Energy Economics 32 (2010) 505–514 Contents lists available at ScienceDirect Energy Economics j o u r n a l h o m e p a g e : w w w. e l s e v i e r. c o m / l o c a t e / e n e c o When do firms generate? Evidence on in-house electricity supply in Africa☆ J. Steinbuks a,⁎, V. Foster b a b Electricity Policy Research Group, University of Cambridge, Austin Robinson Building, Sidgwick Avenue, Cambridge, CB3 9DD, UK The World Bank, 1818 H Street, Washington, D.C., 20433, USA a r t i c l e i n f o Article history: Received 17 August 2008 Received in revised form 2 September 2009 Accepted 19 October 2009 Available online 31 October 2009 JEL classification: O13 Q41 Keywords: Generators Ownership Electricity Reliability Africa a b s t r a c t This paper attempts to identify the underlying causes and costs of own generation of electric power in Africa. Rigorous empirical analysis of 8483 currently operating firms in 25 African countries shows that the prevalence of own generation would remain high (at around 20%) even if power supplies were perfectly reliable, suggesting that other factors such as firms' size, emergency back-up and export regulations play a critical role in the decision to own a generator. The costs of own-generation are about three times as high as the price of purchasing (subsidized) electricity from the public grid. However, because these generators only operate a small fraction of the time, they do not greatly affect the overall average cost of power to industry. The benefits of generator ownership are also substantial. Firms with their own generators report a value of lost load of less than US$50 per hour, compared with more than US$150 per hour for those without. Nevertheless, when costs and benefits are considered side by side, the balance is not found to be significantly positive. © 2009 Elsevier B.V. All rights reserved. 1. Introduction The performance of Africa's power supply sector on the continent is woefully unsatisfactory. Most of the continent's power companies are unreliable sources of supply, inefficient users of generating capacity, deficient in maintenance, erratic in the procurement of spare parts, and unable to staunch losses in transmission and distribution. They also have failed to provide adequate electricity services to the majority of the region's population, especially to rural communities, the urban poor, and small and medium enterprises. In response to the endemic unreliability of Africa's national electric power utilities, self-generated electricity has become an increasingly important source of power. Many end users of electricity, from households to large enterprises, now generate their own power by operating small to medium-sized plants with capacities ranging from 1 MW to about 700 MW (Karekezi and Kimani, 2002). For small-scale enterprises, protection against erratic supply from public utilities often means installing small (less than 5 MW) thermal generators. ☆ The authors would like to thank Rob Mills, Mohua Mukherjee, David Newbery, and two anonymous referees for helpful comments. They appreciate funding and other support from (in alphabetical order): the African Union, the Agence Francaise de Développement, the European Union, the New Economic Partnership for Africa's Development, the Public–Private Infrastructure Advisory Facility, the U.K. Department for International Development, and the U.K. Engineering and Physical Science Research Council (Grant Supergen Flexnet). This paper was commissioned as a part of the Africa Infrastructure Country Diagnostic project (www.infrastructureafrica.org). The views represented in this paper do not necessarily correspond to the views of the World Bank. ⁎ Corresponding author. Tel.: +44 1223 335283; fax: +44 1223 335475. E-mail address: [email protected] (J. Steinbuks). 0140-9883/$ – see front matter © 2009 Elsevier B.V. All rights reserved. doi:10.1016/j.eneco.2009.10.012 Overall, own generation by firms – which has been on the rise in recent years – accounts for about 6% of installed generation capacity in SubSaharan Africa (equivalent to at least 4000 MW of installed capacity). However, this share doubles to around 12% in the low-income countries, the post-conflict countries, and more generally on the Western side of the continent. In a handful of countries (including Democratic Republic of Congo and Nigeria) own generation represents more than 20% of capacity (Foster and Steinbuks, 2009). These adjustments are not without cost, however. Self-generated electricity is generally more expensive than electricity from the public grid, as we shall see, which limits its potential as a permanent substitute for unreliable public supply. Because it adds to the capital and operating costs of doing business, in-house generation affects the range of investment available to budding entrepreneurs, raises production costs, lowers the competitiveness of local products, and blocks the achievement of economies of scale.1 1 These limitations of own-generation do not mean that there are no gains to be had from the decentralization of power generation. But in no African country have the legal and institutional conditions for decentralized power generation yet reached the point where decentralization can provide an alternative to unreliable supply from monopolistic public providers or to the use of expensive generators at the firm level. Some 20 African countries are currently initiating some form of power sector reform. Although most are still in the initial phases of privatization and restructuring, the contemplated changes reflect a profound questioning of the principles that have governed the sector since the early 1960s. Some countries, including the Arab Republic of Egypt and South Africa, have had unbundled power sectors for a long time and are now thinking of introducing private participation. Cōte d'Ivoire and Ghana introduced reforms (privatization and restructuring) in the early and mid-1990s, respectively (Karekezi and Mutiso, 1999). 506 J. Steinbuks, V. Foster / Energy Economics 32 (2010) 505–514 This paper attempts to identify the underlying causes and costs of own generation of electric power in Africa. Our analysis is based on the World Bank's Enterprise Survey Database, which captures business perceptions of the obstacles to enterprise growth for 8483 currently operating firms in 25 African countries sampled between 2002 and 2006. Rigorous empirical analysis shows that unreliable public power supplies is far from being the only or even the largest factor driving generator ownership. Firm characteristics have a major influence, and in particular, the probability owning a generator doubles in large firms relative to small ones. Our model predicts that the prevalence of own generation would remain high (at around 20%) even if power supplies were perfectly reliable, suggesting that other factors such as emergency back-up and export regulations play a critical role in the decision to own a generator. The costs of own-generation are high, driven mainly by the variable cost of diesel fuel. They fall in the range US$0.30–0.70 per kilowatthour; about three times as high as the price of purchasing (subsidized) electricity from the public grid.2 However, since these generators only operate a small fraction of the time, they do not greatly affect the overall average cost of power to industry.3 The benefits of generator ownership are also substantial. Considering only lost sales resulting from periods of power outages, firms with their own generators report a value of lost load of less than US$50 per hour, compared with more than US$150 per hour for those without. Nevertheless, according to our conservative estimates, the balance between the costs and the benefits of own generation is not found significantly positive. This is likely because the analysis is only able to capture one dimension of the benefits of generator ownership — namely reduction in lost sales. The rest of this paper is structured as follows. The second section reviews existing literature on unreliable power supply. The third section describes the data used in the empirical analysis. The fourth section analyzes the effect of power outages and firm characteristics on the decision to generate electricity in-house. The fifth section illustrates the results of cost–benefit analysis of own generation. The final section concludes and presents policy recommendations. 2. The economic literature on unreliable power It is fairly settled in the literature that unreliable power supply results in welfare losses (see Kessides, 1993 and references therein). But the empirical research on the economic costs of power outages and own-generation in developing countries remains limited, owing to the lack of appropriate microeconomic panel data that could be used to infer firms' and households' response to poor provision of electricity supply.4 Only two studies have recently been done on this subject in Africa. Adenikinju (2005) analyzed the economic cost of power outages in Nigeria. Using the revealed preference approach on business survey data (Bental and Ravid, 1982; Caves et al., 1992; Beenstock et al., 1997), Adenikinju estimated the marginal cost of power outages to be in the range of $0.94 to $3.13 per kWh of lost electricity. Given the poor state of electricity supply in Nigeria Adenikinju (2005) concluded that power outages imposed significant costs on business. Small-scale operators were found to be most heavily affected by the infrastructure failures.5 2 The operating costs of own-generation are even higher in countries with unreliable diesel and gasoline supply. During fuel supply shortages firms are either unable to run their generators or have to run them at very high operating costs. 3 Operating costs of running a generator have a significant effect on average cost of power to the industry in a few countries (e.g. Democratic Republic of Congo and Nigeria), where outages are very frequent and sometimes of long duration. Some commercial companies in these countries (e.g. Nestle Nig. Plc. in Nigeria) run entirely on autogeneration. 4 Cross-country aggregate data analysis, widely used in the development economics literature, cannot avoid simultaneity between poor infrastructure and welfare. 5 In earlier work Lee and Anas (1992) also found that poor infrastructure had a negative effect on small enterprises in Nigeria. Reinikka and Svensson (2002) analyzed the impact of poor provision of public capital goods on firm performance in Uganda. Using a discrete choice model on business survey data, the authors predicted that unreliable power supply causes firms to substitute complementary capital (for backup generators) for deficient public services. Estimating investment equations on the same data, they found that poor complementary public capital significantly reduced private investment. Reconciling the results of the two studies is difficult. Both rely on limited datasets from business surveys done in a single country. Both use only a small number of factors among the many that firms might consider in choosing to generate their own power. Neither accounts for effects that may change the provision of power supply. And the estimated marginal costs of electricity and effects of unreliable power supply on firms' investment may be biased because of the failure to address the possible endogeneity in choice of generator, provision of electricity supply, and other observed explanatory variables, such as firms' profitability and access to finance, and the country's industrial structure. This paper combines the advantages of cross-country data analysis with microeconomic analysis of business survey data. Use of a crosscountry dataset can help to identify the effects that affect the provision of power supply, and to some extent, changes in the industrial structure. Microeconomic data can be used to infer firms' and households' response to provision of electricity supply. Because our study relies on crosssectional data, the bias in estimates cannot be fully avoided. However, cross-country comparisons will still be valid, given the one-dimensional direction of bias. 3. The data on self-generated electricity Our main data source is the World Bank's Enterprise Survey Database, which captures business perceptions of the obstacles to enterprise growth, the relative importance of various constraints to increasing employment and productivity, and the effects of a country's investment climate on the international competitiveness its firms.6 Our database comprises 8483 currently operating firms in 25 North and Sub-Saharan African countries sampled from the universe of registered businesses between 2002 and 2006. Though data on all African countries were not available at the time of research, the available data are representative of the continent. The surveys are based on a stratified random sampling methodology. Because in most countries the number of small and medium enterprises is far greater than the number of large firms, surveys generally oversample large establishments. The main advantage of the Enterprise Survey Database is that it provides both managers' opinions concerning the reliability of power supplies and the accounting data needed for structural microeconomic analysis. Table 1 (Appendix A) presents the summary statistics of the variables used in the empirical analysis. The data from the World Bank's Enterprise Survey Database are complemented by engineering data from generator manufacturers and other sector sources that help to capture the cost structure of generating power on-site. For example, the enterprise survey does not ask for information on generating capacity, which is estimated at firm level by taking the ratio of the deflated generator's acquisition cost to the average capital cost per kW of the generator's capacity (assuming thermal generation). The data for the capital cost per kW of installed capacity comes from the World Bank's Energy and Water Department (2005). The GDP deflator data comes from the World Bank's World Development Indicators database. 4. What drives firms to generate their own power? To evaluate the extent to which reliability of power supply and firm characteristics affect the decision to generate electricity in-house, 6 Detailed information on the World Bank's Enterprise Survey Database can be found at http://www.enterprisesurveys.org. J. Steinbuks, V. Foster / Energy Economics 32 (2010) 505–514 507 Table 1 Probit and Tobit regression results. Probit regression (generator ownership) Variable Days of power outages (log) Age (log) Employment (log) PKM (log) Size1 lost days (log) Size2 lost days (log) Size4 lost days (log) Size5 lost days (log) Exporter Estimated coefficient Elasticity Tobit regression (generator capacity) P-value Estimated coefficient (Elasticity) P-value 0.06⁎⁎⁎ 0.02 0.01 0.23⁎⁎ 0.05 0.06⁎⁎ 0.37⁎⁎⁎ –0.001 –0.14⁎⁎⁎ –0.04 0.001 –0.06⁎⁎ 0.29⁎⁎⁎ 0.02 0.12 0.00 –0.04 –0.01 0.00 –0.02 0.10 0.03 0.00 0.31 0.00 0.14 0.99 0.05 0.00 0.33⁎⁎ 1.74⁎⁎⁎ 0.001 0.39⁎⁎ 0.14 0.01 0.22 0.56⁎ 0.02 0.00 0.69 0.03 0.24 0.96 0.15 0.07 ⁎⁎⁎ statistically significant at 1 percent level; ⁎⁎ statistically significant at 5 percent level; ⁎ statistically significant at 10 percent level. we employed two modelling approaches. The first approach follows the binary choice model of Reinikka and Svensson (2002) is based on the following stochastic specification: ! ′ α1 xi ; α2 Zi ; PrðYi = 1Þ = Φ σ ð1Þ where Yi is the probability that firm i invests in a generator, Φ is the standard normal distribution function, xi is the frequency of power outages, Zi is a vector of controls, including country and firm characteristics, and σ is a standard deviation of normally distributed error term. The second approach employs censored regression approach: PrðYi N 0Þ = 1−Φ − ! ′ α1 xi ; α2 Zi ; σ ð2Þ where Yi is the logarithm of the capacity of firm's i generator (leftcensored at zero), and the explanatory variables are the same as in Eq. (1). Eq. (1) is estimated using the probit method. Eq. (2) is estimated using the tobit method. Selected estimated parameters are presented in Table 1, with the complete set appearing in Appendix A, Tables 2 and 3. Reliability of power supply and various firm characteristics — age, size (as measured by number of employees), and export orientation all have a significant positive impact on the estimated probability of investing in generating capacity and the size of the generator.7 The probability that a firm will own a generator can be expressed as a function of the reliability of power supply and the firm's size. The probability of finding a generator on the premises increases by nearly 50% as one moves from small firms (less than 10 employees) to very large ones (more than 500 employees) (Fig. 1). The probability of having a generator remains high (about 20%) even where power supply is completely reliable.8 For large firms the probability of having a generator in the absence of power outages is even higher (about 50%). The evidence thus suggests that both generator ownership and its capacity are greatly affected by firm characteristics, such as size, sector, corporate structure, and export orientation. Large firms that operate 24 h 7 The price-cost margin (PKM) variable was not statistically significant, possibly because of simultaneity bias between firm's profitability and decision to own a generator. 8 This finding is consistent with firms' insurance behavior. Large and risk-averse firms incurring high marginal costs from power outages will invest in back-up generator even if current power supply is completely reliable to keep the option value of insurance from future outages. Fig. 1. Probability that a firm will own a generator, by number of employees. per day are more likely than smaller firms to install backup generation capacity compared to smaller firms, which operate only during daylight hours and therefore are less affected by evening blackouts. Mining firms tend to require own power to keep elevators, air pumps, and other safety devices fully operational regardless of the power supply from public grid. Petroleum firms have very sensitive and delicate equipment that must be protected from damage stemming from power outages. Exporters may need to generate their own power to meet ISO standards (e.g., relating to cold chains). Informal firms may be unable to accumulate significant generating capacity because of security concerns, which may include police raids, unstable land or lease tenure, and other factors. The composite effect of size and reliability of power supply is generally not significant across firms, except for small firms and microenterprises (Table 1). The significant negative coefficient on the product of small firms and large power outages indicates that small firms suffer the most from unreliable power supply, because they lack the resources to invest in own-generation.9 5. The costs and benefits of own-generation 5.1. Costs We use the revealed preference approach to analyze the economic costs of own-generation.10 This approach is based on the presumption that rational, profit-maximizing firms will insure themselves against the risk of frequent power outages. Because insurance contracts for unreliable power supply are not available in developing countries, the only way to minimize losses is to acquire backup generating power. The firm's problem is to choose the optimal amount of backup power that minimizes the sunk costs incurred by acquiring generation capacity as well as the damage that unsupplied power would cause. A competitive, risk-neutral firm will maximize expected profits by equating at the margin the expected cost of generating a kWh of its own power to the expected gain due to that kWh. That gain consists of the continued production (even if partial) that the self-generated electricity makes possible, and the avoided damage to equipment that would have been caused by a power failure. Under profit-maximizing conditions, the expected marginal gain from a self-generated kWh is also the expected marginal loss from the kWh that is not supplied by the utility. Therefore the marginal cost of self-generated power may serve as an estimate for the marginal cost of an outage. 9 Further discussion of this subject becomes complicated because access to electricity and access to finance are frequently simultaneous. For example, in Nigeria small firms may lack internal funds to obtain a generator, and owning a generator may be a prerequisite to secure loan from the bank. 10 See earlier citations to the revealed preference approach in the literature review section of this paper. 508 J. Steinbuks, V. Foster / Energy Economics 32 (2010) 505–514 Table 2 The comparative costs of self generated and publicly supplied electricity, and the effect of own generation on the marginal cost of electricity, in Africa. Country Average variable cost of own electricity (A) Average capital cost of own electricity (B) Average total cost of own electricity (C = A + B) Price of kWh purchased from public grid (D) Weighted average cost of electricity (E = ∂C + (1–∂) D) Algeria Benin Burkina Fasoa Cameroona Cape Verdea Egypt, Arab Rep. Eritrea Kenya Madagascar Malawi Mali Mauritius Morocco Nigera Senegal Senegalb South Africa Tanzania Uganda Zambia 0.04 0.36 0.42 0.41 0.46 0.04 0.11 0.24 0.31 0.46 0.26 0.26 0.31 0.36 0.25 0.28 0.18 0.25 0.35 0.27 0.11 0.10 0.32 0.04 0.04 0.26 0.03 0.06 0.08 0.03 0.26 0.35 0.32 0.04 0.09 0.40 0.36 0.04 0.09 0.18 0.15 0.46 0.74 0.46 0.50 0.30 0.13 0.29 0.39 0.50 0.52 0.61 0.62 0.41 0.34 0.68 0.54 0.29 0.44 0.45 0.03c 0.12c 0.21c 0.12c 0.17c 0.04c 0.11 0.10 – 0.05c 0.17 0.14c 0.08c 0.23c 0.16 0.16 0.04 0.09 0.09 0.04 0.05 0.27 0.23 0.16 0.26 0.12 0.12 0.14 – 0.09 0.21 0.25 0.15 0.26 0.18 0.30 0.05 0.13 0.14 0.06 ∂ Share of total electricity consumption coming from own generation. – = data not available. a Tourism industry (hotels and restaurants sector) only. b Survey of informal sector. c Data not reported in the enterprise surveys (obtained from the public utilities). The cost to the firm of generating its own power consists of two elements. The first is the yearly capacity cost of the generator and other capital outlays. Following earlier literature, that cost will be denoted by b (Kg), where Kg is the generator's capacity measured in kW. The second is the variable cost per kWh-chiefly fuel cost, which is practically constant.11 If the generator is used to capacity during power cuts, the variable cost per year will then be v · H · Kg, where v is the fuel cost per kWh, and H is the expected total duration of outages, measured in hours per year. The total expected yearly cost per kW of backup generating power is then CðKgÞ = bðKgÞ + v⋅H⋅Kg: ð3Þ The expected respective marginal cost is ′ ′ C ðKgÞ = b ðKgÞ + v⋅H ð4Þ and the expected marginal cost of a kWh generated is simply given by ′ C ðKgÞkWh = ′ b ðKgÞ + v: H ð5Þ Applying Eq. (5) to the enterprise survey data allows us (using reasonable assumptions) to estimate the (marginal) cost of owngeneration from observed information about the acquisition and running costs of in-house generating capacity, and from data on the frequency of power outages.12 For these purposes, values for b′, H, and v must be obtained. The operating cost, v, is calculated as a product of the unit cost of fuel and the generator's fuel efficiency (fuel consumption per kWh). Assuming that most firms in the enterprise survey dataset rely on thermal generation, the unit cost of fuel is approximated by an average price per liter of diesel fuel.13 Fuel efficiency data was obtained from the Web sites of leading manufacturers of generators.14 The unit capital cost of self-generated electricity, b′, depends on price schedules for generators, tax and depreciation rules, and the interest rates. Original price schedules (in national currencies) and data on year of acquisition are reported in the enterprise surveys. We converted the original price schedules into current U.S. dollars. First, we deflated the price schedules, applying the corresponding value of the country's GDP deflator and then converting into dollars at the prevailing exchange rate. 15 We then obtained the capital cost per kW of installed capacity (in 2004 dollars, assuming thermal generation, no tax rules, and an internal rate of return of 10%)16 using the data from the World Bank's Energy and Water Department (2005). Our data on the duration of power outages, H, came from the enterprise surveys. Data on the average duration of power outages were generally not available. We assumed a value of 8 h per day.17 In most of the countries of Africa, the average cost of generating electricity in-house is significantly higher than the cost of electricity from the public grid (Table 2). This finding reflects the differences in efficiency between the small backup generators used by commercial firms and the large plants that produce electricity for the public grid. The major exceptions are the countries in which fuel is heavily subsidized (Algeria, Arab Republic of Egypt, and Eritrea), where the average cost of self-generated electricity is close to the cost of the electricity from the public grid. 13 The fuel prices came from GTZ International Fuel Prices 2005. These manufacturers included Wärtsilä and Cummins. 15 Nominal exchange rates were adjusted for price volatility using the World Bank Atlas method. 16 The results from the enterprise surveys show that most firms in Africa rely on internal rather than external financing. Therefore, given limited access to finance, the internal rate of return is preferred to interest rates. 17 Other assumptions about the duration of power outages were considered, including 4 and 12 h. It follows from Eq. (4) that under these assumptions the estimates of the unit capital cost of self-generated electricity will vary within the 50% confidence interval. 14 11 This measure does not account for other variable costs, such as rental costs of generator house, maintenance, wages, and salaries. Omission of these costs does not significantly bias our estimates, because they are likely to be substantial for firms with huge back-up capacity. In our dataset among 1352 firms that owned electric generators, only 2 firms had large (1 MW or larger) back-up capacity. 12 This measure of marginal cost does not account for incomplete backup that may result in additional losses such as destruction of raw materials and damage to equipment. These losses are inversely related to the percentage of backup and the reliability of the firm's backup equipment. J. Steinbuks, V. Foster / Energy Economics 32 (2010) 505–514 Table 3 Losses due to outages (“lost load”) for firms with and without their own generator. 509 Table 4 Marginal benefit of owning a generator. Country Lost load (no generator, $/h) Lost load (with generator, $/h) Reduction in lost sales Algeria Benin Burkina Fasoa Cameroona Cape Verdea Egypt, Arab Rep. Eritrea Kenya Madagascar Malawi Mali Mauritius Morocco Nigera Senegal Senegalb South Africa Tanzania Uganda Zambia 155.8 38.4 114.1 403.6 177.7 201.5 31.9 113.1 434.5 917.3 390.3 468.6 377.5 81.3 166.0 12.9 1140.1 – 27.6 286.6 52.2 23.1 13.0 12.3 36.4 30.4 10.2 37.1 153.0 401.4 9.5 13.9 22.9 22.6 19.2 1.9 66.1 444.3 191.4 39.2 Variable Estimated coefficient P-value Days of power outages (log) Generator ownership Constant F-statistic R2 N 1.94⁎⁎⁎ – 1.16⁎⁎⁎ 0.00 0.01 0.11 0.00 ⁎⁎⁎ statistically significant at 1 percent level. According to Eq. (6), the value of lost load (y) measured in dollars per hour depends on variety of parameters (X), including costs and frequency of outages, seasonal characteristics, and advance notice. Because data on seasonal characteristics and advance notice were not available, the lost load value was based on the costs and frequency of power outages. Lost load values were computed separately for firms with and without their own generators. For firms owning a generator the lost load value was calculated as – = data not available. a Survey of tourism sector. b Survey of informal sector. y = v⋅Kg The second column of Table 2 reports the first term of Eq. (5), the estimated average capital cost of self-generated electricity, adjusted by the frequency of power outages. As might be expected, the average capital cost of self-generated electricity is higher in countries with a reliable power supply (Egypt, Mali, Mauritius, Morocco, and South Africa), and in the informal sector, which uses inefficient low-capacity generators (Senegal). The third column of Table 2 shows the average total cost of selfgenerated electricity, calculated as a sum of the average capital cost and the average variable costs. Overall, the average total cost of selfgenerated electricity is about five times the price of electricity purchased from the public grid and can be as much as ten times more (in Malawi, South Africa, and Zambia). Eritrea is the only country in which the average total cost of self-generated electricity is comparable to the price of purchasing electricity from the public grid. The last column of Table 2 shows the weighted average cost of consumed energy, taking into account the share of self-generated electricity reported in the enterprise surveys.18 It can be seen that while the average total cost of own-generation is very high, its effect on the weighted average cost of power for most countries is not very large, owing to limited use of own-generation. The impact of own-generation costs is higher in countries where electricity from public utilities is subsidized (Egypt, Malawi, and Morocco), where the supply of public power is reliable (Egypt, Mauritius, and Morocco), and where the share of own-generation is large (Benin, informal sector in Senegal). 5.2. Benefits Our analysis of the economic benefits of own-generation takes two paths. The first follows the literature on the reliability of electricity supply (see, for example, Kariuki and Allan, 1995) and computes the value of lost load, defined as the value an average consumer puts on an unsupplied kWh of energy. The value of lost load is represented by the customer damage function y = f ðXÞ: –1.71 26.25⁎⁎⁎ 0.21 4254 ð6Þ where v is the generator's operational cost (in dollars per kWh), as described earlier, and Kg is generator's capacity in kW. For firms without a generator the lost load value was calculated as y= Z t ð8Þ where Z is reported sales lost from power outages and t is reported frequency of power outages, multiplied by their average duration19 The economic benefit of owning a generator is thus expressed as the reduced loss per interrupted kW. The average values of lost load for firms with and without generators are reported in Table 3. In all countries, except Uganda, the lost load is considerably higher for firms without a generator, especially in countries with infrequent (Mauritius, South Africa) or costly (Malawi) power outages. The second way to determine the benefit of own-generation is to estimate the marginal benefit of owning a generator by regressing the percentage of sales lost from power outages against the duration of power outages, generator ownership, and salient characteristics of countries and firms20 Selected estimated parameters of such a regression are reported in Table 4; the complete set of parameters appears in Appendix A, Table 3. The estimated parameters are jointly statistically significant (the p-value associated with the computed F-statistic is less than 0.01), and account for 20% of the variance in the response variable. As expected, the sign of the coefficient for duration of power outages is negative and significant, and the sign of the coefficient for generator ownership is positive and significant. The size of the estimated coefficient for generator ownership suggests that, when controlling for other factors, owning a generator decreases losses from power outages by approximately 1% of a firm's sales. 5.3. Costs vs. benefits 5.3.1. With no improvement in quality of public power supply Here we summarize the costs and benefits of own-generation by integrating them at the firm level, assuming no improvement in quality of public power supply. The costs are computed as the sum of the annualized fixed costs of acquiring a generator and the net annual 19 Power outages were assumed to last 8 h on average. An attempt to estimate the marginal benefit of owning a generator with respect to physical capital losses on a smaller sample of firms did not yield significant results. The details are available from authors upon request. 20 18 This indicator is based on the assumption that the electricity tariffs charged by the utilities are set according to marginal-cost pricing schedules. ð7Þ 510 J. Steinbuks, V. Foster / Energy Economics 32 (2010) 505–514 Table 5a Cost–benefit analysis of own-generation, by country. Percent Country Investment costs Own-generation costs Total costs Reduced sales losses Benefit–cost margin Lost sales without generator Algeria Benin Egypt Eritrea Kenya Madagascar Malawi Mali Mauritius Morocco Senegal Senegala South Africa Tanzania Uganda Zambia 3.12 0.43 2.34 1.54 0.14 0.28 0.09 0.31 0.17 0.06 0.32 0.98 0.10 0.43 0.45 3.02 – 1.62 0.86 0.41 – – 0.78 0.17 0.01 0.39 0.50 – 0.09 1.01 0.49 0.95 – 2.05 3.20 1.95 – – 0.87 0.48 0.18 0.45 0.82 – 0.19 0.94 0.94 3.96 0.61 1.79 1.33 1.28 0.49 1.03 0.23 0.51 0.84 0.08 1.23 0.41 1.19 – 1.35 0.07 – 0.99 2.25⁎⁎ 1.43 – – 0.23 0.04 1.10 0.12 0.18 – 0.90 – 0.62 –3.90⁎⁎⁎ 5.44 7.70 6.47 6.55 10.07 7.48 24.10 2.77 3.93 0.87 6.96 5.66 0.84 5.41 4.35 – = data not available. a Survey of informal sector. ⁎⁎⁎ Statistically significant at 1 percent level. ⁎⁎ Statistically significant at 5 percent level. operating costs of generation. The fixed costs of own-generation were annualized assuming linear depreciation. The net annual operating costs were calculated as the product of the firm's consumption of selfgenerated electricity and the difference between the costs per kWh of self-generated electricity and of electricity from the public grid.21 We use two approaches to calculate the benefits of own-generation. In the first, more conservative approach we assume that firms that own a generator may incur lost sales from power outages, for example, because of disruptions in generator's fuel supply. The marginal benefit of own generation is calculated as the reduced sales loss from the regression analysis in the previous section, adjusted for a corresponding fixed-effect.22 In the second approach we assume that firms that own a generator do not lose sales from power outages. The marginal benefit of own generation is computed as an opportunity cost of not having a generator, e.g. the lost sales from power outages by firms without generator.23 Both costs and benefits of owning a generator are expressed as percentages of sales. The resulting difference between the benefits from the first approach and the costs of own-generation (the benefit-cost margin) was tested for statistical significance from zero using the Student's t test.24 The results are summarized in Tables 5a–5c below. The results from the first approach indicate that in most countries, the costs of own-generation outweigh the benefits (Table 5a). However, only in Egypt and Zambia this difference is statistically significant. In four countries (Mauritius, Senegal, South Africa, and Uganda) the benefits outweigh the costs, and the difference between the benefits and the costs is not statistically significant from zero. These results imply that investment in in-house generation at least allows firms to break even. The results from the second approach indicate that benefits of own generation outweigh the costs for all 21 The exact computational procedure is outlined in a technical appendix, which is available upon request. 22 This measure represents a lower bound estimate of own-generation benefits, because firms that own generators have little lost load, and given various considerations not related to reliability of power supply as discussed earlier in this paper. 23 This measure represents an upper bound estimate of own-generation benefits given that some generator owners reported lost sales from power outages, or because firms without generator can be less productive and incur higher losses from power outages. The degree of this bias cannot be determined without proper counterfactual. 24 One cannot statistically compare the benefits from the second approach and the costs of own generation, because these estimates are based on different set of firms. countries. The results from two approaches can be reconciled under less restrictive assumptions. First, the fixed costs of own-generation can be sunk or depreciated nonlinearly. In Egypt and Zambia the negative and statistically significant difference between benefits and costs of own generation is driven by fixed costs. Second, the analysis presented above does not account for other potential gains from owngeneration, such as reductions in damaged equipment. This is especially important in Benin, where the average losses from damaged equipment account for 1.5% of sales (see Appendix A, Table 2). Third, the results of the analysis do not incorporate the option value of lost load due to future shocks to power supply (e.g. unexpected droughts or power infrastructure damages). The costs and benefits of own-generation differ according to firm size (Table 5b). The total costs of own-generation vary nonlinearly by firm size, being most efficient for medium-sized firms. For small firms own-generation imposes relatively low fixed costs but higher variable costs. Larger firms have relatively high fixed costs, and increasing variable costs. The total benefits of own-generation calculated as reduced sales losses increase non-linearly with firm size, being the highest for medium-size firms. Larger firms without generator are found to incur smaller losses from the power outages. The difference between the costs and benefits of own-generation calculated as reduced sales losses is negative across all size categories, except for the medium size. However, it is statistically significant only for large firms. The difference is insignificant or marginally significant for microenterprises, small medium, and very large firms. For all size categories the average sales losses of firms without generator are higher than total costs of own generation. The costs and benefits of own-generation vary significantly across industries (Table 5c). The costs are highest in energy-intensive industries — chemicals, nonmetal and plastic materials, and mining, and lowest in light industries, such as textiles and wood. Chemicals and construction have the highest fixed costs of own-generation, whereas nonmetal and plastic materials and mining have the highest operational costs. The highest gains from own-generation calculated as reduced sales losses are observed in mining, chemicals, and construction. In most industries, the difference between the costs and the benefits of own generation is not statistically significant. The costs of own-generation significantly outweigh the benefits in food and beverages and metals and machinery. However, these two industries, as well as nonmetallic and plastic products also have the highest average sales losses for firms without generator. Therefore, the difference between two approaches is J. Steinbuks, V. Foster / Energy Economics 32 (2010) 505–514 511 Table 5b Cost–benefit analysis of own generation, by size of firm. Percent Size Investment costs Own-generation costs Total costs Reduced sales losses Benefit-cost margin Lost sales without generator Micro Small Medium Large Very large 0.49 1.19 0.43 1.64 1.20 0.67 0.51 0.36 0.77 1.22 1.16 1.71 0.78 2.41 2.42 0.45 0.82 1.48 0.05 0.54 0.72 0.67⁎ 0.66 1.56⁎⁎ 5.97 6.09 4.93 3.80 3.27 1.97 ⁎⁎ Statistically significant at 5 percent level. ⁎ Statistically significant at 10 percent level. Table 5c Cost–benefit analysis of own-generation, by sector. World Bank, Enterprise Survey Database. Percent Industry Investment costs Own-generation costs Total costs Reduced sales losses Benefit–cost margin Lost sales without generator Textiles Food and beverages Metals and machinery Chemicals Construction Wood and furniture Nonmetallic and plastic materials Mining and quarrying 0.42 0.79 1.08 2.92 2.08 0.42 0.91 0.11 0.29 0.77 0.13 0.14 0.46 0.37 2.30 3.10 0.71 1.56 1.21 3.06 2.54 0.79 3.20 3.22 0.84 0.28 0.41 1.98 1.37 1.33 0.99 2.41 0.10 1.41⁎⁎⁎ 1.72⁎⁎ 0.44 0.22 0.53 2.21 2.40 4.81 6.12 7.00 4.84 3.57 5.30 6.79 3.28 ⁎⁎⁎ Statistically significant at 1 percent level. ⁎⁎ Statistically significant at 5 percent level. likely to be caused by industry's idiosyncratic factors (for example, sales losses because of reductions in damaged equipment are important in the food processing industry). 5.3.2. With improvements in quality of public power supply The results of the probit model discussed earlier can be used to evaluate the extent to which an improvement in the reliability of power supply will affect generator ownership. The marginal effects of the probit model (Eq. (1)) suggest that the probability of a firm's owning a generator is not very sensitive to power supply reliability. Reducing power outages by half the mean outage reduces generator ownership by less than 2% (Table 6). It appears that thoroughly reliable power would reduce generator ownership by no more than 12%. The predictions of the probit regression are extended to individual countries in Appendix A, Table 4. Raising the reliability of power supply to the level of South Africa results in a mere 3–5% reduction in generator ownership. Although the regression results suggest that improving the reliability of power supply would have a relatively small effect on generator ownership, there are several reasons to expect that the Table 6 Simulated change in generator ownership. Change in probability that firm will own a generator Variable Mean Min N Max ½ mean change ½ std change Days of power outages Age Employment Exporter 37.9 18.3 111.7 0.19 0.12 0.16 0.87 0.10 0.02 0.02 0.12 n.a. 0.03 0.02 0.16 n.a. Source: World Bank, Enterprise Survey Database. Note. Exporter is a binary variable, therefore ½ mean change and ½ std change statistics are not reported. n.a. = not applicable. effect would be greater. First, the regression analysis does not account for unobserved explanatory variables, such as firms' access to finance and productivity, which may bias the regression results downward. Second, because investment in in-house generation is irreversible, reductions in generator ownership will occur with a lag as public power supply is improved. The cross-sectional data analysis conducted in this study does not capture these dynamics. Third, the gains to be had by improving the reliability of power supply may be greater if the effects of unreliable power supply on observed industrial structure and external competitiveness are taken into account. Because energy-intensive industries require more stable power supplies, improving reliability will diversify country's production base and result in additional economic gains. 6. Conclusions and policy recommendations This paper aims to deepen our understanding of the widespread phenomenon of own generation of electric power by firms, as well as its relationship to unreliable public power supplies in the African context. It does so by analyzing the World Bank's Enterprise Survey Database, which provides a detailed set of attitudinal and behavioral information about decisions relating to own power generation at the firm level; at least for the case of larger formal sector manufacturing enterprises. The decision of a firm to maintain its own-generation capability is driven by a variety of factors. Our empirical analysis shows that unreliable public power supplies, though an important constraint to business operations, is far from being the only or the largest factor driving generator ownership. Firm characteristics such as size, age, industrial sector and export orientation all have a major influence. In particular, the probability owning a generator doubles in large firms relative to small ones. Moreover, the behavioral model predicts that the percentage of firms owning their own generators would remain high (at around 20%) even if power supplies were perfectly reliable, suggesting that other factors such as emergency driven back-up 512 J. Steinbuks, V. Foster / Energy Economics 32 (2010) 505–514 requirements or export driven quality regulations play a critical role in the decision to own a generator. The costs of own-generation are high, driven mainly by the variable cost of diesel fuel. In most cases they fall in the range US$0.30–0.70 per kilowatt-hour, which is often three times as high as the price of purchasing electricity from the public grid; although the latter is typically subsidized. Nevertheless, in most cases, this does not hugely affect the overall weighted average cost of power to firms given that own-generation is only used during a relatively small percentage of the working year. At the same time, the survey evidence shows that the benefits of generator ownership are also substantial. Considering only lost sales resulting from periods of power outages, firms with their own generators report a value of lost load of typically less than US$50 per hour, which is only a fraction of the value of lost load in excess of US$150 per hour that is reported by firms in the same country that do not have their own generators. Nevertheless, when costs and benefits are considered side by side, the balance is not found to be significantly positive; a pattern which holds across countries, industrial sectors, and business scales. This may simply be because the analysis is only able to capture one dimension of the benefits of generator ownership – namely reduction in lost sales – but fails to capture many other important aspects — such as reduced damage to equipment, higher quality of production, and meeting reliability criterion for access to export markets. Less conservative estimates using the opportunity cost as the measure of the benefit of own generation, show that the benefits of generator ownership outweigh the costs. The following policy implications emerge from our findings. Though improvements in the reliability of public power supplies would reduce generator use, many firms would still maintain their own back-up generators in order to meet international quality standards for participation in export markets. Through own generation, the majority of large formal sector enterprises are able to effectively insulate themselves from the impact of unreliable power supplies. Despite the high cost of running such generators (typically US $0.25–45 per kilowatt-hour), given that outages are only intermittent, the overall impact on the weighted average cost of power supply to these firms is relatively small. The major victims of unreliable power supply are in the informal sector, where the limited survey evidence suggests that generator ownership is an order of magnitude less prevalent than in the formal sector. The cost imposed on these firms for unreliable power is very high, and firms demonstrate high willingness to pay for reliable power through their investments in autogeneration. There is therefore a market for more expensive and higher quality power supply. It should be possible to strike a bargain between government and private sector to the effect that firms pay higher price for grid power to fund investments that will make their power supply more reliable. Many African governments are today contracting emergency generation capacity to avoid further utility outages. This power is very expensive (at least $0.25 per kWh), and thus not far short of the cost that private sector pays for own generation. By the time you add transmission and distribution costs including losses, the costs of emergency generation can easily top $0.30 per kWh. However, governments continue to sell this power to industrial users at regular grid prices. They are therefore subsidizing the public sector to the tune of easily $0.10 per kWh to receive power that they would have been willing to supply themselves at full cost had the government not leased the emergency capacity. Therefore, power from emergency capacity should be sold to the industrial sector at full cost. In countries where own-generation capacity is substantial relative to total national installed capacity, the question is whether this capacity could play a role in improving national power supplies. This would require regulation to allow large consumers to sell excess power into the grid at a price related to cost. There might be a market for such power among industrial users, although it would likely be too expensive to be of interest for the residential sector. Appendix A Table 1 Summary statistics from the enterprise survey data, by country. Country Electricity cited as business constraint (% firms) Power outages (days) Power outages (% sales) Equipment destroyed by outages (% sales) Generator owners (% firms) Power from own generator (%) Generator capacity (KW) Cost of KWH from public grid (US$) Algeria Benin Botswana Burkina Faso Burundi Cameroon Cape Verde Egypt Eritrea Ethiopia Kenya Madagascar Malawi Mali Mauritania Mauritius Morocco Namibia Niger Senegal South Africa Swaziland Tanzania Uganda Zambia 11.47 69.23 9.65 68.97 79.56 64.94 70.69 26.46 37.66 42.45 48.15 41.30 60.38 24.18 29.66 12.68 8.94 15.09 26.09 30.65 8.96 21.43 60.24 43.85 39.61 12.32 56.12 22.29 7.82 143.76 15.80 15.18 10.40 74.61 44.16 53.40 54.31 63.21 5.97 37.97 5.36 3.85 0.00 3.93 25.64 5.45 32.38 63.09 45.50 25.87 5.28 7.79 1.54 3.87 11.75 4.92 6.87 6.12 5.95 5.44 9.35 7.92 22.64 2.67 2.06 4.01 0.82 1.20 2.72 5.12 0.92 1.98 – 6.06 4.54 – 1.54 – – – – – – – – 0.34 0.91 – 1.36 – 0.42 – – – 0.62 – – 0.81 0.74 0.28 29.49 26.90 14.91 29.82 39.22 57.79 43.10 19.26 43.04 17.14 73.40 21.50 49.06 45.33 26.25 39.51 13.81 13.21 27.54 62.45 9.45 35.71 59.05 38.34 38.16 6.22 32.80 17.57 6.52 25.28 7.62 13.53 5.87 9.31 1.58 15.16 2.23 4.44 5.09 11.75 2.87 11.16 13.33 14.74 6.71 0.17 10.33 12.28 6.56 5.13 322 35 – 31 – 25 23 353 103 – 78 190 50 43 – 37 58 – 73 31 64 – 70 31 51 – – – – – – – – 0.11 0.06 0.10 – – 0.17 – – – – – 0.16 0.04 – 0.09 0.09 0.04 Source: World Bank, Enterprise Survey Database. Note: – = data not available. J. Steinbuks, V. Foster / Energy Economics 32 (2010) 505–514 Table 3 (continued) Table 2 Probit regression results (generator ownership). Variable Estimated coefficient Elasticity P-value Days of power outages (log) Age (log) Employment (log) PKM (log) Micro ⁎ Lost Days (log) Small ⁎ Lost Days (log) Large ⁎ Lost Days (log) Very large ⁎ Lost Days (log) Exporter Algeria Benin Botswana Burkina Faso Burundi Cameroon Cape Verde Egypt Eritrea Ethiopia Kenya Madagascar Malawi Mali Mauritania Mauritius Namibia Niger Senegal Swaziland Tanzania Uganda Zambia Food and beverages Metals and machinery Chemicals and pharmaceutics Construction Wood and furniture Nonmetallic and plastic materials Other manufacturing Other services Hotels and restaurants Mining and quarrying Constant Χ2 Statistic Pseudo R2 N 0.06 0.06 0.37 0.001 0.14 0.04 0.00 0.06 0.29 1.53 1.57 1.09 1.43 2.37 2.17 2.11 0.98 1.62 1.20 2.47 0.91 1.49 2.16 1.50 1.53 0.89 1.69 2.42 1.37 2.24 1.80 1.14 0.80 0.32 0.65 0.68 0.19 0.61 0.52 0.18 1.11 0.53 4.00 1360.04 0.26 4246 0.02 0.02 0.12 0.0002 0.04 0.01 0.00 0.02 0.10 0.55 0.57 0.41 0.53 0.71 0.69 0.68 0.35 0.58 0.45 0.73 0.34 0.54 0.69 0.55 0.56 0.34 0.60 0.73 0.51 0.70 0.63 0.43 0.28 0.11 0.24 0.25 0.06 0.22 0.19 0.06 0.42 0.19 0.00 0.00 0.01 0.03 0.00 0.31 0.00 0.14 0.99 0.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.03 0.00 0.00 0.65 0.00 0.11 Note: Base country: South Africa; base industry: textiles; base size category: medium size (50–100 employees), Source: World Bank, Enterprise Survey Database. Table 3 Tobit regression results (generator capacity). Variable Days of power outages (log) Age (log) Employment (log) PKM (log) Micro ⁎ Lost Days (log) Small ⁎ Lost Days (log) Large ⁎ Lost Days (log) Very large ⁎ Lost Days (log) Exporter Algeria Benin Burkina Faso Cameroon Cape Verde Egypt Estimated coefficient/Elasticity 0.23 0.33 1.74 0.001 0.39 0.14 0.01 0.22 0.56 7.74 7.82 2.09 1.87 0.44 5.43 513 P-value 0.05 0.02 0.00 0.69 0.03 0.24 0.96 0.15 0.07 0.00 0.00 0.49 0.46 0.87 0.00 (continued on next page) Variable Estimated coefficient/Elasticity P-value Eritrea Kenya Madagascar Malawi Mali Mauritius Niger Senegal Tanzania Uganda Zambia Food and beverages Metals and machinery Chemicals and pharmaceutics Construction Wood and furniture Nonmetallic and plastic materials Other manufacturing Other services Hotels and restaurants Mining and quarrying Constant χ2-Statistic Pseudo R2 N 7.94 10.86 4.15 6.06 9.75 7.35 2.24 10.31 10.47 8.06 3.94 3.01 1.18 2.46 1.91 0.21 2.11 2.73 1.05 14.02 0.42 18.61 1269.15 0.17 3756 0.00 0.00 0.00 0.00 0.00 0.00 0.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.64 0.00 0.00 0.56 0.00 0.83 0.00 0.00 Note: Base country: South Africa; base industry: textiles; base size category: medium size (50–100 employees), Source: World Bank, Enterprise Survey Database. Table 4 Marginal benefit of generator ownership (lost sales). Variable Days of power outages (log) Generator ownership Algeria Benin Botswana Burkina Faso Burundi Cameroon Cape Verde Egypt Eritrea Ethiopia Kenya Kenya (informal) Madagascar Malawi Mali Mauritania Mauritius Morocco Namibia Niger Senegal Senegal (informal) South Africa Swaziland Uganda Uganda (informal) Agroindustry Metals and machinery Chemicals and pharmaceutics Construction Wood and furniture Non-metallic and plastic materials Other manufacturing Other services Hotels and restaurants Mining and quarrying Micro Small Estimated Coeff. 1.94 1.16 2.20 0.74 3.31 0.56 3.24 1.21 1.85 2.12 1.21 0.70 3.62 28.68 1.70 15.76 0.60 3.39 1.78 0.95 3.24 0.64 0.84 3.75 1.25 3.01 0.54 10.63 0.84 2.20 0.18 0.08 0.04 1.02 0.06 1.80 1.69 0.77 1.40 0.85 P-value 0.00 0.01 0.04 0.56 0.09 0.79 0.03 0.39 0.36 0.03 0.45 0.52 0.00 0.00 0.14 0.00 0.68 0.03 0.19 0.41 0.18 0.75 0.48 0.01 0.25 0.09 0.63 0.00 0.13 0.00 0.81 0.94 0.94 0.15 0.95 0.34 0.39 0.79 0.05 0.12 (continued on next page) 514 J. Steinbuks, V. Foster / Energy Economics 32 (2010) 505–514 Table 4 (continued) Variable Estimated Coeff. P-value Large Very Large Constant F-Statistics R2 N 0.96 0.16 1.71 26.25 0.21 4254 0.17 0.82 0.11 0.00 Source: World Bank, Enterprise Survey Database. Note: Base country: Zambia; base industry: textiles; base size category: medium size (50–100 employees). Table 5 Simulated change in generator ownership from improved reliability of power supply. Country Power outages Predicted generator ownership Simulated generator ownership (no power outages) Simulated generator ownership (outages at South African average) Algeria Benin Botswana Burkina Faso Burundi Cameroon Cape Verde Egypt Eritrea Ethiopia Kenya Madagascar Malawi Mali Mauritania Mauritius Namibia Niger Senegal South Africa Swaziland Tanzania Uganda Zambia 13.96 74.73 24.86 20.42 130.09 30.36 27.30 17.23 110.15 60.63 82.03 74.15 76.88 14.28 65.65 7.49 15.00 38.35 29.15 5.95 34.87 70.15 61.38 36.34 0.28 0.20 0.19 0.26 0.44 0.59 0.46 0.18 0.46 0.19 0.69 0.19 0.46 0.47 0.27 0.41 0.20 0.41 0.61 0.09 0.38 0.57 0.34 0.38 0.21 0.11 0.11 0.17 0.32 0.55 0.39 0.12 0.35 0.07 0.65 0.11 0.36 0.42 0.16 0.37 0.11 0.34 0.56 0.05 0.27 0.49 0.24 0.30 0.25 0.14 0.13 0.20 0.36 0.59 0.43 0.14 0.39 0.09 0.69 0.13 0.40 0.47 0.19 0.41 0.14 0.38 0.60 0.09 0.30 0.53 0.27 0.33 References Adenikinju, A, 2005. Analysis of the cost of infrastructure failures in a developing economy: the case of the electricity sector in Nigeria. AERC Research Paper 148, African Economic Research Consortium, Nairobi. February. Beenstock, M., Goldin, E., Haitovsky, Y., 1997. The cost of power outages in the business and public sectors in Israel: revealed preference vs. subjective valuations. The Energy Journal 18 (2), 39–61. Bental, B., Ravid, S., 1982. A simple method for evaluating the marginal cost of unsupplied electricity. Bell Journal of Economics 13, 249–253. Caves, D.W., Herriges, J.A., Windle, R.J., 1992. The cost of electric power interruptions in the industrial sector: estimates derived from interruptible service programs. Land Economics 68 (1), 49–61. Foster, V., Steinbuks, J., 2009. Paying the price for unreliable power Supplies: In-House generation of electricity by firms in Africa. World Bank Policy Research Paper 4913. April. Karekezi, S., Kimani, J., 2002. Status of power sector reform in Africa: impact on the poor. Energy Policy 30, 923–945. Karekezi, S., Mutiso, D., 1999. Information and Statistics on the Power Sector and the Reform Process in Sub-Saharan Africa. In: Bhagavan, M. (Ed.), Reforming the Power Sector in Africa. Zed Books Ltd., in association with African Energy Policy Research Network, London, pp. 331–352. Kariuki, K.K., Allan, R.N., 1995. Reliability Worth in Distribution Plant Replacement Programmes. Proceedings of the Second International Conference on the Reliability of Transmission and Distribution Equipment, Coventry, U.K, pp. 29–31. March. Kessides, C., 1993. The Contributions of Infrastructure to Economic Development: A Review of Experience and Policy Implications. World Bank Discussion Paper 213. Washington, DC. Lee, K.S., Anas, A., 1992. Impacts of Infrastructure Deficiencies on Nigerian Manufacturing: Private Alternatives and Policy Options. Infrastructure and Urban Development Department Report 98. World Bank, Washington, DC. Reinikka, R., Svensson, J., 2002. Coping with poor public capital. Journal of Development Economics 69, 51–69. World Bank. Technical and Economic Assessment: Off Grid, Mini-Grid, and Grid Electrification Technologies. Discussion paper, Energy and Water Department, World Bank, Washington, DC; November, 2005.
© Copyright 2025 Paperzz