Kraus Group Level 2 – Kraus detail implementation Water reduction project Background Kraus Group’s 850,000 sq ft site in Waterloo, Ontario is a major energy and utility user, spending CAD $3.8 million annually on the water, gas and electricity required for its production processes. Energy and utility reduction was identified as a key focus by Hilco on its acquisition of Kraus in June 2012 and a 90 day improvement plan was put in place to target an initials ‘phase one’ $200,000 annualised saving with any capital expenditure required having a payback within three months. A multi-disciplined energy reduction team was established to detail measures for all major energy and utility usage systems across the site and to devise and to implement low cost initiatives to reduce consumption. The measurement process highlighted a number of initial utility reduction targets, including ‘vacuum pump’ systems. Large vacuum pumps are used to suck the water out from the final treatment process in carpet manufacture and were identified as a key target area for water consumption. By design, these large pumps use vast amounts of town water to achieve a vacuum seal. The water resides in the pump for only few seconds and is then dumped to drain, eventually passing into the municipal water treatment facility. Although modern systems are much more efficient in terms of water use, these replacements would incur a capital cost in excess of $100,000. At Kraus, charges are levied for both supply and disposal amounting to $3.60 per ton of water used giving an annualised water charge of over $120,000 for one vacuum system alone. Hilco’s Role Having led the investigation process to establish the initial reduction targets, the Hilco restructuring team then worked with the site’s engineering manager to devise a creative, low cost water recycling unit to avoid the need to dump the pump supply water to drain. Results The system was based on a combination of new and used components, including a 1 m3 proprietary transport container that cost only $150. The total capital cost of the system, including all automatic control systems, piping and installation, was only $6,500. The entire system was designed and built in house with no external labour costs Commissioned in December 2012, the system is now operating successfully and measurements confirm that water usage has reduced by over 97%, generating an annualised saving in excess of $90,000. In total, the energy team has delivered measured annualised savings of $260,000 with a capital expenditure of less than $18,000, significantly beating original ‘phase one’ targets. Key Facts Results ›850,000 sq ft carpet manufacturing › Total of $260,000 energy and utility ›Energy and utility spend over $3.8m › Total capex of under $17,000 › Water recycling system devised at facility p.a. ›Energy reduction team established to measure and reduce usage by $200,000 in first phase ›Vacuum pump systems identified as a major cause of water wastage www.hilcocapital.com • Tel 020 7317 2050 savings achieved minimal cost ($6,500) ›$90,000 annualised saving on water purchase and disposal charges
© Copyright 2026 Paperzz