Supplement D Queuing Theory Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010 © Wiley 2010 1 Learning Objectives Explain the role of the master production schedule and describe the objectives of master production scheduling. Develop a master production schedule and project the capacity needed using rough-cut capacity planning. Calculate available-to-promise quantities. Describe time fence policies. © Wiley 2010 2 Master Production Scheduling MPS: The anticipated build schedule The Master scheduler is the person responsible for managing, developing, reviewing and maintaining the master schedule © Wiley 2010 3 MPS As a Basis of Communication Master production schedule linkages © Wiley 2010 4 Objectives of Master Scheduling The master scheduler considers these points when developing the (master) schedule: Achieve the desired customer service level either by maintaining finished goods inventory or by scheduling completion of the item or service to meet the customer’s delivery needs. Make the best use of the company’s resources: material, labor, and equipment. Ensure that the inventory investment is at the appropriate level. © Wiley 2010 5 Developing an MPS The master scheduler: develops a proposed MPS, checks the schedule for feasibility in terms of available capacity, modifies as needed, and authorizes the MPS. The master scheduler uses the finished MPS records to develop a proposed master production schedule, which is then checked for feasibility with a rough-cut capacity planning technique. © Wiley 2010 6 The MPS Record W eek BI 1 2 3 4 5 6 7 8 9 10 11 12 50 50 50 50 75 75 75 75 50 50 50 50 110 60 10 -4 0 BI 1 2 3 4 5 6 7 8 9 10 11 12 50 50 50 50 75 75 75 75 50 50 50 50 60 10 85 35 -4 0 F o re c a s t P ro je c t e d a va ila b le Q= 125 units MPS W eek F o re c a s t P ro je c t e d a va ila b le MPS 110 125 Projected Available = beginning inventory + MPS shipments forecasted demand The MPS row shows when replenishment shipments need to arrive to avoid a stock out (negative projected available) © Wiley 2007 Revised and Completed MPS Record W eek BI F o re c a s t P ro je c te d a va ila b le 110 1 2 3 4 5 6 7 8 9 10 11 12 50 50 50 50 75 75 75 75 50 50 50 50 60 10 85 35 85 10 -6 5 MPS W eek 125 BI F o re c a s t P ro je c te d a va ila b le MPS 110 125 1 2 3 4 5 6 7 8 9 10 11 12 50 50 50 50 75 75 75 75 50 50 50 50 60 10 85 35 85 10 60 110 60 10 85 35 125 125 125 125 © Wiley 2007 125 Rough-Cut Capacity Planning Rough-cut capacity planning (RCCP): The process of converting the master production schedule into requirements for key resources such as direct labor and machine time Demonstrated capacity: Proven capacity calculated from actual performance data Capacity planning using overall planning factors (CPOPF): A rough-cut capacity planning technique. MPS items are multiplied by historically determined planning factors for key resources. See Procedures for CPOPF below: © Wiley 2010 9 Rough Cut Capacity Problem: a shoe company produces two models of dance shoes. Over the past 3 years 72,000 pairs of Model M have been produced using 21,600 direct labor hours and 5760 machine hours, and 108,000 pairs of Model W using 43,200 hours of labor and 12,960 hours of machine time. Step 1: Determine the Planning factors: Labor Factors Machine Factors © Wiley 2007 Step 2:Calculate the Workload Generated by This Schedule A B C Planning Factors (hours per pair) Direct Machine Labor Time Model M 0.30 0.08 Model W 0.40 0.12 D E 4 5 6 7 8 9 10 Quarterly Master Production Schedule (MPS) (pairs) 11 Q1 Q2 Q3 Q4 12 Model M 6000 5500 9500 6500 13 Model W 10000 12000 7500 10100 © Wiley 2007 F Totals 27500 39600 Step 3: Calculate the Capacity Needs for Each Resource for Each Time Period A B C Direct Labor Hours Required Q1 Q2 Model M 1800 1650 Model W 4000 4800 Totals 5800 6450 15 16 17 18 19 20 21 Machine Time (Hours) Required 22 Q1 Q2 23 Model M 480 440 24 Model W 1200 1440 25 Totals 1680 1880 D E F Q3 2850 3000 5850 Q4 1950 4040 5990 Totals 8250 15840 24090 Q3 760 900 1660 Q4 520 1212 1732 Totals 2200 4752 6952 © Wiley 2007 Step 4: Calculate Individual Workcenter Capacity Needs Based on Historical Percentage Allocation A B C D 27 Work Center Historical Breakdown 28 Direct Machine 29 Labor Time 30 Center 101 60% 60% 31 Center 102 40% 40% 32 33 Direct Labor Hours Required by Work Center 34 Q1 Q2 Q3 35 Center 101 3480 3870 3510 36 Center 102 2320 2580 2340 37 Totals 5800 6450 5850 38 39 Machine Time Hours Required by Work Center 40 Q1 Q2 Q3 41 Center 101 1008 1128 996 42 Center 102 672 752 664 43 Totals 1680 1880 1660 © Wiley 2007 E F Q4 3594 2396 5990 Totals 14454 9636 24090 Q4 1039.2 692.8 1732 Totals 4171.2 2780.8 6952 Evaluating and Accepting the MPS The master scheduler checks that promised customer delivery dates are met. He also ensures that the MPS provides enough flexibility to cover new customer orders. Once the master scheduled has evaluated and accepted the MPS, the authorized MPS is entered into the MRP system. © Wiley 2010 14 Using the MPS One use of authorized MPS is order promising (the process of making orderdelivery commitments). Order promising relies on available-topromise (ATP), which is the uncommitted portion of a company's inventory and planned production that is maintained in the MPS to support order processing. © Wiley 2010 15 Using the ATP records The ATP records show how much inventory is available to satisfy customer demand. Two rules to help manage the ATP: A negative number is the projected available row is sometimes a problem. A negative number in the available-to-promise row is always a problem. © Wiley 2010 16 Using the MPS to “Order Promise” The authorized MPS is used to promise orders to customers The MPS table is expanded to add customer orders and available-to-promise rows (inventory to satisfy new orders) ATPAction Bucket = (beginning inventory + MPS shipment) less (customer orders before next replenishment). Available in period 1 ATP=MPS shipment – Customer orders between current MPS shipment and next scheduled replenishment in periods 3,5,7,8, & 11 W eek 1 2 3 4 5 6 7 8 9 10 11 12 F o re c a s t 50 50 50 50 75 75 75 75 50 50 50 50 C u s t o m e r o rd e rs 35 25 25 20 0 15 0 0 10 0 0 10 60 10 85 35 85 10 60 110 60 10 85 35 110 125 115 115 125 125 125 125 P ro je c t e d a va ila b le A va ila b le -t o -p ro m is e MPS BI 110 50 80 125 © Wiley 2007 Example of Revising the ATP MPS Record: A customer calls marketing willing to purchase 200 units if they can be delivered in period 5. The two tables below show how the system logic would first slot the 200 into period 5 and then how the order would be allocated across periods 1, 3, and 5 and adjusting the ATP row. © Wiley 2007 Stabilizing the MPS The master scheduler tries to minimize the changes made to an authorized MPS – each change can impact the feasibility of the MPS. This figure shows the demand time fence and the planning time fence which split the MPS into three parts. © Wiley 2010 19 MPS & Rough-cut Capacity Planning within OM: How it all fits together In most companies, the operations manager develops the aggregate plan, which determines the resources available to operations to execute the master production schedule. The plan will clearly indicate the size of the workforce and the aggregate production rate. The master production scheduler then develops the master production schedule. The only feasible plan that can be developed is one by the scheduler working with marketing, operations, demand management, and the customers. The master scheduler’s job is to develop an MPS that achieves the company’s desired customer service level, uses capacity effectively, and minimizes the inventory investment. To make sure that the master production schedule is feasible, rough-cut capacity planning is done. © Wiley 2010 20 Supplement Highlights The MPS shows how the resources authorized by the aggregate plan will be used to satisfy the objectives of the organization. The MPS specifies the products and quantities to be built in each time period. The MPS is a common organizational document used to facilitate communication between different functional areas. The master scheduler develops a proposed MPS based on input received from the aggregate plan and demand management. This MPS is checked for feasibility using a rough-cut capacity planning technique. The objectives of master scheduling are to satisfy customer service objectives, use resources effectively, and minimize costs. An MPS is developed by looking at individual MPS records and calculating when replenishment quantities are needed. The individual MPS records are summed together to show the total proposed workload. © Wiley 2010 21
© Copyright 2026 Paperzz