JCR_268 New ECC and SEMOpx Member registration timeline

I-SEM Programme
Change Request & Impact Assessment Form
JCR 268
Section 1: CHANGE REQUEST DETAILS (to be completed by CR Originator)
CR Title:
New ECC and SEMOpx Member registration timeline including a secondary
deadline date
The current member registration process requires participants to submit all
registration forms for SEMOpx and ECC by 7 August 2017 in order to be included
in Market Trial and Go-Live. This includes confirmation of signed agreements with
Settlement Banks/Clearing Members. This date is a Level 2 Milestone (Milestone
#11).
In response to participant feedback received in Business Liaison Groups, a
revision to the requirements for this 7 August 2017 date is proposed, along with
the inclusion of a later deadline date of 7 February 2018 for some requirements of
the SEMOpx and ECC registration.
Description of Change:
The proposed changes are as follows:
1. Remove Milestone #11 DAM/IDM application deadline (for inclusion in
Market Trial
Last date for registration of participants in the Day-Ahead Market (DAM) or
Intra-Day Market (IDM).
CR
Description &
Reason for
submission:
Baseline date: 7 August 2017.
2. Add Milestone #11a DAM/IDM application deadline (for inclusion in
Market Trial) Part 1 MT
Deadline date for submission of SEMOpx exchange applications and ECC
applications (excluding confirmation of the clearing members/settlement
bank) for Market Trial and pre-registration for Go-Live.
Baseline date: 7 August 2017.
3. Add Milestone #11b DAM/IDM application deadline (for inclusion in GoLive) Part 1 GL
Deadline date for new members not participating in Market Trial to submit
SEMOpx
exchange
applications
and
ECC
applications
(excluding
confirmation of the clearing members/settlement bank) for registration for GoLive.
Baseline date: 1 December 2017.
4. Add Milestone #11c DAM/IDM application deadline (for inclusion in
Market Trial and Go-Live) Part 2 MT&GL
Deadline date for:
a. Confirmation of clearing member/settlement bank for each member.
b. Application for changes to NCM/DCP setup for the remainder of Market
Trial and Go-Live.
c. Existing ECC members not participating in Market Trial to submit SEMOpx
exchange applications and ECC applications (including confirmation of the
clearing members/settlement bank) for registration for Go-Live.
Baseline date: 7 February 2018
The table below summarises the new milestones:
These proposed changes were communicated to the BLG on the 18 May 2017.
The Transition Registration Plan will be updated to reflect the revised dates
above.
CR Originating
TSOs
Party:
CR Sponsor
Name:
Nigel Thomson
CR Originator
Name:
Nigel Thomson
CR Originator
Email:
[email protected]
CR Originator
Phone:
CR Date
Raised:
31 May 2017
Date Required:
09 June 2017
Section 2: CHANGE REQUEST LOGGING (to be completed by CCC / JPLG)
CR ID:
CR_268
JPLG Date:
31 May 2017
Minimum
Moderate
Core Parties :
Other Impacted Parties (please list) :
CR Priority:
TSO
RAs
Impacted
Organisation(s):
ICO
PLGs :
PMG
BLG
TLG
x
Significant
Date issued for IA:
2 June 2017
Due Date for IA completion:
16 June 2017
Section 3: IMPACT ASSESSMENT (to be completed by relevant party)
Name, email and phone number of person
completing IA (if different from CR
Originator):
Date IA completed and returned:
CR Impact Assessment
Include suggested process, impact on dependencies, project schedule, project scope, identify
individuals/organisations involved.
CR Estimated Time Impact / Target Date for Completion
CR Estimated Cost Impact (please state £ or €)
Section 4: RECOMMENDATION AND DECISION (to be completed by JPLG)
JPLG Recommendation to JPB:
Approve
Additional notes / comments:
JPB Decision / Recommendation to Approve
I-SEM SG (Significant CR only):
Additional notes / comments:
I-SEM SG Decision (Significant CR <Approve / Defer / Reject>
only):
Additional notes / comments:
Implementation Date: