January 2016 - Progress Report

Morris Close Burwash
Progress Report January 2016
Prepared by Kim Randall Development Officer Hastoe House Association
Scheme Review
•
•
•
•
•
•
•
•
•
RG Carters have been unable to secure air tightness due to failure in the
membrane
To achieve air tightness all units need to be stripped back to timber stud and new
membrane installed
All kitchens are in the process of being removed and stored in a secure unit until
remedial works are completed
Roof lights have been leaking, inspection highlighted they have not been fitted
correctly
Removal of roof tiles and exposure to gables and roof lights for repair has
commenced
Plots 1,2 & 3 plasterboard has been removed and the versaliner exposed ready for
installation of new membrane
Electrical first fix services have been removed
New front doors have been installed to all units
Scaffolding erected for external repairs to commence.
Remedial Works
New doors installed,
rear wall has been
stripped back to timber
battens
Plasterboard has been
removed to expose the
versaliner
New membrane to be
installed over the
versaliner and floor
area
Key Project Dates
Description
Contract commencement date
Date
29.06.14
Structural investigation & repair
Roofing light repairs
Remedial works finalised
Snagging & desnagging
30.11.15 – 18.12.15
01.02.16
15.02.16
28.05.16 – 17.06.16
Fit out of units
Estimated handover date
29.02.16 – 28.05.16
20.06.16
Scheme Details
• 8 x affordable units
• 2 x shared ownership
• 10 units in total
•
•
•
•
•
1 x 1 bedroom bungalow
2 x 1 bedroom flats
2 x 2 bedroom flats
4 x 2 bedroom houses
1 x 3 bedroom house
Site possession 08.04.14
Hastoe Housing Team - Brede
Contact List
Hastoe
• Kim Randall - Development Officer
• 020 8973 0427 [email protected]
• Responsible for managing the development of the scheme
RG Carter
• Nick Pitcher- Site Manager
• Contact details T.B.C
• Responsible for site management
Rother Council
• Amy Fearn – Housing and Asset Development Officer –
• 01424 787514 [email protected]
• Responsible for allocation queries and Rother Council waiting
lists for local residents
Summary
Uncovering sections of previously completed work has revealed
additional areas of concern therefore delaying site progress.
Although this is a major disappointment we had anticipated
additional problems and had added extra time within the
program to action any unforeseen issues.
We have commenced remedial works on these areas and
finalised the detail to secure air tightness which is required to
achieve Passivhaus standards.
We are still looking to handover on 20.06.16, but this still remains a
provisional date
Hastoe would like to apologise for any inconvenience caused due
to the delay for this scheme and we want to thank the Parish
Council & Local Authority for their continued support.