Stratford-on-Avon District Council: Core Strategy Risk and Assurance Services “Providing assurance on the management of risks” Report status Final Report date 4th December 2015 Prepared by Christopher Portmann, Senior Auditor NOT PROTECTIVELY MARKED Core Strategy RISK AND ASSURANCE SERVICES SDDEV/2016 _____________________________________________________________________________________________________________________________ Background The development of the Core Strategy has been undertaken over a number of years, but particularly the last four years. During that period due in the main to changes in national legislation and guidance the overall housing numbers requirement has changed markedly. Consequently with the passage of time, it has been necessary to revisit evidence that had been obtained to support the emerging Core Strategy. All of the updated reports have been considered by the Cabinet and included in the overall evidence base, however, this has inevitably led to an overall increase to the costs that the Council has incurred. This report also demonstrates that on occasions where revised evidence has been required the Council has requested the original tenderer to undertake additional work so as not to further delay the production of the Core Strategy. It should be noted in addition that a number of the costs that the Council have incurred are not within the control of the Council, this in the main relates to the costs of the Planning Inspectorate, and the cost of running the Examination in Public exercise. Total expenditure on the Core Strategy between the 2007/08 financial year and the end of September 2015 stands at £1,244,909. Key Findings The review included a detailed examination of expenditure transactions from funds allocated to the Core Strategy. This confirmed that all funds allocated to the Core Strategy have been spent on their intended purpose and the recent request to Members for additional funding appears to be necessary. Moreover, there are robust controls as regards budget monitoring and control with the Accountancy section producing detailed monthly budget monitoring reports for the Planning & Housing Policy Manager. The Planning & Housing Policy Manager reports directly to the Chief Executive and reports on any budget variances as appropriate. Introduction Warwickshire County Council's Risk and Assurance Services provides the Internal Audit Function on behalf of Stratford District Council. A request was received for Internal Audit to undertake a review of the expenditure on the Core Strategy. This review was in addition to the agreed 2015/16 audit plan. The objective is to review the expenditure relating to the development of the Core Strategy, including costs of consultants, temporary staff and the planning inspectorate, as well as the forecasting and reporting of such costs. In addition, there is a bi-monthly revenue and capital budget report to Cabinet, which includes expenditure and any variances relating to the Core Strategy and there is an audit trail which shows that all budgets allocated to the Core Strategy have been properly approved. The Core Strategy budget did not take into account the possibility that the Independent Examination might result in the Core Strategy not being approved and consequently no contingency was included for any additional inspection costs and additional work that might arise. It should be noted that the costs of the Planning Inspectorate are outside of the Council's control. NOT PROTECTIVELY MARKED Page 2 of 9 Core Strategy RISK AND ASSURANCE SERVICES SDDEV/2016 _____________________________________________________________________________________________________________________________ An Interim Report was received from the Independent Examination of the Council's submitted Core Strategy dated 18th March 2015 highlighting that more work on the Core Strategy was required. However, whilst the actual costs were not known, the Interim Report should have alerted officers that the costs of the Independent Examination would be greater than anticipated (even though the invoice from the Planning Inspectorate for the original Examination in Public had not been received) and there would also be the need for additional work on the Core Strategy formulation. Budget monitoring reports indicated that the overall budget was on target and a request for additional funding was not submitted to Members until 19th October 2015. Where the requirements of the Core Strategy have changed, the Council has reacted quickly to these. In addition to the budget management issues the review highlighted one instance where no competitive procurement process had been followed for the engagement of consultants, in accordance with the requirements of the Council's Contract Standing Orders, making it difficult to ascertain whether value for money had been obtained. In addition there were three cases where the overall amounts paid to consultants were greater than the total amounts tendered. Instances were also noted where written contracts were not in place for consultancy assignments. NOT PROTECTIVELY MARKED Page 3 of 9 Core Strategy SDDEV/2016 RISK AND ASSURANCE SERVICES Appendix A – Findings & Action Plan Explanation of Priority ratings: Priority Explanation Fundamental: Action that is considered imperative to ensure that the organisation is not exposed to high risks. Major adverse impact on achievement of organisation’s objectives if not adequately addressed. Significant: Action that is considered necessary to avoid exposing the organisation to significant risks. Merits Attention: Action that is considered desirable and should result in enhanced control or better value for money. Minimal adverse impact on achievement of the organisation’s objectives if not adequately addressed. These definitions are illustrative only and professional judgement is exercised when determining the priority rating of recommendations NOT PROTECTIVELY MARKED Page 4 of 9 Core Strategy SDDEV/2016 RISK AND ASSURANCE SERVICES Appendix B – Findings & Action Plan Risks and Implications 01 Risks: The implications on the budget may not have been fully considered and reported appropriately. Finding Recommended Action An Interim Report on the Core Strategy was received from the Independent Examination dated 18th March 2015 highlighting that more work on the Core Strategy was required. However, whilst the actual costs were not known, the Interim Report should have alerted officers that the costs of the Independent Examination would be greater than anticipated and there would also be the need for additional work on the Core Strategy formulation. Budget monitoring reports indicated that the overall budget was on target and a request for additional funding was not submitted to Members until 19th October 2015. Budget monitoring arrangements for the Core Strategy should be reviewed to ensure that outturn forecasts are robust and reported to members in a timely manner. Budgeting for the Core Strategy should be reviewed and more up to date budgets agreed, including setting aside a In the event that plans are not contingency on the basis that achieved, there is no examination costs may be contingency to support this higher than currently anticipated scenario. and also to ensure that there is a contingency covering any additional work that may be Implications: required following the The full financial liability of the examination. This is particularly Council may not be known. It was also noted that the Core important given the ongoing Strategy budget did not take into changes in requirements Insufficient resources to support account the possibility that the regarding the Core Strategy and the Core Strategy. Independent Examination might consequent uncertainty as to result in the Core Strategy not being what is required. approved and consequently no contingency was included for any additional inspection costs and additional work that might arise. Budgets set may not be realistic. It was originally anticipated that the costs of the examination would be around £90,000 but the examination is ongoing and the examination costs are now estimated to be over NOT PROTECTIVELY MARKED Page 5 of 9 Priority Management Action It is accepted that the Budget Monitoring reports did not highlight the resources for the Core Strategy as a risk during the early part of 2015/16. However, as identified within the findings the actual costs were not known and the payment of £113,945.32 was not made to the Planning Inspector until 9th September 2015, ahead of the special report on 19th October 2015. It is accepted however, that some additional costs could have been predicted. In relation to contingencies, it is not the practice of the Council to provide such budgets. Whilst there are virement arrangements in place it is appropriate that requests be made to Cabinet/Council for additional resources is required. Action has already been put in place to ensure better forecasting of year end positions across the Council. Core Strategy SDDEV/2016 RISK AND ASSURANCE SERVICES Risks and Implications Finding Recommended Action Priority Management Action £200,000 and the costs of consultancy work and legal fees have exceeded those budgeted for due to the additional work now required. 02 Risks: It is difficult to demonstrate that value for money has been obtained. Non-compliance with Contract Standing Orders and European Union Procurement Legislation. The overall values of payments to five individual consultants within the expenditure sample reviewed were analysed and tracked to procurement processes conducted: Consultant ref: A Total net value of payments (£) 172,255.18 B 49,666.01 C 117,970 D 85,523 E 99,172 A lack of protection afforded to staff managing contracts. Implications: The Council could be placed in a vulnerable position should the award of contracts be challenged. Period payments made over Sept 2011Sept 2015 May 2011Feb 2013 May 2011 – Oct 2014 January 2012 – August 2015 Dec 2013 – Sep All contracts should be procured in accordance with the requirements of Contract Standing Orders. Wherever possible related work should be packaged and tendered together to seek to maximise economies of scale as well as securing a commitment and accountability from contractors to deliver all that is required by the Council rather than elements of a larger piece of work. NOT PROTECTIVELY MARKED Page 6 of 9 Expenditure on Consultant E was originally an urgent report estimated value less than £15,000 so did not require a rtendering exercise under Council’s Standing Orders. In addition other consultants were not available at the time of the work, which was to review another consultancy’s estimate of housing requirements. The continued use of this consultant (as reported to members) was because the Council had greater confidence in this consultant’s work than others. However it is accepted that if it had been known that the adoption of the Core Strategy would take such an extended period of time, it would have been preferable to undertake a tendering exercise in this instance. Core Strategy SDDEV/2016 Risks and Implications RISK AND ASSURANCE SERVICES Finding Recommended Action Priority Management Action 2015 The following points were noted: In the case of Consultant A, there were two procurement processes and one case where an exemption was applied; however these only account for £140,195 of the overall payments to this consultant; For Consultant B, there are records of competitive tenders being received for this. For Consultant C, a contract was awarded on 01.04.11 to the value of £28,695 following a competitive tendering process. A separate contract was awarded on 09.03.12 to the value of £61,280. These contracts only account for £89,975 of the overall amount paid. For Consultant D, there are records of two competitive tendering processes, however the total value of these contracts is only £32,077. There is no record of a competitive tendering process ever being conducted for Consultants or E. Moreover, some of the sums referred to in the table above were broken down into a number of pieces of work. It was noted that NOT PROTECTIVELY MARKED Page 7 of 9 All tenders undertaken were for discrete pieces of work and it was unknown there would be other packages of work provided to the same consultant. The law and guidance has been developing as the work has been undertaken. It is accepted for any future core strategy adoption a large scale tender may be appropriate, as would shared arrangements for providing the consultancy support. It is not accepted this could have occurred for this core strategy. Core Strategy SDDEV/2016 Risks and Implications RISK AND ASSURANCE SERVICES Finding Recommended Action Priority Management Action these were not packaged together and tendered as a larger piece of work. Under European Union Contract Aggregation Rules, where a series of contracts are awarded without undertaking a competitive procurement process, the arrangement could be deemed as being one significant contract rather than a series of relatively small ones. 03 Risks: Non-compliance with Contract Standing Orders. The record of contacts may be incomplete. Implications: Difficulty in identifying all contracts awarded. 04 Risks: A lack of division of duties. Implications: A lack of protection afforded to the individual concerned. Under Contract Standing Orders, a Contract Registration form has to be completed for all contracts "exceeding £25,000.00 as soon as the contract is entered into." It was noted that this form was not completed for any of the consultancy contracts examined during the review which exceeded this financial value. A Contract Registration form should be completed for all contracts exceeding £25,000.00 as soon as the contract is entered into in accordance with the requirements of Contract Standing Orders. This is only true for some of the works but for those projects it is accepted. A sample of 12 paid supplier invoices relating to the Core Strategy was reviewed. It was noted that in two cases, the same individual approved the purchase order, verified receipt of the goods/services provided and also approved the payment of the supplier invoice. The processes for approving purchase orders, verifying receipt of goods/services and approving invoices for payment should include an appropriate division of duties. This is not accepted as the Council does not have the staffing levels to accommodate this. NOT PROTECTIVELY MARKED Page 8 of 9 Core Strategy SDDEV/2016 05 RISK AND ASSURANCE SERVICES Risks and Implications Finding Recommended Action Risks: A lack of documented approval for expenditure committed. From the sample of 12 paid supplier invoices it was found that in 7 cases, the supplier invoice had been processed as a non-order payment. Wherever possible, an official authorised order should be raised for all purchases prior to receipt of the goods/services required to ensure that a commitment is raised in the budgetary records and to document the approval of the expenditure in advance. This matter has been resolved as a result of the new financial system. There was not a written contract in place in some cases where consultants had been engaged to undertake work on behalf of the Council. Contracts should be in place for all consultancy arrangements detailing the roles and responsibilities of the respective parties. Wherever possible, contracts should also include quantifiable and measureable outputs. Ensuring consultants have written contract requirements with due dates for completion is accepted. Commitments are not shown in the budgetary records. Implications: Budgetary control is reduced. 06 Risks: A lack of clarity over what is required and the respective roles and responsibilities of each party, Implications: Disputes over the arrangements may prove difficult to resolve. NOT PROTECTIVELY MARKED Page 9 of 9 Priority Management Action
© Copyright 2026 Paperzz