Monthly Progress Report of February 2017 Executive Summary Project Details and Building Progress report Completed • 20th to pool deck floor toilet floor tile work • False ceiling work in toilet 20th floor and pool deck floor • False ceiling work in stair lobby & fire hose box covering 20th floor • Electrical work1st & 2nd fix G.F to roof floor • Waterproofing work for Jacuzzi and steam room • Lift work – Ground floor to lift machine room • Lift lobby floor tile 1stto 3rd floor • Final coat painting in kitchen portion 4th to 19th floor In Progress • Floor tile – 20th floor to pool deck floor • Ground floor to Pool deck floor paint Primer & filler work • AC first fix • AC second fix • AC final fix • False ceiling works -4th to pool deck floor • Firefighting work G.F to Pool deck floor • Electrical work 3rd fix G.F to roof floor • Plumbing work 1st fix 4th to Pool deck floor • Plumbing work final fix 4th to 19th floor • Thermal insulation work ground floor to 20th floor • Aluminum doors and windows work 4th to 19th floor • Aluminum doors and windows work 20th floor • Aluminum cladding frame work front elevation • Aluminum cladding work front elevation • Balcony handrail fixing in roof, left, front and right side elevation • Vanity work – 4th to 19th floor • Internal wall 1st coat painting in 5th, 7th to roof deck floor • External wall 1st coat painting in left and right side elevation • External wall final coat painting in rear side elevation • Wooden doors fixing Ground floor to Pool deck floor • Waterproofing in roof area • Gypsum ceiling in lift lobby • Marble fixing in lift lobby wall • Epoxy painting in staircase, pump room and lift machine room • Epoxy painting in parking floor • Wall and floor tile – guard room • False ceiling works - ground floor • Final coat painting in gypsum ceiling 4th to 20th floor • Swimming pool work Progress Review The following is the list of work activities executed until 28th February 2017, as per the progress on site. Activity Floor Status Toilet floor tile work 20Th to pool deck floor COMPLETED False ceiling work in toilet 20Th floor and pool deck floor COMPLETED False ceiling work in stair lobby & fire hose box covering 20Th floor COMPLETED Electrical work1st & 2nd fix G.F to roof floor COMPLETED Waterproofing work Jacuzzi and steam room COMPLETED Lift work Ground floor to lift machine room COMPLETED Lift lobby floor tile 1St to 3rd floor COMPLETED Final coat painting in kitchen portion 4Th to 19th floor COMPLETED Floor tile 20Th floor to pool deck floor COMPLETED Paint primer & filler work Ground floor to pool deck floor COMPLETED Ac first fix COMPLETED Ac second fix COMPLETED Ac final fix COMPLETED False ceiling work 4Th to pool deck floor COMPLETED Firefighting work G.F to pool deck floor IN PROGRESS Electrical work 3Rd fix g.F to roof floor IN PROGRESS Plumbing work 1St fix 4th to pool deck floor IN PROGRESS Plumbing work final fix 4Th to 19th floor IN PROGRESS Thermal insulation work Ground floor to 20th floor IN PROGRESS Aluminum doors and windows work 4Th to 19th floor IN PROGRESS Aluminum doors and windows work 20Th floor IN PROGRESS Aluminum cladding frame work Front elevation IN PROGRESS Balcony handrail fixing in roof Left, front and right side elevation IN PROGRESS Vanity work 4Th to 19th floor IN PROGRESS Internal wall 1st coat painting 5Th, 7th to roof deck floor IN PROGRESS External wall 1st coat painting Left and right side elevation IN PROGRESS External wall final coat painting Rear side elevation IN PROGRESS Wooden doors fixing Ground floor to pool deck floor IN PROGRESS Waterproofing Roof area IN PROGRESS 3 - Jana Tower, Juffair — a project by Haqbaz Development Progress Review The following is the list of work activities executed until 28th February 2017, as per the progress on site. Activity Floor Status Gypsum ceiling Lift lobby IN PROGRESS Marble fixing Lift lobby wall IN PROGRESS Epoxy painting Staircase, pump room and lift machine room IN PROGRESS Epoxy painting Parking floor IN PROGRESS Wall and floor tile Guard room IN PROGRESS False ceiling works Ground floor IN PROGRESS Final coat painting in gypsum ceiling 4Th to 20th floor IN PROGRESS Swimming pool work Pool deck floor IN PROGRESS 4 - Jana Tower, Juffair — a project by Haqbaz Development Site Snapshot Steel work for jacuzzi in 20th floor Steel work for jacuzzi in 20th floor Piping work for jacuzzi in 20th floor Piping work for jacuzzi in 20th floor Floor tile fixing in roof deck floor Floor tile fixing in roof deck floor 5 - Jana Tower, Juffair — a project by Haqbaz Development Site Snapshot Floor tile in 20th floor toilet Floor tile in pool deck floor toilet Gypsum ceiling painting in 20th floor Gypsum ceiling painting in 20th floor Final coat ceiling painting in roof deck floor Final coat wall painting in roof deck floor 6 - Jana Tower, Juffair — a project by Haqbaz Development Site Snapshot 1Stcoat wall painting in 18th floor 1Stcoat wall painting in 19th floor Final coat wall painting in rear side elevation Final coat wall painting in rear side elevation Floortile fixing in 20th floor Floortile fixing in pool deck floor: (lift lobby) 7 - Jana Tower, Juffair — a project by Haqbaz Development Site Snapshot Wall tile works in 20th floor toilet Wall tile works in pool deck floor toilet Wall tile works in ground floor toilet Floortile works in ground floor guard room Floor plaster in 20th floor steam room Floor plaster in 20th floor jacuzzi room 8 - Jana Tower, Juffair — a project by Haqbaz Development Site Snapshot Waterproofing in 20th floor steam room Waterproofing in 20th floor jacuzzi room Gypsum ceiling in 20th floor stair lobby Gypsum ceiling in pool deck floor stair lobby Stair lobby gypsum ceiling painting in 20th floor Stair lobby gypsum ceiling painting in pool deck floor 9 - Jana Tower, Juffair — a project by Haqbaz Development Site Snapshot Thermal insulation work in ground floor Gypsum ceiling painting in ground floor Toilet tile ceiling in 20th floor Toilet gypsum ceiling in 20th floor Toilet gypsum ceiling painting in 20th floor Toilet gypsum ceiling painting in pool deck floor 10 - Jana Tower, Juffair — a project by Haqbaz Development Site Snapshot Gypsum ceiling final coat in 19thfloor Gypsum ceiling final coat in 18thfloor Kitchen gypsum ceiling final coat in 19th floor Kitchen gypsum ceiling final coat in 18th floor Aluminum windows glass fixing in left side elevation Aluminum windows glass fixing in right side elevation 11 - Jana Tower, Juffair — a project by Haqbaz Development Site Snapshot Aluminum louver fixing in parking floor Toilet door fixing in 14th floor Bedroom door fixing in 13th floor Entrance door fixing in 14thfloor Lift lobby marble fixing in 17thfloor Lift lobby marble fixing in 14thfloor 12 - Jana Tower, Juffair — a project by Haqbaz Development Site Snapshot Bitumen paint primer apply in roof: (waterproofing) Bituflame membrane in roof: (waterproofing) Granular membrane in roof: (waterproofing) Screed concrete poring in 20th floor: (gym room) Waterproofing in pool deck floor Primer work in pump room / water tank room 13 - Jana Tower, Juffair — a project by Haqbaz Development Site Snapshot Primer work in staircase Wooden work in suana room 14 - Jana Tower, Juffair — a project by Haqbaz Development Epoxy painting work in pump room / water tank room Site Snapshot Front elevation 15 - Jana Tower, Juffair — a project by Haqbaz Development Site Snapshot Left side elevation 16 - Jana Tower, Juffair — a project by Haqbaz Development Site Snapshot Right side elevation 17 - Jana Tower, Juffair — a project by Haqbaz Development Site Snapshot Rear elevation 18 - Jana Tower, Juffair — a project by Haqbaz Development
© Copyright 2026 Paperzz