Earned Value Management (EVM) Presented by Scott Letasi, SWFWMD Watershed Management Program Consultant Meeting July 19, 2007 What is Earned Value Management? EVM is the use of an integrated management system that coordinates work scope, schedule and cost goals, and objectively measures progress toward these goals. Earned Value Management Approach • The basic concept of earned value is to evaluate a project’s health based on the Work Planned, Work Performed, and Dollars Spent. Planned Performed Spent $80,000 $55,000 $70,000 Behind Plan $25,000 Over Running $15,000 Concept Applied to WMP • Planned Value – Cost and Schedule from the Project Development Task documented in the project Agreement and Work Orders. • Performed (Earned Value) – Task deliverables received and approved by the Districts Project Manager. • Spent (Actual Cost) – Invoiced Amount based on fixed price contract. Earned Value Terminology • • • • • • • • BCWS – Budgeted Cost of Work Scheduled BCWP – Budgeted Cost of Work Performed ACWP – Actual Cost of Work Performed BAC – Budget at Completion EAC – Estimate at Completion CV – Cost Variance SV – Schedule Variance VAC – Variance at Completion Why Earned Value Management? Section 8 of Private Entity Agreements 8. REPORTS. The CONSULTANT will provide the DISTRICT with any and all reports, models, studies, maps or other documents resulting from the PROJECT. Additionally, two (2) sets, electronic and hardcopy, of any final reports must be submitted to the DISTRICT as Record and Library copies. The CONSULTANT must submit a Work Order status report with each invoice to include the Project Manager's assessment of the PROJECT'S actual progress as compared to the approved performance schedule. Details must include any deficiencies and the recovery actions completed and planned. Work Order Status Reports • • • • • Status Report (Memo & Table) Earned Value (Chart) Deficiencies Report (Text) Recovery Action Plan (Chart & Text) Recovery Action Completion Report (Chart & Text) Example Status Report Table – May 2007 Citrus County Crystal River WMP (L657) Project Status Task Number Task Description Scheduled Completion Percent Complete Actual Completion Comments 1. Digital Topographic Information 1.2 Digital Terrain Model (DTM) Generation April 2007 100 February 2007 Approved Deliverables April 2007 100 March 2007 April 2007 100 April 2007 May 2007 100 May 2007 May 2007 70 1.6 2. Watershed Evaluation 2.1 2.2 2.3 2.4 Existing Watershed Feature Data Evaluation Hydrologic Feature Inventory Hydraulic Feature Inventory Field Reconnaissance May 2007 2.5 Identification of Surveys June 2007 2.6 Preliminary Junction Reach Coverage Development October 2007 2.8 Immediate Maintenance Evaluation Work Order 2 2.9 Approved Watershed Evaluation Deliverables Dec 2007 Anticipate Completion in June 2007 Letters to be sent to property owners by the District 70 Deep Creek Gulley Project Planned Value 180000 160000 140000 Dollars ($) 120000 100000 BCWS (PV) 80000 60000 40000 20000 0 0.0 2.0 4.0 6.0 8.0 Tim e (Months) 10.0 12.0 14.0 Deep Creek Gulley Project Earned Value 180000 160000 140000 Dollars ($) 120000 100000 BCWS (PV) ACWP/AC BCWP/EV 80000 60000 40000 20000 0 0.0 2.0 4.0 6.0 8.0 Time (Months) 10.0 12.0 14.0 Performance Indicies • Cost Efficiency CPI = BCWP (EV) / ACWP (AC) • Schedule Efficiency SPI = BCWP (EV) / BCWS (PV) Example: EV = $75k, PV = $100k SPI = $75,000/$100,000 = 0.75 = 75% Efficient Estimate at Completion Based on Cost EAC = Actuals to Date + (Work Remaining / Efficiency Factor) EAC = $75,000 + ($25,000 / 0.75) = $108,333 Based on Schedule EAC = Current Date + (Planned Completion Date - BCWS) / Eff. Factor EAC = 2.8 Months + ( Month 12 - Month 2) / .75 = 16.1 Months Deep Creek Gulley Project Estimate at Completion (EAC) 180000 160000 140000 Dollars ($) 120000 BCWS (PV) 100000 ACWP/AC BCWP/EV 80000 EAC 60000 40000 20000 0 0.0 2.0 4.0 6.0 8.0 10.0 Time (Months) 12.0 14.0 16.0 18.0 Recovery Action Plan Identify what project management practices can be implemented to recover from a SPI < 1. • Increase Level of Effort – Have staff spend 20 hours a week on the project instead of 15 hours. • Increase Manpower – Add additional staff temporarly to the project to complete a task allowing the project to get back on schedule. • Implement a Tool – Increase efficiency of a process to reduce the effort and time spent. Deep Creek Gulley Project Recovery Action 180000 160000 140000 120000 Dollars ($) BCWS (PV) 100000 ACWP/AC BCWP/EV EAC 80000 Recovery 60000 40000 20000 0 0.0 2.0 4.0 6.0 8.0 10.0 Tim e (Date) 12.0 14.0 16.0 18.0 Work Order Status Reports • • • • • Status Report (Memo & Table) Earned Value (Chart) Deficiencies Report (Text) Recovery Action Plan (Chart & Text) Recovery Action Completion Report (Chart & Text) Discussion / Q&A Contact Information Scott Letasi [email protected] (352) 796 -7211 x 4287
© Copyright 2026 Paperzz