2015 06 June Published LL Summary Part I

NERC Lessons Learned
Summary
LLs Published in June 2015
NERC lessons learned published in 2015
Two NERC lessons learned (LL) published in June 2015
• LL20150601 - Real-Time Contingency Analysis Failure due to a Modeling Error
• LL20150602 - Generator Distributed Control System Impact on Automatic Voltage Control
Real-Time Contingency
Analysis
to aError
Real-Time Contingency
Analysis Failure
Failure due todue
a Modeling
Modeling Error
• Real-Time Contingency Analysis (RTCA) failed to converge for 46 minutes
• During this time the State estimator converged intermittently
• Both power flow and contingency analysis were available in study
application, and System Operators (SO) had full visibility and control of the
system via SCADA
• SO did not recognize that the RTCA result had been non-convergent for 29
minutes because the alert status was not in an obvious location on the
screen, it was not a prominent color, and it lacked an indication that it was
critical
Real-Time
Contingency
Analysis Failure
Real-Time Contingency
Analysis
Failure
due
to
a
due to a Modeling Error
Modeling Error
Corrective Actions
• Corrected model topology change
 The error was attributed to a change made during testing that was not reflected in the file that
was used to update the model on the live system
• Modified the process for making similar changes
 The new process now includes an additional step to recreate the file if any changes are made
directly to the development during testing. The changes will be compared and verified to the
original file, and the newly created file will be used to populate the live system
• Display was adjusted with the status information moved to a more visible area, color of the
status alert for “non-converged” was changed from brown to red, and unique audible alarm
was also added to the “non-converged” status alert
• Event was communicated to all SOs, detailing the importance of understanding what the
different solution status terms mean
Real-Time
Contingency
Analysis Failure
Real-Time Contingency
Analysis
Failure
due
to
a
due to a Modeling Error
Modeling Error
Lessons Learned
• Additional change-control procedure needs to be in place to avoid the transfer of bad
data to production after it has been successfully tested on the development system
• For verification of changes, automated review, peer review, or both must be implemented
as part of any change process
• Real-time tools, state estimators, and RTCA solutions need to be validated on the
production system after a model change
• Visual tools must prominently display critical alerts to the SO
• SOs must be able to recognize when their tools are abnormal and react according to
their severity.
• Placement of status indicators, color of the text based upon the level of the alert, and
type of audible alert must be considered for ease of identification by the SO
Generator control
system
impact
Voltage
Generator
control system
impact on
on Voltage
Regulators
Regulators
• RC and TOP observed unusual generator reactive output following the switching of a shunt
reactor near the generators’ point of interconnection
• Generators at the plant were operating with their Automatic Voltage Regulators (AVR)
regulating to maintain a constant voltage schedule
• The expected generator’s change in reactive output was initially observed when the shunt
reactor was switched out of service
• Following switching the shunt reactor out of service, the generators’ reactive output
immediately reduced by approximately the output of the reactor
• The resulting transmission voltage was slightly higher than it was prior to the switching of the
reactor
 This response initially supported the assumption that the generators AVR were functioning properly
and were automatically regulating to maintain a constant voltage schedule
• However, after a few seconds the reactive output of the generators automatically slowly began
to increase.
Generator control
system
impact
Voltage
Generator
control system
impact on
on Voltage
Regulators
Regulators
Corrective Actions
• The coordinated controls review with the GOP resulted in modification of the plant DCS to
prevent this behavior
 The DCS was modified to have the ability to set the reactive objective to be the transmission system
voltage schedule that the plant was directed to control instead of a fixed MVAR output
 This control change to the DCS system resulted in the desired behavior from the plant following a
contingency or transmission element switching
• After a review of other facilities within the RC footprint, there were multiple plants found within
with the same DCS issue
 These have been corrected with the same or similar modifications in coordination with the GOP
Generator control
system
impact
Voltage
Generator
control system
impact on
on Voltage
Regulators
Regulators
Lesson Learned
• While a generator AVR may be properly set to control voltage schedule, other
plant control systems may override or counteract the appropriate AVR
response
 Periodic review of plant AVR response to system events must be conducted to determine if
this occurs
 If proper AVR response is inhibited, the RC, TOP and GOP should review the interaction of
all related plant control systems to develop a corrective action plan for coordinating the
plant control systems to ensure the AVR will have the uninhibited ability to control to the
desired voltage set point.
Link to Lessons Learned
Link to Lessons Learned
Directions to Lessons Learned:
Go to www.NERC.com > “Program Areas & Departments” tab > “Reliability Risk
Management” (left side menu) > “Event Analysis” (left side menu) > “Lessons
Learned” (left side menu)
NERC’s goal with publishing lessons learned is to provide industry with technical
and understandable information that assists them with maintaining the reliability
of the bulk power system. NERC requests that industry provide input on lessons
learned by taking the short survey. The survey link is provided on each Lesson
Learned.
Questions?