Gas Transmission Investment Programme, Status and Development July 2013 Date issued: XX July 2013 Submissions close: XX August 2013 186104.1 31 July 2017 About Gas Industry Co. Gas Industry Co is the gas industry body and co-regulator under the Gas Act. Its role is to: develop arrangements, including regulations where appropriate, which improve: ○ the operation of gas markets; ○ access to infrastructure; and ○ consumer outcomes; develop these arrangements with the principal objective to ensure that gas is delivered to existing and new customers in a safe, efficient, reliable, fair and environmentally sustainable manner; and oversee compliance with, and review such arrangements. Gas Industry Co is required to have regard to the Government’s policy objectives for the gas sector, and to report on the achievement of those objectives and on the state of the New Zealand gas industry. Gas Industry Co’s corporate strategy is to ‘optimise the contribution of gas to New Zealand’. Submissions close: Submit to: Enquiries: 186104.1 31 July 2017 XX August 2013 www.gasindustry.co.nz Ian Wilson 04 472 1800 Steve Bielby’s introduction 31 July 2017 Executive summary [To be completed] GIC is satisfied with the outcomes of the completed projects a. Supply and Demand outlook: GIC engaged Concept Consulting to produce a document, with an associated model, called Gas Supply and Demand Scenarios 2012-2027. Industry submissions were considered and the report was finalised in December 2012. b. Backstop information gathering and analysis: GIC consulted on a Statement of Proposal in late 2011 which set out options for improving processes for GIC to gather information required to assist in its policy development process. Following consultation, GIC’s preferred option was to develop a formalised and transparent protocol for requesting information from industry participants. The protocol is now in place and has been used successfully. GIC is satisfied with the progress of the projects still in train c. Vector capacity determination: Vector is undertaking consultation with industry participants to determine available pipeline capacity. In order to do this, Vector is following a detailed project plan which it intends to complete by December 2013. d. Transmission Access and Pricing project: industry feedback on the PEA’s ‘further advice’ paper will determine its future path. However, GIC believes that the PEA has completed its substantive work on the project. Depending on the future path of the project, it may be useful to refer occasional matters to the PEA for further advice (assuming the PEA are willing to be ‘on hold’) e. Transmission market disclosures: This project has largely been subsumed by other projects. Many of the information gaps originally identified have been addressed: Vector has disclosed its capacity queues and consulting on its security of supply standard, the requirements for pipeline companies to disclose information under Part 4 regulation has been decided by the Commerce Commission. However, GIC is still engaged with Vector on a number of transparency matters, and we consider that it is wise to review what information is available once the other projects are complete. GIC acknowledges that some work remains to be done f. Gas trading arrangements: This was identified as a possible project in the event that a ‘market carriage’ arrangement were identified as a preferred option under the Transmission Pricing and Access project. GIC does not consider that further work on this option is justified at present. g. Testing investment options: The original intention was for GIC to work with the Commerce Commission and Government to help clarify the regulatory arrangements and to ensure that an effective pathway for efficient gas transmission investment is in place. The project will describe the regulatory framework in place and any barriers to investment. GIC 186104.1 31 July 2017 considered that substantial progress on Vector’s capacity review work and the CC’s Part 4 controls should be achieved before beginning this work. A start for the project is scheduled for August 2013. 31 July 2017 Contents Steve Bielby’s introduction 4 Executive summary 5 1 Introduction 1 1.1 Purpose 1 1.2 How to make a submission 1 1.3 Next steps 1 2 Gas Transmission Investment Programme 2 3 GTIP report card 4 3.1 Bridge commitments 4 3.2 Information projects 5 3.3 Market projects 8 3.4 Regulatory projects 9 3.5 Overall assessment 9 4 Panel of Expert Advisers deliberation on transmission access 11 Description of the Transmission Access and Capacity project 11 4.2 PEA’s preliminary advice 12 4.3 Issues considered since preliminary report 13 4.4 April 2013 Workshop 15 5 Description of reasonably practicable options 16 4.1 186104.1 31 July 2017 5.1 Capacity follows end-user 16 5.2 Capacity auctioning 17 5.3 Convergence 18 5.4 Integration 19 6 Proposed evaluative framework 20 7 Way forward for the GTIP 22 Glossary 31 July 2017 23 1 1.1 Introduction Purpose The purpose of this document is to provide a progress report on Gas Industry Co’s GTIP project. This document is being released concurrently with the Panel of Expert Advisers’ (PEA) second piece of advice on the optimal arrangements for gas transmission arrangements and capacity pricing. The present document also serves the purpose of providing additional context to the PEA’s advice and will particularly benefit new readers of this workstream. We also provide our own description of some options, which the PEA may not address in its advice, which are targeted at the problem identified for this workstream. We welcome submitters’ views on these options and any other issues discussed in this paper. 1.2 How to make a submission Submissions are invited from stakeholders on this paper. Submissions should be provided no later than 5pm on XX MONTH 2013. Please note that submissions received after this date are unlikely to be considered. Submissions can be made by logging-on to the Gas Industry Co website (www.gasindustry.co.nz). All submissions will be published on the website after the closing date. The recommended format for submissions is attached as Appendix A and may be downloaded in MS Word format from the website. Because submissions will automatically be made public on Gas Industry Co’s website following the closing date, submitters should discuss any intended provision of confidential information with Gas Industry Co prior to uploading their submissions. 1.3 Next steps The next steps for this workstream are discussed in section 7 of this paper. In short, the next steps depend on the analyses of submissions carried out on this paper and the PEA’s advice. 1 186104.1 31 July 2017 2 Gas Transmission Investment Programme The Gas Transmission Investment Programme (GTIP) was Gas Industry Co’s response to industry concerns over the long-term outlook for gas transmission capacity availability in the Auckland region. This work had its origins in 2009 when Vector announced to the industry that it would no longer be able to sell new capacity on its North Pipeline as that pipeline had reached the limits of its capacity. Large end users on the North Pipeline subsequently experienced a reduction in the number of credible bids they received when seeking a new gas supplier. Gas Industry Co’s investigation of the situation prompted key industry members to put in place (in August 2011) a set of commitments to improve market performance. These are known as the Bridge Commitments; the intention of the Bridge Commitments was to improve current market conditions while providing a bridge to longer term solutions. Gas Industry Co is monitoring the effectiveness of the Bridge Commitments. The wider objectives of the GTIP are to: ensure that existing and future gas transmission assets are used efficiently; establish the need for gas transmission investment; and develop an effective pathway for efficient gas transmission investment to take place. Within these overarching objectives, the GTIP was divided into three separate workstreams: (a) information projects; (b) market projects; and (c) regulatory projects. Each of these projects was divided into sub-projects, as shown in the following table. Table X. Gas Transmission Investment Programme Project area Purpose Component projects Why Information Projects To minimise information Vector’s Capacity Determination For Vector to transparently review the North Pipeline capacity 2 186104.1 31 July 2017 Project area Market Projects Regulatory Projects Purpose Component projects Why asymmetries Supply and Demand Outlook To improve the quality of information so people make better decisions about transmission investment and alternatives Transmission Market Disclosures To ensure that information necessary for efficient operation of the market is available. (Note that the information that would be disclosed is non-financial and sits alongside the work of the Commerce Commission) Backstop Information Gathering and Analysis To ensure access to data for analysis to underpin any conclusions and recommendations in relation to all areas of GIC’s work To provide efficient transport arrangements Transmission Access and Pricing To ensure efficient arrangements for optimal allocation, utilisation, and pricing of capacity Gas Trading Arrangements To ensure efficient arrangements for the gas market To define appropriate regulatory arrangements Testing regulatory options To identify whether there are appropriate incentives in place for investment In order to develop these projects with regular industry input, Gas Industry Co established two advisory panels, one called the Panel of Expert Advisers (PEA) and another called the Panel of Strategic Advisers (PSA). The PEA is comprised of industry experts and it provides advice on a range of market design issues. The PSA is comprised of senior executives and it provides programme oversight. For a thorough background on the GTIP project, please refer to the GTIP website and the various papers contained there: http://gasindustry.co.nz/work-programme/gas-transmission-investment-programme. The next section of this paper provides a report card on how the various component projects of the GTIP have fared to date. 3 186104.1 31 July 2017 3 3.1 GTIP report card Bridge commitments The Bridge Commitments are a set of commitments made by Shippers and Vector Transmission that each signatory will: 1. as a Shipper supplying a large end user (end user) who obtains gas from the Northern Pipeline, where the end user tenders for future supply to: (a) ensure that transmission capacity (capacity) is available to the preferred retailer of the end user of gas, at a price that reasonably reflects the value of that existing capacity to the Shipper, and at a quantity that will reflect the end user’s demand, to the extent practicable; (b) provide that capacity price and quantity information, at the end user’s or another Shipper’s request, within five business days, to allow competing bidders to incorporate it into their supply proposals; and (c) provide the information in 1(b) to Gas Industry Co, together with the name of the end user , relevant ICP number and any other material terms of the capacity transfer offer at the time they are made to assist Gas Industry Co in assessing the efficacy of the arrangement set out in this paragraph. 2. to ensure that within ten business days after the completion of the tender process initiated by the end user or Shipper, the information in paragraph 1(b) will be disclosed on the public version of the Vector Transmission Open Access Transmission Information System (OATIS); 3. to negotiate, and where practicable agree on, a set of reasonable commercial terms to govern the transfer of capacity under Supplementary Agreements and Non-Code Shipper transmission services agreements (including where relevant reasonable amendments to Supplementary Agreements and Non-Code Shipper transmission services agreements), by a target date of 1 December 2011; 4. to disclose to Gas Industry Co such information as Gas Industry Co reasonably requires to enable it to understand and assess the extent of the Northern Pipeline capacity constraint, the efficiency of the current capacity allocation mechanism and the need for asset investment, provided Gas Industry Co only uses the information for the purposes set out in this paragraph and keeps confidential any information identified by a discloser as confidential (including not disclosing that information to any competitor); 4 186104.1 31 July 2017 5. to work with Gas Industry Co on a review of the Northern Pipeline capacity constraint, with the results made public and presented in an open forum by a target date of 1 December 2011; 6. to work together to develop a platform (known as a Bulletin Board) to facilitate the open and transparent trading of capacity between willing buyers and sellers, by a target date of 1 December 2011; and 7. to participate in a project with the objective of developing longer term market solutions; establishing the current need for gas transmission investment; and developing an effective pathway for gas transmission investment to take place, including correctly signalling the price of gas transmission capacity. Assessment The intention of the Bridge Commitments was to improve current market conditions while providing a bridge to longer term solutions. The Bridge Commitments as a whole have, wholly or partly, produced results sufficient to alleviate the short-term capacity problem (see below). Many of the longer-term issues have been folded into the GTIP. We are satisfied with the Bridge Commitments and we commend the efforts of industry participants in putting these together and continuing to make these work. We will continue to monitor these. Notable achievements for the Bridge Commitments are the establishment of a Bulletin Board to facilitate capacity trading, an agreement to disclose useful information where desirable, and the freeing up of additional capacity as a result of power station contract renegotiations. It is this latter point which has alleviated the short-term capacity problem: transmission contracts to the Otahuhu and Southdown power-stations were renegotiated which resulted in an increase in available firm capacity, additional interruptible capacity, and additional supplementary capacity. 3.2 Information projects The Information Projects are designed to improve the quality of information so that market participants are able to make informed decisions about transmission investment and alternatives. The Information Projects are summarised in the table below and then discussed in more detail. Table X. Information projects Purpose Component projects Why Status Notes To minimise information asymmetries Vector’s Capacity Determination For Vector to transparently review the North Pipeline capacity Or green? On track for December 2013 completion (or complete?) Supply and Demand Outlook To improve the quality of information so people make better decisions about transmission investment and alternatives Complete Concept report published 5 186104.1 31 July 2017 Purpose Component projects Why Status Notes Transmission Market Disclosures To ensure that information necessary for efficient operation of the market is available. (Note that the information that would be disclosed is non-financial and sits alongside the work of the Commerce Commission) N/A Subsumed by various other projects Backstop Information Gathering and Analysis To ensure access to data for analysis to underpin any conclusions and recommendations in relation to all areas of GIC’s work Complete GIC published protocol for information requests (rather than regulatory option) Vector’s capacity determination project Vector is undertaking consultation with industry participants to determine available pipeline capacity. In order to do this, Vector has outlined a detailed project plan which it intends to complete by December 2013. The project plan is as follows: Table X. Vector’s capacity determination project Milestone Deadline Interested parties provide Vector with feedback on Pipeline Capacity Consultation paper Complete Physical Modelling Inputs Decision Paper Complete Public forum to answer questions Complete Complete industry feedback on first consultation papers Complete Final copy of Pipeline Capacity Paper Complete Provide indicative timeline for next steps of process Complete Draft Capacity Determination for consultation February 2013 [or complete?] Final Capacity Determination paper Q2 2013 [or complete?] Capacity Determinations and Pipeline Review papers published December 2013 [or complete?] Key points to note from this sub-project are: o when modelling its transmission system, Vector separates the pipeline system into several smaller systems in order to independently assess the component parts. This is particularly necessary as not all of the component systems are connected; and 6 186104.1 31 July 2017 o there is no single way to answer how much capacity there happens to be on a particular pipeline at any one point in time. It therefore makes sense to think of capacity in terms of operational capacity, aggregate contractual capacity, and uncommitted operational capacity. Most delivery points on the Vector system have spare uncommitted operational capacity. However, there is little room for growth in some sections of the North Pipeline, particularly north of Auckland; o no material feedback was received on the process Vector uses for calculating uncommitted operational capacity. As a result of Vector’s project, the industry has a much better understanding of physical and commercial capacity as it related to Vector’s transmission pipelines. We are grateful for Vector’s efforts in carrying out this project. Supply and demand outlook Gas Industry Co engaged Concept Consulting to produce a document, with an associated model, called Gas Supply and Demand Scenarios 2012-2027. As part of the development of this sub-project, industry submissions were considered before the report was finalised. The key findings from the completed report were: o New Zealand’s gas supply position is strong relative to recent decades, mostly due to increased exploration activity encouraged by high oil prices. Increased availability has been reflected in softer gas prices; o long-term gas demand is likely to vary significantly between 75-250 PJ/year depending on price scenarios. Demand is projected to be steady for commercial, residential, and most industrial users. Volatile demand users include petrochemical manufacturers and power generation; and o existing pipelines are expected to have sufficient capacity to accommodate the projected scenarios except Vector’s northern pipeline system for which available capacity is low or zero at current levels. The need for new investment however could be deferred if low cost options are taken up by large users (i.e. power-stations). This sub-project is now complete. A model is available on Gas Industry Co’s website for interested parties to download and use as they wish. The model may be updated periodically. Transmission market disclosures This sub-project has been subsumed by other projects. 7 186104.1 31 July 2017 Backstop information gathering This sub-project is complete, at least for the time being. Gas Industry Co consulted on a Statement of Proposal in late 2011 which set out options for improving processes for Gas Industry Co to gather information required to assist in its policy development process. From that consultation, Gas Industry Co’s preferred option was to develop a formalised and transparent protocol for requesting information from industry participants. The protocol covers, amongst other procedures, how Gas Industry Co will manage confidential information. A successful operation of this protocol will either limit, or remove, the need for a regulated approach to information gathering. The protocol is available here: [insert link] 3.3 Market projects The focus of this project is on whether the VTC allows for efficient arrangements for the optimal allocation, utilisation, and pricing of capacity. The option to pursue more fundamental changes in wholesale and capacity markets may also be considered. The sub-projects are listed in the table and explained in more detail below. Table X. Market projects Purpose Component projects Why Status Notes Market Projects Transmission Pricing and Access To ensure efficient arrangements for optimal allocation, utilisation, and pricing of capacity Ongoing. Gas Trading Arrangements To ensure efficient arrangements for the gas market Longer-term option. Market proposals for gas market are being progressed Transmission Pricing and Access This work is largely being progressed by the PEA. The first deliverable for the PEA was to provide advice to Gas Industry Co on a review of Transmission Access and Pricing Capacity. That report considered the economics of pipeline access, discussed some lessons from overseas jurisdictions, identified problems with current arrangements in New Zealand, and proposed a straw-man for improving current arrangements. These issues are discussed in more detail in section [XX] below. Gas Industry Co analysed the submissions received on the PEA’s report. That analysis included a strategy to progress this workstream: it was decided that the PEA would continue to consider options to improve current arrangements in the short-term; once such short-term arrangements were in place, the PEA would consider reforms and improvements that could be implemented in the medium/long-term. 8 186104.1 31 July 2017 The next piece of work in this workstream is the publishing of the PEA’s further advice, which is being released concurrently with this paper. Gas Trading Arrangements This was identified as a possible sub-project in the event that a ‘market carriage’ arrangement is identified as the preferred option under the Transmission Pricing and Access sub-project. It is therefore on hold/not necessary until the outcomes of the Transmission Pricing and Access project are clarified. In related developments, but outside of the GTIP, there are two separate proposals being developed for a spot gas market. 3.4 Regulatory projects This purpose of this project is to identify whether there are appropriate incentives in place for investment in gas transmission pipelines. There was only one sub-project identified for this project which is discussed below. Table X. Regulatory projects Purpose Component projects Why Regulatory Projects Testing Investment Options To identify whether there are appropriate incentives in place for investment Status Notes On hold. This project is on hold until the Commerce Commission’s regulatory regime affecting gas transmission pipelines has been implemented. Once there is certainty on the Commerce Commission’s regulatory regime, this projection will consider investment scenarios and options for creating certainty for investors. Examples of the latter may include: the introduction of a Regulatory Investment Test; and a review of the Gas Act, to examine how it relates to part 4 of the Commerce Act and to ensure alignment where feasible. 3.5 Overall assessment Our view is that the GTIP to date has been a valuable process, but that further work is required before the original intent of GTIP is realised. The completed and/or implemented GTIP projects include the Bridge Commitments, the Supply and Demand study, the Information Gathering project, and Vector’s Capacity Determination project. 9 186104.1 31 July 2017 Each of the completed projects brings its own set of unique benefits to the industry. More generally, the benefits of the GTIP thus far include: the increased availability of information (i.e. the Supply and Demand outlook and Vector’s capacity consultation project); improved knowledge of physical and commercial arrangements in the industry such as how the physical capabilities of pipelines are assessed, security of supply standards, and how constraints are managed; facilitating systematic discussion of issues between market participants; influencing the renegotiation of transmission contracts for delivering gas to powerstations which has freed up additional capacity on the North Pipeline (via the Bridge Commitments); and allowing the industry to engage constructively on market design issues. However, GTIP has taken longer than expected. In the initial GTIP documents, it was envisaged that each sub-project would be completed around mid-2013. The PEA was to have provided final advice on its review of the VTC and pricing to Gas Industry Co in November 2012 and have submitted an implementation plan by April 2013. Due to robust consultation with the industry and the resulting re-scoping of the project, the sub-project being led by the PEA will require more time. Despite more work being required, we think it is worthwhile for the GTIP to continue with the outstanding projects. This sentiment was endorsed by industry representatives at the PEA workshop held at Gas Industry Co on 23 April 2013. Section 7 describes in more detail how we envisage the GTIP progressing. 10 186104.1 31 July 2017 4 4.1 Panel of Expert Advisers deliberation on transmission access Description of the Transmission Access and Capacity project The purpose of this sub-project is to ensure efficient arrangements for the optimal allocation, utilisation, and pricing of gas transmission capacity. As mentioned above and in the background documents, the genesis of this workstream was the announcement by Vector in mid-2009 that the North Pipeline was constrained and that it would be unable to issue additional reserved capacity. A consequence of this at the time was that larger end-users received lower interest from retailers when tendering gas supply contracts and/or those offers were made conditional on the procurement of capacity. Because that capacity belonged to retailers, Gas Industry Co was concerned that, owing to the capacity constraint, some end-users would not receive offers from other retailers and would have to accept whichever offer included capacity. This was a potential competition concern – the conditions would be present for retailers with capacity, and in circumstances that might be only one retailer, to set the terms of the supply agreement. Because the capacity belonged to the incumbent retailer, the VTC arrangements for grandfathering capacity exacerbated the problem: an incumbent retailer which lost the supply contract with a large end-user could retain the ownership of the capacity. If that capacity was the only capacity sufficient and available to supply an end-user, the customer could be locked-out of the market. Gas Industry Co’s response was to make a Statement of Proposal in which the preferred option would result in capacity ‘following the end user’ in the event of the user changing retailers on a constrained pipeline. Submissions on, and industry workshops following, the Statement of Proposal caused Gas Industry Co to establish the GTIP project. The PEA has been tasked with carrying forward this particular sub-project to date. The key deliverables for the PEA were agreed as: Key deliverable 1: Assessment of current arrangements and identification of options (Access and Capacity Pricing Options Paper) Key deliverable 2: Analysis of submissions on the Access and Capacity Pricing Options Paper 11 186104.1 31 July 2017 Key deliverable 3: Advice on development and analysis of shortlisted options (Decision Paper) Key deliverable 4: Analysis of submissions on the Decision Paper Key deliverable 5: Detailed implementation plan 4.2 PEA’s preliminary advice In its first report, which met key deliverable 1 listed above, the PEA provided Gas Industry Co advice and options for addressing concerns regarding the availability of gas transmission capacity in New Zealand. The PEA examined current access arrangements for Vector’s transmission system from the perspective of economic efficiency (allocative and dynamic). It was noted that capacity allocation mechanisms are most important when capacity is scarce. Primary problems identified were: grandfathering inhibits efficient allocation of capacity; there is no price signal for scarce capacity; there is low uptake of interruptible capacity arrangements; the effectiveness of the secondary market is unclear: it is thinly traded and non-transparent; there is a lack of transparency regarding the determination of the amount of commercial capacity; and there is uncertainty about whether the regulatory incentives are adequate to encourage new pipeline capacity to be built when it is efficient to do so. The PEA made a straw-man proposal which it deemed commensurate with an evolutionary (as opposed to a revolutionary) approach, the small size of the New Zealand market, and was low cost. The straw-man proposal would target each of the problems listed above. The straw-man proposal would: water down grandfathering rights by tapering down the percentage of grandfathering each year and auctioning the remainder if demand for capacity was greater than supply1; encourage higher uptake of interruptible contracts to manage demand peaks and supply-side disruptions; raise fixed charges and lower variable charges; introduce a nominations regime; and improve the available information on capacity, utilisation, and prices of capacity in the secondary market. Further analysis was required regarding the investment uncertainty problem. Submissions received A wide range of submissions were received, but some common themes emerged: there were some concerns that a vision for the future had not been presented; some were dissatisfied with the problem definition; 1 Grandfathering would essentially continue at a rate of 100% of last year’s capacity on a pipeline with excess supply. 12 186104.1 31 July 2017 the straw-man was the only option given considerable attention. Submitters suggested that other options should have been considered, including a common carriage regime; concerns that Vector’s point-to-point contract carriage regime may not allow for full utilisation of physical pipeline capacity and that a shift to common carriage or the introduction of use-it-or-lose-it rules may need to be considered; and support for greater transparency. 4.3 Issues considered since preliminary report The PEA discussed and amended certain aspects of its work plan in response to the submissions received. Characteristics of an ideal gas transmission market The PEA developed characteristics of an ideal gas transmission market which will be a useful check for assessing whether future changes are in the right direction. The development of these characteristics was in direct response to calls for a ‘long-term vision’ – by agreeing on these principles up-front, the industry would be able to assess whether the PEA’s advice was consistent with the long-term vision. The overarching characteristic is a goal of dynamic efficiency, which is to maximise efficiency in the present and in the future. Beneath this overarching goal, there are a number of secondary characteristics which are: minimisation of costs (including transaction costs) of governing and operating efficient transport arrangements; maximum efficient use of physical capacity, particularly at times of capacity scarcity; competition in related markets not distorted; efficient investment in related markets is facilitated; investment in pipelines is facilitated; independence of functions in governance and operation; appropriate operational and commercial transparency; and arrangements evolve in a timely fashion to meet changing needs. Best access regime for the future The PEA considered which particular access regime was best suited to the future New Zealand gas market. It concluded that there are too many uncertainties about the future gas market to reach a confident view 13 186104.1 31 July 2017 about which transmission access regime design would best fit. In any case, incremental changes are preferred to radical changes given the high cost of significant regime changes. Revised problem definition Given submitters’ views on the problem definition, the PEA carried out a gap analysis of current arrangements versus the ideal characteristics. This exercise led to a revised problem definition as follows: Current access arrangements do not provide for: efficient allocation of scarce capacity, both physical and commercial; price signals to facilitate efficient investment; or transparency on physical state of the pipelines and contractual arrangements for the use of pipelines. Also: grandfathering of capacity may reduce competition to supply downstream users; unnecessary costs may arise from different Maui and Vector access arrangements; end users do not need to secure long term capacity rights, as evidenced on the Maui pipeline; and vertical integration demands special care that arrangements cannot favour affiliate businesses. Transmission Access and Capacity Pricing project: Revised purpose statement With all of the re-framing discussed above, the PEA considered that it was necessary to re-examine the purpose statement for the transmission access and capacity pricing project. This was agreed as: The purpose of the Transmission Access and Capacity Pricing project is to ensure that transmission pipeline access arrangements are dynamically efficient. In particular, the arrangements should: transparently provide for the efficient utilisation of physical transmission pipeline capacity ; enable and facilitate efficient investment; be harmonised across both transmission systems, to the extent that it is efficient; and offer transport services that, to the extent that is efficient, meets the needs of users. 14 186104.1 31 July 2017 4.4 April 2013 Workshop Gas Industry Co hosted a workshop in April 2013. The workshop was an opportunity for the PEA to update the industry on the PEA’s work and findings. Detailed presentations for the workshop are available on Gas Industry Co’s website. The workshop included three separate sections. First, Gas Industry Co provided an introduction to the GTIP project including a recap on what was initially intended to be accomplished. We noted that the scene had changed since the initial concerns about the capacity shortage emerged, particularly that all requests for firm capacity were met in the current gas year. Second, Graham Scott and Lewis Evans (the PEA Chair and PEA’s Economics Advisor respectively) provided their and the PEA’s assessments of the current status of the Transmission Access and Capacity project. Some of the points made are worth repeating: the Vector and Maui systems are both multilateral contracts suited for the current position of excess capacity; current Vector and Maui arrangements for interruptible contracts are reasonable for the present state of throughput but not for any future throughput requiring congestion management; future arrangements should include some (at least partial) provision for long-term security of access, particularly for potential green-field investments. However, this must match with a solution to congestion management; the use of grandfathering contracts should be limited; and ideally, both the Maui and Vector systems should publicly reveal the state of capacity and utilisation on each pipeline, as well as the nature of contracts available and in place, including the prices of these. The Vector system may be less transparent than the Maui system to reflect a different regime but there ought to be some convergence between the codes in terms of transparency. If such transparency would be limited by either the VTC or MPOC, the respective Code should be the thing to change. The third part of the workshop provided an opportunity for the industry to discuss the topics presented and some of the options available for making improvements for transmission capacity arrangements. In general, the industry endorsed the GTIP carrying on to complete the incomplete projects. No further options were raised by the industry so only the options presented at the workshop are assessed in section 5 below. 15 186104.1 31 July 2017 5 Description of reasonably practicable options This section describes the options available for improving capacity arrangements for gas transmission pipelines in New Zealand. This description is Gas Industry Co’s own – it is independent of the PEA’s advice. 5.1 Capacity follows end-user This option was first proposed by Gas Industry Co in its Statement of Proposal on Retail Competition and Transmission Capacity in late 2010. The option is simple in design: on a constrained pipeline, which would be defined in a set of rules, a retailer who wins a contract to supply a large end-user receives an amount of capacity to supply that customer. A ‘large end-user’ would be defined in relation to an annual demand threshold which itself would be specified by Gas Industry Co based on the objective of facilitating competition. The amount of capacity to be transferred (by Vector) would be deduced firstly by Vector calculating a ‘Capacity Amount’ based on the historical daily gas demand of the large end-user over the period of peak demand of the incumbent retailer on the constrained pipeline. A Reserved Capacity Increment (RCI) is then agreed by Vector and each retailer (other than the incumbent) that is bidding to supply the large end-user. The RCI is the amount of incremental capacity a retailer will require should its bid be successful. If the incumbent retailer loses the tender a switch takes place. On the switch date, Vector transfers the RCI from the old retailer to the new retailer. Any difference between the RCI and the Capacity Amount is rescinded to Vector. Retailers make no payments to each other in relation to a capacity transfer. At the time, this option was the preferred option in the Statement of Proposal. It was assessed as delivering a ‘good’ rating for the promotion of competition, a ‘moderate’ rating for consistency,2 a ‘very good’ rating for timeliness of implementation, ‘moderate’ for preservation of existing contractual rights, a ‘good’ rating for the avoidance of shocks on end-users and retailers, and a ‘very good’ rating for the curtailment criterion.3 More detail on the option itself is available in the Statement of Proposal. 2 Consistency 3 was defined as… Curtailment was defined as… 16 186104.1 31 July 2017 5.2 Capacity auctioning Capacity auctioning was one of the key components of the PEA’s proposal. We provided an overview of the PEA’s straw-man proposal in section 4.2. For the full proposal, see the paper here. Of course, an option for capacity auctioning need not be limited to the PEA’s advice. This section briefly outlines capacity auctioning at a more general level. Before discussing capacity auctioning, it is useful to outline the capacity reservation process used by Vector to allocate capacity to its pipeline users. Capacity reservation process At present on the Vector system, capacity is primarily allocated on a grandfathered basis which means a Shipper is entitled to the same amount of capacity in the following year that it used in the current year. To be clear, the type of capacity referred to here is reserved capacity: Vector will not issue reserved capacity which exceeds the physical capacity of a pipeline. Capacity must be paid for each year by Shippers. Any capacity that is not grandfathered may be reserved by way of the capacity reservation process. By 5pm on the second Friday of August in each year, a Shipper notifies Vector of its expected reserved capacity requirements between each Receipt Point and each Delivery Point for the following gas year. A process follows whereby Vector confirms a Provisional Reservation Requirement for each Shipper, the Shipper then confirms its reserved capacity requirements, and then Vector confirms the extent to which the reserved capacity requirement is accepted. If there is insufficient transmission capacity in a pipeline to meet the confirmed reservation requirements of all Shippers then Vector will first allocate the same amount of reserved capacity to each of the Shippers that had capacity on the pipeline, provided the amount is less than or equal to the reserved capacity in the previous year. Vector will then allocate any remaining capacity in a pipeline to Shippers based on the proportion that the Shipper’s request for increased capacity from the previous year on that pipeline bears to the aggregate of all Shippers’ requests for increased capacity from the previous year on that Pipeline. The VTC also sets out processes for the reservation of additional capacity during a year and for cancellation of capacity during a year. Shippers may transfer Reserved Capacity to other locations or to another Shipper, subject to Vector’s approval. Problems with capacity reservation process The problem with this approach of grandfathering capacity, from an economic perspective, is that the value of capacity is uncertain and non-transparent. This means that, particularly if a pipeline is constrained, capacity is unlikely to be efficiently allocated amongst Shippers. This situation was played out after Vector’s announcement in 2009 that it would be unable to issue additional reserved capacity. It became apparent that the VTC arrangements would essentially lock-in the existing Shippers’ reserved capacities (if those Shippers wished to roll-over that amount) and the only way for a competing retailer or new entrant to access capacity on the North Pipeline would be for such a retailer to seek a Reserved Capacity trade. 17 186104.1 31 July 2017 The value of capacity in such a trade would be uncertain to the prospective entrant and the incumbent would enter such a negotiation in a dominant position. Capacity auctioning Capacity auctioning would be one way to solve the problem discussed above. Without discussing the specifics of the design of the auction, a price ought to be struck which would ensure those who value the product the highest would receive an allocation, provided they were willing and able to pay for it. This would be particularly useful where the product was scarce – as was the case for the North Pipeline. This allocation by price would in theory improve the efficiency of the capacity allocation process. If capacity auctioning was a preferred option then more analysis could be carried out on the preferred auction design (including a more detailed proposal based on the PEA’s initial advice). That analysis could consider some lessons from capacity auctions used internationally, such as in the Victorian (Australia) market or in the United Kingdom. 5.3 Convergence [Delete this section and replace with a note referring to the PEA’s report?] Convergence, as discussed by the PEA, is the idea that the two transmission systems should merge where they have common processes. The industry’s preferred arrangements appear to be towards a common carriage arrangement which is more similar to the arrangements for the MPOC than the VTC. At the April 2013 workshop, it was discussed that convergence could include: common administrative arrangements, for example: o dispute resolution arrangements: o code change arrangements: o technical standards; common transportation concepts, for example: o extending operational balancing agreements to all receipt and delivery points: o equating Authorised Quantity (AQ) and term capacity: o a common nominations regime across both pipeline systems: o common curtailment arrangements on both pipelines; and a common IT system, such as a less customised system of OATIS. 18 186104.1 31 July 2017 An idea for implementing convergence is to create a new document, perhaps an all-of-industry-code, which would carve out those aspects of the MPOC and the VTC deemed to fit the convergence mould. 5.4 Integration This option is about a wider-ranging reform to the New Zealand gas market. Rather than making piecemeal changes to current transmission codes or carving out aspects of each to be shared in a single code, integration would likely do away with the MPOC and the VTC and replace them with national gas transmission rules. Additional features could also be added, including specified markets for balancing gas transactions and secondary and/or futures trading of products (including gas). Such an option would more closely align the gas market with the procedures for the New Zealand electricity market. In essence, the transmission system would be split up into many entry/exit points (‘nodes’) and there would be a market clearing mechanism for each node taking into account temporal supply and demand at regular specified intervals. Thus, the gas market would transition to a spot market. A common criticism of such a wide-ranging reform from the incumbent industry is that such changes are not commensurate with the small scale of the New Zealand system and/or that implementing such a system would be too costly. [Discuss Victorian example] Pros/cons of this option [TBC] Q1: Do you have a preferred option from those discussed above? If so, do you prefer your option to the one put forward by the PEA? Please provide full reasoning. 19 186104.1 31 July 2017 6 Proposed evaluative framework Gas Industry Co intends to consider submissions from the industry on the PEA’s paper and on the options outlined in section 5. We will then assess the submissions against the framework outlined below. Regular Gas Act objectives In our normal policy development, we would consider any options against the objectives listed in the Gas Act. We would also assess the costs and benefits of the options and whether they would be achievable without having to make regulations. PEA’s characteristics of an ideal gas market Given the considerable work of the PEA, it makes sense to also factor in the characteristics of an ideal gas market that were agreed by PEA members (as discussed in section 4.3 above). Gas Industry Co’s proposed approach to evaluating the options and submissions The question is: which of these should determine the evaluation for the preferred option or options? We have cross-referenced the Gas Act objectives and the PEA’s characteristics of an ideal gas market. This assessment shows that there is a complete overlap between each set of criteria (see the figure below). The implication is that the evaluation at the next stage of this workstream could include either or both of the frameworks mentioned above. Because there is a complete overlap, our preference is to consider the preferred option or options against the Gas Act objectives. This is primarily because, should this workstream eventually result in having to make a recommendation to the Minister, such a recommendation would have to be consistent with the Gas Act. Therefore, it makes sense to use that framework as early as possible. We welcome submitters’ views on this. 20 186104.1 31 July 2017 Cross referencing evaluation criteria with Gas Act objectives Ideal market characteristics 1. Dynamic efficiency Gas Act 1992 s43ZN Objectives ensure that gas is delivered to existing and new customers in a safe, efficient, and reliable manner (s43ZN(a)) 3. Efficient use of physical assets the facilitation and promotion of the ongoing supply of gas to meet New Zealand’s energy needs, by providing access to essential infrastructure and competitive market arrangements: (s43ZN(b)(i)) 4. Related market competition not distorted barriers to competition in the gas industry are minimised (s43ZN(b)(ii)) 2. Minimum governing and operating cost 5. Related market investment facilitated incentives for investment in gas processing facilities, transmission, and distribution are maintained or enhanced (s43ZN(b)(iii)) 6. Pipeline investment facilitated 7. Independence of pipeline business 8. Operational/commercial transparency delivered gas costs and prices are subject to sustained downward pressure (s43ZN(b)(iv)) risks relating to security of supply, including transport arrangements, are properly and efficiently managed by all parties (s43ZN(b)(v)) 9. Able to evolve in timely fashion consistency with the Government’s gas safety regime is maintained (s43ZN(b)(vi)) Q2: What are your views on the appropriate evaluation methodology for assessing the preferred option or options that result from this paper and the PEA’s second piece of advice to Gas Industry Co? 21 186104.1 31 July 2017 7 Way forward for the GTIP There are several projects still to be completed under the GTIP. The industry endorsed the ongoing programme at the April workshop. We therefore intend to continue working on the outstanding GTIP projects, as set out below. Market Projects The Transmission Pricing and Access project is the main focus of this paper and the PEA’s second piece of advice to Gas Industry Co. The outstanding tasks for this project are: 1. to analyse submissions received on the PEA’s report and on this paper; 2. to agree on the preferred option and how to implement it; and 3. to implement the option. Though originally slated to be achieved by mid-2013, we consider that all of the steps above can be achieved by mid-2014. This may require the on-going involvement of the PEA. As discussed above, the Gas Trading Arrangements project is on hold until the outcomes of the Transmission Pricing and Access project are clarified. We will revisit the purpose of this project at the completion of the Transmission Pricing and Access project, however it seems as though this project will no longer be required at this point. Regulatory Project As discussed above, the regulatory project has not yet commenced. A detailed project plan will be formulated at the completion of the Commerce Commission’s set-up of the input methodologies. We expect that our project will begin at some point in the second half of 2013. Q3: Do you agree with the proposed way forward for the GTIP? 22 186104.1 31 July 2017 Glossary GTIP Gas Transmission Investment Programme MPOC Maui Pipeline Operating Code OATIS Open Access Transmission Information System PEA Panel of Expert Advisers RCI Reserved Capacity Increment VTC Vector Transmission Code 23 186104.1 31 July 2017 Gas Transmission Investment Programme, Status and Development - July 2013 Submission prepared by: QUESTION (company name and contact) COMMENT 24 31 July 2017
© Copyright 2026 Paperzz