NOT PROTECTIVELY MARKED Contract for the Provison of Secure Escort Services for Children and Young People SCHEDULE 6: Contract Delivery Indicators Schedule 6 Contract Delivery Indicators Page 1 April 2012 NOT PROTECTIVELY MARKED Contract for the Provison of Secure Escort Services for Children and Young People 1. Definitions and Interpretation 1.1 All Definitions can be found in the main body of Volume 3 Terms and Conditions 2. Introduction 2.1 The Services provided by the Contractor constitute a critical link between Courts, Secure Relevant Premises, the police and other Agencies. Poor performance at any stage in the process is likely to cause disruption to the administration of justice. 2.2 The Authority has identified a number of key performance measures (“Contract Delivery Indicators”), listed at Appendix A to this Schedule 6. The order in which the Contract Delivery Indicators appear does not indicate relative priority. 2.3 Each of the Contract Delivery Indicators specifies the criteria (the “CDI Criteria”) by which each area shall be measured and the remedies that shall apply in the event of poor performance. 2.4 The Contract Delivery Indicators relate solely to the Contractor’s performance in respect of the relevant specific obligations. Absence of a Contract Delivery Indicator for any other aspect of the Contractor’s obligations under this Contract does not mean that the Contractor has no responsibility or liability for poor performance in those areas. 2.5 Poor performance gives rise to the following consequences: (A) Liquidated Damages; and /or (B) a requirement for Improvement. 2.6 In determining the appropriate level of Liquidated Damages (where applicable), the Authority has taken care to ensure that they represent a reasonable but genuine preestimate of loss. 3. Monthly Performance Report 3.1 The Contractor shall submit a monthly report (the “Monthly Performance Report”) to the Contract Manager no later than fifteen (15) Days after the end of the relevant Month. 3.2 The Monthly Performance Report shall: a) provide the Authority with Management Information in accordance with Schedule 1, Part 2 (Authority's Requirements Services Specification); b) state the Contractor’s performance against each of the Contract Delivery Indicators; and Schedule 6 Contract Delivery Indicators Page 2 April 2012 NOT PROTECTIVELY MARKED Contract for the Provison of Secure Escort Services for Children and Young People c) identify any areas in which the Contractor’s performance has resulted in the relevant CDI Criteria occurring, and provide reasons for that occurrence. 3.3 Where the Authority does not agree with the Contractor’s assessment of performance against any of the Contract Delivery Indicators as stated in the Monthly Performance Report, it shall notify the Contractor of the Authority’s assessment of such performance. If the Parties fail to reach agreement as to the assessment of such performance within twenty eight (28) Days of the date of such notification, the matter shall be resolved in accordance with clause 74 (Dispute Resolution). 3.4 Where the Authority accepts the Contractor’s assessment of performance as stated in the Monthly Performance Report, or following agreement or resolution of any dispute over such assessment in accordance with paragraph 3.3, the relevant CDI Remedy as stated in Appendix A shall be applied in accordance with paragraphs 4 and 5. 3.5 The Authority shall review the Contract Delivery Indicators from time to time, and their associated CDI Criteria, with a view to assessing whether they remain appropriate in all the circumstances and deliver value for money. In particular, the Contractor acknowledges and agrees that: (A) the Contract Delivery Indicator for Unplanned Journeys (CDI Reference 3.2) shall be reviewed on a twice yearly basis following the Services Commencement Date by reference to average journey times for such journeys (which data shall be provided by the Contractor as part of the Monthly Performance Report). The Parties shall jointly review the data relating to average journey times and agree (acting reasonably) changes to the Contract Delivery Indicator to reflect Service improvements that may be (or have been) made. The product of these reviews shall, when agreed, be incorporated into Appendix A using the process set out in Schedule 9 (Change Mechanism). 4. Liquidated Damages 4.1 Where the CDI Remedy specified in Appendix A is Liquidated Damages, the Contractor's Monthly Performance Report shall identify the sums due and the Authority shall deduct the amount of such Liquidated Damages from payments of the Contract Price made in accordance with clause 44 (Payment Provisions) and Schedule 5 (Payment Mechanism). 5. Improvement 5.1 Where the CDI Remedy specified in Appendix A is Improvement, within seven (7) days of the date of issue of the Monthly Performance Report the Contractor shall deliver to the Authority a plan (the “Improvement Plan”) in respect of the relevant Contract Delivery Indicators. 5.2 Without prejudice to the provisions of paragraph 5.1, the Authority may at any time Schedule 6 Contract Delivery Indicators Page 3 April 2012 NOT PROTECTIVELY MARKED Contract for the Provison of Secure Escort Services for Children and Young People issue a notice (an "Improvement Notice") if, in its reasonable opinion, the Authority considers the Contractor has repeatedly failed to operate in accordance with the Contract in relation to the safety and welfare of any Children and Young People (an "Operational Failure"). An Improvement Notice shall state: (A) the nature of the occurrence of the failures; (B) the dates on which the occurrences of failure were recorded or took place; (C) an account of any relevant circumstances, so far as known to the Authority; and (D) any other supporting information which the Authority considers to be relevant, following which the Contractor shall, within seven (7) Days of the date of issue of such an Improvement Notice, deliver to the Authority a plan in respect of the relevant failures (which shall also constitute an "Improvement Plan" for the purposes of this Schedule 6). 5.3 The Improvement Plan shall (in either case): (A) provide a detailed statement of the reasons for the occurrence of the CDI Criteria or Operational Failure (as the case may be); (B) identify the remedial action needed to: (1) rectify the circumstances which have resulted in the occurrence of the failure to meet any CDI Criteria identified in the Monthly Performance Report or the Operational Failure (where rectifiable), and (2) achieve a permanent resolution of such poor performance and prevent its re-occurrence; (C) set out the Contractor’s proposals for carrying out the remedial actions, a programme for undertaking such actions and the date by which they will be completed; (D) identify any actions or consents required from the Authority, any Authority Related Party and/or any Agency to facilitate the Contractor’s remedial actions (where these activities do not form part of the Contractor's obligations under this Contract); (E) not increase cost or risk to the Authority and (F) propose criteria for the purpose of auditing completion of the remedial actions and resolution of the poor performance (to include an appropriate period of time to monitor the stability of the resolution). Schedule 6 Contract Delivery Indicators Page 4 April 2012 NOT PROTECTIVELY MARKED Contract for the Provison of Secure Escort Services for Children and Young People 5.4 Following receipt of an Improvement Plan, the Authority may (acting reasonably): (A) agree it; or (B) reject it (identifying the principal reasons for such rejection) and require the Contractor to submit a revised Improvement Plan to address those issues within seven (7) Days of such rejection. 5.5 Where the Contractor fails to submit a revised Improvement Plan in accordance with paragraph 5.4(B), or the revised Improvement Plan is in the Authority’s reasonable opinion unacceptable, the matter shall be resolved in accordance with clause 74 (Dispute Resolution). 5.6 The Contractor shall implement all the remedial actions set out in an Improvement Plan by the date specified in the Improvement Plan and, with respect to those actions to be taken by the Contractor or its Subcontractors, at the Contractor’s own cost, i.e. without any cost to the Authority 5.7 The Authority shall provide the Contractor with the name of a person authorised to act on behalf of the Authority (the “Lead Officer”) for the purposes of measuring progress against an Improvement Plan, completion of the audit and closure following completion. Persons who may be nominated as Lead Officers may include the Contract Manager (or designated representative, including the Contract Monitor). 5.8 Subject to paragraphs 5.10(A) to 5.10(C), an Improvement Plan shall remain open until the remedial actions to be carried out under it by the Contractor have been audited by the Authority and the Lead Officer has confirmed in writing that all such remedial actions have been completed in accordance with the agreed Implementation Plan (and, in addition, performance of the relevant elements of Service have been provided fully in accordance with this Contract (and, where relevant, so as to meet the applicable CDI Criteria) for the monitoring period agreed by the Contractor and the Authority) whereupon it shall be closed. 5.9 Where the remedial actions required under an Improvement Plan are carried out and completed but do not succeed in rectifying the circumstances which have resulted in the occurrence of the failure to meet any CDI Criteria identified in the Monthly Performance Report or Operational Failure (where rectifiable) or in achieving a permanent resolution of such poor performance and preventing its re-occurrence, the Authority shall, without prejudice to its rights under paragraph 6 be entitled to issue a further Improvement Notice pursuant to paragraph 5.2 in which case the process set out in the remainder of this paragraph 5 shall apply (with the necessary changes). 5.10 Where relevant, the Authority shall endeavour to procure any actions or consents identified in an Improvement Plan as required from an Authority Related Party or Agency. Where the Authority is unable to procure such compliance, and it is impossible for the Contractor to implement the Improvement Plan without such actions or consents, it may: Schedule 6 Contract Delivery Indicators Page 5 April 2012 NOT PROTECTIVELY MARKED Contract for the Provison of Secure Escort Services for Children and Young People (A) agree that the Contractor is no longer required to complete the remedial actions identified in the Improvement Plan for which such actions or consents are needed; or (B) agree with the Contractor a revised date for completion of the relevant remedial actions within the Improvement Plan; or (C) close the Improvement Plan and relieve the Contractor of the obligation to complete the relevant remedial actions identified in it. (D) where the Parties agree it is not possible for the Contractor to meet the requirements of the Contract, execute a Contract Change in accordance with Schedule 9 (Change Mechanism). 5.11 An Improvement Plan may relate to one or more Contract Delivery Indicators and to a particular site, a number of sites or a whole contract area. 5.12 Each Improvement Plan shall be sequentially numbered from a central register maintained by the Contractor and Supplier Management Team. In the event a further unconnected circumstance which results in the occurrence of the failure to meet any other CDI Criteria, a separate Improvement Plan shall be raised and recorded in the central register under a separate sequential number. 5.13 A report on progress against each open Improvement Plan shall be provided at each monthly Contract Review Meeting. 6. Rectification 6.1 Where: (A) the Contractor fails to complete the remedial actions in an Improvement Plan by the date specified in it for their completion or to the Authority’s relevant audit standards, or performance of the relevant elements of Service have not been provided fully in accordance with this Contract (and, where relevant, so as to meet the applicable CDI Criteria) for the monitoring period identified within the Implementation Plan; or (B) the Contractor fails to achieve the relevant CDI Criteria in respect of the same Contract Delivery Indicator two (2) or more times in any rolling period of twelve (12) Months (whether or not the Contract Delivery Indicator identifies Improvement Plan as the CDI Remedy), the Authority may at its sole discretion: Schedule 6 Contract Delivery Indicators Page 6 April 2012 NOT PROTECTIVELY MARKED Contract for the Provison of Secure Escort Services for Children and Young People 6.2 (1) agree an extension to any relevant Improvement Plan; (2) agree a revised relevant Improvement Plan; or (3) issue a Rectification Notice requiring the Contractor to provide a Rectification Plan. Notwithstanding the other provisions of this Schedule 6 (including in particular those relating to the production of Improvement Plans in paragraph 5), where a Serious and Significant Incident occurs, due to the act or omission of the Contractor in default of this Contract, the Authority may: (A) issue a Rectification Notice requiring the Contractor to provide a Rectification Plan; or (B) in the case of Death of a Child or Young Person in the Custody of the Contractor only, issue a Termination Notice on grounds of Contractor Default in accordance with clause 49.2 (Remediation). 6.3 Following receipt of a Rectification Notice, the Contractor shall within fourteen (14) Days of the date of its issue provide a Rectification Plan which shall set out the Contractor’s proposals for carrying out the necessary rectification action and the date by which they will be completed. 6.4 On receipt of a Rectification Plan the Authority may: 6.5 (A) agree it; or (B) reject it and require the Contractor to submit a revised Rectification Plan within seven (7) Days of such rejection. If: (A) the Contractor fails to submit a revised Rectification Plan in accordance with paragraph 6.4(B), or (B) the revised Rectification Plan is in the Authority’s reasonable opinion unacceptable, or (C) within 28 days of a Rectification Plan (or a revised Rectification Plan) being agreed the Contractor fails to carry out and complete the rectification works specified in it to the Authority’s relevant audit standards, or in the Authority’s reasonable opinion fails to make substantial progress against actions agreed, the Authority may in its sole discretion: (1) agree an extension to the time for carrying out and completing the Rectification Plan; or Schedule 6 Contract Delivery Indicators Page 7 April 2012 NOT PROTECTIVELY MARKED Contract for the Provison of Secure Escort Services for Children and Young People (2) agree a revised Rectification Plan; or (3) issue a Termination Notice on grounds of Contractor Default in accordance with clause 49.2 (Remediation). Schedule 6 Contract Delivery Indicators Page 8 April 2012 NOT PROTECTIVELY MARKED Contract for the Provison of Secure Escort Services for Children and Young Appendix A: Contract Delivery Indicators The Contract Delivery Indicators are detailed in the table below, together with mechanisms to address performance failure. Performance Area Reference Proposed Performance Measure CDI Remedy Amount of Liquidated Damages 1. Secure Custody 1.1 Each Escape of a Child or Young Person who is the Improvement responsibility of the Contractor. 2. Children and Young Person Welfare 2.1 Each incident of death or suicide in custody either : Improvement • whilst in custody of the contractor and for which the Coroner, Prisons and Probation Ombudsman's or any other body that has a statuary obligation to this contract, findings indicate some or all of the responsibility for the incident to the Contractor, Contractor's Staff or Operating Manual; or • 2.2 Schedule 6 Contract Delivery Indicators Note Contractor The contractor would not have any liability for this CDI within the court environment whilst not in Contractor’s custody where the Coroner, Prisons and Probation Ombudsman's or any other body that has a statuary obligation to this contract, findings indicate some or all of the responsibility for the incident to the Contractor, the Contractor's Staff or Operating Manual Each incident of self harm by a Child or Young Improvement Person whilst in the custody of the Contractor due to a failure to comply with the Operating Manual or Page 9 to April 2012 NOT PROTECTIVELY MARKED Contract for the Provison of Secure Escort Services for Children and Young other default 2.3 2.4 2.5 2.6 3. Service Delivery 3.1.1 Each incident where Physical Restraint is inappropriately used and/or the incorrect Physical Restraint method is applied Each failure to report a Reportable Incident Improvement Each incident where a Child or Young Person is Improvement harmed by another whilst in custody of the Contractor Two (2) or more incidents of failure to provide Improvement Decent Conditions for a Child or Young Person whilst under the responsibility of the Contractor over a 3-Month period Each incident of court delay due to the Contractor's Liquidated actions or omissions resulting in a Child or Young Damages Person (who is the responsibility of the Contractor) not being available in court at the required court appearance If the contractor does not make the schedule hearing and the court sits empty or the contractor was unable to rearrange the hearing for the same day the below Liquated damages will come into effect Three (3) or more such incidents in any rolling 3Month period Crown Court: £931 per hour pro rate for each period of 15 minutes Magistrates Court/Youth Improvement Courts: £470 per hour pro rate for each period of 15 minutes 3.1.2 Schedule 6 Contract Delivery Indicators Improvement Page 10 April 2012 NOT PROTECTIVELY MARKED Contract for the Provison of Secure Escort Services for Children and Young 3.2 Three (3) or more failures within a 6-Month period Improvement of any of the below 3.3 3.4 4. Quality of Compliance 4.1 Schedule 6 Contract Delivery Indicators Failure to collect a Child or Young person within 3 hours of the escorting task being requested (the phone call) by the Authority for unplanned journeys and unplanned bedwatches Failure to arrive within 20 minutes before or after of the agreed pick up time for a planned transfer Failure to deliver a Child or Young Person in time for planned in patient treatment Each failure to confirm a valid Warrant to hold a Improvement . Child or Young Person and that the Child or Young Person is the person identified in the Warrant Ten (10) or more incidents of failure over a 6-Month Improvement period to provide an accurate time of delivery at the start of the journey to the relevant premises. (excluding where the Journey relates to delivery of a Young Person for planned inpatient treatment). The tolerance levels for the accurate time are: < or = 2 hour journey = 20 minutes either way >2 hour journey = 30 minutes either way. The Authority will be looking to review the CDI’s after 2 years . Three (3) or more incidents of failure to provide Improvement complete and accurate required Management Information within the prescribed time scale as required by the Contract in a 6-Month period Page 11 April 2012
© Copyright 2026 Paperzz