Monthly Progress Report of February 2017

Monthly Progress
Report of
February 2017
Executive Summary
Project Details and Building Progress report
Completed
• 20th to pool deck floor toilet floor tile work
• False ceiling work in toilet 20th floor and pool deck
floor
• False ceiling work in stair lobby & fire hose box
covering 20th floor
• Electrical work1st & 2nd fix G.F to roof floor
• Waterproofing work for Jacuzzi and steam room
• Lift work – Ground floor to lift machine room
• Lift lobby floor tile 1stto 3rd floor
• Final coat painting in kitchen portion 4th to 19th floor
In Progress
• Floor tile – 20th floor to pool deck floor
• Ground floor to Pool deck floor paint Primer & filler
work
• AC first fix
• AC second fix
• AC final fix
• False ceiling works -4th to pool deck floor
• Firefighting work G.F to Pool deck floor
• Electrical work 3rd fix G.F to roof floor
• Plumbing work 1st fix 4th to Pool deck floor
• Plumbing work final fix 4th to 19th floor
• Thermal insulation work ground floor to 20th floor
• Aluminum doors and windows work 4th to 19th floor
• Aluminum doors and windows work 20th floor
• Aluminum cladding frame work front elevation
• Aluminum cladding work front elevation
• Balcony handrail fixing in roof, left, front and right side
elevation
• Vanity work – 4th to 19th floor
• Internal wall 1st coat painting in 5th, 7th to roof deck
floor
• External wall 1st coat painting in left and right side
elevation
• External wall final coat painting in rear side elevation
• Wooden doors fixing Ground floor to Pool deck floor
• Waterproofing in roof area
• Gypsum ceiling in lift lobby
• Marble fixing in lift lobby wall
• Epoxy painting in staircase, pump room and lift
machine room
• Epoxy painting in parking floor
• Wall and floor tile – guard room
• False ceiling works - ground floor
• Final coat painting in gypsum ceiling 4th to 20th floor
• Swimming pool work
Progress Review
The following is the list of work activities executed until 28th February 2017, as per the progress on site.
Activity
Floor
Status
Toilet floor tile work
20Th to pool deck floor
COMPLETED
False ceiling work in toilet
20Th floor and pool deck floor
COMPLETED
False ceiling work in stair lobby & fire hose box
covering
20Th floor
COMPLETED
Electrical work1st & 2nd fix
G.F to roof floor
COMPLETED
Waterproofing work
Jacuzzi and steam room
COMPLETED
Lift work
Ground floor to lift machine room
COMPLETED
Lift lobby floor tile
1St to 3rd floor
COMPLETED
Final coat painting in kitchen portion
4Th to 19th floor
COMPLETED
Floor tile
20Th floor to pool deck floor
COMPLETED
Paint primer & filler work
Ground floor to pool deck floor
COMPLETED
Ac first fix
COMPLETED
Ac second fix
COMPLETED
Ac final fix
COMPLETED
False ceiling work
4Th to pool deck floor
COMPLETED
Firefighting work
G.F to pool deck floor
IN PROGRESS
Electrical work
3Rd fix g.F to roof floor
IN PROGRESS
Plumbing work
1St fix 4th to pool deck floor
IN PROGRESS
Plumbing work final fix
4Th to 19th floor
IN PROGRESS
Thermal insulation work
Ground floor to 20th floor
IN PROGRESS
Aluminum doors and windows work
4Th to 19th floor
IN PROGRESS
Aluminum doors and windows work
20Th floor
IN PROGRESS
Aluminum cladding frame work
Front elevation
IN PROGRESS
Balcony handrail fixing in roof
Left, front and right side elevation
IN PROGRESS
Vanity work
4Th to 19th floor
IN PROGRESS
Internal wall 1st coat painting
5Th, 7th to roof deck floor
IN PROGRESS
External wall 1st coat painting
Left and right side elevation
IN PROGRESS
External wall final coat painting
Rear side elevation
IN PROGRESS
Wooden doors fixing
Ground floor to pool deck floor
IN PROGRESS
Waterproofing
Roof area
IN PROGRESS
3 - Jana Tower, Juffair — a project by Haqbaz Development
Progress Review
The following is the list of work activities executed until 28th February 2017, as per the progress on site.
Activity
Floor
Status
Gypsum ceiling
Lift lobby
IN PROGRESS
Marble fixing
Lift lobby wall
IN PROGRESS
Epoxy painting
Staircase, pump room and lift machine room
IN PROGRESS
Epoxy painting
Parking floor
IN PROGRESS
Wall and floor tile
Guard room
IN PROGRESS
False ceiling works
Ground floor
IN PROGRESS
Final coat painting in gypsum ceiling
4Th to 20th floor
IN PROGRESS
Swimming pool work
Pool deck floor
IN PROGRESS
4 - Jana Tower, Juffair — a project by Haqbaz Development
Site Snapshot
Steel work for jacuzzi in 20th floor
Steel work for jacuzzi in 20th floor
Piping work for jacuzzi in 20th floor
Piping work for jacuzzi in 20th floor
Floor tile fixing in roof deck floor
Floor tile fixing in roof deck floor
5 - Jana Tower, Juffair — a project by Haqbaz Development
Site Snapshot
Floor tile in 20th floor toilet
Floor tile in pool deck floor toilet
Gypsum ceiling painting in 20th floor
Gypsum ceiling painting in 20th floor
Final coat ceiling painting in roof deck floor
Final coat wall painting in roof deck floor
6 - Jana Tower, Juffair — a project by Haqbaz Development
Site Snapshot
1Stcoat wall painting in 18th floor
1Stcoat wall painting in 19th floor
Final coat wall painting in rear side elevation
Final coat wall painting in rear side elevation
Floortile fixing in 20th floor
Floortile fixing in pool deck floor: (lift lobby)
7 - Jana Tower, Juffair — a project by Haqbaz Development
Site Snapshot
Wall tile works in 20th floor toilet
Wall tile works in pool deck floor toilet
Wall tile works in ground floor toilet
Floortile works in ground floor guard room
Floor plaster in 20th floor steam room
Floor plaster in 20th floor jacuzzi room
8 - Jana Tower, Juffair — a project by Haqbaz Development
Site Snapshot
Waterproofing in 20th floor steam room
Waterproofing in 20th floor jacuzzi room
Gypsum ceiling in 20th floor stair lobby
Gypsum ceiling in pool deck floor stair lobby
Stair lobby gypsum ceiling painting in 20th floor
Stair lobby gypsum ceiling painting in pool deck
floor
9 - Jana Tower, Juffair — a project by Haqbaz Development
Site Snapshot
Thermal insulation work in ground floor
Gypsum ceiling painting in ground floor
Toilet tile ceiling in 20th floor
Toilet gypsum ceiling in 20th floor
Toilet gypsum ceiling painting in 20th floor
Toilet gypsum ceiling painting in pool deck floor
10 - Jana Tower, Juffair — a project by Haqbaz Development
Site Snapshot
Gypsum ceiling final coat in 19thfloor
Gypsum ceiling final coat in 18thfloor
Kitchen gypsum ceiling final coat in 19th floor
Kitchen gypsum ceiling final coat in 18th floor
Aluminum windows glass fixing in left side
elevation
Aluminum windows glass fixing in right side
elevation
11 - Jana Tower, Juffair — a project by Haqbaz Development
Site Snapshot
Aluminum louver fixing in parking floor
Toilet door fixing in 14th floor
Bedroom door fixing in 13th floor
Entrance door fixing in 14thfloor
Lift lobby marble fixing in 17thfloor
Lift lobby marble fixing in 14thfloor
12 - Jana Tower, Juffair — a project by Haqbaz Development
Site Snapshot
Bitumen paint primer apply in roof:
(waterproofing)
Bituflame membrane in roof: (waterproofing)
Granular membrane in roof: (waterproofing)
Screed concrete poring in 20th floor: (gym room)
Waterproofing in pool deck floor
Primer work in pump room / water tank room
13 - Jana Tower, Juffair — a project by Haqbaz Development
Site Snapshot
Primer work in staircase
Wooden work in suana room
14 - Jana Tower, Juffair — a project by Haqbaz Development
Epoxy painting work in pump room / water tank
room
Site Snapshot
Front elevation
15 - Jana Tower, Juffair — a project by Haqbaz Development
Site Snapshot
Left side elevation
16 - Jana Tower, Juffair — a project by Haqbaz Development
Site Snapshot
Right side elevation
17 - Jana Tower, Juffair — a project by Haqbaz Development
Site Snapshot
Rear elevation
18 - Jana Tower, Juffair — a project by Haqbaz Development