4.5K Cold Box Overview Dana Arenius LCLS-II 4.5K Cold Box Director’s Review November 16, 2016 Outline • 4.5K Cold Box Function • Contractual Milestones • Design Schedule Delays • Schedule Recovery Actions • Summary LCLS-II 4.5K Cold Box Director’s Review, November 16, 2016 2 Cryoplant First Light & Normal Beam Operations First Light 1 Cryoplant 2 Cryomodule Strings U-Tube Connections 14 MV/m Gradient 2.0≤ Qo ≤3.0 He Gas Tanks LHe Dewar LN2 Dewar 2.0 K Coldbox 1 L1 2 3 BC1 U-TUBE JUMPER CONNECTIONS 2.0 K Coldbox Normal Beam Operations 2 Cryoplants 2 Cryomodule Strings LHe U-Tube Connections Dewar Removed Gradient - 16 MV/m 2.0≤ Qo ≤3.0 IB Downstream Downstream Distribution Distribution Box Box Upstream Distribution Box Upstream String LH 4.5 K Coldbox 4.5 K Coldbox IB L0 Compressor System Compressor System L2 Downstream String L3 FC 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 IB 3.9 GHz Cryomodule1.3 GHz Cryomodule End/Feed Cap VacuumBarrier LCLS-II 4.5K Cold Box Director’s Review, November 16, 2016 Cryogenic Bypass Cryogenic Transfer Line Cryoplant Gas Header Interface Box 3 Cryoplant Layout Overview CP1 4.5K Cold Box LN2 storage GHe storage CP1 Oil Removal CP2 4.5K Cold Box CP2 Oil Removal CP2 Compressors CP1 Compressors Oil processor 2K CBX Guard Vacuum CDS Interface Boxes LHe Dewar LCLS-II 4.5K Cold Box Director’s Review, November 16, 2016 LHe Dewar Motor Control Center Instrument Air 4 Single Plant Operation (CP-1) for First Light, 14 MV/m First Light Design Heat Loads with Qo=2.7x1010 Steady State CW Operation @ 14 MV/m Mode 1: Max Capacity of the Cryoplant Temp Level Variation in the 2.0 K Heat Loads of First Light for the Selected First Light Gradient with Qo Heat Load [kW] High Temperature Thermal Shield, (35K) 15.3 Low Temperature Thermal Shield, (5K) 1.3 Primary Temperature 2K 4 Source: Jlab Refrigerator Specification 79220-S001 (Ref: SLAC LCLSII-4.5-EN-0179-R2) LCLS-II 4.5K Cold Box Director’s Review, November 16, 2016 One cryoplant is sufficient to support the First Light Operation 5 Two Plant Operation (CP-1 & CP-2) For Design Heat Loads Design Heat Loads with Qo=2.7x1010 Steady State CW Operations @ 16 MV/m Mode 1: Max Capacity of the Cryoplant Temp Level Variation in the 2K Design Heat Loads with Variable Gradient and Qo Heat Load [kW] High Temperature Thermal Shield, (35K) 15.3 Low Temperature Thermal Shield, (5K) 1.3 Primary Temperature 2K 4 Source: Jlab 4.5K Cold Box Specification 79220-S001 (Ref: SLAC LCLSII-4.5-EN-0179-R2) LCLS-II 4.5K Cold Box Director’s Review, November 16, 2016 Two cryoplant operation to support variation in gradient and Qo 6 4.5K Cold Box Design Challenges Included in plant performance analysis: • Large variation of operational design parameters First Light single plant load (heavy load) vs. Normal two plant operation (~50% load for each plant) Unknown final Qo determination, design basis 2.7x1010 Required extensive heat exchanger/turbine performance analysis for wide possible load variation Level of Seismic design criteria for California Subcontract requirement for CA Seismic licensed PE LCLS-II 4.5K Cold Box Director’s Review, November 16, 2016 7 JLab/SLAC/Air Liquide Engineering Coordination • Weekly status and issue resolution meetings Attended by • AL/SLAC/JLab engineering, vendor PM • JLab procurement Not attended by AL subcontractors • PHPK (cold box assembly engineering and fabrication) • Sumitomo (heat exchanger manufacturer) • Hopper (Seismic PE, Subcontractor to PHPK) LCLS-II 4.5K Cold Box Director’s Review, November 16, 2016 8 4.5K Cold Box Contractual Milestone Schedule Milestone Description Completion of Kick Off Meeting Preliminary Design Review (PDR) Order Long Lead Items Complete final design review (FDR) Delivery of Long Lead Material Cold Box 1 Manufacturing Complete Factory acceptance of completed turbines Cold Box 1 Received at SLAC Cold Box 1 Assembled at SLAC Cold Box 2 Manufacturing Complete Cold Box 2 Received at SLAC Cold Box 2 Assembled at SLAC Commissioning, Train, & Accept (CB1) Deliver Ops & Main Manuals Commissioning, Train, & Accept (CB2) Required Date 08-Oct-15 10-Mar-16 08-Apr-16 11-Jul-16 11-Nov-16 11-Aug-17 25-Aug-17 11-Sep-17 11-Dec-17 12-Feb-18 12-Mar-18 11-Jun-18 11-Oct-18 11-Jan-19 11-Feb-19 Actual Complete 8-Oct-15 10-Mar-16 1-Nov-16 FDR Completion Plan: Nov 28th, Seismic Analysis Last Long Lead Item Ordered: 1-Nov-16 LCLS-II 4.5K Cold Box Director’s Review, November 16, 2016 9 4.5K Cold Boxes, 1.04.08.06/.16 • Preliminary design review completed • Heat exchanger sizing Absorber Beds Process cycle design verification Final Design Review 7-8th Sept ~90% of 92 required documents delivered 3-D modeling of internal piping completed Missing Piping Stress & Seismic Design Hold on top plate (upper cold box) and both cold box vacuum shells until analysis of piping stress and seismic analysis is complete (Note: Internal piping/vessel structure attached to vacuum shell) Missing analysis scheduled to be delivered ~28th November LCLS-II 4.5K Cold Box Director’s Review, November 16, 2016 10 Schedule Recovery Action Items Implemented • Notification of unsatisfactory schedule performance to vendor senior management • Vendor schedule optimization study of remaining work to recover schedule implemented • Continuation of weekly AL/Jlab/SLAC engineering coordination meetings • Invitation by AL to JLab to attend weekly AL/Subcontractor coordination meeting for direct stakeholder communication • PHPK • Hopper LCLS-II 4.5K Cold Box Director’s Review, November 16, 2016 11 Summary • Heat exchanger analysis was longer than expected in completing PDR per contractual date and heat exchanger ordering • Heat exchanger delay affected 3-D piping, piping stress and seismic analysis completion dates for FDR • Lacking stress/seismic analysis, formal approval for cold box shell ordering (needed for CB fabrication) was delayed • FDR Seismic analysis completion is scheduled for Nov 28th • Schedule study implemented to recovery schedule slip • Expanded JLab interaction with vendor subcontractors LCLS-II 4.5K Cold Box Director’s Review, November 16, 2016 12 MAY I ANSWER ANY QUESTIONS? LCLS-II 4.5K Cold Box Director’s Review, November 16, 2016 13 LCLS-II 4.5K Cold Box Director’s Review, November 16, 2016 14 Cryoplant Modes of Operation (1) *Tables from 4.5K Cold Box Procurement Specification 79220-S001 Table 3.4(A) – Mode 1, Max. Capacity Load Warm Shield Cold Intercept 4-K Refrigeration 4-K Liquefaction Sub-Atmospheric w [g/s] 146 37 15 200 Supply p T [atm] [K] Note 1 35 3.25 5.5 3.2 3.2 4.5 4.5 Return p T [atm] [K] 2.5 55 1.29 7.50 1.10 1.20 q [kW] 15.2 1.3 Warm Shield Cold Intercept 4-K Refrigeration 4-K Liquefaction Sub-Atmospheric w [g/s] 96.7 27 157 Supply p T [atm] [K] Note 1 35 3.2 5.5 3.2 4.5 Return p T [atm] [K] 2.5 55 1.29 7.50 1.20 Load Warm Shield Cold Intercept 4-K Refrigeration 4-K Liquefaction Sub-Atmospheric 300.0 30.0 Table 3.4(B) – Mode 2, Nominal turn down Load Table 3.4(C) – Mode 3, Max. Liquefaction q [kW] 10.10 0.9 30.0 w [g/s] 155 20 40 Supply p T [atm] [K] Note 1 44 3.2 5.8 3.2 4.5 Return p T [atm] [K] 2.3 56.5 1.23 10.8 1.10 q [kW] 10.1 0.9 300.0 Table 3.4(D) – Mode 4, Max. Refrigeration Load Warm Shield Cold Intercept 4-K Refrigeration 4-K Liquefaction Sub-Atmospheric w [g/s] 146 31 481 Supply p T [atm] [K] Note 1 35 3.2 5.3 3.2 4.5 Return p T [atm] [K] 2.5 55 1.23 9.0 1.23 4.45 q [kW] 15.2 1.3 9.0 The specification requires the cryoplant to support a wide operational variable domain while maintaining plant efficiency. LCLS-II 4.5K Cold Box Director’s Review, November 16, 2016 15 Cryoplant Modes of Operation (2) Table 3.4(E) – Mode 5, Max. Fill Load Warm Shield Cold Intercept 4-K Refrigeration 4-K Liquefaction Sub-Atmospheric w [g/s] 146 35 45 157 Supply p T [atm] [K] Note 1 35 3.2 5.3 3.2 3.2 4.5 4.5 Return p T [atm] [K] 2.7 55 1.23 7.8 1.10 1.20 Table 3.4(F) – Mode 6, Standby q [kW] 15.2 1.3 300.0 30.0 Load Warm Shield Cold Intercept 4-K Refrigeration w [g/s] 96.7 25 27 Supply p T [atm] [K] Note 1 35 3.2 5.3 3.2 4.5 Return p T q [atm] [K] [kW] 2.7 55 10.1 1.23 7.5 0.9 1.23 4.5 0.5 Mode 7, 50% Turn Down Load w [g/s] Warm Shield Cold Intercept 4-K Liq. Sub-Atm. 7.5 100 Supply p T [atm] [K] [Note 35.0 2] [±5] 5.0 3.2 [±0.5] 3.2 4.5 3.2 4.5 Return p [atm] 2.5 1.29 1.1 1.2 T [K] 55 [±5] 8.0 [±0.5] 300 30 q [kW] 7.5 0.7 1.9 A seventh operating point was checked and validated by the vendor for operation at 50% of maximum single plant operation mode as an additional operating point within the domain *Tables from 4.5K Cold Box Procurement Specification 79220-S001 LCLS-II 4.5K Cold Box Director’s Review, November 16, 2016 16 Process Model Validation- JLAB/SLAC Calculation (Example: Mode 1- Max Capacity), All 7 Modes completed LCLS-II 4.5K Cold Box Director’s Review, November 16, 2016 17 Validation of Heat Exchanger UAs Heat Exchanger Cooling Curve For the heat exchanger sizing, the mode yielding the maximum UA value is considered (highlighted in yellow). Integrated UAs were calculated and compared with the vendor calculated values. Good agreement in the UA and the NTU values LCLS-II 4.5K Cold Box Director’s Review, November 16, 2016 18 Safety Margin on UAs “A uniformly applied UA safety margin of 15% is required for all heat exchangers for the operating mode requiring the highest UA”. The UA provided by the Vendor is in compliance with the requirement for the Heat Exchangers LCLS-II 4.5K Cold Box Director’s Review, November 16, 2016 19 4.5K CB Pressure Drop in Heat Exchangers-Vendor Data Pressure Drops in HXs for Mode 1: Max Capacity (Example for each Mode) “The ratio of the core pressure drop to the distributor pressure drop > 3.” “The ratio of the sum of the core and distributor pressure drops to the sum of the header and nozzle pressure drop > 3.” The pressure drop values provided by the vendor satisfy the above requirements LCLS-II 4.5K Cold Box Director’s Review, November 16, 2016 20
© Copyright 2026 Paperzz