Item no +€DINBVRGH+ I5 ReDort no T H E C I T Y OF E D I N B U R G H C O U N C I L Legal Agreements: Model Section 75 Agreement Final Version - Planning Committee 13 May 201 0 1 Purpose of report 1.1 To inform Committee of the alterations made to the draft model agreement following a consultation exercise and to seek approval of the revised model agreement. 2 Summary 2.1 A draft model agreement was included in the Committee report of 3 December 2009 on legal agreement improvements. It was agreed that the model agreement would be put out to consultation. This report sets out the responses to this exercise and the resulting alterations made to this model agreement. 3 Main report Background 3.1 In September 2008 the Planning Agreements Team was audited by the Council’s Internal Auditing Service. The remit was to review the system in place for developer contributions and ensure that all contributions are formalised in agreements under section 75 of the Town and Country Planning (Scotland) Act 1997. 3.2 On 2 April 2009 a report was presented to the Audit Committee. It noted that there had been improvements made in this service area but also identified areas where further improvement was required. One of the identified improvements was the production of a model Section 75 agreement. 1 Model Legal Agreement 3.3 The Audit Committee identified the need to prepare a standard legal agreement in the interests of consistency and to aid monitoring. 3.4 It is not possible to dictate the terms of Section 75 agreements as they are voluntary agreements. However, the Council as Planning Authority is seeking to approve planning applications in compliance with its policies and there are benefits in setting out the Council’s preferred terms in advance. The preparation of a model agreement is provided as an aid in the preparation of legal agreements when required in connection with planning applications. 3.5 The provisions in this document are not exhaustive. They do not cover all of the circumstances in which contributions will be sought or other requirements that may be placed upon developers. It would not be possible to achieve this and instead it is considered more useful to identify the standard provisions that apply in most instances. It is accepted that the clauses provided will need to be amended to suit individual circumstances. 3.6 It is hoped that this document will be a useful tool in facilitating discussions on developer contributions and streamlining the process. It is intended as a means of making this aspect of the planning process clearer to all parties involved. Consultation Responses 3.7 A total of 164 invitations were made to various firms and bodies to take part in the consultation exercise. Seven written responses were received, amongst which there were responses from Solicitors, Architects and Designers, Registered Social Landlords, relevant professional bodies and planning consultants on behalf of their clients. 3.8 The model agreement has in general been welcomed by the respondents and by others who have been in touch to discuss the document but who have not provided a written response. Some of the consultation responses made reference to wider matters of policy or process, which are not relevant to the consideration of the model agreement. These issues will be considered in any wider review of policy or process. 3.9 The consultation exercise identified a number of useful points for consideration. These points and the responses to them are set out in Appendix 2. Alterations have been made to the model agreement where considered appropriate following consultations with other relevant functions. The final version of the Agreement is attached at Appendix 1 with the amendments underlined. 3.10 The benefits from this exercise and the changes made to the model agreement can be summarised as follows: 0 The incorporation of useful suggestions for improvements to both the introduction and the model agreement document, which have included new and revised clauses and definitions (see Appendix 2). 2 0 0 4 The opportunity to bring matters of importance and concern to the respondents to the attention of relevant colleagues in the planning and other functions involved. The responses received have given colleagues with policy responsibilities the opportunity to liaise with customers about the matters that have been raised, but which do not have a specific bearing on the terms of the current model agreement. Financial Implications 4.1 The effective negotiation and monitoring of section 75 agreements is important in ensuring that the Council is able to deliver infrastructure to meet the needs of development. This report identifies improvements designed for this area of work. There are no significant financial implications arising from this report. 5 Environmental Impact 5.1 This report is concerned with improvements made to the model section 75 agreement and not to any change in policy. It will not have any impact on the quality of development or the actual infrastructure delivered in conjunction with development. There is no resultant environmental impact. 6 Conclusions 6.1 The revised model agreement will make it clearer to all parties involved in the planning process what is actually included in a Section 75 agreement. It will be a useful tool in facilitating the negotiation of section 75 agreements. It is hoped that this document will help to streamline the planning process. 7 Recommendations 7.1 It is recommended that the Committee approves the revised model legal agreement (Appendix 1). Dave Anderson Director of City Development 3 Appendices Appendix 1: Revised Model Section 75 Agreement Appendix 2: Model Legal Agreement Consultation Response and Consideration Contacthe1 David Cooper 529 6233 Ian Williams 529 3752 Wards affected Allkity wide Single Outcome Agreement Supports National Outcome 1: We live in a Scotland that is the most attractive place for doing business in Europe. Supports Edinburgh Outcome: Edinburgh is a thriving, growing city with a high quality of life and environment and a prosperous economy. Supports National Outcome IO: We live in well-designed, sustainable places where we are able to access the amenities and services we need. Supports National Outcome 12: We value and enjoy our built and natural environment and protect it and enhance it for future generations Supports Edinburgh Outcome: Edinburgh’s natural and built environment is supported and enhanced. Background Papers The consultation responses, bar one where a request for anonymity has been made, are available on request. IW/FK/PLANCOM/Model S75 Agreement 4 May 2010 4 APPENDIX I Model S.75 Agreement City of Edinburgh Council 2010 Contents lntroduction Pages 3-4 Section 1 - Title and Preamble Pages 5-6 Section 2 - Definitions Pages 7-14 Section 3 - Operative Clauses Pages 15-25 . Affordable Housing Pages 15-19 Education Page 20 Tram Page 21 Transport Pages 22-25 Section 4 - General Clauses Pages 26-28 2 Introduction This document has been prepared as the City of Edinburgh Council’s ‘model legal agreement’ under Section 75 of the Town and Country Planning (Scotland) Act 1997. It is provided as an aid in the preparation of legal agreements when required in connection with planning applications. The clauses contained in Section 2 - Operative Clauses, represent the preferred terms in which the Council will seek to enter into Section 75 agreements in relation to the Council’s policies that involve developer contributions. These policies are as follows; Affordable Housing; Developer Contributions for Investment in Schools; Tram Developer Contribution Guideline; and, Transport Requirements: Developer Contributions. Further notes on the way in which these policies are implemented via agreements are provided alongside each of the model clauses. These policies can be accessed in full using the Council’s website. Planninq Circular 1110: Plannninq Aqreements sets out Scottish Government policv on the use of aqreements made under Section 75 of the Town and Country Planninq /Scotland) Act 1997. This model Section 75 Aqreement takes into account the policv tests and principles set out in the Circular. The provisions in this document are not exhaustive. They do not cover all of the circumstances in which contributions will be sought or other requirements that may be placed upon developers. It would not be possible to achieve this and instead it is considered more useful to identify the standard provisions that apply in most instances. It is accepted that the clauses provided will need to be amended to suit individual circumstances for example; in connection with large developments the Council will usually be willing to phase large contributions. A Section 69 Agreement under the Local Government (Scotland) Act 1973 mav be acceptable provided 3 pavments are made at the r>oint of sisnina and before the release of Dlanninq permission. It is hoped that this document will be a useful tool in facilitating discussions on developer contributions and streamlining the process. It is intended as a means of making this aspect of the planning process, clearer to all parties involved. 4 Section 1 - Title Page and Preamble MINUTE OF AGREEMENT between THE CITY OF EDINBURGH COUNCIL, the Local Authority for the said City in terms of the Local Government etc. (Scotland) Act 1994, and having its principal office at City Chambers, High Street, Edinburgh (who and whose successors as the Planning Authority and Roads Authority respectively are hereinafter referred to as "the Council") and (ENTER COMPANY NAME) a Company incorporated under the Companies Acts, Company Number (enter company number) and having its Registered Office at (enter address) or (ENTER RSL NAME) registered under the Industrial and Provident Societies Acts a (Registered Number enter Scottish Charity (Registered Number enter )I ) and having its Registered Office at (enter address) (who with their respective successors in ownership of the Agreement Subjects as hereinafter defined are hereinafter referred to as "the Proprietors") 5 CONSIDERING (One) that the Council is the planning authority for the City of Edinburgh in terms of Section 1 of the Town and Country Planning (Scotland) Act 1997 (hereinafter referred to as "the 1997 Act"); (Two) that the Council is the roads authority for the City of Edinburgh in terms of Section 151 of The Roads (Scotland) Act 1984 (as said Section 151 is amended by Section 180 and Paragraph 135( I O ) of Schedule 13 to the Local Government etc. (Scotland) Act 1994); (Three) that the Council as planning authority is entitled in terms of Section 75 of the 1997 Act, to enter into an agreement with any person interested in land in its district (in so far as the interest of that person enables him to bind the land) for the purpose of restricting or regulating the development or use of the land, either permanently or during such period as may be prescribed by the agreement; (Four) that the Proprietors are heritable proprietors of the Agreement Subjects as hereinafter defined; (Five) that the Proprietors have applied to the Council for planning permission under the 1997 Act for the Development as hereinafter defined and the Council has resolved to grant said permission subject inter alia to an Agreement under Section 75 of the 1997 Act being entered into in the terms aftermentioned. NOW THEREFORE the parties hereto have agreed and do hereby agree as follows:- 6 Section 2 - Definitions “the Act“ means the Town and Country Planning (Scotland) Act 1997; “Affordable Housing means: Contracts” (a) a contract or contracts for sale by the Proprietors of land within or forming part of the Agreement Subjects for the purposes of constructing Affordable Housing Units; or (b) a contract or contracts entered into by the Proprietors for sale or lease of Affordable Housing Units to persons in housing need; or such other contract or contracts as may be agreed by the Council for the purposes of providing Affordable Housing Units; “Affordable Housing means that area or piece of ground forming part of Subjects” the Agreement Subjects and shown hatched in black on the Plan, or a site to be agreed by the Council and the Proprietors capable of accommodating the Affordable Housing Units; “Affordable Housing Unit” means a residential unit which is social rented housing, mid rent housing, shared equity housing, shared ownership housing, discount low cost sale, housinq without subsidv or other format of affordable housing tenure which is agreed by the Council as meeting the requirements of persons in housing need and which unit is constructed to Lifetime Homes Standard as defined in the Council’s document “New Build Target Standards - A Practice 7 Note on Design Quality in New Affordable Housing Development”, provided that, in the event that the agreed form of affordable housing units do not attract public funds in respect of their provision, the Council may waive or vary the requirement that such units be constructed to Lifetime Homes Standard; “the Agreement Subjects” means ALL and WHOLE land at [insert address here], Edinburgh, registered in the Land Register of Scotland under Title Number [insert number here]; (or enter Sasines Conveyancing description here) ‘Ithe Application” means the application for planning permission registered by the Council on [ enter date] under the Council’s reference (enter planning application reference) for the Development; “Bus Stop Improvements means the sum of (enter amount in words) Cont ribution” POUNDS (fenter amount) STERLING; “Citv Car Club Contribution” means the sum of (enter amount in words) POUNDS (fenter amount) STERLING; “ Co mmencement Date” means the date on which the Development is initiated by the carrying out of any Material Operation; “Commuted Sum for means the sum of [insert number here] POUNDS Aff o rda ble Ho using” (f[insert]) STERLING to be applied by the Council for the provision of Affordable Housing Units; 8 “Completion of Construction” means the issuinq of a Notice of Acceptance of Completion Certificate by the Buildinq Standards Department of the Council; “the Development” means the development consisting of [enter description of proposed development here] on the Agreement Subjects in terms of the Permission; “Discount Low Cost Sale” means a residential unit sold at a percentage discount of its open market value for households to persons in housing need; “Education Contribution” means the sum of (enter amount) POUNDS (f enter amount) STERLING towards alleviating accommodation pressures at School, Edinburgh. “Housing without subsidy” means non-subsidised Affordable Housing Units with conditions attached to the missives to maintain the units as Affordable Housing Units to subsequent purchasers, such purchasers being persons in housing need; “Index” means the All-in Tender Price Index firm figures as published by the Building Cost Information Service of the Royal Institution of Chartered Surveyors on a monthly basis, or if that ceases to be published or the basis upon which such index is calculated is substantially changed or rebased, such substitute or alternative index most likely to achieve an equivalent result as the parties may agree or, in the absence of agreement, as shall be determined pursuant to 9 Clause (arbitration) of this Agreement; “Indexed” means increased in accordance with the following formula:- bxc a Where: a equals the All-in Tender Price Index published as at the final date of signing of this Agreement, b equals the Index as at the date of payment of the relevant sum to be indexed, and c equals the relevant sum to be Indexed; “Material Operation” Has the meaning given in section 27 of the Act. For the avoidance of doubt, this definition excludes any material operation undertaken in terms of any valid planning permission granted before the date of the Permission; “mid rent housing” means housing with rents set at a level higher than social rented housing, but lower than market rent levels to meet the requirements of persons in housing need, such rent levels to be agreed with the Council, acting reasonably having regard to other schemes in Edinburgh and the Government auidance; 10 most recent “Off-site Affordable Housing means the landdarea known as (enter name of Subiects Site” subiects) and reaistered in the Land Resister of Scotland under Title Number (enter title number) or.. . .that area or piece of ground referred to as “Offsite Location” on the plan annexed and sianed as relative hereto which area of around forms part and portion of ALL and WHOLE (enter convevancinq description here2; “Open Market Housina” means the Residential units comprised in the Total Housina Units which are not Affordable Housing Units; “the Permission” means the planning permission for the Development subject to the conditions set out in the report on the Application to the Council’s Development Quality Sub-committee held on [enter date]; “persons in housing need” means persons with identified housing needs that would not be met by the normal operation of the housing market in terms of criteria set by the Council from time to time for low cost home ownership housing, mid rent housing and social rented housing or such other type of affordable housing units that may be agreed by the Council to constitute affordable housing tenure; I‘ Plan” means the plan annexed and signed as relative hereto; 11 “Registered Social Landlord” means a landlord registered under Section 57 of the Housing (Scotland) Act 2001 or their subsidiarv; “residentiaI unit” means any property within the Agreement Subjects constructed and designed for residential use of any sort and which term may apply individually or to a group of such units whether divided from one another either vertically or horizontally and which term also includes the Affordable Housing Units; “Road and Junction Means the sum of (enter amount in words) Improvements Contribution” POUNDS (f enter amount) STERLING; “Safer Routes to School Means the sum of (enter amount in words) Contribution” POUNDS (f enter amount) STERLING; “shared equity housing ” means the individual owner of a residential unit whilst bearing to own a 100% share of a residential unit owns a part agreed share with the remaining share secured to a registered social landlord or Scottish Ministers or other such landlord or body as may be approved by the Council; “shared ownership housing” means the individual owner purchases part of the residential unit, with the remaining share of the residential unit remaining in the ownership by a Registered Social Landlord. The individual owner pays rent for the share of the residential unit retained by the Reqistered Social Landlord. The Registered Social Landlord benefits from any equity 12 gain when the house is sold; “social rented housing” means property provided at an affordable rent owned, managed, leased or otherwise provided by a Registered Social Landlord (or such other body as maybe approved by the Council) to meet the requirements of persons in housing need; “Temporary TRO” means an order allowing for the Roads Authority/Council to temporarily restrict or prohibit the use of a road, or any part of a road, by vehicles or pedestrians; where works are being or are proposed to be carried out on or near the road and there is a likelihood of danger to the public or of serious damage to the highway. “Temporary TRO means the sum of (enter amount) POUNDS (f enter Contribution” amount) STERLING ; “Total Housing Units” means the total number of residential units which are permitted to be constructed on the Agreement Subjects in terms of the Planning Permission; “Tram Contribution” means the sum of (enter amount) POUNDS (f enter amount) STERLING; “Tram Project” means the proposals to construct and operate tram lines in Edinburgh including the provision of tram vehicles, tram stops, and all associated infrastructure, plant and equipment, as authorised by the Edinburgh Tram (Line One) Act 2006 and the Edinburgh Tram (Line Two) Act 2006 as may be amended from time to time; “Transferring Party” means a Proprietors whom has used all reasonable endeavours to transfer the Affordable Housing and to enter into Contracts, any other Affordable Housing and whom elects to transfer the ownership of the Affordable Housing Subjects to the Council for nil consideration; “Transport Contribution” means the sum of (enter amount) POUNDS (fenter amount) STERLING towards public transport infrastructure improvements in the vicinity of the Development; “Transport Improvement means works to be carried out by the Proprietors in Works” the vicinity of the Development, specifically (enter details of works to be carried out to local transport infrastructure here); “TRO Contribution” means the sum of (enter amount) POUNDS (f enter amount) STERLING; 14 Section 3 - Operative Clauses 3.1 AFFORDABLE HOUSING The requirement for affordable housing will be assessed through the application process. The Council’s guideline, Affordable Housing Policy is a key document in this respect. The usual arrangement between CEC and a Private Developer is that land for 25% of the residential units will be passed on to a Registered Social Landlord at nil value, before 30% of the market units have been completed. The Registered Social Landlord will normally then develop the affordable housing land. There are circumstances in which commuted sums and off-site provision will be acceptable. As a result clauses reflecting these arrangements are also provided. 3.1.I.On-site Affordable Housing (a) Twenty-five percent of the Total Housing Units shall be Affordable Housing Units, which units shall be constructed on the Affordable Housing Subjects; (b) The Proprietors will agree the following details with the Council before the Commencement Date:(i) the type of affordable housing tenure for the Affordable Housing Units; (ii) the location(s) of the Affordable Housing Subjects if not already agreed between the Council and the Proprietors; (iii) the design standards to which the Affordable Housing Units are to be built, which standards shall be agreed with the Council’s Housing Department (Services for Communities) and shall not be deemed to have been agreed by virtue of the grant of the Planning Permission or any other approval granted by the Council’s Head of Planning and Strategy; 15 (iv) the type of Affordable Housing Contracts by which the Affordable Housing Units are to be leased, sold or otherwise made available to persons in housing need whether by transfer of land or completed units to the Council, to a Registered Social Landlord or otherwise; c) The details agreed in Sub-clause (b) shall be implemented by the Proprietors to the satisfaction of the Council but may be varied by agreement of the Proprietors and the Council both acting reasonably at all times. d) The Proprietors shall use all reasonable endeavours to enter into Affordable Housing Contracts with the Council, or a third party nominated by the Council, prior to the completion of construction of twenty-five per cent of the Market Housing. e) The Proprietors shall use all reasonable endeavours to transfer the Affordable Housing Subjects to the Council or to a third party nominated by the Council, prior to the completion of construction of thirty per cent of the Market Housing. f) In the event that the Proprietors have been unable to enter into any other Affordable Housing Contracts in accordance with Clause 3.1 .I (d) prior to the completion of construction of twenty-five per cent of the Market Units, the Proprietors shall give notice to that effect to the Council and shall with any such notice provide the Council with evidence demonstrating that they have used all reasonable endeavours to transfer the Affordable Housing and to enter into any other Affordable Housing Contracts. If, following receipt of the said notice, the Council (being bound to act reasonably) confirms that it is satisfied that the Proprietors have used all reasonable endeavours as aforesaid, then the provisions of Clause 3.1.I(d) shall cease to apply and in that event the Proprietors shall continue to use all reasonable 16 endeavours to transfer the Affordable Housing Subjects to the Council, or to a Registered Social Landlord or to enter into any other Affordable Housing Contracts; provided always that no more than thirty per cent of the Market Units shall be permitted to reach completion of construction until such time as the Proprietors have entered into any other Affordable Housing Contract. g) If, following receipt of the said notice in accordance with clause 3.1.1 (f), the Council (being bound to act reasonably) confirms that it is satisfied that the Proprietors have used all reasonable endeavours as aforesaid, then the Proprietors shall have the option to transfer the Affordable Housing Subjects to the Council for no consideration. In the event that the Council cannot within 60 months of the exercise of such option enter into Affordable Housing Contracts to provide Affordable Housing Units or transfer them to a Registered Social Landlord the Council shall at the request of the party from whom the Council obtained ownership of the Affordable Housing Subjects (“the Transferring Party”) transfer the Affordable Housing Subjects back to that Transferring Party who shall be able to market them for the purposes of Market Housing. h) In the event that the Proprietors exercises the option referred to in Clause 3.1.1(g) the Transferring Party shall be bound to grant the Council or the third party nominated by the Council, as the case may be, a valid marketable title to the Affordable Housing Subjects. i) The terms of the conveyance of the Affordable Housing Subjects shall be agreed prior to the delivery thereof among the Council and the Proprietors and the third party nominated by the Council, as the case may be, declaring that the said conveyance shall contain the Proprietors’ absolute warrandice insofar as relating to the Affordable Housing Subjects and may, at the option of the Proprietors, contain a condition providing that the Affordable Housing Subjects shall be used 17 only for the provision of Affordable Housing Units. j) On the delivery of the duly executed conveyance of the Affordable Housing Subjects to the Council, or the third party nominated by the Council, the limits on the occupation of Affordable Housing Units contained in clause 3.1 shall cease to apply. N.B. For sites which are 100% RSL-owned the following sentence is to be inserted at Clause 3.1. I (b) 3.1.1 (b) The following clauses (b) to 0) inclusive shall only apply if the said Agreement Subjects are sold to a party other than a Registered Social Landlord as defined by the Housing (Scotland) Act 2001 as amended. 3.1.2 Commuted Sum for Affordable Housing The Proprietors will pay to the Council the Commuted Sum for Affordable Housing before the Commencement of Development on the Agreement Subjects. On the delivery of the payment of the Commuted Sum to the Council by the Transferring Party, the limits on the Affordable Housing Subjects contained in clause 3.1 shall cease to apply. In the event of the Commuted Sum for Affordable Housing not being utilised in full by the Council within ten years of the date of payment to the Council (or if phased payments the date of the last payment) for the provision of Affordable Housing Units the such contribution or the unused part thereof, as appropriate, shall be refunded to the Transferring Party following a written request from the Transferring Party for repayment. N.B. Where larger residential developments are proposed the Council may negotiate the payment of the Commuted Sum for Affordable Housing by way of instalments linked to phasing. 18 3.1.3 Offsite Affordable Housing The Proprietors will submit detailed proposals (or the Council and the Proprietors will reach an agreement regarding the terms and conditions that an offsite location must meet, in line with policy requirements) for the off-site provision of the Affordable Housing Subjects. The Proprietors will submit details of the Off-site Affordable Housing Subjects site where they are to be located to be approved by the Head of Services for Communities. Following receipt of the said approval, the Proprietors will deliver to the Council, or to a Registered Social Landlord approved by the Council, the whole title and interest in the Off-site Affordable Housing Subiects Site for nil consideration prior to the Commencement of Development on the Agreement Subjects. On the delivery of the duly executed conveyance of whole title and interest of the Off-site Affordable Housing Subiects Site to the Council, or the third party nominated by the Council, the limits on the Affordable Housing Subjects contained in Clause 3.1 shall cease to apply. 19 3.2 EDUCATION The requirement for a contribution towards school infrastructure will be assessed through the application process. The Council’s guideline, Developer Contributions for Investment in Schools is a key document in this assessment and identifies the circumstances in which contributions will be sought. The clauses below set out the way in which contributions should be delivered. In relation to large developments phased payments may be acceptable and will be paid at appropriate points in the construction programme. Education contributions should be indexed to the date of payment. 3.2.1 Education Contribution (a) Prior to carryi g out any M terial Operation/o xpation of any residential unit (delete as appropriate), the Proprietors shall pay to the Council the Education Contribution Indexed. (b) In the event of the Education Contribution paid under Clause (2.l(a)) hereof not being utilised in full by the Council within [fiveken] (delete as appropriate) years of the date of payment to the Council then such contribution or the unused part thereof, as appropriate, toqether with anv interest that has accrued thereon, shall be refunded to the Proprietors following a written request from the Proprietors for repayment. N.B. The decision as to whether the Council will hold the money for ten years or five years will be dependent upon the programme for delivery of school infrastructure and the need to identify further funding. 20 3.3 TRAM The requirement for a contribution towards the tram project will be assessed through the application process. The Council’s Tram Developer Contributions guideline is a key document in this assessment and identifies a number of contributions which may be sought. The clauses below set out the way in which contributions should be delivered. In relation to large developments phased payments may be acceptable and will be paid at appropriate points in the construction programme. 3.3.1 Tram Contribution Prior to the date on which the Proprietors Commence Development, the Proprietors shall pay to the Council the Tram Contribution Indexed to the date of payment, which Tram Contribution shall be applied towards the Tram Project. In the event that the Council decides not to proceed with the Tram Project or if the Tram Project has not commenced within ten years of the date of payment of the Tram Contribution, the Council shall be entitled to use the Tram Contribution for the provision of alternative public transport improvements serving the Development. The Council shall on receipt of the Tram Contribution pay the Tram Contribution into a separate account held by the Council, which Tram Contribution shall be invested so as to earn the best rate of interest that can reasonably be obtained by the Council. In the event of the Tram Contribution not being utilised by the Council by 31 December 2020 then the Tram Contribution, together with any interest that has accrued thereon, shall be refunded to the Proprietors following receipt of a written request from the 21 Proprietors for repayment. 3.4 TRANSPORT The requirement for a contribution towards transport infrastructure will be assessed through the application process. The Council’s guideline, Transport Requirements: Developer Contributions is a key document in this assessment and identifies a number of contributions which may be sought. The clauses below set out the way in which contributions should be delivered. In most cases it is preferable for the developer to carry out the necessary works although in some cases the payment of a financial contribution will be acceptable. In relation to large developments phased payments may be acceptable and will be paid at appropriate points in the construction programme. 3.4.1 Transport Infrastructure Works Prior to first occupation of the developmentlfirst day of tradinghhe Commencement Date(delete as appropriate) the Proprietors will carry out and complete the Transport Improvement Works to the satisfaction of the Head of Planning 3.4.2 City Car Club Contribution The Proprietorsshall pay the City Car Club Contribution to the Council, which sum shall be applied by the Council towards the Edinburgh City Car Club to fund the provision of a City Car Club vehicle to be located within the vicinity of the Development and associated costs. The Contribution shall be payable in full prior to [first occupation of the Developmentlthe Commencement Date] (delete as appropriate). 22 3.4.3 Road and Junction Improvements Contribution (a) The Proprietors shall prior to the Commencement Date pay to the Council the Road and Junction Improvements Contribution to be applied by the Council towards the upgrading of the (enter details) Road/ (enter details) Road signalised junction. 3.4.4 Bus Stop Improvements (a) Prior to the Commencement Date the Proprietors shall pay the Bus Stop Improvements Contribution to the Council, and the Council will apply the contribution towards bus stop improvements and in particular the part cost of a new bus shelter in the vicinity of the Development . 3.4.5 Safer Routes to School (a) Prior to the Commencement Date The Proprietors shall pay the Safer Routes to School Contribution to the Council, and the Council will apply the contribution towards the Council’s Safer Routes to School programme for improvements to cycling and walking routes to (enter name) School/Acade my. 3.4.6 Vehicle and Pedestrian Movements (a) Upon the Commencement Date the Proprietors shall pay to the Council the Transport Contribution Indexed, from the last date of signing of this Agreement which Contribution shall be applied by the Council towards improvements to vehicular and pedestrian movements at (enter location address), Edinburgh and the surrounding road network. 23 3.4.7 Temporary TRO and TRO Provision Prior to the Commencement Date, the Proprietors shall pay to the Council the TRO Contribution, which Contribution shall be applied by the Council towards the promotion of a Traffic Regulation Order for the purpose of [introducing loading and waiting restrictiondthe redetermination of a road/the installation of a traffic management system] (delete as appropriate) on/at (delete as appropriate) (enter location address), Edinburgh; or Prior to the Commencement Date, the Proprietors shall pay to the Council the Temporary TRO Contribution, which Contribution shall be applied by the Council towards the promotion of a Temporary Traffic Regulation Order for the purpose of [introducing loading and waiting restrictiondthe re-determination of a roadthe installation of a traffic management system ](delete as appropriate) on a temporary basis on/at (delete as appropriate) (enter location address), Edinburgh. 3.4.8 Standard Clause for Re-payment of Contributions In the event of (One) the Planning Permission being refused, revoked or in any way falling; or (Two) the Contribution not being utilised, or fully utilised, by the Council within fivehen years of the Payment Date, then following a written request from the Proprietors, the Contribution or the unused part thereof, together with any interest that has accrued thereon, as appropriate, shall be refunded to the Proprietors. 24 3.4.9 Travel Plans [Within three months of commencement of demolition works in implementation of the Development/Prior to use being taken up/Prior to first occupation of/Prior to the Commencement Date] (delete as appropriate), the Developer shall submit a draft Travel Plan in respect of the Agreement Subjects (“the Plan”) to the Council for approval. The Council shall have a period of not exceeding six months from its receipt of the Plan to approve or reject the same (with written reasons therefore). In the event of the rejection of the Plan by the Council, either party shall have the right to require that the matter is referred to an arbiter in terms of Clause (enter number of arbitration clause). Following approval or determination of the Travel Plan, the Proprietors shall (or shall procure that any person holding a lease of the Development or any part thereof from time to time) shall (i) publicise the Travel Plan appropriately to the satisfaction of the Council, acting reasonably; and (ii) implement the terms of the Travel Plan within six months of [the first occupation of/the first use of the development] (delete as appropriate). 25 Section 4 - General Clauses 4.1 DISCHARGE (a) If so requested in writing by the Proprietors, the Council agrees to grant a partial or full Discharge of the Promietor’s obliqations (enter here a reference to the clauses which contain the Proprietor’s obliqations) under this Agreement on due Performance bv the Proprietor of its obliqations hereunder. Further in the event of the Planning Permission granted pursuant to this Agreement being revoked or in any way falling these presents shall fall and be deemed pro non scripto and the Council shall grant a Discharge of this Agreement. The Proprietors shall be responsible for the Council’s reasonable legal expenses and outlays properly incurred in the negotiation, drafting, preparation, completion and registration of any Discharge hereto. 4.2 VARIATION (a) Without prejudice to Clause (refer to Discharge clause) hereof in the event of the parties hereto agreeing to a variation of the terms hereof the Council shall grant a Discharge of this Agreement and the parties shall contemporaneously enter into a fresh agreement in terms identical to the terms of this Agreement subject only to any variations as may be agreed between the parties hereto. The Proprietors shall be responsible for the Council’s reasonable legal expenses and outlays properly incurred in the negotiation, drafting, preparation, completion and registration of any Discharge or variation hereto. 26 4.3 ASSIGNATION (a) The Proprietors shall not transfer or assign their rights and obligations under this Agreement or dispose of their interests in the Agreement Subjects prior to the recording of this Agreement in the Land Register of Scotland. 4.4 ARBITRATION (a) Any dispute of any kind which may arise between the parties hereto and their successors regarding this Agreement shall be referred to the decision of an Arbiter to be mutually agreed by the parties and failing agreement appointed by the Sheriff Principal of Lothian and the Borders at Edinburgh on the application of any party and the decision of such Arbiter, including any award of expenses, shall be final and binding on the parties and failing such award the cost of any such arbitration shall be borne equally by the parties. 4.5 ENFORCEABILITY (a) This Agreement is made pursuant to Section 75 of the 1997 Act and it is agreed by the Council and the Proprietors that the obligations undertaken by the Proprietors in this Agreement shall be enforceable at the instance of the Council as planning and roads authority against the Proprietors and persons deriving title to the Agreement Subjects or any part thereof from the Proprietors. 27 4.6 REGISTRATION (a) The parties consent to registration hereof for preservation and execution. 4.7 EXPENSES (4 The Proprietors shall meet the Council’s reasonable legal expenses and outlays properly incurred in the negotiation, drafting, preparation, completion and registration of this Agreement, to include the provision of two Extracts of the Agreement for the Council’s own use: IN WITNESS WHEREOF 28 MINUTE OF AGREEMENT under Section 75 of the Town and Country Planning (Scotland) Act 1997 between THE CITY COUNCIL OF EDINBURGH and Subjects:- FAS: 1245 Alastair Maclean Head of Legal and Administrative Services Corporate Services City of Edinburgh Council Waverley Court 3: 1 4 East Market Street Edinburgh EH8 8BG 29 , Edinburgh APPENDIX 2 Model Legal Agreement Consultation Response and Consideration Response Issue Response Consideration The definition of “Affordable Housing” should incorporate all types of affordable housing and all types mentioned in the document should have a definition. Agreed and incorporated Considered inappropriate to have two standards to which housing is designed (one for affordable housing and one for market sector housing). A common standard should be set through the Building Regulations and the definition of “Affordable Housing Unit” should be amended in line with this. This is not a matter which can be considered within this model agreement at the present time, but is a policy matter outwith its remit. It is a model which can be altered as and when necessary. For the purposes of clarity “Mid Rent Housing” rent levels should be defined either in terms of Scottish Government Guidance or other such appropriate guidance in place at the point of entering any agreement. Agreed with the preference for “most recent guidance” given this model agreement is a template and this would allow it to incorporate any changes in the guidance. Within “Shared Ownership” definitions Agreed and change incorporated. the purchaser does pay rent for the share retained by the RSL. Affordable Housing general Comment:- within the agreement model there is a potential for the lack of integration of the affordable The model agreement in itself will not secure the integration of the affordable housing. This will be considered prior to the determination 1 elements within an overall development. Consideration should be given to section 3.1 to ensure that the affordable housing is fully integrated within a development proposal. of the application by the Committee or the Development Management function. The model agreement should make the process of agreeing the first draft of the agreement much quicker than was possible previously. Agreeing the type of affordable housing tenure prior to the ‘Commencement Date” (3.1.1(b)) is too late in the process and may preclude obtaining affordable units through no grant funded options. Establishing whether grant funding is available should be made earlier in the process so as other options can be considered and accounted for in developers appraisals. This is particularly important in an environment of reduced public expenditure. Establishment of grant availability should be undertaken prior to lodgement of a planning application . Agreeing the Affordable Housing tenures prior to the commencement date is considered to be the earliest meaningful trigger point within the model agreement. Before that date would in effect be prior to the concluding of the agreement or prior to the agreement taking effect. In practice it is often agreed well before this, which would mean that it has been agreed prior to the commencement date. Consideration of public subsidy / funding is not a matter for the model agreement. The term Registered Social Landlord should be amended to read “Registered Social Landlord or their subsidiary” as RSL’s require to undertake mid market rent and shared equity through a subsidiary company. Agreed and alteration made The methodology for calculating the Affordable Housing Commuted Sum should be included in section 3.1 2. The Commuted Sum is reviewed annually so should not be included in the template as each case will be different. However, the overall sum should be added on a case by case basis. The draft model agreement refers to the use of the commuted sum within 10 years, whereas CEC policy guidance states the Council should be confident the commuted sum can be spent within 5 years. The time The Affordable housing Policy Guidance is as it says a guidance document. It is as pointed out stating that the Council is confident that the sum will be used within 5 years. This does not mean that it can guarantee 2 scales should be the same. the use within this period. A legal agreement will be setting out a definite period of use. Consideration is therefore to be given to revising the guidance to 10 years so that the timescales will be the same. There will therefore be no change to the model agreement. The affordable Housing clause (3.1.2) should make clear that commuted sums can only be spent on providing affordable homes within the same area of the city as per CEC Affordable Housing Policy Guidance. Guidance on what is the nearest available applicable site has changed (Committee Report of 25/02/2010 for Commuted Sums and 06/08/2009 for offsite provision). These matters would be considered individually during the planning application process. The eventual requirement would then be set out in the concluded agreement and cannot be specifically set out in this model agreement. The affordable Housing clause (3.1.3) should stipulate that offsite provision should be made in the same area of the city to ensure that balanced mixed tenure communities are created. The Guidance has been redefined in report of 06/08/2009. It could change again in the future and has not therefore been included in this model Agreement. Non grant assisted affordable housing units not mentioned in the model agreement and greater guidance should be provided by the Council on the appropriate levels of discount which should be stated in the agreement. The model agreement is provided as a method of hopefully speeding up the first draft of the eventual agreement. It is not intended as an additional guidance document. The provision of unsubsidised affordable housing can be discussed during the consideration, consultation and determination of the application, prior to the conclusion of the agreement. The requirement for properties to be “affordable” in perpetuity should be removed as it is believed to be a blockage to developers in terms of delivering non-grant aided affordable housing through an RSL. Restricting title could “trap” purchasers in a These are matters of policy to be considered separately from the present model agreement. However, keeping these units affordable in perpetuity is the justification for that policy. Whether or not anyone should be advised to purchase a discounted 3 discounted sale house. sale house or whether this means of affordable housing provision is appropriate is not a matter for this model agreement. Indexation of the Education contribution to the date of payment. Agreed with revision completed. Omission of 1 bedroom flats from the calculation of any Education contribution calculation and from any Safer Routes to School contribution. They are already omitted from the Education contribution calculation and in effect from the Safer Routes to School consideration, where a more appropriate contribution would be considered within the consultation for the planning application. No revision is required to the model agreement. Payment of a City Car Club contribution should be at first occupation and not at the commencement date as there will be no residents requiring them at the commencement date. The option to use the commencement date trigger point should be retained as setting up the city car club provisions can take some time and presumably the first occupiers would prefer to see them in place from the date they move in. The requirement for the contribution may have been triggered because of the parking provisions within the application proposal. The trigger points for the bus stop improvements and the safer routes to school contributions to become due should be set out in the model agreement. It is suggested they should be “prior to the commencement date”. Agreed and revision completed. Request that the Council consider exempting RSL’s from all financial contributions within the model agreement. These contributions are not grant eligible and would require private borrowing on the basis of the rental stream from the properties and rents charged cannot be raised to The Council cannot be seen to be giving RSL’s a competitive advantage in the market place. The payment trigger point within the concluded agreement can be set to reflect the necessary borrowing and the question of development viability can be discussed within the application cover these costs. These costs could preclude an RSL from developing sites. considerations before reaching the section 75 stage. It is not therefore relevant to this model agreement. It should be reflected that the issuing of the planning permission following the conclusion of the agreement will be granting a financial benefit to the developer (the RSL in this instance) in terms of an uplift in the value of the land. The term “in the vicinity” should be more clearly defined and in so doing would make the section 75 negotiation process more efficient. What is in the vicinity will vary from case to case and further defining it in the model agreement could in fact have the opposite effect of prolonging the negotiations. What is meant by this phrase could be agreed or considered during the application process and then passed on in the instructions to conclude the agreement. Developers do not have information as to when payments are received and therefore the model agreement should require the Council to make refunds rather than the developer having to raise notice to the Council. If the developer is the party who has paid the contribution, they will have a record of when they paid it. A section 75 has to be registered and in so doing it ties the agreement to the land. Any subsequent purchaser will be aware of the agreement and will enquire either from the seller or the Council whether any particular contribution has been paid and when. They to will then know when the prescribed timescale for the use is to lapse and trigger any repayment should they wish to claim it. ~~ Agreed and revision made accordingly to the introduction. Within the introduction reference is made to the use of Section 69 Agreements. Use of these agreements should be regardless to the size of developments and is most effective where the developer is willing to make payments prior to the release of the planning permission. 5 A question was raised over the necessity for the Council’s practice to seek a Solicitors guarantee as to the developer’s title prior to the agreement being recorded and registered. This is not a matter specifically relating to the model agreement. However, guarantees are required regarding the developer’s title and the obligation not to withdraw the application for registration, which can be done at any time up to the registration. This is significant as the planning permission is not issued unless and until the agreement is concluded. There must therefore be some guarantee against this requirement being circumvented . A comment was made that it would be useful for the model agreement to specify a maximum target number of days between the Council’s receipt of the concluded agreement, or of evidence of it’s recording or registration, and the issuing of the planning permission. Procedures are in place for the planning permission to be released as soon as possible following the receipt of such evidence of recording of the agreement for registration. It is not therefore considered necessary for such a target to be included within the model agreement. It has been the Council’s long Comment was made about the necessity for and/or the amount of the standing procedure to recoup their reasonable expenses in concluding legal expenses and outlays to be both section 69 and 75 agreements. recovered by the Council for The model agreement reflects this concluding an agreement under position and to that extent sets out clause 4.7. what is expected to be included with regard to this matter from the outset. In terms of the overall cost of any proposed development, these expenses are miniscule. It should be reflected that the issuing of the planning permission following the conclusion of the agreement will be granting a financial benefit to the developer in terms of an uplift in the value of the land. All proposed tram works have not yet commenced although obviously some parts have started. For the present the terms of this clause should remain unaltered. Clause 3.l(a) is obsolete as the tram works have commenced. 6 Where a development is 100% RSL owned this should obviate the requirement for section 75 control of affordable housing provision. The control still needs to be in place should the site be sold on or if the RSL should go out of business. No revision has therefore been made to the model agreement. It would be helpful if additional clauses were included to cover the Council’s likely requirements where the affordable provision is to be made by a non grant funded route and where an RSL is not involved. The clauses in the model agreement would accommodate an unsubsidised affordable housing agreement, with clauses being populated in detail when the time comes to produce the first draft. The definition of “Completion of Construction” required revision in line with current legislation and practice. Agreed and revision has been completed. Questions were raised over the wording of clauses 3.1 .l(d), (e) and (9) and what actions were meant to be undertaken by them. Clause (d) refers to the various contractual methods by which the affordable housing can be provided. Clause (e) refers specifically to the transfer of the land on which the affordable housing is to be built. In practice the developer is encouraged to engage with an RSL during the planning application consideration and in most cases it is the RSL who will carry out the negotiations with the developer with regard to these two clauses. Clause (9) is the backstop which says if all else fails then CEC (and not a third party) is allowed to step in and take ownership of the land. It was considered inappropriate to include specific trigger figures in clauses 3.1 1 (d) and (e) as these should be left for negotiation between the Council and the developer on a case by case basis. These figures reflect experience to date as acceptable trigger points for all parties. They are (in the context of the model agreement) starting points for negotiation, but at the same time not figures plucked from thin air. To comply with PAN 74 the transfer of A Local Plan Reporter in 2009 summed up the current transfer “Affordable Housing Subjects” and 7 “Offsite Affordable Subjects” should be changed from no consideration to their value for affordable housing purposes as determined by the District Valuer. arrangement as follows: In Edinburgh, by convention, affordable housing land has a nil value. No revision has been made to the model agreement. Recommendationthat “Discount Low Cost Sale” and “housing without subsidy” should be suitably referred to within the model agreement. Agreed and as suggested these have been referred to in the definition of “Affordable Housing Unit”. Recommendationthat the words “duly Agreed and alteration completed. executed” should be removed from clause 3.1.2 (b). Agreed and alteration completed. Comment was made concerning the legal drafting of clauses 3.1.3 (b) and (c) Standard clause regarding repayment Agreed and alteration completed. of transport contributions should apply to all contributions. The affordable housing commuted sum should only be paid where it is agreed as an alternative to on site provision. The model agreement includes the possibility of an affordable housing commuted sum should such a requirement result from the planning application consideration and is there to aid initial drafting. Off-site (affordable housing) provision needs to be defined. A definition has been included. No mention is made of pre application discussions and what legal form does the agreement between the Council and developers take? Pre application discussions take place prior to a planning application being made and before any decision to require a section 75 agreement is made. What is to be included in the agreement document is a decision resulting from the pre-application and application process. The model agreement does not therefore need to refer to the pre-application 8 discussions specifically. The eventual section 75 agreement is the legal form of agreement between the Council and the developer. The quality of the land to be used for affordable housing and the housing itself needs to be emphasized. The standard to which the homes are to be built is set out in the description of “Affordable Housing Unit”. The land on which the units are to be built has to be suitable for purpose as set out in the description of “Affordable Housing Subjects Site”. Obtaining a suitable quality of site and design is a matter for the preceding application and consultation process. In clause 3.1 .I(f) what is required by ‘reasonable endeavours’ may need to The word reasonable in these circumstances has legal ramifications. Due to the case law on this subject a definition would be complicated, probably lengthy and could tend to make the document non user friendly. It could also result in lengthy negotiations between respective lawyers over an agreed terminology, all of which is contrary to the intentions behind the model agreement. The clauses 3.1 . I (d) to (9) are a recipe for developers to use ‘delaying tactics’ in delivering affordable housing. The agreement clauses are a back-up to earlier discussion, which are encouraged during the application consultations and consideration. They are designed to ensure delivery. Clauses 3.1 . I (d) and (f) are slightly confusing and contradictory. There are two trigger points. After the first has been passed the proprietor or developer has to show to the Council that they have undertaken reasonable endeavours to have complied with clause 3.1 .I(b). These endeavours need to be continued until the second trigger point at which point they will need to have complied with clause (e) and if they have not then the back stop of clause 3.1 .l(g) 9 becomes relevant. The Council’s commitment to ensuring provision of sufficient affordable housing is eroded if (9) comes into play. During the planning application consideration and under clause 3.1.I (d) there is an opportunity for an approved RSL to find a deliverable solution. Sub-clause (9) ensures that the 25% affordable housing provision land is delivered, just that the land would firstly be delivered to the CounciI. The term ‘for no consideration’ needs to be defined. It is considered that the phrase needs no further clarification. The terms ‘valid marketable title’ and ‘warrandice’ need to be defined. These are commonly used legal terms, the definitions of which would lengthen and could further complicate this model agreement, contrary to the intentions of this document. Definitions have not therefore been provided for this reason. Clause 3.1.I(i) is confusing and as another possible get out clause for the developer unacceptable. If sub-clause (9) is utilised it is the land that is delivered (at no cost to the Council) and not the completed units. As this clause is there to ensure delivery of the required affordable housing units it is not unreasonable for the developer or proprietor to require a condition of the transfer to be that the land is then used for the purpose of delivering these required units. What is the significance of the ten year term within clauses 3.1.2. It is considered a reasonable period for the use of the sum given what is involved. The need for clauses 3.1.3 for off-site affordable housing is questionable if not unacceptable. The model agreement does not provide permission to consider off-site or commuted sum provisions. This is done by Committee or under delegated powers to the development 10 management function following consultation on and consideration of the planning application. This model agreement merely sets out a framework in which the detail can be added (by either party) in creating a first draft of a section 75 agreement that would then be subject to mutual agreement, but without which the planning permission would not be issued. The RSL should be in place before the development commences. The RSL is often in place before the commencement of development and the developer is encouraged to do this during the application and consultation process and prior to any agreement taking effect. There should be a diagram showing the various parties sequence, timing and options within the process. Such a diagram would be different in each case and it has been decided that this suggestion should not be incorporated in the model agreement. The term market housing should be marketable housing. A new definition “Open Market Housing” has been included. A clause should be added stating that the landowner shall cease to have any liability under the section 75 once their ownership has ceased. The preamble does refer to respective successors in title who will on purchase be aware of the remaining liabilities under the agreement (and who would be approached when a compliance trigger is reached). Clauses can be added on a case by case basis should further clarification on limiting liability be considered necessary, particularly following the implementation of legislature changes. There is no reference in the model agreement to the financial viability of 3 development and therefore question whether it accords with the intentions The question of financial liability (and therefore compliance with Circular 1/10) is considered within the planning application consultation and 11 of Circular 1 /I 0. consideration process. It is a decision following this process that is then forwarded into the conclusion of the eventual section 75 agreement. It is not a matter which therefore has to be referred to in this model agreement. Reference has been included in the The initiation of the draft model agreement predates Circular 1/2010. introduction to the model agreement. Reference should be made in the model agreement as to how it complies with this circular. The model agreement should explain how it will be reviewed to reflect any new guidelines relating to developer contributions . The introduction does state that the model agreement is not exhaustive and that it does not cover all the circumstances in which contributions will be sought. For the present and for the purposes of this document, it is considered more useful to identify the standard provisions in most instances. The point that this might need future review is noted. Flexibility for staged payments should be extended to all scales of development and this should be considered on a case by case basis. The model agreement does not preclude this degree of flexibility and is open for negotiation on a case by case basis, which is in fact standard practice. The tram contribution definition should make reference to how it is to be spent. This is in fact included in the clause 3.3.1(a). Within the “Transport Improvement Works” definition and in clause 3.4.4 “Bus Stop Improvements” the term in the vicinity of the development should be given a more precise meaning within concluded agreements on a case by case basis. This is a matter for discussion within the planning application process after which any decision can be incorporated within the concluded agreement. It is not a matter for alteration to this model agreement. It is suggested that the first paragraph The suggested revision has not been 12 in clauses 3.3 and 3.4 should be amended to make it sufficiently flexible in all scenarios. incorporated as it in effect removes the possibility of a payment before the construction programme becomes “ 0perat ionaI” . However , the model agreement is an intended first draft, which can be revised on a case by case basis. The tram contribution clause should not include a provision that it can be used for alternative public transport improvements serving the development should the Council not proceed with the Tram Project. The alternative use provisions have been accepted in a number of existing agreements, in which they have been considered “reasonable”. The works to all parts of the proposed tram networks have not commenced. The need for the contribution is as a matter of fact determined at the time of the application. Should circumstances change following the conclusion to any agreement there is a provision, included in the model agreement (clause 4.2), for a revision to be made which is jointly agreed by all parties. The “Transport Infrastructure Works Clause” should be amended to recognise other trigger points for undertaking the works for major phased developments. The model agreement refers to a preferred option, but again is open for revision on a case by case basis. The “Road/Junction improvements Clause” should include an undertaking that the Council has a specific timescale in which to complete the works. The contribution will be proportional to the development proposal to which it relates. This will not necessarily meet the total cost of the works, which in turn could be reliant on contribution(s) from other development proposals to which it also relates. The Council cannot therefore be tied to a specific time scale and legal commitment to carry out works for which they may not have funding at the time. However, there will be a timescale by which the contribution is to be used, after which a claim can be made for the contribution to be refunded. 13 Amend the ‘Vehicle and Pedestrian Movements” clause to specify the intended improvements. Within this clause (3.4.6) there is a set of brackets allowing an address to be inserted. On a case by case basis it could be agreed to use this to further specify the improvements. No further adjustment has been made to the model agreement. Definitions should be included for “Planning Application” and “Planning Permission” They are included respectively under definitions entitled “the application” and “the permission”. The model agreement should include a clause that it will not take effect until the planning permission is implemented. An amendment to the model agreement in these terms has not been considered appropriate. It could in effect restrict optional trigger points for the payment of contributions. Reference to any relevant supplementary guidance should be made in the text of the agreement. An amendment to the model agreement in these terms has not been considered necessary. I The agreement should indicate how contributions are to be used and refunded if applicable. The refunding provisions are found in clause 3.4.8. The model agreement does refer to how the contributions are to be used and is in any case open to revision on a case by case basis if further clarification is agreed. The requirement to pay the Council’s legal expenses is questioned with a suggestion that there should be a fixed ceiling to this. An amendment to the model agreement in these terms has not been considered necessary. Specific revisions can be agreed on a case by case basis. Terms for partial discharges should be included. Agreed and alteration completed. A question was raised that the model agreement makes reference to the fact that the Council is (in addition to the Planning Authority) the Roads Following legal advice it has been considered that reference to other legislation would not raise concerns as to whether the section 75 14 Authority in terms of the Roads Act, and whether by so doing the agreement was being used for a “planning purpose” or for some other purpose. Further, whether in the matter of enforceability, the Council in its role as Roads Authority is entitled to enforce the terms of the agreement. agreement is being used for planning purposes. The contribution or works required have been considered to have a planning purpose within the consideration of the planning application. The agreement is a contract between the Planning Authority and the developer and on the basis that the terms meet a planning purpose and are reasonable they should be enforceable. 15
© Copyright 2026 Paperzz