Better Together Excellence in Programme and Project Management for London: PMO Case Studies London EPPM Programme Example Case Studies: London Borough of Hammersmith and Fulham – The Evolution of a Successful Corporate PMO Hammersmith and Fulham (h&f) Council initially created a Programme Management Office (PMO) simply to serve and deliver their Customer First programme. This has since successfully evolved into a Corporate PMO at the centre of a programme and project governance framework that works well within a local government setting. However this is not the end of h&f’s journey. Much remains to be tackled; this is a big change programme in itself, especially within the setting of a serious shortage of people with real proven programme and project management experience in local government. The challenge A number of challenges were faced at the start of the process. First and foremost the fledgling Customer First PMO found itself facing an overly complex governance structure that had several boards in place, with decisions either taking too long or not being made at all. The roles, responsibilities and most importantly the question of who was ultimately accountable was far from clear. Coupled with this was a lack of clarity over what constituted a workstream, a project or a programme (e.g. with projects calling themselves programmes to “inflate” their own importance), no common definition of what constituted Red, Amber and Green risks / status and many projects being led by someone who was project managing for the first time after attending a two-day training course. At the very beginning project managers even lacked a common set of tools and templates for them to use and one of the early tasks of the PMO was to put a good Project Management Toolkit (PM Toolkit) in place. As a consequence of the above issues, the PMO found itself exerting huge effort to “feed” the various board meetings with reports that mainly showed a “sea of green”. The boards themselves had no real teeth, were adding little value to the process and were reacting to situations rather than managing or governing. Overall this also meant poor management of the benefits cycle – from definition through to delivery and realisation. Given the size and scale of the changes that the Council wanted to pursue to better serve its residents this was an uneasy start point but thankfully there was growing recognition that things needed to change. Shifting the centre of gravity towards a stronger programme framework was and still remains a big change programme in its own right with its own issues, not least of which is having enough “bandwidth” to manage an operational PMO and manage the change and the shaping of new programmes. The Solution – Despite the above challenges, the Customer First PMO managed to gain credibility for both itself and for a programme centred approach for delivering change. This led to the creation of the Corporate Programme Management Office in April 2007 and the agreement at CMT level of the h&f Programme Governance Framework. This moved the focus from a high number of projects (180+) to a small number of strategic programmes, all with experienced managers and with Directors as their Senior Responsible Owners. A total of six strategic programmes are currently in place, two of which are truly corporate-wide programmes – the Corporate Efficiency Programme and the Smart Working Programme. Standard programme dashboards were created and implemented. These are presented monthly to the central Strategic Programme Management Group (SPMG) and the Corporate Management Team (CMT). In further support of these changes a second release of the PM Toolkit was put in place. This incorporates some very fundamental changes including clear categorisation of projects based on their size and duration and a differentiation between projects that are part of programmes and those that are stand-alone. As a consequence it is now far easier to identify between small localised departmental projects and those of much greater significance requiring the ongoing attention of the PMO and the h&f Governance framework. The scope of the PM toolkit was also expanded to include the templates and tools needed for construction projects. Currently under development and nearing completion is a range of specific tools and techniques for developing and managing programmes - from the initial business case / ROI through to the delivery of the programme itself and its business benefits. H&f Programme Management Framework - Homepage Multiple navigation and search options DRAFT VERSION Clickable view of the Framework The Benefits – It remains early days and the key benefits are still difficult to quantify in financial terms but are evident in a number of other ways, primarily in enabling a more efficient and effective prioritisation and management of investments through much better consistency in business cases and ROI calculations, more predictable programme delivery and in allowing the organisation to be made aware of issues and risks at a much earlier stage. The introduction of a consistent set of new and updated tools and related business processes to manage the benefits cycle will directly assist the delivery of Mid Term Financial Strategy (MTFS) commitments and substantially reduce risks through early accurate visibility on all aspects of status. Ultimately this will lead to a much more consistent delivery of programmes and projects, thus reducing costs to h&f. Early indications are very positive with behaviours at all levels up to and including CMT reflecting the much clearer ownership and visibility of key programmes and projects and the time and attention now being given to major issues and risks as they arise. Conclusion – For h&f this has so far been a 3 year journey towards creating a PMO with real power, rather than a central admin shop, with several lessons learned along the way. In taking the first steps don’t try to solve everything at once, but concentrate on one large programme. Get some experienced people into your PMO and onto the big strategic programmes and projects. There is a definite shortage of people with proven programme management experience and skills in local government, so place your best people where they will have the most impact. Tools are important, especially if you don’t really have any, but tackle the people, skills and process issues before you spend much time or money in developing tools. Get CMT level sponsorship as early as possible and make sure that they are intrinsically involved in a clear, well-defined governance framework. It is considerably simpler to define, manage and deliver business benefits through a small number of strategic programmes than through a large number of projects, so focus your approach on delivery via programmes. Finally don’t underestimate the scale of change needed to implement a programme governance, delivery and tracking framework and remember to constantly evangelise about the crucial role of trained, experienced, professional programme and project managers – after all, you will never get very far without them. Manchester City Council – Design, Development and Implementation of a Portfolio Programme and Project Management Solution Manchester has some of the most exciting development opportunities and programmes in the UK but some of the biggest project delivery challenges with a capital programme of 800 projects worth £250M pa. The challenge – A system was procured to enable the third “automation” stage of Manchester City Council’s 4 stage transformation strategy to bring surety to their Capital Programme and improve Programme and Project management capability across the Council. The major challenges faced related to the need to provide user-friendly support and information to a broad spectrum of staff from senior executives to novice project managers. The Solution – A Project Management Portal was designed and implemented that provided a single point of access for on-line practical support for project managers, visibility of programmes and plans and business critical information for decision-making. The system enables delivery of a diverse range of projects from the largest, high value capital construction to product and service delivery in Children, Families and Social Care. The solution has been deployed successfully to 270 users and it is planned to continue to roll-out to 1,000 users across all service departments and delivery partners. In practice a number of different methods were utilised to implement the system. A hierarchical work structure was set up by Portfolio, Programme and Project as per OGC best practice. There was embedded project management process and Gateway support for project scrutiny and approval. This was facilitated by comprehensive web-based reporting including dashboards and GIS interface, cost forecasting and tracking, as well as fund allocation with management and reporting. The management of risks and issues as well as milestones was also important in the successful outcome of the programme. Consulting services were procured in order to complete the deployment. This included Project Scoping and definition with requirements capture and solution design at the outset of the work. Advice regarding the structuring of the Portfolio Programme and Project Management (PPPM) solution was also provided to the Council. In addition technical infrastructure assessment and hardware selection advice was supplied, as was change management and implementation guidance. Training materials were also provided in order to further assist the Council. The Benefits – The solution was developed rapidly to meet the client’s specified requirements and flexibility in the partnership has proved invaluable in developing the functionality to assist with take-up and embedment in the Council’s organisation. Manchester City Council recently reviewed the business case and estimated that a pay-back over the period 2005-10 reveal cashable savings of £950k (£480k weighted) mostly software licence costs, and noncashable savings of £13.7m (£12.6m weighted) mostly time savings released through data sharing and collaborative working. Conclusion – Effective delivery of projects critically depends on the sharing of a common set of data across all members of project teams to provide visibility and control, help the team apply consistent best practice and enable collaboration to achieve a common goal. London Borough of Haringey – Introducing Programme and Project Management Discipline The London Borough of Haringey was running a large number of uncoordinated and differently-run projects and needed to move towards a single disciplined approach under a Programme Management Office (PMO). This piece of work was undertaken to improve transparency and project success. The Challenge – The primary concern for the London Borough of Haringey was the visibility that the senior management had of these projects. The borough was running a large number of complex transformational projects, and elected members of the Council and senior managers had no knowledge of overall project progress at any given point in the lifecycle of the project. This was allowing projects to overrun and in one particular case a project came in at almost double the planned original cost. In addition to this, there was a high turnover of project managers with no coordinated approach to record-keeping and knowledge transfer. This caused the projects to either stall or grow very expensive due to duplication of work. The LBH also suffered from little to no knowledge of or control over projects being delivered by contractors. The Solution – A slim user-friendly Haringey-specific ‘Project Management Framework’ (PMF) was introduced which consisted of project management protocols and guidance on how to run projects, with mandatory templates for project managers. The problem of governance was addressed through the creation of a single, authority-wide, unified pyramid structure for all projects of a certain size and complexity. It is a four-tier governance structure with information funnelled from project boards, through programme boards, to the Chief Executive’s Management Board, and then on to elected members. This addressed the problem of visibility and ensured that members and senior managers could check project success at any one point. Once the Programme Management Framework (PMF) and governance were embedded a Programme Management Office was set up to ensure compliance with the new systems and to support the project managers. The PMO quality assure project documentation and have become holders of best practice for programme and project management across the council. It was also crucial to gain the council-wide support of elected members and the senior management team from the outset. Discipline and governance suffered if project managers did not believe they had the full support from the top of the organisation. The Benefits – There has been a significant improvement in risk management across the programmes and projects. On a project level there is now full and timely information on progress on a monthly basis, allowing the authority to focus on ‘prevention rather than cure.’ The Programme Management Office has created and manages the Corporate-level programmes and projects risk and issue log. The greater visibility of project activity has also allowed better understanding of success and knowledge of budgetary spend. This has also helped with the workload and preparation for audits as the material is already available. A recent IT Scrutiny Review carried out by SOCITM Consulting found, ‘in general, project management / governance was considered to be very good and certainly in the top 10% of local authorities of which SOCITM have experienced.’ No project failure has been experienced since the new system has been in place - at mid-year point for 2007/08 on a total programme budget of £284m there is a predicted under spend of £84k i.e. les than 1%. Conclusion – The introduction of a new discipline and the necessary culture change may not be popular, but following a process of normalisation project managers come to appreciate the feeling of security they get from knowing that they are using an approved and tested process with input and oversight from senior decision-makers. It is also important to strike a balance between ensuring people are kept informed and not overloading the project managers with onerous bureaucracy. Simplicity in relation to the templates and the processes only helps the users and thus the functioning of the projects and in turn the programmes. London Borough of Greenwich – Modernisation Programme Office During the 1980s and 1990s Greenwich, like many Councils, had experienced minimal expansion and investment in infrastructure and services. This had resulted in: housing estates requiring major renovation school buildings that were in poor condition face-to-face service centres that were poorly presented and uncoordinated unreliable ICT that was difficult to support old-fashioned and inefficient Council offices under-occupied Council buildings that were in poor condition a major backlog of maintenance and a legacy of under-investment. By the beginning of 2000 there was a number of drivers for change, including the Gershon Report; the E-Government agenda; the increased value of the Council’s property assets; the need to modernise school buildings and the need to achieve the Decent Homes standard for social housing directly managed by the Council. These drivers led to the Council establishing a Modernisation Programme in 2005 under the leadership of a corporate full-time Programme Office. The Challenge – One of the initial challenges centred on the funding for the programme as it could not be made available from Council Tax. There was a need to assemble the financial package for the overall Programme from a range of sources in line with the individual programme needs. It was also important to ensure these projects and programmes stayed within their financial envelopes once the programme entered the implementation stage. A robust governance system had to be devised and established to ensure that the programme was effectively led, managed and monitored. The Programme Office also needed support from suitably skilled and experienced programme and project personnel. Given the scale of change that would result from the Modernisation Programme there was a need to create clear and consistent messages which could be communicated across the Council, to our residents and to other stakeholders. A communications strategy had to be developed in order to deliver core messages to all audiences and specific messages to target groups. These communications had to align with key milestones in the overall Modernisation Programme and individual programmes and projects. The Solution – Greenwich Council embarked on an ambitious Modernisation Programme in 2005. It centred on three inter-related themes of service delivery, property and technology. The overall value of the Programme was in excess of £750m. A Programme Office was established under the direction of the Deputy to the Chief Executive, with a full-time team of senior managers, to oversee the Programme and ensure effective leadership, planning, execution and control of the Programme. The Programme consisted of 10 key strands: Woolwich Civic Office – new Council offices Eltham Centre – major new leisure centre, college and library Greenwich Centre – major new leisure centre, health centre and library Service Delivery & E-Government – investment in ICT Building Schools for the Future – 5 secondary schools in first wave Children’s Centres – 21 new centres Schools’ Capital Housing Renewal – Decent Homes, major estate demolition and renewal Organisational Change – the development of initiatives for shared services and behavioural change that would maximise the Council’s effectiveness Neighbourhood Property Strategy – rationalisation of Council property A well defined and robust governance structure was established and put in place to ensure that the right decisions were taken quickly yet with a focus on accountability. A number of bodies and tools were set up to facilitate this new structure. This included the Modernisation Implementation Board and the Greenwich Management Team Blue. Project and Programme Boards with Project/Programme Owners (external to the Programme Office) and Project Managers were also utilised. There was also strong financial management led by a dedicated Assistant Director seconded from the Finance Department. The Benefits – The key benefit delivered by the Modernisation Programme was the delivery of projects and programmes within budget and time constraints. Conclusion – The Modernisation Programme has highlighted a number of important areas key to the successful delivery of a programme of this character. Strong, clear management and the need to focus on change were fundamental tenets of the programme. Placing a concentration of expertise in the programme and a strong management team was vital. The use of the correct Project and Programme management systems and processes coupled with providing a greater transparency in regards to projects and programmes all proved to help the Modernisation Programme succeed in its goals.
© Copyright 2026 Paperzz