Why Oxy Combustion ?

Why Oxy Combustion ?
Nitrogen
CPU
Oxygen
Air
Separation
CO2
Keiji Makino
Japan Coal Energy Center
CO2
Because, Oxy Combustion is :
 Simple concept
 Low cost
 Combination of approved technology
 Independent from fuel characteristics
 Small water consumption
 Low NOx, Low SOx
 New plants/Modification plants
…So and so
But Big ASU and Big cost of oxygen production
Courtesy IHI
CO2 Capture from Coal-fired Power Plant
1. Pre-combustion
Coal (C,H,O,N,S,Ash)
Gasifier
CO shift
N2
Gas Refining
Air
(N2、O2)
O2
CO, H2
ASU
CO2 sequestration
2
CO2,
H2
Compression/Cooling
2. Post-combustion
CO2 Storage
Boiler
Coal
(C,H,O,N,S,Ash)
Air
(N2、O2)
HRSG
GT
H
Flue gas
treatment
CO2
sequestration
CO2
N2,H2O,O2
Compression/Cooling
CO2 Storage
3. Oxyfuel
Coal (C,H,O,N,S,Ash) Boiler
N2
Flue gas
treatment
N2,O2
Air
(N2、O2)
CO2 Storage
O2
Oxygen
production
Compression/Cooling
Exhaust gas recirculation (CO2,・・・ ) H2O,SO2
Courtesy IHI
4
Courtesy IHI
GHG Reduction(450 Scenario)
From WEO2011
6
CO2 injection equipment
Courtesy JCOAL
7
Courtesy IHI
Oxyfuel Project in the world
Courtesy Callide Project
9
KEPCO/KOSEP - Yongdong (PC - 100MWe)
FutureGen2 - Illinois (PC - 100MWe)
Endesa/CIUDEN - El Bierzo (CFB - 300MWe) - ???
Alstom
Hitachi Babcock
IHI
Alstom / AL
CIUDEN
CIUDEN
Schwarze Pumpe
Schwarze Pumpe
Callide
Lacq
El Bierzo CFB Facility
El Bierzo PC Facility
2008
2010
2011
2009
2011
2011
30MWth
30MWth
30MWe
30MWth
30MWth
20MWth
Lignite
Lignite
Coal
Gas/Oil?
Coal
Coal
China: 3 Oxyfuel Projects – in progress
UK: Drax Power Plant Oxyfuel
2009 – Lacq – World’s
first 30MWt
retrofitted Oxy-NG
boiler
2008
World’s FIRST 30 MWt
full chain demonstration
at Schwarze Pumpe Pilot Plant
2011 – Callide –
World’s first 30MWe
retrofitted Oxy-coal
power plant
Target :
“Commercialised by 2020”
By 2014-2018
Demonstration of
50– 300MWe full
scale power plant.
2011 – CIUDEN –
World’s first 30MWt
Oxy-CFB Pilot Plant
2007
2003 - 2005
B&W CEDF (30MWt)
large scale burner testing started
Vattenfall (ENCAP ++)
1998 – 2001 CS Energy / IHI Callide Project
CANMET
1990 - 1995 US DOE Project / B&W / Air Liquide
1980’s
EC Joule Thermie Project
- IFRF / Doosan Babcock / Int’l Combustion
NEDO / IHI / Jcoal Project
ANL/Battelle/EERC completed the first
industrial scale pilot plant
Updated by S. Santos (01/12/10)
First large scale 35MWt
Oxy-Coal Burner Retrofit
Test done by
International Combustion
By the end of 2010/2011,
Users (i.e. Power Plant Operators)
will have 6 burner manufacturers
fully demonstrating “Utility Size
Large Scale Burners” which should
give a high level of confidence
toward demonstration
B&W
Alstom
Doosan Babcock
CEDF
Alstom CE
DBEL - MBTF
2008 30MWth Coal
2010 15MWth Coal
2009 40MWth Coal
Courtesy IEAGHG
For the discussion:We are on the Oxyfuel Ship.
If the Ship will sink, we will
sink together!
This course is very good place
to get information about Oxyfuel
technology.