aic installation standards

AIC INSTALLATION STANDARDS
AT&T Integrated Cloud
Issued May 2016
Revised August 2016
AIC INSTALLATION STANDARDS (AICIS)
Introduction
This document presents detailed requirements covering all AIC infrastructure installations.
Requirements are divided into Sections with each sections focused on a key area(s) needed to
realize a quality installation. The expectation is that the vendors will understand these requirements
and apply them to all AIC installation they deliver. These requirements cover all technical spaces AIC
is deployed in which includes CO, SNRCs, IDC, EDC and NTC. As new technical spaces are
introduced an effort will be made to examine and extend application of AICIS to this new space. Any
reference to standard or industry standards should be interpreted as a reference to TIAA standards.
Presented first are the general overall guideline used to craft these detailed requirements.
Overall Guidelines
AIC standards should only include installation requirements that are Critical to Safety and
Critical to Service. Any other requirements become best practices/guidance for the installation
vendors and will not be enforced
This guideline involves inclusion of only those installation requirements, in AIC Installation standards,
that ensure:
1. Safety of AT&T/Vendor employees and
2. Avoiding conditions, caused by poor workmanship, that are highly likely to cause a service
outage within useful life of the platform (3-5 years).
1
Issued May 2016
Revised August 2016
CONTENTS
1.
AT&T
PAGE
GENERAL .................................................................................................................................. 3
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
1.10
2.
Introduction ................................................................................................................................ 3
Scope ......................................................................................................................................... 3
General Requirements .............................................................................................................. 4
Laws, Rules And Ordinances .................................................................................................... 4
Hazardous Waste ...................................................................................................................... 5
Safety ......................................................................................................................................... 5
Tools and Precautions ............................................................................................................... 6
Installation Supplier Warranty .................................................................................................... 6
Quality Assurance Programs ..................................................................................................... 6
Workmanship ...................................................................................................................... 6
RACK/EQUIPMENT .................................................................................................................. 7
2.1
2.2
2.3
2.4
3.
Placement .................................................................................................................................. 7
Leveling ..................................................................................................................................... 7
Securing/Anchoring ................................................................................................................... 7
Shipping ..................................................................................................................................... 9
GROUNDING/BONDING .......................................................................................................... 9
3.1
4.
AIC Grounding ........................................................................................................................... 9
INTRA RACK POWER .............................................................................................................. 9
4.1
4.2
5.
Power ......................................................................................................................................... 9
PDU Installation and load balancing.......................................................................................... 9
CABLING ................................................................................................................................. 10
5.1
5.2
5.3
5.4
6.
Cables and Cabling ................................................................................................................. 10
Securing Power Cables ........................................................................................................... 11
Power Cabling ......................................................................................................................... 11
Power cables AT&T DC Plant Environment ............................................................................ 11
LABELING ............................................................................................................................... 13
6.1
6.2
6.3
2
AIC INSTALLATION STANDARDS
Labeling ................................................................................................................................... 13
DC power cables ..................................................................................................................... 14
Power Labeling ........................................................................................................................ 15
AIC INSTALLATION STANDARDS
AT&T Integrated Cloud
Issued May 2016
Revised August 2016
1.
GENERAL
1.1
Introduction
1.1.1
This document provides the installation standards for AT&T Integrated Cloud (AIC) build outs
in AIC Technical Space environments. This document provides general requirements when
doing equipment installation, modification, removals or building work activity in AIC Technical
Space.
1.1.2
Roles and Responsibilities:
a) “Installation Supplier” refers to organization performing the requested work activity.
b) “AT&T” refers to the Person(s) requesting the work activity.
1.1.3
The fundamental Guiding Principles of all sections of this document are as follows:
a) AIC Installation Standards should only include those requirements that are Critical to
Safety and Critical to Service.
b) Any other requirements will be considered Best Practice/Guidelines but will not be audited
by AT&T.
c) These standards and guidelines are written:
1. To ensure the Safety of AT&T and Installation Supplier employees
2. Avoid conditions caused by poor workmanship that are highly likely to cause a
service outage within the useful life of the platform (generally, 3-5 years)
1.1.4
AT&T assumes no responsibility for any costs incurred by a given manufacturer or the
Installation Supplier in conforming to the requirements of this document. Further,
conformance to all requirements delineated in this document does not constitute a guarantee
of acceptance of a given Installation Supplier’s product/service for use in AT&T AIC
environments.
1.1.5
AT&T reserves the right, without prior notice, to revise this document for any reason.
1.1.6
AT&T reserves the right to audit Installation Suppliers for compliance to this document.
Questions concerning the audit process or quality results should be referred to:
AT&T - U.S. Quality Assurance:
402 N 3RD ST
FLOOR 2
Saint Charles, MO 63301
Attention: Christine Holmes
[email protected]
1.2
Scope
1.2.1
The requirements contained in this document apply to installations in any AIC Technical
Space which is defined as technical space dedicated to housing AIC equipment infrastructure
either in stand-alone buildings or space within shared-use buildings.
3
Issued May 2016
Revised August 2016
AIC INSTALLATION STANDARDS
AT&T
1.2.2
If collocated in buildings with existing Legacy Technical Spaces (e.g. COs, SNRCs, NTCs
etc.) the AIC Technical Space shall be engineered to be separated from the Legacy
Technical Spaces by one-hour fire rated barriers and shall follow applicable NEC and fire
codes.
1.2.3
The standards and requirements for site preparation and conditioning for AIC Technical
Spaces is included in ATT-812-000-723, AT&T Integrated Cloud (AIC) Technical Space
Building Infrastructure Design Requirements.
1.3
General Requirements
1.3.1
The Installation Suppliers shall ensure as part of the evaluation of the installation that all work
has been completed in accordance with the AT&T detail specifications, AT&T engineering
documents or approved changes to the AT&T detail specifications.
1.3.2
All proprietary documents referenced in this document are available to contracted Installation
Suppliers through signed nondisclosure agreements or as detailed in current contracts
between AT&T and Installation Suppliers.
1.3.3
Non-AT&T publications referenced herein should be obtained from the originator of the
publication.
1.3.4
Comments on this document should be submitted by e-mail to:
AT&T - U.S. Quality Assurance:
402 N 3RD ST
FLOOR 2
Saint Charles, MO 63301
Attention: Christine Holmes
[email protected]
1.4
Laws, Rules And Ordinances
1.4.1
The Installation Supplier shall comply with all applicable federal, state, county and local laws,
ordinances, regulations and codes.
1.4.2
The Installation Supplier shall comply with all applicable Occupational Safety and Health
Administration (OSHA) and Environmental Protection Agency (EPA) regulations when
dealing with hazardous materials and other work place hazards.
1.4.3
The Installation Supplier will be responsible for providing all necessary permits from the local
Authority Having Jurisdiction (AHJ).
1.4.4
Where applicable, all work performed by the Installation Supplier shall meet or exceed the
technical requirements of the National Electrical Code (NEC) and all state, county and local
codes.
1.4.5
All work and materials shall conform in every detail to the rules and requirements of the
National Fire Protection Association (if in the US), the State Electrical Code (if in the US) and
present manufacturing standards. All materials shall be listed by UL and shall bear the UL
label.
4
AIC INSTALLATION STANDARDS
AT&T Integrated Cloud
Issued May 2016
Revised August 2016
1.5
Hazardous Waste
1.5.1
The Installation Supplier shall discuss with the AT&T Representative any hazardous
materials existing in the AIC Technical Space and/or hazardous materials to be used on the
job and handled per the requirements of this document.
1.5.2
The AT&T Representative shall adhere to guidelines and procedures established by AT&T
EH&S, available on the AT&T EH&S (Environment, Health & Safety) web site,
http://www.ehs.att.com/, or via contact to the AT&T EH&S Hotline at 1-800-KNOW-EHS (1800-566-9347).
1.6
Safety
1.6.1
The Installation Supplier shall be entirely responsible for the safety and instruction of its
employees or representatives.
1.6.2
The Installation Supplier shall take precautions to avoid harm to personnel, equipment and
building (e.g., cutting installed threaded rod).
1.6.3
The Installation Supplier shall immediately report to the AT&T Representative any accident,
outside agency inspection or hazardous condition, including:
a) Any accident or injury that occurs to employees or subcontractors of the Installation
Supplier while on AT&T premises.
b) Any OSHA inspection or citations issued to the Installation Supplier while on AT&T
premises.
1.6.4
Floors and work area shall be kept free of all potential hazards. The Installation Supplier shall
avoid creating a slip or trip hazard.
1.6.5
All waste materials, such as waste paper, foam, plastic, cloth bags, packing boxes, packing
material and similar material supplied during the installation, shall be removed from the
building by the Installation Supplier on a daily basis (or more frequently if required).
1.6.6
All walkways, entrance and exit routes through the equipment area shall be kept clear of
tools, equipment, equipment packaging, cable, etc. Caution signs/cones shall be posted
where needed.
1.6.7
The Installation Supplier shall not obstruct doorways, equipment aisles, corridors, stairs, fire
exits, fire extinguishers and fire-fighting equipment, pull box alarms and electrical
breaker/fuse panels.
1.6.8
If the Installation Supplier has any questions in regard to safety, contact the AT&T
Representative.
1.6.9
The Installation Supplier shall ensure the following during the installation:
a) That combustibles are not brought into equipment areas.
b) That apparatus or materials are not stored in equipment aisles, corridors, stairs or fire
exits.
c) That Installation Supplier’s personnel adhere to AT&T’s no-smoking policy.
5
Issued May 2016
Revised August 2016
AIC INSTALLATION STANDARDS
AT&T
d) That precaution is taken to prevent fire resulting from the use of temporary wiring, test
wiring, lamps, soldering irons and other similar equipment.
e) That no activity cause the activation of smoke alarms or other sensors.
f)
That Installation Supplier personnel are familiar with the building’s evacuation features.
g) That Installation Supplier personnel are familiar with the location and use of the fire
extinguishing equipment in the installation area.
h) When there is any doubt, check with AT&T Representative for site-specific procedures or
compliance.
1.7
Tools and Precautions
1.7.1
The Installation Supplier shall provide its own tools.
1.7.2
Extension cords shall be NRTL listed, three conductor, 14 gauge or larger, commercial grade.
1.7.3
All battery and AC powered tools shall be grounded or double insulated.
1.7.4
The Installation Supplier shall remove all personal jewelry when performing any installation
activities.
1.7.5
Metal framed ladders, metal desks and metal chairs shall not be allowed in the immediate
vicinity of AIC equipment.
1.7.6
Non-conductive measuring devices (i.e. measuring tapes) shall be used in the vicinity of
working AIC equipment.
1.8
Installation Supplier Warranty
1.8.1
The Installation Supplier shall provide warranty as per AT&T negotiated contracts.
1.9
Quality Assurance Programs
1.9.1
The Installation Supplier shall conform to AT&T’s Quality Assurance Program as specified by
the AT&T’s Quality Assurance organization in support of these requirements.
1.10
Workmanship
1.10.1 The Installation Supplier must be proficient in using the manufacturer’s products, adhere to
the engineering, installation and testing procedures and utilize the approved products and
devices.
1.10.2 The Installation Supplier shall be experienced in all aspects of this work and may be required
to demonstrate direct experience on systems of similar scope and size and shall have
demonstrated competency for the job assigned.
1.10.3 All cut materials that shall be installed shall have any sharp or rough edges finished with a file
or grinder and performed outside of the office.
1.10.4 Additionally, any scratches or blemishes to the materials exposing bare metal shall be
touched up with the appropriate finish coating.
6
AIC INSTALLATION STANDARDS
AT&T Integrated Cloud
2.
Issued May 2016
Revised August 2016
RACK/EQUIPMENT
AIC Rack/Equipment Requirements
2.1
Placement
2.1.1
Rack Placement of Hot / Cold Aisles: Racks shall be arranged with alternating rows fronts of
racks facing each other in a row to create ‘cold’ and ‘hot’ aisles.
2.1.2
Uninterrupted rack rows should not exceed 40 continuous feet in length. Racks shall be
aligned according to the clearance recommendations. (Per ATT –812-000-723 AT&T
integrated Cloud (AIC) technical Space Building Infrastructure Design Requirements)
2.1.3
Computing Equipment Placement: Equipment shall be placed in racks with ‘cold’ air intake at
the front of the rack. Blanking panels shall be installed in empty rack spaces to improve the
functioning of the airflow. Special arrangements and exceptions will be made for large
computing equipment.
2.1.4
Placement relative to floor tile grid: When placed on access floor, racks shall be arranged so
that they permit tiles in the front and rear of the racks to be lifted. Racks shall be aligned with
either the front or rear edge along the edge of the floor tile. Racks shall be placed such that
the threaded rods that secure the racks to the slab will not penetrate an access floor stringer.
2.1.5
For details of Rack-Roll/Rack-Stack refer to Reference ATT-TELCO-IS-JA-000-004-121.
2.2
Leveling
2.2.1
Racks located within Low Seismic Risk regions shall rest on the floor surface with or without
the use of leveling feet and caster assemblies.
2.2.2
Racks located within High Seismic Risk regions shall rest on the floor surface without the use
of leveling feet or caster assemblies.
2.2.3
Racks levelers shall be deployed as per manufactures guidelines.
Note: Seismic Risk regions can be investigated at
http://iecss.web.att.com/zones/ZoneForm.cfm
2.3
Securing/Anchoring
2.3.1
Equipment deployed within High Seismic Risk regions shall be installed within GR-63-CORE
Seismic Zone 4 certified racks Equipment deployed within Low Seismic Risk regions shall be
deployed within racks rated for IBC and UL rated (minimum requirement). Worst case
conditions in the IBC Seismic 4 standard shall be considered when performing the modeling
test.
2.3.2
Racks shall be plumb, level and junctioned together using the appropriate manufacturer
supplied hardware. It assures that the racks are attached and aligned securely to each other,
supporting and dispersing weight equally for the maximum capacity. Uprights of adjacent
racks shall be joined together per manufacturer’s specifications to form a continuous lineup.
2.3.3
Low Seismic Risk regions: Side junctioned racks located within an equipment lineup shall be
anchored with bolts to the floor using a minimum of two AT&T approved floor anchors (refer
7
Issued May 2016
Revised August 2016
AIC INSTALLATION STANDARDS
AT&T
to Figure 1). Free standing non-junctioned racks shall be anchored with bolts to the floor
using a minimum of four AT&T approved floor anchors (refer to Figure 1).
2.3.4
Racks located within High Seismic Risk regions shall be anchored with bolts to the floor using
a minimum of four AT&T approved seismic floor anchors. Refer to Figure 2.
FIGURE 1 -- Cabinet Anchoring – Low Seismic
FIGURE 2 -- Cabinet Anchoring – High Seismic
2.3.5
Racks shall not be mechanically connected to any suspended grid system. This includes
ceiling suspended and stanchion suspended system. This does not include stubbed up
systems supported from the tops of racks or stanchions.
2.3.6
In lineups where racks are the primary or only support for overhead cable rack, the
equipment rack shall be secured to building floor with four anchors and junction to adjacent
racks. Refer to Figure 2.
2.3.7
Where equipment racks shall not be side junctioned, a space of 5 inches minimum shall be
provided between the adjacent racks or building walls, columns or other structural members.
2.3.8
No part of any equipment installed within or apparatus attached to the rack shall extend
beyond the footprint of the rack.
2.3.9
The fronts of the base of all racks in a common lineup shall be aligned. An exception to this
requirement is permitted for racks that are shown on the floor plan to be out of alignment with
the other racks in the lineup. Exceptions should only be made on an as-needed basis and
8
AIC INSTALLATION STANDARDS
AT&T Integrated Cloud
Issued May 2016
Revised August 2016
framework extension beyond existing racks in the lineup into the front or maintenance aisle
shall not exceed 3 inches.
2.3.10 For more detailed information on Equipment framework anchoring (raised access floor) –
refer to ATT-TP-76402, Section 10.
2.4
Shipping
Reference ATT-TELCO-IS-JA-000-004-121, “Potential Rack & Issues” Job Aid Rack-n-Roll
Feasibility Check List
2.4.1
From Manufacture to VAR Facility: The empty equipment rack shall be shipped from the rack
manufacturing warehouse to the VAR facility on standard shipping pallet with cardboard
protective corners, cardboard top plate and shrink-wrap.
2.4.2
From Value Added Resource (VAR) to Site: VAR is to provide a shock resistive pallet
designed for AIC specific racks deployments. VAR to also provide a ramp capable of
allowing AIC racks to be rolled from said pallet, if applicable. The shock pallet is to be
returned to the VAR facility once the rack has been removed from the pallet. More details
can be found in Rack & Roll Checklist ATT-TELCO-IS-JA-000-004-121.pdf.
2.4.3
The VAR Facility is to palletize and crate the assembled equipment rack for shipment to
installation site.
2.4.4
Tilt/shock indicators shall be attached and activated on the shipping container to indicate
potential equipment damage during transit. The VAR facility is to attach tilt/shock indicators
on the shipping container, as per manufacturer’s instructions, in a manner that allows for
front-to-rear and side-to-side tilt monitoring.
3.
GROUNDING/BONDING
3.1
AIC Grounding
3.1.1
All equipment, racks, and overhead racking (if used) shall be properly bonded to the site
grounding system to insure safety of personnel and reliability of service. Rack doors shall be
bonded to the racks.
3.1.2
At a minimum, the grounding installation must comply with all applicable articles of the
current issue of the National Electrical Code NFPA-70.
3.1.3
Grounding conductors shall be sized to handle the maximum possible AC and/or DC fault
current.
3.1.4
The Installation Supplier shall apply a thin coat of NO-OX-ID “A” anti-corrosive compound to
all connections of dissimilar metals to inhibit future corrosion
4.
INTRA RACK POWER
4.1
Power
4.1.1
All AIC Power installation work shall be in accordance with the NEC® and NFPA.
4.2
PDU Installation and load balancing
9
Issued May 2016
Revised August 2016
AIC INSTALLATION STANDARDS
AT&T
4.2.1
Equipment shall be plugged into ports assigned by Design Team.
4.2.2
Once AC devices are powered-up and placed under load, the PDU’s LED readout (or
management tools) shall be reviewed to determine if the load is evenly distributed across the
electrical phases and do not exceed 80% of the PDU branch capacity. If the load is not
distributed equally across the three (3) electrical phases, in consultation with the design
team, care shall be taken to re-locate the power-plugs to other electrical phases. This
approach should also be taken to balance loads across any single phase PDU (CDU)
branches and do not exceed 80% of the PDU branch capacity.
4.2.3
Separate A&B diversely sourced protected PDUs shall be provided. Exception: When the
equipment rack is designed exclusively for single power feed equipment.
4.2.4
Each PDU shall be engineered with a dedicated branch supply circuit sourced from a PPSC
and load managed, not to exceed 80% of the PDU circuit breaker.
4.2.5
Each PDU shall be installed in a rack per manufacturer’s recommendations. PDU’s shall be
placed so as to not impede the removal of any equipment from the rack.
5.
CABLING
5.1
Cables and Cabling
5.1.1
Communication cables/jumpers shall be compliant with ANSI/TIA Standards, 10/40/100
technology, and Method B (Key up Key up).
5.1.2
MPO mated connectors shall include alignment pins.
5.1.3
LC connectors shall permit polarity reversals in the field.
5.1.4
OM4 communications channel shall not exceed 150m limit.
5.1.5
Cables/jumpers shall be protected from sharp edges, hot surfaces, and supported to prevent
excessive strain on the connectors while maintaining proper bend radius.
5.1.6
Vertical drops of fiber into the racks shall always be protected e.g. using split or flexible
tubing. See Figure 8, 9, 10.
5.1.7
Standard inside bending radius (industry standards), by cable type, shall be observed at all
times unless specified differently by the manufacturer.
5.1.8
Cables shall be routed in engineered pathways.
5.1.9
Standing on or applying excessive stress/pressure to cable is prohibited.
5.1.10 Every attempt shall be made to segregate communications cables and power cables in
accordance with the design document.
5.1.11 Cables/jumpers shall be ordered in the shortest standard stocked length to minimize slack.
5.1.12 Inter-rack cable slack storage should be avoided within the racks.
5.1.13 Installed copper backbone cables shall be certified to industry standard specifications per
cable type.
10
AIC INSTALLATION STANDARDS
AT&T Integrated Cloud
Issued May 2016
Revised August 2016
5.1.14 Installed fiber backbone cables shall be certified via 100% Tier 1 testing.
5.1.15 Factory certified fiber jumpers do not require inspection/scope or loss testing.
5.1.16 All fiber end faces shall be dry cleaned before mating.
5.1.17 Unterminated fiber shall have dust protective caps installed.
5.1.18 All test documentation shall be turned over to AT&T in an electronic format for archiving.
5.1.19 Ends of all bare wire/cable shall be insulated during all work activities.
5.1.20 Failed and Unused jumpers shall be removed with appropriate approval.
5.1.21 Communications shall be secured to provide proper support with AT&T approved Hook and
Loop material within the AIC footprint.
5.1.22 Plenum rated cables shall be utilized where required by Authority Having Jurisdiction (AHJ).
5.1.23 All cables/jumpers shall be factory connectorized.
5.1.24 Cable/jumpers shall be dressed to ensure containment within the rack footprint and shall not
block access to future cabling, shelves and hardware.
5.1.25 Cable pathway fill ratios shall be maintained as per the manufacturer’s guideline for the
specified product.
5.1.26 Penciling (Cable Grooming/Combing/Bundling): Cables shall be run in bundles of identical
cable types and run parallel not braided. Cables shall be secured with AT&T approved Hook
and Loop material for easy removal in case of maintenance needs, additions, or removals.
5.1.27 All CAT 5e/6 cables shall be gray.
5.2
Securing Power Cables
5.2.1
Power cables shall be secured within 10 inches of the termination point and every 24 inches
thereafter.
5.2.2
Power cords and cables shall be secured to the vertical and horizontal cable management
systems, dressed to avoid congestion and not impede air flow through the rack.
5.2.3
Lacing bars shall be placed so that all field serviceable items can be easily accessed.
5.2.4
AC power cords and cables shall be secured to provide proper support with AT&T approved
Hook and Loop material within the AIC footprint.
5.2.5
DC power cables shall be secured to provide proper support with 9-Ply wax cord material
within the AIC footprint.
5.3
Power Cabling
5.3.1
When cabling AC hardware to the rack’s PDU, the power cord shall be sized per
manufacturer’s power requirements, these cords shall be ISO, TL or UL compliant.
5.3.2
The equipment AC power cords shall be furnished in the correct stock length (1 foot
increments) to minimize slack.
5.4
Power cables AT&T DC Plant Environment
11
Issued May 2016
Revised August 2016
AIC INSTALLATION STANDARDS
AT&T
5.4.1
DC power cables within the AIC footprint shall be red for -48 battery and black for + ground
return and shall be textile jacketed. Approved non textile jacketed cables shall be protected
where secured or banded.
5.4.2
Approved non-standard color DC power cables or cables that are reversed in color for i.e.
Red + Black -, shall have red and black tape or heat shrink (preferred) applied at the source
to meet Telco DC plant color standards.
5.4.3
Damaged cables within the AIC equipment rack footprint shall be replaced.
5.4.4
UL approved connectors shall be used and the proper tool and die sets must be used for DC
power connectors. Compression connectors shall be properly crimped per manufacturer’s
instructions.
5.4.5
Tool and die sets shall be calibrated as required by the manufacturer.
5.4.6
Connections shall be made to ensure proper electrical operation of equipment and use
appropriate equipment Torque requirements and include Torque markings for lug type
connections.
5.4.7
Intra-rack DC Cables and fuses shall be sized according to requirements for the voltage drop
and amperage based on distance and L2 drain requirements.
5.4.8
Polarity and lack of voltage shall be verified before terminating cables.
5.4.9
Battery and return cables shall be paired and associated with the same return bus as the
fused position.
5.4.10 Verification of lack of current, with a clamp on ammeter, shall be performed before
disconnecting power leads.
5.4.11 All AIC DC powered racks shall be fed from a DC fuse/breaker panel, installed in the top of
rack, (output side of fuse/breaker panel) wiring shall meet manufacturer’s L2 drain
requirements
5.4.12 The Installation Supplier shall apply a thin coat of NO-OX-ID “A” anti-corrosive compound to
all connections of dissimilar metals to inhibit future corrosion
12
AIC INSTALLATION STANDARDS
AT&T Integrated Cloud
Issued May 2016
Revised August 2016
Example of Copper Cable Penciling
Example of Fiber Cable Penciling
6.
LABELING
6.1
Labeling
6.1.1
Labels shall not be hand written.
6.1.2
Labels shall not be modified by placing a designation label onto an existing label.
6.1.3
Lettering shall allow for readability and maximum information.
6.1.4
Racks shall be labeled with AT&T Job Order number at the top left, front & rear. For Preassembled racks, an additional label shall be placed by the VAR stating “Assembled:” and
the VPMO Number at the top left, front & rear. (i.e., ‘Assembled: 123456’).
13
Issued May 2016
Revised August 2016
AIC INSTALLATION STANDARDS
AT&T
6.1.5
Racks shall be labeled using ¾” Font with Rack number & Name (where applicable) at the
top front & rear, close to the center.
6.1.6
Racks shall be labeled with Power Source at the top right, front & rear.
6.1.7
Rack Units (Shelves/Devices) shall be labeled with the machine or host name, shelf number
or rack unit number on the front & rear in a clearly visible location consistent with other racks
in the build. Any shelves added to existing racks shall also include the AT&T Job Order
Number on the front and rear.
6.1.8
Equipment mounted in racks shall have the designation labeled on the rack
door/cover/finishing detail on the front and the inside rack framework on the rear.
6.1.9
Asset Tags provided to and installed by the VAR shall be placed uniformly on the front or rear
of the units in a visible location when possible. When equipment does not allow for
placement on the front or rear of the unit, the top of the unit is acceptable.
6.1.10 PDUs shall be labeled at the 1st position of each plug grouping.
6.1.11 PDUs shall be labeled to identify load diversity (Load A, B etc.).
6.1.12 AC power service rack circuits shall be designated beside the circuit breaker or on the
designation card with the location of the circuit being served and the circuit breaker
amperage.
6.1.13 Every connecting cable/jumper that connects to a device or appliance shall be labeled,
permitting easy identification, tracking/tracing and troubleshooting for connectivity issues.
a) All cable/jumper ends shall be labeled per the AIC engineering design and cable mapping
documentation.
b) Flag Labels shall be placed neatly dressed and readable approximately 3” to 10” from the
connector, fanned, placed in a manner to not cause congestion or require twisting of the
cable. Longitudinal Labels are not permitted.
c) Intra-Rack cables/jumpers shall contain the Rack Unit Number, Slot, & Port with the Near
end assignment 1st, Far end 2nd. Any cables/jumpers added to existing racks shall also
include the AT&T Job Order Number.
d) Inter-Rack cables/jumpers shall contain the Rack Location, Rack Unit Number, Slot & Port
with the Near end assignment 1st, Far end 2nd. Any cables/jumpers added to existing
racks shall also include the AT&T Job Order Number.
e) Duplex fibers shall have one flag label attached at each end (individual label per strand
not required).
6.1.14 AC power cables/cords shall be labeled with AT&T approved 145 P tags or flag tags at both
ends with near and far end information.
6.2
DC power cables
6.2.1
DC Power Cables, from BDFBs to the Network Element SPDUs, shall be labeled at both
ends with AT&T approved 145 P-Tags providing.
14
AIC INSTALLATION STANDARDS
AT&T Integrated Cloud
Issued May 2016
Revised August 2016
6.2.2
DC Power Cables, from Network Element SPDU to the individual Rack Unit’s power
connection, shall be labeled with AT&T approved 145 P-Tags at the Rack unit. The Fuse
Designation card will provide the far end information for the outputs at the SPDU end. See
Figure 3, 4, 5, 6, 7.
6.3
Power Labeling
6.3.1
Labeling shall also follow other guidelines outlined in the labeling section above.
6.3.2
Power source shall be labeled on the outside (front and rear top) of the rack at the time of
installation.
6.3.3
Each PDU shall be labeled indicating its electrical source (RPP) and its terminating circuit
within that RPP. The plug side of the PDU shall be labeled indicating its source receptacle
15
Issued May 2016
Revised August 2016
AIC INSTALLATION STANDARDS
AT&T
FIGURE 3 -- Power/Ground cables on the right. 1 P-tag for each -48v/Rtn combo. Also
notice the Twin-Ax and Cat-6 cables on the left
FIGURE 4 -- -48v and Return cables at the fuse panel. 18 fuses per panel for 36 positions.
Area too congested for P Tags
16
AIC INSTALLATION STANDARDS
AT&T Integrated Cloud
Issued May 2016
Revised August 2016
FIGURE 5 -- Congested Labels at fuse panel, do not follow
FIGURE 6 -- Fuse designation card at fuse panel
17
Issued May 2016
Revised August 2016
AIC INSTALLATION STANDARDS
AT&T
FIGURE 7 -- Front of a Rack. Fuse designation cards at right and left of Rack number at top.
FIGURE 8 -- Split tubing from Horizontal FPS to inside the Rack, attached to vertical rail, then
fiber secured with hook and loop until it arrived at it’ designated Rack Unit.
18
AIC INSTALLATION STANDARDS
AT&T Integrated Cloud
Issued May 2016
Revised August 2016
FIGURE 9 -- Split tubing from Horizontal FPS to inside Rack, attached to vertical rail, then
secured with hook and loop until it arrived at its designated Rack Unit.
FIGURE 10 -- Split tubing protecting fiber from one Arista Shelf to another. No good way to
protect without split tubing in this case.
19