DECISION
APPROVING MASTER PLAN OF DEVELOPMENT OF VIETNAM GAS INDUSTRY IN THE
2015 PERIOD, AN ORIENTATION TOWARD 2025
THE PRIME MINISTER
Pursuant to the Law on Organization of Government dated December 25, 2001;
Pursuant to the Decision No.386/QD-TTg dated March 09, 2006 of the Prime Minister approving
“the development strategy of Vietnam oil and gas industry in the 2006 – 2015 period, an orientation
toward 2025”;
Pursuant to the Decision No.223/QD-TTg dated February 18, 2009 of the Prime Minister approving
“Development plan of Vietnam oil and gas industry in the up to 2015 period, an orientation toward
2025”;
At the proposal of the Minister of Industry and Trade,
DECIDES:
Article 1. To approve the master plan for developing Vietnam gas industry in the up to 2015 period,
an orientation toward 2025 with the following main contents:
1. Development viewpoint
To develop synchronously, efficiently the gas industry through the promotion of domestic resources
and to strengthening international cooperation, promote the decisive role of the state in investment
in infrastructure of gas industry.
To develop gas industry on the principle of using economically, efficiently and rationally the
domestic natural resources; to strengthen import to ensure energy resource for sustainable national
development.
To promote investment in deep processing of natural gas and diversify products to enhance the use
value of gas and the efficiency of gas products in the economy, reduce the proportion of imported
LPG.
To develop infrastructure system on the principle of using the maximum capacity of existing
infrastructure system (pipelines, collection stations, processing,...).
To develop gas consumption markets under the market mechanisms regulated by the State and
gradually integrate into the international and regional gas market.
To contribute the long-term energy security assurance for the country and implement the policy of
sustainable development.
2. Development targets
On exploration, mining of gas in the country: to promote exploration, appraisal in order to correct
potentiality, natural gas reserves for put early detection of commercial gas into exploitation; to strive
to reach exploitation production of domestic natural gas over 14 billion m3 per year in 2015 and
reach 15 to 19 billion m3 per year in the 2016 - 2025 period.
On the import of gas: urgently promote activities of negotiation and preparation of the investment in
infrastructure for importing LNG in order to ensure balance of supply and demand of domestic gas;
and to give priority to implement the project of first LNG import in the South to ensure adequate
supply, maintenance and development of gas markets in the South; to research and implement LNG
import projects in the Northern and Central regions.
On development of infrastructure of domestic gases industry: to complete gas industrial
infrastructure of southern area; to form and develop gas industrial infrastructure in the northern and
Central regions, gradually build up network system connecting inter-regional gas pipelines, joint
sectors; to boost investment in the projects to build plants of processing and processors (GPP) to
deeply process natural gas exploited in the country (separating ethane, LPG, condensate, ...) to
improve the efficiency of gas use and make savings in resource use.
On LPG industrial development: to invest in development of projects to produce domestic LPG (gas
processing plants and refineries), to reduce proportion and gradually replace imported LPG; to
expand the existing storage capacity associated with the deployment of construction of new projects
to meet domestic demand with a size of about 1.6 to 2.2 million tons/year in 2015 and reached a size
of about 2.5 - 4.6 million tons/year in 2025; to ensure to meet minimum reserve requirements over
15 supply days in the up to 2015 period.
On development of gas consumption markets: to continue the development of the electricity market
as the core markets of gas consumption (including LNG) with the proportion of about 70% - 85% of
the total gas production, meeting the input gas fuel resource to produce electricity; to promote use of
gas and gas products in petrochemical production, urban activities and transport to help the
assurance of the environment and improve the added value of the gas; to strive to develop gas
market with a size of from 17 to 21 billion m3/year in 2015 and from 22 to 29 billion m3/year in the
2016 to 2025 period.
To combine harmoniously the resources of the State, the economic sectors for developing
synchronously, efficiently and sustainably the stages in the gas industry.
3. Development orientations
a) Exploration and exploitation of domestic gas
The activities of exploration and exploitation of domestic gas comply with the Decision
No.223/QD-TTg dated February 18, 2009 by the Prime Minister approving development plan of
Vietnam's petroleum industry in the up to 2015 period, an orientation toward 2025.
b) Gas collection pipeline system
- The up to 2015 period
Cuu Long basin area: to develop collection pipeline systems of natural gas/petroleum gas from the
mines Rong, Doi moi, Te Giac Trang and Hai Su Den, Hai Su Trang, connecting to the central
compressed air rigs of the mine Bach Ho; pipeline connecting the Su Tu Trang mine with producing
gas rig of the Su Tu Vang mine, expected capacity of around 1.5 billion m3/year. Natural
gas/petroleum gas of Block 01 & 02 areas and the neighboring Blocks will be collected to
supplement the gas supply for the pipeline system of Rang Dong – Bach Ho – Dinh Co. Nam Con
Son basin area: to deploy the construction of the pipeline systems to collect gas from the mines Hai
Thach – Moc Tinh, Lan Tay, Thien Ung, Chim Sao and other mines for additional provision of
about 3 billion m3/year for the market of southern region.
Malay - Tho Chu basin area: to build pipelines connecting the mine Hoa Mai and Block 46 with the
pipeline system PM3 - Ca Mau from 2013. Gas of the mines discovered of Block B & 48/95, 52/97
and the adjacent Blocks 46, 50, 51 shall be sent to the pipeline Block B - O Mon and PM3 - Ca Mau.
Northern area: to connect gas resources of the northern area of the Red River basin (Block 102-106,
103-107,...) into clusters and research to place central technology rig at the Thai Binh mine (Block
102 to 106 ). To build the pipeline to collect gas from the mines of the Block 111, 112, 113 to the
central gas processing rig of Block 113.
- The 2016 – 2025 period
Southern area: to connect the mines Rong Vi Dai , Hai Au, Thien Nga and nearby mines to
supplement gas supply source for the pipeline system Nam Con Son -1 and Nam Con Son -2 in the
2017 to 2019 period; to build the pipeline system connecting the mines of Block 46-2 such as Rach
Tau, Khanh My, Phu Tan with the pipeline system PM3 - CAA the basin Malay - Tho Chu from
2019; to build the pipelines from the Phu Khanh basin to the Mekong basin, from basin Tu Chinh Vung May to the Nam Con Son basin on the basis of the results of exploration in this area. Southern
area of Red River basin: in case of having appropriate technologies for development and
exploitation of mines with high content of CO2, to send gas back to central gas processing rig on the
Su Tu Bien mine (Block 118) to collect gas from the nearby mines as Ca Heo (Block 119), 115-A
(Block 115).
c) The system of offshore gas transportation main pipelines
- The up to 2015 period
To implement the construction investment by the stages of the pipeline system of Nam Con Son-2
(Hai Thach and Moc Tinh, Thien Ung to Vung Tau) put into operation from 2013 to 2014 with a
design capacity of 7 billion m3/year to transport timely gas and commercial condensate from the
mines Hai Thach, Moc Tinh, Thien Ung, as well as net mines discovered in the Nam Con Son basin,
Tu Chinh - Vung May to the shore for progressive gas consumption demand of the Southeast region.
To complete the construction of pipelines system Block B - O Mon put into operation from 2014, in
accordance with the progress of the development of gas resources in Block B area; and arrange the
offshore, onshore holding points in southwest region where the pipeline system passes through to
develop industrial gas consumers.
Actively research and implement the construction of gas pipeline systems in the northern rea of the
Red River basin (from the mines Thai Binh, Ham Rong of Block 102 to 106, Bach Long, Hong
Long, Hoang Long of Block 103 - 107/04) to the area of Thai Binh province first aiming to supply
gas to the existing consumption market in Thai Binh province and gradually expand to the other
provinces/cities of the Red River Delta (Ha Noi, Hai Phong, Nam Dinh, ...).
To develop pipeline system to transport natural gas to the southern area of Red River basin.
Depending on the appraisal results, plan to build a gas pipeline system from the mine Bao Vang
(Block 113) to Quang Tri province, with a length of about 120 km, the design capacity of about 1-3
billion m3/year.
- The 2016 – 2025 period
Based on the results of the exploration of gas resources of the Phu Khanh basin area with the ability
to exploit expected about 1.5 billion m3/year from after 2019, research to build a new pipeline
system in the after 2019 period to lead gas from the Phu Khanh basin to the Son My area (Binh
Thuan) and connecting with pipeline system collecting Bach Ho mine.
To study the possibility of transporting gas from the added deposit part (if any) in Block B & 48/95,
52/97 and the adjacent mines.
To develop the pipeline system to transport natural gas to the southern area of Red River basin.
During this period, plan to build a gas pipeline system from the mines of the Blocks 117 - 118 - 119
to Quang Ngai/Quang Nam province with a design capacity of about 2-4 billion m3/ year.
To further study the plan of gas import via the TRANS ASEAN system and through the pipeline
system PM3-CAA, Block B, Nam Con Son 1 or Nam Con Son 2.
d) The onshore gas pipeline system
- The up to 2015 period
To continue the research and deployment of the pipeline project Phu My - Ho Chi Minh City after
completion of construction investment phase 1. To research and develop the pipeline system from
the Nhon Trach power plant to Nhon Trach Industrial Zone, from the Hiep Phuoc Power Plant to the
Hiep Phuoc Industrial Zone, Thu Thiem Industrial Zone.
Based on balance of gas supply and demand between two areas, to research the construction of the
pipeline project to connect East - South West from the Hiep Phuoc to O Mon to have the
infrastructure to make gas sources generation between the two areas of the Southeast and Southwest,
to provide gas for the industrial household along the pipeline; the designed capacity of about 2-5
billion m3/year, the total length of about 180 km.
To invest in pipeline system linking from Southern LNG storage to the existing GDC to transport
imported LNG gas and mix it into the southern air supply systems.
In the North, build an onshore pipeline system with a capacity of about 1-3 billion m3/year, leading
gas to the gas consumers of Thai Binh Province.
To develop low pressure gas distribution network all over the country to develop the use of gas in
the fields of industry, civil use, ... to ensure a stable and safe regulatory of gas system, added value
for gas projects, while contributing to the modernization of the economic, social branches,
environmental pollution reduction.
The 2016 - 2025 period
To continue the research and deployment of stage 2 of the pipeline project Phu My - Ho Chi Minh
City in the direction of leading gas to the industrial zones of Dong Nai, Bien Hoa, Binh Duong and
the Thu Duc Power Plant.
To research and build a gas pipeline from Hiep Phuoc - Binh Chanh - Duc Hoa to expand gas supply
ability to the gas consumers in Long An, south and southwest of Ho Chi Minh City, is expected for
operation in 2017.
On the basis of ability to increase gas supply source in the North Central (from domestic or imported
source) and development planning of future gas market, consider to build a closed pipeline system
onshore of the Red River delta region connected between Thai Binh - Hai Phong - Hanoi with a
capacity of transportation of about 1-2 billion m3/year. Pipeline system with ability to connect
additionally with pipelines transporting imported gas from LNG storage of Nghi Son - Thanh Hoa in
the case of project to import gas to this area is implemented.
Besides, in case of additional gas discovery in the Blocks 111 to Block 120, gas supply source will
be added to the Central Central, gradually research expanding development of consumption market,
plan the system of the onshore transportation pipeline, connecting between the two areas of markets
expected to develop first in central region as Quang Tri and Quang Ngai/Quang Nam province to
supply gas to Da Nang city and Thua Thien Hue province.
e) Gas processing plant (GPP)
- The up to 2015 period
The southeast: to invest in upgrading and expanding 02 existing gas treatment plants at Dinh Co,
and actively implement the new investment project in 01 gas processing plant in sync with the 2nd
pipeline project Nam Con Son from 2013 to 2014 to increase the use value of gas on a basis of
consistent with the situation of increasing exploited gas production of the Cuu Long and Nam Con
Son basins according to the plans to predict gas exploitation production.
The southwest: to implement the GPP investment project near the center of gas distribution Ca Mau
to handle common gas source from the pipeline system PM3 and Block B to Ca Mau, to extract
ethane, LPG and condensate, increase the natural resource values. Northern Area: to research and
deploy to build GPP in Thai Binh and Quang Tri provinces at the same time with the construction of
pipeline from the Blocks 102 to 106 and 111 to 113
The 2016 - 2025 period
The area of Quang Ngai/Quang Nam province: to research, build newly GPP with traffic estimated
of about 1-4 billion m3/year, operated from 2018 to process gas from the Blocks 115, 117, 118, 119
and the other Blocks of the southern area of Red River deposit basins.
e) Storage of imported LNG and gas re-gasifying
- The up to 2015 period
Expeditiously study and deploy the first storage project of LNG import of Vietnam in the Southern
region with a stage 1 size of about 3-5 billion m3/year. Actively carry out to research the
construction of onshore LNG storages at the locations with suitable conditions of ports for capability
to receive the LNG ships.
In the North, to research investment in building one to two LNG storage ports and to re-gasify at the
locations with convenient infrastructure such as Hai Phong and Thanh Hoa.
The 2016 - 2025 period
To continue to implement the phase 2 of existing LNG storage in the South with a size of about 7 to
10 billion m3/year, while considering the possibility of new building of one to two LNG storages at
other locations across the country.
g) Hubs LPG storage
The total capacity of LPG storages need to be supplemented at least on a national scale in the 2011 2015 period of about 14,000 to 27,500 tons, the 2016 to 2025 period of about 54,000 to 85,000 tons.
To expand the capacity of the existing storages, and implement new projects of construction for the
capacity to reach at least 75,600 to 85,600 tons in 2015 and about 127,600 to 176,600 tons in 2025.
The hub LPG storages concentrated major in some provinces/cities of each region such as Hai
Phong (North), Thanh Hoa, Ha Tinh (North Central), Da Nang, Quang Ngai (Central) and Ba Ria Vung Tau, Dong Nai, Ho Chi Minh city (South) , …
Total investment capital needs
Preliminary estimates, total investment capital needs for developing infrastructure of Vietnam gas
industry in the up to 2015 period, an orientation toward 2025 is about 9 to 12.5 billion USD under
the basic and high plans. In which, the 2010 - 2015 period, it is needed about 5.3 to 5.4 billion USD,
the 2016 to 2025 period of about 3.6 to 7 billion USD.
The list of investment gas projects in the up to 2015 period and an orientation toward 2025 are
described in the Annex.
4. The solution, the policies of implementation of the Plan
a) Policy of gas prices
- To develop evaluation methods to sell gas to the consumers reflecting the sufficient costs of actual
provision, but it must reflect the proper competitive value of gas with the gas fuels on the market.
- The study the application of the system of "general overall price evaluation" mixing gas from
natural gas sources and from domestic and imported LNG to work out a price rate/cost of general
wholesale gas on the market. Since then, set up the sale price for final consumers, depending on
consumers in the economy, the proportion of consumers on the gas market and the acceptability of
each consumer.
- To develop and promulgate the route and tariff framework for market price access applied to
strategy consumer groups (such as electricity, chemicals, transport) and the cost of gas pipelines (in
particular according to its output level and geographic area).
- The price determination for each stage in the gas industry is made on the point of costs recovery
and having a reasonable profit.
- To apply a policy of gas-buying price determination from the gas producers/importers on the basis
of cost recovery and reasonable profit rate in the up to 2018 period, then gradually promote the
application of competitive gas prices mechanism to determine the sale and purchase price of gas.
- The competitive gas prices calculated for the electricity consumers, transport are calculated with a
long-term vision and by the method with considering environmental protection cost.
b) Solution, policies on gas market models
- To continue to maintain the implementation of market model of a unique wholesaler in the up to
2020 period, gradually develop the gas industry by the competitive wholesale market model.
- To specify and publicize the management mechanisms and regulation of the sale and purchase
activity of the Vietnam national oil and gas Group to "the unique gas wholesaler" create added value
on the gas lines.
- To study and promulgate regulations on regulating air transportation activities to ensure the
management and operation safely and efficiently.
c) Measures and policies to encourage investment
- To combine harmoniously the state investment capital and mobilize maximum participation of the
domestic and foreign private sector to promote the exploration of natural gas in the country, to
develop synchronously, efficiently and sustainably the processes of the gas line.
- To study and propose the application of the incentive policies for oil and gas contracts in the basins
of Red River, Phu Khanh, Malay - Tho Chu, Tu Chinh - Vung May, Truong Sa - Hoang Sa to
promote development of mining small-scale, deep-water mines, mines with high content of CO2 to
recover the natural gas resources.
- To encourage the mine owners, importers of gas, the major gas consumers in joint investment of
gas projects integrated between upstream stage with the stages of middle stream and downstream to
the secondary stage.
- To research and put the investment projects related to collection, transportation, processing,
storage, trade, import of gas, development of using gas and the ability product for transport, urban
city gas ...into the list of sector specially encouraged investment in and specify the incentive policies
for these projects.
- To research and develop policies and mechanisms to ensure safety, simplify procedures and
support arrangement of capital for the gas projects.
d) Solution, self-development policies
- The government continues to invest at the rate of dominant capital in the petroleum enterprises of
Vietnam operating in the field of gas infrastructure.
- To have the policies to develop the units of consultancy, design and construction of gas reserves
and gas pipeline networks.
đ) Measures and policies on science and technology
- To promote economic - technical study and receipt of transferring technology handling and
processing gas of high CO2 content and raw materials, fuel made from natural gas.
- To study the matter of gas reserve, plans linking to the gas pipeline network of the nation and
ASEAN countries.
- To invest, research, transfer technology using CNG, LPG widely in the field of transportation.
- To study and promulgate national regulations on air quality transported through the pipeline
system, terminal; distributed and consumed in Vietnam and design regulations of the natural gas
infrastructure program.
- To develop and promulgate provisions, standards, regulations, rules and norms ... in the collection,
import, export - transportation - handling - storage - distribution of gas and gas products to ensure
the gas industry to operate safely, conveniently and efficiently.
- To prioritize funding in the Ministerial-level, State- level scientific research programs of gas
industry sector.
- To research, disseminate and implement strategies, policies of management of the countries to
draw lessons for Vietnam’s reference to promote and improve the efficiency of gas industry.
e) Human resource development solutions
- To train to improve the qualifications of staffs, engineers and workers working at the units of
existing gas trading, production; additionally train for the weak, deficit stages; to associate with the
forms of training such as new training, in-place practice training, seminar training, training by
projects, by researching theme in a systematic manner from basic level to high level.
- To develop the training plan and plan to use leading, key staffs through collaboration with the
specialized training institutions of international prestige.
- To apply the appropriate policies to attract overseas-based Vietnamese and foreigners who have
experience in the oil and gas activities to work in Vietnam.
g) Measures for safety and environmental protection
- Strictly abide by the provisions of the legislation on safety, prevention of fire, explosion, working
conditions, industrial hygiene, and supply of labor equipment, high-tech use, and safe equipment;
periodically check the system of control, automatic alarm.
- To develop, update, improve, and maintain regularly the response plans in case of emergencies: the
plans of prevention of fire, explosion, control, emergency response, the case of accidents, natural
disasters...
- To enhance the communication, education, knowledge dissemination, training on safety and
environmental protection in the oil and gas activities for officials and employees of oil and gas
industry and the community.
- To coordinate the environmental protection measures in the gas industry with environmental
protection measures in the other activities in the same area of operation. To synthesize, analyze,
evaluate, and implement the necessary measures to ensure workers’ health, actively prevent and
treat, handle timely the cases of occupational diseases.
- To invest much in the stage of basic investigation in the areas of operations or projects for
assessment and environmental protection measures
h) Solution of security and national defense
- To strengthen coordination among investors of gases industrial projects with the Ministry of
Defense, the Ministry of Public Security, Ministry of Foreign Affairs to actively prepare and
implement the fine tasks of protecting the sea area and national sovereignty, ensuring security for
the deployment of activities of upstream, middle stream, downstream of gas industry.
- To coordinate between the Vietnam national gas and oil Group, the Ministry of Defense, Ministry
of Public Security, Ministry of Foreign Affairs to carry out petroleum activities in general within the
framework of the "oil and gas diplomacy", to take advantage of the relationships between
governments to attract investment, create security shield by the works involving foreign investment
Article 2. Organization of implementation
1. Ministry of Industry and Trade
- To direct and supervise the deployment, implementation of the overall development plan of the
Vietnam gas industry in the period toward 2015, an orientation toward 2025, first, to focus on
implementing effectively investment projects in the period toward 2015.
- To preside over and coordinate with the concerned ministries, branches to direct the Vietnam
National oil and gas Group to strengthen and promote the exploration and exploitation in the regions
with great potential oil and gas to increase reserves of verification, to ensure to reach the target of
gas exploitation production in the planning period.
- To preside over and coordinate with ministries and branches in directing the Vietnam National oil
and gas Group to deploy the LNG import project, construction of ports, LNG storage and regasifying to raise the ability of gas supply to domestic market’s demand in the period toward 2015
and orientation toward 2025.
- To preside over and coordinate with concerned ministries and branches in formulating and
promulgating policies of reasonable gas prices to present a flexible gas price definition system, plan
of mixing gas price to ensure financial incentives for investment in exploiting the gas mines
especially the small, deep water, offshore mines, mines with high levels of CO2, ..., while ensuring
the competitiveness of the gas raw material, fuel with other alternative fuels, building a roadmap for
market reform in the period before the year 2020.
- To continue the review for supplementation and adjustment of the planning content in accordance
with the development of Vietnam's petroleum industry and the volatility of world gas industry; to
perfect mechanisms and policies to facilitate the Vietnam enterprises operating in the gas industry to
have conditions to develop, improve and perfect the competitiveness in the trend of regional and
international integration.
- To preside over the appraisal and approval of additional Plan for commercial LPG storage projects
with storage capacity below 5,000 tons.
- To compile the report of strategic environmental impact assessment, submit for approval in
accordance with the current provisions in 2011.
2. Ministry of Finance, Ministry of Planning and Investment, State Bank of Vietnam
Ministry of Finance, Ministry of Ministry of Planning and Investment and State Bank of Vietnam
within their assigned tasks, deploy the specific solutions, the above policies and support investors in
arranging capital for the key projects on gases industry in the Plan.
3. People's Committees of provinces and cities under central government
People's Committees of provinces and cities coordinate with the Ministries of: Industry and Trade,
Transport and the State management agencies and the enterprises building economic- social
development plans of local associated with the development of infrastructure of the gas industry to
have impact of inter-sector support.
Article 3. This Decision takes effect from the date of signing.
Article 4. The ministers, heads of ministerial-level agencies, chairmen of the members’ Council,
General Director of Vietnam national oil and gas Group, Chairman of the Management Board,
General Director of Vietnam National Petroleum Company and the relevant agencies are responsible
for the implementation of this Decision.
PRIME MINISTER
Nguyen Tan Dung
ANNEX
LIST OF GAS AND OIL PROJECTS INVESTED IN THE UP TO 2015 PERIOD, AN
ORIENTATION TOWARD 2025
(Issuing together with the Decision No.459/QD-TTg dated March 30, 2011 of the Prime Minister)
I. NATURAL GAS
No
I
A
Works
The gas collection pipelines
Cuu Long basin
Time to
start to
operate
Expected
capacity
(billion
m3/year)
length
(Km)
1
2
3
4
5
B
1
2
3
4
5
6
7
8
9
C
1
2
3
D
1
2
II
1
Gas collection system of Cluster Mo Rong,
Nam Rong, Doi Moi – Bach Ho
Gas collection system from the mines Hai Su
Trang and Hai Su Den, Te Giac Trang to Bach
Ho
Gas collection pipelines from the mine Su Tu
Trang to Su Tu Vang
Gas collection system of cluster of mines
Block 01 & 02 (Ruby, Pearl, Topaz,
Diamond, Jade, Emerald) Rang Dong
Gas collection pipeline from the mines Thang
Long, Dong Do to the Emerald
Nam Con Son basin
Gas collection pipeline of the mines Lan Do Lan Tay
Gas collection pipeline of the mines Chim Sao
- Nam Con Son 1
Gas collection pipeline of the mines Hai
Thach and Moc Tinh to (KP-75)
Gas collection pipeline of the mines Rong Vi
Dai - Rong Doi/Rong Doi Tay
Gas collection pipeline of the mines Hai Au,
Thien Nga to the Chim Sao
Gas collection pipeline of the mines Kim
Cuong Tay, Nguyet Thach to Hai Thach
Gas collection pipeline of the mines Dai
Hung- Nam Con Son 2
Gas collection pipeline of the mines Block 043 & 04-1 to Thien Ung
Gas collection system from the basin Tu
Chinh - Vung May to the Hai Thach
Ma Lay – Tho Chu basins
Gas collection pipeline of the mines Hoa Mai
- PM3_CAA
Gas collection pipeline Ac Quy/ Kim Long –
CA Voi (Block B, 48/95 & 52/97)
Gas collection pipeline from the mine clusters
Block 46-2 (Khanh My - Phu Tan - Rach Tau
…)
Red River basin
Gas collection pipeline of the mines Bach
Long - Hong Long
Gas collection pipeline of the mines A/Ca Voi
Xanh/Ca Heo – Su Tu Bien (Block 117)
The main offshore pipeline
Pipeline system of Nam Con Son 2 (Hai
Thach - Vung Tau)
2010
0,4
47
2011
0,8
20
2012
2
20
2014
1,3
54
2014
0,1
30
2012
2
25
2012
1
68
2013
4,5
56
2017
0,3
20
2019
0,8
20
2017-2018
0,5
20
2013-2015
0,1
30
2018
2-4
20
2019
2
200
2013
0,4
20
2014
-
-
2019
0,6
50
2017
0,3
20
2019
1
115
2013-2014
7
325
2
3
Pipeline of Block B - O Mon
Pipeline system from the mines Hong Long,
Hoang Long, Bach Long, Ham Rong, Thai
Binh to Thai Binh province
4
Pipeline system from the Block 112-113111/04 (Bao Vang mine) to Quang Tri
province
5
Pipeline system from the mines Block 117118-119 to Quang Nam/Quang Ngai
provinces
6
Pipeline system from the Phu Khanh basin to
Binh Thuan/Ba Ria - Vung Tau provinces
7
Gas pipeline system of the basin Tu Chinh Vung May to Nam Con Son 2
III The onshore pipelines
1
Pipeline from the existing storage of LNG GDC gasifying
2
The pipeline connecting East - West (Hiep
Phuoc - O Mon)
3
Pipeline Phu My - Nhon Trach - Ho Chi Minh
phase 2
4
Pipeline GDC Nhon Trach - Nhon Trach
industrial zone
5
Pipeline GDC Hiep Phuoc - KDT Thu Thiem
6
Pipeline of Nhon Trach industrial zone - Long
Thanh industrial zone - Bien Hoa
7
Pipeline of GDC Hiep Phuoc - Binh Chanh Duc Hoa
8
Pipeline of Can Duoc - Duc Hoa (Long An)
9
The pipeline connecting the industrial zones
of Dong Nai, Bien Hoa, Binh Duong, Thu
Duc
10 Regional pipeline system of Thai Binh
province
11 Pipeline system of Red River Delta region
(Thai Binh to the neighboring provinces)
12 Pipelines system from the northern LNG
storage connected to the pipeline sysem of the
Red River Delta region
13 Pipeline system from Quang Tri - Quang
Ngai/Quang Nam
IV Gas Treatment Plant
1
Gas treatment Plant in Ca Mau
2
Gas treatment Plant in Thai Binh
3
Gas treatment Plant Nam Con Son 2 in Ba Ria
- Vung Tau (phase 1)
4
Gas treatment Plant in Quang Tri
2014
2014-2016
7
2-4
398
80
2014-2016
1-3
120
2014-2017
2-4
120
2017
2
120
2014-2017
-
-
2015-2017
2-5
145
2015-2020
-
57
2013
3
15
2014
2017
1,3
-
18
24
2017
-
45
2017
2021
1,3
40
45
2014
1-3
30
2014-2020
2–6
250
2014-2020
4–6
180
2020
-
2014
2013-2015
2013-2014
4–7
1-3
1-3
2014-2017
1-3
2017-2025
2014-2017
1–4
2018
1–2
V
1
Gas treatment Plant in Quang Ngai/Quang
Nam
Gas treatment Plant Nam Con Son 2 in Ba Ria
- Vung Tau (phase 2)
Imported LNG storage
Southern LNG storage (Phase 1)
2014-2015
2
Southern LNG storage (Phase 2)
2017-2020
3
LNG storage Nghi Son – Thanh Hoa
2014-2020
2015-2018
1–3
million tons
3–5
million tons
2–3
million tons
-
-
-
5
6
4
New LNG Storage in the South/South Central
or other locations (1-2 storages)
5
LNG Storage in the North
II. LIQUEFIED PETROLEUM GAS (LPG)
No. Region
I
Capacity of storages
expanded and built newly
(tons)
2010-2015
2016-2025
Ports
Total (tons)
North
Hai Phong
II
North Central
1
Thanh Hoa
2
Ha Tinh
III South Central
1
Da Nang
2
Quang Ngai
IV South
Dinh Vu
Lach Huyen
5,000
10,000
Nghi Son
Vung Ang
8,100
Tho Quang
Dung Quat
3,000
3,000
6,000
40,000
7,500
50,000
3,500
8,100
3,500
6,000
3,000
9,000
6,000
Thi Vai (cool
60,000
8,100
68,100
storage)
1
Cai Mep
20,000
20,000
Tien Hiang (cool
84,000
84,000
storage)
2
Dong Nai
Go Dau
4,000
4,000
Tra Noc
2,000
2,000
III. COLLECTION OF REQUIREMENTS FOR INVESTMENT CAPITAL FOR GAS
INDUSTRY IN THE 2010-2025 PERIOD
Ba Ria – Vung
Tau
Calculated Unit: million USD
No. Type of works
I
Gas pipeline system
(GPS)
Capital requirements by periods
2010 – 2015
2016 – 2025
Basic
High
Basic
High
PA
PA
PA
PA
2,849 2,874 1,267
3,784
Total
Basic
PA
4,116
High
PA
6,658
1
Gas
collection/exploitation
GPS
2 Offshore gas
transportation GPS
3 Onshore gas
transportation GPS
II Gas separation,
treatment stations
III LPG storage
IV Imported LPG storage
Total investment capital
requirements
729
754
34
1,101
763
1,855
1,679
1,679
1,037
1,743
2,716
3,422
441
441
196
940
637
1,381
1,303
1,383
980
1,383
2,283
2,766
238
924
5,314
268
924
5,449
420
950
3,617
567
1,346
7,080
658
1,874
8,931
835
2,270
12,529
------------------------------------------------------------------------------------------------------