Engineering Earth’s Development, Preserving Earth’s Integrity RISKS AND OPPORTUNITIES IN THE OPERATION OF LARGE SOLAR PLANTS Originally Presented at: Solar POWER-GEN 2013 San Diego, CA, USA Article Re-Print Main Author: Francesco Belfiore Co-Authors: Tekla Taylor, Beth Moisan, Mario Zappia, Ettore Cinarelli 1.0INTRODUCTION A primary objective for any power plant is to ensure the plant continuously and reliably operates, thereby generating the maximum economic and energy performance returns. Solar Photovoltaic (PV) power plants are no exception. The operation and maintenance (O&M) of large PV plants requires an integrated management system that is implemented throughout the entire lifecycle. Since PV power plant management practices are still emerging and evolving, Golder’s experience in managing a very large facility in Italy, can provide critical insight to the actual risks and opportunities involved in the operations as well as their impact on return on investment. The consortium of the international investors for the Montalto di Castro PV Plant retained Golder to conduct a Technical Due Diligence of the project in 2010 while the project was under construction. Golder analyzed and validated both general and technical factors affecting the productivity of the power stations. Since 2011 Golder has supervised the completion of construction and continues to provide supervision of the O&M activities. In the U.S., Golder is able to provide ad hoc integration of engineering and environmental services for the entire solar project lifecycle (such as the Montalto di Castro PV plant) from site selection, planning and environmental permitting through commissioning and operation and finally, decommissioning phases for any solar PV project. This paper is based, in part, on the experience of Golder in the assessment and supervision of O&M activities of the Montalto di Castro power station and other similar large scale PV plants. lated to the upstream phases of the project lifecycle (siting, development, design, etc.) and may have very significant effects on the downstream phase (performance, production). The operation model presented here assumes that a primary O&M contractor has direct responsibility, using its own resources or sub-contractors, to manage all electrical generation and transmission systems, security systems, visual mitigation (green areas on the perimeter) management and pest control. Other contractors are responsible for civil works and general housekeeping, including cleaning of the panels, and specific parts maintenance. In particular, on behalf of the owner of the plant Golder directly supervises the entire operational structure and related activities. Our practical experience suggests that many issues emerging during the O&M phase are strongly re- THIS ARTICLE WAS PRESENTED AT SOLAR POWER-GEN 2013 AND HAS BEEN REPRODUCED WITH PERMISSION FROM Solar POWER-GEN. THE LAYOUT HAS BEEN CHANGED FOR THE PURPOSE OF THIS REPRINT. 2 Article Name from tax incentives currently available only to fossil fuel projects. The proposed Master Limited Partnership Parity Act (S 3275) would amend the federal tax code to allow wind and solar schemes to fall under the attractive Master Limited Partnerships business structure and thereby be taxed as a partnership with access to capital at a lower cost. Figure 1: Renewable portfolio generation goals 1.1THE US ENERGY POLICY AND MARKET FOR LARGE SCALE SOLAR PV PROJECTS The current political climate in the US and lack of a long term energy strategy make it increasingly unlikely that a federal renewable energy plan will emerge any time soon. The extension of key stimulus programs remains uncertain and continued political stalemates will almost certainly delay any progress in renewable energy programs. One example of this uncertainty is the end of the federal PV solar investment tax credit (ITC) set to expire in December 2016. There is a permanent 10% ITC for solar that will remain available after the 30% rate expires, however, unless there is a renewal of the ITC, there will be added pressure to lower balance of system costs. In the absence of comprehensive federal legislation and regulation, the States have continued to evolve their solar programs and incentives to fill the void, primarily through the enactment of legally binding Renewable Portfolio Standard (RPS) legislation or the establishment of non-binding renewable portfolio goals. Specifically, twenty-nine states and the District of Columbia have enacted RPS legislation that specifies the percentage of renewable energy the state’s utilities must contribute by a certain future date. In seventeen of these states, there are specific minimum solar contributions (or carve-outs) required under the RPS. Another eight states and two territories have renewable portfolio generation goals. (See Figure 1) Recent attempts to establish new RPS standards in several states (e.g., Kentucky, South Carolina and Oklahoma) have been unsuccessful. However, other bills in 2012 have passed to strengthen or adjust RPS requirements in Maryland and New Jersey, providing further confirmation of the continued patchwork regulatory and incentive status that solar developers must contend with across the US. Despite the challenges and uncertainty, the US continues to be a bright spot in the global solar market. The trend in the US is toward larger capacities for utility scale projects and it is estimated that a total of 3.2 gigawatts (GW) will be installed in 2012, representing an increase of approximately 70% from 2011. The top utility scale PV projects rated by installed MW currently under construction are located in California and Arizona, due to California’s aggressive RPS and ideal climate conditions in the western US. Other western states, such as Oregon, Nevada and New Mexico are also experiencing increased utility scale development activity. The second quarter of 2012 experienced the largest growth period in US history for solar utility installations, with 742 MWs of solar PV installed. The growth is primarily attributed to two Arizona projects, Agua Caliente project (290 MW) and Mesquite project (170 MW). Once complete, the Agua Caliente project will be the largest solar PV power plant in the world. The Update and Streamline REIT Act (H.R. 5746) calls for revisions to the tax code to clarify the eligibility of renewable energy generation to allow for REIT financing. Like Master Limited Partnerships, REITs avoid the double taxation of traditional corporate structures, and are limited to investing in certain asset classes, which in this case means real property. REITs pass through their income, rather than their tax liability to investors and the dividends are treated as ordinary income to the investor. It is perhaps unlikely that such bills will be passed so late in an election year, but it may herald a new vision of renewables financing in the US. The US Department of Interior, in an effort to promote solar development has identified 17 solar energy zones across six western states totalling 285,000 acres of public lands, which will be regarded as “priority areas” for solar projects. New projects in these energy zones will benefit from faster (streamlined) permitting procedures. It is estimated that the energy zones could support 23.7GW of generating capacity. These initiatives provide a positive message for future growth in the utility scale PV market. Along with this growth will be continued improvement in equipment technology and operational practices that ensure plant reliability and enhanced performance. Sharing of best management practices as the industry evolves will further support these objectives. It is predicted that the utility scale solar market will continue to experience annual growth from 2012-2016 in the 25% to 30% range (SEIA Solar Market Insight Report Q2 2012, http://www.seia. org/research-resources/solar-market-insight-report2012-q2). This growth will be dependent on increasing regulatory certainty through standardized or streamlined permitting processes and providing access to affordable capital. Two US senators have introduced legislation that would allow renewable energy projects to benefit Figure 2: Aerial view of the Montalto di Castro solar PV farm THIS ARTICLE WAS PRESENTED AT SOLAR POWER-GEN 2013 AND HAS BEEN REPRODUCED WITH PERMISSION FROM Solar POWER-GEN. THE LAYOUT HAS BEEN CHANGED FOR THE PURPOSE OF THIS REPRINT. Article Name 3 1.2 CASE STUDY: THE MONTALTO DI CASTRO PV PLANT The Montalto di Castro PV plant is located in central Italy and occupies over 345 acres at two locations. The two locations have a combined capacity of 51 MW (45 + 6) and together represent one of the largest PV farms in Europe. This PV plant delivers enough clean energy to the grid to meet the needs of over 30,000 households annually. (See Figure 2) The 45 MW PV plant is structured in 210 building blocks, each block consisting of a self T0 tracking system, 148,488 modules, or 12,374 stings with 12 modules per string. The power is converted to AC by 68 inverters, each coupled with a 630 kVA transformer that raises the voltage to 20,000 V. The 5 inverter cabins contain inverters, transformers and auxiliary systems are distributed in two main areas of the power station. Each inverter cabin is linked by medium voltages distribution lines grouped in six main distribution rings. The three rings of each area connect to the interconnection switchyard placed approximately in the middle of the power plant. The interconnection switchyard then connects to the Terna (National Transmission System Operator) Substation by means of redundant 20,000 V interconnection lines, where two 25 MVA transformers raise the voltage to 150,000 V and allow the power to flow on the grid. The 6 MW PV plant is structured in 34 building blocks, each block consisting of a self T0 tracking system, 20,088 modules, or 1,674 strings with 12 modules per string.. The power is driven by 9 inverters, each coupled to a 630 kVA transformer that raises the voltage to 20,000 V. The 5 inverter cabins contain inverters, transformers and auxiliary systems that are linked by medium voltages distribution lines which form distribution rings that connect to the interconnection switchyard placed approximately in the middle of the power plant. The interconnection switchyard then connects to the National Transmission System Substation, operated by Terna, by means of redundant 20,000V interconnection lines, where two 25 MVA transformers raise the voltage to 150,000 V and allow the power to flow on to the grid. The Montalto di Castro PV plant is equipped with single axis tracking systems that track the sun on an east-west direction maximizing the exposure of the panels during the day. The tracking system is also capable of a special behavior of “backtracking” so that when the mutual shadings between the rows of panels begin, the tracking system does not follow the sun, but adjusts to prevent any panel shading. (See Figure 3) Figure 3: Ground level view of solar array 2.0 OPERATION AND MAINTENANCE ISSUES 2.1INTRODUCTION Compared to many other power generating technologies, PV plants have minimal maintenance and service requirements. However, a continuous O&M program is essential to optimize energy yield and maximize the lifetime and viability of the entire plant and its individual components. Many aspects of O&M practices are interrelated and significantly affect the performance of all the components in the generation chain and project lifecycle. Our experience in PV plant assessment and supervision allows us to define risks and liabilities, in terms of downtime, production performance, operational costs and time to complete the required activities, that can then be turned in opportunities to meet or even exceed the expectations of the developers and owners in terms of return on the investment. In particular, suitable planning, supervision and quality assurance activities are critical at all stages of the PV plant in order to minimize the risk of damages and outages, optimize the use of warranties, avoid dilution of resources and ultimately optimize the overall performance of the PV plant. For convenience of presentation, the O&M issues have been broadly classified in the following categories: QQ Land availability QQ Engineering features QQ Grid connection QQ Contractors’ selection QQ Extreme weather events QQ Data acquisition QQ Security QQ Housekeeping QQ Environment, Health & Safety QQ Stakeholder management. 2.2LAND AVAILABILITY Land use and availability may be an issue both in terms of the actual plant site and along the main transmission line interconnection route. These issues need to be addressed early enough in the process to avoid any problems during the operational phase. Typically, the transmission line must cross plots of land held by different owners, which can present a challenge to purchasing or leasing the land. This can ultimately result in some access or availability restrictions to properties along the preferred route. Solar parks are not typically proposed in landscapes designated for natural beauty, or protected areas of archaeological or ecological importance. Nevertheless, a careful assessment of these types of potential fatal flaws should be performed early in the project feasibility stage. In the US, environmental laws and regulations vary significantly from state to state and even county to county, increasing the need for a fatal flaw assessment when siting a project. Depending on the state or county, strict environmental requirements could result in lengthy permitting and approval processes. Proper regulatory review is critical to insure appropriate environmental studies are conducted. In the US, lands that are used for solar development are often owned by the federal or state government or are Native American tribal lands. Different mechanisms for leasing public lands are used by each State and the federal government. Many of these entities are well-acquainted with granting grazing or mineral rights but can be less familiar with the installation of utility-scale solar projects. Developers should consider the various forms of land-control rights available from the state or federal government. The Bureau of Land Management has adopted regulations specifying procedures for obtaining land rights, referred to as Right of Way (“ROW”) grants. THIS ARTICLE WAS PRESENTED AT SOLAR POWER-GEN 2013 AND HAS BEEN REPRODUCED WITH PERMISSION FROM Solar POWER-GEN. THE LAYOUT HAS BEEN CHANGED FOR THE PURPOSE OF THIS REPRINT. owner of the plant then requested authorization from the Municipality to proceed with the split of the municipality road and register it as a new land parcel which would include a perpetual easement right in favor of the plant, all without costs on the Municipality side. Thus, it is important to check in depth the cadastral documents, the ownership titles, the land acquisition and easement agreements and the length of the actual availability of the land, and possibly request accurate topographic measurements of the plant and connection line from the EPC contractor. Moreover it may help to push the EPC contractor to perform frequent topographic measures during the construction stage. Figure 4: Panel tracking system Leasing or obtaining a right-of-way on Native American tribal land is an option, particularly in the Southwest. Developers should be aware that leases and rights-of-way on Native American tribal land require approval by the Bureau of Indian Affairs. Developers should consult with the specific tribe regarding potential archaeological or other resources on the tribal land because each tribe is in the best position to evaluate which sites have cultural importance and to determine issues associated with leasing lands for solar projects. In the US, the Environmental Protection Agency has established the RE-Powering America’s Land Initiative, which promotes the reuse of potentially contaminated lands for renewable energy project development. This initiative aims to revitalize degraded land by promoting renewable energy as a productive end use, when aligned with the community vision for the site aiming to turn liabilities into assets for surrounding communities. Of the 60 sites developed thus far, 49 sites are PV solar facilities. In less than four years, RE-Powering tracked a compound annual growth rate of 40%. While the proportion of renewable energy projects on contaminated lands is relatively small, RE-Powering is seeing a marked trend, showing that this land development strategy is gaining momentum. Agricultural land may be suitable for solar farms, especially if it is not used for arable applications, since grazing remains possible within array fields and indeed is particularly synergistic as it prevents vegetation growth which may in due course shadow the solar arrays. Solar farms have been proven to even have the potential to increase the biodiversity value of a site if the land was previously intensively managed. However, it should be noted that political and legal pressure to preserve agricultural lands, particularly in California, are creating controversies when attempting to permit utility scale projects on agricultural lands. In the last few years, concerns over conversion of agricultural land for utility use have begun to gain political steam putting pressure on local officials approving projects. Early management of the above issues may result in a more efficiently managed project from both a time and cost perspective for the permitting, construction, start-up and operation processes. Any grant of a property right must contain certain legal elements no matter where the property is located in the US. Many states require the grant of a solar easement to describe the dimensions of the easement, the estimated amount of sunlight directed to the system, any permitted shading by vegetation and other plantings, the corresponding reduction in access to sunlight, and any proposed compensation to the grantor of the easement. The solar easement must also contain state-specific requirements. A state’s focus may be affected by terrain, character of the area or weather. Some states may be height- or design-sensitive (California, Colorado) or locale-sensitive (Hawaii), or may focus on visibility and placement (North Carolina), orientation (Wisconsin), zoning (Rhode Island), or setback issues (Oregon). 2.3ENGINEERING FEATURES Many important technical aspects concerning the plant should be addressed in the planning and design phases. Issues such as the selection between fixed mount or tracking systems, and centralized (maximum production) or distributed (maximum availability) conversion systems, and the possibility to have flexible control over the power production, in relation to the electricity market demand, should be carefully evaluated in terms of potential implications well before the plant enters into operation. As a practical example of above issues, in our case history the facility was designed to occupy a former cattle-track owned by the Municipality, not recognized until the plant was actually built. The A common choice at the design stage is the type of tracking system. Mono-axial tracking systems have a better yield compared to fixed systems (up to 25%), but may cause an increase in maintenance costs due to the presence of moving parts and management of a larger number of spare parts. In our experience, the incidence of additional O&M costs over a two year timeframe is quite small, but could increase with time. (See Figure 5) Figure 5: Terna switchyard THIS ARTICLE WAS PRESENTED AT SOLAR POWER-GEN 2013 AND HAS BEEN REPRODUCED WITH PERMISSION FROM Solar POWER-GEN. THE LAYOUT HAS BEEN CHANGED FOR THE PURPOSE OF THIS REPRINT. Figure 6: Damages from heavy rainfall Considering the effect on O&M activities as well as costs, a choice can be made between a system with a higher number of smaller electrical components, particularly inverters and transformers, or a system with larger but fewer components. With the latter configuration the production is maximized, but in the case of failure of a component, replacement may be more difficult due to poor availability or long waiting time. Because of the potential yield loss that could result, it is our opinion that the choice of the size of the electrical equipment units should be based on their actual commercial availability and guaranteed supply time. Furthermore, during the operation of the plant it is necessary to have good capability to control and regulate the energy output on the basis of the actual electricity market demand. With the typical current plant configuration, this regulation is only possible by reducing the plant output. As a possible solution, the use of a suitable energy storage system would allow a better flexibility in order to match the actual demand in either case of reduction or increase. 2.4GRID CONNECTION The issues related to the grid connection can often be crucial, both in terms of continuity and convenience of the energy delivery. A reliable and proactive relationship with the transmission system operator can definitely help, especially when unexpected events or emergencies occur. Interruption prevention measures, as well as clear contingency plans and restart procedures, are key to minimizing plant downtime. Failures caused by either faults on the transmission line to the interconnection switchyard or major interruptions downstream in the utility area should be identified and communicated quickly. (See Figure 5) When emergencies occur, there may be many enti- Figure 7: Repair of connection lines ties involved in the location and repair of the failed equipment. Different areas of the plant and utility involve coordination of the utility operators, O&M contractors, substation workers, local authorities and health and safety agencies, which need to be properly trained and prepared to manage the situation in a coordinated and knowledgeable manner to minimize downtime and maximize plant availability and production. a number of factors, such as: In our experience, preventive maintenance training and sharing of plans and procedures with the other stakeholders play a huge role in addressing and resolving unscheduled outages and emergencies in the shortest possible time. A critical issue is to make sure that all the operations and activities that a certain contractor is responsible for are identified early enough and that the suitable conditions or permits are in place. Another aspect that is relevant to the relationship with the transmission system operators is the management of energy delivery required by new dispatching regulations and procedures. Recently the Italian authorities required operators to predict the energy fed to the grid day by day, to adopt a system to modulate the production in case of emergency and to change the calibration of the inverters to support the national electricity grid during transient voltage or frequency variations or to compensate excessive reactive power. These adjustments are necessary due to the fast growth of the production of energy from non-programmable renewable energy sources. A positive relationship with the transmission system operators can help to implement solutions and investments in the right direction to minimize the resources necessary to meet these requirements. 2.5 Contractors’ selection The O&M activities are complex and usually involve a series of different skills and experience that may require the contribution of various contractors and sub-contractors. These should be selected based on Familiarity with the site and equipment; Proximity of the contractor’s premises; QQ Number and qualification of staff; QQ Level of experience and references; QQ Financial status; QQ Health and Safety record; QQ Proper permits and licenses. QQ QQ We recently had an issue with the contractor in charge of panel cleaning who had not obtained the required licence to extract groundwater from a public well. This resulted in a delay of the cleaning activities and consequently in a certain loss of production. 2.6Extreme weather events Extreme natural events, particularly those related to climate change, such as hailstorm, typhoons and floods, may cause serious damage in solar plants. Severe structural and economic losses may be incurred if specific components are damaged such as structural elements, electrical parts and components, control and inverter rooms, and connection lines. Flooding can affect different functions of the plant, both on the electrical generation side and on the balance of plant (BOP) side, including connection lines continuity, accessibility of different parts of the plant, erosion of roads and other infrastructures, fence functionality and interference with electrical, data monitoring and security systems. In one particular case, the effect of excessive water run-off due to an extreme rainstorm created insta- THIS ARTICLE WAS PRESENTED AT SOLAR POWER-GEN 2013 AND HAS BEEN REPRODUCED WITH PERMISSION FROM Solar POWER-GEN. THE LAYOUT HAS BEEN CHANGED FOR THE PURPOSE OF THIS REPRINT. Figure 8: Elevated inverter room Figure 9: Drainage system, perimeter fence and security cameras bility on a slope which washed out the ground that covered both the main and backup underground lines which ran alongside each other, for a length of around 200 meters and subsequently caused the interruption of production for a few days until the ground cover was stabilized and the lines repaired. tion (SCADA) systems might not always be reliable due to possible temporary losses of connection. A regular check of the data, based on the physical reading of the meters to compare the records is strongly advised to confirm the final data. Due to the same weather event, the main control room was also partially flooded. In general, these types of events can be prevented by running a comprehensive risk assessment of the possible impacts on the continuity of the plant resulting from climate change, and particularly extreme weather events. (See Figures 6 and 7) Redundant systems for evacuation and connection lines, as well as for monitoring and security systems, have to be carefully planned and designed in order to constitute a viable alternative to the main systems and guarantee the overall continuity of the plant, under any circumstances. Critical rooms, particularly those containing control systems and critical electrical equipment, should be designed to be raised above the floor of the site and above the possible maximum elevation of water. (See Figure 8) Run-off and drainage systems should be designed for extreme events to guarantee the functionality of civil infrastructures, such as roads and fencing, and grid connection systems. (See Figure 9) 2.7Data acquisition Data acquisition is a crucial issue to be considered to track and maintain optimal system and plant performance. Accurate and reliable monitoring data are also necessary to comply with regulatory reporting requirements. Based on our experience, production data collected through the Supervisory Control and Data Acquisi- Another aspect related to data acquisition is the implication on the contractual goals set for the O&M contractor in terms of guaranteed Performance Ratio, i.e. the overall plant production efficiency. The minimum guaranteed parameters are usually based on relatively safe assumptions by the contractor and therefore an accurate technical assessment is needed to avoid an overall low performance objective. The assessment of the objectives of the contractor is essentially based on the measurements of the meteo station. iIt is critical that these are representative of the actual situation and therefore the instruments need constant calibration and certification. It is also critical that the dust cover conditions of the irradiance sensors are consistent with those on the panels, in order to be comparable, i.e. cleaning should preferably be done at the same time. It could also be advisable to keep additional sensors to be cleaned more frequently in order to act as benchmarks for the optimum values of irradiance. The cleaning schedule can then be optimized based on the difference between the measured irradiance in the two sets of sensors. As a final confirmation of the data, the continuous correlation between different sources of the same data (e.g. different meteo stations on site) can also supply an early warning of problems in the data acquisition systems. 2.8Security Security systems are essential for a suitable operation of a solar farm in order to avoid damages and possibly plant downtime from theft and vandalism. In fact, a recent study on German PV plants shows that up to 16% of the monetary impact of all the possible damages are related to these aspects. The access of unauthorized people to the plant has to be prevented both for security and safety reasons. In order to minimize the occurrence of such events a suitable balance between a remote control system and on site security personnel should be achieved, depending on the size of the plant, the morphology and extension of the site and the general environmental context. (See Figure 10) The anti-intrusion software typically used is able to detect moving objects, but not to recognize false alarms due to movements not necessarily generated by unauthorized access to the site. In our case, when the security operator receives an alarm, he has to verify the real source of the alarm and then assign the proper category/level of attention, based on a predefined classification (i.e. people, animals, vegetation, weather), and record the event accordingly. To address this issue, we are planning to upgrade the software to learn from the past events and to be able to systematically discern between a real and a false alarm, at least for repetitive movements. Figure 10: False alarms detection software THIS ARTICLE WAS PRESENTED AT SOLAR POWER-GEN 2013 AND HAS BEEN REPRODUCED WITH PERMISSION FROM Solar POWER-GEN. THE LAYOUT HAS BEEN CHANGED FOR THE PURPOSE OF THIS REPRINT. Thus, in our experience a specific combination of operators, video cameras and dedicated software has to be implemented to insure a sustainable level of security of the plant, and specifically manage alarms, discerning between real and false ones. 2.9Housekeeping Typical housekeeping activities on a large PV plant include a variety of concerns, such as management of water run-off and drainage, cleaning of panels, control of vegetation, maintenance of civil structures and roads. In our case, we have successfully adopted a very sustainable way to control the development of vegetation, especially in the areas where the modules are located, by letting a substantial flock of sheep live and graze within the plant boundaries. Besides the positive effect on cultural and social continuity (the shepherds did not have to move away from their historical land), we can avoid any damage of the panels associated with the use of mechanical equipment typically employed to trim the vegetation. Another common issue with PV plants is the presence of rodents and their negative effect on cables integrity. In this case, we found out that most of the rats on site were actually introduced at construction stage through the containers used to deliver the different pieces of equipment. Suitable preventive measures include therefore a more careful control of this specific issue at the equipment delivery stage and the use of reinforced cables to ideally withstand the bites. At the operational stage, additional measures may consist in intensifying the frequency of pest control routines to mitigate access by animals and filling the cable connection pits with sand in order to prevent theft of cables. (See Figure 11) In some instances the preventive measures may actually clash with specific permit requirements. At the Montalto di Castro Plant, the operating permit required the plant owner to create holes in the fence in order to allow land continuity for the passage of local fauna, typically medium-sized animals. Once again, having a solid relationship with the local authorities proved to be very helpful and a solution was finally reached. In fact, we were able to demonstrate, through a well-documented photographic survey, that there were already enough pathways through the fence, naturally created by small soil settlements or drainage ditches, and therefore no additional work was necessary. Figure 11: Sheep grazing in the panels area In warmer climates, the temperature in the inverter cabins, as well as in spare parts storage rooms, can raise significantly thus reducing the efficiency of the equipment, therefore it is advisable to design suitable air cooling system, especially for the former. In order to be effective, the cooling system typically needs to be of significant capacity, thus requiring a high energy input. It is then critical to insure its efficiency through an appropriate maintenance program, suitably integrated in the O&M activities. A possible optimization of the system design could entail a proper management of hot and cool air flows within the cabin, by considering the actual heat transfer and flow direction between the equipment and the environment, in order to maximize the air cooling equipment yield. In the photo below, for instance, the hot air exhaust that comes from an inverter is conveyed out of the cabin without mixing with the fresh air that comes from the cooling system. (See Figure 12) As a good practice during the operational stage, the temperature in the cabins should be monitored constantly and recorded through the SCADA system so it can represent an early warning in case of problems. 2.10Environment, Health and Safety There are potential environmental and health and safety issues associated with the full project life cycle that need to be addressed at all stages of development. In particular, we have identified oil spills from the transformers and noise in the inverter cabins as two of the most significant impacts to be managed during the operation of the plant. All transformers at some stages may be subject to leaking, which can be prevented through proper monitoring of their oil temperature, pressure and level, possibly with the aid of an automated system Figure 12: Air temperature management in the inverter cabin connected to the general control software, which in turn leads to a proper plan for routine maintenance. We actually experienced a few oil spills from transformers, but a suitable containment system had been designed in the space under the cabins which allowed us to manage the issue properly through the planned disposal of the resulting waste. With reference to specific health and safety hazards, the inverters noise may be quite high, especially in specific periods of the day and of the year. The exposure of the O&M operators when performing activities inside the inverter room should be carefully controlled, through a proper assessment of the actual equipment emissions. In our case, after having identified the issue, we requested specific personal protection equipment to be included in the contractor’s health and safety plan. THIS ARTICLE WAS PRESENTED AT SOLAR POWER-GEN 2013 AND HAS BEEN REPRODUCED WITH PERMISSION FROM Solar POWER-GEN. THE LAYOUT HAS BEEN CHANGED FOR THE PURPOSE OF THIS REPRINT. 8 Article Name 2.11Stakeholder management Considering the local context, it is always advisable to proactively engage and involve the local community and key stakeholders in order to keep them informed on the plant development and operation at all stages, build positive, trusting relationship with the community and relevant authorities, provide adequate avenues for community feedback and ensure social issues are identified at an early stage, managed and, where feasible, resolved. Proactive and consolidated stakeholders communication lines can definitely improve the management of a number of issues during the plant operation. In terms of dealing with local authorities and regulators, general administrative procedures, as well as contingencies and emergencies, can be managed in a much more straightforward way if the quality and reputation of the plant operator allow establishing a relationship based on trust. The same holds true for communities or neighbours around the plant, where favourable and personal relationships can lead to sharing of information that would not be available otherwise and to peaceful resolution of minor conflicts. In the case of the former cattle-track described earlier, the situation became even more complicated since the authorities had previously authorized another plant to place its connection line under the cattle-track. The other plant’s EPC contractor was under a tight schedule to connect the system in order to maximize revenues. Thanks largely to solid relationships held with the local authorities we were able to avoid the positioning of the line under our plant by the other plant’s EPC contractor, who could only obtain authorization to modify its route. Another example of the use of a proactive and positive relationship with the authorities was given earlier on, when presenting the issue of having to insure the land continuity through the plant for the local fauna. We were also able to witness that if local contractors and citizens are engaged in the operations, the community will be happy to help if needed. For example, as mentioned earlier, the previous owners of some plots of land were shepherds. We agreed with them to let their sheep graze inside the plant. This gives many advantages to the operation of the plant, since by controlling the height of the vegetation in such a sustainable way, the risk of fires or panel shading is greatly reduced. Moreover the shepherds and other local people typically provide useful feedback about the local situation and its evolution. 3.0CONCLUSIONS Our experience in the assessment and supervision of the operation of large scale solar farms is presented through the case study of the 51 MW PV plant in Montalto di Castro in Italy. This case shows that an integrated approach to planning, execution and monitoring of the activities can lead to an optimal performance of the plant. The integration should be accomplished throughout the project lifecycle phases (siting, development, design and operation) and across the different tasks within each phase, in order to identify all the possible synergies, thus minimizing the risks and leveraging the opportunities. All the O&M activities can be recognized as related to upstream lifecycle phases and should be properly considered at the relevant stage. For instance, a proper response to extreme weather events implies the consideration of the associated issues at the siting and planning stage, through the assessments of the risk and the consequent design mitigation measures, and the presence of an adequate response plan in terms of emergencies and repair procedures. In the operation phase, it would still be possible to address most of the critical issues presented in the paper. Periodic audits of the plant can help identify weak points in the systems or margins for their improvement, consequently finding effective solutions. Such audits can be run at a qualitative level by conducting reviews of the design and operational documentation, including historical performance data and records of anomalies, visual inspections of the plant systems, assessments of the operational activities and plans in place, random testing of representative electrical components and direct measurements of key plant performance indicators. Critical issues can then be reviewed at a deeper, more quantitative level with further targeted testing and development of specific analytical models. Based on our international work on PV plants, we can conclude that many of the concepts and practices that have been presented in this paper, suitably adapted for general context and site specific conditions, are applicable to diverse and different contexts, including similar large scale developments in the US. In fact, based on the history of PV plants in Europe, a large overall capacity of PV plants could be developed in a relatively short time period, over 2 to 3 years, but will have to be operated effectively for a much longer time, in the order of 20 years, during which period the existence and application of sound plans and practices will be able to effect the real success of the project. Thus, a thorough planning, execution and monitoring approach to O&M activities will optimize plant performance and maximize production yield, with reference to the potential capacity given by the engineering and design features of the project. About Golder As a global, employee-owned organisation with over 50 years of experience, Golder Associates is driven by our purpose to engineer earth’s development while preserving earth’s integrity. We deliver solutions that help our clients achieve their sustainable development goals by providing a wide range of independent consulting, design and construction services in our specialist areas of earth, environment and energy. For more information, visit golder.com. THIS ARTICLE WAS PRESENTED AT SOLAR POWER-GEN 2013 AND HAS BEEN REPRODUCED WITH PERMISSION FROM Solar POWER-GEN. THE LAYOUT HAS BEEN CHANGED FOR THE PURPOSE OF THIS REPRINT.
© Copyright 2026 Paperzz