VERSION NON CONFIDENTIAL Addressing the adverse effects of market power A FINAL REPORT PREPARED FOR CREG March 2006 © Frontier Economics Ltd, London. i Frontier Economics | March 2006 Addressing the adverse effects of market power Executive summary.......................................................................................1 1 Introduction .........................................................................................5 2 Static concerns - range of mitigating measures...................................7 3 4 2.1 The range of possible contractual measures ............................................7 2.2 Rationale for contractual measures ........................................................ 10 2.3 Possible contractual measures................................................................. 10 2.4 Choice of contractual form ..................................................................... 12 2.5 Regulatory measures to support contractual measures ....................... 14 2.6 Contractual measures and security of supply........................................ 14 2.7 Treatment of existing contracts .............................................................. 15 2.8 Conclusions ............................................................................................... 17 The parameters of contractual measures........................................... 19 3.1 Introduction............................................................................................... 19 3.2 Volume and exercise price....................................................................... 19 3.3 Duration ..................................................................................................... 22 Data, methodology and scenarios......................................................25 4.1 Modelling market power using SPARK ................................................ 25 4.2 Overview of data....................................................................................... 26 4.3 Modelling methodology ........................................................................... 30 4.4 Scenarios for analysis................................................................................ 31 4.5 New entry and soft regulatory constraints ............................................ 35 Contents ii 5 6 Frontier Economics | March 2006 Results ................................................................................................37 5.1 Base case..................................................................................................... 37 5.2 Sensitivity: market entry........................................................................... 45 5.3 Sensitivity: variation in flow over the northern interconnector......... 49 5.4 Summary .................................................................................................... 49 Dynamic concerns – barriers to entry ................................................ 51 6.1 Barriers to entry......................................................................................... 51 6.2 Analysis of incentives to withhold sites................................................. 53 6.3 Possible policy options to address site availability............................... 54 6.4 Conclusion regarding sites....................................................................... 57 Annexe 1: SPARK gaming module .............................................................59 Annexe 2: Data ............................................................................................ 61 Contents iii Frontier Economics | March 2006 Addressing the adverse effects of market power Figure 1: Illustration of the effect of a contractual measure, for a given level of demand (an effective contractual measure)...................................................... 19 Figure 2: Illustration of the effect of a contractual measure for a given level of demand (ineffective contractual measure-insufficient volume)..................... 20 Figure 3: Illustration of the effect of a contractual measure for a given level of demand (ineffective contractual measure-highly uncompetitive market) .... 21 Figure 4: Winter marginal cost supply curve capacity by owner ............................ 26 Figure 5: Summer marginal cost supply curve capacity by owner ......................... 26 Figure 6: Demand adjustment for pumped storage ................................................. 29 Figure 7: Distribution of demand to be met by Belgium plant and the Southern I/C, 2007 ............................................................................................................... 29 Figure 8: Winter installed capacity by owner ( +1,500MW CCGT) ...................... 32 Figure 9: Summer installed capacity by owner ( +1,500MW CCGT) ................... 32 Figure 10: Winter installed capacity by owner ( +2,500MW CCGT).................... 32 Figure 11: Summer installed capacity by owner ( +2,500MW CCGT) ................. 32 Figure 12: Illustration of demand adjustment from different interconnector flows ................................................................................................................................. 33 Figure 13: Distribution of demand to be met by Belgium plant and the Southern I/C with 500 MW more exports to the North ................................................ 34 Figure 14: Distribution of demand to be met by Belgium plant and the Southern I/C with 500 MW less exports to the North ................................................... 34 Figure 15: SPARK price outcomes for different volumes of contract cover for a winter demand level of 12,000 MW .................................................................. 38 Figure 16: SPARK price outcomes for different volumes of contract cover for a winter demand level of 12,800 MW .................................................................. 39 Tables & figures iv Frontier Economics | March 2006 Figure 17: Average market price under a given volume of contract cover (assumed to be baseload) for the base case scenario ...................................... 40 Figure 18: Incremental benefit of an extra 200 MW of contract volume ............. 41 Figure 19: Central case product package (base case): Price outcome by demand level......................................................................................................................... 43 Figure 20: Central case product package plus 1 GW peak (Variant 2): Price outcome by demand level ................................................................................... 44 Figure 21: Average profit maximising price under a given volume of contract cover (assumed baseload) for the entry scenarios compared to the base case ................................................................................................................................. 46 Figure 22: Incremental benefit of extra 200 MW of contract cover for the +1,500 MW new entry scenario....................................................................................... 47 Figure 23: Incremental benefit of extra 200 MW of contract cover for the +2,500 MW new entry scenario....................................................................................... 47 Table 1: Virtual interconnector power plants ........................................................... 27 Table 2: Virtual interconnector power plants ........................................................... 27 Table 3: Base case scenario product mixes and average prices .............................. 44 Table 4: New entry scenario product mixes and average prices............................. 48 Table 5: Northern export scenario product mixes and average prices.................. 49 Table 6: Inventory of installed assets in Belgium ..................................................... 61 Table 7: Installed capacity by plant type .................................................................... 61 Table 8: Fuel prices, taxes and carbon costs ............................................................. 63 Table 9: Availabilities by plant type ............................................................................ 64 Table 10: Run or river and wind power station seasonal duration ........................ 65 Tables & figures 1 Frontier Economics | March 2006 Executive summary Previous studies of the Belgian wholesale market have indicated that Electrabel is a dominant player on the Belgian market. The supposition that Electrabel is indeed dominant is unlikely to be contentious, given the large share of generating assets in Belgium that are under its ownership and control and the limited import capacity. In the light of this, The CREG has asked Frontier Economics to advise on what measures, or combination of measures, could be used to mitigate Electrabel’s dominance and deliver a more competitive market. While the title of this report is “Addressing the adverse effects of market power” this study has not investigated whether there are, in practice, adverse affects arising from Electrabel’s dominant position. In order to take a view on this one would need to investigate Electrabel’s past and present conduct and this exercise was not included in our scope of work. Instead, this study has focused on what could be done to remove the ability or incentive that Electrabel might have to increase prices above the competitive level. Concerns as to the health of competition in a market can be categorised as either: • static concerns related to the extent of competition given the existing asset base; or • dynamic concerns that stem from any barriers to entry that prevent or hinder the competitive development of the market over time through new entry. While static concerns may be important in their own right, any adverse effects associated with these may be exacerbated if there are also dynamic concerns, preventing new entry from eroding such static problems as may exist. In this study we have been asked to look at measures to address both static and dynamic concerns. This report examines these measures from a purely economic perspective and does not address any of the legal aspects pertinent to their potential imposition, nor any detailed aspects of implementation. STATIC CONCERNS - RANGE OF MITIGATING MEASURES The Terms of Reference for this study invited us to investigate a wide range of potential measures1, including: • Virtual Power Plants (VPPs), which are options to call on power at a predetermined exercise price; 1 The CREG asked us not to investigate measures where Electrabel was required to sell any of its assets, requesting that we focus our attention on purely contractual measures instead of measures involving physical divestment. Executive summary 2 Frontier Economics | March 2006 • Power Purchase Agreements (PPAs) linking the sale of power to a specific asset; and • other long terms forward contracts. Following the inception of the study, members of the steering group also invited us to explore further possible measures, including contract swaps between Electrabel and a generator with capacity outside of Belgium. Since any of these measures could, in principle, be combined with any other in any quantity, there is a potentially infinite array of packages of measures, leading to an unmanageably large requirement for analysis. However, as we describe in Section 2, in practice all of these contract forms have a similar effect, i.e. they can decrease the extent to which a dominant firm would benefit from a rise in price as a result of the exercise of market power in respect of its remaining plant. As a result, these measures can be viewed as close substitutes for one another from an economic perspective. This equivalence means that we can conveniently model one type of instrument but can then interpret the results as being a requirement for a level of contract cover that can be met in a wide variety of ways. This aggregate requirement for contract cover could be met in any way that Electrabel found convenient or expedient. This equivalence is explored further in Section 3, where we look at the three main parameters of contract cover: volume; shape; and duration. STATIC CONCERNS – MODELLING RESULTS We have used our SPARK model to analyse the possible effect on wholesale market outcomes of the introduction of measures to curtail Electrabel’s market power in the Belgian electricity market. Our modelling approach is discussed in Section 4 and the results presented in Section 5. Under our base case set of assumptions (described in detail in Section 4), we find that approximately 8 GW of contract cover would be effective in mitigating Electrabel’s incentive to exercise its market power. As noted, this aggregate requirement for contract cover could be met in any way which Electrabel found convenient or expedient. We also stress that the analysis we have conducted assumes that Electrabel has no other long term contracts, or other positions that might have the effect of such a contract (for example as a retail position with regulated tariffs). Should Electrabel have existing positions, then these should be netted off from any requirement identified in this report, in order to determine the remaining contract cover that would be needed to address Electrabel’s incentive to exercise market power. In addition we have also analysed cases where we assume that there is entry (incremental independent entry with a total volume of 1.5 GW and 2.5 GW) into the Belgian market. In the face of such entry our analysis suggests that the volume of contract cover required to mitigate Electrabel’s market power is reduced. With entry of 1.5 GW we would conclude that total contract cover could be reduced by at least 1 GW. With 2.5 GW, proportionately less contract cover would be sufficient. Executive summary 3 Frontier Economics | March 2006 Finally, we have analysed the effect of different patterns of import/export over the Belgium-Netherlands interconnector. With increased exports (by ~500 MW) to the Netherlands, contract cover of 8 GW is marginally less effective, but in our view remains sufficient to mitigate Electrabel’s incentive to exercise market power for the large majority of the time. In contrast, if exports to the Netherlands were to fall (by ~500 MW) then 8 GW of contract cover would be likely to be highly effective at mitigating Electrabel’s incentive to exercise market power and the extent of the contract cover could potentially be reduced. However, we recognise that this would be proportionately the largest capacity release programme by some margin, not only in Europe but world wide. This quantum should only be reached over enough time for markets and participants to adjust. Taking account of existing long term contract positions Our analysis has not included any other contracts (or positions that might have the economic effect of a contract) that Electrabel might have in place at present or might put in place. If Electrabel has in place, or could commit to having put in place, such contracts and/or positions, then they should be deducted from the volumes that we report. For example, if Electrabel already has in place contracts with customers of a reasonable duration at a fixed price for 1,000 MW of base load power, then our recommendation would fall from 8 GW to 7 GW, with the volume of baseload product required reduced by 1 GW to reflect this existing contract position. Similarly, if Electrabel were to have in place a peak load contract at a fixed price for 500 MW, this could be deducted from the required volume of peak load product. DYNAMIC CONCERNS – POLICY OPTIONS TO ADDRESS SITE AVAILABILITY One of the possible concerns that the CREG has identified as potentially restricting competitive new entry is the pattern of ownership of suitable sites for new generation. Specifically, the concern is that if all (or at least a very high proportion of such suitable sites) are owned or controlled by Electrabel, then Electrabel may be able to foreclose potential new entry by not making any of these sites available to would be new entrants. There is a range of possible policy measures that could theoretically be adopted either to provide Electrabel with incentives to release sites voluntarily or to require it to do so. These include: • enforced (or negotiated) release of sites; • a requirement to auction vacant sites; • revising the licensing regime to limit the scope for new build by Electrabel; Executive summary 4 Frontier Economics | March 2006 • resolution of existing issues of market power, thus possibly reducing the benefit of limiting entry; • putting in place a tax on vacant sites; and • using other methods to stimulate entry, such as offering centrally held contracts for the provision of new capacity (as has been done in Ireland for example) although this may formally need security of supply to be an issue. In order to assess which of these options might be preferred it would be necessary to conduct detailed analysis based on a range of data. This has not been possible as we have been unable to obtain the required information within the scope of this assignment. We understand through discussion with the CREG that Electrabel may have agreed with the Minister to release sites that would allow the construction of 1,500 MW of new entry. This understanding has prompted one of the sensitivities that we have modelled, as described above. However, we have not been provided with any details of this programme. Similarly, we have not been provided with any of the data that might have informed the design this arrangement. If a release of sites has been agreed with Electrabel and if this route remains open in the future, then it would seem to represent a useful approach to ensuring site release over time. We would advise that the effectiveness of the first step in this policy be assessed before any decision is taken as to whether further site release would be appropriate. Executive summary 5 Frontier Economics | March 2006 1 Introduction Previous studies of the Belgian wholesale market have indicated that Electrabel is a dominant player on the Belgian market. The supposition that Electrabel is indeed dominant is unlikely to be a contentious, given the large share of generating assets in Belgium that are under its ownership and control, and the limitation that exists on import capacity. In the light of this, The CREG has asked Frontier Economics to advise on what measures, or combination of measures, could be used to mitigate Electrabel’s dominance and deliver a more competitive market. In this report we present our findings on these topics, along with the methodology and data used in the analysis that led us to these conclusions. While the title of our terms of reference is “Addressing the adverse effects of market power” this study has not investigated whether there are, in practice, adverse affects arising from Electrabel’s dominant position. In order to take a view on this one would need to investigate Electrabel’s past and present conduct and this exercise was not included in our scope of work. Instead, this study has focused on what could be done to remove the ability and/or incentive that Electrabel might have to increase prices above the competitive level. Concerns as to the health of competition in a market can be categorised as either: • static concerns related to the extent of competition given the existing asset base; or • dynamic concerns that stem from any barriers to entry that prevent or hinder the competitive development of the market over time through new entry. While static concerns may be important in their own right, any adverse effects associated with these may be exacerbated if there are also dynamic concerns, preventing new entry from eroding any static problems. In this study we have been asked to look at measures to address both static and dynamic concerns. This report examines these measures from a purely economic perspective and does not address any of the legal aspects pertinent to their potential imposition, nor any detailed aspects of implementation. Our report comprises the following sections. | Section 2 identifies a range of contractual measures that have been mooted as having the potential to address market power and provides definitions for these. It then analyses from first principles the way in which contractual measures can affect the ability or incentive of a dominant player to exercise market power and, in the light of this analysis, reviews qualitatively the potential effects of the identified measures. This section is completed by a discussion of the extent to which non contractual measures could play a role in mitigating market power and the possible interaction between contractual and non contractual measures. Introduction 6 Frontier Economics | March 2006 | Section 3 having established the major role that contractual remedies would need to play, this section addresses the parameters that define the required contractual coverage (in essence volume, shape and duration). | Section 4 provides an overview of the data we have used in our analysis, together with the scenarios we have modelled. We also describe the steps that our analysis has followed in order to identify the appropriate volume and shape that any package of measures should have. | Section 5 presents the results of our analysis with our conclusions on the parameters of contract cover needed to address static market power concerns. | Section 6 discusses potential barriers to entry and in particular potential problems arising from the difficulty new entrants may have in procuring sites on which to build generating assets. We also include two annexes: | Annex 1 provides some further detail on the model we have used to analyse static market concerns, SPARK. | Annex 2 provides further detail on our data assumptions. Introduction 7 Frontier Economics | March 2006 2 Static concerns - range of mitigating measures The Terms of Reference for this study invited us to investigate a wide range of potential measures2, including: • Virtual Power Plants (VPPs), which are options to call on power at a predetermined exercise price; • Power Purchase Agreements (PPAs) linking the sale of power to a specific asset; and • other long terms forward contracts3. Subsequent to the inception of the study, members of the steering group also invited us to explore further possible measures, including contract swaps between Electrabel and another international player. Since any of these measures could, in principle, be combined with any other in any mix of quantities, there is a potentially infinite array of packages of measures, leading to an unmanageably large requirement for analysis. However, in practice, many of these potential measures have economic effects which are very similar indeed, and in many cases identical. This section of our report sets out our rationale for this and the consequences of this for both the study and our conclusions. We also consider in this section how regulatory measures might reinforce contractual measures, focussing on one specific proposal raised by the steering group. However, we begin by providing a definition of the main contractual measures that we have been asked to consider. 2.1 THE RANGE OF POSSIBLE CONTRACTUAL MEASURES Before proceeding with an economic analysis of the properties and effect of contractual measures, we first provide a brief definition of each measure. As we describe in more detail in Section 3, each contractual measure has a number of parameters that can be set to modify the impact of the contract(s). We provide a brief introduction to those parameters here. 2 The CREG asked us not to investigate measures where Electrabel was required to sell any of its assets, requesting that we focus our attention on purely contractual measures instead of measures involving physical divestment. 3 We note that long term contracts can, in certain circumstances, give rise to competition concerns. However, contractual measures would only function as intended if they are long term in nature. As is explained in a number of places in this report, any ability that Electrabel might have to increase prices for long term contracts beyond competitive levels should be undermined as long as the total package of measures to which it is subjected is substantial enough. Static concerns - range of mitigating measures 8 Frontier Economics | March 2006 2.1.1 VPPs VPPs are option contracts. The purchaser of a VPP pays a fixed sum, usually monthly, which confers the right, but not the obligation, to buy a specified volume of power at a specified exercise price for the duration of the contract. The seller of a VPP must deliver the required volume of power for the hours during which the VPP is exercised. A VPP is typically not linked to any physical asset. The seller of a VPP can therefore provide power sold under a VPP from any source. A VPP will be exercised whenever the market price (or expected market price) of power rises above the exercise price specified in the VPP. If a VPP is exercised then it will be typically be exercised for its full volume. However, buyers may exercise less than the full volume. The value of the VPP to the purchaser when it is exercised is equal to the volume multiplied by the difference between the market price and the exercise price. If the exercise price of a VPP is low enough, the VPP is certain to be exercised in all periods. In this case, the VPP will have the same effect as a baseload contract of the same duration for the delivery of a fixed volume at a predetermined price. If a generator sells a VPP contract, this will have the effect of reducing the profit of that generator from any given increase in the market price at times when the market price exceeds the VPP exercise price. In the absence of a VPP, the generator would receive the benefit of the price rise on the corresponding volume it is able to sell into the market. With a VPP in place, the generator receives the benefit of the price rise only on a smaller volume. . 2.1.2 PPAs In this report, when we use the term PPA, we refer to a contract that effectively provides physical control of a station to the purchaser through a carefully specified set of terms and conditions. PPAs of this kind are linked to a specified physical asset. PPAs are most common in developing countries where there are a small number of assets that are typically all under contract to a central power procurer, or during the early stages of liberalisation. The purchaser of a PPA has the right, but not the obligation, to take power from the station, usually at some predetermined price linked to the marginal price of the station. In this sense, a PPA resembles a VPP – it has a volume (i.e. the size of the station) and an exercise price (as determined in the contract). However, since a PPA is linked to a real asset, these contracts typically include terms setting out how the volume of power called is allowed to vary over the course of a typical day. Such terms are linked to the physical ramps rates of the asset to which the PPA is linked. PPAs will usually impose a cost on the purchaser for each time the generating unit is stopped and restarted. Similarly, PPA contracts also need to deal with periods where the station is unavailable due to either planned or unplanned maintenance. Static concerns - range of mitigating measures 9 Frontier Economics | March 2006 In addition to paying a marginal cost when the station is called, the purchaser of a PPA will also pay a capacity payment to the seller of the PPA, linked to the availability of the station. 2.1.3 Fixed long term contracts A fixed long term contract is an agreement that determines the sale of a given volume of firm power from the seller to the buyer in exchange for a fixed and pre-determined price4. Contracts of this kind are not associated with any particular physical asset. As such the power could be provided by any asset in a portfolio. Typically, fixed long term contracts are either baseload, in which case deliveries are continuous at the same level for every hour of the day, or peak load, in which case deliveries occur only during specified hours, when demand is typically highest. The hours of the day covered by peak load contract can vary according to the convention of the region (e.g. 7am to 7pm). A fixed long term contract of this kind has an effect similar to that of a VPP when it is called, i.e. the seller of the long term contract no longer benefits from price rises on the volume of power covered by the contract. While a VPP is given shape through the level of its exercise price, which will determine the periods when it is likely to be called, a fixed long term contract is given shape through the hours of the day when it operates. With appropriate calibration, the effect of either of these two contract forms can be replicated by the other. 2.1.4 Contract swaps The final form of contractual measure that we have been asked to consider is a contract swap. A remedy of this form involves the exchange of power in one country with that of power in another country with no price attached. For example, in theory Electrabel could agree to a swap with EDF, where EDF receives the right to some agreed volume of power in Belgium while Electrabel receives the same volume of power in France. In principle, a swap creates an obligation on each party to provide power in their own region to another party for a value which the party cannot influence. In return, they are given rights to a comparable volume of power in the other region. Again, the swap could be base load or peak load, as with a fixed long term contract. We do not envisage swap contracts being linked to specific physical assets, although this is, in principle, possible. The effect of a swap is therefore, likely to be similar to a simple long term fixed contract. 4 In principle the agreed price could be indexed to some exogenous price marker. As long as this price marker was unrelated to the wholesale price of electricity, this would still serve the same purpose as a fixed price. Static concerns - range of mitigating measures 10 Frontier Economics | March 2006 2.2 RATIONALE FOR CONTRACTUAL MEASURES Contracts can be used to create obligations such that Electrabel has a reduced incentive to try to raise the ‘market’ price of power. A dominant firm that has the ability to withdraw plant and raise prices, faces a trade-off. In withdrawing plant, the dominant firm loses any profit that it would have made on the plant that is withdrawn (we can think of this as the cost of exercising market power) but increases the profit from plant that continues to supply power (we can think of this as the benefit of exercising market power). It will have the incentive to withdraw plant if the extra profit from remaining plant exceeds the lost profit on the withdrawn plant (i.e. if the benefits of exercising market power exceed the costs). Contracts can be used to alter the nature of this trade-off and hence the circumstances in which it is profitable to exercise market power. In principle, a contract could be designed either to: • increase the profit lost in relation to the withdrawn plant (i.e. increase the cost of exercising market power); or • decrease the extent to which the firm benefits from the rise in price of power in respect of its remaining plant (i.e. reduce the benefit of exercising market power). For reasons which will become clear below, the latter has always been found to be much more practicable than the former. However, for completeness, we discuss both here. 2.3 POSSIBLE CONTRACTUAL MEASURES 2.3.1 Contracts to increase the profit lost on withdrawn plant Normally, when a plant is withdrawn, there are savings from not operating the plant. In theory a contract could: • decrease the cost reduction from not running the plant; or • introduce an explicit penalty for not running when it ‘should’. When an asset is withdrawn from the market, the owner of that asset no longer incurs the variable cost of operation while the asset is withdrawn. In principle, a contract could be designed that reduces this benefit of withdrawal, thereby increasing the cost of exercising market power. Hypothetically, one could offer the firm rights to subsidised fuel only exercisable if it used the fuel to generate from the plant. However, such subsidies would be neither desirable nor, in all probability, legal. Static concerns - range of mitigating measures 11 Frontier Economics | March 2006 Introducing a contractual penalty for not generating, which would also act to increase the cost of exercising market power, might be more feasible but there are many problems. In particular: • the penalty would have to apply only at the times when that plant should reasonably run on the system. Hence some mechanism would be needed to determine when the plant was wanted and when it was not; and • the penalty would need to be fair in the sense that it did not unreasonably penalise the operator for planned and forced outages that would arise if the plant were not controlled by a dominant firm. Neither of these are easy conditions to meet efficiently. Doing so could well mean moderating any penalty to a level at which it might not alter incentives enough to see a marked reduction in the incentive to exercise market power. It is also not clear who should be the counterparty for a contract based solely on a penalty for non availability. Penalties for non availability could be included within a classical station specific PPA contract where the buyer pays a capacity price and an exercise price based upon its nominations, receiving a penalty payment if electricity is not delivered. However, such contracts are most suitable in electricity systems based around the single buyer model where the buyer is worse off when delivery is not made from the specific station. Regions that operate a single buyer model typically have a central power procurer that has a suite of contracts with a number of different generators in that region. The power procurer therefore decides how these stations should be dispatched in order to meet the profile of demand over the day. In such circumstances, the power procurer is, effectively, playing the role of system operator. The power procurer needs to be sure that when a specific station is called upon to run then that station does actually produce the required power, otherwise it will need to take close to real time actions to ensure system stability and integrity. In order to provide a financial incentive for stations to run when called, contracts in environments such as this typically include a penalty clause that creates a cost for the generator when it fails to generate when called, i.e. a contract clause that increases the profit lost on withdrawn plant. The purchasers of power contracts in more developed regions, including Belgium, are typically retailers (or large consumers) who are completely indifferent as to where the power they consume is generated as long as it is made available. In such circumstances there is no obvious rationale for including a station specific penalty clause for failure to generate from a specific site. The purchaser of the contract will be happy to receive power from any source as long as it is delivered. This is discussed further in the context of station specific PPAs in Section 2.4.1 below. Static concerns - range of mitigating measures 12 Frontier Economics | March 2006 2.3.2 Contracts to decrease the profit from a price rise Any contract for the sale of electricity at a price that is determined independently from the ‘market’ price will reduce the incentive of the seller to raise prices because the seller benefits from the higher prices only in respect of the proportion of its sales not covered by such contracts. There is an infinite variety of contracts that could achieve this result, including all of the contractual forms identified above in Section 2.1. 2.3.3 Summary Given the discussion in the preceding subsections, it is seems clear that remedies focused on reducing the benefit of exercising market power, rather than those that increase the cost of exercising market power, are likely to be easier to design, implement and monitor. This is consistent with what we observe in those regions where such remedies have been imposed, where contractual remedies such as VPPs have typically been used. 2.4 CHOICE OF CONTRACTUAL FORM In Section 2.3 we have identified what we would like any proposed measure to achieve in terms of its affect on the incentives of any large player on which it might be imposed. When we consider the definitions provided in 2.1, it seems clear that any of the proposed measures would have a broadly similar effect. Here we explore further whether there are substantive differences between the measures we have described from an economic perspective. 2.4.1 Measures linked to physical assets Notionally, PPAs might appear to have the same effect as the other possible contractual remedies, together with the potential additional advantage that they could help to inhibit withdrawal of specific plant. If this meant that withdrawal to exercise market power could only be effected by withdrawing lower cost plant, it could increase the loss of profit on withdrawal and thereby have an additional beneficial influence on incentives. However, owing to their complexity, PPAs would be more costly to administer and it is not at all clear to us that purchasers would have either an interest in or the ability to police where the power comes from. The purchaser will request power from the station and expect the seller to make the corresponding block exchange notification to Elia. The purchaser will have no further interest or knowledge as to where the power actually came from or indeed whether the seller really produced the power at all. If there is no economic incentive to enforce an aspect of the contract, enforcement is unlikely to materialise. In practice, therefore, we believe that station specific PPAs would have little or no real advantage over the other possible contractual forms and they would be administratively more expensive. Similarly, it is likely that a PPA would have less Static concerns - range of mitigating measures 13 Frontier Economics | March 2006 appeal than some other contractual forms to a potential purchaser. For example, the purchaser of a PPA needs to deal with periods when the plant is unavailable, whereas other contractual forms are typically for firm power. Given this analysis, it is not clear that a PPA is necessarily a better measure from the perspective of a market regulator or from the perspective of a potential purchaser. 2.4.2 Firm contracts versus option contracts The key differentiating feature of a VPP is that it is an option rather than a fixed contract. If the exercise price of a VPP is such that it is always called, there is no economic and little practical difference between such VPPs and contracts for a baseload strip. A contract for a baseload strip would be administratively simpler, at least if there were no other VPPs. However, even that marginal advantage is eroded substantially if there are going to be other VPPs with higher exercise prices anyway. The aim should be to identify the set of instruments to be imposed that is proportionate in the sense that it meets the criterion of being the minimum necessary to address market power. Given this aim, a significant proportion of the requisite instruments are likely to be targeted at durations less than baseload. Market power is always likely to be more significant when demand is high and the supply/demand balance tight. The issue is whether it is better to meet this requirement with profiles that are fixed ex ante or with VPPs which are called when the market price threatens to rise above their exercise price. VPPs have the advantage that they will always apply if they are needed. An ex ante guess at when instruments are needed may target most of the occasions correctly. However, there are likely to be times when an ex ante profile means that there is insufficient contract cover, unless the profile is made so broad/large that there are many occasions on which there is more contract cover than is necessary to meet the desired objective. In short, VPPs do a better job of applying when needed and being irrelevant when they are not. The key causes of market power are either that a generator is pivotal (demand cannot be met without them) or there is a significant step in the marginal cost plant stack where a modest withdrawal sends the price up to the next level. VPPs are better than firm power contracts as instruments for targeting these circumstances, especially steps in the marginal cost stack. Therefore, while a fixed contract (whether a PPA, a simple contract or a swap) could be tailored to have a shape which closely follows the effective shape of a VPP, there will inevitably be some periods where fixed contracts are either disproportionately large, or inappropriately low. It is appropriate to mention at this point that some members of the steering group have expressed the view that the previous VPPs in Belgium have been ineffective. One member said ‘ VPPs were just another way for Electrabel to sell Static concerns - range of mitigating measures 14 Frontier Economics | March 2006 power expensively’. While it is beyond the scope of this assignment to do a detailed review of the previous VPP releases, we believe that it is at least very plausible that the releases will have had minimal effect because the volume of them was ineffective, not because there is any inherent fault in the nature of the instruments. Our modelling results reinforce this view. Once market participants understand that conditions with the VPPs in place will be competitive, there will be no incentive for them to pay more than the competitive market price to acquire them. 2.5 REGULATORY MEASURES TO SUPPORT CONTRACTUAL MEASURES The CREG has also asked us to consider whether regulatory measures could be implemented, in addition to the contractual measures described above, in order to enhance the effectiveness of any particular package of measures. Specifically, the CREG has asked us to consider an arrangement where generating assets that have been fully depreciated are required to make their output available at a regulated price determined by the CREG. If this arrangement were put into effect, it would require Electrabel to sell some agreed volume of output from some of its assets at a fixed price. Given this, it is clear that an arrangement of this kind would have an identical effect to a long term contract. One complication that an arrangement of this kind would give rise to is deciding who should be allowed to purchase power at the agreed lower price (and in turn who should have to pay the higher prevailing market price). The most obvious mechanism for allocating these imposed regulated contracts would be to auction them, as one would any other contractually imposed release programme. If this were the case, then the effect of a regulatory measure of this kind would precisely replicate any other imposed long term contract and would therefore be captured by the discussion above (and also by the analysis we present later in this report). 2.6 CONTRACTUAL MEASURES AND SECURITY OF SUPPLY We have been asked to consider whether the introduction of a package of contractual measures to mitigate market power could give rise to a concern with regard to security of supply. Concerns over security of supply are typically centred on whether there is sufficient physical capacity to meet demand, or whether there is an existing or future danger of a shortage of physical capacity occurring. Since none of the contractual forms that we consider would be likely to result in the withdrawal of capacity (more likely the opposite) we do not believe that any imposed contractual measure(s) could give rise to any concern over security of supply. Static concerns - range of mitigating measures 15 Frontier Economics | March 2006 2.7 TREATMENT OF EXISTING CONTRACTS As we describe below, in all our analysis we have assumed that Electrabel has no contracts in place at present. Any contracts that Electrabel does have in should therefore be netted off from the total volume that we identify as being sufficient to mitigate any incentive it might have to exercise its market power. This gives rise to a number of issues that warrant discussion. | What characteristics would a contract or similar position need to have in order to be deducted from the total proposed volume? and | In particular, how should contracts between Electrabel and ECS be treated? We have also been asked to consider how existing contracts should be treated if they were struck at relatively high prices. We address each point in turn. 2.7.1 Characteristics required Any contract which, relative to the contract not being there, reduces the profit that would be earned by Electrabel when the market price rises could be a candidate for subtraction from the proposed volume. The most likely contract form (based on typical contracting structures in the power sector) would be a contract that fixes, in advance, the price that Electrabel would receive for a given volume of power. A standard forward contract (with a large consumer for example) would be an obvious form of a contract that could be subtracted from the proposed volume. A contract swap, had Electrabel been persuaded to accept one, would also be suitable for subtraction from the headline quantity, since Electrabel’s revenues from the power covered by the swap would be decoupled from short run prices in Belgium. Contracts where the strike price is indexed according to some variable, or basket of variables, could qualify for subtraction but the terms of indexation would need to be scrutinised carefully. In particular, contracts that are indexed according to changes in headline markers of electricity prices in Belgium would most likely not qualify. This follows as, depending on the detail of the terms of the contract Electrabel could profit indirectly from increasing prices in the electricity market, as this would in turn increase revenue from the contract. Contracts would also need to be assessed for their “shape”, e.g. whether they are baseload, peak load. We discuss contract shape further in Section 3. The duration of contracts is also relevant. Contracts need to be long enough such that the potential effects on the price achieved in their renewal does not become a substantial influence on the shorter term behaviour of Electrabel. There is no hard and fast rule in relation to this. We suggest that contracts which are three years or more should be recognised fully. The volume of contracts with shorter durations might be taken account on a less than 1 MW for 1MW basis. Static concerns - range of mitigating measures 16 Frontier Economics | March 2006 While it is possible to write down simple criteria for contracts that are likely to have the required effect, some scrutiny of any contract that might qualify will inevitably be needed. Therefore, if the CREG proceeds to implementation of some package of measure then we would strongly recommend that the CREG exercises its own judgement on whether any given contract or position should be netted off from the total volume imposed 2.7.2 Contracts between Electrabel and ECS On the basis of our present understanding of the relationship between Electrabel and ECS, together with the prevailing regulatory environment for retail customers in Belgium, we do not believe that contracts between Electrabel and ECS should be netted off from the total volume proposed. This follows since: • Electrabel and ECS are under common ownership and we must assume that they maximise profits jointly; and • all consumers will soon (from 2007) operate in liberalised retail markets where tariffs are determined by competition and not by regulation. The first of these points implies that the price in any contract struck between Electrabel and ECS is essentially equivalent to a transfer price between business units. If Electrabel were able to raise the wholesale market price, this would become the input price to all retailers. As a consequence, the retail price will rise in response to higher wholesale prices – the second point above confirms that prices will not be fixed and would therefore be free to vary in this way. While Electrabel will not profit from this directly, if a contract exists with ECS at a fixed price, it will nonetheless do so indirectly as a higher price will be achieved on retail sales by ECS. Whether those profits are booked by ECS on retail sales or by Electrabel on wholesale sales is irrelevant if Electrabel and ECS jointly maximise profits. Any contract between Electrabel and ECS would therefore have no affect on incentives Electrabel might have to exercise market power in the wholesale market. 2.7.3 Treatment of existing contracts if struck above market prices We have in addition been asked to consider the position of existing contracts were these to have been struck at a price exceeding the current market price. In terms of its impact on future behaviour, the price at which a contract is struck is irrelevant. In order for a contract to be effective in mitigating market power all that is required is that for some volume of power, the price is fixed in advance, i.e. that it has the facets described above. Contracts struck at “high” prices should therefore qualify for subtraction provided they have the facets described above. Static concerns - range of mitigating measures 17 Frontier Economics | March 2006 Of course, if the price written in the contract is “high” then this implies that the counterparty to Electrabel receives no benefit from lower wholesale market prices until it is able to renegotiate the contract or the contract expires. However, this has no impact on the incentives that Electrabel has to exercise, or not, any market power that it might possess. If the original contract was struck on a fair basis that did not reflect any abuse of market power, then in our view it would be appropriate to let it run its course. If on the other hand it were established that a contract was either anti competitive in duration or was set at a price reflecting abuse, cancellation of the contract would be feasible. However, we note that simply being in a position where the contract appears to be ‘out of the money’ is not evidence of abuse. 2.8 CONCLUSIONS VPPs have slightly better characteristics of applying when needed and not when they are not. Other things being equal they are probably the preferred instrument. However, all contracts serve a similar purpose and any set of contracts which provide a similar profile over time will have essentially the same effect in mitigating market power. With an appropriate definition of the parameters, any of the contractual forms we have identified could produce a broadly similar result. As a result, it follows that any of the measures described, with parameters set appropriately, could be combined together in almost any mix of volumes to achieve the similar results. This equivalence means that we can conveniently model one type of instrument but can then interpret the results as being a requirement for a level of contract cover that can be met in a wide variety of ways. This aggregate requirement for contract cover could be met in any way which Electrabel found convenient or expedient. As the discussion in this section has illustrated, there is little or no substantive difference between the different contractual forms that we have been asked to consider. As a result, any combination of these contractual forms could have the desired result. Given this, there is no obvious reason to limit the choice that Electrabel might have in how to put together a package comprising the required volume. If one package of measures is more desirable to Electrabel and still delivers the outcome desired then it would seem unreasonable to unnecessarily restrict Electrabel from choosing its preferred package. One concern raised with us is that Electrabel might choose to meet its obligation using long term bilateral contracts negotiated under its own terms. The issue of transparency of pricing in imposed contracts is essentially one of implementation. However, as long as market participants knew that Electrabel was being required to comply with a programme of a known size, they would (and indeed should) embody this information in their negotiations with Electrabel and therefore be able to achieve a contract price consistent with their expectation of market outcomes after the imposition of contractual measures. Static concerns - range of mitigating measures 19 Frontier Economics | March 2006 3 The parameters of contractual measures In Section 2 we set out the main features of all of the typical forms of contractual measure, including all of those that we have been asked to analyse here. In this section we describe the key parameters of these contractual measures. 3.1 INTRODUCTION Contractual measures diminish the incentives of a large player to increase prices. The precise effect of a contractual measure diminishing a large player’s incentive to exercise market power will, however, depend on the actual characteristics of the contracts in terms of volumes, shape (i.e. the periods during which deliveries will normally take place) and duration. In the following sub-sections we describe in more detail the impact of different contract volumes, the shape of the contracts and the duration of contracts on a large player’s market power. 3.2 VOLUME AND EXERCISE PRICE 3.2.1 Effects of different volumes How effective a given volume of contract cover is in creating competitive constraints on pricing depends principally on the degree of market power already existing in the market (and also on the details of the cost structure of generation). As an illustration, suppose that a large player were in a position in which increasing its price always resulted in increased profits. Then assume that a contractual measure is introduced, for illustrative purposes we initially assume that the contractual remedy is designed so that it is always in effect (e.g. a fixed long term contract or a VPP with a very low exercise price). The relationship between the large player’s profits and its bid price might be like this: No contractual measure profit With contractual measure profit Profit-maximising market price Profit-maximising market price market price market price Figure 1: Illustration of the effect of a contractual measure, for a given level of demand (an effective contractual measure) The parameters of contractual measures 20 Frontier Economics | March 2006 The contractual measure reduces the additional profits resulting from a higher market price. The slope of the profit line is less, “tipping” the profit line down. In this case, the contractual remedy is effective because the change in the slope of the profit line results in a local maximum profit point at which the market price is lower than in the case without the contractual measure. However, the contractual measure will be ineffective in constraining pricing if no such maximum is produced. This may occur if the volume of contractual measure is insufficient in comparison to the degree of market power that exists. For example, suppose that in the same market conditions as those illustrated above, a smaller volume of contractual measure were implemented. Then the contractual measure may not result in a reduction in market price, as illustrated in Figure 2: No contractual measure profit With contractual measure profit Profit-maximising market price market price - Profit maximising market price market price Figure 2: Illustration of the effect of a contractual measure for a given level of demand (ineffective contractual measure-insufficient volume) The contractual measure shown in the figure above would not reduce market prices. Even though the large player gains less from increasing its bid with the contractual measure in place than without, the point of maximum profit is still strictly increasing with the market price. How much contract cover is sufficient depends on the degree of competition already existing in the market. If one firm has very high market shares, then it will lose almost no sales as it increases the market price beyond the point at which all competing capacity is in use. Profits then simply increase linearly with the market price. We illustrate this situation in Figure 3: The parameters of contractual measures 21 Frontier Economics | March 2006 No contractual measure profit With contractual measure profit Profit-maximising market price market price Profit maximising market price market price Figure 3: Illustration of the effect of a contractual measure for a given level of demand (ineffective contractual measure-highly uncompetitive market) 3.2.2 Effects of shape The amount of contractual cover that might be required to mitigate market power is likely to vary over the course of a day/week/year. In periods of high demand it is likely that a larger volume of contract cover will be required, since in such periods the balance between aggregate demand and supply is likely to be tight, making the market more prone to the exercise of market power. In periods of low demand, less cover is likely to be required. Unless measures are shaped to match this requirement, there will be periods of time when the level of contract cover is either inadequate with no effect on market power, or disproportionately large. Contractual measures can be calibrated in order to provide them with shape. For example, a set of VPP products can be put in place at different exercise prices. VPPs with low exercise prices will always be called and will always be in effect. VPPs with higher exercise prices will only be called in periods where the market price is sufficiently high, which is likely to be in a subset of periods of higher demand. In this way a VPP programme can be designed to deliver the appropriate level of cover over time, although practical considerations are likely to limit the number of different product types that could be included in any programme and hence limit the extent to which any programme can precisely match the shape of cover required. This also demonstrates that the effect of a VPP with a lower exercise price will be greater than the effect of a VPP with a higher exercise price. The parameters of contractual measures 22 Frontier Economics | March 2006 Just as a VPP programme can be constructed with different exercise prices to provide the desired shape, a set of long term contracts could be sold that operate over different periods of the day, or over different seasons, to provide the required level of cover at the appropriate time. Again, there will be practical limitations on the degree to which a programme can be perfectly matched to requirements. As described in Section 2, such difficulties are likely to be more substantive with fixed contracts than with VPPs, since the exercise of VPPs will better track prevailing market conditions. While baseload products are at least as effective at mitigating market power, they are also, obviously, a more onerous burden for the party required to sell them than products with more limited time coverage. If all of the capacity of any proposed package of contractual measures were baseload, it is likely that there would be periods where the volume of cover would be excessive – a smaller volume would have the desired effect. By using VPP products at different exercise prices, or long term contracts that are in force over only certain periods of the day, one can create “shape” in the release programme such that, as far as possible, the volume of cover in force in any given period is proportionate to the level required to have the desired competitive effect. In this way the effect of a programme of contractual measures can be managed such that it is generally not materially more than is required. In any event, some buyers may prefer some mid-merit or peaking products rather than solely baseload, to fit better the load profile of their customers. Therefore, including such products in any programme is likely to increase participation by potential purchasers. 3.3 DURATION In general, longer duration products are likely to have a greater competitive effect on market prices. An extreme example illustrates this point. Suppose that some form of contractual measure were auctioned in durations of one hour. This should surely produce almost exactly the same effect as a spot market operating with no mandated release programme. The reason is that a large player is likely (for significant volumes of contract) to become as interested in the auction proceeds from reselling the imposed contract as in profitability in the spot market itself, and may therefore be prepared to bid prices up in that market even when to do so does not maximise profits from spot market sales. The contractual measure’s effect in diminishing the incentive to bid price up in the spot market is ineffective, because the profits from the next hour no longer matter as much as the effect that a higher price in the next hour will have on the future price at which the contractual measure will be sold. At the other extreme, if a contract is in force for ever (no renegotiation of terms at any point) then the large player has no interest in manipulating the wholesale market to influence the proceeds of subsequent auctions, because there will be no subsequent auctions. If a sufficient volume of the contractual measure is sold to create a competitive market structure, then, a large player acting to maximise its profits will behave competitively in the wholesale market. The parameters of contractual measures 23 Frontier Economics | March 2006 As a general proposition, therefore, longer durations lead to more competitive market outcomes. It is therefore possible to argue that only longer term products should be sold and that secondary markets will arise to repackage those products into shorter-term instruments as required. However, there is no real demand for long term products so a requirement to sell longer term products could lead to unreasonably low proceeds and hence could justifiably be viewed as partial expropriation. In most markets only a small proportion of contracts have a duration of more than 1-2 years. 3 years would therefore seem to be the maximum duration that should be imposed and a mix of durations up to 3 years would seem to be appropriate. The parameters of contractual measures 25 Frontier Economics | March 2006 4 Data, methodology and scenarios In this section we describe our modelling methodology and present some key data points. 4.1 MODELLING MARKET POWER USING SPARK We have used our SPARK model to analyse the possible effect on wholesale market outcomes of the introduction of measure to curtail Electrabel’s market power in the Belgian electricity market. SPARK consists of two modules, one of which identifies profit-maximising strategic behaviour (the SPARK gaming module), while the other simulates plant dispatch given that strategic behaviour (the SPARK dispatch module). In this assignment we have only use the gaming module. Using the SPARK gaming module, given the portfolios of plant present on the system, their capacities and costs, we can analyse what incentives players have to withdraw capacity or mark up the price at which they bid their plant. Our approach to analysing the scope for strategic interaction is rooted in game theory. SPARK simply enables us to make the necessary calculations to identify the range of possible non-cooperative Nash equilibria efficiently and robustly. The gaming module of our SPARK model requires six key inputs: • available assets and their capacities; • ownership of the available assets, together with an assumption on whether each owner might behave strategically; • asset efficiencies and availabilities; • fuel prices, taxes and carbon costs; • interconnector capacities; and • demand. In a following subsection, we provide an overview of the data we used; a more detailed description of the data used can be found in Annexe 1. Data, methodology and scenarios 26 Frontier Economics | March 2006 4.2 OVERVIEW OF DATA 4.2.1 Belgian Asset register Central to our analysis is an estimate of the marginal cost of generation for each generating unit attached to the Belgian system. A full list of the assets installed in Belgium is included in this confidential version of the report in Annex 2. In Figure 4 we illustrate the marginal cost curve for winter and in Figure 5 the same curve for Summer. Differences between the two curves arise from seasonal differences in availability (with maintenance typically planned for Summer periods) and fuel prices. Assumed fuel prices, efficiencies, availability rates etc are asset out in Annexe 2. Data on Belgian generating assets were provided by Elia. [Contains confidential information] Figure 4: Winter marginal cost supply curve capacity by owner Source: Elia and Frontier estimates [Contains confidential information] Figure 5: Summer marginal cost supply curve capacity by owner Source: Elia and Frontier estimates Definition of marginal cost Spot price outcomes in wholesale electricity markets are determined by the interaction of supply and demand on the day. Such short run analysis should therefore be conducted by analysing short run costs, specifically short run marginal costs. By this we mean the costs directly incurred in providing one extra unit of power. This will vary from station to station and will be determined by input fuel costs (e.g. gas prices for gas fired stations, plus carbon allowance prices) at the time, the conversion efficiency of the station, variable operations and maintenance costs5. 4.2.2 Interconnectors In electricity markets, the capacity of interconnectors can be a crucial determinant of prices in any region. If the interconnector capacity between two countries, for example, is very large, relative to market size, and is never constrained, that is its use is always below its maximum available capacity, then prices in both regions will equalize (except potentially for a small loss factor). 5 Long run marginal costs would only become relevant when considering entry decisions that might be taken. However, given relatively lengthy lead times for plant construction, they have little influence on short and medium term pricing. If it is possible for a generator to sell power today at a price in excess of long run marginal cost because of prevailing competitive market conditions it will most certainly do so. Data, methodology and scenarios 27 Frontier Economics | March 2006 However, if the interconnector capacity is small relative to market size and it is constrained, prices may differ between regions. It is therefore very important to treat interconnectors properly. For the purposes of this study we are simulating the Belgium electricity market explicitly and surrounding regions implicitly. We model the interconnector between Belgium and France as an adjustment to demand. This reflects our understanding that the Southern interconnector imports into Belgium with a high load factor. By assuming that the interconnector is, in effect, fully loaded at all times, we derive a conservative estimate of the extent of Electrabel’s incentive to increase prices. The capacity that we assume for the Southern interconnector, by season, is set out in Table 1. The capacity of the interconnector has been provided by The CREG. We also note that this treatment assumes that Electrabel is unable to extract rents from the Southern interconnector. This reflects The CREG’s recent ruling on forthcoming access arrangements to the Southern interconnector, in which existing long term contracts over the interconnector have been torn up and replaced by an auction. If Electrabel were to raise the price in Belgium, it would not benefit for the interconnector because the price that it would have to pay to acquire the rights to its use would rise by the same amount. Virtual interconnector Winter capacity (MW) Summer capacity (MW) 2,700 1,700 France Table 1: Virtual interconnector power plants Source: The CREG The interconnector between Belgium and The Netherlands is also treated as an adjustment to demand. The details of this adjustment are described in the following sub-section. This treatment reflects the fact that the extent and direction of flows over the Northern interconnector are less certain than flows over the Southern interconnector. Interconnector Winter capacity (MW) Summer capacity (MW) Belgium - The Netherlands 2,350 2,000 The Netherlands - Belgium 2,400 1,900 Table 2: Virtual interconnector power plants Source: ETSO NTC Values for 2005, Frontier estimate 4.2.3 Demand In order to make full use of our SPARK results, we need to map results for representative periods (see the Results of our analysis in Section 5 for a more detailed explanation of our modelling approach) onto actual demand data. For Data, methodology and scenarios 28 Frontier Economics | March 2006 this, we used the hourly demand data taken from the Elia website for the year 20046. We then made the following adjustments: • demand growth – 1.5% per year up to 2007; • impact of the Belgian/Dutch interconnector – flows from Belgium to the Netherlands (exports) have the effect of increasing the demand to be served by Belgian generating assets, while flows from the Netherlands to Belgium (imports) have the opposite effect; and • pumped-storage pumping and generating decisions – using a pumped storage optimizer module (described in more detail below). Adjustments for flows across the Northern interconnector The Elia website provides data on flows over the Northern interconnector. We have adjusted Belgian demand to take account of these flows, scaled up by 1.5% (capped at the capacity of the interconnector) to reflect demand growth, i.e. our central analysis assumes that prevailing flows persist. As we describe below, we have analysed the sensitivity of our analysis to this assumption by modelling further scenarios that embody different assumptions regarding the extent of flows over the interconnector. Pumped storage stations The pumping and generating decisions of pumped storage units are intertemporal, i.e. is determined within the day by the off-peak/peak price spread; and, in some cases, the spread between weekdays and weekends. To capture this we have dispatched pumped storage assets over the course of representative days based on typical patterns of the total volume of generation. This has the effect of “shaving” demand in peak periods when these assets are generating and “filling” demand in off peak periods when these assets are pumping. 6 This was the most recent year for which data was available at the time the analysis was conducted. Data, methodology and scenarios 29 Frontier Economics | March 2006 Figure 6: Demand adjustment for pumped storage Final demand characteristics In Figure 7 we illustrate a frequency chart of actual demand levels after both the interconnector flow and hydro pumped storage adjustments. Demand level frequencies 700 600 Frequency 500 400 300 200 100 15,200 14,800 14,400 14,000 13,600 13,200 12,800 12,400 12,000 11,600 11,200 10,800 10,400 10,000 9,600 9,200 8,800 8,400 8,000 0 Demand levels (MW) Figure 7: Distribution of demand to be met by Belgium plant and the Southern I/C, 2007 Source: Elia raw data and Frontier adjustments and estimates Data, methodology and scenarios 30 Frontier Economics | March 2006 4.3 MODELLING METHODOLOGY Using our SPARK model we have analysed the scope for Electrabel to increase prices above marginal cost at a wide range of representative demand levels. We have then investigated how the imposition of a given level of contract cover reduces this incentive. | We model two representative seasons, Winter and Summer, to take account of different fuel prices and plant availabilities. | We model each of these seasons in the presence of a soft constraint on prices (set at €150/MWh for demand levels in excess of 10,600 MW in the Winter and 10,000 MW in the Summer, otherwise it is €100/MWh – see Section 4.5 for an explanation of how these assumptions have been derived). | In all analysis, we have assigned Electrabel a strategy space that ranges between bidding all units at their marginal cost up to bidding all units at 20 times their marginal cost, increasing in increments of 0.1. This is an extremely rich strategy space and allows us to be sure that our analysis is not driven by arbitrary restrictions on pricing behaviour. | At each level of demand, we have determined the equilibrium price outcome based on the profit maximising behaviour of Electrabel, taking account of an assumed volume of contract cover. • We have modelled contract volumes from 0 MW to 10,000 MW in increments of 200 MW. • In the first instance, we have assumed this contract volume is firm and is baseload7. This ensures that all volume included in a given run is exercised allowing easy comparison. • By mapping this analysis onto our demand data we have been able to estimate the impact of putting in place a given volume of baseload contract cover on average annual prices. In particular we can assess the incremental benefit of a further increase in contract volume, informing the choice of the size of any set of contractual measures. • Finally, we have used this analysis to determine what mix of VPP products by strike price, might be optimal. We have modelled a variety of volumes and mixes for each scenario in order to provide The CREG with a range of options. While the final step of the analysis, which focuses on the appropriate shape that should be adopted for any package of contractual measures, has been based on use of VPPs, similar analysis could be conducted to identify the mix of fixed long 7 In effect, this is consistent with modelling, for example, VPPs with a strike price of €0/MWh, a fixed long term contract, a contract swap or a PPA with a station that would be expected to run in all periods when it is available (ignoring planned/unplanned outages). Data, methodology and scenarios 31 Frontier Economics | March 2006 term contracts that would be appropriate. However, the broad proportions of different products identified through analysis of VPPs also provides a reasonable indication of the how any other contractual remedy might be broken down into different product types. Note that the analysis we have conducted assumes that Electrabel has no other long term contracts, or other positions that might have the effect of a contract (such as a retail position with regulated tariffs). Should Electrabel have existing positions, for example any volume released under the existing VPP programme, then these should be netted off from any requirement identified in this report. 4.4 SCENARIOS FOR ANALYSIS The Belgium electricity generation market is dominated by Electrabel and this situation confers upon Electrabel market power and thus the potential to raise market prices above competitive levels. Broadly, the aim of this study is to analyse different measures to mitigate that market power. Our approach to the analysis involves assessing the extent of market power for: • a Base Case scenario to determine the total volume and mix of contractual measures required to mitigate Electrabel’s dominance; • scenarios for new entry(where we assume entry of 1.5GW or 2.5GW of CCGT) to determine how such entry might modify the total volume (and mix) required; and • scenarios to explore the results with various different flows over the Northern interconnector (increased and decreased exports to The Netherlands) to determine how sensitive our analysis might be to such variation in external conditions. The base case uses the full set of assumptions and modelling approach described above. Below we describe our sensitivity scenarios in more detail below. 4.4.1 Sensitivity: entry We modelled two entry scenarios as sensitivities around the base case. The first assumes entry of 1.5 GW of CCGT and the second assumes entry of 2.5 GW of CCGT. We illustrate in the following figures the Winter and Summer MC stacks for both sensitivity scenarios. All new entry is assumed to belong to a non-strategic portfolio, ie one not owned /controlled by Electrabel and by assumption one not able to exercise market power. As a result of this new entry, Electrabel has a smaller share of the available generating assets on the system. One would therefore expect that there is a smaller requirement for contract cover under these two scenarios than under the Base Case (as Section 5 demonstrates, this is indeed the case). Data, methodology and scenarios 32 Frontier Economics | March 2006 [Contains confidential information] Figure 8: Winter installed capacity by owner ( +1,500MW CCGT) Source: Elia and Frontier estimates [Contains confidential information] Figure 9: Summer installed capacity by owner ( +1,500MW CCGT) Source: Elia and Frontier estimates [Contains confidential information] Figure 10: Winter installed capacity by owner ( +2,500MW CCGT) Source: Elia and Frontier estimates [Contains confidential information] Figure 11: Summer installed capacity by owner ( +2,500MW CCGT) Source: Elia and Frontier estimates 4.4.2 Sensitivity: Northern interconnector flows We also modelled different interconnector flows to the North (illustration of effect in the following figure): • one increasing exports to the North by 500 MW by hour (subject to the capacity limit); and • one decreasing exports to the North by 500 MW by hour. Given the increasing steepness of the supply curve as demand increase, an increase in flow over the interconnector has a greater positive affect on prices than the negative affect of a similarly sized decrease. Data, methodology and scenarios 33 Frontier Economics | March 2006 More exports increases load to be met by Belgian generators Demand (MW) Less exports decreases load to be met by Belgian generators Hours 24 Figure 12: Illustration of demand adjustment from different interconnector flows Scenario demand distributions In Figure 13 and Figure 14 we illustrate frequency charts of actual demand levels after both the interconnector flow and hydro pumped storage adjustments for both the 500 MW export increase and decrease. As would be expected, higher demand levels occur more (less) often with more (less) exports to the North. Data, methodology and scenarios 34 Frontier Economics | March 2006 Demand level frequencies 700 600 Frequency 500 400 300 200 100 15,200 14,800 14,400 14,000 13,600 13,200 12,800 12,400 12,000 11,600 11,200 10,800 10,400 10,000 9,600 9,200 8,800 8,400 8,000 0 Demand levels (MW) Figure 13: Distribution of demand to be met by Belgium plant and the Southern I/C with 500 MW more exports to the North Source: Elia raw data and Frontier adjustments and estimates Demand level frequencies 700 600 Frequency 500 400 300 200 100 15,200 14,800 14,400 14,000 13,600 13,200 12,800 12,400 12,000 11,600 11,200 10,800 10,400 10,000 9,600 9,200 8,800 8,400 8,000 0 Demand levels (MW) Figure 14: Distribution of demand to be met by Belgium plant and the Southern I/C with 500 MW less exports to the North Source: Elia raw data and Frontier adjustments and estimates Data, methodology and scenarios 35 Frontier Economics | March 2006 4.5 NEW ENTRY AND SOFT REGULATORY CONSTRAINTS The effect of any programme of contractual measures depends on the behaviour that the dominant party would be likely to follow in the absence of such a programme. While there is no formal regulation of generation prices, we believe that the threat of regulatory or competition law based intervention almost certainly does constrain Electrabel’s pricing behaviour. It is clear that at present Electrabel does not price up to anywhere near the level that consideration of its market power alone would imply is feasible and profitable. We refer to the constraints imposed by the implicit threat of such interventions as ‘soft regulatory constraints’. While it is always difficult to quantify such constraints it is important to recognise that they exist and will influence behaviour. For the purposes of this study we have assumed that it is unlikely that Electrabel would choose to price power in a way that left the price permanently well in excess of the price of new entry. We have therefore informed our choice of soft constraint by an estimate of the cost of new entry. We estimate that new entry as a CCGT operating baseload would cost approximately €80/MWh at the prevailing Belgian gas price and the EUA carbon price. With this in mind, we have assumed that Electrabel would not consistently price off peak power above €100 /MWh, nor peak power above €150/MWh at prevailing fuel and carbon prices As noted, it is difficult to identify with any certainty whether soft constraints do in fact operate at the levels we identify. However, a full and comprehensive review of the level at which soft constraints might begin to bind is likely to be unnecessary, since our modelling indicates that the results of our analysis are not highly sensitive to the level of the soft constraint. Data, methodology and scenarios 37 Frontier Economics | March 2006 5 Results In this section of the report we present the results from our analysis for the different scenarios. The results are reported in line with the methodology outlined in Section 4.3 for our Base Case and for the sensitivities we have analysed. 5.1 BASE CASE In this subsection we present results for the Base Case scenario, including: • Step 1: raw output from SPARK on the equilibrium price outcome for given levels of demand and given volumes of baseload contract cover (i.e. equivalent to a given volume of VPP with an assumed exercise price of zero, a fixed long term contract in place in all hours, or a PPA for a station that would be expected to run at full capacity when available); • Step 2: annual average price outcomes, for a given volume of contract cover, calculated by mapping our raw SPARK results on to Belgian demand data for an entire year; and • Step 3: the average annual price for a number of different VPP product package (base, mid, and peak) propositions, building on the results of Step 1, to illustrate how products might be provided with shape to ensure that they are effective but not disproportionate. Please note that the price outcomes which we calculate should not be interpreted as predictions of Electrabel’s behaviour but merely represent the potential were profit maximising behaviour pursued with regard only to the constraints that we noted 5.1.1 Step 1: Raw results The output from SPARK is a set of static Nash equilibria prices by demand level. In general it is possible to get several static Nash equilibria at any given demand level. However, with only one player assumed to have the ability to act strategically, it is typical to identify only one equilibrium at each demand level. For the purposes of this study we investigated the impact on those price outcomes of introducing different volumes of contract cover. As would be expected, we observe that as the volume of contact cover increases for a given demand level so the equilibrium price outcome (weakly) decreases. In some cases, even 10,000 MW of contract cover does not lead to price outcomes equalling the short run marginal cost of meeting incremental demand on the system. While it would be possible to extend the analysis to higher volumes of contract cover in order to find the volume required to achieve marginal cost outcomes, we have not done so as we understand that contractual remedies in excess of this size are regarded as infeasible. Results 38 Frontier Economics | March 2006 In Figure 15, we illustrate price outcomes by contract volume for a winter demand level of 12,000 MW. We observe that price outcomes: • hit the soft constraints for contract volume levels up to 3,600 MW (i.e. a package of contractual measures with volumes up to that level has no effect at all at this level of demand); • plateau around €140/MWh from 3,800 MW up to 7,400 MW of contract cover; • then fall dramatically but remain above marginal cost at €90/MWh; and • never fall as low as marginal costs even as the volume is increased to 10,000 MW. Winter - Demand level of 12,000 MW 160 Price MC 140 120 €/MWh 100 80 60 40 20 0 200 400 600 800 1,000 1,200 1,400 1,600 1,800 2,000 2,200 2,400 2,600 2,800 3,000 3,200 3,400 3,600 3,800 4,000 4,200 4,400 4,600 4,800 5,000 5,200 5,400 5,600 5,800 6,000 6,200 6,400 6,600 6,800 7,000 7,200 7,400 7,600 7,800 8,000 8,200 8,400 8,600 8,800 9,000 9,200 9,400 9,600 9,800 10,000 0 Contract Volumes Figure 15: SPARK price outcomes for different volumes of contract cover for a winter demand level of 12,000 MW Source: Frontier In Figure 16, we illustrate the results for a higher Winter demand level of 12,800 MW, for which, broadly, the main observation is that higher levels of contract volume still are required before price outcomes fall towards (yet never hit) marginal costs. This illustrates a further feature of our results, that the volume of contact cover required to achieve a given outcome typically increases as demand increases (i.e. at higher levels of demand more contract volume is required). Results 39 Frontier Economics | March 2006 Winter - Demand level of 12,800 MW 160 Price MC 140 120 €/MWh 100 80 60 40 20 0 200 400 600 800 1,000 1,200 1,400 1,600 1,800 2,000 2,200 2,400 2,600 2,800 3,000 3,200 3,400 3,600 3,800 4,000 4,200 4,400 4,600 4,800 5,000 5,200 5,400 5,600 5,800 6,000 6,200 6,400 6,600 6,800 7,000 7,200 7,400 7,600 7,800 8,000 8,200 8,400 8,600 8,800 9,000 9,200 9,400 9,600 9,800 10,000 0 Contract Volumes Figure 16: SPARK price outcomes for different volumes of contract cover for a winter demand level of 12,800 MW Source: Frontier 5.1.2 Step 2: Annual average prices by contract volume We have mapped the price outcomes from SPARK to our adjusted demand data in order to calculate volume weighted average prices for the year. This is illustrated in Figure 17, along with the annual average price that would arise if all units were bid at marginal cost (which is, of course, constant as contract volume varies). We observe that average price outcomes: • are on average capped at close to the soft constraint for contract volumes up to 2,200 MW; • decrease with contract volume but only very slowly up to 5,600 MW; • fall more rapidly with increases in contract volume up to 8,000 MW; and • decrease more slowly after that, although never reaching marginal cost levels. Results 40 Frontier Economics | March 2006 160 Base case MC 140 Price (€/MWh) 120 100 80 60 40 20 0 200 400 600 800 1,000 1,200 1,400 1,600 1,800 2,000 2,200 2,400 2,600 2,800 3,000 3,200 3,400 3,600 3,800 4,000 4,200 4,400 4,600 4,800 5,000 5,200 5,400 5,600 5,800 6,000 6,200 6,400 6,600 6,800 7,000 7,200 7,400 7,600 7,800 8,000 8,200 8,400 8,600 8,800 9,000 9,200 9,400 9,600 9,800 10,000 0 Contract volume (MW) Figure 17: Average market price under a given volume of contract cover (assumed to be baseload) for the base case scenario Source: Frontier This analysis suggests that 8,000 MW might be an appropriate gross volume of contract cover to consider, as there is a relatively modest benefit arising from any increase above that level. Again we stress that this volume could be made up of any of the forms of contractual cover discussed in Section 2. We now discuss our reasons for this selection, beginning with the criterion by which different volumes have been assessed. One obvious criterion would be to achieve competitive price levels. A literal interpretation of this objective would lead to a conclusion that there should be fiercely competitive supply even in the peak hours of the year. However, to do so would require large volumes of contract cover, for very little additional competitive effect because the number of periods affected is so small. Furthermore, even quite competitive markets typically exhibit some potential market power in peak periods. We therefore consider, as an alternative, the marginal benefit of additional contract cover. This is defined to be the additional (demand-weighted average) price reduction arising from the “last” 200MW of contract cover imposed. Thus, the marginal benefit of 8,000MW of contract cover is the demand-weighted average market price with 7,800MW of contract cover minus the price similarly defined with 8,000MW contract cover. We identify a level of contract cover at which additional customer benefits from the last increment of product are large and at which the additional benefits from subsequent increments of products are lower. We illustrate the marginal benefit (the price reduction resulting from each 200 MW tranche of additional contract cover) in Figure 18 below. Results 41 Frontier Economics | March 2006 -9 -8 Marginal benefit (€/MWh) -7 -6 -5 -4 -3 -2 -1 9,800 10,000 9,600 9,400 9,200 9,000 8,800 8,600 8,400 8,200 8,000 7,800 7,600 7,400 7,200 7,000 6,800 6,600 6,400 6,200 6,000 5,800 5,600 5,400 5,200 5,000 4,800 4,600 4,400 4,200 4,000 3,800 3,600 3,400 3,200 3,000 2,800 2,600 2,400 2,200 2,000 1,800 1,600 1,400 800 1,200 1,000 600 400 200 0 Contract volume (MW) Figure 18: Incremental benefit of an extra 200 MW of contract volume Source: Frontier Figure 18 reinforces the description of Figure 17 provided above. At low volumes of contract cover each extra increment has little effect, until over 5,000 MW are in place. Beyond this level, additional contract volume results in more substantial benefits until beyond 8,000 MW when the benefit is smaller. Higher volumes result in negligible additional benefits. This reinforces the view that 8,000 MW of imposed contract cover (before accounting for any other form of measures or existing contract positions) might be appropriate. 5.1.3 Step 3: VPP product packages Up to this point we have identified the total volume of contract cover required to reduce the incentives of Electrabel to raise prices. In this sub-section we present an analysis of how this total volume of contract cover might be broken down into a mix of products. For illustration, we focus on VPP products and determine the product mix that will meet that objective while providing an appropriate range of products for potential VPP purchasers. In order to allow potential competitors of Electrabel to compete more effectively, and also to ensure that the total impact of any programme is proportionate, the VPP product (or equivalents) cannot all be (as was assumed for the zero exercise price VPP products analysed so far). For effective competition to occur, potential competitors will need to offer or have the ability to offer a suite of baseload, mid-merit and peak products By inspection of the results of our modelling to identify the volume of products needed at different demand levels, it is possible to make an informed judgement on the mix of products that would be appropriate. As with the choice of total volume this is not a precisely mechanistic exercise but one which seeks to identify a simple portfolio of VPPs Results 42 Frontier Economics | March 2006 that would, when called, give rise to the right quantum of contract cover for the demand level. In doing this we restrict ourselves to a choice of 3 VPP products with exercise prices appropriate to the technology steps in the supply curve. Following this approach we identify a sensible split of our 8GW total as: • a total baseload product volume of 3,000 MW at an exercise price of €11/MWh (just above the nuclear power plant price); • a total mid-merit product volume of 3,000 MW at an exercise price of €41/MWh (just around the coal power plant price); and • a peak product volume of 2,000 MW at a an exercise price of €81/MWh (just around the CCGT power plant price). As noted, the exercise prices reflect clear steps in the Belgium merit order and should therefore be exercised as demand reaches the different steps. In practice we would recommend that the exercise prices of the different products are matched ex ante to prevailing input fuel forward prices so they continue to track the relevant steps in the supply curve. We also note that while this final step of the analysis focuses on VPP products, similar analysis could be conducted to identify how an appropriate shape should be given to any of the other contractual measures discussed above. For example, we could define a similar range of products (base, mid-merit and peak) for an analysis of fixed long term contracts and would identify a similar suggested mix of those products. The volumes that we have selected for each of these products have been informed by analysis of the raw results underlying this analysis and are aimed at attempting to ensure that the volume of VPP likely to be exercised at any given level of demand is not unnecessarily large. However, as neither the overall volume nor the mix can be mechanistically determined, we also explore through our SPARK model, a small number of variants which add or subtract volumes from the volumes of the three products contained in our central package. The raw price results by demand level coming out of SPARK for our Central case VPP product mix are illustrated in Figure 19, along with the underlying marginal costs and demand distribution. Three series are presented in the chart. | The short run marginal cost of meeting demand at the relevant level of demand (measured on the left hand y-axis). This acts as a point of comparison for the Price series described immediately below. | The equilibrium price that our analysis suggests would be profit maximising for Electrabel at the relevant level of demand, given the imposition of the specified package of VPP products (measured on the left hand y-axis). | The frequency distribution of demand (measured on the right hand y-axis). This illustrates how frequently we might expect the given demand level to occur over the course of the year. Results 43 Frontier Economics | March 2006 We observe a number of steps in the marginal cost curve. These reflect the points in the supply curve where all assets of one technology type are deployed and a small increase in demand causes the next most expensive technology type to be deployed. We observe that prices are close to marginal costs except along the final “step” of the supply curve (above 13,200 MW). The ability to price up in peak periods is unlikely to be a major cause for concern, as this is almost inevitable given the fundamental characteristics of electricity markets8. As the demand curve illustrates, such high levels of demand occur relatively infrequently. 160 700 140 600 120 400 80 300 60 Price MC Demand distribution 40 Demand frequency Price (€/MWh) 500 100 200 100 20 0 7,000 0 9,000 11,000 13,000 15,000 17,000 Demand level (MW) Figure 19: Central case product package (base case): Price outcome by demand level Source: Frontier To allow comparison, we have also modelled the affect of increasing the peak load contract volume by 1 GW (Variant 2 in Table 3). We illustrate these results in Figure 20. We observe that price outcome around the final steps are much closer to marginal costs than in the previous results, and that the prices that hit the soft constraint only occur at demand levels that are very rare – only in the small proportion of periods in each year demand is very high. 8 Prices above short run marginal cost are almost certain to occur in some periods of time. The most obvious example is in periods where only a single plant has surplus capacity. In such circumstances this unit can bid its remaining capacity into the market at a price consistent with the willingness to pay of consumers, which typically lies well above the cost of production. In cases where demand at a price equal to the highest marginal cost of plant would exceed available capacity, efficient prices need to exceed marginal cost of supply in order to ration available capacity. The presence of prices above short run marginal cost is, of course, required if peaking plant is to recover its fixed costs. Results 44 Frontier Economics | March 2006 160 700 140 600 120 400 80 300 60 Price MC Demand distribution 40 200 100 20 0 7,000 Demand frequency Price (€/MWh) 500 100 0 9,000 11,000 13,000 15,000 17,000 Demand level (MW) Figure 20: Central case product package plus 1 GW peak (Variant 2): Price outcome by demand level Source: Frontier In the following table, we present the yearly average prices arising from the base case and Variant 2 together with two additional variants: • the impact of 1 GW of mid-merit VPP less on the Central case (Variant 1); and • the impact of an additional 1 GW of baseload VPP on the Central case (Variant 3) Central package Package Variant 1 Package Variant 2 Package Baseload (€11/MWh) 3,000 MW 3,000 MW 3,000 MW 4,000 MW Mid-merit (€41/MWh) 3,000 MW 2,000 MW 3,000 MW 3,000 MW Peak (€81/MWh) 2,000 MW 2,000 MW 3,000 MW 2,000 MW Average price outcome (if Electrabel 90 €/MWh 109 €/MWh 85 €/MWh 80 €/MWh 71 €/MWh 71 €/MWh 71 €/MWh 71 €/MWh Variant 3 profit maximises) Marginal cost Table 3: Base case scenario product mixes and average prices Source: Frontier The above results lead us to the following conclusions: • Package Variant 1 with a lower volume, appears to be substantially less effective than our Central Package; • Packages with an increased volume, Variants 2 and 3, both provide a more stringent constraint on Electrabel; and Results 45 Frontier Economics | March 2006 • The effect of adding a 1GW of product to the baseload requirement produces a slightly greater effect than adding a 1GW requirement to peakload. The average price outcome (if Electrabel were profit maximising) would move down by just over 5 %). Against this background, and given the difficulty there may be in getting an aggressive package agreed, we believe that it is reasonable to adopt our Central Package. We also note that the price outcome from our Central Package is close to the new entry price plus a premium (see Section 4.5), implying that while this level of VPP release is effective in constraining prices, it would still allow scope for new entry if Electrabel were to price up to the level which would maximise its profits. 5.2 SENSITIVITY: MARKET ENTRY In this sub-section we present results from the new entry sensitivity scenarios, assuming 1.5 GW and 2.5 GW CCGT of new entry respectively. We do not present the raw results here but only the aggregated price outcomes (if Electrabel were to profit maximise) by contract volume level, looking at contract cover generically) and the average prices under relevant VPP packages. 5.2.1 Annual average prices by contract volume The purpose of this new entry sensitivity scenario is to test for the impact of non-strategic entry on price outcomes and test, in particular, to what extent entry introduces more competition to the market. In the same way that we presented the previous set of results, we illustrate in Figure 21 the volume weighted average price outcomes with various volumes of contract cover for the base case +1,500 MW and +2,500 MW CCGT entry. We clearly observe that new entry reduces potential price outcomes significantly compared to the base case – therefore new entry has a strong positive impact on maximum extent to which market power could profitably be exercised. In particular, we note that: • as more entry occurs (i.e. going from base case to +1,500 MW, and then to +2,500 MW) average prices tend to be lower and fall faster, in line with what one would anticipate; and • even with new entry, potential price outcomes are not reduced fully to marginal costs for contract volumes of 10,000 MW or less. Results 46 Frontier Economics | March 2006 Base case Base case +1500 Base case +2500 MC MC +1500 MC +2500 160 140 Price (€/MWh) 120 100 80 60 40 20 0 200 400 600 800 1,000 1,200 1,400 1,600 1,800 2,000 2,200 2,400 2,600 2,800 3,000 3,200 3,400 3,600 3,800 4,000 4,200 4,400 4,600 4,800 5,000 5,200 5,400 5,600 5,800 6,000 6,200 6,400 6,600 6,800 7,000 7,200 7,400 7,600 7,800 8,000 8,200 8,400 8,600 8,800 9,000 9,200 9,400 9,600 9,800 10,000 0 Contract volume (MW) Figure 21: Average profit maximising price under a given volume of contract cover (assumed baseload) for the entry scenarios compared to the base case Source: Frontier We also present in Figure 22 (for the +1,500 MW case) the incremental benefit of an additional 200 MW of contract volumes on average annual profit maximising price. The shape of the figure also has peaks and troughs over a large band of contract volume tranches, ranging from about 4,600 MW to about 7,800 MW. The incremental benefit of an additional tranche beyond a total volume of 6,800 MW is, however, relatively small. We present in Figure 23 (for the 2,500 MW case) the incremental benefit of an additional 200 MW of contract volume in reducing the level that it would be profitable for Electrabel to price up to. We observe that the incremental benefit of an additional tranche beyond a total volume of 6,200 MW is relatively small. Results 200 400 600 800 1,000 1,200 1,400 1,600 1,800 2,000 2,200 2,400 2,600 2,800 3,000 3,200 3,400 3,600 3,800 4,000 4,200 4,400 4,600 4,800 5,000 5,200 5,400 5,600 5,800 6,000 6,200 6,400 6,600 6,800 7,000 7,200 7,400 7,600 7,800 8,000 8,200 8,400 8,600 8,800 9,000 9,200 9,400 9,600 9,800 10,00 Marginal benefit (€/MWh) 200 400 600 800 1,000 1,200 1,400 1,600 1,800 2,000 2,200 2,400 2,600 2,800 3,000 3,200 3,400 3,600 3,800 4,000 4,200 4,400 4,600 4,800 5,000 5,200 5,400 5,600 5,800 6,000 6,200 6,400 6,600 6,800 7,000 7,200 7,400 7,600 7,800 8,000 8,200 8,400 8,600 8,800 9,000 9,200 9,400 9,600 9,800 10,00 Marginal benefit (€/MWh) 47 Frontier Economics | March 2006 -9 -8 -7 -6 -5 -4 -3 -2 -1 0 Contract volume (MW) Figure 22: Incremental benefit of extra 200 MW of contract cover for the +1,500 MW new entry scenario Source: Frontier -8 -7 -6 -5 -4 -3 -2 -1 0 Contract volume (MW) Figure 23: Incremental benefit of extra 200 MW of contract cover for the +2,500 MW new entry scenario Source: Frontier Results 48 Frontier Economics | March 2006 5.2.2 VPP package variants In Table 4, we present volume weighted average prices for both the Central Package and for Package Variant 1. (We only analyse Package Variant 1 as new entry can only reduce the requirement). We observe that the average profit maximising prices: • are substantially lower than under the base case scenario regardless of the mix and cumulative volume of VPP modelled and that they are much closer to the underlying marginal cost (which is itself lower than in the base case reflecting entry); • are lower still as more new entry occurs; • while the outcome of Variant 1 in the Base Case might not be regarded as acceptable, Variant 1 appears to deliver entirely adequate results in the presence of 1.5 GW of entry; and • smaller volumes of VPP still might be regarded as effective in the presence of 2.5 GW of entry. Central Package (with 1.5 GW entry) Central Package (with 2.5 GW entry) Package Variant 1 (with 1.5 GW entry) Package Variant 1 (with 2.5 GW entry) Baseload (€11/MWh) 3,000 MW 3,000 MW 3,000 MW 3,000 MW Mid-merit (€41/MWh) 3,000 MW 3,000 MW 2,000 MW 2,000 MW Peak (€81/MWh) 2,000 MW 2,000 MW 2,000 MW 2,000 MW Average price outcome 68 €/MWh 61 €/MWh 76 €/MWh 63 €/MWh Marginal cost 62 €/MWh 59 €/MWh 62 €/MWh 59 €/MWh Table 4: New entry scenario product mixes and average prices Source: Frontier This analysis would suggest that a smaller volume of VPP (or some other contractual remedy) is required in the presence of entry. With 1.5 GW of entry, it would appear that the extent of the VPP programme can be reduced by at least 1 GW. With entry of 2.5 GW, the reduction in the size of the required package of measures could be at least 2 GW. Results 49 Frontier Economics | March 2006 5.3 SENSITIVITY: VARIATION IN FLOW OVER THE NORTHERN INTERCONNECTOR In this sub-section we present results from the Northern interconnector flow sensitivity scenarios of 500 MW more exports and 500 MW less exports. In Table 5, we present the volume weighted average prices for these scenarios under the Central Package VPP volume mix. We observe that: • as expected, both average profit maximising prices and the underlying marginal costs increase compared to the Base Case as exports to the North increase; and • again, as expected, both average profit maximising prices and the underlying marginal costs decrease compared to the Base Case as exports to the North decrease. Central Package (Base Case) Central Package (500 MW more exports) Central Package (500 MW less exports) Average price outcome 90 €/MWh 104 €/MWh 81 €/MWh Marginal cost 71 €/MWh 75 €/MWh 67 €/MWh Table 5: Northern export scenario product mixes and average prices Source: Frontier This analysis would suggest that, with a consistently greater level of exports to the Netherlands, a VPP programme in excess of 8 GW would be needed. In contrast, if exports were to reduce, then an 8 GW VPP programme would be highly effective in constraining prices and the quantum of release could possibly be reduced. 5.4 SUMMARY In this section we have demonstrated that under our base case scenario, a package of measures with a cumulative volume of 8 GW is likely to be quite effective in restraining prices to levels consistent with a more competitive market structure.. We have also shown that the volume of contract cover required to restrain prices at reasonable levels is likely to fall if there is new entry by a nonstrategic player. If there is entry of 1.5 GW then our analysis suggests that 7 GW of contract cover might be appropriate, even less if there is further entry. Similarly, 8 GW of cover is likely to be excessive if exports to the Netherlands were to decrease in the future. Results 50 Frontier Economics | March 2006 Our analysis has not included any other contracts (or positions that might have the economic effect of a contract) that Electrabel might have in place at present or might put in place. If Electrabel were able to demonstrate that it has in place, or could commit to having put in place, such contracts and/or positions, then these should be deducted from the volumes that we identify here. For example, if Electrabel has in place already contracts of a reasonable duration at a fixed price for the sale of 1,000 MW of base load power, then our recommendation would fall from 8 GW to 7 GW, with the volume of baseload product required reduced by 1 GW to reflect this existing contract position. Similarly, if Electrabel were to have in place a peak load contract at a fixed price for 500 MW, this could be deducted from the required volume of peak load product. The total volume we recommend, net of any existing contracts described above, could be made up from a combination of the different contractual remedies discussed in Section 2. If Electrabel were to accept a contract swap of 1 GW, again this could be deducted from the gross requirement we identify in this section, reducing the required size of the remaining package of contractual measures. We note that in proportionate terms, the scale of the package of measures indicated in this report would be unprecedented. While EDF has implemented a capacity release programme that approaches the same absolute capacity (6 GW as opposed to 8 GW), that programme represented a far smaller proportion of the relevant generation market. It is not within the scope of this assignment to address implementation issues in detail. However, we would be negligent if we did not make clear that a programme of this scale needs the volume released to be ramped up gradually to the 8GW over a substantial period of time, if unreasonable market disturbance is to be avoided. The EC required EDF to release capacity at ‘a pace compatible with demand and the proper functioning of the market’. Even though the EDF scheme is proportionately very much smaller, full volume was only reached after two years from the first release. Results 51 Frontier Economics | March 2006 6 Dynamic concerns – barriers to entry The foregoing has addressed primarily concerns regarding static competition with the existing generation park in Belgium. In this section we turn to dynamic concerns, essentially related to barriers to entry that inhibit the competitive development of the generation market over time. Specifically, in this section we discuss: • a range of potential barriers to entry in the Belgian electricity market and the possible measures to alleviate at least some of these. A key concern raised is the availability of sites for new generation; • the incentives that an incumbent could have to hold on to unused sites suitable for generation; and • possible measures facilitate or mandate the release of suitable sites. 6.1 BARRIERS TO ENTRY There are a number of potential barriers to entry in the Belgian wholesale electricity market. Some of these are intrinsic to the activity and arise in all similar markets around the world. Others arise as a result of factors that are more specific to Belgium. 6.1.1 Lumpy investments and large sunk costs Since it is not practical to add capacity in small increments, investments in wholesale generating assets are necessarily large. As a result there are large up front investments to take account of when considering whether to enter a wholesale market. While this makes entry into the wholesale electricity market more risky - and therefore less likely, such costs are unavoidable. Furthermore, all possible entrants to the wholesale market are likely to be large, sophisticated agents, probably participating in generation in other markets. As a result, potential entrants are likely to be well aware of the problems associated with lumpy investment and prepared to deal with them. These problems of lumpy investments are likely to more substantive in markets that are small and poorly interconnected The presence of cross border capacity can partially mitigate the problem. In a small market, the addition of even a modest increment of capacity can have a large impact on prices, whereas larger markets should be able to accommodate a similar volume of entry without seeing a similar impact on prices resulting. Similarly, where markets are connected with their neighbours, potential entrants have the additional option of selling their output to neighbouring regions, assuming that such sales are economic. Interconnectors can therefore help to smooth the introduction of new capacity and minimise the entry deterring effect of large, lumpy investment costs. Dynamic concerns – barriers to entry 52 Frontier Economics | March 2006 The recent expansion of the France – Belgium interconnector should help, as potentially would investment in phase shifting transformers to improve capacity. Furthermore, improved international TSO co-operation working with PTDF models might also allow greater use to be made of existing interconnector assets and thereby reduce this barrier to entry. 6.1.2 Ability to find demand for output Potential entrants into the wholesale electricity market will need to consider whether there is scope for them to sell their output, at a reasonable price, in the market following entry. In markets where consumers of electricity are already supplied under long term contracts (i.e. tied to a rival generator) there might be a concern that they would be unable to find customers for their output. This concern might be exacerbated in markets where vertical integration between generators and retailers is common. We have seen no evidence to suggest that finding a customer base is likely to be a substantive issue in Belgium. Discussion with members of the steering group has indicated that there are many large customers seeking to purchase competitive power supplies. In line with the relevant Directives, the entire Belgian retail market will be open to competition in 2007, which should provide further options for any potential entrant in the wholesale market to sell its output. 6.1.3 Uncertainty arising from illiquid markets Liquid and transparent forward and spot markets can play a valuable role in facilitating entry. Where markets provide reliable and robust price signals, potential entrants will be able to value better their investment opportunities. Where participants are unsure whether market prices are reliable and unbiased, they will typically be less willing to enter. Problems with illiquid markets might, again, be exacerbated by markets in which there is considerable vertical integration, as such some proportion of the trade between generators and retailers will be conducted as transfers within a company. The development of BelPex and the recent increase in the capacity of the link with France should provide increased liquidity and more certainty over forward prices for potential entrants. Similarly, the value of products sold at auction as part of any enforced capacity release programme can also provide very helpful signals to potential entrants on the value of power. In this way, contractual remedies can be used to increase market transparency and reduce one potential barrier to entry. 6.1.4 Availability of sites There is a perception that the sites on which it is both possible and attractive to build new generating assets are likely to be scarce. Belgium, in line with most Western European countries, is a densely populated country. As a result, we understand, there are relatively few locations where it would be acceptable to site a new generating facility. An entrant would need to go through the relevant local Dynamic concerns – barriers to entry 53 Frontier Economics | March 2006 planning processes and gain the relevant local planning and environmental consents. Such consents might not be granted for many potential sites. It is likely that a substantial proportion of the possible sites for new generation will be sites on which there has been electricity generation in the past, where those assets have been decommissioned. The CREG has indicated that the availability of suitable sites for the construction of new generation is a potential concern in Belgium. In particular, the CREG has indicated that Electrabel may own a large proportion of such sites, including the most attractive sites for new build. As we describe below, we have been unable to gather data either to support or refute this assertion. However, it would not be surprising for Electrabel to hold a high proportion of possible sites, since sites on which there has been a generating facility in the past are typically attractive sites for new build. It is at least plausible that Electrabel as the incumbent generator is more likely to own sites on which there was once a generating facility. If all attractive sites are held by Electrabel, this could create an additional barrier to entry. Electrabel might be unwilling to sell sites to potential rivals, or might only do so at prices that would render entry unprofitable. 6.2 ANALYSIS OF INCENTIVES TO WITHHOLD SITES The discussion above has highlighted the availability of sites as a potential concern. It is also one in which there might be a role for a regulatory intervention. A dominant player in the wholesale electricity market that also owns the majority of the most attractive sites on which new generation capacity could be added is likely to have incentives to retain these sites, even if they do not plan to construct assets on them in the foreseeable future. If the dominant player were to release a site to a new entrant who proceeded to build capacity, this would be likely to reduce the dominant player’s market share and also to erode prices. Both of these effects would reduce the profits earned by the dominant player. As such, keeping sites vacant could have considerable value to a dominant player, allowing it to maintain a high market share and achieve a high margin on that volume. The dominant player would no doubt prefer to retain ownership of all possible sites and build on them itself in the fullness of time. Since a dominant player profits from higher market prices, it would wish to avoid creating a situation in which there is “too large” a surplus of plant. By keeping the reserve margin relatively tight, a large player would be more readily able to demonstrate a scarcity of supply that would justify higher prices. It is therefore possible that the rate at which it would build additional capacity would be below that which is socially optimal, but be nearer the rate that will maximise the value of its business. Dynamic concerns – barriers to entry 54 Frontier Economics | March 2006 On the basis of this high level analysis it seems clear that, in principle at least, there is reason to suppose that Electrabel might have both a number of relevant sites and also faces financial incentives to retain those sites even if it does not intend to build on them in the foreseeable future. In addition, this analysis also allows us to consider how a policy response could be used to resolve this potential problem. This is discussed in the following subsection. 6.3 POSSIBLE POLICY OPTIONS TO ADDRESS SITE AVAILABILITY In the absence of concrete information on the relevant facts regarding the availability of sites in Belgium, it is not possible to provide definitive advice on what is likely to be the best policy response to deal with a scarcity of sites should such sites as there are be owned by a dominant incumbent. However, in this section we explore the measures that could in theory be introduced to make sites available to potential entrants and discuss what impact these might have. 6.3.1 Enforced (or negotiated) release of sites We understand through discussion with the CREG that Electrabel may have agreed with the Minister to release sites that would allow the construction of 1,500 MW of new entry. This understanding has prompted one of the sensitivities that we have modelled. However, we have not been provided with any details of this programme. If a release of sites has been agreed with Electrabel and if this route remains open in the future, then it would seem to represent a useful approach to ensuring site release over time. However, we would advise that the effectiveness of this policy be assessed after its first implementation is completed in order to understand whether an extension of the same mechanism is appropriate. 6.3.2 Requirement to auction vacant sites Although it would undoubtedly have implications for required legislation, policy makers could in theory decide to create an obligation to auction vacant sites after they have remained unused for some period of time. This would ensure that the available stock of sites was either used by their owner or made available for use by others. However, this would give rise to a number of potential difficulties. | Definition of a site: adopting this policy would require some independent body to decide how to define a site suitable for generation. While some sites might be obviously suitable and some obviously unsuitable the dividing line could be very difficult to draw and could be disputed. We understand that identification of sites is a problem with the Government’s current sites initiative. Dynamic concerns – barriers to entry 55 Frontier Economics | March 2006 | Definition of timing of release if all such defined sites are not instantly to be released (something which would seem rash, there would have to be a policy as to the pace of release. | Monitoring of compliance: once a definition of a site had been agreed, a list of the status of all such sites would need to be maintained and kept up to date to ensure that sites were being made available as required. Again, the criteria used to assess whether a site is vacant or otherwise could be contentious and might be disputed. | Alternative use of the site: a dominant player could circumvent the intention of such a policy by ensuring that the site is used for some alternative use aside from electricity generation. The site would no longer be vacant but it would no longer be able to support a generating asset. The relevant regulatory body would in effect need a right of veto over change of use. | Participation in the auction: to avoid any issue of discrimination it is likely that it would be necessary to allow any interested party to participate in the auction, including non-energy sector players. Again this could result in the sale and use of the site without supporting entry, either because the site is used for some alternative purpose. If the auction were fair and transparent, and a party wanting the land for a use other than electricity generation paid the higher price, it is very difficult to argue that the site was ‘particularly suitable’ for generation. | Reserve price: companies required to auction sites might require a reserve price to ensure that there is no danger of expropriation of value. The value of the site (as determined by outside assessors) in some other use might provide an appropriate reserve to ensure that sites are not used inefficiently for generation and that companies receive an appropriate value for any land they are required to auction. These difficulties suggest that while enforced auctioning of vacant sites might be a helpful policy in stimulating site release, it could be difficult to implement and enforce in practice. 6.3.3 Licensing regime Given any required legislation, the CREG could use the licensing regime for new generating assets to reduce the value of sites to Electrabel. For example, the licensing regime could be modified to ensure that parties with a market share in excess of some proportion of the total installed capacity were not allowed to build further capacity. This would reduce the value to Electrabel of withholding sites. Over time, coupled with effective merger control to prevent concentration through acquisition, this would be sure to result in Electrabel’s market share falling below the defined threshold. Italy has operated a law prohibiting any company from Dynamic concerns – barriers to entry 56 Frontier Economics | March 2006 owing more than 50% of installed capacity, although we note that implementation of this type of restriction is not without its difficulties. For example: • How should any mothballed plant be treated in such calculations? • How should temporarily or permanently derated plant be treated and who will measure such capacities? • How should variations in capacity with fuel type be dealt with? • Is it reasonable for a party to be put in an illegal position by the unanticipated decommissioning of plant by others over which they have no control and may have no knowledge? • Would such a rule incentivise Electrabel to decommission open cycle gas turbines in order get round the constraint when it would be economically preferable to maintain them albeit as reserve? We do not rule out the use of this type of licensing constraint but caution that its implementation will need very careful specification. 6.3.4 Resolve existing issues of market power A further measure that might reduce, but not eliminate Electrabel’s potential incentive to withhold sites would be to eliminate, through contractual measures, Electrabel’s market power. If it were the case that Electrabel had exerted market power in order to raise prices, then it would be in a position where the loss that new entry would induce would be greater than if lower competitive market prices prevailed. However, if Electrabel is not currently exerting market power, its incentives with regard to withholding sites would remain unchanged with this measure. While resolving dominance might help to reduce the incentives to withhold sites, it would not remove them entirely. As a generator, Electrabel would still be able to profit from allowing the reserve margin to fall and creating genuine physical scarcity. 6.3.5 Tax on vacant sites We also understand that there is an existing proposal to introduce a tax on vacant sites and that this is may be part of the Government’s agreement with Electrabel regarding site release. This would clearly have the effect of reducing the value to Electrabel of withholding sites, although the level of the tax would need to be set to ensure that it was material enough to affect their decisions. Dynamic concerns – barriers to entry 57 Frontier Economics | March 2006 As with a proposal to require vacant sites to be auctioned, this proposal gives rise to many of the same difficulties regarding definitions and monitoring of adherence. 6.3.6 Other methods to stimulate investment The final way in which the sites issue could be overcome is through direct intervention. In theory, for example, the Belgian regulator could put out a tender for the provision of a power station at some agreed site, procured by Government. This would both ensure that a site was made available, but would also ensure that entry occurred. A model involving centralised procurement of this kind has been applied in a number of other countries, including, for example, Ireland. In Ireland this policy has been successful achieving entry. However, the Irish regulator (CER) only has powers to do this to ensure security of supply and has no right to pursue this measure solely for the purpose of reducing the incumbent’s market power. The policy is also a direct intervention in the market and is very likely to reduce the incentive of anyone else to invest independently in generation. 6.4 CONCLUSION REGARDING SITES We have explored the options for dealing with this issue but, given that within this assignment it has not been possible to obtain hard data, we cannot quantify the importance of the issue or make firm recommendations on the way forward. Given the advanced nature of the Government’s current policy to achieve site release, the prudent policy is to wait to assess the way in which this measure has worked before assessing whether a repeat of this or some other initiative should follow. Dynamic concerns – barriers to entry 59 Frontier Economics | March 2006 Annexe 1: SPARK gaming module Our approach to market analysis is based on prices and pay-offs to portfolio generators. We can define a portfolio to be anywhere from a single generating unit within a power station up to all the power stations on a given market. The particular strategy decision (e.g. mark-up levels) of players will depend on their expectation about their competitors’ behaviour. We identify Nash equilibria, where each player takes into account the strategies that other players find optimal. Modelling establishes equilibria as situations in which neither party wants to deviate from a strategy. We use numerical simulations to compute strategic equilibria in electricity wholesale markets. WHAT CONSTRAINS STRATEGIC BEHAVIOUR? Strategic behaviour may be constrained by: | Regulatory control –regulatory offices in many countries monitor electricity wholesale market outcomes closely and have often intervened. In the UK over the past 10 years, this intervention has taken the form of constraints on specific types of behaviour, formal price control and the divestment of plant. | Market entry of new capacity – high prices may induce the construction of new plants by smaller players who aim to benefit from strategic bidding behaviour of larger players. It is both feasible and desirable to model the effect of market entry on market outcomes and, conversely, to evaluate the impact of the market outcome on the entry decision itself. | Contract coverage - if players have hedged against volatile spot prices through financial contracts, net revenue streams for the volumes contracted are pre-determined (by these contracts). Contract coverage may therefore reduce incentives to manipulate prices in the spot market. However, spot prices also affect price expectations and therefore the strike prices in financial contracts. As incumbents also have an interest in high contract prices, their incentives to drive up prices may prevail, even if there is full contract coverage. SPARK allows us to advise clients on the effect of contract coverage on bidding behaviour if required. HOW ARE STRATEGY OUTCOMES COMPUTED? The SPARK Game Module analyses generator strategies on the basis of the main principles of game theory. In essence the Game Module is set up to identify profit maximising bidding strategies. This is done by assigning a number of strategies to players, in terms of: Annexe 1: SPARK gaming module 60 Frontier Economics | March 2006 • mark-ups of bid prices for individual plants above variable generation cost; or • plant withdrawal from the market. Each player can be assigned a large number of strategies that will be tested against each other. All possible combinations of strategies that have been assigned to players define the strategy space. SPARK searches the strategy space for sustainable strategy combinations by computing prices and payoffs for each strategy combination. Annexe 1: SPARK gaming module 61 Frontier Economics | March 2006 Annexe 2: Data In this Annexe we detail the data we used for the purposes of this study. Asset register by plant type The full asset register used in this study is presented in Table 6. Generating Unit Name Plant Type Capacity (MW) [Contains confidential information] Table 6: Inventory of installed assets in Belgium Source: Elia – data confidential. For internal use by the CREG only. Table 7 contains a summary of installed plant by technology type. Plant Type Capacity (MW) [Contains confidential information] Table 7: Installed capacity by plant type Source: Elia and Frontier Asset efficiencies by vintage of plants We have assumed a range of efficiencies for different plant types, which vary according to the date when the station was constructed. Efficiencies for the main technology types (OCGT, CCGT, hard coal, lignite coal, heavy oil, diesel and turbojets) are illustrated in the figure below. The efficiency of each plant on the system is therefore estimated on the basis of the year in which it was constructed. Annexe 2: Data 62 Frontier Economics | March 2006 Plant eifficiencies over time 60% 50% 40% 30% 20% CCGT Coal_hard Coal_lignite Diesel Heavy_oil OCGT Turbojet 10% 19 75 19 77 19 79 19 81 19 83 19 85 19 87 19 89 19 91 19 93 19 95 19 97 19 99 20 01 20 03 20 05 20 07 0% Plant efficiencies over time Source: Frontier Economics estimates Fuel prices, taxes and carbon costs To estimate the marginal cost of generating assets we combine the assumed efficiencies with estimated fuel prices, taxes and carbon costs. We take the Argus September 2005 contract price for all the oil products which we then index to the NYMEX Futures Light Sweet Crude up to 2007. For gas, we take the average of the Zeebrugge quarterly forward prices for 2006 index it as per oil products by season. For coal, we take the Argus September 2005 contract price and keep it constant nominal. We also assume a constant carbon permit price of €22/tonne CO2. Annexe 2: Data 63 Frontier Economics | March 2006 Fuel type 2007 (€/MWh(th)) Carbon permit cost (€/MWh(th)) Winter : 33.73 4.44 Gas Belgium taxes (€/MWh(th)) Summer: 21.89 Coal_hard 5.95 7.49 Coal_lignite 4.51 8.01 Heavy_oil 27.30 6.12 0.57 Diesel 61.41 5.86 1.86 184.24* 5.69 Kerosene Table 8: Fuel prices, taxes and carbon costs Source: Argus and Frontier estimates * we assume the Kerosene price as three times the Diesel price Availabilities We assume that generating assets have expected availability below 100%, reflecting planned and unplanned outages. Availability levels are different for different technology types and for the summer and winter seasons, reflecting the reliability of different generating technologies and the fact that planned maintenance is typically scheduled for summer periods in regions facing peak demand in the winter. The availability figures we have used are based on publicly available Generating Availability Data System (GADs) run by the North American Electric Reliability Council (see http://www.nerc.com/~gads/) combined with information gathered from a range of assignments previously undertaken by Frontier Economics. Our estimates of expected outage rates are shown in the following table. Annexe 2: Data 64 Frontier Economics | March 2006 Plant Type Winter outages (%) Summer outages (%) CCGT 10% 14% Coal_hard 7% 12% Coal_lignite 4% 9% Diesel 7% 12% Heavy_oil 7% 12% Light_oil 7% 12% Nuclear 8% 25% OCGT 10% 14% Table 9: Availabilities by plant type Source: GADS and Frontier Economics estimates Special treatment of CHP units The electrical output from a lot of generation capacity is determined by the demand for heat. Such units produce heat as their main function and electricity as a by-product. From a gaming perspective, therefore, the power that they produce as the by-product from heat generation cannot be withdrawn for the strategic purpose of raising prices. That amount of power should thus be modelled as non-strategic (i.e., cannot be withdrawn) and bid at a marginal cost of zero (i.e., the cost of selling the energy is zero because the electricity is produced as a by-product). Gathering information from public sources about the exact amount of capacity that is heat driven on a plant by plant basis would be a costly exercise and would not be easy to do properly within the project time frame allowed. However, not modelling the amount of electricity that is produced as a by-product of heat generation would grossly over-estimate the potential for market. We have already described the differences in assumed availability but we make further assumptions about heat driven plants. We assumed a higher proportion of heat driven CHP in winter (70% of available CHP capacity) compared to summer (50%). CHP capacity which is committed to run as a consequence of its heat load is given a marginal cost of zero, ensuring that it runs at all times and is not withdrawn from the market. The remaining CHP capacity is bid in with a marginal cost based on the gas price and an assumed efficiency of 50%. Annexe 2: Data 65 Frontier Economics | March 2006 Special treatment of Wind and Hydro units We make special assumptions with regard to the output of constrained power plants like run of river and wind plants. The generation from these plants is, beyond planned and unplanned outages, much lower than their full capacity due to the nature of the force (rivers in the first case, wind in the second) that drives the electricity production. For this reason, we assume a much lower available capacity than implied by planned and unplanned outages alone to reflect an average over the day of the seasonal load factor. The data, presented in Table 10, was collected from public sources and refined over the course of several modelling projects. Plant Type Winter duration (%) Summer duration (%) Run of river 40% 55% Wind 75% 87% Table 10: Run or river and wind power station seasonal duration Source: Frontier Economics estimates Annexe 2: Data Frontier Economics Limited in Europe is a member of the Frontier Economics network, which consists of separate companies based in Europe (London & Cologne) and Australia (Melbourne & Sydney). The companies are independently owned, and legal commitments entered into by any one company do not impose any obligations on other companies in the network. All views expressed in this document are the views of Frontier Economics Limited. THE FRONTIER ECONOMICS NETWORK LONDON | COLOGNE | MELBOURNE | SYDNEY Frontier Economics Ltd 71 High Holborn London WC1V 6DA Tel. +44 (0)20 7031 7000 Fax. +44 (0)20 7031 7001 www.frontier-economics.com
© Copyright 2026 Paperzz