Fort Nelson Main Construction Programme for Exhibition Tendering Purposes V 1 Date: 01.09.10 ID Task Name Duration 1 Fort Nelson 221 days? Mon 05/07/10 Fri 20/05/11 39.1 wks Mon 09/08/10 Fri 20/05/11 Fri 06/08/10 Fri 06/08/10 2 Contract Period Start Finish 3 Contract Finalised 0 days 4 Final Mobilisation 10 days Mon 26/07/10 Fri 06/08/10 5 Start on Site 0 days Mon 09/08/10 Mon 09/08/10 6 Design 63 days Mon 09/08/10 Thu 04/11/10 20 Lead In (Main Items Only) 42 Production 192 days Mon 19/07/10 Fri 22/04/11 221 days? Mon 05/07/10 Fri 20/05/11 Fri 20/08/10 43 Establish Site 10 days Mon 09/08/10 54 Gas Main Diversion 74 days Mon 05/07/10 Fri 15/10/10 77 Other Service Diversions 78 days Wed 07/07/10 Mon 25/10/10 115 Admission Building 196 days Mon 09/08/10 Fri 20/05/11 308 Orienteur Building 196 days? Mon 09/08/10 Fri 20/05/11 45 days Mon 09/08/10 Mon 11/10/10 309 Start on Site 310 Survey 1 day Thu 19/08/10 Thu 19/08/10 311 Setting Out 2 days Fri 20/08/10 Mon 23/08/10 312 Break Out Existing Concrete on top of Water Tank & Remove 3 days Tue 24/08/10 Thu 26/08/10 313 Service Diversion Works Mon 11/10/10 314 Completion of Water Tank Stabilisation Works (Design TBA) 315 316 Lower Ground Floor Groundworks 9 wks Mon 09/08/10 0 days Mon 04/10/10 Mon 04/10/10 26.5 days Tue 26/10/10 Wed 01/12/10 Remove Redundant Services/Manholes 5 days Tue 26/10/10 Mon 01/11/10 317 Lower Ground Floor Excavation to Formation Level 2 days Tue 02/11/10 Wed 03/11/10 318 Retaining Walls 9.5 days Thu 04/11/10 Wed 17/11/10 0.5 days Thu 04/11/10 Thu 04/11/10 4 days Thu 04/11/10 Wed 10/11/10 Thu 11/11/10 319 Install Barrier to Lower Ground Level 320 Formwork & reinforcement to retaining walls incl bases 321 Final fix shutters 1 day Wed 10/11/10 322 Line & level 1 day Thu 11/11/10 Fri 12/11/10 323 Concrete to walls 2 days Fri 12/11/10 Tue 16/11/10 324 Strike Shutters 325 Sub-Station Works 1 day Tue 16/11/10 Wed 17/11/10 10 days Wed 17/11/10 Wed 01/12/10 Wed 24/11/10 326 Remove Asbestos Roof 5 days Wed 17/11/10 327 Brickwork 5 days Wed 24/11/10 Wed 01/12/10 53 days? Wed 10/11/10 Wed 02/02/11 7 days Wed 17/11/10 Fri 26/11/10 328 Structure 329 Glulam Structure 330 Structural Staircase Completion 331 Potential Window for Cranage of Heavy Guns 332 Brick/Blockwork 333 Install Glulam Timber Roof 334 5 days Fri 26/11/10 Fri 03/12/10 5.5 days? Wed 10/11/10 Wed 17/11/10 20 days Fri 26/11/10 Tue 04/01/11 3 days Tue 04/01/11 Fri 07/01/11 Waterproofing to Roof 5 days Fri 14/01/11 Fri 21/01/11 335 Glazing to Angled Roof 5 days Fri 14/01/11 Fri 21/01/11 336 Windows and Doors Installation 2 wks Wed 19/01/11 Wed 02/02/11 337 Roof Lights Installation Fri 14/01/11 338 339 Building Watertight Internal Fit Out 1 wk Fri 07/01/11 0 days Fri 21/01/11 Fri 21/01/11 38 days Fri 21/01/11 Wed 16/03/11 Fri 04/02/11 340 Internal Walkway Installation 10 days Fri 21/01/11 341 Carcass to Upper Gallery Wall 5 days Fri 21/01/11 Fri 28/01/11 342 Suspended Ceiling First Fix 5 days Wed 26/01/11 Wed 02/02/11 343 Mechanical First Fix 3 wks Mon 31/01/11 Mon 21/02/11 344 Electrical First Fix 2 wks Mon 07/02/11 Mon 21/02/11 345 Lift Installation 2 wks Mon 14/02/11 Mon 28/02/11 346 Super Gun Support First Fix (Provision TBA) 3 days Fri 21/01/11 Wed 26/01/11 Project: Fort Nelson Contract Programme Issue 2_hig Date: Thu 02/09/10 Task Progress Milestone ly August September October November December January February March April May June J 5/0 2/0 9/0 6/0 2/0 9/0 6/0 3/0 0/0 6/0 3/0 0/0 7/0 4/1 1/1 8/1 5/1 1/1 8/1 5/1 2/1 9/1 6/1 3/1 0/1 7/1 3/0 0/0 7/0 4/0 1/0 7/0 4/0 1/0 8/0 7/0 4/0 1/0 8/0 4/0 1/0 8/0 5/0 2/0 9/0 6/0 3/0 0/0 6/0 3/0 0/0 7/0 06/08 09/08 04/10 21/01 Summary Project Summary Page 1 External Tasks External Milestone Deadline Fort Nelson Main Construction Programme for Exhibition Tendering Purposes V 1 Date: 01.09.10 ID Task Name Duration 347 Complete Green Roof 348 WC & Lobby Installation Start Finish 3 days Wed 16/02/11 Mon 21/02/11 17 days Mon 21/02/11 Wed 16/03/11 Mon 21/02/11 Tue 22/02/11 Wed 23/02/11 349 Fix Plasterboard 1 day 350 Skim coat plaster 1 day Tue 22/02/11 351 Mist coat paint 1 day Thu 24/02/11 Fri 25/02/11 352 Fit Door Frames 1 day Fri 25/02/11 Mon 28/02/11 353 Second fix mechanical 2 days Mon 28/02/11 Wed 02/03/11 354 Second fix electrics 2 days Wed 02/03/11 Fri 04/03/11 355 Tiling 2 days Fri 04/03/11 Tue 08/03/11 356 First coat paint walls/ceiling 1 day Tue 08/03/11 Wed 09/03/11 357 Second coat paint walls/ceiling 358 Fixtures/Fittings 359 Final Fix IPS 360 1 day Wed 09/03/11 Thu 10/03/11 2 days Thu 10/03/11 Mon 14/03/11 1 day Mon 14/03/11 Tue 15/03/11 1 day Tue 15/03/11 Wed 16/03/11 361 External Finishes 31 days Tue 04/01/11 Wed 16/02/11 364 Internal Finishes 6 days? Mon 21/02/11 Tue 01/03/11 Mon 21/02/11 Mon 28/02/11 Lay flooring to WC 365 Complete Ground Floor Wall finish 5 days 366 FairFaced Concrete Finish 2 days Mon 21/02/11 Wed 23/02/11 367 Concrete Floor Finish 3 days Wed 23/02/11 Mon 28/02/11 Install IRAQI Super Gun and German & British AA Guns to Lower Floor 1 day? Mon 28/02/11 Tue 01/03/11 ly August September October November December January February March April May June J 5/0 2/0 9/0 6/0 2/0 9/0 6/0 3/0 0/0 6/0 3/0 0/0 7/0 4/1 1/1 8/1 5/1 1/1 8/1 5/1 2/1 9/1 6/1 3/1 0/1 7/1 3/0 0/0 7/0 4/0 1/0 7/0 4/0 1/0 8/0 7/0 4/0 1/0 8/0 4/0 1/0 8/0 5/0 2/0 9/0 6/0 3/0 0/0 6/0 3/0 0/0 7/0 368 369 28/02 370 371 Circular Door Installation 372 Lay Matting to entrance door 373 Completion 1 wk Mon 21/02/11 Mon 28/02/11 2 days Mon 21/02/11 Wed 23/02/11 17.5 days? Tue 01/03/11 Thu 24/03/11 Tue 01/03/11 Tue 08/03/11 374 Final Fix M&E 5 days 375 Test & Commission 5 days Tue 08/03/11 Tue 15/03/11 376 Final Clean 1 day Wed 16/03/11 Thu 17/03/11 377 Completion of Orienteur 0 days Thu 17/03/11 Thu 17/03/11 Period for movement of heavy exhibits post building completion 5.5 days? Thu 17/03/11 Thu 24/03/11 Exhibition Installation 31.5 days? Thu 17/03/11 Fri 29/04/11 383 Cess Pool Installation 31 days Mon 08/11/10 Mon 20/12/10 392 Redan 44 days Tue 12/10/10 Fri 10/12/10 396 Lobby from Orienteur to Redan 15 days Mon 22/11/10 Fri 10/12/10 399 Car Parks 46 days Mon 10/01/11 Mon 14/03/11 420 Completion & Handover 20 days Fri 22/04/11 Fri 20/05/11 4 wks Fri 22/04/11 Fri 20/05/11 17/03 378 379 380 381 382 421 Final Snagging 422 Handover 5 days Mon 16/05/11 Fri 20/05/11 423 Mansell Completion of Works 0 days Fri 20/05/11 Fri 20/05/11 79 days? Fri 25/02/11 Fri 17/06/11 60 days? Fri 25/02/11 Fri 20/05/11 10 days Mon 23/05/11 Mon 06/06/11 19 days? Mon 23/05/11 Fri 17/06/11 9 days? Tue 07/06/11 Fri 17/06/11 19 days? Mon 23/05/11 Fri 17/06/11 9 days? Tue 07/06/11 Fri 17/06/11 1 day? Fri 17/06/11 Fri 17/06/11 20/05 424 425 Royal Armouries Post PC Activities 426 Admissions Complex Shop Fit Out Procurememt 427 Admissions Complex Shop Fit Out Delivery 428 Royal Armouries Final global placement of exhibitioin fixing and fittings 429 Royal Armouries Stocking of Shop / Kitchen etc 430 Royal Armouries Staff Training and Familiarisation 431 Final Operation Testing 432 Royal Armouries Ready to Open Project: Fort Nelson Contract Programme Issue 2_hig Date: Thu 02/09/10 Task Progress Milestone 17/06 Summary Project Summary Page 2 External Tasks External Milestone Deadline
© Copyright 2026 Paperzz