1 What would we do? ◦ ◦ ◦ ◦ Photovoltaics (Solar)? Facility Repairs and Improvements? New Classrooms & Facilities? Technology? General Obligation Bond in 2014? ◦ Considerations ◦ GOB Timeline 2 Estimated Cost in 2014 $4,627,000 Total canopy structures 62,800 sf Estimated kWh in year one 1,346,000 kWh Percentage of District need 81% Estimated savings year one $270,600 25 year production 31,712,000 kWh 25 year savings w/REC’s $11,727,000 Estimated simple payback 14 years Estimated CO2 reduced 32,000 tons 3 Measure G outbrief from 2008. Project list as starting point 4 Enable Class Size Reduction / Growth Replace portables Bagby Multipurpose / Kitchen Sartorette media center More outdoor covered eating areas Other ideas? 5 What would be ideal for technology infrastructure and equipment? 6 Bonding capacity. Demographics. Community input. Facilities master plan. Develop project lists. Would we get the votes? Process. 7 8 9