GAUTENG DEPARTMENT OF INFRASTRUCTURE DEVELOPMENT EXPANDED PUBLIC WORKS PROGRAMME STATUS OF EPWP PERFORMANCE & CREATING 300 000 JOBS BY 2019 1 BACKGROUND The Expanded Public Works Programme (EPWP) is now in Phase 3 (2014 to 2019) The target set by our President is 6million work opportunities This was disaggregated by the programme coordinators , the National Department of Public Works (NDPW) by Sphere (National, Provincial, Municipal and Non-state) Sector (Infrastructure, Environment & Culture, Social, Non-state) Targets where set for Gauteng ALL Public Bodies were mandated to: Create jobs through various projects being implemented using ALL funding available to each public body Report on the jobs created on a database administered by the NDPW 2 CREATING JOBS ALL Public bodies are required to use all available funding (equitable share, Municipal Infrastructure Grant, Integrated Grant etc) to create jobs through their projects by: Ensuring job creation potential is considered at project selection. Optimising job creation in projects through the replacement of machines with people wherever practically and economically possible. Ensuring that designers/specifiers produce procurement documentation which compels implementers (contractors) to utilise people instead of machines Ensure that adequate supervision and transfer of skills is undertaken through projects in order to: Upskill participants Ensure quality output 3 REPORTING OF JOBS ALL Public bodies are required to report jobs created on a nationally administered database. Historically, this was done on a system which required certain basic information including the names, ID numbers and days worked by the participants. This raised several Auditor General findings in that: Some participants were deceased Fraud was prevalent as there was not validation of people working on the programme There was not proof that participants were paid Duplication was prevalent 4 REPORTING OF JOBS As are result of this, the NDPW, introduced a new reporting system with several validation requirements in order reduce the potential for fraud. As part of the system, evidence needed to be captured onto the system including: Certified copies of all IDs of participants Contracts with all participants Proof of payment to participants Proof of UIF Proof COIDA Whilst the legislation requires IDS to be copied for all projects, the requirements for certified IDS has presented an administrative challenge which was not catered for in tender documents previously. 5 Gauteng EPWP Targets for Depts and Municipalities 2014 to 2019 Table 1 : Gauteng Provincial departments Targets 2014 - 2019 Gauteng Targets Provincial Sphere Financial Year 2014/15 2015/16 2016/17 2017/18 2018/19 Totals Infrastructure WO FTE 18 758 6 117 19 970 6 512 20 522 6 692 21 250 6 929 21 910 7 145 102 410 33 395 Environmental WO FTE 460 161 423 157 400 157 380 157 361 157 2 025 790 Social WO 26 886 27 198 26 591 26 853 26 997 134 525 Total FTE 17 056 17 268 16 865 17 029 17 138 85 356 WO 46 104 47 591 47 514 48 483 49 268 238 960 FTE 23 334 23 937 23 714 24 115 24 440 119 540 Table 2 : Gauteng Municipal departments Targets 2014 - 2019 Gauteng Targets Municipal Sphere Financial Year 2014/15 2015/16 2016/17 2017/18 2018/19 Totals Infrastructure WO FTE 49 524 16 149 53 742 17 524 58 737 19 153 64 324 20 975 70 791 23 084 297 117 96 886 Environmental WO FTE 10 304 4 864 9 869 4 749 9 620 4 752 9 393 4 753 9 191 4 755 48 378 23 873 Social WO 1 361 1 685 2 320 3 003 3 749 12 120 Total FTE 474 586 807 1 045 1 304 4 215 WO 61 190 65 296 70 677 76 721 83 731 357 615 FTE 21 487 22 860 24 712 26 773 29 143 124 975 6 OVERVIEW OF THE PROGRESS The province exceeded it’s target in 2014/15. Whilst this suggests that the work has been created on the ground, the figure does not take into account data which was invalid. The province has underperformed in the 2015/16 & 2016/17 (current year). This may be attributed to: Under-reporting due to the administrative requirement for data capture Employment of foreign nationals who cannot currently be captured on the system Poor project selection (projects not conducive to Labour) Conventional construction without deliberate labour based activities written into contracts. Lack of ownership of the requirement to create and report on job creation. As a result of this, the Province has underperformed by 382455 work opportunities. The premier has targeted 300’000 Work Opportunities over the next 2 year. 7 OVERVIEW OF PROGRESS (CONTINUED) This presentation aims to: Provide the rationale for a disaggregation of targets Recommend a disaggregation process Provide recommendations on key interventions that need to be implemented to achieve the targets 8 Cumulative Performance against NDPW Phase 3 Targets 700000 Deficit 382455 623761 600000 484833 500000 400000 353887 300000 230165 241306 185644 200000 142950 112080 100000 0 2014/15 2015/16 2016/17 Total WO WO Target 0 0 2017/18 2018/19 9 NDPW Phase 3 Target Splits by Sphere • • • The nature of work undertaken by provincial departments is not the same as that of the municipalities. This has been recognised by NDPW who had split the Gauteng target taking cognisance of the difference. The initial province: municipality split appears to be 40:60 Work Opportunities Provincial Department Work Opportunities % of total Municipal Work Opportunities % of total Total 2014/15 2015/16 2016/17 2017/18 2018/19 Totals 46 104 47 591 47 514 48 483 49 268 238 960 43% 42% 40% 39% 37% 40% 61 190 65 296 70 677 76 721 83 731 357 615 57% 58% 60% 61% 63% 60% 107 294 112 887 118 191 125 203 132 999 596 574 10 SPLITTING THE TARGET BY SPHERE • Whilst this was theoretically undertaken, review of the reported jobs on the reporting system shows that – – 241 306 Work Opportunities (WO) were created (39% of the 5 year total & 60% of where we should be at this time) A province: municipality split appears to be 40:60 400000 350000 300000 250000 200000 150000 100000 50000 0 2014/15 Provincial Department Target 2015/16 2016/17 Provincial Department Progress 2017/18 Municipal Target 2018/19 Totals Municipal Progress 11 DISAGGREGATION BY SPHERE It is therefore same to assume that the targeted 300’000 work opportunities could be split by sphere 60:40. Disaggregated targets Provincial Department , 120000, 40% Municipality , 180000, 60% Municipality Provincial Department 12 DISAGGEGATION BY YEAR It is appreciate that all Public Bodies are not performing optimally but are expected to improve on their job creation and reporting , year on year. The NDWP estimated the increase year on year to be 3% for Provincial departments 7% for Municipalities This disaggregation was adopted for this purpose. Municipal 2018-19 31% Provincial 2017-18 20% Provincial 2018-19 20% Municipal 2017-18 29% 13 COST PER JOB/SECTOR The cost of a project comprises several components including Labour Plant Equipment The proportions of budget allocated for each of these elements varies from project to project depending on the nature of the project. Based on the historical data from the reporting system, the cost per job may be estimated. 2016/2017 Allocated Budget Gross No. of WO Rands/job E&C R 27 097 611.00 669.00 R 40 504.65 Social Sector R 437 799 993.00 12540.00 R 34 912.28 The Infrastructure Sector estimated a cost per job of R40 000/job for the 5 year targets. This was adopted for this exercise. 14 ADJUSTMENT Using the budgets allocated to all public bodies, a theoretical job creation target was calculated. The target was adjusted in consideration of: Projects not conducive to labour (plant intensive) Projects not promoting labour generation Challenges with data collection Challenges with data capturing onto the system Validation failures (fraudulent IDs) 15 300 000 TARGET SUMMARY: Provincial Departments PROVINCIAL DEPARTMENTS 2017-18 2018-19 Total Total Total Total 308 538 846 8516 4851 13367 825 429 1254 11 0 11 9444 13761 23205 8 8 16 505 397 902 496 100 596 30029 33902 63932 GP - ROADS AND TRANSPORT 8971 6901 15872 TOTAL 59113 60887 120000 DEPARTMENT GP - DEPT. OF AGRICULTURE AND RURAL DEVELOPMENT GP - DEPT. OF HEALTH GP - DEPT. OF SPORT, ARTS, CULTURE AND RECREATION GP - DEPT. OF COOPERATIVE GOVERNANCE AND TRADITIONAL AFFAIRS GP - DEPARTMENT OF EDUCATION GP - DEPT. OF COMMUNITY SAFETY GP - DEPT. OF INFRASTRUCTURE DEVELOPMENT GP - DEPARTMENT OF SOCIAL DEVELOPMENT GP - DEPARTMENT OF HOUSING AND LOCAL GOVERNMENT/HUMAN SETTLEMENT 16 300 000 TARGET SUMMARY: Municipalities Municipalities 2017-18 2018-19 Total Total Total Total EKURHULENI 25112 26870 51982 CITY OF JOHANNESBURG 28097 30064 58160 CITY OF TSHWANE 21950 23486 45436 EMFULENI 4886 5228 10113 MIDVAAL 1045 1118 2162 LESEDI 412 441 854 SEDIBENG DISTRICT MUNICIPALITY 22 23 45 MOGALE CITY 2961 3168 6129 MERAFONG CITY 875 936 1811 RAND WEST CITY 1475 1578 3053 WEST RAND DISTRICT MUNICIPALITY 123 131 254 TOTAL 86957 93043 180000 MUNICIPALITY 17 300 000 TARGET SUMMARY: Provincial Departments PROVINCIAL DEPARTMENTS – Infrastructure Only 2017-18 2018-19 Total Total Total Total 83 176 259 GP - DEPT. OF HEALTH 8516 4851 13367 GP - DEPT. OF SPORT, ARTS, CULTURE AND RECREATION 825 429 1254 GP - DEPT. OF COOPERATIVE GOVERNANCE AND TRADITIONAL AFFAIRS 11 0 11 GP - DEPARTMENT OF EDUCATION 9281 13469 22750 GP - DEPT. OF COMMUNITY SAFETY 8 8 16 GP - DEPT. OF INFRASTRUCTURE DEVELOPMENT 505 397 902 GP - DEPARTMENT OF SOCIAL DEVELOPMENT 435 34 469 29581 33182 62763 GP - ROADS AND TRANSPORT 8971 6901 15872 TOTAL 58216 59447 117663 DEPARTMENT GP - DEPT. OF AGRICULTURE AND RURAL DEVELOPMENT GP - DEPARTMENT OF HOUSING AND LOCAL GOVERNMENT/HUMAN SETTLEMENT 18 300 000 TARGET SUMMARY: Municipalities Municipalities – Infrastructure Only 2017-18 2018-19 Total Total Total Total EKURHULENI 24518 26234 50753 CITY OF JOHANNESBURG 27625 29559 57184 CITY OF TSHWANE 21630 23145 44775 EMFULENI 4332 4636 8968 MIDVAAL 1045 1118 2162 LESEDI 412 441 854 SEDIBENG DISTRICT MUNICIPALITY 22 23 45 MOGALE CITY 2514 2690 5204 MERAFONG CITY 875 936 1811 RAND WEST CITY 1475 1578 3053 WEST RAND DISTRICT MUNICIPALITY 23 24 47 TOTAL 84472 90385 174856 MUNICIPALITY 19 Total TARGET SUMMARY: Provincial Departments (300 000 & Phase 3) PROVINCIAL DEPARTMENTS DEPARTMENT GP - DEPT. OF AGRICULTURE AND RURAL DEVELOPMENT GP - DEPT. OF HEALTH GP - DEPT. OF SPORT, ARTS, CULTURE AND RECREATION GP - DEPT. OF COOPERATIVE GOVERNANCE AND TRADITIONAL AFFAIRS GP - DEPARTMENT OF EDUCATION GP - DEPT. OF COMMUNITY SAFETY GP - DEPT. OF INFRASTRUCTURE DEVELOPMENT GP - DEPARTMENT OF SOCIAL DEVELOPMENT GP - DEPARTMENT OF HOUSING AND LOCAL GOVERNMENT/HUMAN SETTLEMENT GP - ROADS AND TRANSPORT TOTAL 2017-18 2018-19 Total Total Total Total 515 748 1263 18137 14632 32769 2465 2097 4562 11 0 11 9492 13810 23302 8 8 16 11150 11220 22371 862 471 1333 54600 58884 113484 9977 7923 17899 107216 109794 217010 20 Total TARGET SUMMARY: Municipalities (300 000 & Phase 3) Municipalities 2017-18 2018-19 Total Total Total Total EKURHULENI 47362 51455 98817 CITY OF JOHANNESBURG 52905 56966 109870 CITY OF TSHWANE 44440 47894 92334 EMFULENI 7513 8060 15572 MIDVAAL 1545 1654 3198 LESEDI 763 823 1587 SEDIBENG DISTRICT MUNICIPALITY 257 316 573 MOGALE CITY 4327 4658 8985 MERAFONG CITY 1560 1691 3251 RAND WEST CITY 2599 2798 5397 WEST RAND DISTRICT MUNICIPALITY 407 460 867 TOTAL 163677 176775 340452 MUNICIPALITY 21 Total TARGET SUMMARY: Provincial Departments (300 000 & Phase 3) PROVINCIAL DEPARTMENTS – Infrastructure Only 2017-18 2018-19 Total Total Total Total 175 270 445 GP - DEPT. OF HEALTH 12766 9233 21999 GP - DEPT. OF SPORT, ARTS, CULTURE AND RECREATION 1549 1177 2726 11 0 11 GP - DEPARTMENT OF EDUCATION 9303 13491 22793 GP - DEPT. OF COMMUNITY SAFETY 8 8 16 GP - DEPT. OF INFRASTRUCTURE DEVELOPMENT 5208 5246 10454 GP - DEPARTMENT OF SOCIAL DEVELOPMENT 597 201 797 40435 44374 84809 GP - ROADS AND TRANSPORT 9415 7358 16774 TOTAL 79466 81357 160823 DEPARTMENT GP - DEPT. OF AGRICULTURE AND RURAL DEVELOPMENT GP - DEPT. OF COOPERATIVE GOVERNANCE AND TRADITIONAL AFFAIRS GP - DEPARTMENT OF HOUSING AND LOCAL GOVERNMENT/HUMAN SETTLEMENT 22 Total TARGET SUMMARY: Municipalities (300 000 & Phase 3) Municipalities – Infrastructure Only 2017-18 2018-19 Total Total Total Total EKURHULENI 45916 49771 95688 CITY OF JOHANNESBURG 47726 51670 99396 CITY OF TSHWANE 39054 42312 81366 EMFULENI 6260 6769 13029 MIDVAAL 1408 1519 2926 LESEDI 713 775 1489 SEDIBENG DISTRICT MUNICIPALITY 22 23 45 MOGALE CITY 3683 3983 7666 MERAFONG CITY 1536 1668 3204 RAND WEST CITY 2454 2661 5115 WEST RAND DISTRICT MUNICIPALITY 23 24 47 TOTAL 148796 161176 309971 MUNICIPALITY 23 Proposed Disaggregated Targets by Spheres (300 000) 2017/18 2018/19 Total Provincial 59 113 60 887 120 000 Municipal 86 957 93 043 180 000 Total 146 070 153930 300 000 24 Proposed Disaggregated Targets by Spheres (300 000 & Phase 3) 2017/18 2018/19 Total Provincial 107 216 109 794 217 010 Municipal 163 677 176 775 340 452 Total 270 893 286 569 557 462 25 KEY INTERVENTIONS Item Action Deliverable By Whom Accountability All political and operation principles are take responsibility for their targets KPIs to include job delivery Premier MECs Mayors HoD MMs EPWP added to the agenda of all key forums Progress to be reported at all forums All Public Bodies to commit to EPWP targets through signing of Protocol Agreements Revised signed Protocol Agreements Premier MEC HODs and Mayors Develop a project selection criteria Selection criteria includes job creation Technical Managers Perform Labour intensive construction workshops for all PMs LI Workshops GDID Align all tender documents to EPWP requirements EPWP aligned pro forma tender documents Public Bodies Increase job creation 26 KEY INTERVENTIONS Item Action Deliverable By Whom Reporting Ensure that all contracts include EPWP requirements for reporting Aligned procurement documents Technical Managers Develop capacity to collect data Collected data All Public Bodies Establish clear data flow processes Data Flow Process All Public Bodies Establish Data Capturing capacity Data Capture Centre All Public Bodies Enhance data management capability to reduce inefficiency Data Managers All Public Bodies 27 KEY INTERVENTIONS Item Action Deliverable By Whom Foreign Nationals Reduce the number of illegal immigrants working on EPWP Increased jobs reported All Public Bodies Liaise with NDPW to allow capturing of legal foreign nationals Increased jobs reported GDID Metros Mayors to be engaged to improve reporting on all projects in all Sectors Increased jobs reported Premier MEC GDID Human Settlements MEC to be engaged to improve job creation and reporting Increased jobs reported Premier MEC GDID Social Sector Ensure that all Programmes are reported for all Municipalities Increased jobs reported MEC GDID Sector Manager 28 Conclusion The 300,000 work opportunities have been disaggregated across public bodies in the province This is achievable by all public bodies, provided that the identified interventions are in place Interventions are required at various levels to achieve these targets Each public body must look at the targets, consider their budgets and programme and develop a detailed estimate of output for the next 2 years It is recommended that a detailed action plan be created for the numerous interventions which must take place in order to achieve the target Monthly monitoring of the action plan and the progress must take place and must be reported at all key meetings 29 THANK YOU 30
© Copyright 2026 Paperzz