regions of the growth in the volume of motor traffic. At the time this scheme was appraised, the most recent one was NRTF97, i.e. dating from 1997. NTEM National Trip End Model Department for Transport’s projections of growth in travel demand, and the underlying car ownership and planning data projections. OPR Order Publication Report ORBIT London Orbital Multi Modal Study (ORBIT) was commissioned by the Government Office for the South East and made its final report in November 2002. The intention of the study was to identify causes of congestion along and approaching the M25, and recommend a preferred strategy of possible solutions to alleviate the impact of congestion on the M25. POPE Post Opening Project Evaluation Before & after monitoring of all major highway schemes in England. PVB Present Value Benefits Value of a stream of monetised benefits accruing over the appraisal period of a scheme expressed in the value of a single present year. For this scheme, and in current guidance, this is 2002. PVC Present Value Cost As for PVB but for a stream of costs PM Evening peak period. In this study 16:00 – 19:00. QUADRO QUeues And Delays at Roadworks. Modelling software which is used to identify the economics impacts of construction and maintenance SAM Scheduled Ancient Monument SAR Scheme Assessment Report SATURN Simulation and Assignment of Traffic to Urban Road Networks Computer software for modelling traffic flows on road networks SCOOT Split Cycle Offset Optimisation Technique Dynamic urban traffic control system tool used for managing traffic on signalised road networks SNCI Site of Nature Conservation Interest SSSI Site of Special Scientific Interest 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx v Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study TEE Transport Economic Efficiency Calculation of transport user benefits based on changes in travel time and vehicle operating costs. TEMPRO Trip End Model Program Computer software that provides access to the Department for Transport’s (National Trip End Model NTEM) Thames Gateway Thames Gateway is the United Kingdom's largest regeneration area. It stretches from inner east London both sides of the Thames to North Kent and South Essex TRANSYT Traffic Network StudY Tool Modelling software developed by the Transport Research Laboratory for the modelling of road junctions including signalised roundabouts. TUBA Transport Users Benefit Analysis. Modelling software which calculates the costs and benefits that would accrue to users of a transport system, companies, national and local government as a result of making improvements to a transport network. webTAG Department for Transport’s website for guidance on the conduct of transport studies at http://www.webtag.org.uk/ 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx vi Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Executive Summary This report presents a study into the impacts of the opening of two Highways Agency Major Schemes: A2 / A282 Dartford Improvement, opened in December 2007; and M25 J1b – 3 widening (section 3), opened in July 2008. These schemes are both located around M25 J2 and their construction periods overlapped hence they are clearly closely interlinked which is why the Post Opening Project Evaluations have been undertaken in tandem. A2/A282 Dartford Improvement Scheme Description The improvement scheme consisted of the following measures: Provision of free-flow links for the principal movements at the junction: - Viaduct linking A2 westbound to M25/A282 northbound; - Viaduct linking M25/A282 southbound to A2 eastbound; and - A free-flow slip road for traffic travelling from the A2 westbound onto the M25 southbound; Widening of the A2 from 3 to 4 lanes in each direction between the M25/A282 and the Bean junction (1.2 miles), mainly within existing highway boundary with hardshoulders; Low noise surfacing on widened sections of carriageway and on existing A2 through and west of M25 J2; and Environmental mitigation measures including noise fences, improved drainage and retaining walls. Objectives - Scheme Assessment Report / Statement of Case Objective Achieved? Reduce journey times and improve reliability; Yes Improve safety at the junction; Yes Provide enhanced access from the M25 to the major regeneration area of Kent Thames-side and other regeneration areas in north and East Kent; Yes To facilitate access to Ebbsfleet International Rail Station from the national motorway and trunk road network; and Yes Limit the environmental impact, especially noise. Yes, except where too early to conclude M25 J1b – 3 widening Scheme Description The scheme consisted of the following measures: Widening within existing highway boundary of: - 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx M25 both carriageways from 3 to 4 lanes from J3 to south facing slips of J2, and M25 southbound from 2 to 3 lanes vii Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study between J1b and J2 and through J2. Low noise surfacing; Lighting on the previously unlit section J2 to J3; Environmental mitigation measures including improved water pollution control measures; and Infrastructure for a Controlled Motorway on J23 was installed at the same time, although it was not formally part of this scheme. Objectives - Scheme Assessment Report / Statement of Case Objective Achieved? Reduce journey times by 30-60 seconds; Y e s Improve reliability; Y e s T o o e a r l y Create jobs in Kent Thames Side Regeneration Area through increased labour t pool and impacts on companies relying on o distribution of goods; c o n c l u d e Y e s , e Mitigate the environmental impacts and x upgrade water pollution control measures; c and e p t w h e 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx viii Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study r e t o o e a r l y t o c o n c l u d e Facilitate future demand management measures to provide some constraint on Y induced traffic and lock in benefits from e widening. These measures would be carried s out separately from this scheme. Key Findings One year after opening, these schemes have been successful in achieving almost all their objectives. The two schemes were constructed at the same time to minimise disruption. Traffic on this section of M25 has not grown since 2006 and hence flows are now below forecast. This is linked below expected growth on the M25 in this period, latterly due to the current economic recession. Rapid widening techniques within the existing highway boundary were successful for the M25 J1b–3. Conversely, traffic on the widened A2 has shown higher than expected growth, which may be linked to the completion of other schemes in the A2 corridor. Journey times on the widened A2 and M25 have seen journey time savings for traffic in peak periods in the main direction of flow. At the junction, there are journey time savings in the peak and inter-peak for most turning movements. As expected, the highest savings are for traffic now using the new free-flow links with savings up to 2 minutes for traffic between the A2 westbound and A282 northbound. Statistically significant safety benefit from the combined effect of the two schemes is much better than the slight impacts expected. Infrastructure for a controlled motorway on M25 J2-3 was installed in the period following the construction of this scheme. At the time of this study, it was not in operation. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx ix Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx x Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Summary of Scheme Impacts Traffic Annual Average Daily Traffic on the widened section of the A2 has increased by 7-8% and is now 130,000 AADT. This growth has occurred particularly during the peak periods when journey time savings are also observed. 44,000 vehicles use the new free-flow links daily rather than needing to use the roundabout. There has been a reduction of ⅓ in traffic using the circulating carriageway of the roundabout. Journey Times using the new free-flow links have improved by up to 2 minutes. Annual Average Daily Traffic on the widened M25 has shown little change and it is much lower than forecast. This can be linked to the current economic recession. No clear impact of traffic rerouting from local roads. Safety Statistically significant safety benefit from the combined effect of the two schemes is much better than the slight impact expected. However, this may have been influenced by a change in driver behaviour resulting from the construction period when traffic cameras were in operation. CCTV cameras installed are beneficial for security. Environment Noise, local air quality and greenhouse gases impacts which are all linked to traffic flows are largely as expected. Noise barriers are higher hence better than originally planned ones. Landscape and townscape mitigation in place but OYA is too soon to establish success. Planting has largely been implemented as expected. Heritage impacts are largely as expected. Impacts to archaeology are unknown due to limited available data at this stage. Biodiversity impacts largely as expected where data is available at this stage. Mitigation by species translocation took place but there is only limited data on success of these. Improved water pollution control measures in place but no clear change in water quality has been measured. Accessibility Schemes have improved access to employment and retail for car users. Schemes provide access to new Ebbsfleet International Station (opened 2007). Integration The schemes are consistent with transport strategy policies targeting the Kent Thameside regeneration area. Summary of Scheme Economic Performance Pre Scheme Forecast Post Opening Reforecast (2002 Prices) (2002 Prices) All prices in 2002 prices, discounted to 2002 at 3.5% A2/A282 M25 J1b-3 A2/A282 M25 J1b-3 £179.0m £207.8m £169.5m £161.2m £0.9m £2.6m £14.8m £22.4m Total 60 Year Benefits (PVB) £179.9m £210.4m £184.3m £183.6m Costs (PVC) £102.2m £69.2m £115.9m £54.6m Journey Time Benefit Safety Benefit Benefit Cost Ratio (BCR) 2.3 2.2 Economic forecast was based on TUBA models of a wide area including the motorway, trunk roads and the Kent Thameside area. POPE evaluation is only possible using a simple method based on changes observed on the key links only. Hence the benefits presented here are likely to underestimates. Higher than expected accident savings have resulted in much higher monetised safety benefits than forecast. Total cost of the two schemes was slightly below the total forecast. The BCR is almost exactly as forecast and therefore the schemes represent good value for money. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx xi Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study 1. Introduction Background to Schemes 1.1 Recently there have been two Highway Agency major schemes undertaken around the intersection between the M25, A2, and A282 in Kent in overlapping time periods. These are: A2 / A282 Dartford Improvement which opened in December 2007. This scheme involved: The construction of three free-flow links at the M25 J2; and The widening of 2km of the A2 east of the junction. M25 J1b – 3 widening (section 3), which opened in July 2008. This scheme involved: Widening from three to four lanes of both carriageways between the junctions J2 – 3 and Widening of the southbound carriageway between junctions J1b – 2, from two lanes to three lanes. 1.2 These schemes overlap around the M25 J2 and their construction was undertaken in tandem although they were appraised and funded as two separate schemes. 1.3 Clearly the two schemes have had significant impacts to the road network and surrounding area and many of these impacts cannot be accurately attributed to one or the other scheme. Hence, the Post Opening Evaluation (POPE) of these two schemes at the One Year After stage (OYA) is combined and presented in this single report. 1.4 The location of these schemes in a regional context is shown in Figure 1.1. This highlights the strategic importance of these schemes. Figure 1.1 – Regional context 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 1 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Other Major Schemes nearby 1.5 Other major road schemes have been undertaken by the Highways Agency in the area east of the A2/A282 scheme. These were: A2 Bean – Cobham widening Phase 1 (Bean to Pepperhill); A2 Bean – Cobham widening Phase 2 (Pepperhill to Cobham); and A2/M2 Cobham to J4 widening – east of Phase 2. Scheme Locations 1.6 The locations of the scheme which are the subject of this report (A2 / A282 Dartford Improvement and the M25 J1b – 3 widening) and the other major schemes on the A2 listed above, are shown in Figure 1.2 and the timelines of the schemes in Figure 1.3. Figure 1.2 – Locations of A2/A282 improvement, M25 J1b – 3 Widening and other Major Schemes Figure 1.3 – Timelines of Construction Periods of Major Schemes (from west to east) Scheme 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N A2/M2 Cobham to J4 widening Ebbsfleet International Station opened November CTRL funded Phase 1a Phase 1b Ebbsfleet jct work A2 Bean to Cobham Phase 1 CTRL1 opened A2 Bean to Cobham Phase 2 A2/ A282 Dartford Improvemen ts M25 J1b - 3 Widening 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 2 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study History of the Schemes 1.7 The history and key dates in the time line of the two schemes evaluated in this study are summarised in Table 1.1. Table 1.1 – Timelines of schemes A2/A282 Dartford Improvement Period Preferred Route developed by Kent County Council for DfT 1992 Scheme added to Targeted Programme of Improvements (now called Major Schemes) 1998 Reassessment of preferred scheme and alternatives 2000Oct 2001 Public consultation Jun-Aug 2002 Draft Orders and ES published Mar-03 Public Inquiry Feb-04 Apr-04 Secretary of State’s Decision One of five M25 rapid widening schemes added to TPI programme following recommendations of the ORBIT MultiModal Study Aug-04 Dec-04 Reassessment of revised scheme with Link E1 deferred early-06 Start of construction work Aug-06 Open for traffic M25 J1b – 3 widening Public exhibitions May-07 Secretary of State’s decision Jun-07 Construction work began Dec-07 Aug-08 Widening work was completed and lanes fully open to traffic 1.8 The timescales of the nearby schemes in the A2 were shown previously in Figure 1.3. 1.9 It should be noted that following the completion of the widening scheme on the M25 which is one of the subjects of this POPE study, communications and signalling work continued into 2009. These works were for the Controlled Motorway scheme which at the time of this evaluation was expected to be introduced later in 2010. The appraisal and evaluation of the Controlled Motorway scheme are not covered by this report. 1.10 Flows on the M25 were also known to have been affected by the change in the tolling regime of the Dartford Crossing on 15th November 2008. 1.11 It should be noted that the M25 widening scheme was constructed entirely within the existing highway boundary and hence the planning stages were simpler than the adjacent A2 / A282 scheme. 1 One of the proposed free-flow links at the junction 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 3 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study 1.12 Details of the two schemes are given in the following sub-sections. A2/A282 Dartford Improvement Problems 1.13 At the time this scheme was appraised, the key problems were: Existing M25 J2 and the A2 were both close to capacity; Incidents on the M25, A2 or Dartford Crossings led to gridlock at the signalised roundabout. Major developments were planned in North Kent including a new international and domestic railway station at Ebbsfleet as part of Channel Tunnel Rail Link (CTRL) Scheme Description 1.14 The scheme included the following measures: Provision of new free-flow links for the principal movements at M25 J2 / A282: - New flyover (E – N) for traffic travelling from A2 westbound to M25/A282; - New flyover (N – E) for traffic travelling from M25/A282 southbound to A2 eastbound; and - New dedicated slip road (E – S) for traffic travelling from the A2 westbound onto the M25 southbound. Realignment of the link roads north of the circulating roundabout at J2: - From J2 to J1b for access from A2 and M25 northbound into Dartford; and - From J1b to J2 for access onto the A2 (eastbound and westbound) and M25 southbound from Dartford. Realignment of the entry and exit slip roads from J2 roundabout and A282 north of the junction; and Widening of the A2 from 3 to 4 lanes in each direction with hardshoulders, between the eastern slips for the new flyovers at J2 and Bean junction in the east covering a total of 2km, primarily within the existing highway boundary. Environmental mitigation measures including: - 1.15 Low-noise surfacing on : the new and widened carriageways; On the existing A2 carriageway through and west of M25 J2; and On the A2 through the Bean junction - Noise fencing at Hawley Manor; - Landscaped earth mounds in many locations 2m high above the carriageway to reduce noise and provide visual screening; - Retaining walls along the widened sections of the A2 to retain the existing highway boundary, e.g. where the A2 passes through the Darenth Wood Site of Special Scientific Interest (SSSI); - Retaining wall to prevent the proposed east to north link road from encroaching into the grounds of Hawley Manor; - New balancing ponds, for flood prevention, and pollution control measures; and - Extensive planting of woodland, shrubs and grassland. Figure 1.4 illustrates the main features of the scheme. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 4 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Figure 1.4 – Detail of A2 / A282 Dartford Improvement scheme 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 5 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Link E deferral 1.16 In the original A2/A282 scheme proposals, the changed links at the junction were labelled A to G. As shown in Figure 1.4, the one labelled Link E was to provide a free-flow link for traffic travelling between the A2 eastbound and A282 northbound, i.e. it was located north-east of the junction. 1.17 At the detailed design stage of the scheme in 2006, a proposal was made for a revised scheme layout to defer the construction of this link. This revised version offered considerable cost savings compared to a small loss of benefit and was subsequently adopted into the scheme as-built. 1.18 The revised plan was that this A2/A282 scheme would not include the construction of Link E but the new layout at the junction would be designed to facilitate the construction of a segregated free-flow link E at an appropriate future date. The revised plans for the link E part of the design were: 1.19 Earthworks for Link E associated with the original plan would be carried out as part of the main works; A direct link between the roundabout of J2 and the A282 northbound, essentially on the line of the existing road, would be built; and Resurfacing of the existing A2 eastbound carriageway and the slip road to J2 from the west limit of works with low noise surfacing as originally planned. The deferral option was tested using the junction modelling tool TRANSYT, then with SATURN and TUBA. These showed that the revised scheme could operate successfully in the opening year and even with high traffic growth, Link E would not be needed before 2014 or by the design year of 2022 with low traffic growth. The Need for the Scheme 1.20 The details of the problems to be addressed by the A2/A282 improvement scheme as summarised in the appraisals were as follows. Problems at the Junction 1.21 The junction between the A282/M25 and the A2 is the M25 J2. The then existing junction was a three level interchange and all turning movement traffic at the junction had to pass through a signal controlled roundabout at the intermediate (second) level. The problems with that layout were: The junction was very heavily trafficked with almost 90,000 vehicles passing through it each day. With this level of traffic, delays occurred regularly and queues at peak hours often extended back onto the main carriageways. Incidents on the M25, A2 or Dartford Crossings lead to gridlock at the signalised roundabout. The operation of the junction was further complicated by the fact that traffic on the northbound M25 wishing to exit at J1b had to pass through the J2 roundabout. Similarly, traffic from J1b wanting to join the southbound M25 also had to navigate the J2 roundabout. Consequently, conflicts occurred between traffic bound for the Dartford Crossings and local traffic accessing Dartford via J1b. Problems on the A2 1.22 At the time of the appraisal, the existing A2 between J2 and Bean Junction carried over 100,000 vehicles per day and was close to capacity. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 6 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Expected issues regarding Future growth It was expected that in the future, as traffic flows on the roads increased and local regeneration in the Kent Thameside area of North Kent took place, the existing problems were expected to deteriorate further. Much development had already taken place and was planned to take place in future years, including such major developments as Dartford Park, Eastern Quarry, Northfleet and Crossways. In addition, the construction of a new international and domestic rail station at Ebbsfleet between Swanscombe and Northfleet accessed from a new junction on the A2 was part of the proposals for the Channel Tunnel Rail Link (CTRL). The scheme was designed to alleviate the existing and anticipated future congestion, improve safety and contribute towards an integrated and sustainable transport strategy for the Kent Thameside area. This would be achieved by improving journey time reliability and by providing better access to local regeneration areas. Scheme Objectives 1.23 1.24 The objectives of the scheme were specified in the following documents: Stage 3 Scheme Assessment Report from Order Publication Report (OPR) ; 1998 Roads Review ; Statement of Case (2004) and Environmental Statement (2003) These have been summarised into the following key objectives: Reduce journey times and improve reliability; Improve safety at the junction; Provide enhanced access from the M25 to the major regeneration area of Kent Thames-side and other regeneration areas in north and east Kent; To facilitate access to Ebbsfleet International Rail Station from the national motorway and trunk road network; and Limit the environmental impact, especially noise. M25 J1b – 3 widening The Problem 1.25 As with the A2/A282 scheme, the existing problems on the M25 J1b – 3 were based around unreliability of journey times. Scheme Description 1.26 The M25 J1b- 3 scheme was undertaken using rapid widening methods. 1.27 The key principle of rapid widening is that widening should be carried out within the existing highway boundary, such that no additional land take is required, thus avoiding the need for any compulsory purchase orders and likelihood of a public inquiry. 1.28 The scheme involved the following: Widening of : - The southbound carriageway of the M25 from two to three lanes between J1b and J2 southbound slip road; 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 7 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study 1.29 - Building the new lanes over the current hard shoulders with new hard shoulders built alongside, except under or over bridges (all within the current highway boundary). Low noise road surfacing/fencing to protect properties and reduce traffic noise; Lighting on the previously unlit section J2 to J3; New water pollution control measures for surface water runoff within the existing motorway boundary. Additionally, during the construction of the scheme, the infrastructure for a Controlled Motorway was installed along the length of the scheme. This was not part of the widening scheme appraisal nor was it costed together. Measures included were: New communications infrastructure including MIDAS, CCTV, emergency telephones, lane signalling and EMS signing. It is important to note that Controlled Motorway (CM) was not directly part of this scheme and this report is based on the period before the Controlled Motorway was operational. The ES stated that one of the objectives of this scheme was: 1.31 Both carriageways of the M25 from three to four lanes in each direction between the south facing slip roads of M25 J2 and the north facing M20 link road merge/diverge at J3; 1.30 - Provision of sufficient communications infrastructure and sign gantries to facilitate the incorporation of variable speed limits for Controlled Motorway. This would produce more reliable journey times hence supporting the objective of reducing driver stress. Figure 1.5 illustrates the main features of the scheme. Figure 1.5 – Detail of M25 J1b – 3 widening scheme 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 8 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study The Need for the Scheme 1.32 The problems to be addressed by the M25 J1b - 3 scheme, as given in the Appraisal Summary Table (2006) are: Unpredictability of travel times; Lack of orbital routes around London. Need for access to Thames Gateway regeneration area. Scheme Objectives 1.33 1.34 1.35 The objectives of the M25 J1b - 3 widening scheme were specified in the following documents: AST (2006); Scheme Assessment Report (SAR) ; and Environment Statement (ES) These have been summarised into the following key objectives: Reduce journey times by 30-60 seconds; Improve reliability; Create jobs in Kent Thames Side Regeneration Area through increased labour pool and impacts on companies relying on distribution of goods; Mitigate the environmental impacts and upgrade water pollution control measures; and Facilitate future demand management measures to provide some constraint on induced traffic and lock in benefits from widening. These would be carried out separately from this scheme and were not detailed at the time of this scheme appraisal although it was planned than they would be coordinated with this scheme. Additionally, the M25 scheme was to be packaged with A2/A282 Dartford Improvement in order to avoid abortive construction work, limit the disruption to road users by completing the two Schemes within the minimum possible time, and minimise the overall cost. Post Opening Studies 1.36 This report is the one year after post opening study for these schemes and was undertaken as part of the Highways Agency’s Post Opening Project Evaluation (POPE) of all major schemes. POPE of major schemes is undertaken one year and five years after opening. One Year After study (OYA) 1.37 This POPE one year after study evaluates whether the original objectives of each of the schemes have been achieved, and provides a comparison of the predicted scheme impacts against those emerging to date. The overall impacts each of the scheme are also assessed against the Government’s key objectives for transport of Economy, Safety, Environment, Integration and Accessibility as defined in the NATA guidance (New Approach to Transport Appraisal). 1.38 More specifically, this report sets out the following: A comparison of the before and after traffic volumes on the M25, A2, A282 and other key roads in the surrounding area; A comparison of before and after journey times on the key routes; An outline of the changes in accident number on the corridor following the opening of the schemes; A monetised comparison of the predicted and actual impacts of the schemes; and 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 9 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Evaluation of the impacts of each scheme upon the environment, accessibility and integration sub-objectives. Five Years After study (FYA) 1.39 The POPE five years after study for these schemes will take place in 2013 and cover a similar scope to this OYA, but allowing for the Controlled Motorway system to be in place and to further evaluate particularly impacts which are slower to evolve such as wider economic impacts. Report Format 1.40 The report is set out as follows: Section 2 – Traffic Analysis. This section is an analysis of the traffic impacts of the scheme and compares them with the forecast impacts. Section 3 – Safety. This section discusses whether at this stage, there are emerging changes in accident patterns as result of the scheme. Section 4 – Economy. This section examines what economic impacts of the scheme can be measured and compares these to the forecast benefits. Section 5 – Environment. A review of the environmental impacts of the scheme is given and supported by an evaluation of the mitigation measures described within the scheme’s Environmental Statement; Section 6 – Accessibility and Integration. A review of how the scheme has affected accessibility for pedestrians, cyclists and public transport users is presented. Furthermore a review of how the scheme links with wider policy objectives. Appendices – data sources used and summary tables Sources 1.41 The sources upon which this evaluation is based are detailed in Appendix A. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 10 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study 2. Traffic Introduction Sources of Data 2.1 The traffic analysis in this section is based on data obtained from a variety of sources representing the best available data covering the relevant area for the time period covered by this study. 2.2 The data used for both schemes is as follows. Traffic volumes on Road Network and Turning movements at the M25 J2 2.3 The data sources used are: Permanent traffic count data from sites on the strategic road network recorded in the HA’s TRADS database; Traffic count data from sites on Kent County Council’s roads; MIDAS data supplied directly by the NTCC to fill the gaps in the data coverage by the TRADS database; 12 hour turning counts undertaken in 2004 for the purpose of providing base data for the original consultant’s scheme modelling which were subsequently made available for this POPE OYA study; and 12 hour counts on the M25 J2 circulating roundabout and selected links undertaken in 2009 for the purpose of this study to compare with the above 12 hours counts and to fill in gaps in the coverage by permanent sites on the section between J1b and J2. Journey Times 2.4 2.5 The journey times around this complex junction have been collected using the moving observer method using GPS technology to collect detailed data on vehicle locations and times for all the important movements around the junction. Additionally Journey Time DataBase (JTDB) data has been collected for the journeys on the links. These can be summarised as: Moving observer surveys from 2004 collected to provide base data for the traffic modelling work for the A2/A282 scheme; Moving observer surveys commissioned in 2009 covering the movements around this junction, the widened sections of M25 and A2; and HATRIS JTDB on the A2 and M25 for the periods June 2006 and June and September 2009. All of the moving observer surveys collected detailed GPS data from each vehicle on all the routes surveyed. This data included recordings of each vehicle’s location at four and one second intervals for the 2004 and 2009 surveys respectively. Using this detailed data combined with GIS software has enabled the processing of journey times between selected points to provide comparative figures for the many possible permutations of movement around the junction even though the works at the junction for the scheme have changed the alignment of most of the links and slip roads. Background Traffic Growth and the Recession effect Current Economic Climate 2.6 The current economic climate must also be borne in mind throughout this report. According to the Office of National Statistics: 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 11 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study ‘Economic growth during the fourth quarter of 2008 contracted by 1.5 per cent. This marks the second successive quarter of negative growth so, according to the widely-held technical definition, the UK is now officially in recession. The pace of the downturn appears to be accelerating and broad-based, with the UK expected to remain in recession throughout 2009’, (Economic & Labour Market Review, Volume 3, No. 2, February 2009). Wider traffic trends 2.7 Historically in POPE scheme evaluation, the traffic counts from the before period counts have been factored to take account of background traffic growth so that they are directly comparable with the counts from the after period. This usually involves the use of National Road Traffic Forecasts (NRTF) with local adjustments made using Trip End Model Presentation Program (TEMPRo). 2.8 However, due to the current economic climate which has seen widespread reductions in motor vehicle travel in the UK as a whole since the latter part of 2008, it is no longer deemed appropriate to use this method. In order to better understand the traffic growth patterns in recent years, it is useful to look at the long term trends of traffic in the area and more particularly on the south eastern part of the M25 where there has been good data availability for the years prior to and following the scheme opening. The disruption caused by the works for the major schemes considered in this report and other major schemes on the A2 means that the best data was obtained from elsewhere on the M25. The three locations on the M25 with reasonable coverage selected for analysis of the trends were: 2.9 J29 - 30 north of Dartford crossing; J3 - 4, just south of the widened section; and J6 – 7, next to M23. Average Daily Traffic (ADT) flows by direction for the period January 2000 to March 2010 were obtained from TRADS for each direction. Figure 2.1 shows the profile of this data. Clearly, at each location there can be a number of local factors impacting on the trend so by showing a variety of sections, the general trend should be apparent. For the purpose of this study, the key points from this graph are: In the early part of the decade, there are clear growth trends on all six sections of the M25; There is little evidence of any traffic growth occurring in the period following 2006; and On the sections J3-4 and J29-30 of the M25, there is some evidence of a decline in traffic flows starting in 2007 or 2008, just prior to the start of the recession. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 12 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Figure 2.1 – Long terms trends in Traffic flows on M25 (ADT by direction) 2.10 Long term traffic data for the A2 has not been included here due to limited availability and more importantly, the confounding impacts of the other A2 schemes, as shown in Figure 1.2. 2.11 The data on specific motorway locations has also been compared with more generic data produced by the DfT on estimated traffic flows for all motor vehicles by local authority, region and for England. This data between 2000 and 2009 is shown in terms of the annual change in the million vehicle kilometres (mvkm) for Kent (excluding the Medway towns) and the South East region in Table 2.1. Table 2.1 – Annual Change in vehicle kilometres on all roads Year GB‡ England* South East* Kent (excl. Medway Towns)* 2000 0.0% 0.0% 0.7% 0.3% 2001 1.6% 1.6% 1.8% 2.3% 2002 2.6% 2.4% 2.1% 2.9% 2003 0.8% 0.7% 0.3% 1.0% 2004 1.7% 1.6% 1.1% 1.4% 2005 0.2% 0.2% -0.1% 0.0% 2006 1.6% 1.4% 1.1% 0.8% 2007 1.1% 1.0% 1.0% 1.2% 2008 -0.8% -0.9% -1.2% -1.2% 2009 -1.0% -1.0% -1.1% -0.5% ‡ Road Traffic and Congestion in Great Britain: Quarter 2 2010, DfT *Taken from: Estimated traffic for all motor vehicles by Local Authority: 1993-2009, DfT 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 13 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study 2.12 It can be seen that Kent traffic data shows a very similar trend to the South East as a whole, with annual increases every year from 2000 to 2007, except 2005 when traffic levels were static. 2.13 Vehicle kilometres showed year on year decline in 2008 and in 2009. 2.14 It is considered therefore that some of the reductions in traffic shown later in this section are more likely to be associated with the impacts of the economic climate than of the schemes. 2.15 Therefore, whilst the impacts of the recession shall be borne in mind, this section of the report presents the observed unfactored traffic flows at each of the count locations. 2.16 When the scheme was appraised and by the time of the scheme public inquiry (A2/A282) and exhibitions (M25) in 2004, traffic was still growing as assumed in the traffic forecasting. Traffic Volumes Volumes at the junction Traffic using new free-flow links 2.17 One of the key features of the A2/A282 scheme was the construction of three free-flow links which are now benefiting traffic making some of the turning movements which previously had to use the circulatory carriageway of the roundabout. The usage of these links compared with the numbers previously observed making these movements as average hourly flows and total 12 hour flows are summarised in Table 2.2. Table 2.2 – Traffic movements using new free-flow links compared to equivalent movement before Link Time period 2004 2009 Difference % Diff AM 800 1,000 200 19% IP 900 1,000 100 12% PM 1,100 1,400 300 28% 12H 10,900 12,800 2,000 18% AM 900 1,400 400 44% IP 800 1,000 100 17% PM 400 700 300 71% 12H 9,000 12,000 3,000 33% AM 700 900 300 38% IP 600 600 0 5% PM 700 800 100 18% 12H 7,700 9,000 1,300 17% AM 2,400 3,300 800 34% IP 2,300 2,600 300 12% PM 2,200 2,900 700 33% 12H 27,600 33,900 6,300 23% (weekday) A282 SB to A2 EB (new free-flow flyover) A2 WB to A282 NB (new free-flow) A2 WB to M25 SB (new free-flow) Total on links directly improved by the scheme 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 14 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study 2.18 The key points on the traffic volumes on the free-flow links are: Counts of traffic using the new free-flow links shows that 33,900 vehicles are using these new free-flow links in the 12 hour period observed. Converted to a 24 hour average day2, this is 44,000. The 2009 data shows that increases in traffic primarily in the peak periods. This is likely to be due to the impact on the congested conditions which in the before period caused trip suppression, rerouting away from the junction and peak period spreading; and The greatest change can be observed in the traffic making the movement from A2 WB to A282 NB which benefits from the new flyover (Figure 2.2) which replaces the need to make a 270° turn at the roundabout. Figure 2.2 – New Flyover (A2 WB – A282 NB) from A2 EB onslip Circulating traffic 2.19 The construction of the new free-flow links was also intended to improve conditions for other traffic using the junction making movements which still include using the signal controlled circulating carriageway. Previously, all turning movements at the junction used the circulating carriageway except for a single free-flow link between the M25 NB and A2 WB. Following the completion of the A2/A282 scheme the only important movements which still need to use the roundabout are: From A2 EB to : - A282 NB, - J1b via link road for access to Dartford - M25 SB From A282 SB to A2 WB From J1 b via link road to A2 EB and WB 2 Conversion of 12 hour weekday flow to 24 hour ADT using a factor of 1.3 derived from the average ratio at nearby locations 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 15 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study 2.20 From M25 NB to: - A2 EB - Link road to J1b for Dartford Table 2.3 shows the change in the total traffic using the circulating lanes of the roundabout at the junction. Traffic using the new free-flow links are not included. The traffic using the roundabout would be expected to benefit from the reduction in circulating traffic. Table 2.3 – Circulating Traffic at Roundabout – not using new free-flow links Time Period 2004 2009 Difference % Diff. AM peak hourly 5,600 3,600 -2,000 -35% Inter Peak hourly 4,900 3,100 -1,900 -38% PM peak hourly 6,300 4,300 -2,000 -32% 12 hour weekday total 65,400 42,200 -23,200 24 hour AADT* 85,000 55,000 -30,000 -35% *Estimated using ratio as 2.18 above 2.21 This clearly shows that: Traffic circulation on the roundabout has reduced by around a third; The reductions are fairly consistent throughout the day; and The traffic volume using the circulating lanes is now 55,000 AADT compared to 85,000 before the new free-flows were added. Traffic using links at roundabout 2.22 A more detailed breakdown of where the changes have occurred at the roundabout is shown in Table 2.4. It should be noted that this data is based on single day video surveys in both 2004 and 2009 and hence may not precisely reflect the pattern over a longer period. 2.23 The main points are: The greatest change has occurred east of the roundabout where the construction of the two new flyovers between the A2 and the A282 and the free-flow slip road to the M25 southbound has resulted in significant drops in the traffic directly accessing the roundabout. Most notable is that from the A2 westbound, traffic using the roundabout circulating carriageway is down by 87%; South of the junction, the new free-flow slip has reduced the traffic travelling from the roundabout to the M25 southbound by 45%; and North of the junction the new flyover has reduced traffic approaching the roundabout from the north by 33%. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 16 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Position from RBT Table 2.4 – On and off slips to and from the roundabout E 2004 Slip movement (RBT=roundabout) 2009 AM IP PM 12 hour AM IP PM 12 hour AM IP PM 12 hour RBT to A2 EB onslip 1,500 1,600 2,300 21,300 800 1,000 1,200 12,400 -47% -38% -48% -42% A2 WB offslip to RBT (inc. new free-flow slip to M25) 1,800 1,600 1,600 19,600 1,200 800 1,100 11,600 -17% -38% -19% -28% A2 WB offslip to RBT (excl. new free-flow slip to M25) RBT to M25 SB onslip (inc. new free-flow slip to M25) S W 1,800 1,500 1,900 20,300 RBT to M25 SB onslip (excl new free-flow slip to M25) 300 200 200 2,600 1,900 1,400 2,000 20,100 6% -7% 5% -1% 1,000 800 1,200 11,100 -44% -47% -37% -45% M25 NB to RBT (exclude existing free-flow slip to A2) 800 800 1,200 10,800 800 1,100 1,300 12,800 0% 38% 8% 19% RBT to A2 WB (exclude existing free-flow slip to A2) 700 500 700 6,900 600 400 500 5,600 -14% -20% -29% -19% 1,600 1,300 1,700 17,500 1,400 1,100 1,500 15,100 -13% -15% -12% -14% RBT to new link road to J1b 800 500 1,100 8,700 RBT to A282 NB 500 300 300 4,500 A2 EB to RBT N % difference both NB routes N of RBT 1,500 1,200 900 14,300 1,200 900 1,400 13,200 -20% -25% 56% -8% A282 SB to RBT 1,400 1,300 1,800 17,400 1,100 800 1,200 11,700 -21% -38% -33% -33% 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 17 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Volumes of Traffic on Strategic network 2.24 The impacts on the traffic volumes on the M25 and A2 including the widened sections are summarised in Table 2.5 and Table 2.6. Following the completion of the two schemes there was considerable ongoing work on the communications infrastructure around the junction and on the widened M25 and A2 especially including the preparations for the controlled motorway. 2.25 The key points regarding changes on the strategic network are: A2 The widened section of the A2 between J2 and the Bean junction has shown significant growth in both directions of 7-8% of weekday traffic. This suggests that the completion of this scheme resulted in traffic growth despite of recessionary influences seen elsewhere. There may also be traffic growth related to using data from 2010 rather than 2009; In March 2010, average daily traffic (ADT) was 130,000 on the widened section; West of J2 , traffic volumes have shown little change suggesting that the improvements at the junction have not attracted traffic onto this route, but this may be expected as the scheme has not made much improvements for traffic movements between the A2 west of the junction and other arms; and East of the widened A2, a paucity of data and the impacts of the Bean to Cobham schemes makes it difficult to isolate any impacts of this scheme over the intermediate years. M25 J2-3 The changes in traffic volumes on the M25 between 2006 and 2009 have been complex; Post opening, average daily traffic (ADT) is 135,000 on the widened section; and Traffic volumes on the widened section are effectively unchanged since before scheme construction, which is similar to the no change seem on the section J3-4 south of the improved section. A282 / M25 The new layout between J2 and J1b in which the new link roads between the junctions are completely separate from the main carriageway of the A282 has resulted in a large increase in traffic using these links and a resultant drop in mainline traffic; and Overall there appears to have been a drop in traffic of 7% northbound and 9% southbound between J1b and J2. However it should be noted that this drop may be possibility attributable to the limitations of the data used: single day video counts due to the lack of permanent counts on these roads which would provide more robust data over a longer period. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 18 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Table 2.5 – Traffic on A2 Location (shaded) ADT AWT % difference Directi on Scheme location 2006 2009 2006 2009 ADT AWT WB 62,300 60,500 66,500 64,400 -3% -3% EB 63,900 61,400 67,900 64,500 -4% -5% WB - 71,200 - 76,400 - - EB - 70,900 - 75,700 within B259 junction B255 to B259 A2/A282 scheme - - 68,700 1 6% 8% 1 4% 5% 64,300 1 62,800 65,500 1 65,900 68,900 WB 31,700 33,000 33,100 34,500 4% 4% EB 31,200 - 32,900 - - - WB 52,500 51,500 53,600 53,300 -2% -1% EB 55,700 56,700 58,300 59,300 2% 2% WB 44,200 43,900 45,000 45,200 -1% 1% EB 44,900 45,800 46,800 47,800 2% 2% M25 J2 to Bean junction (B255) WB EB A2 Main Carriageway beneath M25 J2 61,000 63,800 J2 to A2018 within A2018 junction 1 Post opening data is limited on this section, so March 2010 data was used, unfactored. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 19 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Table 2.6 – Traffic on M25 ADT AWT % difference Directi on Scheme location 2006 2009 2006 2009 ADT AWT NB 65,700 68,000 67,700 70,800 4% 5% J1a - J1b SB 68,500 69,600 71,700 72,900 1% 2% A2/A282 J2 -J1b (exclude link road) NB 64,100 55,6001 65,100 55,6001 -13% -15% M25 & A2/A282 J1b - J2 (exclude link road) SB 65,400 54,1001 68,000 56,3001 -17% -17% A2/A282 scheme J2-J1b link road NB 10,000 14,7001 11,200 15,3001 47% 36% J1b-J2 link road SB 6,200 10,9001 6,600 11,3001 77% 72% J2 -J1b (all roads) NB 74,000 70,3001 76,300 70,9001 -5% -7% SB 71,500 65,0001 74,600 67,6001 -9% -9% J3 - J2 NB 65,600 64,7002 68,100 66,7002 -1% -2% J2 - J3 SB 69,400 70,6003 73,400 73,6003 2% 0% J4 - J3 NB 55,600 55,100 58,100 57,000 -1% -2% J3 - J4 SB 56,300 56,000 58,800 58,200 -1% -1% Location J1b - J1a J1b - J2 (all roads) M25 scheme total (shaded) 1 Post opening data is based on one day’s video count. 2 Post opening data is limited on this section, so March 2010 data was used. 2 Post opening data on this section is limited to only one full day in November 2009. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 20 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Table 2.7 – Traffic on local roads 2006 2009 % difference Location AM PM AWT ADT AM PM AWT ADT AM PM AWT ADT A296 Dartford East WB 300 500 6,500 6,100 500 500 6,600 6,100 37% 1% 1% -1% (east of J1b) EB 500 500 6,700 6,200 400 600 7,400 6,900 -20% 16% 11% 12% A226 Dartford west WB 500 500 7,200 6,800 500 500 6,500 6,300 -8% -12% -10% -8% (west of J1b) EB 300 400 5,800 5,500 300 400 5,500 5,400 0% 4% -4% -2% A225 South Darenth SB 500 400 5,800 5,300 500 500 6,000 5,600 1% 11% 3% 5% (parallel to M25 J2-3) NB 400 600 6,300 5,700 400 700 6,700 6,200 -2% 17% 7% 8% 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 21 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Figure 2.3 – Link Road between J1b and J2 RBT Figure 2.4 – Link Road between J2 RBT and J1b Volumes of Traffic on Local Roads 2.26 To examine whether impacts on nearby local roads can be identified, traffic count data was obtained from Kent County Council as shown in Table 2.7. 2.27 The key points regarding changes in traffic volumes on local roads are: 2.28 The A296 immediately east of J1b, which can be used as a route to the Bluewater Retail centre (opened 1999), and is approximately parallel to the widened section of the A2, has shown some traffic growth in one direction only, suggesting that some traffic is making journeys using the A296 eastbound and A2 westbound; East of J1b, the A296 which links the junction to Dartford Town Centre has shown a reduction in traffic, although this is not expected to be linked to these schemes; and The A225, which is a minor A road parallel to the M25, and could therefore be an alternative to the M25 for some local traffic shows no evidence of rerouting to the M25. Hence, it can be concluded that there is no evidence that the schemes have reduced traffic on local A roads parallel to the widened M25 and A2. Figure 2.5 – M25 J2 – J1b / A282 and link roads (looking south) 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 22 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Traffic flows through the day 2.29 Hourly traffic flows have been analysed to determine whether there have been changes to the distribution throughout the day on the widened sections of the M25 and A2. A2 between M25 J2 and Bean (widened section) 2.30 Post opening data for this widened section is only available from mid-December 2009 onwards. Thus the best post opening data for use in this study has been taken from March 2010. This has been compared with March 2006 data to provide the best comparison ignoring seasonal variation. The difference in the 24 hour weekday traffic flows between these dates was 6% eastbound and 8% westbound. The 24 hour profiles are shown in Figure 2.6 and Figure 2.7. Figure 2.6 – A2 westbound between M25 J2 and Bean hourly flows (weekdays in early March) 8000 March 2006 7000 March 2010 6000 5000 4000 3000 2000 1000 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Figure 2.7 – A2 eastbound between M25 J2 and Bean hourly flows (weekdays in early March) 8000 March 2006 7000 March 2010 6000 5000 4000 3000 2000 1000 0 1 2.31 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 The key points shown in the hourly of hourly traffic on the A2 are: 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 23 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study On the section of the A2 east of the M25 the peak flows show a strong tidal element with the busiest periods occurring on the AM peak westbound (toward London) and in the PM eastbound; Traffic growth in both directions has been greatest during the busiest peak periods. This shows that peak period traffic is benefiting from the widening, as shown in the reduction in congestion included later in this section. M25 Northbound J3-2 2.32 Post opening data for this widened section covering more than a small number of days is only available for July 2009 and February 2010 and at the time this study was compiled, early March 2010. Analysis of July ’09 and February ’10 data both showed reductions in traffic flows during the interpeak period compared to the same months in 2005. However this data is affected by February 2010 experiencing more snow disruption than normal, the effects of the London bombings in July 2005 and the economic downturn. Thus, data was used from early March 2005 (excluding Easter) and early March 2010, as shown in Figure 2.8. Over 24 hours, the total flow is down by 2% between 2005 and 2010. 2.33 The graph of the weekday hourly flows before and after the widening scheme shows that: In the northbound direction, the highest flows continue to occur in the AM peak period; and The small reduction in traffic flows has been spread throughout the day from 6:00 – 18:00 therefore there is no evidence that users have changed the times that journeys are made. Figure 2.8 – M25 J3 - J2 hourly flows (weekdays in early March) M25 Southbound J2-3 2.34 Southbound data in post opening period was only available for a single complete day in November 2009. Being based on only a single day means that conclusions from this may be less robust than the above but these have been included for comparison purposes. The difference between the total day’s flow on two selected days was a reduction of 1%. 2.35 The southbound hourly flow graph is shown in Figure 2.9. The main points from this are: The highest hourly flows occurred in both the AM and PM peak periods, although the PM peak is spread over a longer time period; and 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 24 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Although overall there was only a small reduction, in 2009, there was a reduction in the AM peak flows 6;00 – 9:00 whilst there was growth in the PM peak (15:00 – 18:00). It is unclear why this should have occurred. Figure 2.9 – M25 J2 – J3 hourly flows (second Thursday of November) 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 25 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Classified Data 2.36 Table 2.8 shows the weekday proportions of traffic longer than 5.2m in length in the period before schemes construction and after where data is available. Note that the definition of HGV now generally refers to vehicles longer than 6.6metres, but here 5.2m has been used because that was the length classification used for the data collected during the before period. Direction Table 2.8 – Proportion of HGV traffic (>5.2m) 2006 2009 WB - - EB - - WB - 26.5 EB - 26.4 WB 15.9 15.4 EB 16.6 16.9 WB - - EB - - WB 13.5 13.3 EB 13.4 13.6 WB 13.1 13.2 EB 13.7 13.8 J1b - J1a NB 23.5 - J1a - J1b SB - - (from J2 -J1b NB - - north J1b - J2 SB - - J3 - J23 NB 21.8 20.9 J2 - J3 SB - - J4 - J3 NB 14.9 13.1 J3 - J4 SB 12.3 16.64 Road Location Weekday HGV % (length >5.2m) within B259 junction B255 to B259 A2 (from M25 J2 to Bean junction (B255) east to west) A2 Main c’way beneath J2 J2 to A2018 Within A2018 junction M25 to south) 2.37 The main points shown in this table are: There has been negligible change in the proportion of larger vehicles on the A2; and 3 Data for J3-2 based on March 2005 and 2010 data. Further analysis of the classified data at this site shows that the large increase in the proportion of vehicle >5.2m here occurred in mid 2008 following a short period during which no data was available. The proportion has remained consistently higher than the opposite direction since. This suggests that there is a calibration issue with the count site. On the section J4-5, where classified data is only available for the after period, the proportion of HGVs was 18.9% southbound and 17.4% northbound 4 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 26 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study On the M25 the pattern is mixed with a reduction on the northbound carriageway whilst there has been an increase of four percentage points in the southbound carriageway. Reasons for this disparity are unknown. Journey Times Sources of evaluation 2.38 2.39 Evaluation of the changes in journey times is based on observed data from a variety of sources: Journey times on the main carriageway for the M25 and A2 were obtained using data from the HA’s Journey Time Database (JTDB) in HATRIS. This provides data on average journey times on a link by link basis between the primary junctions for all days and in 15 minute intervals. This covered both the before and after periods; and Journey times for turning movements at the M25 J2 are based on specially commissioned surveys using the moving observed method. This is based on timing of trips made by survey cars on the variety of movements possible at this junction. Data from the 2004 surveys undertaken by the scheme’s consultants for the appraisal was obtained for use in this study to represent the before period. Moving observer surveys were commissioned for the purpose of this study which covered the new movements possible at the junction in 2009. It should be noted that the following findings on the change in journey times are all based on mean journey times. These effectively average out the impacts of the not-infrequent ‘bad days’ where congestion is much worse than average. The impact on ‘bad days’ is considered later in the evaluation of the reliability benefits standard deviation. Journey Times on A2 main carriageway 2.40 For the purpose of this study, journey time data was extracted for June 2006 before the start of construction, and June 2009, one year after opening. The available data for these periods is identified in the database as being of varying quality across the months but only that identified as high quality has been used here. 2.41 The time periods used here are weekdays during the following periods: 2.42 AM:07:00 – 10:00 IP: 10:00 – 16:00 PM: 16:00 – 19:00 Off peak journey times have been omitted due to low traffic flows. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 27 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Table 2.9 – Journey Times on A2 Section Direction Time period Average Journey Time (seconds) (weekdays) 2006 2009 Saving A2 east of J2 WB AM 180 154 26 (widened section) 4.1km IP 146 143 4 PM 143 143 0 EB AM 159 156 3 4.3km IP 163 157 6 PM 204 167 37 WB AM 207 184 22 4.4km IP 170 167 2 PM 168 170 -2 EB AM 165 164 1 4.3km IP 169 165 3 PM 196 172 24 A2 west of J2 Figure 2.10 – Average Journey times on widened A2 east of J2, eastbound 250 200 Seconds 150 100 June 2006 June 2009 50 06:00 ‐ 06:15 06:30 ‐ 06:45 07:00 ‐ 07:15 07:30 ‐ 07:45 08:00 ‐ 08:15 08:30 ‐ 08:45 09:00 ‐ 09:15 09:30 ‐ 09:45 10:00 ‐ 10:15 10:30 ‐ 10:45 11:00 ‐ 11:15 11:30 ‐ 11:45 12:00 ‐ 12:15 12:30 ‐ 12:45 13:00 ‐ 13:15 13:30 ‐ 13:45 14:00 ‐ 14:15 14:30 ‐ 14:45 15:00 ‐ 15:15 15:30 ‐ 15:45 16:00 ‐ 16:15 16:30 ‐ 16:45 17:00 ‐ 17:15 17:30 ‐ 17:45 18:00 ‐ 18:15 18:30 ‐ 18:45 19:00 ‐ 19:15 0 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 28 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Figure 2.11 – Average Journey times on widened A2 east of J2, westbound 250 200 Seconds 150 100 June 2006 June 2009 50 06:00 ‐ 06:15 06:30 ‐ 06:45 07:00 ‐ 07:15 07:30 ‐ 07:45 08:00 ‐ 08:15 08:30 ‐ 08:45 09:00 ‐ 09:15 09:30 ‐ 09:45 10:00 ‐ 10:15 10:30 ‐ 10:45 11:00 ‐ 11:15 11:30 ‐ 11:45 12:00 ‐ 12:15 12:30 ‐ 12:45 13:00 ‐ 13:15 13:30 ‐ 13:45 14:00 ‐ 14:15 14:30 ‐ 14:45 15:00 ‐ 15:15 15:30 ‐ 15:45 16:00 ‐ 16:15 16:30 ‐ 16:45 17:00 ‐ 17:15 17:30 ‐ 17:45 18:00 ‐ 18:15 18:30 ‐ 18:45 19:00 ‐ 19:15 0 2.43 The key points shown in Table 2.9 and Figure 2.10 and 2.11 regarding changes in average journey times are: Journey time savings on the widened section, east of J2 are mainly in the peak periods of AM for westbound traffic and PM for eastbound traffic. These are approximately ½ minute. This reflects the highest flows as shown earlier in Figure 2.6 and Figure 2.7 and is clearly the benefit arising from the widening of the road from three to four lanes; and On the A2 west of J2 which was not widened there has also been savings in the peak tidal period. This is likely to be the impact from reduced congestion at the junction. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 29 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Journey Times on M25 main carriageway 2.44 Journey times on the M25 have been analysed using the same method as for the A2 above. Table 2.10 – Journey Times on M25 Section Direction Time period Average Journey Time (seconds) (weekdays) 2006 2009 Saving J3 – 2 AM 224 160 64 NB IP 204 194 10 PM 333 191 142 J2 – 3 AM 198 197 1 SB IP 179 167 12 PM 185 164 21 AM 49 32 17 IP 42 40 1 PM 58 52 6 J1b – 2 AM 68 52 16 SB IP 62 48 14 PM 63 47 17 Length 4.86km 4.94km J2 – 1b 5 NB 0.94km 1.36km Figure 2.12 – M25 J2-3 widened section 5 No high or medium quality data is available for the before period, so for J1b- 2, low quality has been used. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 30 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 18:45 ‐ 19:00 18:15 ‐ 18:30 17:45 ‐ 18:00 50 18:45 ‐ 19:00 18:15 ‐ 18:30 17:45 ‐ 18:00 17:15 ‐ 17:30 16:45 ‐ 17:00 16:15 ‐ 16:30 15:45 ‐ 16:00 15:15 ‐ 15:30 14:45 ‐ 15:00 14:15 ‐ 14:30 13:45 ‐ 14:00 13:15 ‐ 13:30 12:45 ‐ 13:00 12:15 ‐ 12:30 11:45 ‐ 12:00 11:15 ‐ 11:30 10:45 ‐ 11:00 10:15 ‐ 10:30 09:45 ‐ 10:00 09:15 ‐ 09:30 08:45 ‐ 09:00 08:15 ‐ 08:30 07:45 ‐ 08:00 07:15 ‐ 07:30 06:45 ‐ 07:00 06:15 ‐ 06:30 50 17:15 ‐ 17:30 16:45 ‐ 17:00 16:15 ‐ 16:30 15:45 ‐ 16:00 15:15 ‐ 15:30 14:45 ‐ 15:00 14:15 ‐ 14:30 13:45 ‐ 14:00 13:15 ‐ 13:30 12:45 ‐ 13:00 12:15 ‐ 12:30 11:45 ‐ 12:00 11:15 ‐ 11:30 10:45 ‐ 11:00 10:15 ‐ 10:30 09:45 ‐ 10:00 09:15 ‐ 09:30 08:45 ‐ 09:00 08:15 ‐ 08:30 07:45 ‐ 08:00 07:15 ‐ 07:30 06:45 ‐ 07:00 06:15 ‐ 06:30 Seconds Seconds Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study 450 Figure 2.13 – Average journey Times on widened M25 J3 – 2 (northbound) 400 350 300 250 200 150 100 June 2006 June 2009 0 Figure 2.14 – Average journey Times on widened M25 J2 – 3 (southbound) 450 400 350 300 250 200 150 100 June 2006 June 2009 0 31 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study 2.45 2.46 The key points shown in Table 2.10, Figure 2.13 and Figure 2.14 regarding changes in average journey times on the M25 are: The biggest savings in journey time have occurred on the widened section J3-2 northbound which has shown large improvements in the AM and PM peaks averaging 1 minute and 2 ⅓ minutes respectively, and limited evidence of improvement in the interpeak period; J2 – 3 southbound, also widened, showed an improvement throughout the interpeak period and a saving of ⅓ minute in the PM peak; and On the much shorter section J1b – 2, there have been savings of ¼ minute on the widened southbound section through the day. It should be noted that the journey time data for both directions for J1b – 2 is labelled in the JTDB as being of low quality for the before period which does not fully reflect the congestion problems known to occur then. Data used for the other sections is all high and medium quality. Therefore, it may be considered that the journey time savings observed here represent an underestimate of the journey time savings on this section. Journey times for turning movements at Junction Surveys 2.47 Journey times for turning movements at the M25 J2 are based on specially commissioned surveys using the moving observer method. This is based on timing trips made by survey cars on the variety of movements possible at this junction. 2.48 Moving observer data is based on a more limited sample than the JTDB but it can still illustrate the changes that have occurred for traffic making turning movements at the junction. Improving journey times for this traffic was the key objective of the A2/A282 scheme. 2.49 The 2004 surveys covered movements which used the roundabout to make the right-hand turns between the M25/A282 and the A2. Although this data did not directly cover other movements at the junction, it did include detailed GPS tracking data of the surveys on a second-by-second basis. For POPE analysis, this GPS data was analysed using GIS and associated software which allowed for the construction of proxy journeys using micro segments of the observed data. This allowed for coverage of all movements which used the circulating carriageway of the roundabout. 2.50 The only movement which was not observed and therefore could not be proxied was the use of the single free-flow link which existed in 2004, which links the M25 northbound to the A2 westbound. This is the one part of the junction which was not altered in any way by the A2/A282 scheme so the omission of data here is not an issue. 2.51 The 2009 moving observer surveys covered: 2.52 Journeys using each of the three new free-flow links; and Journeys making turning movements using the circulating carriageway of the roundabout. The surveys covered the same time periods: AM, IP and PM as before. Survey results 2.53 To evaluate the impacts, journey times were compared for traffic making each of the turning movements. Where a free-flow link existed in the after period this was used. 2.54 The results from the journey time surveys in the AM and PM peak periods and the inter-peak (IP) are summarised in Table 2.11. The movements for which traffic is now able to use the new freeflow links are indicated. Other movements use the roundabout (RBT). 2.55 Journey times for traffic in the after period making turning movements for which there is now a free-flow link but they still travel via the RBT to make the turn have been omitted from this analysis 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 32 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Table 2.11 – Journey Times for movements around the junction Time period A2 eastbound to M25 southbound From A282 north of junction A282 southbound to A2 eastbound A282 southbound to A2 westbound From M25 south of junction M25 northbound to A2 eastbound 3:30 IP 3:10 PM 3:10 AM 3:00 IP 2:30 PM 2:20 AM Time -2:00 1:30 -1:40 Free-flow link west of J2 A2 eastbound to M25 northbound AM Difference Via 1:30 1:50 -1:10 1:40 -1:00 2:40 0:20 1:40 1:30 -0:10 IP 1:30 1:40 0:20 PM 1:30 1:40 0:10 AM 2:40 1:50 -0:50 2:40 2:10 -0:30 PM 2:30 1:50 -0:40 AM 2:10 1:30 -0:40 IP 2:00 1:20 -0:40 PM 3:30 AM 2:40 IP 2:30 PM IP RBT From A2 Time Free-flow link A2 westbound to M25 southbound (2009) * * 2:20 -0:10 2:10 -0:20 3:00 3:00 0:00 AM 3:10 2:50 -0:20 IP 3:10 2:40 -0:30 PM 4:00 RBT east of J2 A2 westbound to M25 northbound RBT From A2 After (2004) Free-flow link Via Before RBT Origin Turning movement * *2009 PM peak period surveys on these routes were impacted by serious accident on day of survey, hence have been omitted. Other journey times were measured the day previously. 2.56 Note that the movement M25 northbound to A2 eastbound is omitted from the above table. This turning movement uses the only free-flow link which existed at the junction prior to the A2/A282 scheme and was not expected to be impacted by the scheme. Use of the free-flow link was not included in the journey time surveys in 2004 and hence was also omitted from the 2009 surveys. 2.57 The changes are also summarised in the following figures. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 33 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Figure 2.15 – Journey times from A2 east of J2 Figure 2.16 – Journey Times from A2 west of J2 Figure 2.17 – Journey Times from A282 north of J2 Figure 2.18 – Journey Times from M25 south of J2 2.58 The key points regarding changes to journey times for turning movements at the junction as shown in the above tables and figures are: 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 34 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study The largest observed improvement was for journeys using the new flyover which provides a free-flow link between the A2 eastbound and the A282 northbound, replacing a 270° turning movements around the signal controlled roundabout. This has shown savings of up to 2 minutes; The journeys using the other two new free-flow links (A2 westbound to M25 southbound and A282 to A2 westbound) have also shown large savings; Some of the turning movements which still pass through the signalised carriageway of the roundabout , i.e. that have not been directly changed by the scheme have also clearly been shown to benefit from the lower level of traffic circulation on the roundabout (as shown in Table 2.3). Of this traffic still on the roundabout, the one that particularly benefit are two of the movements making a 270° turning movement: - A2 eastbound to M25 southbound; and - M25 northbound to A2 eastbound. Little change was observed for movements in both directions using the roundabout to travel between the A282 and the A2 west of the roundabout. Traffic Forecasts vs. Outturn Background to both schemes 2.59 The basis of the traffic modelling for the A2/A282 scheme and the M25 scheme was the existing Kent Thames-Side (KTS) 2000 traffic model. This SATURN model was developed on behalf of Kent County Council and other local authorities, including Dartford Borough Council, and was made available to the Highways Agency for the purposes of the A2/A282/M25 traffic studies. 2.60 The forecast networks and demand include all committed and planned highway and development schemes at that time, as discussed and agreed with the Highways Agency, and local authorities. Local planning scenarios for developments and traffic restraint policies were also considered when developing forecasting models for local developments. The forecasting process included: 2.61 Forecasts for future years using the National Trip End Model (NTEM) to apply growth factors to travel movements within the study area; Application of local growth factors from TEMPRO 4.3 to car-based trips; Elastic assignment of trips to Do Minimum and Do Something networks to enable assessment of induced traffic; and Sensitivity testing of variable demand using DIADEM. As there were a number of major public transport initiatives within the KTS area which were being implemented during the appraisal and construction stages of these schemes, a high degree of elasticity was modelled for competing trips. This particularly applies to: Kent Thameside Fastrack Phase 1, a Bus Rapid Transport project comprised of 5.5 km of dedicated and segregated busway between Dartford railway station to Bluewater Retail Centre, completed in March 2006; and Channel Tunnel Rail Link (CTRL), presumably using Ebbsfleet station. A2/A282 Forecasts Original scheme 2.62 The Original forecasts for the scheme at OPR stage were: 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 35 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Traffic Forecasting Report 2002 OPR; Micro Simulation report May 2003; and Public Inquiry Traffic & Economics Proof of Evidence Summary (January 2002). 2.63 A key element of the basis of the modelling for the A2/A282 scheme was to take account of the modelling of the adjacent A2 Bean to Cobham Phase 1 & 2 widening schemes. Although these were undertaken by different consultants, a common approach was used for all. This was based on an upgraded version of the 1993 Kent Thames Side (KTS) model. It was assumed that both phases of A2 Bean to Cobham would be built. 2.64 The SATURN software was used for modelling the area wide traffic assignments and the microsimulation software GETRAM was used to assess the detailed vehicle interactions in the area of the Scheme. Input traffic flows for GETRAM were provided by the SATURN traffic model. 2.65 The future traffic year forecasts were produced for the scheme taking account of the following elements: local and strategic traffic growth; proposed developments; reassignment effects; and induced/suppressed traffic. 2.66 SCOOT data from the signals at the roundabout and TrafficMaster data on the A2 east of the junction were reported in the Traffic and Economics Supplementary Proof of Evidence report (2004) to show congestion regularly occurring at the junction and on the A2. 2.67 The assessment of induced traffic due to the scheme showed that the effects of trip induction or trip suppression would be small for both low and high growth. Revised scheme – Link E deferred 2.68 A summary of the revised modelling for the Link E deferred scheme was described in ‘A2/A282 Dartford Improvement Report on Deferment of Link E and Revised Landscape and Drainage Attenuation Proposals in North West Quadrant of Junction 2’. 2.69 This report stated that the analysis using TRANSYT and micro-simulation (using AIMSUM) of the junction concluded that under the high growth scenario, the revised layout would perform satisfactorily at least until 2016. It was not considered to be practicable for high traffic growth to continue beyond this time due to the limitations which would be imposed by the surrounding network. Thus, assessment of the capacity of the interim solution beyond 2016 was been based on 60:40 low to high growth – a recognized basis for junction design, and on low growth. Under both scenarios, the analyses indicated that the proposed solution would perform satisfactorily up to the design year. 2.70 The traffic programme ARCADY was used to test the option of operating the junction without signal. This indicated that the junction would not operate satisfactorily as an uncontrolled roundabout and that signals would be required. 2.71 The TRANSYT modelling for the original scheme indicated that under high growth forecasts, the junction would operate adequately with signals at both the opening year 2007, and at the design year 2022. With link E missing, the junction would still operate adequately in the design year with low growth, but with higher traffic growth rates, congestion would occur earlier than the design year. 2.72 No new traffic forecasts were included in the deferment report. Evaluation of Forecast vs. Outturn with Scheme 2.73 The Traffic Forecasting Report gave forecast daily traffic (AADT) for the opening year of 2007. For purpose of comparison with the observed data in this study, proxy 2009 forecasts were 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 36 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study calculated using a straight line growth assumption between the forecasts for the opening year and design year of 2022. These proxy forecasts and the observed figures are compared in Table 2.12. Table 2.12 – A2/A282 scheme: Forecast vs. Outturn AADT (2009) % difference Direction Forecast Low growth High growth Observed Low growth High growth WB 59,700 65,900 67,300 13% 2% EB 58,800 65,500 67,000 14% 2% WB 47,800 51,000 51,500 8% 1% EB 46,900 51,400 56,700 21% 10% Flyover from A282 to A2 eastbound 16,000 18,600 16,600* 4% -11% Flyover from A2 westbound to A282 northbound 16,500 19,200 15,600* -5% -19% Dedicated slip A2 eastbound to M25 southbound 12,800 13,600 11,700* -9% -14% M25 J2 -3 NB 71,900 81,900 70,600 -2% -14% M25 J2 -3 SB 69,400 78,600 64,700 -7% -18% M25 J1b-2 & A282 link roads NB 77,300 89,300 70,300* -9% -21% SB 74,700 85,500 65,000* -13% -24% Location A2 east of M25 A2 west of M25 *Observed data from 2009 is based on a single day 2.74 The key points are: Traffic on the A2 has growth in line with the High growth forecasts; One of the new flyovers , from the A282 to A2 east is as expected but the other two free-flow links appear to be below forecast; M25 traffic is well below all forecasts. As shown earlier, traffic has shown negligible growth on this part of the M25 for several years, indicating that without the scheme, traffic would still be below the modelled Do Minimum and that the forecast small increase on opening did not occur; and From this data, it appears that the economic recession has had strong influence on dampening traffic growth on the M25 in line with wider regional trends whilst traffic growth on the A2 has bucked the trend. Evaluation of Forecast without scheme vs. Observed before scheme 2.75 In addition to comparing the forecast traffic flows with the scheme, the forecasts for the main links without the scheme in what would have been the opening year (i.e. the Do Minimum scenario) have also been compared with the observed data before the start of construction in 2006. These are summarised in Table 2.13. Forecasts are as specified for 2007 without factoring and observed data is also unfactored here. Note that 2006 observed data will not have been affected by the recession. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 37 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Table 2.13 – A2/A282 scheme: Forecast Do Minimum (2007) vs. Observed before AADT (2006) % difference Direction Forecast (2007) Low growth High growth (2006) Low growth High growth WB 53,900 58,900 61,000 13% 4% EB 55,000 65,000 62,800 14% -3% WB 44,600 48,000 52,500 18% 9% EB 44,800 48,200 55,700 24% 16% M25 J2 -3 NB 68,700 79,500 65,600 -5% -17% M25 J2 -3 SB 68,500 77,800 69,400 1% -11% M25 J1b-2 & A282 link roads NB 70,500 81,000 74,000 5% -9% SB 71,100 80,900 71,500 1% -12% Location Observed A2 east of M25 A2 west of M25 The key points regarding the accuracy of the Do minimum forecasts are: Before the A2/A282 scheme construction started, traffic growth on the A2 was near or above the high growth forecasts; Of particular note is that the traffic on the widened section of the A2 east of the M25 differed form the forecast Do minimum by a similar proportion to that shown in Table 2.12 for the Do Something forecast compared to the Observed data. This shows that the forecast impact of the scheme on traffic growth on the A2 was accurate because the reason that the outturn data was higher than predicted was due to growth between the time of appraisal and the start of construction; and M25 data was at the low end of the forecast range. M25 J1b – 3 Forecasts 2.76 The M25 scheme was modelled with SATURN models which were based on those used for the A2/A282 Dartford Improvement, with the base year model re-validated to 2004 using 2004 traffic counts enhanced for the addition of the widened M25 J2 to 3 and also updated to include network changes that had occurred up to 2004. 2.77 The modelled scenarios for this M25 J1b – 3 scheme were based around: 2.78 Do Minimum – no M25 scheme and no A2/A282 scheme (without link E); and Do Something – both M25 scheme and A2/A282 scheme (without link E) completed. An assessment of induced traffic due to the proposed improvement showed that the effects of trip induction or trip suppression would be small; there would be a small increase in traffic flows through the M25 corridor in the Do Something scenario compared to the Do Minimum. Evaluation of Forecast vs. Outturn with Scheme 2.79 The M25 Stage 3 Scheme Assessment Report gave forecast daily traffic (AADT) for the opening year of 2008. For the purpose of comparison with the observed data, proxy 2009 forecasts were calculated using a straight line growth assumption between the opening year and design year of 2023. These are shown in Table 2.14. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 38 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Table 2.14 – M25 scheme: Forecast vs. Outturn AADT (2009) % difference Direction Forecast Low growth High growth Observed Low growth High growth NB 80,800 89,400 70,600 -13% -21% M25 J2 -3 SB 74,000 83,500 64,700 -13% -23% M25 J1b-2 excluding link roads NB 71,000 80,300 55,600* -22% -31% SB 69,900 78,200 54,100* -23% -31% Location M25 J2 -3 *Observed data from 2009 is based on a single day 2.80 The key points on the accuracy of the traffic forecasts are: Observed traffic on this section of the M25 is substantially lower than the forecasts; and Both low and high growth forecasts were based on growth from the base year traffic figures of 2004/5 of between 2% and 23% but this clearly has not occurred. Evaluation of Forecast without scheme vs. Observed before scheme 2.81 In addition to comparing the forecast traffic flows with the M25 scheme, the forecasts for the main links without the scheme in what would have been the opening year (i.e. the Do Minimum scenario) have also been compared with the observed data before the start of construction of the A2/A282 scheme in 2006. These are summarised in Table 2.15. Forecasts are as specified for 2008 without factoring and observed data is also unfactored here. Table 2.15 – M25 scheme: Do Minimum (2008) vs. Observed before AADT (2006) 2.82 % difference Direction Forecast (2008) Low growth High growth 2006 Low growth High growth NB 78,000 84,000 65,600 -16% -22% M25 J2 -3 SB 72,000 80,000 69,400 -4% -13% M25 J1b-2 excluding link roads NB 70,000 78,000 64,100 -8% -18% SB 68,000 77,000 65,400 -4% -15% Location M25 J2 -3 Observed The key points on the accuracy of the traffic forecasts are: Clearly even without the two schemes, a high rate of growth was forecast for the M25; and Allowing for the two year difference between the observed data in 2006 before construction and the Do Minimum forecasts, it is clear that the traffic on the M25 was at the low growth end of the range of traffic forecasts. Therefore the below forecast levels of traffic with the scheme as shown in Table 2.14 are partly due to lower growth in the period before construction which also predates the recession impact. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 39 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Journey Time Forecasts A2/A282 2.83 There were no forecasts of journey time savings in the appraisal. Only matrix based results for the whole network were specified. These cannot be compared to observed data. M25 J1b – 3 2.84 As with the A2/A282 scheme, the appraisal was matrix based. 2.85 The Scheme Assessment Report (SAR) states that comparisons of modelled travel times in the peaks and inter-peak periods in the M25 corridor indicated that there would be travel time savings with the Scheme. Average modelled vehicle speeds were similar for M25 traffic for both the Do Minimum and the Do Something models, despite the additional traffic. This is explained by the increase in capacity of the motorway to absorb increased traffic flows during peak periods and hence reduce congestion on the motorway section between junctions 1b and 3. 2.86 The SAR includes the following statements on the effect of the scheme on travel times: 2.87 2.88 2.89 Comparisons of modelled travel times for the three time periods indicated that there would be travel time savings with the Scheme, which are translated into economic benefits ... Average modelled vehicle speeds were similar for M25 traffic for both the Do Minimum and the Do Something models. This is explained by the increase in capacity of the motorway to absorb increased traffic flows during peak periods and hence reduce congestion on the motorway section between junctions 1b and 3. There are no further details on how the model derived travel time savings when the speed with the scheme is similar to that without and there was only forecast to be a small increase in traffic flows. However, the AST did include the following forecast under the wider economic benefits: Average journey times between J1b and 3 would be reduced by 30-60 sec in 2008 …relative to the baseline The journey time savings detailed above indicate that savings have been 81 – 148 seconds northbound and 16 – 38 seconds southbound in 2009. Therefore it is concluded that the forecast saving has been achieved and have been exceeded for some time periods. The better than expected time savings may be an impact of the lower than expected traffic growth. Key Points from Traffic Section Background recession This study has taken place against a background of the current recession which started in mid 2008. DfT data for the wider road network in the South East and Kent showed no traffic growth between 2006 and 2008 and provisional data for Great Britain shows that the decline continued in 2009; and The impact seen on the strategic road network is also seen in long term trends on other sections of the M25 which show negligible change in daily traffic between 2005 and 2009. Impact on traffic numbers At the junction, the new free-flow links between the A282 and A2 east of J2 were used by 12,800 and 12,000 vehicles respectively in a 12 hour period on a weekday. The new link between the A2 east and M25 south of J2 was used by 9,000 vehicles in 12 hours. The flows on the new free-flow links equate to a total of 44,000 vehicles benefiting from these free-flow movements per day; The new free-flow links have resulted in a reduction of a third in the volume of traffic at J2 using the circulating carriageway of the roundabout. This contributes to reduced congestion of this traffic; The Widened M25 J2-3 is used by 135,000 vehicles daily, which is a negligible change from that before the scheme; 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 40 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Changes to the layout of the A282/M25 J1b-2 has resulted in an increase in use of the link roads between the junctions J1b – 2; Traffic on the widened section of the A2 is 130,000 AADT. It has shown growth of 7-8% on weekdays. This has occurred particularly during the peak periods. This increase may be partly explained by the completion of other schemes on the A2 east; There is no evidence that the schemes have reduced traffic on local A roads parallel to the widened M25 and A2; and The proportion of HGVs (vehicles >5.2m) has shown little change following the completion of the schemes. Impact on Journey Times Journey times using the new free-flow links at the junction have improved by up to 2 minutes; For traffic still using the roundabout, journey times have improved for some turning movements, particularly those making 270 degree right turns, and remained little changed for others; On the widened A2, there was been a ½ minute saving in the AM peak westbound and PM peak eastbound, reflecting the tidal flow on this road; On the M25, the biggest savings in journey time have occurred on the widened section J3-2 northbound which has shown with large improvements in the AM and PM peaks, averaging 1 minute and 2 ⅓ minutes respectively and an improvement in the interpeak; On the M25 J2 – 3 southbound, also widened, journey times showed savings through the interpeak period and a saving of ⅓ minute in the PM peak; and On the much shorter widened section J1b – 2, there have been saving of ¼ minute on the widened southbound section through the day but this is probably an underestimate due to the limitations of the data on journey times in the before period. Accuracy of Forecasts Traffic flow forecast for the A2/A282 scheme accurately predicted the growth on the improved section of the A2. Before construction started, actual traffic growth was already high and the recession did not slow this growth. It may also be that the impact of the additional A2 widening schemes (Bean to Cobham phases 1 and 2) has contributed to growth on the A2; Conversely on the M25, the traffic predictions for the scheme, which had shown growth both with and without the scheme, have turned out to be overestimates. This can be linked to growth being lower than forecast before scheme construction and the impact of the recession post opening; and Journey time saving forecasts for the M25 have been achieved, and bettered for northbound traffic. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 41 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study 3. Safety Introduction 3.1 This section presents an evaluation of how the scheme is performing against the NATA safety objective. WebTAG states that this objective is: 3.2 To reduce the loss of life, injuries and damage to property resulting from transport accidents and crime. The Safety Objective has two sub-objectives: to reduce accidents; and to improve security. Data Sources Accident data 3.3 For the purposes of this study, accident data has been obtained from the Managing Agent Contractors (MACs) for the HA Area 4 (which includes the A2 in Kent) and Area 5 (which includes the M25 including J2, the A282 and the section of the A2 west of the M25) for the periods: Five years before start of construction: August 2001 to July 2006; Eighteen months post opening: January 2008 to June 2009 for the whole area and For the widened M25 only, 15 months of post completion data was obtained for Aug 2008 – October 2009. 3.4 The construction period for these schemes have been excluded from the analysis as traffic flows are not typical during this time period and the presence of traffic cameras will have affected driver behaviour. 3.5 The accident data is based on the records of personal injury accidents recorded in the STATS19 data collected by the local police when attending accidents and collated by the local authority. 3.6 For comparison purposes, accident summary data for Kent CC roads was obtained from the Kent Travel Report 2008. 3.7 The accident data referred to in this report has not necessarily been derived from the national validated accident statistics produced by the DfT. As such, the data may subsequently be found to be incomplete or contain inaccuracies. The requirement for up-to-date information and site specific data was a consideration in the decision to use unvalidated data and, as it is sourced from the Highways Agency’s Managing Agency Contractors, it is sufficiently robust for use in this context. Forecasts 3.8 The safety forecasts used in this evaluation are based on those given in the Stage 3 Scheme Assessment Report (M25), Economic Assessment Report (A2/A282) and the schemes ASTs. These were based on a spreadsheet analyses rather than a full COBA model. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 42 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Accidents Scope of Accidents Analysis 3.9 Accident data was obtained for the wide area indicated on the left in Figure 3.1 covering the sections of the strategic road network directly improved by the scheme and sections beyond: A282/M25 between the southern slips for J1a and northern slips for J4; and A2 between the junctions east and west of the M25 J2 (i.e. B255 and A2018). Figure 3.1 – Accident study areas 3.10 3.11 Analysis of this accident data has been undertaken, split into the three areas shown in Figure 3.1: Whole area of trunk roads based on the M25, A282 and A2 including the area directly improved by the schemes and the sections of these roads beyond in each direction to the next junction; A2 improved by scheme, M25 J2 circulating roundabout and free-flow links, A282 and local road links between J2 and J1b (shown in the right inset); and M25 J2 – J3 both directions, excluding junctions (shown in the lower inset). It should be noted that accident data for the local roads surrounding the strategic road network was not collected and analysed. This was because although it was forecast that local roads in the Kent Thameside area would experience safety benefits from some traffic rerouting onto the strategic roads, this impact would be small and spread over a wide area over the long term. It would not be feasible to identify these impacts derived from these schemes as distinct from many 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 43 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study other more significant factors impacting safety on local roads over a wide area in the 6½ years studied. However, overall annual road traffic accident figures for Kent and the Dartford Area are presented primarily for comparison purposes. Wide area strategic road network (A2, A282 and M25) 3.12 The numbers of accidents in the wide area shown in Figure 3.1 over the before and after periods are shown in Table 3.1. Table 3.1 – Accident Numbers over Wide area network Accidents by Severity Total Period Fatal Serious Slight (annual equivalent) 2001 (Aug-Dec) 1 10 59 70 (168) 2002 4 18 160 182 2003 1 17 144 162 2004 2 11 157 170 2005 1 19 177 197 2006 (Jan-Jul) 2 7 92 101 (173) Total 5 years before 11 82 789 882 2008 1 14 158 173 2009 (Jan – Jun) 3 4 72 Total 18 months after 4 18 230 Accident Saving 3.13 Annual Average 79 (158) Fatal + Serious All 18.6 176.4 14.7 168.0 3.9 8.4 252 Key points regarding the accident numbers in the wider area based on the above data and Kent CC data are: The annual average accident total shows a small reduction (5%) between the before and after periods; However, this reduction in accident numbers on these strategic roads is similar to that reported by Kent CC on the local authority roads in both the whole of Kent and in the Dartford area only which both saw a reduction of 6% between 2003 and 2008; and The reduction in both overall accident numbers and of the number of fatal and serious accidents only is too small to be a statistically significant difference at this stage6. Accident locations on routes within the two Schemes only (A2, A282 and M25) 3.14 The locations of the accidents in the before and after periods on the sections of road directly improved by each of the two schemes are shown in Figure 3.2 and Figure 3.3. 3.15 The high traffic volumes and long time periods mean that these figures show a large number of accidents on the routes studied, but there are noteworthy points here: 6 Before the A2/A282 scheme was built, the greatest accident density on this network was clustered around the junction, as would be expected; Based on a Chi-square test using a 95% confidence level. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 44 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study In the 18 months following the opening of the A2/A282 scheme, the new free-flow links show few accidents and the clustering around the circulatory roundabout is reduced; and Accidents of the widened section of the M25 show no distinct pattern of clustering. 3.16 Detailed mapping of the locations of accidents at the junction was investigated but has not been included here as they show little because of the density of accidents over the time period and there are limitations in the accuracy of the locations in the data. 3.17 Analysis of the safety impacts is covered in more detail in the following sub-sections. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 45 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Figure 3.2 – Accidents in five years before within the extents of A2 and M25 schemes 2001‐2006 Accidents Fatal Serious Slight Extent of Scheme © Crown Copyright All Rights Reserved. Highways Agency 100018928.2010 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 46 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Figure 3.3 – Accidents in 18 months (2008-mid 2009) within the extents of A2 and M25 schemes 2008‐2009 Accidents Fatal Serious Slight Extent of Scheme © Crown Copyright All Rights Reserved. Highways Agency 100018928.2010 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 47 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Improved A2/A282/M25 J2 junction and widened A2 3.18 The numbers of accidents on the roads directly improved by the A2/A282 scheme only, as shown in Figure 3.4, over the before and after periods are shown in Table 3.2. Figure 3.4 – Area for A2 and junction accidents (M25 through J2 excluded) © Crown Copyright All Rights Reserved. Highways Agency 100018928.2010 Table 3.2 – Accident Numbers over A2/282 scheme area only Accidents by Severity Annual Average Total Period Fatal Serious Slight (annual equivalent) 2001 (Aug-Dec) 0 2 15 17 (40.8) 2002 2 6 56 64 2003 0 9 50 59 2004 1 2 49 52 2005 0 5 46 51 2006 (Jan-Jul) 1 1 21 23 (39.4) Total 5 years before 4 25 237 266 2008 0 4 46 50 2009 (Jan – Jun) 0 1 17 18 (36) Total 18 months after 0 5 63 68 Accident saving 3.19 3.20 1 Fatal + Serious All 5.8 53.2 3.3 45.3 2.5 7.9 Key points regarding the accident numbers on the improved A2 and the junction based on the above data are: The annual average accident total shows a reduction of roughly eight fewer accidents including 2½ fatal or serious accidents; and However at this stage this change is not statistically significant1. Mapping of the locations of these accidents is shown in Figure 3.2 and Figure 3.3. These pictorially show the density of accident clustering around the junction as expected. The after mapping indicates that the free-flow links have a good safety record with few accidents. Based on a Chi-square test at 95% confidence. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 48 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study 3.21 We attempted to analyse the accident locations at a more detailed level at the junction but unfortunately the detailed mapping of accident locations within the junction was not possible due to limitations of the grid reference information in the available dataset. Widened M25 J2 – J3 3.22 The M25 scheme was the widening of the section from J2 – 3 in both directions and the short section of southbound carriageway between J2 and J1b. However due to the complexity of the section north of J2 and the imprecision of some of the location data in the accident dataset, accident numbers for J1-2 have been included in the above analysis and this sub-section only considers the M25 main carriageway between J2 to J3 and through J2 as indicated in Figure 3.5. Figure 3.5 – Area for M25 J2 – 3 accidents © Crown Copyright All Rights Reserved. Highways Agency 100018928.2010 3.23 Note that no accidents are duplicated in Table 3.2 and Table 3.3. Table 3.3 – Accident Numbers on M25 scheme area only Accidents by Severity Total Period Fatal Serious Slight (annual equivalent) 2001 (Aug-Dec) 0 1 5 6 (14.4) 2002 1 5 28 34 2003 0 3 29 32 2004 0 2 28 30 2005 0 2 22 24 2006 (Jan-Jul) 1 1 11 13 (22.3) Total 5 years before 2 14 123 139 2008 (Aug-Dec) 0 0 8 8 (13.7) 2009 (Jan – Oct) 1 2 16 19 (22.8) Total 15 months after 1 2 24 27 Accident saving 3.24 Annual Average Fatal + Serious All 3.2 27.8 2.4 21.6 0.8 6.2 Key points regarding the accident numbers on the main carriageway of the widened M25 and through the junction based on the above data are: 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 49 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study 3.25 The annual average accident total shows a reduction of roughly six fewer accidents, including one fatal or serious accident in the after period compared to that before; However at this stage this change is not statistically significant1. Analysis of the locations of the accidents in Table 3.3 shows them to be distributed throughout the length studied with no clear pattern between the before and after periods. The data does not include lane information hence the pattern is effectively the same for the two periods. For this reason maps showing these accident locations in the M25 widened section are not included here. Combined Safety Impact of both schemes 3.26 The above tables have shown the accidents in the areas directly impacted by the schemes split into the parts of the road network most impacted by each scheme. However it is clear that safety impacts of the schemes are interlinked. For example, severe congestion at J2 can lead to traffic queues stretching back to the M25 main carriageway creating a safety risk. In this case, the junction improvements of the A2/A282 scheme could be expected to save accidents on the M25. 3.27 Additional analysis has been done to consider the combined safety impact of the two schemes. This also provides a stronger base for statistical analysis. 3.28 Table 3.4 shows the total accidents within the areas of the two schemes. Note that unlike Table 3.1, this does not include accidents on the A2 or M25 beyond the boundaries of these schemes. Table 3.4 – Accident Numbers on A2/A283 and M25 schemes area Accidents by Severity Annual Average Period Fatal Serious Slight Total Fatal + Serious All Total 5 years before Aug 2001-Jul 2006 6 39 360 405 9 81 Total 18 months after Jan 2008 – Jun 2009 2 6 89 97 5.3 64.7 3.7 16.3 Accident saving 3.29 Key points regarding the overall accident numbers around J2 and the improved sections of the M25, A2 and A282 are: The annual average accident total shows a reduction of 16 fewer accidents , including nearly four fatal or serious in the after period compare to that before; and This overall impact of the two schemes combined has produced a large enough saving in total accidents to be statistically significant2. Forecasts 3.30 Normally, accident impacts for major highway schemes are appraised using the COBA modelling software which forecast the saving in terms of both accident numbers and economic benefit thereof. However, in the case of both of these schemes a spreadsheet approach was taken instead and the results summarised in the appraisal reports. The details of the spreadsheet appraisals were not available for this study. 3.31 The Economic Assessment Report (EAR) for the A2/A282 scheme explained the advantages for using a spreadsheet approach. These were: 1 2 Based on a Chi-square test at 95% confidence. Ibid 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 50 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study The analysis would have a direct connection with the SATURN model including the modelling of congestion which would be very different from that modelled by COBA; and COBA assumptions, accident rates and formulae could be used. M25 3.32 The Stage 3 Scheme Assessment Report (SAR) stated that the safety objectives were to: Reduce the number of accidents on the local road network; and Minimise the number of reportable accidents and safety incidents during construction. 3.33 The appraisal included the assessment of the number and severity of accidents that would occur with and without the Scheme. These were assessed by analysing the network flows and applying default accident rates from the Department for Transport’s Cost Benefit Analysis (COBA) model. The SAR did not include details of the scope of roads included. 3.34 The safety forecast in the AST was: 3.35 forecast Increase in accident rate on M25 J1b – 3 as a result of increase in traffic from widening is more than compensated for by reductions in traffic on local roads from traffic reassignment to M25, resulting in monetary benefits and overall reductions in accidents. The AST did not detail the number of accidents forecast to be saved; only giving a range of monetised safety benefits ranging from £0.9m to £4.2m. Using the default accident rates and the accident values specified in the COBA manual1, it can be shown that the forecast accident saving was equivalent to less than one per year. 3.36 Which of the local roads forecast to show a safety benefit from reassignment to the widened M25 was not specified. However it is presumed that that this refers to the A225 which is the only North-south parallel A road in the area. The traffic forecasts (detailed earlier in Table 2.14) did not include non-strategic roads so there is no forecast of the impact, and the observed change on this road as shown in Table 2.7 was an increase. On this basis, it is not reasonable to attribute a safety benefit on this A road due to traffic routed away. A2/A282 3.37 The Economics Assessment Report (June 2002) describes the safety appraisal for this scheme. This was based on a spreadsheet using the traffic flows in the opening year and design year combined with accident rates from COBA which were applied as combined link and junction accident rates. The EAR shows that the forecast accident saving in the opening year under both high and low growth scenarios was three accidents. 3.38 The EAR was based on a 30 year appraisal period. 3.39 The Stage 3 Scheme Assessment AST stated that: 3.40 Improved junction layout to deal with peak-time queuing problem on A2 and M25 should improve safety. (Figures include accidents saved in Kent Thameside area and exclude accidents during maintenance and construction of Scheme.) A saving of 77 accidents was forecast. When the revised scheme (known as Link E deferred) was proposed in 2006, no reappraisal of the safety impact occurred as it was considered that the change in benefits would be small. Only the safety economic impacts were rebased. Therefore the 30 year appraisal period was retained. Combined forecast vs. observed saving 3.41 The forecast opening year savings compared to the outturn are summarised in Table 3.5. 3.42 It should be noted that the forecasts were based on a wider area including Kent Thameside where safety benefits were forecast based on the beneficial impact of some traffic reassignment to the motorway network. Accident data for the local roads was not covered by this analysis because it 1 COBA manual, Part 2 The Valuation of Costs and Benefits 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 51 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study is clear that in the time period covered that it would to be unrealistic to reliably distinguish the (forecast small) impact of the nearby schemes from many more local impacts. Table 3.5 – Forecast vs. observed accident savings Scheme Forecast opening year Saving (including Kent Thameside) A2/A282 Outturn Annual Saving (scheme areas only) 3 16.3 M25 J1b – 3 below 1 3.43 This table of the findings of the observed accident data from the first 18 months shows that the accident saving has been much better than the combined forecasts. 3.44 An explanation for this higher than expected accident saving in the post opening period may reflect some temporary changes in driver behaviour following from the period during the roadworks when traffic cameras were in force . At the time of the site visit in February 2010, a camera sign could still be seen, as shown in Figure 2.5. 3.45 The POPE five years after evaluation will be able to examine the long term trend of the safety impact. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 52 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Security Forecasts 3.46 Forecasts of the security sub-objective impact are included in the AST for each scheme. A2/A282 3.47 The AST states that the impact of the proposed CCTV coverage at J2 would be slightly beneficial in terms of security. M25 3.48 The AST states that there would be slight benefits to security as CCTV was incorporated throughout M25 J1b to 3. Emergency call facilities would be improved compared to the existing situation, a slight positive. 3.49 The SAR states that the provision of four CCTV cameras would ensure that the police could monitor the road between J2 and J1b where the layout means that emergency phones could not be installed. Evaluation 3.50 10 CCTV cameras were installed at locations on the main carriageway of the M25 and A2, and at the junction as planned. 3.51 It is understood from the contractors that most of these cameras were fully operational at the time of this evaluation, although the commissioning of the communications infrastructure as part of the wider works for the Controlled Motorway on the M25 was still being finalised. Images from several of the cameras are publicly accessible from the trafficengland.com website. Figure 3.6 shows an image from the camera next to the anti-clockwise carriageway approaching the slip road for J2. At this location the CCTV enables the monitoring of a bridge section of the widened M25 where there is now no hardshoulder. 3.52 It is concluded that the presence of the CCTV and emergency call facilities is slightly beneficial, as expected. Figure 3.6 – CCTV image of M25 and J2 southern slip road tie-ins 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 53 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Key Points from Safety Section Impact on Accident numbers The numbers of accidents in the areas covered by the schemes has reduced in the post opening period by an annual average of: Eight accidents for the area covered by J2, the widened A2 and the A282/M25 J1b – 2; and Six accidents for the widened section of M25 J2 – 3. Combined accident savings in the areas covered by the two schemes shows a statistically significant saving of 20%. Small savings in the numbers of fatal and serious accidents have been observed although at this stage it is too soon to determine the significance of these changes. An explanation for this higher than expected accident saving in the post opening period may be that there was a continuance of the changes in driver behaviour from the period during the roadworks when traffic cameras were in operation . The POPE FYA will be able to consider the safety impact with greater certainty. Impact on Security The CCTV cameras have been installed as planned providing a beneficial impact to road users as expected. Accuracy of Forecasts The forecast savings in the number of accidents in the opening year for both schemes were very low, hence it was not expected that a real change would be observed at this stage since opening. However the saving in the first 18 months around J2 and over the widened sections of the schemes shows a saving of 16 accidents per year which is a statistically significant improvement and which is better than forecast. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 54 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study 4. Economy Introduction 4.1 As described in the introduction of this report, the A2/A282 and M25 J1b – 3 schemes were developed separately. The A2/A282 scheme was a standalone scheme prior any consideration of the M25 scheme, and the M25 J1b-3 scheme originated from M25 rapid widening proposals which included this as one the considered sections. 4.2 In early 2006, additional economic appraisals were undertaken for each scheme. These each included consideration that the other scheme would be built. There was also appraisal for low and high growth for each of four scenarios for the proposed variations to the approved version of the A2/A282 scheme, namely: Link E built and open in 2007 as previously planned; Link E deferred to 2014; Link E deferred to 2022, the design year; and Link E deferred for whole evaluation period. 4.3 It was possible that the benefits to the Link E deferral from construction cost savings could be offset by the extra vehicle travel time delays and accidents incurred by not building Link E. 4.4 The costs and benefits of the last three of the above scenarios are detailed below. 4.5 Additional to these two schemes, the M25 J2 – 3 Controlled Motorway scheme was separately appraised in 2009. This is based on infrastructure put in place when this section of the M25 motorway was widened. It was not in operation at the time of this study so has not impacted the findings presented here. Economic Appraisals A2/A282 Economic Appraisal 4.6 The original economic appraisal (A2/A282 Dartford Improvement Economics Assessment Report Part 1 Methodology and Part 2 Economic Assessment) was issued in 2003 for the OPR. 4.7 Following a cost challenge review and proposal to modify the scheme by deferring the construction of the free-flow Link E, a revised assessment was undertaken and was summarised in the report A2 / A282 Dartford Improvement Economic Assessment Report Addendum II (June 2006). The review also updated the economic parameters in line with revised Government guidelines. That is the appraisal period was revised from 30 to 60 years, the price base to 2002 prices and discounting changes to 3.5% for the first 30 years and 3% thereafter. This addendum was the final appraisal prior to construction and has been used as the basis of this evaluation. M25 J1b – 3 widening Economic Appraisal 4.8 The scheme was originally modelled as part of a wider study into the rapid widening of sections of the M25 for opening year of 2011 and for scenarios with or without Road User Charging (RUC) based on the NAOMI5 strategic model. 4.9 The Stage 3 Economics Assessment Report (EAR) addendum was issued in September 2006 and included an economic assessment of the M25 J1b to J3 Widening Scheme with Link E of the A2/A282 Dartford Improvement Scheme deferred. 4.10 Modelling was based on TUBA v1.6c2 (Transport User Benefit Appraisal) using standard economic parameter files and output from SATURN Model. This provided details of user benefits, vehicle operating costs and revenue charges. The opening year was assumed as 2008 and the horizon year 2067, providing for a 60 year assessment period. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 55 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study 4.11 The time periods modelled were average morning peak hour, representing the period 0700 – 1000, average interpeak hour, representing the period 1000 – 1600 and average evening peak hour, representing the period 1600 – 1900. 4.12 The approved EAR, dated September 2006 reported the benefits of the Scheme assuming full implementation of the original version of the A2/A282 Dartford Improvement scheme, including Link E, from 2007. However, an Addendum to the EAR, also dated September 2006, was issued reporting the benefits of the M25 J1b to J3 Widening Scheme and reflected the revised proposal for the A2/A282 scheme in which the construction of Link E at J2 would be deferred. This reflects the as-built situation and hence has been used in this study. M25 J2 – 3 Controlled Motorway (CM) 4.13 The appraisal of this additional scheme was reported in an Impact Assessment report in May 2009. This stated that it would cost £9.5m to build followed by a first year cost of £6m. Benefits were assessed for 30 years as £31.4m based on observed impacts of CM on M25 J10-16. Monetary benefits are derived mainly from accident savings. 4.14 At the time this study was completed, the CM was not in operation, therefore had had no impact on the observed benefits of the widening scheme. Therefore, this is comparable with the forecasts which did not include the CM in the appraisals. 4.15 The evaluation of the CM scheme is not covered by POPE. Overall Appraisals Summary with various scenarios 4.16 Table 4.1 shows the alternative appraisals, excluding those which included Link E in the scheme as completed in 2007, as that scenario did not happen. For each scenario low (LG) and high growth (HG) were modelled in TUBA. Table 4.1 – Appraisal of Monetised Costs and Benefits for A2/A282 under various scenarios A2/A282 Dartford Improvement EAR II Link E deferred For full 60 years LG HG to 2022 LG to 2014 HG LG HG Consumer User Benefits £48.5m £98.2m £49.9m £106.0m £50.7m £111.6m Business User Benefits £67.5m £110.7m £76.0m £123.3m £78.6m £130.3m Private Sector Provider Impacts £18.8m £14.3m £20.5m £19.9m £21.2m £20.8m £1.8m £0.0m £1.8m £0.0m £1.8m £0.0m £136.7m £223.2m £148.2m £249.2m £152.3m £262.7m Investment £97.3m £97.3m £103.2m £103.2m £104.9m £104.9m Indirect tax £4.1m £5.8m £4.9m £8.1m £4.9m £8.7m £101.3m £103.0m £108.1m £111.3m £109.7m £113.6m Net Present Value £35.3m £120.1m £40.2m £137.9m £42.6m £149.1m Benefit to Cost Ratio 1.35 Accident Benefits Present Value of Benefits Present Value of Costs 4.17 2.17 1.37 2.20 1.39 2.31 This clearly shows that delaying the construction of Link E was forecast to impact the economics of the A2/A282 scheme by: 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 56 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Reducing the benefits slightly; Reducing the costs slightly; and Reducing the BCR slightly. 4.18 For this scheme, the model shows large private sector provider benefits. The EAR states that this is the revenue gained by the operators of the Dartford Crossing. Equivalent amounts are disbenefits deducted from the consumer and business user benefits total as shown above. No further details are provided. 4.19 Indirect taxation represents the change in the government’s taxation revenue as a result of a scheme. In the case of this scheme, the model forecast that changes in traffic behaviour would result in a reduction tax being raised. In such a case where there is neither change in road length nor a drop in traffic levels, this would be as a result of greater fuel efficiency due to reduced congestion. 4.20 For the M25 scheme, Table 4.2 similarly shows how the economic forecasts were impacted by the alternative scenarios for growth and for the link E in the A2/A282 scheme, excluding that which included Link E in the scheme as completed in 2007, as that did not happen. For each scenario low (LG) and high growth (HG) were modelled in TUBA. 4.21 Note that modelling was based on comparing a Do Something scenario with both schemes completed against a Do Minimum with neither. Table 4.2 – Appraisal of Monetised Costs and Benefits for M25 J1b-3 under various scenarios1 M25 J1b-3 widening EAR II Link E deferred (on A2/A282 scheme) For full 60 years LG LG to 2014 HG LG HG Consumer User Benefits £51.2m £110.7m £52.3m £112.2m £52.7m £120.5m Business User Benefits £75.5m £171.2m £81.9m £175.1m £85.4m £192.0m Private Sector Provider Impacts £0.5m £6.4m -£0.5m £12.6m -£0.5m £12.1m Accident Benefits £0.9m £4.2m £0.9m £4.3m £0.9m £4.3m £128.2m £292.5m £134.6m £304.2m £138.5m £328.9m Investment £65.3m £65.3m £65.3m £65.3m £65.3m £65.3m Indirect tax £1.5m £6.3m £4.2m £8.3m £4.8m £9.7m Present Value of Costs PVC £66.8m £71.6m £69.5m £73.6m £70.1m £75.0m Net Present Value £61.3m £220.9m £65.1m £230.6m £68.4m £253.9m Benefit to Cost Ratio 1.92 Present Value of Benefits PVB 4.22 1 HG to 2022 4.09 1.94 4.13 1.98 4.39 This shows that the economics of the M25 J1b-3 scheme were forecast to be impacted by the deferral of the construction of Link E in the A2/A282 scheme by also: Reducing the benefits slightly; Reducing the costs slightly, through changing the indirect tax impact; and All values are discounted present values in 2002 prices and values. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 57 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study 4.23 Reducing the BCR slightly. For the remainder of this chapter, the full deferral (i.e. by 60 years) of Link E has been assumed, as this option: Can be based on observed traffic and accident data without Link E; Allows comparison of the forecast and outturn cost of the scheme without considering the future cost of Link E; and Provides the most conservative estimate of benefits. Transport Economic Efficiency Evaluation of TEE benefits – Summary of Approach 4.24 4.25 Benefits to business users and consumers in the Transport Economic Efficiency (TEE) component of the TUBA model emerge from the following: Vehicle Operating Costs (VOCs); and Vehicle Hour Savings i.e. Travel Time benefits. For major highways schemes, changes to VOC savings constitute the minority of the TEE benefits. For these schemes, there were forecast savings in VOC for users for the A2/A282 whilst there were increases in VOCs for users of the M25 scheme. These impacts comprised only a small proportion of the overall TEE. Furthermore, given that the scheme’s impact on VOCs is difficult to measure using observed data, evaluation of this impact is not typically included as part of POPE. POPE Methodology 4.26 4.27 Based on the POPE evaluation of numerous other schemes across the national network we have found that a majority of scheme benefits are derived from two sources: Link Transit Time (vehicle hour) benefits which provide economy benefits; and Reduction in accident numbers providing monetised safety benefits. The basis of the POPE methodology (in terms of vehicle hour savings) is a comparison of changes in total link transit times before and after scheme opening using observed journey times and traffic flows and applying this ratio to the predicted savings. As such this method is most commonly applied to schemes that have been appraised using COBA software. Vehicle hour savings for both the A2/A282 and M25 schemes were appraised using TUBA software. TUBA modelling is based on Origin-Destination matrices, and is clearly a more appropriate modelling tool for the schemes of the complexity here. Also important here is modelling growth and elasticity. However, a TUBA model cannot be used as the basis of a post opening evaluation without replicating the whole modelled area which is logistically and financially not feasible. As TUBA output does not report impacts on a link basis it is not possible to extract a subset of traffic impacts to compare against the observed data. Hence the POPE methodology is not suitable for the OYA evaluation of these schemes. PAR Methodology 4.28 1 As an alternative approach, the journey time benefits for these schemes have been evaluated using a PAR approach, typically adopted by the HA for the appraisal of smaller schemes1. This evaluation is therefore subject to a number of caveats and assumptions as listed below: PAR Guidance Project Appraisal Report Guidance Notes Version 5.0 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 58 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study The evaluation only includes journey time savings on the A2 and M25 corridors, and the junction and not the wider network. The appraisal however was based on these strategic roads and those in the Kent Thameside Area. Thus this evaluation is missing potential benefits in the wider area; The impact of future development in the Kent Thameside Area (as modelled in the appraisal) is not considered; This evaluation only considers the impact of the scheme with Link E deferred indefinitely (60 years); The PAR method provides capitalisation factors which depend only on the road type and forecast growth rate whereas modelling tools used for the appraisal consider the complexity of how traffic growth would affect future traffic behaviour in detail. For these schemes, future forecasts will be influenced by timing and severity of forecast congestion with or without the scheme. For example, with high growth traffic, the modelled benefits could be heavily based on the early part of the appraisal period; and The impact of the CM on the M25 widening is omitted. How modelling assumptions affect schemes jointly 4.29 4.30 In the case of both schemes evaluated in this study, the final economic appraisals were based on modelling assumptions of the scenarios: Do Minimum – neither scheme built; and Do Something – both schemes built. This means that there is no double-counting of the benefits across the two economic forecasts. Hence, it is reasonable to sum up the benefits to get a total across the two. PAR Evaluation of TEE Forecast 4.31 The forecast TEE savings for each scheme using this method are summarised in Table 4.3. Table 4.3 – Predicted TEE Benefits from TUBA Scheme LG HG 50:50 Midpoint A2/A282 £134.8m £223.2m £179.0m M25 J1b - 3 £127.2m £288.3m £207.8m Total £386.8m 4.32 Over 60 years post opening with average growth rates, the A2/A282 was forecast to deliver £179m of TEE benefits and the M25 J1b-3 would deliver £207.8m. 4.33 This gives an overall total benefit of £386.8m. Evaluation 4.34 The PAR method of calculating the TEE journey time benefits is based on the vehicle hours saved in the first year, monetised by using a Value of Time (VOT) then converted to a forecast for the whole appraisal period using capitalisation. Values for the VOT for an average vehicle per hour and capitalisation factors are specified in the PAR guidance. 4.35 It is not possible to use TUBA outputs to create a comparable forecast based on the impacts on the same corridor, as TUBA is matrix based and its output does not give any breakdown of the impacts by link or area. 4.36 Therefore, for the evaluation of the selected links, vehicle hours saved in the opening year were calculated using the observed traffic flows and journey times described in the traffic section 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 59 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study extrapolated to a full year based on the AM, IP and PM weekday time periods as used in the appraisal. The vehicle hours covered the following links: M25 J2-3 (both directions); A2 Bean to M25 J2 (both directions); and Turning movements at J2 – both free-flow and using the roundabout. 4.37 This list covers all the improved sections with the exception of the short section M25 J1b-2 mainline carriageway where there is limited data. As this section covers less than 1km, this is only a small part of the overall journey time changes. 4.38 The benefits accrued by additional traffic were calculated at 50% of those for the existing traffic, according to the ‘rule of half’. 4.39 The calculation of the journey time benefits for each scheme using this PAR method are summarised in Table 4.4. Table 4.4 – Outturn TEE Benefits from PAR method Scheme Annual Vehicle Hours VOT (2009) 60 year benefits (capitalised from 2009) (2009) A2/A282 264,233 £12.86 £169.5m M25 J1b - 3 251,296 £12.86 £161.2m Total £330.7m 4.40 Because this evaluation is based only on the benefits for traffic on the improved sections of the A2 and M25 and at the junction, compared to the much wider area used in the TUBA models, it is likely that the figures in Table 4.4 represent underestimates of the benefits to the wider area. Furthermore, it is likely that some benefits are also accrued during the off-peak periods which are not included here. 4.41 The summary of the comparison between forecast and outturn TEE benefits are shown in Table 4.5. Table 4.5 – Forecast vs. Outturn TEE Benefits Scheme Forecast Outturn %difference A2/A282 £179.0m £169.5m -5% M25 J1b - 3 £207.8m £161.2m -22% Total 60 year TEE benefits £386.8m £330.7m -14% 4.42 This shows that evaluation of these schemes using observed data and a simple methodology still supplies a substantial TEE benefit. Considering that these outturn figures only cover a narrow area, they give estimates of the outturn TEE benefits which are nearly as high as those forecast, especially for the A2/A282 scheme. 4.43 Reasons why the Outturn TEE in Table 4.5 are lower that forecast include: Forecast includes benefits from whole Kent Thameside area as opposed to key links only in the outturn; Observed M25 traffic is lower than was forecast; and Although A2 traffic was higher than predicted, the observed journey time savings were fairly small and may be lower than the modelled journey time difference quantified into monetary benefits within TUBA. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 60 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Monetised Safety benefits 4.44 The monetary benefits emerging from changes in safety are calculated by assigning monetary values to the reduction in the number and severity of personal injury accidents over the appraisal period. M25 Forecast 4.45 Accident savings were evaluated using a spreadsheet based on COBA (Cost Benefit Analysis) figures. This was used to predict the number of accidents and accidents by severity in the future. 4.46 The AST states that the Increase in accident rate on M25 J1b – 3 as a result of increase in traffic from widening is more than compensated for by reductions in traffic on local roads from traffic reassignment to M25, resulting in monetary benefits and overall reductions in accidents. 4.47 The economic value ranged from £0.9m at low growth and £4.8m high growth as shown in Table 4.2. The area covered by this spreadsheet appraisal was neither detailed in the appraisal documentation nor the distribution of the benefits over the 60 year period. What can be deduced from this is that the opening year impact would be less than two accidents which is a figure too low to be able to distinguish from random variation with any statistical confidence. A2/A282 Forecasts 4.48 The Traffic & Economics Proof of Evidence (2004) presented safety forecasts based on two different approaches based on spreadsheets, rather than COBA. These were: Default values for accident rates and costs from COBA, for both the Do Minimum and Do Something scenarios. As there is no difference between COBA accident rates for dual 3 lane motorways and dual 4 lane motorways, the increase in traffic in the Do Something case forecasts resulted in an increase in the number of accidents on the A2. However these additional accidents were offset by an expected reduction in accidents elsewhere on the road network caused by a reduction in traffic levels. Forecast economic benefit was £0.85m for 30 years at 1998 prices. This was considered to be the conservative estimate of the benefits; and Observed accident rates were used for the Do Minimum accident rates and COBA accident rates used for the Do Something. As the observed rates in 1996 – 2001 were significantly higher than the number of accidents expected using the COBA rates, this gave benefits of £22m. 4.49 The conservative estimate was used because it was not expected that the full benefit predicted using the COBA rates would be realised due to the complex nature of the layout of this junction meaning that there would still be a significant remaining number of merges and diverges. 4.50 The 2006 appraisal was simply a rebasing of the earlier conservative figure, and remained as being based on the assumption that safety benefits would only occur in the first 30 years. Note that unlike the TEE benefits, this appraisal period was not changed to 60 years and it was stated that it was not expected that safety benefits would extend beyond the 30 years. Summary of Forecast safety benefits. 4.51 Table 4.6 summarises the benefits for each scheme and in total. Note that these exclude the impacts of: Link E as part of the A2/A282 scheme, as shown in Table 4.1 and Table 4.2. This makes negligible difference in the forecasts for both schemes; and 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 61 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Controlled Motorway on the M25 J2-3, which was appraised separately in 2009 to produce £23m in safety benefits1 which was also not included in the 2006 appraisals of either of these schemes. Table 4.6 – Forecast Monetised Safety Benefits Scheme LG HG 50:50 Mid-point A2/A282 £1.8m £0 M25 J1b-3 £0.9m £4.2m Total £2.8m £4.2m £3.5m Evaluation 4.52 The spreadsheet used for the appraisal of the safety benefits was not available for use in this evaluation. 4.53 The chosen method for the evaluation in POPE where details of the forecast are not available is to use aspects of the PAR method which is based on the standard HA method defined for simpler schemes. The PAR method is based on an estimate of the opening year accident saving being monetised to a long term benefit. For post opening evaluation here, the method is based on the observed changes in the number of accidents within the boundaries of the schemes on the M25 and A2 corridors. 4.54 Note that this method does not consider observed savings by accident severity as the numbers are too low to be significant. 4.55 The accident savings for the post opening period converted to annual figures, as shown in Table 3.2 and Table 3.3, have been monetised according to the type of road which is related to both the value of an accident and how the benefits are expected to be valued over the whole appraisal period i.e. capitalisation. National average growth was assumed. As noted above, the forecast only considered benefits in the first 30 years. This time period has been also used for this evaluation as shown in Table 4.7. Table 4.7 – Outturn Monetised Safety Benefits 4.56 Value of an average Accident in scheme opening year by road type 30 year capitalisation factor 30 year outturn benefit A2/A282 6.2 £89,850 26.6 £14.8m M25 J1b-3 7.9 £83,400 34.1 £22.4m Total 14.1 - £37.3m The limitations of the above calculations are: 1 Scheme Annual Accident Saving (observed) This is based on the layout of the road network on completion of the two schemes. It does not include: The completion of Link E at any time; The impact of the Controlled Motorway, which is expected to be in operation later this year and hence for the majority of the 30 years covered in this outturn Impact Assessment M25 Junctions 2 to 3 Controlled Motorway, May 2009 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 62 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study calculation, is not included in this evaluation, but nor was it considered at the appraisal; Growth on the M25 has been below national trends in recent years; if this continues in the long term, then based on this method, the safety impact would be expected to be lower, Only the area within the schemes and the whole of J2 has been included, thus this omits any benefits which may arise in the wider area including the local roads; and The safety impact of future congestion with or without the scheme, especially linked to the use of the junction is not modelled by the simple PAR method. 4.57 As shown in the safety section of this report, accidents were mainly clustered around J2, as would be expected. These have nominally been classified as A2/A282 accidents in this evaluation, but clearly the M25 scheme can also influence safety at the junction, therefore totalling the overall outturn benefit is reasonable. 4.58 The summary of the comparison between forecast and outturn safety benefits is shown in Table 4.8. Table 4.8 – Forecast vs. Outturn Safety Benefits Total 30 year safety benefits Forecast Outturn £3.5m £37.3m 4.59 This shows that outturn safety benefits of the two schemes combined are 10 times higher than forecast. 4.60 The much higher than expected accident saving in the post opening period may reflect some temporary changes in driver behaviour following on from the period during the roadworks when traffic cameras were in force. Summary of Present Value Benefits 4.61 Overall Present Value Benefits are summarised in Table 4.11. Table 4.9 – Present Value Benefits (£m) TEE Safety Total Scheme Forecast Outturn Forecast Outturn Forecast Outturn A2/A282 179.0 169.5 0.9 14.8 179.9 184.3 M25 J1b-3 207.8 161.2 2.6 22.4 210.4 183.6 Total 386.8 330.7 3.5 37.3 390.3 368.0 Scheme costs 4.62 This section compares the forecast costs of the two schemes with the outturn. 4.63 The outturn cost does not include the costs of the Controlled Motorway (CM) works undertaken at the same time as the M25 widening scheme. This evaluation is based on the widening scheme benefits prior to the activation of the CM. 4.64 The EAR Addendum for each scheme from 2006 gave the following details for each scenario for each scheme: Investment cost; Indirect Tax impact; and 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 63 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Overall Present Value Costs 4.65 All were given in 2002 prices, discounted to 2002. Although not explicitly stated in the report, it is assumed these were in market prices. No breakdown of the spend profile was available but as the schemes were constructed within the planned time period, no adjustment was necessary. Present Value Costs are on the same basis as Present Value Benefits and therefore are used to calculate the Benefit Cost Ratio. 4.66 To compare the forecast investment cost with the as-spent cost, the market price factor was removed from the investment costs, and discounting also removed. 4.67 The outturn spend profile for this scheme has been obtained for the purpose of this study from the HA regional finance manager. The as-spent figures for the period 2000 – 2009 have been converted to 2002 prices. This figure can then be compared with the forecast cost on a comparable basis, as shown in Table 4.10. Table 4.10 – Investment costs 4.68 Scheme Forecast, no Link E Outturn % difference A2/A282 £94.2m £105.7m 12% M25 J1b-3 £65.5m £49.9m -24% Total £159.6m £155.6m -3% This comparison of costs indicates that whilst the A2/A282 scheme costs were above that predicted, the M25 widening was below forecast. As the two schemes were under construction at the same time, it is valid to combine the costs and summarise that the total cost was just below the forecast. Indirect Tax 4.69 The Central Government Funding includes the reduction in the indirect taxation the Government would have received from users of the scheme. 4.70 The forecast impact of indirect taxation made up 5% of the A2/A282 PVC and 6% of that of the M25, assuming mid-point growth. 4.71 These figures are calculated by TUBA based on traffic behaviour over the whole appraisal period but no details of the basis are available. As the route lengths are similar, it is assumed that this reduced taxation represents a general improvement in vehicles travelling at more fuel efficient speeds. 4.72 It has not been possible to evaluate the indirect tax impact based on observed data due to limited data on the basis of the forecast (i.e. area and speeds) and the profile of how future congestion with or without the scheme would affect speeds. 4.73 Hence it has been necessary to assume that the forecasts are accurate and this is deemed reasonable on the basis that it is only a small part of the overall impact here. Summary of Present Value Costs 4.74 Present Value Costs including indirect tax are summarised in Table 4.11. Table 4.11 – Present Value Costs Forecast, no Link E Outturn A2/A282 £102.2m £115.9m M25 J1b-3 £69.2m £54.6m Total £171.4m £170.5m Costs in £m 2002 prices discounted to 2002 at 3.5% 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 64 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Benefit Cost Ratio 4.75 The Benefit-Cost Ratio (BCR) is used as a summary of the overall value for money of a scheme. Using the economic benefits (PVB) and costs (PVC) detailed above, the forecast and outturn BCR can be compared as shown in Table 4.12. Table 4.12 – Forecast vs. Outturn Benefit Cost Ratio Combined schemes TEE Present Value Benefits (PVB) Safety Total PVB Present Value Costs (PVC) Benefit Cost Ratio Forecast Outturn £386.8m £330.72m £3.5m £37.3m £390.3m £368.0m £171.4m £170.5m 2.3 2.2 4.76 This shows that despite the TEE benefits being 14% lower than forecast, the much better than forecast safety benefits combined with the slightly lower costs have meant that the BCR is 2.2 which is virtually as predicted. 4.77 The combined BCR above for the two schemes combined meets the DfT criteria for high Value for Money; therefore this evaluation confirms that these schemes represent a good return on investment over 60 years. 4.78 It should be noted that the BCR ignores non-monetised impacts. In NATA assessments, the impact on environmental, accessibility and integration objectives must be assessed but are not monetised. The evaluation of these three objectives is covered in the following sections. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 65 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Route stress/ Journey Time Reliability A2/A282 Forecast 4.79 The Inspectors report noted that the need for the scheme included the existing problem of high traffic levels leading to significant delays and unreliable journey times, especially at peak times and/or following a traffic incident in the area. 4.80 The AST stated that the scheme should improve reliability due to improved flow through M25 J2. No quantitative measure is given. 4.81 The Economics Assessment Report (2004) gives no monetised value for reliability. Evaluation 4.82 POPE methodology for the evaluation of reliability is currently under review. 4.83 Reliability is concerned with travel time variability or journey time variability. Thus a proxy for reliability can be obtained by examining the variation within journey times in the before and after periods using the journey times in the JTDB, as used in the traffic section of this study. The metric used is standard deviation of journey times from the mean time for each time period in the before and after periods. In each time slice, the average time is made up of many individual results. The larger the deviation of the individual journey times from the mean journey time, the greater the unreliability. The difference in the standard deviation in the before and after periods is shown graphically in Figure 4.1 and Figure 4.2 for weekday journey times on the widened section of the A2. Figure 4.1 – Standard Deviation of Journey Times A2 (A296 to M25, westbound) 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 66 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Figure 4.2 – Standard Deviation of Journey Times A2 (M25 to A296, eastbound) 4.84 The above graphs show that the standard deviation of journey times on the widened section of A2 was reduced in the after period. This indicates improved reliability of journey times. M25 J1b - 3 Forecast 4.85 The SAR (Nov 2006) stated that at that time, there was no established software for estimating the reliability of journey times from reductions in incidents for a road scheme, so the accepted alternative was the assessment of route stress. This compares the AADT to a theoretical measurement of congestion called the Congestion Reference Flow. It was forecast that the scheme should improve reliability due to a reduction of delays as a result of the widening. 4.86 However the calculation of the route stress using this method gave values for the sections of the M25 within the scheme, even in the Do Minimum scenario, of below 0.75 which according to the webTAG guidance, indicates that journey time reliability was not a significant concern, which clearly contradicted the known problems at that time. Hence, the AST stated that this approach did not provide a direct quantification of changes in reliability or reliability benefits. Evaluation 4.87 The observed traffic on the improved sections of the M25 is lower than the forecasts used for the calculation of route stress in the appraisal, hence it can be concluded that route stress is better than forecast, and on this measure, the route is rated as being uncongested. However, as pointed out in the SAR, this is not a useful metric for this type of road. 4.88 As for the A2/A282, analysis of the reliability of journey times has been undertaken using the proxy of the standard deviation of journey time data as above for the A2. Figure 4.3 and Figure 4.4 show the standard deviation of weekday journey times on the widened section of the M25. 4.89 Variation on the section J1b-2 has not been evaluated due to the low quality of the before period data. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 67 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Figure 4.3 – Standard Deviation of Journey Time on M25 J3 – 2 northbound Figure 4.4 – Standard Deviation of Journey Time on M25 J2 – 3 southbound 4.90 The northbound carriage J3-2 clearly experienced the greater problems with variation of journey times. After widening, the journeys in the AM peak have shown a big improvement in reliability. Surprisingly the available data for the after period suggests some increased variation hence unreliability during the inter-peak period whilst the PM peak from 17:00 onwards shows the expected reliability improvements. 4.91 The southbound carriageway journey times were and are less unreliable. The standard deviation showed an unexpected worsening during part of the AM peak whilst the early AM peak and PM peak. Overall there is a small improvement in reliability for southbound journeys. Wider Economic Impacts Scheme Forecasts A2/A282 4.92 The EAR (2003) for this scheme does not cover the wider economic impacts sub-objective. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 68 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study 4.93 The AST states that the scheme would: 4.94 Improve access from M25 and A2 to regeneration areas in Kent. Vital for the future development of Kent Thameside. It was also assessed as serving a designated regeneration area. M25 J1b - 3 Forecast Local impact 4.95 The Economic Impact Report (EIR) stated that the study area for the scheme included wards featuring deprivation greater than the national average. 4.96 Improved road access was not considered to improve access to jobs for residents of the wards in northern Dartford most in need of regeneration, since the people resident in these wards were resistant to travelling long distances and did not have the means to acquire a car. Improved public transport and additional job opportunities close to their homes were more important. 4.97 The scheme would increase the catchment area for employers in the study area located within these wards. More reliable journey times on the M25 would increase the attractiveness of committed development sites within or close to these wards. 4.98 The EIR estimated that up to 64 jobs could be realistically attributed to the scheme in 2008 rising to a maximum of 303 jobs by 2018 (with 99 of these jobs being taken by local people from wards in northern Dartford most in need of regeneration), once the benefits of the scheme and all the committed development is complete. Wider Impact 4.99 The SAR states that the M25 in this location is also critical to national competitiveness as it fulfils the Regional Development Agency’s multi-criteria of being a piece of surface infrastructure of national economic performance (SINEI) by providing access between the regions of London, Southeast England and Eastern England, and access to various key ports and airports. Combined Scheme Evaluation 4.100 The Communities and Local Government’s Indices of Deprivation 2004, ranks Dartford as 168th of 354 local authorities in England. 4.101 The details of the local developments upon which the specific forecasts for the M25 scheme were based were not available at the time of this study. Also considering the impact of the recession it was not considered too early to try to identify the job creation impact at this stage. 4.102 Kent Thameside is the regeneration area which covers the urban area north of the A2 in Dartford and Gravesham borough. Through the improvements to infrastructure and observed beneficial impacts on journey times and reliability, both schemes benefit the regeneration area. 4.103 The increase capacity and improved journey times is considered to be a benefit to the wider impact of this part of the strategic road network on national competitiveness. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 69 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Key Points from Economic Section Impact on Transport Economic Efficiency TEE was forecast to provide 99% of the benefits of these schemes; The evaluation of the outturn value of TEE based on observed savings in journey times one year after opening for the turning movements at J2 and on the improved sections of the mainline A2 and M25 shows savings of £170m (A2/A282 scheme) and £161m (M25) over 60 years; and These evaluations of the impacts to give outturn benefits are 14% below the overall benefits forecast, but these are a conservative estimate of the benefits based only on a narrow corridor whilst the forecast was based on detailed modelling of the impacts on not only the strategic roads in the HA network but also the local authority roads within the wider Kent Thameside Area. Therefore it can reasonably be assumed that the schemes have met or exceeded the TEE benefit forecasts for the wider area. Impact on Safety Safety benefits were forecast to be relatively minor but based on OYA observed savings have been evaluated to be £37m which is 10% of the overall benefits, much higher than the 1% forecast; This evaluation of the outturn Safety benefits may be overestimated based on short term benefits of reduced accidents in the post opening period from short term changes in driver behaviour e.g. the following the removal of the roadworks but not all of the safety camera notices. Scheme costs and Benefit Cost Ratio The forecast scheme costs forecasts were accurate; The outturn benefit cost ratio is 2.2 which is very close to the forecast of 2.3 and shows that the schemes represent good value for money. Impact on Reliability Analysis of the variation in journey times shows a clear reduction in variability on the A2 and hence there has been an improvement in reliability; On the M25, there is also a reduction in variation of journey times northbound, suggesting an improvement in reliability. Impact on Wider Economic Impacts The schemes have fulfilled their objectives in terms of putting in place the infrastructure to improve road access to the regeneration areas of northern Kent and the Thames Gateway area; At this stage of the post opening period and during a recession it is too early to identify job creation in this area as a result of the highways schemes. Future works not evaluated at this stage The impact of the Controlled Motorway scheme on M25 J2-3 becoming operational in the near future is expected to have significant beneficial impacts on safety and to a lesser extent on TEE. If the deferred link E part of the A2/A282 scheme is constructed in the future it is not likely to change the overall profile of the findings of this evaluation. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 70 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study 5. Environment Introduction 5.1 This section evaluates the impacts of the scheme on the environmental sub-objectives of each scheme. 5.2 The Environmental Statement (ES) for the M25 J1b-3 stated that the environmental objectives for the scheme were: 5.3 To seek to minimise any increase in noise to adjacent property and achieve a reduction in noise where reasonably practicable; To minimise any deterioration in local air quality, particularly at local Air Quality Management Areas (AQMAs) and achieve improvements in local air quality levels where reasonably practicable; To minimise adverse impact on landscape character and visual amenity, particularly on locally designated landscapes and the Kent Downs Area of Outstanding Natural Beauty (AONB), particularly in sensitive views; reinforce existing retained vegetation with on and (subject to agreement) off-site planting; To minimise adverse impact on the setting of listed buildings and conservation areas; to avoid direct impact on archaeological remains, particularly in areas for site compounds and storage; To minimise direct loss of locally valuable habitats within the highway boundary, some of which may also provide habitat for protected species; and To minimise adverse impacts on water environment through use of enhanced pollution control measures and adequate balancing storage. The ES for the A2/A282 Dartford Improvement stated that the environmental objectives for the scheme were: To minimise the impact of traffic and of maintenance operations on watercourses, groundwater and flooding; To respect the landscape character and quality of an area when designing new roads or improving existing roads. Seek to enhance the integration of the HA network into rural areas using a combination of sensitive road alignment, earthworks, the use of appropriate materials and planting to minimise the adverse effects of trunk road traffic on the countryside; To manage the network in a practical way that promotes the maintenance and enhancement of biodiversity (the variety of life). In particular, seek to manage the HA’s estate so as to add to its existing value as a refuge and a linking feature for wildlife; To ensure that in the planning and resourcing of trunk road projects there is an appropriate response to any adverse effects on the historic environment and that the historic fabric of the landscape is respected; To take practical steps to minimise noise and disturbance. This includes providing appropriate highway designs and making more use of noise reducing technologies; To take practical steps to minimise emissions. This includes appropriate highway designs to influence vehicle operation plus controls on the performance of contractors; and To provide improved facilities along and across trunk roads and improve links to other key destinations and to provide improved facilities for cyclists along and across trunk roads and improve links to other key destinations. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 71 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study 5.4 The A2/A282 objectives are not scheme specific and are in line with the HA’s Environmental Strategic Plan. A2/A282 Dartford Improvement Link E Deferral 5.5 The ES for the A2/A282 was based on the approved scheme design at the time of the OPR. As detailed earlier in 1.16, one of the planned new free-flow links included in as part of the junction design the approved scheme, known as Link E was not constructed in the scheme completed 2007. The basis of the planned scheme used in the ES and January 2004 AST considered the impacts of this link. 5.6 For the purposes of this study, the environmental impacts associated exclusively with Link E as reported in the ES and the 2004 AST have been omitted. The impacts of the scheme without Link E – as defined in the April 2006 Deferment Report and January 2008 AST Comparison – have been assessed instead. 5.7 The key impacts avoided by the deferral of works to River Darent1 overbridges, is that the River Darent is unaffected by the scheme, and construction of steepened embankments and retaining walls at Hawley Manor have been avoided. Hawley Manor has instead been screened from the existing A2 by a 2m environmental barrier (wooden fence). Data Collection 5.8 The following documents have been used in the environmental evaluation part of this study: M25 J1b-3 Appraisal Summary Table (AST), December 2006 M25 Junctions 1b to 3 Widening Scheme ES, November 2006: Volume 1A – main text; Volume 1b – figures; Volume 3 – appendices; Non-Technical Summary. Public Inquiry Landscape Proof of Evidence 2004 Handover Environmental Management Plan (HEMP), October 2008. As Built drawings for drainage. A2/A282 5.9 AST, January 2004. AST Link E Deferral, June 2006. A2/A282 Dartford Improvement ES, March 2003: Volume 1 – main text and appendices; Volume 2 – figures. A2/A282 Dartford Improvement Report on Deferment of Link E and Revised Landscape and Drainage Attenuation Proposals in North West Quadrant of Junction 2, Issued at IFI, April 2006. A2/A282 Dartford Improvement AST Comparison, Issued at IFI, January 2008. HEMP, Issued at IFI, February 2008. As Built drawings for drainage. A full list of the background information requested and received to help with the compilation of this reports is included in Table A.1 in the Appendix. Site Inspections 5.10 A site inspection was undertaken on 25th and 26th February 2010 by an environmental specialist and a member of the POPE team. 1 Note, the place names in this area spell the name of the village, wood and country park as Darenth while the river and its valley are spelt Darent. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 72 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Consultations 5.11 Table 5.1 lists the organisations contacted regarding their views on the impacts they perceive the road scheme has had on the environment, and whether they feel that the mitigation measures implemented have been effective. Table 5.1 – Summary of Environmental Consultation Responses Organisation Dartford Borough Council Field of Interest General Comments Noise: No evidence of changes in noise level. Local residents, close to the M25 and A2 have informally mentioned that the background traffic noise seems to be lower. No information available. Sevenoaks District Council General on noise complaints No emissions data available. Recommended contact with Kent County Council on rights of way and ecology. Comments provided on visual impacts on Swanley Conservation Area and surrounding environs. Kent County Council General No response. Environment Agency Water No data available on water impacts of the scheme. However, it stated that if all drainage and mitigation was implemented as expected, the water environment should have improved. Natural England Landscape and Ecology Declined to comment on impacts of scheme but said that it expected a detailed post-construction study to be undertaken to monitor the effectiveness of landscape and ecological mitigation. English Heritage Heritage Declined to comment on either scheme. Kent Wildlife Trust Biodiversity The Trust had been unable to undertake any monitoring in relation to the scheme and so cannot provide comment. Kent Downs AONB Unit Landscape and Biodiversity No specific comments on the impact of either scheme provided. However, generic comment and advice on the impacts of highways schemes and on Kent Downs AONB was received. Sutton-at-Hone and Hawley Parish Council General POPE was raised at Parish Council meeting but no further feedback received. 5.12 The Highways Agency Part 1 Team has been contacted regarding part 1 claims and it is understood that it is too early in the claims period to say how many will be successful and this information will be made available for the FYA report. 5.13 It should be noted that Part 1 Claims only cover permanent homes and not mobile homes, where a different mechanism is in place. There is a caravan park adjacent to the A2 and claims made for these homes should also be made available for the FYA report. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 73 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study 5.14 The MAC was also consulted with regard to animal mortality figures which have been made available for the period May 2006 to March 2009. The MAC should be re-contacted for the FYA report. Traffic Forecasts and Evaluation 5.15 Three of the environmental sub-objectives (noise, local air quality and greenhouse gases) are directly related to traffic flows. No new environmental surveys are undertaken for POPE and an assumption is made that if the observed level of traffic is in line with forecasts then it is likely that local noise and air quality are as expected. The baseline, forecast opening and design years for each scheme are shown in Table 5.2. Table 5.2 – Existing, Opening and Design Years for the M25 J1b-3 and A2/A282 Schemes A2/A282 M25 J1b-3 Existing (Baseline) 2004 2002 Opening Year 2008 2007 Design Year 2023 2022 A2/A282 5.16 The traffic forecasts used in the noise and local air quality appraisals and the observed flows are summarised in Table 5.3. Table 5.3 – A2/A282 Traffic: Opening year Forecasts and Observed Forecast1 Location Low Growth High Growth Observed Direction WB 59,700 65,900 67,300 EB 58,800 65,500 67,000 WB 47,800 51,000 51,500 EB 46,900 51,400 56,700 Flyover from A282 to A2 eastbound EB 16,000 16,900 16,600* Flyover from A2 westbound to A282 northbound NB 16,500 19,200 15,600* Dedicated A2 eastbound to M25 southbound SB 12,800 13,600 11,700* M25 J2 -3 NB 71,900 81,900 64,700 M25 J2 -3 SB 69,400 78,600 70,600 NB 77,300 89,300 70,300* SB 74,700 85,500 65,000* A2 east of M25 A2 west of M25 M25 J1b-2 & A282 link road *based on a single day video count 5.17 Table 5.3 shows the forecast used in the ES. These have the same basis as those discussed in the traffic section of this report, which showed that traffic growth on the A2 increased in line with the high growth forecasts whilst traffic on the M25 and movements at the junction have seen little change. Because growth had been forecast on the M25 between the base year and the opening 1 2009 forecasts given in this table are based on the 2007 opening year forecasts in the ES growthed up using a straight line growth rate between 2007 and the design year forecasts. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 74 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study year, the observed traffic levels are, therefore, not as high as expected along the M25 and on the A282 links. M25 J1b-3 5.18 The ES used slightly differing types of traffic figures for the noise and air quality appraisal. Noise was based on 18hour weekday figures (AAWT) whilst air quality used 24hour figures based on the whole week (AADT). Table 5.4 – M25 J1b-3 Traffic: Opening year Forecast and Observed AAWT (Noise) 18 hour AAWT Location Forecast Observed J1a-1b 174,200 140,800 J2-J3 160,900 137,500 Table 5.5 – M25 J1b-3 Traffic: Opening year Forecast and Observed AADT (Air Quality) 24 hour AADT Location 5.19 Forecast Observed J1a-1b 184,000 143,700 South of J1b 156,000 138,500 J2-J3 170,001 140,300 J3-J4 136,000 115,200 Growth in traffic was predicted along the M25 but this has not been realised, possibly due to the effects of recession. Present traffic levels are, therefore, well under those expected along the M25. Noise Forecast A2/A282 5.20 The AST for the A2/A282 Link E deferral stated that no properties would experience an increase in noise levels in the Design Year and that 51 properties would experience a decrease in noise levels of between 0.7 and 7.5 dB(A). 30 less people would be highly annoyed in the Design Year. 5.21 The ES for the A2/A282 stated that the following noise mitigation measures would be included in the scheme design: 5.22 Low noise surfacing across the length of the scheme (however this would also be implemented by Design Year with the Do Minimum scenario); A 2m high barrier along the A2 at Hawley Manor; and No properties would be eligible for noise insulation. In the Design Year, with mitigation in place, the scheme was predicted to result in 51 properties experiencing a significant decrease in noise in comparison to the 2002 baseline situation. Without the scheme, 41 properties were predicted to experience a slight decrease in noise in the Design Year in comparison to 2002. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 75 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study M25 J1b-3 5.23 The AST for the M25 J1b-3 stated that traffic flows on the scheme would increase slightly, resulting in annoyance for properties nearby. However, the introduction of environmental barriers at Hawley Road would result in an overall reduction in population annoyed by noise. In the Do Minimum, 146 people would be subject to noise levels in excess of 69dBLA10,18hr, whereas with the scheme, 108 would be exposed to this level of noise – a reduction of 38 people annoyed. 5.24 For the Do Minimum scenario, the AST estimated that 113 people were likely to be annoyed by Design Year compared to 105 with the scheme – a net reduction of 8 people annoyed. 5.25 The ES for the M25 scheme stated that the following noise mitigation measures would be included in the scheme design: Low noise surfacing across the length of the scheme (however this would also be implemented by Design Year with the Do Minimum scenario); 650m of environmental barriers along the M25 north and southbound carriageways at Hawley; and No properties would be eligible for noise insulation. 5.26 The greatest benefits for noise were predicted at Hawley, which was predicted to receive substantial and moderate beneficial impacts, but noise impacts along the whole corridor are generally predicted to fall due to the introduction of noise fencing and low noise surfacing. 5.27 Properties distant from the scheme, for example at Shirehall Road in Hawley were expected to receive a marginal increase in noise in the design year as barriers are less effective at distance. At Ship Lane, properties would also experience increases in noise at design year due to the carriageway moving closer to properties. Such increases were not expected to be significant. Consultation 5.28 Dartford Borough Council said it had no survey information to evidence any changes in noise level due to either scheme. However, anecdotally local residents close to the M25 and A2 have informally mentioned that the background traffic noise seems to be lower since the schemes were operational. The Council does not record noise complaints and so have no data regarding numbers of noise complaints before and after the schemes were implemented. 5.29 Sevenoaks District Council said it had no noise data available to comment on the noise impact. Evaluation 5.30 For both schemes, the observed traffic flows differ from those predicted in the ES for the Do Something scenarios, but are within 20% predictions. Therefore, it is likely that the impact of both schemes on the local noise climate is generally as expected with regard to traffic flows. Low noise surface has been used throughout the schemes as expected. It is understood that no post opening noise surveys have been undertaken. 5.31 Much of the length of each scheme already lies within cutting prior to scheme construction and thus had existing noise mitigation. Environmental barriers for noise mitigation have been incorporated into the scheme at the locations identified in the ES. 5.32 Figure 5.1 to Figure 5.4 show environmental barriers across the M25 and A2/A282 schemes. Along the M25 3m high, rather than 2m high environmental barriers have been implemented following consultation on the ES. It is understood from the HEMP for the scheme that additional barriers have been provided and although designed primarily for visual impact reasons, these barriers also have a benefit to the noise environment. 5.33 Figure 5.1 and Figure 5.2 show the environmental barrier constructed at Hawley Manor. The section of the A2 here was also resurfaced with low noise surfacing and was not affected by widening or any of the new links provided at M25 J2. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 76 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Figure 5.1 – 2m high environmental barrier (wooden fence) at Hawley Manor on the A2 Figure 5.2 – 2m high environmental barrier (wooden fence) at Hawley Manor on the A2 Figure 5.3 – 3m high environmental barriers (metal and wooden fencing) at Hawley (M25/ Dartford Road underbridge) Figure 5.4 – Environmental barriers (earth mounds) at edge of Links A and D at M25 J2 . 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 77 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Figure 5.5 – Additional environmental barrier near Pond 3 Figure 5.6 – Additional environmental barrier at M25/ Button Street underbridge Table 5.6 – Summary of Noise Evaluation – A2/A282 Summary of Noise Impacts Assessment AST (forecast) No properties would experience an increase in noise level in the Design Year (2022) due to use of low noise surfacing, mounds and fencing. 51 properties would experience a reduction greater than 3dB(A). Without the scheme use of low noise surfacing in the Design Year would mean 45 properties would experience a reduction between 1 and 3 dB(A). 30 less people highly annoyed in 2022 EST Mitigation implemented as expected. The growth in traffic predicted on the A2 has been slightly above predicted but on the links around the junction and the A282 traffic growth as has generally not materialised (possibly due to recession factors discussed in the traffic section of this report). Likely to be as expected at OYA stage. Origin of Assessment (OYA evaluation) However, traffic flows are generally as predicted and so it is likely that the noise climate is as expected. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 78 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Table 5.7 – Summary of Noise Evaluation – M25 J1b-3 Summary of Noise Impacts Assessment AST (forecast) Traffic flows on the scheme would increase slightly, resulting in an increase in annoyance for properties nearby. However, the introduction of environmental barriers at Hawley Road result in an overall reduction in population annoyed. Parkwood Hall School is more than 400m from the proposed alignment. It is not close enough to the scheme for the noise change to have an effect on overall noise levels in excess of 69dBLA10,18hr whereas with the scheme 108 would be exposed to noise levels in excess of 69dBLA10,18hr. This is a reduction of 38 people. Net reduction in estimated population annoyed: 8 EST More mitigation implements than expected (additional and higher fencing across M25 corridor). The rate of growth in traffic predicted on the M25 for the opening year has not materialised (possibly due to recession factors discussed in the traffic section of this report) and implementation of additional mitigation compared to that expected may mean a reduction in noise compared to expectations. Probably better than expected at OYA stage. Origin of Assessment (OYA evaluation) Local Air Quality Forecast A2/A282 5.34 The AST stated that local air quality was poor, particularly in close proximity to the A2 and A282. ‘Cleaner’ vehicles in the future were likely to contribute to an improvement in local air quality with or without the scheme, but there would be less of an improvement with the scheme compared to the Do Minimum scenario. 5.35 An Air Quality Management Area (AQMA) was present within Dartford Borough which could be affected by the scheme. However, the ES showed that the effect on air quality at properties within the AQMA would not be discernable. Properties near the Littledale Viaduct would generally have an increase in concentrations, while those near the Bean Junction would generally have a decrease in concentrations. 5.36 The scheme was noted as having a slight negative effect on local air quality in comparison to the Do Minimum with eight of the ten receptors expected to have an increase in concentrations. 5.37 The ES noted that National Air Quality Standards would be exceeded for both NO2 and PM10 in the base year, although these were likely to be met in the opening and design years. 5.38 Of 91 properties within 200 metres of the Scheme, 27 properties were predicted to experience better air quality as a result of the scheme and 64 properties were predicted to experience a marginal deterioration in air quality. In general terms, properties predicted to experience improvements in air quality were located around Bean Junction and those expected to experience poorer air quality were located in the vicinity of the Littledale Viaduct and locations where elements of the Scheme, such as new slip roads, would bring the road closer to the properties. M25 J1b-3 5.39 The AST stated that traffic flows would increase slightly and properties adjacent to the M25 between J1b and 2 within Dartford Borough Council’s AQMA could experience a slight improvement in air quality due to speed changes. It is presumed that this referred to the impact of reduced congestion at the junction. Properties south of Junction 2, some of which were within 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 79 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Sevenoaks District Council’s AQMA were expected to experience no discernable change in air quality. 5.40 AQMAs are present within Dartford Borough Council and Sevenoaks District Council and could be affected by the scheme. However, the ES predicted that no AQMAs would experience deterioration in air quality because of the scheme. 5.41 176 properties lie within 200m of the scheme and of these, 63 were predicted to experience an improvement in air quality. These improvements were associated with J1b - 2 which was widened on the southbound carriageway only. The remainder of properties were predicted to experience a decrease in air quality. 5.42 2010 annual mean EU Value Limits for nitrogen dioxide (NO2) were predicted to be exceeded both with and without the scheme at 8 out of 19 receptors in the opening year (2008) and at 6 out of the 19 receptors by 2010, both with and without the scheme. Consultation 5.43 Sevenoaks District Council said it did not have any data on local air quality. Evaluation 5.44 Traffic on the A2, M25 and the A282 links vary above and below the high and low growth forecasts, mainly below. The biggest difference is on the A2 eastbound which is 10% above the high growth forecast. 5.45 As all observed traffic flows are within 10% of either the high or low forecast levels and many are below forecast, it is possible, therefore, that scheme impacts for both schemes are better than expected at OYA stage. It is likely that, as expected, neither of the AQMAs in Dartford BC or Sevenoaks DC have suffered a deterioration in local air quality. Table 5.8 – Summary of Air Quality Evaluation – A2/A282 Origin of Assessment AST (forecast) Summary of Local Air Quality Impacts Local air quality is poor particularly in close proximity to the A2 and A282. ‘Cleaner’ vehicles in the future are likely to contribute to an improvement in air quality. Nevertheless anticipated improvement overall would be less with the Scheme when compared to Do Minimum Scenario. Assessment Weighted property concentrations (opening year): PM10 +1780.2_g/m3 NO2 +2344.60_g/m3 EST (OYA evaluation) All observed traffic flows are within 10% of either the high or low forecast levels. Therefore, it is likely that the air quality on the A2/A282 is as expected. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx Likely to be as expected 80 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Table 5.9 – Summary of Air Quality Evaluation – M25 J1b-3 Summary of Local Air Quality Impacts Origin of Assessment AST (forecast) EST (OYA evaluation) Traffic flows would increase slightly. Properties adjacent to the section of M25 between J1b and 2 before slip roads show very slight improvements in air quality due to speed changes. This area is within Dartford BC’s AQMA. Properties adjacent to the section of M25 before J2 slip roads and J3 show no discernable change in air quality. Some of these properties fall within Sevenoaks DC’s declared AQMA. The level of growth in traffic predicted on the M25 has not materialised (possibly due to recession factors discussed in the traffic section of this report). Observed traffic across the M25 is at least 10% less than expected, meaning that air quality is likely to be better than expected. As expected it is likely that there has been no worsening in air quality within local AQMAs. Assessment Weighted property concentrations (opening year): PM10 +209.73_g/m3 NO2 +126.65_g/m3 Likely to be better than expected. Greenhouse gases 5.46 According to the DfT’s WebTAG guidance, CO2 is considered to be the most important greenhouse gas and, therefore, is been used as the key indicator for the purposes of assessing the impacts of transport options on climate change. 5.47 The ESs and ASTs for each scheme included assessments of the CO2 impact. Although the focus is on CO2 emissions, the current guidelines are to express the change in terms of the change in the equivalent tonnes of carbon released as a result of implementing a transport scheme. Therefore the original forecasts figures have been converted to tonnes carbon for the purpose of this evaluation. Forecast A2/A282 5.48 5.49 5.50 The greenhouse gas impact of the scheme was assessed using the guidance for regional air quality modelling from the DMRB. This models fuel consumption related carbon emission rates and requires the following basic inputs: Annual average daily traffic flow to include heavy good vehicles (HGVs) and light duty vehicles (LDVs); Percentage of HGVs on each road; Average speed of vehicles; and Assessment year. Paragraph 3.2.6.1 of the ES stated: The detailed modelling of complex major junctions is not included within the prediction methodology as it relies on average speeds, traffic composition and road lengths. However, improvements at the A2/A282 junction are likely to result in reduced congestion which results in reduced CO2 emissions at higher speeds. Therefore the increase in greenhouse gases is likely to be overstated. Detailed modelling of major junctions is not part of this assessment. The published forecast was 5,187 additional CO2 impact of 2022. No data was given for the opening year. This is equivalent to 1,415 tonnes carbon. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 81 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study 5.51 The assessment in the Link E deferral report stated that the revised layout would not affect the greenhouse gases assessment. This was because traffic which was previously forecast to have used Link E will now flow onto a temporary Link located on the existing roundabout, which does not result in traffic flow changes to any other road links. M25 5.52 The greenhouse gas impact of the scheme was also assessed using the DMRB air quality spreadsheet. The forecast was a net impact of 3,390 CO2 impact in the opening year of 2008, equivalent to 925 tonnes carbon. This was a net increase of 4% between the Do Minimum and Do Something scenarios. Evaluation A2/A282 5.53 As described above, the appraisal did not consider the junction; hence the evaluation here has also been based only on the mainline traffic on the widened section of the A2. M25 J1b - 3 5.54 The area covered by the appraisal was not known. The evaluation has been based on flows and speeds in the AM, IP and peak periods for the section J2-3 for the situation before and after the scheme was implemented. The improved section of J1b – 2 cannot be evaluated due to insufficient data of the necessary granularity. Table 5.10 – Summary of Greenhouse Gases Evaluation – A2/A282 Origin of Assessment Summary of Greenhouse Gases Impacts Assessment AST (forecast) Increase due to increased traffic flows, but likely to be overstated due to impact on junction congestion 1,415 tonnes carbon, a 9.5% increase (in design year 2022) EST Increased emissions due to traffic growth above forecast 1,349 tonnes carbon, 11% increase (2009) (OYA evaluation) Table 5.11 – Summary of Greenhouse Gases Evaluation – M25 J1b-3 Origin of Assessment Summary of Greenhouse Gases Impacts Assessment AST (forecast) Increased emissions due to increased traffic 924 tonnes carbon, 4% increase with scheme (2008) EST Increased emissions due to increased speeds 724 tonnes carbon, 4% increase with scheme (OYA evaluation) 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 82 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Landscape and Townscape Forecast A2/A282 5.55 The AST for the A2/A282 predicts that the scheme would have a slight adverse impact on landscape due to degradation of the urban fringe landscape. The existing motorway/ link road/ junction would be screened by mounding and planting but the fourth tier of the new junction works at M25 J2 would remain visible after mitigation. 5.56 Townscape has not been appraised for the A2/A282 scheme due to the lack of townscape features in the vicinity of the scheme. 5.57 The ES described impacts of the scheme as incremental on a landscape described as ‘urban fringe’, rather than introducing new features to a landscape already dominated by road infrastructure. New link roads would have new lighting, whilst the existing A2 and A282 lighting would be replaced with lighting of the same standard as the link roads, in the central reservation. This modern lighting should reduce light spillage. Gantries would be also be included and locations are noted on Figure 5 Volume 2 of the ES. The Landscape Proof of Evidence also notes that both lighting and overhead gantries were taken into consideration in the visual appraisal for the scheme, although the ES Volume 1 text would appear to make no reference to gantries. The impacts to the landscape character of the area were considered to be moderate at opening year in the areas northeast and northwest of M25 J2 and the Littledale Viaduct (A2). The affected landscape includes the Darenth Country Park, Fleet Downs and Blackdale Farmland. 5.58 Other landscape impacts to the south west of J2 towards Hawley, and to the east of the Littledale Viaduct, through Darenth Wood Site of Special Scientific Interest (SSSI) towards Bean, were considered to be slight at opening, reducing to neutral at design year. 5.59 Key visual impacts for the scheme would generally be in the vicinity of the Littledale Viaduct and M25 J2. Blackdale Farm Cottages and residential properties on Green Street, Green Road including Littledale and Gore Cottages, all near M25 J2, were predicted to experience a substantial adverse impact in the opening year, reducing to moderate in the design year. 5.60 Properties on the edge of Dartford would also experience a slight/moderate impact at opening year, reducing to slight impact in the design year, due to views of M25 J2. 5.61 The Northern edge of Hawley was predicted to experience a moderate adverse visual impact at opening, reducing to slight impact at design year, also due to views of J2. 5.62 Hope Cottages near the Bean Interchange were predicted to receive a slight visual impact in opening year. 5.63 A number of public rights of way within the vicinity of the scheme would also receive substantial and moderate visual impacts. 5.64 The elements of design proposed to mitigate landscape impacts were: Protection and management of existing retained highway vegetation; Reinforced planting to existing retained highway vegetation; Woodland planting on newly constructed earthworks; Woodland planting on land beyond that required for highway earthworks, but acquired for the purposes of essential landscape mitigation; All planting to be native and stock of UK provenance wherever possible; Creation of wildflower grassland; Creation of low-lying wetland areas; Creation of balancing ponds/ ditches/ reed beds; 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 83 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Provision of visual and noise attenuation mounding above new/ existing carriageway; Regrading of embankments; and The return of some of the re-graded land back to agricultural use. M25 J1b-3 5.65 The AST for the M25 scheme predicted a slight adverse impact overall. The AST noted a Special Landscape Area and two Areas of Local Landscape Importance (ALLI) in the study area, although the scheme was predicted not to detract from or be in conflict with the area’s existing features and landscape character. Tranquillity and land cover were predicted to be slightly affected by the scheme and proposed lighting would add to the impact with a change in night time landscape character from several visual receptors. Effects of lighting on the Kent Downs Area of Outstanding Natural Beauty (AONB) would be slight due to the existing lighting at J3. 5.66 The AST predicted the impact on townscape to be neutral as the increased dominance of the M25 on views would be offset by new environmental barriers; particularly at Hawley. Adverse impacts were not expected to the Conservation Area at Swanley Village. 5.67 The ES noted that the landscape around J2 would be dominated by the junction improvement associated with the A2/A282 project and the impacts of improving the M25 to the north of this junction would be overridden by these impacts, although the Blackdale Farmland landscape character area would receive slight adverse impacts at opening due to new gantries. The ES also predicted slight adverse landscape impacts at opening for the Darent River Valley, Hawley Downs, Swanley and Broom Hill Fringe and Sutton at Hone Downs local landscape character areas. Because of its proximity to the scheme a small area of the Kent Downs AONB directly adjacent to J3, mostly occupied by a golf course, would suffer a localised slight adverse night time impact due to the proposed lighting north of J3. The ES noted that the character of the Kent Downs AONB would remain largely unaffected. 5.68 The ES noted that the M25 was already lit between J1b and J2 and unlit between J2 and J3.The scheme proposals were to upgrade existing lighting through J2 and to introduce new lighting from J2 to just north of J3. The lighting would be located in the central reserve north of Yew Tree footbridge and in the verges south of Yew Tree footbridge. 5.69 Farningham and Rams Woodland character area would experience a moderate adverse impact both at opening and design year, largely due to removal of screening vegetation adjacent to the M25 and due to the effects of the proposed lighting on night time character, and the increased dominance of the motorway on a rural landscape and landscape features of moderate quality. Farningham Wood is also designated as an SSSI. 5.70 The only properties predicted to experience substantial and moderate adverse visual impacts were at Hawley and Blackdale Farm Cottages, although the impacts at the Farm Cottages would be overridden by the impact of the J2 improvement undertaken under the A2/A282 scheme. Impacts were predicted largely due to removal of screening vegetation and the close proximity of the properties to the widened M25. 5.71 A number of public rights of way within the vicinity of the scheme would also receive substantial and moderate visual impacts reducing to slight by the summer of the design year due to mitigation screen vegetation maturing. 5.72 The elements of design proposed to mitigate landscape impacts were: Protection and management of existing retained highway vegetation; Reinforced planting to existing retained highway vegetation; Replacement planting for existing highway vegetation that is lost to the scheme; All planting to be native and stock of UK provenance wherever possible; Creation of wildflower grassland; and 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 84 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Installation of environmental barriers at Hawley Road underbridge. Consultation 5.73 Sevenoaks District Council stated that the large gantries have an adverse impact on the rural setting of Swanley Village Conservation Area. It also noted that due to the paucity of screening to the eastern side of the M25 in the area of the village, moving vehicles dominate long-views of the village from the east. 5.74 Kent Downs AONB stated that it was unable to make specific comments on the impacts of the scheme on the AONB at this stage. Evaluation 5.75 The site visit confirmed that mitigation had largely been implemented as expected. Environmental barriers were installed at Hawley (Figure 5.3) and Hawley Manor (Figure 5.1 and Figure 5.2) as expected, but the height of the barriers along the M25 were increased from 2m – as described in the ES – to 3m after consultation on the ES. They were also extended along a further distance to reduce the visual impact of the widened scheme, as demonstrated in Figure 5.5 and Figure 5.6. 5.76 Reinforcement planting (Figure 5.2) and new planting (Figure 5.7) was evident throughout the schemes and vegetation was retained where expected. Planting has been individually guarded with shelters, as shown in Figure 5.7. Figure 5.7 – View southbound along A282 towards M25 J2 showing new planting with individual shelters 5.77 As compensation for land lost to the scheme at Darenth Country Park, it is to be exchanged with land behind Gore Farm Cottages (as described in the ES), although it is understood that this has not yet been completed. This transfer should be confirmed as part of the FYA evaluation. 5.78 Due to the time of year it was not possible to confirm whether wildflower grassland had been implemented, although the HEMPs for both schemes note that grassland seeding had been undertaken and that wildflower areas are present at the lower sections of some embankments. The HEMP also confirmed that land to be returned to agriculture post construction had been seeded and this was evident on the site visit. 5.79 Further details on vegetation retention and translocation can be found in the ecology section. Creation of wetlands is also covered in the ecology and water sections. 5.80 Landscape effects and visual impacts were generally as expected at OYA stage. Implementation of barriers at Hawley and Hawley Manor have screened the A2 and widened M25 from visual receptors. New and reinforced planting has been implemented across both schemes were expected and, subject to ongoing maintenance and management, should established satisfactorily 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 85 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study and, given time, reduce visual and landscape impacts. Establishment of the landscape measures should be considered at the five years after stage. 5.81 The townscape impacts on Hawley are also as expected at OYA. Barriers (see Figure 5.3) and planting have been implemented as expected, screening Hawley from the M25. New gantries are visible from the town, but this is offset by the new environmental barriers which reduce the visual and noise impacts of traffic. 5.82 Sevenoaks District Council commented that long views from the east of the M25 have been changed due to installation of gantries. Gantries are also visible from the rural land situated around the Conservation Area. The ES clearly stated that gantries would form part of the scheme proposals and also indicated that the Conservation Area is outside the scheme’s visual envelope. During the site visit, it was not evident that the scheme was visible from within the Conservation Area itself. Therefore it is not considered that the scheme impacts on it. 5.83 Visual impacts at Blackdale Farm Cottages are considered to be substantially adverse as expected, and, again, new planting has been implemented to soften the impact of the embankment. Figure 5.8 shows a view of the scheme from this location. Figure 5.8 – View of M25 J2 Link A from Blackdale Farm Cottages 5.84 Views from the edge of Dartford at the northern edge of Darenth Country Park are also considered to be as expected. The Year 1 photomontage in Figure 25 of the A2/A282 ES Figure 5.9 is an accurate representation of the actual view taken on site (Figure 5.10). 5.85 Visual impacts from properties near to the Littledale Viaduct (A2) were also predicted to be substantially adverse due to the addition of raised carriageways on either side of the existing A2 viaduct. The new viaducts were finished, as proposed, in weathered steel. 5.86 Figure 5.12 recreates the proposed view shown in the photomontage in Figure 26 of the A2/A282 ES and demonstrates that the predicted visual impacts are as expected. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 86 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Figure 5.9 – Figure 25 Proposed View Year 1 photomontage from the A2/A282 ES (2003). View towards M25 J2 from Darenth Country Park, taken during summer. Figure 5.10 – Recreation of photomontage from Figure 25 of the A2/A282 ES. View towards M25 J2 from Darenth Country Park, taken February 2010. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 87 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Figure 5.11 – Figure 26 Proposed View photomontage from the A2/A282 ES (2003). View towards M25 J2 from Darenth Country Park, taken during summer. Figure 5.12 – Recreation of photomontage from Figure 26 of the A2/A282 ES. View towards Littledale Viaduct (A2) from Gore Farm Cottages, taken February 2010. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 88 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study 5.87 Impacts of scheme lighting are also largely as expected, such as at Farningham and Rams Woodland. However, the effect of lighting Kent Downs AONB may be considered to be negligible due the already lit nature of M25 J3 and other development skirting the edge of the designation. The AONB was unable to make any specific comments on the impacts of the scheme. Lighting is visible from other receptors along the M25 corridor, but increased length of 3m high environmental barriers (wooden fences) has reduced the impacts of the headlights of vehicles using the M25. Table 5.12 – Summary of Landscape Evaluation – A2/A282 Origin of Assessment Summary of Landscape Impacts Assessment AST (forecast) Degraded urban fringe landscape, existing motorway/ link road/ junction screened by mounding and planting. Fourth tier to J2 visible. Slight adverse EST Mitigation generally implemented as expected but it is too soon to evaluate the success of the new landscape planting in screening traffic and integration of the scheme into the local landscape. Further study required at FYA. Landscape effects and visual impacts as expected at OYA. As expected (OYA evaluation) Table 5.13 – Summary of Landscape Evaluation – M25 J1b-3 Origin of Assessment Summary of Landscape Impacts Assessment AST (forecast) 1 Special Landscape Area and 2 ALLIs in Study Area. Scheme would not detract or be in conflict with existing features and landscape character of the area, although tranquillity and land cover across the area would be slightly affected. Proposed lighting would add to impact, with a change in night time landscape character from several visual receptors. Effects on lighting on the Kent Downs AONB would be slight as currently lit J3 intervenes. Slight adverse EST Mitigation generally implemented as expected but it is too soon to evaluate the success of the new landscape planting in screening and integration. Further study required at FYA. Additional height (3m rather than 2m high) environmental barriers provided along a greater length of the M25 may have reduced effect of headlights at night. Impact on landscape designations as expected. Kent Downs AONB should be consulted again at FYA stage. Landscape effects and visual impacts as expected at OYA. As expected (OYA evaluation) 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 89 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Table 5.14 – Summary of Townscape Evaluation – M25 J1b-3 Origin of Assessment Summary of Townscape Impacts Assessment AST (forecast) Although the scheme would impact upon housing at Hawley, in terms of views and increasing the dominance of major roads in the area, adverse impacts would be offset with installation of environmental barriers. Neutral EST Limited townscape character within scheme area. Mitigation generally implemented as expected. Although new gantries are visible from Hawley, the new environmental barriers have offset the impacts of the M25. As expected (OYA evaluation) 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 90 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Cultural Heritage and Archaeology Forecast A2/A282 5.88 The AST predicted impacts on regionally important archaeological remains and on the settings of Listed Buildings and Scheduled Monuments. A moderate adverse impact was predicted. 5.89 However, the ES predicted only slight adverse impacts on cultural heritage and archaeology. Once the link E deferral was taken into account, this impact was considered to be neutral on the settings of designated heritage assets due to screening of Listed Buildings and a Scheduled Monument at Hawley Manor. 5.90 The ES noted that the A2 had already severed a Scheduled Monument at Darenth Wood – a medieval earth boundary, but this would not be affected by the scheme. 5.91 Impacts were predicted to known sites of buried archaeology within the footprint of the scheme (see Table 5.15) 5.92 Other cultural heritage assets within the vicinity of the scheme would not be affected. 5.93 Mitigation proposals comprised: Targeted fieldwork and watching brief. Archaeology report to be published. Environmental barrier at Hawley Manor (although no additional impacts were predicted from the A2 adjacent to Hawley Manor as a result of the scheme). M25 J1b-3 5.94 The AST predicted slight adverse impacts to regionally important archaeology, but these would be limited due to restricted width of land-take. 5.95 The ES predicted negligible impacts to Grade II Listed Buildings around Darenth. These comprise a listed wall at Sutton Place and Mill House, Chequers Inn and Ivy Cottage on Darenth Road, which have a distant view of the scheme. 5.96 Swanley Conservation Area and associated Listed Buildings would not be affected by the scheme. It is not possible to see the scheme from this location. 5.97 Impacts were predicted to known sites of buried archaeology within the footprint of the scheme (see Table 5.16). 5.98 Mitigation proposals comprised: Consultation with Kent County Council; Targeted fieldwork and watching brief; and Archaeology report to be published. Consultation 5.99 English Heritage was consulted but responded that its involvement with either scheme was minimal. Evaluation 5.100 Impacts are generally considered to be as expected. The only designated buildings to be affected by the schemes were the Listed Buildings and Scheduled Monument at Hawley Manor. The setting to these buildings was affected due to construction of a 2m high environmental barrier. This barrier introduced a new feature to the area, and now provides screening against the existing A2 (see Figure 5.13). This was noted in the Deferral Report as being a neutral impact but in fact there is a slight to moderately 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 91 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study positive impact on Hawley Manor as traffic is no longer visible from the site and noise impacts would have also been reduced. Figure 5.13 – Scheduled Monument and Listed Buildings at Hawley Manor with screening environmental barrier 5.101 Swanley Conservation Area and the Listed Buildings located there remain unaffected by the scheme, as predicted (further comment is provided in the landscape sub-section). The settings of the Listed Buildings around Darenth have received negligible impacts, as expected; although the M25 and new gantries are visible from these buildings, due to the distance from the scheme, these impacts only have a negligible impact on the settings of the buildings, which were already in view of the pre-existing M25. Figure 5.14 shows the Listed Building (wall) at Sutton Place illustrating a new M25 gantry visible in the middle of the photograph. Figure 5.14 – Listed Building (wall) at Sutton Place with new gantry in distant view 5.102 The Scheduled Monument at Darenth Wood – a medieval earth boundary – passes close to the A2 widening but remains unaffected by the scheme. It was formerly severed by the pre-existing A2. 5.103 At the time of writing no archaeological information has been provided to POPE and this should be considered as part of the five years after study. The archaeology report, produced by Oxford Archaeology has not yet been completed but is due during 2010. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 92 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Table 5.15 – Summary of Heritage Evaluation – A2/A282 Origin of Assessment Summary of Heritage Impacts Assessment AST (forecast) Deterioration to setting of Listed Buildings and Scheduled Monument and impact on regionally and locally important archaeological remains. Moderate adverse EST Based on effects on settings to Scheduled Monuments and Listed Buildings, impacts are better than expected in the AST due to improvements at Hawley Manor. The ES reports only slight adverse impacts to buried archaeology and the setting of Hawley Manor (an impact not realised due to the deferral of Link E). As expected (OYA evaluation) Table 5.16 – Summary of Heritage Evaluation – M25 J1b-3 Origin of Assessment Summary of Heritage Impacts Assessment AST (forecast) The scheme will have a negative impact on regionally important sites, but the actual extent of the impact is limited because of the width of the land-take. Slight adverse EST Impacts to settings of cultural heritage assets such as Listed Buildings and Swanley Conservation Area are considered to be minimal and as expected. As expected (OYA evaluation) 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 93 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Table 5.17 – Summary of predicted heritage and archaeology effects, proposed mitigation and evaluation of impacts Cultural Heritage Features Hawley Manor Grade II and II* Listed Buildings Proposed Mitigation Evaluation Original mitigation as stated in ES not required due to Link E deferral. Deferral Report proposes a 2m high barrier to provide screening from existing A2. 2m high environmental barrier constructed at Hawley Manor and reinforced planting undertaken. Barrier provides screening from A2. Impact is neutral as expected in Deferral Report – actual impact is positive due to screening of traffic. Targeted programme of archaeological fieldwork, including publication. The HEMP states that a site-wide watching brief was carried out in risk areas. Dovecote at Hawley Manor Scheduled Monument Later prehistoric and Roman sites possibly disturbed by A2/A282 earthworks: Site of 14 pits and 7 post holes of a Bronze A combined archaeology report for both schemes by Oxford Archaeology is due later in 2010 and should be made available to POPE for the FYA report. Age to Iron Age Pottery and flint finds. Site of late prehistoric/early Roman(?) settlement including19 Roman ovens/kilns and 9 possibly prehistoric pits. 2 concentrations of possible pits and cut features may represent settlement/activity. prehistoric Possible plough-levelled lynchets/field system perhaps associated with site of Roman kilns (above). Known sites of buried archaeology that may be affected by M25 earthworks (unknown condition): Find site of Palaeolithic hand axes adjacent Targeted programme of archaeological fieldwork to be confirmed with Kent County Council Heritage Conservation Group, including publication. The HEMP states that a site-wide watching brief was carried out in risk areas. Trial trenching to bar carried out at foot of treatment pond where there is a high risk of uncovering archaeological remains. A combined archaeology report for both schemes by Oxford Archaeology is due later in 2010 and should be made available to POPE for the FYA report. to Swanley. Mesolithic find at M25 J3 from possible lithic work site. Iron Age Farmstead near Sutton at Hone and Hawley. Iron Age settlement. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 94 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Biodiversity Forecast A2/A282 5.104 The AST stated that there would be no direct impact to Darenth Wood SSSI but there would be impacts to calcareous grassland, dormice and reptiles. Overall impacts were predicted to be slight adverse. 5.105 The ES predicted that there would be no direct loss of land from any designated sites. The A2 already ran through Darenth Wood SSSI and some loss of vegetation would occur along the edge, removing screening between the A2 and the SSSI. This would also have impacts upon dormice, which were known to be present in the area. 5.106 Other impacts on species included wood ants. A number of colonies would be lost by the widening of the road. This would be mitigated by translocation of colonies to the edge of the SSSI. 5.107 Calcareous grassland would also be lost along this length of the A2, but it was proposed that this should be transplanted to a pre-prepared site within Darenth Country Park. 5.108 Another scarce species of plant, dittander, would also be transplanted from a soakaway to be removed as part of the scheme, to a suitable wetland location. M25 J1b-3 5.109 The AST predicted that there would be no impacts to designated sites but there would be loss of habitat for reptiles and breeding birds, which would be enhanced through appropriate mitigation. Overall impacts were predicted to be slight adverse. 5.110 The ES stated that the impacts of the scheme would be limited due to the small amount of landtake required. It was predicted that there would be no direct loss to any designated sites, although there would be loss of screening planting at the edge of Rams Wood East and West, which is an ancient woodland. 5.111 Potential operational impacts on Sutton-at-Hone Lakes SNCI (Site of Nature Conservation Interest) would be avoided due to the scheme allowing no direct discharge to the River Darenth. New drainage and pollution mitigation systems would be implemented to prevent pollution to the river (discussed in the water and drainage section). 5.112 Impacts to protected species included loss of habitat for reptiles and loss of bird breeding territory within verges where vegetation would be removed. Consultation 5.113 Natural England declined to comment on the impacts of the scheme but said it expected detailed monitoring of landscape and biodiversity scheme mitigation to be undertaken. Evaluation 5.114 Impacts of the scheme are generally as expected, although sufficient information on ongoing mitigation has not yet been made available to POPE and should be provided at FYA stage. During the site visit it was possible to see that some of the mitigation proposed by the ES had been implemented. 5.115 Impacts at Darenth Wood SSSI were largely as expected and there was no material loss to the designated woodland. Additional planting has been provided along the verge at the edge of the A2 although this is not yet mature (see Figure 5.15). Personal communication with the Managing Agent also confirmed that dormouse mitigation had been implemented within the woodland and that ongoing monitoring was being undertaken. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 95 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Figure 5.15 – Planting at edge of Darenth Wood SSSI 5.116 New drainage and pollution mitigation has been implemented as expected for both schemes and it is therefore assumed that the impacts of the scheme on the sensitive aquatic habitats, including Sutton-at-Hone Lakes SNCI are as predicted. POPE has not been made aware of any information suggesting that there have been further impacts to aquatic habitats. 5.117 As stipulated in the ES, the dittander was transplanted to a new location (as confirmed by the Managing Agent), although details on the success of this relocation are not yet known to POPE. The calcareous grassland was also transplanted, as expected, to Darenth Country Park. Details on the success of this relocation are not yet known to POPE. Monitoring details for dittander and calcareous grassland are not yet available and will be made available to POPE for inclusion in the FYA. 5.118 Impacts to Rams Wood East seemed at the time of the site visit to be less than expected. Screening vegetation along the M25 embankment next to the wood was not lost, as predicted in the ES, and replanting was therefore not required. Figure 5.16 shows Rams Wood, to the right of the photograph, and the adjacent M25 embankment, which remains thickly wooded. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 96 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Figure 5.16 – Ancient Woodland at Rams Wood East 5.119 Verges and embankments lost to reptiles at construction phase have been replaced with new areas of embankment, replacing lost habitat, as expected. Details of post-construction reptile surveys have not been made available to POPE for this OYA report but should be available at FYA stage. 5.120 Biodiversity should be considered at the FYA stage when further monitoring information may be available. Table 5.18 – Summary of Ecology Evaluation – A2/A282 Origin of Assessment Summary of Biodiversity Impacts Assessment AST (forecast) No direct impact to any designated sites but indirect impact on Darenth Wood SSSI. Direct impacts on calcareous grassland, dormouse habitats and reptiles. Slight adverse EST Mitigation seems to have been implemented as expected and impacts to Darenth Wood SSSI are as expected. Calcareous grassland was relocated to Darenth Country Park and dittander was relocated to a new watercourse. Further information on success of relocation should be made available at FYA stage. Impacts to protected species appear to have been adequately mitigated. New embankments have provided replacement habitat for reptiles and management of SSSI has been undertaken to encourage dormice. Wood ants relocation was successful and local populations threatened by the scheme have been safeguarded (see Table 5.20). As expected (OYA evaluation) Table 5.19 – Summary of Ecology Evaluation – M25 J1b-3 Origin of Assessment Summary of Biodiversity Impacts Assessment AST (forecast) No impact on designated sites. The reduction in the width of the soft estate as a result of widening would contribute to a loss of habitat for reptiles and breeding birds. However, the biodiversity of the retained habitats would be enhanced through appropriate mitigation. Slight adverse EST No impact on designated sites, as predicted, and mitigation largely implemented as predicted although planting has not yet matured. Lost habitat for reptiles has generally been replaced due to new verges created along the J2 improvements as part of the A2/A282 scheme. As expected (OYA evaluation) 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 97 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Table 5.20 – Ecology potential impacts, mitigation and evaluation of impacts Designated Sites Aspect Predicted Impact Mitigation Measures Evaluation Loss of vegetation and grassland at A2 carriageway edge adjacent to Darenth Wood SSSI. Replanting to be undertaken in the verge at Darenth Wood. Replanting has been undertaken along the verge next to Darenth Wood but has not yet matured. Impact on Darenth wood as expected. Sutton-at-Hone Lakes SNCI downstream of M25 widening scheme along River Darent. Potential surface water pollution. No run-off to be discharged directly to River Darent from either scheme. All run-off to be collected and carried to attenuation ponds via pollution control infrastructure. Nationally scarce plant – Dittander – normally associated with salt marsh habitat found in soakaway at Blackdale Farm to be lost as part of A2/A282 scheme. Collection of Dittander seeds and plants and translocation to new suitable location. Vegetation Translocation of calcareous grassland to Darenth Country Park. An area of calcareous grassland would be lost along the A2 near Darenth Wood. Loss of hedgerow due to A2/A282 scheme in Disused Mabledon Hospital Grounds. Loss of screening vegetation at Rams Wood (ancient woodland) to east and west of M25. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx Translocation of hedgerow to safe location a few metres from original position or steepening of earthworks and protection of hedgerow during construction to allow hedge to remain in-situ. Replanting at edge of Rams Wood to replace lost planting as part of landscaping proposals New drainage has been implemented on both M25 and A2/A282 schemes and interceptors and attenuation ponds have been implemented. No information has been provided to POPE which would indicate that there has been any impact through surface water pollution to Sutton-at-Hone Lakes SNCI, as expected in the ES. The Managing Agent has confirmed that dittander was relocated to a new site. However, it is not yet known whether this transplantation was successful. Further information on the success of the relocation has not been made available to POPE and the FYA report should assess this issue if monitoring data becomes available. The Managing Agent confirmed that Calcareous grassland had been relocated to Darenth Country Park. No further information has been made available to POPE post-relocation. The FYA report should assess this issue if monitoring data becomes available. Hedgerow was not moved in eventuality and the HEMP states that it was protected during construction by a retaining wall. Long term monitoring and management of the hedgerow has been committed to. No evidence of replanting was noted at Rams wood during the site visit. However, access was only possible to Rams Wood East. The verge remained well wooded and replanting did not seem to be required as shown in Figure 5.15. 98 Reptiles potentially present at areas required for construction and areas of potential reptile habitat lost at operation of each scheme. Survey, trapping and relocation of reptiles in areas affected by construction to safe areas. New lighting may affect bat foraging. No bat roosts directly lost through either scheme but some foraging habitat lost. Appropriate lighting to be implemented. Landscape proposals including new planting will help mitigate lost foraging habitat. HEMPs for both schemes state that reptiles were captured and relocated to safe habitats not affected by construction. Newly created verges have provided new reptile habitat but monitoring data has not been made available to POPE. The HEMPs state that bat boxes have been installed on mature trees and posts adjacent to attenuation ponds and next to the River Darent. Landscape planting proposals implemented as expected but not yet mature. Bats Reptiles Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Badgers Birds Modern lighting with reduced light spillage has been implemented across both schemes. No information has been made available to POPE which would inform whether bat foraging has been affected by the scheme lighting. New lighting may affect birds. habitat lost. Some foraging Appropriate lighting to be implemented. Landscape proposals including new planting will help mitigate lost foraging habitat. Landscape planting proposals implemented as expected but not yet mature. It is not known by POPE whether lighting has affected the local bird population Modern lighting with reduced light spillage has been implemented across both schemes Badgers close to construction works and living within Darenth Wood. Mitigation to be undertaken during construction. HEMP states that appropriate mitigation was undertaken during construction. Badger fencing to be provided through Darenth Wood to reduce badger deaths on A2. Site visit showed badger recommended within the ES. fencing had been installed as No animal mortality data has been made available to POPE for this OYA study and will be requested again at FYA. Dormouse Potential dormouse habitat lost, particularly at edge of Darenth Wood and Rams Wood. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx Replanting of habitat adjacent to Rams Wood and Darenth Wood to replace lost habitat. Agreement with HA and Natural England to be sought to manage replanted verge and SSSI adjacent to Darenth Wood for dormice. Replanting has been undertaken in areas identified within ES. Woodland not yet mature enough to be managed for dormouse habitat. According to the HEMP for the A2/A282, dormouse boxes have been provided within Darenth Wood. Ongoing monitoring has been undertaken for dormice. No survey information has been made available to POPE and should be provided to POPE for the FYA evaluation 99 Wood Ant Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Wood ant nests on embankments lost due to widening of A2. The species is in decline throughout its range. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx Translocation of wood ant nests to pre-prepared sites at edge of Darenth Wood SSSI and 2 year post-translocation monitoring programme. 100 HEMP for A2/A282 states that ants were moved in 2006 and 2007. Monitoring was undertaken and has shown that 2006 colonies were generally abandoned, but 2007 colonies proved more successful. The HEMP considers that the wood ant population along the A2 embankments has been safeguarded. Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Water Quality and Drainage Forecast A2/A282 5.121 The AST stated that soakaways would be relocated or replaced with balancing ponds. Enhanced pollution control would be implemented before discharge. This would have a slightly beneficial impact on the water environment. 5.122 The ES predicted that there would be a reduced pollution threat to the River Darent and source protection zone due to provision of balancing ponds and removal of existing soakaways. New soakaways would be provided in areas less vulnerable to groundwater pollution and pollution control features such as oil separators would also be implemented on all discharges to groundwater and the River Darent. 5.123 Due to mitigation measures and flood compensation the scheme would have a neutral impact on flood risk. M25 J1b-3 5.124 The AST stated that provision of pollution facilities, including spillage containment and oil interception at outfall locations, would result in improved pollution control, resulting in a benefit in terms of protecting groundwater quality, meaning an overall slight beneficial assessment score. 5.125 The ES stated that the scheme would increase run-off due to additional lanes, meaning greater flow at discharge points. There would be a changed risk of spillage due to new lanes, lane-widths and traffic management, and changes to the scheme hydrology and drainage. 5.126 The M25 drainage would discharge to ground at fewer locations than the Do Minimum and impacts would be mitigated by installation of pollution control measures at each discharge, improving pollution control and reducing risk to ground and surface waters. A vegetative treatment pond would also be provided at Pond 3. The result of the scheme would be a predicted slightly beneficial impact. 5.127 Due to mitigation measures and flood compensation the scheme would have a neutral impact on flood risk. Consultation 5.128 The Environment Agency stated that it did not have any monitoring data available, but expected water quality to have improved if all mitigation stipulated in the ESs was implemented. Jacobs’ Handover Water Quality Monitoring Report (March 2010) was not available in time to consult the EA with and so they should be consulted at FYA stage. Evaluation 5.129 The HEMP and as-built drainage drawings for both schemes illustrate that all mitigation has been implemented as expected. Water from both schemes was previously discharged – unmitigated – to ground through soakaways but is now captured through pollution controlled drainage and treated. The risk to ground and surface waters by spillage has now also been mitigated, and a spill event on either the A2, A282 or M25 will now be intercepted before discharge to ground or to the River Darent. 5.130 The Managing Agent confirmed that there were no spill events during construction or since and this is supported by the data available in the Handover Water Quality Monitoring Report. The report noted that there is litter within the drainage and surface waters associated with both schemes, and summarised that “the water in each environment; groundwater, natural surface water and highways drainage, was fairly consistent with little change over the monitoring period. However, as not all of the monitoring locations were consistently visited or sampled from, direct correlation is difficult to assess. The only locations which were generally visited on each occasion were the surface water locations along the river - which could be argued to be the most important as an indicator of contamination from the Works. A more in-depth look consideration of the results 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 101 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study from these locations indicates little if any change in the quality of the water over the period of the works. 5.131 It is recommended that, if possible, water quality monitoring is continued and reported again at FYA stage. Efficacy of mitigation measures in relation to spill events should also be assessed at FYA. 5.132 New drainage installed on each scheme to cope with run-off from additional lanes and links carries all run-off to the edge of the carriageway to single discharges, some of which are mitigated by baffled spillways to reduce flow-speeds (see Figure 5.17). Spillage containment tanks and oil interceptors then intercept run-off before discharge into attenuation ponds. Figure 5.18 shows such an attenuation pond – Combined Pond A – which was provided as part of the A2/A282 scheme. Towards the centre of the photograph it is possible to see the outlet / flow control structure with isolated penstock, which discharges to the River Darent. Figure 5.17 – Baffled spillway to north-west of M25 J2 Figure 5.18 – ‘Combined Pond A’ to the north-west of M25 J2 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 102 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Table 5.21 – Summary of Water Evaluation – A2/A282 Summary of Water Impacts Origin of Assessment Assessment AST (forecast) Soakaways relocated and/or replaced with balancing ponds. Enhanced pollution control facilities before discharging into river. Slight beneficial EST Soakaways have been replaced with balancing ponds. Oil separators have been installed at all discharge points and spillage containment tanks, baffled spillways and penstocks have also been installed to mitigate water pollution impacts. Mitigation has been implemented as expected. Monitoring data suggests that there has been no significant change in water quality as a result of the scheme. Likely to be as expected (OYA evaluation) Table 5.22 – Summary of Water Evaluation – M25 J1b-3 Summary of Water Impacts Origin of Assessment Assessment AST (forecast) Water features in the study area are typical of the locality with a major aquifer (chalk) providing abstraction water, and the River Darent crossing under the M25. Provision of pollution control facilities, including spillage containment and oil interception at outfall locations, will result in improved pollution control, resulting in a benefit in terms of protecting groundwater quality. Slight beneficial EST Soakaways have been replaced with balancing ponds. Oil separators have been installed at all discharge points and spillage containment tanks, baffled spillways and penstocks have also been installed to mitigate water pollution impacts. Mitigation has been implemented as expected. Monitoring data suggests that there has been no significant change in water quality as a result of the scheme. Likely to be as expected (OYA evaluation) Physical Fitness Forecast 5.133 The ASTs for both schemes predict no changes to distances travelled by non-motorised users and a neutral impact on physical fitness. 5.134 The ES for both schemes noted that there would be no physical change to any public rights of way, with the exception of a slight diversion of footpath DR36 near Blackdale Farm Cottages. The possible depreciation to amenity value for public rights of way crossing and situated close to the schemes was predicted. There would be no additional severance of recreational or community land for either scheme. A neutral impact was predicted for non-motorised users. Consultation 5.135 No comments on physical fitness have been made by consultees. Evaluation 5.136 A number of public rights of way were severed when the existing M25, A2 and A282 were constructed. The M25 J1b-3 and A2/A282 schemes did not seek to mitigate any of this pre- 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 103 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study existing severance; neither do they cause any additional negative material effects to any public rights of way. This is as expected. 5.137 A number of public rights of way pass close to the schemes and have been affected by the scheme by changes in views. These impacts are tempered by the pre-existing character of the landscape, already dominated and severed by the M25, A2 and A282. 5.138 With the exception of DR36, no public rights of way have been materially affected by either scheme. Figure 5.19 shows DR36 (to the right of the carriageways), which has been moved slightly to skirt the edge of the new embankment supporting Link A at M25 J2. It is considered that this diversion has had a negligible change to the footpath, as expected in the ES. Figure 5.19 – Diversion to footpath DR36 Table 5.23 – Summary of Physical Fitness Evaluation – A2/A282 Origin of Assessment Summary of Physical Impacts Assessment AST (forecast) No change to distances walked or cycled Neutral EST Public rights of way are unaffected by the scheme and there is no new severance. As expected (OYA evaluation) Table 5.24 – Summary of Physical Fitness Evaluation – M25 J1b-3 Origin of Assessment Summary of Physical Impacts Assessment AST (forecast) The health benefits would remain unchanged as there are no changes to the public right of way network Neutral EST Apart from minor changes to footpath DR36, public rights of way are unaffected by the scheme and there is no new severance. As expected (OYA evaluation) 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 104 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Journey Ambience Forecast A2/A282 5.139 The AST predicted that journey ambience would be improved through reduced congestion and improved signage, with a slightly beneficial impact. 5.140 The ES commented on driver stress, predicting that it would be improved due to reduced congestion, and traveller care would also be improved by provision of new signage. M25 J1b-3 5.141 The AST stated the scheme would be beneficial due to reduced congestion, improved road layout, signage and lighting, tempered by the possible perception of fear of accidents due to reduced lane width. 5.142 The ES predicted that: Traveller views would be opened at OYA stage due to removal of vegetation, but views would largely be unchanged after design year due to establishment of planting. Driver stress would be improved by reduced congestion at peak times and provision of more road space. Traveller care would be improved by new gantries and signage and implementation of new lighting. Evaluation 5.143 The Journey Ambience sub-objective considers Traveller Care (facilities and information), Traveller Views and Traveller Stress (frustration, fear of potential accidents and route uncertainty). Traveller Views 5.144 Traveller views are generally as expected, although additional height of 3m barriers (rather than 2m high barriers as presented in the ES) along additional lengths of the M25 will have constrained predicted views. Driver Stress 5.145 Driver stress should have generally reduced on both schemes due to the reduction in congestion (this may be due to less traffic growth, as a result of recession) and thus reduced frustration. Improved links on the A2/A282 scheme has improved route certainty and fear of accidents and improved signs and signals on both are likely to have further reduced driver stress by improving route certainty. Improved lighting would have also reduced fear of accidents. Narrower lanes on the M25 may have possibly contributed to drivers’ fear of accidents. Traveller Care 5.146 Gantries and lighting have been implemented as expected, improving driver information. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 105 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Table 5.25 – Summary of Journey Ambience Evaluation – A2/A282 Origin of Assessment Summary of Journey Ambience Impacts Assessment AST (forecast) Less congestion and stress reduced due to improved signing Neutral EST New gantries and signage have improved driver information. Provision of more lanes and new junction layouts have generally improved journey times. Additional lighting will have improved night time driving conditions. As expected (OYA evaluation) Table 5.26 – Summary of Journey Ambience Evaluation – M25 J1b-3 Origin of Assessment Summary of Journey Ambience Impacts Assessment AST (forecast) The proposals are beneficial in terms of anticipated reduction in traffic, improved road layout, signage and lighting. However, this is balanced by reduced lane width possibly causing increased fear of accidents. Neutral EST New gantries and signage has improved driver information. Provision of more lanes and should have generally improved journey times. Additional lighting will have improved night time driving conditions. Driver views are more restricted than expected due to implementation of higher environmental barriers on additional lengths of the scheme. As expected (OYA evaluation) 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 106 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Key Points from Environment Section Noise – On the M25, it is likely that local noise impacts are generally better than expected due to traffic flows being lower than forecast (possibly due to recession impacts) and improved noise mitigation. For the A2/A282 scheme, it is likely that overall local noise impacts are generally as expected based on overall traffic impacts compared to forecast; Local Air Quality – As with noise, based on traffic flows, it is possible that local air quality impacts are generally better than expected on the M25 and as expected for the A2/A282 scheme. There should be no worsening of air quality at AQMAs, as expected. Greenhouse Gases – The proportional increase in opening year carbon emissions is as predicted for the A2. Opening year emissions on M25 are similar to the only published forecast which is for 2022. Landscape – Mitigation measures generally provided in line with proposals. Too soon to evaluate establishment of new planting and seeding which should be reviewed as part of the FYA report. Visual impacts and landscape effects are considered to be generally as predicted at OYA. Biodiversity – There have been no direct impacts as a result of either scheme to any designated sites, but indirect effects on Darenth Wood SSSI due to vegetation loss adjacent to the A2 as expected. Mitigation has been implemented generally as expected. Translocation of species and habitats has generally been undertaken as described in the ES but - with the exception of wood ants, which proved successful - monitoring data has not been made available to POPE to confirm the success of relocation. Cultural Heritage – Based on the information available it is considered that impacts of the M25 scheme are as expected. Impacts to Listed Buildings and the Scheduled Monument at Hawley Manor are better than expected due to screening of traffic by environmental barriers. Water –It is considered that the impacts of both schemes are as expected as mitigation measures have been implemented as planned. Water quality reporting suggests that there has been no significant change to water quality as a result of the schemes. Physical Fitness – Impacts on public rights of way and community land were predicted to be minimal for both schemes and were generally limited to visual impacts. As such, the neutral impact for both schemes is as expected. Journey Ambience - Congestion has been reduced on both schemes (this is partly due to traffic growth predictions not being realised, possibly due to recession impacts), the routes are well signed - removing uncertainty - and new links have generally improved vehicle movements between the schemes. This is tempered by reduced lane widths on the M25, which increase fear of accidents. Views from certain areas of the M25 may be more restricted than expected at OYA stage due to increased height and length of environmental barriers, but impacts on journey ambience are generally as expected. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 107 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study 6. Accessibility and Integration Introduction 6.1 Accessibility and Integration are the remaining objectives of the five Government objectives for transport. As part of each scheme’s appraisal, forecasts for the impacts on these objectives were covered in the AST (see Table D.1 / D.2 and Table D.3) and formed part of the schemes’ preopening assessments. Data Sources 6.2 The evaluation presented here is based on the site visit and on literature searches. Forecast impacts are available from the ASTs for each scheme. 6.3 For the M25 scheme, Stage 3: Scheme Assessment Report Part 2 Engineering, Traffic and Economics section (SAR) also included accessibility objectives. Option Values 6.4 Option values, as defined in WebTAG, largely relate to measures which will substantially change the availability of transport services within the study area. Forecast 6.5 The forecast impacts of the A2 and M25 schemes were both no impact. Evaluation 6.6 It is considered that appraisals are valid for both schemes and that no more detailed evaluation would reveal any changes to options values connected with the schemes. Severance 6.7 This sub-objective is concerned with severance as it affects those using non-motorised modes, especially pedestrians. Forecasts A2/A282 scheme 6.8 The AST stated that the existing junction already caused severance and assessed the impact as neutral. 6.9 A Pedestrian and Cyclist Report was prepared at OPR stage (May 2004). This states that the junction was unsuitable for use by cyclists and pedestrians in both its then existing form and that proposed in the scheme. 6.10 Use of the A2 by pedestrians was described as minimal or non-existent due to the lack of infrastructure and was only likely to occur as a result of vehicle breakdown or accident. The nature of the road meant that equestrian users did not use the route. 6.11 Cyclists were permitted on the A2 and A282, although the study identified a number of conflict zones at the junction. The National Cycle network passes through J1b and Dartford town centre. Consultation with the Kent CC Cycling Officer confirmed that no cycling provision was required for this scheme. 6.12 The report concluded by recommending that: 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 108 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Pedestrians, cyclists and equestrians be prohibited by a Traffic Regulation Order from using or crossing the A2 between the Bean junction and the Dartford Heath junction and from the A282 south of J1b. Appropriate signage would be provided; An alternative route for cyclists be signposted between the A2 at Bean and the Dartford Heath junction via the National Cycle Route 1 where appropriate; and No mitigation measures were required for other vulnerable users. 6.13 The ES stated that in general, off-road rights of way for pedestrians, cyclists and equestrians were not expected to be impacted by the scheme. The promotion of transport such as walking and cycling within Dartford would not be prejudiced by the Scheme. 6.14 In the Environmental Impact Tables, assessment of the impact of the scheme for Pedestrians, Cyclists and Equestrians was: No new severance would be created; and Only change in amenity value would be a minor diversion to one footpath near Blackdale Farm Cottages (DR36), north-west of the junction. M25 scheme 6.15 The AST stated that five footpaths ran close to the widening, and two crossed over this section of the M25 but none would be affected by the scheme. Evaluation 6.16 The as-built drawings confirm that the impacts on rights of way are as predicted. The only footpath diversion is minor, makes negligible change to its route length or amenity value. This was confirmed by the site visit. Figure 6.1 – Relocated Stile on footpath DR36 Access to the Transport System 6.17 WebTAG states that access to the transport system is strongly influenced by the two key variables introduced at the start of this section, i.e. access to a private car and proximity to a public transport service. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 109 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Forecast A2/A282 6.18 The original AST stated that neither benefits to existing network nor increased opportunities for public transport initiatives were assessed. 6.19 The later AST compiled following the completion of construction additionally said that it would facilitate access to Ebbsfleet International station and to regeneration areas. 6.20 The assessment in both ASTs was neutral. M25 J1b – 3 6.21 The AST stated that although access to public transport systems (e.g. Ebbsfleet railway station) is improved, the scheme does not form part of a public transport route. Hence the assessment was neutral. 6.22 The SAR stated that the scheme’s accessibility objective included: Facilitating access to Ebbsfleet International Rail Station; and Improving access to regeneration areas of North and East Kent Evaluation 6.23 It is not possible to evaluate the impacts using the webTAG 'Access to the transport system' indicator current at the time of the schemes’ appraisals because this was based on the impacts for the local population without access to a car and data on the local public transport services. These schemes have had no impact on local bus routes or bus stops. The analysis in the traffic section of this study has shown no clear impact on traffic flows on the local roads in Dartford hence no impact on bus reliability can be inferred. 6.24 Draft guidance for the accessibility objective (TAG Unit 3.6.3 January 2010) replaces the Access to the Transport System sub-objective. This new guidance recognises the link between transport and social exclusion of vulnerable groups. These groups include older people and people in receipt of Jobseekers Allowance. It is however considered that the schemes have produced real benefits for members of these groups who have access to a car in terms of journey times and reliability to destinations including: 6.25 Employment opportunities in Regeneration areas; Ebbsfleet Station which opened in November 2007; and Retail facilities at Bluewater shopping centre. It is not possible to quantify these access benefits. The overall evaluation is this conservatively concluded to be slight beneficial for both schemes. Integration 6.26 The integration objective is to ensure that all decisions are taken in the context of the Government's integrated transport policy. 6.27 The forecast integration objectives were given in the AST for each scheme for each of the integration sub-objectives: Transport interchange Land-use policy Other Government policies 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 110 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study A2/A282 Forecast 6.28 The scheme formed an integral part of public transport based strategy for Kent and Thameside development and hence was assessed to be moderate beneficial for the transport interchange sub-objective. 6.29 The impact on policy objectives was assessed as adverse due to loss of good agricultural land, and the direct and indirect effect on Green Belt, nature and heritage conservation designations which are contrary to local and national policy objectives. Evaluation 6.30 Kent Thameside forms part of the Thames Gateway area of regeneration as set out in the Government’s Thames Gateway Interim Plan (2006). For Kent Thameside this means the delivery of 25,000 homes and 50,000+ jobs by 2026. 6.31 The scheme is consistent with the Kent Thameside Strategic Transport Programme which supports delivery of this programme and has therefore been evaluated to have a beneficial impact, as expected. 6.32 The omission of link E from the as-built scheme will have slightly reduced the adverse impact on heritage policy, but otherwise the scheme’s impact on land use policy and other government polices is adverse as forecast, and therefore the evaluation of the impacts is as expected. M25 J1b – 3 Forecast 6.33 This scheme was forecast to have a neutral impact on all of the integration sub-objectives. 6.34 No transport interchanges would be affected by the scheme. 6.35 In terms of land use policy and other government policies, the scheme was consistent with policies supporting a reduction in congestion and network capacity enhancement whilst having a slight adverse impact on some local environmental policies. Evaluation 6.36 The forecast capacity and congestion improvements have been met by this scheme. The environmental impacts of this widening scheme, as detailed in the environment section of this report, are clearly less than the A2/A282 scheme. Therefore the evaluation of the overall policy impact is assessed to be neutral, as expected. 6.37 The OYA evaluation is that these forecast impacts have been as expected for each sub-objective. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 111 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Key Points from Accessibility and Integration Section Accessibility (A2/A282 and M25 J1b – 3) Option Values and Severance – no impact as expected. Access to the Transport System – improved access to employment and retail for car users, improved access to new Ebbsfleet International Station. Integration- A2/2A282 Transport Interchange – A2/A282 scheme is part of wider transport strategy for Kent Thameside regeneration area. Land Use Policy – adverse as expected. Other government policies – adverse as expected. Integration – M25 J1b Transport Interchange – no impact as expected. Land Use policy –neutral overall impact as expected. Other Government Policies – neutral overall impact as expected. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 112 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study 7. Conclusions Measurement against NATA Objectives: AST & EST 7.1 The appraisal of each scheme against the NATA objectives was given in Appraisal Summary Tables (AST). The Appraisal Summary Table (AST) is a one page summary of a scheme covering the Government’s five goals for transport taking into account of all the economic, social, environmental and financial impacts of an intervention. 7.2 The AST therefore provides a checklist against the standard set of objectives. 7.3 Evaluation of accuracy of the AST forecasts is summarised in a POPE table called the Evaluation Summary Table (EST). 7.4 The AST and EST tables for these schemes are given in Appendix D. Measurement against Scheme-specific Objectives 7.5 The performance of the A2/A282 and M25 schemes, against the specific objectives of the schemes, as opposed to the NATA ones are as follows, followed by brief details of the basis of the evaluation. 7.6 The objectives listed here are based primarily on the Scheme Assessment Report for each scheme, with some additional details from the Statement of Case, AST or ES of each scheme. Traffic and Economy Objective Objective Fulfilled? Improve journey times and reliability on A2 (A2/A282) Reduce journey times by 30-60 seconds and improve reliability on M25 (M25 J1b-3) Provide good value for money for business users and consumers (both schemes) Facilitate future demand management measures1 to provide some constraint on induced traffic and lock in benefits from widening. These measures would be carried out separately from this scheme. (M25 J1b-3) Reduce congestion and improve reliability at M25 J2 (A2/A282) Support objectives of the Regional Planning Guidance for South-East (RPG9) and the Thames Gateway Planning Framework (RPG9a). (M25 J1b-3) 1 At the time of appraisal, several types of measures were under consideration including Controlled Motorway, Ramp Metering, and controlled access using existing signals on roundabouts. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 113 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study 7.7 The journey time surveys in the traffic section of this report show: Reduced journey times for the key movements at the junction; Reduced journey times on the A2 and M25; and Reduced variation in journey times on A2 and M25. These observations show that the first 3 objectives above have been met. 7.8 The economic evaluation of the outturn costs and reforecast of the benefits money over the 60 year appraisal period shows that the overall BCR for the two schemes combined is 2.2, representing good value for money. 7.9 Provision of infrastructure for a Controlled Motorway system on the M25 at the same time as the widening scheme evaluated here will have improved incident detection. Arguably, when the variable speed limits of the CM are activated, this will lock in the benefits of the widening scheme. 7.10 The schemes are consistent with regional planning guidance. Safety Objective Objective Fulfilled? Improve safety on A2 / A282 and M25 (both) Improve safety on nearby local roads due to reassignment of traffic onto the M25 and A2 (both) ? Improve security through use of CCTV (both) 7.11 The safety section of this report shows improved safety through reduced accident numbers on both the M25 and on the A2, despite increased traffic on the latter. 7.12 It is not possible to evaluate the safety impact on the local road network because this was forecast to be very small and was based on traffic rerouting from these roads to the motorway and trunk road network. The traffic data does not indicate clear evidence of rerouting from the local roads and any small accident saving on these roads would be impossible to distinguish from statistical noise and possible larger impacts on safety through local authority safety measures. 7.13 CCTV has been installed around the junction and on the M25. Environment Objective Minimisation of environmental impacts through low noise surfacing, noise barriers and full cut-off lighting (A2/A282 and M25 J1b-3) Minimisation of environmental impacts through construction of scheme within existing highway boundary (M25 J1b-3) ? Improve water pollution control measures (M25 J1b-3) 7.14 Objective Fulfilled? The environment section of this report shows that mitigation measures have been put in place. Where data exists, these have shown to be working. At this stage it is too soon to evaluate 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 114 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study impacts on landscape and biodiversity which take longer to come into full effect. Water monitoring data is required to confirm the success of the improved pollution control measures. Accessibility and Integration Objective Objective Fulfilled? Provide access to new Ebbsfleet International station from the national motorway and trunk road network (both) Provide beneficial economic impacts to Kent Thameside Regeneration Area (both) 7.15 Ebbsfleet International Station opened in November 2007, just prior to the completion of the A2/A282 scheme. Access to the station is clearly benefited by the improvements to the A2, the junction and the M25. 7.16 At this stage post scheme completion, and in a recession, it is not feasible to measure actual job creation linked to the scheme. The regeneration area will be able to benefit from the improvements to journey times and reduced congestion. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 115 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Appendix A Summary of Sources A.1.1 The sources upon which this evaluation is based include the following: Traffic counts and journey times from the Highways Agency’s databases, and surveys specifically commissioned for this study; Accident records obtained from the HA MACs for Area 4 (A2 in Kent) and Area 5 (M25 and A2 within M25); A site visits by a transport planner and a landscape architect; Consultation with the local authorities and statutory environmental bodies; Reports appraising the scheme, prior to construction as detailed below. A2/A282 Dartford improvement A2/A282 Dartford Improvement & M25 J1b - J3 Rapid Widening Traffic Survey (March 2005) A2/A282 Dartford Improvement Statement of Case (January 2004) Inspectors Report (March 2004) Pedestrian and Cyclist Report (May 2004) Public Inquiry: Traffic & Economics Proof of Evidence Summary (January 2004) Engineering Proof of Evidence (Jan 2004) Proof of Evidence documents for Environment objectives (Landscape, Archaeology, Ecology, Noise & Vibration, Air Quality, Water Quality) (January 2004) OPR stage: A.1.2 Traffic Forecasting Report (June 2002) Economic Assessment Report Part 1: Methodology (June 2002) Economic Assessment Report Part 2: Economic Assessment (December 2003) A2/A282 Dartford Improvement Environmental Statement Volumes 1 & 2 (March 2003) Sources for the appraisal of the modified version of the Dartford Improvement scheme known as Link E deferred: Economic Assessment Report Addendum II (June 2006) Report on Deferment of Link E and Revised Landscape and Drainage Attenuation Proposals in North West Quadrant of Junction 2 (April 2006) Appraisal Summary Table Comparison (January 20081) 1 Note that this was a post opening review of the link E deferred scheme which updated the previous AST for the earlier version of the layout. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 116 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study M25 J1b-3 Widening M25 Rapid Widening – Summary and Implementation Strategy Report (May 2004) Volume 3A M25 Rapid Widening - Section 3 - Junction 1b-3 Stage 1 Report: (May 2004) Volume 3B M25 Rapid Widening - Section 3 - Junction 1b-3 Stage 1 Report: (May 2004) M25 Rapid Widening Scheme Section 3 Junctions 1b to 3 – Environmental Scoping Report (August 2004) M25 – Section 3 Junctions 1b To 3 Phase 1 Habitat Survey (February 2005) Appraisal Summary Table Date: 1/12/06. Stage 3 - Version IFU Rev 1 A2/A282 Dartford Improvement & M25 J1b - J3 Rapid Widening Traffic Survey (March 2005) M25 J1b to J3 Widening Scheme Order Publication Report (October 2006) M25 J1b to J3 Environment Statement and Non-technical Summary(November 2006) Stage 3 Scheme Assessment Report : Engineering Traffic and Economics (November 2006) Economic Assessment Report Addendum (Sept 2006) 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 117 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Appendix B Scheme Objectives 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 118 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Details of the objectives as stated in published documents during appraisal stages of each scheme are given below. B.1 A2/A282 Dartford Objectives B.1.1 B.1.2 B.1.3 The Stage 3 Scheme Assessment Report gives the objectives at the Order Publication Report (OPR) stage as: To improve the flow and safety of traffic at the interchange of the A2/A282, together with the provision of a dual four lane carriageway in each direction on the A2, east of the M25; To limit the environmental impact of the Scheme, and to reduce noise impact on adjacent residential properties. In particular, to limit the impact on the Darenth Wood Site of Special Scientific Interest (SSSI) and the Darenth Wood Scheduled Ancient Monument (SAM); To improve safety at the junction by reducing congestion and the consequent queuing of traffic back onto the A2, A282 and M25; To reduce journey times and improve reliability in order to provide enhanced access from the M25 to the major regeneration area of Kent Thameside, as part of the Thames Gateway Planning Framework RPG9a. Also to improve access to other regeneration areas in North and East Kent, helping to support jobs and prosperity; To facilitate access to Ebbsfleet International Rail Station from the national motorway and trunk road network; and To be part of and to support other elements of an integrated and sustainable public transport based strategy for the Kent Thameside regeneration area. The scheme’s objectives as given in the 1998 Roads Review were to: Reduce congestion at the junction of A2 and A282; Provide additional road capacity to cater for predicted future traffic growth; and Improve accessibility of the Thames Gateway area. The Statement of Case (2004) and Environmental Statement (2003) documents both give the scheme objectives as: To improve the flow and safety of traffic at the interchange of the A2/A282, together with the provision of a dual four lane carriageway in each direction on the A2, east of the M25; To limit the environmental impact of the Scheme and to reduce noise impact on adjacent residential properties. In particular, to limit the impact on the Darenth Wood Site of Special Scientific Interest (SSSI) and the Darenth Wood Scheduled Ancient Monument (SAM); To improve safety at the Junction by reducing congestion and the consequent queuing of traffic back onto the A2, A282 and M25; To reduce journey times and improve reliability in order to provide enhanced access from the M25 to the major regeneration area of Kent Thameside, as part of the Thames Gateway Planning Framework RPG9a. Also to improve access to other regeneration areas in North and East Kent, helping to support jobs and prosperity; To facilitate access to Ebbsfleet International Rail Station from the national motorway and trunk road network; and To be part of and to support other elements of an integrated and sustainable public transport based strategy for the Kent Thameside regeneration area. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 119 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study B.2 M25 J1b – 3 Objectives B.2.1 B.2.2 B.2.3 The objectives of the M25 J1b - 3 widening scheme can be summarised based on the AST (2006) as: To improve journey time reliability; To reduce journey times for consumers and business users by 30-60 seconds in the opening year and increasing in future years; To provide beneficial economic impacts due to journey time reliability improvements: - Increased labour pool within Kent Thameside Regeneration Area; - Job creation for residents of Kent Thameside Regeneration Area through increasing the labour pool; To improve security through CCTV and improved emergency call facilities; and To improve safety on nearby local roads due to reassignment of traffic onto the M25. The Scheme Assessment Report (SAR) included details of the objectives of this scheme against the Government’s five key objectives for transport (NATA). These include those listed above and the following: In terms of environmental objectives, the scheme would seek to minimise adverse impacts on noise, air quality, landscape, and the water environment; Support objectives of the Regional Planning Guidance for South-East (RPG9) and the Thames Gateway Planning Framework (RPG9a); and Facilitate demand management measures to provide some constraint on induced traffic and lock in benefits from widening, which were to be developed, together with improvements to junctions and incident detection measures. This development work would be carried out separately, by others, to the development of the widening Scheme, but there would be close liaison between those taking forward the different work streams. The implementation of any emerging demand management measures would be coordinated with the Scheme. Additionally to the NATA objectives, the SAR stated that: The M25 scheme was to be packaged with A2/A282 Dartford Improvement in order to avoid abortive construction work, limit the disruption to road users by completing the two Schemes within the minimum possible time, and minimise the overall cost. The Environment Statement (ES) included a full set of scheme objectives including those above and: B.2.5 Benefits to existing and future transport-reliant businesses; B.2.4 - To minimise the environmental impacts through the use of: - Lower noise surfacing to minimize noise levels; - Environmental barriers in the Hawley area to reduce adverse visual impacts for properties and provide noise attenuation; and - Full cut-off lanterns to minimise the visual impact of the lighting; and To produce a positive effect on the environment with the inclusion of up to date pollution control facilities and the incorporation of vegetative treatment of the surface water run-off prior to disposal via soakaway. Although the planned Controlled Motorway (CM) was not directly part of this scheme, one of the objectives of this scheme (as stated in the ES) was: 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 120 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Provision of sufficient communications infrastructure and sign gantries to facilitate the incorporation of variable speed limits for Controlled Motorway. This would produce more reliable journey times hence supporting the objective of reducing driver stress. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 121 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Appendix C Environmental Sources 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 122 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study C.1 Standard list of information required to evaluate the environmental sub-objective Information Requested Environmental Statement (ES) (or Stage 3 Scheme Appraisal Report) Information Received M25 junctions 1b to 3 Widening Scheme ES, November 2006: Volume 1A – main text; Volume 1b – figures; Volume 3 – appendices; NonTechnical Summary. A2/A282 Dartford Improvement ES, March 2003: Volume 1 – main text and appendices; Volume 2 – figures. Appraisal Summary Table (AST) A2/A282 2004. AST, January A2/A282 AST Link Deferral, June 2006. M25 2006 Amendments, updates or addendums to the ES or relevant further studies or reports. AST, E December A2/A282 Dartford Improvement Report on Deferment of Link E and Revised Landscape and Drainage Attenuation Proposals in North West Quadrant of Junction 2, Issued at IFI, April 2006. A2/A282 Dartford Improvement AST Comparison, Issued at IFI, January 2008. ‘As Built’ drawings for landscape, ecological mitigation measures, drainage, fencing, earthworks etc. Not yet completed for landscape and ecology. A2/A282 drainage drawings received. M25 drainage drawings received. Landscape and Ecology Management Plans Not yet completed, but generic HEMPs received for both schemes. Relevant contact names, of people with knowledge of the scheme at: the Statutory Consultees (Environment Agency, English Heritage and Natural England); 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx Contact details received 123 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Information Requested Information Received the local authorities; parish councils the designer or environmental coordinators for the scheme and for the MAC; and, any other relevant specialist consultees that were contacted Archaeological reports (popular and academic) Not yet completed. Due for completion later in 2010. List of properties eligible for noise insulation No properties eligible for noise insulation List of Part 1 Claims regarding noise, air quality or lighting (from HA National Part 1 Team) Due to be received by FYA stage. Results of any post opening survey or monitoring work, e.g. ecology surveys. Not made available to POPE. Animal mortality data, pre and post scheme construction (from MAC) Not made available to POPE Water quality monitoring data A2/A282 Dartford Improvement & M25 J1b-J3 Widening Scheme Handover Water Quality Monitoring Report. Scheme newsletters or publicity material for the scheme. Material utilised from HA website. Copy of the Non-Motorised User (NMU) post opening survey No NMU survey completed for either scheme due to lack of impacts on NMUs Information available regarding environmental enhancements to streetscape/townscape for bypassed settlements N/A Employer’s Requirements Works Information - environment section Not made available to POPE 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 124 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Appendix D Appraisal Summary Tables & Evaluation Summary Tables 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 125 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study D.1 Appraisal Summary Table D.1.1 The Appraisal Summary Table (AST) is a one page summary of the scheme covering the Government’s five goals for transport taking into account of all the economic, social, environmental and financial impacts of an intervention. The NATA AST is designed to provide decision takers with a concise overview of impacts across the board. A2/A282 scheme D.1.2 Several ASTs have been compiled for this scheme since it first entered the TPI programme in 1998 including: Initial AST for 1996 Scheme (1998) Key Stage 3 AST for Public Inquiry (Jan 2004) Key Stage 4 AST (start ECI phase 2) taking into account deferral of Link E (June 2006) D.1.3 Normally the Stage 3 version of the AST as shown in Table D.1 would be the final version, but in this case the decision to defer Link E mean that further appraisal was undertaken including the revision of the AST. The final revised AST is shown in Table D.2 D.1.4 The important changes between the last two versions are: D.1.5 The removal of the construction of Link-E (free-flow A2 eastbound to A282 northbound) from the scheme; The addition of the M25 J1b – 3 widening scheme Change of normal appraisal period from 30 to 60 years and price base year to 2002. These changes are reflected in changes in the assessment for the sub-objectives: Accidents – a small increase in economic benefit linked to revised price base Economy – increases in both the cost of the scheme to public accounts and the Transport Economic Efficiency benefits. These are primarily due to the change in price base, appraisal period and reducing discounting rate rather than from Link E. All other sub-objectives were considered to be unchanged by the deferral of Link E. M25 J1b – 3 D.1.6 The AST for the M25 widening is shown in Table D.3. This was prepared shortly before the start of construction and is for the scheme without the Controlled Motorway in operation. D.2 Evaluation Summary Table D.2.1 In order to ascertain the accuracy of predictions made prior to the scheme construction, a review of the AST has been undertaken. Whilst the AST format is a standard from the NATA process, the Evaluation Summary Table (EST) has been devised for the POPE process to record a summary of the outturn impacts for the NATA objectives, compared to the predictions in the AST. D.2.2 Where possible, the format of the EST mirrors the appearance and process of the AST to enable comparison between the two. D.2.3 The ESTs for these schemes are shown in Table D.4 and D.5. 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 126 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Table D.1 – Appraisal Summary Table: A2/A282 Dartford Improvement (Stage 3 assessment, Jan 2004) Appraisal Summary Table (REV 2) A2 / A282 Dartford Improvement Option: Description: Problems: Junction needs improvement and A2 needs widening to avoid peak period Present Value of Costs to Government £70.4m (all costs are 1998 values discounted to 1998) QUALITATIVE IMPACTS QUANTITATIVE ASSESSMENT ASSESSMENT No properties would experience an increase in noise levels in the Design Year (2022) due to use of low noise surfacing, mounds and fencing. 51 properties would experience a reduction in noise levels of between 0.7 and 7.5 dB(A), 20 of which would experience a reduction greater than 3 dB(A). Without the Scheme, use of low noise surfacing in the Design Year would mean 45 properties would experience a reduction of between 1 and 3dB (A). No. of properties experiencing: 30 less people highly annoyed in 2022 Improvement comprising free flow links for E-N, N-E and W-N movements. Includes 3 multi-span viaducts and 4 further interchange bridges. Also includes 2km of A2 widening between M25 and Bean. OBJECTIVE SUB-OBJECTIVE Noise Environment Increase in noise 0 Decrease in noise 51 Local Air Quality Local air quality is poor particularly in close proximity to the A2 and A282. ‘Cleaner’ vehicles in the future are likely to contribute to an improvement in air quality. Nevertheless anticipated improvement overall would be less with the Scheme when compared to Do-Minimum Scenario. Greenhouse Gases Overall CO2 emissions from the road network will increase slightly over the period 2007 to 2022 as a result of increased traffic flows. This broad assessment does not take into account the likely benefits due to the reduction in congestion at the junction. Landscape Degraded urban fringe landscape, existing motorway/link road/junction screened by mounding and planting. ‘4 tier’ to Junction 2 visible. Not applicable Slight Adverse Townscape Not applicable Not applicable Not applicable Heritage of Historic Resources Deterioration to the setting of listed buildings and Scheduled Ancient Monument at Hawley Manor and reduction in the completeness of later prehistoric and Roman remains. Not applicable Slight Adverse Biodiversity No direct impact on designated sites, but indirect effect on Darenth Wood SSSI, calcareous grassland, hedgerows of county significance and potential disturbance to Dormouse habitat. Not applicable Moderate Adverse th No. of properties experiencing: 27 properties – Better air quality 64 properties – Worse air quality Weighted property concentrations (opening year): PM10 +1780.2μg/m3 NO2 +2344.60μg/m3 Not applicable Increase in greenhouse gases as a result of the Scheme in Year 2022 of +5187 tonnes/year = +9.5% Water Soakaways relocated and/or replaced with balancing ponds. Enhanced pollution control facilities before discharging into river. Not applicable Slight Beneficial Physical Fitness No change to distances cycled or walked Not applicable Neutral Journey Ambience Less congestion and stress reduced due to improved signing Not applicable Slight Beneficial Accidents Improved junction layout to deal with peak-time queuing problem on A2 and M25 should improve safety. (Figures include accidents saved in Kent Thameside and exclude accidents during maintenance and construction) Accidents -77 Deaths 0 Serious -3 Slight -103 Safety Security Proposed CCTV coverage at Junction 2 Not applicable Transport Economic Efficiency Provides positive benefits in both high and low growth forecasts Public Accounts PVB =£1.3m (£0.8m if maintenance and construction accidents are included) Slight beneficial Central Govt PVC = £70.4m Users PVB = £54.3m TEE Bus users and Transport Providers T’prt P’vders PVB = £2.4m Economy Accessibility Integration TEE consumers Users PVB = £50.4m Reliability Scheme should improve reliability due to improved flow through M25 J2 Not applicable Moderate beneficial Wider Economic Impacts Improve access from M25 and A2 to regeneration areas in Kent. Vital for the future development of Kent Thameside. Serves designated regeneration area? Development depends on scheme Yes No Option Values No effect Not applicable Neutral Severance Severance already caused by existing junction. Not applicable Neutral Access to the Transport System Benefits to existing network, increased opportunities for public transport initiatives not assessed. Not applicable Neutral Transport Interchange Forms integral part of public transport based strategy for Kent and Thameside development. Not applicable Moderate Beneficial Land-use Policy Some loss of good agricultural land which is against local and national policy objectives Not applicable Adverse Other Government Policies Direct and indirect effect on Green Belt, nature and heritage conservation designations which is contrary to local and national policy objectives Not applicable Adverse 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 127 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Table D.2 – Appraisal Summary Table: A2/A282 Dartford Improvement (ECI Phase 2 with Link E deferral, Jan 2004) Changes highlighted Appraisal Summary Table (REV 2) A2 / A282 Dartford Improvement Option: Description: Problems: Junction needs improvement and A2 needs widening to avoid peak period congestion Present Value of Costs to Government £102.2m (all costs are 2002 values discounted to 2002) QUALITATIVE IMPACTS QUANTITATIVE ASSESSMENT ASSESSMENT No properties would experience an increase in noise levels in the Design Year (2022) due to use of low noise surfacing, mounds and fencing. 51 properties would experience a reduction in noise levels of between 0.7 and 7.5 dB(A), 20 of which would experience a reduction greater than 3 dB(A). Without the Scheme, use of low noise surfacing in the Design Year would mean 45 properties would experience a reduction of between 1 and 3dB (A). No. of properties experiencing: 30 less people highly annoyed in 2022 Improvement comprising free flow links for E-N, N-E movements. Includes 3 multi-span viaducts and 4 further interchange bridges. Also includes 2km of A2 widening between M25 and Bean. OBJECTIVE SUB-OBJECTIVE Noise Increase in noise 0 Decrease in noise 51 Local Air Quality Local air quality is poor particularly in close proximity to the A2 and A282. ‘Cleaner’ vehicles in the future are likely to contribute to an improvement in air quality. Nevertheless anticipated improvement overall would be less with the Scheme when compared to Do-Minimum Scenario. Greenhouse Gases Overall CO2 emissions from the road network will increase slightly over the period 2007 to 2022 as a result of increased traffic flows. This broad assessment does not take into account the likely benefits due to the reduction in congestion at the junction. Traffic which would have previously used link E will now flow onto a temporary Link located on the existing roundabout, which does not result in traffic flow change to any other road links. Therefore, the assessment score does not alter with Link E omitted from the scheme. Not applicable Increase in greenhouse gases as a result of the Scheme in Year 2022 of +5187 tonnes/year = +9.5% Landscape Degraded urban fringe landscape, existing motorway/link road/junction screened by mounding and planting. ‘4th tier’ to Junction 2 visible. Not applicable Slight Adverse Environment No. of properties experiencing: 27 properties – Better air quality 64 properties – Worse air quality Weighted property concentrations (opening year): PM10 +1780.2μg/m3 NO2 +2344.60μg/m3 Townscape Not applicable Not applicable Not applicable Heritage of Historic Resources Deterioration to the setting of listed buildings and Scheduled Ancient Monument at Hawley Manor and reduction in the completeness of later prehistoric and Roman remains. Not applicable Slight Adverse Biodiversity No direct impact on designated sites, but indirect effect on Darenth Wood SSSI, calcareous grassland, hedgerows of county significance and potential disturbance to Dormouse habitat. Not applicable Moderate Adverse Water Soakaways relocated and/or replaced with balancing ponds. Enhanced pollution control facilities before discharging into river. Not applicable Slight Beneficial Physical Fitness No change to distances cycled or walked Not applicable Neutral Journey Ambience Less congestion and stress reduced due to improved signing Not applicable Slight Beneficial Accidents Improved junction layout to deal with peak-time queuing problem on A2 and M25 should improve safety. (Figures include accidents saved in Kent Thameside and exclude accidents during maintenance and construction) Accidents Safety Security Proposed CCTV coverage at Junction 2 Not applicable Transport Economic Efficiency Provides positive benefits in both high and low growth forecasts Public Accounts -77 Deaths 0 Serious -3 Slight -103 PVB =£1.5m (£0.9m if maintenance and construction accidents are included) Slight beneficial Central Govt PVC = £102.2m Consumer Users PVB = £73.326m TEE Bus users and Transport Providers Private Sector P’vders PVB = £16.550m* Economy Accessibility Integration TEE consumers Business Users PVB = £89.123m* Reliability Scheme should improve reliability due to improved flow through M25 J2 Not applicable Moderate beneficial Wider Economic Impacts Improve access from M25 and A2 to regeneration areas in Kent. Vital for the future development of Kent Thameside. Serves designated regeneration area? Development depends on scheme Yes No Option Values No effect Not applicable Neutral Severance Severance already caused by existing junction. Not applicable Neutral Access to the Transport System Benefits to existing network, increased opportunities for public transport initiatives not assessed. Facilitates access to Ebbsfleet International Rail Station and to regeneration areas Not applicable Neutral Transport Interchange Forms integral part of public transport based strategy for Kent and Thameside development. Not applicable Moderate Beneficial Land-use Policy Some loss of good agricultural land which is against local and national policy objectives Not applicable Adverse Other Government Policies Direct and indirect effect on Green Belt, nature and heritage conservation designations which is contrary to local and national policy objectives Not applicable Adverse *These figures corrected from AST entries with apparent typos (Private sector providers - $16550m Business users £89123m) 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 128 Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Table D.3 – Appraisal Summary Table: M25 J1b – 3 widening (2006) Appraisal Summary Table Date: 1/12/06. Stage 3 - Version IFU Rev 1 Option: Description: Widening from three to four lanes in each direction between the south facing slip roads of M25 J2 and the north facing M20 link road merge/diverge at J3. The southbound carriageway of M25 to be widened from two to three lanes between J1b and M25 J2 southbound slip road. Lighting 2 from J2 to J3. Additional land available for construction of vegetative treatment pond for surface water runoff. This land measures approximately 6000m and is contiguous with the existing M25 Motorway Boundary Problems: Unpredictability of travel times. Lack of orbital routes around London. Need for access to Thames Gateway regeneration area. Present Value of Costs to Public Accounts QUALITATIVE IMPACTS QUANTITATIVE ASSESSMENT ASSESSMENT Noise Traffic flows on the Scheme would increase slightly resulting in an increase in annoyance for properties nearby. However, the introduction of environmental barriers at Hawley Road result in an overall reduction in population annoyed by noise. Parkwood Hall School is more than 400m from the proposed road alignment. It is not close enough to the Scheme for the noise change to have an effect on overall noise levels due to other existing roads dominating the noise environment at this location. In the Do-minimum 146 people will be subject to noise levels in excess of 69 dB LA10,18hr whereas with the Scheme 108 would be exposed to noise levels in excess of 69 dB LA10,18hr. This is a reduction of 38 people. Do-minimum (DM): est. 113 people likely to be annoyed by traffic noise in the longer term. Do-something (DS): est. 105 people likely to be annoyed by traffic noise in the longer term. Net reduction in estimated population annoyed: 8 Local Air Quality Traffic flows would increase slightly. Properties adjacent to the section of M25 between J1b and 2 before slip roads show very slight improvements in air quality due to speed changes. This area is within Dartford BC’s declared AQMA. Properties adjacent to the section of M25 before J2 slip roads and J3 show no discernable change in air quality. Some of these properties fall within Sevenoaks DC’s declared AQMA. Air quality would improve at 63 properties and deteriorate at 112 properties. Whilst an additional 3 properties (total 22) would be exposed to NO2 levels in excess of the Air Quality Objectives, contrary to PPS23, the change in concentration would be indiscernible compared to current levels. Greenhouse Gases Overall increase in vehicle flows would result in a slight increase in CO2 emissions. Landscape 1 Special Landscape Area and 2 Areas of Local Landscape Importance (ALLI) in the Study Area. Scheme would not detract from or be in conflict with existing features and landscape character of the area, although tranquillity and land cover across the area would be slightly affected. Proposed lighting would add to impact, with a change in night time landscape character from several visual receptors. Effects of lighting on the Kent Downs AONB would be slight as currently lit J3 intervenes. Slight adverse Townscape Although the Scheme would impact on housing at Hawley , in terms of views and increasing the dominance of major roads in the area, adverse impacts, this would be offset by mitigation with the installation of environmental barriers. Neutral Heritage of Historic Resources The scheme will have a negative impact on regionally important sites, but the actual extent of the impact is limited because of the width of the land take. Slight adverse Biodiversity No impact on designated sites. The reduction in the width of the soft estate as a result of scheme widening would contribute to a loss of habitat for reptiles and breeding birds however the biodiversity value of retained habitats would be enhanced through appropriate management. Slight adverse Water Water features in the study area are typical of the locality with a major aquifer (Chalk) providing abstraction water and the River Darent crossing under the M25. Provision of pollution control facilities, including spillage containment and oil interception at outfall locations, will result in improved pollution control resulting in a benefit in terms of protecting groundwater quality. Slight benefit Physical Fitness The health benefits would remain unchanged as there are no changes to the PROW network. Neutral Journey Ambience The proposals are beneficial in terms of anticipated reduction in traffic congestion, improved road layout, signage and lighting. However this is balanced by reduced lane width possibly causing increased fear of accidents. Neutral Accidents Increase in accident rate on M25 J1b – 3 as a result of increase in traffic from widening is more than compensated for by reductions in traffic on local roads from traffic reassignment to M25, resulting in monetary benefits and overall reductions in accidents. PVB £0.934m low growth, £4.221m high growth: average £2.58m. Security Would be slight benefit as CCTV is incorporated throughout M25 J1b to 3. Emergency call facilities would be improved compared to existing situation. Slight positive Public Accounts PVC does not include the anticipated value engineering savings which are reflected in the current Forecast Outturn Scheme Cost Estimate. PVC £66.828m low growth, £71.598m high growth: average £69.213m. Transport Economic Efficiency: Bus.Users & Transport Providers Scheme gives good value for money for business users. PVB £75.507m low growth, £171.236m high growth: average £123.4m. Transport Economic Efficiency: Consumers Scheme gives good value for money for consumers. PVB £51.239m low growth, £110.727m high growth: average £81m Reliability Reliability benefits assessed using the stress-based approach described in TAG Unit 3.5.7. This measures the change in stress by calculating the ratio of AADT to Congestion Reference Flow (CRF). Values of less than 0.75 indicate no stress to the road system. For the widening scheme, all reliability ratios are less than 0.75, & are less than for the Do-Minimum. This approach does not provide a direct quantification of changes in reliability or reliability benefits. Improved Journey Time Reliability Wider Economic Impacts Better journey time reliability would increase the labour pool for Kent Thames Side Regeneration Area. Average journey times between J1b and 3 would be reduced by 30-60 sec in 2008 and by 40-300 sec by 2023 relative to the baseline. The strategic nature of Scheme means it would have beneficial impacts for companies relying on distribution of goods, with wider benefits likely. It has been assumed in the quantitative analysis that only 10% of the jobs created in the Regeneration Area would be attributable to the Scheme. Many firms in existing and future business parks are transport reliant (e.g. logistics firms) and therefore improvements to highway capacity would be beneficial for their long-term future. Up to 303 jobs in the RA directly influenced by 2018. Up to 99 jobs for residents of the RA Up to 99 jobs for residents of the RA Option Values No options as part of scheme. Neutral Severance 5 footpaths run close to the proposed widening, and two cross over the M25, however none would be affected by the scheme. Neutral Access to the Transport System Although access to public transport systems (e.g. Ebbsfleet train station) is improved, the Scheme does not form part of a public transport route. Neutral On-line widening to 4 lanes, with discontinuous hard shoulders OBJECTIVE SUB-OBJECTIVE Environment Safety Economy Accessibility DM: 91,739 t/annum CO2. DS: 95,129 t/annum CO2. 3.7% increase in CO2 from traffic, compared with the DM scenario. Concentrations weighted for exposure: NO2 : +209.73 PM10: +126.65 3,390 t/annum more CO2 compared with Dominimum Transport Interchange Not applicable as no interchange facilities available between Junction 1b to 3 of the M25. Land-use Policy Proposals consistent with most plans/polices at national and regional level, supporting reduction in traffic congestion. Local policy objectives for protection of existing vegetation, habitat and heritage, and encouragement of limited lighting proposals not met by the Scheme, causing some adverse impacts. Neutral Other Government Policies Some unavoidable impacts on environment set out in documents by ODPM (now DfCLG). However some policies supported, such as maintenance of existing transport network capacity enhancement and improvements to key access routes to Kent Thameside. Neutral Integration . 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 129 Neutral £69m Neutral Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Table D.4 – Evaluation Summary Table A2/A282 Dartford Improvement A2/A282 Dartford Improvement OBJECTIVE SUB-OBJECTIVE QUALITATIVE IMPACTS Environment Noise Overall traffic impacts within 10% of forecast range, hence noise impact assumed as forecast As expected Local Air Quality Overall traffic impacts as expected hence noise impact assumed likewise, with no worsening in air quality in AQMAs. As expected Greenhouse Gases Increased emissions due to traffic growth above forecast Landscape Mitigation generally implemented as expected but it is too soon to evaluate planting impact on landscape As expected Townscape n/a - Heritage of Historic Resources Slightly less impact due to deferral of Link E As expected Biodiversity Mitigation seems to have been implemented as expected. Further information on success of species relocation needed in FYA As expected Water Mitigation seems to have been implemented as expected. As expected Physical Fitness Public rights of way are unaffected by the scheme and there is no new severance. As expected Journey Ambience New gantries and signage have improved driver information. Provision of more lanes and new junction layouts have generally improved journey times. Additional lighting will have improved night time driving conditions. As expected Accidents Annual accident saving much better than expected Security CCTV installed Transport Economic Efficiency Positive benefits for users, even based on narrow corridor only. Combined with M25 J1b- 3 scheme, BCR of 2.2 against forecast of 2.3 Reliability Reduction in journey time variability As expected Wider Economic Impacts Infrastructure provided to serve regeneration area. Recession means too early to assess impact on jobs As expected Option Values No impact - As expected Severance No impact - As expected Access to the Transport System Access improvements to Ebbsfleet International Station, employment opportunities and retail for car users - Transport Interchange - As expected Land-use Policy Slightly less impact on heritage policy from omission of link E As expected Other Government Policies - As expected Safety Economy Accessibility Integration 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx QUANTITATIVE ASSESSMENT 1349 tonnes net increase (11%) in 2009 8 accidents saved ASSESSMENT As expected Better than expected As expected 130 £170m PVB TEE As expected Slightly better than expected Post Opening Project Evaluation A2 / A282 Dartford Improvement & M25 J1b – 3 Widening schemes: One Year After Study Table D.5 – Evaluation Summary Table: M25 J1b – 3 widening M25 J1b – 3 widening OBJECTIVE SUB-OBJECTIVE QUALITATIVE IMPACTS Environment Noise Traffic flows are lower than forecast (possibly due to recession impacts) and improved noise mitigation than originally planned Better than expected Local Air Quality Traffic flows are lower than forecast (possibly due to recession impacts) Better than expected Greenhouse Gases Safety Economy Accessibility Integration QUANTITATIVE ASSESSMENT Increased emissions due to increased speeds, but as with appraisal, this does not fully consider the impact of reduced congestion 4% net increase, 727 tonnes in 2009 (over a narrower area than appraisal) ASSESSMENT As expected Landscape Mitigation generally implemented as expected but it is too soon to evaluate the success of the new landscape planting in screening and integration. As expected Townscape Mitigation generally implemented as expected. As expected Heritage of Historic Resources Impacts to settings of cultural heritage assets such as Listed Buildings and Swanley Conservation Area are considered to be minimal As expected Biodiversity No impact on designated sites, as predicted, and mitigation largely implemented as predicted although planting has not yet matured. As expected Water Improved water pollution control measures installed as expected. No monitoring data to confirm success As expected Physical Fitness Negligible change to one footpath. No new severance As expected Journey Ambience New gantries, improved signage, additional lighting all improve ambiance. Accidents Annual accident saving much better than expected Security CCTV installed As expected 6 accidents saved, J2-3 Better than expected As expected Transport Economic Efficiency Combined with A2/A282 scheme, BCR of 2.2 against forecast of 2.3 Reliability Reduced journey time variation, especially J3-2 northbound As expected Wider Economic Impacts Infrastructure provided to serve regeneration area. Recession means too early to assess impact on jobs As expected Option Values No impact - As expected Severance No impact - As expected Access to the Transport System Access improvements to employment and retail for car users - Transport Interchange - As expected Land-use Policy - As expected Other Government Policies - As expected 5084038/POPE A2 A282 M25 J1b-3 OYA final jul 2011.docx 131 PVB £161m narrow area only TEE As expected Slightly better than expected
© Copyright 2026 Paperzz