P ri n ce Mo h a m m a d B in Fa h d Un i ve rs i t y College of Engineering Department of Mechanical Engineering Internship Progress Report 3 at [Saudi Aramco] Reporting Period: [14/7/2012 - 25/7/2012] Submitted by: [Rakan A. Al-Ghoufaili] [200600725] [submission date (27/7/2012)] Mechanical Engineering Department Summer 2012 Summary: In the last two weeks from July 14 until July 25, I had many activities that I did during this period. I have been introduced to the field survey and I had a site visit and did inspections in the plants of Saudi Aramco. I participated to the schedule of Quarterly Safety Inspections (QSI), and Work Permit at some departments I will mention it later in this report. I attended a Safe Operations Committee (SOC) Meetings in some departments. I participated to site inspection and conduct work permit survey at Dhahran District Cooling Project. In this report I will provide a listed of highlights for these last two weeks. Background: PLANT OPERATIONS The safe processing and movement of oil from underground to ship or transmission pipeline is the primary Saudi Aramco objective. Any construction operation which could affect the safety of oil processing and movement must be planned and performed in accordance with the operating procedures of the area in which the job is located. Every plant area in Saudi Aramco operations has a specific set of operating instructions and the operating supervisor for that area has full responsibility for safety precautions. With this responsibility, he also has authority to issue work permits and stop any work if it is not in accordance with proper procedures. It is therefore necessary for anyone expecting to work in an area where oil or gas is handled to know the rules and regulations and obey them. Failure to follow the operating rules can result in not only destruction of Saudi Aramco property but also death of construction and operating personnel. This type of disaster must be prevented. Contractor Site Safety Program (CSSP) Contractor shall properly plan and establish job-specific safe work procedures for all contracted work. For long form capital project construction contracts where SA Project Management is the proponent or as requested in writing by the SAPO, the contractor shall develop, implement and adhere to a job-specific contractor site safety program (CSSP) that conforms to the requirements of the contract, this document and all other applicable SA safety requirements. If requested by the SAPO, the contractor shall submit a supplementary detailed safety plan as may be needed before starting a new major phase of work. Hazard Identification Plan (HIP) For all SA contracts (e.g., long form, mid form and short form contracts), the contractor and/or their subcontractor(s) shall develop, implement and adhere to a contract-specific HIP. The HIP shall list all tasks/activities associated with the contracted work, potential hazards of each activity and control measures to mitigate these hazards. The contractor’s HIP shall identify all potential hazards associated with the work to be performed. The HIP shall not be a list of generic hazards. Progress: Qatif Diesel Bulk Plant Partial Mechanical Completion Walkthrough Dhahran Area Loss Prevention Department (DHALPD) participated in the partial mechanical completion certificate walkthrough for the Additional Capacity Phase II Project, BI-10-00612-001. The scope of the inspection covered the new loading pumps and their associated piping to the inlet of the new loading skid. We highlighted 22 “yes” exception items, including the new loading pump emergency shutdown system not able to isolate the existing loading racks as required by SAES-B-058. Infractions at Dhahran Bulk Plant Tank Farm Contractors Laydown Yard DHALPD conducted a job site inspection of a contractor’s (ALASCO) lay down yard facility located at Dhahran Bulk Plant Tank Farm area. We noted several infractions including storing excess combustible materials next to a welding area, improper storage of gas cylinders, and several other fire hazards. We also noted that the contractor did not post the required material safety data sheets, the presence of unlabeled chemical containers, poor housekeeping, and no project identification sign at the main entrance of the site. Written recommendations regarding the above issues were forwarded to Eastern Regions Distribution Department’s management. Infractions at District Cooling Project Contractor Laydown Yard DHALPD observed many safety infractions over the course of several site visits to the District Cooling Project contractor laydown yard. We noted a less than adequate yard layout, poor fire prevention equipment maintenance, a lack of adequate dust control and no approved traffic flow plan. We also observed unsafe practices within the yard such as congested storage areas, improper storage of flammable and combustible materials. Our findings were entered into the site safety log book and were also communicated to Utilities Department and the contractor during the weekly project progress meeting. We recommended temporary closure of the laydown yard until the outstanding items are rectified. Work Permit Infractions at Dhahran District Cooling Project Sites DHALPD conducted work permit reviews at Dhahran District Cooling project sites within Dhahran community. We noted infractions such as work permit receiver or delegate not at the work site, improper storage of flammable materials, lack of excavation barricades, and workers standing at the edge of excavations that were not barricaded. We notified Utilities Department and contractor representatives of these infractions and advised that immediate corrective measures be taken. Furthermore, all infractions were discussed during the contractor weekly safety meeting. Safe Operations Committee Meetings DHALPD attended the Safe Operations Committee (SOC) meetings held at EXPEC Network Operations Department and Materials Planning & Services Department. We presented and promoted the information related to the “Injury Prevention Workshop for Non-Industrial Supervisors”. We also presented an “SOC Overview” topic and encouraged the management of the two departments to align their SOCs with SMS element #1. Plan:
© Copyright 2026 Paperzz