Acterna Headquarters Germantown, Maryland John M Sekel The Pennsylvania State University Architectural Engineering 2003 Senior Thesis Presentation Structural Emphasis Presentation Overview • • • • • • • Existing Building Proposal Structural Redesign Construction Considerations Architecture Redesign Mechanical Considerations Conclusions and recommendations Structural Option 2 John M Sekel Existing building • Project Team – – – – – Owner: Milestone Industrial, LLC Architect: Hickok, Warner, Fox Architects Structural Engineer: Structural Design Group MEP Engineer: Girard Engineering General Contractor: L.F. Jennings Structural Option 3 John M Sekel Existing Building • General – New corporate campus for Acterna Corporation – Site clearly visible off I-270 outside Washington, D.C. – Six story, 187,500 sf office building – 253’x126’ building footprint – $10 million construction cost – BOCA 1996 design code Structural Option 4 John M Sekel Existing Building • Structural – Floor framing • Composite beam and slab construction • 50 ksi wide flange shapes • 30’x25’ typical bays • 3 ¼” lightweight concrete slab on 2” metal decking • 2 – transfer girders over conference room on level 1 – Foundations • Spread footing foundations • 4” first floor slab on grade Structural Option 5 John M Sekel Existing Building • Structural – Lateral Frames • 2 – braced frames in each direction ROOF SIXTH FLOOR FIFTH FLOOR FOURTH FLOOR THIRD FLOOR SECOND FLOOR FIRST FLOOR FRAME #1 E-W Direction Structural Option FRAME #2 N-S Direction 6 FRAME #3 N-S Direction FRAME #4 E-W Direction John M Sekel Existing Building • Typical framing plan FRAME #4 FRAME #1 FRAME #2 FRAME #3 Structural Option 7 John M Sekel Existing Building • Mechanical – – – – VAV boxes with electric duct heaters and reheat coils with VFD 2 – 15000 cfm VAV A/C units per floor 2 – 350 ton cooling towers Plate and frame heat exchanger • Electrical/Lighting – 277/480 volt, 3-phase, 4 wire system • 4000 amp primary switchboard • 2000 amp secondary switchboard – 2’x4’ 277 volt florescent fixtures Structural Option 8 John M Sekel Presentation Overview • • • • • • • Existing Building Proposal Structural Re-design Construction Considerations Architecture Re-design Mechanical Considerations Conclusions Structural Option 9 John M Sekel Proposal • Structural design goals – – – – – Eliminate intermediate column line outside of core Use long span steel from core to exterior Economize the structure Design for ease of construction Update to IBC 2000 code FRAME #4 FRAME #1 FRAME #2 FRAME #3 Structural Option 10 John M Sekel Proposal • Architectural design goals – Reflect structural changes in the façade – Open interior spaces, column free areas – Add glazing to lessen “holepunch” look – Emphasize the drum shape • Predominant architectural feature Structural Option 11 John M Sekel Proposal • Construction goals – Reduce construction cost – Reduce construction schedule time – Design building for ease of construction • Mechanical considerations – Analyze impact of façade design on system Structural Option 12 John M Sekel Presentation Overview • • • • • • • Existing Building Proposal Structural Re-design Construction Considerations Architecture Re-design Mechanical Considerations Conclusions Structural Option 13 John M Sekel Structural depth • Framing Re-design Overview – New bay size outside of core 30’x50’ – 50 ksi wide flange shapes • Most readily available shapes – Possible options – 3 ¼” lightweight concrete slab on 2” metal deck • 2 hour fire rating – Re-size frames for additional gravity load • IBC 2000 lateral loads Structural Option 14 John M Sekel Structural depth • Economic steel design measures – – – – Redundant shapes Simple shear tab connections Efficient spacing and span direction Efficient bay size 1.5 w Original w 1.5 * 25’ = 37.5’ Redesign 1.5 * 30’ = 45’ Use 50’ to maintain core size Structural Option 15 John M Sekel Structural Depth • New framing plan Structural Option 16 John M Sekel Structural Depth • New gravity member sizes – Typical Girders • Original: W18 • New Design: W24 – Typical Beams • Original: W14 • New Design: W24 – Typical Interior Column • Original: W12x65 • New Design: W14x120 – Typical Exterior Column • Original: W10x54 • New Design: W14x90 – Deflection criteria controls (L/360) Structural Option 17 John M Sekel Structural Depth ƒn calculation • Vibration Analysis – – – – – – – – 0.18 √[g/(Δg+Δj)] Typical bay analyzed Wj=157.8 kips Δj=1.040” Wg=156.8 kips Δg’=0.191” Po=65 lb β=0.03 W=157.6 kips Structural Option 3.19 Hz ap/g calculation [Po e^(-0.35ƒn)]/βW 0.45%g 18 John M Sekel Structural Depth 25 • ap/g vs. fn chart 10 – Most accurate between 4 and 8 Hz – Combined mode frequency is 3.19 Hz – Peak acceleration is 0.45% of g – Meets acceptable criteria for office buildings 5 Peak Acceleration (% Gravity) 2.5 1.5 1 Office Buildings 0.5 (3.19, 0.45) 0.25 • 0.64% of g at 3.19 Hz 0.1 0.05 1 3 45 810 25 40 Frequency (Hz) Structural Option 19 John M Sekel Structural Depth • New Braced Frame Sizes – Original frame layouts and geometries were maintained • Frames 1 & 4: Inverted “V” • Frames 2 & 3: Diagonal • All web members are TS 10”x10”x5/16” – Column sizes increased for higher gravity load – Designed for member strength and drift • Foundations – Spread foundation system – Size and depth increased due to greater load Structural Option 20 John M Sekel Presentation Overview • • • • • • • Existing Building Proposal Structural Redesign Construction Considerations Architecture Redesign Mechanical Considerations Conclusions Structural Option 21 John M Sekel Construction Breadth • Cost Comparison – RS Means cost estimate for both systems – Cost includes material, labor and equipment Item Original Design New Design Difference Structural Steel $1,182,852 $1,263,433 $80,581 Fire Proofing $145,957 $118,316 $28,641 Foundations $182,790 $159,800 $22,990 Total $1,511,599 $1,541,549 $28,950 Structural Option 22 John M Sekel Construction Breadth • Schedule Comparison – Fewer beams to place • Typical floor original: 222 members • Typical floor redesign: 127 members – Fewer columns and foundations • 16 columns removed in redesign – 30% reduction in structure construction time Original Design Redesign 20 days foundations 14 days foundations 9 weeks superstructure 6 ½ weeks superstructure Structural Option 23 John M Sekel Presentation Overview • • • • • • • Existing Building Proposal Structural Redesign Construction Considerations Architecture Redesign Mechanical Considerations Conclusions Structural Option 24 John M Sekel Architectural Breadth • Reflect change in floor framing Square box-like windows Structural Option Long, continuous windows 25 John M Sekel Architectural Breadth • Increase glazing • Emphasize the drum – Vertically spanning glass Structural Option 26 John M Sekel Architectural Breadth Structural Option 27 John M Sekel Architectural Breadth Structural Option 28 John M Sekel Architectural Breadth Structural Option 29 John M Sekel Architectural Breadth Structural Option 30 John M Sekel Presentation Overview • • • • • • • Existing Building Proposal Structural Redesign Construction Considerations Architecture Redesign Mechanical Considerations Conclusions Structural Option 31 John M Sekel Mechanical Breadth • Increase in cooling load – – – – – Greater glazing area on facade Carrier hourly analysis program analysis Additional 1.5 tons of cooling required per floor Original system capacity is 92 tons per floor 1.6% increase • Most likely will not need to resize equipment – Further analysis required Structural Option 32 John M Sekel Presentation Overview • • • • • • • Existing Building Proposal Structural Redesign Construction Considerations Architecture Redesign Mechanical Considerations Conclusions Structural Option 33 John M Sekel Conclusions • Insignificant cost difference by implementing new system • Shorter construction time – Faster cost return • Improvement to building architecture – Greater tenant flexibility with interior spaces • Good selling point for owner – More notable exterior façade Final Recommendation: Use re-designed structural system Structural Option 34 John M Sekel Thank You • Structural Design Group – Mike Weiss • LF Jennings – Kevin Malpass • AE Faculty and staff – Prof. Parfitt, Dr. Geschwinder, Dr. Hanagan • AE classmates – Chris Flynn, Tim Nolan • My parents and roommates for their encouragement and support Structural Option 35 John M Sekel Questions? ? ? ? ? Structural Option ? 36 John M Sekel Structural Depth • Building Height Comparison Structural Option 37 John M Sekel Structural Depth • Plenum heights – 11 ¾” increase per floor – 5’-10 ½” total building height increase 514" 514" W30 W18 2'-5" 3'-1043" 4'-1012" 2'-5" 14'-343" 13'-4" 9' Structural Option 38 9' John M Sekel Structural depth • Plenum comparison Typical In-Bay Framing Member Deepest Member at Duct Crossing Required Plenum Depth Original Design W14x22 [17] 1” W18 46 ¾” New Design W24x55 [48] 1 ¼” W30 58 ½” Structural Option 39 John M Sekel Structural Depth • Deflections and camber 3" 116 4" 2" 514" 5" W Shape Structural Option 40 John M Sekel Structural Depth • Connections W14x22 Full fillet weld both sides (typ.) (4) A 325 7/8" bolts Shear tab 2.80" 10.39" W24x62 W24x62 W14x120 W24x55 Structural Option 41 John M Sekel Structural Depth • Drift Structural Option Frame Drift Ratio #1 1.77” 1/583 #2 1.49” 1/693 #3 1.44” 1/717 #4 2.43” 1/425 42 John M Sekel Structural Depth • Drift Frame #1 Frame #2 Frame #3 Frame #4 Level Drift Ratio Drift Ratio Drift Ratio Drift Ratio 2 0.290” 1/662 0.219” 1/877 0.226” 1/850 0.371” 1/518 3 0.288” 1/583 0.268” 1/627 0.270” 1/622 0.386” 1/435 4 0.299” 1/562 0.265” 1/634 0.260” 1/646 0.414” 1/406 5 0.295” 1/570 0.254” 1/661 0.244” 1/689 0.415” 1/405 6 0.292” 1/575 0.240” 1/700 0.224” 1/750 0.411” 1/409 R 0.302” 1/616 0.238” 1/782 0.212” 1/877 0.430” 1/433 Structural Option 43 John M Sekel Construction Breadth • Working crews – – – – – – – – – RS Means assumes a steel crew of the following: (2) Steel foremen (5) Steel workers (1) Welder (1) Welding machine (1) Oiler operator (1) Crane operator (1) 90 ton crane The daily operating cost for this crew is $4091.40. Structural Option 44 John M Sekel Construction Breadth • Crane reach – 60 ton crane – 4 ton pick at 60’ – W21X182 frame column Structural Option 45 John M Sekel Construction Breadth • Project delivery system OWNER Contract Line Milestone Industrial, LLC Conversation Line FIXED PRICE FIXED PRICE CIVIL ENGINEER FIXED PRICE ARCHITECT GENERAL CONTRACTOR Hickok Warner Fox Architects L.F. Jennings FIXED PRICE STRUCTURAL ENGINEER MEP ENGINEER Structural Design Group, Ltd. Girard Engineering, Ltd. FIXED PRICE COST PLUS FEE STEEL CONTRACTOR LUMP SUM LUMP SUM LOBBY CONTRACTOR COST PLUS FEE LUMP SUM MECHANICAL CONTRACTOR OTHER ENGINEERS Structural Option COST PLUS FEE GMP ELECTRICAL CONTRACTOR STEEL ERECTOR OTHER CONTRACTORS 46 John M Sekel Construction Breadth • Linear footage comparison – Original structure: 43,300 feet – Redesigned structure: 32,700 feet – Additional cost is hidden in fabrication and materials Structural Option 47 John M Sekel
© Copyright 2026 Paperzz