ATLAS ITk BD2 R&D Project Claudio Bortolin (EP-ADO-PO) Bart Verlaat (EP-DT-FS) Lukasz Zwalinski (EP-DT-FS) ATLAS cooling team – 2016 ATLAS ITk and CO2 During LS3 a new tracker (Pixels and strips) will replace the actual Inner Detector. The total power to be remove from the new detector will be about 159kW (PIXELS only) with a maximum working temperature of -35 C in any location of the detector using CO2 as coolant. In order to meet these specifications it will be required to install a certain number of distribution manifolds inside the ATLAS toroid (PP2) connected to 5 cooling plants (+1 for redundancy) of 30kW each operative in the service cavern of ATLAS. The total number of loops will be in the order of ≈1000 and the fluid distribution balancing will be a critical task. The maximum evaporation temperature of -35 C can be achieved considering the cooling capabilities of the plants and the pressure gradients between the detector and the cooling stations. What is the minimum attainable temperature achievable in any location on the detector (cooling pipe temperature)? What is the best design of the transfer lines and manifolds to distribute the fluid properly keeping as low as possible the pressure gradient in the return pipe? The goal of the Baby-Demo project is to answer to these questions that will be part of the TDR of the ITk pixel detector to be submitted before the end of 2017. 2 Baby-Demo project It consists of: • Baby-Demo1 (BD1): design, construction and operation of a 5kW (the size of 1 transfer line) cooling plant to demonstrate the operation of the CO2 plant at the lowest attainable temperature. • Baby-Demo2 (BD2): the design, construction and installation of a full scale fluid distribution setup according to the real piping paths available in the experimental cavern. This installation will be coupled to the produced BD1 cooling plant, to demonstrate the full system loop performance in realistic conditions with realistic prototype detector structures. Where the height differences will play a key role. Junction box Manifold boxes Vacuum insulated transfer line Vacuum insulated concentric tubes (7x1.6x0.3mm inlet inside 4x0.5mm outlet) Vacuum terminal and concentric split Vacuum line Tile Calorie LAR Tracking Connection tube bundle 14x 3x0.5mm ID end plate dry volume 3 Baby-Demo BD2 in building 180 It consists of a cooling infrastructure setup which include the design, production and installation of 1 or 2 transfer lines (foam and/or vacuum insulated), distribution manifolds and “splitter box” concepts development equipped with many p,T sensors connected to a DAQ system. These elements will be used to connect the CO2 cooling plant (BD1) to the detector load modules, in a real scale environment, using the ATLAS Inner Detector distribution 1:1 scale mockup available in building 180. ATLAS Project Office agreed to help with the infrastructure design. 4 Infrastructure layout: Sector 5 The actual position of the mock-up with the plant installed at the ground level is correct to reproduce the sector 5 manifold height difference. Electrical Cabinet PP2 box with PT & TT Sensors Cooling Station PP1 box with PT & TT Sensors Foam box with detector measurements Use of the B180 basement agreed with TSO. HSE contacted to discuss about CO2 piping installation in a closed area. PP2 box with PT & TT Sensors Realistic height differences Crane limit switch Sector 5 Access Platform 2230 mm 3000 mm USA 15 Compressors Room Floor Sector 13 Platform between Muon BIL-BML, over metal rack (0.4 x0.5 x2.5m) or on the area of existing PP2 box Sector 13 Platform between Muon BML-BOL 1200 mm 530 mm 1700 mm 6435 mm 8979 mm IP 0 3800 mm In order to test the sector 13 distribution the Foam Box should be moved up of 1.2m Picture taken from presentation of Dina Giakoumi (ITk cooling meeting 15.03.2016) 9600 mm 8110 mm 3000 mm BD1 & DB2 schedule The target is to provide the answer what is the minimum attainable temperature in the detector modules before the end of 2017 for the Pixels TDR Baby DEMO BD2 schedule (taken from the Baby-Demo project schedule): 7 Transfer lines design Before the end of 2016 the design of the distribution parts should be completed Concentric Transfer lines and manifolds: from the cooling station to PP1, totally vacuum insulated or only from PP2 to PP1, keeping as a backup solution, the TL from the plant to PP2 standard insulated with Armaflex. Vacuum TL Vacuum or Armaflex insulated TL Design in collaboration with (preliminary contribution offered from): MPI (Germany) ANL (US) UK institutes Vacuum TL 8 PP1 box design: 1 line with warm nosing Dry-air volume Warm nose loop Well accessible standard VCR type connectors + Electrical breaks IDEP Detector volume Vapor return Liquid feed Warm nose loop Slide taken from presentation of B. Verlaat (ITk cooling meeting 15.03.2016) If the detector boundary becomes the dry-air boundary than warm nosing is not possible! Design: Genova (Italy)? Others? 9 Detector foam box construction – possible concept PIXELS Innermost Layers Z=0 Z=-1400 Z=-3000 Z=+1400 L1 ~750W L0 ~ 400W Z=3000 Line cooling pipe ~ 4KW Orifice orifice Local Support Liquid Flow Pictures taken from presentation of D. Giugni (ITk cooling meeting 15.03.2016) A test setup for the orifice design will be prepared soon in ATLAS SR1 using a foam box available at Crystal palace. Once the test will be over the same FM can be used for BD2. 10 Conclusions The Baby-Demo (BD) project: in order to define the minimum attainable temperature of the detector modules it has been recommended to build a test setup to reproduce the pressure gradients from the cooling plant to the detector. The BD project consists of 2 main tasks, the design and construction of: • a CO2 cooling station (BD1) • the replica of piping distribution from the plant to the detector module (BD2). As regards BD2, the installation of the real scale piping distribution will be carried out using the ATLAS Inner Detector distribution 1:1 scale mockup available in b. 180. The use of the building basement has been agreed with the TSO and soon I will discuss about the safety aspects with HSE. Agreed with the project office of ATLAS to design the support structures. The help and support of the ITk institutes is fundamental on the design and development of the cooling distribution: TLs, PP2 manifolds and the PP1 splitter box. 11
© Copyright 2026 Paperzz