Review LIU PS TT2

EN-CV Review TT2
12-01-2016
Cooling PS – TT2: existing
Booster cooling plant :
For all equipments from
Booster + TT2
Nominal pressure:14 bar
Flow capacity: 310 m3/h
Central building cooling plant :
Copper circuit for power converters, RF,..
All equipments except main magnets
Nominal pressure: 15 bar
Flow capacity: 160 m3/h
Main magnet cooling plant :
Aluminium circuit for main magnets.
Nominal pressure:10 bar
Flow capacity: 260 m3/h
Cooling 1/2
Consolidation during LS2 :
• Project approved:
• Refurbishment of the Booster TT2 cooling plant
• Refurbishment of the PS Central building
cooling plant
• Refurbishment of the PS Main magnet cooling
plant
• The connection of the TT2 cooling to the PS
central building plant is not included in the
consolidation program.
• A reasonable technical solution should be found
to supply TT2 (including the new power
converters in bldg. 269) by the PS circuit during
this YETS.
Cooling 2/2
• The central building cooling plant can’t take
the future needs for the PS (even without
the TT2) because of the 10 MHz cavities
and probably other requirements (new
beam dumps, new ionization profile
monitor and one additional magnet, new
vertical correctors,..)
• In the PS the diameters of the pipes are
already small compare to the actual flow. A
replacement of the distribution lines are not
included in the consolidation packages.
Ventilation TT2: Existing
• 4 air handling units only for thermal load.
• No smoke extraction, fresh air, ventilation
mode, etc..
• Air handling units replaced in 2001
• Chilled water coming from the ISR circuit.
• Consolidation have been postponed after
LS2
• The thermal load is low so the impact of a
chilled water failure does not have an
immediate effect. This allows in many cases
to repair before affecting the beam.
Summary
Installation
Work
Budget
Schedule of
installation
TT2 magnet
cooling
New lines in order
to supply cooling
from the PS
Following the
technical solution
could be
consolidation or
LIU
Probably in LS2
TT2 power
converters in bldg.
269
New distribution
inside the
renovated bldg.
269
LIU budget
See presentation
LIU in September
Ventilation of the
bldg. 269.
Replacement of
the existing
ventilation with a
new one.
LIU budget
See presentation
LIU in September
Summary
Installation
Work
Budget
Schedule of
installation
Ventilation in TT2
No work foreseen
Chiller water for
the air handling
units TT2
Replacing the
existing pipes
Consolidation
After LS2
PS distribution:
from cooling
central bldg
If needed replace
LIU
the pipes by bigger
ones to cope with
the LIU additionnal
needs.
LS2
Summary
Installation
Work
Budget
Schedule of
installation
Booster cooling
plant
Full refurbishment Consolidation
Without TT2 needs
LS2
PS Central
building cooling
plant
Full refurbishment
including TT2
needs.
Consolidation
LS2
PS Main magnet
cooling plant
Full refurbishment
Consolidation
LS2