Danilo Domenici – LNF Detector Upgrades Overview QCAL Inner Tracker CCAL CSN1 - 4 Maggio 13 2 Old Interaction Region Fake QCAL (actually Pb shields) CSN1 - 4 Maggio 13 In January the old DAFNE Interaction Region has been extracted from KLOE and completely disassembled 3 Modifications of IR components New IP Spherical vacuum chamber New beryllium shields New BPMs Moving devices for quadrupoles QF Cooling of IP vacuum chamber added Cooling of Y vacuum chambers added Lead toroidal shields added New Cylindrical vacuum chamber support Improvements on alignment tools H supports reinforced with plates Modification of tail support of the girder Temperature probes added CSN1 - 4 Maggio 13 4 New spherical vacuum chamber CSN1 - 4 Maggio 13 Single vacuum chamber tapered New bellows with improved design 2 BPMS around the IP Water cooling added New beryllium screens 5 Mounting the new IR CSN1 - 4 Maggio 13 6 CCAL 12 LYSO crystals in each module CSN1 - 4 Maggio 13 PCB housing SiPM and calibration LED housed by a 3d-printed ABS case 7 CCAL Beam Position Monitor Copper coil for IR cooling Support flange for IT QD0 CSN1 - 4 Maggio 13 8 CCAL Test Test performed with the embedded calibration LED CSN1 - 4 Maggio 13 9 IT Layers assembling In February the last Layer of the IT has been completed and in the π-day (March 14) the four detectors have been assembled together Layer4 Ø 410 mm CSN1 - 4 Maggio 13 Layer3 Ø 360 mm Layer2 Layer1 Ø 310 mm Ø 260 mm 10 IT Layers assembling Starting from the outermost one, all the layers have been inserted one into the other PCB Faraday-cage cap CSN1 - 4 Maggio 13 11 Inner Tracker CSN1 - 4 Maggio 13 12 IT FEE cooling There are 90 FEE per side (180 GASTONE chips) The heat power created is 100W per side There will be a general air-cooling for the IR region and a dedicated water-colling for the IT FEE The system is completed by 4 distributors with valves 5 copper rings as radiators CSN1 - 4 Maggio 13 13 IT positioned on the sliding support BP temporary supported by Al arm BP welded IT in final position CSN1 - 4 Maggio 13 14 IT positioning on the IR Internal FR4 support flange Al support flange on QD0 0,5 mm clearance CSN1 - 4 Maggio 13 15 QCALT 2 halves of one calo ready to be mounted LET house Both QCALT installed on the IR CSN1 - 4 Maggio 13 16 IR equipped with all the detectors CSN1 - 4 Maggio 13 17 Movement of IR May 20 the IR has been moved close to KLOE Here QCALT and IT are being cabled and tested CSN1 - 4 Maggio 13 18 QCALT FEE mounting and cabling Each module is read out using 80 SiPM channels positioned with 0.05 mm precision on aluminum dioxide PCB Each PCB has 4 front end boards with 20 channels each with HV regulator, preamplifier and splitter CSN1 - 4 Maggio 13 19 QCALT cabling Cabling of all 22 modules completed last week CSN1 - 4 Maggio 13 20 QCALT test Every channel has been tested after cabling to check SiPM working point and discriminator/scaler chain SiPM procedure will be done only using scaler (no ADC present) looking at the variation of rate when moving discriminator threshold CSN1 - 4 Maggio 13 PED 1pe 2pe Now we are preparing the set up with final crate to perform long cosmic run using KLOE final data format 21 IT cabling Each IT side has: 90 readout cables 69 HV cables 36 gas tubes 8 cooling tubes 6 Temp. probes cables The first 2 layers have been cabled CSN1 - 4 Maggio 13 22 Final HV and DAQ systems Trigger logic HV distributor back side GIB + TB crate HV powe supply and Current meter CSN1 - 4 Maggio 13 VME crates and optic link concentrator 23 Final gas system Gas rack with mass flowmeters and control in KLOE assembly hall Gas distributors in KLOE pit CSN1 - 4 Maggio 13 24 IT cosmic ray test We check that all the connections are properly done To complete the scan we move the trigger in 6 positions 600 cosmics (1 ÷ 4 hours) per each position are enough 2 scintillators trigger Layer1 test completed last week CSN1 - 4 Maggio 13 25 Next step: insertion into KLOE KLOE DC inner hole (500 mm diameter) CSN1 - 4 Maggio 13 Rails and shell used for the extraction of the old IR 26 Insertion clearances The shell will be shifted upward to increase the top clearance Sides will be machined to gain 2 mm CSN1 - 4 Maggio 13 8 mm will be the minimum clearance available between DC and IR 27 Modification of the Shell A 50 cm extension part of the shell has been built to allow the routing of the cables Shell Extension Cable routing CSN1 - 4 Maggio 13 28 Time Schedule 6 week delay due to Be screens delivery Now we have 3 weeks delay CSN1 - 4 Maggio 13 29 Conclusioni La fase 2 di KLOE-2 è iniziata a gennaio 2013 La vecchia IR è stata completamente disassemblata e rinnovata I 3 nuovi rivelatori (CCALT, QCALT, IT) sono stati installati con successo sulla IR CCALT e QCALT sono stati cablati e verificati Cablaggio e test dell’IT sono in corso e dureranno 4 settimane CSN1 - 4 Maggio 13 30
© Copyright 2026 Paperzz