Streamlined Permitting Policy Combined Land Use/Civil Plan Review (90 Day) Process* Fact Sheet What is the Combined Process? It is the City of Vancouver’s policy to offer a combined review process for land use and engineering approval. In the standard permit review process, the land use approval usually precedes the detailed civil plan review, and at the time of site plan approval, only conceptual engineering plans, sufficient to show that the project can work, have been reviewed. This optional process combines the land use review (e.g. site plan) process with the civil engineering review process by basically “frontloading” the detailed civil plan review early on in the land use review. So, while city staff is reviewing the development for compliance with applicable land use regulations, a detailed review of the public improvements (water, sewer, transportation, drainage) is occurring simultaneously. In addition, requests for building permits may be submitted at the same time and reviewed concurrently. The up-front submittal of detailed engineering plans as part of the land use review process is estimated to result in a minimum time savings of three months, or about 50 percent, to the overall permitting process. What Projects Qualify for the Combined Process? Any project is eligible to be processed under the combined review process, upon request. In order for the land use and civil plan reviews to be combined, however, substantially more information is required at the time of the initial project application than is required under the land use only review process, including construction-level civil plans. The City commits to reviewing Type 2 projects within 90 calendar days for projects which do not involve a public hearing or substantial issues (environmental, debate over conditions, road modifications, appeals, etc.) and when the applicant submits detailed, accurate and complete engineering plans with the land use application. A typical project that could qualify for 90-day processing would be one where the use is permitted outright, the site has minimal development constraints, and potential issues have been addressed early on (e.g. neighborhood opposition, off-site improvements, etc.), ideally before an application is even submitted. At the pre-application conference, the applicant must state whether the combined review process will be utilized. Planning staff should be able to inform the prospective applicant City of Vancouver Combined Review Process Revised November, 2014 Page 1 as to whether a 90-day review would be possible, given the scope of the development and potential issues identified. How are the 90 Days Measured? The 90-day process measures city staff time only (in calendar days), from the date a counter complete land use/civil plan application is received, to the date a pre-construction meeting is held. Included in the 90-day process is the review for technical completeness, the required 30-day public comment period, a SEPA review using the Optional DNS method, preliminary site plan approval, civil plan approval, final site plan approval, and a pre-construction conference. At several points in the process, when the City has requested new information or revisions from the applicant, the City’s “review clock” will be stopped. Once the requested information is received the review clock will start up again. The maximum timeline for review, per the City’s Procedural Ordinance (VMC 20.210), is 120 calendar days from the date of full completeness (FC) to issuance of the land use decision. The timelines outlined in the 90-day review process are internal performance standards established by policy, not by code. Applicant’s Responsibilities: The City’s ability to provide a 90-day combined review process is highly dependent on the applicant and his/her consultants: 1) submitting complete, detailed, and accurate plans and information, and 2) being extremely responsive to any requests for further information or revisions. The optional combined review process is intended for those applicants who provide detailed site plan and civil plan information, as well as any required studies, up-front. In order for the City to meet a 90-day timeline, any deviation from adopted public improvement standards (streets, water, sewer, or stormwater) must first be approved in writing by the applicable department prior to submitting a land use application; otherwise, if plans do not meet the minimum standards they will be returned to the applicant for corrections. The 90-day process can only accommodate two full civil plan reviews (initial plans plus one set of revised plans) before the final mylar copies are requested, therefore civil engineering plans will need to be construction-level drawings at first submittal. Failure to make required corrections may result in more than two civil plan reviews, which will add time to the 90 days. Protracted negotiations over required improvements and conditions of approval may also delay the project. If the site design changes substantially mid-way through the review, or requested information is not provided, or the project is otherwise delayed by the applicant or third party, then the applicant will be informed that staff will continue to process the review, but will no longer be able to meet the 90-day timeline, and an estimate of the additional time required to complete the review will be provided. Pre-submission Meeting: Prior to submitting the land use application and civil plans at the Permit Center, the applicant must arrange a pre-submission meeting with the case manager (planner) where City of Vancouver Combined Review Process Revised November, 2014 Page 2 the planner, an engineering tech, and a permit specialist will go over the plans and application materials to make sure that all required information will be submitted, fees can be calculated, etc. What additional fees apply? There are no additional fees in order to utilize the combined review process. Important Notes and Exceptions Regarding Timelines: 1. The timelines shown on the attached sheet reflect the City’s review time, from receipt of a counter complete land use application to a pre-construction meeting being held. When additional information is requested, the City will “stop the review clock” and any time for waiting for applicant revisions or additional information will be in addition to the 90-day total timeframe, except as noted in the above procedures. 2. City review staff commit to meeting the 90-day timeline for minor administrative land use applications, with the following exceptions: a. Information submitted by the applicant must be accurate and substantially complete from the first submittal on, as the 90–day process can only accommodate one incomplete (Not FC) submittal and two full civil plan reviews; b. 14 days will be added to the 90-day timeline for the third and each subsequent review for completeness. c. 21 days will be added to the 90-day timeline for the third and each subsequent civil plan review. d. 30 days will be added to the 90-day timeline in the following instances: When a public hearing is required (e.g. conditional use permit, shoreline permit, subdivision, etc.); When environmental issues are present (wetlands, shorelines, archaeological site, etc.) that require a SEPA determination other than an Optional DNS; When substantial changes are made to the site’s design/layout after the project is determined to be complete; When significant development issues are identified, such as off-site improvements, debate over requirements and conditions, etc. e. An appeal of the land use or SEPA decision or issuance of a SEPA Determination of Significance (DS) will stop the review clock until the appeal or SEPA process has concluded. f. City review staff and applicant, by mutual agreement, may determine that the review will take longer than 90 days. Questions? For more information on the combined review process, please contact: Greg Turner, Land Use Manager Community & Economic Development Department PO Box 1995 Vancouver, WA 98668-1995 Tel.: (360) 487-7883 Email: [email protected] City of Vancouver Combined Review Process Revised November, 2014 Page 3
© Copyright 2024 Paperzz